cgc overseas construction group co. ltd . - [f[]

14
I . CGC OVERSEAS CONSTRUCTION GROUP CO. LTD . : ri\.l . . Ethiopia Branch: Nefas Silk Lafto Sub City, Kebele 02, Addis Ababa, l!.J . i Ethiopia Project Office: Contractor's Camp, Dinsho. Tel: 00251-221-190934 [f[] Date: 04 March 2010 Our Ref: CGCOC/DG3/A 1001 TO: The Engineer's Representative, Transport Construction Design Share Company Engineer's Site Camp Office I>insho. Attention: Ato Beshewa Teshome, Resident Engineer Dear Sir, Ref:- Nazareth-Assela-Dodola and Shashemene-Goba Road Upgrading Project CONTRACT 3: Dodola Junction - Goba Sub:- Submission of Environmental and Social Management Plan We are pleased to submit herewith the Environmental and Social Management Plan for our project for your kind perusal and further instructions. The Plan has been upd::lted up to the end of February 2010 and in the new format provided by the Employer. Regards. Yours faithfully, For CGC Overseas Construction Group Co. Ltd. Mingge Jiang Project Manager Ene 1:- Environmental and Social Management Plan Cc:- '" Construction Contract Implementation Division, ERA. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: khangminh22

Post on 26-Feb-2023

0 views

Category:

Documents


0 download

TRANSCRIPT

I

. CGC OVERSEAS CONSTRUCTION GROUP CO. LTD . : ri\.l . . Ethiopia Branch: Nefas Silk Lafto Sub City, Kebele 02, Addis Ababa, l!.J . i Ethiopia _~ Project Office: Contractor's Camp, Dinsho. Tel: 00251-221-190934

[f[]Date: 04 March 2010 Our Ref: CGCOC/DG3/A 1001

TO: The Engineer's Representative, Transport Construction Design Share Company Engineer's Site Camp Office I>insho.

Attention: Ato Beshewa Teshome, Resident Engineer

Dear Sir, Ref:- Nazareth-Assela-Dodola and Shashemene-Goba Road Upgrading

Project CONTRACT 3: Dodola Junction - Goba

Sub:- Submission of Environmental and Social Management Plan

We are pleased to submit herewith the Environmental and Social Management Plan for our project for your kind perusal and further instructions. The Plan has been upd::lted up to the end of February 2010 and in the new format provided by the Employer.

Regards.

Yours faithfully,

For CGC Overseas Construction Group Co. Ltd.

Mingge Jiang Project Manager

Ene 1:- Environmental and Social Management Plan

Cc:­

'" Construction Contract Implementation Division, ERA.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb350881
Typewritten Text
E2392 v1

Contract 3: Dodola Junction-Goba Road Upgrading Project

Environmental and Social Management Plan (Updated by end of February 2010)

CONTENTS

PART I Project Background

PART n General EMP for the Whole Project Road

A Reinstatement of borrow and quarries sites

B Reinstatement of detours and access roads

C Establishment and Reinstatement of camp sites

D Erosion control and slop stability

E Waste management

F Water pollution control and utilization

G Deforestation in the road corridor and replanting activities

H Protection of wild 1 ife

I Smooth traffic management and occupational safety

J Noise and air pollution

K Prevention and control of HIVIAIDS

L Prevention of cultural heritage, etc) the guiding principles and the

reinstatement measures should be discussed in detail.

PART III EMP for the Park Section

PART IV Project site photos, documentations and accident records (if any).

PART V Layout or plan for the material sites with chainages

PART VI Summary Table

PART I Project Background

This particular project is located in the State of Oromiya and passes mostly through

plain, rolling and also rolling-to-hilly terrain. The project road is part of the

'lazreth-Assela-Dodola and Shashemene-Goba Road Upgrading Project. It starts from

Dodola Junction, passes through Dodola Town, Heraro Town, Adaba Town, Washa

Town, then about 24kms of escarpment area, about 6kms of Bale National Park area,

and again Dinsho Town, Homa Town, Robe Town and Goba Town and ends at Goba

Tow n with a total length of 132kms. Apart from the escarpment area and park section,

the rest of the project length is located in thickly populated area and with most of the

land cultivated. Out of 24kms of escarpment section, there are about 10kms of length

pas~es through forest area. The Bale National Park is a well reserved natural park with

a 101 of animals living in the park.

PART II General EMP for the Whole Project Road

A Reinstatement of borrow and quarries sites

Up to date the following borrow pits and quarries have been explored and their

respective conditions are as follows: ·~·~-·~~·-·-l

I Remarks III~:o l:::~~~ In ~:~~nt SM"s

-021Quarry I Km 1 00 RHS I In use

Q3 IQuarry ! Km 138 LHS I In

-----T!-F-o-r-crusher

1 For m/stones

IFor crusher use

r---~.-----11----------41'------------~1--------~ Q4 i Quarry ; Km 163 RHS . In use ! For m/stones

osr~arry --rKm 1_7_5_R_H_S__----i!_I_n_u_s_e____-l-IF_o_r~_·~_r;.;h~~ B] : Borrow Pit . Km72 LHS : Not yet explored I Cinder

I B2 I Borrow Pit KmlOO RHS ~·-n-us-e------+I------1

~.B3 I ·Borrow Pit i Km 1 09 In use ICinder ,I ~~ I i LHS+] ]km

I B4 iBorrow Pit IKm 109 RHS lIn use

3

I B5 IBorrow Pit Kml12 LHS I In use I

I J

I B6 iBorrow Pit Kml42 LHS Tn use

i -~..---..

LB7 Borrow Pit Km 159 RHS+6km \In use

I

! Borrow Pit i Km 160 RHS

, B P' I K 172 LHS 3k

B8

B9i

I orrow It m + m n use

II I i

I BIO ! Borrow Pit Kml73 LHS+3km . In use Base binder i

~ I B 11 Borrow Pit • Km 189 RHS+3km In use ! I

B12 Borrow Pit I Km 193 RHS I In use II i

I IB 13 Borrow Pit ! Km200 LHS+ 3km lIn use I Cinder I I I

Following mitigation measures are being taken:

I S.No. I Measures I Action up-to-date Actor

Quarry sites and Borrow pits I Fo-I-Io-w--'·e-d-.--·--r-C·-o-n-t-ra-c-to-r-/·-E-n-gi~

should be avoided as much as

possible from farm lands,

residences, schools, churches, i

mosques and health institutions

Contractor/Engineer

borrow pits to the level of the explored quarries

general topography of the area and borrow pits

Landscape the quarry sites and Followed. All2

I

are still in use.

Contractor/Engineer

creation of stagnant water

favorable for breeding of

Rehabilitate the area to avoid Followed.

I . mosquito

H. 4 Plant tree seedlings on the

leveled land to restore the ! I ! biological diversity of the area I

Followed. Contractor/Engineer

I 5 Restore, rehabilitate and Followed. All Contractor/Engineer I reinstate the Borrow pit after I borrow pits are:

I

B Reinstatement of detours and access roads

By end of February 20 I 0, the Contractor has taken possession of site from

Km95 to Km202. Up-to-date the full taken section is under construction.

Therefore, detours have been constructed in most of the reaches with a total

length of 85kms. In the places where there are no space for detours, the

Contractor is maintaining the existing road to accommodate traffic.

The Contractor at the time being is deploying his main resources working in the

sections between Km97 & Kml14 and Km154 & Km195. In these two working

sections detours are being maintained properly in general. For the section

between Km 114 & Km 154, the detour has been damaged by rains and traffic

and the Contractor has assigned one grader and one roller reinstating the detour

since mid January 20 10. So far, 15km of detour has been reinstated properly and

the operation is on-going.

C Establishment and Reinstatement of camp sites

The Contractor so far has established the following camps:

• Main Camp at Km 154

• Sub-camp at Km88

• Sub-camp at Km114

• Sub-camp at Km138

• Sub-camp at Km 175

• Sub-camp at Km 184, and

• Sub-camp at Kml96

Sub-camp at Km 114 has been demolished and all others are still in use. However,

the demolished sub-camp at Km114 has not yet been reinstated as the Contractor

has not yet decided whether to abundant it permanently.

Sub-camps at Km 184 & Km 196 are rented private houses in Robe & Goba Town

respectively, to accommodate Contractor's staff only.

D Erosion control and slop stability

Erosion and slop stability are being monitored by both the Contractor and

Engineer. So far, no incident has been found.

E Waste management

Following principles are being observed and no offend has been found so far: • Disposal of waste materials in accordance with the Laws and Regulations

in effect and the Contract.

• Provide septic tanks in camps, sub-camps. • Disposal areas for waste materials shall be approved by the concerned

authority and away from farmland, residential areas, grazing land and especially Park Areas.

• Deep burial or burning of waste materials shall be allowed, but not cause damage or pollution to underground water sources and local inhabitants.

• Select designated dumping site away from farm land, residential areas, grazing land and park.

• Construct septic tank to dispose used chemicals like oils, lubricants and other chemicals.

• Contact oil companies for safer disposal of used or waste chemicals. • Proper toilets are constructed in each camp and cleaned daily. • All rubbish are dumped at designated locations and burnt. • All used oils are stored in containers and buried at designated places.

F Water pollution control and utilization Following principles have been observed and no offend has been found so far:

• Dispose oils, lubricants, other chemicals and wastes away from the surface in designated disposal septic tank.

• Spray water in the vicinity of rivers properly and regularly to suppress dust that spreads & spoils the rivers.

• Limit earth work operation to the dry seasons to minimize merging of soil to the water bodies. Proper temporary side ditches to be constructed in the rainy seasons to minimize scouring of soils to rivers.

G Deforestation in the road corridor and replanting activities Following principles have been observed and no offend has been found so far:

• Limit clearing and grubbing vegetation. • Reserve top soils for further rehabilitation of quarry sites and borrow pits. • A void as much as possible detours and access roads from vegetation and

cultivation lands. • Keep away quarry sites and borrow pits from vegetation areas when possible. • Re-plant the removed trees along the road project on its completion will be

carried out as per Contract.

H Protection of wild life ~ Awareness has been created among the Contractor's staff and workers

on safeguarding the wild life; ~ No dumping of oils, lubricants and disposable wastes in the Park has

been found so far; )- Frequent contact with the Park Management has been maintained as

I

regard to wild life protection.

Smooth traffic management and occupational safety

Traffic signs and safety man have been deployed at some key places but

insufficient. The Contractor has been instructed by the Engineer to deploy more

at more locations.

Workers working at quarries, steel bar bending workshop and blasting places have been provided with some safety materials such helmet, goggle, rubber safety shoes, gas masks and mouth muffle. However, many of them are to be replaced.

The Contractor is maintaining liaison with local clinics in different towns for

treatment of his workers as well as health information and cooperation. As all

the camps are adjacent to towns, the Contractor dose not have clinics at his

camps. However, first aid is available in all camps.

J Noise and air pollution

The following principles are being observed:

• If not inevitable, avoid working at night, especially in town sections and Bale Mountains National Park to erase acoustic disturbance to local inhabitants and wild animals. If construction at night is insurmountable, proper measures, such as control of working hours and selection of construction equipments, shall be adopted to minimize noise and enough information shall be given to the neighbor communities in advance for their understanding.

• All machinery and plant shall conform to the applicable noise standards, and plant will be provided with effective noise mufflers.

• Blasting shall be well controlled in the Park areas. • Spray water properly and regularly to suppress dust along the

construction sections.

• Pay attention to quarry sites, avoid selecting quarry sites near villages or towns.

Mitigation actions: );- No working at night so far;

);- Machinery and plant are in normal working conditions and no extra noise has been created so far;

);- Detour has been maintained wet in January due to rains; );- No quarry site is close to town or village so far.

K Prevention and control of HIVIAIDS

The work is being carried out by a nominated Sub-contractor, namely Action For

Substantial Development (AFSD), which is a NGO organization based in Addis

Ababa. The Sub-contractor is carrying out the works as per their approved

program and under close supervision of both the Contractor and Engineer. The

Sub-contractor submits monthly reports to both the Contractor and the Engineer

detailing the activities carried out and works done during the month.

So far the Sub-contractor has successfully carried out their major activities

between Dinsho Town and Goba Town and they are now focusing between

Dodola Town and Washa Town.

Monthly Report for the month of January 2010 has been submitted to both the

Contractor and the Engineer and February Report is being prepared. So far the

Sub-contractor is carrying out the activities as per his program.

L Prevention of cultural heritage, etc.

The project is an upgrading road project and the construction is on the existing

road except in few places where there are slight realignments. Therefore, there is

hardly any possibility of encountering cultural heritage sites, etc ..

However, in case any cultural heritage site or historical site, etc. is encountered,

we will immediately suspend the work at that particular site and inform the

Engineer, Employer and the national authorities in concern without delay and

further actions will be taken as per the instructions from the authorities.

PART III EMP for the Park Section The project road passes through the Bale National Park between Krn I 46 and Krn 152 with a total length of 6kms.

A Following principles are being followed: • Keep the detour in the Right of Way or close to the Existing Road. • Limit the speed of construction equipments to minimize potential

nuisance noise and dust. • A void land requisition of quarry and borrow pits from the Park. • Spray water to suppress dust during construction of the section. • Prohibit any subjective and purposive hurt to wild life. • Education to the Contractor's staff to safeguard wild life. • Avoid dumping oils, lubricants and disposable wastes in the Park. • Cooperation with the Park Administration for precaution and protection

measures to safeguard wild life from construction activities.

B Mitigation actions taken so far: y Detour has been maintained properly; y Construction machinery has been controlled properly; y No quarry or borrow pit has been explored in the Park area; y Detour is maintained wet due to rains; y No wild life hunting has been found so far; y Awareness has been created among the Contractor's staff and workers

on safeguarding the wild life; 'Y No dumping of oils, lubricants and disposable wastes in the Park has

been found so far; y Frequent contact with the Park Management has been maintained.

PART IV Project site photos, documentations and accident records (if any).

Nil.

PART V Layout or plan for the material sites with chainages

As attached.

PART VI Summary Table

As attached.

.. ilL •

CONTRACT 3: DODOLA JUNCTION - GOBA

Plan of Material Sites

3 ml09

Q3 Quarry B6· Ql Bl B8Km142Km96 ~

Km72 Km160~'r"* * *' [69+400/75

UU

J8-0:T85 190 195 !16fl1051110 1115 1120 1125 [130~135 1140 [145 1150JIsD160

* B4

Kml09 Q4

Quar

KmlQ2Quarry.

Crusher&B2

B/Pit * Kml00 /;;-,

l... ~

•PART VI SUMMARY TABLE

No Socio-Envir Location/Chai Proposed 1% % IPeriod of Execution I Executor onmental nage (km) Mitigatio I accom Remaini \ (When to do it?) s

! Impact including LHS plished

I, n ngwork I (Byi

ID orRHS measures whom)

1 A Km72-Km202 Refer to 50% 50% Sept 2007 June Contracto fA 2011 r

I 2 B Km69-Km203 Refer to 50% 50% Sept 2007-June 2011 Contracto

I ! B r!

I i I 3 C !Refer to C Refer to 160% 40% I Aug 2006-May 2012 Contracto

C ! ! r

I 4 i D Refer to D Refer to 70% 30% May 2007-Apri12011 Contracto

! I J

D r

5 E Refer to E Refer to E 70% 30% Aug 2006-June 2012 Contracto

I r I

I 6 F Refer to F Refer to F 70% \ 30% Aug 2006-June 2011 Contracto

I I r I I I

7 I G Refer to G Refer to 70% 30% Aug 2006-June 20 II Contracto ,G r

t i 8 H IRefer to H Refer to I 70% 30% IAug 2006-June 2012 Contracto

IH I r I·-~··

i 9 I -I Refer to I Refer to I 170% 30% Aug 2006-June 2011 Contracto

I Ir

10 J Refer to J Refer to J 70% 30% IAug 2006-June 2011 Contracto

I i \ r , ! I

J 11 K Refer to K Refer to 70% 30% IAug 2006-JUne_201 ~ontracto

K , I

-~.

12 L Refer to L Refer to L 80% 20% IAug 2006-Apr 2011 Contracto

I r I -

• •