document of the world bank report no: icr00003289 implementation completion and results … · date...

132
Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-45600 IDA-H4620) ON A CREDIT IN THE AMOUNT OF SDR 3.8 MILLION (US$5.5 MILLION EQUIVALENT) AND A GRANT IN THE AMOUNT OF SDR 3.1 MILLION (US$ 4.5 MILLION EQUIVALENT) TO THE KYRGYZ REPUBLIC FOR A SECOND RURAL WATER SUPPLY AND SANITATION PROJECT April 27, 2015 Water Global Practice (GWADR) Central Asia Country Management Unit Europe and Central Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 06-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

Document of

The World Bank

Report No: ICR00003289

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IDA-45600 IDA-H4620)

ON A

CREDIT

IN THE AMOUNT OF SDR 3.8 MILLION

(US$5.5 MILLION EQUIVALENT)

AND A GRANT

IN THE AMOUNT OF SDR 3.1 MILLION

(US$ 4.5 MILLION EQUIVALENT)

TO THE

KYRGYZ REPUBLIC

FOR A

SECOND RURAL WATER SUPPLY AND SANITATION PROJECT

April 27, 2015

Water Global Practice (GWADR)

Central Asia Country Management Unit

Europe and Central Asia Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

CURRENCY EQUIVALENTS

(Exchange Rate Effective October 31, 2014)

Currency Unit = Kyrgyz Som (KGS)

KGS Som 1.00 = US$ 0.0174

US$ 1.00 = KGS 57.47

FISCAL YEAR 15

ABBREVIATIONS AND ACRONYMS

ADB Asian Development Bank

AO Ayil Okmotu (Village Administration – Local Self-Government Body)

CAS Country Assistance Strategy

CBISSP Community Based Infrastructure Services Sector Project (ADB-financed)

CDD Childhood Diarrhea Diseases

CDS Country Development Strategy

CDWSA Community Drinking Water Supply Association

CDWUU Community Drinking Water Users Union (Association)

DFID Department for International Development (UK)

DRWS Department of Rural Water Supply

DWSS Department of Water Supply and Sanitation

FM Financial Management

FMR Financial Monitoring Report

FSU Former Soviet Union

GIS Geographical Information System

GoKR Government of the Kyrgyz Republic

IA Impact Assessment

ICR Implementation Completion Report

IDA International Development Association

IEG Independent Evaluation Group

IFR Interim un-audited Financial Report

IRR Internal Rate of Return

ISR Implementation Status Report

KAS Kyrgyz Ayil Suu

M&E Monitoring and Evaluation

MAWRPI Ministry of Agriculture, Water Resources, and Processing Industry

MOF Ministry of Finance

MOH Ministry of Health

MIS Management Information System

MTR Mid-term Review

NALSG National Agency for Local Self-Governance

NCHP National Center for Health Promotion

NGO Non-governmental Organization

OECD Organization for Economic Cooperation and Development

Page 3: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

O&M Operation and Maintenance

PAD Project Appraisal Document

PHAST Participatory Hygiene and Sanitation Transformation

PMC Project Management Consultant

PMU Project Management Unit

QAG Quality Assurance Group

RCHP Republican Center for Health Promotion

RHSP Rural Hygiene and Sanitation Project

RRK Rapid Response Kit

RWSSP Rural Water Supply and Sanitation Project

SAACS State Agency for Architecture, Construction and Communal Services

SDA Service Delivery Agreement

SES Sanitary Epidemiological Surveillance

SNIPs State Technical Engineering Standards (acronym from Russian)

Vice President: Laura Tuck

Country Director: Saroj Kumar Jha

Senior Global Practice Director, Water Junaid Kamal Ahmad

Practice Manager: Dina Umali-Deininger

Project Team Leader: Anna Cestari/Pier Francesco Mantovani

ICR Team Leader: Sanyu Lutalo

Page 4: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)
Page 5: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

KYRGYZ REPUBLIC

SECOND RURAL WATER SUPPLY AND SANITATION PROJECT

CONTENTS

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

A. Basic Information ........................................................................................................ i

B. Key Dates .................................................................................................................... i C. Ratings Summary ........................................................................................................ i

D. Sector and Theme Codes ........................................................................................... ii E. Bank Staff ................................................................................................................... ii F. Results Framework Analysis ..................................................................................... iii

G. Ratings of Project Performance in ISRs ................................................................. viii H. Restructuring (if any) ................................................................................................ ix

1. Project Context, Development Objectives and Design ............................................... 1 2. Key Factors Affecting Implementation and Outcomes .............................................. 8

3. Assessment of Outcomes .......................................................................................... 17 4. Assessment of Risk to Development Outcome ......................................................... 25

5. Assessment of Bank and Borrower Performance ..................................................... 26 6. Lessons Learned ....................................................................................................... 29

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 32 Annex 1. Project Costs and Financing .......................................................................... 33 Annex 2. Outputs by Component ................................................................................. 34 Annex 3. Economic and Financial Analysis ................................................................. 43 Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 47

Annex 5. Beneficiary Survey Results ........................................................................... 49 Annex 6. Stakeholder Workshop Report and Results ................................................... 55

Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 56 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 89 Annex 9. List of Supporting Documents ...................................................................... 90

Page 6: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)
Page 7: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

A. Basic Information

Country: Kyrgyz Republic Project Name: Second Rural Water

Supply & Sanitation

Project ID: P110267 L/C/TF Number(s): IDA-45600,IDA-

H4620

ICR Date: 02/18/2015 ICR Type: Core ICR

Lending Instrument: SIL Borrower: KYRGYZ REPUBLIC

Original Total

Commitment: XDR 6.90M Disbursed Amount: XDR 6.90M

Revised Amount: XDR 6.90M

Environmental Category: B

Implementing Agencies1:

Community Development and Investment Agency (ARIS)

Co-financiers and Other External Partners2: UNICEF

UK Department for International Development (DFID )

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 03/21/2008 Effectiveness: 08/19/2009 08/19/2009

Approval: 04/21/2009 Mid-term Review: 05/31/2011 06/02/2011

Closing: 05/31/2013 10/31/2014

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately Satisfactory

Risk to Development Outcome: Substantial

Bank Performance: Satisfactory

Borrower Performance: Moderately Satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately

Unsatisfactory Government:

Moderately

Unsatisfactory

1 At approval, the Implementing Agency was the Department of Rural Water Supply under the National

Agency of Local Self Governance Affairs, Kyrgyz Republic.

2 UNICEF was contracted by ARIS to support implementation of Component 2. DFID was a co-financier.

Page 8: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

Quality of Supervision: Satisfactory Implementing

Agency/Agencies: Moderately Satisfactory

Overall Bank

Performance: Moderately Satisfactory

Overall Borrower

Performance: Moderately Satisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem Project

at any time (Yes/No): No

Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): Yes

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status:

Moderately

Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Public administration- Water, sanitation and flood

protection 10 10

Sanitation 30 15

Water supply 60 75

Theme Code (as % of total Bank financing)

Rural policies and institutions 30 30

Rural services and infrastructure 70 70

E. Bank Staff

Positions At ICR At Approval

Vice President: Laura Tuck Shigeo Katsu

Country Director: Saroj Kumar Jha Motoo Konishi

Practice

Manager/Manager: Dina Umali-Deininger Wael Zakout

Project Team Leader: Anna Cestari Mirlan Aldayarov

ICR Team3 Leader: Anna Cestari

ICR Primary Author: Sanyu Lutalo

3 The ICR team included Sanyu, Lutalo, Pier Francesco Mantovani, Paula Restrepo Cadavid and Luis

Eduardo Quintero.

Page 9: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document)

The original Project Development Objective of RWSSP-2 was to assist the Borrower in:

(i) improving access to potable water for the participating communities; and (ii) to

improving hygiene, sanitation and water-related practices at individual, family and

institutional levels in the rural areas.

Revised Project Development Objectives (as approved by original approving authority)

The revised Project Development Objective was to assist the Borrower in (i) improving

access to potable water for the participating communities: (ii) improving hygiene,

sanitation, and water related practices at individual, family, and institutional levels in the

rural areas, and (iii) strengthening the institutional framework and capacity for the rural

drinking water supply and sanitation sector.

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1

(Original)

Percentage of people with access to drinking water in the network (for at least 4

days a week/12 hours a day) as a result of the project.

Value

quantitative or

Qualitative)

0

50/54

Target not

revised.

See comment

below.

Indicator 1

(Revised)

Number of people in rural areas provided with access to improved water supply

service under the project.

Value

quantitative or

Qualitative)

0 Not applicable 60,000 83,000

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The revised target was fully achieved and exceeded (138%) at completion. The

revised indicator (a core indicator) was introduced as part of project restructuring

in November 2012. The original indicator was not formally measured at

completion since it was dropped as part of the same restructuring.

Indicator 2 : Percentage of water quality tests in the service area of the rehabilitated schemes

that meet national standards for drinking water.

Value

quantitative or

Qualitative)

No data. 80% Target not

revised. 90%

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded (112.5%). The indicator was revised

as part of restructuring to focus on samples in the service areas.

Page 10: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

Indicator 3 : Percentage of people in communities in project area reporting about the use of

soap for hand-washing after toilet use.

Value

quantitative or

Qualitative)

60 70 Target not

revised. 72.7

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

Target fully achieved and exceeded. This indicator was introduced during

implementation and upon restructuring.

Indicator 4 : Average level of O&M cost recovery by utilities targeted by the project. (%)

Value

quantitative or

Qualitative)

Data not available. 60 Target not

revised. 70

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded (117%).

Indicator 5 :

Reduction in the incidence (number of cases) of water supply and sanitation

related illnesses (Giardia and/or Hepatitis A) in communities that participate in

the project (%).

Value

quantitative or

Qualitative)

Data not available. -60% Target not

revised.

See comment

below.

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

This indicator was moved to Intermediate Outcome indicators during

implementation as part of restructuring (See IO 13 below).

Indicator 6 : State Water Supply and Sanitation Strategy endorsed by government.

Value

quantitative or

Qualitative)

No strategy in place.

This indicator was

introduced during

implementation.

Strategy

completed and

endorsed.

Strategy completed

and endorsed.

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved.

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Number of water supply systems rehabilitated by the project.

Value

(quantitative

or Qualitative)

0 60 35 37

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Page 11: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

Comments

(incl. %

achievement)

The revised target was fully achieved. The original target was revised as part of

project restructuring in 2012.

Indicator 2 : Number of improved community water points constructed or rehabilitated under

the project.

Value

(quantitative

or Qualitative)

0 Not applicable. 226 226

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved. This core indicator was introduced as part of

project restructuring in 2012.

Indicator 3 : New piped household water connections resulting from the project intervention.

Value

(quantitative

or Qualitative)

0 Not applicable. 2000 3902

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved. This core indicator was introduced as part of

project restructuring in 2012. The target was not included in the approved

Project Paper.

Indicator 4 : Piped household water connections benefitting from rehabilitation works

undertaken by the project.

Value

(quantitative

or Qualitative)

0 Not applicable. 1000 1000

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved. This core indicator was introduced as part of

project restructuring in 2012. The target was not included in the approved

Project Paper.

Indicator 5 : People provided with access to improved sanitation facilities under the project.

Value

(quantitative

or Qualitative)

0 Not applicable 5000

9151 (mainly

school children and

staff in beneficiary

schools)

Date achieved 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded. This indicator was introduced

during implementation.

Indicator 6 : Number of improved latrines constructed under the project

Value

(quantitative

or Qualitative)

0 Not available. 10 18 *

Date achieved 12/14/2012 10/31/2014 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded (180%). This indicator was

introduced during implementation. * Of the 18 toilets, 10 were constructed

outside the school buildings and 8 rehabilitated and refurbished inside school

buildings.

Indicator 7 : Equipment units procured for operation and maintenance of schemes (Number).

Page 12: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

Value

(quantitative

or Qualitative)

0 Not available. 10 60

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded (600%).

Indicator 8 : Number of schools in project area with a functioning water supply connection as

a result of the project.

Value

(quantitative

or Qualitative)

0 35 35 44

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded (126%).

Indicator 9 : Percentage of households in the service area reporting a distance to the nearest

improved water source at 500/1000 m or less.

Value

(quantitative

or Qualitative)

59 69 69 71

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded.

Indicator 10 : Number of people trained to improve hygiene behavior or sanitation under the

project (% of whom are women)

Value

(quantitative

or Qualitative)

0 Not applicable. 100,000

82,160 people were

trained; of these

60,798 or 74%

were women.

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The overall target for number of people trained was partially achieved (82%).

However the targeted number of women (51,000 was exceeded). This indicator

was introduced as part of restructuring during implementation.

Indicator 11 : Percentage of people reporting washing hands before food preparation/washing

children's hands.

Value

(quantitative

or Qualitative)

35/24 50/40 Not

applicable. 53/81

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The targets were fully achieved and exceeded. (106%/202.5%)

Indicator 12 : Number of schools with hand-washing facilities in use with soap and water

available near toilets in participating communities.

Value

(quantitative Not available Not available 35 52

Page 13: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

or Qualitative)

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded (149%).

Indicator 13 : Reduction in the incidence of waterborne diseases

Value

(quantitative

or Qualitative)

Data not available -60 Not applicable -62.5

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved and exceeded (104%). Three main diseases were

considered: acute intestinal infections, viral hepatitis, and helminthic

(worm) invasion.

Indicator 14 : Number of water utilities the project is supporting.

Value

(quantitative

or Qualitative)

0 Not applicable 35 38

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved. This core indicator was introduced as part of

restructuring in 2012.

Indicator 15 : Average tariff collection rate in villages served by the project (%)

Value

(quantitative

or Qualitative)

0 Not applicable 70 74

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The target was fully achieved (105%). This indicator was introduced through

restructuring.

Indicator 16 : Number of CDWUU staff trained in fee collection and management of water and

sanitation schemes.

Value

(quantitative

or Qualitative)

0 Not applicable * 200 289

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The revised target was achieved and exceeded (144.5%). *The original target

was based on the number of CDWUUs trained and not on individual staff

numbers.

Indicator 17 : Number of CDWUU Service Agreements signed.

Value

(quantitative

or Qualitative)

0 60 35 38

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The revised target was fully achieved. The original target was reduced as part of

restructuring to reflect the reduced number of schemes to be rehabilitated.

Indicator 18 : CDWUUs with women taking one of the three most senior positions (%).

Value 0 Not applicable. 45 65

Page 14: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

(quantitative

or Qualitative)

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The revised target was fully achieved. This indicator was introduced as part of

the project restructuring in 2012.

Indicator 19 : Number of villages with information on water supply and sanitation included in

the national database.

Value

(quantitative

or Qualitative)

0 1000 1700 1899

Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014

Comments

(incl. %

achievement)

The original and revised targets were fully achieved and exceeded (199.9% and

111.7%, respectively).

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 06/26/2009 Satisfactory Satisfactory 0.00

2 03/02/2010 Moderately Satisfactory Moderately Satisfactory 0.90

3 10/18/2010 Moderately

Unsatisfactory

Moderately

Unsatisfactory 1.06

4 03/07/2011 Unsatisfactory Unsatisfactory 1.17

5 09/21/2011 Unsatisfactory Unsatisfactory 1.10

6 02/01/2012 Moderately

Unsatisfactory

Moderately

Unsatisfactory 2.30

7 06/26/2012 Moderately

Unsatisfactory

Moderately

Unsatisfactory 3.19

8 12/26/2012 Moderately

Unsatisfactory

Moderately

Unsatisfactory 5.84

9 06/20/2013 Moderately

Unsatisfactory

Moderately

Unsatisfactory 6.92

10 07/29/2013 Moderately

Unsatisfactory Moderately Satisfactory 7.35

11 03/13/2014 Moderately

Unsatisfactory Moderately Satisfactory 8.47

12 04/27/2014 Moderately Satisfactory Moderately Satisfactory 8.57

13 10/29/2014 Moderately Satisfactory Moderately Satisfactory 10.51

Page 15: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

H. Restructuring (if any)

Restructuring

Date(s)

Board

Approved

PDO Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in USD

millions

Reason for Restructuring &

Key Changes Made DO IP

07/25/2011 N U U 0.7

To transfer project executing

and implementing

responsibilities to a new entity

(ARIS) due to non-performance

of original entities.

11/29/2012 Y MU MU 5.60

To address a series of

implementation and sector

challenges; changes were made

to the PDO and other aspects,

such as scope, Results

Framework, expenditure

categories, and safeguard

policies. Details are discussed

under Sections 1.7 and 2.2 of

the main text.

03/13/2014 N MS MS 8.85

To optimize the scope of

investments in light of a

funding shortfall; also to allow

for reallocation of funds among

categories, mobilization of

US$500,000 in additional co-

financing by the GoKR, and

adjustments to the Result

Framework.

If PDO and/or Key Outcome Targets were formally revised (approved by the original approving

body) enter ratings below:

Outcome Ratings

Against Original PDO/Targets Moderately Satisfactory

Against Formally Revised PDO/Targets Satisfactory

Overall (weighted) rating Moderately Satisfactory

Page 16: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)
Page 17: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

1. Country and Sector Background. The Kyrgyz Republic is a mountainous landlocked

country in Central Asia, bordering Kazakhstan, China, Tajikistan and Uzbekistan. At appraisal in

2009, the country had a population of about 5.2 million, about two thirds of whom were living in

rural areas. Almost 40 percent of the population lived below the poverty line, and rural areas were

home to about three quarters of the country’s poor, many of whom live in remote and mountainous

areas. More than half of the population works in agriculture, and the sector is still the backbone of

the economy. With a Gross National Income (GNI) per capita of US$600 in 2007 and US$1,080

in 2014, the country was and remains one of the poorest in the Europe and Central Asia region.

2. Prior to independence from the Former Soviet Union (FSU), potable water was supplied

free of charge nationwide, and systems were designed to very conservative technical standards in

line with FSU engineering standards. Following independence however, the Kyrgyz Republic

faced the reality of economic constraints linked to the break-up of the Soviet economic zone and

the end of centralized subsidies from Moscow. While the country eventually registered a gradual

economic recovery due to the adoption of market-based reforms in the 1990s, sectors such as

infrastructure and social services continued to suffer from low investment and basic public services

such as water supply and sanitation suffered particular degradation.

3. The reduction in Government subsidies to the sector resulted in a steep decline in the

quality of water supply and sanitation services, contributing to an increase in the non-income

dimensions of poverty. Access to adequate service coverage was low, with only about one third of

the national population having household water connections, another 40 percent receiving water

from stand-posts or water tankers, and the rest having no organized water service. The situation

was exacerbated by factors such as: (a) the poor physical state of plant and pipe networks, which

were in dire need of rehabilitation and replacement; (b) inefficiencies in operations, which drove

up operating costs; (c) weak institutions; (d) limited human resource capacity; (e) critical financial

shortfalls which precluded operating enterprises to cover even basic operating and maintenance

costs; and (f) and affordability constraints. Declining health indicators were linked to the

deteriorating water supply systems, and service reliability and safety had become a critical source

of discontent among the population. Problems associated with the sub-optimal water supply and

sanitation situation were particularly pronounced in rural areas.

4. According to a Sector Review conducted by the World Bank in 1999, an estimated US$

180 - 200 million would be needed for the rehabilitation of existing facilities and system

expansions for new consumers to provide all of the Kyrgyz people with modest, but safe water

supply and sanitation services. Yet the financial situation in the country and affordability limits on tariffs

made it impossible to raise the financial resources needed in the near term. As part of efforts to fight

poverty and improve the standard of living and the health of its people, the Kyrgyz Government

identified improvement in basic infrastructure services, including water supply and sanitation as

one of its priorities, and approached the World Bank and other development partners, including

Page 18: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

2

the Asian Development Bank (ADB) and British Department for International Development

(DFID) to support the sector.

5. The First Rural Water Supply and Sanitation Project (RWSSP). In 2001 the World

Bank approved an IDA Credit in the amount of SDR 12 million (US$15 million equivalent) for a

Rural Water Supply and Sanitation Project (RWSSP) to support the Government’s efforts to

improve access to water supply and sanitation services and reduce poverty. The RWSSP, which

became effective in April 2002, was the first Bank operation in the Kyrgyz Republic and in the

ECA Region to apply a participatory community managed approach to rural water supply and

sanitation. The project’s development objectives were two-fold: (i) to improve access to potable

water from water supply systems which the communities own, operate, maintain and manage in a

sustainable manner; and (ii) to improve hygiene, sanitation, and water related practices at

individual, family and institutional levels in rural areas. DFID provided TA to finance the

components on Institutional Strengthening and Project Management in the amount of GB £ 4.5

million. The standalone Sanitation and Hygiene Project was also financed through a grant of

GB£ 3.3 million from DFID. The project focused on the three northern Kyrgyz Oblasts of Naryn,

Talas, and Issyk Kul. The Asian Development Bank (ADB) concurrently extended a Credit to the

GoKR for a Community Based Infrastructure Services Sector Project (CBISSP) in the amount of

SDR 27.30 million (US$ 36 million equivalent). The latter was implemented in parallel to RWSSP

as part of the “Taza Suu” (Clean Water) governmental program, and focused on the southern

Kyrgyz Oblasts of Chui, Jalalabad, Osh, and Batken. The ADB project closed in January 2010 and

was rated Partly Successful.

6. The RWSSP closed in 2009. According to its Implementation Completion Report (ICR),

the project provided improved access to clean drinking water to about 340,500 people in 169

villages in the three northern oblasts. It was also instrumental in improving water quality and

hygiene in the beneficiary areas, contributing to a six-fold decrease in the reported incidence of

stomach pain and diarrhea in children. It facilitated the creation of a community-based model for

water service delivery and improved the effectiveness of institutions in managing rural water

supplies. Despite these achievements, the RWSSP experienced some problems. The project ran

out of resources before completion of all envisaged activities due to increased unit costs, and

construction works in three problem sub-projects4 (Korumdu, Temir, and Chelpek) had to be

suspended before completion. The costs of works on the sub-projects increased mainly due to

technical factors such as unexpected ground conditions (in Korumdu) and failure of the surface

water sources (in Temir and Chelpek). Completion of these outstanding works was included in

design of the follow-on project, the Second Rural Water Supply and Sanitation Project (RWSSP2).

Another problem which emerged towards the end of the project was that, despite their efficiency,

the design standards and technical innovations introduced by the PMC (for instance the HDPE

pipe relining technology) became the subject of controversy in that they deviated from the State

Technical Engineering Standards (SNIPs) inherited from the Former Soviet Union. Although not

always technically well-informed, the controversy was amplified among certain stakeholders,

fueling criticisms of the quality of RWSSP works as well as opposition to the PMC-led

implementation arrangements. Such controversy became a serious legacy issue and reputational

4 Individual sub-projects typically encompassed clusters of several villages.

Page 19: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

3

risk to be dealt with under RWSSP-2. A lasting unfavorable impact on the sector was the

entrenchment of stakeholder reticence to use international consultant expertise for engineering-

design needs, or to engage in a critical review and revision process of unsustainable design

standards.

7. Rationale for Bank Assistance for the Second Rural Water Supply and Sanitation

Project (RWSSP2). The RWSSP2 was identified at the back end of RWSSP implementation. It

was designed as a “Repeater Project”5 with similar objectives, to scale up the latter’s development

outcomes in rural communities in the Talas, Naryn, and Issyk Kul Oblasts. A repeater project was

considered to be the most appropriate approach for two main reasons: (i) to build on the successes

of RWSSP while allowing for the introduction of important modifications to improve project

design; and (ii) to allow for quick preparation of the follow-on operation using existing resources.

The project was also seen as an opportunity to complete construction and/or rectification of

outstanding works on the problem sub-projects initiated under RWSSP. It was included in the

Bank’s Joint Country Support Strategy (JCSS) Report No. 39719-KG dated May 23, 2007. The

total project cost was estimated at US$18.37 million: US$10 million equivalent was to be financed

by IDA (as a blend of an IDA Credit in the amount of SDR 3.8 million/US$ 5.5 million equivalent

and a US$4.5 million IDA grant); GBP5 million (about US$7.15 million equivalent) co-financing

was to be provided by DFID; US$1.55 million equivalent was to be provided by Government of

Kyrgyz Republic (GoKR), and US$0.49 million equivalent by participating communities as

contribution (5 percent) to civil works. The project was approved by the Bank’s Board of Directors

on April 29, 2009, and it became effective on August 19 the same year.

1.2 Original Project Development Objectives (PDO) and Key Indicators

8. The original PDO of RWSSP2 was to assist the Kyrgyz Republic in: (i) improving access

to potable water for the participating communities; and (ii) improving hygiene, sanitation

and water-related practices at individual, family and institutional levels in the rural areas.

9. Project outcomes were expected to be improved access, quantity, and quality of water

supply services available to rural citizens of the Kyrgyz Republic. In particular, project

performance was to be assessed against the following indicators6: (a) the increase in number of

residents benefiting from regular availability of safe potable water; and (b) a decline in waterborne

diseases in project communities.

1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and

reasons/justification

10. The development objective of RWSSP2 was revised in November 2012 to add a third

objective, (iii) below, focusing on the need for strengthening sector institutions. Accordingly, the

5 According to Bank guidance documents, “Repeater Projects” are defined as projects whose basic design and

effectiveness have been proven, and which a Borrower proposes to augment and scale up. 6 While this indicator was identified in the main text of the PAD as a key performance indicator, it was not included

in the original Results Framework. For purposes of analysis of the PDO however, it is taken into consideration.

Page 20: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

4

revised PDO was to assist the Kyrgyz Republic in: (i) improving access to potable water for the

participating communities; (ii) improving hygiene, sanitation and water-related practices at

individual, family and institutional levels in the rural areas; and (iii) strengthening the

institutional framework and capacity for the rural drinking water supply and sanitation

sector.

11. The institutional dimension of the PDO was introduced in an effort to address the

weakening institutional framework and capacity in the sector. Performance in respect to the third

objective was to be measured through two indicators: (i) the level of operation and maintenance

(O&M) cost recovery in utilities targeted by the project (%); and (ii) the number of CDWUUs with

sufficient revenues (from fees collection and other sources) to cover at least O&M.

1.4 Main Beneficiaries

12. The primary beneficiaries for the water supply component were the population in

participating communities in rural villages in the northern Kyrgyz Oblasts of Naryn, Talas, and

Issyk Kul, who would directly benefit from improved access to potable water supply through the

project. According to the PAD, the project initially targeted about 100,0007 people in the three

Oblasts. However, the targeted number of beneficiaries was scaled down substantially to 60,000

when the project was restructured in November 2012, reflecting a significant reduction in DFID

co-financing. Likewise, primary beneficiaries for the sanitation and hygiene improvements

included the populations at targeted institutions such as schools where new sanitation facilities

were to be constructed, medical centers and members of the communities in the three Oblasts who

were expected to benefit from hygiene and behavior change interventions. Access to improved

water supply, sanitation and hygiene were expected to bestow multiple benefits such as improved

health, economic, and environmental outcomes.

13. Primary beneficiaries for the institutional strengthening activities were national, local

government, and community level institutions, including: the Department of Rural Water Supply

(DRWS) within the Ministry of Agriculture, Water Resources and Processing (MAWRPI), and the

Sanitary Epidemiological Surveillance (SES) units located within the Ministry of Health8 at the

central government level; the local self-government units (Ayil Okmotus) in the participating areas

of Naryn, Talas, and Issyk Kul Oblasts; and the Community Drinking Water User Unions

(CDWUUs) at the community level, who were to directly benefit from capacity building activities

such as training and knowledge sharing, provision of equipment and facilities, introduction of

management systems for activities such as monitoring, billing and collection systems for water

operations, and other resources financed through the project, resulting in enhanced efficiency and

effectiveness in management of rural water and sanitation services.

7 This number was used as the target in the Economic Analysis conducted at appraisal.

8 The DRWS was later renamed the Department for Drinking Water and Sanitation and was located under the State

Agency for Architecture, Construction and Communal Services – SAACCS, also known as GOSSTROY.

Page 21: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

5

1.5 Original Components (as approved)

14. Component A: Water Supply Infrastructure and Equipment (estimated US$ 15.25

million). This component was to provide financing to local communities represented by CDWUUs

to rehabilitate or expand existing village water supply systems. As part of the civil works contracts,

this component was to also finance the following: refurbishment or construction of demonstration

sanitation facilities at schools and medical posts; equipment supplied to selected CDWUUs and/or

their associations to maintain the water systems; and consultancy services for technical supervision

of construction activities to ensure the quality of infrastructure financed by the project.

15. Component B: Sanitation and Hygiene Promotion Program (estimated cost US$0.68

million). This component was to support village-level promotion of healthy hygiene and sanitation

practices through technical assistance. Component activities were to be coordinated with the

Republican Centre for Health Promotion (RCHP) that is working under the Health and Social

Protection Sector-Wide Approach project (SWAP; P084977) to foster health awareness

throughout the country. (The refurbishment of demonstration sanitation facilities at schools and

medical posts was included in Component A as part of the infrastructure works). Component B

was to be implemented through consulting services (to be provided by a national NGO or firm)

and in direct coordination with the RCHP.

16. Component C: Institutional Development (estimated cost US$0.49 million). This

component was to finance consultancy services to assist Government to ensure sustainability of

the rural water supply programs, including support to: (a) endorse and implement the sector

strategy prepared under the earlier project; (b) develop or revise legislation to ensure synergies

among CDWUUs and local self-governance, including develop and institutionalize new

agreements between Ayil Okmotu and CDWUUs; (c) train and assist CDWUUs and DRWS to

build on the experience and tools developed by RWSSP, including ensuring that gender, voice,

and choice in participatory processes are taken into account; and (d) strengthen the project

Management Information System by adding a GIS interface and consolidating a country-wide

database on village-level water supply and sanitation. Detailed Terms of Reference for Component

C were to be developed during project implementation.

17. Component D: Project Management (estimated cost US$1.95 million). The component

was to finance project management costs including: limited equipment and vehicles, operating

costs (staff salaries, in-country travel, and mandatory employer contributions to the Social Fund

of the Kyrgyz Republic) and training associated with project implementation; as well as

monitoring and evaluation activities, including regular impact surveys/assessments and annual

audits.

18. Retroactive Financing (US$0.80 million). The Bank agreed to finance under Component

A, retroactive costs for the completion of approximately 16 sub-projects financed by Government

under the previous project, the Rural Water Supply and Sanitation Project (RWSSP), subject to

submission of supporting documentation acceptable to the Bank.

Page 22: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

6

19. Project Preparation Advance (PPA), US$0.l5 million. A PPA for Components A and D

was provided to carry out preparatory activities including community mobilization campaigns and

feasibility studies.

1.6 Revised Components

20. Several changes were made to individual components and activities as part of the Level 1

project restructuring in November 2012. Reasons for the restructuring are discussed in more detail

under Section 1.7 below. The following changes were made to individual components as part of

the restructuring.

21. Under Component A. Water Supply Infrastructure and Equipment

The estimated number of rural water supply schemes that the project would rehabilitate

was reduced from 70 to 35.

Two sub-components were merged: i.e., tasks under the detailed design (A3) and the

Technical Supervision (A4) were merged into one sub-component (A3) to streamline

budget use by ARIS.

Contractor payment procedures were streamlined to allow payment directly by ARIS, as

opposed to by individual CDWUUs; and

The provision to extend sub-loans to CDWUUs was eliminated as it had been made

redundant by the above streamlined payment procedures. Therefore the provisions in the

Financing and the Project Agreements referring to Sub-Loans and Sub-Grants were

dropped.

22. Under Component B. Sanitation and Hygiene Promotion Program. (This component

was fully financed by DFID and executed by UNICEF, which was contracted by ARIS). Changes

involved:

Introduction of communication campaigns and advocacy activities to promote rural

sanitation.

Introduction of village level WASH campaigns for hygiene and sanitation awareness.

Building institutional capacity for ARIS in the field of sanitation and hygiene.

.

23. Under Component C. Institutional Development. This component was strengthened by

allocating an additional US$150,000 to maximize the impact on improving the institutional

framework and capacity for the RWSS sector in light of the scaled down infrastructure component.

24. Component D. Project Management. The funding for this component was reduced and

reallocation in disbursement categories made accordingly in light of substantial savings in project

management due to the entity utilizing already existing resources (staff and equipment).

1.7 Other significant changes

25. Project Restructuring. The project underwent three restructurings over the course of

implementation, resulting in several significant changes. These restructurings became necessary

to address several challenges the project faced, and were driven mainly by: (i) the need to

strengthen project implementation capacity in light of sub-optimal performance with the existing

Page 23: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

7

arrangements after the project became effective; (ii) a growing need to strengthen the overall

institutional framework and capacity in the sector; (iii) an increase in unit costs linked to more

robust design standards introduced during implementation; (iv) unexpected additional costs to

rectify works in several villages where rehabilitation or upgrading works undertaken under the

RWSSP were malfunctioning, these included modest retrofits in 26 additional RWSSP systems;

(v) the need for more effective implementation approaches for works contracts and for hygiene

and sanitation promotion activities; (vi) the partial withdrawal in January 2012 of DFID co-

financing, amounting to GBP 4 million, resulting in an overall reduction in the project funding

from US$18.37 million equivalent to US$13.08 million equivalent; (vii) the need to activate the

Involuntary Resettlement (OP 4.12) Safeguard Policy; and last but not least (viii) to accommodate

a request for extension of the closing date by seventeen months to allow for completion of works.

Changes made as part of restructuring in response to the above issues are outlined below.

a. Change in Project Executing and Implementing Agencies. As part of the first (Level

Two) restructuring approved by Bank Management on July 25, 2011 changes were made

to the project’s Executing Agency (EA) and the Implementation Entity (IE) on October

28, 2011. The changes were made in response to a proposal from the Government to

strengthen implementation arrangements in light of ongoing performance issues,

including chronic implementation delays and disruptions encountered after project

effectiveness. Government requested the transfer of responsibilities for both the EA and

IE, previously held by the State Committee of Water Resources and Amelioration

(SCRWA) and the Joint Project Management Unit (JPMU) respectively, to the

Community Development and Investment Agency (ARIS). As a non-governmental

organization (NGO), ARIS had a good track record of executing projects funded by the

World Bank and other donors, including the Village Investment Project, the Small Towns

Infrastructure and Capacity Building Project, and the Bishkek and Osh Urban

Infrastructure Project, and improvements in overall implementation were registered soon

after the change was effected. Primary beneficiaries for the Institutional Development

Component however remained the CDWUUs and the Department for Water Supply and

Sanitation (DWSS), which absorbed the former Department for Rural Water Supply

(DRWS). The DWSS is under the State Agency for Architecture, Construction and

Communal Services (SAACCS).

b. As part of the subsequent (Level One) restructuring approved by the Bank’s Board of

Directors on November 29, 2012, following decisions taken during the project Mid-Term

Review (MTR), the following changes were made:

(i) Project Development Objective. The PDO was revised as described in Section 1.3 above.

(ii) Project Components and Scope. The project components and scope were revised as

described in Section 1.6 above. The changes mainly relate to the reduced scope of

activities in light of reduced availability of resources and cost increases, and included,

inter-alia, a reduction from 70 to 35 in the targeted number of rural water supply systems

to be rehabilitated. Investments entailed comprehensive rehabilitations in six new village

clusters, as well as in the three villages (Korumdu, Terim-Kashat, and Chelpek) which

had suffered from unfinished rehabilitations under RWSSP. They also included

Page 24: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

8

rectifications on an additional 26 schemes previously rehabilitated under RWSSP that

were experiencing no longer functioning optimally. The failures in these 26 villages were

mostly associated with poor design of the water sources at the time of RWSSP.

(iii) Results Framework. The project results frameworks was revised to reflect reduced target

values in light of the reduced funding and investment scope for water supply and sanitation

components, and to introduce indicators to capture the new institutional strengthening

objective. Indicators were consolidated.

(iv) Project Financing. Project financing was revised to reflect the reduced budget, following

the partial withdrawal of DFID funds, bringing the available budget from US$18.37

million to US$13.08 million equivalent.

(v) Reallocation of Expenditure Categories. Expenditure categories were revised to reflect

the reallocation of DFID financing to fully fund Component B and 80 percent of

Component C, as well as register a reallocation of funds among components and

categories, with a substantial decrease of the infrastructure component and a slight

increase in the institutional strengthening component.

(vi) Safeguard Policies. OP 4.12 Involuntary Resettlement was triggered on a precautionary

basis given the nature of envisaged investments, and the potential for temporary

expropriation or permanent acquisition of land.

(vii) Project Closing Date. The project closing date was extended by a total of seventeen

months, from May 31, 2013 to October 31, 2014, to allow for completion of all the works

required to achieve the project objectives after initial implementation delays.

(viii) Other Changes to Implementation Arrangements. Other changes to implementation

arrangements involved a simplification in the implementation approach, with elimination

of sub-loans to communities for contracting of sub-project works; and the inclusion of the

United Nations Children’s Fund (UNICEF) as service provider for implementation of

some tasks under the Hygiene and Sanitation Promotion Component.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

26. The project’s quality at entry is assessed as having been moderately satisfactory on balance

on the basis of project preparation and design aspects that contributed to the overall

implementation experience and outcome. Key aspects as discussed below.

27. Soundness of Background Analysis. The PAD presented a generally sound understanding

of the challenges that the Kyrgyz Republic continued to face in providing and managing rural

water supply and sanitation services, in spite of ongoing interventions. The Bank assessed a

repeater operation as the most desirable option to maximize development outcomes based on a

Page 25: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

9

satisfactory assessment of RWSSP’s performance. Background analysis undertaken as part of

project preparation was informed by identified lessons learned from detailed reviews of completed

and then ongoing sub-projects under the RWSSP, consultations with beneficiaries, Non-

Governmental Organizations (NGOs), Government agencies and the PMU, interventions in the

sector financed by other donors, including the ADB and DFID, and global good practice in the

sector. The project accordingly incorporated key lessons to improve important elements of design

such as sub-project selection and engineering design criteria, to ensure that sub-projects are simple,

technically sound, cost effective, demand driven, and ultimately more sustainable. For instance,

unlike the previous project which mainly offered basic service levels through mainly stand-posts,

all sub-projects under RWSSP2 were designed to accommodate demands for providing household

water connections in order to respond to future likely beneficiary needs and priorities. It is worth

noting that design of the repeater project prior to full completion of the RWSSP meant that perhaps

not all lessons that could be learned from the latter were captured at the time.

28. Assessment of the Operation’s Design. Given the prevailing challenges in the sector,

including the need to not only scale up outcomes but also complete outstanding works from

RWSSP, the project design as a “repeater” with improved design elements was sound. The sector

was still learning and adjusting to the new approach to managing rural water supply introduced

under RWSSP, combining elements of Community Driven Development (CDD) and centralized

provision of services. A full CDD approach would have precluded construction of larger or

complex schemes, although community involvement in project implementation is considered more

suitable for enhancing sustainability of services because it better addresses local demands and

facilitates decentralized operations and maintenance. The selected delivery strategy allowed for

the implementation of larger and more complex schemes which can supply sufficient water to large

villages as well as small ones, and for community engagement in the process, increasing the

likelihood of sustainability. As noted above however, timing of the design and failure to fully

capture some critical lessons, evidence, and/or results, for instance in terms of mal-functional

systems, were factors that contributed to some design shortcomings.

29. The ICR therefore notes some significant shortcomings in the design of (a) initial project

implementation arrangements, (ii) identification of the scope of work and subsequent assessment

of cost estimates; and (iii) the monitoring and evaluation (M&E) arrangements. M&E

arrangements are discussed in Section 2.3 below. Implementation arrangements were based on a

Joint Project Management Unit (PMU) responsible for implementation and coordination of the

current project, as well as a then recently approved Asian Development Bank (ADB) financed

Rural Water Supply and Sanitation Project. The JPMU was established in 2008 at the national

level to manage implementation of rural water supply projects. The Bank initially proposed

implementation arrangements based on a qualified Project Management Consulting (PMC) firm

similar to the model that had been used for the RWSSP. The Government however requested the

use of the JPMU during negotiations. While the approach appeared sound in principle for aligning

donor efforts, promoting consistency in approaches, and ensuring shared lesson learning across

projects, it required sound capacity within the Unit in order to be effective. Although the PAD

noted weaknesses in existing capacity as a key risk, the model was maintained, and fundamental

changes needed to be made to strengthen implementation arrangements through restructuring

during implementation. Carrying out a comprehensive feasibility study in planning the water

supply systems would also have benefitted the project. Shortcomings regarding the failure to

Page 26: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

10

properly define the scope of sub-projects to be included was linked to the legacy issues from the

RWSSP, evidence of which was perhaps not fully available at the time of design. Addressing

these issues called for restructuring of the project during implementation as discussed below.

30. Adequacy of Government Commitment. Government commitment to the project during

preparation was generally adequate. Overall support for the project was strong given

Government’s prioritization of provision of a reliable and well-functioning system of basic

infrastructure services. Dialogue between the Bank and Government counterparts was maintained

even where there were differences in opinion such as was the case during negotiations, in selecting

implementation arrangements.

31. Risk Assessment and Mitigation. The risk assessment undertaken as part of project

preparation and summarized in the PAD was candid and it covered key issues that could potentially

affect implementation. Most of the risk ratings were ‘moderate’ or ‘substantial’, with an overall

project risk rating of ‘moderate’. Identified risks mainly centered around three general themes: (a)

institutional capacity constraints at central government, local government, and community levels

and their implications for project implementation and operation; (b) appropriateness of sub-project

designs and their implications on project costs and financing; and (c) ineffective management

arrangements at local government and community level, including inadequate community cash

contributions and collections, and inadequate construction, operation and maintenance of systems.

Appropriate mitigation measures were identified, with mitigation measures to address them

intertwined with design of the technical assistance and capacity building elements and

implementation support. The following section, which presents factors that affected

implementation, highlights the fact that these critical risks did in fact materialize during

implementation. While the pre-identified risk mitigation measures contributed to some extent to

addressing some of the challenges, resolution of some called for additional measures, in some

cases requiring fundamental structural changes as discussed below.

2.2 Implementation

32. The project encountered a series of challenges that affected progress through much of its

implementation. Resolution of many of these issues called for proactive intervention by the Bank

team and financing and implementing partners. The following paragraphs summarize the main

issues it faced and describes how they were addressed.

33. Weaknesses in implementation structures and capacity affected project performance. Soon after it became effective in August 2009, the project begun to encounter major performance

challenges, resulting in chronic implementation delays and disruptions. These circumstances were

linked to a combination of factors, including, inter-alia, weak implementation capacity, repeated

changes within the original Ministry-level project Executing Agency, the prevailing political

instability in the country, and liabilities inherited from the previous project. The Ministerial home

of the Project Executing Agency was changed four times in the space of 18 months, and Project

Directors changed three times between 2008 and 2011. These changes affected the institutional

memory, capacity, and commitment to the project overall.

Page 27: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

11

34. The need to address previously unidentified liabilities inherited from RWSSP in form

of incomplete or malfunctioning systems further slowed progress and took up significant

resources. By the end of 2009 and just a few months into implementation, it emerged that in

addition to the three problem sub-projects, Koromdu, Tamir-Kashat, Chelpek pre-identified at

appraisal, water supply schemes in another 26 villages across the three participating Oblasts

required rectification, redesign and/or overhauling. The failures in the 26 villages were mostly

associated with poor design of the water sources under the RWSSP, influenced by the DRWS’

preference for gravity sources such as springs or river drainage over wells. While the latter involve

higher energy costs, the preferred gravity systems in several cases proved unsustainable due

mainly to inadequate CDWUU capacity and source yields, and led to the failure of entire schemes.

35. Progress was further hampered by the fact that the recommendation by the Bank

team to optimize technical designs through the introduction of more efficient design

standards and materials encountered strong institutional resistance. Local engineers

accustomed to the use of technical engineering standards (SNIPs) inherited from the FSU initially

expressed very strong opposition to the adoption of alternative standards proposed as part of efforts

to address some of the identified problems. Agreement was eventually reached in 2010 after drawn

out discussions involving the Bank and a local team of technical experts on the need to adopt the

revised technical and service standards to assure the quality of rehabilitation works and enhance

the efficiency of resource use. While these measures in principle improved the technical soundness

of systems, implementation performance continued to be plagued by capacity weaknesses within

the JPMU, and finalization of scheme designs and procurement progressed very slowly. By the

MTR in early 2011, the World Bank, DFID and ADB had serious concerns on the overall viability

of the JPMU as an implementing agency.

36. The recommendation by the Bank team during the MTR, and subsequent decision by

Government to transfer project Executing Agency and Implementing Entity responsibilities

to ARIS were instrumental in getting the project back on track, and in supporting the

turnaround from the unsatisfactory performance at its lowest point in 2011. Following the

MTR, the project was restructured, in two steps, between June 2011 and November 2012. The first

restructuring, a Level 2 restructuring, was approved by Bank Management in June 2011, and it

transferred implementation responsibilities to ARIS. The transfer became effective in October

2011 after a delay in obtaining government countersignature for the ensuing amendment. This

transfer once effective, became one of the single most important factors the contributed to the

project turnaround.

37. Implementation of the second restructuring (Level 1), originally scheduled to be processed

in the fall of 2011 was impeded by several factors occurring around the same time. The first related

to the delay in obtaining government countersignature for the first restructuring. Second, there

was uncertainty at the time regarding DFID’s decision to continue co-financing the project in light

of changing internal priorities within the British Government. Following a review of its worldwide

portfolio in November 2012, DFID communicated a decision in January 2012 to partially

withdrawal its co-financing, reducing it from GBP 5.0 million to GBP 1 million. Finally, there

was a delay in completion of the project audit for the period August 2009-June 2011 corresponding

to JPMU operations before the transition to ARIS. A situation of non-compliance subsequently

emerged with the delayed publication of the project audit report for the period. Following the

Page 28: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

12

issuance by IDA of a suspension threat on May 30, 2012, the Government of the Kyrgyz Republic

submitted and acknowledged the audit report with a "disclaimer opinion" on June 20, 2012 and

committed to a repayment schedule for ineligible expenditures (due to weak supporting

documentation) identified in the report. In a letter dated August 9, 2012 the Bank accepted the

audit report and the proposed repayment schedule. With compliance restored and the suspension

threat lifted, the second restructuring could move forward and it was approved in November 2012.

38. As a result of the reduced funding, revised construction standards and unit costs, and

subsequent reduction in scope of works, targeted results were almost halved vis-à-vis what

had been envisaged at appraisal. Although implementation improved considerably after ARIS

took over the project, envisaged results were substantially reduced by the mentioned factors.

Following the inclusion of the 26 additional villages from RWSSP; it was determined that instead

of the 70 new schemes planned at appraisal, the project could only cover 35 schemes, serving

clusters of villages (in total 55 villages are served by the 35 schemes). Moreover, unit costs had

also increased significantly due to increases in the cost of construction material and civil works in

view of market factors such as inflation and real appreciation of the Kyrgyz Som, and the changes

in technical standards. Availability of resources for the water supply and sanitation components

was also affected by the withdrawal from these activities and subsequent refocus of DFID support

on promotion of improved health and hygiene practices (Component B) and capacity building and

institutional development at community and national levels (Component C). Responsibility for

implementation of the Hygiene Component (Component B) was contracted to UNICEF given its

comparative advantage and prior involvement in the sector in the Kyrgyz Republic. The

contracting process was however delayed by administrative complexities, as UN agencies require

particular procurement procedures and contractual arrangements to work on a borrower executed

project financed by the World Bank. Eventually all hurdles were overcome and the contract with

UNICEF was signed in June 2013. Once all three project components were up and running, the

team was able to upgrade the ISR implementation rating to Moderately Satisfactory.

39. The project was faced with a financing gap in late 2013, requiring a further

optimization of technical designs and reduction in investment scope. In June 2013 it became

apparent based on expenditures already committed on the first 13 rectifications and detailed design

costs estimates for the remaining 13, that the funding available for the 26 rectifications (amounting

to about US$1.6 million) would not be sufficient. It was estimated at the time that up to US$2.5

million in additional funds would be needed to meet the PDO and honor the commitments made

to the villages. Government requested the Bank to consider providing additional financing to cover

the financing gap. Given the project’s performance history and status however, Bank Management

rejected the request. In efforts to address the financing gap, the task team initiated a comprehensive

technical design and cost review process with ARIS engineers. This resulted in optimized

investment scope and designs and reduced cost estimates. The process involved, inter alia, a

substantial investment scope reduction in the village of Chelpek, where it was decided that a

US$1.5 million complement of service rehabilitations and expansions be deferred. Opportunities

were also identified to reallocate proceeds from "consulting services" to "works", and to mobilize

an additional US$500,000 in GOKR co-financing. These measures were agreed with GOKR and

ARIS during a Bank implementation support mission in November 2013 and approved through a

third restructuring (level 2). In April 2014, with the financing problems resolved and the

Page 29: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

13

perspective that the project would have achieved its objective by October 2014, the ISR PDO

rating was also upgraded to Moderately Satisfactory.

40. Civil Society opposition initially detracted progress, but effective partnerships were

eventually formed to mutually benefit the project. The highlighted technical concerns

stemming from the RWSSP translated into a number of social concerns the resolution of which

constituted a major problem, especially earlier during implementation. Along with the ADB-

funded CBISSP, the RWSSP2 became the focus of civil society criticism and polemic as a result

of the liabilities inherited from RWSSP and subsequent complaints from some beneficiary

communities. Key issues mainly concerned the failed rehabilitation works in the three problem

sub-projects, with accusations including, inter alia, the alleged use of contaminated pipes – which

was later proved to be unfounded. Concerned communities approached civil society after

apparently failing to receive satisfactory responses to complaints filed with the JPMU. It is worth

noting that similar complaints were concurrently being raised with the ADB financed project in

the Southern Oblasts. Local civil society formed coalitions with international counterparts such

as the so called World Bank Watch and ADB Watch groups and brought these issues to the

attention of Bank Management in Washington during the Spring meetings of 2009, as well as to

ADB management in Manila. Following these actions, affected project sites were visited by the

Bank’s Executive Director and a platform for heightened dialogue between key stakeholders

including the GoKR, the Bank and beneficiaries represented by civil society established to ensure

that issues raised were resolved in a satisfactory manner. Civil society representatives were

incorporated as important partners in project implementation and an open communication channel

opened with them, enhancing transparency and allowing for knowledge exchange and greater

citizen input in critical decisions affecting them. Civil society representatives were also included

in project activities such as study tours organized for stakeholders, and as observers in contract

evaluation committees.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

41. M&E Design. While project M&E design at approval had sound elements in several

respects, there were shortcomings. Project M&E arrangements built on practices developed under

the previous RWSSP. In addition to the regular M&E to be conducted as part of regular monitoring

of progress during implementation, M&E design envisaged the application of tools such as

Baseline Surveys and Impact Evaluations using a combination of interviews and participatory

techniques. Primary responsibility for M&E lay with the JPMU, which was also supposed to work

on the ADB financed project. Arrangements also included a role for involvement of CDWUUs at

the Oblast level. The capacity of the JPMU for M&E was assessed on the RWSSP experience,

where the team had included support from the experienced Project Management Consultant (PMC)

team. In fact, although the JPMU had inherited some local M&E staff from the PMC, its capacity

was in general far short of the PMC’s.

42. Shortcomings with regard to M&E were mainly linked to design of the Results Framework

presented in the PAD at approval, and design of the Impact Evaluation. In regard to the Results

Framework, issues included: (i) the absence of baseline data for several indicators, including PDO

indicators; and (ii) the appropriateness of some indicators, for instance in terms of ease of data

collection. Major changes to the Results Framework, including to PDO and intermediate outcome

Page 30: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

14

indicators and targets, were made as part of restructuring in order to better capture project results

and achievements. A shortcoming in regard to design of the Impact Evaluation study was the

failure to establish a control group from the start. Control groups were in fact introduced at the

end, which precluded establishment of reliable baseline data.

43. M&E Implementation and Utilization. Although M&E like other aspects of

implementation was initially affected by the overall performance issues faced during the earlier

part of the project, the function benefitted from the overall capacity strengthening with the transfer

of implementation responsibility to ARIS. Streamlining of key elements of M&E design such as

the Results Framework, through restructuring, were also instrumental in improving M&E during

implementation, and arrangements were later implemented as designed. The Bank team, working

closely with government counterparts, actively monitored overall implementation progress based

on achieved results or the lack thereof, identifying issues affecting the project and providing

recommendations to address issues and to steer the project towards its intended objectives.

Implementation Status and Results (ISR) reports tracked the indicators in the project’s Results

Framework and project supervision documents, including mission aide memoires reported

candidly on results. Data collected through the baseline study carried out during project

preparation informed the refinement of the project’s M&E framework in line with realistic targets,

allowing for better monitoring of project results and achievements. The Impact Evaluation Study

conducted between August and September 2014 also provided a detailed review of project results

and achievements, and highlighted important findings on management of water supply, sanitation,

and hygiene at the community and household levels in participating areas. While the Impact

Evaluation study was originally envisaged to be carried out around mid-term to be able to influence

implementation, information will still be useful for design of future interventions in the sector.

44. The project supported the development of two MIS databases: (i) for water supply and

sanitation sector performance data collection and management within DRWS; and (ii) for

collection and management of data on parasitic diseases and water quality by the Department for

Disease Prevention and Sanitary and Epidemiological Supervision. Development and utilization

of both systems represented important capacity building and institutional strengthening efforts for

the respective departments.

2.4 Safeguard and Fiduciary Compliance

45. The project triggered two Safeguard policies at appraisal; Environmental Assessment (OP

4.10) and International Waters (OP 7.50). It was classified as Category B for Environmental

Assessment given the nature of envisaged works which were not expected to have any significant

or irreversible environmental impacts. Environmental Assessment was implemented in accordance

with required procedures and was rated Satisfactory throughout implementation. Some sub-project

activities were expected to take place on trans-boundary waterways as defined in OP 7.50, however

an exception to the policy to notify riparians of the project was granted by Bank management since

activities were not expected to modify the course of waterways, nor significantly increase the

volume of water abstraction.

46. It was assessed at appraisal that the project would not trigger the Involuntary Resettlement

Policy (OP/BP4.12) as it was expected to deal exclusively with rehabilitation or upgrading of

Page 31: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

15

existing infrastructure and installations on existing premises or public rights of way. The task team

later determined that the policy should be triggered and introduced it as part of the restructuring

given envisaged potential for land acquisition, temporary encroachment, damage of assets or

restrictions on access during implementation. A Resettlement Policy Framework was prepared and

disclosed together with an updated ISDS on July 16, 2012, to address any issues relating to

permanent or temporary involuntary resettlement associated with project activities. 118 Project

Affected Persons (PAPs) in ten villages were identified in accordance with the policy and

compensation, mainly affected by temporary restrictions to access or loss of trees and crops. All

PAPs were fully paid by the project closing date. It is worth noting that compensation costs were

financed by IDA on an exceptional basis. The amount of compensation payments to PAPs

amounted to KGS 1 979 254 (or about US$ 50 000).

Fiduciary Compliance

47. Financial Management Compliance. The ICR rates Financial Management compliance

under the project Moderately Satisfactory overall, considering both project preparation and

implementation aspects throughout the project’s life. During preparation the Bank conducted an

assessment of the JPMU FM capacity and reviewed accounting, financial reporting, auditing,

internal controls, budgeting, and staff capacity. Then the JPMU was already implementing the

ADB’s CBSSIP-S and was to become responsible for implementation of the RWSSP2. The FM

system was found to be unsatisfactory because the JPMU utilized an obsolete version of 1-C

accounting software with insufficient capacity to generate Interim Financial Reports (IFRs) in a

format satisfactory to the Bank. Internal control policies and procedures were also found to be

weak, and a time bound action plan was included to strengthen FM by negotiations through, inter-

alia, update of the accounting software, addressing internal control weaknesses, and refund of

ineligible expenses incurred during the course of the first project. The overall FM risk for the

project before mitigation measures was assessed as Substantial and Moderate after mitigation.

48. After project effectiveness, the fiduciary capacity of the JPMU remained low and concerns

were raised by the Bank in regard to its overall performance. ADB had similar concerns. Problems

were specifically flagged in respect to aspects such as record-keeping and accounting, including

occurrence of missing primary documents, un-reconciled balances, deleted records from the

accounting software, and mix-up of payments between different sources of funds. A situation of

non-compliance emerged with the delayed publication of the project audit report for the period

August 2009 to June 2011 corresponding to project operations before the transfer of

implementation responsibility from the JPMU to ARIS. After issuance by IDA of a suspension

threat in May 2012, the Audit report was issued in June 2012. Prior to approval of the Level One

restructuring in 2012, Government acknowledged the audit report and committed to a repayment

schedule for ineligible expenditures due to weak supporting documentation identified in the report.

Financial Management under ARIS was generally satisfactory through the remainder of the project

implementation period, with minor shortcomings. The final ISR rated the project’s FM

performance Satisfactory; however the ICR takes into consideration the experience throughout the

project’s life.

49. Procurement Compliance: The ICR rates implementation of the Procurement function

under the project Moderately Satisfactory, based on its overall compliance with Bank and country

Page 32: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

16

procedures during project preparation and implementation, with moderate shortcomings. A

Procurement Capacity Assessment for the JPMU was conducted as part of preparation, and the

overall procurement risk in regard to the project was rated Moderate after mitigation. After transfer

of implementation responsibility to ARIS, procurement was generally conducted in accordance

with the Bank’s Guidelines for Procurement under IBRD Loans and IDA Credits dated May 2004,

and revised October 2006, and specific provisions stipulated in the DCA, Grant Agreements, and

the Procurement Act. In order to facilitate the contracting of UNICEF by ARIS for implementation

of the Hygiene and Sanitation Promotion activities, World Bank Guidelines for Selection and

Employment of Consultants dated January 2011 were applied after signing the Level-1

restructuring Amendment to Financing Agreement. This change had no implications on other

procurements, and was cleared by the Bank’s Regional Procurement Manager (RPM).

2.5 Post-completion Operation/Next Phase

50. Sustainable post-completion operation of water supply and sanitation facilities financed

through the project will be driven by community level (CDWUU) capacity to manage service

delivery, an outcome linked to the availability of adequate human and financial capacity and

resources for effective operations and maintenance of facilities. While there are improvements in

overall sector capacity at all levels as a result of institutional strengthening and capacity building

activities under the project and its predecessor, there is need for further institutional strengthening

and capacity building to improve or maintain capacity of the CDWUUs to deliver water supply

services in an efficient and sustainable manner. This will require sustained effective support to the

service providers, requiring commitment and engagement at multiple sector levels.

51. It is recommended that post completion action plans to maintain progress beyond the

project be developed by Government and supported through adequate budget and other resources

if outcomes are to be sustained. In addition, the local governments or Ayl Okmotus will need to

be able to continue to plan, budget, and monitor system operation at the local level. As the

adequacy of budget provision to the sector in the Kyrgyz Republic remains in question, the risk to

development outcomes remains substantial.

52. Results on the ground in terms of the effectiveness of different CDWUUs in managing the

delivery of rural water supply services vary. There have been some notable successes and advances

towards cost recovery in some cases. A few CDWUUs, such as Korumdu, Jele-Dobo and Baltabay

have fully installed meters and are collecting tariffs based on volumetric consumption. An average

cost recovery level of 70 percent has been achieved from participating CDWUUs. However, less

than half (only 15 out of the 37) are collecting sufficient revenues to cover their O&M costs. Fee

collection is mainly seasonal, largely based on income streams such as tourist and harvest seasons

in the rural areas. The financial sustainability of many of the systems is therefore at risk. To

enhance sustainability at the local level, the government, with the support of local parliament

representatives, should continue to advocate for payments of services with the beneficiaries.

53. Institutional structures also need to be further supported to provide the enabling

environment for effective service delivery for the beneficiary areas and the rest of the sector. The

assets of water supply systems have been handed over to the municipal ownership of Ayl Okmotus,

Page 33: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

17

who have signed Service Agreements with their respective CDWUUs. Performance monitoring in

respect to these Agreements should be conducted with the support of DDWS.

54. Opportunity for a Follow-On RWSS Project: The GoKR has expressed interest in a

follow on operation to scale up the outcomes of the RWSSP2. The Government sent a formal

request to the Bank on July 25, 2014 to this end. The Bank has advised that consideration of

Government’s request would require clarification of the rationale for the intervention and

agreement with GOKR on a comprehensive re-prioritization, scope, and time-frame for IDA

support to the sector under the Country Partnership Strategy. A follow-up project would build on

the lessons and successes of RWSSP2 to achieve a sustainable transformational impact on the

sector while supporting GOKR’s strategy and reform objectives.

55. With a US$ 1 million grant received from the Russian Federation, UNICEF will scale up

its WASH in Schools program using the methodology applied under the RWSSP2. To implement

this project, UNICEF will work in partnership with ARIS. The project will have a strengthened

focus on focus on hand-washing among children and improving civic engagement in the WASH

sector. UNICEF will use its core funds and a US$1 million grant received from the Russian

Federation.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

Objectives

56. Rating. High. The PDO adequately responded to diagnosed sector challenges and

priorities for rural water supply and sanitation and remains highly relevant to the Kyrgyz

Republic’s development priorities and the Bank’s Strategy for the country. The GoKR articulated

its development priorities of ensuring the delivery of high quality water supply services through

inter-alia, an Order of the President, No. 194, dated 27 September 2013, as well as in the National

Strategy for Sustainable Development of the Kyrgyz Republic 2013-2017, dated January 21, 2013,

approved by the Decree of the President of the Kyrgyz Republic No.11. It is also aligned with

the new Strategy for the Water Supply and Sanitation Sector – the State Program for Development

of Water Supply and Wastewater Disposal in Settlements of the Kyrgyz Republic for the 2014-2024

period (hereinafter referred to as the State Program), which was developed with RWSSP2 support.

The State Program aims at improving the quality of water supply and wastewater disposal services,

addressing the main challenges to service delivery, and identifying directions for further

strengthening the sector’s institutional framework.

57. The PDO is also highly relevant to the Bank’s priorities and development objectives. It

remains aligned with the Bank’s Country Partnership Strategy (CPS) for FY14-17 with Kyrgyz

Republic, approved by the Bank’s Board of Directors on June 24, 2013, which focus on three broad

areas of engagement: (a) more efficient public administration and public services-especially those

relating to lowering poverty, improving accountability, enhancing human capital, and reducing

ethnic, gender, and social disparities; (b) an improved business environment and investment

Page 34: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

18

climate; and (c) better management of scarce natural resources and physical infrastructure, while

at the same time taking into account climate change, environmental sustainability, and regional

considerations, which are deemed crucial for improved poverty outcomes, in particular for the

almost two-thirds of the population that live in isolated rural and mountainous areas. It is also

aligned with achieving the Bank’s twin goals of reducing extreme poverty and increasing shared

prosperity.

Design and Implementation

58. Rating. Substantial. The relevance of the project design and implementation are assessed

as Substantial from a number of perspectives. The PDO and other elements of design reflected

proper diagnosis of critical development priorities for Kyrgyz Republic, which remain high on the

development agenda. Revision of the PDO to add the institutional strengthening objective is

further evidence of the project’s efforts to maintain relevance in light of prevailing circumstances.

The project design was generally technically sound, and the components well-structured for a WSS

operation of its nature. It duly considered key lessons from the RWSSP and other rural water

supply and sanitation projects. While there were a few design shortcomings, highlighted earlier in

the ICR, they were recognized during implementation and the project design’s relevance to the

context sustained through the adjustments made as part of restructuring, which aligned the PDO

and targets with changes in priorities and availability of resources.

3.2 Achievement of Project Development Objectives

59. Rating: Moderately Satisfactory. The ICR assesses efficacy with respect to project

outcomes as Substantial, based on the aggregated achievement of the development objectives and

outcomes. This section assesses the extent to which the project achieved each objective as well as

its key outcomes, highlighting key outputs that contributed to the outcomes. Details on the outputs

under each project component are presented in Annex 2. In accordance with the Bank’s ICR

guidelines for projects whose objectives have been formally revised, the analysis of efficacy with

respect to achievement of project objectives involved an assessment of performance against

original and revised targets where applicable, weighted by the amount disbursed at the time the

targets were revised. At the time of PDO restructuring in November 2012, grant disbursements

were at 53.1 percent. Assessment of efficacy by individual objective is presented below and

summarized in Table 3.1.

Outcome 1 - Improved access to potable water supply for participating communities,

measured by the increase in the number of residents benefitting from regular availability of

safe potable water.

60. The project achieved its objective of increasing access to potable water supply to

participating rural communities in Talas, Naryn, and Issyk Kul Oblasts in a moderately

satisfactory9 manner on balance. It was able to provide improved access to water supply of good

quality to about 83,000 people in 55 villages in participating communities, substantially exceeding

9 Table 3.1 presents the analysis for efficacy taking into consideration the original and revised targets.

Page 35: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

19

the revised target of covering 60,00010 people established when the project was restructured in

2012 and substantially achieving the original target of 100,000 (83 percent). About 86 percent of

households in the participating areas now have access to potable water, and the project provided

more than 3900 households with water supply connections on their premises. Facilities financed

through the project were also able to substantially improve the quality of water supplied to people

with 90 percent of tests in the service area of rehabilitated schemes meeting national standards for

drinking water, representing an improvement of at least 10 percent. Improved access to potable

water supply services is expected to bestow benefits on many levels including environmental,

social, and economic benefits. The Impact Evaluation study carried out at the end of the project

confirmed greater convenience in accessing water overall. As a result of the project over 70 percent

of households in the service areas reported distances to improved water sources at 500/1000 meters

or less. The study also revealed significant improvements in overall satisfaction among project

beneficiaries on key aspects of service delivery such as the quantity, quality, and pressure of water

supplied.

61. Key Outputs contributing to improvements in access to potable water supply and

associated outcomes. The project, through the Water Supply Infrastructure and Equipment

Component (Component 1) financed the repair, rehabilitation, and replacement or upgrading of 37

rural water supply systems covering a total of 55 villages. A total of 226 water points were

constructed or rehabilitated and 3902 new household connections were installed through the

project. Outputs directly contributing to the improvements in access, quality and reliability of

water supply specifically involved the reconstruction or rehabilitation of production facilities and

distribution networks, as well as improvement of management efficiency and likelihood of

sustainable operation and maintenance through technical assistance and training to improve

CDWUU technical capacity. Sixty maintenance equipment units were provided to CDWUUs

and/or their associations to maintain the water supply systems in their jurisdictions. (Further details

are provided in Annex 2).

Outcome 2. Improved hygiene and sanitation and water related practices at individual,

family and institutional levels

62. The project fully achieved its objective of improving hygiene and sanitation and water

related practices at individual, family, and individual levels. A total of over 9000 people,

including school children, were provided with access to improved sanitation facilities, almost

doubling the 5000 people originally targeted. There is also evidence that the project contributed

to positive health outcomes in the participating communities. While a range of factors, such as

access to healthcare and other services, can affect health outcomes, it may be reasonably concluded

that the improvements in hygiene and sanitation and water related practices facilitated through the

project contributed to the decreased incidence of waterborne diseases such as acute intestinal

infections, viral hepatitis, and helminthic (worm) invasion in participating communities by an

average of 62.5 percent, exceeding the targeted 60 percent reduction. According to a

comprehensive assessment carried out by the Sanitary Epidemiology Surveillance (SES) Unit in

10 The original number of beneficiaries expected for the project was 100,000 people. While included as an indicator

in the PAD text and presented in the economic analysis, it was not included in the Results Framework.

Page 36: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

20

the Ministry of Health, acute intestinal infections and viral hepatitis fell by 55 and 54 percent,

respectively, while helminthic infections fell by 75 percent in the project areas. This assessment

was conducted through pre- and post-intervention tests of fecal and blood samples from school

children by SES laboratory staff working with village health centers. Where infection was found,

children and their families were treated, enhancing the health outcomes of the project.

63. There were also significant improvements in hygiene related practices such as hand-

washing with soap and management of school toilet facilities. At the end of the project an average

of almost 73 percent of people in the project areas reported using soap for hand-washing at critical

times such as after using the toilet compared to only 60 percent before the intervention. There were

variations in individual outcomes among villages and Oblasts, with Issyk-Kul Oblast registering

the highest levels (up to 91 percent) hand-washing post-project compared with the lowest, Talas

(49 percent). A UNICEF study also indicated that school expenditure on water supply, sanitation,

and hygiene was only a fraction of what was required to fulfill national standards. These findings,

as well as the variation in results among Oblasts indicate that although achievements are

commendable, there is a need for sustained promotion of hygiene and sanitation related behavior

change and for actual uptake and usage of facilities.

64. Key Outputs contributing to improvements in hygiene, sanitation, and water related

practices and related outcomes. The project, mainly through the Sanitation and Hygiene

Promotion Program (Component B) financed by DFID and implemented by UNICEF, supported

village level promotion of healthy hygiene and sanitation practices. Similar promotions were

conducted at schools in the three Oblasts, where the project, through Component A financed the

refurbishment or construction of demonstration facilities at a total of 18 schools in 18 villages

(details are provided in Annex 2). Representatives of schools, healthcare centers, and communities

in all the 55 villages were engaged in sanitation and hygiene promotion campaigns. Two school

teachers from each village participated in an Oblast level training session based on the Water

Hygiene and Sanitation Guidelines for Teachers conducted by UNICEF, and used the Participatory

Hygiene and Sanitation Transformation (PHAST)-based materials developed to work with schools

and communities in their respective oblasts.

Outcome 3. Strengthened Institutional Framework and Capacity of Rural Drinking Water

Supply Sector

65. The project partially achieved its objective of strengthening the institutional

framework and capacity of the drinking water supply sector in Kyrgyz Republic at the

national, local government, and community levels. Achievement of this objective is assessed as

moderately satisfactory on balance. Outcomes at the national level were linked to strengthened

sector policy and planning capacity for sustainable development of water supply and sanitation

sector, while community level interventions sought to strengthen operational capacity to ensure

sustainability. Achievement of this objective is however deemed partial given the large variation

in outcomes at different levels and among communities. Measurement of performance in respect

to this outcome at the community level was mainly linked to financial sustainability indicators at

the operational level, specifically: (i) the level of operation and maintenance (O&M) cost recovery

in utilities targeted by the project; and (ii) the number of CDWUUs with sufficient revenues (from

collection of fees and other sources) to cover O&M. All thirty eight participating CDWUUs

Page 37: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

21

demonstrated their commitment to operation and maintenance of their water supply systems by

signing Service Agreements with their respective local governments. There are large variations in

performance at individual CDWUU levels. In some CDWUUs, such as Korumdu, Jele-Dobo and

Baltabay, 100% of individual water connections had installed meters by the end of the project. All

CDWUUs, with the exception of two, Chelpek and Tort Kul in Issyk Kul Oblast, and Ak Kuduk

in Naryn Oblast, had set tariffs and started collecting fees. Although an average level of cost

recovery of 70 percent was achieved, less than half (15) CDWUUs were collecting sufficient

revenues to cover O&M costs. Although there have been some successes and improvements in

cost recovery in some cases, there is still need for sustained support to the CDWUUs.

66. The project was able to support several other activities that are expected to contribute to

improved planning and management capacity of the water supply and wastewater sector. In

addition to training for different staff for instance, the development of the new Strategy for the

Water Supply and Sanitation Sector – the State Program for Development of Water Supply and

Wastewater Disposal in Settlements of the Kyrgyz Republic for the 2014-2024 period is expected

to provide strategic direction to the sector that will enhance sector planning capacity. Similarly,

the development of Management Information System Databases for both water supply

performance and on water quality and the occurrence of parasitic diseases are expected to

contribute to improved management, including monitoring and evaluation of these sectors. While

the transfer of implementation responsibility to ARIS, a non-governmental organization, was a

pragmatic solution to the chronic challenges the project faced and played an important role in

improving overall implementation as earlier discussed, it somewhat denied Government

institutions responsible for rural water supply the full benefit of sustainable institutional capacity

building for design and implementation of investment projects/sub-projects.

67. Key Outputs contributing to Institutional Strengthening Outcomes. Project outputs

included a series of activities focused on strengthening sector institutions at all levels to improve

rural water supply and sanitation management systems and service delivery. Activities specifically

targeted staff of CDWUUs, Local Self-Governments, and DRWS to strengthen capacity in various

areas, such as technical aspects for improved operations and maintenance, and financial

management, particularly in operation of a billing system. A total of 40 DRWS personnel were

trained in management and planning for rural water supply and sanitation, and 196 CDWUUs

trained in fee collection and management of schemes. Other notable outputs at the national level

included:

a. Development of a Sector Strategy for Water Supply and Sanitation. The Strategy was

before the country’s Parliament’s for consideration at the time of the ICR review.

b. Review of legislation in the field of water supply and water disposal. Review and update

of the existing legislation regulating the sector in order to support implementation of the

above State Sector Development Program was conducted with engagement of key

stakeholders at national, local government, and community levels.

c. Creation of Management Information System (MIS) database with GIS interface. Two MIS databases were developed for (i) water supply and sanitation sector performance

data collection and management within DRWS; and (ii) for collection and management of

data on parasitic diseases and water quality by the Department for Disease Prevention and

Sanitary and Epidemiological Supervision.

Page 38: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

22

d. Development of a financial model for water supply and water disposal development.

The project hired an international consultant to design the financial model for the water

supply and sanitation sector and delivered training for DWSS staff on how to use the model.

e. Review technical norms and standards. The project financed the review and

recommendations on optimization of technical standards for water supply and sanitation,

and technical advisory support of chlorination in disinfection of potable water

f. Capacity building for LSG bodies and CDWUUs in managing and maintaining water

supply systems to provide population with high quality potable water supply to population;

g. Introduction and adoption of an effective billing system at the CDWUU level. To

improve CDWUU operations, including tariff collection, 80 sets of office equipment

(computer, printer, stabilizer) were provided through the project, and staff trained in

operating the billing program.

Table 3.1 Summary of Analysis of PDO11

Objective Performance

against original

PDO/Targets

(53% of

disbursements)

Performance

against revised

PDO/Targets (47%

of disbursements)

Overall performance

weighted by

disbursement

Outcome 1. People

with improved

access to potable

water supply for

participating

communities

Moderately

Satisfactory

(4)

Satisfactory

(5)

Outcome 2.

Improved hygiene,

sanitation and

water related

practices at

individual, family

and institutional

levels

Satisfactory

(5)

Satisfactory

(5)

Outcome 3.

Strengthened

institutional

framework and

capacity of rural

drinking water

supply sector

Not applicable Moderately

Satisfactory

(4)

11 In accordance with IEG guidelines, the project is rated against both sets of objectives separately, for the entire

duration of the project – not just the period for which each of the objectives was in effect.

Page 39: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

23

Overall rating Moderately

Satisfactory

(4.5)

Moderately

Satisfactory

1/3(5+5+4)=4.6

Moderately Satisfactory

(0.53*4.5)+(0.47*4.6)=4.6

Weighted ratings: Highly Satisfactory - 6; Satisfactory – 5; Moderately Satisfactory – 4; Moderately

Unsatisfactory – 3; Unsatisfactory – 2; Highly Unsatisfactory – 1

3.3 Efficiency

68. Rating: Moderate. Efficiency of the project is rated Moderate based on the results of the

economic analysis conducted as part of the ICR, as well as other pertinent factors such as per capita

investment costs and the implementation time.

69. Economic Analysis. The project’s viability is based on the Economic Rate of Return

(ERR) and Net Present Value (NPV) of the measurable, incremental benefits and total project costs

using actual investment expenditures as well as annual O&M costs through the asset life. Three

main sets of benefit streams were considered: (a) decreases in the time spent collecting water; (b)

welfare gains at household level associated with reduced expenditure on water storage tanks as

well as need for in-house treatment (i.e. boiling water); and (c) reduced incidence of water related

diseases such as infectious hepatitis and acute enteric infections as a result of improved access to

high quality water and decline in the reliability on standing water sources. As with all economic

analyses, the costs are perfectly observed while the benefits are not. Detailed analysis, including

the assumptions for the analysis are provided in Annex 3.

Table 3.2: Results of the Economic Analysis

Overall Project Economic Viability

ICR (at completion) PAD (at appraisal)

ERR NPV (USD) ERR NPV (US$)

15% 1,890,648 32% 12.9million

70. The estimated ERR at ICR was 15% and the NPV was US$$1,890,648, assuming a social

discount rate of 12% and 26 years of asset life, including 6 years of project implementation, with

corresponding benefits to be realized starting in 2015. The analysis reveals that actual economic

indicators (ERRs) are much lower than those projected during appraisal. Given the conservative

assumptions used (low skill wages, low number of daily trips), and the fact that no benefits could

be accounted for part of the activities of component B, and all of the activities of component C and

D, the project’s NPV and ERR are in fact expected to be even higher than those estimated.

Additionally, the project has relatively low per capita investment costs of about US$ 163 per capita,

which are consistent with average unit costs from the region12. This is considered to be reasonable

given the low population density of the project area. Based on these results, combined with the

12 Data from similar projects supported by Oxfam had average unit costs of US$ 157 per capita.

Page 40: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

24

need for an additional 17 months to complete implementation of investments, the efficiency of the

project is considered to be Moderate compared with the ex-ante analysis conducted at appraisal.

3.4 Justification of Overall Outcome Rating

71. The project’s overall outcome is rated Moderately Satisfactory considering the

aggregate of its High relevance, Substantial efficacy in achieving the PDO, and Moderate

efficiency. The project is still highly relevant and provision of potable water supply and sanitation

services remain high priorities for the GoKR. While the project has resulted in improved access to

potable water supply to about 83,000 people, improved hygiene, sanitation and water related

practices in project areas, and strengthened institutions responsible for water supply and sanitation

in Kyrgyz Republic, the risks to development outcomes remain substantial.

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

72. While there was no formal poverty reduction assessment conducted at any stage of the

project, it can be reasonably concluded that in providing access to safe water and improved

sanitation services to people in rural communities, most of whom are poor, the project improved

the well-being of these people thus contributing to overall poverty reduction. Similarly impacts on

gender are envisaged to have been positive given that women in the Kyrgyz Republic, like many

other countries, are usually responsible for managing water collection and hygiene related issues

at the household and community levels. Women are an integral part of Water Committees

established through the project, and 65 percent of CDWUUs have women occupying at least one

of the three most senior positions on their committees. Inclusion of women has not only enabled

greater gender balance, but also adds value in knowledge and management of services since

women are primarily responsible for managing WSS at the household and in often at community

levels.

(b) Institutional Change/ Strengthening

73. The PDO aimed to strengthen the institutional framework and capacity for managing rural

water supply and sanitation services in Kyrgyz Republic in a sustainable manner. Interventions

included capacity building and technical assistance targeting institutions at the national, local

government, as well as community levels responsible for these services. The project has registered

achievements in terms of capacity built through training of national and local government staff in

subjects needed to sustainably manage water and sanitation services; and provision of equipment

and facilities to strengthen sector institutions. Key achievements in terms of institutional

strengthening are summarized under the discussion on Institutional Strengthening outcomes in

Section 3. 2 above.

(c) Other Unintended Outcomes and Impacts (positive or negative)

There were no significant unintended outcomes from the project.

Page 41: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

25

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

74. A Beneficiary Survey was not conducted for the project. However an Impact Assessment

was carried out by the Government with support from IDA. Key findings of the Impact

Assessment are presented in Annex 5.

4. Assessment of Risk to Development Outcome

75. Rating: Substantial. The maintenance and sustainability of the project’s development

outcomes will depend on several factors. The project’s risk to development outcome is rated

“Substantial”, based on the aggregate of technical, financial, institutional and social

considerations that could affect the sustainability of outcomes achieved under different project

components.

76. Financial and Institutional Risks: On the financial front there is a substantial risk that

not all CDWUUs will be able to collect sufficient revenues to cover the costs of operating and

maintaining the water supply systems, and that limited national budget allocations to the sector

would not be able to adequately cover budget deficits. Similar risks exist with regard to sustained

financial support for adequate maintenance of school sanitation facilities. Actual O&M costs for

WASH facilities based on data obtained from participating rural schools and private schools in

Bishkek revealed that the rural schools were spending substantially less than is needed to properly

maintain the facilities. In the pilot schools of Talas Oblast for instance, KGS 27.5 per student per

year was spent for operation and maintenance of WASH infrastructure on average, compared to

KGS 196.6 from one the private schools in Bishkek. In contrast, according to the Russian

Federation’s sanitary standards, average annual expenses for household goods, disinfectants and

health goods as converted to KGS, were KGS 287 per student per year. Mitigation of these risks

would require a combination of political will and institutional factors, primarily involving central

and local governments, as well as school administrators, Education and Health Ministries, as

applicable, maintaining policies for sound management, provision of continued support and

allocation of adequate resources for system operation and maintenance, including cost-recovery in

the medium- to long-term supported by adequate budgetary provisions for covering deficits in the

interim. While the project has helped strengthen the enabling environment by strengthening sector

policy and capacity building for DDWS, Ayil Okmotus and CDWUUs, and there has been progress

by many CDWUUs to collect revenues, there is still need for sustained support to the sector at all

levels.

77. Social and Attitudinal Risks: Risks from a social and attitudinal perspective are

considered Moderate. While there is a strong awareness, support, and appreciation of project

achievements by most project beneficiaries, maintaining the development outcomes achieved by

the project will require project beneficiaries to remain motivated to continue operating and

maintaining the facilities in a sustainable manner, including paying needed contributions towards

cost recovery or user charges as applicable. The provision of hygiene and sanitation education and

sensitization to beneficiaries was a first step in addressing this risk by creating a greater awareness

of the benefits of using improved sanitation facilities and services. More should be done to

maintain the engagement with beneficiary communities on these issues, including continued

sensitization of school children and adults on the proper use and maintenance of toilet facilities.

Page 42: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

26

This will require a joint effort by relevant stakeholders, including school administration officials,

parents, and students.

78. Technical Risk: Risks from a technical perspective are considered moderate. While the

quality of construction of investments in most sub-projects was adequate and technologies used

more efficient, particularly after revision of norms, there is evidence of some sub-projects

experiencing issues linked in part to the fact that envisaged works were not fully completed due to

resource limitations. Additionally, technical risks relate to inadequate capacity for proper operation

and maintenance of facilities in some CDWUUs, and the availability of engineers and technicians

that are adequately trained and fully understand the application of international technical standards.

The need for chlorination of water supplies for instance is an issue for much of the FSU, due to

concerns about potential over-dosing. While the new sector strategy outlines the need for

chlorination of water supplies, there is need for continued advocacy on its benefits in regard to

water quality, and CDWUUs must be trained in proper chlorine handling and dosing. Technical

sustainability of all facilities is thus closely dependent on appropriate management and

maintenance systems remaining in place, supported by the enforcement of policies to ensure

continued availability of resources, and adequate capacity and availability of tools and spare parts.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

79. Rating: Moderately Unsatisfactory. Bank performance in ensuring quality at entry is

rated Moderately Unsatisfactory based on its role in facilitating and supporting design, preparation,

and appraisal of the project, with some significant shortcomings. Project design and preparation

activities were consistent with the Bank’s fiduciary requirements, and appraisal took into

consideration pertinent technical, financial, and economic aspects of proposed activities. Design

duly considered lessons from RWSSP and incorporated implementation measures to address some

of the challenges and outstanding issues from that project. As part of due diligence conducted

during preparation the team identified key risks to project implementation and outcomes and

mitigation measures to address them. Shortcomings mainly relate to the Bank’s judgment in

accepting at negotiations to entrust project implementation on the JPMU, which was assessed to

have limited capacity and experience with Bank projects, as well as inadequate design of project

M&E arrangements.

(b) Quality of Supervision

80. Rating: Satisfactory. The ICR rates Bank performance for quality of supervision as

having been satisfactory, taking account of the extent to which the Bank managed its fiduciary

and technical support responsibilities during implementation, steering the project back on track

after a very difficult start, allowing it to substantially achieve its intended objectives. Project

implementation was closely supervised by the Bank, with adequate resources allocated in terms of

budget and staff with an appropriate skill mix for supervision throughout the project

implementation period. Formal supervision missions were carried out at least twice a year by the

Page 43: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

27

team and the locally based co-TTL followed implementation on a daily basis. Visits to

participating communities were routinely carried out implementation issues were described

candidly in aide-memoires and ISRs, and sufficient attention paid to safeguards and fiduciary

aspects as needed. To further strengthen implementation support to the project in view of the

challenges it faced, the Bank assigned a Lead Water and Sanitation Specialist based in Washington

as Task Team Leader (TTL), and stationed another seasoned co-TTL in Bishkek to provide support

on the ground to address technical issues, as well as manage the day to day dialogue on concerns

encountered by the project. The Bank exercised sound judgment in its decision to restructure the

project in light of the serious performance issues. In recognition of the positive turn-around in

project performance and outcomes, the GOKR even awarded the Bank co-TTL a rare medal of

“Honorable Builder of the Kyrgyz Republic” in early 2013. Bank Management should be

commended for understanding the importance of remaining committed to the project/sector

through the very difficult 2010-2013 period, were multiple intractable problems accumulated

against it. Bank patience, and the commitment of an unusual level of supervision resources are

among the factors that enabled an improbable project turnaround and gradual rebuild of sector

capacities.

(c) Justification of Rating for Overall Bank Performance

81. Rating: Moderately Satisfactory. Overall Bank performance is rated Satisfactory on the

basis of the Bank’s performance during preparation and implementation, and its contribution as

discussed above to the Moderately Unsatisfactory project quality at entry and Satisfactory quality

of supervision, ultimately resulting in the overall Moderately Satisfactory project outcome.

5.2 Borrower Performance

(a) Government Performance

Rating: Moderately Unsatisfactory

82. Government performance is assessed as Moderately Unsatisfactory on balance on the basis

of the overall performance of the national government, including the executing and implementing

agencies, and of the participating local governments and the CDWUUs over the project lifetime.

The ICR would like to emphasize that while some individual entities did demonstrate good

performance at different times, this rating assesses the aggregate of performance of government

over the entire implementation period, including in light of issues the project faced at critical times.

83. National Government. The ICR assesses the performance of the Ministry of Finance

(MoF) as the Borrower, and the line Ministries/Government Agencies in charge of rural water

supply and sanitation during project preparation and implementation, as implementers as having

been Satisfactory and Moderately Unsatisfactory, respectively, on balance, although there were

variations in performance of the different agencies and at different times during implementation.

Government commitment to the project was considered to have been adequate at the time of entry,

and part of the justification for processing the project as a “Repeater” was confirmation of the

Borrower’s interest in scaling up the existing project activities in this manner. During

implementation however, Government commitment to the project was affected by the political

Page 44: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

28

instability in the country, and repeated changes of line Ministries/Government Agencies

responsible for the project.

84. The DRWS was in fact transferred to different Ministries four times between 2008 and

2012, initially being transferred from the Ministry of Agriculture to the National Agency for Local

Self Governance (NALSG) as part of efforts by government to ensure closer links between the

sector and rural self-government bodies. The Project was negotiated with NALSG as Executing

Agency, when DRWS and its JPMU were then located under its supervision. However, following

negotiations, in the first 18 months of project implementation, DRWS and JPMU changed

institutional home repeatedly, moving from the NALSG to the Ministry of Natural Resources, and

then on to the State Committee of Water Resources and Amelioration (SCWRA). SCWRA was

supposed to oversee project implementation at the line Ministry level but it lacked specific WSS

expertise and it was not able to provide adequate oversight to ensure sound implementation

performance. Line agency/Ministry support and commitment to the project was further affected

by instabilities from the prevailing political climate. The Project was later transferred under the

direct supervision of the Prime Minister’s office and ARIS was appointed as both the

Implementing Entity and Executing Agency. DRWS, which had by then moved under State

Agency for Architecture Construction and Regional Development (later .and Communal Services,

SAACCS or GOSSTROY), remained the primary institutional partner of the project and was the

main beneficiary for all Institutional Development activities facilitated by ARIS. It took the

GOKR a lot of pragmatism to allow an NGO such as ARIS, – admittedly highly experienced with

implementation of Bank projects - to step in to not only take on Implementation Entity (i.e. PIU)

responsibilities, but to also represent the Government as Execution Agency (Ministry) for the

sector.

85. After project Executing and Implementing Agency responsibilities were transferred to

ARIS, there was a significant improvement in performance. Similarly, with the transfer of DRWS

to GOSSTROY, a department with all functional responsibilities in it, stronger leadership was

established in the sector, and Government provided more effective support to the project. These

developments, combined with the strong support from MoF, which was a strong advocate for the

project restructuring within Government, were instrumental in the project’s turn-around.

86. Local Governments/ Ayl Okmotus. Performance of the Ayl Okmotus varied considerably

among individual participating local governments, but is also assessed as having been Moderately

Satisfactory on balance. Performance varied based on factors such as capacity of individual

members and strength and independence of the individual local governments. Of the 453 Ayl

Okmotus in Kyrgyz Republic only 18 percent are independent.

(b) Implementing Agency or Agencies Performance

87. Rating: Moderately Satisfactory. The implementing agency performance rating is based

on assessment of the performance of the different agencies, JPMU, ARIS, and the CDWUUS, as

well as the project’s overall outcome.

Page 45: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

29

88. JMPU. Performance of the JMPU originally assigned responsibility for project

implementation is assessed as having been Unsatisfactory. The JPMU was envisaged as a

temporary unit of DRWS, structured to increase the capacity of NALSG/DRWS to take over future

work. Unfortunately however the capacity of the JPMU was found to be weak and its performance

sub-optimal after the project became effective, leading to a series of implementation challenges

discussed in Section 2.2 above. Responsibility for implementation was eventually transferred from

the JPMU to ARIS.

89. ARIS Performance. ARIS’s performance is assessed as having been Satisfactory based

on its performance after transfer of implementation responsibilities to it as part of project

restructuring. ARIS, an NGO with a good track record of project implementation, showed courage

and dedication in accepting a project with very serious implementation issues. It adequately

fulfilled its key project implementation roles in accordance with the Project Agreement it signed

with IDA, and supervision ratings for financial management, procurement, and safeguards aspects

under the Agency’s watch were generally satisfactory. In overseeing overall project

implementation, the agency also coordinated and supervised required tasks, including supporting

the engineering design and technical supervision aspects during the difficult transition from the

SNIPs to the revised standards for sub-project design. The transfer of supervision responsibilities

to ARIS was instrumental in contributing to the project’s overall outcome after the initial

challenges.

90. CDWUUs. CDWUU performance is assessed as having been Moderately Satisfactory, on

balance, with some exhibiting exemplary or satisfactory performance while others performed

poorly. Differences in the performance of CDWUUs are attributed to various factors such as

existing capacity and commitment to the project. Some CDWUUs had relatively experienced staff,

often with a technical professional background relevant to management of water supply facilities.

(c) Justification of Rating for Overall Borrower Performance

91. Rating: Moderately Satisfactory. The rating for Borrower performance combines the

mixed ratings for the Government’s and the aggregated rating of the implementing agencies’

performance during preparation and implementation as well as consideration of the overall

outcome rating for the project in general.

6.0 Lessons Learned

92. Design of so called ‘repeater’ or follow-on operations should involve comprehensive

consultations with various key stakeholders to capture any legacy issues and incorporate

important lessons on what has and has not worked at different stages of the original project. The repeater project should build in arrangements to address the legacy issues and provide

solutions to outstanding challenges from the original project. Accordingly, also the timing of a

repeater project should allow for such lessons to be available.

93. Design of project implementation arrangements should hinge on building robust

institutional structures that can withstand internal and external shocks such as the

Page 46: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

30

withdrawal of individual champions or changes in government. The project preparation

process on the part of Government was championed by strong individuals within the NALSG.

Project oversight and implementation capacity however, declined considerably following the

departure of these individuals after the project became effective, given the weak institutional

capacity within the broader DRWS and the JPMU. The frequent transfer of the project’s

institutional home from one agency to another, without strong leadership, exacerbated

implementation problems.

94. Strengthening local engineering-design capacities and standards should be an

important element of capacity building efforts to enhance the technical sustainability of

water supply and sanitation infrastructure investments. In contexts of low local technical

design capacities as was the case in the Kyrgyz Republic, it is important to foster the acceptance

of international expertise and standards, and to mobilize it in partnership with local firms.

95. Improved convenience in access to water through the provision of household

connections motivates payment for water supply services among rural communities. The

culture of not paying for services in many Kyrgyz villages remains a challenge. However, the

provision of yard or household connections – which really makes the difference in cold rural areas

– has proved to be an important factor in determining whether or not people pay for services.

Improved quality of water alone, on the other hand, has not seemed to influence people’s

motivation to pay as much, as villagers generally perceive their water as clean.

96. The community-based CDWUU rural water supply delivery model is not always a

panacea for success, but requires careful design based on sector maturity and context,

including a candid assessment of existing capacity at the local level. Stakeholders must be

prepared for the fact that some CDWUUs may underperform or fail because of inadequate capacity

or financial resources to address issues, and must plan for solutions to assist CDWUUs in need.

These CDWUUs will require sustained support to ensure success. It is imperative that the next

project makes progress in developing a system to support CDWUUs effectively.

97. Sustained Bank engagement and support to client governments in the face of serious

sector challenges can enable an improbable project turnaround and gradual rebuild of sector

capacities. Bank patience, and the commitment of a substantial level of supervision resources are

among the factors that enabled the project to be turned around. Sustained Bank engagement kept

the window for continued dialogue open to rebuild capacities and provide strategic direction to the

sector. Bank Management should be commended for understanding the importance of remaining

committed to the project/sector through the very difficult 2010-2013 period, were multiple

intractable problems accumulated against it.

98. Turn-around of problem projects requires intensive supervision through staff on the

ground. Decentralization of staff for instance through assignment of a senior co-TTL in country

can enhance implementation support and greatly improve the effectiveness of Bank supervision

capacity on problem projects.

Page 47: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

31

99. To achieve the full health benefits, hygiene and sanitation interventions should always

accompany water supply investments. The Synergies that exist between rural water supply and

sanitation programs and health programs, and should be exploited more. A key lesson from the

RWSSP2 was that optimal health results were achieved when water supply, hygiene, and sanitation

interventions were implemented together. For example, the identification through the project of

school children infected by helminths, and subsequent treatment for the same, had a positive result

on the project’s impact and how it was perceived by the local communities.

100. Improving sanitation and hygiene practices in schools may trigger positive changes

at home; however much more must be done to support Sanitation at the household level in

Kyrgyz Republic to fully achieve health outcomes. Using the toilet in parts of rural Kyrgyz

Republic remains a challenge, especially for women and children. Although the project focused

mostly on schools, greater promotion of sanitation at the household level using appropriate

mechanisms such as a “sanitation marketing” approach to further improve sanitary conditions in

homes would be important.

101. Bank teams should manage expectations and ensure that sufficient and meaningful

dialogue is maintained with all key stakeholders prior to and throughout project

implementation. The project implementation experience could have benefitted from better

communication with clients and beneficiaries on not only the envisaged results, but also on the

limitations and potential challenges which called from frequent adaptation.

102. Civil society can be important allies and partners to project implementation. Civil

society support to project beneficiaries to draw attention to issues that they felt were not being

adequately addressed by Government were initially seen as an unwelcome distraction to a project

already plagued by numerous challenges. However the ultimate incorporation of civil society as

allies and partners in project implementation helped to improve overall project transparency and

relationships among key stakeholders by allowing civil society to act as a bridge between

beneficiaries and Government often helping to facilitate difficult discussions as independent

parties.

103. Project implementation arrangements should always be designed to strengthen

internal Government capacity. Even where circumstances may call for non-governmental

implementation support, the selected implementing entity should work closely with the respective

government counterparts to ensure that their capacity is built. Transferring implementation

responsibility to ARIS was a pragmatic solution to chronic implementation challenges, and it

played an important role in improving overall project performance, as earlier discussed. ARIS

worked closely with DWSS, involving the latter in critical implementation steps, including

procurement and dedicated TA activities. With such approach, although the Government entity

may not have the required skills to implement a project without external support, in the long term,

their sustained engagement should progressively help develop the necessary capacity to run similar

operations.

Page 48: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

32

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners

(a) Borrower/implementing agencies

104. Annex 7 presents a summary of the Borrower’s ICR. The Borrower’s ICR was well

prepared and informative, and findings drew from a strong evidence base based on project

experiences. The assessment of project implementation and outcomes are generally consistent

with the Bank ICR.

105. In addition to the Borrower’s ICR, comments on the Bank’s ICR were received from the

Government, both from the Ministry of Finance and the State Agency for Architecture,

Construction, and Housing and Utility Infrastructure/ DWSS, and they have been incorporated in

the report, where possible. In particular, comments from the DWSS reflect a broad view of issues

that have affected the Water Supply and Sanitation Sector and operations financed by the Bank as

well as other donors in the Kyrgyz Republic since 2002. Some of them do not pertain to RWSSP2.

Copies of the respective Government letters providing the full list of comments are included as

Annex 8b, and footnotes have been added in that section to clarify and respond to some of the key

issues raised. Comments provided also capture important considerations for future interventions

in the sector. Comments from the Ministry of Finance on the other hand mainly relate to

clarification of outputs.

(b) Co-financiers

106. Comments to the ICR received from DFID focused on clarification of specific details in

the main text and were incorporated directly in that regard. A detailed report of the DFID financed

activities is provided in Annex 8a). The DFID ICR accordingly focuses mainly on the Hygiene

and Sanitation, and the Institutional Strengthening components of the project. The main findings

from the DFID report are consistent with the ICR lessons.

(c) Other partners and stakeholders

107. UNICEF also provided comments and clarifications to the main text in regard to activities

implemented by the agency. These comments have been accordingly incorporated in the ICR text.

Page 49: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

33

Annex 1. Project Costs and Financing

(a) Project Cost by Component (in USD Million equivalent)

Components

Appraisal

Estimate (USD

millions)

Restructured

Appraisal

Estimate (USD

millions)

Actual/Latest

Estimate (USD

millions)

% of

Appraisal

at approval

% of

Appraisal

after

restructuring

Component 1: Water Supply

Infrastructure and Equipment

12.67 11.11 10.97

86.6 98

Component 2: Sanitation and

Hygiene promotion

0.56 0.68 0.68

82.4 100

Component 3: Institutional

Development

0.36 0.64 0.97

269 151

Component 4: Project

Management

1.44 1.0 1.06

73.6 106

Total Baseline Cost 14.31 13.08 13.68 95.6 104.6

Physical Contingencies 0.94 0.00 0.00

Price Contingencies 2.00 0.00 0.00

Total Project Costs 17.25 13.08 13.68 79.3 104.6

Front-end fee PPF 0.00 0.00 0 0

Total Financing Required 17.25 13.08 13.68 79.3 104.6

(b) Financing

Source of Funds Type of Co-

financing

Appraisal

Estimate

(USD millions)

Estimate after

restructuring

(USD millions)

Actual/Latest

Estimate

(USD millions)

% of

Appraisal

% of

Appraisal

after

restructuring

Borrower

Government

Counterpart

Funds

2.04 1.75 2.6 127 148

International

Development

Association (IDA)

Grant and

Credit13

10.0 10.0 9.4 94 94

DFID Grant 6.33 1.33 1.38 22 103.8

СDWUU Community

Contributions

0 0 0.30 0

Total 18.37 13.08 13.68 104.6

13 The IDA financing was broken down as follows: US$ 4.50 grant and US$ 5.50 credit.

Page 50: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

34

Annex 2. Outputs by Component

A. PROJECT OUTPUTS BY COMPONENTS

COMPONENT A. WATER SUPPLY INFRASTRUCTURE AND EQUIPMENT

This component was to provide financing to local communities represented by CDWUUs to

rehabilitate or expand existing village water supply systems. The component provided a

combination of grants and credits to local communities in the participating oblasts, for rural water

supply and sanitation infrastructure and equipment required for delivery of improved and more

sustainable community water supply and sanitation services.

The project specifically achieved the following:

a) Repair, rehabilitation, and replacement or upgrading of existing village water supply

systems in 55 villages in participating communities; and improvement of sanitary and

technical conditions in the villages. A total of 37 sub-projects/contracts were

implemented for water supply improvement in the 55 villages for a total of USD

9653448.41. Thirty seven water supply sub-projects were implemented in 55 villages for a

total of USD 9 653 448.41. Specific investments included: rehabilitated or construction of

a total of 40 reservoirs, and drilling of 24 wells, with installation of new water towers and

chlorination station. Works also included replacement of old and economically inefficient

pumps and electrical equipment with energy efficient Grundfos pumps with 3- year

warranties and service period. Meters were also provided to several CDWUUS; 100% of

water connections in Korumdu, Jele-Dobo and Baltabay now have meters as a result of the

project.

b) Rehabilitation and/or construction of demonstration sanitation facilities at selected

schools. The project financed the construction of sanitation facilities at schools in 18

villages at a cost of USD 263733,24. There was an overwhelming demand for facilities

from communities, and applications were received from 49 schools in the 36 participating

Ayil Okmotus. Selection was carried out by a committee which reviewed applications

received from the Ayil Okmotus, accompanied by photographs of existing sanitation

facilities to demonstrate status, letters of guarantee from the Ayil Okmotus confirming

willingness to contribute 5% co-financing and intention to increase financing for WSS,

existence, and operation of school parliaments and Parents’ Committees as well as

sanitation and hygiene education plan for schools. Standard-type schools with in-door

sanitation facilities were selected from the three pilot Oblasts for rehabilitation. Based on

applications received and in line with the evaluation criteria, 10 schools were selected for

construction of outdoor sanitation works and 8 schools for rehabilitation of in-door facilities

(toilets and washstands). Accordingly, outdoor facilities were built at 10 schools and 8

schools had their in-door sanitation facilities rehabilitated. On-site technical supervision of

subprojects was provided by ARIS supervisors and by AO technical supervisors while AO

(Clients) kept continuous control over the quality of civil works.

c) Supply of equipment to selected CDWUUs and/or their associations to maintain the

water supply systems.

Maintenance Equipment. The Project provided special machinery for water supply

system operation to 63 CDWUUs, comprising: 7 diggers, 30 tricycles (motor scooters),

Page 51: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

35

60 kits of equipment and tools and 60 generators for the total of USD 298 090.

Appropriate training was provided in their use. Meetings held with AO and CDWUU

representatives were devoted to issues such as ensuring water economy, loss reduction,

replacement of street standpipes by household connections, installation of meters and

proper operation of submersible well pumps.

Computers for CDWUUs. A total of 80 sets of computer equipment (PC,

multifunctional devices, UPS devices) were provided to CDWUUs for the introduction

of improved billing systems and improvement of CDWUU subscriber awareness and

fee collection. All 80 CDWUUs provided with equipment have been trained. The

CDWUU chairpersons and accountants received training in introducing and operating

the billing system. Beneficiaries noted that the new billing system was very user-

friendly and accessible to use.

Personal safety apparel for water disinfection. 35 CDWUU were provided with

personal protection means such as overalls, gloves, caps, masks, goggles, rubber boots

to provide protection during the chlorination process.

Computers and laboratory equipment for Department of Disease Prevention and

State Sanitary and Epidemiological Surveillance (SES – sanitary and

epidemiological service). Technical assistance has been provided to SES in form of

capacity building to support improvement of Raion SES for water quality control and

monitoring of parasitic diseases in order to improve the SES capacity and performance

in the water supply and sanitation sector. ARIS developed a database for this purpose,

with software that will be placed on the Department’s Web-page. Specific outputs

provided with this capacity building included: (i) the provision of computers and

laboratory equipment. Computer equipment comprised 30 sets of Personal Computers

and office equipment (system block, monitor, multifunctional device, UPS) and a

server for the database; while (ii) laboratory equipment for water tests was provided

for 13 pilot Raion SES laboratories. The database has been introduced for the Central

Department and its units in Bishkek, as well as for 13 target Raion (regional) services.

Additionally, to operate the database ARIS procured and handed over computer

equipment to the Department. All specialists from 13 Raion pilot SES received training

in database and started introducing this system at the central and Raion level.

d) Provision of consultancy services for preparation of design and bidding documents,

and for technical supervision of construction activities to ensure the quality of

infrastructure financed by the Project.

COMPONENT В. SANITATION AND HYGIENE PROMOTION PROGRAM. This

component supported village-level promotion of healthy hygiene and sanitation practices through

technical assistance. As discussed above, actual refurbishment or construction of demonstration

sanitation facilities at schools was financed through Component A, as part of the infrastructure

works. An agreement for implementation of this component was signed between ARIS and

UNICEF on June 17, 2013, and most activities were carried out after this. Activities have been

completed under this component for pilot villages at the community and school level. The focus

of work in the pilot communities mainly aimed at social mobilization in order to involve people in

improvement of sanitation and hygiene practices at the school or household level.

Page 52: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

36

Specific outputs under this component are as follows:

a) Hygiene and sanitation promotion in communities and schools.

Sanitation and hygiene promotion in communities. Sanitation and hygiene have

been promoted in the communities by training of community members in PHAST

method and training of students using UNICEF WASH in Schools methodology.

Community training was delivered in two stages. Stage 1 covered VHC members

during two-day training by PHAST method, 556 VHC members in total represented by

427 women and 129 men from 55 pilot villages. During the second stage the VHC

trained members of all households in pilot villages. A total of 30,101 participants were

trained.

Training of teachers and students. For the training of students in sanitation and

hygiene by UNICEF WASH in Schools methodology, the first stage involved training

of two teachers from each school as trainers – 87 women and 23 men totaling 110

trainees. These trainers, subsequently trained teachers of primary classes and

classroom teachers in their respective schools, covering 1 957 trainees in total (414

men and 1543 women).

In addition, extra-curricular activities have been held in each class of 1st to 11th grades

covering all students of schools. Each school was provided with 5 to 10 manuals

“WASH in schools” developed by UNICEF. For higher efficiency of classes and

developing proper hygienic behavior, UNICEF also handed over a hand-washing

demonstration kit GloGerm. Teachers and children reported continued use of the

manual and the kit after completion of the RWSSP2.

b) Social mobilization in pilot communities. Social mobilization in pilot villages has been

carried out in various ways such as the following.

Community meetings in the beginning and upon completion of project activities in

each of pilot villages.

Exchange visits between villages.

- In Issyk-Kul Oblast, an exchange visit took place on March 5, 2014 in one

secondary school in Tuura-Suu village of Ton Raion. It invited heads of Aiyl

Okmotu, Aiyl Kenesh members, school management, CDWUU, parents’

committees and VHC from pilot villages hosting 110 participants including 55

women. The visit showed that it is possible to maintain school toilets in proper

condition and ensure access to water for students.

- In Naryn Oblast, an exchange visit dedicated to World Water Day took place

on March 22, 2014 in Kazybek village (At-Bashy Raion) and on March 23,

2014 in Bash-Kuugandy village, Jumgal Raion. Exchange visits involved

around 100 participants.

Page 53: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

37

- In Talas Oblast, an exchange visit between villages was held on March 27, 2014

and dedicated to World Water Day. This event took place in a community club

in Kum-Aryk village, Talas Raion. Around 160 villagers participated in the visit

including government officials from Bakai-Ata, Talas and Kara-Buura raions,

Aiyl Okrug, school management/teachers, CDWUU, VHC and parents

committees etc. The participants shared their experiences of social

mobilization, PHAST training in their villages and overcoming the emerging

difficulties etc. almost all schools presented their wall newspapers, contests of

paintings/essays, design sketches of school and household toilets etc.

Parents’ conferences proved to be efficient means of outreach activity. They discussed

the importance of S&H for child health, sanitation and hygiene status in schools,

personal hygiene rules, frequency of changing underwear and bedclothes for a child

treated oxyuricide, and the need for mobilization of local resources to ensure adequate

financing of O&M costs for WASH facilities. Many parents began realizing the need

for financial support to schools for maintaining the WASH infrastructure.

School parliaments. Each school’s parliament was invoked to introduce WASH

principles. This involved a series of activities, such as: revival of sanitary assistants

elected from among students, who together with parliaments organized contests for

“Most Clean Classroom”, monitored the appearances and tidiness of

students/classrooms, held Saturday cleaning days around schools, and organized

contests of paintings, essays and newspapers devoted to “Water, Sanitation and

Hygiene”. Results of contests were recognized at school lineups.

Raion-level round tables for discussion of O&M for school WASH facilities. Representatives from Raion governments, education departments, SES, Family

Practitioners Centers, Aiyl Okmotu, school management, CDWUU, VHC, HPC, RHC

and other stakeholders took part in these events. The participants have been provided

with data on standard rates and actual O&M costs for WASH both in-kind and cash.

Village-level round tables were organized with the support of Aiyl Okmotus and

attended by school management, CDWUU, VHC, parents committees, school

parliaments and other stakeholders. Participants have been informed of maintenance

costs for sanitation facilities, hygienic needs (soap, toilet paper) per student per year

and expense rates for health aids.

Awareness campaign. An awareness campaign was implemented through celebration of

World Water Day, release of promotional and propaganda leaflets/videos, creation of a

Webpage, general school/classroom stands with visual information, performance by

famous singers and amateur performances by people from pilot villages. The World Water

Day’s celebration coincided with an exchange visit accompanied by performance of

improvising Akyn (story-tellers) and Komuz players. Akyns are very popular and respected

in the communities, therefore these communication channel has been innovatively used to

convey key WASH messages to villagers and decision makers. AHP made presentations

of the project progress followed by reports of invited Raion deputy governors, directors of

VHC, CDWUU, schools and members of parents committees. This event made good effect

leaving positive emotions in the hearts of the participants.

Page 54: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

38

Promotional materials included:

Video Production. Three videos were produced and broadcast over national and Oblast

TV: “Always wash hands”, “School toilets as seen by children” and animated graphics.

Posters. Three types of posters were produced and devoted to solicitous attitude to

water, proper sanitation and hygiene at the household level and the importance of

washing hands with soap. Posters have been distributed to all pilot communities and

displayed in schools, VHC and other public places.

Comic books. 20 000 copies of a comic book for children “Let’s keep it clean” have

been distributed to all schools for reading by junior students.

Webpage. A Web-page on basic health principles developed.

General school/classroom health points established in every school.

c) Dehelminthization. Two laboratory studies were carried out in each school, covering 25

school students (grades 1-4) each time. As result of the first testing, 211 children were

diagnosed with invermination, 209 of whom received medical treatment. One child from

Ak Olon village did not receive treatment due to his change of residence to Balykchy. The

costs of treatment with piperazine, albendazole, and mebendazole were paid by the parents.

All persons being in contact with the infected children (parents and other family members)

were sent to the rayon-level sanitary and epidemiological service for medical examination.

Local family practitioners issued prescription for medical treatment of these children. In

addition, doctors met with parents to provide detailed information regarding the need for

re-treatment.

d) Comprehensive needs assessment performed and annual costs of expendables and

services required for routine and limited extraordinary maintenance of WASH

facilities in schools estimated. The analysis was conducted based on the data obtained

from schools in the pilot villages covered by the RWSSP-2, as well as the data provided

by the Ministry of Education and Science, Ministry of Health and its local units, and

municipal authorities. The assessment of needs/ costs for expendables and services of

medical aid points was not performed due to the decision not to construct any sanitary and

technical facilities of the Ministry of Health (this suggestion goes beyond the context).

According to the data of the Ministry of Education, average annual per student costs

planned for 2013 under the standard budget financing for rural schools were KGS 6.2.

Since the actual funding for this category of costs was 62.7%, the actual annual spending

per student amounted to KGS 3.89. Based on the data provided by the schools, calculations

were made for actual spending for operation and technical maintenance of WASH facilities.

The pilot schools in Talas on average spent KGS 27.5 per student per annum for operation

and technical maintenance of WASH infrastructure. For the purpose of comparison,

similar data were requested from a private school in Bishkek. According to data obtained

a private school in Bishkek spends KGS 196.6 per student per annum. According to the

sanitary norms of the Russian Federation, average annual costs for disinfection and hygiene

expendables, expressed in Kyrgyz Soms, amounts to KGS 287 per student per year. Thus,

the estimated monthly costs for purchasing cleaning/ disinfection and hygiene products per

student (based on the current local market prices) amount to KGS 23.5 (if liquid soap is

Page 55: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

39

used) and KGS 28.7 (if bar soap is used), i.e. the costs for nine months of school would be

KGS 211.5 and the annual costs would be KGS 258 in 2013. This data was confirmed by

the actual costs data incurred by the school in Tuura Suu village, Ton rayon, Issyk Kul

oblast.

e) Strengthening the institutional framework for sustainability of WASH infrastructure

at schools. The following activities were carried out.

Establishment of WASH committees composed of school management, parents

committees, VHC, CDWUU, Aiyl Okmotu, school parliament and local Kenesh members

to assist management of schools in identifying and planning resources for financing O&M

costs of WASH facilities; implementing activities for changing the hygienic behavior of

students; monitoring of WASH facilities status at schools etc. Many WASH committees,

in conjunction with parents committees, undertook to organize supplies of soap and paper

towels and schedules of procuring hygiene items.

Approval of Standard Operational procedures (SOP) for O&M of sanitation and hygiene

facilities in each school from pilot villages. SOP are meant for supervision of proper

operation and maintenance of toilets, hand-washing facilities and garbage bins. They have

been approved by headmasters of schools and countersigned by each person in charge of

sanitation facilities. SOP are displayed by relevant sanitation facilities in schools and/or

offices of respective persons in charge.

Memoranda of cooperation have been signed for maintaining adequate level of school

sanitation and hygiene between schools, Aiyl Okmotu, CDWUU, VHC and parents

committees. They are aimed to ensure better cooperation and coordination in the sphere of

S&H education, sustainability of WASH facilities operation, increased public awareness

of S&H practices both in schools and among community members.

f) Water connections have been built in 9 schools and 144 wash-stands installed over the project period as part of the Healthy Nutrition Program.

Table A2.1 Summary of WASH Results in the 3 Oblasts

Oblast Total

households

Of these,

trained HH

Toilets

improved

Wash-stands

upgraded

Began

using soap

Use boiled

water

Arranged

garbage pits

Issyk-Kul 6550 85 7 16 44 16 3

Naryn 5578 84 26 30 34 86 34

Talas 8806 79 3 15 34 32 4

Total 20934 248 36 61 112 134 41

g) Activities in villages. Activities in villages included organization of cleaning days to

remove garbage, clean ditches up and other works including installation of garbage bins,

potable water connections and hand-washing stands.

Page 56: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

40

COMPONENT С. INSTITUTIONAL CAPACITY BUILDING

The principle objective if Component C was to strengthen the institutional framework and capacity

for sustainable development of water supply and sanitation sector. A summary of key

achievements in respect to the above is presented below.

a. Development of a Sector Strategy for Water Supply and Sanitation. A State Program

for Development of Water Supply and Sanitation (2014-2024) was prepared with intensive

stakeholder participation, and approved by a Government Decree dated 24 September 2014.

The Strategy was before the country’s Parliament’s for consideration at the time of the ICR

review.

b. Review of legislation in the field of water supply and water disposal. Review and update

of the existing legislation regulating the sector in order to support implementation of the

above State Sector Development Program was conducted with engagement of key

stakeholders at national, local government, and community levels.

c. Creation of Management Information System (MIS) database with GIS interface. Two MIS databases were developed for (i) water supply and sanitation sector performance

data collection and management within DRWS; and (ii) for collection and management of

data on parasitic diseases and water quality by the Department for Disease Prevention and

Sanitary and Epidemiological Supervision.

d. Development of a financial model for water supply and wastewater. The Project hired

an international consultant to design a financial model for the water supply and wastewater

and handed it over to the Department for Drinking Water Supply and Wastewater, and

selected Department staff were trained on the use of this model.

e. Review technical norms and standards. The project financed the review and

recommendations on optimization of technical standards for water supply and sanitation,

and technical advisory support of chlorination in disinfection of potable water

f. Capacity building for LSG bodies and CDWUUs in managing and maintaining water

supply systems to provide population with high quality potable water supply to population;

g. Introduction and adoption of an effective billing system at the CDWUU level. To

improve CDWUU operations, including tariff collection, 80 sets of office equipment

(computer, printer, stabilizer) were provided through the project, and staff trained in

operating the billing program.

h. Performance Agreements. A Standard Agreement between AOs and CDWUUs was

drafted for provisioning of rural water supply services. The AOs maintained ownership of

the rural water supply assets. Cooperation agreements for provisioning of rural water

supply services were subsequently signed between AOs and respective CDWUUS.

i. LSGB and CDWUU capacity building

Page 57: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

41

Exchange visits

Example of effective management of water supply system and development of CDWUU is Chyrak,

Korumdu, Orgochor, Baltabai and Jele-Dobo in Issykkul Oblast. Virtually each household has

electronic water meters and water heaters installed. In order to spread successful experience,

exchange visits to Issykkul Oblast were arranged for all ARIS oblast specialists, LSGB

representatives and region CDWUUs. The participants of the exchange visit were shown

subprojects in Korumdu, Temirovka, Orgochor, Baltabai and Chyrak villages. During the

exchange visit, the participants were able to ask questions to AO head, CDWUU chairpersons,

technical supervision engineers and other project specialists. Following the exchange visit round

tables with participation of deputies of local keneshes, LSGBs, CDWUU administration bodies,

NGOs were arranged at aiyl aimak level to discuss the mechanisms of effective management of

water supply system and the improvement of relations with consumers in collection of tariffs for

use of water etc.

TO exchange experience and practice that will be useful in CDWUU capacity building and in

indicating mechanisms of improvement of water use tariff collection process, exchange visits for

local AK deputies, AO heads and CDWUUs should be arranged.

Experience in conduction of exchange visits shows high efficiency, particularly in terms of

introduction of new approaches (individual connections through water meters), setting the system

of registering of consumers and accounting of water supply.

Training.

ARIS specialists conducted assessment of CDWUU staff needs in training and capacity building.

A total 21 trainings were conducted in three oblasts. 578 people were trained in those trainings.

The training covered 159 CDWUUs of the first and second RWSSP phases. A summary of

participants is presented in the table below.

Participants Naryn Talas Issyk-Kul Total

CDWUU chairpersons 55 38 66 159

CDWUU accountants 49 34 63 146

CDWUU carpenters 53 33 69 155

DWSWD chairpersons 2 1 2 5

Chairpersons of raion state

administration

1 1

АО chairpersons 42 26 44 112

Total 202 132 244 578

Training in water supply, engineering, water disinfection and sanitation. In line with

recommendations provided by a WB Supervision mission, in the purpose of improvement of

further activities on building the capacity of LSGBs and CDWUUs, a decision was made to hire a

consulting firm to conduct trainings and training activities. A local consultant conducted additional

Page 58: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

42

assessment of the needs of each 37 CDWUUs and LSGBs. To conduct training, 2 training modules

were produced. The training modules consisted of two-day trainings in administrative and financial

management of CDWUUs and in relations with consumers as well as two day training in water

supply, engineering, water disinfection and sanitation. Under these modules, presentations, prior

and post tests in water supply and water disinfection were produced. Based on the produced

training modules, trainings were conducted for CDWUU and LSGB staff, deputies of local

keneshes and village activists in all 37 municipalities.

Training in accounting and operation of billing system. A three-day training was conducted in

Issyk-Kul with participation of LSGB heads, CDWUU chairpersons and accountants in all 37

municipalities. In this training, CDWUU accountants and operators underwent training in

accounting and operation of billing system. The project also prepared video lessons on key topics

of training modules that will be recorded on electronic media and sent to CDWUUs.

COMPONENT D. PROJECT MANAGEMENT

This component supported overall Project management carried out by the Community

Development and Investment Agency (ARIS) through financing of:

Provisioning of services of independent experts for assistance in developing subprojects

under components;

Creation and maintaining the system of monitoring and evaluation of project effectiveness

and outcome;

Operational expenses of ARIS Project Management Unit;

Annual audit of project accounts.

Page 59: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

43

Annex 3. Economic and Financial Analysis

Methodology. The ex-ante economic analysis included in the project PAD yielded a Net Present

Value of US$12.9 million and an internal economic rate of return (EIRR) of 32 percent. The main

differences between the ex-ante and ex-post are the assumptions related to the way opportunity

costs were measured, to health benefits, and to time spent collecting water, as well as the

consideration of reductions in the cost of potable water for the households. GDP per capita was

used to quantify opportunity cost of time spent collecting water and spent sick due to waterborne

related illnesses instead of our measurement of rural income, which should be a more accurate

approach for the villages treated by the project. Improvements in infectious diarrhea were used as

a measurement of health related benefits. It was assumed that only villages lacking water service

presented cases of this condition. In the ex-post analysis, it was acknowledged that some cases of

water related diseases still occur in treated villages after the project. Also, only infectious hepatitis

and acute enteric infections were taken into account, for which there was both more complete data

and also could be more accurately linked to water conditions. Finally, the assumptions regarding

the time spent and saved collecting water overestimated the effect of the project in this dimension

when contrasted to the assessment survey results. The ex-ante analysis assumed that collection

time was 66 minutes before the project, and that it would decrease around 46 minutes. The actual

numbers obtained in the assessment surveys showed a collection time of 17 minutes and a decrease

of 9 minutes after the project.

The ex-post economic analysis includes (a) the cost of all project components, including other

donors contributions and estimated O&M costs, and (b) all measurable benefits, including: (i)

reduced time in collecting water decreases in the time spend collecting water; (ii) welfare gains at

household level associated with reduced expenditure on water storage tanks and on water treatment

(i.e. boiling water); and (iii) and reduced incidence of water related diseases such as infectious

hepatitis and acute enteric infections as a result of improved access to high quality water and

decline in the reliability on standing water sources. As with all economic analyses, the costs are

perfectly observed while the benefits are not.

Although the project investments complement investments made under the first Rural Water

Supply and Sanitation Project (RWSSP) the Economic Analysis considers only costs and benefits

associated to the investments financed under RWSSP-2. For the Economic Analysis the evaluation

period was defined at 26 years including 6 years of project implementation, with corresponding

benefits to be realized starting on 2015. The adopted social discount rate is 12 percent and the

standard conversation factor for the cost is assessed at 0.85. All assumptions and key results are

outlined below.

Benefits: The RWSSP-2 project benefited around 83,000 people in 55 villages, by expanding

access and supplying them with better quality and more reliable water services. The project

provided financing to local communities represented by Community Drinking Water Users Unions

(CDWUUs) to rehabilitate or expand existing village water supply systems. As part of the civil

works contracts, this project also financed several improvements in sanitation facilities at schools.

Additionally, the project supported village-level promotion of healthy hygiene and sanitation

practices through technical assistance aimed at enhancing the positive health effects of the access

to better water quality. The detailed list of benefits and main assumptions can be found below:

Page 60: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

44

Reduced time in collecting water: Before the project, the average household spent 17

minutes collecting water by trip. This time was lowered to 8 minutes on average14. It is

assumed that households make 1.5 trips on average per day, an assumption that is in

agreement with the lowered distance between the housing units and the new pumps. This

was also supported by anecdotal evidence from the field. A rural average hourly wage of

US$0.6615 is used as a measurement of the opportunity cost of this time savings. Under

these assumptions, the project is generating annual benefits of USD 1,626,075 from

economic gains of saving time to collect water.

Reduced coping costs: At the time of appraisal, it was a common practice for households

to boil water prior to consuming it. Also, a large percentage of households invested in water

tanks for security of supply. The analysis assumes that approximately 20 percent of

households forgo investments in water tanks following the project due to improved water

services. Water storage tanks cost US$250 in the country and a depreciation of around 5%

a year is assumed to calculate the future annual savings implied by not purchasing new

tanks. Energy savings associated with reduced need to boil water due to improved water

quality are estimated based on a 10 liters per capita per day benchmark. According to the

household survey 42 percent of households used to boil water before consuming, this

practice fell to 21 percent after the project. Well established benchmarks for the regions

are used in terms of energy requirements to boil water (0.09 KhW per liter of water) and

an economic cost of 0.27 dollars per KhW16 . Under these assumptions the project is

expected to generate annual benefits of USD 2,123,358 from energy savings linked to

boiling water and USD75,000 due to reduced investments in water storage tanks.

Benefits associated with lower incidence of water related or waterborne illnesses. Prior

to the project the incidence of waterborne diseases in benefiting villages was high. The

economic analysis focuses on infectious hepatitis and acute enteric infections, conditions

commonly associated with poor water quality. The incidence of infectious hepatitis went

from affecting 0.38% of the population to 0.22% after the project implementation. The

incidence of acute enteric infections went from 0.20% to 0.12%, equivalent to a 40 percent

decrease in illness incidence17. The first quantifiable benefit comes from a decrease in the

days lost due to these illnesses. With an average of 10 days lost per person for each case,

the reduction in the incidence resulted in savings of around US$ 14,045 (pricing each day

using the rural wage as before). The second quantifiable benefit is the reduction in

expenditure to treat these illnesses. Taking an average cost of treatment of US$88 before

the project and US$92 after the project for acute enteric infections, and US$151 before and

after the project for infectious hepatitis, give a total annual savings of US$ 33,911 due to

the decrease in the incidence.

14 Rebicon (2014). Assessment of Impact and Preparation of Analytical Report. 15 Provided by ILO data for the country. 16 World Bank (2012) Europe and Central Asia Balancing Act; Cutting subsidies, protecting affordability, and

investing in the Energy Sector in Eastern Europe and Central Asia Region. 17 Rebicon (2014). Assessment of Impact and Preparation of Analytical Report.

Page 61: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

45

Direct or indirect benefits from the activities in component C and D were not taken into account,

as they are difficult to measure.

Costs: All project costs, including Components A, B, D and front end fees were applied in the

economic analysis. DFID financing and IDA credit and grant were included. It was assumed that

annual O&M costs were equal to 5% percent of the total investment costs (component A and the

sanitary facilities portion of component B), net of VAT. These costs were adjusted by a standard

conversion factor of 0.85, as mentioned above.

Results: Based on these assumptions the total estimated annual benefits of the project are

US$ 3,872,389, yielding an ERR of 15% and a NPV of US$ 1,890,648.

Efficiency: The RWSSP-2 has low per capita investment cost of USD 163 per capita. This is

particularly good given the low population density of the area.

Results of the Economic Analysis

Overall Project Economic Viability

ICR (at completion) PAD (at appraisal)

ERR NPV (USD) ERR NPV (US$)

15% 1,890,648 32% 12.10 million

108. The estimated ERR at ICR was 15% and the NPV was US$$1,890,648, assuming a social

discount rate of 12% and 26 years of asset life, including 6 years of project implementation, with

corresponding benefits to be realized starting in 2015. The analysis reveals that actual economic

indicators (ERRs) are much lower than those projected during appraisal. Given the conservative

assumptions used (low skill wages, low number of daily trips), and the fact that no benefits could

be accounted for part of the activities of component B, and all of the activities of component C and

D, the project’s NPV and ERR are in fact expected to be even higher than those estimated.

Additionally, the project has relatively low per capita investment costs of about US$ 163 per capita.

This is considered to be reasonable given the low population density of the project area. Based on

these results, combined with the need for an additional 17 months to complete implementation of

investments, the efficiency of the project is considered to be Moderate compared with the ex-ante

analysis conducted at appraisal.

Page 62: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)
Page 63: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

47

Annex 4. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Mirlan Aldayarov Senior Energy Specialist GEEDR TTL

Anna Cestari Senior Water Resources Specialist GWADR WSS Specialist

Jonathan S. Kamkwalala Practice Manager GWADR Management

Nurbek Kurmanaliev Procurement Specialist GGODR Procurement

John Otieno Ogallo Senior Financial Management

Specialist OPSOR

Financial

Management

Wolfhart Pohl Adviser GCFDR Safeguards

Richard W. Pollard Senior Water & Sanitation

Specialist

MNSWA

- HIS WSS Specialist

Nargis Ryskulova Operations Officer GTIDR Operations support

Janna Ryssakova Social Development Specialist ECSSO -

HIS

Social

Development

Supervision/ICR

Pier Mantovani Lead Water & Sanitation Specialist GWADR Program

Leader/TTL

Anna Cestari Senior Water Resources Specialist GWADR Co-TTL

Sana Kh.H. Agha Al Nimer Senior Water & Sanitation

Specialist GWADR WSS Specialist

Galina Alagardova Financial Management Specialist GGODR Financial

Management

Christophe E. Bosch Lead Water and Sanitation

Specialist GWADR WSS Specialist

Roxanne Hakim

Senior Anthropologist GSURR Social Safeguards

Asli Gurkan

Social Development Specialist GSURR Social Safeguards

Cesar Niculescu Environmental Specialist GENDR Environmental

Specialist

Arcadie Capcelea Environmental Specialist GENDR Environmental

Specialist

Leila Talipova Consultant GWADR Water &sanitation

Specialist

Irina Goncharova Procurement Specialist GGODR Procurement

Mary P. Judd Consultant GSURR

Nurbek Kurmanaliev Procurement Specialist GGODR Procurement

Irina Petrovna Novikova HQ Consultant ST GSURR

Janna Ryssakova Social Development Specialist ECSSO -

HIS

Social

Development

Yuling Zhou Lead Procurement Specialist GGODR Procurement

Page 64: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

48

Sanyu Lutalo Senior Water and Sanitation

Specialist GWADR ICR Author

Paula Restrepo Cadavid Urban Economist GSURR ICR Economist

Luis Quintero Consultant GSURR ICR Economic/

Financial Analyst

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD (including travel and

consultant costs)

Lending

FY08 4.48 15, 230

Supervision/ICR

FY09 34.17 35,968.87

FY10 27.37 91,136.22

FY11 29.12 153,463.65

FY12 22.38 138,362.47

FY13 26.88 160,709.88

FY14 23.91 119,585.16

FY15 16.90 106,473,00

Total: 185.21 699,226.25

Page 65: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

49

Annex 5. Beneficiary Survey Results

There was no beneficiary survey conducted for the project. However an Impact Evaluation

Study was carried out. A summary of the study, its methodology and key findings is presented

below.

IMPACT ASSESSMENT STUDY

Goals of the survey

Assessment of access of villagers to drinking water in project impact zones (component

1)

Assessment of sustainability of village public unions of consumers of drinking water

(further CDWUU) as an instrument designed to provide access to drinking water

(component 2)

Assessment of sanitary-hygiene practices in rural areas (component 3)

The following tasks were carried out to achieve the survey goals:

Component 1

Quality, quantity and reliability assessment of drinking water supply based on

consumers’ feedback.

Assessment of satisfaction level of beneficiaries with the supply of drinking water.

Assessment of potential project impact on the welfare and lifestyle level of

beneficiaries, as well as on their health.

Beneficiaries’ feedback assessment about work of CDWUU and questions about local

water resource management

Component 2

Assessment of management efficiency (fee collection, maintenance of water supply

systems, staff turnover, support from Ayil Okmotu, MPs, allocation of funds from local

budget, potential of the employees) of CDWUU in supply of villagers with drinking

water.

Assessment of readiness of villager to pay for good quality water and regular drinking

water supply by CDWUU.

Assessment of the level of cost cover of exploitation and technical maintenance of

CDWUU water supply systems (CDWUU budgets, AO and other resources)

Component 3

Assessment of sanitary-hygiene education in schools

Assessment of improvements of sanitary-hygiene conditions in schools.

Public awareness assessment about issues with water, sanitary and hygiene.

Methodology

Quantitative and qualitative survey methods were used to achieve the survey goals. They

included the following.

Page 66: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

50

3.1 Quantitative survey of households

Survey geography

The survey area included 25 villages of Issyk-Kul, Naryn, and Talas oblasts, covered by

the project. The list of villages was provided by the Client.

The control included 25 villages of Issyk-Kul, Naryn and Talas oblasts not covered by the

project. The list of non-project villages included those villages which, based on information

from the Client, didn’t have WSS located in the proximity of project villages, and which

are of the approximately same population. The list was agreed with Client.

Survey sample. As part of the quantitative research, 888 respondents were surveyed: 444 in

project impact villages (further project villages) and the rest in villages not impacted by the

project (further non-project villages).

Survey object. Selection of households was done using routing sampling method in accordance

with steps calculated using the formula: selection step=households number/sample size.

Survey respondents. Respondents included heads of households, or members of households that

were 18 years old and above, who are responsible for the payment of municipal services and

solving issues related to them.

Survey subjects: Subjects covered included opinions, thoughts and assessments of respondents

based on their personal experience with regard to the survey topic.

Survey duration: 20.08-20.09.14

3.2 Focus group discussions (FGDs). In order to obtain contextual information about changes

initiated by the project, 12 FGDs were conducted in participating communities. Each FGD consisted

of 8-10 people. This number of FG participants is optimal to allow all participants express their

thoughts on each question. Target groups of FG:

Group 1 – villagers, residing in households with in-house/in-yard connections

Group 2 – villagers, residing in households and using public water taps/no-users of

VWSS

Group 3 – leaders of villages and specialists: AO employees, CDWUU, educational and

medical institutions.

66 residents of project villages and 34 specialists – employees of AO, CDWUU, MP of Ayil

Kenesh, workers of education and medical institutions, representatives of public organization,

village leaders participated in the FGDs

3.3 Expert interviews.

Survey geography: project villages of Issyk-Kul, Naryn and Talas oblasts

Survey objects:

- Executives or representatives of CDWUU executives (1 for each village, 25 interviews)

- Informed AO or Ayil Kenesh representatives (one for each village, 25 interviews in

total)

Page 67: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

51

Summary of results presented in the survey report

1. Results of the research showed that in general the goals of RWSSP-2 were achieved.

2. 86% of HH have access to WSS services, 85% use it as the main source. In eleven project

villages covered by the survey, all residents have access to WSS services. Mainly only

those HH are not covered by the WSS services that are located in new settlements and in

further settlements where RWSSP2 activities are not planned

3. After rehabilitation of WSS under RWSSP-2, the process of in-house/in-yard installations

have started and are still going on. The share of HH that have installed in-house/in-yard

connections that use tap water as the main source of drinking water, compared to 2012 has

increased from 9% up to 43%. The main obstacle in installing in-house/in-yard connections

is the relatively high installation costs.

4. In project villages in comparison with 2012, the share of those HH that use open sources

of water for drinking and cooking has significantly decreased from 29% down to 5%. In

non-project villages the share of such HH is 23% and the situation during the last three

years has not changed.

5. As a result of RWSSP2 activities for the households residing in project villages and using

WSS services, the distance to the main source of drinking water has significantly decreased.

During 2012 and 2014 the share of HH – WSS service users that deliver drinking water

from the sources that are located at distance less than 100 m has increased from 47% up to

77%. The share of those HH for whom the distance to water pipes is more than 500m has

decreased from 7% down to 0.3%.

6. Since the distance until the closest source of drinking water has decreased and in general

the quality of water supply has improved (the water supply interruption has decreased and

the water supply pressure has increased), HH-WSS service users residing in project villages

are now spending less time on delivery of water. The average time that HH used to spend

on delivery of water, in comparison with 2012 has decreased from 17 minutes to 8 minutes.

Also the physical load on women and children, who are usually responsible for the delivery

of water, has decreased.

7. The majority of HH WSS service users in project villages (77%) think that the tap water

that they use for drinking and cooking is of good or very good quality. This is confirmed

by the water quality checks that are conducted by sanitary-epidemiological stations as per

agreements made with CDWUU. During 2012 and 2014 56 checks were conducted and the

results showed that the quality of tap water meets the national norms. The share of HH that

think that they use very good and good quality water, in comparison with 2012, has

increased from 47% up to 77%. For comparison, in non-project villages only 19% of HH

think that the consumed water are of good and best quality, and in comparison with 2012

the situation hasn’t changed. 70% of HH that do not use tap water have noted that water

they use for drinking and cooking is not clean and muddy

8. Because the quality of drinking water has improved, the share of HH that improve the

quality of water prior to using it has decreased. 81% of HH-WSS service users who are

residing in project villages consume tap water without pre-treating it. The share of has

increased by 12% in comparison with 2012. For comparison, 88% of households that do

Page 68: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

52

not use WSS services have to pre-treat water by boiling or settling it. The practice of using

filters and disinfectant means is not popular in surveyed villages.

9. WSS services users resident in project villages note the increase of water supply pressure

in water pipes after RWSSP2 activities were completed. The share of HH that rate the

supply pressure in pipes as good and very good has increased during 2012 and 2014 from

36% up to 53%. As per opinion of survey participant the main reason of decrease of supply

pressure is the usage of drinking water for the irrigation purposes in spring and summer.

10. During 2012 and 2014 the duration of water supply interruption decreased. The share of

HH – WSS service users – that are residing in project villages and who have access to

drinking water 12 hours or more per day, has increased over the last three years from 63%

to 83%.

11. Since the WSS rehabilitation works were completed relatively recently the interruptions in

water supply related to failure of WSS occur rarely and are fixed by CDWUU employees

quite promptly. The reasons of interruption in water supply in most of the cases have

seasonal character. In spring and summer the interruptions in water supply occur because

of usage of drinking water for irrigation purposes. In 2014 the problem in shortage of

irrigation water got worse because the summer was a drought.

12. Expansion of coverage with in-house/in-yard connection, and the improved quality of

water supply services mean that most HH have no need in reserving drinking water. In

2012 the share of HH of project villages that reserve water was higher than in non-project

villages – 87% and 81% respectively. In 2014 in comparison with 2012 in non-project

villages the share of HH that reserve water and the average volume of reserved water almost

hasn’t changed, whereas in project villages the share of HH that reserve water has

decreased until 68% of HH. The average volume of reserved water in project villages has

decreased from 40 liters down to 32 liters. The main reason why the majority of HH – WSS

service users, residing in project villages (56%) - reserve water is the absence of water

pipes.

13. Implementation of RWSSP2 has improved living quality of residents of project villages.

Survey participants have noted that their living conditions are similar to urban life

standards. Connection to WSS provides the possibility to install water heaters, shower

cabins, baths, flush toilets, laundry machines and build saunas. This way the sanitary-

hygiene conditions of HH living conditions are improving.

14. It should be noted that women, who carry most of the workload in housekeeping duties,

had felt the impact after implementation of RWSSP2. Also, the time spent for water

delivery has decreased. Using home appliances and existence of communal comforts

decreases the time and physical load on housekeeping.

15. Attempts to teach sanitation and hygiene principles sometimes cause misunderstanding and

hostility among the population because it is believed that these rules are known to

everybody. However, the survey revealed that regardless of the fact that 100% of HH noted

that they use soap to wash hands, particularly after visiting toilets, the share of HH that had

no soap available by wash sinks at the time of the survey was 21%.

Page 69: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

53

16. Activities to inform the population about following sanitation and hygiene principles were

conducted in all project villages in the form of seminars and trainings. 74% of HH residing

in project villages, during last year received information about improving hygiene in HH.

In all project villages village health committees deal with informing population.

17. Survey participants note that after implementation of RWSSP2, the attitude of villagers to

sanitation and hygiene have changed – they pay more attention to cleanliness of toilets and

using toilet paper etc. Special attention is paid to following rules of hygiene in schools: for

instance, class meetings take place, containers with liquid soap are installed; wet wipes and

toilet paper are purchased, etc.

18. After conducting rehabilitation of rural WSS under RWSSP2, all schools in surveyed

villages have received uninterrupted access to drinking water. At the moment of preparing

the report, in schools of 22 villages wash sinks were installed to wash hands, and in

seventeen schools – water heaters.

19. Facilities to wash hands (basins and sinks) are available in all schools of project villages.

The vast majority of them are located within the school near to canteen. Basin to wash

hands near toilets is only available in one school for now.

20. Improved access to high quality drinking water supply services, as well as information on

sanitation and hygiene contributed to a decrease in the incidence of infections related to

the quality of drinking water in project villages. Thus, from information provided by Ayil

Okmotus, there were no infection cases in 2014 related to quality of drinking water, where

in 2012 in project villages there were 137 incidence of infecting with hepatitis A.

21. Participation in RWSSP2 allowed the strengthening of human resource capacity of

CDWUUs. During 2012 and 2014 the staff members of CDWUU had increased by one

third in general and have technical personnel. More than half of the CDWUU employees

went through trainings under RWSSP2: 51% of CDWUU employees were trained in

collection fees, technical training on servicing the system received 55%

22. Participation in RWSSP2 allowed increasing financial sustainability of CDWUU. Main

statement of income of CDWUU budgets is collection of tariff from individuals and legal

entities. By providing uninterrupted water supply by exploiting rehabilitated/newly built

WSS, the CDWUU will have constant source of income of financial means.

23. Currently majority of WSS subscribers make payments per number of HH members. Only

18HH have water meters installed in their houses. Coverage of population with in-house/in-

yard connection with preinstalled water meters would allow measuring and controlling

water consumption and compare with the amount tariffs. The obstacles in installing water

meters may be the cost of water meter and fear that after installing the meter the WSS

service fee payments will significantly increase.

24. Running WSS and installation of tariffs on WSS service would allow the setting up wages

in 12 CDWUU, where in 2012 employees used to work voluntarily. Under RWSSP2 all

CDWUU in surveyed villages received computers with software to keep billing system of

Page 70: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

54

accounting payments, and they are installing the system for their practice. Beside

advantages that this billing system has compared to manual accounting, it should be noted

that population trusts to automated calculations more.

25. Social status and relevance of CDWUUs in village communities have increased. The

majority of HH (89%) in project villages trust CDWUUs in solving village water supply

issues, and 75% rate their work as good and very good.

26. Along with the achieved success in CDWUU activities, serious problems occurred. The

main problem is the existence of debts on payment for tariffs by individuals. Twenty

CDWUUs out of twenty five, at the time the survey was conducted, had debts from

individuals. Consequently, CDWUUs suffer from shortage of funds for maintenance of

WSS, purchase of tools and materials. Moreover, because of low wages and delays in

payment, difficulties occur in attracting skilled professional and the employee turnover is

high.

27. The stability of the water supply systems is dependent on how correctly and promptly

CDWUUs perform technical servicing. It was found that in seven CDWUUs there are no

plans of technical maintenance.

Page 71: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

55

Annex 6. Stakeholder Workshop Report and Results

No stakeholder workshop was conducted for the project.

Page 72: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

56

Annex 7. Summary of Borrower's ICR and/or Comments on

Draft ICR

IMPLEMENTATION COMPLETION REPORT

SECOND RURAL WATER SUPPLY AND

SANITATION PROJECT

Page 73: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

57

October 2014

Basic information:

1. Country Kyrgyzstan

2. Project title Second Rural water Supply and Sanitation

Project

3. Заемщик Borrower Government of the Kyrgyz Republic

4. Implementing Agency Kyrgyz Republic’s Community Development

and

Investment Agency (ARIS)

5. Financing amount: US$ XXX million including

IDA Credit – 5557462 USD ;

IDA Grant – 4505496 USD

DFID Grant – 1306105 USD

GoK - 3071131 USD

6. GoK Contribution:

7. Loan conditions: 0.75% per year for 40 years

with 10 years of grace period

8. Date of signature: May 21, 2009

9. Effective date: August 19,2009

10. Project closing date: October 31,2014

Page 74: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

58

Structure of Report:

I. Project description

A. Background and rationale

B. Overall evaluation of the project objectives and tasks

II. Assessment of implementation

A. Project results by components

B. Project disbursements

C. Performance of the Government of the Kyrgyz Republic, LSG, Contractors and

Consultants

D. Performance of the World Bank

III. Performance assessment

A. Efficiency in achieving the results

IV. Overall assessment and recommendations

A. Overall assessment and lessons learned

B. Challenges encountered and ways for dealing with them

C. Recommendations

Annexes

1. PROJECT DISBURSEMENTS

2. PROJECT INDICATORS

Page 75: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

59

I. Project Description

A. Background and Rationale

Kyrgyz Republic, a small and land-locked country, has a population of 5.8 million, of who 66%

are residing in rural area. Since independence the country has pursued a determined policy of

privatization and market development.

The Kyrgyz Republic faces substantial challenges in rebuilding basic infrastructure in rural

areas. Since the collapse of the former Soviet Union, there has been rapid deterioration in the

availability and quality of basic public services. Services once taken for granted (drinking water,

solid waste collection, treatment, etc.) are often available only intermittently or not available at

all. Steady deterioration in the quality of services has led to public health hazards.

Today, after more than twenty years of severe neglect, large portions of local service

infrastructure, installations, and equipment have deteriorated beyond repair and need to be

rebuilt or replaced entirely if service delivery is to be restored to minimally acceptable levels.

The capacity of local governments in providing infrastructure services is limited by lack of

available fiscal resources, weak institutions that are unable to function under such constrained

environment, and utilities that are unable to cope with the rapidly deteriorating infrastructure.

An important factor in the current conditions is that as part of the Kyrgyz Republic's move

towards decentralization, responsibility for the delivery of most basic local public services was

turned over to local self governments (LSGs) in the mid 1990's. Most LSGs were then – and

continue to be today - unable to assume the new responsibilities due to the lack of necessary

fiscal resources, technical means, and institutional capacities.

The Kyrgyz Government policy aimed at improving provision of quality infrastructure services

and decentralization of governance in the country identified the relevance of the Project.

Infrastructure facilities and services offered to the public by government agencies before

became, first, an integral part of the local authorities’ responsibility, and secondly - the critical

state of infrastructural facilities required an immediate rehabilitation and reconstruction

In this regard, improving access to quality infrastructure services and rehabilitation of

infrastructure facilities in villages has become one of the most important social tasks of the

Government. It should be noted that before the Rural Water Supply and Sanitation Project

(RWSSP-1 and RWSSP-2 none of investment projects was involved in providing access and

rehabilitation of infrastructure facilities. Four problem and six new subprojects under RWSSP-

2 plus 26 problem subprojects continuing from RWSSP Phase 1 have been selected.

Through improvement of rural water supply and capacity building, the project has created good

preconditions for sustainable development of CDWUU and further independent solving of

problems in water supply sector. The Project was the first initiative that supported upgrading

infrastructure in villages at the national level as part of the decentralized governance framework.

B. Overall assessment of the Project objectives and tasks

The Second Rural Water Supply and sanitation Project focused its efforts in 55 villages of

Issyk-Kul, Naryn and Talas Oblasts. The Project beneficiaries were the villages’ residents, rural

water supply systems, sanitation facilities in schools, local self-government bodies, NGOs and

the Project partners.

The key Project objective was to improve access for participating communities to safe

potable water; improved sanitation and hygiene practices in the rural area at individual,

household and institutional level; strengthen institutional framework and capacity for further

sustainable development of the water supply and sanitation sector.

Page 76: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

60

This objective was achieved by (a) financing the rehabilitation rural water supply systems and

construction of sanitation facilities in the schools; (b) improving sanitation and hygiene

practices at individual and household level; and (c) assisting local governments in increasing

the effectiveness of the WSS sector management.

The urgency of the key objective of RWSSP-2 did not diminish over the Project

implementation; on the opposite, given the deterioration of the existing infrastructure it became

even more important. The same is true about the tasks set for achievement of this objective.

Successful achievement of the project goals built on the following approaches:

First, decentralized approach to utilization of investment. This has contributed to increased

accountability of local self-government bodies, participation of community members in

decision making regarding the use of investments.

Second, supervision of subprojects by local governments enabled to improve the quality of

works and monitor the material investments provided.

In third, necessary trainings were delivered for local government bodies and CDWUU as part

of institutional development activities. The Project assisted CDWUU in improving their

performance efficiency in delivering local infrastructure services and contributed to

strengthening their capacity to implement further reforms.

Components addressed three critical tasks:

These included management of rehabilitated facilities, rehabilitation of water supply and

sanitation facilities, improvement and strengthening the CDWUU capacity.

The positive results achieved under the project in improving access to water supply services

were limited to zones (areas) of specific beneficiaries residence in the area of rehabilitation

works. It impeded to fully cover and solve the problem of drinking water in some villages.

There is a need for improvement of the CDWUU technical status, reconstruction of facilities

and networks, and improvement of management efficiency. This would enable to better address

the challenges faced by the Government. Given the critical state of the drinking water supply

systems in villages at the beginning of the project, the project involved villages for

rehabilitation of head water intakes and replacement of equipment. Due to limited resources,

the project did not provide for complete rehabilitation and construction of water supply systems

in villages.

The assets of water supply systems have been handed over to the municipal ownership of Aiyl

Okmotu.

II. Evaluation of implementation

B. Project results by components

In order to achieve Project objective, the below structure of the project was adopted. The

project comprised four components, each component dealing with specific tasks. In general, the

components were designed to accomplish the tasks set for the Project by the Government of the

Kyrgyz Republic.

RWSSP-2 included following components:

Component A. Water Supply Infrastructure and Equipment;

Component B. Sanitation and Hygiene Education Program;

Component C. Institutional Development;

Component D. Project Management.

Page 77: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

61

Component A. Water Supply Infrastructure and Equipment

This component will provide a combination of grants and credits to the local communities, who

independently established Community Drinking Water Users’ Unions (CDWUUs).

Financing is provided for the following purposes:

to rehabilitate and expand existing village water supply systems and improve sanitary

and technical conditions in the villages. The component will include rehabilitation or

construction of demo sanitation and technical facilities at schools;

to supply equipment to selected CDWUUs and/or their associations to maintain the

water supply systems;

to provide consultancy services for preparation of design and bidding documents as well

as for technical supervision of construction activities to ensure the quality of

infrastructure financed by the Project.

Construction of water supply and sanitation infrastructure

The purpose of this component was to provide grants and credits for the repair, rehabilitation,

and replacement or upgrading of rural water supply works and systems required for community

services improvement. The subcomponent was aimed to address priorities in the water supply

sector.

37 contracts have been implemented for water supply improvement in 55 villages for total USD

9 653 448,41 (details by contracts are enclosed in Annex 1).

Disbursements under completed RWSS contracts

No. and name of Contract Contractor Date of

Contract

signing

Date of

Contract

completion

Disbursement,

USD

Problem subprojects

RWSSP-2/W/NCB/IK5-2-09

Rehabilitation of rural water supply

system in Korumdu

“Yug-Stroyservis” OJSC 23.06.2011 28.12.2012 1 027 931,88

IDA-RWSSP-CW-2011-1

Rehabilitation of rural water supply

system in Temir

JV: FMU-1 Ltd. plus

BIOR Ltd.

29.12.2011 26.12.2012 692 990,13

IDA-RWSSP-CW-2011-1/2

Rehabilitation of rural water supply

system in Kashat

Minur Ltd. 29.12.2011 15.02.2013 580 672,37

IDA-RWSSP-CW-2011-2 Rehabilitation

of rural water supply system in Chelpek

JV: “Yug-Stroyservis”

OJSC and OJSC “Usta”

03.08.2012 30.04.2014 1 331 772,66

Subtotal: 3 633 367,04

New subprojects of Phase 2

IDA-RWSSP-CW-2011-6 Rehabilitation

of rural water supply system in Jele-Dobo

Minur Ltd 29.12.2011 31.12.2012 471 985,27

IDA-RWSSP-CW-2011-7

Rehabilitation of rural water supply

system in Baltabay

“Yug-Stroyservis” OJSC 29.12.2011 28.11.2012 436 285,21

Page 78: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

62

IDA-RWSSP-CW-2011-5

Rehabilitation of rural water supply

system in Ak-Kochkor

JV: Remservis CJSC,

«MNK» and «Poisk» Ltd

10.01.2012 31.05.2013 588 925,21

IDA-RWSSP-CW-2011-3

Rehabilitation of rural water supply

system in Uch-Emchek

JV: «Talas-MSPMK»

CJSC, «MPMK-Talas»

CJSC, «Jolchu» CJSC

22.03.2012 24.05.2013 615 693,49

IDA-RWSSP-CW-2011-4 Rehabilitation

of rural water supply system in Tugol-Say

village

JV:

«Kochkorsuukurulush

and EMG-Stroy»

18.05.2012 16.08.2013 557 667,77

IDA-RWSSP-CW-2011—8

Rehabilitation of rural water supply

system in Koochu

JV: Enesai Ltd. plus

AleksStroi Ltd.

26.07.2012 15.11.2013 556 169,74

Subtotal: 3 226 726,64

Rectification of Phase 1 problem subprojects

RWSSP-W-Shopping-12-1

Rehabilitation of rural water supply

system in Ak-Olon

Minur Ltd. 11.09.2012 28.01.2013 38 652,16

RWSSP-W-Shopping-12-2

Rehabilitation of rural water supply

system in Chon-Tash

“Yug-Stroyservis” OJSC 11.09.2012 22.03.2013 83 224,09

RWSSP-W-Shopping-12-3

Rehabilitation of rural water supply

system in Orgochor

“Yug-Stroyservis” OJSC 11.09.2012 25.01.2013 135 610,06

RWSSP-W-Shopping-12-4

Rehabilitation of rural water supply

system in Archagul

Enesai Ltd. 20.09.2012 19.12.2012 22 834,14

RWSSP-W-Shopping-12-5

Rehabilitation of rural water supply

system in Terek

CJSC

Kochkorsuukurulush

20.09.2012 18.12.2012 174 193,89

RWSSP-W-Shopping-12-6

Rehabilitation of rural water supply

system in Jergez

Enesai Ltd. 20.09.2012 25.09.2013 76 639,59

RWSSP-W-Shopping-12-8

Rehabilitation of rural water supply

system in Kara-Oi

“Usta” OJSC 19.10.2012 25.04.2013 33 415,76

RWSSP-W-Shopping-12-9

Rehabilitation of rural water supply

system in Kara-Burgon

CJSC

Kochkorsuukurulush

16.01.2013 01.10.2013 139 312,54

IDA-RWSSP-SW-2012-10

Rehabilitation of rural water supply

system in Kopuro-Bazar

CJSC Talas-MSPMK 21.01.2013 01.09.2013 148 055,15

IDA-RWSSP-SW-2012-11

Rehabilitation of rural water supply

system in Yntymak

CJSC Talas-MSPMK 17.01.2013 15.11.2013 130 149,73

IDA-RWSSP-SW-2013-1 Rehabilitation

of rural water supply system in Min-

Bulak

FMU-1 Ltd. 17.04.2013 15.10.2013 70 312,75

Page 79: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

63

IDA-RWSSP-SW-2013-2 Rehabilitation

of rural water supply system in Suulu-

Maimak, Kuru-Maimak, Joon-Dobo

FMU-1 Ltd. 17.04.2013 16.10.2013 165 213,06

IDA-RWSSP-SW-2013-3 Rehabilitation

of rural water supply system in Bash-

Kuugandy

OJSC Jumgalsuukurulush 19.04.2013 16.12.2013 174 118,86

IDA-RWSSP-SW-2013-4 Rehabilitation

of rural water supply system in Moldo-

Asan

FMU-1 Ltd. 28.05.2013 27.09.2013 72 690,76

IDA-RWSSP-SW-2013-5 Drilling new

well for rural water supply system in

Jergez

Issyk-Kul Plus Ltd. 29.05.2013 13.09.2013 39 471,24

IDA-RWSSP-CW-2014—5

Rehabilitation of rural water supply

system in Chon-Kara-Buura

Pobeda Ltd. 09.04.2014 30.09.2014 37 843,52

IDA-RWSSP-CW-2014—6

Rehabilitation of rural water supply

system in Ogonbaev, Kalba, Chyiyrshyk

JV: “Yug-Stroyservis”

OJSC and Nuska Ltd.

09.04.2014 30.09.2014 45 801,60

IDA-RWSSP-CW-2014—7

Rehabilitation of rural water supply

system in Tort-Kul, Tuura-Suu

CJSC

Kochkorsuukurulush

09.04.2014 30.09.2014 65 031,91

IDA-RWSSP-CW-2014—8

Rehabilitation of rural water supply

system in Kum-Dobo, Buguchu

CJSC

Kochkorsuukurulush

09.04.2014 30.09.2014 41 516,38

IDA-RWSSP-CW-2014—9

Rehabilitation of rural water supply

system in Kosh-Dobo

FMU-1 Ltd. 09.04.2014 30.09.2014 153 057,60

IDA-RWSSP-CW-2014—10

Rehabilitation of rural water supply

system in Kyzyl-Oktyabr’, Madaniyat,

Urmaral, Kok-Tash, Tash-Kuduk

Pobeda Ltd. 09.04.2014 30.09.2014 48 761,83

IDA-RWSSP-CW-2014—11

Rehabilitation of rural water supply

system in Arashan, Kozuchak, Kum-

Aryk

CJSC Talas-MSPMK 09.04.2014 30.09.2014 96 110,46

IDA-RWSSP-CW-2014—13

Rehabilitation of rural water supply

system in Ak-Muz

CJSC

Kochkorsuukurulush

16.04.2014 30.09.2014 136 491,37

IDA-RWSSP-CW-2014—14

Rehabilitation of rural water supply

system in Baktuu-Dolonotu

“Yug-Stroyservis” OJSC 16.04.2014 15.10.2014 154 289,33

Page 80: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

64

IDA-RWSSP-CW-2014—15

Rehabilitation of rural water supply

system in Kazybek, Kyzyl-Tuu, Kara-

Bulun

JV: FMU-1 Ltd. plus

Poisk Ltd.

16.04.2014 15.10.2014 286 882,29

IDA-RWSSP-CW-2014—17

Rehabilitation of rural water supply

system in Shoro

OJSC Jumgalsuukurulush 16.04.2014 15.08.2014 49 788,76

IDA-RWSSP-CW-2014—12

Rehabilitation of rural water supply

system in Kyrgyzstan, Pervomaiskoye,

Joon-Korgon

Pobeda Ltd. 30.04.2014 29.09.2014 53 177,05

IDA-RWSSP-CW-2014—16 Rehabilitation of rural water supply

system in Ornok

OJSC Jumgalsuukurulush 03.06.2014 03.10.2014 120 708,82

Subtotal: 2 793 354,73

Grand total: 9 653 448,41

Note on the achieved efficiency of implemented subprojects – civil works have been completed

in full amounts as per all approved detailed designs.

18 contracts for improvement of sanitation facilities at schools in 18 villages have been

implemented for the total of USD 263 733,24 (details by contracts are enclosed in Annex 2).

Disbursements to implemented RWSSP-2 sanitation subprojects

No. and name of Contract Contractor Date of

Contract

signing

Date of

Contract

completion

Disbursement,

USD

IDA-RWSSP-CW-2014-23/1 Rehabilitation of

12-hole toilet at secondary school n.a. K.Orozov

in Korumdu, Issyk-Kul Raion, Issyk-Kul

Ai-Kol Kurulush

Ltd.

30.06.2014 30.10.2014 16 054,54

IDA-RWSSP-CW-2014-23/2 Rehabilitation of

toilet as secondary schools n.a. B.Mambetov in

Tort-Kul, Ton Raion, Issyk-Kul

Ai-Kol Kurulush

Ltd.

30.06.2014 30.10.2014 17 673,45

IDA-RWSSP-CW-2014-23/3 Rehabilitation of

14-hole toilet at secondary school n.a.

E.Kerimgaziev in Temir, Issyk-Kul Raion, Issyk-

Kul

Ai-Kol Kurulush

Ltd.

30.06.2014 30.10.2014 16 762,61

IDA-RWSSP-CW-2014-23/4 Rehabilitation of

18-hole toilet at secondary schools n.a.

K.Kudaiberdiev in Kashat, Issyk-Kul Raion,

Issyk-Kul

Ai-Kol Kurulush

Ltd.

30.06.2014 30.10.2014 17 100,28

IDA-RWSSP-CW-2014-23/5 Rehabilitation of

12-hole toilet at secondary school n.a. T.Ataev in

Baktuu-Dolonotu, Issyk-Kul Raion, Issyk-Kul

Ai-Kol Kurulush

Ltd.

30.06.2014 30.10.2014 16 595,95

IDA-RWSSP-CW-2014-24 Rehabilitation of

toilet at secondary school n.a. N.Usenaliev in

Kazybek, At-Bashy Raion, Naryn

Marin-Stroi Ltd. 16.07.2014 16.10.2014 26 268,88

Page 81: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

65

IDA-RWSSP-CW-2014-25/1 Rehabilitation of

toilet at secondary school n.a. R.Osmonov in

Joon-Dobo, Kara-Buura Raion, Talas

Pobeda Ltd. 30.06.2014 30.10.2014 8 519,26

IDA-RWSSP-CW-2014-25/2 Rehabilitation of

toilet in secondary school n.a. A.Borubaev in

Kara-Oi, Talas Raion, Talas

Pobeda Ltd. 30.06.2014 30.10.2014 10 679,74

Subtotal: 129 654,71

IDA-RWSSP-CW-2014-18/1 Construction of

toilet in secondary school n.a. S. Karalaev in Ak-

Olon, Ton Raion, Issyk-Kul

Ai-Kol Kurulush

Ltd.

20.06.2014 20.10.2014 12 329,36

IDA-RWSSP-CW-2014-18/2 Construction of

toilet in secondary school n.a. A.Kayduev in

Koochu, Tyup Raion, Issyk-Ku

Ai-Kol Kurulush

Ltd.

20.06.2014 20.10.2014 15 204,29

IDA-RWSSP-CW-2014-18/3 Construction of

toilet in secondary school n.a. M.Tynaev in

Orgochor, Jeti-Oguz Raion, Issyk-Kul

Ai-Kol Kurulush

Ltd.

20.06.2014 20.10.2014 15 953,71

IDA-RWSSP-CW-2014-19/1 Construction of

toilet in secondary school n.a. S.Sadybakasov in

Bash-Kuugandy, Jumgal Raion, Naryn

Nuska Ltd. 19.06.2014 19.10.2014 11 984,94

IDA-RWSSP-CW-2014-26 Construction of toilet

in secondary school named after I. Orozaliev in

Ornok, Jumgal Raion, Naryn

Bem-As Ltd. 10.07.2014 10.10.2014 11 745,19

IDA-RWSSP-CW-2014-19/3 Construction of

toilet in secondary school named after K.

Kerimaliev in Kyzyl-Tuu, At-Bashy Raion, Naryn

Nuska Ltd. 21.06.2014 21.10.2014 12 718,96

IDA-RWSSP-CW-2014-19/4 Construction of

toilet in secondary school named after E.

Meymanov in Kosh-Dobo, At-Bashy Raion, Naryn

Nuska Ltd. 21.06.2014 21.10.2014 12 657,13

IDA-RWSSP-CW-2014-20 Construction of toilet

in secondary school named after E. Kapalov in

Yntymak, Bakai-Ata Raion, Talas

Nuska Ltd. 19.06.2014 19.10.2014 12 803,83

IDA-RWSSP-CW-2014-27/1 Construction of

toilet in secondary school named after J.

Toychubekov in Kyzyl-Kyrgyzstan, Bakai-Ata

Raion, Talas

Bem-As Ltd. 10.07.2014 10.10.2014 16 059,82

IDA-RWSSP-CW-2014-27/2 Construction of

toilet in secondary school named after Nurbekov in

Kum-Aryk, Talas Raion, Talas

Bem-As Ltd. 10.07.2014 10.10.2014 12 621,30

Subtotal: 134 078,53

Grand total: 263 733,24

The project built and rehabilitated 40 reservoirs, 24 wells, installed new water towers and

chlorination stations; supported replacement of old and economically inefficient pumps and

electrical equipment with energy efficient installations manufactured by Grundfos and having

3- years warranty and service period; rehabilitated existing and built new reservoirs; built 2*700

m3 new reservoirs in Chelpek. In Kashat, 700 m3 reservoir has been rehabilitated. 50 m3 water

tower has been built in Baltabay while 2*500 m2 reservoirs rehabilitated in Yntymak. In Tugol-

Sai, 500 m3 reservoir has been rehabilitated.

Page 82: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

66

For instance, one of the project achievements and success is that 100% of water connections in

Korumdu, Jele-Dobo and Baltabay have meters.

Maintenance equipment

Computers for CDWUU

For improvement of CDWUU subscriber awareness and fee collection, in 2013-2014 ARIS

procured and handed over to CDWUU 80 sets of computer equipment (PC, multifunctional

devices, UPS devices) for introduction of billing system. All 80 CDWUU provided with

equipment have been trained. The CDWUU chairpersons and accountants received training in

introducing and operating the billing system. They noted that this system was very user-

friendly and accessible to use.

Personal safety apparel for water disinfection

In order to ensure safe water supply and to assist in improving disinfection of water by

chlorination, a need emerged to provide CDWUU with primary means of protection during

chlorination process. So, 35 CDWUU have been provided with personal protection means such

as overalls, gloves, caps, masks, goggles, rubber boots. In addition, each of 35 CDWUU

received 50 kg of hypochloride for water disinfection.

Computers and laboratory equipment for Department of Disease Prevention and State

Sanitary and Epidemiological Surveillance (SES – sanitary and epidemiological service)

Technical assistance has been provided to SES by supplying computers and laboratory

equipment in order to improve the SES capacity and performance in the water supply and

sanitation sector.

One of the areas for capacity building is support to improvement of Raion SES for water quality

control and monitoring of parasitic diseases. For this purpose, ARIS developed a database with

relevant software that will be placed on the Department’s Web-page. Also, to operate the

database ARIS procured and handed over computer equipment to the Department. The list of

equipment includes 30 sets of PC and office equipment (system block, monitor, multifunctional

device, UPS) and a server for database. The database is introduced both for Central Department

and its units in Bishkek and 13 target Raion services under RWSSP-2.

All specialists from 13 Raion pilot SES received training in database and started introducing

this system at the central and Raion level.

Equipment for water tests has been procured for 13 pilot Raion SES laboratories for the total of

59 178 USD SES specialists have been trained locally to operate the equipment.

Special machinery

The Project provided special machinery for water supply systems operation including 7 diggers,

30 tricycles (motor scooters), 60 kits of equipment and tools and 60 generators for the total of

USD 298 090. So, special machinery and equipment have been supplied to 63 CDWUU.

Detailed designs, studies, preparation of bidding documents and technical supervision

A contract with OJSC Design Institute “Kyrgyzgiprostroy” was signed on January 26, 2012 for

preparation of detailed designs for procurement of construction works for rehabilitation of 26

problem subprojects in the villages of Issyk-Kul, Naryn and Talas Oblasts. Specialists of design

institute inspected 26 these subprojects of Phase 1 in Issyk-Kul, Naryn and Talas.

An agreement between ARIS and the Department of Disease Prevention and State Sanitary and

Epidemiological Surveillance was signed and cost estimates were prepared for laboratory tests

of 16 potable water sources in 26 sub-projects.

Page 83: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

67

Because of high workload for the Design Institute detailed designs for some problem

subprojects were delayed.

ARIS engineers prepared cost estimates and excluded works tables for 13 problematic

subprojects and sent to the Bank for review. During preparation of BoQ for four subprojects

(Tort-Kul, Arashan, Kalba, Yntymak) modifications were introduced according to

recommendations of the Bank’s consultants i.e. orifices were replaced by pressure reducing

valves in the design. Also, pre-bid conference was held where the bidders had an opportunity

to learn more details of bidding documents including materials and equipment to be applied for

the works.

Meetings held with AO and CDWUU representatives were devoted to water economy, loss

reduction, replacement of street standpipes by household connections, installation of meters

and proper operation of submersible well pumps; mitigation the risk of repeated bidding and

singing of agreements between ARIS and Aiyl Okmotu.

Prior to bidding advertisement and because of limited resources, upon additional review of

market cost for works the design institute together with ARIS engineers prepared detailed

design estimates and BoQs for completed 13 problematic subprojects.

Modifications to specific types of works not requiring qualification / experience were

introduced in detailed designs and BoQ for 13 problematic subprojects. In addition, agreements

were prepared and signed between ARIS and AO for performing such works.

The detailed designs approval procedure for 13 problematic subprojects brought to delay with

advertisement of biddings for works.

Designs of sanitation facilities were provided for construction as agreed with UNICEF.

Meetings were held with ARIS engineers to discuss designs of sanitary facilities to be used

under RWSSP-2.

On February 28’2014, ARIS distributed requests to 36 AO covered by the Project whether they

were interested in construction/rehabilitation of sanitation facilities at schools as part of RWSSP-

2.

As of March 14, applications were received from 49 schools of 36 participating AO. Members

of selection committee reviewed applications received from AO, documents of 49 schools,

photographs of sanitation facilities status, letters of guarantee from AO on willingness to

contribute 5% cofinancing and intention to increase financing for WSS, existence and operation

of school parliaments and Parents’ Committees as well as sanitation and hygiene education plan

for schools.

In preparation of school in-door sanitation facilities rehabilitation designs, three engineering

consultants were hired to prepare self-assessment forms for sanitation works in selected schools

of Naryn, Talas and Issyk-Kul. The Consultants prepared BOQ, technical specifications and

drawings. Standard-type schools with in-door sanitation facilities were selected from the three

pilot Oblasts for rehabilitation.

Based on applications received and in line with evaluation criteria, 10 schools were selected for

construction of outdoor sanitation works and 8 schools for rehabilitation of in-door facilities

(toilets and washstands).

As a result, outdoor facilities were built at 10 schools and 8 schools had their in-door sanitation

facilities rehabilitated.

On-site technical supervision of subprojects was provided by ARIS supervisors and by AO

technical supervisors while AO (Clients) kept continuous control over the quality of civil works.

Author’s supervision of the sanitation works construction at 10 schools was delivered by the

Contractor, Musai Ltd. who developed the detailed designs.

Page 84: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

68

Training in technical supervision procedures has been delivered for RWSSP-2 infrastructure

engineers and technical supervisors in order to increase their technical cpacity. The training has

also been attended by BOUIP, VIP-2 and Debt Swap-2 engineers and technical officers, 37

participants in total.

Resettlement Policy

Surveys have been held in order to meet WB Resettlement Polict, in 10 villages, viz. Korumdu,

Kashat, Koochu, Chelpek, Ak-Kochkor, Jele-Dobo, Baltabay, Uch-Emchek, Tugol-Sai, Tort-

Kul, Kyzyl-Tuu, Ornok and Kalba. The survey identified 118 PAP. The amount of

compensation payments to PAP made KGS 1 979 254.

Below is the list of subprojects surveyed for RAP.

List of subprojects surveyed for RAP

Contract No. / title Numbe

r of

PAP

Assets affected Compensati

on, Som

RAP status Further

actions

RWSSP-2/W/NCB/IK5-2-09

Rehabilitation of RWS in

Korumdu

14 Gardens, alfalfa, fruit trees (apple,

apricot)

818 960 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2011-3

Rehabilitation of RWS in Uch-

Emchek

8 Crop fields, beans, trefoil, barley,

hay

26 100 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2011-6

Rehabilitation of RWS in Jele-

Dobo

8 Crop fields; alfalfa, garlic, potatoes,

pea, raspberry. Trees: willow,

poplars, apple trees

142 925 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2011-5

Rehabilitation of RWS in Ak-

Kochkor

14 Land parcels in the village, trees

(willow, poplars, Siberian elm),

apricot

275 698 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2011-7

Rehabilitation of RWS in Baltabai

41 Land parcels with trees (willow and

poplar)

521 985 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2011-4

Rehabilitation of RWS in Tugol-

Sai

16 Land parcels with trees (willow and

poplar, Siberian elm); fences of

sun-dried bricks

105 005 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2011-8

Rehabilitation of RWS in Koochu

1 Land parcel with willow trees 1 800 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2011-2

Rehabilitation of RWS in Chelpek

5 Land parcels with trees (willow and

poplar)

10 255 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2014—15

Rehabilitation of RWS in

Kazybek, Kyzyl-Tuu, Kara-Bulun

7 Hay fields 15 600 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2014—16

Rehabilitation of RWS in Ornok

1 Hay field 48 660 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2014—6

Rehabilitation of RWS in

Ogonbaev, Kalba, Chyiyrchyk

1 Alfalfa 12 000 Approved

by WB

Compensation

paid to PAP

IDA-RWSSP-CW-2014—7

Rehabilitation of RWS in Tort-

Kul and Tuura-Suu

2 Alfalfa and wheat 266 Approved

by WB

Compensation

paid to PAP

Total 118 1 979 254

Page 85: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

69

Environmental management

Monitoring of environmental activities has been held during subprojects implementation on a

regular basis viz. impact on land, surface/ground waters, air. Necessary impact mitigation

measures have been taken: construction sites brought to proper conditions by cleaning up from

wastes, installing garbage bins and toilets. Special areas have been arranged for construction

machinery.

Environmental preservation checklist has been developed and included activities and

requirements to contractors for avoiding, mitigating and diminishing adverse environmental

impact during the subprojects implementation.

Operational safety

Monitoring of operational safety measures showed that fire safety was secured in due manner.

Operational safety instruction logs were available at the construction sites. Workers had special

protective clothes, boots, helmets and gloves. There were also first-aid kits available at the sites.

The sites have been kept clean and safe conditions in order to avoid incidents.

Component В. Program on sanitary and hygiene education

Agreement for implementation of this component has been signed between ARIS and UNICEF

on June 17, 2013.

Activities have been completed under this component for pilot villages at the community and

school level. The entire work in the pilot communities has been aimed to social mobilization in

order to involve people in improvement of sanitation and hygiene practices at the

school/household level.

Establishing stakeholders and their involvement in the Project

Establishing of stakeholders was at both Oblast and local level. For Oblast level, it

included workshops in the capitals of three pilot Oblasts. Participants were represented

by Raion governors / officials, education departments, Raion Family Practitioners

centers, Raion SES, heads of AO from pilot areas, managers of Raion CDWUU

associations and Raion health committees. The workshops adopted a resolution to

support the Project activities.

At the local level, meetings have been held in the pilot villages inviting community

members, partners from NGO and government authorities, RHC, CDWUU, rural clinics,

Aiyl Kenesh members Aiyl Okrug members being 2156 people altogether including

1100 men and 1056 women.

Sanitation and hygiene promotion in communities

Sanitation and hygiene have been promoted in the communities by training of community

members in PHAST method and training of students using UNICEF methodology for WASH

in Schools.

Community training has been delivered in two stages. Stage 1 covered VHC members during

two-day training by PHAST method, 556 VHC members in total represented by 427 women

and 129 men from 55 pilot villages.

During second stage the VHC trained members of all households in pilot villages. 30101

participants have been trained in total.

Training of students in sanitation and hygiene by UNICEF methodology for WASH In

Schools. The first stage trained two teachers from each school as trainers – 87 women and 23

men making 110 trainees altogether.

Page 86: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

70

Facilitating trainers, in turn, trained teachers of primary classes and classroom teachers in their

respective schools covering 1 957 trainees in total represented by 414 men and 1543 women.

Extra-curricular activities have been held in each class of 1st to 11th grades covering all students

of schools.

For extra-curricular classes, each school has been provided with 5 to 10 manuals “WASH in

schools” developed by UNICEF. For higher efficiency of classes and developing proper

hygienic behavior, UNICEF handed over a hand-washing demonstration kit GloGerm.

Social mobilization in pilot communities

Social mobilization in pilot villages has been carried out in various ways such as:

Community meetings in the beginning and upon completion of the project in each of

pilot villages. As a result, stakeholders were established at the village level.

Exchange visits between villages.

o In Issyk-Kul, exchange visit took place on March 5’2014 in secondary school

named after K.Tailakov, Tuura-Suu village of Ton Raion. It invited heads of

Aiyl Okmotu, Aiyl Kenesh members, school management, CDWUU, parents’

committees and VHC from pilot villages hosting 110 participants including 55

women. The visit showed that it could be possible to maintain school toilets in

proper condition and ensure access to water for students.

o Naryn. Exchange visit dedicated to World Water Day took place on March

22’2014 in Kazybek village (At-Bashy Raion) and on March 23’2014 in Bash-

Kuugandy village, Jumgal Raion. Exchange visits included around 100

participants.

o Talas. Exchange visit between villages has been held on March 27’2014 and

dedicated to World Water Day. This event took place in community club of

Kum-Aryk village, Talas Raion. Around 160 villagers participated in the visit

including government officials from Bakai-Ata, Talas and Kara-Buura raions,

Aiyl Okrug, school management/teachers, CDWUU, VHC and parents

committees etc. The participants shared their experiences of social mobilization,

PHAST training in their villages and overcoming the emerging difficulties etc.

almost all schools presented their wall newspapers, contests of paintings/essays,

design sketches of school and household toilets etc.

Parents’ conferences proved to be efficient means of outreach activity. They discussed

the importance of S&H for child health, sanitation and hygiene status in schools,

personal hygiene rules, frequency of changing underwear and bedclothes for a child

treated oxyuricide, mobilization of local resources to ensure adequate financing of

O&M costs for WASH facilities. Many parents began realizing the need for financial

support to schools for maintaining the WASJ infrastructure.

Working with school parliaments. Each school’s parliament has been invoked to

introduce WASH principles. This included revival of sanitary assistants elected out of

students. Jointly with parliaments the sanitary assistants organized contests for “Most

Clean Classroom”, monitored the appearances and tidiness of students/classrooms, held

Saturday cleaning days around schools, contests of paintings, essays and newspapers

devoted to “Water, Sanitation and Hygiene”. Results of contests have been summarized

and highlighted at school lineups.

Raion-level round tables for discussion of O&M costs for WASH facilities of schools.

In Issyk-Kul Oblast, round tables took place on April 1’2014 in Karakol and on April

2’2014 in Balykchy; Naryn: April 3-4 in Kochkor and Naryn, respectively. Meetings in

Page 87: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

71

Talas have been held on April 15 for Talas and Bakai-Ata Raions, April 16 – in Kara-

Buura Raion. Representatives from Raion governments, education departments, SES,

Family Practitioners Centers, Aiyl Okmotu, school management, CDWUU, VHC, HPC,

RHC and other stakeholders took part in these events. The participants have been

provided with data on standard rates and actual O&M costs for WASH both in-kind and

cash.

Village-level round tables. Round tables have been organized with the support from

Aiyl Okmotu of respective Raions and attended by school management, CDWUU,

VHC, parents committees, school parliaments and other stakeholders. Participants have

been informed of maintenance costs for sanitation facilities, hygienic needs (soap, toilet

paper) per student per year and expense rates for health aids.

Awareness campaign

Awareness campaign has been implemented through celebration of World Water Day, release

of promotional and propaganda leaflets/videos, creation of Webpage, general

school/classroom stands with visual information, performance by famous singers and amateur

performances by people from pilot villages.

World Water Day. Activities devoted to World Water Day have been implemented in

all pilot villages. These events involved parents committees, WASH committees, VHC

and CDWUU. Activities included general school lineups, “homerooms”, “Clubs of the

Funny and Inventive”, performances, contests of wall newspapers, handicrafts,

sayings/proverbs, quizzes, contests “AkyyaAitysh” and “Sarmerden”. Note on the

special role of local self-governance body in Orgochor Village (Jeti-Oghuz Raion,

Issyk-Kul) that allocated funds for awarding the village health committee with prize

money of 5000 Som for contribution to successful implementation of local project

activities and 300 Som to five students and during spring vacation the winners of the

contest for “Most clean classroom” have been taken to Karakol to visit the museum and

memorial complex named after Nikolai Przhevalskiy. During each activity members of

Health Promotion Association awarded sports accessories to each of the schools as

recognition gifts.

The World Water Day’s celebration coincided with exchange visit accompanied by

performance of improvising Akyn (story-tellers) and Komuz players Aaly Tutkuchev

and Altynbek Akelov. AHP made presentations of the project progress followed by

reports of invited Raion deputy governors, directors of VHC, CDWUU, schools and

members of parents committees. This event made good effect leaving positive emotions

in the hearts of the participants.

3 videos produced and broadcasted over national and Oblast TV: “Always wash hands”,

“School toilets as seen by children” and animated graphics.

Three types of posters produced and devoted to solicitous attitude to water, proper

sanitation and hygiene at the household level and the importance of washing hands with

soap. Posters have been distributed to all pilot communities and displayed in schools,

VHC and other public places.

20 000 copies of a comic book for children “Let’s keep it clean” have been distributed

to all schools for reading by junior students.

Web-page on basic health principles developed.

General school/classroom health points established in every school.

Deworming

Page 88: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

72

Laboratory tests of 25 students (1-4 grades) from each school have been taken twice under

Component B. The first testing revealed 211 children of which 209 were treated. 1 child from

Ak-Olon village was not treated due to moving to Balykchy. Treatment costs have been paid

by parents, with Piperazine, Albendazol and Mebendazole medicines. All contacted persons

(parents and members of infested childrens’ households) have been sent to Raion SES for

medical survey. In Naryn, one child was not found because of wrong personal data provided.

68 child infestation cases have been revealed during second test. Specialists of rural clinics

prescribed treatment for those children. In addition, meetings have been held with their parents

to explain the need for repeated treatment.

Comprehensive analysis of needs and annual costs for consumables and services required

for routine and limited extraordinary maintenance of proposed water, sanitation and

hygiene facilities in schools and health points

The analysis has been made on the basis of data obtained from schools in RWSSP-2 pilot

villages, Ministry of Education and Science (MoES), Ministry of Health and its local units and

from municipalities. The needs/costs analysis of consumables and services has not been carried

out for health points due to the decision not to construct sanitation facilities therein.

According to MoES, in 2013 within the standard budgetary financing, the average expenses in

rural schools consisted of 6.2 Som per student per year. Since actual percentage allocation of

these expenses in 2013 was estimated at 62.7% of this budget, the actual average expenses in

rural schools totalled to 3.89 Som per student per year.

Based on data obtained from schools actual O&M costs for WASH facilities have been

estimated. In the pilots schools of Talas Oblast, 27.5 Som per student per year have been spent

for operation and maintenance of WASH infrastructure on average. For comparative analysis,

similar information has been requested from one the private schools in Bishkek according to

which the school spends 196.6 Som per student per year. According to the Russian Federation’s

sanitary standards, average annual expenses for household goods, disinfectants and health

goods as converted to Kyrgyz Som, were 287 Som per student per year.

Thus, estimated need in cash for purchase of household goods, cleaning / disinfectant agents

and hygiene items per student per month (current local market prices) is 23.5 Som (using liquid

soap) and 28.7 Som (solid soap). With nine academic months the amount needed was 211.5

Som and 258 Som for whole year of 2013, respectively. These data correlate with and are

validated by actual expenditures of the secondary school in Tuura-Suu Village, Ton Raion,

Issyk-Kul.

Establishing institutional framework for sustainability of WASH infrastructure at schools

Establishment of WASH committees composed of school management, parents

committees, VHC, CDWUU, Aiyl Okmotu, school parliament and local Kenesh

members. Objectives of WASH committees were to assist management of schools in

identifying and planning resources for financing O&M costs of WASH facilities;

implementing activities for changing the hygienic behavior of students; monitoring of

WASG facilities status at schools etc. Many WASH committees, in conjunction with

parents committees, undertook to organize supplies of soap and paper towels and

schedules of procuring hygiene items.

Approval of Standard Operational procedures (SOP) for O&M of sanitation and hygiene

facilities in each school from pilot villages. SOP are meant for supervision of proper

operation and maintenance of toilets, hand-washing facilities and garbage bins. They

have been approved by headmasters of schools and countersigned by each person in

charge of sanitation facilities. SOP are displayed by relevant sanitation facilities in

schools and/or offices of respective persons in charge.

Page 89: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

73

Memoranda of cooperation have been signed for maintaining adequate level of school

sanitation and hygiene between schools, Aiyl Okmotu, CDWUU, VHC and parents

committees. They are aimed to ensure better cooperation and coordination in the sphere

of S&H education, sustainability of WASH facilities operation, increased public

awareness of S&H practices both in schools and among community members.

Water connections have been built in 9 schools and 144 wash-stand installed over the project

period as part of the Healthy Nutrition Program.

Oblast Total

households

Of these,

trained HH

Toilets

improved

Wash-stands

upgraded

Began

using soap

Use boiled

water

Arranged

garbage pits

Issyk-Kul 6550 85 7 16 44 16 3

Naryn 5578 84 26 30 34 86 34

Talas 8806 79 3 15 34 32 4

Total 20934 248 36 61 112 134 41

Activities in villages

Cleaning days have been held in schools to remove garbage, clean ditches up and other works

including installation of garbage bins. In Orgochor, 20 garbage bins have been installed with

support from Aiyl Okmotu and local Kenesh.

In Jele-Dobo, the VHC extended its membership. Nine households had ventilation conduits

installed in toilets as a result of training.

A wash-stand, liquid soap, paper napkins and toilet paper have been procured by the school in

sufficient quantities. Four wash sinks have been rehabilitated in the dining room and self-made

tanks for water boiling are in place and connected to wash sinks. Carbon boxes are available

for waste paper collection. In the school named after B.Ismailov, parents installed 7 wash-stands

in classrooms, purchased 11 waste buckets, liquid soap, paper napkins and toilet paper. Self-

made rolls are installed in the toilets.

In Ak-Kochkor Village, water pipeline has been connected at the school years and standpipe

installed.

The schools in Orgochor and Tort-Kule villages procured thermo pots and one-use plastic cups.

In Burma-Suu, children carry potable water in plastic bottles. The intention is to connect the

school local water supply system.

In addition, it is worth noting on positive impact on schools not covered by the Project. In the

secondary school named after Imanov in Jeti-Oghuz Village, parents of students installed wash-

stands and garbage buckets in 9 classrooms and procured liquid soap, paper napkins and toilet

paper.

Ornok. Through support from Aiyl Okmotu and parents, all classrooms are provided with wash-

stands; construction of sports complex with shower and water connection is in progress. 13

additional wash-stands have been supplied in total.

In Atai Ogonbaev school, the dining and cooking rooms are connected to water supply system.

Four wash-stands have been installed at the entrance to dining room while waste water is

disposed to a septic tank.

In Yntymak, the school has been connected to water supply and wash-stands installed. Also,

water boiling tank has been installed.

Page 90: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

74

Potable water supply, wash-stands and towels for primary classes has been introduced in the

school of Kopuro-Bazar Village. The WASH committee ensures also supply of soap and paper

napkins.

Component С. Institutional capacity building

The principle objective if Component “Institutional capacity building” is to build the capacity

of institutional framework and capacity for sustainable development of water supply and

sanitation sector. To achieve the objective, the component includes the following goals and

activities:

Support development of the Water Supply, Water Disposal and Sanitation Sector

Strategy of the Kyrgyz Republic;

Review legislation in the field of water supply and water disposal;

Create database and GIS interface;

Develop national financial model for water supply and water disposal development;

Advisory support of chlorination in disinfection of potable water;

Review technical norms and standards in the field of water supply and sanitation;

Build the capacity of LSG bodies and CDWUUs in managing and maintaining water

supply systems to provide population with high quality potable water supply to

population.

Support of development of the Water Supply, Water Disposal and Sanitation Sector

Strategy of the Kyrgyz Republic

1 June 2012, the Government of the Kyrgyz Republic issued an Order No 239-p “On

establishment of an Interagency Working Group on development of a Program (Strategy) for

development of water supply and water disposal in residential areas in the Kyrgyz Republic”.

To assist to the Working Group, a draft action plan was prepared for development of the

Program together with a preliminary structure and list of matters that might be included in the

draft Program as well as proposals on methodology and approaches to Program development.

To discuss and produce proposals to be included in the draft Sector Development Program,

round tables were arranged in the regions with participation of stakeholders- LSG bodies,

CDWUUs and NGOs from all oblasts. Following the round tables, proposals were collected

and sent for review by the Interagency Strategy Development Working Group.

In the purpose of development of the Draft State Program for development of water supply and

water disposal in residential areas in the Kyrgyz Republic 2014-2024, a consultant was selected

who produced the Draft Program based on review and analysis of documents and incorporating

the results of workshops, meetings and consultations with the representatives of stakeholders.

Draft State Program for development of water supply and water disposal in residential areas in

the Kyrgyz Republic 2014-2024, produced with the Project’s support, was approved by the

Decreed Government of the Kyrgyz Republic dated 24 September 2014 and sent for the

Parliament’s consideration.

Review of legislation in water supply and water disposal sector

To support implementation of the State WSWD Sector Development Program, the Project

envisaged review and analysis of the current legislation regulating the sector. In this regard, a

Local consultant was selected. Following analysis of legislation for potable water supply, the

Consultant identified discrepancies, gaps and deficiencies in regulations. In review and analysis

of legislation, a number of meetings and discussions with DWSWD and member of the

Working Group, whereupon recommendations on improvement of legislation for potable water

Page 91: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

75

supply were provided for more effective implementation of the State Program for development

of water supply and water disposal in residential areas. Final report, based on legislation review,

incorporating recommendations on harmonization of regulations in the sector, was sent for

review to the Government of the Kyrgyz Republic, particularly to the SAAC and DWSWD.

With adaption of the State WSWD Sector Development Program, the activity on revision and

development of new regulations mentioned in the report started.

Development of sector database and GIS interface

International Consultant for development of the State WSWD Sector Development strategy

provided indicators of sector performance and service quality as well as a questionnaire for data

collection and the guidelines for filling the questionnaire. The indicator and questionnaire were

discussed and agreed with DWSWD and Working Group. In compliance with the

recommendations provided by the Review Mission of the World Bank, a decision was made to

hire a consulting firm for collection of data, creation of database and GIS interface. In total,

817 were collected. All of them were entered in the database. The Consultant also developed

software of the database: module for entering and displaying data through web-interface,

desktop application for data entering and GIS interface for cartographical displaying of data.

Besides, an addendum to the Contract signed with the consultant for development of similar

database for the Department for disease prevention and sanitary and epidemiological

supervision was drafted and signed in the purpose of supervision and monitoring of parasitic

diseases and water quality. Therefore, two databases and GIS interface for DWSWD and SES

were developed and introduced under the project.

Development of national financial model for WSWD sector development

To develop financial model for WSWD sector development, tender was conducted and contract

signed with international consultant company “Aspiro”. The Consultant collected information

and assessed the current situation, developed an investment plan based on the working financial

model. This financial model will serve as an objective, transparent and updatable tool to get a

plan for investment to the sector that will ensure a basis for investment in 5 and 10-year cycles

(and further) of development planning as well as of annual budgeting.

The model also reflects conclusions and discrepancies between the hands-on experience and

the consequences caused by a certain service provisioning investment strategy. Therefore, the

model serves as a prompt message to make real the improvements and upgrades in the sector in

the process of implementation at state, oblast, and raion levels.

Sector investment plan combined with the investment model may enable the water supply sector

of the Kyrgyz Republic to analyze financial consequences upon achievement of targets set forth

in the current and future strategies. Besides, there is an opportunity to get a feasible tool for

monitoring to compare the objectives with achievements in various subsectors and oblasts.

Additionally, the model may ensure the ways of mitigation of discrepancies in allocation of

funds between subsectors and categories of population (i.e. between water supply and sanitation,

or between city and village) to extend cooperation within the sector.

This financial model was provided to DWSWD accompanied with training of its staff in use of

the financial model.

Advisory support in chlorination for disinfection of potable water

To provide proposals on improvement of water quality situation and on building the capacity

of CDWUUs in disinfection, a contract was signed with an international consultant. The

International Consultant assessed the current situation and technological solutions and

produced a report and guidelines for chlorination. In Quarter II, 2014, a presentation of the

report was held with participation of key stakeholders, LSG bodies, and CDWUUs. The

presentation introduced the participants in issues identified, recommendations on improvement

Page 92: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

76

of situation, optimization of technological solutions, construction/installation and operation of

structures and equipment for disinfection of potable water. The consultant also conducted

training of trainers who, in their turn, started training of CDWUU in chlorination.

Review of technical standards (SNIPs) in water supply and water disposal

Tender was conducted and contract was signed with an international company that reviewed

the current norms and technical standards in the field of WSWD. Based on the analysis, a report

was produced with recommendations on optimization of technical standards. In preparation of

the report, consideration was given to the results of meetings with stakeholders, field-specific

state bodies, design institutes and experts. The report was cycled among all stakeholders,

following which a round table was arranged for discussion and feedback. By the end of the

project, a final report was produced, incorporating the results of round tables and all comments

and proposals received. The report was sent for consideration to SAAC and DWSWD.

LSGB and CDWUU capacity building

Agreements

Standard agreement between AOs and CDWUUs was drafted for provisioning of rural water

supply services. Cooperation agreements for provisioning of rural water supply services were

signed between AOs and CDWUUS.

Exchange visits

Example of effective management of water supply system and development of CDWUU is

Chyrak, Korumdu, Orgochor, Baltabai and Jele-Dobo in Issykkul Oblast. Virtually each

household has electronic water meters and water heaters installed. In order to spread successful

experience, exchange visits to Issykkul Oblast were arranged for all ARIS oblast specialists,

LSGB representatives and region CDWUUs. The participants of the exchange visit were shown

subprojects in Korumdu, Temirovka, Orgochor, Baltabai and Chyrak villages. During the

exchange visit, the participants were able to ask questions to AO head, CDWUU chairpersons,

technical supervision engineers and other project specialists. Following the exchange visit

round tables with participation of deputies of local keneshes, LSGBs, CDWUU administration

bodies, NGOs were arranged at aiyl aimak level to discuss the mechanisms of effective

management of water supply system and the improvement of relations with consumers in

collection of tariffs for use of water etc.

TO exchange experience and practice that will be useful in CDWUU capacity building and in

indicating mechanisms of improvement of water use tariff collection process, exchange visits

for local AK deputies, AO heads and CDWUUs should be arranged.

Experience in conduction of exchange visits shows high efficiency, particularly in terms of

introduction of new approaches (individual connections through water meters), setting the

system of registering of consumers and accounting of water supply.

Training

ARIS specialists conducted assessment of CDWUU staff needs in training and capacity

building. The International Consultant for development of the WSWD Sector Strategy proposed

training materials and tools for business planning in water utilities and investment management.

These materials and training modules earlier developed by local consultant as well as training

needs assessment have been provided by a selected consulting company that in its turn adopted

those and adjusted for more effective training of CDWUU and LSGBs.

At the beginning of implementation of the program, tender was conducted, 6 trainer-

consultants were selected (2 trainers for each oblast) to train LSGBs, CDWUUs and regional

employees of DWSWD. Two-day trainings were also conducted based on training modules

Page 93: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

77

developed earlier. Total 21 trainings were conducted in three oblasts. 578 people were trained

in those trainings. The training covered 159 CDWUUs of the first and second RWSSP phases.

Participants Naryn Talas Issyk-Kul Total

CDWUU chairpersons 55 38 66 159

CDWUU accountants 49 34 63 146

CDWUU carpenters 53 33 69 155

DWSWD chairpersons 2 1 2 5

Chairpersons of raion state

administration

1 1

АО chairpersons 42 26 44 112

Total 202 132 244 578

In Issykkul Oblast, Chyrak Village, trainings were arranged for the participants from Jety-

Oguz, Aksuu and Tyup Raions. During these trainings, exchange visits for participating

CDWUUs were arranged.

Following the trainings, LSGBs and CDWUUs started reconsidering tariffs with use of a new

methodology for tariff calculation. It is noteworthy that deputies of local keneshes, who

subsequently shared information with their colleagues, emphasizing water supply issues. For

instance, following training of two deputies, Ak-Myun aiyl kenesh (Naryn Oblast) decided to

allocated KGS 50,000 for development of two CDWUUS of subordinate area. In Aral aiyl

kenesh in Issykkul Oblast, during public hearings, all three CDWUUs of this aimak managed

to justify their grounds, including those regarding tariff calculation, on the necessity to finance

budget organizations; this matter was addressed positively. After training, representatives of

CDWUU of Issykkul Raion raised the initiative and visited Chyrak Village, Jety-Oguz Raion

for exchange of experience and best practices.

In line with recommendations provided by a WB Supervision mission, in the purpose of

improvement of further activities on building the capacity of LSGBs and CDWUUs, a decision

was made to hire a consulting firm to conduct trainings and training activities. Terms of

reference was prepared for selection of company and agreed with the World Bank. Training

was conducted and company (“Public analysis institute” NGO) was hired.

Local consultant conducted additional assessment of the needs of each 37 CDWUUs and

LSGBs. To conduct training, 2 training modules were produced. The training modules consist

of two-day trainings in administrative and financial management of CDWUUs and in relations

with consumers as well as two day training in water supply, engineering, water disinfection and

sanitation. Under these modules, presentations, prior and post tests in water supply and water

disinfection were produced. Based on the produced training modules, trainings were conducted

for CDWUU and LSGB staff, deputies of local keneshes and village activists in all 37

municipalities. Besides, with the ARI efforts, an additional three-day training was conducted

in Issyk-Kul with participation of LSGB heads, CDWUU chairpersons and accountants in all

37 municipalities. In this training, CDWUU accountants and operators underwent training in

accounting and operation of billing system. The project also prepares vide lessons in key topics

of training modules that will be recorded on electronic media and sent to CDWUU.

Page 94: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

78

Practical work with CDWUUS

Work was conducted on improvement of CDWUUs by LSGBs in tariff collection, in payment

for water consumption by social institutions, in ensuring the safety of street stand pipes and

other water supply structures.

Institutional development specialist of Naryn Oblast assisted to CDWUU Borondu-Murok, Ak-

Muz Village, Naryn Oblast in development of business plan taking into consideration technical

condition of water supply system and financial support of LSGBs. Based on this plan, a standard

for of business plan for CDWUU was developed.

Round-table discussion was conducted in Kashat Village in topic “Provisioning of potable

water to Kashat Village: outcome of construction of WSS and matters of further operation”.

The round table involved 32 people, including an Authorized representative of KR government

in Issykkul Oblast, NGO representatives, chairpersons of other CDWUUs, representatives of

raion state administration, aiyl okmotu, deputies of aiyl keneshes, SES and public members.

Following the round table discussion, a decision was as follows:

1. Accept that the works under the subproject have been commissioned according to the

current legislation.

2. Raise population’s awareness on the necessity of attitude of care towards water supply

system; necessity to pay for potable water supply; necessity to use water efficiently; sign

agreements with consumers on provisioning of water supply.

3. Within 10 days, AIyo lomotu head and CDWWUU should develop tariff and approve it

at the session of aiyl kenesh within one month.

4. Taking into consideration the complexity of the situation, AO head should undertake

crisis management in CDWUU activity for three months.

Introduction of billing system

To improve CDWUU activity on counting consumers and improvement of tariff collection,

ARIS procured and transferred to CDWUUs 60 sets of office equipment (computer, printer,

stabilizer) in 2013 and 20 sets in 2014. All 80 CDWUUs having obtained equipment underwent

training in operating billing program and started introducing this system. The billing system

enabled CDWUU to improve work with consumers and enhance the level of tariff collectability.

Competition among students

To raise population’s awareness of the necessity of attitude of care towards water supply

structures and tariff collection, guided tours to water supply facilities were arranged for students

in 11 villages. The students established groups on ensuring the safety of stand pipes. Aiyl

okmotu and CDWUUs conduct competition among these groups for best maintenance of these

stand pipes as well as for best essay on the topic of provisioning of potable water to population.

For instance, in Uch-Emchek Village a competition was arranged among students on topic

“Water is a source of life”. 16 May 2013, during a press tour, with participation of mass media,

to Uch-Emchek Village, where winners were awarded. Prior to writing of essay, a guided tour

to water supply facilities had been organized for students by CDWUU staff. Based on the results

of competition, the committee nominated four students. They were awarded with valuable

prizes and certificates of honor. Similar competition for best essay and guided tour to water

supply facilities were arranged for students in Tugol-Sai Village, Naryn Oblast. A guided tour

was also organized for students in Kopuro-Bazar Village. The main purpose of this guided tour

was to familiarize the students with subproject “Rehabilitation of water supply system in

Kopuro-Bazar Village”. After familiarization with the subproject, volunteer cleaning of the site

was carried out with active participation of CDWUU staff, teachers and students.

Page 95: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

79

Competition among LSGBs and CDWUU

On 25 December 2012, a competition was organized among local self-government bodies

(LSGBs) and community drinking water users unions (CDWUUs). It aimed to improve the

outcome of the activity on provisioning of potable water supply to population and strengthening

the responsibility of LSGBs and CDWUUs. To organize the competition, the ARIS staff

produced the following documents:

Request for submission of proposals, where competition terms and procedures are

described

Standard form of Action plan for improvement of activity outcome for CDWUUs and

the guidelines for development of the Plan.

Participants having followed competition terms and requirements would get equipment for

operation and maintenance of water supply systems. The list of equipment was earlier produced

and approved by the World Bank.

In total 131 applications were submitted from LSGBs and CDWUUs:

Issykkul Oblast – 57 applications

Naryn Oblast – 45 applications

Talas Oblast – 29 applications

Oblast ARIS institutional development specialists on-site verified documents and indicators

given in the applications and conducted consultations with CDWUUS for monitoring and

supervision of accomplishment and actual availability of documents and indicators specified in

Action plans.

Aiyl aimaks (AAs) and CDWUUs having won in the competition and fulfilled the terms of the

completion were awarded with 7 excavators, 30 motor scooters (trycicles) and 60 sets of

equipment and tools for operation and maintenance of water supply systems.

Awareness campaign

To carry out awareness campaign under the Second Rural Water Supply and Sanitation Project,

an assessment of needs of target groups was in obtaining the information about the project was

conducted. Preliminary analytical work showed that unsatisfactory implementation of project

“Taza-Suu” by previous implementers (before transferring the project to ARIS) had an adverse

impact. Public opinion on the activity in water supply and water disposal sector in general, and

particularly the activity under Taza-Suu project, had been extremely negative (undue

expectations, poor quality of construction works under subprojects selected earlier).

Local consultant for awareness campaign organized the following activities:

6 press-tours

4 TV programs

14 video clips

12 radio stories

10 radio programs

58 materials published in internet issues

26 articles published in printed mass media

Informal meeting organized and conducted of media representatives of the Kyrgyz

Republic with the staff of “Second Rural Water Supply and Sanitation Project”

Competition documents (information products) produced; applications collected from

applicants for competition among mass media announced under RWSSP2. In total, 14

mass media companies expressed their will to participate in this competition.

Page 96: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

80

To promote among population the necessity of attitude of care to water resources, 3

video clips were produced, highlighting the water supply sector issue.

o First video clip – “Presence of a problem in water supply sector”

o Second video clip – “Household connection to water supply systems”

o Third video clip – “attitude of care to water sources”

Rental of all three video clips on TV channels OTRK and ElTR, oblast TV (Issyk-Kul,

Naryn, Talas) was organized periodically from 2013-2014.

Under the awareness raising campaign, a meeting of RWSSP-3 management with media

representatives was organized. The participants had a straight talk about the progress of the

project and issues in the sector. Following the meeting, the participants noted the necessity to

visit regions and familiarize with the situation on-site. 6 press tours were arranged and

conducted with participation of leading mass media of the Kyrgyz Republic (12-18 people for

each press-tour) to pilot water supply facilities in three oblasts: Yssykkul, Naryn, Talas. The

visits helped in forming a pull of media representatives. The latter, in their turn, possess

comprehensive information about issues and positive trends in water supply sector.

Due to considerable outcome of project staff activity and smoothly running cooperation with

media, the Water Supply and Water Disposal Development Strategy was introduced as a

separate section in the National Strategy for Sustainable Development of the Kyrgyz Republic

2013-2017.

Competition among mass media

In order to attract the journalists of electronic, tele-radio and printed media of the Kyrgyz

Republic for broader highlighting of implementation of certain aspects of RWSSP-2 activity,

28 June 2013, competition was organized among the journalists of electronic, tele-radio and

printed media of the Kyrgyz Republic for broader highlighting of the matters regarding

provisioning of potable water supply to population and the matters of promotion of sanitation

and hygiene practice. The competition resulted in forming an information field enabling to

attract public attention to the matters of provisioning of access to potable water supply,

sanitation facilities as well as to inculcation of hygiene skills.

Under organization of the competition among mass media, competition documents (information

products) produced; applications collected from applicants for competition among mass media.

14 mass media companies expressed a will to participate in the competition.

21 June 2013, a meeting of the judges of competition took place followed by counting of votes

of the judges. Winners were selected under 4 nominations: TV, radio, printed, internet-

publication.

Following the competition in nomination “Television”:

First place awarded to producer of Ala-Too studio, Naryn Idinov.

Second place awarded to journalist of newsroom ElTR, Jaksylyk Matanov.

Third place awarded to journalist of national branch of ITRC “Mir”, Stanislav

Kasianov.

Following the competition in nomination “Radio”:

First place awarded to observer, presenter of programs “Kundun temasy”, “Birinchi

radio”, Taalaigul Chabdarova.

Second place awarded to journalist of newsroom “Kabarlar”, “Birinchi radio”, Nurbek

Borkoshev.

Page 97: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

81

Following the competition in nomination “Printed media”:

First place shared between economic observer of newspaper “Slovo Kyrgyzstana”,

Galina Luneva and correspondent of newspaper “Kyrgyz Tuusu”, Jypar Isabaeva.

Third place awarded to economic observer of newspaper “Finansist”, Daria Sytenkova.

Following the competition in nomination “Internet publications”:

First place awarded to correspondent of IA K-news, Yuliya Diveeva.

Second place awarded to correspondent of IA Vesti.kg, Aida Tokoeva.

Component D. Project Management

This component supported overall Project management carried out by the Community

Development and Investment Agency (ARIS) through financing of:

Provisioning of services of independent experts for assistance in developing

subprojects under components;

Creation and maintaining the system of monitoring and evaluation of project

effectiveness and outcome;

Operational expenses of ARIS Project Management Unit;

Annual audit of project accounts.

In the purpose of effective project implementation, due attention was paid to selection of staff

for project management unit (PIU). All PIU specialists were provided with required computer

equipment and office equipment, furniture and other equipment that was procured in line with

procurement procedures of the World Bank. As co-financing, the government of the Kyrgyz

Republic allocated a building for ARIS.

Under operational project support, impact assessment activities were carried out to define the

indicators of accessibility, quality, and satisfaction of rural population with water supply

services. Find more details in Table No. 1.

Table 1 Data on survey carried out

Purpose of monitoring and evaluation Type of survey Results

Assessment of impact in 25 project and

25 non-project villages. “Rebikon” Ltd

Questionnaire survey – 888

households

Expert interview – 50 specialists

Focus groups - 12

20.06.2014 –

31.10.2014

(final report

dubmitted

In compliance with the World Bank requirements, audit of financial statements was carried

out; the results thereof were sent to the World Bank and reviewed at the meeting of the ARIS

Supervisory Board.

Results achieved in the field of material investments:

a) Activities carried out under the project, construction, reconstruction of water intake facilities,

replacement of outdated pumps with the pumps with higher water pressure and efficiency,

Page 98: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

82

partial reconstruction of water supply network enabled to increase the volume of water

supply, improve the access and quality of CDWUU services.

b) Rehabilitation and construction of chlorination stations, pumping station enabled to improve

the quality and disinfection of potable water.

c) Improve efficiency of activity of communal utilities, replacement of outdated pumps with

less energy-consuming ones with higher efficiency and with high protection level (s levels

of protection) and 3-year guarantee maintenance. This all enables to extend the operating

life of pumps from 10 to 15 years, resulting in reduction of electricity costs.

d) Level of satisfaction of population with potable water increased: water supply volumes

increased in all villages covered by the project.

e) In certain villages, rehabilitation of water supply system gave an opportunity to supply water

to the raions, where rehabilitation works had not been carried out. In all villages,

rehabilitation of water supply system significantly improved pressure of water supplied,

which allowed to connect houses to pipeline and install washing machines, shower cabinets

and water heaters..

Results achieved in institutional development

Project impact was aimed to improvement of management system and population servicing. To

improve institutional development, the following activities were carried out under the project:

a) Trainings and seminars for the staff of CDWUU and Department of Potable Water

Supply and Water Disposal to strengthen the capacity of staff, particularly in installation

and maintenance of billing system. It is not only technical investments that are important

for institutional development but also improved management, including financial

management.

C. Project disbursements

Project disbursement under the project in the period of project implementation from

2009 to 31 October 2014 amounted to 13 490 147,81. (see detailed table in annex No.3).

Government of Kyrgyz Republiuc

ARIS: Second Rural Water Supply and Sanitation Project

Credit # 456KG; Grant # H462KG

Uses of Funds by Component and Expenditure Type

For period 1/1/2011 - 11/28/2014

(in USD)

Project Components Actual

A. Water Supply Infractructure and Equipment 10 563 425,13

А.1. Civil Works for Water Supply Infrastructure 10 092 573,77

A.2. Maintenance Equipment 244 956,71

A.3. Detailed Design, Studies 116 176,04

A.4. Technical Supervision 109 718,60

A.5. Retroactive financing (Works)

B. Sanitation and Hygiene Promotion 279 572,94

Hygiene and Sanitation Education Program 5 154,83

Page 99: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

83

Works on the sanitary facilities 274 418,11

C. Institutional Development 226 706,76

С.1 Analytical Work on Sector Strategy 164 411,09

C.2 Analytical work on Legislation and Linkages with LSG

C.3 Training of DRWS and CDWUUs 40 265,99

C.4 Development of Consolidated Rural Water Access 22 029,68

D. Project Management 1 050 923,27

D.1 Equipment and Vehicles 28 365,78

D.2 Salaries and retributions 538 597,78

D.3 Community mobilization

D.4 Monitoring and Evaluation 20 931,13

D.5 Audit 46 243,40

D.6 Operational Costs 350 818,15

D.7 Training 65 967,03

Expenditure on bank fees 1 361,15

Total Project Expenditure 12 121 989,25

Page 100: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

84

Government of Kyrgyz Republiuc

ARIS: DFID Co-financing Trust Fund for the Second Rural Water Supply and

Sanitation Project

Grant # TF013105

Uses of Funds by Component and Expenditure Type

For period 1/1/2011 - 11/28/2014

(in USD)

Project Components Actual

C. Institutional Development 687 422,71

C.1. development and implementation of the strategy for

sustainable supply of safe drinking water 226 248,74

C.2. improving the institutional framework, develop normative

acts 108 358,53

C.3. Training, workshops and seminars to enhance the capacity

of CDWUUs, LSG, DRWS and ARIS 232 298,86

C.4. Strengthening the management information system of the

Project 120 516,59

B. Sanitation and Hygiene Promotion 680 000,00

B.1. Hygiene and Sanitation Education Program 680 000,00

Expenditure on bank fees 735,85

Total Project Expenditure 1 368 158,56

C. Activity of the Government of the Kyrgyz Republic and LSG bodies

The Government of the Kyrgyz Republic in project implementation

In project implementation period, cooperation of ARIS and LSG bodies was successful. Village

LSGBs were taking active part in the process of reparation and implementation of subprojects.

LSGBs appointed subproject managers who were directly supervising contract implementation

and addressing to ARIS in case of disputes. However, it is necessary to note the following:

LSG bodies didn’t always timely fulfill their obligations on 5% subproject co-financing. Paying

out the 5% could be delayed for up to 6 months, which caused discontent of contractor

organizations that had, using the funds, to conduct mobilization for commencement of works.

The project had a number of times to address and resolve co-financing issues with higher

managerial bodies. Cofinancing delay took place in implementation of subprojects in Ak-

Kochkor, Tugol-Sai, Uch-Emchek Villages.

D. World Bank input

The WB activity in the process of implementation of the project may be evaluated as

satisfactory. In course of implementation, the WB was actively conducting monitoring of

project progress and providing recommendations and consultations on the progress of project

activities, as needed. WB timely provided approvals on the matters related to project

implementation. WB was timely assisting in decision-making and rendering consultation

support. The WB staff was supervising project implementation through supervision missions,

meetings with the representatives of the Government of the Kyrgyz Republic as well as field

visits. WB procurement review was carried out in line with the procedures of prior and post

review in accordance with approved procurement plan. Being adequate, project implementation

mechanism fosters future development of communal utilities. The project implementation

Page 101: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

85

mechanism proposed by the Bank was appropriate. It was necessary to create preconditions for

sustainable development of CDWUUs. This is a transfer from unprofitable to profitable utilities

in the field of potable water supply through improved accessibility, quality and effectiveness.

For instance, following the project activity, CDWUUs started collecting more tariffs, which

shows the fact that the project arrangements created preconditions for further sustainable

development of CDWUUs.

III. Evaluation of performance

A. Effectiveness and achievement of results

Direct impact of construction contracts aimed to rehabilitate water supply systems and

sanitation facilities may be evaluated by the following indicators given in Table No. 3

Report by project indicators

PDO indicators

Results as of

31.10.

2014

Comments

1 Number of rural residents with access to improved

water supply services under the project

83 000 Residents of 55 villages of completed subprojects

2

Percentage of water quality tests at the area of

rehabilitated water supply systems, the results of

which meet the national potable water quality

norms

80 “35” is removed to allow flexibility on the number of

schemes. Also “SES” is removed given that test may

have to be carried out directly by the project if SES does

not perform water analysis in the target villages.

3

Percentage of people in communities participating

in the project, reporting about the use of soap for

hand washing after using toilet

72,7 Based on the survey of households conducted by village

health committees under HPA , UNICEF partner

At average in three oblasts the indicator increased by

12.7%. In Issuk-Kul oblast from 80% to 91%, in Talas

oblast form 41% to 49%,and in Naryn oblast from 66%

to 85%, as of November 2013 and July 2014,

respectively .

4

Average level of compensation of expenses on

O&M of water supply systems covered under the

project (%)

70 Percentage of CDWUUs in 35 subproject villages

5 National strategy in water supply and sanitation

sector approved by the government

Draft State program for development of water supply

and water disposal in residential area 2014-2024

prepared with support of the Project was approved by the

Decree of the Government of the Kyrgyz Republic dated

24 September 2014 and sent for review to the

Parliament..

Indicators of outputs

Component A

1 A1. Number of water supply systems rehabilitated

under the Project

37 In 55 villages covered by the project, 37 subprojects

implemented

2

A2. Number of improved water supply points in

communities constructed or rehabilitated under the

project

226 226 new stand pipes were installed in course of

implementation of the project

3 A3. Number of new household connections as a

project result

3 902 Number of yard connections in completed subproject

villages

4 A4. Number of households water lines of which are

impacted by rehabilitation works under the project

1 000 Number of households connected earlier in project

covered villages

Page 102: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

86

5 A5. Number of rural residents with access to

improved sanitation facilities under the project

9 151+teachers about 9151students and teachers

6 A6. Number of improved toilets constructed under

the project

18 8 contracts signed for rehabilitation of indoor toilets and

10 contracts- for construction of pit latrines

7 A7. Number of equipment procured for feasibility

study of water supply and sanitation systems

0 Following the competition, Action plan for improvement

of activity, equipment for O&M of WSS, 7 excavators,

30 tricycles, 60 sets of equipment will be provided

8

A8. Number of schools in project implementation

area connected to water supply system under the

project

44

9

A9. Percentage of households at the area of service

of rehabilitated systems where the distance to the

nearest improved water supply source is 500/1000

m or less

71 Percentage of residents in 35 subproject villages

Component B

10 B1. Number of people trained in hygiene or

sanitation skills under the project (% of women)

82 160

(women –

74%)

In total, UNICEF covers 82 160 village residents

11 B2. Number of people reporting that they use soap

before cooking washing children’s hands

53/81

VHC(HPA) data/data of survey of knowledge, practice

and experience (CAICo)

12

B3. Number of schools in communities

participating under the project with functioning

wash basins and soap beside toilets

52 According to UNICEF data, 52 schools have different

types of washbasins installed

13

B4. Reduction in water-borne disease incidence

(number of cases a year/ number of beneficiaries

under the project) (Cases of acute intestinal

infections, Hepatitis A) in communities

participating under the project (percentage)

0 Cases of acute intestinal infections in 2012 - 428;

Hepatitis A - 228 in target villages. Data for 6 months of

2014 shows that there are 126 cases of acute intestinal

infection, and 69 of Hepatitis A. Total decrease ia about

62.5% (data for the half of 2012 in comparison for data

for half of 2014

Component C

14 C1. Number of bodies (CDWUU) supported by the

project

38 The project currently covers 38 CDWUUs. CDWUUs

serving Kazybek, Kyzyl-Tuu and Kara-Koyun Villages

are merged in two independent CDWUUs. of Kazybek

Village CDWUU and Kyzyl-Tuu and Kara-Koyun

Villages CDWUU

15 C2. Average tariff collection in villages covered

under the project

74

16 C3. Number of CDWUU staff trained in tariff

collection and WSS system management

289

17 C4. Number of service agreements signed by

CDWUUs

38 Number of CDWUUs covered by RWSSP-2

18

C5 Percentage of CDWUUs covered under the

project, where women take one of three top

positions

65 at CDWUUs, women usually work as accountants

19 C6. Number of villages, WSS information of which

is included in the national database 1 899

Page 103: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

85

Main trends of project impact

First: project impact trend aimed to improve potable water quality, access to water, water

pressure in water supply network and water supply.

1. In investigated 25 project villages, compared with 2012, a number of households

using open sources as main sources of water for drinking and cooking has decreased

from 29% to 5%, which considerably reduced the risk of infectious diseases,

especially among children.

2. 86% households have access to WSS services, 85% use it as a main one. In eleven

project villages covered by survey, all residents have access to WSS services.

Mainly, households in Novostroiki and far-flung sites where RWSSP-2 works were

not envisaged are not covered by WSS services.

3. Following implementation of RWSSP-2, in households in project villages and

using WSS services, the distance to main potable water source has significantly

decreased. In 2012-2014 period, a number of households using WSS located at

the distance at100 m has increased from 47% to 77%. The number of households

where the distance is over 500 m has reduced from 7% to 0.3%.

4. In general, the distance to the nearest water source has reduced and the water supply

services quality has been improved (time of interruption of water supply has

decreased, pressure improved). Households using WSS in project villages spend

less time to bring potable water. Average time spent by HHs to bring water,

compared with 2012, has shortened from 17 to 8 minutes. Physical load on women

and children, who are mainly responsible for carrying water home, has lessened.

5. Most HHs using WSS in project villages (77%), think that the pipe water they use

for drinking and cooking is of an excellent and good quality. This is confirmed by

the results of water quality tests conducted by sanitary and epidemiological stations

according to agreements signed with CDWUUs. In 2012-2014 period, 56 tests were

carried out, the results of which show that the quality of pipe water meets the

national quality norms. The number of HHs that think that they use potable water

of an excellent and good quality, compared with 2012, increased from 47% to 77%.

6. Residents of project villages using WSS note increase in pressure in water supply

and in pipeline after RWSSP-2 interventions. Thus, the number of HHs that

evaluate water pressure as good and excellent has increased in 2012-2014 period

from 36% to 53%.

7. Following rehabilitation of WSS under the project, household/yard connections is

continually and actively ongoing. The number of HHs having installed

household/yard connections and using pipeline as a main water source compared

with 2012 has increased from 9%to 43% in project villages. The main obstacle for

installation of household/yard connections is a relatively high cost of connection

works.

Page 104: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

86

Second: project impact trend aimed to improve management system in population serving

1. Trainings conducted for LSG bodies and CDWUU staff in operation and

maintenance of pumps and electric equipment based on new technologies and

opportunity to disinfect potable water, in management and maintenance of

pumping and electric equipment.

The indicators given in the project matrix generally allowed to reflect main results

of project activity. In discussion with WB mission, additional indicators were

introduced so as to cover comprehensively project benefits by separate project

impact trends. For instance, indicator “Number of new household connections after

the project” introduced reflects improvement of water supply system in villages,

where project activities on household/yard connections were carried out.

IV. Overall assessment and recommendations

A. Overall assessment and lessons learnt

It stands to mention that RWSSP-2 is one the projects where an effective dialogue with

local self-government bodies was set up, where priorities on addressing water supply issues

were amicably discussed and selected subprojects were implemented.

However one of serious problems in project implementation was preparation of

detailed design estimates and limited project funds. Remaining 13 DDEs of challenging

subprojects from 26 challenging subprojects of the phase one were adjusted in conjunction

with the Design institute “Kygyzgirostroi” OJSC.

ARIS engineers produced and sent for review to the World Bank the cost estimates

of works under the 13 challenging subprojects. In reparation of BoQ under four subprojects

for Tort-Kul Arashan, Kalba, Yntymak Villages, modifications were introduced according

to the requirements of WB consultants, i.e. diaphragms envisaged in DDE were replaced

with pressure reducing valves. Pre-bid meeting was also conducted with bidders, which

enabled the bidders to more comprehensively study bidding documents, materials and

equipment used for the facility. Discussions with AO and CDWUU representatives on

saving potable water, reduction of water loss, replacement of standpipes with yard and

household connection, connection through water meters and appropriate operation of

submersible well pumps as well as on risk of rebidding and signing “Agreements between

ARIS and Aiyl okmotu”.

Prior to announcing bidding, due to limited funds, design institute

“Kurgyzgiprostroi” in conjunction with ARIS engineers, having additionally studied

market prices, prepared DDEs and BoQs under completed 13 subprojects.

Under the 13 subprojects, changes were introduced in DDEs and BoQs by separate

types of works not requiring qualification experience in construction. Agreements have

been drafted and will be signed between ARIS and aiyl aimak for some works in

implementation of subproject, not requiring qualification experience in construction.

Page 105: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

87

According to DDE under 13 subprojects, there were delays in announcing bidding

fro construction works.

Supervision

In the course of supervision of contract implementation, there were the following main

challenges:

Lack of financing of non-qualification works from AO. Weak knowledge among CDWUU

chairpersons in rectification of leakages and break downs of distribution networks and

pipelines as well as lack of knowledge of water chlorination and signing agreements with

the representatives of raion SES. Lack of specialists for operation and maintenance of water

supply system.

B. Challenges encountered and ways of dealing with them

There were not complicated problems during preparation and implementation of the project.

All challenges regarding preparation and implementation of subprojects by ARIS and LSG

were resolved at working order. The government timely signed Project Financing

Agreements.

Regardless of achievement of goals, there are problems that occurred beyond the project

mandate and in the process of project implementation:

Rehabilitation of potable water supply facilities envisaged improvement of the activity of

main structures, repair and drilling of wells, construction of stations for disinfection and

reservoirs. Increased volume of water supply and pressure in water supply system resulted

in aggravation of poor condition of main and distribution pipelines. The poor condition

caused frequent break downs in water supply networks.

Poor condition of main and distribution networks. For a long period, the networks were

without rehabilitation. They used pies of various diameter made of various materials, which

enables to ensure required pressure in villages.

Lack of equipment for accounting of potable water in villages result in inefficient and

wasteful use both by CDWUUs and beneficiaries. This lack was related to lack of

equipment for accounting of potable water. Installation of accounting equipment would

enable to reduce water losses, enhance the efficiency of its use and increase the level of

tariff collection. This also would enable to move form old water accounting system, i.e.

from normative consumption to actual consumption. While behavior of consumers

changed in terms of payment for water, the attitude of care is still not there.

Inefficient CDWUU management resulted in misbalance between the volume of water

supply to system and the volumes of potable water consumption. Inefficient use of new

and current equipment results in unjustified increase of water supply. These are both

commercial and technical losses, which ultimately leads to indebtedness of CDWUUs to

power companies.

Lack and sometimes absence of qualified specialists able to manage not only high tech

equipment and structures but also water supply networks remains a pressing issue. Without

Page 106: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

BORROWER ICR

88

proper maintenance from qualified specialists, equipment, structures and networks may

get out of order. Low qualification of specialists, operators of billing system and poor

technical equipment may lead to decrease in quality of services provided. Inefficient

management will lead to inadequate collection of tariffs. This will also lead to inability to

invest in main facilities.

Active participation of civil sector (NGO) in management and quality service provisioning

is the project achievement. The results of impact assessment showed that LSG bodies and

CDWUUs carry out awareness campaign among population aimed at appropriate operation

water supply network, attitude of care to potable water.

C. Recommendations

The government of the Kyrgyz Republic would propose the following activities for further

improvement of access, quality of infrastructure services provided:

In project implementation in some villages, household and yard connections to water

supply system were carried out. They installed shower cabinets, washbasins, water

heaters, washing machines and other conveniences.

Villages face pressing issues regarding condition of treatment facilities and

disinfection of waste waters. Villages virtually don’t have structures for treatment of

waste waters.

The second priority is availability of treatment facilities, the lack of which results in

environmental risks, epidemiological outbreaks and diseases among population.

Currently, due to lack of sewage system and treatment facilities, population has to

use pit latrines and cesspits. One of project approaches could be consideration of

construction of structures in villages.

In the field of institutional development, CDWUUs should get support in

improvement of management system, conduction of seminars and trainings aimed at

building the capacity of specialists. There is a need in training orienting specialists

from quantitative indicators to qualitative indicators (achievement of targets,

efficiency).

In order to improve CDWUU activity, it is needed to reduce credit indebtedness

through efficient management. It is necessary to set up billing system.

It is needed to create material, technical and institutional preconditions for

sustainable development of CDWUUs as well as NGOs dealing with infrastructure

issues, particularly, in terms of information support.

Page 107: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

89

Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders

Page 108: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

90

Annex 8a) DFID Programme Completion Report - Top Sheet This Top Sheet captures the headlines on the programme performances performance over the course of its lifetime. Teams should

attach summary sheets from each annual review over the life of the programme.

Review Date: 2-9 September 2014

Title:

Second Rural Water Supply and Sanitation Project (RWSSP-2)

Programme Code:

114044

Start Date:

1st July 2009

End Date:

31st October 2014

Summary of Programme Performance

Year 2010 2011 2012 2013 2014

Programme Score 4 3 B A

Risk Rating Medium Medium Medium Medium

Financial Position

Original Programme Value £5,000,000

Extensions/ amendments Original end date was end May 2013 but this was

extended to October 2014 during the latest annual review

(November 2013).

After the mid-term review in 2011 DFID cut its budget

from £5 million to £1 million.

Log-frame revisions (with dates) - After the mid-term review in November 2011 support

for water supply infrastructure was withdrawn so the two

remaining outputs supported by the reduced budget were:

(i) improved hygiene and sanitation practices, and

(ii) improve capacity of the GoK, local government and

communities to develop and maintain their WSS services

in participating communities

- Following the 2013 Annual Review the phrasing of the

indicators was amended to align with the World Bank

logframe

Total programme spend £1,000,000

Programme Accountability

Original SRO (with dates of tenure)

Subsequent SROs (with dates of tenure)

1.

2.

3.

Follow up actions required following closure

Page 109: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

91

A. Introduction and Context (1 page)

DevTracker Link to Business Case: DevTracker Link to Log frame:

Outline of programme and what it has achieved

1. The Second Rural Water Supply and Sanitation Project (RWSSP-2) is a World Bank/DFID programme which

builds on a first phase RWSSP, which was implemented in 2002-2008.

2. In the second phase, DFID contributed £1 million to a World Bank Trust Fund over five years to finance

improvements in sanitation and hygiene practices at individual, family and institutional levels in rural areas in the

Kyrgyz Republic, as well as to strengthen institutional capacity for the rural drinking water supply and sanitation

sector. The Joint WB/DFID intervention was designed to reach approximately 110,000 beneficiaries (the end target

of people trained on improved hygiene and sanitation practices).

3. In the first phase, DFID provided complementary technical assistance to the World Bank for their RWSSP project

implemented in the northern oblasts of Issyk-Kul, Naryn and Talas. This was done through two DFID projects –

RWSSP for water supply and a Rural Hygiene and Sanitation Project (RHSP) which worked with the Centre for

Health Promotion (CHP) on sanitation and hygiene in the home and at schools and medical centres, through Village

Health Committees (VHCs). At the same time, ADB was implementing a similar water supply project in the four

remaining oblasts. RWSSP-2 continued to work in the same three northern oblasts.

4. The agency responsible for overseeing rural water supply (Department of Rural Water Supply) has been moved

from one institutional location to another. Until 2011 RWSSP-2 was implemented by a joint project management

unit (JPMU) which implemented both RWSSP-2 and the ADB project (until it was halted). RWSSP-2 faced long

delays and major disruptions from the start due to low capacity and limited leadership of the water supply and

sanitation sector institutions and service providers. The revolution in 2010 and the subsequent political upheaval

was also a significant disruptive factor which caused considerable delays.

5. Following the Project’s World Bank mid-term review in 2011 the Government of the Kyrgyz Republic dissolved

the JPMU and transferred the Project to the Community Investments and Development Agency (ARIS). The first

phase of RWSSP was successful in developing a community based participatory model for service delivery, balanced

with centralised provision of services, and achieved measurable reductions in water borne diseases. It was less

successful in institution building in the water supply sector, largely due to the fact that throughout the project, the

DRWS then located in the Ministry of Agriculture, Water Resources, and Processing Industry, was inadequately

supported. [It has since been under the Prime Minister’s Office and is now under the State Agency on Architecture,

Construction and Housing under the Government of KR.] However, the CHP and its partner VHCs continue to be

an active partner under the Ministry of Health.

6. Despite the desperately poor performance in the first half of the project, DFID continued to support the project,

though with reduced financial contribution, partly to maintain DFID’s reputation given their support to other projects

and programmes, and to achieve the benefits of supporting the institutional and legal reforms proposed. DFID

reduced their contribution from £5m to £1m by withdrawing contributions to water supply construction and focusing

its support on promotion of improved health and hygiene practices (Component B) and capacity building and

institutional development at community and national levels (Component C).

7. The Annual Review in late-2013 suggested that despite still limited tangible progress against project indicators,

ARIS and UNICEF were in a position to achieve dramatic progress in the final year of the project. A time-bound

action plan was put in place and a mid-year review was conducted in May 2014 to assess progress. The progress

achieved in the first six months 2014 was dramatic and there was high confidence that project purpose of providing

improved access to potable water and improve water related hygiene practice in participating communities, with

associated indicators and outcomes, would be achieved. The PCR can confirm that the outcomes were achieved,

though due to the rushed nature of the final year’s programme, it will be important to ask World Bank/UNICEF/ARIS

to ensure the sustainability of the achievements. However, the continued commitment of the CHP and VHCs to

health promotion in the villages and the fact that school latrines built under RHSP ten years ago continue to be used,

in good condition and well maintained provides some reassurance.

Page 110: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

92

8. The achievements in the last year are remarkable and due credit should go to the World Bank, ARIS and UNICEF

for huge efforts to accomplish this, and to DFID for continuing to support this project despite the challenges.

B: PERFORMANCE AND CONCLUSIONS (1-2 pages)

Performance is measured against the revised log frame – the latest revision was in October 2013 and was aligned

with World Bank’s log frame.

Overall Outcome Assessment

DFID funds are only used to support sanitation, hygiene promotion and institutional capacity building activities so

only the second indicator “Decreased rate of incidence of waterborne diseases in communities participating in this

project” is assessed. The assessment is based on tests of faeces and blood from pre- and post- project matched

samples of schoolchildren for worms, acute intestinal infections and viral hepatitis done by SES laboratory staff

working with village health centres (FAPs). Where infection was found children and families were treated in

almost all cases. Data for 2014 was only available for the first half of the year so 2014 totals have been doubled

before comparison with an average of annual totals for 2010 – 2013. Acute intestinal infections and viral hepatitis

A fell by 55% and 54% respectively whilst worm infections (including ascariasis, enterobiasis and giardiasis)

reportedly fell by 75%. Only rare helminth cases were reported to have increased, from 23 cases to 94 cases due to

non-treatment of parents, later revealed to be the main source of infection. Whilst this is not a statistically

significant study and the data may not be wholly reliable, it is certainly clear that there has been a big improvement

in participating communities’ water and hygiene related health. What is also clear from the Output reporting (in

Section C below) is that the success has been as a consequence of delivering DFID’s original aim (in Phase 1

through RWSSP-1 and RHSP) of improved health through combined improvements in water supply, sanitation and

hygiene. Results are summarised below.

Acute Intestinal Infection Viral Hepatitis A

– infected children in project schools – infected children in project schools

Average 2010-2013 2014 Average 2010-2013 2014

Issyk Kul 66 62 Issyk Kul 46 40

Naryn 44 14 Naryn 43 18

Talas 236 80 Talas 92 26

Total 345 156 Total 181 84

Change -55% Change -54%

Number of helminthic invasion diseases in the three project oblasts (SES data)

Average 2010-2013 2014

ascariasis 881 362

enterobiasis 1,507 166

hymenolepiasis 36 0

giardiasis 296 72

dysenteric amoeba 3 0

rare helminths 23 94

Output Score and Description

Output 1 (Improved hygiene and sanitation practices) has three indicators on participation and behaviour change

which are reported on in more detail in the next section. Score = A.

Page 111: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

93

In the log frame, some assumptions were made for this output about key factors for success. These were that: the

actual change in behaviour would be as a result of wider factors than just participation in programmes (including

availability of soap and home water management); that communities do not neglect sanitation when deciding on

resource allocation (adequate split between water supply and public sanitation) and that hygiene promotion is well

targeted with appropriate channels and tools used during the campaigns. These assumptions were borne out in this

project with major changes in soap availability and use in the home and at schools, improved allocation of

resources for sanitation in homes and schools (especially increasing salaries of staff doing the cleaning and

maintenance of sanitation facilities), and a wide selection of materials, tools and visual aids (as well as social

networking and video exercises for schoolchildren) used to emphasise the importance and effectiveness of good

sanitation and hygiene. UNICEF did a study of school expenditure on water supply, sanitation and hygiene and

overall the picture was that current expenditure was only a tiny fraction of what was required to fulfil national

standards. There is considerable reliance on parent sponsorship of classes and this seems to have been effective in

providing materials but it is inequitable with this inequality likely to be self-perpetuating with better schools visited

(such as Kazybek in At Bashy rayon of Naryn) seeming to receive much higher levels of sponsorship than

struggling schools (such as Kum Dobo in Kochkor rayon of Naryn).

Output 2 (Improved capacity of the GoK, local government and communities to develop and maintain their WSS

services in participating communities) is focussed on institutional capacity building, of the CDWUUs and DRWSS

in particular. Score = A.

The biggest indicators of success for CDWUUs relate to commitment through signed service agreements (done)

and through fee collection and management. All CDWUUs except Chelpek and Tort Kul in Issyk Kul and Ak

Kuduk in Naryn have set tariffs and started collecting fees. Seasonal collection (post tourist season in Issyk Kul

and post harvest in all three oblasts) mean that 2014 figures are currently much lower than 2013 figures. The tables

below are based on data for all CDWUUs compiled by ARIS for 2013, the year with the most complete fee

collection data.

The reported tariff charges are similar for Naryn and Talas at between 60 and 70 KGS per household. Assuming

about five people per household, Issyk Kul charges are higher at about 100 KGS per household. Some Issyk Kul

CDWUUS have already installed meters and are charging per cubic metre. This is beginning to be implemented in

some CDWUUs in Naryn and Talas too. The tariffs are reasonable and should deliver sufficient revenue to cover

staff costs (CDWUU staff members were paid between 2,000 and 10,000 KGS per month) and routine operation

and maintenance costs and to contribute to depreciation costs where higher collection rates are achieved.

CDWUUs reported collection rates of 60-80%. The analysis in the second table below would suggest that, on

average, collection rates may be lower at 30-50%. However, these figures should be treated with caution as many

schemes were not fully functioning though the whole year so revenues are not for the whole year. Nevertheless the

collection rates would seem to bear out the claims based on tariff rates that income is sufficient to cover O and M

costs so the target has been achieved.

Average monthly tariff and basis of tariff for each oblast

Oblast Per household Per person Per m3

Issyk Kul - 20 25

Naryn 60 15 -

Talas 70 11 -

To support this Output DFID contributed to the funding of a set of activities to help the sector more widely, all of

which are expected to be completed by project close at the end of October 2014. The World Bank is keeping a

close eye on all activities to ensure their successful conclusion before project closure. The most important

activities were: the development of a sector strategy (complete and awaiting parliamentary approval); a legal

review (needs a major rewrite before approval – World Bank will ensure its completion); creation of a water and

wastewater financial model (still in progress but due to be complete before the end of October 2014); advisory

support on chlorination (completed but see end of Section C for follow-up) and a review of technical norms and

standards (still in progress but off to a good start and expected to be complete before end of October 2014).

Page 112: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

94

CDWUU annual revenues and average per household

Value 2013 Income

2013 income per

household/month

Income in

£(approx.)

All CDWUUs Maximum 600,900 (in Issyk Kul) 75 7,500

Mean 157,602 21 2,000

Minimum 5,500 (in Talas) 5 70

Lessons and how these have been shared

1. Only when water is provided to the home do you get the maximum improvements in hygiene and only

when water, sanitation and hygiene are all in place do you get the full health gains. These messages are

clear to all involved but this learning needs to be incorporated in any new water supply initiatives such as

those being considered by ADB and the World Bank. Sanitation and hygiene has so far been primarily

grant supported by bilateral donors (DFID primarily although a Russian project under UNICEF will also

include this) and if DFID is to cease supporting this work then any new activities need to find a way to

support.

2. CDWUUs are a valuable technical and management resource in rural areas, especially where they are run

by people previously involved in state management of rural supply. There is good evidence of CDWUUs

being backed up by Ayl Okmotus (AOs – local government) and this partnership will be a key factor for

sustainability going forward. Many AOs have contributed to water supply construction or school sanitation

and hand washing facilities.

These lessons have been shared with all project partners.

Page 113: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

95

C: DETAILED OUTPUT SCORING (1 page per output)

Output Title Improved hygiene and sanitation practices

Output number per LF Output 1 Output Score A

Risk: Low Impact weighting (%): 50%

Risk revised since last AR? N

Impact weighting % revised

since last AR?

N

Key Points

1. There were several reports that the residual knowledge on hygiene from the RHSP in the first phase contributed to quick

success. 2. The continued activeness of the VHCs 10 years on was most encouraging for sustainability.

Indicator(s) Milestones Progress Output indicator 1.1: Number of villages

participating in campaigns on hygiene and

sanitation carried out by the project

By end of project – 55 villages Target met with all 55 villages (schools,

medical centres and communities)

participating in the hygiene and sanitation

campaigns. Two school teachers per village

attended an oblast level training session by

UNICEF and then used the training and the

Participatory Hygiene and Sanitation

Transformation (PHAST)-based materials to

work in the schools and communities (with

health centres (FAPs) and VHCs) and with

UNICEF support/monitoring. Output indicator 1.2: Percentage of people

reporting using soap for washing hands after

using the toilet.

By end of project – 70% Target met. Pre- and post-intervention data

collected by CHP suggests that 75% of

people are washing hands with soap after

using the toilet (Issyk Kul – pre-project 80%

to 91% post-project, Naryn - 66% to 85%

and Talas - 41% to 49%). The biggest

reason for the increase, and the reason to

believe (based on site visits) that hygiene

behaviour has genuinely improved, is the

availability of water (heated as required) in

the home and at school. The availability of

water in wash basins located indoors in

households increased from 62% to 78% in

Issyk Kul, 81% to 97% in Naryn and 46% to

61% in Talas. Output indicator 1.3: Percentage of people

reporting using soap for washing hands

before handling food/washing children’s

hands

By end of project - 50%/40% Target 1 met in Issyk Kul and Naryn but not

Talas, with CHP data suggesting that the

percentage of respondents who reported

washing hands before meal preparation

increased from 26% to 49% in Issyk Kul,

29% to 48% in Naryn and 16% to 20% in

Talas. It is not clear why Talas lagged

behind on all hygiene targets. Target 2

unknown. For some unknown reason, CHP

did not collect data on washing children’s

hands but the availability of hot water and

soap in schools, high level of awareness

shown by children, and in-school monitoring

of hand washing suggests that hand washing

among children is at a high level – children

were often reported to have educated their

parents after the hygiene activities at school.

Page 114: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

96

Page 115: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

97

Output Title Improve capacity of the GoK, local government and communities to develop and maintain their WSS

services in participating communities

Output number per LF Output 2 Output Score A

Risk: Medium Impact weighting (%): 50%

Risk revised since last AR? N

Impact weighting % revised

since last AR?

N

Indicator(s) Milestones Progress Output indicator 2.1: Number of DRWS

personnel trained in management and

planning for rural water supply and

sanitation

By end of project – 40 Target met with ARIS reporting that all local

DRWSS engineers had been trained with the

CDWUUs. It is not clear how effective

DRWSS engineers are since the main project

relationships are between ARIS, CDWUUs

and AOs. Output indicator 2.2: Number of CDWUUs

trained in fee collection and management of

the water and sanitation schemes

By end of project - 196 Target met with all 196 CDWUUs (Phase 1 -

159, Phase 2 - 37) trained in fee collection

and management of the water and sanitation

schemes. All 37 Phase 2 CDWUUs have

been given computers and printers for

tracking fee collection, though some are not

yet using them – but accounts clerks have

been appointed and training is on-going. Output indicator 2.3 Number of CDWUUs

service agreements signed. By end of project – 37

Target met with all 37 CDWUUs have

signed service agreements. Output indicator 2.4: Number of CDWUUs

with sufficient revenues (from fees collection

and other sources) to cover at least O and M.

By end of project - 15 of 37 or

44%

Target met. In 2013, 15 CDWUUs had

income in excess of KGS 100,000 (5 so far

in 2014) with 25 CDWUUs having income

in excess of KGS 100 per household (15 so

far in in 2014). Fee collection is mainly

seasonal and as tourist seasons and harvests

had not finished by the review total revenue

for 2014 is currently lower. All 12

CDWUUs visited in May and September

2014 had sufficient revenue to cover

operation and maintenance. Depreciation is

only partially covered so ARIS was to invite

Oxfam to report on its successful project in

Tajikistan (where revenue covers

depreciation) at the closing workshop.

Some CDWUUs are highly successful at

revenue collection. Output indicator 2.5: Number of villages for

which information on water supply and

sanitation is included in the national

database

By end of project – 1,700 Target met. There are two databases being

prepared, one for DRWSS (technical) and

one for SES (water quality and diseases).

The DRWSS one is complete and data for

2,000 villages has been entered. 800

questionnaires were sent to local DRWSS

staff to fill in (covering more than 2,000

villages) and 700 were filled in, of which

650 have been entered. The Sanitary

Epidemiological Station (SES) and the

developers are working on the variables to

be included in the SES database. It will be

completed close to project end but the

consultants will support SES IT staff for a

while after. Both will be online. The

DRWSS one will be public domain but a

decision on the SES one will depend on

sensitivity of final data.

Page 116: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

98

Key Points

Summary of responses to issues raised in previous annual reviews (where relevant)

1. One of the main concerns relates to water quality and the chlorination of water supplies. Chlorination units

have been installed in all 37 schemes but whilst an extremely useful guide to disinfection has been produced

by ARIS, and there was evidence of chlorination going on in some schemes visited, there is no testing of

residual chlorine so there is no knowledge or understanding of the effectiveness (or healthiness) of the

chlorine regimes in place. Whilst Kyrgyz standards and SES in Bishkek advocate a formula based approach

to chlorine dosing (based on raw water quality and concentration of chlorine powder), all CDWUUs reported

having been told to use the same dosage (3g/m3) even though raw water quality and concentration of chlorine

in the bleaching powders used in each case was different. This is a major concern. If chlorine is to be used

(recommended, especially for surface water supplies) then residual chlorine must be measured. SES are

aware of this and will be promoting it with their staff and CDWUUs in the final workshop but without testing

equipment (CDWUUs have none) the reliance is solely on SES on an occasional basis.

Recommendations for future programmes

1. Wherever possible, incorporate WASH training for communities within existing or future community

structures linked to state institutions to ensure sustainability. The main reason for the sustainability and

continued support of the Village Initiative Groups (VIGs) from RHSP is that they were incorporated into the

VHCs which work on a variety of health issues with FAPs. Without this the VIGs may well have ceased to

function.

2. If chlorination is to be promoted as part of water supply improvements then monitoring systems and

equipment must be in place at the earliest opportunity.

3. Actively engage with local government (AOs) and not just target communities to support water supply. AOs

have a legal responsibility for water supply and have responded positively to requests for support by

CDWUUs and strong partnerships are now in place.

4. Use RWSSP-2 as a model for making difficult decisions up front on the most effective way of project

management and implementation. The problems in the first half of the project came as no surprise, nor did

the improvements in performance with the change in management.

5. To achieve significant improvements in hygiene behaviour water must be easily to hand.

6. There should be plans in place to follow-up outstanding activities that are part of a project but outside of the

control of that particular project. For example, the long-term strategy for WASH has been finalised following

government and sector review. It is awaiting partliamentary approval but this is unlikely to be achieved

before the end of the project. Following this up is a not a time-consuming process but is important in terms

of the project’s legacy and future sector progress.

Page 117: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

99

D: VALUE FOR MONEY & FINANCIAL PERFORMANCE (1 page)

Key cost drivers and performance

DFID’s contribution to this project dropped from £5 m to £1 million to focus on sanitation, hygiene and

institutional capacity building. The revised budget went to UNICEF for the school sanitation and school and

community hygiene programme in the 51 villages supplied by the 37 water supply systems, and to ARIS as

contribution to project management and institutional strengthening activities. UNICEF rates are relatively high but

economies of scale are achieved with existing work being done elsewhere and some staff supported by core

funding. The long delays and rush to complete the work quickly meant that spend occurred rapidly. All of the

funds were spent.

VfM performance compared to the original VfM proposition in the business case

The mid-term review concluded that there was poor value for money being demonstrated compared to the original

assessment in the Project Memorandum (project was pre business case process) since the number of beneficiaries

was going down and the per capita cost of water supply construction was going up two, three, even four-fold.

DFID ensured that value for money increased again by cutting support to the construction schemes and focusing

the support on sanitation and hygiene promotion. Whilst it is not possible to directly compare overall project

completion VfM with project preparation VfM as the water supply construction component was not common to

both, it is possible to compare the components on sanitation and hygiene. The costs were the same but the audience

reached by UNICEF during its hygiene campaigns was greater than would have been the case under the JPMU.

UNICEF calculated that almost 600 VHC members carried out hygiene and sanitation training of just over 82,000

people (75% of target population) of which just over 53,000 were women. Hygiene and sanitation videos were

broadcast on national TV and several regional radio programmes were broadcast.

Assessment of whether the programme represented value for money

Without DFID’s support the hygiene and sanitation components of this project would not have been delivered at all

and so many of the potential health benefits of improved water supply would not have been achieved. Many

studies demonstrate the economic and social benefits from improved health in terms of reduced expenditure on

medicines and hospital visits, increased work productivity and school attendance, particularly for girls so DFID

have delivered economic benefits. DFID’s £1 million supported successful implementation of hygiene and

sanitation programmes in 55 villages and schools, as well as a sector strategy awaiting parliamentary approval, a

legal review, a water and wastewater financial model, advisory support on chlorination, a review of technical

norms and standards and databases for all villages in the project oblasts. These short term outputs will, based on

the continuing benefits observed from the Phase 1 RWSSP and RHSP, deliver long term outcomes and represent

value for money. UNICEF’s resources and experience were used to achieve benefits far beyond the project sites

with regional and national activities on TV and radio as well as school media and social networking activities.

DFID’s profile with the Government of the Kyrgyz Republic has been low over this project and it would help to

maximise value for money if the Government were to be made aware of DFID’s support for this project, though

exposure needs to be managed so as to not create expectation by the Government for further DFID support. This

will be a high profile issue over the coming months as discussions between the government and World Bank over a

further phase of work evolve. DFID had a fine line to tread. It was only in the last 18 months that this project

moved ahead at pace and was viewed most positively by the government. It might have helped for DFID to more

closely associate itself with the World Bank in meetings with the government.

Quality of financial management during programme

When it was clear that the original £5 million was not going to represent good value for money the decision was

taken to reduce the budget and transfer the money to ARIS and from there to UNICEF and consultants. ARIS were

audited and found to be sound in their financial management, so much so that high profile NGOs that were highly

Page 118: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

100

critical of the project being given to ARIS were, by project end, effusive in their appreciation of ARIS’ financial

and technical dealings in the project.

Date of last narrative financial report

Date of last audited annual statement

E: RISK (½ page)

Quality of risk management over the life of the programme

The main risks identified at project outset were institutional, political and fiduciary. In the first half of the project

the risks associated with government became a reality and lack of (or confused) government leadership for or

through DRWS and poor project management by the PMU (much linked to poor project design, especially in terms

of design standards) held up the project’s progress. This was certainly not helped by the political consequences of

the revolution of 2010 which left an institutional vacuum for a significant period. The key risks identified under

Component A (Water Supply Infrastructure and Equipment) also became a reality and were fundamental to first

half project delays. These were disagreement over design standards for the water supply projects which, when

finally resolved, resulted in a doubling of the per head volumes of water supplied and significant increases in sub-

project costs and the requirement to complete sub-projects from Phase 1 of RWSSP which were either not

completed or which contained defects requiring work to ensure water supply. As a result the costs rose and the

number of schemes included in RWSSP-2 was reduced. The delays in Component A impacted upon B and C,

exclusively funded by DFID.

In agreement with the government, the risks were managed by transferring the project management responsibility

from direct government control to ARIS. This was a pragmatic and commendable decision by government which

meant that, whilst the World Bank still had to fight hard to control costs, project implementation was faster

(Components A and C) and UNICEF were able to bring their considerable experience and resources to enable rapid

implementation of Component B.

When costs spiralled and value for money was considerably reduced DFID took the decision to withdraw its

support to Component A and to support only Components B and C.

Funds were disbursed via a World Bank Trust Fund and the Bank considered financial management at ARIS during

RWSSP2 (accounting, reporting, budgeting, external auditing, contract monitoring, funds flow and staffing) to be

Satisfactory throughout.

F: COMMERCIAL CONSIDERATIONS (½ page)

Delivery against planned timeframe

The project was extended from May 2013 to October 2014 so delivery was not achieved by original timeframe.

However, DFID supported activities have either already been completed or expected to be completed by end of

project. The only outstanding activities are legal review rewrite, work on reviewing and suggested amendments to

design standards, and database completion under Component C.

Performance of partnership (s)

The partnerships improved hugely in the second half of this project. The main partnerships were between UNICEF

and villages for hygiene promotion and sanitation (and between schoolteachers, schoolchildren, parents and

communities, and medical centre staff). In all 12 villages visited these partnerships were evident and supportive.

The longevity of the VHCs and their continued work with FAPs is particularly striking, as is the continued linkage

between FAPs and the CHPs.

Page 119: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

101

For water supply the main relationships were between ARIS, CDWUUs, communities and AOs. The good

working relationships observed between AOs and CDWUUs and between CDWUUs and communities were

encouraging to see for sustainability.

As this project was transferred from direct government control (JPMU) to ARIS, there are possible concerns about

government ownership. However, government is pleased with the oputcomes and anyway the key relationships are

at village/CDWUU/AO level. The relationship between central SES, local SES and CDWUUs for water quality

control (especially in relation to chlorination) remains a concern.

Asset disposal and value obtained by DFID

There were no assets to dispose of under this project. All of DFID’s spend went on activities.

H: MONITORING & EVALUATION (½ page)

Evidence and evaluation

The evidence base has not changed during the project. The evidence for project evaluation is not statistically

significant but is substantial and provides enough information upon which to make conclusions with a fair degree

of confidence. For DFID’s areas of support, hygiene behaviour change was a critical measure of success and this

was reported as being achieved in CHP’s impact assessment survey. It should be noted that the behaviour change

noted is only reported behaviour change, as in what answers were given by people when asked about hygiene

behaviour (hand-washing practices in particular). Research by ICDDR-B in Bangladesh seem to confirm what

many in the sector have suspected for a while - that reported behaviour change is considerably greater than actual

behaviour change (in Bangladesh 10% improvements in reported behaviour were representing an approximate 1%

improvement in actual behaviour). However, in this case, the supporting evidence on facilities (proximity of water

especially) and school and community self-monitoring programmes gives a higher than normal level of confidence

about the actual impact achieved and its sustainability.

The data on CDWUU progress and performance is internally collected and collated by ARIS but has been

independently corroborated in 12 cases through site visits by DFID and World Bank evaluation teams.

Monitoring progress throughout the programme

Monitoring of progress throughout the programme’s duration has been regular, timely and comprehensive in light

of the major challenges encountered. There have been four Annual Reviews and each of these has been closely

coordinated with the World Bank to ensure a consistent line of enquiry and recommendations for improvement.

Recommendations have been thorough and responded to by project partners and have resulted in a project which

has delivered much. DFID has engaged regularly and supportively with project implementing partners and with the

World Bank and this was appreciated by all during PCR Mission.

Page 120: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

89

Smart Guide

The Programme Completion Report is the opportunity to reflect on the entire programme, its performance,

achievements, lessons and how learning will be shared to inform future programming.

The Programme Completion Report assesses and rates outputs using the following rating scale. ARIES

and the separate programme scoring calculation sheet will calculate the overall output score taking

account of the weightings and individual outputs scores

Description Scale

Outputs substantially exceeded expectation A++

Outputs moderately exceeded expectation A+

Outputs met expectation A

Outputs moderately did not meet expectation B

Outputs substantially did not meet expectation C

Teams should refer to the considerations below as a guide to completing the annual review template.

Summary Sheet

Complete the summary sheet with headline information on the programme and any follow up actions

Introduction and Context

Briefly outline the programme, results achieved and contribution to the overall Operational Plan and

DFID’s international development objectives. Where the context supporting the intervention has

changed from that outlined in the original programme documents explain what this will mean for UK

support

B: Performance and conclusions

Outcome Assessment

Brief assessment of whether the programme achieved the Outcome

Overall Output Score and Description

Progress against the milestones and results achieved that were expected as at the time of this review.

Lessons

Any key lessons you and your partners have learned from this programme

Have assumptions changed since design? Would you do differently if re-designing this programme?

How will you and your partners share the lessons learned more widely in your team, across DFID and

externally

C: Detailed Output Scoring

Output

Set out the Output, Output Score

Score

Enter a rating using the rating scale A++ to C.

Impact Weighting (%)

Enter the %age number which cannot be less than 10%.

Page 121: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

90

The figure here should match the Impact Weight currently shown on the log frame (and which will need

to be entered on ARIES as part of loading the Annual Review for approval).

Revised since last Annual Review (Y/N).

Risk Rating

Risk Rating: Low/Medium/High

Enter Low, Medium or High

The Risk Rating here should match the Risk currently shown on the log frame (and which will need to

be entered on ARIES as part of loading the Annual Review for approval).

Where the Risk for this Output been revised since the last review (or since inception, if this is the first

review) or if the review identifies that it needs revision explain why, referring to section B Risk

Assessment

Key points

Summary of response to issues raised in previous annual reviews (where relevant)

Recommendations for future programmes

Repeat above for each Output.

D Value for Money and Financial Performance

Key cost drivers and performance

Consider the specific costs and cost drivers identified in the Business Case

Have there been changes from those identified in previous reviews or at programme approval. If so,

why?

VfM performance compared to the original VfM proposition in the business case. Performance

against vfm measures and any trigger points that were identified to track through the programme

Assessment of whether the programme represented value for money? Overall view on whether the programme was good value for money

Quality of Financial Management

Consider our best estimate of future costs against the current approved budget and forecasting profile

Have narrative and financial reporting requirements been adhered to. Include details of last report

Have auditing requirements been met. Include details of last report

E Risk

Quality of risk management over the life of the programme. How were risks managed, the degree to

which they were realised and/or mitigated.

F: Commercial Considerations

Delivery against planned timeframe. Y/N

Compare actual progress against the approved timescales in the Business Case. If timescales are off track

provide an explanation including what this means for the cost of the programme and any remedial

action.

Performance of partnership

How well are formal partnerships/ contracts working

Are we learning and applying lessons from partner experience

Could DFID be a more effective partner

Asset disposal and value obtained by DFID

How were assets managed throughout the programme? How have they been (or will they be) disposed to

get maximum value?

H: Monitoring and Evaluation

Evidence and evaluation

Changes in evidence and implications for the programme

Page 122: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

91

Where an evaluation is planned what progress has been made

How is the Theory of Change and the assumptions used in the programme design working out in practice

in this programme? Are modifications to the programme design required?

Is there any new evidence available which challenges the programme design or rationale? How does the

evidence from the implementation of this programme contribute to the wider evidence base? How is

evidence disaggregated by sex and age, and by other variables?

Where an evaluation is planned set out what progress has been made.

Monitoring process throughout the programme

Direct feedback you have had from stakeholders, including beneficiaries

Monitoring activities throughout review period (field visits, reviews, engagement etc)

The Annual Review process

Page 123: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

90

Annex 8b. Government Comments to the ICR18

/unofficial translation/

Letterhead of the State Agency for Architecture, Construction, and Housing and Utility

Infrastructure

under the Government of the Kyrgyz Republic

April 13, 2015

Outgoing # 18/573

Ministry of Finance of the Kyrgyz Republic

Cc: World Bank Country Office in the Kyrgyz Republic

Community Development and Investment Agency (ARIS)

of the Kyrgyz Republic

Having reviewed the submitted draft Implementation Completion and Results Report

(ICR) for the Second Rural Water Supply and Sanitation Project in the Kyrgyz Republic,

we would like to inform you of the following.

1. It should be noted that, in our opinion, the Implementation Completion Report for the

first and second phases of the Rural Water Supply and Sanitation Project financed by

the World Bank was prepared with due attention paid to every aspect.

2. Taking into account the difficult drinking water supply situation in the country, and

particularly in the rural areas, in the early 2000s, the Kyrgyz Government concluded

agreements with the World Bank and Asian Development Bank for financing projects

implemented in the drinking water supply sector.

3. At the same time, it should be noted that during that period the Kyrgyz Government

lacked experience and skills required for implementation of such large-scale projects

not only in drinking water supply but also in other sectors.

18 Footnotes included in this section were not part of the original comments from the Borrower, rather they

have been introduced to put in context, clarify, or comment on some of the Government comments where

deemed necessary.

Page 124: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

91

4. Moreover, the hastily adopted Taza Suu19 National Program did not contain concrete

goals and tasks and lacked requisite calculations and implementation action plan that

would have outlined the development prospects for this sector.

5. Without such clearly stated goals, tasks, and calculations, the Kyrgyz Government

undertook these broad yet unrealistic commitments and promised within 5-6 years to

provide safe drinking water supply to over 1,000 rural communities all over the country.

6. As it is well known, the numerous attempts by international consultants and local

specialists to design and adopt a strategy for drinking water supply and sewerage

development were blocked by the Ministry of Finance of the Kyrgyz Republic.

7. Besides, local communities were not properly prepared for implementation of the

projects and there was no improved legislation regulating not only the water supply and

sanitation sector but also operations of local self-governments responsible for handling

local issues.

8. For these reasons, the project was implemented by an international consulting company

together with newly established rural drinking water user associations (RDWUAs),

although there existed the respective laws of the Kyrgyz Republic “On State

Administrations and Local Self-Governance,” “On Financial and Economic Principles

of Local Self-Governance,” and “on Municipal Ownership of Property.”

9. Based on provisions of these laws, local self-governments could have established

municipal enterprises for operation and maintenance of water supply lines, while

creation of RDWUAs was not stipulated in the existing legislation.

10. As a result, the role of local self-governments was ignored, and they remained

unengaged in the preparation and implementation of projects by implementing agencies

and donors.

11. In addition, we need to acknowledge that division of the country’s regions into the

South and North by the donors was not carefully thought-through for ethical and other

reasons.

12. Another matter of contention under the Project was hiring an international consulting

company20 for implementing the Project, that was not familiar with the situation in the

Kyrgyz drinking water supply sector and in the country in general.

19 The Taza Suu is the program launched by the GoKR in 2002, which included the previous RWSSP and

the ADB financed CBICBP.

20 This comment does not apply to the current project, as there was no international consulting company

hired for it. Similarly, comment 13 does not apply to RWSSP2. Finally, Comment 14 highlights a general

weaknesses in local capacity for geological and topographic surveys in the Kyrgyz Republic, also

Page 125: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

92

13. This led to irrevocable mistakes also caused by the lack of required supervision by the

implementing agencies at the stage of determining subsurface and other types of water

sources. In most cases, these water sources were selected based on responses of

residents in villages that were to be included in the project.

14. These facts demonstrate that geological and site surveys were not duly and properly

performed.

15. The analysis held in 2012 by the State Agency for Construction and Regional

Development under the Government of the Kyrgyz Republic showed that 30% of water

supply facilities constructed or rehabilitated under this project and recognized as

problematic had design cost estimates that were prepared without due regard to their

quality and the established procedures.

16. In our opinion, another mistake made in the implementation of this project was

involvement of foreign construction companies 21 hired for rehabilitation and

construction of water supply systems, that were selected without proper assessment of

their competence and production capacities and that could withdraw from the project

whenever any difficulty arose.

17. This could be exemplified by Alke Insaat Sanain Ticaret Turkish company that stopped

construction of the water supply system in Kerben, Jalal Abad oblast, before the end of

the construction works due to the lack of production capacity and left the country.

Currently, the water supply facilities in Kerben are included in the list of problematic

facilities and a part of the local population have no access to drinking water.

18. We would also like to note that the report includes well-deserved recognition for the

Community Development and Investment Agency of the Kyrgyz Republic.

19. After ARIS was appointed as an implementing agency for water supply and sanitation

projects in 2011, the problems existing in geological and site surveying, design and

construction of rural water supply systems were successfully resolved as a result of

efforts undertaken by the Agency’s competent staff and management.

20. So far, there have been no complaints from local self-governments and population

regarding the 55 facilities constructed or rehabilitated by ARIS in Issyk Kul, Naryn,

and Talas oblasts.

acknowledged in supervision aide memoires. Any follow on operation will have to consider strengthening

capacity in these areas.

21 Comment (16 and 17) do not apply to RWSSP2. There were no foreign construction companies hired

for the project, and the projects did not work in Kerben or the Jalalabad Oblast.

Page 126: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

93

21. In this regard, the Department for Drinking Water Supply and Sewerage Development

shares the World Bank’s position with regard to ARIS as an implementing agency for

projects financed not only by the World Bank but also by other foreign and domestic

donors and investors.

22. We would also like to inform that the submitted report was discussed at the

Department’s meeting attended by all oblast- and rayon-level specialists who provided

the following recommendations for the next tranche to finance the third phase of this

project:

(i) split the functions of an implementing agency and implementing unit to prevent

conflict of interest, where the functions of an implementing agency should be

transferred to another state body;

(ii) the third phase of the project should be implemented in 62 villages in Chui, Osh,

Batken, and Jalal Abad oblasts in order to save funds for preparing design cost

estimates, as these documents were previously prepared and later revised by ARIS;

(iii) abandon division of the country into the Southern and Northern parts, i.e. donors

should cover the whole territory of the country with their activities;

(iv) projects should be implemented in strict compliance with the Presidential Decree

“On Amendments to the Presidential Decree ‘On the National Sustainable

Development Strategy of the Kyrgyz Republic for 2013-2017’” and the State Program

for Development of Drinking Water Supply and Sewerage for 2014-2024 adopted by

the Kyrgyz Government Resolution;

(v) settlements to be included in the list of facilities to be financed by the World Bank

should be selected by the State Agency for Architecture, Construction, Housing and

Utility Infrastructure in its capacity of a state body responsible for implementation of

the state policy for the drinking water supply and sanitation, with participation of the

World Bank and Kyrgyz Government’s Designated Representatives; the list of such

facilities should be provided to an implementing unit as per the established procedure;

(vi) the new project should pay due attention to institutional capacity building for

design engineers, construction personnel, the Water Supply and Sanitation Department,

the Architecture Agency, drinking water supply organizations engaged in the project

implementation, and other stakeholders;

(vii) local self-governments should be the key actors in the project implementation as

it is stipulated in the legislation of the Kyrgyz Republic;

(viii) abandon design and installation of street stand-pipes, but provide connection for

household water supply systems;

Page 127: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

94

(ix) provide support to the Department of Drinking Water Supply and Sewerage

Development in implementing fundamental reforms in the drinking water supply and

sewerage sector based on the experience of other European countries in this sector.

The Department of Drinking Water Supply and Sewerage Development remains to be the

key institutional partner of the project and main beneficiary under all activities aimed at

institutional development and implemented in other areas within the limits prescribed by

the Kyrgyz legislation.

Director T.

Mambetov

Page 128: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

95

/unofficial translation/

Letterhead of the Ministry of Finance of the Kyrgyz Republic

April 16, 2015

Outgoing # 16-2-2/4066

World Bank Country Office in the Kyrgyz Republic

Re: Rural Water Supply and Sanitation Project – 2

Herewith, the Ministry of Finance of the Kyrgyz Republic would like to express its respect

to the World Bank Country Office in the Kyrgyz Republic and inform you of the following.

After reviewing the draft Implementation Completion and Results Report for the Second

Rural Water Supply and Sanitation Project, the Ministry of Finance of the Kyrgyz Republic

in cooperation with the Community Development and Investment Agency and the State

Agency for Architecture, Construction, and Housing and Utility Infrastructure under the

Government of the Kyrgyz Republic would like to submit its comments and additions to

this report.

We would like to request you to incorporate the following changes and additions to the

report as stated below:

1) Clause 55 shall be revised to read as follows:

With regard to the issues of sanitation and hygiene, the Russian Federation provided USD

1mln. to UNICEF for implementing the project to finance water supply, sanitation, and

hygiene (WASH) facilities in Kyrgyz schools. This Project is comprised of two

components: 1) Sanitation and Hygiene Promotion and Education Component; 2)

Rehabilitation of WASH Facilities Component. Taking into account the fact that ARIS has

been successfully cooperating with state bodies (the Healthcare Ministry, Ministry of

Education and Science, National Health Promotion Center, Disease Prevention Department,

State Sanitary and Epidemiological Supervision Service, Department for Water Supply and

Sewerage Development) and civic organizations (rural healthcare committees, rural

drinking water user associations) in all villages nationwide and is a sustainable institution

having extensive experience of promoting WASH among local communities and schools

and mobilizing stakeholders’ support for resolving issues in this area, UNICEF signed an

agreement with ARIS for the implementation of the Russian Federation-sponsored project.

ARIS will be implementing the WASH Program in 90 selected schools all over the country

drawing on the models used together with UNICEF under the RWSSP-2. ARIS is planning

and taking active measures to replicate successes of the WASH program in additional

schools and communities through the use of best practices and for broader outcomes.

Page 129: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

96

2) Clause 64 shall be revised to read as follows:

The key outputs supporting better hygiene, sanitation, and water use practices and

pertinent outcomes. The Project, mainly through its Sanitation and Hygiene Promotion

Component (Component B) funded by the DFID and implemented by UNICEF, supported

promotion of better hygiene and sanitation practices in rural areas. Similar activities were

undertaken in schools in the three oblasts where the Project, through its Component A,

financed reconstruction or construction of demonstration facilities in total of 18 schools in

18 villages (see Annex 2 for more details). Representatives of schools, healthcare centers,

and communities in all the 55 villages were engaged in sanitation and hygiene promotion

campaigns. Two school teachers from each village participated in the UNICEF oblast-level

trainings based on the Water, Sanitation, and Hygiene Guidelines for Teachers and now

use the PHAST (Participatory Hygiene and Sanitation Transformation) method designed

for working with schools and communities in their respective oblasts.

3) Clause 67d shall be revised to read as follows:

d. Design of the financial model for water supply and sewerage development.

The Project hired an international consultant to design the financial model for the water

supply and sewerage sector and handed it over to the Department for Drinking Water

Supply and Sewerage with delivery of further trainings for their staff on how to use this

model.

4) Paragraphs c and d in Annex 2 “Component B” shall be revised to read as follows:

c) Dehelminthization. Two laboratory studies were carried out in each school, covering 25

school students (grades 1-4) each time. As result of the first testing, 211 children were

diagnosed with invermination, 209 of whom received medical treatment. One child from

Ak Olon village did not receive treatment due to his change of residence to Balykchy. The

costs of treatment with piperazine, albendazole, and mebendazole were paid by the parents.

All persons being in contact with the infected children (parents and other family members)

were sent to the rayon-level sanitary and epidemiological service for medical examination.

Local family practitioners issued prescription for medical treatment of these children. In

addition, doctors met with parents to provide detailed information regarding the need for

re-treatment.

d) Comprehensive needs assessment performed and annual costs of expendables and

services required for routine and limited extraordinary maintenance of WASH facilities in

schools estimated. The analysis was conducted based on the data obtained from schools in

the pilot villages covered by the RWSSP-2, as well as the data provided by the Ministry of

Education and Science, Healthcare Ministry and its local branches, and municipal

authorities. The assessment of needs/ costs for expendables and services of medical aid

points was not performed due to the decision not to construct any sanitary and technical

facilities of the Healthcare Ministry (this suggestion goes beyond the context). According

to the data of the Ministry of Education, average annual per student costs planned for 2013

Page 130: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

97

under the standard budget financing for rural schools were KGS 6.2. Since the actual

funding for this category of costs was 62.7%, the actual annual spending per student

amounted to KGS 3.89. Based on the data provided by the schools, calculations were made

for actual spending for operation and technical maintenance of WASH facilities. The pilot

schools in Talas on average spent KGS 27.5 per student per annum for operation and

technical maintenance of WASH infrastructure. For the purpose of comparison, similar

data were requested from a private school in Bishkek, according to which a private school

in Bishkek spends KGS 196.6 per student per annum. According to the sanitary norms of

the Russian Federation, average annual costs for disinfection and hygiene expendables,

expressed in Kyrgyz soms, amounts to KGS 287 per student per year. Thus, the estimated

monthly costs for purchasing cleaning/ disinfection and hygiene products per student

(based on the current local market prices) amount to KGS 23.5 (in case if liquid soap is

used) and KGS 28.7 (in case if bar soap is used), i.e. the costs for nine months of schooling

would be KGS 211.5 and the annual costs would be KGS 258 in 2013. These data were

confirmed by the actual costs data incurred by the school in Tuura Suu village, Ton rayon,

Issyk Kul oblast.

5) Paragraphs d in Annex 2 “Component C” shall be revised to read as follows:

d. Design of the financial model for water supply and sewerage development.

The Project hired an international consultant to design the financial model for the water

supply and sewerage sector and handed it over to the Department for Drinking Water

Supply and Sewerage with delivery of further trainings for their staff on how to use this

model.

We would like to note that the comments from the State Agency for Architecture,

Construction, and Housing and Utility Infrastructure under the Kyrgyz Government for the

aforesaid report were sent to you as Letter No. 18/573 dated April 13, 2015.

Best regards,

Deputy Minister M. Baigonchokov

Page 131: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

98

Annex 9. List of Supporting Documents

1. Project Appraisal Document dated March 27, 2009

2. Conformed Copy of Development Credit Agreement, dated May 21, 2009

3. Project Papers on Restructuring.

4. Development Credit Agreement (DCA) Amendment letters

5. Project Supervision Aides-Memoires

6. Project Implementation Status and Results Reports.

7. Project Financial Reports

8. Project Procurement Plans

9. Borrower’s Implementation completion report for Second Rural Water Supply and

Sanitation Project prepared by Community development and Investment Agency (ARIS),

October 2014.

10. Implementation Completion Report for the Rural Water Supply and Sanitation Project,

World Bank ICR00001084, dated May 15, 2009.

11. Programme Completion report, UK department for International development (DFID),

Review date September 2-9, 2014.

12. National Strategy for Sustainable Development of the Kyrgyz Republic 2013-2017, dated

January 21, 2013.

13. State Program for Development of Water Supply and Wastewater Disposal in Settlements

of the Kyrgyz Republic for the 2014-2024 period.

14. Verbal Interviews. In addition to the above documents, the ICR benefitted from a series

of interviews with various representatives of key stakeholders, including the Ministry of

Finance, the DRWS, the ministry of Health, ARIS, Various Local Governments (Ayil

Okmotus) and CDWUUs in Naryn Oblast, representatives of civil society, a sample of

participatory school teachers and pupils, Task Team Leaders, and representatives of

donor partners including DFID, UNICEF, and the ADB.

Page 132: Document of The World Bank Report No: ICR00003289 IMPLEMENTATION COMPLETION AND RESULTS … · Date achieved 06/22/2009 05/31/2013 10/31/2014 10/31/2014 Comments (incl. % achievement)

89