soft landscaping method statement
TRANSCRIPT
Page i of 14
Project Lower Road, Loughton.
Report Type
Soft Landscape Method Statement
Checked by
Date Checked
Page ii of 14
CONTENTS PAGE
1 SUMMARY REPORT .................................................................................................................. 4 SCOPE AND LIMITATIONS ................................................................................................................................ 4 METHODOLOGY AND GUIDANCE ..................................................................................................................... 4 AREAS CONSIDERED ......................................................................................................................................... 5 RELEVANT PLANS AND DOCUMENTS ............................................................................................................... 5
2 SEQUENCE OF OPERATIONS ..................................................................................................... 6
3 GENERAL PRINCIPLES TO AVOID DAMAGE TO RETAINED TREES ................................................ 6
4 PREPARATION OF PLANTING AREAS ......................................................................................... 7
5 NURSERY STOCK PROTECTION .................................................................................................. 7
6 PLANTING ................................................................................................................................ 8
7 REINSTATEMENT & GRASSING OF AREAS ................................................................................. 9
8 IMPLEMENTATION ................................................................................................................... 9
9 AFTERCARE AND MAINTENANCE ............................................................................................. 10 SPRING ........................................................................................................................................................... 10 SUMMER ........................................................................................................................................................ 10 AUTUMN ........................................................................................................................................................ 10
10 IRRIGATION ....................................................................................................................... 11
11 REFERENCES ...................................................................................................................... 12 TITLE ............................................................................................................................................................... 12
APPENDIX 1 .................................................................................................................................. 13
Page 4 of 14
1 SUMMARY REPORT
1.1 This soft landscape method statement has been commissioned by Jabhill Properties
Ltd in order to discharge conditions 8, 9 & 10 of planning reference EPF/2043/12
dated 03 December 2012.
1.2 This report includes:
Methodology for the preparation, planting and maintenance of new soft
landscaping
Detailed planting scheme and specifications for proposed planting.
Scope and limitations
1.3 The contents of this report are copyright of Tim Moya Associates and may not be
distributed or copied without the author’s permission. Tim Moya Associates standard
Limitations of Service apply to this report and all associated work relating to this site.
A copy has been supplied with our original quotation and further copies are available
on request.
Methodology and guidance
1.4 This report has been prepared in accordance with British Standard 4428:1989 Code
of Practice for general landscape operations (excluding hard surfaces) and British
Standard 5837: Trees in relation to design, demolition and construction –
Recommendations (2012) which provides a methodology for the assessment and
protection of trees and other significant vegetation on development sites.
Page 5 of 14
Areas considered
1.5 For successful implementation and establishment of the proposed landscaping this
document covers the following key areas:
Preparation of the planting areas
Nursery stock protection
Planting technique
Arrangements for implementation of the scheme
Aftercare
Irrigation
Relevant plans and documents
1.6 As well as any other approved plans and particulars the following are to be read in
conjunction with this statement and are attached to this report in the appendices.
Document Location
Landscape scheme 220106-P-13 Appendix 1
Page 6 of 14
2 SEQUENCE OF OPERATIONS
2.1 The sequence of operations followed as part of the landscaping process are:
ground clearance works
preparation and cultivation
Planting of trees and other vegetation
Maintenance and aftercare
3 GENERAL PRINCIPLES TO AVOID DAMAGE TO RETAINED TREES
3.1 No fires will be permitted within 20m of the crown of any tree.
3.2 No changes in soil levels will take place within the tree protection zones without prior
written consent of the local authority.
3.3 No materials, vehicles, plant or personnel will be permitted into the tree protection
zones at any time without the prior consent of the arboricultural consultant.
3.4 Any liquid materials spilled on site will be immediately cleared up and removed from
the site. If liquid fuel or cement products are spilled within 2m of the tree protection
zone, the contractor will report the incident to the arboricultural consultant
immediately.
3.5 The contractor will report any damage to trees or shrubs, whether caused by
construction activities or from any other cause, to the arboricultural consultant
immediately.
Page 7 of 14
4 PREPARATION OF PLANTING AREAS
4.1 Refer to BS 4428:1989 Code of practice for general landscape operations.
4.2 All debris and weeds will be cleared from the planting areas prior to the soil
preparation.
4.3 New shrub beds to be planted outside of tree protection zones will be prepared using
machinery to a depth of at least 0.4m. A rotovator will then be used to create a fine
tilth and to incorporate soil improvers where necessary.
4.4 A layer of bark chip mulch, 75mm in depth will be applied following planting to reduce
the colonisation of weeds and to assist with moisture retention. (Section 7.10.3
BS4428).
4.5 New trees will have an area of at least 1m² mulched with the tree centrally located
unless otherwise stated.
5 NURSERY STOCK PROTECTION
5.1 All plants purchased from the supplier will be clearly labelled with the botanical name
of the plant; the suppliers name and other information i.e. plant passport number.
Also provided will be country of origin and age of plant.
5.2 Plants will be free from pests and diseases and show no signs of damage. All plants
will be inspected upon delivery to the site.
5.3 Exposure to adverse weather conditions will be avoided. Plants will not be allowed to
dry out and will be stored away from strong winds.
5.4 Bare rooted plants will have protective wrapping removed and will be firmly heeled
into a prepared trench and covered with topsoil.
5.5 All plants will be appropriately maintained until used and be kept away from possible
sources of contamination or damage. The drying out of all plants will be avoided by
watering of the roots if necessary.
5.6 All plants will be in accordance with BS3936:1992 Specification for nursery stock,
and Horticultural Trades Association (HTA) National Plant specification guidance.
Page 8 of 14
6 PLANTING
6.1 Refer to the Landscape scheme 220106-P-13 at Appendix 1 for species, numbers,
sizes and planting densities.
6.2 Planting will be carried out in the next available planting season. This usually runs
from October to March but is dependent on weather conditions. Container grown
plants can be planted outside of this time providing adequate aftercare is available.
6.3 All bare root hedges will be either notch planted or trench planted. Hedge trenches
will be a minimum of 400mm deep and up to 750mm wide for double rows.
6.4 Excavations for tree pits will be at least twice the diameter of the root spread and 1.5
times the depth of the roots of the stock to be planted.
6.5 The bottom and sides of the pit will be broken up to allow deep root penetration and
so as not to create a sump effect in the hole.
6.6 Following pit excavation, the plants will be carefully placed into the hole with all roots
spread out and any damaged roots pruned back to sound growth. Container grown
plants will be carefully removed from the pots and the roots gently teased out by
hand to ensure no circling roots remain.
6.7 The plant will be placed into the pit ensuring roots of adjacent trees are retained
during the process.
6.8 The plant will be carefully held upright in the middle of the pit whilst the excavated
soil is put back over the roots in thin layers.
6.9 The plant will be shaken gently up and down, so that when backfilling the soil gets
between and around the roots. The soil will be firmed down.
6.10 The plant will be planted ensuring that the nursery mark on the stem is level with the
final level of the backfilled soil.
6.11 The final backfill layer will sit slightly proud of the existing surrounding soil levels.
6.12 All trees planted will be staked using the method shown on the planting plan.
6.13 A maximum depth of 75mm of composted wood chip mulch will be applied for the
entire width of the pit around the base of each plant to form a continuous line of
mulch along new planting areas.
6.14 Preparation and planting of all trees and plants will be in accordance with BS 4428:
1989.
Page 9 of 14
7 REINSTATEMENT & GRASSING OF AREAS
7.1 All new lawn areas will be stripped of the top 100mm of soil and layer of new
multipurpose topsoil added.
7.2 Turves should be in accordance with the recommendations given in BS 3969 and
should be composed of grass varieties suitable for the intended use of the area to be
laid.
7.3 The newly levelled area will be turfed in accordance with BS 4428:1989.
8 IMPLEMENTATION
8.1 The landscape proposals will be implemented and maintained as detailed in section
9, by a client approved landscape contractor for a period of 12 months following
completion.
8.2 On completion of the implementation of the landscape proposals, the contractor
contact will invite the Planning Authority to inspect the completion of the scheme.
8.3 Any necessary amendments to the implemented landscape proposals will be
undertaken immediately after the inspection and reported back to the Planning
Authority.
8.4 Any tree or shrub forming part of the landscaping that dies, is damaged, diseased or
removed within 5 years following completion shall be replaced during the next
available planting season (October to March inclusive) with a tree or shrub of the
same species and size.
8.5 Within one month of the end of the 12 month maintenance period the contractor will
issue a report to the local authority detailing all visits and work undertaken within the
period.
Page 10 of 14
9 AFTERCARE AND MAINTENANCE
To be carried out by a client approved Landscape contractor in accordance with the maintenance agreement.
Spring
9.1 In March/April plants will be checked for survival.
9.2 Any plants that have died will be replaced using the same methods for planting.
9.3 Any loose soil around the base of the new plants and any plants lifted by frost will be
firmed down by foot.
9.4 Mulching depth will be checked and reinstated to a depth of 75mm if inadequate.
9.5 Regular watering will occur. See section 10.Irrigation.
Summer
9.6 Plants will be inspected and checked for any diseases or problems and rectified as
appropriate.
9.7 The mulch will be checked and reinstated if found to be inadequate.
9.8 Weeds will be removed by hand if found to be growing in the mulched area.
9.9 The plants will be formatively pruned where identified as necessary to ensure good
long term form.
9.10 Regular watering will occur. See section 10. Irrigation.
Autumn
9.11 Ties and plants will be checked to establish whether or not they have a secure root-
hold and can remain upright.
9.12 Stakes and supports will be removed where plants indicate they can support
themselves.
9.13 Mulching depth will be checked and reinstated if inadequate.
9.14 Regular watering will continue if prolonged summer temperatures extend into the
season or if drying winds occur. See section 10. Irrigation.
Page 11 of 14
10 IRRIGATION
10.1 All areas of new planting will require irrigation throughout the growing season.
10.2 Water requirement will be dependent on species, soil types and weather conditions,
however newly planted standard trees up to 18-20cm in girth will require
approximately 30litres per day from april-september. This can be reduced in
prolonged wet spells.
10.3 Watering will be carried out using a hose pipe fitted with a fine rose (subject to local
restrictions).
10.4 Irrigation will be carried out for the first two growing seasons to ensure good root
establishment.
10.5 Irrigation will be carried out first thing in the morning or late in the afternoon to avoid
excessive evaporation or leaf scorch.
Page 12 of 14
11 REFERENCES
11.1 The following publications have been used in the production of this method
statement;
Title
British Standard 5837: Trees in relation to design, demolition and construction –
Recommendations (2012)
British Standard 3882: Specification for Top soil (2007)
British Standard 4043: Recommendations for Transplanting root balled trees
(1989)
British Standard 3936: Nursery stock (various parts) (1992)
British Standard 4428: Code of practice for General Landscape Operations (1989)
British Standard 7370: Recommendations for Maintenance of Soft landscape
(Other than amenity turf): Part 4 (1993)
British standard 3969: Recommendations for turf for general purposes (1998)
HTA National Plant Specification
LO
WE
R R
OA
D
38
39
10
37a
SEYMOUR'S
35
37a
lounge
27sq/m
LO
W
ER
R
OA
D
SEYMOUR'S
120 sq/m
kitchen / dining
16 sq/m
lounge
27sq/m
kitchen / dining
16 sq/m
NT2
NT1NT1
NT3
Sh2
SP1Sh3
SP3
NT4
38
39
10
37a
SEYMOUR'S
35
DBH -
100mm
RPA -
1.2m
DBH -
150mm
RPA -
1.8m
Elder, Bramble, Conifer Hedge
N
1m0
5m 10m
Title
Client
Project
Date
Drawing No
Drawn by
Scale
Landscape Scheme
37 Lower Road, Loughton
January 2013
220106-P-13
KL
1:100 @A1
REVISIONS
DO NOT SCALE Use only figured dimensions
Jabhill Properties Ltd and RichardJohns
Unit 8 Feltimores ParkHarlow
Essex CM17 0PF
Tel: 0845 094 3268Fax: 0845 094 3269
www.tma-consultants.co.uk
Rev-
Base Drawing
The original of this drawing was produced in colour -amonochrome copy should not be relied upon.
SPECIES DENSITY/SPACING
QTYCODE
Verbena bonariensis 5Spreadacrossbed
5
Festuca glauca 'ElijahBlue'
4 perm2
22
Pachysandra terminalis'Green Carpet'
36
SIZE
3Ltr
3Ltr
3Ltr 4 perm2
Grass
NT1
NT2
NT3
Phyllostachys vivaxaureocaulis
720Ltr 2mspacing
Lonicera periclymenun'Graham Thomas'
53Ltr -
CODE SPECIES SIZE QTY
SP1 Corylus avellana 'Contorta'160L2m specimen 1
Sh2 Mahonia x Media 'Charity' 30L 1Sh3 Philadelphus coronarius 'Aureus' 30L 1
SP3Pittosporum tenuifolium 'SilverQueen' 15L 1
NT1 Alnus cordata
12-14cm girthContainergrown 2
NT2 Quercus robur 'Fastigiata'
12-14cm girthContainergrown 1
NT3 Corylus colurna
12-14cm girthContainergrown 1
NT4 Malus trilobata 8-10cm 1