minutes of 238 seac meeting date 09/10/2015 - enviroment
TRANSCRIPT
Minutes of 238th
SEAC Meeting Date 09/10/2015
The 238th
meeting of SEAC was held in Directorate of Environment, U.P. on
09/10/2015. Following members were present in the meeting along with Secretary, SEAC:
1. Dr. S.N. Singh Chairman
2. Shri S.C. Bramhchari Member
3. Dr. D. C. Gupta, Member
4. Shri Ajay Kumar Shukla, IAS, Secretary, SEAC &
Director, Environment, UP
The Chairman welcomed the members to the 238th
SEAC meeting.
The Members of SEAC unanimously taken following decisions on the agenda points
discussed:
1. Group Housing Project “VVIP Addresses” at Khasra No-826, 1111-1113, 1117, 1119, 1120, 1125,
1126,1144m, 1146, 1147, Vill-Noor Nagar, Distt-Ghaziabad.- Sri B K Jain, CEO, 58, Rajnagar
Extension, Ghaziabad. File N0. 3091/OSD-T.
The committee noted that an application dated 15/05/2015 was made by the project
proponent for environmental clearance of Expansion of Group Housing Project “VVIP Addresses”
at Khasra No-826, 1111-1113, 1117, 1119, 1120, 1125, 1126, 1144 M, 1146, 1147, Vill-Noor
Nagar, Sadik Nagar, Distt-Ghaziabad, M/s Vibhor Vaibhav Infrahome Pvt. Ltd. The terms of
reference were prescribed in SEAC meeting dated 27/06/2015. Final EIA was submitted by the
project proponent through letter dated 03/08/2015.
A presentation was made by Shri B.K. Jain, CEO, VVIP Ltd., project proponent along with
their consultant M/s GRC Pvt. Ltd. The proponent, through the documents submitted and the
presentation made, informed the committee that:-
1. The environmental clearance is sought for Expansion Group Housing Project “VVIP
Addresses” at Khasra No-826, 1111-1113, 1117, 1119, 1120, 1125, 1126, 1144 M, 1146,
1147, Vill-Noor Nagar, Sadik Nagar, Distt-Ghaziabad, M/s Vibhor Vaibhav Infrahome Pvt.
Ltd.
2. Earlier, M/s Vibhor Vaibhav Infrahome Private Limited has obtained Environmental
Clearance from SEIAA, U.P. vide Letter no. 2531/SEAC/785/2011/DD(S)/ dated
11.11.2011 for existing plot area 67,819.59 m2 (16.76 acres) and built up area 2,48,505.17
m2. Now, the expansion of the project is proposed.
3. Comparative salient features detail for earlier and expansion project:
PROJECT FEATURES EXISTING EXPANSION TOTAL
Plot Area 67,819.59 12,268.59 80,088.18
Built Up Area 2,48,505.170 1,09,775.89 3,58,281.06
Ground Coverage 14,791.250 3,900.26 18,691.51
FAR + Additional FAR 1,93,956.58 47,728.52 2,41,685.10
Basement Area 54,548.590 5000.77 59,549.36
Green Area 13,563.91 -771.1 12,792.81
Estimated Population 11,422 (2098 DU) 5,568 (958 DU) 16,990 (3056 DU)
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 2 of 48
Estimated Water Requirement
Construction Phase
Operation Phase
1,243 ML
879.06 KLD
549 ML
585.94 KLD
1,792 ML
1,465 KLD
Estimated Wastewater 740.89 KLD 511.11 KLD 1,252 KLD
Power Demand
Power Back-up
6,430 kVA
5,240 kVA (2 × 600 kVA + 4
X 1,010 kVA)
2,380 kVA
2,920 kVA
8,810 kVA
8,160 kVA (4 x750 kVA +
1 x 630 kVA + 2 x 600
kVA + 4 x 500 kVA + 2 x
365 kVA + 2 x 300 kVA)
Source of Power Uttar Pradesh Power Company Limited
Total no. of RWH structures 22 Pits 12 Pits and 9 tanks
Solid Waste Generation 5,140.3 kg/day 2,537.7 kg/day 7,678 kg/day
Parking Facilities
Required
Proposed
2,233 ECS
2,352 ECS
1,392 ECS
1,286 ECS
3,625 ECS
3,638 ECS
4. Comparative area details of earlier and proposed project:
S.
No.
Particulars Existing (EC Accorded)
(in m2
)
Expansion
(in m2
)
Total
(Existing +
Expansion)
(in m2
)
Percentage
1. Plot Area 67,819.59 12,268.59 80,088.18 100
2. Area left for road
widening
3136.04 628.37 3764.41 4.70
3. Area left for green 9702.5325 1068.72 10771.26
4. Effective Plot Area (after
road widening& green [1-
(2+3)]
54,981.018 10,571.492 65,552.51
5. Permissible Ground
Coverage
19,243.356
(@ 35% of net plot area)
6,977.644 26,221(@ 40%
of net plot area)
6. Proposed Ground
Coverage
14,791.250 (@ 26.90% of
net plot area)
3,900.26 18,691.51(@
28.51% of net
plot area)
23.34
7. Permissible F.A.R. 2,19,924.070 (@4) 22,863.84 2,42,787.91
(@3.70 of net
plot area)
8. Proposed F.A.R. 1,93,956.58 47,728.52 2,41,685.10
(@3.69 of net
plot area)
8. LIG and EWS FAR Area - 16,362.63 16,362.63
9. Basement Area 54,548.590 5000.77 59,549.36
10. Non FAR(Mumty,
machine room, Fire
staircase and other
services)
4528.95 20326.69 24,855.64
11. Stilt Area 13,874.09 1,954.24 15,828.33
12. Built Up Area 2,48,505.170 1,09,775.89 3,58,281.06
13. Green Area 13,563.91 -771.1 12,792.81 (@
19.51% of net plot area)
15.97
14. Surface Parking Area 6,187.00 16,536.33 22,723.33 28.37
15. Remaining Open Area 30,141.39 -8,025.27 22,116.12 27.61
16. Maximum Height of
Building (upto terrace)
45 m 79.2 m
5. Built up area calculation details for earlier and expansion project:
S. No. Particulars Existing Area
(m2
)
Expansion
Area(m2
)
Total (Existing + Expansion) (m2
)
1. Proposed F.A.R. 1,93,956.58 47,728.52 2,41,685.10
2. LIG and EWS FAR - 16,362.63 16,362.63
3. Basement Area 54,548.590 5000.77 59,549.36
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 3 of 48
4. Non-FAR 4528.95 20326.69 24,855.64
5. Stilt Area 13,874.09 1,954.24 15,828.33
Total Built Up Area 2,48,505.170 1,09,775.89 3,58,281.06
6. % wise proposed activates details:
S. No. PARTICULARS AREA (Sq.m.) (%)
Plot Area 80,088.18 100
1. Residential Area 16460.05 20.55
2. EWS & LIG 1055.60 1.31
3. High School 400 0.49
4. Club 775.86 0.96
5. Space for road widening 3764.41 4.70
6. Green Area 12792.81 15.97
7. Surface parking Area 22,723.33 28.37
8. Paved area 22116.12 27.65
7. Comparative water and waste water details:
S. No. Particulars EC accorded (KLD) Total (Existing + Expansion)
(KLD)
1. Total Water Requirement 879.06 1465
2. Domestic Water 861.50 1422
3. Total Fresh Water 603.05 1027
4. Wastewater 740.89 1252
5. STP capacity 370 3 STP of capacity 500 KLD, 125 KLD
and 255 KLD
STP 1 (500 KLD) STP 2 (125 KLD) STP 3 (255 KLD)
Buildings served Existing block + Expansion
block E1 + High School
Block A1 + Block B1 Block C1 + Block D1
Fresh Water 739 KLD 84 KLD 172 KLD
Flushing Water 317 KLD 36 KLD 74 KLD
Wastewater 937 KLD 103 KLD 212 KLD
8. Water and waste water requirement details for expansion project:
S. No.
Description Existing (Block
A-R1)
Expansion (E1 Block and High
School)
Total Occupancy
Rate of water
demand
Total Water Requirement
(KLD)
A. Domestic Water
For Existing Block, Expansion E1 Block and High School
Residential Population 9520 198 9718 86 lpcd 835.75
Students 588 588 30 lpcd 176.40
Staff 952 22 974 30 lpcd 29.22
Visitors 950 30 980 15 lpcd 14.70
Total domestic water demand (i) 1056.07 KLD,
say 1056 KLD
B. Horticulture and Landscape
development
9416.66 1 l/m2
/day 9.41 KLD
C. Make up requirement for
swimming pool & Filter
backwash
(435.321
m2
)
(217.14 m2
) 31.96 KLD
Grand Total (A+B+C) 1097.44 KLD,
say 1097 KLD
Domestic Water Requirement 1056 KLD
• Total Fresh water = Fresh (@ 70% of domestic) 739 KLD
• Flushing (@ 30% of domestic) 317 KLD
Wastewater Generated
(80% fresh + 100% flushing + 90% of swimming pool water)
937 KLD
The committee noted that the project proponent through affidavit dated 21/07/2015 has submitted that no activity relating to the expansion of Group Housing Project "VVIP Address"
including civil construction will be done in expansion part without getting environmental clearance.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 4 of 48
The project proponent also submitted Khatuni details/papers related to project. Ghaziabad
Development authority through letter dated 31/MP/2-1/15 dated 10/04/2015 is given approval for
building maps wherein it is also mention that ^^LFky ds e/; ls xqtj jgh ,p0Vh0 ykbu ls fdlh Hkh fuekZ.k dh nwjh mifof/k ds izLrj&3-11-4 ds vuqlkj j[kuh gksxh**. The committee directed that no
construction shall be undertaken on related part of site which is prohibited as above clause by GDA.
The committee discussed the matter and directed to submit following information: 1. There is a change in area statements of ToRs approved in SEAC meeting dated 21/06/2015
and the area statement submitted alongwith EIA report. A detailed explanation/clarification
should be submitted.
2. Sanctioned letter submitted but the copy of maps/drawing showing FAR, proposed built up
area details under the expansion scheme should also be made available.
3. The project proponent should submit an affidavit that there is no change in the proposals
submitted for scoping and proposals being presented before the committee for
appraisal/EIA.
4. No change in basement area and stilt area in the existing/previously issued EC, however
proposal for additional basement as per the sanctioned maps can be undertaken as
committed by project proponent.
5. No podium area is proposed under the project as committed by project proponent. 6. NOC from Fire Department and Airport Authority of India/copy applied should be
submitted. 7. Structural design certificate signed by architect and vetting authority should be submitted.
8. Project proponent submitted that external drain is being constructed by GDA. The committee directed that if it does not complete prior to completion of project, the project
proponent shall make their own provision for safe discharge of treated waste water. In no case, water logging situation should arise. An affidavit in this regard shall be submitted by
the project proponent. 9. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to
2% of project cost (Rs. 1.64 Crore) shall be prepared and approved by Board of Directors of
the company. A copy of resolution as above shall be submitted to the authority alongwith
list of beneficiaries with their mobile nos./address.
The matter shall be discussed after submission of information as above.
2. Group Housing at Plot No-GC-03K/GH-03, Sector-16C, Noida Extension, Greater Noida.-Sri B K
Jain, CEO, VVIP Addresses, NH-58, Ghaziabad. File N0. 3097/DD-Sh.
The committee noted that an application dated 21/05/2015 was made by the project
proponent for environmental clearance of Expansion of Group Housing Project at Plot No-GC-
03K/GH-03, Sector-16C, Noida Extension, Greater Noida, M/s Solitaire Infrahome Pvt. Ltd. The
terms of reference were prescribed in SEAC meeting dated 27/06/2015. Final EIA was submitted
by the project proponent through letter dated 04/8/2015.
A presentation was made by Shri B.K. Jain, CEO, VVIP Address, authorized signatory for
the project alongwith their consultant M/s GRC India Pvt. Ltd. The proponent, through the
documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Expansion of Group Housing Project at Plot No.
GC-03K/GH-03, Sector-16C, Noida Extension, Greater Noida, U.P. M/s Solitaire Infrahome
Pvt. Ltd.
2. Earlier, M/s Solitaire Infrahome Pvt. Ltd. has obtained Environmental Clearance from
SEIAA, U.P. vide Letter no. 1727/Parya/SEAC/1648/2013/AD(VB) dated 11.10.2013 for
the plot area of 31,475 m2 and built-up area of 1,40,796.405 sq.m.
3. Comparative area details of the earlier and expansion project are as follows:
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 5 of 48
PROJECT FEATURES DESCRIPTION
EC Accorded Expansion Total (EC accorded +Expansion)
Estimated Population 5,975 Nos. 763 Nos. 6,738 Nos. (Residents, staffs and visitors)
Estimated Water
Requirement
Construction
Phase
Operation Phase
705 ML
480 KLD
157 ML
94 KLD
862 ML (Agency: Treated water from STP of
GNIDA)
574 KLD (Fresh water = 385 KLD) (Agency:
GNIDA)
Estimated wastewater
Generation
397 KLD 70 KLD 467 KLD
Power Demand 3,080 kVA 570 kVA 3,650 kVA
Source of Power Noida Power Company Limited (NPCL)
Power Back up 2,500 kVA (2 ×
1,250 kVA)
1,030 kVA 3,530 kVA (3 ×1010 + 1 × 500 kVA)
Rain Water Harvesting
Structures
10 Pits - 7 Pits & + 2
Tanks
3 Pits and 2 Tanks
Solid Waste Generation 2,740 kg/day 399 kg/day 3,139 kg/day
Parking Facilities
Required
As per MoEF norms As per Greater Noida Bye
Laws
Proposed
846 ECS
1,057 ECS
1,295 ECS
256 ECS
307 ECS
112 ECS
1,102 ECS
1,364 ECS
1,364 ECS
4. Comparative area details for earlier and proposed project:
SI.
No.
Particulars Existing
(EC
accorded)
(in m2
)
Expansion
(in m2
)
Total
(EC accorded
+ Expansion)
(in m2
)
Percentage
(in %age)
1. Plot Area 31,475.00 100
2. Permissible Ground Coverage (@ 35% of plot
area)
11,016.25
3. Proposed Ground Coverage 7,025.955 +288.55 7,314.51 (@
23.23% of plot
area)
23.23
4. Permissible F.A.R. (@ 2.75 of total plot area) 86,556.25 - 86,556.25
5. F.A.R. Purchased (@ 0.75 of total plot area) - +23,606.25 23,606.25 (@
0.75)
6. Total Permissible F.A.R. (4 + 5) 86,556.25 +23,606.25 1,10,162.50
(@ 3.5)
7. Total Permissible Ancillary area
• Permissible Ancillary area as per
2.75 FAR
• Permissible Ancillary as per
0.75 FAR
-
-
-
+16,524.375
+12,983.438
+3,540.938
16,524.375
12,983.438 (@
15% of 2.75
FAR)
3,540.938 (@
15% of 0.75
FAR)
8. Total Proposed Ancillary area
(including Basement service area) (a) Ancillary Area ( 15% of FAR)
(b) Extra ancillary area part of Main FAR*
- +18,205.317 18,205.317
16,524.375
1,680.942
9. Proposed F.A.R
• FAR achieved for residential +
commercial + community
• Extra ancillary*
84,596.453
(@ 2.687)
84,596.453
-
+25,557.158
+23,876.216
+1,680.942
1,10,153.611
(@ 3.499)
1,08,472.669
1,680.942
10. Total Permissible Commercial area
• Permissible commercial @ 1%
of 2.75 FAR
• Permissible commercial @ 1%
of 0.75 FAR
-
-
-
+1,101.625
+865.563
+236.063
1,101.625
865.563
236.063
11. Total Proposed Commercial area (@ 0.9884% - +1,085.032 1,085.032
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 6 of 48
of total Permissible FAR)**
12. Non FAR
• Stilt area
• Basement area (Excluding
basement service area which is
included in Extra ancillary area)
• Podium area
• Other Non-FAR
56,954.662
4,742.822
27,231.004
15,699.252
9,281.584
-11,425.039
-58.428
-1,027.122
-1,057.905
-9,281.584
45,529.623
4,684.394
26,203.882
14,641.347
-
13. Built Up Area 1,40,796.405 +31,411.204 1,72,207.609
14. Open Area 24,449.045 -302.65 24,160.49
15.
Landscape Area
12,946.451 +306.915 13,253.366
(@ 54.88% of
open area)
42.15
16. Surface Parking area 3,933.36 -793.36 3140.00 9.97
17. Road area 3,815.237 -91.872 3,723.365 11.8
18. Paved area 3,753.997 +289.492 4,043.489 12.85
19. Height of the tallest Building (till terrace) 65 m +6.7 71.70
5. Tower wise comparative details for earlier and proposed project:
S.No. EC Accorded Total (EC Accorded + Expansion)
Towers Height DU Height DU
Tower- A S+1 4 S+22 128
Tower- B S+1 4 S+23 110
Tower- C S+19 109 S+19 114
Tower- D S+16 123 S+19 152
Tower -E and H S+19 2 X 114 S+19 2 X 114
Tower -F and G S+19 2 X 152 S+19 2 X 152
Tower- I S+19 152 S+19 152
Tower-J S+19 114 S+19 114
Total DU 1,038 1,302
6. Built-up area calculation details:
S. No. Particulars Area (in m
2
)
1. Proposed FAR including extra ancillary area 1,10,153.611
2. Ancillary area 16,524.375
3.
Non FAR
• Stilt area
• Basement area (Excluding basement service area which is
included in Extra ancillary area)
• Podium area
45,529.623
4,684.394
26,203.882
14,641.347
Total Built Up Area 1,72,207.609
7. Proposed facilities wise area details:
SI. No. PARTICULARS AREA (Sq.m.) Percentage
(%)
1. Plot Area 31,475.00 100
2. Residential 6,059.809 19.25
3. Commercial 669.212 2.13
4. Community 542.409 1.72
5. Guard room and Meter room 43.08 0.14
6. Landscape area 13,253.366 42.15
7. Surface Parking Area 3,140.00 9.97
8. Road Area 3,723.365 11.8
9. Paved area 4,043.489 12.85
8. Water requirement details earlier and proposed:
SI.
No.
Description Total Occupancy Rate of water
demand
Total Water
Requirement
(KLD)
A. Domestic Water
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 7 of 48
Residential Population 5,859 86 lpcd 504
Staff 293 30 lpcd 9
Visitors 586 15 lpcd 9
Total domestic water demand 522 KLD
B. Horticulture and Landscape
development 13,253.366 m
2
1 lt./m2
/day 13
C. DG Sets Cooling (3 × 1010 kVA
+ 1 X 500 kVA )
0.9 lt./KVA/hr 19
D. Make up & Filter backwash
requirement for swimming pool
20
Grand Total (A+B+C+D) 574 KLD
9. Waste water details earlier and proposed:
Domestic Water Requirement 522 KLD
• Total Fresh water = Fresh (@ 70% of domestic)+ Make up
water for Swimming Pool
365 + 20 = 385 KLD
• Flushing (@ 30% of domestic) 157 KLD
Wastewater Generated
(@ 80% fresh + 100% flushing + 90% Make up & Filter backwash requirement
for swimming pool)
292 + 157 + 18 = 467 KLD
• It is expected that the project will generate approx. 467 KLD of wastewater.
• The wastewater will be treated in the STP of 600 KLD capacity provided within the complex generating
374 KLD of recoverable water from STP which will be recycled within the project for Flushing, DG
Cooling, Horticulture and rest will be discharged to nearby construction activity/sewer line.
10. Solid waste generation details earlier and proposed:
SI.
No.
Category Occupancy kg per capita per day Waste generated (kg/day)
1. Residents 5,864 @ 0.5 2,932
2. Staff 293 @ 0.25 73
3. Visitors 586 @ 0.15 88
4. Landscape waste 3.27 acres @ 0.2 kg/acre/day 0.654
5. STP Sludge 47
TOTAL SOLID WASTE GENERATED 3,140.65 Say 3,141 kg/day
11. Proposed parking details of the project:
SI. No. Description Area
(in m2
)
Norms Parking Proposed (in ECS)
1. Stilt Parking 3,900 @ 30 sq. m./ECS 133
2. Podium Parking 11,220 @ 30 sq. m./ECS 374
3. Basement Parking 21,000 @ 30 sq. m./ECS 700
4. Surface Parking 3,140 @ 20 sq. m./ECS 157
Total Parking Proposed 1,364 ECS
12. The project proposals are covered under category 8"b" of EIA Notification, 2006.
The committee discussed the matter and observed that approved maps with FAR details
have been submitted. Details of ToRs and the details submitted in the EIA report are same. The
committee examine the EIA and found it to be satisfactory and recommended grant of
environmental clearance on the project proposals alongwith general conditions as earlier prescribed
by the authority for construction project and following specific conditions:
1. The proponent shall submit the copy of structural safety certificate/fire NOC showing the details of blocks/towers etc duly vetted by competent authority.
2. 03 m peripheral green shall be provided around the project inside the project boundary.
3. Parking provisions as per Development Authority bye-laws should be made.
4. Revised road section as per norms showing all services in view of fire tender movement.
5. Construction material should be recycled/utilized for internal roads.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 8 of 48
6. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt.
7. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
8. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for
construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement. 9. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be treated in captive STP conforming to prescribed standards of receiving body for designated use.
Monitoring of STP to be done daily till its stabilization. 10. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with
regular testing and monitoring of treated water. 11. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users.
STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
12. Total cost of the project is 498 crore. Environmental Corporate Responsibility (ECR) plan
along with budgetary provision amounting to 2% of total project cost shall be prepared and
approved by Board of Directors of the company. A copy of resolution as above shall be
submitted to the authority. A list of beneficiaries with their mobile nos./address should be
submitted alongwith six monthly compliance reports.
13. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided
in the open areas/ stairs cases. 14. Parking guideline as per Noida Development Authority should be followed. Parking for
disabled persons should be explored. 15. All entry/exit point should be bell mouth shaped.
16. To discharge excess treated waste water into public drainage system, permission from the competent authority to be taken prior to any discharge.
17. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only from the roof top. RWH from green and other open areas shall be done only after permission
from CGWB. 18. An underground Pucca tank for collection/reuse of rain water may be constructed.
19. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
20. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be
carried out as CPCB Guidelines.
21. Crèche to be provided during the construction/operation phase.
22. Provision of separate room for senior citizen with proper amenities shall be made.
23. Protection shall be provided on the windows of the high rise flats for security of residents.
24. Unless and until all the environmental issues are sorted out the occupancy will be restricted
and would be only allowed after achieving the Permission from the competent authority.
25. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law. 26. For any extraction of ground water, prior permission from CGWB shall be taken.
27. Sprinkler to be used for curing and quenching and ready mix concrete may be used for construction.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 9 of 48
28. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
29. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall
be made available to the temporary residents/workers at the project site including the proper
treatment and the disposal of the wastes.
3. Revision and Expansion of Group Housing Project at Plot No-GH-16 A, Sector-1, Greater Noida.-
Sri Rakesh Singh, CEO, 154, 5th Floor, Tower A, Plot No-A-41, Sector-62, Noida. File N0.
3079/AD-H.
The committee noted that an application dated 07/05/2015 was made by the project
proponent for environmental clearance of Revision and Expansion of Group Housing Project at Plot
No-GH-16 A, Sector-1, Greater Noida, U.P. M/s. Morpheus Developers Pvt. Ltd. The terms of
reference were prescribed in SEAC meeting dated 27/06/2015. Final EIA was submitted by the
project proponent through letter dated 05/8/2015.
A presentation was made by Shri Triloki Kumar, authorized representative of project
proponent alongwith their consultant M/s GRC India Pvt. Ltd. The proponent, through the
documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Revision and Expansion of Group Housing
Project at Plot No-GH-16 A, Sector-1, Greater Noida, U.P.
2. Earlier, M/s MMR Infrastructure Developers Private Limited has obtained Environmental
Clearance from SEIAA, U.P. vide Letter no. 1984/Parya/SEAC/1760/2013/OSD(T) dated
12.10.2013 for plot area of 42,309.101 sq.m (or 10.454 acres) and built up area
2,12,034.026 sq.m.
3. M/s. Morpheus Developers Pvt. Ltd. is a 90% Equity subsidiary company of M/s. MMR
Infrastructure Developers Pvt. Ltd. M/s Morpheus Developers Pvt. Ltd. has got the right to
develop and marketing of the Group Housing Project and has in turn got the permission
from GNIDA for development of the project as per Letter No.
GRANO/BUILDERS/2013/671 dated 1st November, 2013.
4. Comparative area details of the earlier and expansion project are as follows:
S. No.
Particulars EC accorded
(in m2
)
Revision
(in m2
)
Expansion
(in m2
)
Total (EC accorded + Revision +
Expansion)
(in m2
)
Percentage (in %age)
1. Plot Area 42,309.101 - +111.069 42,420.170
• Phase-I –
10,000.17
• Phase-II – 32,420
100
2. Permissible Ground Coverage (@ 35% of plot area)
14,808.154 - +38.916 14,847.070
• Phase-I –
3,008.032
• Phase-II –
6,882.033
3. Proposed Ground Coverage
11,715.768 -
1,825.703
- 9,890.065 (@ 23.31% of plot
area)
23.31
4. Permissible F.A.R. 1,16,349.778 - 305.69 1,16,655.468 (@ 2.75)
5. F.A.R. Purchased - - 31,815.128 31,815.128 (@ 0.75)
6. Total Permissible F.A.R. (4 + 5) 1,16,349.778 - 32,120.818 1,48,470.595 (@ 3.5)
7.
Proposed F.A.R.
1,16,288.200 (@ 2.748)
-
+31,964.341
1,48,252.541 (@ 3.495)
• Phase-I –
35,012.288
• Phase-II -
1,13,270.253
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 10 of 48
8. Total Permissible Shopping
area
• Permissible shopping @ 1% of 2.75 FAR
• Permissible shopping @ 1% of 0.75 FAR
-
- -
-
- -
+1,484.474
+1,166.554 +318.151
1,484.474
1,166.554 318.151
9. Total Proposed shopping area (@ 97.17% of total permissible shopping area)
• Phase-I
• Phase-II
- - +1,442.474
348.00 1,094.474
1,442.474
348.00
1,094.474
10. Total Permissible Ancillary area
• Permissible Ancillary
area as per 2.75 FAR
• Permissible Ancillary
area as per 0.75 FAR
17,452.467 17,452.467
-
- -
-
+4,818.138 + 45.866
+4,772.272
22,270.605 17,498.333 (@ 15% of 2.75
FAR) 4,772.272 (@ 15% of 0.75
FAR)
11.
Total Proposed Ancillary area 6,739.436 - +13,910.913 20,650.349 (@ 13.91% of Permissible FAR)
12. Non FAR
• Stilt area
• Upper Basement area
including services
• Lower Basement area
including services
• Other Non-FAR
89,006.39 -
36,646.65
36,646.65 15,713.09
-1,082.836
-
-541.418 -541.418
15,713.09
+4,739.499 +4,739.499
-
- -
76,949.963 4,739.499
36,105.232
36,105.232 0.00
13. Built Up Area 2,12,034.026 - +33,818.827 2,45,852.853
14. Open Area 30,593.242 - +1,936.863 32,530.105
15.
Landscape Area
15,381.13 - +1019.674 16,400.804
(@ 50.42% of open area)
38.66
16. Road and remaining open area 15,212.112 - 917.189 16,129.301 38.1
17. Maximum Height of Building (till terrace)
43.5 m - +37.95 m 81.45 m
5. Tower wise comparative details: S.No. EC Accorded Total (EC Accorded + Expansion)
Tower’s Name Height DU Tower’s Name Height DU
Tower- 1 G+12 104 Tower- A1 S/C+18 108
Tower- 2 G+12 104 Tower- A2 S/C+18 108
Tower- 3 G+12 104 Tower- A3 S+18 108
Tower- 4 G+11 78 Tower- A4 S+18 108
Tower- 5 G+11 48 Tower- B1 S/C+23 + (Duplex) 96
Tower- 6 G+11 47 Tower- B2 S/C+23 92
Tower- 7 G+11 47 Tower- B3 S+23 + (Duplex) 96
Tower- 8 G+11 48 Tower- B4 S+23 + (Duplex) 96
Tower- 9 G+12 78 Tower- B5 S+23 184
Tower- 10 G+12 104 Tower- B6 S+23+ 184
Tower-11 G+12 104 Tower- B7 S+23 184
Tower- 12 G+12 104 Tower- B8 S+23+ (Duplex) 96
Tower- B9 S+23 184
Tower- B10 S/C+24+ (Duplex) 100
Total DU 970 1,744 Residential and 148 Servant units
6. Built up are calculation details: S. No. Particulars
Area (in m2
)
1. Proposed FAR 1,48,252.541
2. Proposed Ancillary area 20,650.349
3. Non FAR
• Stilt area
• Upper Basement area including services
• Lower Basement area including services
76,949.963
4,739.499
36,105.232
36,105.232
Total Built Up Area 2,45,852.853 m
2
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 11 of 48
7. Comparative salient features details of the project:
PROJECT FEATURES DESCRIPTION
EC Accorded Revision + Expansion Total (EC accorded +
Revision + Expansion)
Estimated Population 5,801 Nos. 3,557 Nos. 9,358 Nos. (Residents, staffs
and visitors)
Estimated Water Requirement
Construction Phase
Operation Phase
1,060 ML
467 KLD
70 ML
339 KLD
1,230 ML (Agency: Treated
water from STP of GNIDA)
806 KLD (Fresh water = 544
KLD) (Agency: GNIDA)
Estimated wastewater Generation 348 KLD 310 KLD 658 KLD
Power Demand 5,300 kVA -120 kVA 5,180 kVA
Source of Power Uttar Pradesh Power Corporation Limited (UPPCL)
Rain Water Harvesting Structures 10 Pits -3 Pits and 4 Tanks 7 Pits and 4 Tanks
Solid Waste Generation 2,452 kg/day 1,919 kg/day 4,371 kg/day
Parking Facilities
Required
As per MoEF norms
As per Greater Noida Bye Laws
Proposed
1,163 ECS
1,455 ECS
2,308 ECS
320 ECS
401 ECS
- 452 ECS
1,483 ECS
1,856 ECS
1,856 ECS
8. Water and waste water requirement details:
SI.
No.
Particulars EC
Accorded
(KLD)
Total (Revision + Expansion)
(KLD)
Phase-I Phase-II Total
1. Total Water Requirement 467 198 608 806
2. Domestic Water 405 173 554 727
3. Total Fresh Water 293 136 408 544
4. Wastewater 348 163 495 658
5. STP capacity 420 195 595 2 STPs of 195 and 595 KLD
capacity
9. Solid waste generation details:
EC Accorded Revision & Expansion
Phase-I Phase-II Total
Solid waste generated 2,452 kg/day 1,041 kg/day 3,330 kg/day 4,371 kg/day
10. The project proposals are covered under category 8"b" of EIA Notification, 2006.
The committee discussed the EIA report/the presentation made by the project proponent and
observed that the project proponent/consultant were not able to explain the proposed expansion in a justified manner. The committee defer the matter with direction to prepare the proposals
appropriately and submit for further consideration of the matter. The matter the deferred till
submitted of information as above. The committee also directed to give specific attention to following points while preparing the presentation next time:
1. The project proponent should submit an affidavit that there is no change in the proposals submitted for scoping and proposals being presented before the committee for appraisal/EIA.
2. The project proponent should submit an affidavit that there is no construction proposed in the towers/blocks where construction has already been started. There is no construction started in
the towers where expansion is proposed under this expansion. 3. Justification regarding comparatively less increase in no. of DU against the increase in no. of
floors. Submit floor wise details about Dwelling Units proposed earlier and after expansion.
4. Status of floor wise construction with photographs.
5. Certificate from architect that no. of floors and nos. of DU has been constructed as per bye-
laws.
6. Structural design certificate for revised proposal/expansion signed by architect and vetting
authority should be submitted.
The matter shall be discussed after submission of information as above.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 12 of 48
4. Group Housing Project-3 at Kanpur Road, Lucknow, U.P. Sri Swapnil Nigam, Manager,
Miranpur Pinwat, Lucknow-Kanpur Road, Lucknow. File N0. 2664/SPO-V
The committee noted that an application dated 27/09/2014 was made by the project
proponent for environmental clearance of Environmental Clearance of Group Housing Project-3 at
khasra no. 233, 218, 219, 211, 212, 220, 221, 227, 228, 262, 209, 210, 214, 215, 229, 133, 192, 197,
199, 200, 201, 224, 225, 226, 239, 130, 195, 196, 213, 240 and 193, Kanpur Road, Lucknow, U.P.
M/s Paarth Infrabuild Pvt. Ltd. The terms of reference were prescribed in SEAC meeting dated
25/05/2015. Final EIA was submitted by the project proponent through letter dated 06/8/2015.
A presentation was made by Shri Abhishek Singh, authorized representative of project
proponent along with their consultant M/s Greencindia Consulting (P) Ltd. The committee
discussed the matter and observed that the project proponent have not brought the complete
information in their presentation. The committee directed to defer the matter till next day meeting
and directed to appear with complete documents in meeting dated 10/10/2015.
5. Expansion of Group Housing Project located at Sector-1, Plot No-GH-05A, Greater Noida- Sri
Satyapal Singh, Director, H-123, Sector-63, Noida. File N0. 2989/OSD-T
The committee noted that an application dated 08/04/2015 was made by the project
proponent for environmental clearance of Expansion of Group Housing Project “Paramount
Emotions” at Plot No. GH-5 A, Sector-1, Greater Noida, U.P. M/s. Paramount Homeland Pvt. Ltd.
The terms of reference were prescribed in SEAC meeting dated 10/07/2015. Final EIA was
submitted by the project proponent through letter dated 19/8/2015.
A presentation was made by Shri Madan Bisht, representative of project proponent
alongwith their consultant M/s Grass Roots Research & Creation India (P) Ltd. The proponent,
through the documents submitted and the presentation made, informed the committee that:-
1. The Environmental Clearance is sought for Expansion of Group Housing Project
“Paramount Emotions” at Plot No. GH-5 A, Sector-1, Greater Noida, U.P. M/s. Paramount
Homeland Pvt. Ltd.
2. M/s Paramount Homeland Pvt. Ltd. has been granted Environment Clearance for Group
Housing Project “Paramount Emotions” located at Plot No. GH-5A, Sector-1, Greater
Noida, District Gautam Budh Nagar, Uttar Pradesh vide reference no.
268/988/SEAC/2010/AD(H) dated 6th May,2013 for plot area 45,641 sq.m (11.2781
acres) and built up area 1,79,136.24 sq.m.
3. The Project Proponent expand the project built up area from 1,79,136.24 sq.m. to
247496.957 sq. m.
4. Comparative area details of earlier and proposed expansion project are as follows:
S.NO. DESCRIPTION VALUES IN
ACCORDED
EC
EXPANSION TOTAL
(EXISTING+
EXPANSION)
Percentage
wise area
1. Total Plot Area 45,641 (11.2781 acres) 100
2. Permissible ground coverage
(@ 35% of plot area
15974.35
3. Proposed ground coverage 10454.59 795.74 11250.33 24.65
4. Total Permissible FAR (a+b) 125512.75 34230.75 159743.5 350
a. Permissible FAR
(@275% of plot area)
125512.75
b. Purchasable FAR --- 34230.75 34230.75
5. Permissible Additional FAR
(@15% of total permissible
18826.91 5134.615 23961.525
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 13 of 48
FAR)
6. Total proposed FAR 123774.019 35915.03 159689.046 349.8
7. Proposed Additional 15%
FAR
12693.216 4596.586 17289.802 37.9
8. Total Basement 1 area (a+b) 40409.256 88.53
a. Basement area included
in 15% additional FAR
1127.38 --- 1127.38
b. Basement area
excluding 15% additional
FAR
39281.876 --- 39281.876
9.
Stilt/podium Area 7014.329 27849.101 34863.43 76.38
a. Stilt/podium area included
in FAR & 15% Additional
FAR
3627.197
b. Stilt excluding FAR &
15% additional FAR
3387.132 27849.101 31236.233
10. Open Area 35186.41 -795.74 34390.67 75.35
11. Landscape Area (@50% of
open space)
17300 37.67
12. Total Built up area
(6+7+8b+9b)
179136.24 68360.717 2,47,496.957
6. Proposed land use details: S. N. DESCRIPTION EXISTING (AREA
INSQ.M.) % Wise
area Expansion (AREA IN
SQ.M. ) % wise
area
1 Area under residential
facility (GC)
9265.59 20.3 10,053.33 22
2 Area under commercial
(GC)
589 1.3 597 1.3
3 Area under community
(GC)
600 1.3 600 1.3
4 Area Under Landscaping 17300 38 17300 38
5 Area under road &
remaining open area
17,886.41 39.19 17,090.67 37.4
TOTAL PLOT AREA 45641 100% 45641 100%
7. Built up area calculation details; S.
No.
Particulars EC ACCORDED
AREA
EXPANSION+ EXISTING
AREA (in m2
)
1. FAR 123774.019 159689.046
2. Additional FAR 12693.216 17289.802
3. Basement area excluding 15% additional FAR 39281.876 39281.876
4. Stilt excluding FAR & 15% additional FAR 35186.41 31236.233
Total Built-up area 179136.24 247496.957
8. Tower wise FAR details of earlier and proposed expansion project: S. No. TOWER Values in Accorded
EC
Expansion Total (Existing+
Expansion)
1 TOWER A 9,155.94 2,284.79 11440.731
2 TOWER B 5,381.80 1,836.69 7218.492
3 TOWER C 9,111.38 2,284.79 11396.17
4 TOWER D 9108.228 2,517.95 11626.18
5 TOWER E 4623.609 1,648.06 6271.672
6 TOWER F 4623.609 1,648.06 6271.672
7 TOWER G 9108.234 2,107.63 11215.86
8 TOWER H 5,484.99 384.61 5869.602
9 TOWER J 6,906.93 484.04 7390.973
10 TOWER K 6,674.76 468.78 7143.541
11 TOWER L 6,674.76 468.78 7143.541
12 TOWER M 6,906.93 484.04 7390.973
13 TOWER N 5,484.99 384.61 5869.602
14 TOWER P 5,484.99 1,283.38 6768.386
15 TOWER Q 7142.022 2,084.45 9226.472
16 TOWER R 4,009.35 5,904.81 9914.161
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 14 of 48
17 TOWER S 4,009.35 5,904.81 9914.161
18 TOWER T 7142.026 2,084.45 9226.472
19 TOWER U 5484.99 1,283.40 6768.386
20 COMMERCIAL 1255.127 341.873 1597
23 METER Room ---- 25 25
TOTAL 123,774.016 35915.03 159689.046
9. Comparative salient features details of earlier and proposed expansion project are as
follows: PROJECT
FEATURES
Values in accorded EC Expansion Total (Existing + Expansion)
Estimated Population 8080 persons 1,991 persons 10071 persons
Estimated Water
Requirement
Construction
Phase
Operation
Phase
896 ML (Agency: Treated
water from Private
Tanker)
641 KLD (Fresh water =
435 KLD) (Agency:
Municipal Supply)
342ML (Agency: Treated
water from Private
Tanker)
179 KLD (Fresh water =
545 KLD) (Agency:
Municipal Supply)
1238 ML (Agency: Treated
water from Private Tanker)
820 KLD (Fresh water = 545
KLD) (Agency: Municipal
Supply)
Estimated wastewater
Generation
532 KLD 138 670 KLD
Power Demand 4900 KVA 1,550 6,450 KVA
Power Backup 3020 KVA (4 X 380 + 2 X
75) capacity
1,250 4270 kVA (4 X 500 + 2 X 1010
+ 250 kVA each) capacity One
of 1010 kVA and one of 500
kVA will be kept as stand by
Source of Power Noida Power Company Limited (NPCL)
Rain Water Harvesting Pits
20 Pits -14 pits & +4 tanks 6 Pits & 4 tanks
Solid Waste
Generation
3741.48 kg/day 879.52kg/day 4,621 kg/day
Parking Facilities
Required
Proposed
1592 ECS
1676 ECS
405 ECS
321 ECS
1997 ECS
1997 ECS
10. Water and waste water details for existing and expansion project: S. No. Description Area (m
2
)
or D.U
Total
Occupancy
Rate of
water
demand
(lpcd)
Total Water
Requirement
(KLD)
% in term
of total
water
requirement
A. Domestic Water
• Residents 1802 8109 86 697.374 85.04
• Service
personnel
288 648 86 55.728 6.79
• Visitors 876 15 13.14 1.60
• Maintenance
Staff
438 30 13.14 1.60
Total domestic water demand 779.382
B. Horticulture and
Landscape development
17300 1
l/sqm/day
17.3 2.10
C. *DG Sets (4*500 + 2*1010
KVA + 1*250 KVA)
0.9
l/KVA/hr
23.058 2.81
Grand Total (A+B+C) = 819.74KLD say 820 KLD
Domestic Water Requirement 779
• Fresh (70% of domestic) 545
• Flushing (30% of domestic) 234
Waste Water Generated
(80% fresh + 100% flushing)
670
11. Solid waste management details for existing and expansion project: S. No.
Category Population kg per capita per day
Waste generated (kg/day)
% in term of total waste
generated
1. Residents
• Residents 8109 @ 0.5 4054.5 87.76
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 15 of 48
• Service
personnel
648 @0.5 324 7.01
• Visitors 876 @ 0.15 131.4 2.84
• Maintenance
Staff
438 @ 0.25 109.5 2.36
2. Landscape waste
(4.27 acres)
@ 0.2
kg/acre/day
0.854 0.018
TOTAL SOLID WASTE GENERATED 4620.254
say 4621 kg/day
100
12. The project proposals are covered under category 8"b" of EIA Notification, 2006.
The committee discussed the matter and recommended grant of environmental clearance on
the project proposals alongwith general conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. Provision of parking should be restricted to ECS as required under Development Authority
bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs as obtained from different Department should be submitted.
4. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
5. Approach road location should be clearly marked on layout and should be submitted.
6. Necessary planning for any anticipated expansion should be incorporated in present design in
view of structural stability.
7. An underground water body shall be planned within the premises for storage of rain water.
8. Structural design certificate signed by architect and vetting authority should be submitted.
9. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and Handling) Rules, 2000 (as amended).
10. 03 m peripheral green shall be provided around the project inside the project boundary. 11. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt. 12. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked. 13. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for
construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement.
14. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be treated
in captive STP conforming to prescribed standards of receiving body for designated use.
Monitoring of STP to be done daily till its stabilization.
15. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with
regular testing and monitoring of treated water.
16. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
17. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to 2%
of total project cost shall be prepared and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority. A list of beneficiaries with
their mobile nos./address should be submitted alongwith six monthly compliance reports.
18. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided
in the open areas/ stairs cases.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 16 of 48
19. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
20. All entry/exit point should be bell mouth shaped.
21. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
22. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only
from the roof top. RWH from green and other open areas shall be done only after permission
from CGWB. 23. An underground Pucca tank for collection/reuse of rain water may be constructed.
24. Height of the stack should be provided based on combined DG sets capacity and be 6mt higher than the tallest building.
25. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be carried out as CPCB Guidelines.
26. Crèche to be provided during the construction/operation phase. 27. Provision of separate room for senior citizen with proper amenities shall be made.
28. Protection shall be provided on the windows of the high rise flats for security of residents. 29. Unless and until all the environmental issues are sorted out the occupancy will be restricted
and would be only allowed after achieving the Permission from the competent authority.
30. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
31. For any extraction of ground water, prior permission from CGWB shall be taken.
32. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
33. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
34. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall
be made available to the temporary residents/workers at the project site including the proper treatment and the disposal of the wastes.
6. Group Housing “Spring Meadows” at Plot No-GH-07-A, Techzone-4, Greater Noida- Sri Gajen
Jain, Director, 16- 17FF, Konark Building RDC, Ghaziabad. File N0. 2965/DD-Sh.
The project proponent did not appear. The committee discussed and deliberated that project
file should be closed and should be opened only after request from the project proponent. The file
shall not be treated as pending at SEIAA/SEAC.
7. Group Housing Project “Aunipark” at Plot No-INS-02, CHI-V, Yamuna Expressway, Greater
Noida. Sri Dinesh Kumar, GM, File N0. 3272/DD-Sh.
The committee noted that the proposals do not include details of the floors 1-5. Complete
details should be submitted for which EC required alongwith is proposed landuses of the project
site. Firm up plan should be submitted. The project proponent submits that they should be deferred
for this meeting and they shall submit complete information at the earliest. The committee defer the
matter till submission of complete proposals. The matter shall not be treated as pending with
SEAC/SEIAA. 8. Revision of Group Housing project “Saya Gold Avenue” at Plot No-10 (10/1), Vaibhav Khand,
Indirapuram, Ghaziabad. Sri Manoj Jai, CEO, GH-11, Ahinsa Khand-II, Indirapuram,
Ghaziabad.File N0. 3312/DD-Sh.
The committee noted that an application dated 05/08/2015 was made by the project
proponent for environmental clearance of Revision of Group Housing project “Saya Gold Avenue”
at Plot No-10 (10/1), Vaibhav Khand, Indirapuram, Ghaziabad, U.P. M/s Saya Homes Pvt. Ltd.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 17 of 48
A presentation was made by Shri Jatin Goyal, representative of project proponent alongwith
their consultant M/s Grass Roots Research & Creation India (P) Ltd. The proponent, through the
documents submitted and the presentation made, informed the committee that:-
1. The Environmental Clearance is sought for Revision of Group Housing project “Saya
Gold Avenue” at Plot No-10 (10/1), Vaibhav Khand, Indirapuram, Ghaziabad, U.P. M/s
Saya Homes Pvt. Ltd.
2. Environmental clearance for the earlier proposal was issued through SEIAA letter no.
1960/Parya/SEAC/1327/2013/DD (Sh) dated 12th
Oct., 2013 to Shipra Sun City located at
plot no. 10, Vaibhav Khand, Indirapuram, Ghaziabad, M/s Shipra Estate Ltd.
3. Now, M/s Shipra Estate Ltd. has transferred plot 10/1 (type-C) measuring to 20036 sqm
alongwith the sanctioned FAR to M/s Saya Homes Pvt. Ltd. by way of transferred deed
duly registered in the office of sub registrar vide no. 1/29584/145-182/8688 dated
05/05/2015. M/s Shipra Estate Ltd. also submitted an undertaking that they have not
started any kind of construction activity on any other land parcels on the said plot which is
mentioned in EC. M/s Shipra Estate Ltd. further undertakes that they shall submit their
revised proposal for environmental clearance before the start of construction on the
balance land parcels comprised under plot no. 10, if required.
4. M/s Saya Homes Pvt. Ltd. has submitted that plot no. 10/1 is a part and parcel of plot no.
10, Vaibhav Khand, Indira Puram Ghaziabad for which an environmental clearance dated
12/10/2013 was obtained by M/s Shipra Estate Ltd. from SEIAA. The subject plot has
now been transferred to M/s Saya Homes Pvt. Ltd. so they are presenting their case before
SEAC for revised EC. Their building plans have been revised for which approval has
been obtained from GDA. Structural stability study for the revised building plans has been
done through IIT.
5. Area details of the project (plot 10/1) are as follows:
S. No. Particulars Area (in m
2
) In terms of %
1. Plot Area 20,036 100
2. Ground Coverage 4,267.377 21.30
3. Permissible FAR (including community building) 1,62,473.869
4. Services FAR (5% ) 8,123.668
5. Total Permissible FAR 1,70,597.537
6. Total Proposed FAR
• Residential FAR
• Community Building Area
• Service FAR
1,69,979.955
1,59,253.259
2,500
8,226.696
7. Total Basement Area (3 Nos.) 48,794.046
Basement-I 16,264.682
Basement-II 16,264.682
Basement-III 16,264.682
8. Stilt 11,958.980
9. Total Built Up Area (6+7+8) 2,30,732.981
10. Open Area (1-2) 15,768.623
11. Landscape Area (@ 51.65% of the open area) 8130.91 40.58
12. Road Area 4,239.02 21.16
13. Remaining Open area (1-2-11-12) 3,398.693 16.96
14. Height of the tallest building (upto terrace) 144.25 mtrs
6.Tower details of the project:
S. No. Tower Dwelling
Units
Floors Ground
Coverage
FAR Service
FAR
1. Tower-SG 1 504.508 16,749.550 717.527 204 S+P+34
2. Tower-SG 2 593.087 20,909.974 520.640 250 S+P+36
3. Tower-SG 3 430.7 16,936.736 1317.408 156 S+P+39
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 18 of 48
4. Tower-SG 4 584.649 23,970.617 1049.059 164 S+P+41
5. Tower-SG 5 584.649 24,223.953 1049.059 164 S+P+41
6. Tower-SG 6 430.7 16,797.285 1317.408 156 S+P+39
7. Tower-SG 7 634.577 22,947.886 1538.068 322 S+P+36
8. Tower-SG 8 504.508 16,717.257 717.527 204 S+P+34
9. Community
Building
2,500
Total 4,267.37 1,61,753.258 8,226.696 1,620
7.Built up area calculation details:
S. No. Particulars Area (in m
2
)
1. Proposed FAR
• Residential FAR
• Service FAR
• Community Building Area
1,69,979.955 1,59,253.259
8,226.696
2,500
2. Basement Area (3 Nos.) 48,794.046
3. Stilt Area 11,958.980
Total Built Up Area 2,30,732.981m
2
8.Salient features details of the project:
PROJECT FEATURES DESCRIPTION
Estimated Population 9,565 Nos. (Residents, staffs and visitors)
Estimated Water Requirement
Construction Phase
Operation Phase
1150 ML (Source: Treated water from nearby STP)
759 KLD (Fresh water = 532 KLD*) (Source: Ghaziabad
Development Authority)
Estimated wastewater Generation 649 KLD
Power Demand 5,310 KVA
Source of Power Paschimanchal Vidyut Vitran Nigam Limited (PVVNL)
Rain Water Harvesting Structures 2 Pits and 2 Tanks
Solid Waste Generation 4,921 kg/day
Parking Facilities
Required
Proposed
As per MoEF norms: 1,642 ECS
As per Ghaziabad Bye Laws: 2,439 ECS
2,899 ECS
9.Population details of the project:
S. No. Unit Type Nos. /Area PPU Total Population
1.) Residential 9,315
a. Permanent Resident 1,620 @ 5 persons per unit 8100
b. Staff @ 5% of the residents 405
c. Visitors @10% of the residents 810
2.) Community Center 2,500 m
2
@1 person /10sq.m. 250
a. Staff @ 10% of the
community center
population
25
b. Visitors @90% of the community center
population
225
Total Population 9,565
10. Water calculation details:
S. No. Unit Type Occupancy/Area Per capita demand Total Water
requiremend (KLD)
A. Domestic water
1 Residential
Residents 8,100 86 696.6
Staff 405 15 6.075
Visitors 810 30 24.3
2 Commercial
Staff 25 30 0.75
Visitors 225 15 3.375
Domestic Water Requirement (1+2) 731.1 KLD or 731 KLD
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 19 of 48
B. Horticulture 8,130.91 m
2
1lt./sqm/day 8.1
C. Filter Backwash 15
D. Make up (recirculation)
water for swimming pool
5
Total Water Requirement (A+B+C+D) = 759.2or 759 KLD
11. Waste water details:
Domestic Water Requirement 731 KLD
Fresh Water Requirement* (@ 70 % of the domestic water) 512 KLD
Total Fresh Water Requirement 512+15+5 = 532 KLD
Flushing Water Requirement (@ 30% of the domestic water) 219 KLD
Wastewater Generated (@ 80% of the fresh water + 100% of the flushing
water + 100% of filter backwash + 100% of swimming pool)
410+219+15+5= 649 KLD
12. Solid waste generation details:
S. No. Category Occupancy kg / capita / day Waste generated
(kg/capita/day)
1. Residents 9,315 @ 0.5 kg/capita/day 4,657.5
2. Staff 430 @ 0.25 kg/capita/day 107.5
3. Visitors population 1,035 @ 0.15 kg/capita/day 155.25
4. Landscape waste
(2.009acres)
@ 0.2 kg/acre/day 0.40
TOTAL SOLID WASTE GENERATED 4,920.65 say 4,921 kg/
day
STP sludge 38.76 kg/day
13. Parking details of the project:
S.No Particular Area proposed for
parking (m2
)
Area required/ECS Parking Proposed (ECS)
1. Stilt 11,958.980 28 427
2. Basement- I Parking 15,818.618 32 494.33 * 2 (Stack) = 989 ECS
3. Basement-II Parking 15,818.618 32 494.33 * 2 (Stack) = 989 ECS
4. Basement-III Parking 15,818.618 32 494
Total Parking Proposed 2,899
14. The project proposals are covered under category 8"b" of EIA Notification, 2006.
The committee discussed the matter and observed as follows:
1. In view of undertakings given by M/s Shipra Estate Ltd., the environmental clearance dated
12/10/2013 for plot no. 10 Vaibhav Khand, Indira Puram Ghaziabad shall become null and
void.
2. The matter of environmental clearance for plot no. 10/1 M/s Saya Homes Pvt. Ltd. shall be
treated as a fresh case and not as a revision of earlier EC dated 12/10/2013 issued for plot
no. 10, M/s Shipra Estate Ltd.
3. An affidavit shall be submitted by both M/s Shipra Estate Ltd. and M/s Saya Homes Pvt.
Ltd. that no construction has been undertaken on plot no. plot no. 10 Vaibhav Khand,
Indirapuram Ghaziabad and plot no. 10/1 Vaibhav Khand, Indira Puram Ghaziabad
respectively.
The committee, subject to compliance of above points, recommended following TORs and
general guidelines for conducting EIA studies regarding the proposals. Further PP has requested
the committee to accept the baseline data generated during March to May2013 for its earlier EIA
report. The committee also directed PP to submit EIA report as per MoEF guidelines:
Additional TORs : 1. Specific area statements regarding proposed expansion.
2. Comparative area and other environmental parameter statements showing values earlier and
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 20 of 48
proposed as expansion.
3. All approved revised drawings/maps alongwith all approved revised services plans. All
original maps should be shown during EIA presentation.
4. The revised structure design certificate by qualified structure engineer should be submitted.
The structural design certificate should preferably be vetted by IITs/CBRI. Provision of
alarm system, to timely notify the employees/residents, in case of occurrence of
earthquake/other natural disasters/fire should be provided.
5. Status of construction undertaken till date (block wise/tower wise/floor wise).
6. Compliance of earlier EC.
7. Master plan of the area showing proposed project.
8. Permissible uses of the proposed site as per zoning regulation.
9. Allotment letter from concerned development authority.
10. Physical features within 30 m of the project sites with their ownership.
11. Section details of all road.
12. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
13. Details of land Scape plan.
14. Land use approved by the competent authority.
15. Complete details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
16. Plan for no of trees, one tree per 80.0sq.mt.of area.
17. Use of reflecting paints on roof top and side walls.
18. Details of rain water harvesting are to be given.
19. Provision of 100% solar lighting along the road site, stair cases, common places.
20. A site plan showing the project site and its surroundings with physical features and
topographical details, such as land use, contours and drainage pattern, along with
photographs of the site from all four sides, should be included in the background
information.
21. 10% EWS / LIG housing provision shall be made as per Development Authority bye-laws. 22. Sanctioned plans/maps regarding the project with all services plans.
23. All plans and elevation sections/all service plan/landscape plan/standard electrification
plan/drainage/sewerage plan.
24. Structural plan is to be submitted signed by qualified structural designer.
25. All service plans like sewer drainage water supply rain water harvesting fire fighting
landscape plan is to be submitted.
26. Section of all inter roads as proposed along R/W and C /W as well dimension is to be
to map.
27. Examine in detail the proposed site with reference to impact on infrastructure covering
water supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw
wastes from the complex on land/water body and into sewerage system.
28. Water requirement and water management plan alongwith necessary permissions for
discharge.
29. Hydro-geological investigations be carried out and obtain permission from Central Ground
Water Authority for withdrawal of ground water.
30. Consider soil characteristics and permeability for rainwater harvesting proposals, should be
made to prevent ground water contamination. Maximize use of treated water by recycling
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 21 of 48
and utilization of rainwater.
31. Make provision for safety against failure in the operation of wastewater treatment facilities.
Identify acceptable outfall for treated effluent.
32. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
33. Landscape plan, green belts and open spaces may be described separately.
34. Study the existing flora and fauna of the area and the impact of the project on them.
35. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
36. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
37. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
38. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.
39. Identification of recyclable wastes and waste utilization arrangements may be made.
40. Explore possibility of generating biogas from biodegradable wastes.
41. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission and
refuse including MSW, biomedical and hazardous wastes. Special attention should be made
with respect to bird menace.
42. Provisions made for safety in storage of materials, products and wastes may be described.
43. Disaster management plan should be prepared.
44. Traffic management plan including parking and loading/unloading areas may be described.
Traffic survey should be carried out both on weekdays and weekend.
45. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF.
46. Exclusive Parking area in the basement (excluding other facilities) and surface is to be
clearly mentioned.
47. Provide service road for entry and exit to project site.
48. Use of local building materials should be described.
49. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with
provisos of sampling port for monitoring be described.
50. Work out MGLC for the combined capacity of DG sets.
51. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
52. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
53. Examine separately the details for construction and operation phases both for Environmental Management Plan and Environmental Monitoring Plan.
54. Total cost is 350 crores. Environment Corporate Responsibility (ECR) plan along with
budgetary provision of minimum 2% of the project cost as discussed in meeting shall be
submitted on need base assessment study in the study area.
55. Details of all internal and peripheral roads width.
56. Source and quantity of required water during construction and management of generated
waste water.
57. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 22 of 48
58. Declare/submit the running cost of STP and other environmental management services (e.g.,
Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the
proposals which are to be including in the allotment letters.
59. The proponent will submit the schedule of monitoring/data collection programme to the
Office of Directorate, Member Secretary, UP Pollution Control Board and District
Magistrate of related District.
60. Aforesaid proposal is the part of Shipra Suncity (Shipra Estate) with an overall sanctioned
FAR 2.5 (including purchasable FAR) and the same shall be maintained.
General Guidelines:
a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested
by Public Notary, stating that:
I. “There is no litigation pending against the project and/or land in which the project is proposed to be set up (please give name & ownership etc. of the project) and that for any
such litigation what so ever, the sole responsibility will be borne by the Project proponent.” II. “No activity relating to this project (i.e. name of the project) including civil construction
has been undertaken at site except fencing of the site to protect it from getting encroached and construction of temporary shed(s) for the guard(s). (if fencing has not been done, then
the same may be deleted). III. “I/We hereby give undertaking that the data and information given in the application,
enclosures and other documents are true to the best of my knowledge and belief and I/We
am/are aware that if any part of the data and information submitted is found to be false or
misleading at any stage, the project will be rejected and clearance given, if any to the
Project will be revoked at our risk and cost.” IV. Project does not fall under any buffer zone of no-development as declared /identified under any
law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with
EIA.
c. Current, site photographs viewing towards the project area from four directions indicating date
of photograph taken, direction from which taken, name of the project, and signature of Project
proponent along with consultant with seal should be submitted, so as to ensure that no
construction has been started before the grant of EC.
d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of
2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of
representativeness and reliability of baseline environmental attributes detailed under EIA
manual January, 2001 and other guidelines in the matter. e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically
mentioned. The consultant shall certify that his accreditation is for the sector for which this EIA is prepared.
f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with their complete details including their accreditation, if any shall be indicated.
g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in
the preparation of these reports and the Name of laboratory through which the samples have
been got analysed should be stated in the report. It shall clearly be indicated whether said
laboratory is accredited by NABL or approved under the Environment (Protection) Act, 1986 (Please refer MoEF office memorandum dated 4th August, 2009). The name project leader of
the EIA study shall also be mentioned. h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted
within 15 days from the date of receipt of the letter and remaining of the information’s is to be
submitted along with the EIA.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 23 of 48
9. Expansion of Group Housing “Purvanchal Royal City” at Plot No-GH-05, Sector-CHI, Greater
Noida. Sri Shah Alam, MD, Purvanchal House, N-04, Sector-18, Noida. File N0. 3325/AD-Sub.
The committee noted that an application dated 08/08/2015 was made by the project
proponent for environmental clearance for expansion of Group Housing “Purvanchal Royal City” at
Plot No-GH-05, Sector-CHI, Greater Noida..
A presentation was made by Shri Jauhar Abbas, authorized representative of project
proponent alongwith their consultant M/s Ind Tech House. The proponent, through the documents
submitted and the presentation made, informed the committee that:-
1. The Environmental Clearance is sought for expansion of Expansion of Group Housing
“Purvanchal Royal City” at Plot No-GH-05, Sector-CHI, Greater Noida. M/s Purvanchal
Projects Pvt.Ltd.
2. The Environmental Clearance (EC) for the earlier proposal was issued through SEIAA,
U.P., vide letter no. 602 / Praya / SEAC / 1482/ 2012 / DD(SH) Dated 21th June, 2013.
3. Comparative details of existing and expansion proposals:
Sl.
No.
Particulars As per Approved
EC
As per revised
proposal
Quantity
Change
% Change
1. Plot Area 87965.51 87965.51 No Change No Change
2. Built Up Area 381956.462 455996 74039.54 inc 19.38 inc
3. Permissible FAR 241905.153 307,879 65973.85 inc 27.27 inc
4. Proposed FAR (350) 241,876.09 307762 65886 Inc 27.23 inc
5. Max. No. of Floors 2B+G+23 2B+G/ST/PO+24 - -
6. Total No. of Residential
Towers
18 18 No Change
7. No. of DUs 2062 2674 612 29.6 inc
8. Population 12346 16239 3893 31.5 Inc
9. Total Water Requirement 1146 1337 191 inc 16.67 inc
10. Fresh Water Requirement 776 932 156 inc 20.10 inc
11. Total Waste Water
Generation
874 1058 184 inc 21.05 inc
12. STP 1050 1270 220 inc 20.95 inc
13. MSW Generation 4.85 7.23 2.38 inc 49.07 inc
14. Landscape Area Proposed 35192.467 34910 282.47 dec 0.80 dec
15. Parking Proposed 4393 3878 515 dec 11.72 dec
16. Maximum Height of Building
74.7 77.75 3.05 inc 4.08 inc
17. Rainwater Harvesting Pits 09 20 11 inc 122.22 inc
18. Total Power Requirement 18800 18800 No Change No Change
4.Salient features details for expansion project:
SN Description Details Unit
GENERAL
1 Plot Area 87965.51 SQM
2 Proposed Built Up Area 455996 SQM
3 Number of Building Blocks (Residential 18+2 Facilty blocks) 20 (18+2) NOS
4 Total no of DU's 2674 NOS
5 Max Height of Building 77.75 M
6 Max No of Floors (Residential Tower) 2B+G/ST/PO+24 NOS
7 Cost of Project 684 CR
8 Expected Population (Residential 13739+2501 Floating) 16239 PERSONS
AREAS
9 Permissible Ground Coverage Area (40%) 35186 SQM
10 Proposed Ground Coverage Area ( 20.7%) 18248 SQM
11 Permissible FAR Area (350) 307,879 SQM
12 Proposed FAR Area (349.86)) 307,762 SQM
13 Total Basement Area 103790 SQM
14 Ancillary areas 35847.67 SQM
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 24 of 48
15 Total Stilt Area 1765.69 SQM
16 Proposed Built Up Area 455996 SQM
WATER
17 Total Water Requirement 1337.20 KLD
18 Fresh water requirement (69.66% of total water req) 931.52 KLD
19 Waste water Generation 1057.84 KLD
20 Proposed STP Capacity 1270 KLD
21 Treated Water Available for Reuse 846.27 KLD
22 Recycled Water (30.33% of total water requirement) 405.68 KLD
23 Surplus treated water 440.59 KLD
RAIN WATER HARVESTING
24 Proposed Quantity of Rain Water to be Harvested 27749.84 CUM
25 No of RWH of Pits Proposed 20 NOS
PARKING
26 Total Parking Required as / Building Bye Laws 3848 ECS
27 Proposed Total Parking 3878 ECS
28 Proposed Parking on Surface 647 ECS
29 Proposed Parking in Stilt+Podium 225 ECS
30 Proposed Parking in Upper Basement 1850 ECS
31 Proposed Parking in Lower Basement 1156 ECS
GREEN AREAS
32 Required Green Area (39.62% of Plot Area) 34859 SQM
33 Proposed Open & Green Area (39.68% of Plot Area) 34910 SQM
WASTE GENERATION
34 Municipal Solid Waste Generation 7.23 TPD
35 Quantity of E-Waste Generation- Kg/Day 47 KG/DAY
36 Quantity of Hazardous waste Generation 4125 LTS/ANNUM
37 Quantity of Sludge Generated from STP 380.8 KG/DAY
POWER
38 Total Power Requirement 18800 KW
39 DG set backup 16500 KVA
5.Water calculation details:
S. No. Water Uses Occupancy/
Capacity/Area
Rate Total Water Demand
(KLD)
A. Domestic Water Requirement
(i) Residential 13739 @86 lpcd 1181
(ii) Non Residential (Employees /
Workers)
724 @45 lpcd 33
(iii) Visitors 1777 @15 lpcd 27
Total Domestic Water Requirement 1241
B. DG cooling 16500 KVA @ 0.9 lt/hr/KVA 45
C. Green Area 34910 sq m @ 1 lt/Sq.m. 35
D. Swimming pool (Makeup Water) 1 LS 5
E. Filter back wash LS 12
Total Water Requirement 1338
6.Water and waste water calculation details:
Head Quantity, KL
Total Water Requirement 1338
Fresh Water Requirement 932
Treated Water Requirement 405
Water for Flushing 326
DG Cooling 45
Waste Water Generation(80% of total domestic fresh water demand + 100% of Flushing
Water)
1058
Capacity of STP (120% of Waste Water Generation) 1270
Treated Water Generation 846
Surplus Treated water (250-129) 440
Water Required for Fire Suppression (UGT- 200KL OHT- 25KL X 18 ) 650 (More than 1% of the
total water req.
7.Municipal Solid waste and other waste generation details:
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 25 of 48
Total Waste Generation 7.23 TPD
Organic Waste Generation 4.34 TPD
E- Waste Generation 47 KG/Day
Sludge Generation 686.93 KG/Day
Hazardous Waste Generation (DG Waste Oil) 4125 Lts/ Annum
8.The project proposals are covered under category 8"b" of EIA Notification, 2006.
The committee discussed the matter and recommended following TORs and general
guidelines for conducting EIA studies regarding the proposals:
Additional TORs :
1. The project proponent should submit an affidavit that there is no construction proposed in the towers/blocks where construction has already been started. There is no construction
started in the towers where expansion is proposed under this expansion. 2. Justification of increase in population should be given in view of increase in dwelling units.
3. Justification of decrease in parking provisions. 4. Specific area statements regarding proposed expansion.
5. Comparative area and other environmental parameter statements showing values earlier and
proposed as expansion.
6. All approved revised drawings/maps alongwith all approved revised services plans.
7. The revised structure design certificate by qualified structure engineer should be submitted.
The structural design certificate should preferably be vetted by IITs/CBRI. Provision of
alarm system, to timely notify the employees/residents, in case of occurrence of
earthquake/other natural disasters/fire should be provided.
8. Status of construction undertaken till date (block wise/tower wise/floor wise).
9. Compliance of earlier EC.
10. Master plan of the area showing proposed project.
11. Permissible uses of the proposed site as per zoning regulation.
12. Allotment letter from concerned development authority.
13. Physical features within 30 m of the project sites with their ownership.
14. Section details of all road.
15. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
16. Details of land Scape plan.
17. Land use approved by the competent authority.
18. Complete details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
19. Plan for no of trees, one tree per 80.0sq.mt.of area.
20. Use of reflecting paints on roof top and side walls.
21. Details of rain water harvesting are to be given.
22. Provision of 100% solar lighting along the road site, stair cases, common places.
23. A site plan showing the project site and its surroundings with physical features and
topographical details, such as land use, contours and drainage pattern, along with
photographs of the site from all four sides, should be included in the background
information.
24. 10% EWS / LIG housing provision shall be made as per Development Authority bye-laws.
25. Sanctioned plans/maps regarding the project with all services plans.
26. All plans and elevation sections/all service plan/landscape plan/standard electrification
plan/drainage/sewerage plan.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 26 of 48
27. Structural plan is to be submitted signed by qualified structural designer.
28. All service plans like sewer drainage water supply rain water harvesting fire fighting
landscape plan is to be submitted.
29. Section of all inter roads as proposed along R/W and C /W as well dimension is to be
to map.
30. Examine in detail the proposed site with reference to impact on infrastructure covering
water supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw
wastes from the complex on land/water body and into sewerage system.
31. Water requirement and water management plan alongwith necessary permissions for
discharge.
32. Hydro-geological investigations be carried out and obtain permission from Central Ground
Water Authority for withdrawal of ground water.
33. Consider soil characteristics and permeability for rainwater harvesting proposals, should be
made to prevent ground water contamination. Maximize use of treated water by recycling
and utilization of rainwater.
34. Make provision for safety against failure in the operation of wastewater treatment facilities.
Identify acceptable outfall for treated effluent.
35. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
36. Landscape plan, green belts and open spaces may be described separately.
37. Study the existing flora and fauna of the area and the impact of the project on them.
38. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
39. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
40. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
41. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.
42. Identification of recyclable wastes and waste utilization arrangements may be made.
43. Explore possibility of generating biogas from biodegradable wastes.
44. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission and
refuse including MSW, biomedical and hazardous wastes. Special attention should be made
with respect to bird menace.
45. Provisions made for safety in storage of materials, products and wastes may be described.
46. Disaster management plan should be prepared.
47. Traffic management plan including parking and loading/unloading areas may be described.
Traffic survey should be carried out both on weekdays and weekend.
48. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF.
49. Exclusive Parking area in the basement (excluding other facilities) and surface is to be
clearly mentioned.
50. Provide service road for entry and exit to project site.
51. Use of local building materials should be described.
52. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with
provisos of sampling port for monitoring be described.
53. Work out MGLC for the combined capacity of DG sets.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 27 of 48
54. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
55. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
56. Examine separately the details for construction and operation phases both for Environmental Management Plan and Environmental Monitoring Plan.
57. Total cost is 350 crores. Environment Corporate Responsibility (ECR) plan along with budgetary provision of minimum 2% of the project cost as discussed in meeting shall be
submitted on need base assessment study in the study area.
58. Details of all internal and peripheral roads width.
59. Source and quantity of required water during construction and management of generated
waste water.
60. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
61. Declare/submit the running cost of STP and other environmental management services (e.g.,
Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the
proposals which are to be including in the allotment letters.
62. The proponent will submit the schedule of monitoring/data collection programme to the
Office of Directorate, Member Secretary, UP Pollution Control Board and District
Magistrate of related District.
General Guidelines:
a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by Public Notary, stating that:
I. “There is no litigation pending against the project and/or land in which the project is proposed to be set up (please give name & ownership etc. of the project) and that for any
such litigation what so ever, the sole responsibility will be borne by the Project proponent.” II. “No activity relating to this project (i.e. name of the project) including civil construction
has been undertaken at site except fencing of the site to protect it from getting encroached and construction of temporary shed(s) for the guard(s). (if fencing has not been done, then
the same may be deleted).
III. “I/We hereby give undertaking that the data and information given in the application,
enclosures and other documents are true to the best of my knowledge and belief and I/We
am/are aware that if any part of the data and information submitted is found to be false or
misleading at any stage, the project will be rejected and clearance given, if any to the
Project will be revoked at our risk and cost.” IV. Project does not fall under any buffer zone of no-development as declared /identified under any
law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with EIA.
c. Current, site photographs viewing towards the project area from four directions indicating date of photograph taken, direction from which taken, name of the project, and signature of Project
proponent along with consultant with seal should be submitted, so as to ensure that no
construction has been started before the grant of EC.
d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of
2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of
representativeness and reliability of baseline environmental attributes detailed under EIA
manual January, 2001 and other guidelines in the matter.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 28 of 48
e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically
mentioned. The consultant shall certify that his accreditation is for the sector for which this
EIA is prepared.
f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with
their complete details including their accreditation, if any shall be indicated.
g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in
the preparation of these reports and the Name of laboratory through which the samples have
been got analysed should be stated in the report. It shall clearly be indicated whether said laboratory is accredited by NABL or approved under the Environment (Protection) Act, 1986
(Please refer MoEF office memorandum dated 4th
August, 2009). The name project leader of the EIA study shall also be mentioned.
h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted
within 15 days from the date of receipt of the letter and remaining of the information’s is to be
submitted along with the EIA.
10. Residential Complex “Panchsheel Green” at Plot No-GH-01A, Sector-18, Greater Noida. Sri
Gulshan Kumar, H-169, Sector-63, Noida. File N0. 3345/AD-Sub.
The committee noted that an application dated 22/08/2015 was made by the project
proponent for environmental clearance for Residential Complex “Panchsheel Green” at Plot No-
GH-01A, Sector-18, Greater Noida, U.P., M/s Panchsheel Buildtech Pvt. Ltd.
A presentation was made by Shri Gulshan K. Dua, project proponent alongwith their
consultant M/s Eco Pro Engineers Pvt. Ltd. The proponent, through the documents submitted and
the presentation made, informed the committee that:-
1. The Environmental Clearance is sought for Residential Complex “Panchsheel Green” at
Plot No-GH-01A, Sector-18, Greater Noida, U.P., M/s Panchsheel Buildtech Pvt. Ltd.
2. Area details of the project:
Total Plot area 52850.22 m
2
Permissible FAR (including purchasable) 3.5 or 184975 m
2
Proposed FAR 3.498 or 184857.37 m
2
Permissible Non-FAR Area (15% of FAR Area) 27746.365 m
2
Proposed Non-FAR Area (10.744% of FAR Area) 19872.92 m
2
Permissible Ground Coverage 35% or 18497.58 m
2
Ground Coverage achieved 25.92% or 13697.88 m
2
Basement 41164.95 m
2
Built up Area 245895.24 m
2
Permissible Apartments (2100 person/Ha & 4.5
person/flat)
2466
Expected number of Apartments 2199
Permissible person 11097
Proposed No. of Person 9896
Permissible Green Area (Minimum, 50% of open area) 19576.19 m
2
Proposed Green Area 37% of plot area or 19592.4 m
2
Permissible Number of Trees (minimum, 1 tree/m2
of
open area)
392
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 29 of 48
Proposed Number of Trees 400 (Evergreen 200 + Shrubs 200)
3.Salient features details of the project:
Total Domestic Water Requirement
(@ 86 LPCD)
851 KLD
Freshwater Requirement (2/3rd
of Total domestic water requirement)
567 KLD
Source of Water Greater Noida Piped water supply
Wastewater Generation (90% of water requirement) 766 KLD
STP Capacity 800 KLD
Treated Wastewater (95% of total wastewater) 760 KLD
Reuse of Treated Wastewater Flushing (284 KLD), Horticulture (20 KLD),
Wastewater discharge in Sewerage System 456 KLD
Solid Waste generated (0.6 Kg/person/day + 10% extra) Approx. 5938 Kg/day
Composition of MSW Biodegradable (2969 Kg); Recyclable (1781 Kg); Others
(1188 Kg)
Solid Waste Management It will be segregated into biodegradable, recyclable and
others components and disposal will be ensured into
municipal bins.
Separate bins for biodegradable waste and recyclable
waste will be provided.
Solid waste would be lifted and managed by Greater
Noida Authority.
Rainwater Harvesting Terrace area = 13500 m2 (approx.)
Avg. rainfall = 650 mm/year
Hourly rainfall = 90 mm/hour (23 mm/15 minutes) Runoff Coefficient = 0.8 (terrace)
Avg. rainwater collection per 15 minute during peak
rainfall =
Terrace = 13500 X 0.8 X 0.023
= 248 m3/15 minutes
No. of Harvesting Wells 5 sets of recharge pit and desilting tank
Desilting Tank – 6 X 3 X 2 m effective depth
- 36 m3
Recharge Pit – 3 X 2.5 X 2 m effective depth
- 15 m3
Total Capacity of one set – 51 m3
Total Electrical Requirement 5070 kw
DG Sets 1 x 1600; 2 X 1010 kVA
Use of Solar energy Solar lighting for common areas and solar water heaters
Soil Excavation Total – 42000 X 5 = 210000 m3
Top Soil – 15000 m3
Landscaping + roads – 120000 m3
External Development – 75000 m3
CSR Activity 2% of total project cost
Education, health care and village development
No Development Zone/ Eco-sensitive Zone Project area does not fall in buffer zone of any such area.
Nearest protected area is Okhla Bird Sanctuary located
more than 15 Kms from the site
4.Municipal solid and other waster generation details:
Sl. No. Characterization Amount
1 Expected total solid waste generation 5938 kg/day
2 Biodegradable waste 50 % of total solid waste
2969 kg/ day
3 Recyclable non-biodegradable waste 30 % of total solid waste
1781 kg/ day
4. Other Waste 20% of Total Solid Waste
1188 kg/day
5. The project proposals are covered under category 8"b" of EIA Notification, 2006.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 30 of 48
The committee discussed the matter and recommended following TORs and general
guidelines for conducting EIA studies regarding the proposals:
Additional TORs :
1. All approved drawings/maps alongwith all approved services plans.
2. The structure design certificate by qualified structure engineer should be submitted. The
structural design certificate should preferably be vetted by IITs/CBRI. Provision of alarm
system, to timely notify the employees/residents, in case of occurrence of earthquake/other
natural disasters/fire should be provided.
3. Master plan of the area showing proposed project.
4. Permissible uses of the proposed site as per zoning regulation.
5. Allotment letter from concerned development authority.
6. Physical features within 30 m of the project sites with their ownership.
7. Section details of all road.
8. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
9. Land use approved by the competent authority.
10. An underground Pucca tank for collection/reuse of rain water may be constructed.
11. Complete Details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
12. Use of reflecting paints on roof top and side walls.
13. Details of rain water harvesting are to be given.
14. Provision of 100% solar lighting along the road site, stair cases, common places. Calculation
of required space for solar provisions should also be calculated and submitted.
15. A site plan showing the project site and its surroundings with physical features and
topographical details, such as land use, contours and drainage pattern, along with
photographs of the site from all four sides, should be included in the background
information.
16. Plan for EWS / LIG housing provision as per Development Authority bye-laws.
17. Sanctioned plans/maps regarding the project with all services plans.
18. All plans and elevation sections/all service plan/landscape plan/standard electrification
plan/drainage/sewerage plan.
19. Structural plan is to be submitted signed by qualified structural designer.
20. All service plans like sewer drainage water supply rain water harvesting fire fighting
landscape plan is to be submitted.
21. Examine in detail the proposed site with reference to impact on infrastructure covering
water supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw
wastes from the complex on land/water body and into sewerage system.
22. Water requirement and water management plan alongwith necessary permissions for
discharge.
23. Hydro-geological investigations be carried out and obtain permission from Central Ground
Water Authority for withdrawal of ground water.
24. Consider soil characteristics and permeability for rainwater harvesting proposals, should be
made to prevent ground water contamination. Maximize use of treated water by recycling
and utilization of rainwater.
25. Make provision for safety against failure in the operation of wastewater treatment facilities.
Identify acceptable outfall for treated effluent.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 31 of 48
26. Required no of trees should be proposed @ 01 tree/80 sqm
27. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
28. Landscape plan, green belts and open spaces may be described separately.
29. Study the existing flora and fauna of the area and the impact of the project on them.
30. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
31. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
32. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
33. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.
34. Identification of recyclable wastes and waste utilization arrangements may be made.
35. Explore possibility of generating biogas from biodegradable wastes.
36. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission and
refuse including MSW, biomedical and hazardous wastes. Special attention should be made
with respect to bird menace.
37. Provisions made for safety in storage of materials, products and wastes may be described.
38. Disaster management plan should be prepared.
39. Traffic management plan including parking and loading/unloading areas may be described.
Traffic survey should be carried out both on weekdays and weekend.
40. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF.
41. Exclusive Parking area in the basement (excluding other facilities) and surface is to be
clearly mentioned.
42. Section of all internal roads should be provided. Right of way and carriage way width
should be clearly marked on the map.
43. Provide service road for entry and exit to project site.
44. Use of local building materials should be described.
45. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with
provisos of sampling port for monitoring be described.
46. Work out MGLC for the combined capacity of DG sets.
47. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
48. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
49. Examine separately the details for construction and operation phases both for Environmental Management Plan and Environmental Monitoring Plan. Break up of environmental
management cost should also be submitted.
50. Environmental Corporate Responsibility (ECR) plan along with budgetary provision
amounting to 2% of project cost shall be prepared and approved by Board of Directors of
the company. A copy of resolution as above shall be submitted to the authority alongwith
list of beneficiaries with their mobile nos./address.
51. Details of all internal and peripheral roads width.
52. Source and quantity of required water during construction and management of generated
waste water.
53. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 32 of 48
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
54. Declare/submit the running cost of STP and other environmental management services (e.g.,
Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the
proposals which are to be including in the allotment letters.
55. The proponent will submit the schedule of monitoring/data collection programme to the
Office of Directorate, Member Secretary, UP Pollution Control Board and District
Magistrate of related District.
General Guidelines:
a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested
by Public Notary, stating that:
I. “There is no litigation pending against the project and/or land in which the project is
proposed to be set up (please give name & ownership etc. of the project) and that for any such litigation what so ever, the sole responsibility will be borne by the Project proponent.”
II. “No activity relating to this project (i.e. name of the project) including civil construction has been undertaken at site except fencing of the site to protect it from getting encroached
and construction of temporary shed(s) for the guard(s). (if fencing has not been done, then the same may be deleted).
III. “I/We hereby give undertaking that the data and information given in the application, enclosures and other documents are true to the best of my knowledge and belief and I/We
am/are aware that if any part of the data and information submitted is found to be false or
misleading at any stage, the project will be rejected and clearance given, if any to the
Project will be revoked at our risk and cost.” IV. Project does not fall under any buffer zone of no-development as declared /identified under any
law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with
EIA.
c. Current, site photographs viewing towards the project area from four directions indicating date
of photograph taken, direction from which taken, name of the project, and signature of Project
proponent along with consultant with seal should be submitted, so as to ensure that no
construction has been started before the grant of EC.
d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of
2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of
representativeness and reliability of baseline environmental attributes detailed under EIA
manual January, 2001 and other guidelines in the matter.
e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically mentioned. The consultant shall certify that his accreditation is for the sector for which this
EIA is prepared. f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with
their complete details including their accreditation, if any shall be indicated. g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in
the preparation of these reports and the Name of laboratory through which the samples have
been got analysed should be stated in the report. It shall clearly be indicated whether said
laboratory is accredited by NABL or approved under the Environment (Protection) Act, 1986
(Please refer MoEF office memorandum dated 4th
August, 2009). The name project leader of the EIA study shall also be mentioned.
h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted
within 15 days from the date of receipt of the letter and remaining of the information’s is to be
submitted along with the EIA. The presentation for EIA shall be made TOR wise.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 33 of 48
11. Group Housing “Cosmic Corporate Park-3” at Plot No-1, Sector-154, Noida, U.P. Sri Sandeep
Pahwa, Director, 281, Azad Mandi, Delhi. File N0. 2082/AD-H
The committee noted that the matter was earlier discussed in SEAC meting dated
21/02/2015 wherein the project proponent was directed to submit following information:
"The committee observed that plot area of the project is mentioned as 20,002.40 sqm
however the possession on the site has only been provided for plot area 15,000 sqm by the
Noida Authority. The committee also observed that the whole proposal is calculated for plot
area 20,002.40 sqm which should be revised as per actual availability of land. The
committee also found that some constructed areas like parking, basement etc. have not been
included in built-up area. The committee directed the project proponent to revise and submit
the matter for appraisal. The matter is deferred till submission of revised proposals."
The project proponent submitted their replies through letter dated 09/03/2015 and the matter
was again discussed in SEAC meeting dated 01/06/2015 wherein the committee directed to submit
following information:
1. Podium should be covered under built-up area. Area details should be accordingly
modified.
2. Area statement with tower wise and floor wise details alongwith no. of units.
3. Area details showing proposed uses as residential, commercial, parks, parking, roads,
other services, facilities of the project also in percentage.
4. Provision of 100% solar lighting along the road site, stair cases, common places.
5. Physical features within 100 m of the project sites with their ownership.
6. Running cost of STP and other environment management facilities which shall be
transferred to the alloties during operation phase.
7. Parking plan.
8. Environmental Corporate Responsibility (ECR) plan along with budgetary provision
amounting to 2% of project cost shall be prepared and approved by Board of Directors of the company. A copy of resolution as above shall be submitted to the authority
alongwith list of beneficiaries with their mobile nos./address.
The project proponent submitted their replies through letter dated 14/08/2015. A
presentation was made by Shri Lakhvendar Deep Singh, project proponent alongwith their
consultant M/s Development Consultant Pvt. Ltd, Kolkata. The committee discussed the replies
submitted by the project proponent and found it unsatisfactory and directed the project proponent to
submit following information:
1. The project proponent should submit an affidavit that there is no change in the proposals
submitted on dated 09/03/2015 and the proposals being presented before the committee in meeting dated 09/10/2015.
2. Population calculation should be submitted alongwith commensurate water balance diagram.
3. Solar power requirement in places as submitted by project proponent should be calculated. Space required for solar provisions alongwith its location on layout should be
provided.
4. Parking provisions as per Development Authority bye-laws should be provided.
5. Copy of Fire and AAI NOC.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 34 of 48
6. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting
to 2% of project cost shall be prepared and approved by Board of Directors of the
company. A copy of resolution as above shall be submitted to the authority.
The matter shall be discussed after submission of information as above.
12. Group Housing “Orchard Green” No-2, Sector-K, Sushant Golf City, Hi Tech Township
Extension Area, Lucknow. Sri Vinod Tikku, Ex. Director, (Project). File N0. 2530/AD-H
The committee noted that the matter was earlier discussed in SEAC meting dated
27/06/2015 wherein the project proponent was directed to submit following information:
2. Readable copy of layout plan as approved by the competent authority.
3. Copy of approved layout plan/maps/services plans.
4. Structural safety certificate prepared by qualified engineer/vetted by authorized institution.
5. Details/dimensions of water body (pond) proposed in the project with holding capacity.
6. Plan for 15% soft green only for tree plantation.
7. Break-up of built-up area under FAR and non FAR head.
8. E-waste calculation should be rechecked and submitted.
9. (i) What is the proposed date of completion of project? (ii) What is the project status of
proposed centralized 300 TPD pyrolysis plant in township? Has the necessary permissions for
this plant been obtained or not. (iii) What is the distance of this pyrolysis plant from group
housing project? (iv) What is the proposed date of start of functioning of this pyrolysis plant?
Agreement with LDA for management of MSW as proposed by PP till start of operation of
this plant.
10. Proposal for use of STP in modular form in proportion to its actual uses.
11. It is proposed to release 120.3 KLD Tertiary Treated Waste Water into drain. A feasibility
study shall be undertaken and submitted to channelize this Tertiary Treated Waste Water into
artificial KUCHCHA pond as the complete project is dependent on underground water
extraction. Project Proponent himself accepted during presentation that the underground water
situation will become very bleak in coming 10 years/due to underground water extraction in
this project, which itself is a part of a mega township, having multiple similar projects, in
close vicinity. Hence, offensive measures are required to recharge the underground water up
to maximum possible extent.
12. The proposed water body in the project covers around 0.77 % of Net plot area. This proposed
area shall be decided on the basis of a feasibility study undertaken to recharge the
underground water up to maximum possible extent.
13. Explore in increase of no. of trees under proposed green plan.
14. Sludge disposal plan with required area should be submitted with earmarking its location on
the layout plan. (i) An allocated space (with calculated area) on layout, required for the
processing of sludge, with proper justification about "sludge to manure" conversion process
management, and prominent wind direction. (ii) Amount of total manure generated per day/
per year.(iii) Amount of manure required inside the project boundary per day/ per year.(iv)
Plan to handle the extra manure.
15. Plan for solar provisions proposed for the project with required area and location. Project
proponent has mentioned that "Solar Photo Voltaic Lighting shall be provided for partial
landscape lighting". In this regard:
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 35 of 48
• This term "partial" should be quantified.
• Calculate the Total load for street lighting.
• Submit plan for installation of solar panels and other necessary requirements to fulfil this
requirement of solar power, supported with justifications,
• Show the allocated required space (with calculated area) on layout, required for solar power
generation
16. Regarding quantity of hazardous waste, minimum and maximum quantity, based on justified
calculations, should be submitted.
The project proponent submitted their replies through letter dated 11/08/2015. A
presentation was made by Shri Jonaed Khan, authorized representative of project proponent along
with their consultant M/s Min Mec Consultancy Pvt. Ltd. The committee discussed the replies
submitted by the project proponent and observed as follows:
1. The project proponent has submitted that the project has got technical sanction by the
LDA vide letter dated 18/05/2011. Careful examination of this letter dated 18/05/2011
shows that this technical clearance is only for 520 flats whereas the project proposals
submitted to SEIAA for environmental clearance is for 568 dwelling units. This
difference in dwelling units should be explained by the project proponent as it will
result in change of complete proposal. A self explanatory statement alongwith
supporting documents should be submitted by the project proponent.
2. An agreement with competent agency for management of Municipal Solid Waste
should be done and submitted.
3. Provisions of a pucca underground tank for rain water collection should be undertaken.
4. Structural design certificate signed by architect and vetting authority after
incorporating proposed expansion structure should be submitted. All structural design
drawings should be signed by architect and counter signed by vetting authority.
A firmed up plan as above in-line with sanction given by LDA should be submitted.
The revised proposals as above shall not be treated as pendency and shall be treated
afresh.
13. Group Housing at Plot No-GH-5 & 6, Sector-8B, Vrindavan Awas Yojna, Lucknow, Col. C. N.
Rawat, Project Director, Chappan Chauraha, Lal Bahadur Shashtri Marg, Luckcnow Cantt. File
N0. 2822/AD(H)
The committee noted that the matter was earlier discussed in SEAC meting dated
10/07/2015 wherein the project proponent was directed to submit following information:
1. Approved maps/plans/layout plan from Lucknow Development Authority. 2. Copy of approved layout plan/maps/services plans.
3. No construction affidavit by the project proponent. 4. NOC from Fire Department and Airport Authority of India.
5. Provision for underground storage tank for collection of runoff. 6. Plan for municipal solid waste management.
7. Letter/Permission regarding Municipal Water Supply. 8. Written commitment from Lucknow Development Authority that the project is linked with
Central sewage system of Vrindavan Yojna as submitted by project proponent for
justification of no STP.
9. Proposal for rain water harvesting only from the rooftop. Plan for underground water tank
for storm water storage.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 36 of 48
10. Setback details.
11. Section details of all road. All roads width to be written with carriage and Right of way.
12. 03 m peripheral green shall be provided around the project inside the project boundary.
According plans should be submitted.
13. Internal road width/carriage way/right of way alongwith design should be submitted.
14. Action plan regarding plantation of 500 trees as committed by project proponent.
15. Landscape plan.
16. Plan for convenient shopping and other facilities for residents.
17. Written request from project proponent regarding exemption of CSR with justification as made by project proponent.
The project proponent submitted their replies through letter dated 24/08/2015. A
presentation was made by Shri Shyam Sundar Nayak, authorized representative of project
proponent along with their consultant M/s Ascenso Enviro Pvt. Ltd. The committee discussed the
matter and recommended grant of environmental clearance on the project proposals alongwith
general conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. Provision of parking should be restricted to ECS as required under Development Authority
bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs as obtained from different Department should be submitted.
4. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
5. Approach road location should be clearly marked on layout and should be submitted.
6. Necessary planning for any anticipated expansion should be incorporated in present design in view of structural stability.
7. An underground water body shall be planned within the premises for storage of rain water. 8. Structural design certificate signed by architect and vetting authority should be submitted.
9. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and Handling) Rules, 2000 (as amended).
10. 02 m peripheral green shall be provided around the project inside the project boundary. 11. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt.
12. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
13. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for
construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement.
14. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be treated
in captive STP conforming to prescribed standards of receiving body for designated use.
Monitoring of STP to be done daily till its stabilization. 15. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with
regular testing and monitoring of treated water. 16. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the compliance of the E-waste and municipal solid waste disposal.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 37 of 48
17. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided
in the open areas/ stairs cases.
18. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
19. All entry/exit point should be bell mouth shaped.
20. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
21. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only from the roof top. RWH from green and other open areas shall be done only after permission
from CGWB. 22. An underground Pucca tank for collection/reuse of rain water may be constructed.
23. Height of the stack should be provided based on combined DG sets capacity and be 6mt higher than the tallest building.
24. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be carried out as CPCB Guidelines.
25. Crèche to be provided during the construction/operation phase. 26. Provision of separate room for senior citizen with proper amenities shall be made.
27. Protection shall be provided on the windows of the high rise flats for security of residents.
28. Unless and until all the environmental issues are sorted out the occupancy will be restricted
and would be only allowed after achieving the Permission from the competent authority.
29. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
30. For any extraction of ground water, prior permission from CGWB shall be taken.
31. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
32. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose. 33. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall
be made available to the temporary residents/workers at the project site including the proper treatment and the disposal of the wastes.
14. “Gas Based Power Plant of Capacity 16 MW” at Grand Venezia Mall, Greater Noida at Plot No.
SH-3, Site-IV, UPSIDC, Surajpur, Greater Noida, M/s Bhasin Infotech and Infrastructure Pvt.
Ltd. File N0. 1128/TA-J
The project proponent did not appear. The committee discussed and deliberated that project
file should be closed and should be opened only after request from the project proponent. The file
shall not be treated as pending at SEIAA/SEAC.
15. Residential Complex “Panchsheel Hynish” at Pot No-GH-08A, Sector-01, Greater Noida. Sri
Gulshan Kumar, H-169, Sector-163, Noida. File N0. 2570/AD-H
The committee noted that the matter was earlier discussed in SEAC meting dated
13/08/2015 wherein the project proponent was directed to submit following information:
1. Copy of Environmental clearance issued for the project in 2011 as informed by project
proponent.
2. Allotment letter from concerned development authority.
3. Land use approved by the competent authority.
4. Specific area statements regarding proposed expansion.
5. All approved revised drawings/maps alongwith all approved revised services plans.
6. The revised structure design certificate by qualified structure engineer should be submitted.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 38 of 48
The structural design certificate should preferably be vetted by IITs/CBRI. Provision of
alarm system, to timely notify the employees/residents, in case of occurrence of
earthquake/other natural disasters/fire should be provided.
7. Revised landscape plan.
8. Use of treated waste water.
9. Status of construction undertaken till date (block wise/tower wise/floor wise) alongwith
photographs.
10. Compliance of earlier EC.
11. Physical features within 30 m of the project sites with their ownership.
12. Section details of all road.
13. Solid waste site to be shown on map. Name address of Vendor is to be submitted.
14. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
15. Complete Details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
16. Use of reflecting paints on roof top and side walls.
17. Plan for provision of 100% solar lighting along the road site, stair cases, common places
with calculation of load and required area for solar provisions.
18. Plan for 10% EWS/LIG housing provision shall be made as per Development Authority
bye-laws. 19. All plans and elevation sections/all service plan/landscape plan/standard electrification
plan/drainage/sewerage plan.
20. Total project cost is 64.0 crores. Environmental Corporate Responsibility (ECR) plan along
with budgetary provision amounting to 2% of project cost shall be prepared and approved
by Board of Directors of the company. A copy of resolution as above shall be submitted to
the authority alongwith list of beneficiaries with their mobile nos./address.
The project proponent submitted their replies through letter dated 26/08/2015. A
presentation was made by Shri Gulshan Kumar, authorized representative of project proponent
along with their consultant M/s Eco Pro Engineers Pvt. Ltd. The committee discussed the matter
and recommended grant of environmental clearance on the project proposals alongwith general
conditions as earlier prescribed by the authority for construction project and following specific
conditions:
1. Provision of parking should be restricted to ECS as required under Development Authority
bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs as obtained from different Department should be submitted.
4. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
5. Approach road location should be clearly marked on layout and should be submitted. 6. Necessary planning for any anticipated expansion should be incorporated in present design in
view of structural stability. 7. An underground water body shall be planned within the premises for storage of rain water.
8. Structural design certificate signed by architect and vetting authority should be submitted. 9. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management
and Handling) Rules, 2000 (as amended). 10. 03 m peripheral green shall be provided around the project inside the project boundary.
11. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt.
12. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 39 of 48
13. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for
construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement.
14. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be treated in captive STP conforming to prescribed standards of receiving body for designated use.
Monitoring of STP to be done daily till its stabilization. 15. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with
regular testing and monitoring of treated water. 16. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the compliance of the E-waste and municipal solid waste disposal.
17. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided
in the open areas/ stairs cases.
18. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
19. All entry/exit point should be bell mouth shaped.
20. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
21. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only
from the roof top. RWH from green and other open areas shall be done only after permission
from CGWB.
22. An underground Pucca tank for collection/reuse of rain water may be constructed. 23. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building. 24. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be
carried out as CPCB Guidelines. 25. Corporate Social Responsibility CSR) plan along with budgetary provision amounting to 2%
of total project cost shall be prepared and approved by Board of Directors of the company. A copy of resolution as above shall be submitted to the authority. A list of beneficiaries with
their mobile nos./address should be submitted alongwith six monthly compliance reports. 26. Crèche to be provided during the construction/operation phase.
27. Provision of separate room for senior citizen with proper amenities shall be made.
28. Protection shall be provided on the windows of the high rise flats for security of residents.
29. Unless and until all the environmental issues are sorted out the occupancy will be restricted
and would be only allowed after achieving the Permission from the competent authority.
30. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
31. For any extraction of ground water, prior permission from CGWB shall be taken.
32. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
33. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation purpose.
34. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. shall be made available to the temporary residents/workers at the project site including the proper
treatment and the disposal of the wastes.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 40 of 48
16. Construction of cultural and heritage building centre “Awadh Shilp Gram”, at Sec-1, Awadh
Vihar Bhoome Vikas Evem Grahisthaan Yojna, Amar Saheed Path, Lucknow- Executive
Engineer, Construction Division-7, Indira Nagar, Lucknow. File N0. 2790/OSD-T
The committee noted that an application dated 22/01/2015 was made by the project
proponent for environmental clearance for Construction of cultural and heritage building center
“Awadh Shilp Gram”, at Sec-1, Awadh Vihar Bhoome Vikas Evem Grahisthaan Yojna, Amar
Saheed Path, Lucknow.
A presentation was made by Shri V.B. Singh, Executive Enginner, Awas Evam Vikas
Parishad project proponent alongwith their consultant M/s Sawen Consultancy Services Pvt. Ltd.
The proponent, through the documents submitted and the presentation made, informed the
committee that:-
1. The Environmental Clearance is sought for Construction of cultural and heritage building
center “Awadh Shilp Gram”, at Sec-1, Awadh Vihar Bhoome Vikas Evem Grahisthaan
Yojna, Amar Saheed Path, Lucknow-
2. Proposed activities details of the project:
Project Components: Nos.
Food Courts 08 stalls
Exhibition Halls 03 Halls
Amphitheatre and Dormitories 216 Beds
Craft Shops 151 Shops
A.C. Shops 44 Shops
Non A.C. Shops 27 Shops
Entrance Court, Ticketing, Admin, Kids Play Area -
Banquet 02 nos.
Craft Courts 30 nos.
3.Area details of the project:
Ground Coverage As per Bye Laws-40% Proposed-25.18%
325385 sqm 20480.085 sqm
Total floor area As per Bye Laws-40% Proposed-36.61%
325385 sqm 29784.00 sqm
FAR As per Bye Laws-1.75 Proposed - 0.37
No. of Floors G+1
Setback Front -15 m Front -15 m
Rear side -12 m Rear side -12 m
4.Salient features details:
Total Population 3510 Proposed Capacity of ETP 2 KLPH
Parking Provision 427 ECS Water Treatment –RO
Plant
2000 lph
Rain water harvesting pits 04 nos.
Total HVAC capacity 1000 KW RT -Rain Water Recharge
Pit
09 nos.
Skylight Provision In an area of 260.0 sqm Fire Hydrant Tank 02 nos x 100.00 cum
Total Water Requirement 194.17 KLD Premonsoon Gr.Water
Level
2.6-6.4 m bgl
Water Supply Source Trunk water supply through Awadh Vihar Yojana
Underground Water Tank 150 KL capacity
Total Electrical Load 1000 KVA x 03 nos. DG Sets 500 KVA x 04 nos. &
630 KVA x 02 nos.
Solar Panel 20 KW
5.Land use distribution details:
S.No. Land Use Area (sqm) %
1 Ground Coverage 20480.08 25
2 Road Area 7216.56 9
3 Green Area 18938.0 23
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 41 of 48
4 Open Parking Area 9821.0 12
5 Hardscape Area 24891.53 31
6 Total Area 81347.17 100
6.Population details of the project:
S.No. Detail Population
1 Food Court 393
2 Exhibition Hall 167
3 Amphitheatre and Dormitories 216
4 Craft Shops 1374
5 A.C. Shops 782
Non A.C. Shops
6 Craft Courts 193
7 Banquet 358
8 Service Staff (Electrical, AHU Control, Gardener, Entrance Court, Ticketing, Admin, Kids Pool Life Guards, Parking etc.)
30
3510
7.Parking details of the project:
Parking Acquired Vehicle Type
1 ECS per 4 scooter parking SCOOTER 252 63
CARS 334 334
6 ECS for 1 Bus Parking BUS 5 30
TOTAL
427 ECS
8.Water calculation details:
S.No. Detail Population LPCD*/
Description
Consumption
KLD
Discharge
KLD
1 Food Court 393 15 5.90 4.72
2 Exhibition Hall 167 15 2.51 2.00
3 Amphitheatre and Dormitories 216 86 18.58 14.86
4 Craft Shops 1374 45 61.83 49.46
5 A.C. Shops 782 45 35.19 28.15
Non A.C. Shops
6 Craft Courts 193 45 8.69 6.95
7 Banquet 358 15 5.37 4.30
8 Service Staff (Electrical, AHU
Control, Gardener, Entrance Court, Ticketing, Admin, Kids Pool Life
Guards, Guards, Parking etc.)
30 45 1.35 1.08
Total Domestic 3510 139.40 111.52
9 Restaurant, Food Court -Kitchen
Process Waste
393 70 27.51 24.75
10 DG Set Cooling 0.9 l/ KVA/ 2 hrs 500 KVA x 04
nos. & 630
KVA x 02 nos.
5.86 0.00
11 Horticulture & Landscape Area 18938+4840 0.9-1.0
l/ sqm
21.40 0.00
Total 194.17 136.27
9.Municipal solid waste generation and other waste details of the proejct:
Type of Waste Colour of Bins Category Disposal Percent by
Weight
Total Waste
(Kg/day)
Organics Green Bio Degradable Municipal Solid Waste
Site
40.15 290.51
Paper
Metals
Glass
Textiles
Plastic
Blue Recyclable Approved Recycler 6.316 45.70
Stone, Ash &
Miscellaneous
Grey Non-Bio
degradable
Municipal Solid waste
Site
53.54 387.39
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 42 of 48
S.No. Source Rate of Waste Generation Total Amount of Waste (Kg/ Day)
1 Amphitheatre and Dormitories @ 0.65 Kg/ Person 216 x 0.65 = 140.4
2 Visitors at Restaurant, Food Court,
Craft Courts
@0.15 Kg/Person 3294*0.15 = 494.1
3 Kitchen Waste ETP Sludge Lumpsum 1.0
4 Garden Waste @ 15 Kg/acre/day 5.87 acre x 15 = 88.05
Total 723.55
10. The project proposals are covered under category 8"a" of EIA Notification, 2006.
The committee discussed the matter and recommended grant of environmental clearance on
the project proposals alongwith general conditions as earlier prescribed by the authority for
construction project and following specific conditions:
1. Provision of setback on all sides should be made as per Awas Evam Vikar Parishad bye-laws. 2. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management
and Handling) Rules, 2000 (as amended). 3. 03 m peripheral green shall be provided around the project inside the project boundary. Add
Astonia in list of trees.
4. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt.
5. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
6. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for
construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth movement.
7. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be treated
in captive STP conforming to prescribed standards of receiving body for designated use.
Monitoring of STP to be done daily till its stabilization.
8. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with
regular testing and monitoring of treated water.
9. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users.
STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal. 10. Effluent Treatment Plant(ETP)/Sewage Treatment Plant(STP) including proper Oil and Greas
e Trap for the effluent arising from kitchen and /or laundry and shall comply MoEF Standards.
11. All required sanitary and hygienic measures should be in place before starting construction activities and to be maintained throughout the construction phase.
12. Corporate Social Responsibility CSR) plan along with budgetary provision amounting to 2% of total project cost shall be prepared and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority. A list of beneficiaries with their mobile nos./address should be submitted alongwith six monthly compliance reports.
13. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided
in the open areas/ stairs cases.
14. Parking guideline as per Lucknow Development Authority should be followed. Parking for
disabled persons should be explored.
15. All entry/exit point should be bell mouth shaped.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 43 of 48
16. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
17. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only
from the roof top. RWH from green and other open areas shall be done only after permission
from CGWB.
18. A water body with kachcha base shall be planned within the premises for storage of storm
water apart from rain water harvesting pits.
19. Height of the stack should be provided based on combined DG sets capacity and be 6mt higher than the tallest building.
20. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be carried out as CPCB Guidelines.
21. The project proponent shall ensure that the project site does not attract/infringe any buffer zone of no activity identified/declared under law.
22. For any extraction of ground water, prior permission from CGWB shall be taken. 23. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction. 24. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
25. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall
be made available to the temporary residents/workers at the project site including the proper
treatment and the disposal of the wastes.
17. “500 Bedded” Bal Rog Chikitsa Sansthan, BRD Medical College, Chargawa, Sadar,Gorakhpur-
Dr.P. K. Kushwaha,Principal, BRD Medical College, Gorakhpur. File N0. 2941/ AD(H)
The project proponent did not appear. The committee discussed and deliberated that project
file should be closed and should be opened only after request from the project proponent. The file
shall not be treated as pending at SEIAA/SEAC.
18. “Police Bhawan” (Signature Building) at Plot No-7/30. Sector-7, Gomti Nagar Ext. Lucknow- Sri
Satyasen Yadav, C.O., Gomti Nagar, Lucknow. File N0. 2984/OSD-T
The project proponent did not appear. The committee was informed that the project
proponent could not appear because of election duty. The committee discussed and deliberated to
defer the matter till next meeting.
19. Training & Hostel Institution, Oriental Bank of Commerce at Plot No-B-31, Sector-62, Noida- Sri
Debarchan Sahoo, AGM, Plot No-5, Institutional Area, Sector-32, Gurgaon (HR). File N0.
3054/OSD-T
The committee noted that an application dated 16/04/2015 was made by the project
proponent for environmental clearance for Training & Hostel Institution, Oriental Bank of
Commerce at Plot No-B-31, Sector-62, Noida.
A presentation was made by Shri Debarchan Sahu, AGM, authorized representative of
project proponent alongwith their consultant M/s GRC Pvt. Ltd. The proponent, through the
documents submitted and the presentation made, informed the committee that:-
1.The Environmental Clearance is sought for Training & Hostel Institution, Oriental Bank
of Commerce at Plot No-B-31, Sector-62, Noida.
2.Area details of the project are as follows:
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 44 of 48
S.No. Particulars Area (m2
) %
I. Total Plot area 20,000
II. Permissible ground
Coverage (@ 33% of the
total plot area)
6600
III. Ground Coverage
Achieved
/Proposed
Before 2006 Demolished Proposed
Expansion
Total
2,760.26
(@13.80 % of
the total plot area)
Main Admin
Building =
1516.58
Hostel
Building =
1243.68
675.31
(@3.38 % of the
total plot area) Main Admin
Building =
406.23
Hostel Building
= 269.08
1979.04
(@9.90% of the
total plot area) New Admin
Building = 928.81
Hostel-1 = 488.75
Hostel -2 =
561.48
4,063.99
(@20.32%
of the total plot area)
20.32%
IV Permissible FAR (@1.5
of the total plot area)
30,000
V. Existing/ Proposed FAR 5,437.78
(@27.19% of
the total plot
area) Hostel
Building =
3105.88
Admin
Building =
2331.90
675.31
(@3.38 % of
the total plot
area) Main Admin
Building =
406.23
Hostel Building
= 269.08
13,027.37
(@27.19% of the
total plot area)
New Admin Building = 2768.7
Hostel-01 =
2843.69
Hostel-02=
7414.98
17,789.84
(@0.89 of
the total
plot area)
VI. Stilt --- --- Hostel-02 =
561.48
561.48
VII. Refuge Area --- --- 45
Hostel-01 = 15
Hostel-02 = 30
45
VIII. Basement Area --- --- 6,969.67 6,969.67
VIII
(a)
Basement I --- --- 4197.14
For Parking=
2,456.5
For Services=1,740.64
VIII
(b)
Basement II --- --- 2772.53
For Parking=
1925.1
For
Services=847.43
IX. Service Floor Non-FAR --- --- 359.72 359.72
X. Services 1499.55 1499.55
XI. Built up Area
(V+VI+VII+VIII+
IX+X)
5,437.78
675.31 22,462.79 27,225.26
XII. Open Area (Total Plot
Area- Total Ground
Coverage)
15,936.01
XIII. Green Area 4537.76 -- 3,427.245 7,968.005
(50 % of
the open area)
39.84%
XIV. Area under surface
parking
1240 6.2%
XV. Open Area excluding
green area and parking
area
6728 33.64%
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 45 of 48
XVI. Height of the tallest
building upto mumty
level
45.6 mtrs
3.Floor wise area details:
S.No Floors Nett coverd
Area(m2
)
Cut out
Area(m2
)
Refuge Area Services FAR NON FAR
1. Basement-01 4718.94 ---------- ---------- ------- 521.8 4197.14
2. Basement-02 2772.53 --------- ---------- --------- ----- 2772.53
3. Ground/stilt 8456.05 3490.84 ---------- 163.99 4239.74 561.48
4. 1st floor 5628.67 2220.51 ---------- 138.64 3269.52 --------
5. 2nd floor 3542.49 840.28 ---------- 114.03 2588.17 --------
6. Services floors 385.47 25.75 ---------- ------- ----- 359.72
7. 3rd
floor 1037.55 60.39 ---------- 102.67 874.49 --------
8. 4th
floor 1061.91 60.39 ---------- 102.67 898.85 --------
9. 5th
floor 1076.01 60.39 30 102.67 912.95 --------
10. 6th
floor 1061.91 60.39 ---------- 102.67 898.85 --------
11 7th
floor 1076.01 60.39 ---------- 102.67 912.95 --------
12 8th
floor 640.73 29.95 ---------- 59.86 550.92 --------
13 9th floor 654.83 29.95 ---------- 59.86 565.02 --------
14 10 th floor 640.73 29.95 ---------- 59.86 550.92 --------
15 11th
floor 654.83 29.95 ---------- 59.86 565.02 --------
16 12th
floor 640.73 29.95 ---------- 59.86 550.92 --------
17 13th
floor 654.83 29.95 15 59.86 565.02 --------
18 Mumty floor 210.68 ------ ---------- 210.68 ---- --------
Total 34914.9 7059.03 45 1499.85 18465.14 7890.87
4.Built up area calculation details:
Sr. No. Particulars Area in (m
2
)
1. FAR (Existing-Demolished + Expansion) 17,789.84
2. Stilt 561.48
3. Refuge Area 45
4. Basement Area 6,969.67
5. Service Floor Non-FAR 359.72
6. Services 1,499.55
BUILT UP AREA 27,225.26
5.Salient features of the project are as follows:
PROJECT FEATURES DESCRIPTION
Estimated Population 1,525 Nos.
Estimated Water Requirement
Construction Phase
Operation Phase
136 ML (Agency: Private water tanker)
176 KLD (Fresh water = 90 KLD) (Agency: Noida Development
Authority)
Project cost Rs. 50 Crores
Estimated wastewater Generation Approx. 110 KLD
Power Demand
Power Back-up
1,200 kVA
254 kVA (2 x 62 + 1 x 100 +1x30 kVA)
Source of Power Noida Power Corporation Limited
Rain Water Harvesting Pits 5 Pits
Solid Waste Generation 749 kg/day
Parking Facilities
Required
Proposed
As per MoEF norms:225 ECS
As per Noida Bye Laws :225 ECS
225 ECS
6.Population details of the proejct:
S. No. Unit Type Existing Expansion Total Population
1. Trainee 270 1200 1,470
2 Staff 30 25 55
Total Population 1,525
7.Water and waste water details of the project:
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 46 of 48
S. No. Description Area (in m2
) Total
Occupancy
Rate of water
demand
(lpcd)
Total water requirement
(KLD)
1. Trainee 1470 86 126.42
2. Staff 55 30 1.65
Domestic Water requirement 128.07 say 128 KLD
Horticulture &
Landscape
development
7,968.005 -- 6 ltr/m2
/day 48
Total Water Requirement (1 + 2 + 3 ) 176 KLD
Domestic Water Requirement 128 KLD
• Fresh (70% of domestic) 90 KLD
• Flushing (30% of domestic) 38 KLD
Wastewater Generated
(80% fresh + 100% flushing)
(72 + 38) = 110 KLD
8.Solid waste generation details of the project:
S. No. Category Total
Occupancy/Area
kg per capita per
day
Waste generated Kg per day
1. Institutional (Solid waste generation):
1 (a) Trainee 1470 @ 0.5 kg/day 735
1 (b) Staff 55 @ 0.25 kg/day 13.75
2. Horticulture & Landscape Solid waste generation
2(a) Horticulture & Landscape
area
1.9689 acres @ 0.2 kg/acre/day 0.394
Total Solid waste generation 749.144 Say 749 Kg per day
9.The project proposals are covered under category 8"a" of EIA Notification, 2006.
The committee discussed the matter and recommended grant of environmental clearance on
the project proposals alongwith general conditions as earlier prescribed by the authority for
construction project and following specific conditions:
1. The proponent shall submit the copy of structural safety certificate/fire NOC showing the
details of blocks/towers etc duly vetted by competent authority.
2. 03 m peripheral green shall be provided around the project inside the project boundary.
3. Parking provisions as per Development Authority bye-laws should be made. 4. Construction material should be recycled/utilized for internal roads.
5. 15% area of the total plot area shall be compulsorily made available for the green belt development including the peripheral green belt.
6. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
7. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement.
8. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be treated
in captive STP conforming to prescribed standards of receiving body for designated use.
Monitoring of STP to be done daily till its stabilization.
9. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with
regular testing and monitoring of treated water.
10. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users.
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 47 of 48
STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
11. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to 2%
of total project cost shall be prepared and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority. A list of beneficiaries with
their mobile nos./address should be submitted alongwith six monthly compliance reports.
12. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided in the open areas/ stairs cases.
13. Parking guideline as per Noida Development Authority should be followed. Parking for disabled persons should be explored.
14. All entry/exit point should be bell mouth shaped. 15. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge. 16. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only
from the roof top. RWH from green and other open areas shall be done only after permission from CGWB.
17. An underground Pucca tank for collection/reuse of rain water may be constructed.
18. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
19. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be
carried out as CPCB Guidelines.
20. Unless and until all the environmental issues are sorted out the occupancy will be restricted
and would be only allowed after achieving the Permission from the competent authority.
21. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
22. For any extraction of ground water, prior permission from CGWB shall be taken.
23. Sprinkler to be used for curing and quenching and ready mix concrete may be used for construction.
24. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose. 25. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall
be made available to the temporary residents/workers at the project site including the proper treatment and the disposal of the wastes.
20. 200 Bedded Hospitals, at Banda, U.P. Dr. Shekha, Chief Medical Suptt. Banda. File N0. 3154/
AD(H)
The project proponent did not appear. The committee was informed that the project
proponent could not appear because of election duty. The committee discussed and deliberated to
defer the matter till next meeting.
Discussion matter with permission of Chairman:
1. Karaundi Khurd Silica Sand Mine at Village-Karaundi Khurd, Taluka-Mau, District-
Chitrakoot, U.P. (Leased Area 13.02 Ha.) File no. 896/AA(S) The committee was informed that an application dated 30/05/2011 was submitted to SEAC
for environmental clearance of above titled Silica Sand Mine against which a query letter dated
29/06/2011 was communicated to project proponent to submit their replies within 15 days failing
which the case shall be closed. The project proponent informed through letter dated 22/07/2011 that
Minutes of 238th
SEAC Meeting Dated 09/10/2015
Page 48 of 48
the lease was executed to 23/05/1987 for a period of 15 years i.e. 22/05/2002. He applied for its
renewal through letter dated 12/05/2001 to the State Govt. and the application is pending with State
Govt. Hence, he is operating under clause 24-A (6) of MCR 1960 i.e. deemed renewal. He also
submitted that as per EIA Notification 14/09/2006 such mining projects which were operating
before 14/09/2006 would continue to operate without obtaining environmental clearance till the
mining lease is due for renewal. In view of this, he also submitted that as per notification dated
14/09/2006 environmental clearance for non coal mine upto 50 ha lease area is exempted. In this
continuation a letter dated 12/10/2011 was communicated by Director, Environment to Director,
Geology and Mining, U.P. in which details of the case were sent to Director, Geology and Mining.
Director, Environment requested to inquire and inform that whether the mining activity/project is
being considered as lawful renewal by District Administration/Mining Department or not. Also,
what is the validity period of this renewal. Copy of this letter dated 12/10/2011 was endorsed to
Member Secretary, SEIAA, District Magistrate, Chitrakoot, Joint Secretary, Industry Department,
U.P. and Shri Anand Agarwal who is the applicant. A reminder was again sent to Director, Geology
and Mining through letter dated 14/12/2011. ADM, Allahabad through his letter dated 19/11/2011
requested to give comment that whether environmental clearance would be required for the lease
holder whose lease period have been expired prior to 14/09/2006 and to whom format-G were being
issued considering deemed to be renewed.
In this connection Director, Environment through letter dated 23/12/2011 informed District
Magistrate, Allahabad regarding provisions of EIA Notification, 2006. Director, Environment gave
is opinion that leases (05 ha or more) which are being treated as deemed to be renewed shall also
require environmental clearance. However, legal opinion may be taken by District Magistrate in the
matter. Again, Director, Environment through his letter dated 19/03/2012 communicated to
Director, Geology and Mining that SEIAA has not exempted the said matter from the requirement
of environmental clearance and requested to take necessary action in continuation to letter dated
12/10/2011 and 14/12/2011 of SEAC. No communication from Director, Geology Mining, U.P. has
been received till now.
The committee, in view of long pendency of this matter and no information from Mining
Department/project proponent, discussed and deliberated that in light of above facts the matter
should be finally closed. A copy of decision should also be communicated to District Magistrate,
Allahabad, Mining Directorate, U.P.
(Dr. S. N. Singh)
Chaiman, SEAC, UP (S. C. Brahmachari)
Member, SEAC, UP (Dr. D. C. Gupta)
Member, SEAC, UP
(Ajay Kumar Shukla)
Secretary, SEAC, UP/
Director, Environment, UP