ground improvement for tunnels & cross passages
TRANSCRIPT
1
Ground Improvement
for Tunnels & Cross Passages
Babak HamidiPhD, MEng, BEng, MIEAust, AGS, ISSMGE TC-211
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Main Objectives of Ground Improvement 2
• Strength increase
• Bearing capacity
• Slope and wall stability
• Liquefaction
• Deformation reduction
• Vertical (settlement)
• Horizontal
• Differential
• Permeability increase or reduction
• Cut-off of fluid ingress
• Incoming water
• Outgoing fluid
• Water drainage
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
https://www.youtube.com/watch?v=MS4H_u0ARpo
https://independent-photo.com/news/italy/
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Category Method PrincipleA. Ground
improvement
without
admixtures in
non-cohesive
soils or fill
materials
A1. Dynamic compaction Densification of granular soil by dropping a heavy weight from air onto
ground.
A2. Vibro compaction Densification of granular soil using a vibratory probe inserted into
ground.
A3. Explosive compaction Shock waves and vibrations are generated by blasting to cause
granular soil ground to settle through liquefaction or compaction.
A4. Electric pulse
compaction
Densification of granular soil using the shock waves and energy
generated by electric pulse under ultra-high voltage.
A5. Surface compaction
(including rapid impact
compaction).
Compaction of fill or ground at the surface or shallow depth using a
variety of compaction machines.
B. Ground
improvement
without
admixtures in
cohesive
soils
B1.
Replacement/displaceme
nt (including load
reduction using
lightweight materials)
Remove bad soil by excavation or displacement and replace it by good
soil or rocks. Some lightweight materials may be used as backfill to
reduce the load or earth pressure.
B2. Preloading using fill
(including the use of
vertical drains)
Fill is applied and removed to pre-consolidate compressible soil so that
its compressibility will be much reduced when future loads are applied.
B3. Preloading using
vacuum (including
combined fill and
vacuum)
Vacuum pressure of up to 90 kPa is used to pre-consolidate
compressible soil so that its compressibility will be much reduced when
future loads are applied.
B4. Dynamic
consolidation with
enhanced drainage
(including the use of
vacuum)
Similar to dynamic compaction except vertical or horizontal drains (or
together with vacuum) are used to dissipate pore pressures generated
in soil during compaction.
B5. Electro-osmosis or
electro-kinetic
consolidation
DC current causes water in soil or solutions to flow from anodes to
cathodes which are installed in soil.
B6. Thermal stabilization
using heating or freezing
Change the physical or mechanical properties of soil permanently or
temporarily by heating or freezing the soil.
B7. Hydro-blasting
compaction
Collapsible soil (loess) is compacted by a combined wetting and deep
explosion action along a borehole.
C. Ground
improvement
with
admixtures
or inclusions
C1. Vibro replacement or
stone columns
Hole jetted into soft, fine-grained soil and back filled with densely
compacted gravel or sand to form columns.
C2. Dynamic replacement Aggregates are driven into soil by high energy dynamic impact to form
columns. The backfill can be either sand, gravel, stones or demolition
debris.
C3. Sand compaction
piles
Sand is fed into ground through a casing pipe and compacted by either
vibration, dynamic impact, or static excitation to form columns.
Category Method PrincipleC4. Geotextile
confined columns
Sand is fed into a closed bottom geotextile lined cylindrical hole to form
a column.
C5. Rigid inclusions Use of piles, rigid or semi-rigid bodies or columns which are either
premade or formed in-situ to strengthen soft ground.
C6. Geosynthetic
reinforced column or
pile supported
embankment
Use of piles, rigid or semi-rigid columns/inclusions and geosynthetic
girds to enhance the stability and reduce the settlement of
embankments.
C7. Microbial methods Use of microbial materials to modify soil to increase its strength or
reduce its permeability.
C8 Other methods Unconventional methods, such as formation of sand piles using blasting
and the use of bamboo, timber and other natural products.
D. Ground
improvement
with grouting
type admixtures
D1. Particulate
grouting
Grout granular soil or cavities or fissures in soil or rock by injecting
cement or other particulate grouts to either increase the strength or
reduce the permeability of soil or ground.
D2. Chemical grouting Solutions of two or more chemicals react in soil pores to form a gel or a
solid precipitate to either increase the strength or reduce the
permeability of soil or ground.
D3. Mixing methods
(including premixing or
deep mixing)
Treat the weak soil by mixing it with cement, lime, or other binders in-
situ using a mixing machine or before placement
D4. Jet grouting High speed jets at depth erode the soil and inject grout to form columns
or panels
D5. Compaction
grouting
Very stiff, mortar-like grout is injected into discrete soil zones and
remains in a homogenous mass so as to densify loose soil or lift settled
ground.
D6. Compensation
grouting
Medium to high viscosity particulate suspensions is injected into the
ground between a subsurface excavation and a structure in order to
negate or reduce settlement of the structure due to ongoing excavation.
E. Earth
reinforcement
E1. Geosynthetics or
mechanically stabilized
earth (MSE)
Use of the tensile strength of various steel or geosynthetic materials to
enhance the shear strength of soil and stability of roads, foundations,
embankments, slopes, or retaining walls.
E2. Ground anchors or
soil nails
Use of the tensile strength of embedded nails or anchors to enhance
the stability of slopes or retaining walls.
E3. Biological methods
using vegetation
Use of the roots of vegetation for stability of slopes.
Chu, J., Varaksin, S., Klotz, U. & Mengé, P. (2009) State of the Art Report: Construction Processes. 17th International
Conference on Soil Mechanics & Geotechnical Engineering: TC17 meeting ground improvement, Alexandria, Egypt, 7
October 2009, 130.
Ground Improvement Techniques 3
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
TechSpan (Reinforced Earth Company)
Tunnel Type: Buried Structure 4
Tunnel Type: Cut and Cover 5
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Sydney Metro Waterloo Station
Tunnel Type: Excavated/Bored/Pipe Jacking 6
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Binningup Desalination Plant (SSWA)
Grouting Technology in Tunnelling 7
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Kogler, K. (2013) Grouting Technology in Tunnelling. Geomechanics and Tunnelling 6, 3, 261-273.
Ground Tunnelling method Purpose of grouting Construction conditions Geometrical requirements Grout
material
rock or solid stone TBM consolidation from above ground grouted canopy or screen suspensions
alluvium or soil conventional waterproofing from underground face support mortars and
pastes
Compensation from shafts ring-shaped temporary support Solutions
prestress grouting of pressure tunnel compensation bodies emulsions
grouting to remedy a collapse Resins
polyamide
Construction Conditions 8
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Arroyo, M., Gens, A., Croce, P., and Modoni, G. "Design of jet-grouting for tunnel waterproofing." 7th International Symposium on Geotechnical Aspects of Underground Construction in Soft Ground, Rome, 181-188.
Croce, P., Flora, A., and Modoni, G. (2014). Jet Grouting Technology, Design and Control, CRC Press, Boca Raton, FL, USA.
Kogler, K. (2013) Grouting Technology in Tunnelling. Geomechanics and Tunnelling 6, 3, 261-273.
Grouting from Shafts
Grouting from above ground
Grouting from underground
Grouting from underground
Geometric Requirements 9
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Canopy (umbrella)
Compensation body
Canopy with face support
Support ring
British Standards Institution (2001) BS EN 12716: Execution of Special Geotechnical Works - Jet Grouting.
Kogler, K. (2013) Grouting Technology in Tunnelling. Geomechanics and Tunnelling 6(3):261-273.
Guatteri, G., Koshima, A., Lopes, R., Ravaglia, A. & Pieroni, M. R. (2008) Historical Cases and Use of Horizontal Jet Grouting Solutions with 360o Distribution and Frontal
Septum to Consolidate Very Weak and Saturated Soils. 6th International Symposium on Geotechnical Aspects of Underground Construction in Soft Ground, pp. 287-294.
Geometric Requirements 10
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Arroyo, M., Gens, A., Croce, P., and Modoni, G. "Design of jet-grouting for tunnel waterproofing." 7th International Symposium on Geotechnical Aspects of Underground Construction in Soft Ground, Rome, 181-188.
Filippini, R., Kovari, K. & Rossi, F. (2012) Construction of a Cavern under an Autobahn Embankment for the Ceneri Base Tunnel. Geomechanics and Tunnelling, 5, 2, 175-185.
Perri.3SARMC.1990.Jet Grouting in Tunneling - Consolidation in the El Silencio Manouvering Section of the Second Line Caracus Subway
Trunk, U. & Winkler, F. (2013) Jet Grouting in Tunnelling. Geomechanics and Tunnelling, 6, 3, 274-289.
Ceneri Base Tunnel, Switzerland 11
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Filippini, R., Kovari, K. & Rossi, F. (2012) Construction of a Cavern under an Autobahn Embankment for the Ceneri Base Tunnel. Geomechanics and
Tunnelling, 5, 2, 175-185.
Jetting the foundation bodies
Driving the abutment headings
Bench excavation to complete profile
Concreting the abutments
Excavation of the top heading with jet
grout canopy and shotcrete support
Grout Material
Grout Definition Composition Main application
Mortars and
pastes
suspensions with high solid
content
water, cement and sand, possible with
additives W/C ratio < 1
filling of cavities and fissures
Suspensions fine suspension of undissolved
solids in a liquid
water, cement or fine cement, if required
bentonite PFA W/C value > 1
waterproofing and consolidation of gravelly and sandy
soils, joints and fissures in rock
Solutions solution of solids in solvent water, silicate and hardener synthetic resins
and plastics
waterproofing and consolidation of sandy and fine gravelly
soils
Emulsions mixtures of two or more liquids water, bitumen, emulgators water-insoluble
silicate hardener
waterproofing of fine sand soils
resin grouts two-component resins with
high viscosity
rubber and chemical hardener, possible with
fillers
waterproofing of very fine fissures and cracks mechanically
effective grouting or rock and building elements
PU foams polyurethane foam, mostly two
components
polyurethane with chemical hardner temporary waterproofing of large water passages in gravel
and rock
Polyamide melted polyamide granulate single-component polyamide granulate with
high viscosity
temporary and permanent waterproofing of large water
passages in soil and rock
12
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Kogler, K. (2013) Grouting Technology in Tunnelling. Geomechanics and Tunnelling 6, 3, 261-273.
Grouting Technologies: Soil/Rock Grouting
• With or without pressure
• With or without packer
• Tube a Manchette (TAM)
13
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Houlsby, A. C. (1990) Construction and Design of Cement Grouting - A Guide to Grouting in Rock Foundations. USA, John Wiley.
Storeb Aelt Tunnel Cross Passages, Denmark 14
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
• 1992- 1995
• Sandy-clayey glacial till: consolidated and made impervious by grouting with bentonite cement or ultra-fine cement slurry.
• Half length of each cross passage was treated from each side to keep borehole length to less than approximately 12 m long and maintain the necessary degree of accuracy.
Glacial deposits
Marl
Glacial ???
Melbourne West Gate Tunnel Southern Portal 15
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
WGT Inbound Portal Ground Conditions 16
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
WGT Inbound Portal Ground Conditions 17
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Fractured Newer Volcanics (NVF) Core Sample
Slightly Weathered Newer Volcanics (NVS) Core Sample
Brecciated Newer Volcanics (NVB) Core Sample
Groundwater level
• Inbound: RL 3 m to RL 1.5 m
• Outbound: RL 5 m
WGT Inbound Portal Grouting Sections 19
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
WGT Grouting Details
• Upstage grouting using packer and grouting at 6 m intervals
• Termination criteria:
• Maximum pressure: 2 * overburden at the bottom of the hole
• Flow rate: 5litres/min for 5 min
• Max Volume: 500 litres/stage
• Grouting stages
• Primary (at 12 m)
• Secondary
• Tertiary
• Quaternary
• Quintenary
20
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Grouting Technologies: Jet Grouting 23
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Sequencing 25
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Croce, P., Flora, A., and Modoni, G. (2014). Jet Grouting Technology, Design and Control, CRC Press, Boca Raton, FL, USA.
Alignment and Variability 26
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Croce, P., Flora, A., and Modoni, G. (2014). Jet Grouting Technology, Design and Control, CRC Press, Boca Raton, FL, USA.
Modoni, G., Flora, A., Lirer, S., Ochmański, M., and Croce, P. (2016). "Design of Jet Grouted Excavation Bottom Plugs." Journal of Geotechnical and Geoenvironmental Engineering, ASCE, 142(7), 04016018.
Overlapping 27
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Croce, P., Flora, A., and Modoni, G. (2014). Jet Grouting Technology, Design and Control, CRC Press, Boca Raton, FL, USA.
Liu, Y., Pan, Y., Sun, M., Hu, J., and Yao, K. (2018). "Lateral compression response of overlapping jet-grout columns with geometric imperfections in radius and position." Canadian Geotechnical Journal, 55(9), 1282–1294.
Modoni, G., Flora, A., Lirer, S., Ochmański, M., and Croce, P. (2016). "Design of Jet Grouted Excavation Bottom Plugs." Journal of Geotechnical and Geoenvironmental Engineering, ASCE, 142(7), 04016018.
Controlling Alignment
• Correct location and angle at collar level
• Maintaining/verifying straightness
29
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
QA-QC: Visual Observation & Measuring by Excavation 30
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
QA-QC: Indirect Tests 32
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
• Informative suggestions in EN12716:2001
• Cross-hole geophysical tests
• CPT
• SPT
• DPC
• PMT
• Other
• Calliper
• Inspection holes using painted pipes
• Acoustic monitoring (hydrophone)
• Temperature measurement
Jet
Recording holes
Croce, P., Flora, A., and Modoni, G. (2014). Jet Grouting Technology, Design and Control, CRC Press, Boca Raton, FL, USA.
Langhorst, O. S., Schat, B. J., de Wit, J. C. W. M., Bogaards, P. J., Essler, D. R., Maertens, J., Obladen, B. K. J., Bosma, C. F., Sleuwaegen, J. J., and Dekker, H. (2007) Design and validation of jet grouting for the Amsterdam Central Station, 14th ECSMGE, 18-21.
QA-QC: Electrical Resistivity Tomography
• Recording & analysing the potential differences generated by an induced electric current around a borehole.
• Instrumentation introduced into the test hole consists of a multi-core cable with emission electrodes interspersed with receiving electrodes.
• Potential difference is set up between each emission electrode and the receiving electrode.
• Electric field around hole takes the form of a cylinder, 5m to 10m in diameter.
• Deflections in the resistivity equipotential lines identify features such as voids, loose zones, clay beds, etc.
• Resistivity
• Ground resistivity is usually tens of ohm-m
• Jet grouted column:
• Initially a few ohm-m.
• Increases over time as the material hardens →contrast diminishes & eventually reverses.
• Advantage: Provides results shortly after construction of the column has been completed without waiting for column exposure, core drilling, etc.
33
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
QA-QC: Grout Mix & Spoil Quality
• Grout
• Apparent Viscosity (Marsh funnel test)
• Bulk Density: Mud balance test
• Bleeding (if specified)
• Unconfined Compressive Strength (if specified)
• Jet Grouted Material
• Bulk density (as specified)
• Unconfined Compressive Strength (where relevant)
• Setting time (if specified and applicable)
• Permeability (if required)
34
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
La Duchere Tunnel, France 35
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
• Blasting in weathered gneiss
• Extremely weathered rock covered by 15 to 20 m of clayey-sandy colluvium → collapse
• Collapse: 15-20 m diameter, 4 to 5 m depression
• Grouting works:
• Compaction grouting from surface
• Jet grouted canopy
Project 2: Typical Cross Passage Grouting Detail 40
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Up to 40 m deep
Typical Cross Passage Plan View 41
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Typical Cross Passage Sections 42
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Typical Cross Passage Isometric View 43
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Cross Passage Jet Grouting from Under a Bridge 44
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
Cross Passage Jet Grouting from Under a Bridge 45
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019
QA-QC – Electrical Resistivity Tomography 46
16-18 June 2019 ATS Tunnel Design & Construction Short Course 2019