earthquake emergency assistance project
TRANSCRIPT
Initial Environmental Examination
Haldebesi – Dhobi - Dhandebesi Road Rehabilitation and Reconstruction Sub-project July 2017
NEP: Earthquake Emergency Assistance Project
Prepared by District Coordination Committee (Ramechhap)- Central Level Project Implementation Unit – Ministry of Federals Affairs and Local Development for the Asian Development Bank.
This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Environmental Assessment Document
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
Initial Environmental Examination (IEE)
Haldebesi – Dhobi - Dhandebesi Road Rehabilitation
and Reconstruction Sub-project
July 2017
NEP: Earthquake Emergency Assistance Project Loan: 3260 Project Number: 49215-001
Prepared by the Government of Nepal for the Asian Development Bank (ADB).
This Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
Initial Environmental Examination (IEE) of
Haldebesi-Dhobi-Dhandebesi Road Rehabilitation and Reconstruction Sub-project,
Ramechhap District
Submitted to
Government of Nepal
National Reconstruction Authority
Singhadurbar, Kathmandu
Submitted through
Government of Nepal
Ministry of Federal Affairs and Local Development
Earthquake Emergency Assistance Project
Central Level Project Implementation Unit, Lalitpur
Submitted by
District Coordination Committee, Ramechhap
July, 2017
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
i
Executive Summary (in Nepali)
!= k[i7e"ld
@)&@ ;fn a}zfv !@ ut] uPsf] ljWj+;sf/L e"sDk / ;f]xL jif{ a}zfv @( uPsf] d'Vo k/fsDksf sf/0f Ifltu|:t :yfgLo ;+/rgfx?sf] k'g:yf{kgf tyf k'glg{df{0f u/L :yfgLo ;d'bfosf] cfly{s tyf ;fdflhs k'gp{Tyfg ug{ Pl;ofnL ljsf; a}+ssf] ;xof]udf tyf :jL; ljsf; lgof]usf] k|fljlws ;xof]udf k|efljt !@ lhNnfdf e"sDk cfktsfnLg ;xfotf cfof]hgf nfu' ul/Psf] 5 . o; cfof]hgfsf] dfWodåf/f Pl;ofnL ljsf; a}+sn] dxTjk"0f{ ;8s ;+hfnsf] k'glg{df{0f ug{, xhf/f}+ afnaflnsfnfO{ k'gM ljBfno k'¥ofpg, k|efljt ;d'bfonfO{ cTofjZos ;sf/L ;]jf pknAw u/fpg g]kfn ;/sf/nfO{ ;xof]u ug]{5 . o; cfof]hgfn] e"sDk tyf klx/f]åf/f Ifltu|:t sl/a !#% ls=ld= /0fg}lts ;8s tyf $%) ls=ld= u|fld0f ;8ssf] k'glg{df{0f ug]{5 . o; cfof]hgfsf] sfo{sf/L lgsfo /fli6«o k'glg{df{0f k|flws/0f /x]sf] 5 . u|fld0f ;8ssf] xsdf o; cfof]hgfsf] cfwf/e"t ;fem]bf/sf ?kdf lhNnf ;dGjo ;ldlt, lhNnf k|fljlws sfof{no, ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /x]sf 5g\ .
xNb]a];L—wf]aL—9fF8]a];L -#*=*(( ls=ld=_ ;8ssf] k'g:yf{kgf tyf k'glg{df{0f pkcfof]hgf sf] e"sDk cfktsflng ;xfotf cfof]hgf cGtu{ts} Pp6f pkcfof]hgf xf] . lhNnf:t/Lo sfo{sfl/0fL lgsfosf] ?kdf tTsflng /fd]5fk lhNnf ljsf; ;ldlt -xfn /fd]5fk lhNnf ;dGjo ;ldlt_ o; pkcfof]hgfsf] lhNnf:t/Lo sfo{sfl/0fL lgsfo xf] . pkcfof]hgf ;~rfngsf qmddf kg{;Sg] ;sf/fTds tyf gsf/fTds jftfj/0fLo Pj+ ;fdflhs k|efjnfO{ ;Daf]wg ug{sf] of] k|f/lDes jftfj/0fLo kl/If0f (IEE) k|ltj]bg ;f] tof/ ul/Psf] xf] .
k|:tfljt pkcfof]hgf sfof{Gjogn] @)&@ ;fn a}zfv !@ ut] uPsf] ljWj+;sf/L e"sDk / ;f]xL jif{ a}zfv @( df uPsf] d'Vo k/fsDksf sf/0f pNn]Vo ?kdf Ifltu|:t o; ;8s v08nfO{ k'gM ;+rfngdf NofO{ /fd]5fk lhNnfsf] lnv' ufFpkflnsfsf] j8fx? @, #, $, % / & -;fljs ;}+k', lah'nLsf]6, gfubx / ltNk'ª uf=lj=;=_ tyf ToxfFsf !$ eGbf j9L jl:tx?nfO{ tTsflng lhNnf ;b/d'sfd dGynL tyf b]zsf cGo If]q;Fu ;8s ;+hfn dfkm{t hf]8\g]5 .
@= k|:tfjs
e"sDk cfktsfnLg ;xfotf cfof]hgf (EEAP) cGtu{t xNb]a];L—wf]aL—9fF8]a];L ;8s -#*=*(( ls=ld=_ k'g:yf{kgf tyf k'glg{df{0f pkcfof]hgfsf] lhNnf:t/Lo sfo{sf/L lgsfo Pj+ k|f/lDes jftfj/0f kl/If0fsf] nflu k|:tfjssf] ?kdf tTsflng lhNnf ljsf; ;ldlt -xfn /fd]5fk lhNnf ;dGjo ;ldlt_ sf] sfof{no /fd]5fk /x]sf] 5 .
k|:tfjssf] k'/f 7]ufgf lhNnf ;dGjo ;ldltsf] sfof{no /fd]5fk dGynL, /fd]5fk ;Dks{ kmf]g M )$*—%$)#$&, %$)!!$ km\ofS; M )$*—%$))@( #= k|f/lDes jftfj/0fLo k/LIf0fsf] cf}lrTo tyf p2]Zo
e'sDkaf6 k|efljt ;+/rgfsf] k'glg{df0f{ ;DaGwL] P]g, @)&@, e'sDkaf6 k|efljt ;+/rgfsf] k'glg{df0f ;DaGwL lgodfjnL, @)&@ tyf e"sDk k|efljt ;+/rgfsf] k'glg{df{0fsf] nflu jftfj/0fLo k|efj d'Nof+sg ;DaGwL sfo{ljlw @)&@ / klxnf] ;+;f]wg @)&# -cg';'rL !_ Pj+ Pl;ofnL ljsf; a}+ssf] ;'/If0f
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
ii
gLlt syg -;]kmuf8{ kf]nL;L :6]6d]G6_ @))( cg';f/ jftfj/0fLo k|efjsf] Jojxf/Ls tyf 7fFp laif]z Go"lgs/0f tyf nfea[[¢Lsf pkfox? ;'emfj ug{ k|f/lDes jftfj/0fLo kl/If0f cWoog sfo{ cfjZos b]lvG5 .
k|f/lDes jftfj/0fLo k/LIf0f k|ltj]bg cWoogsf] d'Vo p2]Zo pkcfof]hgf If]qsf] ef}lts, h}ljs, ;fdflhs, cfly{s tyf ;f+:s[lts jftfj/0fdf kg]{ k|efjx? kQf nufpg'sf ;fy} jftfj/0fdf kg]{ gsf/fTds k|efjsf] Go"lgs/0fsf pkfox? / ;sf/fTds k|efj a9fpg] pkfox? af/] ;'emfj lbg' / jftfj/0fLo Aoa:yfkg of]hgf agfO{ sfof{Gjog u/fpg' /x]sf] 5 .
$= k|:tfjsf] ljj/0f tyf cWoog ljlw
k|:tfljt pkcfof]hgf /fd]5fk lhNnfsf] lnv' ufpFkflnsfsf j8f @, #, $, % / & -;flas ;}+k', lah'nLsf]6, gfubx / ltNk'ª uf=lj=;=_ af6 k|j]z ub{5 . tTsflng lh=lj=;= /fd]5fkn] o; ;8ssf] xNb]a];L b]vL 9fF8]a];L;Dd #*=*(( (Ch 0+000 to 38+899) ls=ld= v08nfO{ e"sDk cfktsfnLg ;xfotf cfof]hgf cGtu{t k'glg{ld{0fsf] k|:tfj u/]sf] 5 . o; ;8snfO{ k|yd :t/sf] lhNnf ;8ssf] dfkb08df u|fe]n :t/df k'glg{df{0f ul/g] 5 . 5]psf] 9n / ;f]Nh/ ;lxt o;sf] s'n rf}8fO{ ^=@% ld= x'g]5 . o; pkcfof]hgfsf] OlGhlgol/ª nfut d'=c=s= ;lxt g]=?=@*#,$@*,)&!=$@ /x]sf] 5 .
of] k|f/lDes jftfj/0fLo kl/If0f k|ltj]bg g]kfn ;/sf/sf] sfg"gL cfj:ostf k'/f ug{ cfjZos ;Gbe{ ;fdfu|Lx?sf] k"j{cWoog tyf :ynut cWoog / ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfnosf] ;lrj:t/Lo lg0f{oåf/f @)&@.!@.!) ut] :jLs[t sfo{;'rLsf] clwgdf /lx tof/ ul/Psf] 5 .
%= pkcfof]hgfsf] ljBdfg jftfj/0fLo cj:yf
pkcfof]hgf If]q dWo kfxf8L ef}uf]lns If]qdf /x]sf] 5 . o; If]qsf] e'uf]ndf 7f8f eL/ tyf pkTosf /x]sf 5g\ . ef}ule{s b[li6sf]0fn] of] If]qdf dWo kfxf8L If]qsf] dWo / pRr sf]6Lsf] kl/jlt{t -d]6fdlkm{s r§fg_, d'Vo?kdf lkmnfO6, PlDkmaf]nfO{6, d]6f:ofG8:6f]g / l;:6 kfOG5 .
ef}uf]lns prfO{sf] leGgtfsf sf/0f o; pkcfof]hgf If]qdf pi0f, pkf]i0f / Gofg] ;dlztf]i0f xfjfkfgL kfOG5 . o; If]qsf] tfkqmd udL{df #) l8=;]=;Dd k'Ug] / lxpFbdf % l8=;]= ;Dd emg]{ u/]sf] 5 . oxfF jflif{s ;/b/ !&)) ld=ld= jiff{ x'g] u/]sf] 5 . k|:tfljt ;8sdf !@ eGbf j9L ;fgf v]flN;x? /x]sf 5g\ 7"nf vf]nf o; v08df kb}{gg\ . k|:tfljt ;8s 5]psf] e"pkof]udf jgIf]q, s[lif, cfjf; tyf ahf/ If]q /x]sf 5g\ .
of] pkcfof]hgf v]taf/L, cfjf; If]q, jg tyf v'Nnf If]qaf6 k|j]z ub{5 h;dWo] )±)*) b]lv )±&*) tyf @±%() b]lv #±)^), !±%@) b]lv !±*$%, !^±*)) b]lv !&±))), @$±!)) b]lv @$±@%), @^±))) b]lv @^±@)), #)±)!) b]lv #!±!)), #^±)!) b]lv #&±)() / #&±!%) b]lv #&±$$% ;Ddsf v08x? ljleGg cf7 -*_ j6f ;fd'bfls jg qmdzM v'Djf/L ;f=j=, /fDr] ;f=j=, v/fª v'?Ë ;f=j=, em§]Zj/L ;f=j=, e[Ë]Zj/ ;f=j=, kf]s' ;fn3f/L -;}k'_ ;f=j=, tf?s] ;Nn]gL ;f=j= / ;}k' kfvf ;f=j=af6 k|j]z ub{5 . o; ;8ssf] ;'?jflt v08df ;fn / af]6 wo/f] h:tf ?vx? kfOG5g\ eg] clwsf+z If]qdf lrnfpg], ;NNff, plQ; cflb kfOG5 . To;}u/L ;8ssf] clGtd v08df lnv' vf]nfsf] lsgf/df vo/, l;dn, l;;f} cflb kfOG5 . ;8s lsgf/df e]l6Psf jg:kltx?df eg] ;fn, c:gf, af]6 wo/f], hfd'gf, lug]/L, ufof] cflb /x]sf 5g\ . o; If]qsf] h+undf kfOg] jGo hGt'x?df d[u, dn;fk|f]] cflb k'b{5g\ .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
iii
k|:tfljt ;8s /fd]5fk lhNnfsf] lnv' ufpFkflnsfsf j8f @, #, $, % / & -tTsflng ;}+k', lah'nLsf]6, gfubx / ltNk'ª uf=lj=;=_ cGtu{t cGtu{t xNb]a];L, /ftdf6], ltNk'ª, bfl/daf]6, 9fF8], rfvs{, nfdfufpF, wf]jL, sf]6ufpF, wf/fkfgL, kf]s', l;l/;], a]nf}/L, 9fF8]a];L nfufotsf !$ eGbf a9L jl:tx? kb{5g\ . k|efljt If]qdf $(@* 3/w'/Lddf !)^!% k'?if / !@$($ dlxnf u/L hDdf @#!)( hg;+Vofsf] a;f]af; /x]sf] 5 . o; If]qd If]qL hftLsf dflg;sf] afx'Notf /x]sf] 5 eg] cGo k|d'v hfltdf tfdfª / du/ /x]sf 5g\ . cfof]hgf If]qsf] ;fIf/tf b/ ^@=(* k|ltzt /x]sf] 5 . cfof]hgf If]qsf w]/}h;f] AolQmx? s[lif / kz'kfng k]zfdf ;+nUg 5g\ . cGo d'Vo k]zfdf Aofkf/ / j}b]lzs /f]huf/ dxTjk"0f{ 5g\ . ;8s If]qdf Rff/j6f pk:jf:Yo rf}sLn] :jf:Yo ;]jf k'¥ofpFb} cfPsf 5g\ . vfg]kfgLsf] nflu ()=!@ k|ltzt 3/w'/Ln] kfOkåf/f ljtl/t kfgLsf] k|of]u ub{5g\ . k|efljt If]qdf tTsflng ltNk'ª / ;}+k' uf=lj=;=sf s]xL 3/w'/Ldf dfq ljB't ;]jf k'u]sf] 5 . oxfFsf] k|d'v :yfgLo ahf/ xNb]a];L, wf]aL / 9fF8]a];L x'g\ eg] d'Vo ahf/ eg] dGynL, /fd]5fk / rl/sf]6df /x]sf] 5 .
^= jftfj/0fLo k|efjx?
^=! ;sf/fTds k|efjx?
pkcfof]hgf lgdf{0fsf qmddf tTsfn b]lvPsf ;sf/fTds k|efjx?df o;n] #(!,%*) JoQmLlbg a/fj/sf] c:yfoL /f]huf/Lsf] cj;/ ;[hgf ug]{ 5 . o;}u/L pkcfof]hgf ;~rfng kl5 x'g] ;sf/fTds k|efjx?df /fd]5fk lhNnfsf] lnv' ufpFkflnsfsf j8f @, #, $, % / & sf hgtfnfO{ aif}e/L oftfoftsf] ;'ljwf tyf kx'Fr, s[lif pBf]usf] k|j4{g, cfly{s ljsf;, cfbL /x]sf 5g\ . ;8s ;+rfngdf cfPkl5 pkcfof]hgf k|efljt If]qsf hgtfx?nfO{ ;fdflhs ;]jf h:t}M :jf:Yo, lzIff, ;fd'bflos ;]jf, ahf/ tyf cGo ;'lawfdf ;xh / b|"t kxF'r k|fKt x'g]5 . o; ;8ssf] k'g:yf{kgf tyf k'glg{df{0f kl5 o; If]qdf b}lgs pkEff]Uo a:t'x?, vfB tyf cGo a:t'x?sf] cfk'lt{ ;xh x'g]5 eg] o; If]qsf] s[lif pkh cflbn] klg ;xh ahf/ k|fKt ug]{5 h;n] ubf{ hLjg:t/ a[l4 x'g]5 / e"sDk k|efljt hgtfsnfO{ ;fdflhs tyf cfly{s k'g:yf{kgfdf d2t k'Ug]5 .
^=@ gsf/fTds k|efjx?
pkcfof]hgf lgdf{0fsf qmddf jftfj/0fsf] ;fdflhs cjojdf b]lvg;Sg] k|d'v gsf/fTds k|efjx?df pknAw ;]jf ;'ljwfdf bjfj, :yfgLo / cfuGt's sfdbf/x? lar åGb l;h{gf, k]zfut :jf:Yo tyf ;'/Iffdf k|efj, cflb d'Vo ;/f]sf/sf /x]sf 5g . ;8s lj:tf/ tyf gfln lgdf{0f ubf{ ljleGg lsQf tyf hUufwlgdf ljeflht @=(* x] lghL hUuf k|fKt ug'{kg]{ b]lvG5 . cGo c;/x?df sfo{ / Hofnf ljt/0fdf n}+lus lje]b, hf]lvdk"0f{ sfo{df gfjfnsfx?sf] k|of]u, c:j:y cfjf;sf sf/0f km}lng] /f]u, zf/Ll/s ;Dks{sf sf/0f ;g]{ of}g /f]u tyf cGo ;?jf /f]ux? x'g;Sg] b]lvG5g\ . ;fy} cfof]hgf ;+rfng kZrft pknAw ;'ljwfsf sf/0f ;8s lsgf/df cJojl:yt j;f]jf; a9\g uO{ ;8s If]q cltqmd0f x'g] ;Defjgf klg /xG5 .
;8s lgdf{0f k|s[ofdf k|of]u x'g] pks/0f, ;jf/L;fwg Pj+ /;folgs tTjx?sf] sf/0f Wjlg, xfjf / kfgL k|b'lift x'g ;S5 . kmf]xf]/sf] plrt Joj:yfkg gePdf hn tyf hldgsf] k|b'if0fn] cGo gsf/fTds k|efj lgDTofpg] ;Defjgf /xG5 . lgdf{0f ;fdlu|x?sf] ;d'lrt e08f/0f tyf ;+rfng gubf{ r'xfj6sf sf/0f ;txL tyf e'ldut hn k|b'lift x'g;Sb5 . h}ljs jftfj/0fdf kg]{ k|efjsf] ;Gbe{df rf]/Llzsf/Lsf sf/0f jGohGt'df kg]{ k|efjnfO{ dxTjk"0f{ dfGg ;lsG5 . ;8s lj:tf/sf qmddf @$±!)) b]lv @$±@%), @^±))) b]lv @^±@)), / #)±)!) b]lv #!±!)), #^±)!) b]lv #&±)() / #&±!%) b]lv #&±$$% ;Dd qmdzM em6\6]Zj/L, e[Ë]Zj/, kf]s' ;fn3f/L -;}k'_ ;f=j=, tf?s] ;Nn]gL ;f=j= / ;}k' kfvf ;f=j=sf] hDdf !)% j6f lrnfpg], plQ;, af]6 wo/f], kf}jf / dn]bf]sf ?vx? sf6\g'kg]{ b]lvG5 .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
iv
&= Go"lgs/0fsf pkfox?
cfof]hgfsf] gsf/fTds c;/x? Go"lgs/0f ug{sf nflu ljleGg Jojxfl/s tyf ldtJooL pkfox? ;'emfj ul/Psf] 5 . cfof]hgfsf k|:tfjsn] cfof]hgf lgdf{0f tyf ;~rfngsf] cjlwdf o:tf pkfox? cjnDag ug]{ 5g\ . cfof]hgf lgdf{0f cjlwsf] qmddf k|:tfjsn] lgdf{0f Joj;foL dfkm{t Go'gLs/0fsf pkfox? nfu" ug]{]5 . cjnDag ul/g] s]xL k|d'v pkfox? lgDgfg';f/ 5g\ .
cled'lvs/0f tyf Ifdtf ljsf; tflnd dfkm{t dxLnf tyf ljkGg au{sf] ;;lQms/0f ul/g]5 .
lghL hUuf, lghL ;+/rgf / lghL ?vla?jf nufotsf lghL ;DklQsf] clwu|x0f ubf{ Ifltk'lt{ lbOg]5 .
l;+rfO{sf s'nf]x?sf] xsdf ;se/ ltgsf] ;+/If0f jf Iflt k'u]df lgdf{0f kZrft k'g:yf{kgf ul/g]5 .
:yfgLo ;]jf ;'ljwfdf bjfj sd ug{ 7]s]bf/n] b}lgs pkef]Uo cfjZostf h:t} vfg] kfgL, ;+rf/, tyf vfgf ksfpg] OGwg, cflbsf] Joj:yf SofDkleq} ug]{ 5 . lgdf{0f ultljlwsf sf/0f s'g} ef}lts ;+/rgfdf Iflt x'g uPdf To;sf] k'glg{df{0f jf k'g:yf{kgf ul/g] 5 .
k]zfut :jf:Yo / ;'/Iffsf] ;/f]sf/sf nflu cfjZos tof/L ul/g] 5 . sfdbf/x?nfO{ x]Nd]6, kGhf, a'6, ;'/IffTds k]6L, r:df, df:s cflb k|bfg ul/g] 5 . lgdf{0f / e08f/0f:yndf cgflws[t k|j]z / ultljlw /f]Sg vt/fsf ;+s]tx?, 5]saf/ Pj+ kfn]sf] Joj:yf ul/g] 5 .
SofDk tyf lgdf{0f If]qaf6 %) ld k/ c:yfO{ rkL{sf] Joj:yf ul/g] 5 / ltgnfO{ kfgLsf] ;|f]taf6 %) ld k/ /flvg] 5 .
pTvgg\af6 lg:s]sf] df6f]nfO{ lgwf{l/t :yfgdf 6f] jfn, l/6]lgË jfn, j[Iff/f]k0f / cfjZostf cg';f/ gfnLx? lgdf{0f u/L ;xL tl/sfn] Joj:yfkg ul/g]5 .
ljBdfg / ;Defljt klx/f]nfO{ pko'Qm h}ljs k|ljlwsf] k|of]u u/L lgoGq0f tyf /f]syfd ul/g]5 .
cfof]hgf lgdf{0fsf] qmddf lg:sg] 3/]n' tyf lgdf{0fhGo kmf]xf]/d}nfnfO{ gbLIf]q af6 k/ pko'Qm :yfgdf / efF8f]df ;+sng ul/g] 5 / ltgsf] k|sf/ cg'?k Joj:yfkg ul/g]5 .
lgdf{0f ultljlwdf k|of]u x'g] t]n tyf cGo /;folgs kbfy{x?nfO{ pko'Qm :yfgdf Wofgk'j{s e08f/0f tyf pkof]u ul/g] 5 .
cfof]hgfn] sf6\g] kfFr ;fd'bflos agsf !)% ?vx?sf] Ifltk'lt{sf nflu @,^@% -!M@% sf] cg'kftdf_ j6f ?vx? /f]kL ;fd'bfls jg dfkm{t ;+/If0fsf] Joj:yf ldnfOg] 5 .
jGohGt'sf] rf]/Ll;sf/L lgoGq0f tyf ltgsf] ;+/If0f ;DaGwL ;r]tgf hufpg] ;Gb]z af]s]sf] xf]l8{Ë af]8{x? /flvg]5 .
*= ;fj{hlgs k/fdz{ tyf ;"rgf ;fj{hlgs ug]{
k|f/lDes jftfj/0fLo k/LIf0f k|ltj]bg tof/Lsf] nflu !% lbg] ;fj{hlgs ;'rgf g]kfn ;dfrf/kq /fli6«o b}lgsdf lj=;+= @@÷!@÷@)&@ df k|sflzt u/L ;DalGwt ;fljs uf=lj=;=, lh=j=sf=, ;fljs lh=lj=;=, ljBfno, :jf:y rf}sL, ;fd'bflos jg pkef]Qmf ;d"x tyf cGo ;/f]sf/jfnf AolQm jf ;+:yfx?af6 /fo ;'´fa ;+sngsf] nfuL k|sfzLt u/l/Psf] lyof] . k|f/lDes jftfj/0fLo k/LIf0f ug]{ qmddf k|:tfljt ;8s glhssf j:tLx?df ufpmF:t/Lo ;+3;+:yfsf k|ltlgwL tyf cGo :yfgLo AolStx?;Fu k|:tfjLt pkcfof]hgfaf6 kg{ hfg] ;sf/fTds tyf gsf/fTds c;/ jf/] hfgsf/L u/fpg ;fj{hlgs 5nkmn u/LPsf] lyof] .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
v
:yfgLo ;/f]sf/jfnfx?sf] /fo;'emfj ;lxt ;dfj]z u/L tof/ ul/Psf] k|ltj]bg :jLs[tLsf] nflu /fli6«o k'glg{df{0f k|flws/0f ;dIf k]z ul/g]5 . l:js[t k|ltj]bg ;/f]sf/jfnf / cGo AolQm jf ;+:yfx?sf] kx'rsf] nfuL /fd]5fk lhNnf ;dGjo ;ldlt ;ldtLsf] ;'rgf s]Gb|, PlzofnL ljsf; a}+s, ;+3Lo dfldnf tyf :yflgo ljsf; dGqfno, /fli6«o k'glg{df{0f k|flws/0f, e"sDk cfktsfnLg ;xfotf cfof]hgfsf] j]e;fO6df /flvg]5 .
(= u'gf;f] lgbfg ;+oGq
pkcfof]hgfsf] jftfj/0fLo / ;fdflhs sfo{;Dkfbgsf] ;Gbe{df :yfgLo hgtfsf] hgu'gf;f] ;'Gg / tLgsf] plrt tyf ;dofg's'n ;Daf]wg ug{ o; k|f=j=k= k|ltj]bgdf $ txsf] u'gf;f] lgbfg ;+oGqsf] af/]df cf}+NofOPsf] 5 .
!)= jftfj/0fLo Aoj:yfkg of]hgf
pkcfof]hgfsf] c;/, l:ylt, ltgsf Go"lgs/0fsf pkfox?, cg'udgsf] tl/sf / ;do tlnsf ;d]6]/ cWofo ( df jftfj/0fLo Joj:yfkg of]hgf tof/ kf/LPsf] 5 . o;sf ;fy} Go"lgs/0fsf pkfo sfof{Gjog / cg'udgsf] lhDd]jf/ lgsfosf] klxrfg o; jftfj/0fLo Aoj:yfkg of]hgfdf ul/Psf] 5 . k|:tfljt cfof]hgfsf ef}lts, h}ljs, ;fdflhs tyf ;f+:s[lts jftfj/0f cGtu{tsf ljleGg cg'udgsf ;"rsx? klg kQf nufOPsf 5g\ . pkcfof]hgf k'glg{df{0fsf] cg'udg /fli6«o k'glg{df{0f k|flws/0f tyf lhNnfsf cGo lgsfox?n] ug]{5g\ . jftfj/0fLo cg'udgsf] nflu ? @)),))) ljlgof]hg ul/Psf] 5 . o; pkcfof]hgfsf] jftfj/0fLo Joj:yfkgsf] nfuL ? !#,%@),*(*=!* 5'6ofOPsf] 5 . h;dWo] ? !@,)%*,#&(=$# o;sf] l;len nfutdf ;dfj]z ul/;lsPsf] 5 .
!!= lgisif{
o;:t/sf] pkcfof]hgfsf nflu pkcfof]hgfaf6 x'g] gsf/fTds c;/x? guGo 5g\ . w]/}h;f] c;/x? :yfgLo :t/d} lgdf{0f r/0fdf dfq l;ldt 5g\ . cfof]hgfaf6 x'g] clwsf+z gsf/fTds c;/x?nfO{ lbOPsf Go"lgs/0fsf pkfox?af6} sd jf Ifltk"tL{ ug{ ;lsG5 / :yfgLo:t/df / lgdf{0f r/0fd} l;ldt ug{ ;lsG5 . jftfj/0fLo Aoj:yfkg of]hgfsf] leq ;d]6LPsf pkfox? cjnDag u/LP kl/of]hgf If]qdf ef}lts, h}ljs, ;fdflhs tyf ;f:s[lts jftfj/0fdf 7"nf] c;/kg]{ b]lvb}g . To;}n] cfof]hgfsf] k|s[lt, o;sf] cjl:ylt, :yfgLo hg;d'bfox?sf] cfof]of]hgf k|ltsf] ?lr tyf klxrfg ul/Psf ;Defljt gsf/fTds c;/x?nfO{ dWogh/ ub{} k|f/lDes jftfj/0fLo kl/If0f cWoogn] lgb]{zg u/] cg'?ksf] Go"lgs/0f tyf clej[l4s/0fsf pkfox? cjnDag u/L pkcfof]hgf ;~rfng ug{ pko'Qm b]lvG5 . o;sf] nflu k|f/lDes jftfj/0fLo kl/If0f cWoog g} oy]i7 /x]sf] 5 .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
vi
Executive Summary
1. Background
In order to accelerate economic and social recovery of the communities through
rehabilitation and reconstruction of local infrastructures damaged due to devastating
earthquake of 25 April 2015 and the major aftershock of 12 May 2015, Earthquake
Emergency Assistance Project (EEAP) has been implemented under financial support of
Asian Development Bank (ADB) and technical support of Swiss Agency for Development
and Cooperation (SDC) in 12 affected district. Through this project, the ADB will support the
Government of Nepal (GoN) in its efforts to put thousands of children back into schools,
return vital government services to desperate communities, and create jobs and income for
families by repairing critical road networks. The project will also repair and improve about
135 km of strategic roads and about 450 km of rural roads damaged by the earthquake and
landslides. The National Reconstruction Authority (NRA) is the coordinating government
agency. The Ministry of Federal Affairs and Local Development (MoFALD) and the District
Coordination Committees (DCCs)/District Technical Office (DTO) are the implementing
agencies at central and district levels respectively.
Haldebesi – Dhobi – Dhandebesi (38.899 km) Road Rehabilitation and Reconstruction Sub-
Project is one of the projects under EEAP. As the district level implementing agency of the
sub-project, this IEE study report has been prepared by DCC (then District Development
Committee, DDC) Ramechhap to address the likely environmental and social impact, both
beneficial and adverse, due to the proposed upgrading of the road.
The proposed reconstruction and reconstruction of Haldebesi – Dhobi – Dhandebesi Road
will render the existing infrastructure devastated by devastating earthquake of 25 April 2015
and the major aftershock of 12 May 2015 fully operative and reinstate the road access to
more than 14 settlements of the wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality (then
Saipu, Bijulikot, Nagdaha and Tilpung VDCs) of Ramechhap District to the district
headquarter in Manthali and other parts of the country.
2. The Proponent
The DCC (then DDC), Ramechhap is the executing agency at the district level under
Earthquake Emergency Assistance Project (EEAP) project and the proponent of the Initial
Environmental Examination (IEE) study for the reconstruction and rehabilitation of Haldebesi
– Dhobi – Dhandebesi (38.899 km) Road.
Full Address of the Proponent:
Office of the District Coordination Committee, Ramechhap
Manthali, Ramechhap
Telephone No. 048-540347, 540114
Fax No. 048-540029
3. Rationale and Objectives of the IEE
Preparation of IEE for district road is mandatory according to Act relating to Reconstruction
of the Earthquake Affected Structures 2015, Rule relating to Reconstruction of the
Earthquake Affected Structures 2016, Work Procedure Related with Environmental Impact
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
vii
Assessment for Rehabilitation of Earthquake Affected Structures, 2016 and First
Amendment 2016 (Schedule 1) and ADB Safeguard Policy Statement, 2009 to suggest the
appropriate practical & site specific mitigation and enhancement measures to address the
environmental impact of the proposal.
The main objective of the IEE study is to identify the impacts of physical, biological, socio-
economic and cultural environment of the sub-project area and recommend practical and
site specific environmental mitigation and enhancement measures, prepare and implement
environmental management plan for the sub-project.
4. Project Description and Study Methodology
The proposed sub-project passes through wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality
(then Saipu, Bijulikot, Nagdaha and Tilpung VDCs) of Ramechhap District of Nepal. Then
DDC has proposed to reconstruct the 38.899 km (CH 0+000 to 38+899) km road under
EEAP. It will be rehabilitated and reconstructed into a District Road Core Network (DRCN)
standard road with gravel pavement. The road will have 6.25 meter formation width including
shoulder and drainage. The estimated total engineering cost including VAT is NRs.
283,428,071.42
This IEE report has been prepared following necessary desk and field study and defined
procedure and also on the basis of the ToR approved by the secretary level decision of the
MoFALD on 2016-03-23 A.D. to fulfill the statutory requirement of GoN.
5. Existing Environmental Condition
The project area lies in the Mid-hills (Lesser Himalayan) physiographic zones of Nepal. The
area has a rugged topography consisting steep hills and river valleys. Geologically, the study
area comprises medium to high grade metamorphic rocks of Lesser Himalayan Sequence of
Central Nepal mainly phyllites, amphibolites, metasandstone and schists.
Considering the elevation, the area has tropical, sub-tropical and warm temperate climatic
conditions. The temperature reaches as high as 300C in the summer and falls as low as 50C
in the winter. It receives annual rainfall is 1700 mm. The road alignment passes through
more than 12 small streams. No major stream fall along the alignment. The landuse in the
ZoI includes cultivated/agricultural land, settlement and market area and forest.
The sub-project segment lies among cultivation area, settlement, forest patches and barren
land among which sections at Ch 0+080 to 0+780 and Ch 2+590 3+060, Ch 1+520 to
1+845, Ch 16+800 to 17+000, Ch 24+100 to 24+250, Ch 26+000 to 26+200, 30+010 to
31+100, Ch 36+010 to 37+090 and Ch 37+150 to 37+445 fall under eight different
Community Forests: Khumbari CF, Ramche CF, Kharang Khurung CF, Jhatteswari CF,
Bhringeshwar CF, Saipu CF, Taruke Salleni CF and Saipu Pakha CF respectively. The
beginning section of the road has trees like Sal (Shorea robusta), and Bot dhayero
(Lagerstroemia parviflora), whereas the most of the remaining section Chilaune (Schima
wallichii), Khote Salla (Pinus roxburghii) and Uttis (Alnus nepalensis) etc. Likewise, ending
section of the road alongside of the Likhu Khola has Khayar (Acacia catechu), Simal
(Bombax ceiba), Sissoo (Dalbergia sissoo). The trees reported alongside of the road
alignment include Sal (Shorea robusta), Asna (Terminalia alata), Bot dhayero
(Lagerstroemia parviflora), Jamun (Syzygium cumini), Gineri (Premna integrifolia),
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
viii
Gayo (Bredelia retusa) etc. Wildlives reported near project area are Mriga(Muntiacus
muntjak), Malsapro (Martef flabiguli) etc.
The road alignment passes through wards 2, 3, 4, 5 and 7 Likhu Rural Municipality of
Ramechhap District and more than 14 major settlements along the alignment that include
Haldebesi, Ratmate, Tiplung, Darimbot, Dhande, Chakharka, Lamagau, Dhobi, Kotgau,
Dharapani, Poku, Sirise, Belauri and Dhandebesi. Around 23109 persons with 10615 male
and 12494 female live in 4928 households in the ZoI of the sub-project. The population of
the project area is dominated by Chhetri followed by the indigenous group Tamang and
Magar. Total literacy of then project VDC is 62.98%. Agriculture and livestock rearing are the
major occupations of the project area. Other occupations include small business and aboard
jobs. Health care service is being delivered by four Sub-Health Posts along the road
alignment. Almost 90.12% of the household are benefitted by piped drinking water. Almost
all of the households in the project area have been supplied with electricity. Haldebesi,
Dhobi and Dhandebesi are the local market centers and the major nearest markets are
Manthali, Ramechhap and Charikot.
6. Environmental Impacts
6.1 Beneficial Impacts
The immediate beneficial impact from the project during construction phase is generation of
temporary employment opportunity of 391,580 persondays. The major beneficial impacts
after project completion includes enhanced accessibility and transportation facility
throughout the year to the people of wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality of the
Ramechhap District, promotion of agro-enterprises based on local agricultural products and
economic development. Once in operation the road will offer easy, comfortable and quick
access to people of the area to social service facilities like health, education, market and
other facilities. After rehabilitation and reconstruction of the road, the supply of daily
consumables, food and others will be easy and provide market to local agricultural products,
especially Junar which will improve the living standard of and help the the earthquake
affected people in social and economic recovery.
6.2 Adverse Impacts
Among the adverse impact on the social domain of the environment, pressure on existing
service facilities, possible conflict and clash between local and outside workers, occupational
health and safety are of chief concern. For widening of road and construction of side drains
2.98 ha of private land distributed in different plots belonging to different owners will be
acquired. Other impacts are gender discrimination in task and wage distribution, involvement
of children in risky works, diseases due to unhygienic living condition, communicable
diseases and STDs, etc. During operation phase, ribbon settlement along the project
alignment could develop haphazardly and encroachment might occur along road alignment.
Operation of construction equipment and vehicles and use of chemical substances during
construction activites may produce noise, water and air pollution. Improper management of
waste may cause water and soil pollution leading to other deleterious consequences.
Improper storage and handling of construction materials and equipments may cause water
and soil pollution through leakage and seepage. Regarding the impact on biological
environment, hunting and poaching of wild animal is also possible during construction and
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
ix
operation but the chances are very low. In course of widening the road, altogether 105 trees
of Uttis, Chilaune and Maledo need to be felled down from five CFUGs: Jhateswari,
Bhringeshwar, Poku Salgharni (Saipu CF), Taruke Salleri and Saipu Pakha CFs at Ch
24+100 to 24+250, Ch 26+000 to 26+200, 30+010 to 31+100, 36+010 to 36+090 and Ch
37+000 to 37+150 respectively.
8. Mitigation Measures
A number of practical and cost effective mitigation measures have been suggested to
prevent, correct and compensate the adverse effects of the project implementation. The
project proponent is bound to implement these measures during the construction and
operation of the project. For construction phase, the proponent will implement the mitigation
measures through contractor. Some of the major measures to be adopted are as follows:
Women and disadvantaged people will be empowered through awareness and
capacity development training.
Private properties including private land, private structures and private trees will be
acquired after compensation.
Irrigation will be protected or rehabilitated after construction in case of damage.
To reduce the pressure on service facilities, contractor will manage utilities like
communication, lighting and cooking energy, drinking water supply, etc within the
camp. Any damages to physical infrastructures will be reconstructed or rehabilitated.
To address the issue of occupational health and safety, proper safety arrangements
will be made. Safety equipment such as helmets, boots, gloves, safety belts, safety
glasses and masks will be provided to the workers working in the construction sites.
Warning signs, posts, barriers and guards will be installed to restrict access of
unauthorized persons to storage areas.
Arrangements of temporary latrines will be made for workers and they will be placed 50
m away from water bodies.
Spoil generated from earthwork will be disposed in designated location and managed
properly with toe wall and retaining wall, vegetation cover and necessary drainage
structures.
Existing and possible landslides will be controlled or prevented by appropriate bio-
engineering technique.
All the camp wastes and construction wastes will be placed in the designated waste
collection pits away from the water path.
Oils and other chemicals used in construction activities will be handled carefully and
stored in fallow land away from the river beds by using impervious layers.
Arrangement will be made to plant 2,625 trees and protect them through the respective
CFUGs to compensate the 105 trees felled from the three Community Managed
Forests along the road corridor.
Hoarding boards carrying messages to aware people on control of hunting and
poaching of wildlife and their conservation will be placed.
8. Public Consultation and Information Disclosure
In order to prepare the IEE report, 15 days public notice was published on 04/04/2016 AD in
Nepal Samacharpatra, a national Nepali daily newspaper seeking written opinions from
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
x
concerned then VDCs, DFO, CFUGs, schools, health posts and related local organizations.
Public consultation was done with the local people living near the proposed road, members
of local organizations and local leaders during the preparation of IEE report in order to aware
them of incoming road rehabilitation and reconstruction sub-project and to identify the
possible beneficial and adverse impacts due to this sub-project.
IEE report prepared by incorporating the suggestions of local stakeholders will be presented
to NRA for review and approval. The approved report will be made accessible to interested
parties and the general public through the information center of MoFALD, NRA, Likhu Rural
Municipality and websites of ADB and EEAP.
9. Grievance Redress Mechanism (GRM)
The IEE report has suggested four (4) levels of GRMs to receive and facilitate resolution of
affected people’s concerns and grievances regarding project’s environmental and social performances and impacts in a timely and satisfactory manner.
10. Environmental Management Plan
Environmental Management Plan (EMP) has been proposed with present report including
issues identified, possible effects and impacts, measures for their mitigation, monitoring
methods and schedule in Chapter 9. In addition, agencies responsible for executing
environmental mitigation measures and monitoring have been identified in the EMP.
Different monitoring indicators on the physical, biological, socio-economic and cultural
environment have also been identified. The NRA with local bodies will monitor during
reconstruction and operation phase. For the environmental monitoring, NR 200,000 has
been allocated. The cost for environmental mitigation measures and benefit augmentation is
NRs. 13,520,898.18 where NRs. 12,058,379.43 is allocated within civil work cost. This does
not include the cost required for implementation of Resettlement Plan (RP) and Gender
Equality and Social Inclusion (GESI) Plan.
11. Conclusion
Most of the identified and perceived impacts of the project are of low significance compared
to the project of this scale. With the set of mitigation measures, most of the identified
adverse impacts can be minimised and/or compensated and limited to locality and
construction period. Once the measures outlined in the EMP are implemented, there is no
risk for residual impacts that may affect the physical, biological, socio-economic and cultural
environment of the project area. Hence, it is suitable to implement the project addressing the
impacts through the mitigation and enhancement measures suggested by this IEE,
considering the nature of the project, its location, and people’s positive perceptions and
identified environmental impacts. This IEE study is considered sufficient for this project.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
xi
Table of Contents
1. INTRODUCTION ..................................................................................................... 1
1.1. Background ..................................................................................................... 1
1.2. Project Implementation Unit ............................................................................. 2
1.3. Consultant ....................................................................................................... 2
1.4. Objectives of ToR ............................................................................................ 3
1.5. Objectives of IEE Study ................................................................................... 3
1.6. Rationale for Conducting IEE ........................................................................... 3
1.7. Limitations of the IEE Study ............................................................................. 4
2. DESCRIPTION ON RECONSTRUCTION & REHABILITATION WORKS ............... 5
2.1. Project Location ............................................................................................... 5
2.2. Salient Features of the Project ......................................................................... 9
2.3. Components and Activities of the Sub-Project ............................................... 10
2.4. Construction Materials Requirement .............................................................. 10
2.5. Source of Construction Materials and Quarry Sites ....................................... 11
2.6. Land Requirement ......................................................................................... 11
2.7. Human Resource Requirement ..................................................................... 12
2.8. Campsite ....................................................................................................... 12
2.9. Spoil Disposal Area ....................................................................................... 12
2.10. Project Implementation Schedule .................................................................. 13
2.11. Construction Approach .................................................................................. 13
2.12. Cost ............................................................................................................... 14
2.13. Impact Zone .................................................................................................. 14
2.14. Environment Protection Policy ....................................................................... 14
3. STUDY APPROACH AND METHODOLOGY ....................................................... 15
3.1. General.......................................................................................................... 15
3.2. Study Team ................................................................................................... 15
3.3. Project Area Delineation ................................................................................ 15
3.4. Desk Study and Literature review .................................................................. 16
3.4.1. Review of Existing Information ............................................................... 16
3.4.2. Map Reading ......................................................................................... 16
3.4.3. Checklists .............................................................................................. 16
3.5. Field Study .................................................................................................... 16
3.5.1. Initial Interaction and Consultation with Stakeholders ............................ 17
3.5.2. Public Notice .......................................................................................... 17
3.5.3. Public Consultations .............................................................................. 17
3.5.4. Physical Environment ............................................................................ 18
3.5.5. Biological Environment........................................................................... 18
3.5.6. Socio-Economic and Cultural Environment ............................................ 19
3.6. Impact Identification, Prediction and Evaluation ............................................. 20
3.7. Group Judgement .......................................................................................... 21
3.8. Designation of Mitigation Measures and Monitoring Plans ............................. 21
3.9. Report Preparation ........................................................................................ 21
3.10. Information Disclosure ................................................................................... 21
4. EXISTING ENVIRONMENTAL CONDITION ......................................................... 22
4.1. Physical Environment .................................................................................... 22
4.1.1. Topography ............................................................................................ 22
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
xii
4.1.2. Geology and Soil Type ........................................................................... 22
4.1.3. Slope Stability and Erosion .................................................................... 24
4.1.4. Seismicity of the Project area ................................................................. 24
4.1.5. Climate .................................................................................................. 25
4.1.6. Drainage and Hydrology ........................................................................ 25
4.1.7. Land Use ............................................................................................... 26
4.1.8. Air Quality, Water Quality and Noise Levels ........................................... 26
4.2. Biological Environment .................................................................................. 26
4.2.1. Vegetation and Forest Type ................................................................... 26
4.2.2. Forest Management Regimes ................................................................ 27
4.2.3. Domesticated Plants .............................................................................. 31
4.2.4. Ethno-botany and NTFPs ....................................................................... 31
4.2.5. Rare, Threatened and Protected Plants ................................................. 32
4.2.6. Wildlife ................................................................................................... 32
4.2.7. Rare, Threatened and Protected Wildlife ............................................... 32
4.3. Socio Economic and Cultural Environment .................................................... 33
4.3.1. Population, Household and Settlement .................................................. 33
4.3.2. Caste and Ethnicity ................................................................................ 35
4.3.3. Language ............................................................................................... 35
4.3.4. Literacy and Education .......................................................................... 35
4.3.5. Occupation............................................................................................. 35
4.3.6. Agriculture and Cropping Pattern ........................................................... 36
4.3.7. Livestock ................................................................................................ 36
4.3.8. Migration Pattern.................................................................................... 36
4.3.9. Public Health and Sanitation .................................................................. 37
4.3.10. Public Service Infrastructures and Facilities ........................................... 37
4.3.11. Food Sufficiency .................................................................................... 39
4.3.12. Potential Development Areas ................................................................. 39
4.3.13. Project Affected Families ....................................................................... 40
5. IMPACTS OF RECONSTRUCTION PLAN IMPLEMENTATION ON
ENVIRONMENT ........................................................................................................... 44
5.1. Beneficial Impacts and Augmentation Measures ........................................... 44
5.1.1. Construction Phase ................................................................................ 44
5.1.2. Operation Phase .................................................................................... 45
5.2. Adverse Impacts ............................................................................................ 46
5.2.1. Pre-construction Phase .......................................................................... 46
5.2.2. Construction Phase ................................................................................ 47
5.2.3. Adverse Impacts during Operation Phase .............................................. 51
5.3. Climate Change Impacts ............................................................................... 52
5.4. Cumulative Impact ......................................................................................... 53
5.4.1. Beneficial Impacts .................................................................................. 53
5.4.2. Adverse Impacts .................................................................................... 53
6. PROJECT ALTERNATIVES .................................................................................. 55
6.1. No Action Option ........................................................................................... 55
6.2. Project Alternative ......................................................................................... 55
6.3. Alternative Alignment ..................................................................................... 55
6.4. Alternative Design and Construction Approach .............................................. 55
6.5. Alternative Schedule and Process ................................................................. 56
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
xiii
6.6. Alternative Resources .................................................................................... 56
6.7. No Forest Option ........................................................................................... 56
7. ENVIRONMENTAL IMPACTS MITIGATION AND MINIMIZATION TECHNIQUES57
7.1. Augmentation Measures ................................................................................ 57
7.1.1. Beneficial Impacts during Construction Phase ....................................... 57
7.1.2. Beneficial Impacts during Operation Phase ............................................ 57
7.2. Mitigation Measures....................................................................................... 58
7.2.1. Pre-construction Phase .......................................................................... 58
7.2.2. Construction Phase ................................................................................ 59
7.2.3. Adverse Impacts during Operation Phase .............................................. 65
7.3. Climate Change Impacts ............................................................................... 66
8. LEGAL FRAMEWORK AND REGULATORY REQUIREMENTS FOR THE
PROJECT ..................................................................................................................... 67
9. ENVIRONMENTAL MANAGEMENT PLAN .......................................................... 73
9.1. Institutions and their Roles............................................................................. 73
9.2. Reporting and Documentation ....................................................................... 75
9.3. Implementation of the Mitigation Measures .................................................... 75
9.4. Matter to be monitored while implementing the Proposal ............................... 86
9.4.1. Baseline Monitoring ............................................................................... 86
9.4.2. Compliance Monitoring .......................................................................... 86
9.4.3. Impact Monitoring .................................................................................. 86
9.5. Monitoring Indicator ....................................................................................... 87
9.5.1. Pre-Construction Phase ......................................................................... 87
9.5.2. Construction Phase ................................................................................ 87
9.5.3. Operation Phase .................................................................................... 87
9.6. Monitoring Indicators ..................................................................................... 88
9.7. Cost of Mitigation and Enhancement ............................................................. 97
9.8. Costs of Environmental Monitoring ................................................................ 98
9.9. Grievance Redress Mechanism ..................................................................... 98
9.9.1. First level of GRM .................................................................................. 98
9.9.2. Second level of GRM ............................................................................. 99
9.9.3. Third level of GRM ................................................................................. 99
9.9.4. Fourth level of GRM ............................................................................. 100
9.9.5. Procedure for Grievances Handling as Per National Law ..................... 100
10. CONCLUSION..................................................................................................... 102
List of Tables
Table 1: Restructuring of Affected VDCs of Ramechhap District ........................................... 2
Table 2: Salient Features of Haldebesi – Dhobi – Dhandebesi Road .................................... 9
Table 3: Quantity of Construction Materials ......................................................................... 11
Table 4: Possible Quarry Sites ............................................................................................ 11
Table 5: Permanent Land Requirement by Land Use Type ................................................. 12
Table 6: Manpower Requirement ........................................................................................ 12
Table 7: Recommended Spoil Disposal Sites ...................................................................... 13
Table 8: Sub-Project Implementation Schedule................................................................... 13
Table 9: Study Team ........................................................................................................... 15
Table 10: Impact Area Delineation ...................................................................................... 16
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
xiv
Table 11: Summary of the Meeting Minutes during Public Consultations ............................ 18
Table 12: Numerical scales as proposed in the National EIA Guidelines ............................. 20
Table 13: Cumulative scores of level of significance ........................................................... 20
Table 14: Geology and Soil Type along Road Alignment .................................................... 23
Table 15: Landslides and Erosion Prone Areas along Road Alignment ............................... 24
Table 16: Major Streams along the Road Alignment ........................................................... 25
Table 17: Landuse along the Road Alignment ..................................................................... 26
Table 18: Chainage wise Dominancy of Tree Species ........................................................ 27
Table 19: Community Forest along the Road Alignment ..................................................... 28
Table 20: Medicinal Plants and Local Use ........................................................................... 31
Table 21: Rare, Threatened and Protected Animals Found in Project Area ......................... 33
Table 22: Population Distribution in District, Rural Municipality and Project Area ................ 34
Table 23: Settlements and Population of the along the Road Corridor ................................ 34
Table 24: Occupations of Surveyed Households ................................................................. 36
Table 25: Migration Status in the ZoI ................................................................................... 37
Table 26: Food Sufficiency and Income level of the Affected Households ........................... 39
Table 27: Status of People Losing their Struturues in Road Sub-project ............................. 41
Table 28: People Losing their Land to Road Sub-project .................................................... 43
Table 29: Trees to be felled at different chainages .............................................................. 50
Table 30: Trees to be Felled and Compensatory Plantation Requirement ........................... 64
Table 31: Review of Relevant Acts, Rules, Regulations and Guidelines ............................. 67
Table 32: Institutional Roles and Responsibilities ................................................................ 73
Table 33: Summary of the Beneficial Impacts and Enhancement Measures ....................... 76
Table 34: Summary of Adverse Impact Prediction and Mitigation Measures ....................... 78
Table 35: Monitoring Indicators Selected for this IEE .......................................................... 88
Table 36: Compliance Monitoring of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation
and Reconstruction Sub-project .......................................................................................... 90
Table 37: Impact Monitoring of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation and
Reconstruction Sub-project ................................................................................................. 94
Table 38: Estimate of Environmental Cost of the Sub-Project ............................................. 97
Table 39: Estimated Cost for Environmental Monitoring ...................................................... 98
List of Figures
Figure 1: Haldebesi – Dhobi – Dhandebesi Road in DTMP Map of Ramechhap
District ........................................................................................................................ 6
Figure 2: Road Alignment in Topographical Map ....................................................... 7
Figure 3: Road Alignment in Ecological Map .............................................................. 8
Figure 4: Road Alignment in Google Earth Map ....................................................... 22
Figure 5: Location of Sub-project in Geological Map ................................................ 23
Figure 6: Seismic risk map of Nepal ......................................................................... 25
Figure 7: Environment Management Organization Structure ................................... 74
Figure 8: Grievance Redress Mechanism as Per EARF of EEAP .......................... 100
Figure 9: Grievance Redress Mechanism in National Law ..................................... 101
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
xv
Appendices
Appendix 1: Terms of Reference approval letter & Approved ToR .................................... 106
Appendix 2: Environmental Assessment Checklists .......................................................... 117
Appendix 3: Checklists for Baseline Information Collection ............................................... 122
Appendix 4: Public Notice ................................................................................................. 126
Appendix 5: Deeds of Inquiries ......................................................................................... 128
Appendix 6: Recommendation Letters .............................................................................. 140
Appendix 7: Minutes of Public Consultations ..................................................................... 146
Appendix 8: Tree Loss and Compensatory Plantation ....................................................... 152
Appendix 9: Abstract of Costs ........................................................................................... 168
Appendix 10: List of Affected Structure ............................................................................. 177
Appendix 11: Grievance Redress Mechanism ................................................................... 184
Appendix 12: Environmental and Social Monitoring Report Outline ................................... 185
Appendix 13: Pictorial Highlights ....................................................................................... 186
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
xvi
Acronyms and Abbreviations
ADB: Asian Development Bank
amsl: above mean sea level
BS: Bikram Sambat
CBO: Community Based Organization
CFUGs: Community Forest User Group
CISC: Central Implementation and Support Consultant
CITES: Convention on International Trade in Endangered Species
CL-PIU: Central Level Project Implementation Unit
dBA: Decibel (A)
DCC: District Coordination Committee
DRCN: District Road Core Network
DDC: District Development Committee
DDR: Detail Design Report
DISC: District Implementation and Support Consultant
DIA : Direct Impact Area
DL-PIU: District Level Project Implementation Unit
DMG: Department of Mines and Geology
DNPWC: Department of National Parks and Wildlife Conservation
DoLIDAR: Department of Local Infrastructure Development and Agricultural Roads
DoR: Department of Roads
DTMP: District Transport Master Plan
DTO: District Technical Office
DWSC: Department of Watershed and Soil Conservation
EA: Environmental Assessment/Executing Agency
EARF: Environment Assessment and Review Framework
EEAP: Earthquake Emergency Assistance Project
EIA: Environmental Impact Assessment
EMP: Environment Management Plan
IIA : Indirect Impact Area
GESI AP: Gender Equality and Social Inclusion Action Plan
GIS: Geographical Information System
GoN: Government of Nepal
HH: Household
HIV: Human Immune Deficiency Virus
IEE: Initial Environmental Examination
IUCN: International Union for Conservation of Nature
LEP: Labor based Environmentally Friendly and Participatory Approach
LPG: Liquefied Petroleum Gas
MoFALD: Ministry of Federal Affairs and Local Development
MoPE: Ministry of Population and Environment
NGO: Non-Governmental Organization
NTFPs: Non Timber Forest Products
NRA: National Reconstruction Authority
ODF: Open Defecation Free
PAFs: Project Affected Families
PAM: Project Administration Manual
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
xvii
PIU: Project Implementation Unit
RCC: Reinforced Cement Concrete
RP: Resettlement Plan
RoW: Right of Way
SDC: Swiss Agency for Development and Cooperation
STDs: Sexually Transmitted Diseases
SWCA: Soil and Water Conservation Act
ToR: Terms of Reference
VDC: Village Development Committee
www: World Wide Web
ZoI: Zone of Influence
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
1
1. INTRODUCTION
1.1. Background
1. Earthquake Emergency Assistance Project (EEAP) is a project being implemented
with the loan financing of ADB, Swiss technical support and counterpart funding from the
Government of Nepal (GoN). It aimed at accelerating economic and social recovery of the
communities through rehabilitation and reconstruction of local infrastructures damaged due
to devastating earthquake of 25 April 2015 and the major aftershock of 12 May 2015. The
project will support the Government of Nepal (GoN) in its efforts to put thousands of children
back into schools, return vital government services to desperate communities, and create
jobs and income for families by repairing critical road networks. The Project covers 12
affected districts in eastern, middle and western development region of Nepal namely:
Kathmandu, Bhaktapur, Lalitpur, Kavrepalanchowk, Ramechhap, Okhaldhunga, Sindhuli,
Solukhumbu, Ramechhap, Gorkha, Lamjung and Chitwan. The project will repair, retrofit or
rebuild at least 700 schools and 300 district-level government buildings damaged by the
earthquake to disaster-resilient standards. The project will also repair and improve about 135
km of strategic roads and about 450 km of rural roads damaged by the earthquake and
landslides. The roads will be rebuilt with improved road safety features and designed to
withstand future disasters and the impact of climate change.
2. National Reconstruction Authority (NRA) is the legally mandated agency for leading
and managing the earthquake recovery and reconstruction in Nepal and is the Executing
Agency (EA) of EEAP. The Central Level Project Implementation Unit (CL-PIU) for rural road
component of EEAP is under the Ministry of Federal Affairs and Local Development
(MoFALD).
3. The proposed rehabilitation and upgrading of Haldebesi – Dhobi – Dhandebesi Road
will provide easy access to the rural Eastern part of Ramechhap District to the district
headquarter in Manthali and other parts of the country through Nayapul – Manthali Road.
The road serves wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality (former Tilpung, Nagdaha,
Bijulikot and Saipu VDCs) of Ramechhap District and settlements like Haldebesi, Jhangre,
Katahare, Kharibote, Aarubote, Nagdaha, Dhobi, Kotgau, Poku, Sirise Setapahara and
Dhade thereof to the rest of the world through road network. These areas have high potential
in vegetable, fruits, livestock, dairy and broom grass production.
4. While already, very low number of vehicles was plying on the road because of the
bad road condition, the road had been further damaged due to devastating earthquake of 25
April 2015 and the major aftershock of 12 May 2015. Transportation of goods and services
from the market centers to the rural areas and vice-versa has been difficult, insufficient and
costly due to poor geometry, standards and earthen nature of the road. The proposed
rehabilitation and upgrading will facilitate the easy access to the rural people of Ramechhap
District. The enhanced road network will provide access to the rural people to the basic
service facilities like health, education and daily economic activities hence improving their
living standard. Hence, there is an urgent need of rehabilitating and upgrading this road to
facilitate easy accessibility for isolated villages and the road has attracted DTMP priority No-
21DR025.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
2
5. The project affected then Tilpung, Nagdaha, Bijulikot and Saipu VDCs are now
restructured as wards of Likhu RM (please refer Table 1). Then office of Bijulikot VDC will be
the centre of Likhu RM for now. Office of then DDC, Ramechhap has been acting as office of
Distict Coordination Committee. The name of affected then VDCs mentioned in this reports
are now ward 2, 3, 4, 5 and 7 of Likhu Rural Municipality.
Table 1: Restructuring of Affected VDCs of Ramechhap District
VDCs mentioned in report Wards of the VDC Current reformation
Tilpung VDC 1-9 Likhu RM 7
Nagdaha VDC 1-9 Likhu RM 5
Bijulikot VDC 5-9 Likhu RM 4
Bijulikot VDC 1-4 Likhu RM 3
Saipu VDC 1-9 Likhu RM 2
6. The Terms of Reference (ToR) was prepared and approved before the formulation of
Work Procedure Related with Environmental Impact Assessment for Rehabilitation of
Earthquake Affected Structures, 2072 (2016) based on Environment Protection Act 1997
and Environment Protection Rule 1997. It was approved by the secretary level decision of
the MoFALD on 2072-12-10 (March 23, 2016) right before the mobilization of the design
team. The road design parameters were revised in the course and the length and formation
width fixed at 38.899 km and 6.25 m respectively. So, there is a discrepancy in the design
information in the IEE Report, ToR and the public notice. The IEE Report, ToR and the
public notice deals with the same road, DRCN No. 21DR025 and the name of the obligatory
points are the same. This IEE Report has been prepared based on the final DPR.
1.2. Project Implementation Unit
7. DCC Ramechhap is the implementing agency at the district level (DL-PIU) and the
proponent of the Initial Environmental Examination (IEE) study for the rehabilitation and
reconstruction of Haldebesi – Dhobi – Dhandebesi Road. The National Reconstruction
Authority (NRA) is the concerned authority for the approval of IEE study report.
Address of the Proponent
Office of the District Coordination Committee, Ramechhap
Manthali, Ramechhap
Telephone No. 048-540347, 540114
Fax No. 048-540029
Email: [email protected]
1.3. Consultant
Central Implementation Support Consultant (CISC)
Earthquake Emergency Assistance Project (EEAP)
Ekantakuna, Lalitpur
P.O. Box 113
Telephone No: 977-1-5543142/43
Fax No: 977-1-5543144
E-mail: [email protected] ; Website: www.drilpnepal.org
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
3
8. Af-Iteco Ltd., Switzerland acting as Central Implementation Support Consultant of
EEAP has awareded consultancy services to the JV of Gaurav Integrated Development
Associates Nepal P. Ltd (GIDA Nepal P. Ltd), NEST P. Ltd. and JAARSA Engineering
Consultancy (P) Ltd., Sankhamul, Kathmandu who was responsible for conducting the
necessary desk and field study and preparing IEE report on behalf of the proponent adhering
with the approved ToR and all the prevalent policies, acts, rules and guidelines.
NEST P. Ltd.
Sankhamul-34, Kathmandu
Telephone No. 01-4784515
Email: [email protected]
1.4. Objectives of ToR
9. The main objective of the TOR was to guide the preparation of the comprehensive
and coherent Initial Environmental Examination (IEE) study report as per the Environment
Protection Act 1997 (EPA ’97) and Environment Protection Rules 1997 (EPR ’97) and amendments. The specific objectives of the study were to:
Identify the data requirement of IEE study and general methods for acquisition of such
information.
Identify major issues that may arise as a result of proposed works on bio-physical,
socio-economic and cultural environment of the project area,
Identify relevant legal documents that need to be reviewed during the IEE study and
subsequent project implementation.
Provide an outline on structure of IEE study report
1.5. Objectives of IEE Study
10. The objective of the IEE study is to identify the environmental impact due to
implementation of the sub-project in the area and to suggest a sustainable way out, help
decision makers to balance development and protection of human well being and the
environment. The specific objectives of the study are to:
Provide information on the general environmental setting of the project area as
baseline data,
Identify, predict and evaluate the major issues that may arise as a result of proposed
works on bio-physical, socio-economic and cultural environment of the project area,
Recommend practical and site specific environmental mitigation and enhancement
measures,
Prepare and implement environmental management and monitoring plan for the
project, and
Ensure that IEE is sufficient for the proposed road project.
1.6. Rationale for Conducting IEE
11. As prescribed in the Work Procedure Related with Environmental Impact
Assessment for Rehabilitation of Earthquake Affected Structures, 2016 and First
Ammendment 2016 promulgated under the Act Made to Provide for Reconstruction of the
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
4
Earthquake Affected Structures (Act relating to Reconstruction of the Earthquake Affected
Structures), 2072 (2015), Schedule 1 (2) (Projects Requiring IEE) under Rule 3,
rehabilitation and reconstruction of district, urban and rural roads need to undergo IEE study
and the report requires approval from the NRA. This IEE has been conducted following the
ToR for IEE approved by MoFALD prior to enactment of aforementioned laws according to
Environment Protection Act 1997 and Environment Protection Rules 1997. Preparation of
IEE report by concerned DCC and approval of the IEE report by the NRA according to
Nepali legal provision is considered sufficient and Nepali legal provisions in essence satisfy
ADB's requirements. EEAP sub-projects fall under category "B" (categorization is as "A", "B"
and ''C'' based on the significance of sub-projects impact and risks on the environment and
environmental safeguard considerations) where IEE is mandatory for all sub projects
according to Safeguard Policy Statement (SPS), 2009 of ADB. The road section does not fall
within the boundary of protected area of any category.
1.7. Limitations of the IEE Study
12. The study has following limitations:
Site specific environmental management plan is not prepared
Name of private owner (tree loss) could not be listed, and RP will be referred for this
purpose
Since the IEE was carried before the restructuring of local level, the IEE report is in line
with old structure’s roles and responsibilities.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
5
2. DESCRIPTION ON RECONSTRUCTION & REHABILITATION
WORKS
2.1. Project Location
13. The proposed Haldebesi – Dhobi – Dhandebesi Road (DTMP No- 21DR025) passes
through wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality (former Tilpung, Nagdaha, Bijulikot
and Saipu VDCs) of Ramechhap District of Central Development Region of Nepal. Then
DDC has proposed to rehabilitate and reconstruct the 38.899 km (CH 0+000 to 38+899)
road from Haldebesi to Dhandebesi (CH 0+000 to 38+899) to gravel standard. The road
section starts from Haldebesi of Likhu Rural Municipilatiy-7 (former Tilpung VDC-2) along
Nayapul – Manthali Road (27o25’55” N Latitude and 86o05’36”E Longitude) and ends at Dhandebesi of Likhu Rural Municipality-2 (then Saipu VDC-4, 27o26’23” N Latitude and 86o15’17”E Longitude) of Ramechhap District passing through 14 settlements along the
alignment. The major settlement areas are Haldebesi, Jhangre, Katahare, Kharibote,
Aarubote, Nagdaha, Dhobi, Kotgau, Poku, Sirise Setapahara and Dhade. The road connects
eastern part of Ramechhap district with the district headquarter in Manthali and rest of the
country through all-weather connectivity. The road is directly connected to Nayapul –
Manthali Road.
14. The road alignment is depicted in DTMP Map, Topographical Map and Ecologicl Map
in Figure 1, Figure 2 and Figure 3 respectively.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
6
Figure 1: Haldebesi – Dhobi – Dhandebesi Road in DTMP Map of Ramechhap District
21DR025
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
7
Figure 2: Road Alignment in Topographical Map
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
8
Figure 3: Road Alignment in Ecological Map
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
9
2.2. Salient Features of the Project
15. The features of the proposed project are summarized in the table below (Table 2).
Table 2: Salient Features of Haldebesi – Dhobi – Dhandebesi Road
Features Description
Name of the Road Haldebesi – Dhobi – Dhandebesi Road
Type of Work Reconstruction and Rehabilitation
Project starting date April, 2016 Project ending date June, 2019 Road Classification DCRN; 21DR025
Location
District: Ramechhap
Rural Municipality Likhu Rural Municipality 2, 3, 4, 5 and 7
Major Settlements
Haldebesi, Jhangre, Katahare, Kharibote, Aarubote,
Nagdaha, Dhobi, Kotgau, Poku, Sirise Setapahara,
Dhade
Length 38.899 km
Starting Point Haldebesi of Likhu Rural Municipality-7 (then Tilpung
VDC-2) (0+000)
End Point:
Dhandebesi of Likhu Rural Municipality-2 (then
Saipu VDC-4); Steel Truss Bridge bordering
Ramechhap and Okhaldhunga districts (38+899)
Geographical feature
Terrain Mid-Hills
Altitudinal Range 531 m to 1831 m
Climate: Tropical to Sub-tropical
Geology: Lesser Himalayan Rocks (Phyllite and Gneiss),
Colluvium, Alluvium and Residual Soil
Meteorology: Unevenly Distributed Precipitation Controlled by
Monsoon
Design Standard
Standard NRRS 2055, 2nd Revision December 2014
Existing Surface: Earthen, Stone pitched
Proposed Pavement: Gravel, Cobble for grade >8%
Right Of Way: 10 m on either sides (Center line)
Formation Width: 6.25 m (includes 1m drainage & 0.75 m Shoulder)
Carriage Way Width: 3.75 m
Shoulder Width: 0.75 m on either side
Maximum Gradient 12%
Minimum Gradient 0.5%
Lane Single
Structures (Qty/No.)
Drainage Structures
a) Side Drain Throughout the alignment at hill side, Cascade drain
for grade greater than 7%
b) Causeway 11
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
10
Features Description
c) Slab Culvert 1
d) Pipe Culvert 67
e) Irrigation Crossing 34
Retaining Structures
a) Stone Masonry Wall 11,322.13 cu.m.
b) Gabion Retaining and
Breast Walls 7,506.50 cu.m.
c) Stone Masonry Revetment
Wall
722.20 cu.m.
Earth Work
a) Excavation/Cutting 178,866.87 cu.m.
b) Embankment/Filling 20,341.14 cu.m. cu.m.
Pavement Volume
a) Gravel 17,492.34 cu.m
b) Cobble 16,222.43 cu.m.
Project Cost (NRs)
a) Civil Works (Base cost) 224,942,913.83
b) 13% VAT (of a) 29,242,578.80
c) Sub-Total (a+b) 254,185,492.62
d) Work Charge Staff and Small Miscellaneous Expenses @ 3% (of c)
6,534,499.41
e) Physical contingency @ 10% (of c)
6,748,287.41
f) Grand Total (c+d+e) 22,494,291.38
Total Household 1273
Population 6204
Monitoring Cost (Nrs.) 200,000.00
Mitigation cost (Excluding Monitoring)
12,62,518.75
EMP Cost included in Civil Cost 12,058,379.43
Total Project Cost including Environmental and Social Cost
287,975,755.71
Source: DPR Haldebesi – Dhobi – Dhandebesi Road Sub-project
2.3. Components and Activities of the Sub-Project
16. Total length of the road is 38.899 km with 6.25 m formation width. Project
components are: construction of structures like roadway, toe wall, retaining wall, breast wall,
side drain, pipe culvert, slab culvert, irrigation crossings, etc. Site clearance, earthwork
(excavation and filling), bioengineering, spoil disposal management, paving, compensatory
plantation, roadside plantation are the activities during the construction of this road sub-
project.
2.4. Construction Materials Requirement
17. Suitable materials including fill materials, base material and sub-base and pavement
material will be required for road construction. Besides these materials, boulders and river-
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
11
based aggregates and sand will be required for gravelling road, building retaining walls, RCC
culverts, side drains and drain covers and other road features. The quantity of construction
materials required for rehabilitation and reconstruction works as derived from the design
report is summarized in the Table 3.
Table 3: Quantity of Construction Materials
SN Materials Unit Quantity
1 Embankment and Filling Materials Cu.m 21,637.93
2 Gravel Cu.m 68,782.53
3 Cobble Cu.m 16, 222.43
4 Stone Cu.m 19,625.43
5 Geotextile Sq.m 5,844.80
6 Cement Mt. 1,560.00
7 Steel Mt. 16.73 Source: DPR Haldebesi – Dhobi – Dhandebesi Road Sub-project, 2016
2.5. Source of Construction Materials and Quarry Sites
18. Construction materials like cement and geotextiles will be bought from the nearest
market within the country. The major construction materials that include suitable materials
(fill, base and sub-base materials, gravel, cobble, stone etc.) have to be sourced from local
sources or quarries. The sources of these materials have been presented in the Table 4.
Table 4: Possible Quarry Sites
Material Site Distance
Gravel Tamakoshi River, Haldebeshi Within 1 km from starting point
Likhu Khola At Ch: 35+000 (Sirise)
Sand Tamakoshi River, Haldebeshi Ch: 0+000
Likhu Khola Ch: 35+000
Boulder Tamakoshi River, Haldebeshi Ch: 0+000
Likhu Khola Ch: 35+000
At site of roadway cutting
Aggregate Tamakoshi River, Haldebeshi Ch: 0+000
Likhu Khola Ch: 35+000
Roadway Cutting
Source: Field Survey, 2016 2.6. Land Requirement
19. It is an existing road with average width of 5.25 m. To upgrade it to the prescribed
standard, 3.89 ha of additional land will be permanently required for the sub-project. Private
agricultural land constitute major portion of this land. The permanent land requirement of the
sub-project is described in the Table 5.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
12
Table 5: Permanent Land Requirement by Land Use Type
SN Land use Area (ha)
1 Agriculture (Including settlement) 2.98
2 Forest Land 0.45
3 Open/Barren Land 0.46
Total 3.89
Source: Field Survey, 2016
20. Additionally, land will be required for sitting ancillary facilities like construction camp,
storage yard and spoil disposal. These are located in private land or open/barren land.
Private land necessary for sitting temporary structures will be hired from interested owner at
prevailing market rate. After completion of the work, the camps and facilities will be
dismantled and rehabilitated and returned to the owner. Permanent land will be acquired
from the respective owner following due compensation and deed transfer in the name of
proponent.
2.7. Human Resource Requirement
21. People will be required for excavation, spreading, concrete works, gabion weaving,
transportation, supervision and management during construction of this project. The work
force requirement for the reconstruction works has been describe in Table 6.
Table 6: Manpower Requirement
SN Type of Workforce Input Unit
1 Unskilled 368,962 Person/days
2 Skilled 22,574 Person/days
3 Operator 44 Person/days
Total 391,580 Person/days
Source: DPR Haldebesi – Dhobi – Dhandebesi Road Sub-project, 2016
2.8. Campsite
22. As stated in the preceeding section, the project will require large number of workforce
that cannot be provided by the project area alone. Workers have be be procured from
outside to complete the work in stiputated time. Hence, camp facilities will be required to
house the outside worker. Appropriate camp sites have been identified at Ch 4+100, Ch
13+500, Ch 19+900, 26+300 and Ch 36+900. These ares have availability of water for
drinking and sanitary use. Toilets will be arranged with respect to the number of workers
stationed in the camp.
2.9. Spoil Disposal Area
23. As per the design report of the sub-project, about 257,382.93 cu.m of spoil is
expected to be generated from cutting and excavation of road and drains and some of the
spoil, 17,091.15 cu.m, will be used in filling road. Surplus volume needs to be managed
properly. Appropriate spoil disposal sites have been presented in the Table 7.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
13
Table 7: Recommended Spoil Disposal Sites
Chainages Recommended Spoil Disposal Sites
2+430 Kholsi, Spoil disposal in valley side of the road
11+150 Kholsi
28+050 Simle Khola site
31+040 At valley side spoil disposal Source: DPR Haldebesi – Dhobi – Dhandebesi Road Sub-project, 2016
2.10. Project Implementation Schedule
24. Table 8 shows the implementation schedule of Devitar-Phulasipokhari Road
Rehabilitation and Reconstruction Sub-Project.
Table 8: Sub-Project Implementation Schedule
SN Activity 2016 2017 2018 2019
I II III IV I II III IV I II III IV I II III IV
1 Detailed survey, design
and estimate
2 Preparation of resettlement
plan
3 Environmental Assessment
and Implementation
3.1 IEE report preparation and
approval from NRA and
ADB
3.2 Implementation of EMP
3.3 Environmental Monitoring
4 Work Implementation
4.1 Civil construction work Note:
I = (January, February, March) II = (April, May, June)
III = (July, August, September) IV = (October, November, December)
2.11. Construction Approach
25. Implementation of road sub-project works will be carried out by employing a
Construction Contractor through National Competitive Bidding. However, the contract
package will include the following features:
Use of equipments and manpower to execute the contract within the stipulated
deadline.
Balancing cut and fills and reuse of excavated materials as construction materials, and
thus not generating excess spoils as far as possible.
Use of bio-engineering techniques with integrated use of vegetation, small civil
engineering structures and proper water management systems to ward of erosion.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
14
2.12. Cost
26. Length of this road is 38.899 km and formation width is 6.25 m. Total project cost of
the road is estimated NRs. 287,975,755.71 and civil work cost is NRs. 283, 428,071.42
(Refer Appendix 9).
2.13. Impact Zone
27. The project will have direct impact on Wards 2, 3, 4, 5 and 7 of Likhu Rural
Municipality (former Tilpung, Nagdaha, Bijulikot and Saipu VDCs) and indirect impact on
Areas within the geographical boundary of Likhu Rural Municipality excluding wards 2, 3, 4,
5 and 7. Please refer Table 10 for detail.
2.14. Environment Protection Policy
28. The project has aimed to carry out rehabilitation and reconstruction activities in build
back better features for road safety and climate resilience. The project activities are primarily
guided as per National Reconstruction and Rehabilitation Policy, 2072 B.S. (2016 A.D.), Act
relating to Reconstruction of the Earthquake Affected Structures 2072 B.S (2015 A.D.), Rule
relating to Reconstruction of the Earthquake Affected Structures 2072 B.S. (2016 A.D). The
project has been screened as per Work Procedure Related with Environmental Impact
Assessment for Rehabilitation of Earthquake Affected Structures (First Amendment, 2016
A.D.). Project has carried out IEE study and prepared the report as per the work procedure
of NRA and Environment Assessment and Review Framework (EARF) of ADB. For
implementation of EMP as prescribed by IEE, project has provision of human resource and
budget.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
15
3. STUDY APPROACH AND METHODOLOGY
3.1. General
29. The approach, methodology and procedure followed were according to the objectives
of IEE, and the legal requirements guided by Work Procedure Related with Environmental
Impact Assessment for Rehabilitation of Earthquake Affected Structures, 2072 (2016) of
GoN and the ToR approved by the secretary level decision of the MoFALD on 2072-12-10
(March 23, 2016). Adhering with the ToR, the study included desk study, literature review,
field survey/inspections/observations with measurements, discussions with local
communities, stakeholders, concerned agencies, and IEE team judgment. The copy of
approved ToR is given in Appendix 1. Rapid Environmental Assessment (REA) Checklist
and Checklist for preliminary climate risk screening were also considered during IEE report
preparation as given in Appendix 2.
3.2. Study Team
30. The study was carried out by a team of qualified professionals which consisted of the
followings (Table 9).
Table 9: Study Team
SN Position Name of Member Qualification
1 Team Leader (IEE Expert) Shyam Prasad Adhikari MSc in Env Sc.
2 Biologist Jaya Raj Mishra MSc in Forestry
3 Geologist Basanta Raj Adhikari PhD in Geology
4 Socio-economist Angishwor Shrestha MA Sociology
5 Civil Engineer Sabin Bajracharya BE Civil
3.3. Project Area Delineation
31. For the purpose of the IEE study, then VDC along which the sub-project passes
through was taken as the project area or the zone of influence (ZoI). ZoI has been
categorized into Direct Imapact Area (DIA) and Indirect Impact Area (IIA). Although the area
within 10 m on either side of the road from the centerline has been considered as the RoW,
DoR and DoLIDAR have been following 100 m on either side form the centerline within the
DIA. However, the width of the corridor to be studied depended on the legal requirement
plus the predicted extent of impacts. As the established practice, the wards of Likhu Rural
Municipality along which the road passes have been considered under DIA in this report and
the geographical boundary of the rual municipality excluding the DIA is considered for IIA
and has been taken into account for the socio-economic information including
impacts/issues assessment for the study purpose. This area has been further distinguished
into core project area and surrounding area as given in Table 10.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
16
Table 10: Impact Area Delineation
Zone Locations
Direct Impact Area
(DIA)
Wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality (then Tilpung,
Nagdaha, Bijulikot and Saipu VDCs).
Indirect Impact
Area (IIA)
Area within the boundary of Likhu Rural Municipality excluding
wards 2, 3, 4, 5 and 7
3.4. Desk Study and Literature review
32. The study commenced with desk study and review of relevant literatures. The
following activities were performed through desk study:
3.4.1. Review of Existing Information
33. Various existing sources of information were collected and reviewed to determine a
frame of reference for the assignment. Such sources of information included existing laws,
rules, guidelines and manuals, IEE reports of similar projects, Reference Manual for
Environmental and Social Aspects of Integrated Road Development, Environmental
Management Guidelines of DoR, APPROACH for the Development of Agricultural and Rural
Roads, 1999 of DoLIDAR, etc. Detailed Engineering Survey and design of the Haldebesi –
Dhobi – Dhandebesi Road Rehabilitation Sub-project were also reviewed to determine the
nature and scope of activities of the project. Similarly, pertinent sources of secondary
information were identified, collected and reviewed to build acquaintance with the
environmental settings of the project area under physical, biological and socio-economic and
cultural domains of the environment. These sources included publications of then DDC, then
VDCs, District Forest Office (DFO), Central Bureau of Statistics (CBS), NGOs, INGOs and
other governmental and non-governmental bodies. Data on rainfall and other meteorological
conditions were also acquired from secondary sources and authenticated with that obtained
from Department of Hydrology and Meteorology (DHM).
3.4.2. Map Reading
34. Preliminary acquaintance with the general environmental setting of the project area
was built by reading maps of different types like topographical maps, geological maps and
ecological maps. Similarly, geographical boundary of the Zone of Influence (ZoI) was defined
and delineated on the topographical map.
3.4.3. Checklists
35. Based on the desk study, project specific checklists were prepared for focus group
discussion and data collection on physical, biological and socio-economic and cultural
baseline data of the project area. This is based on APPROACH manual produced by
MoFALD.
3.5. Field Study
36. A multi-disciplinary team comprising of environmental expert, biologist, sociologist
and geologist visited the project site from 2073-01-01 B.S. (2016-04-13 A.D.) to 2073-01-11
B.S. (2016-04-23 A.D.) and carried out thorough field investigation through survey,
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
17
inspection, observation and measurement to collect baseline information on physical,
biological and socio-economic and cultural environments and identify possible issues and
impacts on these three environmental domains. Various participatory methods like focus
group discussion, key informant interview, consultations and interactions were employed to
aid collection of relevant information. The collected baseline data were verified by citing
standard references and evaluated before accessing impacts on them.
3.5.1. Initial Interaction and Consultation with Stakeholders
37. Prior to conducting the field study, interaction was carried out with the design team
and the proponent. Proponent was contacted on the first working day of field visit, i.e., 2073-
01-02 B.S. (2016-04-14 A.D.). The existing information about socio-economic condition of
the people in and around the proposed project site was also collected by interacting with
local communities, environment related organization, concerned government and non-
government agencies and other local and district level stakeholders.
3.5.2. Public Notice
38. The local people and stakeholders were involved in the study process through
various activities like public consultation, meetings, interactions and discussions. These
activities were employed to collect relevant information on various environmental domains
and peoples’ issues and concerns on the project. Public participation is essential to ensure
the quality, comprehensiveness, effectiveness of IEE as well as to ensure that the public
view's are adequately taken into consideration in the decision making process.
39. According to Working Procedure relating to Reconstruction of the Earthquake
Affected Structures 2016, 7 days notice had to be published in national daily newspaper.
However, 15 days public notice was published on 2072-12-22 B.S (2016-04-04 A.D.) in
“Nepal Samacharpatra”, a national level daily newspaper (Appendix 4) seeking written
opinion from then VDC, DFO, then DDC, schools, health posts and related local
organizations; immediately after approval of ToR as per EPA 1997 and EPR 1997. Copies of
the public notice were affixed in the notice board of the affected then DDC, DTO, then VDC,
Schools, Health posts, Post Office, Public Places etc. of the then VDC and deeds of
recognition (Muchulkas) were drawn to confirm the affixation of the notice in the
aforementioned locations (Appendix 5). Recommendation letters were obtained from the
affected municipality and attached in the IEE report (Appendix 6).
3.5.3. Public Consultations
40. The IEE team carried out a series of public consultation meetings with local
communities and related stakeholders. The consultation and interactions were focused on
the environmental sensitivity and concerns in the area, importance of environmental features
located in the area, present status, present problems or difficulties, potential solutions, and
consequences that are related in minimizing the possible impacts. A summary of meeting
minutes with local people is given in Table 11 and the meeting minutes are in Appendix 7.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
18
Table 11: Summary of the Meeting Minutes during Public Consultations
Date Venue and
Location
Participant Issues and suggestion of meetings
Male Female
2073-01-06
B.S. (2016-
04-18 A.D.)
Likhu RM-2
(former Saipu
VDC-8)
12 3 Provision of bridges and culverts as
necessary over the seasonal streams
Compensation of private land and
properties
Making construction works environment
friendly
Priority to blacktopping than increasing the
width
2073-01-06
B.S. (2016-
04-18 A.D.)
Likhu RM-3
(former Bijulikot
VDC-1)
17 0 Management of proper drainage structures
Employment priority to local people in
construction related jobs
Due consideration to landslides and erosion
during construction.
Consideration should be given to making
the construction environment frindly
2073-01-07
B.S. (2016-
04-19 A.D.)
Likhu RM-5
(former Nagdaha
VDC-8)
16 2 Timely implementation of the sub-project
and adoption of appropriate mitigation
measures for all the impacts on the
environment
2073-01-07
B.S. (2016-
04-19 A.D.)
Likhu RM-7
(former Tilpung
VDC-5)
11 2 Due consideration to landslides and erosion
during construction.
Consideration should be given to making
the construction environment friendly
Management of proper drainage structures
Compensation of private land and
properties
2073-01-08
B.S. (2016-
04-20 A.D.)
DCC Ramechhap
(then DDC),
Manthali
21 2 Proper mitigation measures should be
adopted to mitigate the adverse
environmental impact due to sub-project
implementation. (Source: Field survey, 2016)
3.5.4. Physical Environment
41. Walkthrough survey and field observation were carried out to collect site-specific
information about physical environment of the project area.
42. Geological investigation was made to explore the general geology, geomorphology,
geological features like discontinuities and possible geologic hazard within the road corridor.
3.5.5. Biological Environment
43. Information on existing flora was documented by reconnaissance survey of the
project site and its vicinity and listing of the plants encountered. Most of the plants were
identified in the field with the help of standard reference (Polunin and Stainton 1984).
Botanical nomenclature followed Press et al. (2000). Total enumeration was conducted for
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
19
trees that need to be felled. Plants with diameter at breast height greater than 10 cm were
considered as trees.
44. Forest management regimes were identified by discussion with the local people and
consulting the publication of District Forest Office.
45. Information on mammalian species was and their movement was obtained from
discussions with the Herders, Rangers, Security personnel, FUGs etc. Identification of
mammalian species followed Baral et.al. (2008) and Shrestha T.K. (1997).
46. An inventory of avifauna and herpetofauna was performed by direct observation
method using standard checklists and keys. Birds were observed with the help of binocular
and identified using standard key developed by Fleming (1976) and Inskipp (1985).
47. Ethno-biological survey comprised collection of representative species during
vegetation survey with analysis and recording of local information on their utilities by
administering interview/discussion session with relevant local informants, thereby showing
them the species in question and illustrated manuals (Martin, 1995; Shrestha, 1985).
48. Documented plants and animals were tallied with relevant references (IUCN Red
Data Book, CITES Appendices, Government of Nepal’s list of protected plant and animal) and assigned respective threat and protection statuses.
3.5.6. Socio-Economic and Cultural Environment
49. Socio-economic study was based on primary information collected from the field
through methods like focus group discussion (FGD), key informant interview (KII),
observation and household survey using socio-economic survey tools like checklists and
questionnaire. The study also used information available in the general documents on district
and then VDC and National Population Census, 2011 to compare with the primary findings.
FGD: Twelve (12) FDGs were conducted at the five major settlements along the road
alignment (Haldebesi, Jhangre, Katahare, Kharibote, Aarubote, Nagdaha, Dhobi, Kotgau,
Poku, Sirise Setapahara and Dhade.). On an average, 5 people were present in the
discussion whereby discussion was held on socio-economic condition of the area and
availability of resources and service facilities.
KII: KIIs were conducted with then VDC secretary and the representatives of CFUGs. The
interviews were focused on availability of natural resources and public service facilities.
Household Survey: Household survey was carried out in the study area to assess the
socio-economic condition and loss to be incurred by the project affected families as well as
to gather general socio-economic and cultural condition of the study area. The survey
covered 300 households of wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality (former
Tilpung, Nagdaha, Bijulikot and Saipu VDCs/not in order). Out of 40 of the project affected
families, 39 families were represented in the household survey and one family was absent in
the project area, meaning they are living outside the project area.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
20
50. Regarding the analysis technique, mainly descriptive analysis technique was used.
Nonetheless, simple quantitative analysis techniques (eg percentage and average) were
used for some environmental components.
3.6. Impact Identification, Prediction and Evaluation
51. Based on the project details and field investigation, potential issues related to
physical, biological, socio-economic and cultural environment due to the implementation of
the project were identified, predicted and evaluated. Issues and concerns were also solicited
from concerned agencies and local stakeholders through public notification and public
consultation meetings. While identifying and predicting the impacts, due consideration was
given to the proposed actions/activities during project construction and post construction
(Operation and Management) phase on the existing physical, biological and socio-economic
and cultural resources. Both beneficial and potential adverse impacts have been analyzed.
52. The Environmental impacts were evaluated on the basis of guidelines given in the
National EIA guidelines 1993, based on the Magnitude, Extent & Duration of the impact and
the respective numerical ranking. The criteria for the rating of the impacts in terms of their
magnitude, extent, and duration are elaborated below:
Magnitude: This can be low-Lo (minor), medium-M (moderate), and high-H (major),
depending on the scale or severity of change.
Geographical extent: If the action is confined to the project area, it is referred as site-
specific (Ss), if it occurs outside area but close to project area, the extent of impact is local
(L), if it occurs far away from the project, it is referred as regional (R).
Duration: It can be short term (ST - i.e. less than 3 years), medium term (MT - i.e. 3-20
years), and long term (LT - i.e. more than 20 years).
Table 12: Numerical scales as proposed in the National EIA Guidelines
Magnitude Score Extent Score Duration Score
High/Major 60 Regional 60 Long Term 20
Moderate/Medium 20 Local 20 Medium Term 10
Minor/Low 10 Site-specific 10 Short-Term 05 (Source: National EIA Guidelines, 1993)
53. The cumulative scores on this analysis have been used to decide the significance of
the impacts. Following Table 13 depicts the cumulative score of level of significance:
Table 13: Cumulative scores of level of significance
Total scores Significance of Impacts
Up to 44 Insignificant
45-74 Significant
Beyond 74 Very significant
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
21
3.7. Group Judgement
54. The IEE team worked as a group. Multi-sectoral analysis was done through
discussion in the group to identify inter linkages among various environmental issues. The
IEE team used group judgment as the basic tool to establish the significance of
environmental impact, identification and design of potential mitigation and enhancement
measures, and preparing EMP of the project.
3.8. Designation of Mitigation Measures and Monitoring Plans
55. Based on the identified impacts, their nature, extent and magnitude, the mitigation
and monitoring prescriptions were designed. A realistic approach was applied for the
application of the mitigation measures in the local context. Environmental monitoring plan
was developed to assess the effectiveness of the mitigation measures and implementation
status.
3.9. Report Preparation
56. Based on the processed information, a draft IEE report has been prepared with
detailed site specific baseline information and alternative analysis. All identified and
predicted likely environmental impacts have been included in the draft report, which also
contain environmental management plan (EMP). EMP has focused on realistic mitigation
measures, environmental monitoring including implementation responsibilities, staffing, and
budget and co-ordination aspects. The report has followed Schedule-4 under Subsection 1
of Section 12 of the Work Procedure Related with Environmental Impact Assessment for
Rehabilitation of Earthquake Affected Structures (Fundamental Procedure), 2072 (2016).
Final report will incorporate the comments of the review committee from NRA.
3.10. Information Disclosure
57. IEE report containing the executive summary in Nepali language, identified impacts,
recommended mitigation measures and the EMP will be sent to the Likhu Rural Municipality.
Approved IEE report will be made accessible to interested parties and general public through
DTO. Moreover, NRA, MoPE and CLPIU-EEAP will get the copy of final approved IEE
report. The e-copy will be available in ADB website also.
.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
22
4. EXISTING ENVIRONMENTAL CONDITION
58. This section deals in brief with the existing environmental setting of the project area
with regard to physical, biological, socio-economic and cultural environment and
interpretation of the baseline information with view of impact assessment and environmental
management.
4.1. Physical Environment
4.1.1. Topography
59. The project area lies in the Mid-hills (Lesser Himalayan) physiographic zone of
Central Nepal. The area has a rugged topography consisting steep hills and river valleys
(Figure 4). The elevation of the road ranges from 532 m to 1828 m asl.
Figure 4: Road Alignment in Google Earth Map
4.1.2. Geology and Soil Type
60. Geologically, the study area comprises rocks of Lesser Himalayan Sequence of
Central Nepal mainly phyllite, amphibolites, shists and metasandstone (Figure 5). There are
no major thrusts along the road alignment. The dominant rock types along the road
alignment are also phyllite, amphibolites, shists and metasandstone. The entire area is
composed of residual and colluvial soil. Rock outcrops are found at some locations.
Distribution and thickness of these soil types depend on the topography.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
23
Source: Dhital, 2015
Figure 5: Location of Sub-project in Geological Map
61. The detail topography, geology and overlying soil type along the road alignment is
presented in the Table 14.
Table 14: Geology and Soil Type along Road Alignment
Section Chainage Elevation
(m asl)
Aspect Geology Soil Type
Haldebesi-
Nagdaha
0+000-
13+900
531-1604 West-
East
Phyllite, Schist,
Gneiss,
Colluvial, Residual
Nagdaha-
Dhobi
13+900-
19+930
1604-
1831
West-
East
Phyllite Collivual, Residual
Dhobi-Sirise 19+930-
34+400
1831-780 West-
Northeast
Phyllite, Gneiss,
Shists and
Quartzite
Colluvial, Residual
Sirise-
Dhandebesi
34+400-
38+899
780-682 South-
North
Quartzite Residual, Colluvial,
Alluvial Source: Field Survey, 2016
Project
Area
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
24
4.1.3. Slope Stability and Erosion
62. The road alignment passes along a hilly terrain of the mid-hills. The stability of slopes
along the road corridor depends upon slope angle, the material constituting the slope, rock
discontinuities and hydrological conditions. There are few small scale slides or erosion prone
areas along the road alignment especially in Likhu Rural Municipality wards 2 and 7 (then
Tilpung and Saipu VDCs). The main causes for occurring slides are surface runoff and toe
cutting. The detail inventory of the landslide with location has been provided in Table 15.
Table 15: Landslides and Erosion Prone Areas along Road Alignment
SN Chainages Locations or
(Left/Right)
Length
of
Failure
Cause of
Failure
Protection
Structure From To
1 4+360 4+380 Tilpung, Likhu Rural
Municipality-7
20 m Toe cutting absent
2 6+600 6+660 Darimbot, Likhu
Rural Municipality-7
60 m Toe cutting absent
3 36+980 37+160 Sirise, Likhu Rural
Municipality-2
180 m Toe cutting absent
4 37+840 37+940 Dhadebesi, Likhu
Rural Municipality-2
100 m Toe cutting absent
5 38+340 38+480 Dhadebesi, Likhu
Rural Municipality-2
140 m Toe cutting absent
Source: Field Survey, 2016
4.1.4. Seismicity of the Project area
63. As we know, the evolution of the great Himalayan arc is the result of collision
between the Indian and the Eurasian tectonic plates and as the Himalaya lies in the plate
boundary, the region is considered as one of the active seismic zone of the World. Being a
part of the Himalaya, Nepal is considered to be an active seismic zone. The existence of
tectonic features such as MCT, MBT, HFT and other active regional faults further
accelerates the rate of seismic risk. However, the project area is fairly far from such features.
In order to determine seismic coefficient, a seismic design code for Nepal has been
prepared. Bajrachrya (1994) divided the whole country into five seismic risk zones (Figure
6). According to the map of Bajracharya (1994), the road sub-project lies in the medium
seismic risk zone of Nepal (Figure 6). However, Ramechhap District was one of the severely
affected districts due to the major Earthquake of 25 April 2015 and the major aftershock of
12 May 2015.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
25
Source: Bajracharya, 1994
Figure 6: Seismic risk map of Nepal
4.1.5. Climate
64. Climate of the sub-project area is controlled by variation in altitude and aspect.
Considering the elevation, the area has tropical to warm temperate climatic conditions. As
mentioned in the District Profile based on the DHM data of Ramechhap recorded in the
nearest meteorological station located in Manthali Municipality, annual rainfall is 1700 mm.
The temperature reaches as high as 300C in the summer and falls as low as 50C in the
winter.
4.1.6. Drainage and Hydrology
65. The road alignment passes through more than 12 small streams. All of them are
seasonal streams. There are no perennial streams along the road. Some of these streams
drain into the Tamakoshi River towards west through Tilpung Khola and some drain into the
Likhu Khola. The inventory of major streams has been presented in Table 16.
Table 16: Major Streams along the Road Alignment
SN Chainage Name of River/Stream Existing Structure New Structure Needed
and Size
1 6+100 Kartike Khola Existing None
2 10+900 Hile Khola Existing None
3 13+840 Chandi Khola Existing None
4 15+100 Airan Khola Existing None
5 17+000 Pahiro Khola Existing None
6 19+800 Swara Khola Existing None
7 29+340 Dhunge Khola None Causeway (15 m)
8 29+620 Poku Khola None Causeway (15 m)
9 33+100 Seti Khola Causeway None
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
26
SN Chainage Name of River/Stream Existing Structure New Structure Needed
and Size
10 34+755 Taruke Khola None Causeway (12 m)
11 35+972 Belauri Kholsi None Slab Culvert (6 m)
12 37+491 Pahare Kholsi None Causeway (6 m) Source: Field Survey, 2016
4.1.7. Land Use
66. The road alignment passes through various settlements, forest and agricultural land.
The land use of the road alignment is summarized in Table 17.
Table 17: Landuse along the Road Alignment
Type of Land Chainage Length
(m)
Existing
Width
(m)
Additional
Width (m)
Existing
area (ha)
Additional
Area (ha)
Total
Area
(ha) From To
Agriculture land
(Including
settlement)
0+000 38+899 29,794 5.25 1 15.64 2.98 18.62
Forest 0+080 37+445 4,510 5.25 1 2.37 0.45 2.82
Barren/Shrubland 1+780 38+899 4,595 5.25 1 2.41 0.46 2.87
Total 38,899 20.42 3.89 24.31
Source: Field Survey, 2016
4.1.8. Air Quality, Water Quality and Noise Levels
67. There are no permanent environmental monitoring stations in the project area. Site
specific expert assessment indicated that the air quality in the project area was extremely
good during the evaluation period. However, around 100 vehicles run along the road every
day. These cause instantaneous dust pollution during the vehicle movement owing to the
condition of road. During the vehicular movement in the semi-earthen road, fugitive
emissions and dust could be high at the local level. There are no other sources of air and
noise pollution like major or minor industry. As the road alignment does not cross or pass by
major perennial stream, the issue of water pollution is irrelevant for this sub-project. And any
point source of water pollution is not visible along the river alignment in the project area.
4.2. Biological Environment
68. The sub-project alignment passes through cultivation and settlement area. Few
shorter segments (totaling 4.51 km at different chainages) pass along the eight Community
Forest. The road section does not fall under any protected area or buffer zone area.
4.2.1. Vegetation and Forest Type
69. The road alignment passes through three distinct bioclimatic zones have: Tropical,
Sub-Tropical and Lower Temperate and these bioclimatic zones are reflected in the forest
types found along the road alignment. The project area in the beginning section of the road
has Tropical Sal Forest. The major section of the road has Sub-tropical Broadleaved Forest
interrupted by Sub-tropucal Pine Forest and Alder Forest at places. The ending section of
the road along side of the Likhu River has Tropical Riverine Forest.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
27
70. The beginning section has trees like Sal (Shorea robusta), Asna (Terminalia alata),
Bot dhayero (Lagerstroemia parviflora), Jamun (Syzygium cumini) and Khote Sallo (Pinus
roxburghii). Road section at higher elevation has dominancy of trees like Chilaune (Schima
wallichii), Khote Salla (Pinus roxburghii), Katush (Castanopsis indica) and Mauwa
(Engelhardtia spicata) and Uttis (Alnus nepalensis). Vegetation of Tropical Riverine Forest
like Khayar (Acacia catechu), Simal (Bombax ceiba), Sissoo (Dalbergia sissoo) and Haldu
(Adina cordifolia) are found along the side of the Likhu Khola. At the higher elevations, the
Sup-tropical Forest is penetrated by Lower Temperate species like Bajh (Quercus lanata)
and Guras (Rhododendron arboreum).
Table 18: Chainage wise Dominancy of Tree Species
Chainages Dominant Tree Species
From To
0+000 3+500 Sal (Shorea robusta)
3+500 10+000 Chilaune (Schima wallichii), Khote salla (Pinus roxburghii)
10+000 15+000 Uttis (Alnus nepalensis), Chilaune (Schima wallichii)
15+000 25+000 Uttis (Alnus nepalensis), Chilaune (Schima wallichii)
25+000 34+000 Chilaune (Schima wallichii), Uttis (Alnus nepalensis)
34+000 38+899 Karam (Adina cordifolia), Khair (Acacia catechu), Sissoo
(Dalbergia sissoo) Source: Field Survey, 2016
71. Besides these dominant species, other trees reported in the surrounding area are
Lampate (Duabanga grandifolia), Bel (Aegale marmelos), Gineri (Premna integrifolia), Gayo
(Bredelia retusa), Phaledo (Erythrina sps.), Khirro (Sapium insigne), Tooni (Cedrela toona),
Kutmiro (Litsea monopetala), Chuletro (Brassaiopsis hainla), Dudhilo (Ficus nerifolia),
Khanyo (Ficus semicordata), Taki (Bauhinia purpurea), Lakuri (Fraxinus floribunda), Gogan
(Sauraria nepaulensis), Bhalayo (Ricinus communis), Kaulo (Persea odoratissima), Jhigane
(Eurya acuminata), Nemaro (Ficus auriculata), Paheli (Litsea salicifolia), Maledo (Macaranga
denticulata), Kafal (Myrica esculenta) etc.
72. Shrub species include Dhairo (Woodwordia fruticosa), Aasuro (Adhatoda vasica),
Bilaune (Maesa chisia), Jhadi banmara (Lantana camara), Jhingani (Eurya acuminata),
Bansuli (Dichroa febrifuga), Aiselu (Rubus ellipticus, Rubus paniculatus), Chutro (Berberis
aristata) etc. Ground vegetations include Dhursul (Colebrookia oppositifolia), Rudhilo
(Pogostemon benghalensis), Banmara (Eupatorium adenophorum), Bukiphool (Osbeckia
sps.), Datiwan (Achyranthus sikkimensis), Gandhe (Ageratum conyzoides), Titepati
(Artemisia sps.), Sisno (Utricia diocia), Amriso (Thysanolena maxima).
4.2.2. Forest Management Regimes
73. Two types of forest are existent in the project area based on management practices:
Community Managed Forest and Private Forest.
Community Forest: According to DFO Ramechhap, the forests in the Ramechhap District
have been handed over to 339 forest user groups while some patches are managed by the
government itself. Altogether 4.510 km of the proposed road section passes along eight
community forests as described in the Table 19:
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
28
Table 19: Community Forest along the Road Alignment
Chainage Name of
CF,
Address
Major Species Existing
Area (ha)
Additional
Area (ha)
Total
Area
(ha)
Total Area
of CF (ha)
Beneficiary
HH
Mammals
Found
Birds Recorded
From To
0+080 0+780 Khumbari
CF,
Tiplung-2
Sal (Shorea
robusta), Asna
(Terminalia
alata), Bot
dhayero
(Lagerstroemia
parviflora),
0.614 0.117 0.731 15.12 68 Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak), Langur
(Semnopithecus
entellus), Dumsi
(Hystrix indica)
Kalij (Lophura
leucomelanos),
Lampuchhre
(Urocissa
erythrorhyncha) ,
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps)
2+590 3+060
1+520 1+845 Ramche
CF,
Tiplung-3
Chilaune
(Schima
wallichii), Salla
(Pinus
roxburghii),
0.171 0.033 0.203 25 53 Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak), Langur
(Semnopithecus
entellus), Dumsi
(Hystrix indica)
Kalij (Lophura
leucomelanos),
Lampuchhre
(Urocissa
erythrorhyncha) ,
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps)
16+800 17+000 Kharang
Khurung
CF,
Nagdaha 8
Chilaune
(Schima
wallichii), Salla
(Pinus
roxburghii), Uttis
(Alnus
nepalensis)
0.105 0.020 0.125 17.59 31 Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak), Langur
(Semnopithecus
entellus), Dumsi
(Hystrix indica)
Kalij (Lophura
leucomelanos),
Lampuchhre
(Urocissa
erythrorhyncha) ,
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
29
Chainage Name of
CF,
Address
Major Species Existing
Area (ha)
Additional
Area (ha)
Total
Area
(ha)
Total Area
of CF (ha)
Beneficiary
HH
Mammals
Found
Birds Recorded
From To
24+100 24+250 Jhatteswari
CF,
Bijulikot 1,2
Chilaune
(Schima
wallichii), Uttis
(Alnus
nepalensis)
0.079 0.015 0.094 45.0 60 Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak), Langur
(Semnopithecus
entellus), Dumsi
(Hystrix indica)
Kalij (Lophura
leucomelanos),
Lampuchhre
(Urocissa
erythrorhyncha) ,
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps)
26+000 26+200 Bhringesw
ar CF,
Bijulikot
7,8,9
Chilaune
(Schima
wallichii), Salla
(Pinus
roxburghii), Uttis
(Alnus
nepalensis)
0.105 0.020 0.125 35.74 126 Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak), Langur
(Semnopithecus
entellus), Dumsi
(Hystrix indica)
Kalij (Lophura
leucomelanos),
Lampuchhre
(Urocissa
erythrorhyncha) ,
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps)
30+010 31+100 Poku
Salgharni
CF (Saipu
CF)
Chilaune
(Schima
wallichii), Uttis
(Alnus
nepalensis)
0.572 0.109 0.681 20.0 152 Malsapro
(Martef flabiguli),
Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak), Langur
(Semnopithecus
entellus)
Kalij (Lophura
leucomelanos),
Lampuchhre
(Urocissa
erythrorhyncha) ,
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
30
Chainage Name of
CF,
Address
Major Species Existing
Area (ha)
Additional
Area (ha)
Total
Area
(ha)
Total Area
of CF (ha)
Beneficiary
HH
Mammals
Found
Birds Recorded
From To
36+010 37+090 Taruke
Salleni CF,
Saipu 2-7
Sal (Shorea
robusta), Salla
(Pinus
roxburghii),
0.567 0.108 0.675 85.5 181 Malsapro
(Martef flabiguli),
Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak),
Kalij (Lophura
leucomelanos),
Lampuchhre
(Urocissa
erythrorhyncha) ,
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps), Dhukur
(Sterptopelia
senegalensis)
37+150 37+445 Sipu Pakha
CF, Saipu-
4
Khayar (Acacia
catechu), Sissoo
(Dalbergia
sissoo)
0.155 0.030 0.184 34.1 106 Malsapro
(Martef flabiguli),
Rato badar
(Macaca
mulatta),
Mriga(Muntiacus
muntjak), Langur
(Semnopithecus
entellus)
Kalij (Lophura
leucomelanos),
Ranichari
(Pericrocotus sps),
Jureli (Hypsiperes
sps), Dhukur
(Sterptopelia
senegalensis)
Total 2.368 0.451 2.819
Source: DFO, 2015/Field Survey, 2016
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
31
74. Local people have planted trees in some patches of their private land or at the edge
of the terrace of their agricultural land. They generally plant fruit and fodder trees in their
private land. These are not registered as private forest in District Forest Office (DFO).
Additionally, people also own forest land as Kharbari which supply them with fodder and
fuelwood.
4.2.3. Domesticated Plants
75. Local people have planted other fruit trees like Junar (Citrus sinensis), Naspati
(Pyrus communis), Suntala (Citrus reticulata), Nibuwa (Citrus limonum), Aaru (Prunus
persica), Kagati (Citrus aurantifolia), Aamp (Magnifera indica), Katahar (Artocarpus
heterophyllus), Amala (Emblica officinalis), Lapsi (Choerospondias axillaris), Banana (Musa
paradisia) and Gauva (Psidium guajava), etc and fodder trees like Paiyu (Prunus
cerasoides), Gogan (Sauraria nepalensis), Nemaro (Ficus auriculata), Bhimal (Grewia
optiva), Kimu (Morus alba), Kutmero (Litsea monopetala), Ipil Ipil (Leucaena leucocephala),
Dabdabe (Garuga pinnata), etc. Besides, people grow numerous other crops, vegetables,
pulses and fruits for household utilization or selling in the market and those form quite a long
list.
4.2.4. Ethno-botany and NTFPs
76. The biological resources play influential role in the socio-economic condition and life
style of local people. Diverse ethnic groups inhabit the project area. They use different
biological resources in various ways, like food, medicine and others. People around the
project location reported different utilities of the plant resources found in the area, though
currently, there is no record of commercial utilization of such resources in the project area.
Table 20: Medicinal Plants and Local Use
S
N
Scientific Name Common Name Part Used Purpose
1 Achyranthes aspera Datiwan Stem/Root Jaundice
2 Artemesia sps Titepati Leaf Cut and Rashes
3 Centella asiatica Ghodtapre Leaf Urinary Disorder
4 Cinnamomum tamala Tejpat/Dalchini Leaf/Bark Spices
5 Cuscuta reflexa Akas Beli Shoot Jaundice
6 Gaultheria fragrantissima Dhasingare Leaf juice Muscle Pain
7 Jatropha curcas Sajiwan Stem Toothache
8 Ocimum sanctum Tulsi Leaves Cold, Cough and Fever
9 Rhododendron arboreum Gurans Flower Diarrhea
10 Schima wallichii Chaliune Bark Juice Cut and Wound
11 Smilax ovalifolia Kukur Daino Shoot Stomach Disorder
12 Syzygium cumini Jamun Fruit Diarrhea
13 Utricia diocia Sisno Leaf Vegetable
14 Zanthoxylum armatum Timur Fruit Stomachache and Cold Source: Field Survey, 2016
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
32
4.2.5. Rare, Threatened and Protected Plants
77. Among the plant species recorded in the project area, commercial felling of Shorea
robusta has been banned by government of Nepal under the Forest Act, 2049. However, no
Sal trees need to be felled for project implementation.
4.2.6. Wildlife
78. A major portion of road alignment lies in agricultural land and settlement area, hence
does not hold permanent habitat of wildlife. The edges of forest designated as various
Community Forests with small segment of the alignment does not hold major habitat of
wildlife. However, the forests continue to a large tract of forest which harbours common
wildlife which sometimes find their way around the road corridor. Since the patches of forest
lie close to one another, moreover, they are virtually connected to one another; the wildlife
composition of the area is in general similar. There are no such unique habitat condition in
the area contributing to unique wildlife composition.
Mammal: Common prey species of the area is Muntiacus muntjak (Barking Deer). Common
carnivores of the project area are Canis aureus (Golden Jackal), Felis chaus (Wild Cat),
Martes flavigula (Malsapro) and Panthera pardus (Common Leopard). While animals like
Barking Deer and Golden Jackal are commonly seen in the project area, Common Leopard
is an infrequent visitor. Other mammals encountered in the area include primates like
Macaca mullata (Rhesus Macaque) and Semnopithecus entellus (Langur) and rodents like
Funambulus pennanti (Northern Palm Squirrel), Hystrix indica (Porcupine), Herspestes
edwardsi (Grey Mongoose) and various species of bats (Pteropsus sps) etc.
Avifauna: Lophura leucomelanos (Kaliz), Megalaima virens (Great Barbet), Magalaima
asiatica (Blue-thorated Barbet), Corvus splendens (House Crow), Corvus macrorhyncos
(Jungle Crow), Columba livia (Rock Pigeon), Passer domesticus (House Sparrow), Milvus
migrans (Black Kite), Acridotheres tristis (Common Mayna), Streptopelia orientalis (Oriental
Turtle Dove), Seicercus xanthoschistos (Grey-hooded Warbler), Phycnonotus cafer (Red-
vented Bulbul), P. leucogenys (Himalayan Bulbul), Urocissa erythrorhyncha (Red-billed Blue
Magpie), Halcyon smyrnensis (White-breasted Kingfisher), Copsychus saularis (Oriental
Magpie Robin), Lanius schach (Long-tailed Shrike), Rhyacornis fuliginosus (Plumbeous
Water Redstart), Dicrurus macrocercus (Black Drongo), Bubulcus ibis (Cattle Egret), Bubo
nepalensis (Spot-bellied Eagle Owl), Glaucidium radiatum (Jungle Owlet) and Orthrotomus
sp (Wabler) were recorded by direct sighting during the field visit in the area.
Herpetofauna: The common herpeto-fauna reported in the project area were Ptyas
mucosus (Common Rat Snake), Amphiesma stolatum (Buff-striped Keel back), Trimeresurus
albolabris (White Lipped Pit Viper), Laudakia tuberculata (Himalayan Rock Lizard), Calotes
versicolor (Common Garden Lizard), Hemidactylus spp (House Gecko), Scincella
sikkimensis (Sikkim skink), Bufo melanonostictus (Asian Toad), Hoplobatrachus rugulosus
(Pani Bhyaguta) and Paha (Bufo spp.).
4.2.7. Rare, Threatened and Protected Wildlife
79. Among the faunal species recorded in the project location, ten (10) species including
six mammals, three birds and one reptile were specified different protection statuses.
Though none of the animals recorded were nationally protected by GoN under National
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
33
Parks and Wildlife Conservation Act, 1973, all of these species were listed in different
appendices of CITES. Additionally, one species were listed as Near Threatened (NT) in
IUCN Red List of Threatened Species. Others were of Low Risk (LR) or Least Concern (LC)
or had not been assessed for their threat status.
Table 21: Rare, Threatened and Protected Animals Found in Project Area
SN Scientific Name Local Name Legal Status Local Status
Local Use GoN IUCN CITES
1 Macaca mullata Rato Bandar II Common Pest 2 Panthera pardus Chituwa NT I Rare Pest 3 Semnopithecus
entellus Langur LC I Common
4 Canis aureus Syal LC III Common Pest 5 Felis chaus Ban Biralo LC II Rare Pest 6 Herpestes edwardsi Nyauri Musa III Common 7 Milvus migrans Kalo Chil LC II Common 8 Bubo nipalensis Mahakaushik LC II Rare 9 Glaucidium radiatum Dundul LC II Rare 10 Ptyas mucosus Dhaman II Common
CITIES Appendices
Appendix I: Species threatened with extinction Appendix II: Species not yet threatened, but could become endangered if trade is not controlled Appendix III: Species identified by any party as being subject to regulation in that country and which require international co-operation to control trade IUCN Red List (1995)
LR: Low Risk, NT: Near Threatened, LC: Least Concern, VU: Vulnerable, EN: Endangered, CR: Critically Endangered, K:
Insufficiently Known
4.3. Socio Economic and Cultural Environment
4.3.1. Population, Household and Settlement
District Context:
80. Ramechhap District is a hilly district in the Central Nepal and covers an area of 1546
sq.km. According to the National Population Census, 2011, this district has a total population
of 202,646 with a density of 137.4 per sq.km. There are now 8 new local administrations
namely; Manthali Municipality, Ramechhap Municipality, Umakunda Rural Municipality,
Khandadevi Rural Municipality, Gokulganga Rural Municipality, Doramba Rural Municipality,
Likhu Sunkhoshi Rural Municipality and Sunapati Rural Municipality. The population of the
district is dominated by Brahmin/Chhetri followed by Tamang and Magar, hence the major
language spoken in the district are Nepali and Tamang.
Rural Municipality Context:
81. Likhu Rural Municipality has been reformed by incorporating former Duragau, Sipu,
Bijulikot, Nagdaha, Khimti and Tilpung VDCs. There are now 7 wards in this Rural
Municipality. According to National Population Census, 2011, the total population of this
Rural Municipality is 23,109. With an area of 124.51 sq.km. the population density of this
186.6 per sq.km. Detail is given in the Table 22 below
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
34
Table 22: Population Distribution in District, Rural Municipality and Project Area
District/Rural municipality Total
HH
Total
Population
Male Female HH
Size
Ramechhap District 43,910 202,646 93,386 109,260 4.62
Likhu Rural Municipality 4,928 23,109 10,615 12,494 4.69
Project Wards 3,308 15,808 7,206 8,602 4.78 Source: CBS, 2011
Settlements Context:
82. The road alignment traverses wards 2, 3, 4, 5, and 7 of Likhu Rural Municipality
(then Tilpung, Nagdaha, Bijulikot and Saipu VDCs) of Ramechhap District via 14 settlements
namely Haldebesi, Ratmate, Tilpung, Darimbot, Dhade, Chakharka, Lamagau, Dhobi,
Kotgau, Dharapani, Poku, Sirise, Belauri and Dhadebesi. According to National Population
Cesnsus ( 2011), 15,808 people with 7,206 male and 8,602 female live in 3,308 households
in wards 2, 3, 4, 5 and 7 of Likhu Rural Municiplaity. The average household size is 4.78.
Field discussion in the major settlements along the road alidnment shows that there are
altogether 6,204 persons with 2,881 male and 3,311 female live in 1273 households in the
14 settlements along the sub-project alignment. The average household size is 4.87. The
detail demographic information is provided in the Table 23.
Table 23: Settlements and Population of the along the Road Corridor
SN Settlement Former VDCs
HH Population
Caste/Ethnicity Male Female Total
1 Haldebesi Tilpung 105 238 274 512 Chhetri, Newar
2 Ratmate Tilpung 94 269 289 558 Chhetri, Brahman
3 Tilpung Tilpung 103 237 263 512 Chhetri, Newar
4 Gahate/ Darimbot
Tilpung 82 219 258 477
Chhetri, Magar
5 Dhade Nagdaha 69 153 198 351
Tamang, Magar, Chhetri
6 Chakharka Nagdaha 89 185 239 424
Tamang, Magar, Chhetri
7 Lamagau Nagdaha 97 206 222 428
Tamang, Magar, Chhetri
8 Dhobi Bijulikot 108 230 246 476 Chhetri, Newar
9 Kotgau Bijulikot 157 292 365 657 Chhetri, Tamang
10 Dharapani Bijulikot 103 244 263 507 Chhteri, Tamang
11 Poku Saipu 97 213 252 465 Chhetri, Magar
12 Sirise Saipu 47 121 145 266 Chhetri, Brahman
13 Belauri Saipu 32 61 78 139 Newar, Chhetri
14 Dhadebesi Saipu 90 213 219 432 Newar, Chhetri
1273 2881 3311 6204 Source: Field Discussion, 2016
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
35
4.3.2. Caste and Ethnicity
83. The population of Project Area (Likhu Rural Municipality) is dominated by Chhetri
(32%) followed by Tamang (29%) and Magar (12%). Other castes include Newar, Sunuwar,
Kami, Sarki, Gharti/Bhujel, Sanyasi, Hill-Brahmin, Damai, etc. The household survey of 300
households in the sub-project area shows that 61% of the households belong to Janajati
group. Similarly, Brahmin/Chhetri comprised about 36% of the households and 2 % were
Dalit.
84. The area is a home to diverse ethnic or indigenous communities like Tamang,
Newar, Magar, Sunuwar and Gharti/Bhujel and occupational castes like Damai/Dholi, Kami,
Sarki. Occupational caste households are distributed in almost all the settlements. They
have the lowest status in all sectors, i.e. they lack land resources, livestock, education,
sufficient income, access to all services and facilities.
4.3.3. Language
85. Majority of the people of the project area speak Nepali language (57%) while another
widely spoken language is Tamang owing to their second dominancy. Remaining people
speak other languages like Magar, Newar, Sunuwar and others based on their origin. But
almost all can also speak Nepali language.
4.3.4. Literacy and Education
86. Considering the population above 5 years of age, the total literacy of the project area
is 62.98% with male literacy rate 72.23% and female literacy rate 55.38%. The literacy of
project area is comparable with that of the whole district. Project area has people with all
levels of academic achievements. Local people have realized the importance of education in
their life and most of them send their children to school. However, dropout rate of female
students is still higher than male students.
4.3.5. Occupation
87. Almost all of the households are involved in agriculture, horticulture and livestock
along with other occupation. However, because of the size of the landholding and hardship
related with the geo-topographic setting, the agricultural output is insufficient to last whole
year; hence they resort to other occupations specially wage labour to fill the deficit. The
household survey data of the project area shows that 95% of the male population was
engaged in paid work including farming, livestock farming, business and other types of
employment; 16% of female are involved in these works. 84% of female are not involved in
any income generating activities. This high proportion of women in unpaid work is an
indicator of their hardship in their own house, and also their low involvement in direct
economic activities.
88. The main occupation of the surveyed households is agriculture and livestock with
more than half of the households (56%) dependent mainly on it. People are also involved in
wage labor and few in service in different organizations. Actually, the households resort on
more than one occupation for living (Refer Table 24).
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
36
Table 24: Occupations of Surveyed Households
Occupation Agriculture Wage Labor Service Business No
Occupation
Others Total
HHs
HH 168 43 37 0 15 37 300
Percentage 56.0 14.3 12.3 0.0 5.0 12.3 100
Source: HH Survey, 2016
4.3.6. Agriculture and Cropping Pattern
89. As known from field discussion with the local people, they grow cereal crops like rice,
wheat, maize, millet and buckwheat along with pulses like lentils, soybeans, beans and
vegetables like potato, cabbage, cauliflower, garlic and onion. Rice-Wheat-Fallow and Rice-
Wheat-Maize were major cropping pattern of Khet land and Maize/finger millet-fallow and
Maize/finger millet-Wheat was major cropping pattern in Bari land in the project area. People
have recently started to grow seasonal vegetables and fruits like Junar and Naspati. With the
upgrading of the road, transportation of these products will become easy.
4.3.7. Livestock
90. Livestock is closely associated with agricultural occupation of the population, hence
is an integral part of agriculture for their livelihood. Those who have adopted agriculture as
their main occupation, used to hold the livestock as well, as such 89.6 % of the households
have held livestock. Majority of the HH have raised local breeds of all kinds of livestock such
as cattle, buffaloes, goats, and pigs. Improved breeds of cows and buffaloes were raised by
a negligible number of HH.
91. People grow cereal crops like wheat, maize, millet, rice and buckwheat along with
pulses like lentils, soybeans, beans and vegetables like potato, cabbage, cauliflower, garlic
and onion along with various types of fruits. With the upgrading of the road, transportation of
these products will become easy. Regarding livestock, people raise cow, buffalo, pig and
goat. People are also engaged in foreign employment with most of the youth working
abroad.
4.3.8. Migration Pattern
92. Table 25 shows the status of migration among the surveyed households. About
48.7% respondents were found living in the own village for many years. Likewise, among the
respondents, only 40.7% of the respondent had stayed outside their homes of over 6 months
and only 11.0% had stayed out of the country for more than 6 months.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
37
Table 25: Migration Status in the ZoI
Migration Status No. of Respondents Total Percentage
Male Female
No been away (lived continuously) 114 32 146 48.7
Been away for above 6 months in Nepal 118 4 122 40.7
Been away for above 6 months outside Nepal 32 1 33 11.0
Total 264 36 300 100.0
Source: HH Survey Data, 2016
93. Both in-migration and out-migration were reported in the project area. According to
latest census (CBS, 2011), 704 male and 181 female are absent in the project area. The
reasons of absenteeism have been found to be private jobs (60%), government jobs (10%),
education (15%) and others. Permanent migration takes places generally to the district
headquarter in Manthali, plane areas in the Terai and the capital city, Kathmandu. Likewise,
from all settlements, people migrate seasonally from Shrawan to Poush mainly in various
parts of Nepal like Kathmandu, Dhulikhel, Banepa as well as various parts of India to work
as wage labours and guards. Going abroad for employment is more common these days
among the youths. The major destinations in order of preference are Middle-East, India and
Malaysia
4.3.9. Public Health and Sanitation
94. Health care service is being delivered by four Sub-Health Posts located in each of
the project VDCs (former) along the road alignment. District level government facilities are
available in Ramechhap and Bamti. According to the District Health Office (2072), the major
health problems of the area are pulmonary obstructions/respiratory tract infection, skin
diseases, diarrhea, gastritis, ear infection, helmenthiasis, typhoid and others. The health
status of people has improved because of increased awareness towards health and
sanitation.
95. Ramechhap District has been enforcing prohibition on open defecation by providing
technical and financial support for household to build their own toilet. As of 2011, more than
64.3% of the households had built permanent toilet in the project area (CBS, 2011). As
understood from conversation with then VDC secretaries and Focus Group Discussion held
in the project area, the some rural households are yet to build permanent toilet.
4.3.10. Public Service Infrastructures and Facilities
Drinking Water Supply: Piped drinking water facilities are available to almost all the
settlements in the ZoI. The water supply generally use spring sources located at higher
elevations. The water is conveyed by pipes from the sources to the public taps through
gravity flow. These taps are located in common places so that each serves a particular
number of households. Some houses have managed private connection. CBS, 2011 shows
that 90.12% of the families have been relying on tap/piped supply while remaining 9.88 %
have been relying on well, spout or stream water.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
38
Education: The project area has various levels of educational institutions and all are
managed by community (Government Institutions). There are altogether 26 formal
educational institutions in the project area including a secondary school in each of the
project VDC (former). All the schools are fairly far to be affected by the construction
activities.
Communication: Communication facility has infiltrated to almost all the areas in the project
area through mobile services of various types. The cable phones used in the past are losing
popularity due to easily accessible mobile network. Radio, FM and Television networks have
come within the access of local people. Internet service and printed media is yet to gain
popularity in the area. There is one additional post office at each of the project VDCs
(former).
Electricity and Lighting: Electricity supply is limited to the settlements alongside the road
alignment towards the start and the end only (then Tilpung VDC and Saipu VDC). Others
have managed solar panel for domestic lighting.
Fuel Wood: Fuel wood is still the common source of cooking energy with more than 98%
dependent on it. While some people have managed to grow trees in the backyard but still
large number of these fuelwood dependent people rely on surrounding forests managed as
community forests. However with the growing access, the conventional fuel is losing
popularity and people have started catering towards modern fuel like Liquid Petroleum Gas
(LPG) for cooking purpose.
Road and Transportation: The project area is connected with the district headquarter and
other parts of Nepal by road network.
Irrigation: The areas along the road alignment are mostly dependent on seasonal irrigation
from rainwater for agriculture. The seasonal kholsis have been the major source of irrigation
along the road alignment. The reconstruction works need to consider the irrigation canals at
various places.
Health Care System: Health care service is being delivered by four Sub-Health Posts (one
in each former VDC) along the road alignment. District level government facilities are
available in Ramechhap and Bamti. People also go to cities, especially Dhulikhel and
Kathmandu with more equipped and advanced services in case of complex health problems.
People also believe in local faith healers, Dhamis and Jhakris.
Market Centers: Local markets available along the road alignment are Haldebesi, Dhobi
and Dhadebesi which has shops of daily commodities, garments and restaurants. The major
market centers are Manthali, Ramechhap and Charikot which are fairly far but but connected
with road network.
Business and Industries: The project area lacks major industries however there are
various other types of businesses selling goods and services in the local area, especially
shop stalls of various types like garments, construction materials, groceries, restaurants,
liquors, cosmetics, tailor etc.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
39
96. The area has the potentiality of vegetable farming and livestock based ventures
(such as dairy production) as well as furniture and bamboo crafts.
Financial Institutions: There are eight saving and credit cooperatives in the project area.
Major Banks are available in the district headquarter only.
Other Infrastructures: Community use structures like ghats (Cremation sites) are available
in the ghyangs located in the project area but are far from the road alignment. Playground
and community centers are found in most of the settlements along the road alignment.
Religious and Cultural Sites: Most of the settlements have a religious and cultural site
depending on the dominant religion and ethnicity. There are altogether 4 Gumbas and 20
(Temples) in the project area. Among the Gumbas, Peepaldip Ghyang of former Nagdaha
VDC has the local cremation site. However, these shrines are fairly far from the road
alignment to be affected by the road construction activities.
Non-Governmental Organization and Activities: A number of NGOs, clubs, mother
groups, cooperatives, forest user groups, credit and saving groups, etc are working in the
field of emergency management, water supply, sanitation, disaster, sports, women
awareness, capital mobilization, rural livelihood and income generating activities in the
project area.
4.3.11. Food Sufficiency
97. According to the household survey performed in 300 households, none of the
households in the ZoI are able to save part of their production and have to rely on other
resorts to fill up the deficiency. Such resorts include small businesses, wage labour, services
and remittance. The data on food sufficiency in the settlements along the road alignment
shows that 75 % HHs have food sufficient for less than three months, 15 % HHs for 3-6
months, 7 % HHs for 6-9 months and 3% of HHs for 9-12 months (HH Survey, 2016).
Table 26: Food Sufficiency and Income level of the Affected Households
Food Sufficiency Frequency Percent
<3 Months 225 75
3-6 Months 45 15
6-9 Months 21 7
9-12 Months 9 3
Total 300 100
Source: HH Survey, 2016
4.3.12. Potential Development Areas
98. Most of the settlements, especially in higher elevations along the proposed road
alignment and its neighborhood have immense potential of vegetable and livestock farming.
Dhobi is the major checkpoint to reach Thalari (located in former Bijulikot VDC) which could
be developed as sunset view point. Likewise, there are ancient cemeteries which date back
to the Kirant Regime. Other things of attraction could be ancient tunnels bored for copper
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
40
mining. Similarly, Giddhedada (located in former Saipu VDC) can be developed as a view
point. This is the best location to view Pokali Waterfall of Okhaldhunga District. As such, the
project area has immense potential for tourism development. Nonetheless, people from all
the settlements will be directly benefited through development in agriculture, education,
health and food security sector.
4.3.13. Project Affected Families
99. Altogether 24 households will lose all or part of their private structures including
cottage and houses due to widening of the road to achive prescribed standard. Similarly, 19
households will lose part of their land for this. The name and detail of these people have
been presented in the Tables 27, 28 and Appendix 10.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
41
Table 27: Status of People Losing their Struturues in Road Sub-project
S.N Name Structure Occupation Chainage
no.
Land
Holding
Food
Sufficiency in
Average
Income Ethnicity Remarks
1 Govinda
Shrestha
House Agriculture/retail
shop
21+900 Self 6 month Agriculture Janajati
2 Maila
Mahatra
House Retail shop 21+900 Self 3 Month Agriculture
/ wages
Dalit
3 Sher
Bdr.Tamang
House/
cottage
Agriculture 22+400 Self 6 Month Agriculture /
wages Janajati
4 Dolkumari
Shrestha
Cottage Agriculture 22+500 Self 6 Month Agriculture /
wages Janajati
5 Dhal Bdr.
Shrestha
Balkuni of
house /
Cottage
Agriculture 23+000 Self 6 Month Agriculture /
wages Janajati
6 Chun Naryan
Shrestha
House Agriculture 25+000 Self 6 Month Agriculture /
wages Janajati
7 Indra Naryan
Shrestha
House Agriculture 25+000 Self 6 Month Agriculture /
wages Janajati
8 Tilak
Limilsina
Cottage/
Shop
Agriculture/ Shop 25+200 Self 6 Month Agriculture /
wages Brahmin/Chhetri
9 Kewal
Timilsina
Cottage Agriculture 25+600 Self 6 Month Agriculture /
wages Bramin/Chhetri
10 Chakra Bdr.
Tamang
Cottage Agriculture /Shop 26+300 6 Month Agriculture /
wages Janajati Public
land
11 Dhudhi
Tamang
House Agriculture 26+300 6 Month Agriculture /
wages Janajati Public
land
12 Suntali
Tamang
Suntali
Tamang
Agriculture 26+300 Self 6 Month Agriculture /
wages Janajati
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
42
S.N Name Structure Occupation Chainage
no.
Land
Holding
Food
Sufficiency in
Average
Income Ethnicity Remarks
13 Yam Bdr.
Tamang
Cottage Agriculture 26+400 Self 6 Month Agriculture /
wages
Janajati
14 Tilak Bdr.
Tamang
House Agriculture 27+300 Self 6 Month Agriculture /
wages
Janajati
15 Gumba
Tamang
Balkuni Agriculture 28+100 Self 6 Month Agriculture /
wages
Janajati
16 Jit Bdr.
Tamang
House
/Cottage
Agriculture 28+200 Self 6 Month Agriculture /
wages
Janajati
17 Gole Tamang Cottage Agriculture 28+400 Self 6 Month Agriculture /
wages
Janajati
18 Voj Bdr.
Mahara
Cottage Agriculture/
Waving cutting
29+200 Self 6 Month Agriculture /
wages
Janajati
19 Gope
Tamang
Small
Cottage
Agriculture 29+300 Self 6 Month Agriculture /
wages
Janajati
20 Jit Bdr.
Tamang
Balkuni+
Cottage
Agriculture 32+800 Self 6 Month Agriculture /
wages
Janajati
21 Lok Bdr. Raut Cottage Agriculture 33+000 Self 6 Month Agriculture /
wages
Janajati
22 Chet Bdr
Thapa
Cottage
/Balkuni
Agriculture 33+050 Self 6 Month Agriculture /
wages
Bramin/Chhetri
23 Dhan Raj
Raut
House Agriculture 33+050 Self 6 Month Agriculture /
wages
Bramin/Chhetri
24 Gopal Basnet Balkuni Agriculture 33+100 Self 6 Month Agriculture /
wages
Bramin/Chhetri
Source: Field Survey, 2016
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
43
Table 28: People Losing their Land to Road Sub-project
S.N Name of owner Affected Chainage
No.
Standing
Crops
Affected
area
(Average)
Remarks
1 Tika Kami Land 21+900 Maize 15 to 25 m2 Right side
2 Amrit Bdr. Khadka (
Badri Khadka)
Land Maize Right side
3 Krishna Sunar, Land Maize Right side
4 Chatra Bdr. Mahara land Maize Right side
5 Dilip Sunar Land Maize Right side
6 Fatta Bdr. Khada Land Maize Right side
7 Ram Bdr Tamang Land 22+ 100 to
22+ 600
Maize Right side
8 Amrit Bdr Tamang Land Maize Right side
9 Som Bdr Tamang Land Maize Right side
10 Mohan Bdr. Magar Land Maize Left side
11 Sushila Magar Land Maize Right side
12 Anita Shrestha Land Maize Right side
13 Padam Bdr. Khatri Land 26+400 to
26+ 90.50
Maize Right side
14 Yogesh Pandit Land Maize Right side
15 Krishna Khatri Land Maize Right side
16 Chet Bdr Thapa Land 33+050 to
33+ 900
Paddy Left side
17 Gopal Basnet Land Paddy Right side
18 Dhanraj Raut Land Paddy Left side
19 Chhatra Bdr. Basnet Land Paddy Right side
Source: Field Survey, 2016
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
44
5. IMPACTS OF RECONSTRUCTION PLAN IMPLEMENTATION
ON ENVIRONMENT
100. The impacts are examined on the basis of baseline condition of project area and
likely impacts during construction and operation phases. Such impacts have been identified
based on site observation, field survey & information obtained from the stakeholders and few
were identified from value judgment. The impacts are evaluated in terms of their magnitude,
extent and duration.
101. Adverse and beneficial impacts that are not identified or anticipated at this stage, if
latter discovered during the construction and operation stage of the project shall be duly
taken care of by the proponent.
5.1. Beneficial Impacts and Augmentation Measures
5.1.1. Construction Phase
Employment Opportunities
102. As estimated in the design report, during construction, the project will generate
391,580 persondays of temporary employment opportunities that constitutes 368,962
persondays of unskilled and 22,574 persondays of skilled workers including engineers and
technicians, 44 persondays of an operator. People will be required for excavation, spreading,
concrete works, gabion weaving, transportation, supervision and management during
construction of this project and local people based on their qualification and skill will have
additional income opportunities. The district rate for skilled labour, unskilled labour,
foreman/operator and heavy driver is NRs 670, 535, 670 and 600 per day respectively. The
envisaged impact will be direct, local, short term in nature, having high magnitude and hence
will be very significant.
Enhancement of Technical Skills
103. Through regular orientation during the course of involvement in the sub-project, the
workers will be able to develop additional knowledge and skill on building roads and
associated structures at climate/disaster resilient standard. These standards are sure to be
the part of minimum standard in every development activities to take place in the future.
These skills will encourage the locals in getting long term employment opportunities. The
envisaged impact will be indirect, local, long term in nature, having medium magnitude and
will be significant.
Increased Trade and Business Opportunities
104. During construction period, different types of commercial activities will come into
operation in order to meet the demand of construction crew. In general, the enterprises will
include food and tea shops, groceries, lodges and restaurants for serving construction
crews. The demand for local products such as pulses, milk, meat, vegetables, fruits etc. will
rise during the construction period which may provide added impetus for local production
and marketing. This will contribute to the local rural economy and may help reduce rural
poverty. Such benefits may contribute to enterprise development, which often continues to
entrench beyond construction period. The envisaged impact will be indirect, local, short term
in nature, having medium magnitude and will be significant.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
45
5.1.2. Operation Phase
Improved Accessibility and Reduced Travelling/Transportation Time and Cost
105. Reconstruction will improve the road condition and facilitate smooth operation of
vehicles all year round reducing the travel time and cost significantly. Good quality of road
and structures will give rise to number of public vehicles and competition thereby resulting
low transportation cost. Once the road is in smooth operation, people will have cheap and
easy access for various goods such as seeds, chemical fertilizer and technology leading to
increase in agricultural production and diversification as well as their market. The envisaged
impact will be direct, local and the long terms having high magnitude hence will be very
significant.
Promotion of Agro-enterprise
106. Road access is crucial for socio-economic recovery of the earthquake affected
communities. With the smooth operation of the road, a reliable access will be established
with the rural villages and people will have cheap and easy access for various goods such
as seeds, chemical fertilizer and technology leading to increase in agricultural production
and diversification as well as their market. This will promote agro-based (crops and
horticulture) and livestock based (dairy and meat) enterprises which have higher prospects
in the area. The envisaged impact will be indirect, regional and long term having high
magnitude, hence will be very significant.
Increase in Trade, Commerce and Development of Market centers
107. There is a possibility of increased economic opportunities and significant growth and
extension of the minor local markets along the road like in Haldebesi, Dhobi, Dhandebesi
and other places. Number of shops, their business volume and diversity in business type will
be accelerated with improved access. The farmers will be more interested to increase
agricultural production due to market accessibility. Similarly, there will be diversification in
occupational pattern of local people, who are till now mainly dependent on subsistence
farming. This will lessen pressure on local natural resources. There will be many non-farm
employment opportunities for the growing rural population especially for IPs and
occupational caste groups due to extension of market center and development of small
towns. The project will have indirect, long term, local and high benefits.
Access to Public Services and Basic Utilities
108. The upgrading of road will provide unobstructed and reliable access to different basic
facilities like education, health, market, etc to the people of eastern part of Ramechhap
District through sufficient means of transportation for daily conveyance. People of remote
villages of the western part of the district will have easy access to Manthali, Charikot and
other places for bigger health care facility, so is the case for markets centers. Smooth road
will ease the vehicular movement and immediate service of ambulance. The envisaged
impact upon education, health and others will be direct, long term, regional, of medium
magnitude, hence will be very significant.
Benefits from Increased Land Value
109. As per the discussion with local people, real estate business is rare and existing land
value is variable depending on proximity to existing and planned road. However, upgrading
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
46
of the road will lead to appreciation of land values particularly along road alignment due to
the reliable transportation facilities. The price is expected to be increased by two to three
folds depending on proximity to the road. This might be enhanced by increased crop
production, business and enterprise development in study area and increased land value
also enhances farmer's capability for banking transaction. This in turn will uplift the economic
condition of the local people. The envisaged impact will be indirect, local and long term
having medium magnitude, hence will be very significant.
Promotion of Tourism
110. Dhobi is the major checkpoint to reach Thalari (located in former Bijulikot VDC) which
could be developed as sunset view point. Likewise, there are ancient cemeteries which date
back to the Kirant Regime. Other things of attraction could be ancient tunnels bored for
copper mining. Similarly, Giddhedada (located in former Saipu VDC) can be developed as a
view point. This is the best location to view Pokali Waterfall of Okhaldhunga District.
Moreover, the indigenous Tamang community and their cultures can be another attraction of
cultural tourists. Increase in tourist flow along the road will bring additional economic
opportunity related with services required by national and foreign tourists.
Women Empowerment
111. All the people will be benefited from the reconstruction of the road. However, women
may be benefited more from improved access to the market centers and various service
providing agencies like health centers, banks, training institutions, women development
office etc. Frequency of visit to such agencies will increase awareness level and empower
them. The project will have indirect, significant, local and long-term impact.
Conservation and Environmental Awareness
112. The major objective of the project is to build back safer infrastructures that are able to
withstand future disasters and impacts of climate change. This requires general awareness
among the local people about conservation of the local environment. So, imparting
conservation awareness to the local people for safeguarding the reconstructed infrastructure
will enable them to conserve overall environment.
5.2. Adverse Impacts
5.2.1. Pre-construction Phase
Route Selection
113. Since, this is an existing road and proposed for rehabilitation, there is no new route
selection rather than designing geometrical improvements (as required) and widening of the
road formation to the specified width. Local conditions (structures, switchback, lay-byes,
mass balancing and safe disposal site for the excess excavated material, community utilities,
slopes, sensitive spots etc) were taken into consideration as to which side widening should
take place in order to minimize land acquisition from forest, cultivable lands, settlements and
cultural properties.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
47
Detail Survey and Design
114. The road design has followed the national rural road standards developed by
DoLIDAR. The works will be executed through Contractor selected through National
Competitive Bidding. Bio-engineering techniques will be applied for stabilization of slopes,
which is sustainable, environmental friendly and can be done by using local resources and
manpower. The survey team has selected the least valuable, least agriculturally productive
land for the lay-bys and improvement and took care to avoid the demolition of houses. These
changes have been designed and incorporated into the sub-project detail design.
Additionally, all provision proposed in the EMP of IEE document will be properly reflected in
the design.
Land and Property Acquisition, Compensation and Resettlement
115. Altogether 2.98 ha of private agricultural land (including settlement) along the road
corridor need to be acquired at for widening the road. Similarly, 24 private structures
belonging to 24 different owners will be affected wholly or partly by the road sub-project.
Land will also be required for temporary facilities like construction/labour camps, stockpiling
area, warehouse, etc.
5.2.2. Construction Phase
Socio-economic and Cultural Environment
Loss or Degradation of Farm Land and Productivity
116. The sup-project will permanently acquire 2.98 ha of agricultural land and convert it
into built-up area. Moreover, spoil on farm land will also affect the production of agricultural
crops. It is clear that the loss of crops from the land acquired by the project will have
adverse impact on the financial stability of the affected households who are dependent on
the agricultural productivity of their land. The impact is expected to be direct, high in
magnitude, local in extent and of long term in duration.
Impact on Social Services and Community Infrastructures
117. Construction activities are likely to affect the irrigation canals (kulo) down and across
the road alignment. A 4 inch polythene pipe meant for irrigation is likely to be affected at
chainage 33+050. These envisaged impacts of the project will be direct, site specific, short
term and of high magnitude hence will be very significant.
Occupational Health and Safety measures
118. During the construction phase, the construction workforces will be exposed to a
number of constructions related health risks and hazards. Fugitive emissions (harmful
smoke and gases from vehicles and equipment), noise and physical injury during
construction works may cause serious health impact. Unsafe drinking water, unhygienic
sanitary condition (i.e. lack of the latrine and sanitary facilities) in the construction camp can
increase the risk of additional and endemic diseases such as diarrhea, dysentery and
cholera. The envisaged impact will be direct, local and short term having high magnitude
hence will be very significant.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
48
Prevalence Communicable Diseases
119. Certain communicable diseases (flu, influenza, diarrheal disorder, dysentery, etc.)
might be transmitted by the outside workers. Workers sharing the same camp facility are at
higher risk of such diseases. Intimacy between workers and local people may spread
diseases like HIV/AIDS and STDs. The envisaged impact will be indirect, regional and long
term having medium magnitude, hence will be very significant.
Conflict between Locals and Outside Workers
120. Conflict may arise between the local people and outside labours during the project
construction. Presence of nonnative people may not be welcomed by the local residents.
Additionally, the construction workers may involve in gambling, alcoholism etc and
eventually may get into conflict among themselves or with the surrounding people. Similarly,
workforce from outside may not be familiar with the local culture of the project area and the
disagreement may take the form of argument ultimately creating conflict with local people.
The envisaged impact will be direct, local, short term, of low magnitude, hence will be
insignificant.
Gender Discrimination
121. As known from local consultation, discrepancy is already prevalent in the project area
in wage distribution among male and female labour forces. It is very likely that similar
treatment is continued while reimbursing the construction workforce involving the local. The
envisaged impact will be direct, local, short term, of medium magnitude, hence will be
significant.
Physical Environment
Change in Land Use Pattern
122. The existing present land use pattern of the project area will be changed due to the
implementation of the sub-project. 2.98 ha of additional private/agricultural land, 0.46 ha of
additional barren land and 0.45 ha of additional forest land will be permanently changed to
concrete and paved structure. The envisaged impact will be direct, site specific, long term, of
high magnitude, hence will be very significant.
Stockpiling, Spoil Disposal and Transportation of Material
123. The major construction materials are suitable materials, cement, sand and
aggregate. Stockpiling of the materials will create a major issue in the area as barren public
land are already lacking in the area. Hence, some environmental implications are envisaged
on air, water and land due to stockpiling and storage of the construction materials.
124. As per the design report of the sub-project, about 295,820.34 cu.m of spoil is
expected to be generated from cutting and excavation of road and drains. Some of the spoil
39,594.66 cu.m will be used in filling road. Surplus volume needs to be managed properly.
125. Although, limited quantity of material will be used for construction, and some of the
spoil will be used up, there may be some environmental implication of temporary storage of
these materials as well as their permanent disposal.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
49
Quarrying and Extraction of the River Bed Material
126. Suitable materials including fill materials, base material and sub-base and pavement
material will be required for road construction and most of them can be derived from the
excavated materials by crushing and refining. Besides these materials, boulders and river-
based aggregates and sand will be required for gravelling road, building retaining walls, RCC
culverts, side drains and drain covers and other road features. These materials have to be
sourced by quarrying from rocky areas along the road alignment and nearby rivers as listed
in the Table 4 in Chapter 2. The potential adverse impacts of quarrying are accelerated
erosion, landslides, disturbance in natural drainage patterns, water logging and water
pollution. Inappropriate operation of quarry sites and overexploitation can adversely impact
to adjoining area as well as the river. The envisaged impact will be direct, short term, site
specific, of high magnitude, hence will be very significant.
Impact on Air Quality (Air Pollution)
127. Diesel generator, machinery equipment, excavators, dozers and transportation
vehicles may introduce the fugitive & combustion emissions into atmosphere. As the project
site lies in dry location, dust emission can be expected to be high. Smoke & Dust will also
affect the road site, vegetation, local people residing along alignment and workers. The
envisaged direct impact due to air pollution will be, site specific and short terms and of
medium significance hence will be insignificant.
Impact on Water Quality (Water Pollution)
128. During construction, water bodies may be polluted by spoil and construction wastes,
open defecation in natural streams by construction workers. Furthermore, inappropriate use,
storage & application of chemicals (i.e. fuel, lubricants, oils and other materials) for the
construction and construction equipment may cause soil, surface and ground water pollution.
These envisaged impacts due to the water pollution will be direct, local and short term in
nature and having moderate magnitude, hence will be significant.
Noise Pollution
129. During the construction period, operation of machines, excavators, rock breakers,
power tiller, roller, transporting vehicles, trucks and other construction equipment will
increase the existing noise level causing noise pollution. The envisaged direct impact will be,
site specific, short term, local and of medium magnitude hence will be significant.
Impact due to Solid Waste Generation
130. Construction activities will produce solid wastes such as synthetic materials and
some forms of inorganic wastes, whereas, domestic activities will produce mainly food
wastes and excretory wastes. Improper dumping and management of these wastes can
result in unpleasant odors, deterioration of water quality in the river water and groundwater,
visual impacts that can cause health related hazards to the local inhabitants. The envisaged
impact will be direct, site specific, short term, of high magnitude, hence will be very
significant.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
50
Campsite Management
131. As the sub-project is being executed through construction contractor, camps will be
required to house construction labour. Sitting of camps may cause encroachment of forest,
agriculture land, and alteration of drainage, solid and liquid waste and waste water problems.
The construction crew will need services like water supply, electricity, telephone, provision
shop, health facilities, fuel, etc. which they will have to utilize from the existing facilities in the
area. This may create pressure on the existing common resources; especially water supply,
electricity and health service are already limited. Impact will be direct, of medium
significance, site specific and for short-term.
Biological Environment
Loss of Forest and Vegetation
132. Site clearance for construction works will affect some trees and the ground
vegetation including regeneration on both sides of the road. Altogether 0.45 ha of additional
forest land will be acquired for the sub-project and these forests have been handed over to
the eight (8) different Community Forest User Groups. Altogether 105 trees (dbh>10cm) of
species like Chilaune (Schima wallichii), Uttis (Alnus nepalensis) and Maledo (Macaranga
denticulata) need to be felled from 5 of the 8 Community Forests at Ch 24+100 to 24+250
(Jhateswori CF), Ch 26+000 to 26+200 (Bhringeshwar CF), Ch 30+010 to 31+100 (Poku
Salgharni CF (Saipu CF)), Ch 36+010-36+090 (Taruke Salleri CF), Ch 37+000-37+150
(Sipu Pakha CF) No protected tree needs to be cut by any means for sub-project
implementation (Refer Table 29).
133. Additionally, the construction crews may get to the nearby community forest for
firewood collection and they can also filch valuable floras. The envisaged impact of the
proposed construction works on vegetation will be direct or indirect, local, short term, of
medium significance, hence will be significant.
Table 29: Trees to be felled at different chainages
Chainages Name of Forest
Name of Species to be Felled
Scientific Name Number of Trees to be Felled
24+100 to 24+250
Jhateswari CF
Chilaune Schima wallichii 6 Uttis Alnus nepalensis 2
Sub-Total 8
26+000 to 26+200
Bhringeshwar CF
Chilaune Alnus nepalensis 5
Sub-Total 5
30+010 to 31+100
Poku Salgharni CF (Saipu CF)
Chilaune Schima wallichii 9
Uttis Alnus nepalensis 5
Maledo Macaranga denticulata 1
Sub-Total 15
36+010-36+090
Taruke Salleri CF
Chilaune Schima wallichii 20
Sal Shorea robusta 5
Bhot Dhangera Lagerstroemia parviflora 5
Sub-Total 30
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
51
Chainages Name of Forest
Name of Species to be Felled
Scientific Name Number of Trees to be Felled
37+000-37+150
Sipu Pakha CF
Chilaune Schima wallichii 30
Other 12
Uttish Alnus nepalensis 5
Sub-Total 47
Total 105
Source: Field Survey, 2016
Hunting and Poaching of Common, Rare, Endangered and Threatened Species of
Fauna
134. Though infrequently, animal and birds visit the area. Of the wildlife species reported,
10 are rare and protected (by CITES and IUCN Red List). Visiting birds and animals could
be disturbed due to construction activities. Workforce may involve in hunting and poaching
activities at nearby community forest during construction. This anticipated impact will be
indirect, local, short term, having medium magnitude, hence will be significant.
5.2.3. Adverse Impacts during Operation Phase
Socio-economic and Cultural Environment
Ribbon Settlement along the Project Alignment
135. There is a possibility of gathering of commercial activities and settlements from
hinterland to road alignment. There are chances of erecting new and haphazard settlements
along the improved road infrastructure to open marketing options and reap the increased
trade and business opportunities. This practice could disturb the traffic, promote
encroachment of the RoW (Right of Way), increase possibility of accidents, decline the
aesthetic value and reduce the overall capacity of road. If such practices are not controlled
by enforcing specific legal actions, the envisaged impact will be indirect, site specific, long
term, of high magnitude, hence will be very significant.
Road Safety Measures
136. Frequent movement of vehicles along the road increases the chance of accidents.
Inadequate provision of the road safety measures like lack of signals and lack of
enforcement of traffic rules during operation period may invite accidents. Road sections near
local market and schools are often crowded inviting chances of accidents. The envisaged
impact will be direct, site specific, long term, of high magnitude, hence will be very
significant.
Biological Aspects
Encroachment and Depletion of Forest
137. The forest resources depletion may occur due to ineffective drainage works,
inappropriate spoil disposal and construction practices. The development of market centers
may lead to encroachment of forest eventually exerting pressure on forest resources. To
meet the increasing needs of the forest products, illegal felling/cutting of poles and trees may
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
52
occur. Operation of road may increase in timber smuggling due to easy access and easy
transportation facilities. The impact will be indirect, moderate, local and long term in nature.
Physical Environment
Slope Stability and Drainage Management
138. The road alignment passes along a hilly terrain of the mid-hills. The existing slides
and slumps may be triggered during heavy rainfall situations. Sensitive areas for possible
road slope failure are at Ch 4+360 to 4+380, Ch 6+600 to 6+660, Ch 36+980 to 37+160, Ch
37+840 to 37+940 and Ch 38+340 to 38+480). Additionally, there is possibility of slope
instability caused by the opening of branch roads connecting village settlement with
RM/DCC funding. Likewise, inadequate maintenance of the road, blockage of drains and
human activities such as grazing and irrigation water may cause slides and slope failure.
The impact will be direct, high, local and long term in nature.
Impact due to Air, Water and Noise Pollution
139. Increased number of additional vehicles due to availability of easy road access can
cause air and noise pollution. The noise of horns from vehicles can cause problem to nearby
community. Washing of vehicles in natural streams may cause contamination in drinking
water sources. As this road falls under DCRN, the vehicular movement is not expected to be
very high, the overall impact of will be direct, low, site specific and long term in nature.
5.3. Climate Change Impacts
140. Climate change is an inevitable fact which needs to be considered for future
planning, construction and maintenance of roads especially in hilly and mountainous areas
which are more vulnerable to climate change than the plain areas. According to MoE/NAPA
(2010) vulnerability assessment, Ramechhap District is ranked very highly vulnerable
(second among 75 districts) based on overall vulnerability index. As evident from the
preliminary climate screening (Appendix 2b), Haldebesi – Dhobi – Dhandebesi road is
highly vulnerable to environmental and climate change attributes, such as change in
precipitation, higher rainfall intensity causing flood accelerated soil erosion and landslides.
141. Impacts of climate change on road infrastructure as screeded through Checklist for
Preliminary Climate Risk Screening will be as follows:
Due to the slope stability conditions on roadside at different chainages (chainages
stated above), the routing of the project is likely to be affected by extreme weather
events like heavy rainfall.
Road drainage could be of inadequate size or very frequently blocked causing damage
to the road calling for regular maintenance and cleaning of the drains.
Due to regular humid codition, the movement of heavy vehicles is likely to create
potholes on the road calling for regular maintenance and maintenance costs could be
considerably higher for the gravel roads.
Climate change could cause an increase in hydro-meteorological extreme events such
as storms, landslides, debris flows, that could greatly affect roads in mountain region
causing blockages.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
53
5.4. Cumulative Impact
142. Cumulative impact is the sum of project impacts and interaction impacts of a single
large scale project or multiple projects of similar or different nature. No other major projects
have been reported within the ZoI of the Haldebesi – Dhobi – Dhandebesi road. So the
assessment of cumulative impacts considers the impacts due to interaction of impacts of this
very project only. The following cumulative impacts may arise due to the reconstruction
activities in the surrounding of Haldebesi – Dhobi – Dhandebesi road sub-project in
Ramechhap district.
5.4.1. Beneficial Impacts
143. The availability of the employment in the neighbourhood will reduce the migration of
local people to other parts of the country, as well as to foreign countries for wage-based
labour. The amount of money that is earned in wages will directly enhance the operation of
various economic activities and enterprise development in a chained manner creating other
income generating activities. Similarly, the skill and knowledge acquired during road
construction will enhance employment opportunities. Such trained manpower can earn
livelihoods from similar project in future.
144. Reconstruction of road will enhance the access of people by reducing travel time and
costs as well as quick transportation of goods. Various farm-based enterprises, including a
wide range of agricultural and livestock products will also gain momentum as a result of
transportation facilities. Vegetables, fruits, cash crops, sale of farm, fruit and livestock
products will be increased in almost all the settlements along the road corridor. Similarly,
there will be diversification in occupational pattern of local people, who are till now mainly
dependent on subsistence farming. This will lessen pressure on local natural resources.
145. Due to an increase in employment opportunities, trade, business and agricultural
income, money will be channeled into the local economy. This will increase income level of
the individual household and the local community. It is possible that some money may be
spent by the individual for community development activities such as education, school,
health and sanitation services.
5.4.2. Adverse Impacts
146. Fresh cuts also invite landslides and erosion, particularly during monsoon. The
common likely problems from inappropriate disposal of spoils are gullying and erosion of
spoil tips especially when combined with unmanaged surface water runoff, damage to farm
lands and crops as well as property at downhill. The concentrated water from the road outlet
causes erosion and landslide eventually affecting the stability of the road.
147. This sub-project passes through community forest. There will be vegetation loss from
the forests during construction of the road. Increase in vehicular movement will further affect
the movements of wildlife. Total 105 trees need to be cut down from the three community
forests. Felling of trees, further change in land use due to potential trading opportunity and
increased number of vehicles will lead to high GHGs emission as well as low carbon
sequestration. Similarly change in land use might accelerate soil erosion.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
54
148. Loss of private properties, crops and trees from the land acquired by the project will
have adverse impact on the financial stability of the affected households. Increased
opportunities for trade and commerce along the roadside will attract people to build shops,
restaurants, stalls and hotels and may encroach RoW. Movement of vehicles in the road
may invite accidents.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
55
6. PROJECT ALTERNATIVES
149. The aim of the project is to reconstruct and rehabilitate existing road and revive the
transportation network for the promotion of fast and safe connectivity. The following
alternatives were considered to achieve the project’s objectives in environment friendly manner.
6.1. No Action Option
150. Haldebesi – Dhobi – Dhandebesi Road already exists and is serving the
southeastern part of Ramechhap District (Wards 2, 3, 4, 5 and 7 of Likhu Rural Municipality).
For the existing pavement condition and geometry of the road, travelling and transportation
has been difficult and time-consuming. Around 100 vehicles pass through the road daily
loading the local air with dusts in dry season and muddening the road during the rainy
season. If the sub-project is not implemented, the existing condition of the road will persist
and so is the hardship of the local people traveling through the road and living by the side of
the road, local people will be deprived from mainstream of development through improved
access and the direct and indirect benefit that implementation of this proposal would bring.
No action option will avoid the possible environmental implications but the hardship people
are currently facing outweighs the environmental cost of implementing the sub-project. So,
no project option is avoided.
6.2. Project Alternative
151. Road has no other alternatives for local access. The primary objective of the project
is to rehabilitate existing rural road and provide easy and all weather connectivity by
reconstructing and upgrading the existing infrastructure. As the road already exists but is
unable to provide full-fledged service for its poor surface condition and geometry, it is
indispensable to maintain and upgrade it to render it serviceable all weather. So the
reconstruction and upgrading has no other alternatives.
6.3. Alternative Alignment
152. By nature, it is a rehabilitation and reconstruction sub-project. The road already
exists, although in partly damaged condition due to land failure triggered by earthquake, and
vehicles plying in most sections limited during fair weather. It aims at improving the condition
of existing road by rehabilitating damaged sections, widening and gravelling it. Moreover, the
existing alignment does not cross major stream or river and passes through the major
settlements of northwestern part of Ramechhap. It is also assumed that the existing
alignment has been considered the best among all the alternatives considered during
design. Therefore, other alternative alignment has not been surveyed at this phase.
6.4. Alternative Design and Construction Approach
153. Alternative design based on lane/formation width was considered. Based on the
significance of the road as being an important road connecting major settlements of Likhu
RM and the projected traffic volume according to existing traffic volume and also considering
the Nepal Rural Road Standard (NRRS, 2012), the formation width of 6.25 m was
considered.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
56
154. For the exigency of the infrastructure, it will be reconstructed by employing a
construction contractor with deployment of necessary equipments for timely delivery of the
work. Nonetheless, the contractor will be made to utilize local people as construction
workforce and respect the environmental sensitivity of such hilly terrain.
6.5. Alternative Schedule and Process
155. A construction schedule (i.e. 15 months) has been proposed taking the climatic and
drainage condition of the area into consideration. During the rainy season, construction work
is stopped to allow the natural compaction of the road. Collection of sand and aggregates
from the river bed during dry period will minimize the impacts on river water quality &
downstream aquatic ecology and hence the schedule of construction is proposed
accordingly.
6.6. Alternative Resources
156. The physical resource requirements include stone for gabions, dry masonry walls
and stone pitching. Stones are available in nearby areas of various sections of the road,
whereas fine aggregates, sand will be sourced from Tamakhoshi River. The pavement
construction, earthwork, construction of simple structures such as side drains, gabion walls,
bioengineering works, etc will be carried out manually. The contractor in his discretion will
use necessary equipments and human resources for timely delivery of the work.
6.7. No Forest Option
157. While selecting the alignment, no forest option was also considered, under which the
project would have no impact on the community forest, However, as it is simple
reconstruction of the existing road alignment, the widening of the road to prescribed
standard is expected to affect a very narrow strip of forest at few shorter sections.
Realignment of the road to avoid forest area is expected to affect larger parcel of private
land that increase compensation and resettlement cost. Moreover, even if the road is
realigned, it is sure to encounter some forest along the way. Additional forest to be affected
by the project is only about 0.45 ha.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
57
7. ENVIRONMENTAL IMPACTS MITIGATION AND MINIMIZATION
TECHNIQUES
158. For the impacts, practical mitigation measures (or actions) have been proposed to
mitigate the possible environmental and social impacts that may result due to project
implementation (construction and operation). The proponent of the project has prime
responsibility in carrying out the indicated mitigation measures. Keeping in mind the current
political and social situation, several of these require sharing of responsibilities with public
authorities and local stakeholders.
159. Adverse and beneficial impacts that are not identified or anticipated at this stage, if
latter discovered during the construction and operation stage of the project shall be duly
taken care of by the proponent.
7.1. Augmentation Measures
7.1.1. Beneficial Impacts during Construction Phase
Employment Opportunities
160. No augmentation measure has been suggested for this benefit. However, the
contractor will be encouraged to give priority to local and marginalized people including
women in construction works as per their skills. Women will be employed in compensatory
tree plantation for afforestation and slope protection works through bio-engineering.
Enhancement of Technical Skills
161. Workers will acquire additional knowledge through training in material handling,
occupational safety, general environment, health and social precautionary measures. The
workers will be formally and informally oriented about the specific requirements for climate
and disaster resilience.
Increased Trade and Business Opportunities
162. The project will give due priority to the local markets and local products.
7.1.2. Beneficial Impacts during Operation Phase
Improved Accessibility and Reduced Travelling/Transportation Time and Cost
163. Necessary arrangement will be made for regular inspection and maintenance of the
road and its accessorial features with the help of other stakeholders. Bioengineering
operation will be continued for the sustainability of the road.
Promotion of Agro-enterprise
164. No augmentation measure has been suggested for this benefit to be within the scope
of this sub-project.
Increase in Trade, Commerce and Development of Market centers
165. DCC/Likhu RM will manage planned growth with required infrastructure facilities for
healthy and hygienic environment in the market areas.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
58
Access to Public Services and Basic Utilities
166. Timely implementation of the sub-project and regular maintenance of the
infrastructure will generate the service in time and sustain the service.
Benefits from Increased Land Value
167. The local people will be made aware of the fact that high value land is easily
acceptable to the banks and microfinance institutions as a guarantee to provide loans. Local
people can start their own business by mortgaging their land.
Promotion of Tourism
168. Awareness raising programs will be conducted in collaboration with concerned
stakeholders to support the promotion of tourism activities and infrastructures development
of lodges, hotels, restaurants and preferably home stays. People will be oriented about
village tourism with home stay provisions for the tourists especially in the homes of highly
marginalized Tamang community. A three days homestay management training will be
provided to 15 interested people from the project area with a cost of 150,000.00.
Women Empowerment
169. Women will be further empowered through awareness and training programs. The
awareness programs will be related to health and sanitation and training program will be
related to agriculture and livestock raising. A cost of NRs 100,000.00 has been allocated for
empowering women.
Conservation and Environmental Awareness
170. Environmental awareness programmes will be conducted in the project area to aware
the local people on value of local natural resources and necessity of conservation of
environment. These programs will consist of general training conducted at field level by local
conservationists and subject experts through lecture, documentary showcasing and
interaction. Total cost of NRs 250,000.00 has been estimated for conducting environmental
awareness programs.
7.2. Mitigation Measures
7.2.1. Pre-construction Phase
171. The mitigation measures adopted during design or pre-construction phases are
preventive in nature with two basic objectives.
Avoid costly corrective and/or compensatory measures.
Increase awareness among the stakeholders for the environmental management.
Route Selection
172. Since, this is an existing road and proposed for rehabilitation, there is no new route
selection rather than designing geometrical improvements (as required) and widening of the
road formation to the specified width. Local conditions (structures, switchback, lay-byes,
mass balancing and safe disposal site for the excess excavated material, community utilities,
slopes, sensitive spots etc) were taken into consideration as to which side widening should
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
59
take place in order to minimize land acquisition from forest, cultivable lands, settlements and
cultural properties.
Detail Survey and Design
173. The road design has followed the national rural road standards developed by
DoLIDAR. The works will be executed through Contractor selected through National
Competitive Bidding. Bio-engineering techniques will be applied for stabilization of slopes,
which is sustainable, environmental friendly and can be done by using local resources and
manpower. The survey team has selected the least valuable, least agriculturally productive
land for the lay-bys and improvement and took care to avoid the demolition of houses. These
changes have been designed and incorporated into the sub-project detail design.
Additionally, all provision proposed in the EMP of IEE document will be properly reflected in
the design.
Land and Property Acquisition, Compensation and Resettlement
174. Mitigation for land and property acquisition includes compensation at prevailing
market rate. The following measures will be followed:
Compensation will be provided to the land owners on prevailing market rate. The total
compensation cost for the land to be acquired based on the rate of Land Revenue
Office (LRO) Ramechhap is NRs 2,98,777.28. The time given by the affected
household during deed transfer and other purpose will be compensated. The cost of
deed transfer assistance and deed transfer fees has been estimated to be 17,100.00.
The private structures that will be affected during reconstruction of the road will be
compensated at replacement cost. The individual owners will be provided the cost. The
total physical compensation amount of the affected structures is NRs 1,440,000.00.
Compensation will be provided for the standing crop in the affected private plots. The
cost to be provided is based on the rate of paddy (since it is the highest value crop) in
the local market considering the average productivity as 1.713 kg of rice per square
meter and has been estimated to be NRs 65,094.
Project affected families will be imparted income generation and livelihood
improvement generation training by residential training. In total, 10% of the affected
people are interested to join the program. The estimated cost for conducting the
training program is Nrs 800,000.00.
Private land necessary for sitting temporary structures will be hired from interested
owner at prevailing market rate.
After completion of the work, the camps and facilities will be dismantled and
rehabilitated and returned to the owner.
7.2.2. Construction Phase
Socio-economic and Cultural Environment
Loss or Degradation of Farm Land and Productivity
175. Mitigation measures will be as follows:
Compensation will be provided for loss of property as mentioned in section 7.2.1,
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
60
Compensation will also be provided for loss of standing crops and temporary use of
agriculture land,
Plantation of trees of local variety like Harro, Barro, Siris, Mauwa, Chilaune and other
ornamental trees along the both sides of road to act as dust and noise barrier. A cost
of NRs 200,000.00 has been allocated for roadside plantation.
Income restoration and rehabilitation program will be carried out whereby the members
of affected household will undergo residential training on income generating activities.
The tentative cost of the training program is NRs 800,000.00.
Impact on Social Services and Community Infrastructures
176. The following mitigation measures will be adopted:
The contractor will be responsible for reconstruction and rehabilitation of damages due
to their activities; any damage to existing road in project location, like formation of
ditches, will be controlled and rehabilitated.
Altogether 34 irrigation crossings have been proposed along the road.
The construction activities will be scheduled during off-season to avoid the impact of
disruption of irrigation facilities.
Occupational Health and Safety measures
177. The contractor will maintain occupational health and safety arrangement and strictly
enforce the safety measures.
Construction workers will be prior informed about job hazards, emergency procedures
and any other relevant safety measures.
Personal Protective Equipment (PPE) such as helmets, boots, gloves, safety belts,
safety glasses and masks will be provided to the workers working in the construction
sites.
Contractor will arrange the First Aid Kit Box and standby medicine for workforce during
working period and emergency situations.
In case of serious injury and accidents, the injured will be run to the nearest hospital
with the necessary diagnosis and treatment facilities.
Warning signs, posts, barriers and guards will be installed to restrict access of
unauthorized persons to construction sites.
Only authorized person will be allowed to operate heavy machinery and equipment.
Temporary drinking water supply and latrine pit will be established at site.
Dust control will be done in the construction areas by sprinkling water.
Vehicles and equipment will be maintained in proper condition so that they produce
less noise.
Group accidental insurance will be done for the workers.
178. The cost of occupational health and safety measures has been incorporated in the
civil cost of the sub-project.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
61
Prevalence of Communicable Diseases
179. Sanitary condition will be maintained in the construction camp by arranging toilets
and water supply. Workers will be encouraged to keep their camps clean and tidy. Workers
will be made aware through awareness program about STDs and the preventive measures.
Conflict between Locals and Outside Workers
180. Construction workers from outside the project area will be well-informed about the
general norms and values of society. The construction workforce will be instructed to respect
local people, especially the female members and observe/follow the local culture and
tradition. Workforce will be discouraged to involve in activities like gambling and alcoholism.
Local people will be informed about project activities, requirements and time schedules.
Local people will be given maximum priority in employment.
Gender Discrimination
181. Project will establish agreement with contractors to consider male and female equally
for wage distribution for works of similar nature. Male workers will be instructed to respect
their female counterparts.
Physical Environment
Change in Land Use Pattern
182. There will be no mitigation measures for the permanent loss of agricultural, forest
land. However, following mitigation measures will be adopted to compensate the loss of land
into built up area:
Roadside plantation of trees will be done to increase greenery in the area. Local plants
like Harro, Barro, Simal, Siris, Chilaune, Bains, Katush, Lakuri, Mauwa, Bajh, Guras,
Paiyu, etc and other suitable ornamental plants will be planted along the roadside.
During re-vegetation, local species identified during the survey will be used.
Agricultural extension services will be improved to compensate loss of production.
Stockpiling, Spoil Disposal and Transportation of Material
183. Although, limited quantity of material will be used for construction, and some of the
spoil will be used up, there may be some environmental implication of temporary storage of
these materials and can be minimized by adopting following measures:
Wherever possible, surplus spoil will be used to fill eroded gullies, quarries and
depressed areas etc. Suitable sites have been listed in Table 7 of Chapter 2.
Top soil will be stored and utilized in farm land
Remaining excess spoils will be disposed in specified tipping sites in a controlled
manner and the tipping sites will be covered by vegetation through bio-engineering
techniques after surplus material is tipped.
Spoils will not be disposed on fragile slopes, farmland, marshy land, dense forest
areas, natural drainage path, canals and other infrastructures. (Although spoil disposal
and tipping areas have been proposed within the boundary of community forests, these
areas have very sparse stands of trees.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
62
After the disposal, the site will be provided with proper drainage, vegetation and
adequate protection against erosion.
Necessary toe walls and retaining walls will be provided to protect the disposal of soil.
Material will be stockpiled at fallow land and covered,
Proper drainage will be arranged around the stockpile area,
Stockpiling of the cement and other materials in shaded structures within the
construction camp will be made.
Quarrying and Extraction of the River Bed Material
184. The following mitigation measures will be adopted to address the issues related to
quarrying:
Sediments derived from the excavation will be used for backfilling.
Coarse aggregates and sand will be obtained from designated and approved quarries
and borrow areas that have already taken environmental clearances (if such sites are
available). No such sites having environmental clearances were available. Possible
quarry sites have been identified in Table 3 of Chapter 2. These sites will be used with
due consideration to local environmental condition.
Unstable sites, erosion prone areas, dense forest areas, settlements and fertile farm
land will be avoided for quarry operation.
Stones and boulders will be collected from the environmentally suitable and legally
recognized quarry sites.
After the extraction is completed, the quarry site will be rehabilitated to suit the local
landscape.
The materials to be transported will be covered by plastic sheets. Arrangements will be
made in trippers to arrest water dripping from the materials.
Impact on Air Quality (Air Pollution)
185. To mitigate the air pollution and its effect the following measures will be carried out:
Construction equipment and vehicles will be regularly examined and maintained in
proper condition.
Water will be sprinkled at major settlements along the road at least two times a day
during peak construction.
Construction materials will be properly covered during conveyance.
Open burning of garbage will be strictly prohibited.
Impact on Water Quality (Water Pollution)
186. The impacts can be mitigated by:
Ensuring safe storage and wise use of chemicals to prevent spillage;
Avoiding the disposal of excavated materials in or near water bodies;
Discouraging open urination and defecation and construction of toilets in camp sites.
Noise Pollution
187. The following mitigation measures will be adopted to minimize the noise pollution:
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
63
Construction equipment will be maintained in proper condition by applying grease and
lubricants.
Sound producing equipment will be preferred to use only in day time.
Earplug will be provided to the worker involved in equipment operations.
Impact due to Solid Waste Generation
188. The solid waste generated from the construction/labor camp will be segregated at
source and degradable waste will be used for composting. All the camp wastes and
construction wastes will be placed in the designated waste collection pits away from the
water path. The separate storage areas will be established for all punctured containers
(drums, carboys, flasks etc) and will be processed for selling to scavengers. Similarly, the
offsite activities of the workforce that are potential to cause pollution of surface and
subsurface waters will be prohibited.
Campsite Management
189. Use of local labours will avoid the chance of campsite management. In case labours
have to be brought from outside, they will be housed in local houses brought in rent instead
of camp. If it is indispensable to establish a camp, they will be sited away from productive
lands and forest areas. The following mitigation measures will be adopted to mitigate the
impact of camp establishment:
Respectable compensation will be paid for using private farm or lands for storage or
camp. The camp and storage sites will be properly cleaned, reinstated and handed
over to the respective owner followed by receiving necessary clearance from the
owner.
Toilet, water and other basic facilities will be provided to workers. The contractor will
manage the utilities like communication, lighting and cooking energy, drinking water
supply etc within the camp so as to avoid the pressure on local services. The
responsibility of looking after the amenities of the workers is the responsibility of the
contractor.
Labor camp will have room with proper ventilation and natural light, safe drinkable
water, mosquito net, sanitary facility, and solid waste management.
Construction material will be properly stored.
Appropriate camp sites have been identified at Ch 4+100, Ch 13+500, Ch 19+900,
26+300 and Ch 36+900.
Biological Environment
Loss of Forest and Vegetation
190. The following measures will be adopted to address this impact:
For construction crews at camp, contractor will provide kerosene or LPG cylinder for
cooking and heating for avoiding firewood collection. The respective provisions will be
set in contract document.
Similarly, restriction will be put on construction workers to enter into the local forest
areas for firewood and NTFP collection and the provision will be enforced as
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
64
punishable offence. They will be made aware about importance of conservation and
restricted activities.
191. The following activities will be strictly followed to cut trees from the forest area during
road reconstruction:
Forest clearance approval will be obtained from the MoFSC.
Forest site clearance for construction will be limited to minimum width of road.
No tree or vegetation will be cut unless absolutely necessary.
Project will hand over the felled trees to CFUGs.
192. According to the Working Procedure to Use National Forest area for National
Priority Projects, 2074 B.S. of GoN, the sub-project has to carry out plantation (with
protection for five years) or pay for the plantation and protection cost to the District Forest
Office. The trees to be felled from different forests and compensatory plan have been
described in Appendix 8. In total, 105 trees need to be cut down from the five (5) of the
eight (8) community forests along the road. So, in total 2,625 seedlings have to be planted
for compensatory plantation with estimated cost of NRs 412,518.75 considering the
plantation of each plant as calculated in the table given in Appendix 8a and Appendix 8b.
This cost will be provided to CFUGs through DFO in two installments. Location and type of
species for the plantation will be selected by the CFUGs/DFO. However, emphasis will be
given to local, multiple use, rare, endangered and protected species. The samples of
agreement between the proponent, DFO and concerned CFUGs for compensatory
plantation with disbursement schedule are presented for individual CF in Appendix 8c and
the plantation plan is presented in Table 30 and Appendix 8d.
Table 30: Trees to be Felled and Compensatory Plantation Requirement
Name of Forest Number of
Trees
Compensatory Plantation Cost of Plantation
Jhateswari CF 8 200 31,430.00
Brhingeshwar CF 5 125 19,643.75
Poku Salgharni CF
(Saipu CF)
15 375 58,931.25
Taruke Salleri CF 30 750 117,862.50
Sipu Pakha CF 47 1,175 184,651.25
Total of CF 105 2,625 412,518.75 Source: Field Survey, 2016
Hunting and Poaching of Common, Rare, Endangered and Threatened Species of
Fauna
193. Hunting and poaching by the construction crew will be strictly prohibited. The
construction activity will be managed so as to minimize disturbance to wildlife; speed limit
will be enforced for transporting vehicles. The impact can be minimized by employing the
local labours. Similarly, restriction will be put on construction workers from entering into the
local forest areas and the provision will be enforced as punishable offense. In addition, restriction will be put on the use of wildlife meat in the construction camps. Hoarding boards
will be placed at sensitive sites (Ch 0+080, 1+520, 16+800, 24+100, 26+000, 30+100,
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
65
36+010 and 37+150 where the road passes along the forest areas) at a cost of NRs 200000
to aware workers and locals alike on importance of wildlife and conservation.
7.2.3. Adverse Impacts during Operation Phase
Socio-economic and Cultural Environment
Ribbon Settlement along the Project Alignment
194. Respective DCC and Likhu Rural Municipality will regulate the possible development
along the road access so as to minimize the likely road accident. Road safety signals or
signposts will be installed at places. Road side plantations of trees will be done in the RoW
to prevent possible encroachment.
Road Safety Measures
195. Appropriate design will be adopted focusing required road safety measures.
Required delegators, safety signs will be used as appropriate along road. Permanent traffic
signposts will be installed along the road corridor. Signposts will be installed at major
markets, schools and settlements to inform about drivers to control the speed of the vehicles
to ward off associated accidents at temple and school areas. Road safety measures will also
be adopted following 3-Es (i.e. Engineering, Enforcement and Education). The road will be
repaired and maintained regularly. The DCC/Rural Municipality will allocate budget for the
regular inspection and the maintenance of road.
Biological Aspects
Encroachment and Depletion of Forest
196. These impacts will be mitigated through awareness raising programmes to educate
local people and providing support to locals for the conservation of forests.
Physical Environment
Slope Stability and Drainage Management
197. The following mitigation measures will be adopted:
Bio-engineering works will be carried out to control the slides and retain the slopes.
Rill and gully formations will be regularly monitored and immediately fixed at critical
areas.
Repair and maintenance of the slope protection measures and drainage works.
Minor landslide and mass wasting will be immediately cleared and slope restored with
appropriate technology (bioengineering).
Soil conservation will be promoted in the RoW and vulnerable areas beyond the road
alignment.
CFUGs will be promoted to conserve and manage their CFs property.
Causeways (11), RCC Slab Culverts (1) and Pipe Culverts (67) will be placed to
maintain cross drainage at places and allow passage of runoff. All these activities have
already been considered in BoQ so no extra cost is allocated.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
66
Impact due to Air, Water and Noise Pollution
Following mitigation measures will be adopted:
Signboards restricting the use of horns will be erected near health posts, schools and
settlements.
Plantation will be done near the settlement around school and health post to act as
dust and noise barrier.
Vehicle washing in natural streams will be discouraged.
7.3. Climate Change Impacts
198. Following climate change adaptation measures will be considered during the
reconstruction and operation of the road:
Likely local effects of climate change will be assessed through observation and regular
monitoring of drainage system, erosion etc.
Adequate and timely maintenance and retention of the slides as soon as they appear.
Awareness raising activities will be conducted about climate change issues and
adaptation and mitigation measures.
No tree or vegetation will be removed unless absolutely necessary to reduce
deforestation and compensatory plantation will be done to cut carbon per capita
emissions.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
67
8. LEGAL FRAMEWORK AND REGULATORY REQUIREMENTS
FOR THE PROJECT
199. GoN has adopted various policies, acts, rules, regulations and guidelines to ensure
the integration of the development and conservation of environment. The policies and
legislative provisions of Nepal that have a direct relevance to proposed project are given in
Table 31. These laws and policies provisions have been duly followed in the IEE process
and proposed mitigation measures.
Table 31: Review of Relevant Acts, Rules, Regulations and Guidelines
A Constitution
The Constitution of Nepal: It has guaranteed every person the right to live in a clean
environment as a fundamental right. As per the constitution, it is also a matter of State
policy to adopt appropriate measures to abolish or mitigate existing or possible adverse
environmental impacts on the nature, environment or biological diversity.
B Plans and Policies
National Reconstruction and Rehabilitation Policy, 2072 B.S. (2016 A.D.): It has
identified restoration and improvement of access to service and improve environmental
resilience as one of its strategic recovery objectives.
Forest Policy, 2071 B.S. (2015 A.D.): Plantation is mandatory for environmental friendly
physical infrastructure development along settlement area, road and irrigation canal.
Land Acquisition, Resettlement and Rehabilitation Policy, 2071 B.S (2014 A.D.):
This policy has been formulated to strengthen socioeconomic conidition of project
affected families with the provision of necessary land acquisition, justifiable
compensation, appropriate resettlement and rehabilitation for the public welfare and
implementation of infrastructure development projects.
Three Years Interim Plan, 2070/71-2072/73 B.S. (2013/14-2015/16 A.D.): Identified the
importance of road sector in promoting national unification, socio-economic development
and regional balance contributing to overall development of the country and also in
promoting the access to service and facilities. It aims to achieve sustainable, broad-
based, inclusive economic growth. The plan also addresses climate change adaptation
and mitigation and overall environmental protection.
ADB Safeguard Policy Statement, 2009 A.D.: ADB’s Safeguard Policy Framework consists of three operational policies on the Environment, Indigenous people and
Involuntary resettlement. It requires that (i) impacts are identified and assessed early in
the project cycle, (ii) plans to avoid, minimize, mitigate or compensate for the potential
adverse impacts are developed and implemented and (iii) affected people are informed
and consulted during project preparation and implementation.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
68
20 Year Road Plan, 2059 –2079 B.S. (2002-2022 A.D.): With main objectives of
development of Strategic Road Networks (SRN), the implementation strategies include
all weather road connection to the District Headquarters (DHQ) and provision of road
linkages from the DHQ to the adjacent road network of the neighboring districts and
countries
Policy Document, Environmental Assessment in the Road Sector of Nepal, 2056
B.S. (2000 A.D.): It proposes to adopt measures to improve the way of life of the
affected people and safeguard natural surroundings. In case damage is inevitable
environmental assessment should find ways of reducing or compensating for such
damage. It suggested five types of environmental assessment activities like Screening,
IEE,EIA and Monitoring.
National Biodiversity Strategy and Action Plan, 2014-2020 FY: It is prepared to
provide guiding framework for the management of Nepal’s biodiversity. It has focused on national needs of biodiversity management and conservation, fulfillment of the
international obligations, sustainable use of its components and equitable sharing of
benefits accrued from conservation and utilization of genetic resources. It has a long
term (i.e. 35 years) vision, and includes specific short term (up to 2020) strategies and
priorities for action.
C Act
Act Relating to Reconstruction of the Earthquake Affected Structures 2072 B.S
(2015 A.D.): This act provides for the creation of the NRA for a period of five years
(which may be extended) and defines its functions, duties and powers. It has mandated
NRA for leading and managing the earthquake recovery and reconstruction in Nepal. It
has delegated the NRA the authority to frame rules (Section 30), may make and enforce
necessary guidelines or procedures in order to conduct its business (Section 31).
Solid Waste Management Act, 2068 B.S. (2011 A.D.): It outlines the duties of local
government to take action to control haphazard waste generation, disposal or collection
and has provisions for various punitive measures against those engaged in activities
detrimental to the intentions of the Act.
Child Labour (Prohibition and Regulation) Act, 2057 B.S. (2000 A.D.): Engaging
children including those who has not attained the age of 14 in risky activities against
his/her will by any means is prohibited. In case any enterprise has to engage a child in
works, an approval has to be obtained from concerned body.
Local Self Governance Act 2055 B.S. (1999 A.D.): Empowers the local bodies for the
conservation of soil, forest and other natural resources and implements environmental
conservation activities
Forest Act, 2049 B.S. (1993 A.D.): Requires decision makers to take account of all
forest values, including environmental services and biodiversity, not just the production
of timber and other commodities.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
69
Water Resources Act, 2049 B.S. (1992 A.D.): It has legal arrangements for
determining beneficial uses of water resources, preventing environment and other
hazardous effects thereof and also keeping water resources free from pollution. It has
clearly mentioned that no one shall pollute water resource by way of using or putting any
litter, industrial wastes, poison, chemical or toxicant to the effect that the pollution
tolerance limit of the water resource as prescribed.
The Labor Act, 2048 B.S. (1992 A.D.): Regulates the working environment, deals with
occupational health and safety.
Soil and Watershed Conservation Act (SWCA), 2039 B.S. (1982 A.D.); It empowers
GoN to declare any area of Nepal as a conserved watershed area, specifying the
borders thereof. The Watershed Conservation Officer (WCO) has the authority to
implement protective infrastructure, vegetation program and regulate agricultural
practices pertinent to soil and watershed conservation. It empowers WCO to prohibit the
commission of any acts that may cause soil-erosion or soil cutting in a land where any of
the acts has been done
Public Roads Act, 2031 B.S. (1974 A.D.): Act mandates requirement of permission
from the DoR to carry out activities within the limits of the road boundaries and also
provision of notifying the DoR by local governmental offices prior to the start of activities
in the limits of the public roads.
National Park and Wildlife Conservation Act, 2029 B.S. (1972 A.D.): This act
provides protection to 27 species of mammals, 9 species of birds and three species of
reptiles.
D Rules and Regulations
Rule Relating to Reconstruction of the Earthquake Affected Structures 2072 B.S.
(2016 A.D): It provides the basis for prioritization of reconstruction. More importantly, it
defines functions, duties and rights of the Chief Executive Officer and Secretary of NRA
and District Coordination Committee.
Local Self Governance Rules 2056 B.S. (2000 A.D.): It provides procedural guidelines
for implementation of the Local Self Governance Act.
Forest Rules, 2051 B.S. (1995 A.D.): It elaborates legal measures for the conservation
of forests and wildlife and provides procedural guidelines for implementation of the
Forest Act. It stipulates that in case the execution of any project having national priority
in any forest area causes any loss or harm to any local individual or community, the
proponent of the project itself shall bear the amount of compensation to be paid.
E Work Procedures, Guidelines, Standards and others
Local Body Restructuring Notice, MoFALD, GON, 2017 A.D: Declaration of the
name, number, boundary, ward’s boundary of 744 rural municipality and municipality with 481 rural municipalities, 246 municipalities, 13 sub-metropolitan cities, 4
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
70
metropolitan cities and dissolve of VDC/DDC.
Work Procedure Related with Environmental Impact Assessment for Rehabilitation
of Earthquake Affected Structures 2072 B.S. (2016 A.D.) and First Amendment,
2073 B.S. (2016 A.D.): These provide procedural guidelines for undertaking
reconstruction and rehabilitation projects. These include a comprehensive suite of
procedures for different activities like environmental impact assessment, land
acquisition, and public procurement for reconstruction projects (2072 B.S.) and
grievance management (2073 B.S.). It determines the format of IEE and EIA.
The first amendment has revised the threshold for projects to undergo IEE or EIA. It
prescribes (under Clause 2 of Schedule 1) that upgrading, rehabilitation and
reconstruction and new construction of district, urban and rural road should follow IEE
study and approval.
Working Procedure to Use National Forest area for National Priority Projects, 2074
B.S. (2017 A.D.): Following are the main features:
EMP/IEE/EIA study is mandatory for obtaining forestry clearance.
Alternative analysis has to be done during feasibility study for avoiding forest
area or if not having minimal loss of vegetation.
Concerned Ministry has to obtain concurrence from Ministry of Forest and Soil
Conservation before approving IEE/EIA
Provision of compensatory plantation (with protection for five years) at the ratio of
1:25 plants by the project or provide plantation and protection cost to concerned
DFO.
ADB Environmental Assessment and Review Framework (EARF), 2015 A.D. for
EEAP: It elaborates environmental legal requirements and procedures according to the
Government of Nepal and Safeguard Policy Statement, 2009 of ADB and guides the
preparation of environmental assessments and environmental management plans.
ADB Resettlement Framework (RF), 2015 A.D. for EEAP: It guides the preparation of
resettlement plans by elaborating legal and procedural guidelines according to GoN and
ADP SPS.
Batabaran Parichhyan - Resource Booklet - 2070 B.S. (2013): It provides guidance
for local body to prepare environmental assessment reports of different projects;
construction materials extraction and local roads, on their own.
Environment Friendly Local Governance Framework (EFLG) 2070 B.S (2013 A.D.):
This framework is prepared to promote environmental conservation through local
institutions to materialize environment friendly local development concept. There are
different level of environment friendly indicators like basic, advanced and special
indicators at household, tole/settlement, ward, VDC, Municipality and District level. Main
objectives of this framework are as follows:
Mainstreaming the environment, climate change, disaster management issues in
local development planning process.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
71
Making environment friendly local governance mechanism.
Strengthening basic level to make environment friendly sustainable development.
Promoting coordination and cooperation within environment and development.
Strengthening local organization to enhance local ownership for the sustainable
development of environment.
Nepal Rural Road Standard, 2012 A.D.: Sets the classification and geometric design
standards for the Local Road Network to be followed by all those involved in the
development of the network, including Users, User Committees, VDCs, DDCs, DTOs,
DoLIDAR and its development partners.
National Adaptation Program of Action, 2068 B.S. (2010 A.D.): The NAPA has been
instrumental in mainstreaming climate change in development planning. The NAPA has
developed a framework for adaptation programme, and has identified key adaptation
needs, existing adaptation practices and options for developed projects including
infrastructure.
Reference Manual for Environmental and Social Aspects of Integrated Road
Development, 2060 B.S (2003 A.D): Suggests stepwise process of addressing
environmental and social issues alongside the technical, financial and other issues.
Batabaraniya Nirdesika (Nepali), 2057 B.S. (2000 A.D.): Focuses in the practical
implementation of small rural infrastructures through the minimization of environmental
impacts and outlines simple methods of environmental management in the different
phases of the project cycle. More emphasis is given to prevention rather than cure.
APPROACH for the Development of Agricultural and Rural Roads, 2055 B.S. (1999
A.D.): Emphasizes labor based technology and environmental friendly, local resource
oriented construction methods to be incorporated actively in rural infrastructure process.
Green Roads in Nepal, Best Practices Report – An Innovative Approach for Rural
Infrastructure Development in the Himalayas and Other Mountainous Regions.
GIZ, 1999 A.D.: It focuses on participatory, labor based and environment friendly
technology with proper alignment selection, mass balancing, proper water management,
bioengineering and phased construction.
Environmental Management Guidelines, Geo Environmental and Social Unit, DoR,
2054 B.S. (1997 A.D.): It consists of environmental mitigation measures to be
incorporated into DoR projects, procedures for public participation, and socio-economic
consideration. The Environmental Mitigation Measures are broken down into 12
categories or activities and a method for implementation is given for each mitigation
measures including implementation strategies. These environmental mitigation
measures should be used in conjunction with good engineering design, construction and
operation practices. It also suggests considering the various socio-economic issues like
land acquisition and compensation, economic impacts and cultural heritage.
Community forest development program guideline (third revision 2071 B.S.):
Sustainable and scientific management of forest by the local users including
environment services and facilities for the mitigation of natural calamities, wildlifes nad
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
72
forest fire
National Environmental Impact Assessment Guidelines, 2050 B.S. (1993 A.D.):
Provides guidance to project proponent on integrating environmental mitigation
measures, particularly on the management of quarries, borrow pits and stockpiling of
materials, operation of the work camps, earthworks and slope stabilization, location of
stone crushing plants etc.
F International Conventions
Convention on International Trade in Endangered Species of Wild Fauna and Flora
(CITES), 2053 B.S., amended, 2059 B.S. (1973 A.D., amended 1979 A.D.): It regulates
international trade in endangered wild flora and fauna with the aim of reducing or
eliminating trade in species whose numbers or conditions suggest that further removal
from their natural habitat would lead to their extinction. It urges parties not to allow trade
in specimen of species included in the CITES Appendices I, II and III with some
exception. As the area holds some CITES listed species, this convention is attracted in
case of their trade.
Convention on Biological Diversity, 2049 B.S. (1992): It focuses on the conservation
of biological diversity, the sustainable use of its components and the fair and equitable
sharing of the benefits. It urges parties to introduce appropriate procedures requiring EIA
of the proposed projects that are likely to have significant adverse effects on biological
diversity.
Convention (No. 169) Concerning Indigenous and Tribal People in Independent
Countries, 2046 B.S. (1989A.D): The convention provides right to the indigenous and
tribal people to decide their own priorities for the process of development. It mandates
participation in formulations of the plan and programs, decision making regarding
national development. It safeguards rights of the indigenous people in territories
traditionally occupied by them.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
73
9. ENVIRONMENTAL MANAGEMENT PLAN
200. The environmental management plan (EMP) is prepared to guide the implementation
of mitigation measures and monitoring requirements. It includes institutions and their roles,
environmental management activities, environmental management organizational structure
and budget for mitigation measures.
9.1. Institutions and their Roles
201. Different institutions involved in the IEEs and EMP implementation and their roles are
described in the Table 32:
Table 32: Institutional Roles and Responsibilities
Institution Roles Responsibility on the Project
National
Reconstruction
Authority (NRA)
It is the legally mandated to lead
and manage earthquake recovery
and reconstruction in Nepal. NRA
provides strategic guidance to
identify and address the priorities
for recovery and reconstruction. It
is authorized to frame rules and
working procedures to implement
recovery and reconstruction
programs.
As Project EA of EEAP, manages
overall project implementation and
monitoring, reviews and approves
ToR and IEE Report and conduct the
environmental monitoring from the
central level.
Ministry of
Federal Affairs
and Local
Development
(MoFALD)
It is the Central Level
Implementation Unit (CL-PIU) for
district/rural road component of
EEAP.
Overall coordination and the
supervision for implementation of
district/rural road component of
EEAP in the central level. It also
supports the DCCs (DL-PIU) to
implement the project activities.
Central
Implementation
Support
Consultant
(CISC)
Supporting consultants at central
level. AF-Iteco Ltd., Switzerland,
on behalf of Swiss Agency for
Development and Cooperation
(SDC)’s technical assistance has been providing technical supports
through the Decentralized Rural
Infrastructure and Livelihoods
Project III (DRILP-III) to NRA for
the implementation of EEAP.
Technical and management support
to NRA/MoFALD on rural/district road
component of EEAP including the
design specifications and necessary
environmental and social safeguard
issues.
Review, comment and forward ToR
for IEE and IEE report to ADB for
concurrence and to NRA for approval
District
Coordination
Committee
(DCC)
DCC is project implementing
agency in district (District Level
Project Implementation Unit/DL-
PIU)
Prepare ToR for IEE and submit for
approval to NRA through CISC.
Conduct IEE study, public
consultation and prepare IEE report
and submit for approval from NRA.
Implement IEE and EMP of sub-
projects and conduct environmental
monitoring and reporting.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
74
Institution Roles Responsibility on the Project
District
Technical Office
(DTO)
Project implementation office
working directly under DCC (DL-
PIU)
Responsible for overall activities
related to implementation of the
works at field level.
Safeguard Desk
(Safeguard
expert has been
provisioned in
PAM)
Safeguard desk will be the focus
of all safeguard related issues
Responsible for supervising,
coordinating, networking, monitoring
and reporting environmental
safeguard compliances. The desk will
conduct regular monitoring of EMP
compliance and record them.
Grievance
Redress
Committee
Support in addressing grievances
caused due to road construction
related to environment
Responsible for addressing
grievances due to road construction
which affects their livelihood.
Contractors Road construction work Reconstruction of road and
implementation of contractor’s part of
environmental responsibility.
202. Framework of environmental management for the proposed activity is depicted in the
Figure 7.
Figure 7: Environment Management Organization Structure
National Reconstruction Authority
(NRA)
Earthquake Emergency
Assistance Project (EEAP)
CL-PIU/MoFALD
DL-PIU/DCC/DTO
ADB and SDC
Contractor
DFO/CFUG DISC
Community
Infrastructure Division
Environment Safeguard Unit, CISC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
75
9.2. Reporting and Documentation
203. Work Procedure for Environmental Impact Assessment for Reconstruction of
Earthquake Affected Structures, 2072 B.S. (2016 A.D.) entitles the monitoring
responsibilities to the NRA. DL-PIU/DISC will prepare and submit monthly monitoring and
implementation reports to the CL-PIU/CISC, who will take follow-up actions if necessary. CL-
PIU/CISC will prepare and submit quarterly and semi-annual monitoring and implementation
reports to the NRA and ADB. Appendix 11 provides a content outline for monitoring reports.
204. Contract document will categorically include provision of the environmental
protection, health and safety, waste management and other environmental mitigation
measures identified during the IEE study. It will spell out clearly the measures that will be
taken in case on non compliance. This will make them comply with the provisions.
205. The monthly reports will be based on recurrent site inspections and will report on the
effectiveness of the mitigation measures;
The Contractor's compliance with the environmental specifications;
Measures recommended in the events of non-compliance and
Recommendations for any other remedial actions, etc
9.3. Implementation of the Mitigation Measures
206. The proponent will be responsible for the implementation of the mitigation measures
proposed in Chapter 7. The detail action plan for activities to be carried out to augment
beneficial impacts and reduce/mitigate adverse impact produced from the implementation of
the proposal, and the responsible implementing and supporting agencies are provided in
environmental management plan is presented in Table 33 and Table 34.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
76
Table 33: Summary of the Beneficial Impacts and Enhancement Measures
Activity Issues Related beneficial impacts
Type of impact
Sign
ifica
nc
Beneficial augmentation measures Responsible agencies
Impa
ct
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Supporting agencies
Construction Phase
Construction of road and opportunities
Employment opportunities
Employment generation of 391,580 persondays and Increase in income level
D L
20
ST
05
H
60
Vs
85
No augmentation.
The contractor will be encouraged to give priority to local and
marginalized people including women in construction works.
Contractor/ DL-PIU
CL-PIU/ DISC/ CISC
Enhancement of technical skill
Increase in income generating activities and employment opportunities
IN L
20
LT
20
M
20
S
60
The workers will be formally and informally oriented about the
specific requirements for climate and disaster resilience.
Contractor/ DL-PIU
CL-PIU/ DISC/ CISC
Increased trade and business opportunities
Increase in income level of non-worker
IN L
20
ST
05
M
20
S
45
Priority to local markets and local products Contractor/ DL-PIU
CL-PIU/ DISC/ CISC
Operation stage
Operation of road
Improved accessibility
Safe travel, Improve accessibility, saving of travel time and cost
D L
20
LT
20
H
60
Vs
100
Regular inspection and maintenance and bioengineering.
Allocation of budget for regular inspection and maintenance of
the road.
Contractor/ DL-PIU
DL-PIU/ CL-
PIU
Access over public services and basic utilities
Easier access to educational institutions, health institutions, religious places etc.
D R
60
LT
20
Mo
20
Vs
100
Timely implementation of the project Regular maintenance of the road
Facilitate the fair price transportation of agricultural and other day to day consumables in ZoI
DCC/DTO DL-PIU/ CL-
PIU
Benefit of increased land value
Appreciation of land value and local benefit by improvement of local economy
IN L
20
LT
20
Mo
20
S
60
RoW encroached will be observed along with awareness to local Promotion of land development and land use planning along the road corridor and other local areas
DCC/DTO DL-PIU/ CL-
PIU
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
77
Activity Issues Related beneficial impacts
Type of impact
Sign
ifica
nc
Beneficial augmentation measures Responsible agencies
Impa
ct
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Supporting agencies
Women empowerment
Empowering women in road maintenance and othe farm and of farm activities
IN L
20
LT
20
H
60
Vs
100
Preparation and implementation of GESI Action Plan
Assist to organize women groups, provide training in social
mobilization. A cost of 100,000.00. has been allocated.
DL-PIU/ DISC/ NGOs/ Community
CL-PIU/ CISC
Conservation and environmental awareness
Conservation of overall environment
IN L
20
LT
20
H
60
Vs
100
Environmental awareness programmes. A cost of 250,000.00. has been allocated.
DL-PIU/ DISC/ NGOs
CL-PIU/ CISC
Promotion of Tourism
Influx of tourist due to easy access and addition o livelihood option.
IN L
20
LT
20
Mo
20
S
60
Awareness training. Tourism management training like cookery and homestay management. A cost of 150,000.00. has been allocated.
DCC/NGOs CL-PIU/ CISC/ NTB
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
78
Table 34: Summary of Adverse Impact Prediction and Mitigation Measures
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
Pre- construction
Project Planning and design
Process and reliability of detail survey and design
Inappropriate alignment, quarry sites and burrow pits etc., encroachment of sensitive area
D L
20
ST
5
H
60
Vs
85
The road design will follow the standard methods. All provision proposed in the EMP of IEE document will be properly reflected in the design.
DCC DL-PIU/ CL-
PIU/ NRA
Land and the Property Acquisition
Loss of 2.98 ha of private land
Change of existing land to the permanent structure and difficulties in livelihood
D Ss
10
LT
20
Mo
20
S
50
Appropriate compensation will be provided to the land and property title holder for private land, private structures and private trees. (NRs 2,98,777.28 and 1,440,000.00 for structure) After dismantling the construction camp and other facilities, original land will be rehabilitated.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Construction Phase
Socio-economic and Cultural Environmental Impacts
Construction of road
Loss of 2.98 ha of agricultural land and its production
Impact on food security and financial stability of the dependent households
D Ss
10
LT
20
Mo
20
S
50
Appropriate compensation will be provided to the land and property title holder. Compensation for standing corps ( NRs 65,094)
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Construction of road
Impact on the social services and community
Pressure on social service facilities like water supply, Damage of irrigation canals
D Ss
10
ST
10
H
60
Vs
80
Provision of basic utilities within camp perimeter Building consensus with local people for using community infrastructures and resources
Any damage to existing road in project location like formation of ditches shall be controlled and rehabilitated.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
79
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
infrastructure
Crossings will be provisioned for irrigation canals (34 nos.) and rehabilitation will be done in case of damage.
Construction force and occupational safety
Occupation Health and Safety measures
Exposure of construction workforce to related health risks and hazards due to operation of machines & construction work, improper sanitation etc.
D L
20
ST
05
H
60
Vs
85
Safety arrangements like provision of First Aid Kit Box and standby medicine for workforce during working period and emergency. Provision of PPE like helmet, boots, globe, mask and safety belts etc. Provision of temporary drinking water and toilets in the construction camps. Use of sigposts, barriers and guards to restrict unauthorized entry. Group accidental insurance
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Construction force and communicable diseases
Communicable diseases
Impact on health of locals and construction workers due to proximity to infected person, Sexual contacts and proliferation of HIV/AIDs and STDs
ID R
60
LT
20
Mo
20
Vs
100
Regular health check-up in the construction camp. Awareness using pamphlets boards and browsers. Encouragement to keep the camp clean and tidy.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Operation of construction camp
Conflict between locals and outside workers
Conflict during work due to distinct thought and cultural perception; alcoholism and gambling.
D L
20
ST
05
Lo
10
In
35
Informing worker about general norms and values of local community; instructing them to respect local culture and tradition with humility. Job opportunities to local people will be maximized. Discouraging gambling and alcoholism.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Construction Gender Discrimination in D L ST M S Enforcement of non-discriminatory policy Contractor/ DL-PIU/ CL-
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
80
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
activity, wage and female participation
discrimination
wage/salary distribution 20 05 o
20
45 Positive discrimination, empowerment and social mobilization; related trainings/programs
DCC PIU/ NRA
Physical Environmental Impacts
Construction activity
Change in Land Use Pattern
Present land structure will permanently change
D Ss
10
LT
20
H
60
Vs
90
Roadside plantation of trees will be done to increase greenery in the area. During re-vegetation, local species identified during the survey will be used.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Quarry of construction aggregates
Sediment load in river water
Impacts on the river and its biota by enhanced soil erosion
D Ss
10
ST
05
Lo
10
In
35
Proper drainage arrangement in stockpile area; Immediate clearance of the river path in case of blockade; Minimal cut and fill approach
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Excavation and Storage of construction materials
Stock piling, spoil/waste disposal, Transport of construction materials
Impact on the local ecology by cement, soil and excavated materials on water and others resources
D Ss
10
ST
05
Mo
20
In
35
Material will be stockpiled at fallow land and will be covered. Proper drainage will be arranged around the stockpile area. Floodways, natural drainage paths, water bodies, farmlands will be avoided. Sustainable collection of river bed materials whenever required, Excavated materials will be used for filling works.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Construction activity, Quarrying & burrow pits during construction phase
Quarrying and extraction of river bed material
Impacts due to quarry site operation, river bank cutting, change in river regime and rising Water pollution due to unfriendly management practices of quarries
D Ss
10
ST
05
H
60
Vs
75
Sediments derived from the excavation will be used for backfilling. Coarse aggregates and sand will be obtained from designated and approved quarries and borrow areas that have already taken environmental clearances (if such sites are available). Unstable sites, erosion prone areas, dense forest areas,
Contractor/DCC
DCC/DL-PIU/ CL-PIU/ NRA
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
81
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
and spoils settlements and fertile farm land will be avoided for quarry operation. Stones and boulders will be collected from the environmentally suitable and legally recognized quarry sites. After the extraction is completed, the quarry site will be rehabilitated to suit the local landscape. The materials to be transported will be covered by plastic sheets. Arrangements will be made in trippers to arrest water dripping from the materials.
Construction work :Air, Water and Noise pollution
Impacts on air quality due to operation of equipments and vehicles
Introduction of fugitive and combustion emissions, dust (PM10) and smoke, etc. and its impact on workers, local people and vegetation
D Ss
10
ST
05
Mo
20
In
35
Construction equipments and vehicles will be regularly
examined and maintained in proper condition.
Water will be sprinkled at major settlements along the road
at least two times a day during peak construction.
Construction materials will be properly covered during
conveyance.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
Impact on ground water quality
Mixing of pollutants like turbidity, fecal contamination, oil and grease and other inorganic and organic wastes resulting pollution of water body.
D L
20
ST
05
Mo
20
S
45
Ensuring safe storage and wise use of chemicals to prevent spillage; Avoiding the disposal of excavated materials in or near water bodies; Discouraging open urination and defecation and construction of toilets in camp sites.
Impact of noise from operation of
Health of local people and worker
D L
20
ST
05
Lo
20
S
45
Construction equipments will be maintained in proper
condition by applying grease and lubricants.
Sound producing equipments will be preferred to use only in
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
82
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
equipments and vehicles
day time.
Earplug will be provided to the worker involved in equipment
operations.
Construction work and Solid waste generation
Impact due to solid waste generation
Synthetic materials, construction and domestic wastes reduce land and water quality, aesthetics impacting on human and environmental health
D Ss
10
ST
05
H
60
Vs
75
Segregation of solid waste at source; Composting degradable waste; Separate collection and storage arrangements and that too far from waterway; Selling sellable wastes like metals, bottles, drums, etc.
Contractor/DCC
DL-PIU/ CL-
PIU
Contractor camp establishment
Pollution and impact due to location of camp sites
Encroachment of forest, agriculture land, solid waste, and waste water may cause pollution
D Ss
10
ST
05
H
60
Vs
75
Use of local labours will avoid the chance of campsite management. If it is indispensable to establish camps, they will be sited away from productive lands and forest areas. Respectable compensation will be paid for using private farm or lands for storage or camp. The camp and storage sites will be properly cleaned, reinstated and handedover to the respective owner followed by receiving necessary clearance from the owner. Toilet, water and other basic facilities will be provided to workers. Labor camp will have room with proper ventilation and natural light, safe drinkable water, mosquito net, sanitary facility, and solid waste management. Appropriate camp sites have been identified at Ch 4+100, Ch 13+500, Ch 19+900, 26+300 and Ch 36+900.
Contractor/DCC
DL-PIU/ CL-
PIU/ NRA
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
83
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
Biological Environment Impacts
Site clearing for construction activity
Impact on forest and vegetation
Loss of forest and vegetation due to site clearance , exploitation by workforce
ID L
20
ST
05
Mo
20
S
45
Maximization of local employment for the project development. Provision of LPG or kerosene for labor and engineer camp. Workers will be made aware about the importance of conservation and restricted activities. Plantation of trees 2,625 (@1:25) of suitable type for compensatory plantation (NRs. 412,518.75)
Contractor/DCC
DFO/CFUG/ DCC/ DTO
Construction work, vehicle movement on wildlife distribution
Impacts on rare, endangered, threatened and endemic species
Hunting and poaching by workforce; road collision and fatal injury to wildlife and death; disturbance to wildlife due to movement of vehicles
ID
L
20
ST
05
Mo
20
S
45
Prohibiting construction crew from hunting and poaching
Enforcing speed limit and traffic regulation for transport vehicles Maximizing numbers of locals in construction crew
Putting restriction on the use of wildlife meat in the construction camps and treating breaching as punishable offense. A hoarding board will be placed at sensitive sites (Ch 0+080, 16+800, 19+500, 24+100 and 30+050 where the road passes along the forest areas) to aware workers and locals alike on importance of wildlife and conservation.
Contractor /CFUG
DFO/CFUG/DL-PIU
Operation Phase
Socioeconomic and Cultural Environment Impacts
Operation of road
Ribbon settlement along the project alignment
Development of Ribbon settlement and Encroachment of RoW, increased accidents, delay in traffic movement
ID Ss
10
LT
20
H
60
Vs
90
Appropriate planning and enforcement of law; Road side plantations of trees will be done in the RoW to prevent possible encroachment.
DCC/VDC CDO/ DCC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
84
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
Use of road Road safety issues
Chances of road accidents in the turnings of the Road and Loss of life and property
D Ss
10
LT
20
Mo
20
Vs
50
Awareness by signboards and traffic signs at critical places; Adopting 3Es: Engineering, Enforcement and Education.
Local people and drivers
DCC
Biological Impacts
Operation of road
Encroachment and Forest Depletion
Destruction due to spoil and runoff; Illegal cutting of trees because of access
ID Ss
10
LT
20
Mo
20
Vs
50
Awareness raising programmes to educate local people and providing support to locals for the conservation of forests
Hoarding board for awareness (NRs 200000)
Local people
DFO/CFUG/DCC
Physical Environment Operation of road
Slope stability and Drainage management
Slope instability at Chianages Ch 4+360 to 4+380, Ch 6+600 to 6+660, Ch 36+980 to 37+160, Ch 37+840 to 37+940 and Ch 38+340 to 38+480
D Ss
10
LT
20
Mo
20
S
50
Bio-engineering works to control the slides and retain the slopes. Rill and gully formations will be regularly monitored and immediately fixed at critical areas. Repair and maintenance of the slope protection measures and drainage Minor landslide and mass wasting will be immediately cleared and slope restored with appropriate technology (bioengineering). Soil conservation will be promoted in the RoW and vulnerable areas beyond the road alignment. Causeways (11) RCC Slab Culverts (1) and Pipe Culverts (67) will be placed to maintain cross drainage at places and allow passage of runoff.
DL-PIU/ Contractor
CL-PIU/ DL-
PIU/ DCC
Operation of vehicle
Impact due to Air, Water
Dust, smoke, noise level, due to vehicle
D Ss
10
LT
20
Lo
10
In
40
Signboards restricting the use of horns will be erected near health posts, schools and settlements.
Local people/
DCC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
85
Activity Issues Related adverse Impacts
Type of impacts
Sign
ifica
nce
Mitigation measures Responsible agencies
Impa
ct n
atur
e
Exte
nt
Dur
atio
n
Mag
nitu
de
Executing agencies
Monitoring agencies
and Noise pollution
movement and Water pollution due to vehicle washing
Plantation will be done near the settlement around school and health post to act as dust and noise barrier. Vehicle washing in natural streams will be discouraged.
RMs
Note: D= Direct; ID = Indirect, S= Site Specific; L = Local, R = Regional; ST= Short Term, NA = Not Applicable of No Impact, MT = Medium Term, LT = Long Term; Lo = Low, Mo = Moderate, H = High, I=Insignificant, S=Significant, Vs=Very Significant, Hs=Highly Significant
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
86
9.4. Matter to be monitored while implementing the Proposal
207. Monitoring of the implementation of environmental protection measures provides a
basis for logical comparison for the predicted and actual impacts of a proposal.
Environmental monitoring will involve the systematic collection of data to determine the
actual environmental impacts of the sub-project, compliance of the sub-project with
regulatory standards, and the degree of implementation and effectiveness of the
environmental protection. Monitoring will be an integral part of the implementation of the
mitigation measures during project construction, and will generate important information. It
will improve the quality of sub-project implementation.
208. The Work Procedure for Environmental Impact Assessment for Reconstruction of
Earthquake Affected Structures, 2072 B.S. (2016 A.D.) requires a monitoring plan and
indicators, schedules and responsibility be identified in the IEE report. The National EIA
Guidelines for the Forestry sector, 1995 has proposed three stages of the monitoring i.e.
baseline monitoring, compliance monitoring and impact monitoring.
9.4.1. Baseline Monitoring
209. Baseline monitoring aims to determine the baseline condition of the environmental
resources. It is carried out if significant time elapse between preparation of the IEE report
and the construction stage or change in the environmental quality is noticeable. This project
will proceed for the immediate construction after the approval of this IEE report and hence
baseline monitoring is not necessary.
9.4.2. Compliance Monitoring
210. Compliance monitoring is essential in order to ensure that environmental protection
measures recommended by this study and other requirements set forth during the approval
of the sub-project are complied with. This monitoring is not concerned with determining the
actual effect of the sub-project activities on the environment.
211. The proponent will ensure compliance of activities such as; inclusion of mitigation
measures in the design and tender documents, budget allocation for mitigation measures
and monitoring, compensation arrangements and other compliances spoil disposal, storage
sites, arrangement of construction activities etc.
9.4.3. Impact Monitoring
212. This monitoring detects environmental changes and estimates inherent variation
within the environment, establishes long term trends in the natural system, and derives
conclusion by making comparison against standard or targets.
213. Impact monitoring is generally carried out to access the effectiveness of the
environmental mitigation measures and provides the actual level of the impact in the field.
Hence, an impact monitoring evaluation study is proposed by the end of project construction
phase or within 2 years of the project implementation. Impact monitoring will focus on the
each predicted impact and effectiveness of environmental protection measures.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
87
9.5. Monitoring Indicator
214. These would be based on the level of site-specific information or existing data series
and impacts prediction. Efforts have been made to make the indicators measurable and
diagnostic with low natural variability and broad applicability. In this context, the following
physical, biological and social indicators will be monitored during the construction and
operational stages of the sub-project.
9.5.1. Pre-Construction Phase
215. Pre-construction phase monitoring is aimed at ensuring that the environmental and
social safeguard considerations are adequately incorporated in the Project design and that
the respective clauses to address the identified impacts are sufficiently included in the
specifications and work contracts.
9.5.2. Construction Phase
216. In this phase the monitoring focuses on impacts on the environmental and social
setting caused by the ongoing sub-project. This monitoring checks compliance with the
practices, norms, standards and technical solutions prescribed in the design and in the EMP.
The specific monitoring tasks will include the following activities:
Verify and quantify the ongoing slope protection measures, and propose rectifying
measures as needed;
Verify and quantify the ongoing activities in quarry operations and propose rectifying
measures as needed;
Verify and quantify the ongoing/completed tree felling actions;
Verify and quantify the course of any environmental degradation caused by the sub-
project activities, their likely consequences, and propose corrective measures,
including identification of the responsibilities and costs;
Verify and quantify the effects of disposal of spoil and construction wastes and their
consequences;
Verify and quantify the effects of disruption of natural water courses, drainage network,
and their consequences;
Monitor by utilizing structured checklists and questionnaires, the contractor’s full compliance with the occupational health and safety regulations for the work staff;
Verify and quantify the effects of losses in wildlife, degradation of forests, illegal
extraction of forest products, hunting, wildlife trade and disturbance to wildlife;
Identify and assess the environmental implications on the people’s status of knowledge and awareness in relation to ongoing awareness campaigns;
Verify and quantify losses/damage to private property and community facilities;
Verify and quantify losses/damage to cultural properties;
Explore mechanisms to stipulate strict application of the EMP and identify
consequences to be borne by the contractors in case of non-compliance.
9.5.3. Operation Phase
217. The specific monitoring tasks in this phase will include the followings:
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
88
Assess changes in land-use patterns, development of cottage industries, services and
demographic composition that may be caused by the road development;
Verify and quantify the occurrence of ribbon development, resulting in encroachment
and hindrance of traffic on the road;
Verify all activities for decommissioning work sites and construction to their former
functional stage, as applicable. This refers also propose rectifying measures as
needed.
Verify and quantify the adequacy of the executed bio-engineering works for slope
protection and erosion control;
Verify and quantify the adequacy of the drainage structures, functionality of these
structures, shortcomings in maintenance, and possible effects on private and
communal lands, as well as on aquatic resources;
Verify and quantify the course of any environmental degradation caused by Project
activities, their likely consequences, and propose corrective measures, including the
identification of responsibilities and costs;
Verify and quantify the effects of disruption of natural water courses, drainage work,
and their consequences;
Verify and quantify the effects of losses in wildlife, degradation of forests, illegal
extraction of forest products, hunting, wildlife trade and disturbance to wildlife.
9.6. Monitoring Indicators
218. Monitoring will be carried out in a transparent and credible manner by using
established indicators. To ensure that the monitored parameters are replicable, i.e. they do
not depend on the person or specific methodology used, the selected indicators are easy to
be verified and controlled by the agencies where the final monitoring and supervision
responsibility remains.
219. Use of standard checklists and formats is sought to be used by the monitoring staff
both for site surveys and in the subsequent reports. Much of the monitoring is related to
quantifying the observed impacts, and to verify the nature and extent of impacts,
photographs, parameter tests, collect local accounts of stakeholders and technical experts.
The monitoring will also include specific cause-effect analyses for the impacts observed.
Following Table 35 specifies the set of verifiable indicators that will be used for monitoring.
Table 35: Monitoring Indicators Selected for this IEE
Monitored Sector Parameters Selected for Monitoring
Soils, Landslides, Erosion, Waste
management Sites
Number, location and extent of slope failures
Cause analysis for slope failure natural/man-made
Area (ha.) of land, forest and properties affected
Number and extent of gully erosions and pavement
failures
Suitability of corrective/bio-engineering measures
Sites and suitability for safe disposal of wastes and
garbage
Bio-engineering Number and plant species selected for bio-
engineering, disaggregated by protective function
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
89
Monitored Sector Parameters Selected for Monitoring
Water Pollution, Water
Resources and their uses
Blockage of waterways - extent and secondary
impacts
Water pollution incidents due to unsafe disposal of
waste and spoil
Damage to farm lands
Air and Noise Level in relation to
traffic volume
Assessment of noise level in site by direct
observation and interview with stakeholders
Visual assessment of dust development at selected
sites/sensitive spots and interview with local
stakeholders
Traffic volume measurements
Road Safety Number and type of road accidents recorded in the
Traffic Police and in local health service centers
Suitability of local road signs
Wildlife/ Habitat Disturbance &
Impacts on Forest Resources
Nos and extent of road accidents inflicting wildlife
DFO records of illegal timber extraction and wildlife
trade
Observations and handling of invasive species.
Socio-economic Development
near Road
Number and extent of new settlements /types and
ethnic groups
Number and extent of new businesses
Number and extent of new services and utilities
Resettled Households and
livelihood restoration
Number of HHs resettled
Income situation and opportunities for the resettlers
Verification of compensation and assistance to
resettlers
Community awareness
programmes relating to
environment protection and
avoidance of social conflicts
Number /schedule of campaigns and number of
beneficiaries
Revision of training agenda & information material
Number of beneficiaries having received awareness
training
220. The following Table 36 identifies the specific compliance monitoring activities.
Phase-wise/chronological details are provided for the methods, schedules, responsible
implementing agency and the responsible monitoring agency. The compliance monitoring
refers primarily to the pre-construction and construction stage of the project. Table 37 details
the impact and effect monitoring activities envisaged for this sub-project.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
90
Table 36: Compliance Monitoring of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation and Reconstruction Sub-project
Parameters/Provisions for Compliance
Implementation Responsibility
Verifiable Indicator Verification Methods
Frequency
/Time
Responsible Monitoring authority
Final site selection as per IEE/EMP recommendation
Consultant Incorporation of the IEE/EMP recommendations to the designing document
Review of revised design document and field verification.
Initial stage of surveying
DISC/DCC/DTO/ MoFALD/NRA
Site selection and preparation of construction logistics
Contractors Project arrangement for the materials storage and the construction activities
Review of the design and construction planning documents
Once during construction period
DCC/MoFALD/CDO
Land and property acquisition and compensation
DL-PIU Cadastral records, land and properties acquisition procedures; verification report
Review and verification of reports, photos; geo-
referencing
Initial stage pre-
construction phase
DTO/DCC
Use of the local labours/ particularly vulnerable groups and women
Contractors Specification which obligate the contractors to observe certain quotas for employing local labour, especially vulnerable groups , and women, use of child-labour
Review of contract specifications; records of workers, attendance; payments made to workers followed by interview.
Trimester during construction period
DTO/DCC
Awareness and job training on the road construction to the technicians and the locally employed laborers
Contractors Training programmes for the skill development, OHS and environmental protection associated with the road construction work
Review of records of training programmes, reports, and documents with feedback from the participant; Review
Once before construction
DTO/DCC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
91
Parameters/Provisions for Compliance
Implementation Responsibility
Verifiable Indicator Verification Methods
Frequency
/Time
Responsible Monitoring authority
of attendance records
Compliance to occupational health safety measures
Contractors Health and safety regulations, first aid and medical arrangement, contingency plan, number and type of the safety equipment, mask, helmet. glove and safety belt
Spot checklist at the work sites, photo, accident record, interviews
Trimester during construction period
DTO/DCC
Compliance to environmental protection measures, including pollution prevention, water and spoil management, slope stabilization, landfill, waste management
Contractors Arrangement specified in the code of the practice and manuals relating to the environmental protection, records and the observation pollution, waste management, spoil deposit
Review of related logs and codes along with site inspection, discussion with the project management, consultants and the local people. Review of air quality and noise level measurement and water quality test reports.
Trimester during construction period
DTO/DCC
Measures to protect environment from air and noise pollution
Contractors Dust level and noise level at work sites, major settlements and sensitive spots like health centers and private spots
Review of noise measurement records, Observation of good construction
Trimester during construction period
DTO/DCC/DFO
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
92
Parameters/Provisions for Compliance
Implementation Responsibility
Verifiable Indicator Verification Methods
Frequency
/Time
Responsible Monitoring authority
practices and discussion with residents and workers
Measure to protect water body from pollution
Contractors Dust level and the noise level at the work site, major settlements and the sensitive spot like health centre and schools
Review of water quality check records. Observation of the good construction practices and discussion with residents and workers
Trimester during construction period
DTO/DCC/DFO
Grievance Redress Mechanism
Contractor/DLPIU/ DISU/ CLPIU/CISC
Project arrangements for the affected people's concerns and grievances about the projects environmental and social performance
No of complaints and grievances record
During construction
DCC/DTO
Measures to avoid pressure on forest and wildlife
DLPIU/DTO/DISC Use of firewood or fossil fuel by construction crew, events of hunting and poaching of wildlife
Inspection, interview with local people
Once a month during construction
DTO/DCC/DFO/CFUGs
Restoration, rehabilitation, reconstruction of all the infrastructure, service
Contractors Continued service by the facilities and functional public life
Site observation, RM/DCC records public consultation meeting, photos
Once at the end of construction
DTO/DCC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
93
Parameters/Provisions for Compliance
Implementation Responsibility
Verifiable Indicator Verification Methods
Frequency
/Time
Responsible Monitoring authority
disrupted or damaged by the proposal activities
Adequate technical and the environmental supervision
CL-PIU/DCC/ DTO/CISC/
Adequate number of technicians regularly at site
Review of records of number and type of technician available at site, Skill of work carried out.
Trimester during construction period
DTO/DCC
Clean up and reinstatement of the construction sites (camps, quarries, burrow pits)
Contractors Decommissioned site indicate no adverse/residual environmental impacts and are rehabilated to the satisfication of supervisor and land owner
Review of clearance from the owners; Site observation, Comparing Photos, Consulting to owner or local community
Once at the end of construction
DTO/DCC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
94
Table 37: Impact Monitoring of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation and Reconstruction Sub-project
Parameters
/Indicator
Verifiable Indicators Verification
Methods
Location Schedule Responsible
Implementation and
Monitoring Agency
Slope stability
and
erosion
Inclination, slope failures,
causes; drainage facilities such
as catch drain, side drains and
functionality of cross drainage
structures; fresh gullies and
erosion; success/failure of bio-
engineering solutions
Site observation,
photos
discussion with
people and
technicians
Near steep slopes
and at landslide
areas and sites
Continuously
during
construction and
operation
DL-PIU/NRA during
construction;
DCC/DSCO during
operation
Quarrying of
aggregates
Changes in the river regimes,
Bank cutting and loss of
agricultural land
Site observation,
photos, discussion
with the local people
Quarry sites areas Trimester during
construction
DISC/DCC/DTO
Bio-engineering
of disturbed
slopes
Re-vegetation through bio-
engineering application on
disturbed slope; establishment of
nursery
Site observation;
inspection of nursery
and its production
rate,
photos,
measurements
Cut slope area,
where vegetation is
cleared;
nursery sites
During and at
the end of Sub-
project
construction
DISC/DCC/DTO
Disposal of
spoils and
construction
wastes
Affected aesthetic value, affected
forest and agriculture land,
initiated land erosion by local
blocked drainage, hazard to
downhill slope residents and
agricultural lands
Site observation and
interviews, photos,
geo-referencing sites
At specific locations
where such sites
occur
During
construction
DISC/DCC/DTO
Loss or
degradation of
farmland,
houses and
Status of road side land;
production/yield;
status of road side houses; status
of standing crop along alignment
Observation, data
collection and
analysis and
interview with
Road side land and
houses
During
construction
DISC/DCC/DTO
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
95
Parameters
/Indicator
Verifiable Indicators Verification
Methods
Location Schedule Responsible
Implementation and
Monitoring Agency
properties stakeholders
Water quality Observation of open defecation
and waste disposal around water
sources near construction sites
Visual observation Local streams During
construction;
upon demand
for testing with
field kit
DISC/DCC/DTO
Air quality Dust level in ambient air Visual inspection At construction sites
and at sensitive
spots
During
construction
DISC/DCC/DTO
Forest and
vegetation
Numbers of trees, presence of
ground vegetation, signs of illicit
logging and extraction of NTFPs
Observations,
DFO/CFUGs
records, photos
In and around the
construction sites,
markets
During
construction and
Operation
DFO/DCC/DTO/
DISC/CFUGs
Wildlife Wildlife hunting and poaching by
workforce, trade of wildlife, road
accidents inflicting wildlife
Interview with local
people/CFUGs/DFO
and
observations
Forest areas at
roadside
Twice a year
during
construction and
routine during
operation
DFO/DCC/DTO/
DISC/CFUGs
Change in
economy
Numbers of people employed by
the project during construction,
numbers of women in work
forces
Records kept by the
project management,
discussion with
stakeholders
Sub-project area Trimester during
construction
phase
DISC/DCC/DTO
Trade and
commerce
Numbers of shops increased or
decreased, rental of houses and
land spaces
Records, interviews,
observations, photos
Throughout sub-
project area
Once in a year DISC/DCC/DTO/RM
Occupational
safety and
hazard
Type and number of accident
occurred during construction;
adequacy of occupational safety
Observations,
photos, spotchecks,
contractors and
Throughout sub-
project area
During
construction
DCC/DTO/DISC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
96
Parameters
/Indicator
Verifiable Indicators Verification
Methods
Location Schedule Responsible
Implementation and
Monitoring Agency
measured provided;
compensation provided in case of
fatal accidents
health centre records
interview with
workers
Change in
socio-economic
structure
Number and extent of new
settlements/types and ethnic
groups; nos. and extent of new
businesses; nos and extent of
new services and utilities, social
conflicts
Observations,
interview with local
people, DCC, Police
and RM records
Throughout sub-
project area
During operation DCC/RM
Acess to social
services
Increase in number of people
receiving social service facilities
(Schools, health post)
Records, interviews Project area During operation DCC/RM
Enhancement of
transportation
services
Change in transportation cost
and time
Records, interviews Project area During operation DCC/RM
Change in
livelihood
pattern
Change in number of porters and
their livelihoods, change in
occupational status
Interviews with local
people, observation
and FGDs with local
community
Project area During operation DCC/RM
Ribbon
settlement
Congestions to road users and
nos. of accidents, RoW
encroachment
Records,
observations
Throughout sub
project area
During operation DCC/Local
administration
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
97
9.7. Cost of Mitigation and Enhancement
221. Various activities of mitigation measures such as slope stabilization, quarry site
management, spoil disposal, supply of the masks, helmets, ear mufflers, accidental
insurances, slope retention and toe wall protection, spoil disposal, relocation of utilities, etc.
have been incorporated in the design and cost estimates. Therefore, most of the mitigation
measure suggested would be a part of the road design and construction without additional
cost. The estimate of the environmental cost of the sub-project has been itemized in Table
38. All proposed mitigation measures will be an integral part of the project design during
reconstruction and operation phases. The cost for environmental mitigation measures and
benefit augmentation is NRs. 13,520,898.18 where NRs. 12,058,379.43 is allocated within
civil work cost and 1,462,518.75 will be in addition to civil work cost.
Table 38: Estimate of Environmental Cost of the Sub-Project
SN Particulars Amount
(NRs.)
1 Environmental Management Cost
1.1 Environmental/conservation awareness program 250,000.00
1.2 Tourism promotion awareness (A three days homestay management
training to 15 people from project area)
150,000.00
1.3 Hoarding boards at road site (4 places) for awareness about
important wildlife and their conservation.
200,000.00
1.4 Compensatory plantation & protection cost for trees on CF 412518.75
1.5 Roadside plantation 200,000.00
1.6 Solidwaste collection bins 50,000.00
1.7 Environmental monitoring cost 200,000.00
Sub-total (I) 1,462,518.75
2 Other environmental cost (included in civil works cost also)
2.1 Contractor's workmen and employees and third party insurance
against damage to other persons and property (Ref Appendix 9, item
1.1)
900,000.00
2.2 Relocation of Utilities (water supply and telephone poles) (Ref
Appendix 9, item 1.4)
300,000.00
2.3 Maintenance of existing road, providing and maintaining traffic
safety, control measures and temporary diversions during
construction including water spraying thrice a week to avoid dust
pollution. (Ref Appendix 9, item 1.5)
38,000.00
2.4 Labour camp maintenance (Ref Appendix 9, item 1.7) 20,000.00
2.5 Environmental Mitigation Works (Ref Appendix 9, item 1.9) 300,000.00
2.6 Social Compliance and Safeguard (Ref Appendix 9, item 1.10) 150,000.00
2.7 Spoil Disposal 4,810,498.03
2.8 Bioengineering and landslide retention (Ref Appendix 9, item 7) 5,188,738.62
2.9 Installation of traffic signals (Ref Appendix 9, item 6.4) 351,142.78
Sub-total II 12,058,379.43
Total EMP Cost 13,520,898.18
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
98
9.8. Costs of Environmental Monitoring
222. Monitoring is an integral part of the project in finding the unlikely impacts and
implement corrective measures for them. The proponent will develop in-built monitoring
mechanism to show its additional commitment for environmental improvement and mitigate
undesirable changes, if any during construction and operation stage. District Level
Implementation Team in district and Environmental specialist for EEAP will conduct
environmental monitoring with the support of DCC/DTO.
223. According to the Work Procedure for Environmental Impact Assessment for
Reconstruction of Earthquake Affected Structures, 2072 B.S. (2016 A.D.), the NRA is
responsible for the monitoring and evaluation of identified impacts during implementation of
the project. CL-PIU(MoFALD) and DL-PIU (DCC/DTO) will make arrangements for the
project level monitoring. Beside this, it is recommended that an external team hired by NRA
will take the responsibility for the monitoring. In addition, regular supervision and guidance
will be also provided by the CISC. At least one monitoring in each construction season is
necessary. The reporting requirement has been discussed in the preceeding section. Total
cost of environmental monitoring (professional fees, transportation and visit and report
preparation) is estimated NRs. 200,000 and is presented in Table 39.
Table 39: Estimated Cost for Environmental Monitoring
Manpower requirement Duration (days) Rate
(NRs)
Amount
(NRs)
Team Leader/Environmental Specialist 5 4,000 20,000
Engineer 3 3,000 9,000
Forestry expert 3 3,000 9,000
Socio-economist 3 3,000 9,000
Support staff 3 1000 3,000
Transportation cost LS 25,000
Report preparation LS 25,000
Central level monitoring LS 100,000
Total 200,000
9.9. Grievance Redress Mechanism
224. Four levels of grievance redress mechanism (GRM) have been sought in order to
resolve complaints related to sub-projects in timely and satisfactory manner and preferably
at the local level through a process of conciliation; and, if that is not possible, to provide clear
and transparent procedures for appeal. All affected persons will be informed about their
rights, and the detailed grievance redress procedures will be publicized through an effective
public information campaign.
9.9.1. First level of GRM
225. The contractors, and design and supervision consultants on site are the most
immediate and accessible and thus responsible party to hear and address the grievances.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
99
Prior to construction works, the CL-PIU and DL-PIU will ensure local community meetings
are held to notify local residents of the sub-project activities and their possible implications. If
any complaints arise, the contractors, consultants, and DL-PIU will immediately resolve the
complaint on site if it falls within their scope or jurisdiction. The CL-PIU can also be involved
in grievance redress at this stage. The CL-PIU and DL-PIU office phone number will be
posted in public areas within the sub-project areas and construction sites. Any person with a
grievance related to the sub-project can contact the project to file a complaint. The DL-PIU
offices will have a safeguards focal person to resolve complaints. The safeguards focal
person will document the complaint, and immediately address and resolve the issue with the
contractor within 1-2 days, if the complaint remains unresolved at the field level. The DL-PIU
may seek assistance of the consultant safeguards specialists (the environmental specialist
or social safeguards specialist) to resolve the issue. The DL-PIU safeguards focal person will
notify the CL-PIU safeguards focal person about the receipt of the complaint, and whether it
was resolved. The DL-PIU safeguards focal person will document the following information:
(i) name of the person; (ii) date complaint was received; (iii) nature of complaint; (iv) location,
and (v) how the complaint was resolved.
9.9.2. Second level of GRM
226. If the grievance remains unresolved, the DL-PIU will forward the complaint to the CL-
PIU safeguards focal person notifying the person filing the grievance. The CL-PIU will
address the grievance through continuous interactions with affected persons. Corrective
measures will be undertaken at the field level by the CL-PIU safeguards focal person within
7 days. He/she will document the following information: (i) name of the person; (ii) date
complaint was received; (iii) nature of complaint; (iv) location and (v) how the complaint was
resolved.
9.9.3. Third level of GRM
227. Third level of GRM involves a Grievance Redress Committee (GRC) to address the
complaints that could not be resolved by the CL-PIU. It is constituted by the EA and will,
based on review of the grievances, address them in consultation with the NRA, CL-PIU, DL-
PIU, and affected persons. The GRC will consist of at least five members including NRA
leadership, affected persons, and stakeholder representative and others nominated to
provide impartial, balanced views on any issues. A hearing will be called at the GRC, if
necessary, where the affected person can present his/her concern and issues. The process
will promote conflict resolution through mediation. The GRC will meet as necessary when
there are grievances to be addressed. The GRC will suggest corrective measures at the field
level and assign clear responsibilities for implementing its decision within 15 days. The
functions of the GRC are: (i) to provide support to affected persons on problems arising from
environmental or social disruption, asset acquisition (where required), and eligibility for
entitlements, compensation, and assistance; (ii) to record grievances of affected persons,
categorize and prioritize them, and provide solutions within 15 days; and (iii) to report to the
aggrieved parties developments regarding their grievances and decisions of the GRC. The
safeguards focal person will be responsible for processing and placing all papers before the
GRC, recording decisions, issuing minutes of the meetings, and taking follow-up action to
see that formal orders are issued and the decisions carried out.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
100
9.9.4. Fourth level of GRM
228. If the grievance is not addressed by all the above mechanisms, the affected person
can seek legal redress in the formal legal court system. The GRM however does not prevent
affected persons from seeking legal redress at any time. The grievance redress mechanism
and procedure is depicted in Figure 8.
Figure 8: Grievance Redress Mechanism as Per EARF of EEAP
9.9.5. Procedure for Grievances Handling as Per National Law
229. The Work Procedure for Management of Grievance related to Reconstruction and
Rehabilitation, 2016 framed under the Reconstruction of Earthquake Affected Structures Act,
2015 has defined four mechanisms for grievance management which are listed below in
order of ascending hierarchy:
Local (Rural Municipality/Municipality Ward) Level Grievance Redress Committee
coordinated by the head of the adminsistrative unit.
District Level (District Administration Office (DAO)/DCC) Level Grievance Redress
Committee headed or coordinated by Chief District Officer (CDO).
Sub-regional Office of NRA
NRA coordinated by the committee member deployed by Executive Committee.
230. Complaints or greivances are received at the local level grievance redress committee
which will record and categorize them according to their subject. The grievances that cannot
be redressed by the local level committee are passed on to district level committee within 15
Not Redressed
15 days
Not Redressed
3rd
Level Grievances
4th
Level Grievances Higher Authority/Court of Law
GRC Grievances
Redressed
7days
1-2 days
Not Redressed
1st Level Grievances
2nd
Level Grievances
Contractor,
DL-PIU
Grievances
Redressed
CL-PIU Grievances
Redressed
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
101
days of receipt and so on. The sub-regional office is also mandated to coordinate and
facilitate in redress of grievance at local and district level. The work procedure provides
detailed guideline for receiving and addressing grievances related to construction of private
residence only. Although it mentions about other grievances related to rehabilitation and
reconstruction of other infrastructures and economic and social recovery, it is silent about
the detail procedure of handling such grievances. Nonetheless, these mechanisms can be
used to redress grievances related with reconstruction and rehabilation activites.
231. The Work Procedure related to land acquisition for Earthquake Affected Structures,
2016 has provisions related receiving and addressing complaints related to land acquired for
rehabilitation and reconstruction of infrastructures. The details about the land allowed for
acquisition shall be published in a national or local daily newspaper to solicit grievance from
the respective owner. The affected party can lodge a complaint with reasons at the executive
committee within 15 days. The executive committee will conduct necessary investigations
and address the complaint within 10 days of receipt of the complaint and notify the affected
party and program head. As per the procedure, complaints can be lodged regarding
dissatisfaction on the compensation fixed for the land to be acquired. The complaint will to
be addressed by the executive committee within 7 days of receipt.
Figure 9: Grievance Redress Mechanism in National Law
Local Level
GRC
Not Redressed
1st Level Grievances Grievances
Redressed
Grievances
Redressed
Not Redressed
3rd
Level Grievances
4th
Level Grievances NRA/Central Office
Sub-Regional
NRA Office
Grievances
Redressed
Not Redressed
2nd
Level Grievances District Level
GRC
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
102
10. CONCLUSION
232. The condition due to poor geometry of the Haldebesi – Dhobi – Dhandebesi Road
was further aggravated by the landslides triggered after the April 25 and May 12 earthquake.
The proposed road rehabilitation and reconstruction sub-project is essential to realize the full
potential of the existing infrastructure and for providing safe and easy access to people living
in the region. It will have long-term impact on the development of local areas. Besides these,
implementation of this sub-project is expected to bring several immediate short term benefits
like employment generation, increase in the local economy and enhancement of the
technical skills, especially during construction phase.
233. Moreover, the project has been expected to have minimal detrimental effect on the
physical, biological, socioeconomic and cultural environment of area. Most of the adverse
impacts (identified and predicted) are short and medium term in nature as well as reversible
in nature. Similarly, identified environmental adverse impacts are locally confined and limited
mainly to the period of construction. The sub-project needs acquisition of private land, but
that will not bring any resettlement. Few stands of trees have to be felled and few community
structures to be relocated. With set of the proposed mitigation measures, most of impacts
can be minimized or even set off. Bioengineering measures have been proposed in the
Design to stabilize slopes and control further slides. In addition, proposed road does not
exceed any of the thresholds prescribed by Work Procedure Related with Environmental
Impact Assessment for Rehabilitation of Earthquake Affected Structures, 2072 (2016) and
other relevant acts and rule. For this time, IEE is sufficient for implementation of project.
234. The sub-project can be undertaken with minimal harm to the physical, biological and
social environment of the area by adopting the safeguard measures described in this IEE
report.
235. The proposed rehabilitation and reconstruction sub-poject is recommended for
implementation with incorporation of the mitigation measures and environmental monitoring
plan. Key consideration should be given to settle down all the social and environmental
issues related to sub-project before implementation of sub-project works.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
103
REFERENCES:
ADB. (2009). Safeguard Policy Statement, June 2009. Asian Development Bank, Manila.
ADB. (2015). Environmental Assessment and Review Framework: Earthquake Emergency
Assistance Project, June 2015.
ADB. (2015). Project Administration Manual: Earthquake Emergency Assistance Project,
June 2015.
ADB. (2015). Resettlement Framework: Earthquake Emergency Assistance Project, June
2015.
An Act Made To Provide for Reconstruction of the Earthquake Affected Structures, 2015,
Nepal Gazette Section 65) Kathmandu 20 December 2015 (5 Poush 2072) (Extraordinary
Issue)
Baral, H.S and Shah K.B, (2064). Wild Mammals of Nepal. Himalayan Nature, Kathmandu.
Constitution of Nepal 2072, Ministry of Law, Justice and Parliamentary Affairs, Law Books
Management Board, Kathmandu
DDC Ramechhap. (2061). District profile of Dolakha, 2061, District Development
Committee, Ramechhap.
Dhital M.R. (2015). Geology of the Nepal Himalaya, Regional Geology Reviews, Springer
International Publishing Switzerland 2015, DOI 10.1007/978-3-319-02496-7_30
DoR. (2003). Reference manual for the Environmental and Social aspects of the Integrated
Road Development. Ministry of the Physical Planning and works Department of the Road,
Kathmandu.
DoR. (2007). Environmental and Social Management Framework, a guideline to the
environmental and social issues associated with new road construction and upgrading.
Ministry of the Physical Planning and Works, Department of Road, Kathmandu.
Earthquake Affected Structures Reconstruction Rules, 2016, Nepal Gazette Section 65)
Kathmandu 20 December 2015 (5 Poush 2072) (Extraordinary Issue)
Earthquake Affected Structures Reconstruction Work Procedures, 2016, Nepal Gazette
Volume 5, Section 65) Number 49 (2072/12/01) (Notices 1, 2 and 3), Kathmandu
Fleming, R Sr. and Jr. and Bangdel, L.S. (1976). Birds of Nepal. R.C. Fleming (Sr. and Jr.)
Kathmandu, Nepal.
GoN. (1995). Topographical Sheet No. 2786 01, 2786 05A and 2786 05B, Department of
Survey.
GoN. (1999). Approach for development of Agricultural and Rural roads
Grievance Management Procedure for Reconstruction of Earthquake Affected Structures,
2016, National Reconstruction Authority, Kathmandu
Inskipp, C. and Inskipp, T. (1985). A guide to birds of Nepal. Croom Helm, London,
England.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
104
IUCN. (2014). IUCN red list of threatened species, version 2012.2, www.iucnredlist.org
Jnwali, S.R., Baral, H.S., Lee, S., Acharaya, K.P., Upadhyay, G.P., Pandey, M., Shrestha, R.,
Joshi, D., Laminchhane, B.R., Griffiths, J., Khatiwada, A.P., Subedi, N., and Amin, R.
(2011). The Status of Nepal Mammals: The National Red List Series, Department of National
Parks and Wildlife Conservation Kathmandu Nepal
Labor Act, 1991, Ministry of Law, Justice and Parliamentary Affairs, Law Books
Management Board, Kathmandu
Local Self-Governance Act, 1999, Ministry of Law, Justice and Parliamentary Affairs, Law
Books Management Board, Kathmandu
Local Self-Governance Regulations, 2000, Ministry of Law, Justice and Parliamentary
Affairs, Law Books Management Board, Kathmandu
Martin, G.J. (1995). Ethnobotany: A People and Plant Conservation Manual. Chapman and
Hall, London.
MoE/NAPA. (2010). Climate Change Vulnerability Mapping for Nepal. Kathmandu, Nepal.
National Population and Housing Census, 2011, Central Bureau of Statistics.
National Environmental Impact Assessment Guidelines, 1993, Nepal Gazette Volume, 45
Number 19 Kathmandu
Polunin, O. and Stainton, A. (1984): Flowers of the Himalaya. Oxford University Press.
Press, J.R., Shrestha K. K. and Stainton, J. D.A. (2000): Annotated Checklist of the
Flowering Plants of Nepal, The Natural History Museum, London and Central Department
of Botany, Tribhuvan University, Kathmandu, Nepal
Shrestha, K. (1985). A Field Guide to Nepali Names for Plants. Natural History Museum,
Institute of Science and Technology, T.U., Kathmandu, Nepal.
Singh, A.P. (2001). Flowering Plants of Nepal (Phanerogams). Bulletin of Department of
Plant Resources No. 18. HMG/N, MoFSC, Dept. of Plant Resources, National Herbarium and
Plant Laboratories, Godavary, Lalitpur, Nepal.
Solid Waste Management and Resource Mobilization Act 2011, Ministry of Law, Justice and
Parliamentary Affairs, Law Books Management Board, Kathmandu
Solid Waste Management and Resource Mobilization Regulation 2012, Ministry of Law,
Justice and Parliamentary Affairs, Law Books Management Board, Kathmandu
Uprety, B.K. (2003). Safeguarding the resources Environmental Impact Assessment process
and Practice. Utara Uprety, Kathmandu.
Water Resources Act 1992, Ministry of Law, Justice and Parliamentary Affairs, Law Books
Management Board, Kathmandu
Water Resources Regulation 1993, Ministry of Law, Justice and Parliamentary Affairs, Law
Books Management Board, Kathmandu
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
105
Appendix
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
106
Appendix 1: Terms of Reference approval letter &
Approved ToR
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
107
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
108
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
109
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
110
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
111
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
112
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
113
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
114
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
115
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
116
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
117
Appendix 2: Environmental Assessment Checklists
2a: Rapid Environmental Assessment (REA) Checklist Instructions:
(i) The PMU completes this checklist to support the environmental classification of a
project. It is to be attached to the environmental categorization form and submitted
to ADB.
(ii) This checklist focuses on environmental issues and concerns. To ensure that social
dimensions are adequately considered, refer also to ADB's (a) checklists on
involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook;
(c) staff guide to consultation and participation; and (d) gender checklists.
(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.
Subroject Title:
IA:
SCREENING QUESTIONS Yes No REMARKS
A. Project sitting
Is the project area adjacent to or within any
of the following environmentally sensitive
areas?
Cultural heritage site
Protected area
Wetland
Mangrove
Estuarine
Buffer Zone of Protected Area
Special area for protecting
biodiversity
B. Potential environmental impacts
Will the project cause…
Haldebesi-Dhobi-Dhandebesi Road Rehabilitation and Reconstruction
Sub-Project
MoFALD and DCC/DTO
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
118
SCREENING QUESTIONS Yes No REMARKS
Encroachment on historical/cultural
areas; disfiguration of landscape by
road embankments, cuts, fills, and
quarries?
There are no historic or cultural
areas along the road alignment.
Disfiguration of landscape will
occur due to cut and fill, however,
cut and fill volume will be
balanced.
Encroachment on precious ecology
(e.g. Sensitive or protected areas)?
Alteration of surface water hydrology
of waterways crossed by roads,
resulting in increased sediment in
streams affected by increased soil
erosion at construction site?
Deterioration of surface water quality
due to silt runoff and sanitary wastes
from worker-based camps and
chemicals used in construction?
There will be no significant
impact.
Increased local air pollution due to
rock crushing, cutting and filling
works, and chemicals from asphalt
processing?
There will be no significant air
pollution as is reconstruction of
existing gravel road
Risks and vulnerabilities related to
occupational health and safety due to
physical, chemical, biological, and
radiological hazards during project
construction and operation during
project construction and operation?
Noise and vibration due to blasting
and other civil works
Dislocation or involuntary
resettlement of people
Resettlement Plan will be
prepared to address involuntary
resettlement of the affected
people.
Dislocation and compulsory
resettlement of people living in right-
of-way?
Private structures like house and
shop will be dislocated within the
formation width of the road and
they will be provided with
compensation based on
Resettlement Plan.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
119
SCREENING QUESTIONS Yes No REMARKS
Disproportionate impacts on the poor,
women and children, Indigenous
Peoples or other vulnerable groups?
Other social concerns relating to
inconveniences in living conditions in
the project areas that may trigger
cases of upper respiratory problems
and stress?
Not envisaged.
Hazardous driving conditions where
construction interferes with pre-
existing roads?
Poor sanitation and solid waste
disposal in construction camps and
work sites, and possible transmission
of communicable diseases from
workers to local populations?
The road will be constructed by
the local people who will come
from their home for work and
campsite management will be
done for workers outside the
project area.
Creation of temporary breeding
habitats for mosquito vectors of
disease?
Road construction is in hilly
region. So, there will be no
breeding habitats for
mosquitoes.
Accident risks associated with
increased vehicular traffic, leading to
accidental spills of toxic materials and
loss of life?
Traffic volume is negligible.
Increased noise and air pollution
resulting from traffic volume?
Traffic volume will be minimal
and traffic speed will be very
slow (<20km/hour) due to
earthen raod.
Increased risk of water pollution from
oil, grease and fuel spills, and other
materials from vehicles using the
road?
Social conflicts if workers from other
regions or countries are hired?
Large population influx during project
construction and operation that
causes increased burden on social
infrastructure and services (such as
water supply and sanitation
systems)?
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
120
SCREENING QUESTIONS Yes No REMARKS
Risks to community health and safety
due to the transport, storage, and use
and/or disposal of materials such as
explosives, fuel and other chemicals
during construction and operation?
Community safety risks due to both
accidental and natural causes,
especially where the structural
elements or components of the
project are accessible to members of
the affected community or where their
failure could result in injury to the
community throughout project
construction, operation and
decommissioning.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
121
2b: Checklist for Preliminary Climate Risk Screening Country/Project Title: Nepal, Earthquake Emergency Assistance Project (EEAP)
Sector : Emergency Assistance
Sub-sector: Road
Division/Department: District/Rural Road(MoFALD/DCC)
Screening Questions Score Remarks
Location and
Design of
project
Is sitting and/or routing of the project (or its components) likely
to be affected by climate conditions including extreme weather
related events such as floods, droughts, storms, landslides?
1 Landslide
Would the project design (e.g. the clearance for bridges) need
to consider any hydro-meteorological parameters (e.g., sea-
level, peak river flow, reliable water level, peak wind speed
etc.)?
0
Materials
and
Maintenance
Would weather, current and likely future climate conditions
(e.g. prevailing humidity level, temperature contrast between
hot summer days and cold winter days, exposure to wind and
humidity hydro-meteorological parameters likely affect the
selection of project inputs over the life of project outputs (e.g.
construction material)?
1
Would weather, current and likely future climate conditions,
and related extreme events likely affect the maintenance
(scheduling and cost) of project output(s)?
1
Performance
of project
outputs
Would weather/climate conditions and related extreme events
likely affect the performance (e.g. annual power production) of
project output(s) (e.g. hydro-power generation facilities)
throughout their design life time?
2 Gravel
Road
Options for answers and corresponding score are provided below:
Response Score
Not Likely 0
Likely 1
Very Likely 2
Responses when added that provide a score of 0 will be considered low risk project. If adding all
responses will result to a score of 1-4 and that no score of 2 was given to any single response, the
project will be assigned a medium risk category. A total score of 5 or more (which include providing a
score of 1 in all responses) or a 2 in any single response will be categorized as high risk project.
Result of Initial Screening (Low, Medium, High): 5 (High)
Other Comments: For it is a hill road, the road and its performance is very likely to be affected by
impacts of climate change and climate induced extreme events, especially heavy rainfall.
Prepared by:
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
122
Appendix 3: Checklists for Baseline Information Collection
A. Physical Environment
Parameter Description
Topography
Geology (Rock and Soil Types)
Erosion and Sedimentation
Quarry Sites
Sites for Labour Camp
Site for Storage and Stockpiling
Access and Diversion if necessary
River Training Works
Land Use
Air Quality
Water Quality
Noise Level
Spoil disposal sites
Drainage Network and Ground
Water
Status of Channel Shifting
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
123
B. Vegetation and Wildlife
Vegetation in the project area
SN Local
Name
Botanical
Name
Location Vegetation
Type
Local
Status
Local
Use
Protection Status
GoN IUCN CITES
Mammals in the project area
SN Common
Name
Scientific
Name
Habitat Local
Status
Crop/Livestock
Raider
Local
Use
Protection Status
GoN IUCN CITES
Birds Sighted in the project area
SN Common
Name
Scientific
Name
Type Habitat Local
Status
Protection Status
IUCN CITES GoN
Herpeto-fauna in the Project Area
S.N. Local Name Scientific Name
Habitat Local Status
Status Code Local Use CITIES IUCN GoN
Fish in the Project Area
S.N. Local Name Scientific Name Status of Occurrence
Migratory Status/Season
Observed Location
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
124
C. Socio-Economic and Cultural Environment along road alignment
Parameter Description (Chainagewise Detail)
Demography
a) Population (Male, Female)
b) Caste Ethnicity
c) Language
d) Religion and Culture
e) Literacy
Occupation
Migration Patten
Public Health and Sanitation
Drinking Water Supply
Education Facilities
Communication
Fuel and Energy
Road and Transportation
Land Holding
Food Sufficiency
Irrigation
Health Care System
Market
Business and Industries
Religious and Cultural Sites
Non governmental activities
Development Potential
Detail of Project Affected Structures
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
125
D. Landslides and Erosion Prone Areas along Road Alignment
SN Chainages Locations or
(Left/Right)
Size of
Failure Cause of Failure
Protection
Structure From To
E. Settlements and Population of the along the Road Corridor
SN Settlement VDC & Ward HH Population
Caste/Ethnicity Male Female Total
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
126
Appendix 4: Public Notice
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
127
Government of Nepal
Ministry of Federal Affairs and Local Development
Office of District Development Committee
Earthquake Emergency Assistance Project
District Level Project Implementation Unit
Ramechhap
Public notice for comments and suggestion on the Initial Environmental Examination
(Date of first publication: 2072/12/22)
Through the Earthquake Emergency Assistance Project (EEAP) being implemented by loan
and grant assistance from Asian Development Bank (ADB) and technical and grant assistance
from Swiss Agency for Development and Cooperation (SDC), counterpart funding from
Government of Nepal (GoN), District Development Committee (DDC) Ramechhap has
proposed rehabilitation and reconstruction of the following roads. In the course, this notice
has been published for the implementation of an Initial Environmental Examination (IEE)
report as per the provision of the Rule 7 (2) of the Environment Protection Rules 1997
(amended 1999 AD).
SN Proposed Road Affected VDCs Description of Project
1 Devitar-
Phulasipokhari
Phulasipokhari VDC Proposed road starts at Devitar of Phulasi
VDC and ends at Pokharidada of the same
Phulasi VDC. This road will be 16 km long
and 6.25 m wide with side drain.
2 Haldebesi-Dhobi-
Dhandbesi
Tilpung, Nagdaha,
Bijurikot, Saipu
VDCs
Proposed road starts at Haldebesi of Tilpung
VDC and ends at Dhandbesi of Saipu VDC.
This road will be 36 km long and 6.25 m
wide with side drain
It is requested to provide comments and suggestions about the impacts on the environment
through the implementation of sub-project, from the relevant VDCs, school, health post,
forest user group, concerned stakeholders, organization and local people within 15 days from
the first date of its publication in the following address. The comments and suggestions can
be sent to Department of Local Infrastructure Development and Agricultural Roads,
Pulchwok and Ministry of Federal Affairs & Local Development, Singhadurbar.
Address to send comments and suggestions:
District Development
Committee, Ramechhap
Telephone no: 048-540114
Fax No: 048-540029
District Technical Office,
Ramechhap, District
Implementation Unit
Telephone no: 048-540491
Fax No.: 048-540491
Earthquake Emergency Assistance
Project, Central Project
Implementation Unit
Telephone no: 01-5532331
Fax No: [email protected]
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
128
Appendix 5: Deeds of Inquiries
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
129
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
130
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
131
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
132
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
133
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
134
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
135
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
136
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
137
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
138
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
139
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
140
Appendix 6: Recommendation Letters
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
141
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
142
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
143
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
144
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
145
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
146
Appendix 7: Minutes of Public Consultations
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
147
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
148
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
149
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
150
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
151
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
152
Appendix 8: Tree Loss and Compensatory Plantation
8a) Trees to be Felled from Community Forest and Compensatory Plantation Requirement
Chainages Name of Forest Name of Species
to be Felled
Scientific Name Number of Trees
to be Felled
Compensatory
Plantation (1:25)
24+100 to
24+250
Jhateswari CF Chilaune Schima wallichii 6 150
Uttis Alnus nepalensis 2 50
Sub-Total 8 200
Cost of Plantation @NRs 157.15/plant (NRs) 31,430.00
26+000 to
26+200
Brhingeshwar CF Chilaune Schima wallichii 5 125
Sub-Total 5 125
Cost of Plantation @NRs 157.15/plant (NRs) 19,643.75
30+010 to
31+100
Poku Salgharni CF
(Saipu CF)
Chilaune Schima wallichii 9 220
Uttis Alnus nepalensis 5 125
Maledo Macaranga denticulata 1 25
Sub-Total 15 375
Cost of Plantation @NRs 157.15/plant (NRs) 58,931.25
36+010 to
36+090
Taruke Salleri CF Chilaune Schima wallichii 20 500
Sal Shorea robusta 5 125
Bhot Dhangera Lagerstroemia parviflora 5 125
Sub-Total 30 750
Cost of Plantation @NRs 157.15/plant (NRs) 117,862.50
37+000 to
37+150
Sipu Pakha CF Chilaune Schima wallichii 30 750
Pauwa 12 300
Uttish Alnus nepalensis 5 125
Sub-Total 47 1175
Cost of Plantation @NRs 157.15/plant (NRs) 184,651.25
Total 105 2625
Total Cost of Plantation in all CFs (NRs) 412,518.75
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
153
8b) Cost Calculation for Compensatory Plantation in CF
SN Description Unit Total quantity
Rate (NRs.)
Amount (NRs.)
Remarks
Seedling cost No 1760 20 35,200.00 20 Plantation per ha 20(1) Site selection and survey Persondays 3 535 1,605.00 20.2(b) Site clearance Persondays 10 535 5,350.00 25% shrubs and
grasses 20.3 Fixing of pit distance (1600 pits) Persondays 3 535 1,605.00 20.5(a)i Pitting of 45X30X30 cm pit Persondays 32 535 17,120.00 50% slope 20.6(a)iii Seedling transportation Persondays 6 535 3,210.00 1 km distance 20.6(b)iii Seedling transportation (within) Persondays 3 535 1,605.00 20.7(a) Plantation Persondays 20 535 10,700.00 Up to 50% slope 32.1(b) Weeding Persondays 18 535 9,630.00 32.3 Replacement plantation (10%) Persondays 9 535 4,815.00 33.1(b) Prunning Persondays 25 535 13,375.00 Up to 50% slope Sub-total 104,215.00 35 Fencing per 200 running meter 35.2(a)ii Preparation of 100 poles of 30-40cm girth and
1.8m height Persondays 8 535 4,280.00
35.4 Five line barbed wire fencing (100 running meter) 35.4(a) Barbed wire (14 gauge) Kg 143 125 71,500.00 Wooden pole (10cmx10cmx1.8m) No 88 No cost Unail Kg 4.2 125 2,100.00 35.3(b) Pitting for poles Persondays 14 535 29,960.00 35.4(c) Stretching and tightening of barbed wire Persondays 24 535 51,360.00 Sub-total 159,200.00 Total 263,415.00 Contingency (5%) 13,170.75 Grand Total 276,585.75 Per plant cost 157.15 1600+10% plants
with 2.5m x 2.5m spacing
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
154
8c) Sample Compensatory Plantation Agreement
Ifltk"lt{ a[Iff/f]k0f(Compensatory Plantation)
k[i7e"dL e"sDk cfktsfnLg ;xfotf cfof]hgf (EEAP) PlzofnL ljsf; a}+ssf] ;x'nLotk"0f{ C0f ;xof]u, :jL; ljsf; ;xof]u lgof]usf] k|fljlws ;xof]u tyf g]kfn ;/sf/sf] nufgLdf z'? ePsf] xf] o; cfof]hgfsf] p2]Zo @)&@ a}zfv !@ ut]sf] e"sDk kl5 e"sDkLo If]qdf k"glg{df0f / k"g{:yfkgf sfo{df ;xof]u ug{' xf] . o; cfof]hgfn] ljBfno, ;8s, ;/sf/L ejg k"glg{df0f ul/ ;Defljt k|sf]kaf6 ;dfg's"ng ug{' /x]sf] 5 . of] sfo{s|d k"glg{df0f / k"g{:yfkgf sfo{k2tLdf cfwfl/t /xg] 5 . o;n] ;8s If]qsf e"sDk k|efljt hgtfnfO{ ;xhtf k|bfg ug]{5 . sfe|]knf~rf]s lhNnfdf cjl:yt k|:tfljt xNb]a];L—wf]aL—9fF8]a];L u|fld0f ;8s pk–cfof]hgf e"sDk cfktsfnLg ;xfotf cfof]hgf (EEAP) cGtu{t
;+rfng ug{ nfuLPsf] Ps pkcfof]hgf xf] . xNb]a];L—wf]aL—9fF8]a];L ;8s pk–cfof]hgf /fd]5fk lhNnfsf] lnv' ufpFkflnsfsf] j8f &, %, $, # / @ -;fljs ltKn'ª, gfubx, lah'lnsf]6 uf=lj=;=_ af6 k|j]z ub{5 . of] ;8ssf] rf}8fO{ ^=@% dL= / hDdf nDafO{ #*=*(( ls=dL= kb{5 . ;fGb{lestf g]kfn ;/sf/sf] ;/sf/L ?vx? x6fpg] ;DaGwL dfkb08 @)&! cg';f/ b]lj6f/—km'n;Lkf]v/L ;8s pk–cfof]hgfsf] lgdf{0f s|ddf sfl6g] ?vx?sf] Ifltk"lt{ ;DaGwdf hlt ?v sfl6G5g To;sf] !M@% cg'kftdf Ifltk"lt{ a[Iff/f]k0f / % aif{ ;Dd ;+/If0f ug'{ kg]{ x'G5 . jgdf sfl6g] ?vx?sf] ;+Vof / Ifltk"lt{ jfkt a[Iff/f]k0f ug'{ kg]{ ?v ;+Vof / cg'dflgt nfut pk/f]Qm cg';f/ xNb]a];L—wf]aL—9fF8]a];L ;8s pk–cfof]hgf ;fd'bflos eP/ hfg] / sfl6g] ?vx?sf] ;+Vof, Ifltk"lt{ jfkt a[Iff/f]k0f ug'{ kg]{ ?v ;+Vof / cg'dflgt nfut ;d]t 6]a'n !df lbO{Psf] 5 . 6]a'n != ;fd'bflos jgdf sfl6g] ?vx?sf] ;+Vof, Ifltk"lt{ jfkt a[Iff/f]k0f ug'{ kg]{ ?v ;+Vof / cg'dflgt nfut l;g+
jgsf] gfd sfl6g] ?v ;+Vof
Ifltk"lt{ a[Iff/f]k0f ?v ;+Vof -!M@%_
la?jf, a[Iff/f]k0f / 3]/jf/ nfut klxnf] ls:tf -g]=?=_
uf]8d]n, k'g/f]k0f nfut bf]>f] ls:tf -g]=?=_
hDdf nfut -g]=?=_
! em6]Zj/L ;f= j= * @)) @*,!!)=)) #,#@)=)) #!,$#)=))
@ >L e[Ë]Zj/ ;f= j= % !@% !&,%^*=&% @,)%)=)) !(,^$#=&%
# kf]s' ;fn3f/L -;}k'_ ;f= j=
!% #&% %@,&)^=@% ^,@@%=)) %*,(#!=@%
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
155
l;g+
jgsf] gfd sfl6g] ?v ;+Vof
Ifltk"lt{ a[Iff/f]k0f ?v ;+Vof -!M@%_
la?jf, a[Iff/f]k0f / 3]/jf/ nfut klxnf] ls:tf -g]=?=_
uf]8d]n, k'g/f]k0f nfut bf]>f] ls:tf -g]=?=_
hDdf nfut -g]=?=_
$ tf?s] ;Nn]gL ;f=j=
#) &%) !)%,$!@=%) !@,$%)=)) !!^,*^@=%)
% ;}k' kfvf ;f=j= $& !,!&% !^%,!$^=@% !(,%)%=)) !*$,^%!=@%
hDdf #^*,($#=&% $#,%&%=)) $!@,%!*=&%
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
156
lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no /
lhNnf jg sfof{no /
;fd'bflos jg pkef]Qmf ;d"xsf] aLrdf Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_ sfof{Gjog ug { ePsf] ;+Demf}tf -Agreement_ kq s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf ;dGjo ;ldlt ÷lhNNff k|fljlws sfof{no, /fd]5fk != Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{, a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
. #= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf ldnfpg] . lhNnf jg sfof{no, /fd]5fk != lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] . @= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf ;dGjo ;ldlt÷lhNnf k|fljlws sfof{nodf k|utL k|ltj]bg k]z ug]{ . #= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf ;dGjo ;ldlt ÷lhNnf k|fljlws
sfof{nonfO{ ;xof]u k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] . ;fd'bflos jg pkef]Qmf ;d"x, >L e[Ë]Zj/ ;f= j= != a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ . @= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x 'g] . $= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
157
%= lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no÷lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ . v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf sfof{Gjog ;xof]u OsfO ÷lhNnf :t/Lo cfof]hgf sfof{Gjog OsfO, /fd]5fk
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf jg sfof{no tyf lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no;+u ;dGjo ug]{ . @= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] . $= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfoaf6 a[Iff/f]k0f cg'udg ug{ cfPsf] 6f]nLnfO{ ;xof]u k'¥ofpg] . u_ e'QmfgL ug]{ sfo{ ljlwM ;8s lgdf{0f s|ddf sfl6g] % ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f - !@% ?vx?_ jfkt hDdf g] ?= !(,^$#=&% lgDgfg';f/ pknAw u/fO{g] 5 . !—klxnf] ls:tfM a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? !&,%^*=&% ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @—bf]>f] ls:tfM a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd g] ?= @,)&%=)) ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] . lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf] tkm{ af6
;fd'bflos jg pkef]Qmf ;d"xsf] tkm{ af6
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
158
lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no /
lhNnf jg sfof{no /
;fd'bflos jg pkef]Qmf ;d"xsf] aLrdf Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_ sfof{Gjog ug { ePsf] ;+Demf}tf -Agreement_ kq s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf ;dGjo ;ldlt ÷lhNNff k|fljlws sfof{no, /fd]5fk != Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{, a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
. #= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf ldnfpg] . lhNnf jg sfof{no, /fd]5fk != lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] . @= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf ;dGjo ;ldlt÷lhNnf k|fljlws sfof{nodf k|utL k|ltj]bg k]z ug]{ . #= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf ;dGjo ;ldlt ÷lhNnf k|fljlws
sfof{nonfO{ ;xof]u k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] . ;fd'bflos jg pkef]Qmf ;d"x, em6]Zj/L ;f= j= != a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ . @= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x 'g] . $= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
159
%= lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no÷lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ . v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf sfof{Gjog ;xof]u OsfO ÷lhNnf :t/Lo cfof]hgf sfof{Gjog OsfO, /fd]5fk
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf jg sfof{no tyf lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no;+u ;dGjo ug]{ . @= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] . $= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfoaf6 a[Iff/f]k0f cg'udg ug{ cfPsf] 6f]nLnfO{ ;xof]u k'¥ofpg] . u_ e'QmfgL ug]{ sfo{ ljlwM ;8s lgdf{0f s|ddf sfl6g] 8 ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f - @)) ?vx?_ jfkt hDdf g] ?= #!,$#)=)) lgDgfg';f/ pknAw u/fO{g] 5 . !—klxnf] ls:tfM a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? @*,!!)=)) ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @—bf]>f] ls:tfM a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd g] ?= #,#@)=)) ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] . lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf] tkm{ af6
;fd'bflos jg pkef]Qmf ;d"xsf] tkm{ af6
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
160
lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no /
lhNnf jg sfof{no /
;fd'bflos jg pkef]Qmf ;d"xsf] aLrdf Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_ sfof{Gjog ug { ePsf] ;+Demf}tf -Agreement_ kq s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf ;dGjo ;ldlt ÷lhNNff k|fljlws sfof{no, /fd]5fk != Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{, a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
. #= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf ldnfpg] . lhNnf jg sfof{no, /fd]5fk != lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] . @= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf ;dGjo ;ldlt÷lhNnf k|fljlws sfof{nodf k|utL k|ltj]bg k]z ug]{ . #= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf ;dGjo ;ldlt ÷lhNnf k|fljlws
sfof{nonfO{ ;xof]u k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] . ;fd'bflos jg pkef]Qmf ;d"x, kf]s' ;fn3f/L -;}k'_ ;f= j= != a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ . @= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x 'g] . $= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
161
%= lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no÷lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ . v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf sfof{Gjog ;xof]u OsfO ÷lhNnf :t/Lo cfof]hgf sfof{Gjog OsfO, /fd]5fk
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf jg sfof{no tyf lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no;+u ;dGjo ug]{ . @= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] . $= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfoaf6 a[Iff/f]k0f cg'udg ug{ cfPsf] 6f]nLnfO{ ;xof]u k'¥ofpg] . u_ e'QmfgL ug]{ sfo{ ljlwM ;8s lgdf{0f s|ddf sfl6g] !% ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f - #&% ?vx?_ jfkt hDdf g] ?= %*,(#!=@% lgDgfg';f/ pknAw u/fO{g] 5 . !—klxnf] ls:tfM a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? %@,&)^=@% ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @—bf]>f] ls:tfM a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd g] ?= ^,@@%=)) ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] . lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf] tkm{ af6
;fd'bflos jg pkef]Qmf ;d"xsf] tkm{ af6
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
162
lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no /
lhNnf jg sfof{no /
;fd'bflos jg pkef]Qmf ;d"xsf] aLrdf Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_ sfof{Gjog ug { ePsf] ;+Demf}tf -Agreement_ kq s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf ;dGjo ;ldlt ÷lhNNff k|fljlws sfof{no, /fd]5fk != Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{, a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
. #= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf ldnfpg] . lhNnf jg sfof{no, /fd]5fk != lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] . @= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf ;dGjo ;ldlt÷lhNnf k|fljlws sfof{nodf k|utL k|ltj]bg k]z ug]{ . #= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf ;dGjo ;ldlt ÷lhNnf k|fljlws
sfof{nonfO{ ;xof]u k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] . ;fd'bflos jg pkef]Qmf ;d"x, tf?s] ;Nn]gL ;f=j= != a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ . @= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x 'g] . $= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
163
%= lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no÷lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ . v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf sfof{Gjog ;xof]u OsfO ÷lhNnf :t/Lo cfof]hgf sfof{Gjog OsfO, /fd]5fk
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf jg sfof{no tyf lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no;+u ;dGjo ug]{ . @= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] . $= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfoaf6 a[Iff/f]k0f cg'udg ug{ cfPsf] 6f]nLnfO{ ;xof]u k'¥ofpg] . u_ e'QmfgL ug]{ sfo{ ljlwM ;8s lgdf{0f s|ddf sfl6g] #) ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f - &%) ?vx?_ jfkt hDdf g] ?= !!^,*^@=%) lgDgfg';f/ pknAw u/fO{g] 5 . !—klxnf] ls:tfM a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? !)%,$!@=%) ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @—bf]>f] ls:tfM a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd g] ?= !@,$%)=)) ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] . lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf] tkm{ af6
;fd'bflos jg pkef]Qmf ;d"xsf] tkm{ af6
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
164
lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no /
lhNnf jg sfof{no /
;fd'bflos jg pkef]Qmf ;d"xsf] aLrdf Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_ sfof{Gjog ug { ePsf] ;+Demf}tf -Agreement_ kq s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf ;dGjo ;ldlt ÷lhNNff k|fljlws sfof{no, /fd]5fk != Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{, a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
. #= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf ldnfpg] . lhNnf jg sfof{no, /fd]5fk != lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] . @= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf ;dGjo ;ldlt÷lhNnf k|fljlws sfof{nodf k|utL k|ltj]bg k]z ug]{ . #= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf ;dGjo ;ldlt ÷lhNnf k|fljlws
sfof{nonfO{ ;xof]u k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] . ;fd'bflos jg pkef]Qmf ;d"x, ;}k' kfvf ;f=j= != a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ . @= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x 'g] . $= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
165
%= lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no÷lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ . v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj lhNnf sfof{Gjog ;xof]u OsfO ÷lhNnf :t/Lo cfof]hgf sfof{Gjog OsfO, /fd]5fk
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf jg sfof{no tyf lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{no;+u ;dGjo ug]{ . @= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] . #= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] . $= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfoaf6 a[Iff/f]k0f cg'udg ug{ cfPsf] 6f]nLnfO{ ;xof]u k'¥ofpg] . u_ e'QmfgL ug]{ sfo{ ljlwM ;8s lgdf{0f s|ddf sfl6g] $& ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f - !,!&% ?vx?_ jfkt hDdf g] ?= !*$,^%!=@% lgDgfg';f/ pknAw u/fO{g] 5 . !—klxnf] ls:tfM a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? !^%,!$^=@% ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t pknAw u/fpg] . @—bf]>f] ls:tfM a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL / k'gM/f]k0f ug{_ afFsL /sd g] ?= !(,%)%=)) ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] . lhNnf ;dGjo ;ldlt÷lhNNff k|fljlws sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf] tkm{ af6
;fd'bflos jg pkef]Qmf ;d"xsf] tkm{ af6
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
x:tfIf/M gfdM kbM ldltM 5fkM
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
166
8d) Plantation Plan in District A. Compensatory plantation
Requirements for plantation activities 1) Coordination with DFO - Meeting will be held with DFO and CFUGs to discuss about the
plantation management
2) Agreement with DFO/CFUGs/DCC - Agreement will be done with DFO and DCC/DTO
for the compensatory plantation
3) Managing planting stock - Nursery establishment and operation
From DFO/CFUG nursery
From private nursery owner from districts
Fruit trees in private land - Horticulture farms in districts.
4) Identification and survey of plantation area - Plantation area will be identified by DFO
and survey will be done.
5) Fencing - Fencing will be done by concerned DFO/CFUG.
6) Pitting - Pits of 45cmx30cm x 30cm size will be dug.
7) Transportation of seedlings - From nursery to the planting sites
8) Planting - It will be done by the DFO/CFUGs in the starting of monsoon
9) Weeding - After the monsoon season, weeding is done to reduce the competition by
weeds.
10) Survival count - Before winter starts, survival of the plantation will be done for casualty
replacement before next monsoon.
Plan of Action for Plantation in CF Activities March
18 April 18
May 18 June 18
July 18 Aug 18 Sep 18 Oct 18
Agreement with DFO/CFUG/ DCC
Managing planting stock
Survey of plantation area
Fencing Pitting Transportation of seedlings
Planting Weeding Survival count
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
167
B. Roadside plantation
1) Coordination with local communities, RM and DFO - Meeting will be held with concerned
local communities, RM and DFO to discuss about the plantation management
2) Agreement with concerned stakeholders - Agreement will be done with concerned local
communities, RM and DFO for the road side plantation
3) Managing planting stock - Nursery establishment and operation
From DFO nursery
From private nursery owner from districts
Fruit trees in private land - Horticulture farms in districts.
4) Identification and survey of plantation area - Plantation area will be identified by
concerned local communities, RM, and DFO and survey will be done.
5) Fencing - Fencing will be done by concerned local communities, RM and DFO.
6) Pitting - Pits of appropriate size will be dug depending on species
7) Transportation of seedlings - From nursery to the planting sites
8) Planting - It will be done in the starting of monsoon
9) Weeding - After the monsoon season, weeding is done to reduce the competition by
weeds.
10) Survival count - before winter starts, survival of the plantation will be done for casualty
replacement before next monsoon.
Plan of Action for Roadside Plantation Activities March
18 April 18
May 18 June 18
July 18 Aug 18 Sep 18 Oct 18
Agreement with DFO/CFUG/ DCC
Managing planting stock
Survey of plantation area
Fencing Pitting Transportation of seedlings
Planting Weeding Survival count
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
168
Appendix 9: Abstract of Costs
9a: Civil Cost
Pay Item
No.
Description Unit Quantity Rate (NRs.) Amount (NRs.)
1 General 1.1 Insurance of works, plants, materials, loss and damage to equipments,
Contractor's workmen and employees and third party insurance against damage to other persons and property as per GCC clause 19.
L.S. 1.00
900,000.00
900,000.00
1.2 Provide site office at the mid-section of the road at location acceptable to the project manager within the contract package with accommodation facilities as specified in special provision
month
18.00
35,000.00
630,000.00
1.3 Carry out additional tests for material and works as required and instructed by the Engineer.(GCC Clause No. 33.1)
PS 1.00
200,000.00
200,000.00
1.4 Relocation of the utilities (water supply, telephone, etc,) and services as instructed by the Engineer as per DoLIDAR-Technical Specifications for Labour Based Construction Work of Agricultural & Rural Roads (Tech. Spec. for LBCWARR Clause No. G-10.
PS 1.00
300,000.00
300,000.00
1.5 Carry out maintenance of the existing road to keep the road serviceable throughout the contract period. Also provide and maintain traffic safety, control measures and temporary diversions during construction including water spraying thrice a week to avoid dust pollution as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. G-12.
month
18.00
38,000.00
684,000.00
1.6 Provide and installation of project information board of size 1.80 mx1.2 m along with iron posts including excavation, concreting, backfilling etc all complete as per DoR Standard Specification for Road and Bridge Works (SSRBW) July 2001,Section-108
No. 2.00
10,000.00
20,000.00
1.7 Provision and maintenance of labour camps payable monthly in equal instalments as per DoR Standard Specification for Road and Bridge Works (SSRBW) July 2001,Section-109 (3)
month
18.00
20,000.00
360,000.00
1.8 Establish, maintain and operate labaratory at the site with equipments furnishing required for testing specified quality of the materials as per DoR-
month
18.00
20,000.00
360,000.00
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
169
Pay Item
No.
Description Unit Quantity Rate (NRs.) Amount (NRs.)
SSRBW, Section-511
1.9 Environmental Mitigation Works as per EMP and as Instructed by the Engineer(DOR Section 109)
P.S. 1.00
300,000.00
300,000.00
1.10 Social Compiliance and safegaurds as per Resettlement Action Plan and GESI and as instructed by the Engineer(DOR Section 109)
P.S. 1.00
150,000.00
150,000.00
Sub-Total 3,904,000.00 2 Site Clearance
2.1 Clearing and Grubbing including cutting of all types of plants as per DoLIDAR-Technical Specifcations for Labour Based Construction of Agricultural and Rural Raods (Tech. Spec. for LBCWARR) Clause No.: 1-1.5(a), 1-1.5(b) & 1-1.6
m2 56,907.57
26.76
1,522,846.57
2.2 Dismantling of Culverts, bridges, pavements and other structures, including excavation, backfilling, stacking, disposing, handling and haulage up to a lead of 100 m along the lead route as per DoLIDAR-Technical Specifcations for Labour Based Construction of Agricultural and Rural Raods (Tech. Spec. for LBCWARR) Clause No.: 1-2(a)
m3 118.80
1,338.48
159,011.42
2.3 Dismantling gabion works and cobble pavements including stockpiling the reusable materials materials within 50m lead and disposal of nonusable material as per DoR-SSRBW, Section 202
m3 5,598.00
756.30
4,233,767.40
Sub-Total 5,915,625.40 3 Earthworks
3.1 Excavation in roadway and drain in all types of soil and rock materials including removal and satisfactory disposal of all materials at approved environmentally safe tipping area as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 2-1
m3
172,158.66
84.85
14,607,662.13
3.2 Excavation in foundation in structure in all types of soil materials including removal and satisfactory disposal of all materials at approved environmentally safe tipping area as per DoLIdar-Tech. Spec, for LBCWARR Clause No. 2-5
m3
6,708.21
137.02
919,158.93
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
170
Pay Item
No.
Description Unit Quantity Rate (NRs.) Amount (NRs.)
3.3 Construction of embankments, shoulders and other miscellaneous filling and backfilling in structure with approved materials as per design and drawing as per DoLIDAR-Tech. Spec. for LBCWARR Clause No.2-5
m3
20,341.14
100.64
2,047,132.53
3.4 Transportation of material beyond the initial lead within 1 km distance with safe disposal sites as instructed by the engineer.
m3 102,198.81
47.07
4,810,498.03
Sub-Total 22,384,451.63 4 Structural/ Side Drain/Cross Drainage Works Stone Masonry
4.1 Supply & place un-coursed random rubble stone masonry works in MM 5 cement sand mortar in the line & level all complete stone masonry work including full compensation for all labour, materials and other incidentals required to complete the work as per the specifications and drawings. It includes full compensation for using specially dressed stones on the face of wall with batter and provisions for weep hole as necessary as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 8
m3 11,322.13
6,941.26
78,589,875.85
Sub-Total 78,589,875.85 Gabion Works
4.2 Supply machine made fabrication of gabion boxes of different sizes with hexagonal mesh size of 100 mm x 120 mm including rolling, cutting and weaving (mesh wire 3.0 mm, selvedge wire 3.9 mm, binding wire 2.4 mm, all heavy zinc coated wires),assembling, placing in position, packing and filling of gabion create with rubble stone and tying by 2.4 mm binding wires all complete as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 17-1.4, 17-5 & 17-6
m3 7,506.50
4,384.85
32,914,876.53
4.3 Provide and place Geo-textile all complete as per drawing and specifications as per (DOR-SSRBW Section No.: 2404,3110)
m2 5,844.80
166.29
971,931.79
Sub-Total 33,886,808.32 Cross Drainage, Side Drainage and Protection Plain and Reinforced Cement Concrete
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
171
Pay Item
No.
Description Unit Quantity Rate (NRs.) Amount (NRs.)
4.4 Supply & place P.C.C. works M 10/20 as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 11
m3 227.92
8,349.77
1,903,096.28
4.6 Supply & place P.C.C. works M 20/20 as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 11
m3 1,196.32
12,762.72
15,268,297.19
4.7 Supply & place P.C.C. works M 25/20 as per DOR-SSRBW,July 2001,Section 2000
m3 139.10
16,065.59
2,234,643.24
4.8 Supply and place formwork for concrete works with all complete as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 9
m2 765.75
718.74
550,375.16
4.9 Supply & place TMT high tensile strength steel reinforcement of specified grade ( Fe 500) for RCC works including bending, centring & binding in position as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 10
T 16.73
101,226.84
1,693,018.97
4.10 Supply, Laying, fitting and fixing of hume pipe class NP3. It includes all operations required to complete the work and the jointing of pipes with 1:2 cement sand mortar as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 15-5 and 15-6
a 300 mm diameter pipe for irrigation purpose rm 112.50 4,599.91 517,489.88
b 600 mm diameter pipe as per DOLIDAR Item no 47-15-5,15-6-b
rm 165.00
8,113.43
1,338,715.95
c 900 mm diameter pipe as per DOLIDAR Item no 47-15-5,15-6-b
rm 52.50
14,938.65
784,279.13
4.11 Supply & place100 mm Dia. HDPE Pipe (6 kg/cm2) for weep hole as per Nepal Standard & directed by Engineer
rm 523.00
545.84
285,474.32
4.12 Backfilling works with approved soil materials with compaction as per DoLIDAR-Tech. Spec. for LBCWARR Clause No-2.5.4
m3 1,140.96
240.69
274,615.82
4.13 Supply and Place graded filter in backfilling in structures and cross drainage works as per (DOR-SSRBW Section No.: 2404,3110)
m3 155.83
2,080.16
324,140.79
Sub-Total 25,174,146.71 5 Pavement Works
5.1 Preparation of subgrade for rehabilitation works as per DoR-SSRBW (Standard Specification for Road & Bridge Works, 2001) SECTION No. 1003
m2 109,298.78
17.85
1,950,983.28
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
172
Pay Item
No.
Description Unit Quantity Rate (NRs.) Amount (NRs.)
5.2 Providing, laying, spreading, watering, leveling and compaction of natural sand gravel sub base grading as specified and according to the designed camber all complete as per DoR-SSRBW SECTION No. 1201
m3 11,625.90
1,284.10
14,928,815.62
5.3 Providing, laying, spreading, watering, leveling and compaction of capping layer of approved materials according to the designed camber all complete asper DoR-SSRBW, Section 1004
m3 241.62
1,075.28
259,807.00
5.4 Supplying and preparing 20 cm thick stone pitching work on the prepared granular bedding with stone available at site
m3 796.80
2,760.84
2,199,834.55
5.5 Providing, laying, spreading, watering, leveling and compaction of 12 cm thick natural sand gravel sub base grading for cobble pavement as specified and according to the designed camber all complete as per DoR-SSRBW SECTION No. 1201
m3 5,152.82
1,284.10
6,616,738.73
5.6 Supplying and preparation of 5 cm thick granular material and sand with mixing red soil and spreading in layer, watering, compacting and all complete.
m2 51,290.19
69.88
3,584,158.48
5.7 Supplying and construction of 8 cm thick coble pavement ( Breaked Coble ) on the prepared granular material bedding with spreading the spall/ Granular material and compacting with Steel Roller with all complete
m3 10,115.22
956.08
9,670,954.76
5.8 Breaking and supplying of rock for cobble manually and chiesel dressing it in the 8 cm sizes with all complete
m3 6,107.22
852.72
5,207,744.37
5.9 Providing, laying, spreading, watering, levelling and compaction of natural sand gravel wearing course class -1/class -2 lead upto 10m as per DoR-SSRBW SECTION No. 1205.
m3 472.00
1,427.72
673,880.98
Sub-Total 45,092,917.78 6 Road Furniture/Traffic Sign Boards
6.1 Supplying and placing standard RCC kilometer post (place at each km) all complete including painting, and writing etc. all complete as per specification and drawings (DOR-SSRBW SECTION No. 1501)
Nos. 32.00
2,677.65
85,684.80
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
173
Pay Item
No.
Description Unit Quantity Rate (NRs.) Amount (NRs.)
6.2 Supplying and placing standard RCC kilometer post (place at 5km interval ) all complete including painting, and writing etc. all complete as per specification and drawings (DOR-SSRBW SECTIONNo. 1501)
Nos. 7.00
6,018.46
42,129.22
6.3 Supplying and fixing in place R.C.C.delineater and guard post including excavation,paintng,and erectionetc. all complete as final drawing (DOR-SSRBW SECTION No. 1504)
Nos. 3,112.00
1,200.56
3,736,142.72
6.4 Supplying and erecting traffic sign in place including 50 mm dia steel tube, 2mm thick steel plate, cement concrete, painting, writing and supporting steel angle nut and bolt etc complete as per DoR-SSRBW SECTION No. 1501)
a 60 cm dia circular, 60 cm equilateral triangle and 60 x 45 cm rectangular shaped sign (Single post)
Nos. 180.00
1,697.45
305,541.00
b 1.2m x 0.75 m size bigger traffic sign with back support and two or more post
Nos. 14.00
3,257.27
45,601.78
Sub-Total 4,215,099.52 7 Bio-engineering Work
7.1 Slope trimming work DoLIDAR : 4 Spec.Clause No.: 2-1.3.2,2-1.8 and 2-1.95
m2 6,100.00
77.97
475,617.00
7.2 Construction of Rip-rap drain with the stone pitching work of 20 cm thick and 1.2 m wide as per DoLIDAR-Tech. Spec. for LBCWARR Clause No. 8
rm 450.00
576.73
259,528.50
7.3 Dry stone check/toe walls for segmentation and support of slopes DoLIDAR Tech. Spec. clause No. 8
m3 722.20
3,030.02
2,188,280.44
7.4 Brush layering work: including preparation of terraces of 30 - 40 cm wide and laying live cuttings of selected Species along the terrace @ 5 cm c/c with 2/3 of cuttings in to terrace and leaving one bud and up to 1/3 of the cuttings sticking beyond the terrace edge (Cutting can be of assuro,simali etc of 45 - 60 m length) DoLIDAR Spec.Clause no.70-6.7 b
rm 6,100.00
124.04
756,644.00
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
174
Pay Item
No.
Description Unit Quantity Rate (NRs.) Amount (NRs.)
7.5 Planting rooted grass slips on slopes < 45˚ including preparation of slips on site. Operation includes digging planting holes to a maximum of 5 cm depth with metal or hardwood peg, depending on nature of soil. The planting drills should be spaced 10 cm apart as per Bio engineering information of DOR
m2 6,100.00
243.17
1,483,337.00
7.6 Planting containerised tree and shrub seedlings, including pitting, transplanting, composting and placing tree guards, on toe of embankment slopes in plain areas, not less than 8 m from the road centre line. Pit size 30 cm diameter×30 cm depth. Compost volume ⅟₄ of the volume of pit, mixed with original soil as per Bio engineering information of DOR
Nos. 407.00
62.24
25,331.68
Sub-Total 5,188,738.62 8 Day works
8.1 Supply of labour as required as per preamble and as instructed by the Engineer.
b) Skilled labour day 150 735.00
110,250.00
c) Unskilled labour day 400 565.00
226,000.00
8.2 Supply of excavator for maintenance of road as required and instructed by engineer
hr 180 1,000.00
180,000.00
8.3 Provide Built up Drawings as completed
L.S. 75,000.00
Sub-Total 591,250.00 Base Cost (A) 224,942,913.83 13% VAT (B) 29,242,578.80 Total Cost including Base Cost and VAT (C) 254,185,492.62 Cost Per Kilometer of construction works including Base Cost and
VAT (D) 6,534,499.41
Work Charge Staff & Miscellaneous Expenses @ 3% (E) 6,748,287.41 Physical Contingency @ 10% (F) 22,494,291.38 Grand Total (G) 283,428,071.42
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
175
9b: Project Cost including Socio-Environmental Cost
SN Particulars Amount (NRs.)
1 Environmental Management Cost
1.1 Environmental/conservation awareness program 250,000.00
1.2 Tourism promotion awareness (A three days homestay management training to 15 people from project
area)
150,000.00
1.3 Hoarding boards at road site (4 places) for awareness about important wildlife and their conservation. 200,000.00
1.4 Compensatory plantation & protection cost for trees on CF 110005.00
1.5 Roadside plantation 200,000.00
1.6 Solidwaste collection bins 50,000.00
1.7 Environmental monitoring cost 200,000.00
Sub-total (I) 1,462,518.75
2 Other environmental cost (included in civil works cost also)
2.1 Contractor's workmen and employees and third party insurance against damage to other persons and
property (Ref Appendix 9, item 1.1)
900,000.00
2.2 Relocation of Utilities (water supply and telephone poles) (Ref Appendix 9, item 1.4) 300,000.00
2.3 Maintenance of existing road, providing and maintaining traffic safety, control measures and temporary
diversions during construction including water spraying thrice a week to avoid dust pollution. (Ref
Appendix 9, item 1.5)
38,000.00
2.4 Labour camp maintenance (Ref Appendix 9, item 1.7) 20,000.00
2.5 Environmental Mitigation Works (Ref Appendix 9, item 1.9) 300,000.00
2.6 Social Compliance and Safeguard (Ref Appendix 9, item 1.10) 150,000.00
2.7 Spoil Disposal 4,810,498.03
2.8 Bioengineering and landslide retention (Ref Appendix 9, item 7) 5,188,738.62
2.9 Installation of traffic signals (Ref Appendix 9, item 6.4) 351,142.78
Subtotal II 12,058,379.43
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
176
SN Particulars Amount (NRs.)
3 Civil Work Cost
3.1 Total Civil Cost (Including VAT and Contingencies) 283,428,071.42
3.2 Other environmental cost included in civil works cost as given in SN 2 12,058,379.43
3.3 Civil excluding other environmental cost (Subtotal III) 271,369,691.99
4 Resettlement Plan Cost (This plan is under preparation, hence the cost is not included here)
4.1 Compensation cost (land, relocation cost for private and community structures within RoW) 1,803,871.28
4.2 Deed transfer assistance and fees 17,100.00
4.3 Income generation and livelihood improvement training 800,000.00
4.4 Contingency (20%) 364,194.26
Subtotal IV 2,985,165.54
5 Gender Equality and Social Inclusion Plan Cost
5.1 WASH Awareness Training 25,000.00
5.2 Psycho-social Counseling 25,000.00
5.3 Livelihood Improvement Training 50,000.00
Subtotal V 100,000.00
Total Project Cost (I+II+III+IV+V) 287,975,755.71
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
177
Appendix 10: List of Affected Structure
SN Picture Detail
1 Chainage 21+900
Name of Owner Govinda Shrestha
Address Likhu -4
Structure Type house
Built Year 2072
Present Status Good
Family Member (no.) 5
Food Sufficiency (Month) 6 Months
Total Agricultural Income
(NRs.)
30000
Total Non-agricultural
Income (NRs.)
50,000
Total Affected Area (sqm)
Total cost (NRs.)
2
Chainage 21+900
Name of Owner Maila Mahara
Address Likhu -4
Structure Type house
Built Year 2072
Present Status Good
Family Member (no.) 6
Food Sufficiency (Month) 3 Months
Total Agricultural Income
(NRs.)
Total Non-agricultural
Income (NRs.)
Total Affected Area (sqm)
Total cost (NRs.)
3
Chainage 22+400
Structure Type House/Cottage
Name of owner Sher Bdr Tamang
Address Likhu Rural Muni. -3
Built Year 2030
Use & Beneficiary
Present Status House is fare but cottage
is half damage
Total cost (NRs.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
178
4
Chainage 22+500
Structure Type Cottage
Name of owner Dolkumari Shrestha
Address Likhu Rural Muni. -3
Built Year 2068
Use & Beneficiary
Present Status weak
Total cost (NRs.)
5
Chainage 2300
Structure Type House/Cottage
Name of Owner Dal Bdr. Shrestha
Address Likhu Mun.-3
Built Year 2058
Use & Beneficiary
Present Status House is fare but cottage
is half damage
Total cost (NRs.)
6
Chainage 0+2500
Structure Type Balkuni
Name of owner Chun Naryan Shrestha
Address Likhu Mun.-3
Built Year 2040
Use & Beneficiary
Present Status Good
Total cost (NRs.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
179
7
Chainage 0+2500
Structure Type Balkuni of house
Name of Owner Indra Narayan. Shrestha
Address Likhu Mun.-3
Built Year 2058
Use & Beneficiary
Present Status Good
Total cost (NRs.)
8
Chainage 25+ 200
Structure Type Cottage
Name of owner Tilak Timilsina
Address Likhu Mun.-3
Built Year 2073
Use & Beneficiary
Present Status good
Total cost (NRs.)
9
Chainage 25+600
Structure Type Cottage
Name of Owner Kewal Timilsina
Address Likhu Mun.-3
Built Year 2058
Use & Beneficiary
Present Status Good
Total cost (NRs.)
10
Chainage 26+300
Structure Type Cottage
Name of owner Chakra Bdr. Tamang
Address Likhu Mun.-3
Built Year 2055
Use & Beneficiary
Present Status Some are good and some
are worth
Total cost (NRs.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
180
11
Chainage 26+300
Structure Type Cottage
Name of owner Dhudhi Tamang
Address Likhu Mun.-3
Built Year 2055
Use & Beneficiary
Present Status Some are good and some
are worth
Total cost (NRs.)
12
Chainage 26+400
Structure Type Balkuni of house
Name of Owner Suntali Tamang
Address Likhu Mun.-3
Built Year 2058
Use & Beneficiary
Present Status weak
Total cost (NRs.)
13
Chainage 26+450
Structure Type Top corner of the hose
and cottage
Name of owner Yam Bdr. Tamang
Address Likhu Mun.-3
Built Year 2040
Use & Beneficiary
Present Status good
Total cost (NRs.)
14
Chainage 27+300
Structure Type Half part of house
Name of Owner Tilak Tamang
Address Likhu Mun.-3
Built Year 2043
Use & Beneficiary
Present Status Good
Total cost (NRs.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
181
15
Chainage 28+100
Structure Type Half part of house
Name of Owner Gumba Tamang
Address Likhu Mun.-3
Built Year 2038
Use & Beneficiary
Present Status good
Total cost (NRs.)
16
Chainage 28+200
Structure Type House and Cottage
Name of Owner Jit Bdr. Tamang
Address Likhu Mun.-3
Built Year 2040
Use & Beneficiary
Present Status weak
Total cost (NRs.)
17
Chainage 28+400
Structure Type House
Name of owner Gole Tamang
Address Likhu Mun.-3
Built Year 2072
Use & Beneficiary
Present Status good
Total cost (NRs.)
18
Chainage 29+200
Structure Type Cottage with fence
Name of Owner Bhoj Bdr. Magara
Address Likhu Mun.-3
Built Year 2070
Use & Beneficiary
Present Status Good
Total cost (NRs.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
182
19
Chainage 29+300
Structure Type Cottage
Name of owner Gope Tamang
Address Likhu Mun.-3
Built Year 2072
Use & Beneficiary
Present Status good
Total cost (NRs.)
20
Chainage 32+800
Structure Type Balkuni of house and
Cottage
Name of Owner Jit Bdr. Tamang
Address Likhu Rural Muni. 2
Built Year 2058
Use & Beneficiary
Present Status Good
Total cost (NRs.)
21
Chainage 33+000
Structure Type cottage
Name of owner Lok Bdr. Raut
Address Likhu Rural Muni.
Built Year 2072
Use & Beneficiary
Present Status good
Total cost (NRs.)
22
Chainage 33+050
Structure Type Half part of house
Name of Owner Chet Bdr. Thapa
Address Likhu Rural Muni.
Built Year 2030
Use & Beneficiary
Present Status Good
Total cost (NRs.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
183
23
Chainage 33+050
Structure Type Half part of house
Name of Owner Dhan Raj Raut
Address Likhu Rural Muni.
Built Year 2040
Use & Beneficiary
Present Status good
Total cost (NRs.)
24
Chainage 33+100
Structure Type Half part of house
Name of Owner Gopal Basnet
Address Likhu Rural Muni.
Built Year 2030
Use & Beneficiary
Present Status good
Total cost (NRs.)
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
184
Appendix 11: Grievance Redress Mechanism
Sample Grievance Intake Form Name of Project
Project ____________ welcomes complaints, suggestions, comments and queries
regarding the project implementation and its stakeholders. We encourage persons with
grievance to provide their name and contact information to enable us to get in touch with
you for clarification and feedback.
Should you choose to include your personal details but want that information to remain
confidential, please inform us by writing/typing "(CONFIDENTIAL)" above your name.
Thank you.
Contact Information
Name Gender Male
Female
Home Address Age
Phone No
City/District
Complaint/Suggestion/Comment/Question Please provide the details(who ,what
where and how) of your grievance below:
How do you want us to reach you for feedback or update on your comment/grievance?
Portion to be filled in by the staff:
Date received:
Received through:
Name of Staff who
receive
comment/complaint
Position of staff:
Type of Grievance;
Remarks
Signature of Staff
Update on the case:
Date: Update
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
185
Appendix 12: Environmental and Social Monitoring Report
Outline
The level of detail and comprehensiveness of a monitoring report is commensurate with the
complexity and significance of social and environmental impacts. A safeguard monitoring
report may include the following elements:
(a) Background/context of the monitoring report (adequate information on the project,
including physical progress of project activities, scope of monitoring report, reporting period,
and the monitoring requirements including frequency of submission as agreed upon);
(b) Changes in project scope and adjusted safeguard measures, if applicable;
(c) Qualitative and quantitative monitoring data;
(d) Monitoring parameters/indicators and methods based on the monitoring plan/program
previously agreed upon with ADB;
(e) Monitoring results compared against previously established benchmarks and compliance
status (e.g., national environmental emission and ambient standards and/or standards set out
in the World Bank Group’s Environmental, Health and Safety Guidelines guidelines;
timeliness and adequacy of environmental mitigation measures; involuntary resettlement
compensation rates and timeliness of payments, adequacy and timeliness of involuntary
resettlement rehabilitation measures including serviced housing sites, house reconstruction,
livelihood support measures, and training; budget for implementing environment
management plan (EMP), resettlement plan,, timeliness and adequacy of capacity building,
etc.);
(f) Monitoring results compared against the objectives of safeguards or desired outcomes
documented (e.g. involuntary resettlement impacts avoided or minimized; livelihood restored
or enhanced; environmental impacts avoided or minimized, etc.);
(g) If noncompliance or any major gaps identified, include a corrective action plan;
(h) Records on disclosure of monitoring information to affected communities;
(i) Identification of key issues, or complaints from affected people, or recommendations for
improvement;
(j) Monitoring adjustment measures recommended based on monitoring experience/trends
and stakeholders response;
(k) Information about actual institutional arrangement for implementing the monitoring
program/plan provided or adjusted, as may be required;
(l) Proposed items of focus for the next report and due date.
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
186
Appendix 13: Pictorial Highlights
Participants of Public Consultation
Participants of Public Consultation
IEE of Haldebesi – Dhobi – Dhandebesi Road Rehabilitation & Reconstruction Sub-Project DCC, Ramechhap
187
Participants of Public Consultation
Existing Road Alignment