development of cost effective swimming pools

201
DEVELOPMENT OF COST EFFECTIVE SWIMMING POOLS FOR SRI LANKA THIS THESIS IS SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING IN PARTIAL FULFILMENT OF THE REQUIREMENT FOR THE DEGREE OF MASTER OF ENGINEERING IN STRUCTURAL ENGINEERING DESIGN E. M. WIJESINGHE Supervised By By Dr. M. T. R. JAYASINGHE Associate Professor Department of Civil Engineering 7/5- ?0 <- s DEPARTMENT OF CIVIL ENGINEERING UNIVERSITY OF MORATUWA University of Moratuwa SRI LANKA MM Thesis coll 77705 77705 11105 JANUARY 2003

Upload: khangminh22

Post on 28-Jan-2023

1 views

Category:

Documents


0 download

TRANSCRIPT

DEVELOPMENT OF COST E F F E C T I V E

SWIMMING POOLS FOR SRI L A N K A

THIS THESIS IS SUBMITTED TO THE DEPARTMENT OF CIVIL

ENGINEERING IN PARTIAL FULFILMENT OF THE REQUIREMENT

FOR THE DEGREE OF MASTER OF ENGINEERING IN STRUCTURAL

ENGINEERING DESIGN

E. M. WIJESINGHE

Supervised By

By

Dr. M. T. R. JAYASINGHE

Associate Professor

Department of Civil Engineering

7/5- ?0 <-s

DEPARTMENT OF CIVIL ENGINEERING

UNIVERSITY OF MORATUWA

University of Moratuwa SRI LANKA MM Thesis coll

77705 77705 11105 JANUARY 2003

DECLARATION

I, Ernest Merrill Wijesinghe, hereby declare that the content of this thesis is

the original work carried out for a period of one year by me. Whenever

others' work is included in this thesis, it is appropriately acknowledged as a

reference.

i

Abstract

Swimming is an ideal recreational activity in Sri Lanka since it is a tropical

country. The island is blessed with beautiful sea beaches right round. However due to the V

financial limitations and other restrictions, majority of Sri Lankans are not so fortunate to

have ready access to the sea coast. Thus, people really interested in swimming are

directed to swimming pools constructed inland. As can be seen in recent t imes, Sri

Lankan sport has gained some rejmarkable achievements. Once the facilities are provided, i

Sri Lanka may reach international level in swimming too. The main obstacle for all these

is the non-availability of adequate .number of swimming pools in Sri Lanka due to high

capital cost involved.

This exercise is to achieye cost effective structural forms for the construction of i

swimming pools for Sri Lanka. .[Conventional type pools are constructed using cantilever

type retaining walls as vertical n u m b e r s designed to retain water limiting the crack width

exerted by the water pressure. Highest cost is involved in the materials and workmanship

associated with the walls. If this is reduced, many of the citizens will be able to afford to

construct their own private swimming pools. The middle level schools may collect a

nominal sum of money from parents and build the school swimming pool. Sports clubs

and other institutions will also be interested to have their own pools. The operational and

maintenance cost compared to the capital cost is very low and can be collected from the

users of the pools very easily. ' •

First of all, a comprehensive literature survey was conducted to determine the

alternative structural forms used in other countries. These alternatives were compared

with the conventional forms. It was observed that there are more effective methods still

not widely used in Sri Lanka. Direct application of these will not be suitable to Sri Lankan

context. Hence certain modifications were made to match to our conditions. When these

alternatives were still behind the expected effectiveness, further desk studies were carried

out to invent more effective methods. The methods developed will not be suitable for sites

with higher level of ground watfer. Construction of pools using this method without deep

ends will be possible if the ground water table is l m below the pool top level. Similarly

pools with deep ends will be possible using this method when the ground water level is 2m

below the pool top level. Again the soil needs to be firm for the use of this method.

The structures needed for water treatment process were also studied to observe the

effectiveness by changing the structural forms.

11

Acknowledgements

First, I wish to express my gratitude and thanks to the Vice Chancellor of the University. And I wish to thank the Dean, Faculty of Engineering and Head of the Department of Civil Engineering of the University.

Next, I would like to express my sincere gratitude to the staff of the University of Moratuwa who taught me Engineering since the day I entered as an undergraduate to this excellent institution. Then I wish to give my thanks to all the staff of the structural Engineering Division of Department of Civil Engineering at the University of Moratuwa for teaching me throughout the Post Graduate course fruitfully.

It is my duty to give my special thanks to Dr.M.T.R.Jayasinghe, Associate Professor at the Dept. of Civil Engineering who guided me throughout this research work with excellent comments and suggestions. He was always enriched to create new things over conventional patterns to make this research a useful one. His continuous monitoring work for last fifteen months with valuable additions to this work is indispensable.

I am very much grateful to Mrs.D.Nanayakkara, the course coordinator of the Post.Graduate.Diploma course, who conducted the course with great devotion. It is my thanks to Dr. (Mrs.) M.T.P.Hettiarachchi, the research coordinator who monitored the progress of the research work timely and coordinated effectively.

Finally I must be thankful to National Water Supply & Drainage Board for giving me this valuable opportunity to follow the Master of Engineering course.

iii

T A B L E OF CONTENTS

Declaration

Abstract

Acknowledgements

Contents

List of Tables

List of figures

IV

Page No

Chapter 1

1.0 Introduction

1.1 General 1

1.2 Main Objectives 1

1.3 Methodology 2

1.4 The main findings 2

1.5 The arrangement of the report 2

Chapter 2

2.0 Literature Review

2.1 General 4

2.2 Types of Swimming Polls 4

2.2.1 Pools for private houses, clubs and hotels 4

2.2.2 Covered pools for clubs and hotels 6

2.2.3 School Pools 7

2.2.4 Teaching or learner pools 8

2.3 Components of swimming pool 9

2.3.1 Pre - cleansing areas - showers and footbaths 9

2.3.2 Changing Accommodation 9

2.3.3 Pool loading - user capacity of swimming pools 10

2.3.4 Sanitary Accommodation for Pool Users 11

2.3.5 Spectator Accommodation 11

2.3.6 Sanitary Accommodation for Spectators 11

2.3.7 Engineering services for swimming pools 12

2.3.7.1 Water supply 12

2.3.7.2 Drainage 12

2.3.7.3 Electricity 13

2.3.7.4 Water Treatment 13

2.4 Design Methodology adopted for conventional swimming pools 14

2.4.1 General Considerations 14

•i

2.4.2 Limit state design 14

2.4.3 Serviceability limit state of cracking 15

2.4.3.1 Flexural tension in mature concrete 15

2.4.3.2 Direct tension in mature concrete 17

2.4.3.3 Direct tension in immature concrete 18

2.4.4 Limitation on steel stress 19

2.4.5 Serviceability limit state of deflection 20

^ 2.4.6 Joints in floor and walls of swimming pools 20

2.4.6.1 Reasons for providing joints 20

2.4.6.2 Types of joints 21

2.4.6.3 Full Movement Joints 22

2.4.6.4 Partial movement joints

(Contraction and stress - relief joints) 23

2.4.6.5 Sliding joints 25

2.4.6.6 Monolithic Joints (Construction joints) 25

2.5 Alternative Structural Forms 26

* 2.5.1 Reinforced Sprayed Concrete 26

2.5.1.1 Introduction 26

2.5.1.2 General Considerations 26

2.5.1.3 Advantages 26

2.5.1.4 Disadvantages 26

2.5.1.5 Dry and Wet Mix Processes 27

2.5.1.6 Reinforcement 27

2.5.1.7 Joints 28

2.5.2 Swimming polls constructed with an insitu reinforced

+ concrete floor and plain mass concrete walls 29

2.5.2.1 Introduction 29

2.5.2.2 The floor 29

2.5.2.3 The Walls 29

2.5.3 Swimming pools constructed with reinforced concrete block walls and insitu reinforced concrete floor 30 2.5.3.1 Introduction 30

4 vi

-i

2.5.3.2 The floor 30

2.5.3.3 The walls 31

2.5.4 Swimming pools constructed with insitu reinforced concrete floor and walls, using dense aggregate concrete blocks as permanent formwork 31

2.5.5 Pools with brick, block or stone walls with an inner lining

of reinforced sprayed concrete 32

2.6 Simply Supported Wall concept 34

«, 2.6.1 Advantages of simply supported wall concept 34

2.6.2 Disadvantages of simply supported wall concept 35

2.7 Summary 35

Chapter 3

3.0 The Case study 36

3.1 General Considerations 36

3.2 Design of swimming pool without a deep end using

conventional method 36

3.2.1 General arrangement of the swimming pool 37

3.2.2 Conventional swimming pool design 38

3.2.2.1 Wall design 38

3.2.2.2 Slab design 40

3.2.3 Detailing of the joints 41

3.2.4 Summary of Structural arrangement 41

3.2.5 Design Drawings 42

3.3 Design of Swimming pool without deep end - Proposed

method 42

3.3.1 Need for an alternative structure 42

3.3.2 Use of gravity wall type swimming pools for Sri Lanka 43

3.3.3 Solution for the rising water table 43

3.3.4 The prevention of lateral movement of the wall 44

3.3.5 The material for the gravity wall 44

3.3.6 Structural design aspects of the proposed structure 44

vii

3.3.7 Design of the random rubble gravity wall 44

3.3.8 Design of the wall 45

3.3.9 Reinforced concrete ground slab 46

3.3.10 The structural arrangement of the swimming pool

without deep end using proposed method 47

3.3.11 Design drawings of the proposed pool without a deep end 47

3.4 Design of swimming pool with deep end - Conventional method 48

3.4.1 General arrangement 48

3.4.2 The structural arrangement of the swimming pool

with a deep end using conventional method 49

3.4.3 Design drawings of the conventional pool with a deep end 50

3.5 Design of swimming pool with a deep end - Proposed method 50

3.5.1 Need for an alternative method 50

3.5.2 Counter fort retaining walls at deep end 50

3.5.3 Reinforced concrete ground slab design 53

3.5.4 Design Drawings 54

Chapter 4

4.0 Cost Study

4.1 General 55

4.2 Basic Rates for the main structure 55

4.3 Cost of construction of reinforced concrete pool structure without a deep end 55

4.4 Cost of construction of Proposed pool structure without a deep end 57

4.5" Cost of Construction of reinforced concrete pool structure

with a deep end 58

4.6 Cost of construction of proposed pool structure with a deep end 60

4.7 Cost Comparison 61

4.8 Conclusions 62

4 viu

Chapter 5

5.0 Alternatives for associated structures 63

5.1 Introduction 63

5.2 Methods of removal of pollution 63

5.2.1 Removal of surface pollution 63

5.2.2 Removal of dissolved pollution 64

5.2.3 Removal of suspended pollution 64

5.2.4 Removal of deposited insoluble pollution 64

5.2.5 Removal of the biological pollution in the swimming pool 64

5.3 Structural forms for water treatment 64

5.3.1 Traditional swimming pool forms for water treatment 64

5.3.2 Alternative forms - Aerators built using ferro - cement technology 65

5.4 Cost study 65

5.4.1 Cost for pool without deep end 65

5.4.2 Cost for pool with deep end 66

5.5 Cost savings 66

5.6 Summary 67

Chapter 6 68

6.0 Conclusions and Recommendations 68

6.1 General 68

6.1.1 Main features of Swimming pools without deep ends 68

6.1.2 Main features of Swimming pools with deep ends 68

References 71

Appendices

Appendix A : Design calculations for conventional swimming pool with deep end.

Appendix B : Design calculations for proposed swimming pool with deep end.

Appendix C : Design drawings of conventional swimming pool without deep end.

Appendix D : Design drawings for proposed swimming pool without deep end.

IX

Appendix E : Design drawings for conventional swimming pool with deep end.

Appendix F : Design drawings for proposed swimming pool with deep end.

LIST OF TABLES

Page

2.1 Dimensions of swimming pools for private houses 6

2.2 Dimensions of swimming pools for clubs and. hotels 6

2.3 Dimensions of swimming pools for schools 7

2.4 Dimensions of teaching pools 8

2.5 Area required in swimming pools per person according to

depth of water and use 9

2.6 Gradients of pipes for self cleansing 13

2.7 Variation in temperature due to seasonal changes 19

2.8 Allowable steel stresses in direct or flexural tension for Serviceability limit state 19

3.1 Summary of reinforcement for pool without a deep end 42

3.2 Structural arrangement of the conventional pool with

a deep end 49

4.1 Cost calculation of reinforced concrete pool structure without a deep end 56

4.2 Cost calculation of proposed pool structure without a deep end 58

4.3 Cost calculation of reinforced concrete pool structure with a deep end 60

4.4 Cost calculation of proposed pool structure with

a deep end 61

4.5 Cost comparison of different swimming pools 62

6.1 Structural costs, cost saving and cost saving as a percentage 69

6.2 Total costs, cost saving and cost saving as a percentage 70

LIST OF FIGURES

P a g e

2.1 Dimensions of a typical 25m long pool 7

2.2 Reinforcement arrangement for crack width calculations 16

2.3 Section subjected to combined bending and tension 17

2.4 Full movement joint in reinforced concrete wall 22

ir 2.5 Full movement joint in reinforced concrete floor slab 23

2.6 Stress relief joint in reinforced concrete floor slab showing recommended proportion for crack inducement 23

2.7 Stress - relief joint in reinforced concrete wall showing recommended proportion for crack inducement 24

2.8 Possible arrangement of joints in floor and walls of the reinforced concrete swimming pools 24

2.9 Diagram of mass (gravity) type wall of pool with reinforced sprayed concrete lining and floor 33

2.10 Diagram of mass (gravity) type wall of pool with reinforced + sprayed insitu lining and reinforced insitu concrete floor 33

3.1 Plan and section of a swimming pool for a school without

a deep end 37

3.2 The possible arrangement of joints in floor and walls 38

3.3 Arrangement used for the study 39

3.4 Fixed joint between wall and base slab 41

3.5 Section of wall of 1.5m deep 45

3.6 Plan and section of a conventional swimming pool for a school

with a deep end 48

3.7 Dimensions of the counter fort retaining wall used to retain water

at deep end 51

3.8 General arrangement of the counter forts 51

3.9 Dimensions of the counter fort 52

3.10 Section of pool showing slab thicknesses for design 53

3.11 Base slab arrangement 54

3.12 Base slab reinforcement arrangement 54

XI

5.1 Water pollution zones in pools 63

5.2 Schematic diagram of an aerator 65

X l l

Chapter 1

Introduction

1.1 General

Water is the blessing to the mankind as one of the fundamental needs to live with. By and

large, it takes the body heat away and neutralizes the physical fatigue of the human when

immersed in. Ancient Ceylon, as for many other trades, was in fore front using this

natural resource for pleasure by designing surprising models of swimming pools such as

twin ponds in Anuradhapura. It is surprising to see a swimming pool on a huge stone as

on "Sigiriya" using clay bricks. Sinhalese Kings were so engineered to craft things to be

named as wonders of the 2 1 s t Century.

Today, Swimming pools are considered as luxurious components for private houses,

institutions and schools in Sri Lanka due to high cost of capital investment.

The basic requirements for any swimming pool may be summarized as follows:

1. The pool shell must be structurally sound.

2. The pool must be watertight when it is full and, if constructed below ground

level, against infiltration of water from the subsoil when it is empty.

3. It must be finished with an attractive, smooth, impermeable surface.

4. The water must be maintained at a proper standard of clarity and purity, either

by a continuous flow - through system or by means of a correctly designed and

operated water treatment plant.

5. A walkway, of adequate width and a non-slip surface, should be provided

around the pool.

The traditional and alternative structural forms should fulfill the requirements stipulated

above. Those should fulfill the provisions of BS 8007:1987 when reinforced concrete is

used.

1.2 Main Objectives

The main objectives of this study was to develop cost effective structural forms for

swimming pools for Sri Lanka so that the capital cost of a swimming pool could be

affordable to many institutions and private clients.

1

1.3 Methodology

The following methodology was used to achieve the above objective:

1. A detailed literature review was carried out to determine the various structural

concepts and materials adopted in other countries. The alternatives that could

be cost effective were identified.

2. These concepts were further investigated to determine the applicability to the

soil types and ground water available in Sri Lanka.

3. Detailed structural designs were used to determine the suitability of the proposed

concepts.

4. Detailed Survey was carried out to collect alternative water treatment processes

in Sri Lanka to be used for water purification system in the swimming pool.

1.4 The main findings

The main findings of this study are listed below.

1. Cost of traditional swimming pools could be reduced significantly using

alternative methods.

2. The reduction is mainly achieved by changing the structural forms used in the

construction of structural walls and base slab of the swimming pools.

3. The reduction of the cost of water treatment process of the swimming pool is not

in considerable magnitude. This is because the structural components used for

treatment process is only the aerator of the system. Traditional methods to

construct the structures and pressure filters can therefore be used for

purification.

1.5 The arrangement of the report

The report is arranged in the following manner.

Chapter 2 gives a detailed literature review including design methodologies and

construction details

Chapter 3 presents the design calculations and detailed drawings of traditional swimming

pools and the alternative structural forms

Chapter 4 describes the cost calculations and comparisons of the traditional swimming

pool with alternative structural forms to show the effectiveness of the alternative structural

forms.

Chapter 5 deals with alternatives for associated structures mainly in water purification

systems of swimming pools to obtain any cost savings using alternatives.

Chapter 6 presents the conclusions and recommendations

Chapter 2

Literature Review

2.1 General

The literature review was mainly focused upon different types of structural forms used for

swimming pools in other countries to select cost effective options. Reference was also made

to different structural engineering concepts to transfer the loads excerted on pool walls and

ground slab electively. Further references were made on water purification systems and soil

stabilization methods.

Generally the size of a swimming pool must be large enough for a swimmer to take several

strokes, and the minimum effective size is likely about 5.0m long by 2.5m wide with a

minimum depth of water of 1.0m. However, a depth of 1.0m would not be sufficient for even

a very flat drive. An experienced swimmer can make a flat drive from 0.30m above water

level in to 1.20m of water. It is recommended that for public pools a minimum of 2.0m 2 of

pool water area is required per person in the pool. For comfort, an allowance should be made

of about 3.5m 2 for each person who wishes to swim. In other words, the swimming area of the

pool should be based on 3.5m 2 per swimmer. For proper swimming, a 'lane' at least 2.0m

wide and 5.0m long is required. This means that to accomodate four people who really wish

to swim, a pool 10.0m x 4.0m is required.

The pools, which are intended only for swimming, and not for diving and water polo, the

maximum depth of water need not exceed about 1.5m. The provision of a depth in excess of

this figure really serves little useful purpose, but adds significantly to the capital cost and

running expenses of the pool.

2.2 Types of Swimming Pools

2.2.1 Pools for private houses, clubs and hotels (Perkins, 1988)

With pools in this category there is generally a limited choice of site since they usually have

to be built on the same plot as the main building. However, clubs and hotels are likely to be

better off in this respect than private houses, because the plot area is greater. The larger the

garden the more scope there is for selecting the most favorable position for the pool. Even

with a comparatively small garden there are certain factors, which should be taken into

account, and these apply to all open-air pools in countries with a temperate climate like Sri

Lanka. These factors are (Perkins-1988):

1. Select a position, which will receive as much sun as possible preferably in the

afternoon.

2. Avoid the vicinity of large trees.

3. If there is an existing wind - break, in the form of an attractive stone, brick or

block wall, or thick hedge, it would be advantageous to utilize this if at all

possible.

4. Provision has to be made for emptying the pool and for disposing of the wash -

water from filters.

5. The location of existing services - water, electricity.

6. Following on from the provision of services to the pool is the location of a small

building to house the plant and equipment such as circulating pump, water

treatment and heating installations, and ancillary equipment required for cleaning

and maintenance of the pool

7. There should be reasonable access for plant and materials to build the pool.

Item Length Width Water depth Water depth Water area Volume of

No m m • m min m

m max m m 2 water m 3 (gal)

1 6.00 3.00 0.90 1.10 18 18

(3960)

2 10.00 5.00 0.90 1.50 50 60

(13200)

3 12.5 5.00 0.90 1.50 62.5 75

(16500)

4 16.67 6.0 1.00 1.50 100 125

(27500)

5 16.67 6.0 1.00 3.00 100 212

(46640)

Table 2 .1: Dimensions of swimming pools for private houses

NOTE: The pool described in Item 5 is provided with a diving pit. Although this pool has

the same water area as the pool in Item 4, the volume of water is increased by 70%,

with a significant increase in capital cost and the cost of operation.

2.2.2 Covered pools for clubs and hotels (Perkins, 1988)

There are obviously many advantages in having a covered swimming pool instead of an open

air one generally in temperate climates where the temperature could be below 0°C during

certain times of the year. The disadvantage is the additional cost, which can be considerable.

An important point is the location of the swimming pool in relation to the rest of the building

and, in particular, the use to which the adjacent rooms are put. One point is quite clear. That

is having a covered pool, a pool inside a building; it can be used in comfort 365 days of the

year. The initial capital investment and the annual operating costs of a covered (indoor)

swimming pool are much greater than those of a pool in the garden. However such

advantages may not be there in tropical climates except the privacy offered by a covered pool

(Perkins-1988).

Item Length Width Water depth Water depth Water area Volume of

No m m m i n m m max" 1 m m 2 water m 3 (gal)

1 12.50 6.00 0.90 1.10 75 75

(16500)

2 16.67 8.00 0.90 1.50 133 160

(35200)

3 20.00 8.00 0.90 3.00 160 312

(68640)

4 25.00 12.50 0.90 3.00 312 562

(123640)

Table 2.2 : Dimensions of swimming pools for clubs and hotels

2.2.3 School Pools (Perkins, 1988)

With school pools, there is generally a much wider choice of site since the pool forms part of

the recreational facilities of the school. It may therefore be constructed as part of the sports

ground buildings, or it may form part of the main school building and generally could be next

to the gymnasium (Perkins-1988).

O.fnJ 1 .4m

1

3.0m

J 15.5m J - 2 . 7 m J 6.8m-

Figure 2.1 : Dimensions of a typical 25m long pool

7

Item Length Width Water depth Water depth Water area Volume of

No m m m i n m m m max m m 2 water

m 3 (gal)

1 10.00 5.00 0.90 1.10 50 50

2 16.67 8.00 0.90 1.50 133

(11000)

160

3 20.00 10.00 0.90 1.50 200

(35200)

240

4 25.00 12.50 0.90 1.50 312

(52800)

314

5 25.00 12.50 0.90 3.00 312

(82280)

562

(123640)

Table 2.3 : Dimensions of swimming pools for schools

2.2.4 Teaching or learner pools (Perkins, 1988)

The principal feature of this type of pool is that it must be absolutely safe for non -

swimmers. It can be rectangular in plan, with the depth generally varying from 0.80m to

1.0m. The maximum depth should not exceed 1.20m. The minimum length of 12.0m and a

minimum width of 7.0m are recommended. A useful feature for teaching pools is for the

walkway around the pool to be lower than the deck level, so that the instructor can carry out

his duties without having to bend down (Perkins-1988).

8

Length Width Depth Capacity

m m m m 3 (gal)

12.5 7.00 0 . 7 5 - 0 . 9 0 72

(16000)

16.67 8.00 0 . 7 5 - 0 . 9 0 108

(24000)

20.00 10.00 0 . 7 5 - 0 . 9 0 165

(36000)

20.00 12. 0 0 . 7 5 - 0 . 9 0 210

(44000)

25.00 16.67 0.75 - 0.90 340

(74000)

Table 2.4 : Dimensions of teaching pools

2.3 Components of swimming pools

2.3.1 Pre - cleansing areas - showers and footbaths (Perkins, 1988)

It is better if the layout of the pool should be such that all bathers have to pass through the pre

- cleansing area before entering the pool. Unless the public are prepared to use showers,

footbaths and wash - hand basins in a civilized way, it is extremely difficult to maintain a

proper standard. There should be an adequate number of showers, with a water supply pipe

work of sufficient size to allow all showers to be operated simultaneously. One further point

is that some bathers like to take a shower after swimming, particularly if the pool water is

chlorinated.

2.3.2 Changing Accommodation (Perkins, 1988)

The changing accommodation can be arranged in many ways. Individual cubicles of

dimensions of 1.0m long by 0.9m wide are about the minimum.

Pools, which cater specially for family activities, provision should be made for a limited

number of family changing cubicles, so that very young children can change with their

parents.

The reasonable changing accommodation would be as follows:

1. One changing place for each 8.0m 2 of pool area for normal swimming pools. This

is increased to one place for each 6.5m 2 in leisure centre pools.

2. For learner pools one place for each 4 .0m 2 of water area.

3. When there is a separate diving pool, extra two places should be provided.

2.3.3 Pool loading - user capacity of swimming pools (Perkins, 1988)

When considering the physical safety aspect of the pool, a maximum number of bathers in the

pool at any time should be limited to one person per 2m 2 of pool water surface. For

maintenance of water quality, the maximum number of bathers per day should be limited to

one bather for each 2m 3 , of satisfactorily filtered and disinfected water circulated in the pool

per 24-hour period. Table 2.5 below shows the area required in swimming pools per person

according to depth of water and use (Perkins-1988).

Description Indoor Outdoor

m 2 (f t 2 ) m 2 (f t 2 )

Water not exceeding 1.52m (5ft) deep 1.3(14) 1.40(15)

Advanced swimming 1.86 (20) 2.32 (25)

Learner pools 3.72 (40) 4.18 (45)

Recreational swimming 1.86 (20) 2.32 (25)

Table 2.5 : Area required in swimming pools per person according to depth

of water and use

10

2.3.4 Sanitary Accommodation for Pool Users (Perkins, 1988)

The following sanitary accommodation can be recommended.

Women: I WC for each 30 up to the first 90 and one for each additional 40, with a minimum

of 3 WCs. Provide 1 WHB for each WC

Men: I W C for each 50 up to the first 100 and then one for each additional 75, with 1 WHB

for each WC. 1 urinal stall for each 30 with a minimum of 4 stalls.

2.3.5 Spectator Accommodation (Perkins, 1988)

Accommodation for spectators can be divided into two categories.

1. Standing and / or seating for friends and relatives of bathers.

2. Permanent seating for galas and competitions.

It is desirable that part of accommodation under (1) should be located as near as possible to

the learner pool, as many parents like to watch their children under instruction.

Fixed seating for spectators watching competitions requires special planning and the capital

cost can be considerable. A valid question is therefore the extent to which this seating is

really needed that is, the use that will be made of it. This can be expressed in the number of

times a year that the accommodation will be utilized on a percentage basis, i.e. 100% (a "full

house"), 75%, 60%, 50%, 40%., etc., of maximum capacity. The result of such an

investigation may cause a more realistic approach to the problem. In a tropical country, this

accommodation could be steps formed using rubblework as in open-air theaters so that the

cost can be minimized.

2.3.6 Sanitary Accommodation for Spectators (Perkins, 1988)

Separate sanitary accommodation for spectators of both sexes must be provided. The

recommendations for this accommodation is as follows:

Men : WCs, minimum 2; 1 for each 100 up to 500, then 1 for each 200: Urinals, minimum

3 stalls; 1 stall for each 40 up to 300, then 1 stall for each 50:

WHBs, 1 for each WC.

Women: WCs, minimum 3;1 for each 50 up to 300, then 1 for each 75: WHBs, l for each WC.

11

2.3.7 Engineering services for swimming pools

The Engineering services of the pool and ancillary buildings will vary according to the size

and complexity of the pool. But the smallest pool will require the following services.

1. Water Supply

2. Drainage

3. Electricity

4. Water treatment and disinfection

2.3.7.1 Water Supply

This is usually taken from the mains of a public supply, and in this case it can usually be

assumed to be satisfactory. If the source is a private one from a well or borehole, it should be

tested chemically and bacteriological at regular intervals. Apart from quality, the supply must

be adequate in quantity for topping up the pool and washing the filters. In Sri Lanka, it is

advisable to rely on well if it is possible since the cost of water above 2 5 m 3 per month is quite

high even for homes.

2.3.7.2 Drainage

Some satisfactory arrangement must be made for the disposal of the wash water from the

filters, and the pool itself when it is emptied for cleaning and maintenance. The quantities of

water to be disposed of, will vary according to the type, size and number of filters installed.

Table 2.6 gives self-cleansing discharges with respective pipe diameters and gradients.

12

Pipe diameter

(mm)

Gradient Discharge

(litre / min)

100 1 in 50 520

150 1 in 100 1000

200 1 in 150 1860

225 1 in 120 2800

250 1 in 220 2760

Table 2.6: Gradients of pipes for self cleansing

The above table indicates the sort of discharge, which pipes of diameter ranging from 100 to

250mm laid to normal self - cleansing gradients are likely to give. The drain should

discharge to a sewer or public watercourse for which permission from the drainage authority

would have to be obtained. Pipes up to about 150mm diameter are usually of clayware or

plastics; for pipes of larger diameter concrete may be found more economic.

2.3.7.3 Electricity

In Sri Lanka Electricity is normally be used for power. For lighting, the electrical supply is

410V, AC, 3 - phase. Since any voltage above about 50V is considered dangerous, special

care must be taken in detailing and executing electrical installations.

2.3.7.4 Water Treatment

The necessity for the treatment and purification of water in public swimming pools is now

recognized than in the recent past, and no private party or public authority would consider

constructing a swimming pool without a properly designed plant to maintain the water at an

13

adequate standard of purity. The method for purification of water will depend on a number of

factors; some methods are better than others, but they may be classified under two main

headings.

1. Continuous flow - through, or intermittent flow - through, without treatment.

2. Continuous circulation with filtration and treatment.

2.4 Design Methodology adopted for conventional swimming pools

2.4.1 General Considerations

The conventional swimming pools in Sri Lanka are built in insitu reinforced concrete and

generally follow the recommendations in BS 8007, British standard code of practice for

Design of concrete structures for retaining aqueous liquids;

This is generally known as the code of practice for water retaining structures.

The design of water - retaining structures may be carried out using either

1. a limit state design, as recommended by BS 8007, or

2. an elastic design, which is not now covered by the British code of practice.

A limit state design is based on both ultimate and serviceability limit states. As the restraint

of cracking is of prime importance with water retaining structures, the simplified rules for

minimum steel areas and maximum spacing are no longer adequate. It is necessary to check

the concrete strains and crack widths. The calculations tend to be lengthy and depend on

factors such as the degree of restraint, shrinkage and creep which are difficult to assess

accurately.

2.4.2 Limit state design

The principal steps for the limit state design of a reinforced concrete structure are:

1. Ultimate limit state design calculations.

2. Serviceability limit state design calculations with either

a. Calculation of crack widths

b. "Deemed to satisfy" requirements for applied loading effects on the

mature concrete. These are based on maximum service stresses in the

reinforcement.

14

For the ultimate limit state the procedures followed are exactly the same as for any other

reinforced concrete structure. The partial factor of safety on imposed loading due to

contained liquid should be taken as 1.4 for strength calculations to reflect degree of accuracy

with which hydrostatic loading may be predicted. Calculations for the analysis of the

structure subject to the most severe load combinations will then proceed in the usual way.

Serviceability design will involve the classification of each member according to its crack

width category. External members not in contact with the liquid can be designed using

criteria in BS 8110 for normal reinforced concrete work.

There are two basic concepts regarding the formation of cracks in concrete, i.e. tensile

strength and tensile strain capacity of concrete. Tensile strain capacity of concrete is more

relevant in case of cracking in plastic stage whereas cracking of hardened concrete can be

explained by tensile strength capacity of concrete. BS 8007 recommends a maximum design

surface crack width of 0.2mm for severe or very severe exposure condition and 0.1mm for

surfaces where critical aesthetic appearance is important. These limitations imply that all

surface cracks less than 0.2mm will prove to be water tight under all circumstances. When

water percolates through cracks it dissolves calcium hydroxide from the hydrated cement

matrix and then, on contact with carbon dioxide in the atmosphere deposits calcium

carbonate. This action can be very effective at sealing cracks although the process is likely to

produce unsightly white deposits on the surface.

The maximum likely crack widths may be calculated using the methods given in the

appendices of the code and then checked for compliance with the allowable values.

Alternatively, reinforcement stresses due to bending or direct tension may be calculated and

checked for compliance with the deemed to satisfy limits.

2.4.3 Serviceability limit state of cracking

Serviceability calculations will be required to consider three specific cases (Nanayakkara,2000):

2.4.3.1 Flexural tension in mature concrete.

This may result form both dead and imposed loads.

15

Procedure for the calculation of surface crack width due to applied bending moment Ms,

involves the following.

a. Calculation of the depth of neutral axis, lever arm and steel stress by elastic

theory.

b. Calculation of the surface strain allowing for the stiffening effect of concrete.

c. Calculation of the crack width.

Crack width is then computed using the following formula.

w Figure 2.2 : Reinforcement arrangement

3 a c r £

1 + 2 ^cr -Cmion

h - x

where, £ m = £i • £2

£1 = £ is E s

h - x . d - x_.

£2 — bt (h — x) ( a 1 — x) for a limiting design surface crack width of 0.2mm 3E S A s (d - x)

1.5b,fh-x') f a ' - x ) 3E S A s (d - x)

for a limiting design surface crack width of 0.1mm

BS 8007 specifies that above crack width formula given is valid only if the compressive stress

in the concrete f < 0.45 fcu and the tensile stress in the steel under service conditions fs

<0.87fy

r 16

Where al -Distance from the compression face to the point at which the crack width is being calculated

a c r -distance from the point considered to the surface of the nearest longitudinal bar

A s width of the section at the centroid of the tension steel

Cmin -minimum cover to the tension steel

d -effective depth

E s -modulus of elasticity of reinforcement

h -overall depth of member

W -design crack width

x -depth of neutral axis

£ m -average strain at the level where the cracking is being considered.

2.4.3.2.Direct tension in mature concrete.

This may be caused by hydrostatic loadings. In water retaining structures, a crack due to

tensile force is of greater importance than a crack due to flexure since the crack due to a

tensile force penetrates the full depth of the section with a more likelihood to allow leakage.

In a situation where the whole section is under tension with an applied tensile force and a

bending moment (no compressive strain in section),the following formulae can be used.

• A s 2 '

• As l •

S e c t i o n S t r e s s

Figure 2.3 : Section subjected to combined bending and tension

17

W = 3 a c r e m

where, s m = si • 62

61 = fs l + (fal - fs2) x a E s ( h - 2a) x Es)

E2 - 2 b h for 0.2mm crack width 3E S A s

= bh for 0.1mm crack width Es A s

fs. = M + _ T _ 2 b h p , ( 0 . 5 h - a ) 2bhp,

fs2 = I J T - Pi fsi P2 I bh

2.4.3.3 Direct tension in immature concrete. .

This is caused by restrained thermal and shrinkage movement.

Thermal cracking is taken to have a maximum spacing. S m a x = fax 0

fb 2p Where p = steel ratio, As

Ac 0 = bar diameter

fct = 3 day tensile strength of concrete

fb = average bond strength between concrete and steel

Fully developed crack width,

W m a 2 = S m a x R d ( T, + T 2 )

Where, Ti = Fall in temperature between the hydration peak and ambient (use table A.2 BS8007)

T2 = Variation in temperature due to seasonal changes

R = External restrain factor (BS 8007)

& = Coefficient of thermal expansion of mature concrete ( = 10 x 10"6)

18

Temperature records of 14 cities over a 10 year period (1987 - 1996) were analysed to obtain

appropriate values for T2 for various locations in Sri Lanka. It shows that Vauniya has the

highest 'I^of 24°C. Table 2.7 shows the monthly variation of maximum and minimum

temperatures (Nanayakkara -2000) .

City T 2 ( °C)

Anuradhapura 21

Badulla 20

Hambantota 14

Katugastota 20

Colombo 15

Galle 13

Ratmalana 15

City T 2 ( °C)

Bandarawela 15

Baticaloa 18

Vavuniya 24

Puttalam 17

Mahailluppallama 20

Nuwaraeliya 22

Kurunegala 21

Table 2.7 : Variation in temperature changes due to seasonal changes (T 2 )

2.4.4 Limitation on steel stress

Crack width limitation requirement in mature concrete due to external loads may also be

considered satisfactory if the stress in the steel under service conditions does not exceed the

appropriate values specified in BS 8007 (Table 3.1) and reproduced as table 2.8 below.

Table : 2.8 Allowable steel stresses in direct or

flexural tension for serviceability limit states

Design crack width (mm)

Allowable stress (N/mm 2 )

Design crack width (mm) Plain bars Deformed bars

0.1 85 100

0.2 115 130

This method of satisfying the limit state of crack control requirement is known as the

"deemed to satisfy" method of design. This method does not give an economical solution

because the steel stress is limited to a low value. It is evident that, under the limitation of

19

77705

steel stress, the crack width is far below the allowable value and the steel requirement is much

higher.

2.4.5 Serviceability limit state of deflection

The recommendations for span / effective depth ratios given in BS8110 : Parti : 1985 apply to

horizontal members carrying uniformly distributed loads. For a cantilever wall which tapers

uniformly away from the support and which is loaded with a triangular pressure, a net

reduction factor should be applied to the above ratios if the thickness at the top is less than 0.6

times the thickness at the base. This reduction factor can be assumed to vary linearly between

1.0 and 0.78 where the thickness of the top varies between 0.6 and 0.3 times the thickness at

the bottom. In addition, allowance should be made for the significant additional deflection,

which occurs at the top of the wall due to rotation, if the pressure distribution under the base

is triangular or very asymmetrically trapezoidal. Limits for deflection will normally be those

for non - liquid - retaining structures since only in exceptional circumstances will deflections

be more critical with regard to freeboard, drainage or redistribution of load. Retaining walls

should be backfilled in even layers around the structure, the thickness of the layers being

specified by the designer. Over compaction adjacent to the wall should be avoided otherwise

large differential deflections (and sliding) of the wall may occur. At least 7 5 % of the liquid

load should be considered as permanent when calculating deflections (BS 8007-1987).

2.4.6 Joints in floor and walls of swimming pools

It is to be noted that the BS 8007 allows, in the design, options for continuous construction

with full restraint. Nevertheless, it is normally necessary to provide construction joints but

these are treated in the design as "Calculated cracks" and the concrete is considered, at least in

theory, to be monolithic at these joints.

2.4.6.1 Reasons for providing joints

There are a number of important reasons why joints are normally provided in the reinforced

concrete shell of a swimming pool, and these include the following:

20

a. Unless the pool is very small one, the shell cannot be cast in one continuous

operation, and even with small pools this does present certain practical difficulties.

b. It may be necessary for structural reasons to make provision for movement in the

shell of the pool.

The expression "Provision for movement" is used in this context in its widest sense and

includes thermal contraction and drying shrinkage, which takes place as the concrete matures,

as well as thermal expansion and contraction, creep and foundation movements that may

occur during the lifetime of the pool.

2.4.6.2 Types of joint

Joints are considered essentially of two basic types, construction joints and movement joints.

Construction joints are introduced as a convenience in construction. Movement joints are

intended to accommodate relative movement between the adjoining parts, but special

provision has to be made to ensure that the joints are watertight (BS 8007-1987).

Division of the structure into suitable lengths separated by movement joints may be required

to control cracking of the mature concrete. Approximately, the tensile strength should exceed

the resistance to sliding of one half the length of the wall (or slab). Spacing of expansion

joints at about 70m centres should generally be more than adequate and even longer lengths

may be considered if necessary before making a definite division. However, the desirability

of introducing movement joints at closer spacing to resist cracking in immature concrete

depends on the design philosophy adopted; whether to restrain, or to permit, thermal

contraction in walls and slabs. At one extreme control is provided by substantial distribution

reinforcement in the form of small diameter bars, preferably of the high - bond type, at close

spacing with no joints in the concrete other than construction joints. At the other extreme,

control is provided by closely spaced movement joints, which permit movement in the

member and reduce the requirement for reinforcement to a very small amount. Between these

two extremes intermediate options exist whereby a change in joint spacing can be

compensated for by a change in the amount of reinforcement required. The three main

choices are summarized in Table 5.1 in BS 8007.

21

The following are the principal types of joints used in reinforced concrete swimming pools.

a) Full movement joints; these are often called expansion joints.

b) Partial movement joints, also known as contraction joints, semi contraction joints

and stress - relief joints.

c) Sliding joints, where one structural member slides over an adjacent member that is

in close contact.

d) Monolithic joints, also known as construction joints.

2.4.6.3 Full Movement Joints

Full movement joints should accommodate both expansion and contraction of the concrete on

each side of the joint. The basic features of this type of joint are that there is no structural

continuity across the joint, which should be able to open and close with minimum restraint,

and at the same time remain completely watertight under all anticipated conditions of

movement. It is essential for full movement joints to be continuous in one plane right through

floor and walls of the pool. These joints are detailed so that there is a definite gap between

one structural member and the next one; this gap is usually not less than 20mm wide, but

seldom needs to exceed 25mm.

Figure 2.4 shows a full movement joint in a wall and figure 2.5 shows a full movement joint

in a floor taken from BS 8007-1987.

EPOM or Neoprene strip

20mm

FIG. 2.4. Full movement joint in reinforced concrete wall.

22

Preformed Neoprene or EDPM I

Figure 2.5 :FuII movement joint in reinforced concrete floor slab

The use of centrally placed water bar is not recommended in a floor slab because of the

difficulty in compacting the concrete underneath the bar. To ensure watertightness, the

concrete must be well compacted all around the water bar, and steps taken to ensure that the

bar is not displaced during concreting.

2.4.6.4 Partial movement joints (Contraction and stress - relief joints)

This is the basic type of joint recommended between bays in floor slabs and between wall

panels as shown below in figures 2.6 and 2.7 respectively.

Site c o n c r e t e — '

Figure 2.6 : Stress-relief joint in reinforced concrete floor slab showing

recommended proportions for crack inducement

23

Water face 1 l-^Seolant

u 0.750

~Saw cut with b a c k - u p material

Induced crack

j _ L Neoprene gasket

Figure 2.7 : Stress-relief joint in reinforced concrete wall showing

recommended proportions for crack inducement

It is better if the stress - relief joints in the floor slab are in line with those in the walls when it

is intended that there will be transverse movement joints in the tiling, screed and rendering. If

sufficient care is exercised, all these joints can coincide with each other.

-4- The figure 2.8 is intended to illustrate in diagram form the arrangement of joints (and

therefore bay layout and panel lengths) in the floor and walls of the pool considered in this

exercise

4.75rr

4.75m

.^m

-4.5m—1—4.5m—I—4.5m—I—4.5m—J—4.5m—I 1 1.0m 1.5m

Figure 2.8 : Possible arrangement of joints in floor and walls of the

reinforced concrete swimming pool.

24

2.4.6.5 Sliding joints

When a swimming pool is inside a building, it is recommended that the shell of the pool

should be separated from the superstructure by a full movement joint. Then a sliding joint is

detailed so that the restraint between the superstructure and the pool shell is reduced to a

minimum. The lower member on which the upper member is supported should be finished

with as smooth a surface as possible. One method to achieve this is to trowel in a cement

mortar on the concrete surface while the latter is still plastic. The mortar layer should be

finished with a steel trowel. Before the upper member is cast, the surface of the lower one

should be covered with two layers of 1000 gauge polythene sheets, or with bituminous

enamel followed by one layer of polythene.

2.4.6.6 Monolithic Joints (Construction joints)

Where it is decided to use this type of joint, the joint should be detailed and specified so that

maximum bond is obtained between the old concrete and the new.

It is desirable to design a swimming pool so that the floor and walls are completely

monolithic throughout. However , in practice, because of the stresses set up in the early life

of the concrete and later on during fluctuations in temperature in the swimming pool, it is

difficult indeed to achieve completely monolithic shell.

A kicker around the perimeter of the floor slab is recommended which forms base for the

wall, and it is most important that the joint between the kicker and the wall should be

watertight. There is no need to allow for shrinkage or thermal movement at right angle to this

joint. The aim should be to obtain maximum bond between the old concrete in the kicker and

the fresh concrete in the wall. If it is decided that a water bar is needed, then a mild steel

sheet can be used. This should be at least 150mm wide and 3mm thick and is usually vibrated

into the top of the kicker and hour or so after placing is complete. This type of bar can be

formed with rubber and PVC where as there is no bond.

25

2.5 Alternative Structural Forms

2.5.1 Reinforced Sprayed Concrete (Perkins, 1988)

2.5.1.1 Introduction

Sprayed Concrete was previously known as 'gunite ' in the UK and 'shotcrete' in the USA.

Sprayed concrete is mainly divided in to two distinct materials; one is a sprayed mortar,

consisting of cement, fine aggregate (sand) and water, the other consists of cement, fine

aggregate, coarse aggregate and water. The inclusion of the coarse aggregate converts the

mortar to a concrete.

2.5.1.2 General Considerations

There are a number of advantages in using sprayed concrete for the construction of a

swimming pool shell; there are also some disadvantages. The position may be summarized as

follows.

2.5.1.3 Advantages

a. High speed of construction; a swimming pool 18.0 x 12.0m with a depth of 1.0 -

2.5m can be constructed from a prepared excavation in about 20 working days.

This is all the work necessary for the structural shell, but does not include finishing

and pipe work, etc.

b. The pool can be built on a congested site where access for equipment and

materials is severely restricted because the delivery hose to the gun can be at least

100m long.

c. The only joints in a normal sprayed concrete pool are plain built joints that do not

require sealing.

d. For pools larger than about 12 x 6m it is often cheaper than reinforced concrete.

e. It is cheaper than reinforced concrete for 'free - formed' pools.

f. Little or no formwork is required.

2.5.1.4 Disadvantages

a. For a successful job it should be entrusted to specialist firms.

26

b. Size for size, a sprayed concrete pool is appreciably lighter than one in reinforced

concrete and is therefore more liable to flotation unless special precautions are

taken.

c. The usual design incorporates a wide cove angle between the wall and the floor. If

the pool is to have a finish of ceramic tiles, this cove angle must be changed to a

right angle.

d. The quality of the finish of the pool shell is more dependent on the skill of the

'gun ' operator than on the concreting gang when insitu concrete is used.

e. Particular care and skill are required to ensure that the sprayed material properly

surrounds all the rebars as voids behind the rebars are difficult to eliminate

completely; this is a criticism frequently met when discussing sprayed concrete.

2.5.1.5 Dry and Wet Mix Processes.

a. The 'dry mix ' in which the cement and aggregate is weigh or volume - batched

without the addition of water, and this is then conveyed pneumatically to the 'gun '

which consists of a mixing manifold and nozzle. It is here that the gun operator

admits water.

b. The 'wet mix ' in which the constituents are normally weigh - batched and mixed

with a predetermined amount of water. The mix is then pumped to the nozzle

where compressed air is admitted which conveys the mix at high velocity into

place.

Tests performed showed that, the compressive strength of cores taken from dry mix sprayed

concrete were in the range 50 - 72 N / m m , whereas cores from wet mix material were in the

range 3 7 - 4 0 N / m m

2 .

2.5.1.6 Reinforcement

High tensile steel is generally used; often in the form of a fabric for smaller pools, with

vertical bars to hold the mesh in position. The cover to reinforcement is usually accepted as

25mm instead the 40mm required for reinforced concrete.

27

Cover in excess of 40mm is undesirable, as crack control is reduced with increase in distance

from the surface. The wall reinforcement must be securely anchored into the floor slab and

carried up into the ring beam at the top of the wall.

2.5.1.7 Joints

Full movement joints are not provided in normally designed sprayed concrete pools.

However, even the smallest private pool is unlikely to be gunned in one continuous operation

and therefore construction joints are required. A plain butt joint is tapered. The factors to

describe why sprayed concrete pool is satisfactory without any contraction joints are:

a. Usually the walls of a sprayed concrete shell are thinner than with insitu concrete.

This, together with the absence of formwork at least on one side, results in less

built - up of heat. Consequently lower thermal stresses are developed, and thermal

strain is correspondingly reduced.

b. Sprayed concrete is generally reinforced with heavy high tensile steal fabric and

the amount of distribution (horizontal) steel is likely to be greater than is normally

provided in a reinforced concrete wall. This results in the design being similar in

effect to Option 1, continuous construction with full restraint, recommended in BS

8007.

c. Good quality sprayed concrete has a low water/ cement ratio (0.35 0.40) while

concrete used for a similar purpose is likely to have a water/ cement ratio in the

range 0 . 4 5 - 0 . 5 5 .

d. The compressive strength of high quality sprayed concrete will depend on whether

the dry mix or wet mix is used.

The factors mentioned above will tend to reduce the tendency for thermal contraction

cracking to occur. This does not mean that such cracking (including drying shrinkage

cracking) does not take place. It is experienced that the drying shrinkage cracking is not

28

unusual in sprayed concrete pools, such cracks are less likely to penetrate below the level of

the reinforcement.

2.5.2 Swimming pools constructed with an insitu reinforced concrete floor and plain

mass concrete walls (Perkins, 1988)

2.5.2.1 Introduction

In theory there is no limit to the size of pool that can be constructed by this method.

However, owing to the thickness of the walls and the number of joints or crack - inducers

required, a size larger than about 10 x 6m with a depth of 1 - 1.5m is unlikely to be an

economic proposition.

2.5.2.2 The floor

The floor slab should have a minimum thickness of 150mm and be laid in bays of convenient

size to suit the pool dimensions. If the wall is constructed on the floor slab, the slab should be

thickened below the wall to 250mm. The reinforcement should consist of high-tensile mesh,

placed 40 - 50mm from the top surface of the slab. The mesh should be rectangular, with a

minimum weight of 3.41kg/m and the main wires running Longitudinally.

It should be noted that because the walls derive their stability from their mass, there is no

reinforcement connecting the floor slab with the walls, as was the case with walls of

reinforced concrete. This, of course, greatly simplifies the construction of the floor slab. All

joints should be provided with sealing groove and properly sealed. If the depth of water

exceeds about 2.0m, an external type water bar should be used below the joint.

2.5.2.3 The Walls

The external and internal loading is resisted by the weight (or mass) of the wall itself. This is

the theoretical idea; in practice, the end walls provide some restraint to the sidewalls and the

materials used to possess some tensile and shear strength, as well as considerable compressive

strength.

29

In view of the fact that there is no reinforcement in the wall to take thermal and drying

shrinkage stresses, the wall must be cast in short lengths to its full height; the length of the

wall panels should not exceed 3.0m.

The joints between the panels should be considered as contraction joints. The provision of a

water bar, and sealing grooves on both faces of the wall, is recommended. The contraction

joints can be detailed with crack inducers so as to reduce the number of stop ends and this

speed up the casting of the wall.

The vertical ducts extend for the full height of the wall and can be formed by an inflatable

former. The holes should be carefully plodded as soon as the former is removed, and the final

filling of the voids should be carried out as late in the construction process as possible.

The water bar between the wall and the floor slab can be a mild steel flat measuring 150mm x

3 mm.

2.5.3 Swimming pools constructed with reinforced concrete block walls and insitu

reinforced concrete floor (Perkins, 1988).

2.5.3.1 Introduction

The use of reinforced concrete block work for the walls of swimming pools can be considered

as satisfactory basically sound provided the pool shell is properly designed and constructed.

It should be noted that pool shell constructed in this way would not comply the

recommendations in BS 8007 because this code covers only reinforced insitu and pre stressed

concrete.

2.5.3.2 The floor

The insitu reinforced concrete floor slab is constructed with the reinforcement for the walls

securely fixed in position so as to be firmly anchored into the floor slab before the latter is

cast.

30

2.5.3.3 The walls

The concrete blocks for the walls should comply with BS 6073, Precast concrete masonry

units, with a minimum compressive strength of 10N/mm 2 , and should be made with natural

aggregates complying with the relevant clauses in BS 882.

The mortar should have mix proportions of 1:4 by weight, and a plasticiser should be used to

improve workability. It should preferably be mixed in a pan mixer. The plasticiser can, with

advantage, be a styrene butadiene rubber emulsion added to the mix in the proportion of 10

liters to 50kg cement.

The infill concrete should be batched by weight and have mix proportions of about 1 part

cement, 2 parts clean concreting sand (coarse to medium, BS 882) and 2 parts coarse

aggregate, 10mm maximum size (BS 882). The water/ cement ratio should not exceed 0.5

and the slump should be in the range of 150 - 200mm; to secure such a slump, a plasticiser

would have to be used.

Two rows of vertical bars are likely to be needed to ensure an adequate factor of safety when

the pool is full and when it is empty.

It is advisable to provide vertical movement joints at about 6.0m centers (these are contraction

joints), and these should be provided with greased dowels in alternate courses to resist lateral

movement.

2.5.4Swimming pools constructed with insitu reinforced concrete floor and walls, using

dense aggregate concrete blocks as permanent formwork (Perkins, 1988).

This method gives entirely satisfactory results when properly designed and constructed. A

question, which arises with the design of the walls, is whether the concrete blocks (which act

as permanent formwork) can be considered as structurally part of the wall for the purpose of

the design calculations. The answer must be in the negative because the concrete of the

31 "^7 c

blocks does not comply with the recommendations in the Code of Practice for water-retaining

structures, BS 8007.

Many private pools (houses, clubs and hotel) are what is known as free formed, that is, the

walls are curved on plan. By using concrete blocks for the formwork there is a very

substantial saving in cost compared with timber formwork.

2.5.5Pools with brick, block or stone walls with an inner lining of reinforced sprayed

concrete (Perkins, 1988)

In this case the walls must be stable by their own weight when under pressure from the

ground when the pool is empty, and from the water in the pool when it is full; in other words,

they are gravity type retaining walls and the sprayed concrete provides a structural watertight

lining.

This type of wall, built in mass concrete, follows the basic principles of stability with regard

to retaining walls. With mass concrete the wall itself should be watertight, but with bricks,

blocks or masonry reliance for water tightness must be placed on the sprayed concrete.

Either the walls can be built on independent foundations, and the floor constructed separately,

or the floor can be of insitu reinforced concrete and the wall supported on that. In the latter

case the edge of the slab should be thickened. Sections through the two types of wall support

are shown in figures 2.9 and 2.10.

Pools built in this way can be very successful provided the water table does not raise much

above the floor of the pool. A small external head can be tolerated because, if the work is

properly executed, the sprayed concrete lining will bond strongly to the walls, and with a

large cove angle and mesh reinforcement quite considerable pressure would be needed to

force it off the wall.

32

I, 300mm u M i n

Sprayed concrete —

-Mesh reinforcement —*~\

-Large stones (rejects)

Figure 2.10 : Diagram of mass (gravity) type wall of pool with reinforced sprayed

insitu lining and reinforced insitu concrete floor

33

The sprayed concrete lining should be applied to a thickness of 75mm, reinforced with a

medium - weight steel fabric - A 193 (BS 4483). It is usual to fix the reinforcement with

steel pins driven into joints in the wall, and for the joints in the wall to be raked out to assist

bond. In fact there is no objection to the wall being built as a dry stone one (without mortar).

The cover to the reinforcement should be about 25mm. If the walls are on an independent

foundation, than it is better to construct the floor of 'rejects' , covered with 150mm of sprayed

concrete, and to bring the wall reinforcement down round the cove and into the floor. The

sprayed concrete floor should also have a similar layer of steel fabric to the walls. One of the

attractions of this method is that a considerable part of the whole job can be carried out by a

comparatively inexperienced contractor, and only the sprayed concrete lining need be put on

by a specialist firm.

2.6 Simply Supported Wall concept (Wamsley, l982)

Walls of conventional swimming pools are designed as cantilevers fixed at the wall/ slab

joint. The change of the concept of this cantilever to simply supported wall economizes the

design considerably. The simply supported wall has a number of advantages and few

disadvantages when compared with the cantilever and propped cantilever walls.

2.6.1 Advantages of s imply supported wall concept

The following are the advantages this type.

1. Economics

2. Elimination of flexural tensile stresses on the water face when the wall is subjected

to internal water pressure.

3. Removal of any risk of over turning owing to external water pressure developing

under the reservoir.

4. Smaller sliding and shear forces at the base of the wall than in corresponding

cantilever and propped cantilever walls.

5. Ready accommodation of thermal movement of the roof (unlike the propped

cantilever wall)

6. Avoidance of high foundation pressures normally associated with cantilever and

propped cantilever walls.

34

7. Absence of the crack at the junction of the underside of the roof and wall

commonly seen in propped cantilever walls.

2.6.2 Disadvantages of simply supported wall concept

The following are the disadvantages.

1. Expense of the wall / roof joint.

2. Initial increased design/drawing office costs. On balance, there is little difference

in design time between the three types of wall. The simple wall can be designed

very quickly; the additional time spent on the roof / wall joint and generally

stability calculations will usually equate with the longer stability calculations

required for the cantilever and propped cantilever walls.

2.7 Summary

Apart from the conventional method of designing of the swimming pool, there are numerous

ways of designing the pool. From the above it is seen that there are more economical means

for designing. But all will not be applicable to the Sri Lankan context. Certain concepts were

adopted with modifications and fresh methods were introduced to obtain the most economical

form for the design of the swimming pool. Next chapter describes the conventional

swimming pool design against the proposed methods to prove the economy in developing a

new concept for the design of swimming pools.

r

35

Chapter 3

The Case Study

3.1 General Considerations

In this case study, two different areas were considered. They are:-

1. Swimming pools without a deep end

2. Swimming pools with a deep end

For each of the above cases designs were performed in conventional method and in the

proposed method. These are presented separately.

3.2 Design of swimming pool without a deep end using conventional

method

As explained in details in chapter 2.2 there are different types of swimming pools.

This case study covers the design aspects of a swimming pool for a school, which is

25m in length and 12.5m in width. The water depths of the pool at the ends are 0.9m

and 1.5m (Figure 3.1). There is a freeboard of O.lm.Thus the heights of the walls at

the ends are 1.0m and 1.6m respectively The design shall include all stability

considerations, analysis of the structure to all possible load cases, design the structure

for the ultimate load cases and finally checking of the structure for serviceability limit

states.

It is to be noted that this study is aimed on swimming pools built on firm ground and

the ground water table is lm below the ground level. The following design data was

used in the design of the swimming pool.

Density of water = lOkN/m 3

Density of earth = 18kN/m 3

Density of concrete = 25kN/m 3

Grade of concrete = 30N/mm 2

Grade of reinforcement = 460N/mm 2

Superimposed dead load on earth = 5kN/m 2

36

2

Bearing capacity of soil = 150kN/m

Friction angle = 30°

Service moment from water = 10 x 3 3 = 45kNm/m 2

Horizontal pressure from earth = 18 rT-Sin30' 1+Sin30

6kN/m 2

3.2.1 General arrangement of the swimming pool

T B 1 o

1 16.0m

SECTION

PLAN

Fig 3.1:Plan and section of swimming pool without a deep end

Note : All dimensions shown above are internal

The structural design aspects of conventional swimming pool are first discussed and

the design aspects of alternative swimming pool are presented thereafter.

37

3.2.2 Conventional swimming pool design

3.2.2.1 Wall design

The vertical walls of the swimming pools are designed as reinforced concrete

cantilevers for pool empty and full conditions. When the pool is empty, the soil

pressure is considered. When the pool is full, the pressure from the soil is ignored

since this could be the situation when the water test is performed. The wall acts as a

cantilever since it is rigidly connected to the base slab with sufficient width (300mm is

favourable) to provide the weight and the rigidity required for the stability. The

possible arrangement of joints in floor and walls are as below.

1 .£m

4.75m

4.75m

1.£m 1.£m

1_ — 4 . 5 m — — 4 . 5 m — — 4 . 5 m — • — 4 . 5 m — — 4 . 5 m —

1.0m 1.5m

Fig 3.2:Possible arrangement of joints

The Figure 3.3 shows the cantilever wall arrangement in plan used for this study to

minimize the complexity of the design using option 1 of BS 8007 with continuous

construction of the base slab for full restraint.

38

-21m-

Fig 3.3:Arrangement used for the study

As seen form the above figure, a heel of 2m width and 0.3m thick is provided right

round the periphery of the pool from inside. A toe of 0.3m wide and 0.3m thick is

required along three edges of the pool for fulfilling the stability requirements (i.e : Toe

is not required at 1.0m high wall edge).

All the necessary steps of design calculations for the pool without a deep end is

included in the design for a pool with a deep end. Hence a separate design calculation

file for a pool without a deep end is not included in this report. The comprehensive

design calculation file for a pool with a deep end is attached as Appendix A. The

design consisted of the following steps.

1. Check for stability of the walls for the three cases for tank full with no soil

backfill, tank empty with soil & surcharge and tank full with soil &

surcharge.

2. Check for soil pressure under the base.

3. Check for floatation.

4. Crack width calculation.

39

5. Design for ultimate moment.

6. Design for ultimate shear.

7. Check minimum areas of reinforcement for BS 8007 & BS 8110

8. Check for deflection.

9. Footing reinforcement.

10. Detailing of the joints.

The design calculation show that the walls require T 12 @ 200 c/c vertical and

horizontal in each face. The heel along all the four edges and toe along the three

edges require T 12 @ 200 c/c both ways top and bottom. The detailed drawings are

given in Appendix C.

3.2.2.2 Slab design

As can be seen from Fig 3.3, base slab is 21m long and 8.5m wide and the base slab

thickness is 0.3m to prevent floatation effects. The base slab is connected to the heel

of the wall as a hinge along all four edges. When the pool is full, total downward

pressure is resisted by soil pressure under the base. When the pool is empty, net

pressure applied on the slab is due to the difference of self-weight of the base slab

acting downwards and uplift force due to ground water. Upward force is less than the

weight of the slab. Hence the slab is designed without taking the uplift force and it will

be the most critical case to design the base slab. (i.e. the case if the pool is emptied for

some reason during dry season where no upward pressure due to ground water).

This yields T12@175 c/c in short span direction at top of the slab. This reinforcement

is sufficient for the prevention of the thermal and shrinkage cracking according to

figure A.2 of BS 8007.. Prevention of thermal & shrinkage cracking in long span

requires T12@175 c/c as the top reinforcement.

The slab is 300mm thick which needs the bottom surface zone of 100mm thick to be

considered to resist thermal and shrinkage cracking according to figure A.2 of BS

8007. The bottom r/f of T 10 @ 200 c/c both ways will be sufficient for bottom

surface zone.

40

Horizontal ties (T12 @ 200) are provided to take the vertical reaction between base

slab and the heel of the wall. These same ties provide resistance to horizontal

movement of the wall due to horizontal force on the wall due to water pressure

3.2.3 Detailing of the joints

All the wall and base slab joints are detailed as fixed joints as shown in Appendix C.

Sample drawing of a joint between wall and base slab is shown in Fig 3.4 below.

rn—

Fig 3.4:Fixed joint between wall and base slab

3.2.4 Summary of Structural arrangement

As mentioned in paragraph 3.2.2, detailed calculations for the pool without a deep end

is not included in this report since all the design steps are presented in the calculation

file for the pool with deep end which is annexed as Appendix A. Summary of the

calculations are tabulated in Table 3.1.The design was performed to following codes

of practice

BS 8110:1985 British standard code of practice for

Structural use of concrete

BS 8007:1987 British standard code of practice for

Design of concrete structures for retaining aqueous liquids

41

Component Concrete

thickness

Main

reinforcement

Transverse

Reinforcement

Additional

components

Drawing

Reference

1.1.6m

deep wall

300mm T 1 2 @ 2 0 0 e.f T 1 2 @ 2 0 0 e.f 2m heel

0.3m toe

Formwork-

b.f

Appendix

C

Page

A-42

2.Wall of

varying

depth from

1.0mtol.6m

300mm T 1 2 @ 2 0 0 e.f T 1 2 @ 2 0 0 e.f 2m heel

0.3m toe

Formwork

b.f

Appendix

C

Page

A-42

3.1.0m

deep wall

200mm T 1 2 @ 2 0 0 e.f T 1 2 @ 2 0 0 e.f 2m heel

Formwork

b.f

Appendix

C

Page

A-35

4.Base slab 300mm T12 @ 175

top

T10 @ 200

bottom

T12 @ 175 top

T10 @ 200

bottom

Appendix

C

Page

A-46

Table 3.1: Summary of reinforcement for pool without a Deep end

3.2.5 Design Drawings

Design drawings for the conventional pool without a deep end is presented in

Appendix C.

3.3 Design of swimming pool without deep end - Proposed method

3.3.1 Need for an alternative structure

The cost of construction of the conventional pool includes 300mm thick concrete

walls, high reinforcement quantities, and formwork for both sides of the walls, 300mm

thick concrete base slab, high reinforcement quantity for the base slab. The objective

of this study is to construct the walls and slab of the pool at a lower cost while

42

satisfying the basic requirements for a swimming pool as mentioned in section 1.1.

Generally gravity type retaining walls would be sufficient to fulfill the structural

requirements of the walls. Random rubble masonry is used as material of gravity type

retaining walls as described in Appendix B. The specific requirement of the walls to

be watertight will be met by constructing reinforced concrete lining wall from inside

the random rubble masonry walls. Random rubble masonry walls act as outside

formwork to these walls. As explained in the next paragraphs, base slab for this

proposed pool will be 150mm thick with relatively less reinforcement amount

compared to the base slab of the conventional type swimming pool. The base slab of

this proposed alternative has no discontinuity of the slab as required for the heel/slab

hinge arrangement in the conventional pool as describe in section 3.2.2.2.

3.3.2 Use of gravity wall type swimming pools for Sri Lanka

When gravity type swimming pools are designed, the following issues should be

addressed (Jayasinghe,2001):

1. The possibility of water table rising outside.

2. The prevention of any lateral (outward or inward) movement of gravity

walls.

3. The type of materials suitable for gravity walls.

3.3.3 Solution for the rising water table

In the gravity type swimming pools, the ground floor slab is not designed to withstand

the hydrostatic pressure exerted by the high water table. Therefore, it is necessary to

ensure that the water table remains sufficiently below the swimming pool floor.

Ensuring a part of the swimming pool is located above the ground can quite easily

satisfy this condition. For example, for a depth of 1.6m, 0.6m could be below ground.

The remainder can be above ground. It is quite unlikely for the water table to rise to

within 0.6m in laterite soil, unless in a low-lying area. Even if it rises, the self-weight

of the base, which consists of 75mm screed, 150mm base and further 25mm for

finishes, would be able to balance the upward thrust. This weight is about 6kN/m 2

whereas the upward pressure is also 6kN/m 2 .

43

3.3.4 The prevention of lateral movement of the wall

Since any minute inward or outward movement of the gravity wall can cause leakage

of water, it has to be prevented. The easiest way is to firmly anchor the wall by

locating it over the ground concrete slab. Having a projecting key below the retaining

wall can further enhance the anchoring effect. The starter bars for the concrete walls

also can be fixed prior to laying of concrete for the ground floor slab.

3.3.5 The material for the gravity wall

One material that could become a strong candidate for the gravity wall is random

rubble masonry. It is recommended by Chandrakeerthi (1998) that the random rubble

masonry walls should be constructed with 1:5 cement sand mortar. The characteristic

compressive strength that can be expected is about 2.0N/mm 2 . It is not advisable to

rely on the tensile strength. It is also not possible to rely on the random rubble

masonry for impermeability since it could be quite permeable through the mortar joint.

Therefore, the concrete lining should be constructed with adequate precautions to

avoid any weak or honeycombed concrete.

3.3.6 Structural design aspects of the proposed structure

The main structural components of the proposed arrangement consist of the following:

1. The random rubble masonry gravity retaining wall.

2. The reinforced concrete ground slab.

3. The reinforced concrete sidewalls.

The structural concepts and the additional precautions to be taken for each component

are described in detail.

3.3.7 Design of the random rubble gravity wall.

The random rubble gravity wall has to be designed for the lateral pressure due to

water. The size of the retaining wall is selected so that no tension will occur in it due

to the flexural stresses induced as a result of lateral loads. The dimensions of the wall

suitable for 1.5m depth indicated in Fig 3.5 were selected on this basis.

44

600 450

750

400

10QQ

600

150

S c r e e d c o n c r e t e

Fig 3.5:Section of wall of 1.6m deep

Random rubble walls require joints when the length is more than 15m. However, in

this wall, the length is 25.0m. Therefore, it is advisable to have a strategy to prevent

any cracks due to shrinkage although it is unlikely in this particular case. One strategy

is to construct the wall in lengths of about 12.0m while keeping gaps of 1.0m. (This is

anyway optional, provided good workmanship is available. Otherwise filling between

two adjacent walls may lead to porous finish). When the wall is about 2 weeks old,

the gaps can be filled up so that a portion of shrinkage has already occurred, thus

reducing the chances of cracking. Once the concrete lining is cast, the possibility for

shrinkage cracking is extremely remote.

3.3.8 Design of the wall

The reinforced concrete wall is cast by using the random rubble gravity wall as the

formwork on one side. Therefore, the same method adopted for the floor can be used

to determine the reinforcement to restrict the crack width in immature concrete. Since

plywood formwork would be used as the shuttering on the other side, the value of Ti

should be 25°C + 10°C (Table A.2 of BS 8007).

In C1.A.3 of BS 8007:Part 1, a restraint factor, R is introduced with R = 0.5 for

immature concrete with rigid end restraints. Since concrete is cast against the random

45 _ ^

7/

rubble wall, it is advisable to use the value of R as 0.5. It was suggested by Fonseka

(1995) that the use of the maximum value for R would be beneficial in Sri Lanka since

any error in estimating the value of T l would be adequately compensated. The use of

minimum steel ratio of 0.0035 would result in a crack width of 0.167mm (<0.2mm).

Therefore, the provision of 0.0035 as the reinforcement ratio is sufficient.

3.3.9 Reinforced concrete ground slab

The reinforced concrete ground slab need not have any flexural strength since the

weight of water can be resisted by the soil below. Therefore, it needs reinforcement

only to prevent early thermal cracks in immature concrete. BS 8007: 1987 allows the

prevention of early thermal cracks in continuously cast concrete member by the

provision of adequate amount of small diameter bars. It also allows the provision of

this reinforcement in a single layer. In this type of construction, it is advisable to

compact the soil below the ground floor slab thoroughly to avoid any weak pockets of

soil prior to laying the screed concrete.

For the design of the reinforcement in the slab, the crack width allowed should be

taken as 0.2mm. Equation 1 gives the maximum spacing of the cracks:

fa x Eq. 1

fb 2p

For deformed b a r s , ^ t , the ratio of the tensile strength of concrete to average bond

strength is equal to 0.67 (Table A. l of BS 8007: 1987). When a minimum steel ratio,

p, of 0.0035 is used with 10mm diameter bars,

Smax = 0.67 x 10 = 957mm

2 x 0.0035

The corresponding maximum crack width can be found from Equation 2.

46

fmax = Smax x a x J j Eq. 2

2

The value of Ti for the ground floor slab is 17° + 10° = 27°C. The value

recommended in BS 8007: 1987 for T, is 17°C (Table A.2). An additional 10° C is

allowed for seasonal variations.

Wmax = 957 x 10 x 10' 6 x 27°C = 0.129 < 0.2mm

2

Hence, the provision of 0.0035 on the reinforcement ratio is sufficient.

3.3.10 The structural arrangement of the swimming pool without deep end

using proposed method

On the basis of the calculations described above , the structural arrangement is shown

in Appendix D. The reinforcement details are also given. Since, it is necessary to

have a walkway of adequate width around the swimming pool, an embankment can be

formed using the excavated soil. This embankment should be paved at the top to

ensure that all the water collected will be drained and removed from the location of the

swimming pool in order to avoid any build-up of hydrostatic pressure.

Using the cement stabilization can further enhance the stability of the earth

embankment. It was reported by Jayasinghe & Perera (1999) that it is possible to

achieve compressive strengths in excess of 1.0 N / m m 2 for blocks when about 2 %

cement is used for stabilization of laterite soil. Therefore, the use of cement stabilized

properly compacted embankment would give a long lasting solution which is a pre­

requisite for a swimming pool. The soil excavated from the site can be used for this

purpose. For the cost calculation, this is not considered since the use of cement

stabilized soil is optional.

3.3.11 Design drawings of the proposed pool without a deep end

Design drawings of the proposed pool without a deep end is presented in Appendix D.

47

3.4 Design of swimming pool with a deep end -Conventional method

3.4.1General arrangement

SECTION

Designed as side w a l l — ,

Designed as • shallow end wall

:m long heel right round r— 1

PLAN

-!-2.7m-L —6.8m-

I.Jm

0.3m thick w

1 > ght round

lot g

Designed as deep end wall

;toe

Fig 3.6:Plan and section of conventional swimming pool with a deep end

Conventional design concepts of swimming pools with deep end are very much

similar to the design concepts of conventional of swimming pools without deep ends.

The major changes are only the dimensional differences. In the design included in this

study, the deep end wall detail is extended to the sidewall up to a distance of 9.5m

from the deep end as shown in the above figure. Then it changes to a less strong detail

called side wall and remains same up to the shallow end. The shallow end has another

detail that is the weakest and it is called the shallow end wall. The complete

calculation exercise is attached to this report as Appendix A.

48

3.4.2 The structural arrangement of the swimming pool with a deep end using

conventional method

The detailed design was carried out using the same steps mentioned in 3.2 ,ie for pool

design without deep end. The comprehensive calculation file is attached in appendix

A. The detailed drawings are attached in appendix E.

The summary of the findings of the pool with deep end using the conventional method

is tabulated below.

Component Concrete Main r/f Transverse Additional Calculation Drawing

thickness r/f components reference Reference

1 .Deep end 300mm T 1 6 @ T12 @ 2m heel Appendix Appendix

wall 175 e.f 125 e.f 0.6m toe A E-2

formwork- Page

b.f A-27

2.Side wall 300mm T12 @ T 1 2 @ 2m heel Appendix Appendix

200 e.f 200 e.f 0.3m toe A E-4

formwork Page

b.f A-42

3.Shallow 200mm T12 @ T12 @ 2m heel Appendix Appendix

end wall 200 e.f 200 e.f formwork A E-3

b.f Page

A-35

4.Base slab 300mm T 1 6 @ T 1 2 @ — Appendix Appendix

175 top 175 top A E-5

T 1 0 @ T 1 0 @ Page

200 200 A-46

bottom bottom

Table 3.2: Structural arrangement of the conventional pool With a deep end

49

3.4.3 Design drawings of the conventional pool with a deep end

50

Design drawings of the conventional pool with a deep end are presented in Appendix E.

3.5 Design of swimming pool with a deep end - Proposed method

3.5.1 Need for an alternative method

The concepts highlighted in Section 3.3.1 are still valid in looking for an alternative

method to design a swimming pool with a deep end. The same arguments for

designing the walls and the slab provide a cost effective solution. Random rubble

masonry sections obtained for the deep end require 2.4m widths at bottom. This

section does not gain the expected cost savings and it is very inconvenient to go for

sections of that much wide. Supply and storing of huge material quantities make

inconvenience to other site arrangements as well. Further investigations diverted the

study to use counter fort retaining walls for the deep end, which would be structurally

satisfactory and less inconvenient than larger rubble sections. The other common

features of the proposed method without a deep end discussed in Section 3.3 are not

presented here to avoid repetition. Design and detailing of shallow end and sidewalls

up to a total depth of 1.5m will be identical as swimming pool without a deep end.

3.5.2 Counter fort retaining walls at deep end

The length and height of the deep end are 12.5m and 3.1m respectively. A reinforced

concrete wall of 150mm thick, simply supported at top and bottom bears the triangular

load exerted by water pressure. This thickness is minimum required for the structural

requirements. This has to be increased to 175-200mm due to constructional

requirements.(4 layers of T10 reinforcement bars are to be provided). Cost study in

Chapter 4 has been done taking this thickness as 175mm. As can be seen from Fig 3.7

below, this wall rests on 750mm deep beam at the top (i.e. the walk way slab) and the

bottom slab vertically.

Fig 3.7:Dimentions of the counter fort retaining wall

Used to retain water at deep end

Fig 3.8:General arrangement of the counter forts

This wall spans horizontally between counters forts placed at 3.125m centers (5

counter forts totally for 12.5m long deep end wall). Thus the slab spans two-way to

withstand the triangular load exerted by the water pressure. The moment applied to

the wall is very small compared to the load on cantilever deep end wall in the

conventional swimming pool. The crack width of wall needs to be checked over the

51

vertical supports for hogging moment where cracks open to water contacting side.

Nevertheless the crack widths are calculated in the outside faces to verify any

possibility of exceeding the allowable limits. That calculation shows there is no such

exceeding of crack widths and hence no harmful effects will occur due to ground

water outside. This service moment is very small and the reinforcement requirement is

T12@200 c/c at the inner face horizontally. Inner face vertical & outer face vertical &

horizontal reinforcement requirement is T10@250 centers. These quantities are very

much lesser compared to the reinforcement requirements for the cantilever deep end

walls of the conventional swimming pool. The counter fort is designed as flanged

cantilever T-beam with varying depth. Links have to be provided adequately between

the wall slab and counter fort and between the base slab and counter fort to avoid

tearing off.

750

Section thro' wall

Fig 3.9: Dimensions of the counter fort

T10@175 for both faces vertical & horizontal will be sufficient as the links of the

counter fort.

Pressure exerted on the counter fort is calculated by dividing the height into ten equal

horizontal segments. This pressure is transferred to the base through a heel of 1.5m

long and a toe of 1.2m long.

52

The longitudinal walls of the deep end are also provided with counter forts of this sort

at 3.4m centers (Refer Fig 3.8).

3.5.3 Reinforced concrete ground slab design

The base slab is of two thick nesses. One part is 150mm thick as shown in the fig 3.10

below (slab A). Slab B is a combination of the foundation of the counter fort of

250mm thick (of a heel of 1.5m long and a toe of 1.2m long) and a middle portion of

150mm thick.

Slab A : 150mm thick to resist « S-thermal cracks only

-5* Slab B :250mm thick to foundation of counter fort & 150 mm for rest

0.9m 1.4m

"m

GWT 2 j "

-15.5m- -2.7m 1 6.8m 1 ^ 1.35m

Fig 3.10:Section of pool showing slab thick nesses for design

Slab A is designed as in section 3.3.9 only to resist early thermal cracks in immature

concrete.

Foundation of the counter fort is designed considering all possible load cases on the

wall. The arrangement of reinforcement of the base of the counter fort is shown in Fig

3.11. y

The rest of the slab B is of 150mm thickness.

53

250mm ihick slab for foundation of counter fort

150mm thick slab for rest of the base

Fig 3.1 l:Base slab arrangement

hi -el

io e aoo c.c

Yl£ 8 £00 c.c 1jon f o r

•toe

Fig 3.12:Base slab reinforcement arrangement

3.5.4 Design Drawings

The drawings for the proposed pool with the deep end are in Appendix F.

54

Chapter 4

Cost Study

4.1 General

The cost study was carried out to determine the cost effectiveness of the proposed

structural arrangements. The cost will be a better indicator since the alternative structural

forms suggested involve different materials than only reinforced concrete.

4.2 Basic Rates for the main structure.

The basic rates of the construction materials and workmanship are as given below.

Excavation

Rubble work

Grade 30 concrete

Reinforcement

Shuttering

Screed

Rs. 350.00 p e r m 3

Rs .2,400.00 per m 3

Rs. 9,000.00 per m 3

Rs.75,000.00 per M T

Rs. 750.00 per m 2

Rs. 350.00 per m 2

4.3 Cost of construction of reinforced concrete pool structure without a

deep end.

Appendix C shows the dimensions and details of the reinforced concrete pool structure

without a deep end and Table 4.1 shows the cost calculation of the reinforced concrete

pool structure without a deep end.

55

Item Sub Items Unit Quantity (Rs) Rate(Rs) AmountfRs)

1. Excavation - m 3 848 350 296,800

2. Blinding concrete -

m 2 354 350 123,900

3. Form work

a. Stop board around

base

m 2 24

3. Form work b. External Formwork m 2 106

3. Form work

c. Internal Formwork m 2 103

3. Form work

Total m 2 233 750 174,750

4. Reinforcement

a. Base slab kg 6223

4. Reinforcement

b . 1.6m high wall kg 482

4. Reinforcement c. 1.0m high wall kg 341 4. Reinforcement

d. Side walls kg 1634

4. Reinforcement

Total with 7 % lsps &

wastage

kg 9,288 75 696,600

5. Concrete

a. Base slab m 3 106

5. Concrete

b. 1.6m high wall m 3 6

5. Concrete c. 1.0m high wall m 3 3 5. Concrete

d. Side Walls m 3

21

5. Concrete

Total m 3 136 9000 1,224,000

T O T A L C O S T 2,516,050

Table 4 .1 : Cost calculation of reinforced concrete pool structure without a deep

end

56

4.4 Cost of construction of Proposed pool structure without a deep end.

Appendix D shows the dimensions and details of the proposed pool structure without a

deep end.

Table 4.2 shows the cost calculation of the proposed pool structure without a deep end.

Item S u b Items Unit Quantity Rate Amount

1. Excavation - m 3 788 350 275,800

2. Blinding concrete -

m 2 394 350 137,900

3.Random Rubble

masonry

a. For 1.0 m high wall m 3 8

3.Random Rubble

masonry

b. For 1.6 m high wall m 3 15 3.Random Rubble

masonry c. For side walls m 3 50

3.Random Rubble

masonry

Total Random Rubble

masonry quantity

m 3 73 2400 175,200

4. Form work

a. Stop board around base m 2 13

4. Form work b. Internal formwork m 2 103 4. Form work

c. Stop board of top slab m 2 12

4. Form work

Total Formwork Area m 2 128 750 96,000

5. Reinforcement

a. Base slab kg 3272

5. Reinforcement

b . 1.6m high wall kg 180

5. Reinforcement c. 1.0m high wall kg 133 5. Reinforcement

d. Side Walls kg 685

5. Reinforcement

e. Top Slab kg 531

5. Reinforcement

Total with 7 % for wastage kg 4801 75 360,075

57

Item Sub Items Unit Quantity Rate Amount

6. Concrete

a. Base slab m 3 59

6. Concrete b. Top Slab m 2 9 6. Concrete

c. Side Walls m 3 14

6. Concrete

Total m 3 82 9000 738,000

T O T A L C O S T - - 1,782,975

Table 4.2 : Cost calculation of proposed pool structure without a deep end

4.5Cost of Construction of reinforced concrete pool structure with a

deep end.

Appendix E shows the dimensions and details of the reinforced concrete pool structure

with a deep end. Table 4.3 shows the cost calculation of the reinforced concrete pool

structure with a deep end.

58

Item Sub Items Unit Quantity Rate Amount

1. Excavation - m 3 1131 350 395,850

2. Blinding concrete -

m 2 364 350 127,400

a. Stop board m 2 24

b. 1 .Om high wall external m 2 13

c. 1.0m high wall external m 2 12

3. Form work d. 3.1m high wall external m 2 41

3. Form work e. 3.1m high wall internal m 2 39

f. Side walls external m 2 96

g. Side walls internal m 2 93

Total m 2 318 750 238,500

a. Base slab kg 6223

b. Deep end wall kg 1490

4. Reinforcement c. Shallow end wall kg 341

4. Reinforcement d. Side walls kg 2307

e. Tie bars kg

333

Total with 7% as wastage kg 10,694 75 802,050

59

Item Sub Items Unit Quantity Rate Amount

a. Base m 3 106

b. Shallow end wall m 3 3

5. Concrete c. Deep end wall m 3 12

d. Side walls m 3 28

Total concrete Volume m 3 149 9000 1,341,000

T O T A L C O S T 2,904,800

Table 4.3 : Cost calculation of reinforced concrete pool structure with a deep end

4.6Cost of construction of proposed pool structure with a deep end.

Appendix F shows the dimensions and details of the pool structure with a deep end. Table

4.4 shows the cost of proposed pool structure with a deep end.

Item Sub Items Unit Quantity Rate Amount

1. Excavation - m 3 1102 350 385,700

2. Blinding concrete -

m 2 404 350 141,400

3. R.R. masonry - m 3 35 2,400 84,000

a. Stop boards m 2 28

b. 3.1m high walls m 2 162

4. Formwork c. Counter forts m 2 64

d. Side walls m 2 62

e. 1.0m high walls m 2 13

f. Walkway slab m 2 19

Total m 2 348 750 261,000

60

Item Sub Items Unit Quantity Rate Amount

a. Base slab kg 4685

b. Deep end wall kg 506

5. Reinforcement

c. Shallow end wall kg 133

5. Reinforcement d. Side walls kg 1138

e. Top slab kg 340

f. Counter forts kg 249

Total with 7% wastage kg 7,534 75 565,800

a. Base concrete m 3 69

b. Walls m 3 16

6. Concrete c. Top Slab m 3 9

d. Counterfor ts m 3 5

Total m 3 99 9,000 891,000

T O T A L C O S T 2,328,900

Table 4.4 : Cost calculation of proposed pool structure with a deep end

4.7 Cost Comparison

Table 4.5 shows the cost comparison among the four cases discussed above.

61

Cos

t fo

r co

nven

tion

al s

wim

min

g po

ol w

itho

ut a

dee

p en

d

Cos

t fo

r pr

opos

ed s

wim

min

g po

ol w

itho

ut a

dee

p en

d

Cos

t fo

r co

nven

tion

al s

wim

min

g po

ol w

ith a

dee

p e

nd

Cos

t fo

r pr

opos

ed s

wim

min

g po

ol w

ith a

dee

p e

nd

a) Excavation 296,800.00 275,800.00 395,850.00 385,700.00

b) Blinding concrete 123,900.00 137,900.00 127,400.00 141,400.00

c) Random rubble masonry 175,200.00 84,000.00

d) Formwork 174,750.00 96,000.00 238,500.00 261,000.00

e) Reinforcement 696,600.00 360,075.00 802,050.00 565,800.00

f) Concrete 1,224,000.00 738,000.00 1,341,000.00 891,000.00

T O T A L 2,516,050.00 1,782,975.00 2,904,800.00 2,328,900.00

Fig:4.5: Cost comparison of different swimming pools

4.8Conclusions

From the cost comparison ,it can be seen that the alternative structural forms suggested

could give a cost saving in the range of 3 0 % for one without a deep end and 2 1 % for one

with deep end. This indicate that it is worthwhile adopting these alternative structural

systems in future swimming pools constructed on firm ground with low water table.

62

Chapter 5

Alternatives for associated structures

5.1 Introduction

As mentioned in Chapter 2 water treatment or purification is the next most important

consideration of swimming pools. The physical and chemical pollution of swimming

pools can be divided into the following four zones.

1. Surface Pollution

2. Dissolved Pollution

3. Suspended Pollution

4. Deposited insolubles

. Surface pollution

\ D i s s o l v e d pollution

Suspended pollution

Insolubles

Fig 5.1: Water pollution zones in pools

5.2 Methods of removal of pollution

5.2.1 Removal of surface pollution

1. Remove surface water as soon as possible

2. Add sufficient chlorine to maintain free chlorine residual of 1 - 2 mg/L at all

t imes.

63

5.2.2 Removal of dissolved pollution

1. Provide adequate filtration cycle

2. Add sufficient chlorine to breakdown, nitrogenous matter and render it

harmless

5.2.3 Removal of suspended pollution

1. Use minimum quantity of chemicals

2. Maintain balanced water in the pool

3. Maintain careful control of pH and Alkalinity

4. Use chemicals which do not produce suspended solids.

5.2.4 Removal of deposited insoluble pollution

1. Adopt vacuum cleaning of the pool bottom daily.

5.2.5 Removal of the biological pollution in the swimming pool

1. Maintain free chlorine residual of 1 - 2 mg/L in the pool water at all times,

chlorine will kill - off all the bacteria immediately and render the pool water

safe for public bathing.

2. Provide an efficient top water drew - off system

3. Provide an efficient filtration system

5.3 Structural forms for water treatment

5.3.1 Traditional swimming pool forms for water treatment

The study made on the system shows no important structural components are present

within it

But for removal of dissolved gases and for aesthetics of swimming pools cascade aerators

are part of several pools. Figure 5.2 shows a schematic diagram of an aerator. The aerator

is generally made using reinforced concrete. This is now built using ferro - cement

technology which is cheaper to reinforced concrete structure.

64

Fig. 5.2: Schematic diagram of an aerator

5.3.2 Alternative forms - Aerators built using ferro - cement technology

The cascade aerator are built using ferro - cement technology. This cuts down the cost by

3 0 % of the aerator. This reduction of cost when compared with the total cost is not

significant. The pools built in schools may use this since the smallest saving is important

to the government funded school system.

5.4 Cost study

The cost study for the ancillary work of the swimming pool is as given below.

5.4.1 Cost for pool without deep end

Following list comprises the cost incurred in ancillary structures for a swimming pool

without deep end. N o spectator accommodation facility is taken into consideration for this

cost study.

1. Pre-cleansing areas - showers and footbaths Rs. 60,000.00

2 Ceramic Tiling Rs . 450,000.00

3 Walkway slabs and floors of changing and

shower rooms (wet areas) Rs. 80,000.00

4 Stainless steel hand rails Rs. 40,000.00

65

5. Sanitary accommodation Rs. 40,000.00

6. Pipe work for water circulation, water

supply & drainage Rs. 50,000.00

7. Electrical installations & power supply

8. Electrically - driven centrifugal pump

Rs. 60,000.00

Rs. 60,000.00

9. Filters Rs . 80,000.00

10. Plant room for 7., 8., 9. above Rs. 30,000.00

11. Chlorinator Rs . 60,000.00

12. Aerator (optional)

Total

Rs . 40.000.00

Rs. 1,100,000.00

5.4.2 Cost for pool with deep end

The items for the pool with deep end are some as for 5.4.1 above. But the quantities

increase in several items.

The cost for the pool with deep end =Rs. 1,600,000.00

5.5 Cost savings

There are no significant cost savings with regard to the other ancillaries as shown above.

The maximum possible saving would be less than 1% of the total cost.

66

5.6 Summary

The cost study carried out for other ancillary structures and facilities shows that a

significant cost is involved for providing these.

These need to be further studied with respect to modern technological findings with the

aspect of water purification to minimize the cost incurred.

•A

7 f:\

67

Chapter 6

Conclusions and Recommendations

6.1 General

For developing countries, it is useful to promote cost effective structural solutions for most

of the civil engineering activities in order to make the maximum use of limited resources

since most of the cost effective solutions tend to use less materials. The same is true for

swimming pools as well.

In this study, alternative solutions were developed for swimming pools without and with

deep ends.

The following are the main features of these alternative solutions:

6.1.1 Main features of Swimming pools without deep ends

1. The swimming pool without deep end does not have any cantilever walls. But

its walls act as gravity retaining walls to withstand the forces exerted by water

pressure and earth pressure when the pool is full and empty respectively. The

material used is Random rubble masonry.

2. The walls have inner lining of reinforced concrete to eliminate any possibility

of water leaking through the random rubble masonry wall.

3. The base slab is designed to resist only thermal and shrinkage cracking.

6.1.2 Main features of Swimming pools with deep ends

1. Gravity retaining wall concept is still valid. But the deep end requires very

wide random rubble sections. Hence deep end was designed using counter fort

retaining walls. The service moment applied on the wall is of small magnitude

making reinforcement requirement to a lesser value.

68

2. At the shallow end base slab was designed only to prevent thermal and

shrinkage cracking. Base for deep end was designed to fulfill foundation

requirements of the counter fort retaining wall.

In order to determine the cost effectiveness of these alternative solutions a detailed cost

study was carried out The study has revealed the following. First the structural cost alone

was computed since this study was mainly aimed on reduction of costs using new methods

for structural design concepts.

Table 6.1 gives the structural cost, cost saving and the cost saving as a percentage.

Cost Cost Saving of

proposed pool

over

conventional

pool

(Rs.)

Cost Saving as a

percentage

(%)

1 .Pool using reinforced

concrete without deep end

2,516,050.00

2.Proposed pool without

deep end

1,782,975.00 733,075.00 2 9 . 1 %

3.Pool using reinforced

concrete with deep end

2,904,800.00

4.Proposed pool with deep

end

2,328,900.00 575,900.00 19.8%

Table 6.1 :Structural costs, cost saving and the cost saving as a percentage

The study was directed to see whether there was any possibility of reducing the cost for

other ancillaries associated with the swimming pool. But no significant achievement was

attained. The costs for all components were studied. Table 6.2 gives the total cost, cost

saving and the cost saving as a percentage.

69

Cost Cost Saving of

proposed pool

over

conventional

pool

(Rs.)

Cost Saving as a

percentage

(%)

1 .Pool using reinforced

concrete without deep end

3,616,050.00 - -

2.Proposed pool without

deep end

2,882,975.00 733,075.00 2 0 . 3 %

3.Pool using reinforced

concrete with deep end

4,504,800.00 - -

4.Proposed pool with deep

end

3,928,900.00 575,900.00 12.8%

Table 6.2:Total costs cost savings and cost saving as a percentage

The two tables above clearly depict the cost saving, using the alternative structural forms.

This reduction of cost is very important to Sri Lanka where there are many parties and

private houses interested to build their own swimming pool. Especially this will benefit

the schools. Majority of schools in Sri Lanka do not belong swimming pools. Certain

schools share swimming pools with other schools with difficulties.

This study will be beneficial to the interested parties in Sri Lanka in future.

70

REFERENCES: -

1 .Cost effective structural forms for swimming pools Dr.M.T.R Jayasinghe

2.Design for controlled cracking of water retaining structures based on Bs 8007 - 2000 Dr. S.M.A.Nanayakkara

3.Swimming P o o l s - 1 9 8 8 Philip. H. Perkins

4.British standard code of Practice Structural use of Concrete BS 8110:part 1: 1985

5.British standard code of Practice for Design of concrete structures for retaining aqueous liquids BS 8007: 1987

6.The design of water retaining structures Ian Batty & Roger Westbrook

7.Reinforced Concrete Design's Handbook Charles E. Reynolds & James C. Steedman

8.Reinforced Concrete Design Mosley and Bungay

9.Reinforced Concrete Design theory and Examples T.J. McGinley & B.S. Choo

10.Design and Planning of Swimming Pools-1979 John Dawes

11 .Chandrakeerthy, S.R.De. S. (1998) " A study of random rubble masonry construction in Sri Lanka", Transactions- 1998, Part B, Volume 1, pp 124-149.

12.Fonseka, M.C.M. (1995), "On Bs 8007 recommendation for reinforcement to control thermal and shrinkage cracking", Engineer - Journal of institution of Engineers-Sri Lanka, Vol: XXDINo: l,pp 5-12.

13.Jayasinghe, C. & Perera A.A.D.A.J. (1999), "Studies on load bearing characteristics of cement stabilized soil blocks", Transactions-1999, Vol: 1, part B, pp 63-72.

14.Foundation Analysis and Design Joseph E. Bowles

15.Design of Liquid Retaining Concrete Structures R.D Anchor & Edward Arnold

16. Water Supply Engineering Santosh Kumar Garg

17.Service reservoir design ,with particular reference to economics and the 'Simple Supported Wall' concept J.WamesleyThe Structural Engineer /Volume 59A/No.9 September 1981

71

Appendix A

Design calculations of the conventional swimming

With Deep End

The following diagram was extracted from 2.2.3 where a set of dimensions are given for

swimming pools for schools. The deep end is 3m which is quite sufficient.

0.<5m

Designed as • shallow end wall

I2.5n

1.4m i

-15.5m- -L2.7m-J 6.8m-

S E C T I O N

Designed as-side wall

-9.5m--25.0m-

3.0m

- Designed as deep end wall

P L A N

Fig.A-1 :Plan and section of deep end wall

In the above figure it can be seen that there are three different wall types. The wall designed to

withstand 3m height of water at the deep end is detailed along the side wall also for a length of

9.5m as shown above. The shallow end wall is designed to withstand a water height of

0.9m.The side wall which is to withstand 1.7m height of water at deep end side is continued to

shallow end.

Several trial and error attempts concluded the following heel, toe and thickness arrangements to

be satisfactory on stability requirements.

Heel : 2m from wall intenal face

Toe : 0.6m from wall external face for deep end wall type

Toe : 0.3m from wall external face for side wall type

No toe is required for shallow end

Base slab thickness is 0.3m

Walls are 0.3m thick except shallow end wall which is 0.2m thick

A - 2

Ref Calculat ions O u t put

Design of Deep end wall

3000

3 E -2000- - 4 ^ 6 0 0 ^

300

Fig A-2: Section of deep end wall

For the design

Design data :-

Density of water = 10kN/m 3

Density of earth = 18kN/m 3

Density of concrete = 25kN/m 3

Grade of concrete = 30N/mm 2

Grade of reinforcement = 460N/mm 2

Freeboard is 0.1m below top of wall

Ground water table is 2m below ground level.

Superimposed dead load on earth = 5kN/m 2

Bearing capacity of soil

Friction angle

Service moment from water

= 150kN/m'

= 30°

= 1 0 x 3 3 = 45kNm/m 2

6

Horizontal pressure from earth = 18 rT-Sin30

M + S i n 3 0 J

6kN/m 2

A - 3

Ref Calculat ions Ou t pu t

Case

Stability Calculations

Tank full with no soil backfill

3000

W3 3 0 0

Fig A-3:Forces acting on deep End wall

Weight of water on heel

W, = 3 x 2 x 10 = 60kN/ m

Weight of wall,

W 2 = (0.3) (3.1) (25) = 23 .3kN/ m

Weight of heel,

W 3 = (2.9) (0.3) (25) = 21.8kN/ n

Force due to water pressure,

P = 1 0 x 3 z = 45kN/ m

2

Taking moments about A,

Overturning moment = 45 x 1.3

= 5 8 . 5 k N m / n

Restoring moment

= W, x 1.9 + W 2 x 0.65 + W 3 x 1.45

= 60 x 1.9+ 23.3x 0.75 + 21.8 x 1.45

= 163kNm/ m

A- A - 4

Ref Calculations Out put

Factor of safety against overturning

= 163.00

58.5

= 2.79 > 2

Hence satisfactory

Case I I : Tank empty & soil + Surcharge

2 0 0 0

Water _ Table

Toe 1 1 0 0

4 , )f 2 0 0 0 ^ ^ S O O T C

3 0 0

Fig A-4:Tank empty condition

Take moments about B,

Restoring moments

Soil = 1 8 x 2 x 0 . 6 x [ 2 . 3 + 0.3]

+ ( 1 8 - 1 0 ) (1.1) (0.6) [2.3 + 0.3]

= 58.2kNm/ m

Surcharge = 5 x 0.6 x [2.6] = 7.8

Water = 10 x 1.1 x 0.6 [2.6] = 1 7 . 2

Wall = 2 5 x 3 . 1 x 0 . 3 x 2 . 1 5 = 5 0

Base = 25 x 2.8 x 0.3 x 2.9/ 2 = 30.5

Total restoring moment = 163.7 kNm in

A - 5

Ref Calculat ions O u t put

Calculation of overturning moments

V r—K

K N / m 2

Fig A-5: Pressures acting from outside

Pressure due to dry soil above water table

= 1/3 x 1 8 x 2

p i = 12kN/ m

2

Pressure due to submerged soil

= 1/3 ( 1 8 - 1 0 ) (1.1)

p i = 2 .9kN/ m

2

Pressure due to water

= l O x 1.1

p3 = l l k N / m

2

Surcharge pressure, p4 = 5 x 1 / 3 = 1.7kN/m

Overturning moment

= Moment due + Moment due. + Moment due to soil to surcharge. To water

= ' / 2 x p l x 2 x ( 2 x + 1.4) + ! / 2 x p l x 2 x 1.1

+ ' / 2 p 2 x 1.1 x 7.1x2 + 0 3 + p 4 x 3 J . + 0.3

1.3 - J ^2 J

U +0.3 " ~ 2

+ lA

x p3x

= 45.98 kNm/,

U . + 0.3 13

A - 6

Ref Calculat ions O u t p u t

Factor of safety against overturning

= 163.7

45.98

= 3.56 Hence Satisfactory

Case I I I : Tank full + Soil + Surcharge Take moments about B,

Overturning moment about B,

= 4 6 k N m / m

Restoring moment due to water

= 3 x 1 0 x 3 x 1 2

= 45kNm/ m

Total restoring moment = 163.7 + 45

= 208.7 kNm/„ Factor of safety = 208.7

46

= 4.5

Hence satisfactory

Soil Pressure under the base

Case II

FoS = 3.6

Overturning

OK

Calculate moment about center line of base

I W1 • P = 4 5 K N / m 2

W3 - 2 1 5 0 - 7 5 0 - 7 '

A - 7

Rcf Calculat ions O u t p u t

Case I : (Tank full with no soil)

W, = 60kN/ m (as before) W 2 = 23 .3kN/ m ( -do- ) W 3 = 21 .8kN/ m ( -do- )

Total vertical load V = Wi + w 2 + w 3

= 60 + 23.3 + 21.8

= 105.1 k N / m

Overturning moment = P x 1.3

= 45 x 1.3

= 58.5kNm/ m

Restoring moment = Wi x 0.45 - W 3 x 0.7

= 6 0 x 0 . 4 5 - 2 3 . 3 x 0.7

= 10.69 k N m / m

Net restoring moment = 1 0 . 6 9 - 5 8 . 5

= - 4 7 . 8 k N m / m

Soil pressure = 105.05 + 4 7 . 8 x 2 . 9 2 . 9 x 1 1/12 x 1 x 2 . 9 J x 2

= 36.22 ± 3 4 . 1

= 70.32 or 2.12 k N / m

2

Hence satisfactory

Case 2 (Tank empty, soil + surcharge) Total vertical load

= W 2 + W 3 + Soil + Surcharge

= 23.3 + 21.8 + (18) (3.1) (0.5) + 5 x 0.5

= 75.5 kN

Restoring moment about B = 163.7 (previous calculation - page A5)

Balance restoring moment about B

= 1 6 3 . 7 - 4 6 = 117 .7kNm/ m

A - 8

Ref Calculat ions Ou t put

Mc = 1 1 7 . 7 - 7 5 . 5 x 1.45

= 8 .2kNm/ m

Soil Pressure

= 75.5 ± 8.2 x 2j)

2 . 9 x 1 1 / 1 2 x 1 x 2 . 9 ' 2

= 26 ± 5 . 9

= 32 or 20 k N / m

2

Hence satisfactory

Case I I I : Tank full + Soil + Surcharge

Vertical load = W, + W 2 + W 3 + Soil + Surcharge

= 60 + 75.5 = 135.5 kN

Restoring moment about B

= Restoring moment + Moment due to in case II water

= 163.7 + 6 0 x 1

= 223.7 kNm

m

Overturning moment about B,

= 4 6 - 5 8 . 5

= -12.5 kNm

m

Net restoring moment about B,

= 2 2 3 . 7 + 12.5

= 236.2 k N m / m

4 A - 9

Ref Calculat ions O u t p u t

Moment about center line

= 2 3 6 - 1.45 x 135.5

= 39.7 k N / m

2

Soil pressure = 135.5 ± 39.7 x 2/9

2.9 x 1 V2 x 1 x 2 .9 '

= 46.7 ± 2 8 . 3

= 75 or 18.4 kN

m

Hence satisfactory

Design of cantilever wall for water pressure

G.L

3 0 0 0 3 1 0 0

J4 3 0 0

3 0 0

Fig A-7:Cantilever wall for Water pressure

fa, = 3 0 N / n

fy = 4 6 0 N / m m (Type II deformed bars)

Cover to horizontal reinforcement

= 40mm

Cover to vertical reinforcement

= 4 0 + 1 2

= 52mm

A - 10

Ref Calcula t ions O u t put

E concrete = OkN/mm

E steel = 2 0 0 k N / m m

2

Effective height of wall

= 3 0 0 0 + ( 3 0 0 - 5 2 - 8 )

= 3240mm

Effective depth = 3 0 0 - 5 2 - 8

= 240mm

Sorvice moment from water = 45 kNm

Ultimate moment from water,

Mu = 1.4 x 10x3 .24 /6

= 79.4kN/m

Ultimate shear from water,

Vu = 1 0 x 3 2 x l . 4

2

= 63 kN

Design for m a x m crack width

For the service moment of 45kNm from the Table,

A2.5, y l 6 @ 175 is satisfactory.

A - 11

Ref Calculat ions Ou t pu t

Table

A2.5 Check for floatation (weight of the toe is not taken

into consideration)

Vertical

bars

Y 1 6 @

175

Fig A-8: Weight of the structure against floatation

Weight of wall (with no heel)

Wa = (12.5 + 0.3 x 2) (0.3) (3.1 + 0.3) x 25

= 334.05kN

S o , W b = (13.1) (0.2) (1.3) (25)

= 85.15kN

Weight of 2 side walls

Wc = (1 + 1.4) Y2 (15.5) (0.3) x 2 5 x 2

= 279 kN

Wd = (1.4 + 3.1) (2.7) (0.3) (25) (2)

= 91.1kN

We = 3.1 x 6 . 8 x 0 . 3 x 2 5 x 2

= 316.20kN

A - 12

Ref Calculations O u t pu t

Weight of the base

Weight of F = 1 3 . 1 x 1 5 . 5 1 x 0 . 3 x 2 5

Wf = 1523.86kN

Wg = 13.1 x 3 . 1 4 x 0 . 3 x 2 5

= 308.51kN

Wh = 1 3 . 1 x 6 . 8 x 0 . 3 x 2 5

= 668.1kN

Total weight against floatation

= Wa + Wb + Wc + Wd + We + Wf + Wg + Wh

= 334.05 + 85.15 + 279+91.1 +316.20 +

1523.86 + 308.51 +668 .10

= 3605.97 kN

Calculation of upthrust

G . L

W1

W.T •

2 7 0 0 •6800-

Fig A-9:Upthrust on the structure

A - 13

Ref Calculations Out put

Upthrust = W, + W 2

= (6.8 + 0.3) (12.5 + 0.6) (1.4) (10) +

(2.34 x 1.4) (1/2) (13.1) (10)

= 1302.14 + 214.58

= 1516.72kN

FoS against floatation

= 3605.97 1516.72

= 2.4 > 1.1 Hence Satisfactory

Crack width calculation

B

h

Z

-•C x

Section Stress distribution

Fig A- 10: Stress distribution for crack

Width calculation

A - 14

Ref Calculat ions Ou t put

ae = 15 As = 1149mm 2/m (Y16 @ 175 )

P '-= As/bd

1 14.0

1 0 3 x 240

= 0.00479

X = d

-ae/? + / ae \ /

p (ae p + 2)

- -15 x 0 . 0 0 4 7 9 ^ / 15 x 0.00479(15 x 0.00479 +2)

= 0.314

X = 0 . 3 1 4 x 2 4 0

- - 75.35mm

Z_ = 1 - 0 . 3 1 4 = 0.895 d 3

Z = = (0.895) (240) : 215mm

Stress in steel = M = 4 S v 1 n 6

A s x Z 1 1 4 9 x 2 1 5

Stress in steel = 182 N / m m 2

Cs = as < 0.8/y Es

182 = 0.00091 200 x 10 3

CI = C s x h - x ^ d - x _

= 0.00091 ( 3 0 0 - 7 5 . 3 5 ) ( 2 4 0 - 7 5 . 3 5 )

= 0.00124

The stiffening effect of concrete C2 = b t ( h - x ) (a' - x )

3Es A s ( d - x)

= 1000 x ( 3 0 0 - 7 5 . 3 5 ) 2

3(200 x 10 3) (1149) (240 - 75.35)

= 0.00044

-A A - 15

Ref Calculations Out put

Average strain

Cm = CI - C 2

= 0 . 0 0 1 2 4 - 0 . 0 0 0 4 4

= 0.000795

The crack width,

© = 3 acr Cm

= 1 + 2 (acr - Cmin) ( h - x )

Where

acr =

acr = distance from the point considered to

the surface of the nearest longitudinal

bar

98mm 175 2 + ( 6 0 ) 2 8

to = 3 x 98 x 0.000795 1 + 2(98 - 52)

( 3 0 0 - 7 5 . 3 5 )

= 0.166 < 0.2 Hence crack width O.K.

Design for Ultimate Moment K = Mu

fcuW

79.4 x 10 6

30 x 1 0 3 x 2 4 0 2

= 0.046 < 0.156

= d 0.5 + 0.25 - K 0.9

= d 0.5 0.25 - 0.046 0.9

= 0.95d

= 0.95 x 240

= 228mm

A - 16

Ref Calculations Out put

As required = Mu 0.87 x fy x Z

= 79.4 x 10 3

0.87 x 460 x 228

= 870mm 2 /m

As provided = 1149mm/m

Hence O.K.

Design for ultimate shear

Vu = 63kN

t. = 63000 1 0 0 0 x 2 4 0

100 As = 100 x 1149

0.2625N/mm 2

0.479 bd 1 0 0 0 x 2 4 0

0.79 ym

100 As bd

1/3 40C

0.79 0.479 1/3 400 V. 30 1.25 ^240_ 25

25

1/3

1/3

= 0.597

W c > D

Hence O. K.

Minimum areas of steel

Surface zones for walls

h = 300mm

h < 50Qmm

A - 17

•4

Ref Calculat ions O u t p u t

(1) peril for vertical steel

Minimum As/zone = 0.0035 x 150 x 10 3

= 525mm /m

= < 1149mm 2 /m

Hence O.K.

(21 Horizontal steel

Smax = Jct_ x 0

Fb 2p

co max = S max x R a T1

= f c t x 0 _ x R a T l

fb 2p

Hence,

ocrit = fc tx 0 x R a Tl x 100

fb x 2 co max

= (0.67) (12) x 0.5 x 0.000012 x 30 x 100

2 x (0.2)

= 0.36%

M i n m area of reinforcement/ Surface zone

= 0.0036 x 150 x 10 3

= 540mm 2 /m

Y12 @ 200 c/c for horizontal reinforcement O.K.

(As = 565 mm 2 /m)

A - 18

Ref Calculations Out put

BSS110 Slab tension reinforcement

Table 3.27 = 0.13 x 10 3 3 00/100 2 = 390 mm /m both ways each face

Bond length for Anchorage

min. bond length

Fig A-l 1 :Bond length of bar

Force in bar = Bond force between steel and concrete

Allowable bond stress (ult)

= fbu = B J feu

Jbu = 0.5 j 30

= 2.74N/mm 2

M a x m resistance of bar

= n x d x / xybu

Ult. Force in bar = 0.87/5/ * " d 2 / 4

n d / / b u = 0.87)5/ x 7 i d 2 / 4

/ = 7 t d x 0 . 8 7 x fy 4 7t fbu

= 0 .218dfy/2 .74

= 0.218 x 460 xd /2 .74

= 37d

For 16mm dia. Bars bond length

= 37 x 16 = 592mm

A - 19

Ref Calculations Out put

Design of tie bet" slab to resist the horizontal force

Critical condition for this is tank full with no soil outside

G.L

3 0 0 0 3 1 0 0

3 0 0

3 0 0

Fig A-12:Tie bar against horizontal force Horizontal force = Vi x 10 x 3 x 3

= 45kN/m

Vertical load = (3.1 x 0.3) x 25 + (2.3 x 0.3) x 25 + (3 x 2) x 10

= 100.5kN/m

Requised factor of safety against sliding = 2

Resistance requrised = 45 x 2

= 90kN/m

Coefficient of friction between concrete & soil

= 0.3

Resistance provided by wall & water on base slab

= 0.3 x 100.5

= 30.15kN/m

Hence tie force = 9 0 - 3 0 . 1 5

= 59.85kN/m

Permitted stress, /s = 130N/mm

A - 2 0

Ref Calculations Out pu t

Hence required area of steel = 59.85 x 10 3

130

= 460mm 2 /m

U s e T 1 2 @ 2 0 0 c/c

Bond length = 37d_ = 53 x 12 = 636mm 0.7

Footing reinforcement Case I

weight of water^ ^ weight of base

heel 2

toe

Fig A-13:Forces acting when tank is full

Pressures applied on base are marked in above figure

Moment at root of toe = Vi x 70 x 0.6 2 x 2/3 + Vi x 56 x 0.6 2 x 1/3 - 7.5 x 0.6 2 x 1/2 = 10.41 kNm/m

Moment at root of heel = - (30 + 7.5) (2 2 ) (1/2) + y2 x 49 x 2 2 x 1/3 + Vi x2 x 2 2 x 2/3 = -39.6 kNm/m

Moment at Base (ULS) = 1.4(10.41+39.6) = 70 kNm/m

A - 2 1

Ref Calculat ions O u t put

Case 2

weight of base v •

weight of soil weight of surcharge weight of base

Fig A-14:Forces acting when tank is empty

Pressures applied on base are marked in above figure

Moment at root of toe

= V2 x 32 x 0.6 2 x 2/3 + «/2 x 30 x 0.6 2 x 1/3 - (5+55.8+7.5 x 0.6 2 x 1/2

= -6.9 kNm/m

Moment at root of heel

= - ( 7.5) (2 2 ) (1/2) + l/ 2 x 28 x 2 2 x 1/3 + >/> x20 x 2 2 x 2/3

= 30.3 kNm/m

Moment at Base (ULS)

= 1.4(6.9+30.3)

= 52 kNm/m

A - 2 2

Ref Calculat ions O u t pu t

Case 3

weight of wate weight of base

heel 18

weight of soil weight of surcharge weight of base

Fig A-15:Forces acting due to water and

Soil outside

Moment at the root of toe

= y2 x 74 x 0.6 2 x 2/3 + V2 x 64 x 0.6 2 x 1/3 - 0 .5 2 x 7 2 x

(5 + 55.8 + 7.5)

= 0.5 kNm/m

Moment at the root of heel

= y2 x 58 x 2 2 x 1/3 + l/ 2 x 18 x 2 2 x 2/3 - (7.5 + 30) (2) (2)/2

= -12.3

Ultimate moment at base (Maximum)

= 1.4(0.5+12.3)

= 8.6 kNm/m

A - 2 3

Ref Calculat ions O u t p u t

K = M 70x 10

Feu brT 30 x 1 0 3 x 2 4 0 2

= 0.04 < 0.156

Z = d 0.5 +J 0 . 2 5 - K

0.9

B88110

Table 3.10

B88110

Table 3.11

= d 0.5 +/ 0.25 - 0 . 0 4

0.9

= 0.95d

= 0.95 x 240

= 228 mm

As required = Mu

0 . 8 7 x f y x Z

70 x 10"

0 . 8 7 x 4 6 0 x 2 2 8

= 767 mm /m

Provide Y 16 @ 200c/c

(As) provided = 1005mm2/m

A - 2 4

Ref Calculations Out put

B8S110

Table 3.12 Check for deflection of the wall

Span = ( 3 1 0 0 + 120)

effective depth

For a cantilever.

240

= 13.4

Span

depth = 7

Modification factor for tension steel

= 0.55 + ( 4 7 7 - / s )

120 0.9 + Mu

0.55 + ( 4 7 7 - 182)

120 0.9 + 7 0 x 10 b

1 0 0 0 x 2 4 0 '

= 1.629

Modification factor for compression reinforcement.

A s ' = As

Modification factor

= 1+100 As' /bd

(3+As'/bd)

= 1+100 x 1149/10 3 x 240

3 + 1149/ 10 3 x 240

= 1.159

Deflection

OK

A - 2 5

Ref Calculations Out put

Summary of reinforcement req d for walls

As

-forizontal As Vertical Conclusion

Face Inner Outer Inner Outer Inner Outer

Ultimate

Moment 1149

Crack

th 1149

Criteria

Ultimate 1149 1149

Shear (T16/175c/y

Direct

Tension

Deflection 1149 1149

B8 8007 565 565

Min" (T12@200c/c)

BS 8110 390 390 390 390

Min" (As detailed)

B8 8007 540 540

3 day crack (T12@200c/c)

(pi. refer to sketch in next page also)

Table A-l ;Summary of reinforcement for

Deep end wall

A - 2 6

Ref Calculations Out put

Summary of reinforcement for Deep end wall

+ 30(K

3100 Y16@175c / c e/f vertical Y12@125 c/c e/f horizontal

— 6 0 0 —

Fig A-16:Summary of reinforcement for

Deep end wall

Design of Shallow end wall

G.L

1000

30C

100

\ 4 - - 2 0 0 0 -

200

Fig A-17: Dimensions of shallow end wall

A - 2 7

Ref Calculations Out put

Service moment from water

= 1 0 x 0 . 9 3

6

= 1.2kNm

From Table A 2 .1 ,

Use h - 200mm

Cover to main bars = 52

Crack width = 0.2

Y12 @ 200 c/c will suffice as main bars.

Stability for tank full condition (Case I)

G . L

W1 P = 4 5 K N / m 2

W2-

W3

Fig A-18: Forces acting on shallow end wall

Weight of water on heel,

W, = (0.9 + 1) Y2 x 2 x 10 = 19kN/m

Weight of wall,

W 2 = (0.2) (1.3) (25) = 6.50kN/m

Weight of heel,

W 3 = (2) (0.3) (25) = 15kN/m

A - 2 8

Ref Calculat ions O u t pu t

Force due to water pressure,

P = 10 x (0.9V2 = 4.05kN/m 2

Taking moments about point A,

Overturning moment = 4.05 x 0.6

= 2.43 kNm/m

Restoring moment

= Wi x 1 . 2 + W 2 x 0.10 + W 3 x 1.2

= 1 9 x 1.2 + 6 . 5 x 0 . 1 + 1 5 x 1.2

- 41.45kNm/m

The FoS for the above is much higher.

Hence satisfactory

Case 2 Tank empty - Soil & surcharge

fig A-19:Forces on shallow end when pool is empty

Pressure due to soil,

P, = 7 2 K a y h 2

PI = V2x 1/3 x 18 x 1.32

= 5.07kN/m

A - 2 9

Ref Calculat ions O u t p u t

Submerged pressure,

P 4 = 5kN/m

Taking moments about B,

Overturning moment

= P , (1 .3x l/3) + P 4 ( 1 . 3 x ' / 2 )

= 5.07(1.3) (1 /3 )+ 5(1.3) (1/3)

= 5.72kNm/m

Restoring moment

= W 3 x 1 + W 2 x 2 . 1

= 15 x 1+6.5x2.1

= 28.65 kNm/m

Hence FoS against overturning is much higher.

Hence satisfactory.

Case 3

Tank full + Soil + Surcharge

As in case (2^

Overturning moment = 5.72kNm/m

Restoring moment is increased due to weight of water.

FoS is much higher.

Hence satisfactory.

A - 3 0

Ref Calculations Out put

Soil Dressure under the heel

Case 1 : Tank full with no soil

Total vertical load = WI + W2 + W3

= 40.5kN/m

Net restraining moment about center line of heel

= ( 4 1 . 4 5 - 2 . 4 3 ) - 4 0 . 5 x 1.1

= -5.53 kNm/m

Soil pressure = 40.5 ± 5.53 x 2.2

2.2 x 1 1/12 x 1 x 2.2 3 x2

= 18.41 ± 6.86

= 25.27 or 11.55kN/m 2

< 150 kN/m 2

Hence satisfactory

Similarly case II & III are satisfactory.

Design of cantilever wall for water pressure

feu = 30 N / m m 2

fy = 460 N / m m 2

Cover to horizontal reinforcement = 40 mm

Cover to vertical reinforcement = 52 mm

E concrete = 13 kN/mm 2

E steel = 200 kN/mm2

A - 3 1

Ref Calculations Out put

Effective height of wall

= 9 0 0 + (200-- 5 2 - 8 )

= 1040 mm

Effective depth

= 200 + 5 2 - 8

= 140 mm

Service moment from water = 1.2 kNm/m Ultimate moment from water,

Mu = 1.4 x 1 0 x 0 . 9 3 / 6

= 1.7 kNm/m

Ultimate shear from water,

Vu = 1 . 4x 1 0 x 0 . 9 2 x 1/2

= 5.67 kN/m

Design for max"1 crack width

Table For the service moment of 1.2 kNm/m Y12 @ 200 is satisfactory.

A 2 . 1 Crack width calculation is not necessary since Yl 2(5)200 for h = 200,

withstands a service moment of 16.4 kNm according to above table.

Design for Ultimate moment K = Mu

fcxx bd 2

1 7 x 10 6

30 x 1 0 3 x 140 2

= 0.003 < 0.156

Z = d 0.5 + 0 . 2 5 - K ^ " 0.9 - 1

= d 0.5 +| 0.25 -_JL - i 0.9 -

= 0.99 d

Take Z = 0.95 d

= 0.95 x 140

= 133 mm

A - 3 2

Ref Calculations Out put

As required Mu 0.87 xJyxZ

1.7 x 10" 0.87 x 460 x 133

= 3 1 . 9 m m 7 m

As provided = 565 mm2/2

(y 12 @ 200 c/c)

Hence OK

Design for ultimate shear

Vu = 5.67 kN/m

D 5670 = 0.0405N/mm i

lOOOx 140

0.79 100 A7 ym bd

i/: 400 feu

25

1/3

0.79

1.25

100 x 5 6 5

10 J x 1 4 0

1/3 400

140

30

25

1/3

= 0.2012 N / m m 2

x>c > v

Hence shear capacity is OK

A - 3 3

Ref Calcula t ions Out put

M i n i m u m areas of steel

(i) Pcrit for vertical steel 2 2

- 525 mm /m (as before) < 565 mm /m

Hence OK

Pcrit OK

(2) Horizontal steel

Min m required = 540 m m 2 / m (as before)

< 565 mm 2 /m

Hori. Steel

Y 1 2 @ 2 0 0

Y12 @ 200 c/c for horizontal reinforcement OK

Bond length for an chorage = 37d (as before)

For 12mm dia. Bars bond length

= 37 x 12

= 444mm

Bond

length

= 37d

= 444mm

A - 3 4

Ref Calculations Out put

Summary of design of shallow end wall

. Y12O200 c / c e / ( verticol

. Y120 200 c / c e / f horizontal

Fig A-20: Summary of reinforcement Of shallow end wall

Design of side wall

1 7 0 0

\- 2000 J ^ 6 0 0 7 | ' '

3 0 0

Fig A-21:Dimensions of side wall for design

Service moment from water

= l O x 1.73

= 8.2 kNm

From Table A 2.5

U s e h = 300mm

Cover to main bars = 52mm

Crack width = 0.2mm

Y12 @ 200 c/c will suffice as main bars

A - 3 5

Ref Calculations Out put

Stability for tank full condition Case (1)

W1 WZ

W3

Fig A-22:Forces acting on side wall when pool is full

= l O x l.T

W,

W 2

W 3

= 14.5 kN/m

= 2 x 1.7 x 10

= 0.3 x 1 .8x25

= 2 . 6 x 0 . 3 x 25

= 34kN/m

= 13.5kN/m

- 19.5kN/m

Taking moments about A,

Overturning moment = P x 0.9

= 1 4 . 5 x 0 . 9

= 13.05kNm/m

Restoring moment

= W, x 1.6 + W 2 x 0.45 + W 8 x 1.3

= 34 x 1.6+ 13.5 x 0.45 + 19.5 x 1.3

= 85.8 kNm/m

Factor of safety against overturning

= 85J* 13.05

= 6.6 Hence satisfactory

A - 3 6

Ref Calculations Out put

Case II : Tank empty & soil + surcharge

Take moments about B,

Restoring moments

Soil = 18 x 1 .8x0.3 [2.45] = 23.8

Surcharge = 5 x 0.5 x [2.45] = 6.1

Wall = 13.5 x 2.15 = 29.0

Base = 19.5 x 1.3 = 25.4

Total restoring moment = 84.3 kNm/m

Calculation of overturning moments

Pressure due to soil

= 1/3 x 18 x 1.8

= 10.8 kN/m 2

Surcharge pressure

= 1 / 3 x 5

= 1.7 kN/m 2

Overturning moment

= 1/2 x 10.8x1.8|L8_+03] +1.7 x l .SFJJJ + OJL

[3 J L? J = 12.42 kN/m 2

Resforing Moment = 84.3k Nm/m

FoS against overturning

= 84.3 = 6.8

12.42

Hence satisfactory

Case III can be shown satisfactory

A - 3 7

Ref Calculat ions O u t pu t

Soil p ressure unde r the base

Case I : Tank full with no soil

Wi = 34kN/m (as before)

W 2 = 13.5 kN/m ( -do- )

W 3 = 19.5 kN/m ( -do- )

Total vertical load, V

= w, + w2+w3

= 3 4 + 1 3 . 5 + 19.5

= 67 kN/m

Overturning moment = 13.05kNm/m

Restoring moment = 85.8kNm/m

Net restoring moment = 8 5 . 8 - 1 3 . 0 5

= 72.75 kNm/m

Soil pressure 67 + 72.75 x 2.6

2 . 6 x 1 1 / I 2 x l . 6 3 x 2

= 25.8 ± 6 4 . 6

= 90.4 o r - 3 8 . 8

Hence satisfactory

It can be shown that cases II & III are OK

A - 3 8

Ref Calculations Out put

Design of cantilever wall for water pressure

fig A-23:Design of side wall for water pressure

/ cu = 30H/mm 2

fy = 460N/mm 2

Cover to horizontal reinforcement = 40mm

Cover to Vertical reinforcement = 52mm

Ewn.

Esteel

- 13 kN/m ni

= 2 0 0 k N / m m 2

Effective height of wall

1700+ ( 3 0 0 - 5 2 - 8 )

1940mm

Effective depth of wall

= 3 0 6 - 5 2 - 8 )

= 240mm

A - 3 9

Ref Calculat ions Ou t pu t

Service moment from water

= 8.2kNm

Ult. Moment from water

Mu = 1.4 x 10 x 1.943/6

= 17 kN/m

Ult. Shear from water

Vu = 1.4 x 10 x 1 . 7 2 x ' / 2

= 20.23 kN/m

Design for Ult. M o m e n t

K = MM

feu bd 2

= 17 x 10 6

30 x 10 3 x 2 4 0 2

= 0.0098 < 0.156

Z = d 0.5 + / 0 . 2 5 - 0 . 0 0 9 8

I V 0.9 J = 0.99d

Hence Z = 0.95 = 0.95 x 240 = 228mm

As required Mu 0.87 xJyxZ

1 7 x 1 0 6 0.87 x 460 x 228

= 186 mm 2 /m

As provided = : 565 m m 2 / m

(Y 12 @ 200 c/c)

Hence OK

A - 4 0

Ref Calculations Out put

Design for Ult. Shear

Vu = 20.23kN/m

x> = 20230 0.08 N / m m 2

1 0 0 0 x 2 4 0

DC = 0.79 x

ym

lOOAs 400 v. feu 1/3

- b c U

= 0.471 N / m m '

l i e > v

Hence shear capacity OK

Min" 1 areas of steel

(i) Pcrit for vertical steel

= 525mm 2 /m (as before)

<565 mm /m

Hence OK

(ii) Horizontal steel

Minm required = 540mm /m (as before)

<565mm /m

Y12 @ 200 c/c for hori. Steel O K

Bond length for anchorage = 37d (as before)

For 12mm dia bars bond length

= 37 x 12

= 444mm

Vert. Steel

Y12@200

Pcrit OK

Hor. Steel

Y12(5),200

Bond

length

= 37d

= 444mm

A - 4 1

Ref Calculations Out put

Summary of design of side wall •f300f

Y12@200 c/c e/f vertical Y12@ 200 c/c e/f horizontal

1800

300

Fig A-24: Summary of reinforcement of side wall

Design of base (Reinforced concrete pool with deep end)

11111 ITtTfTrTtf^ 1 I n • • • •

13500 2700 4800

Fig A-25: Pressure applied on the base

The thickness of base is 300mm The widthof the base is 8500mm Moment is applied to base slab when the pool is empty.

p = 21 x 8 5 x 0 3 x 7 4 = 7.2 kN/m 2

21 x 8.5

ly = 21 = 2.5 > 2 Ix 8.5

A - 4 2

Ref Calculat ions O u t put

Design for ultimate moment

M

b d 2 / c u

91 x 10 b

1000 x 2 4 2 ' x 30

= 0.0518

No compression reinforcement is required.

Z = d 0 . 5 + 0 . 2 5 - K

0.9

= d C .5 + 0 . 2 5 - 0.037

0.9

= d 0.5 + 0.44

= 0.94 d

Hence Z = 0 . 9 4 x 2 4 2

= 227mm

As = M 91 x 10 6

O.ZlfyZ 0 . 8 7 x 4 6 0 x 2 2 7

= 1002 mm 2 /m

Provided Y 16 @ 175 c/c (As = 1148 mm 2 /m)

A - 4 3

Ref Calculations Out put

BS 8110

Table 3.27

Ultimate shear

Vs = 7 . 2 x 8 . 5 30.6 kN

Vu = 1 .4x30.6 = 42.84 kN

v = Vu

bd

0.79

= 42.84 x 10 3

1 0 0 0 x 2 4 2

= 0.177 N / m m 2

Urn

lOOAs

bd

1/3 400 30

25.

1/3

0.79 " lOOx 114? 1/3 "~400~~ "30

1.25 _1000x24_2 _242^ _25_

1/3

= 0.595 N / m m 2 > 0.177

Hence OK

Provide minimum in long span direction M i n m area of reinforcement required=0.13x1000x300

100

=390 m m 2 / m

v l0@200 (A s =393 m m 2 / m ) will be just sufficient

A - 4 4

Ref Calculat ions O u t p u t

End Reaction

End reaction=42.84 kN

This is taken by the ties alone placed between the

Slab and the heel of the cantilever wall (i.e y l 2

@200c/c)

Ultimate force by the tie bars=0.87x 460x x 12 2x5

4

=226 kN

Hence O.K.

Reinforcement to resist thermal and shrinkage cracking

Fig A-26:Surface Zones

A - 45

Ref Calculat ions Ou t put

H = 300mm

p c r i t = 0.35%

W max = S max R a (T, + T 2 )

S max =_fa x _ 0 _

fb 2 p

p ^ t x R a ( T , + T Z ) 0

Jb 2 W max

= 0 . 6 7 x 0 . 5 x 10-6 ( 3 0 + 1 O U 0

2 x 0 . 2

= (3.35 x 10" 5)x 16

= 0.000536 < 0.0035

Provide p crit As in top surface zone

= 0.0035 x 300 x 1000 = 525 m m 2 / m

2

Y12@175 is OK in short span direction

Hence provided Y 12 @ 175 in long span at top surface zone.

As = 646 mm Im

As req- for bottom surface zone

= 0.0035 x 100 x 1000

- 350 mm Im

Provided Y 10 @ 200 both ways for bottom surface zone.

A s =393 mm 2 /m

A - 4 6

4

Appendix B

Design calculations for proposed alternative with a deep end

Ref Calculat ions O u t pu t

Plan and section of the pool

O.gn

-l-2.7m-l 6.8m-

!.Jm

S E C T I O N

P L A N

Fig B - l : Plan and section of the pool with deep end

The above dimensions are all internal.

The structural arrangement of the walls are as shown below. All the walls are designed with random rubble sections

12.5m

Y

-•z p <«—1

Y

15.5n

t g.7rjl 6.8n

X •

0.15n 0.15n PLAN

Fig B-2:Plan of pool showing different wall sections

B - 2

Ref Calculat ions O u t p u t

Detail of wall X - X

150

450 r ^ H - 6oo

450

450 - 4

750

750

T ^ r j 750

> 9 0 0

1150

1400

150

R.C.C. wall

R.R. Masonory

zL R.C.C Base Screed

Fig B-3: Wall section X-X for deep end

Dimensions of detail X - X are in mm.

Detail of wall Y- Y

1 5 0

4 5 0

3 0 0

1 5 0

7 5

6 0 0

7 5 0 1 5 0

R.C.C. wall

- R.R. Masonary R.C.C Base Screed

Fig B-4: Wall section Y-Y for shallow end

B - 3

Ref Calculat ions Ou t put

Detail of wall Z - Z

This detail varies with the length

3875

B - 4

Ref Calculat ions Ou t put

Detail of wall P - P

1350 1350

1500 depth

Fig B-6: Wall section P-P for side wall With steep slope

B - 5

R e f Calculations Out put

Design of the random rubble gravity wall

The random rubble gravity wall is designed for the lateral pressure due to

water.

a). Design of deep end wall

(1) Forces on the pool wall when full

W6

t W1

W2 W7

p

W: 4

W5 W6

Fig B-7: Forces on wall when full

Take density of random rubble masonry as 22.5kN/m 3 which is conservative. The dimensions are selected so that no tension occurs in RRM.

B - 6

Ref Calculat ions O u t p u t

Wi = 0 . 6 x 2 . 9 5 x 1 x 2 2 . 5 kN/m = 39.8kN/m

W 2 = 0.15 x 2 .50x 1 x 2 2 . 5 kN/m = 8.4kN/m

W 3 = 0.15 x 2.05 x 1 x 22.5 kN/m = 6.9kN/m

W 4 = 0.25 x 1.6 x 1 x 2 2 . 5 kN/m = 9kN/m

W 5 = 0.25 x 0.85 x 1 x 22.5 kN/m = 4.8kN/m

W 6 = 0.6 x 0.15 x 1 x 24 kN/m = 2.2kN/m

W 7 = 0 . 1 5 x 3 . 1 x 1 x 24 kN/m = 11.2kN/m

W 8 = 1.55 x 0.2 x 1 x 24 kN/m = 7.4kN/m

W 9 = 1.55 x 0.075 x 1 x 2 3 . 5 kN/m = 2.7kN/m

Force due to water pressure

P = l - x 3 2 = 45 kN/m 2

Stability Analysis

For resistance to overturning, moments are taken about the point X.

Overturning moment about X = 45 x 1.275kNm/m

= 57.375 kNm/m Resforing moment about X

= 84.13 kNm/m

B - 7

Ref Calculat ions Ou t put

Factor of safety against overturning

= 84.13 57.375

= 1.46 > 1.5

Hence not satisfactory

The section is changed to satisfy the above stability considerations. But it

was revealed that the width of the suitable section was 2400mm wide. This

section would not gain the expected economic effectiveness. Hence the

design concept was revised for the deep end consideration.

The walls are designed as two way spanning slabs. Vertically walls are

panning between top walkway slab and bottom base slab. Horizontally they

span between counter forts placed at 3125mm centers as shown below.

Arrangement of counter forts

Fig B-8:Isometric view of the counter fort

B - 8

Ref Calcula t ions O u t p u t

Table 9.24 PCA

Design of the wall slab

Using PCA tables the moments and shear forces are calculated.

2

r

Panel moment positions Panel shear Pressure diagram

Fig B-9:Moment and shear coefficients

b/a=l,Coefficients are as below. Coefficient for Mhi

Moment M h 2

M h 3

Mh4

Mvi

M v 2

= 0

= 0

Coefficient for V n i = 0

shear

-35

+ 16

= 0

= +1

V h 2 = +26

V h 3 = +32

V V | = +24

V v 2 = +8

Moment

M h 3

Coefficient x y x a 3

1000

-35 x 9.81 x 3 3 -9.27 kNm/m

Mll4 + 1 6 x 9.81 x 1000 x 3 3 = 4.24 kNm/m

M v 2 = +11 x 9.81 x 1000 x 3 3 = 2.91 kNm/m

Shear Force 1000

= Coefficient x y x a 100

v n 2 = 2 6 x 9 . 8 1 x 1000 x 3 2 = 22.96kN/m 100

v h 3 = 3 2 x 9 . 8 1 x 1000 x 3 2 = 28.25kN/m

100

Vvl = 2 4 x 9 . 8 1 x 1000 x 3 2 = 21.19kN/m 100

B - 9

Ref Calculat ions O u t pu t

r Vv 2 = 8 x 9.81 x 1000 x 3 100

7.06 kN/m

Design the slab for ultimate moments

(a) Midspan horizontal Mult, hor, mid = 1 .4x4.24

= 5.94 kNm/m

M Bd2/cu

d = 1 5 0 - 4 0 - 6 = 104 mm

5 Q 4 x 1nfi lOOOx 1042 x 3 0

0.5 +^|0.25 - J C

= 0.977 d 0.9

< 0.95 d = 0.95 x 104 = 99mm

0.018 0.018 < 0.156

X

As

d - Z = 11mm

= 5 . 9 4 x 1 0 6 0.45

M O.SlfyZ 0 . 8 7 x 4 6 0 x 9 9

150 mm /m

Y10 @ 300 will be sufficient

(b) Midspan vertical Mult, Vert, mid = 1 .4x2.91

= 4.07 kNm/m

d = 1 5 0 - 4 0 - 1 0 - 6 = 94 mm

M bd2/cu

4.07 x 10° I 0 0 0 x 9 4 z x 3 0 = 0.015 < 0.156

Z = d 0.5 + 0 . 2 5 - K M 0.9

B - 10

Ref Calculat ions O u t p u t

= d 0 .5+/ 0 . 2 5 - 0.015 L ^ ' 0.9 J = d x 0.983 < 0.95 d

= 0.95 x 94 = 89mm

X = d - Z = 1 1 0.45

As = M = 4.07 x 10 6

0.87/yZ 0.87 x 460 x 89 = 1 1 4 m m 2 / m

Y 10 @ 300 will be sufficient (As = 261 mm 2 /m)

(c) Edge horizontal moment Mult, hor, edge = 1 .4x9 .27 kNm/m

= 12.98 kNm/m

M = 1 ? Q R Y 1 0 6

bd2/cu 1 0 0 0 x 9 4 ^ x 3 0 = 0.049 < 0.156

Z = d 0.5 + |0 .25 - K

L X> 0.9 J = d [0.942]

= 9 4 x 0 . 9 4 2

= 88

x = d - Z = 13mm 0.45

As M 12.98 x 10 6

0.87/yZ 0.87 x 460 x88 = 368.6mm Im

Y 10 @ 200 will be sufficient (As = 392mm 2 /m)

B - 11

Ref Calcula t ions Ou t put

Design for shear

Maximum shear force

Ultimate shear

V u

= 28.25 kN/m

= 1 .4x28.25

= 39.55 kN/m

1) = 39.55 x 10 J = 0.26 N / m m 2

-- ~" = 0.79

ym 100 As L bd _

1/3 400 _d J

%

_ 2 5 _

1/3

= 0.79 x 1.25

1 0 0 x 3 1 4 1 0 0 x 1 5 0

1/3 400 105

V4 30 25

1/3

= 0.56 N / m m 2

Hence ultimate shear at the critical location is O.K.

Other plans need cost to check for shear.

Design for crack width

a, =

Ms =

P =

15

9.27

As bd

As = 392.5 m m 7 m

kNm/m d = 1 5 0 - 4 0 - 5

= 105

392.5 3.738 x 10" 1 0 0 0 x 1 0 5

X = - at p + v la/ p (a/ p + 2 d

-3

X = z =

d

-15 x 3.738 x 10

0.2835

0.2835 x 150 = 42.5mm

1 - 0 . 2 8 3 5 = 0.9055

15 x 3.738 x 10"3 (15 x 3.738 x 10"3 + 2)

Z = 9 5 mm

B - 12

Ref Calculat ions O u t p u t

Stress in steel = M = 9 . 2 7 x l 0 6 = 248.6 < 0.8/;

8s = S_s = 248.6 = 0.001243

E s 200 x 10 3

8 ' = 8s h " - X = 0.001243 1 5 0 - 4 2 . 5

d - - X 1 0 5 - 4 2 . 5 = 0.00214

Stiffening effect, of concrete £ 7 = b t ( h - x ) Ca' -x)

3 Es As (d --x) = 1000 M S O - 47.W = 0 000785

3x 200 x (392.5) ( 1 0 5 - 4 7 . 5 )

g m = £ | - £2

= 0.00214 - 0.000785

= 1.355 X 1 0 " 3

acr = J 100 2 + 4 5 2 - 5

= 105mm

co = 3 acr £ m

1 + 2 acr - C min h - x

—' = 3 x 105 x 1.355 x 10"J

1 + 2 1 0 5 - 4 0

J 5 0 - 4 2 -

= 0.193 < 0.2 mm

Hence crack width OK

B - 13

Ref Calculat ions O u t pu t

RJf to control thermal and shrinkage cracking

p crit = £ c t = 1.3 = 0.00283 fy 460

S max = j e t x 0 = 12 x 0.67 yb 2p 2p

W max - RS_max a (Ti + T 2 ) = R / c t 0 a (T, + T 2 )

2p

p = 0.67 x 0.5 x 12 x 1(T(30 + 10) x 12 2 x 0 . 2

= 4.8 x 1 0 " 4 < p e r i l

Provide p crit in each surface zone.

= 0.283 x 150 x 1000 100 x 2

= 212 mm 2 /m

Design of the Counter forts

Counter forts have the dimensions as follows and those are spaced at 3.125m

centers at the deep end.

1500 1200

Fig B-10 : Dimensions of counter fort

B - 14

Ref Calculat ions Ou t put

There are counter forts at the sides also. Those have the same dimensions

Are spaced at 3.4m centers. The arrangement of the counter forts are as

follows.

Fig B-l 1 : Arrangement of counter forts

The effective area for loading of one counter fort is as shown below. The

loading coefficients for the slab are taken from PCA tables.

. HinjTnH(nn tnp UJllk Way Slab)

3 Conitnuous (over counter forts) C o n t i n u o u s (over counter forts)

1" 3i(H) " 1

Hingcd(on bottom slab)

Fig B-l 2 : Slab of counter fort

The height of the wall is equally divided into ten horizontal segments, and

the force coefficient on each of the segment and therefore the force

coefficient on the counter fort are as shown below. The values given within

brackets are the distances to the point of action of each of the force from the

point X on the base.

Prior to start analysis, the adequacy of the width of the base to transfer the

loads excreted on the counter fort due to water pressure is checked.

B - 15

Ref Calculat ions O u t put

Case for water pressure from inside with no soil backfill outside.

150 6 0 0

(3.1)0.0421 — (2.8)0.1016— (2.5)0.1574— (2.2)0.2118— (1.9)0.2628 — (1.6)0jQ28-~ (1.3)03231—WlZ (1.0)0.3250— (0.7)0.2968 — (0.4)0.1379—

1500

W6

Fig B-13 : Forces acting on the counter fort

W, = 1.5 x 1 x 3 x 10 = 45 kN/m

W 2 = 0.15 x 3.1 x 25 x 10 = 11.63 kN/m

W 3 = 0.60 x 1 x 0.15 x 2 5 = 2.25 kN/m

W 4 = 0 . 6 0 x 0 . 1 5 x 2 . 9 5 x 2 5 = 6.64 kN/m

W 5 = 0 6 0 x 0 . 1 5 x 2 . 9 5 x 2 5 = 3.32 kN/m 2

W6 = 2.85 x 1 x 0.25 x 25 = 17.81 kN/m

B - 16

>

4

Ref Calculat ions Ou t put

Take moments about point X on the base. Moment due to horizontal forces,

M x h = 3.52 x 3.275

+ (0.0421 x 3.1 + 0.1016 x 2.8 + 0.1574 x 2.5

+ 0.2118 x 2.2 + 0.2628 x 1.9 + 0.3028 x 1.6

+ 0.3231 x 1.3 + 0.3250 x 1.0 + 0.2968 x 0.7

+ 0.1379 x 0.4) x 10 x 3 2 x 0.3

+ 3 2 . 7 8 x 0 . 1 2 5

= 11.528 + 81.089 + 4.098

96.715 kNm.

Moment about point X due to vertical force on base,

M x v = \ - W, x 0.75 + W 2 x 0.15 + W 3 x 0.375 + W 4 x 0.225 + W 5 x 0.625

= -45 x 0.75 + 11.63 x 0.15 + 2.25 x 0.375

+ 6 .64x 0.225 + 3 . 3 2 x 0 . 6 2 5

= -27.59 kNm

Total vertical load on base,

V = Wi + w2 + w3 + w4 + w5 + w6

= 45 + 11.63 + 2.25 + 6.64 + 3.32 17.81

= 86.65 kN

B - 17

>-

Ref Calculat ions O u t p u t

Assume the Breadth required transferring the moment & vertical load to the

soil safely is " B " .

Soil pressure under the base

P = F ± My A I

= (86.65) x B ± (96.715 - 27.59B) (2.85) x B 1/6 B x (2.85) 2

P = 3 0 . 4 + (71.44 - 20.3) B

P = 10.02 + 71.44 eg. (1) B

When B varies from 0.51 to infinity P varies from 150 kN/m 2 to 10.02

P = 50.78 - 71.44 eg. (2) B

when B varies from 1.41 to infinity P varies from 0 to 50.78 kN/m 2

Flence B > 1.41m. satisfies no tension & maximum allowable soil pressure

conditions.

Distance between counter forts is 3.4m.

Hence the width of the base for transferring load and moment is satisfied.

B - 18

Ref Calculat ions Ou t pu t

Consider a section of the base with 1.5 long into the water . as shown below,

to a width of lm.

Fig B-14 : Loads for Stability Calculations

W, = 1.5 x 1 x 3 x 10 = 45 kN

W 2 = 0.15 x 1 x 3.1 x 2 5 = 11.63 kN

W 3 = 0.60 x 1 x 0.15 x 25 = 2.25 kN

W 4 = 0.60 x 0.15 x 2.95 x 25 = 6.64 kN

W 5 = 0 . 6 0 x 0 . 1 5 x 2 . 9 5 x 25 = 3.32 kN

W 6 = 2.85 x 1 x 0.25 x 25 = 17.81 kN

P = 1 0 x 3 x 3 x 2 0 . 5 = 45.00 kN

B - 19

Ref Calculations Out put

Stability Calculations

Case 1 : Tank full with no soil backfill

Take moments about A,

Overturning moment = P x 1.2

= 45 x 1.2

= 54 kNm/m

Restoring moment

= W1 x 2 . 1 + W 2 x 1.275+ W 3 x 0.9

W4 x 0.9 + W5 x 0.4 + W6 x 1.425

= 45 x 2.1 + 11.63 x 1.275 + 2.25 x 0 . 9 + 6 . 6 4 x 0 . 9 + 3 . 3 2 x 0 . 4

+ 17.81 x 1.425

= 144.04 kNm/m

Factor of safety against overturning

= 144.4 54

= 2.67 > 2

Hence satisfactory.

B - 2 0

Ref Calcula t ions Out pu t

Case 2 : Tank empty , soil & surcharge outside

K N / m :

Fig B- l5 : Forces due to soil, surcharge & ground water

Pressure due to dry soil above water table, p i = 1 x 18 x 2 3

p , = 12 kN/m 2

Pressure due to submerged soil, p 2 = 1 ( 1 8 - 1 0 ) (1.1)

3

p 2 = 2.9 kN/m 2

Pressure due to water, p 3 = 10 x 1.1 p 3 = 11 kN/m 2

B - 2 1

1 Ref Calculat ions Ou t put

Surcharge pressure, p 4 = 5 x 1/3

= 1.7 kN/m 2

Take moments about B,

= Moment due to soil + Moment due to surcharge + Moment due to water

= i x P i x 2 x ( 2 x J_+ 1.3) + J _ x P i x 2 x 1.1 ( 1 . 1 + 0 . 2 ) 2 3 2 2

+ l x P 2 x 1.1 CLi + 0.2) + P 4 x ( 3 . 1 + 0 . 2 ) 2 3 2

+1 x P 3 x ( U . + 0.2) 2 3

= 23.6 + 9.9 + 0.9 + 3.0 + 3.1

= 40.5 kNm/m

Res tor ing moments

Soil = 18 x 0.6 x 1.85 x (1.65 + 0.3)

+ 18 x 0.6 x 2.00 x (1.65 + 0.9)

+ ( 1 8 - 10) x 1.2 x 1.1(1.65 + 0.6)

= 38.96 + 55.08 + 23.76 = 117.8 kNm/m

B - 2 2

Ref Calculat ions O u t pu t

Surcharge = 5 x 1.2 x (1 .65+ 0.6)

= 13.5

Water = 1.1 x 1.2 x 10 x (1 .65+ 0.6)

- 29.7 kNm/m

W3 = 0.6 x 0.15 x 25 x (1.65 + 0.3)

= 4.39

W2 = 0 . 1 5 x 3 . 1 x 25 x (1 .5+ 0.15) 2

= 18.31

W6 = 2 . 8 5 x 0 . 2 5 x 2 5 x 2 . 8 5 x 0 . 5

= 25.38

W4 = 0 .6x 0 . 1 5 x 2 . 9 5 x 2 5 x 1.95

= 12.94

W5 = 0 6 x 0 . 1 5 x 2 . 9 5 x 2 5 x 2 . 4 5 2

= 8.13

Total restoring moment

= 30.15

Factor of safety against overturning

= 230.15 40.5

= 5.68

Hence satisfactory

B - 2 3

Ref Calculations O u t put

Soil Pressure under the base

Case 1 : Pool is full, no soil outside

Fig B-16 : Forces on wall when pool is full

Consider l m wide section,

Load Distance from A

w2 = 0.15 x 3.1 x 25 = 11.625 kN 1.275

W6 = 2 . 8 5 x 0 . 2 5 x 2 5 = 17.81 kN 1.27

w, = 1.5 x 3.0 x 10 = 4 5 k N 1.27

w3 = 0.6 x 0.15 x 25 = 2.250 kN 0.9

w4 = 0.6 x 0.15 x 2.95 x 25 = 6.6375 kN 0.9

w5 = 6.6375/2 =3 .31875kN 0.4

P = 1 . 5 x 3 x 1 0 = 45kN 1.2 (Vertically)

B - 2 4

Ref Calculat ions Ou t pu t

1 w = w , + w2 + w3 + w4 + w5 + w6

= 86.64

Moments about A,

Overturning moments = P x 1.2 = 54kNm.

Restoring moment = W l x 2.1 x W2 x 1.275 + W3 x 0.9 + W4 x 0.9 + W5 x 0.9 + W6 x 1.425 = 144.03

Net restoring movement = 144.03 - 54 = 90.03 kNm/m

Moment about centre line = 90.03 - 86.64 x 1.425 = "33.44

= 86.64 ± 33.44 xj" 2^85 j

2.85 l x l x ( 2 . 8 5 ) 3

12

= 30.40 ± 25.07

= 56.10 or 5.33

B - 2 5

Ref Calculations Out put

Case 2 : Pool is empty, soil & surcharge outside

K N / m :

Fig B-17: Forces acting on wall when pool is empty

pi = I x 18 x 2 12 kN/m 2

3 p 2 = I x ( 1 8 - 10) (1.1) = 2.9 kN/m 2

3 p 3 = 10 x 1.1 x 2 11 kN/m 2

P4 = 5 x 1 = 1.7 kN/m 2

3

Overturning moment = 1 x 2 x pi ' 2 x 1 + 1 . 1 + 0 . 2 1

2 3 = + pi X 1.1 X > L i + 0.2-

2

= + p2 L i x 1.1 + 0 . 2 " 2 . 3

= + p 3 L i X ' 1 .1 + 0 . 2 " 2 I 3 J

40.75 kN/m'

= + p 4 x 3 J . + 0.2 I 2

B - 2 6

Ref Calculat ions Ou t put

Loads Distance from B

W 2 = 11.63kN 1.5775

W 3 = 2.25kN 1.95

W 4 = 6.64kN 1.95

W 5 = 3.32kN 2.45

W 6 = 17.81kN 1.425

Surcharge = 5 x 1.2 = 6.0 kN 2.25

Soil 1 = 1 8 x 0 . 6 x 1.85 = 19.98 kN 1.95

Soil 2 = 1 8 x 0 . 6 x 2 . 0 0 = 21.6 kN 2.55

Soil 3 (wet) = ( 1 8 - 10) x 1.2 x 1.1 = 10.56 kN 2.25

Water = 1.1 x 1.2 x 10 = 13.2 2.25

B - 2 7

> Ref Calculations Out put

Total vertical load = 112.99 kN/m

Balance restoring moment about B, = 2 3 0 . 1 7 - 4 0 . 7 5 = 189.42

M c = 1 8 9 . 4 2 - 112.99 = 28.40

Soil pressure = 112.99 ± 28.4 x 2.85/2 2.85 I x (2.85) 3

12

= 39.65 ± 20.98

= 60.63 or 18.67

Water Pressure from inside, No soil outside

5.33kN/;q.m 31.98kN/sq.m 34.65kN/sq.m 56.10kN/sq.m

Fig B-18 : Soil pressure under base

B - 2 8

>

Ref Calculat ions O u t p u t

Moment at the root of the toe = 1 x 5 6 . 1 x l . 2 2 x 2 + 1 x 34.65 x 1.22 x 1

2 3 2 3

-2.25 x 0.3 -6 .64 x x0.3 - 3.32x 0.8 - 1.2x 0.25 x 25 x 0.6

= 25.425 k N m / m .

Moment at the root of the heel

= 1 x 31.98 x l . 5 2 x l + 1 x 5 . 3 3 x l . 5 2 x 2

2 3 2 3

- 1 . 5 x 3 x l O x 1.5 - 1.5 x 0.25 x 25 x 1.5

2 2

= - 24.79 kNm / m.

Moment at Base (ULS)

=1.4(25.425 + 24.79)

Mu = 70.3 kNm/m.

D=250-40-8

=202 mm

K= M = 70.3 x 10 6 =0.069 < 0.156

bd 2 f c u 25 x 1000 x 202 2

Z = d 0 . 5 + / 0.25 - K v . V-i

B - 2 9

Ref Calculations Out put

202

= 185 mm.

0.5 + / 0.25 - 0.069

V 0.9

A s required = M u

0 . 8 7 x f y x Z

= 70.3 x 10 e

0.87 x 460 x 185

949 m m 2 / m.

Provide y 16 @ 200 c/c ( A s provided = 1005 m m 2 )

No water inside,soil and surcharge outside

l8.67kN/sq.m 40.76kN/sq.n 42.965kN/sq.m 60.63kN/sq.m

Fig B-19 : Soil pressure under base, no water inside

B - 3 0

> Ref Calculat ions O u t put

Moment at the root of the toe = 1 x 60.63 x 1.22 x 2 + 1 x 42.97 x 1.22 x 1

2 3 2 3

-2.25 x 0.3 -6 .64 x x0.3 - 3.32x 0 . 4 - 1.2x 0.25 x 2 5 x 0 . 6

- 6 x 0 . 6 - 1 9 . 9 8 x 0 . 3 - 21.6 x 0.9 - 10.56 x 0.6 - 13.2 x 0.6

= -6.04 kNm / m.

Moment at the root of the heel

= 1 x 18.67 x 1.52 x 2 + 1 x40 .76x 1.52 x 1

2 3 2 3

- 1.5 x 0 . 2 5 x 25 x 0.75

= - 22.26 kNm / m.

Moment at Base (ULS)

= 1.4(22.26 + 6.04)

Mu = 3 9 . 6 2 kNm/m.

Reinforcement in previous case will suffice.

B - 31

Ref Calculations Out put

Design of the counter fort

Counter fort is designed as a varying depth cantilever Tee beam. At top and bottom counter fort is supported on top walkway slab and bottom slab respectively. The following figure shoes the segmental forces exerted on the counter fort.

150 600

l.!4kN 2.74kN — 4.25kN — 5.72kN — 7.10kN — 8.18kN, — 8.72kN — 8.78kN — 8.01kN — 3.72kN —

1500

Fig B-20 : Forces on counter fort

Bending moment diagram and the shear force diagram for these loads are as shown below.

1200

BMD SFD

Fig B-21: Bending Moment Diagram & Shear force diagram

B - 3 2

Ref Calculat ions Ou t pu t

M= 118 kNm

D= 1200-40-8 = 1152mm.

K= M = 118 x 10 6 =0.024 < 0.156

bd 2 f c u 2 5 x l 5 0 x l l 5 2 2

Z = d f 0 . 5 + / 0 . 2 5 - K 1

L V . . . J

= 1152 0.5 + /0.25 - 0.024

[J °"9 J

= 1094 mm.

A s required = M u

0.87 x fy x Z

= 118 x 10 6

0.87 x 460 x 1094

= 269 mm / m.

Provide 2 y 12 at the edge face & 2y l0 @ 175 mm c/c vertically along the base.

B - 3 3

Ref Calculat ions O u t pu t

150 .600

2 Y 1 2 — J

Y 1 0 @ 175 e/

2Y12

2Y10(ffi 175 e/f

Fig B-22 : Reinforcement for counter fort

The same calculation is carried out for the case of no water inside, but soil and surcharge from outside. Again 2y l2 is sufficient as main tensile reinforcement along the edge sloping face. Y10 & 175mm c/c is sufficient as links in each face vertically and horizontally to join the counter fort to the base and the wall as links to avoid tearing.

B - 34

Ref Calculat ions O u t put

Design of shallow end wall

/ 6 0 0 // 1 5 0

4 5 0

4 0 0

1 5 0

W 3 I T

W1

W 2

W 3

W 4 & W 5

P

Fig B-23: Forces on shallow end wall

The self weights are calculated as below.

w, = 0.60 x 0.75 x 1 x 2 3 . 5 = 10.58 kN/m

w2 = 0.15 x 0.30 x 1 x 2 3 . 5 = 1.06 kN/m

w3 = 0 . 6 0 x 0 . 1 5 x 1 x 2 4 . 0 = 2.16 kN/m

w4 = 0.90 x 0.15 x 1 x 2 4 . 0 = 3.24 kN/m

w5= 0.90 x 0.075 x 1 x23 .5 = 1.59 kN/m

w6 = 0.15 x 1.125 x 1 x 2 4 . 0 = 4.05 kN/m p = . 9 x 1 0 3 x 9 . 8 1 x 10" 3 x0 .5 x 0 . 9 = 3.97 kN/m

B - 3 5

Ref Calculat ions O u t pu t

Stability Analysis

Overturning moment about X ,

= 3 . 9 7 x 0 . 5 2 5

- 2.08 kNm/m

Restoring moment about X ,

= W 2 x 0.075 + (W, + W 3 + W 4 + W 5 ) 0.45

+ W 6 x 0.825

= 1 .06x0.075

+ (10.58 + 2.16 + 3 .24+ 1.59) x 0.45

+ 4.05 x 0 . 8 2 5

= 11.33 kNm/m

Factor of safety against overturning = 11.33 = 5.4 » 2

2.08

Hence satisfactory

Check for sliding

Frictional force = u x Gk

= 0.45 x (Wi + W 2 + + W 6 )

= 0.45 x (10 .58+ 1.06 + 2.16

+ 3 .24+ 1.59 + 4.05)

= 0.45 x 22.68

= 10.21 kN/m

Horizontal force = yf Hk

= 1 .6x3 .97

= 6.35 kN/m

Frictional force > Horizontal sliding force. Hence Satisfactory.

B - 3 6

Ref Calculat ions O u t pu t

Bearing pressure analysis

Total vertical load applied on soil

= W, + W 2 + + W 6

= 10 .58+ 1.06 + 2.16 + 3 .24+ 1.59 + 4.05

= 22.68 kN/m

Net overturning moment about center line of base ,

^ C ^ = W 2 x 0.375 + P x 0.525 - W 6 x 0.375

= 1.06 x 0.375 + 3.97 x 0.525 - 4.05 x 0.375

= 0.97 kNm/m

Soil pressure under base

= 22.68 + 0.97 0.9 1/6 x 0 . 9 2

= 25.2 + 7.19

= 32.39 or 18.01 kN/m 2

Hence satisfactory.

B - 3 7

Ref Calculat ions O u t pu t

Design of wall Z - Z

Wall section at 3.875 m from shallow end

4 5 0

5 5 0

1 5 0

/ 600 XX

W 2

1 5 0

I

W 3 I T

W1

W 3

W 4 & W 5

Fig B-24:Forces on side wall

Self weight & force due to water are as below

w, = 0.6 x 0.9 x 1 x 2 3 . 5 = 12.69 kN/m

w2 = 0.15 x 0.45 x 1 x 2 3 . 5 = 1.59 kN/m

w3 = 0.60 x 0.15 x 1 x 2 4 . 0 = 2.16 kN/m

w4 = 0.90 x 0.15 x 1 x 2 4 . 0 = 3.24 kN/m

w5 = 0 . 9 0 x 0 . 0 7 5 x 1 x 2 3 . 5 = 1.59 kN/m

w6 = 0.15 x 1.05 x 1 x 2 4 . 0 = 3.78 kN/m

p = 1 .05 x 1 0 3 x 9 . 8 1 x 0.5 x 1.05 x 10"3= 5.41 kN/m

B - 3 8

Ref Calculat ions Ou t put

Stability Analysis

Overturning moment about X ,

= 5.41 x 0.575

= 3.11 kNm/m

Restoring moment about X ,

= W 2 x 0.075 + (W, + W 3 + W 4 + W 5 ) x 0.45

+ W 6 x 0.825

= 1 .59x0.075

+ ( 12.69 + 2.16 + 3.24 + 1.59 ) x 0.45

+ 3 .78x 0.825

= 12.09 kNm/m

Factor of safety against overturning

= 12.09 = 3.9 > 2 3.11

Hence satisfactory.

Check for sliding

Frictional force = u Gk

= 0.45 x ( W , + W 2 + + W 6 )

= 0.45 x (12 .69+ 1.59 + 2.16

+ 3 . 2 4 + 1.59 + 3.78)

= 0.45 x 25.05

= 11.27 kN/m

Horizontal force = yf Hk

= 1.6 x 5.41

= 8.66 kN/m

Frictional force > Horizontal sliding force

Hence satisfactory.

B - 3 9

T

Ref Calcula t ions Ou t put

Bearing pressure analysis

Total vertical load applied on soil

= W, + W 2 + + W 6

= 12.69+ 1.59 + 2.16 + 3 .24+ 1.59 + 3.78

- 25.05 kN/m

Net overturning moment about center line of base ,

/^T\ = W 2 x 0.375 + P x 0 . 5 7 5 - W 6 x 0.375

= 1 .59x0.375 + 5.41 x0 .575

- 3.78 x 0.375

- 2.29 kNm/m

Soil pressure under base

= 25.05 + 2.29

0.9 1/6 x 0.9 2

= 27.83 ± 16.96

= 44.79 or 10.87 kN/m 2

Hence satisfactory

B - 4 0 A.

Ref Calculat ions O u t pu t

Design of wall Z - Z

6 0 0

-fit-1 5 0

4 5 0

4 5 0

4 5 0

1 5 0 W 2

I

T" W 4

I T W1

W 3 W 6 & W 7

Fig B-25;Forces on side wall deepest end

Self weights and forces due to water are as follows.

P = 1.5 x 1 0 3 x 9.81 x 0.5 x 1.5 x 10"3

= 11.04 kN/m

Wi = 0.6 x 1.35 x 1 x 2 3 . 5 = 19.04 kN/m

w2 = 0.15 x 0.9 x 1 x 2 3 . 5 = 3.17 kN/m

w3 = 0.15 x 0.45 x 1 x 2 3 . 5 = 1.59 kN/m

w4 = 0 . 6 x 0 . 1 5 x 1 x 2 4 . 0 = 2.16 kN/m

w5 = 0.15 x 1.5 x 1 x 2 4 . 0 = 5.40 kN/m

w6 = 1.05 x 0.15 x 1 x 2 4 . 0 = 3.78 kN/m

w7 = 1.05 x 0.075 x 1 x 2 3 . 5 = 1.85 kN/m

B - 4 1

Ref Calcula t ions Ou t put

Stability Analysis

Overturning moment about X ,

= 11 .0x0 .725

= 8.00 kNm/m

Restoring moment about X ,

= Wi x 0.6 + W 2 x 0.225 + W 3 0.075

+ W 4 x 0.6 + W 5 x 0.975 + W 6 x 0.525

+ W 7 x 0.525

= 21.79 kNm/m

Factor of safety against overturning

= 21.79 8.00

= 2.72 > 2 Hence satisfactory.

Check for sliding Frictional force = p. Gk

= 0.45 x (WI + W2 + + W7)

= 0.45 x (19 .04+ 3.17

+ 1.59 + 2.16 + 5.4 + 3.78

+ 1.85)

= 0.45 x 36.99

= 16.65 kN/m Horizontal force = yf Hk

= 1.6 x 11.04

= 17.66 kN/m Horizontal force exceeds frictional force at the deepest length.

This will be balanced by other areas because of the small difference. Hence no additional precaution is needed.

B - 4 2

Ref Calculat ions O u t pu t

Bearing pressure analysis

Total vertical load applied on soil

= W, + W 2 + + W 7

= 19.04 + 3 .17+ 1.59 + 2.16 + 5.44 + 3 .78+ 1.85

= 36.99 kN/m

Net overturning moment about center line of base

C = W2 x 0.3 + W3 x 0.45 + P x 0.725

(WI + W4) x 0.075 - W5 x 0.45

= 3 . 1 7 x 0 . 3 + 1 .59x0.45 + 11 .04x0 .725

(19.04 + 2.16) x 0.075 - 0.45 x 5.4

= 5.65 kNm/m

Soil pressure under base

= 36.99 + 5.65 1 .05x1 l / 6 x l . 0 5 2

= 35.23 + 30.75 = 65.98 or 4.48 kN/m 2

Hence satisfactory

Design of wall P - P

Change wall section to X - X which is satisfactory in all checking.

B - 4 3

Ref Calculat ions O u t put

Design of base (Proposed pool with deep end is designed here since the design of base with no deep end was discussed in detail in chapter 3)

0.9r£"t

-15.5m- J 1—6.8m-5.6m GWT 2.ym

2.7m SECTION

12.5r BASE 3 (thickness-150mm)

(thickne; BASE 2

s-2S0inm)

BASE 1 (thickness 250mm)

-25.0m-PLAN

Fig B-26:Base slab arrangements

Base 3 is above the ground water table. Hence design of this slab require reinforcement for prevention of thermal cracks. This design was covered in detail in Chapter.(refer to 3.3.9)

Design of base 1 was covered under the design of the counter fort. But the base required of the counter fort was only 1.5m into the water. Up to this point base thickness is 250mm. Then the base thickness is changed to 150mm.

With 25mm finishes and 75mm screed this slab is weighing 6.25kN/m 2 . The upward water pressure when the pool is empty is 12.5 kN/m . The net pressure exerted on the slab is 6.25kN/m 2 .

Y10 @ 150mm c/c both ways at top will be sufficient to withstand the bending moments and shear forces exerted on the slab. This reinforcement will be sufficient in dealing with thermal and shrinkage cracking.

B - 4 4

Ref Calculat ions O u t pu t

Check for Floatation (consider only the deep end)

Weight of 150 mm walls =(6.8x2+2.7x2+12.5)x0.15 x 2.95x25=348.5kN

Weight of top slabs =9.5x2x0.75x0.15x25 + (12.5+2x0.75)x0.75x0.15x25

=92.8kN

Weight of counterforts

=Hx(0.6+1.2)x0.5x2.95x0.15x25+2x(0.6+.875)x0.5xl .35x.l5x25=117.0kN

Weight of base slab=(6.8+l.35+2.7)x(12.5+l.35x2) x 0.2x25 =824.6kN

Weight of soil

=2.975x1.2x2.95x4x18+3.25x1.2x2.95x4x18+2.55x(0.875+1.2)x0.5x(l.35+2

.95)x.5xl8

=1689kN

Total weight =348.5+92.8+117+824.6+1689=3071.9kN

Fig B-27:Calculation of upthrust

W l = 12.8x6.95xl .35xl0=1200.96kN

W2-12.8x2.3x0.5xl0=198.72kN

Upthrust =1200.96+198.72=1399.68kN

Factor of safety against floatation=3071.9/1399.68=2.2>1.1 Hence O.K

B - 4 5

Appendix C

Design drawings of conventional swimming pool without deep end

Figure C-l : Plan & section of the pool with no deep end

c O n

J / / <> / •> •> J > > > ) T

-16.0m- -9.0m-

Section

• / •

/ /

/ /

/ /

/ /

' /

/ /

/ /

/ /

/ /

/ /

/ ' / /

• /

• /

/ /

/ /

• /

/ /

/ /

/ /

/ /

/ /

/ /

/ /

/ /

/ /

/ •

/

25.0m

Plan

F i g u r e C - 2 : S t r u c t u r a l A r r a n g e m e n t

Joint right round.

0.2m thick v/af

/

1 m high wall

0.3m thick wa l l 0.3m toe

at shallow end

2 m heel r ight

0.3m th ick w a l l

0.3m th ick wa l l

/ // // ; / / ; / ; / / / / / / / ; / // ; / // // // // // / ; / / / / / / / / / / / / / / / / /

A 21m

4- 4.

F i g u r e C - 3 : D e t a i l s o f l m h i g h w a l l

200

1000

300

Y12@200 c / c e / f b / w

2000

Y12@200c/cT&B .Y12@200c/cT&B / T 1 2 @ 2 0 0 c / c n

joint sealing compound

/ \ / \

Polythene ^-hard core/blinding

bar wrapped with thick t ape

Water s top Non absorben t jooint filler

j ^ 3 0 0 - j

1 6 0 0

3 0 0

J ^ 3 0 0 ^ r

Figure C-4 : Details o f 1.6m high wa l l

Y 1 2 O 2 0 0 c / c e / f b / w

2 0 0 0 •

Y 1 2 @ 2 0 0 c / c T & B Y1 2 @ 2 0 0 c / c T & B

T 1 2 @ 2 0 0 c / c - | joint sea l ing c o m p o u n d

Polythene ^-hard core /b l ind ing

bar wrapped with thick t a p e

Water s t o p ^ N o n a b s o r b e n t jooint filler

4-

Figure C-5 : Details of side walls

j — 3 0 0 — j

varies:— 1m —1.6m

3 0 0

L

'Y12O200 c / c e / f b /w

2000 •

Y12@200c/cT&B

-Y12@200c/cT<5cB T 1 2 @ 2 0 0 c / c - i r-joint sealing compound

_* _ • *_ _• • • •_

\— 300—If 7 ^ 7 \

Polythene ^-hard core/blinding

bar wrapped with thick tape

Water sto p / ^ N o n absorbent jooint filler

4-

Figure C-6 : Base slab details

Plan

Appendix D

Design drawings of proposed swimming pool without deep end

4-

Figure D-1 : Plan & section of the pool with

no deep end

© I 1 £ —

i n

16.0m- -9.0m-

2 Section

Plan

4

F i g D - 2 : D e t a i l o f w a l l Y - Y

150nm

4 5 0 n r

400mm

600

750

150mm

Walk way slab

150 mm

T10@ 150c/c

R.C.C lining

T10@ 150c/c

I

T10(a} 150c/c \ T10@ 150c/c T10(2) 150c/c

Maximum water level

R.C.C base

Screed concrete

4-

Fig D-3 : Detail of wall Z-Z

150mm

450mr

400mri

600mm

150mm

600

750

1000

f • r

T10@ 150c/c

Walk way slab

150 mm

T10@ 150c/c

T10(S) 150c/c

R.C.C lining

T10@ 150c/c T10@ 150c/c

Maximum water level

R.C.C base

Screed concrete

1

Appendix E

Design drawings of conventional swimming pool with deep end

Fig E.l: General Arrangement of R.C.C Pool with deep end

0.3m wall ff

0.§n m r i m

m

-15.5m- J-2.7m-J 6.8m-

SECTION

3 . 0 m

Designed as shallow end wall (0.2m

[J

th It

•I 12.5n

Designed as side wall (0.3m thick)

f 2m long heel right round

a

II < m t h i r l f J t n p

-9.5m.

0.6n I

c e e p Designed as end wall (0.3m

long toe

•25.0m

PLAN

Fig E-2 : Details of 3.1m high wall

T 1 2 @ 2 0 0 c / c

T 30<D

1

I -300H Maximum_ water level

7 1

3100

-2000-- Y 1 2 @ 2 0 0 c / c T & B

Y 1 6 ® 1 7 5 c / c / e / f vertical

Y 1 2 @ 1 2 5 c / c / e / f

— 6 0 0 — | 6 ® 2 0 0 c / c T & B

bar wwpRea^with Water s t o p

itr pe

hard c o r e / b l i n d i n g

y

Fig E-3 :Details of 1 .Om high wall

| — 2 0 0 — |

1000

3 0 0

Maximum "water level

,Y12@ 2 0 0 c / c e / f b / w

2 0 0 0

Y 1 2 @ 2 0 0 c / c T&B b / w

^-hard c o r e / b l i n d i n g

Fig E-4:Details of 1.8m high wall

J—300—|

varies 1 — 1

• 3 0 0

3 0 0

m

Maximum "water level

,Y12@ 200 c / c e / f b /w

2 0 0 0 -

X Y12@200c/c T&B b/w r-T 2@200c /c

V V / \ / \

Water stop

Figure E-5 : Base slab details

3 0 C t [

• 4 8 0 0

Detail at A

A p p e n d i x F

Design drawings of proposed swimming pool with deep

Fig F.l: General Arrangement of Proposed Pool with deep end

R.R.M walls

0.5m

j j*--Counter fort walls-TJ'

I 1.4m

m

-15.5m- -J-2.7m-l 6.8m-

3.0m

SECTION

CF2

CF1

CF1

CF1

CF1

CF1

CF1 CF1 CF1

PLAN

NOTES:-1.Sections Y-Y & Z-Z are R.R.M walls (Ref Fig F-2 & F-3 for details)

2.CF1 & CF2 are Counter forts (Ref Fig F-4 & F-5 for details)

Fig F-2: Detail of wall Y-Y

150mm

450mr

400mm

_ J _

150mm

600

7 5 0

Walk way slab

150 mm

T10@ 150c/c

R.C.C lining

T10@ 150c/c

I

T10 (2), 150c/c T10@ 150c/c \ T10@ 150c/c

_Maximum water level

R.C.C base

Screed concrete

V

Fig F-3: Detail of wall Z-Z

150mm

450mm

400mm

600mm

150mm

600

7 5 0

1000

i r-

T10 150c/c

Walk way slab

150 mm

T10(£) 150c/c

T10@ 150c/c

R.C.C lining

I T 1 0 @ 150c/c \ T 1 0 @ 150c/c

Maximum water level

R.C.C base

Screed concrete

Fig F-4 : General Arrangement of Counter forts

I F-5 : Reinforcement Details of Counter fort CF1

600

2 Y 1 2 -

Y 1 0 @ 1 7 5 e / f a s l i n k s

2 Y 1 0 ( 2 > 1 7 5 e / f a s

V

Fig F-6 : Reinforcement Details of Counter fort CF2

2Y12-

Y10(5>200 e/f as links 2Y12

2 Y 1 0 @ 2 0 0 e/f as links

Fig F-7 : Counterfort wall and Base Reinforcement details