document of the world bank · 2018. 7. 6. · document of the world bank for official use only...

72
Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00002349 IMPLEMENTATION COMPLETION AND RESULTS REPORT TF Number: 010024 ON A GRANT IN THE AMOUNT OF $114.12 MILLION TO THE Islamic Republic of Afghanistan FOR A PUBLIC FINANCIAL MANAGEMENT REFORM II ( P120427 ) June 28, 2018 Governance Global Practice South Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 05-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • Document of The World Bank 

    FOR OFFICIAL USE ONLY  

     Report No: ICR00002349 

      

     IMPLEMENTATION COMPLETION AND RESULTS REPORT 

    TF Number: 010024 

    ON A 

    GRANT  

    IN THE AMOUNT OF $114.12 MILLION 

    TO THE 

      Islamic Republic of Afghanistan  

     FOR A 

    PUBLIC FINANCIAL MANAGEMENT REFORM II ( P120427 )  

     June 28, 2018   

    Governance Global Practice South Asia Region 

       

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  •  CURRENCY EQUIVALENTS  

     (Exchange Rate Effective June 1, 2018) 

     

    Currency Unit  =   Afghani (AFN) 

    71.20 AFN =  US$1  

     FISCAL YEAR 

    July 1 ‐ June 30                 

     

    Regional Vice President: Hartwig Schafer 

    Country Director: Shubham Chaudhuri 

    Senior Global Practice Director: Deborah L. Wetzel 

    Practice Manager: Ismaila B. Ceesay 

    Task Team Leader(s): Syed Waseem Abbas Kazmi, Adenike Sherifat Oyeyiola 

    ICR TTL: Bernard James Haven 

    ICR Main Contributor: Sati Achath  

  • ABBREVIATIONS AND ACRONYMS  

    ADB  Asian Development Bank  KPI  Key Performance Indicator ACCA  Association of Chartered Certified 

    Accountants LTO  Large Taxpayer Office 

    ACSI  Afghanistan Civil Service Institute  M&E  Monitoring and Evaluation ADB  Asian Development Bank  IAD  Internal Audit Department  AF  Additional Financing  IDA  International Development 

    Association AFMIS  Afghanistan Financial Management 

    Information System ISR  Implementation Status 

    Report ANDS  Afghanistan National Development 

    Strategy MOF  Ministry of Finance 

    ARDS  Afghanistan Reconstruction and Development services 

    PFC  Procurement Facilitation Consultant 

    ARTF  Afghanistan Reconstruction Trust Fund  PEFA  Public Expenditure and Financial Accountability 

    ATP  Audit Training Program  PFM  Public Financial Management CAS  Country Assistance Strategy  PMIS  Procurement Management 

    Information System CAT  Certified Accounting Technician  PPU  Procurement Policy Unit DFID  Department for International 

    Development RIMU  Reform Implementation and 

    Management Unit DG  Director General  SAO  Supreme Audit Office EA  Environmental Assessment  SBD  Standard Bidding Document FM  Financial Management  SIGTAS  Standard Integrated 

    Government Tax Administration System 

    FMC   Financial Management Consultant  SDU  Special Disbursement Unit GDP  Gross Domestic Product  STO  Small Taxpayer Office HR  Human Resources  TA  Technical Assistance NPA          National Procurement Authority  TOR  Terms of Reference NPC  National Procurement Commission  USAID  United States Agency for 

    International Development  NPI  National Procurement Institute  UNDP  United Nations Development 

    Program NPV  Net Present Value  VAT  Value Added Tax 

        

  •  

    TABLE OF CONTENTS  

    DATA SHEET ............................................................................................................................ 1 ABSTRACT ................................................................................................................................ 5 I.  PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ........................................................ 6 

    A. CONTEXT AT APPRAISAL ........................................................................................................... 6 B. SIGNIFICANT CHANGES DURING IMPLEMENTATION ................................................................. 9 

    II.  OUTCOME ...................................................................................................................... 11 A. RELEVANCE OF PDOs .............................................................................................................. 11 B. ACHIEVEMENT OF PDOs (EFFICACY) ........................................................................................ 12 C. EFFICIENCY ............................................................................................................................. 15 D. JUSTIFICATION OF OVERALL OUTCOME RATING ..................................................................... 18 E. OTHER OUTCOMES AND IMPACTS .......................................................................................... 18 

    III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 21 A. KEY FACTORS DURING PREPARATION..................................................................................... 21 B. KEY FACTORS DURING IMPLEMENTATION .............................................................................. 23 

    IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 24 A. QUALITY OF MONITORING AND EVALUATION (M&E) ............................................................. 24 B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ..................................................... 24 C. BANK PERFORMANCE ............................................................................................................. 25 D. RISK TO DEVELOPMENT OUTCOME ........................................................................................ 26 

    V.  LESSONS AND RECOMMENDATIONS .............................................................................. 26 ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ............................................................ 28 ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 44 ANNEX 3. PROJECT COST BY COMPONENT............................................................................. 46 ANNEX 4. EFFICIENCY ANALYSIS ............................................................................................ 47 ANNEX 5. BORROWER’S ICR .................................................................................................. 50 ANNEX 6. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ... 66 ANNEX 7. SUPPORTING DOCUMENTS .................................................................................... 67 ANNEX 8. SPLIT RATING CALCULATION .................................................................................. 68  

      

  • The World Bank Public Financial Management Reform II (P120427)

    Page 1 of 68

          DATA SHEET  

     

    BASIC INFORMATION  Product Information Project ID  Project Name 

    P120427  Public Financial Management Reform II 

    Country  Financing Instrument 

    Afghanistan  Investment Project Financing 

    Original EA Category  Revised EA Category 

    Not Required (C)  Not Required (C) 

    Related Projects            Relationship  Project  Approval  Product Line Additional Financing  P150632‐Second Public 

    Financial Management Reform Project (PFMRP II) ‐ Additional Financing 

    10‐Feb‐2016  Recipient Executed Activities 

    Organizations 

    Borrower  Implementing Agency 

    Islamic Republic of Afghanistan  The Islamic Republic of Afghanistan 

    Project Development Objective (PDO)  Original PDO The proposed PDO is to strengthen public financial management through effective procurement, treasury and audit structures and systems in line with sound financial management standards of monitoring, reporting and control.  Revised PDO To further strengthen the efficiency and effectiveness of Afghanistan’s procurement, treasury, and audit systems.   

  • The World Bank Public Financial Management Reform II (P120427)

    Page 2 of 68

    FINANCING    Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) World Bank Financing        TF‐10024  73,000,000  114,070,775  109,209,939 

    Total    73,000,000  114,070,775  109,209,939 

    Non‐World Bank Financing       Borrower     0     0     0 

    Total     0     0     0 

    Total Project Cost  73,000,000  114,070,775  109,209,939  

      KEY DATES 

       

    Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 14‐Jun‐2011  09‐Aug‐2011  01‐Nov‐2013  31‐Dec‐2014  31‐Dec‐2017    RESTRUCTURING AND/OR ADDITIONAL FINANCING 

     

     Date(s)  Amount Disbursed (US$M)  Key Revisions 01‐Sep‐2014  45.47   19‐Dec‐2015  66.20  Change in Loan Closing Date(s) 27‐Jan‐2016  68.72  Additional Financing 19‐Apr‐2017  90.49  Change in Loan Closing Date(s)   KEY RATINGS 

     

     Outcome  Bank Performance  M&E Quality 

    Moderately Satisfactory  Satisfactory  Substantial  

  • The World Bank Public Financial Management Reform II (P120427)

    Page 3 of 68

    RATINGS OF PROJECT PERFORMANCE IN ISRs  

     

    No.  Date ISR Archived  DO Rating  IP Rating Actual 

    Disbursements (US$M) 

    01  20‐Sep‐2011  Satisfactory  Satisfactory  0 

    02  18‐Apr‐2012  Satisfactory  Satisfactory  7.00 

    03  24‐Dec‐2012  Moderately Satisfactory  Moderately Satisfactory  15.89 

    04  24‐Jun‐2013  Moderately Satisfactory  Moderately Satisfactory  27.58 

    05  17‐Dec‐2013  Moderately Satisfactory  Moderately Satisfactory  33.73 

    06  30‐Jun‐2014  Moderately Satisfactory  Moderately Satisfactory  43.39 

    07  02‐Feb‐2015  Moderately Satisfactory  Moderately Satisfactory  49.81 

    08  30‐Jun‐2015  Moderately Satisfactory  Moderately Satisfactory  57.82 

    09  08‐Feb‐2016  Moderately Satisfactory  Moderately Satisfactory  68.72 

    10  21‐Jun‐2016  Moderately Satisfactory  Moderately Satisfactory  73.37 

    11  16‐Nov‐2016  Satisfactory  Satisfactory  77.90 

    12  15‐May‐2017  Satisfactory  Satisfactory  91.88 

    13  18‐Apr‐2018  Satisfactory  Satisfactory  106.21  SECTORS AND THEMES 

     

     Sectors Major Sector/Sector  (%)  Financial Sector   100 

    Public Administration ‐ Financial Sector  100   Themes   Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  

  • The World Bank Public Financial Management Reform II (P120427)

    Page 4 of 68

    Public Sector Management  101  Public Finance Management  48  

    Public Expenditure Management  48    

    Public Administration  53  Transparency, Accountability and Good Governance  53 

        ADM STAFF 

     

    Role  At Approval  At ICR 

    Regional Vice President:  Isabel M. Guerrero  Ethel Sennhauser 

    Country Director:  Nicholas J. Krafft  Shubham Chaudhuri 

    Senior Global Practice Director:  Onno Ruhl  Deborah L. Wetzel 

    Practice Manager:  Jennifer K. Thomson  Ismaila B. Ceesay 

    Task Team Leader(s):  Paul Edwin Sisk  Syed Waseem Abbas Kazmi, Adenike Sherifat Oyeyiola 

    ICR Contributing Author:      

            

  • The World Bank Public Financial Management Reform II (P120427)

    Page 5 of 68

    Abstract  

    The  Second  Public  Financial  Management  Reform  Project  (PFMR‐II,  2011‐2017)  sought  to  enhance  public financial management  by  strengthening  Afghanistan’s  procurement,  treasury,  and  audit  systems.  A  revenue mobilization component was added to the project in 2016. The project was completed in 6.5 years at a total cost of $106.2 million, which  included a  three‐year extension and $41.13 million additional  financing. The project achieved measurable results across the targeted areas in a challenging context.   Procurement  –  A  National  Procurement  Commission  and  National  Procurement  Authority  were  established during the project. This was a two‐dimensional reform model which addressed political and technical dimensions of procurement reform and has proven beneficial in the fight against corruption.    Treasury ‐ The implementation of an upgraded Afghanistan Financial Management Information System (AFMIS) was  completed,  providing  real‐time  access  to  financial  data  allowing  organizations  to manage  budgets  and financial transactions. The AFMIS is built around a centralized payment‐processing model,  in which all budget executions are managed at the Central Treasury in Kabul, and the ‘Mustofiats’ in the provinces.   Audit  ‐ The project provided employees with  training  in  Internal Audit  through  the Professional Certification Program (PCP), raising employee skills and abilities within the Ministry of Finance (MOF) and the line ministries. External audit coverage increased, including coverage of on‐budget donor financing.   Revenue ‐ The Afghanistan Revenue Department adopted a new organizational structure. Risk‐based compliance, audit,  legal and HR reforms were either fully completed or are at an advanced stage. The decline in domestic revenue collection was reversed and revenues have recovered.   As  a  result  of  the  outcomes  achieved  under  these  project  components,  donor  confidence  in  procurement, treasury and audit systems grew. At the time of project design, approximately $1.8 billion of donor financing was off budget. By the end of the project, 65% of this baseline off‐budget ODA was shifted on‐budget.  The  lessons  learned  in  this  project  will  inform  similar  operations  in  the  sector  in  Afghanistan  and  in  other countries.  For  example:  (i)  reducing  aid  dependency  requires  a  long‐term  transition  plan;  (ii)  the  shift  from projects to programs should be planned from the outset; and (iii) PFM is a key ingredient for a transition to on‐budget support, and (iv) in a fragile context, activities should be primarily driven by problem solving, rather than international best practices.  While project objectives have  largely been met,  the sustainability of some activities remains a challenge. For example, while the project successfully transitioned many tasks from advisors to government employees, many of those employees are paid a significant premium through donor funding.   Even though the project has met and is likely to meet all its targets, the overall outcome is rated as ‘Moderately Satisfactory’,  because of  separate outcome  ratings based on  the  share of  actual  disbursements made  in  the periods before and after the restructuring.   

  • The World Bank Public Financial Management Reform II (P120427)

    Page 6 of 68

    I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES  A. CONTEXT AT APPRAISAL 

    Context 

    1. Building an effective state was at the heart of  the reconstruction effort  in Afghanistan at the time of project design. After decades of war and civil  strife, Afghanistan  remained  fragile and security was a  serious obstacle  to  the  implementation  of  reconstruction  programs.  Strengthening  public  financial  management  to accelerate aid utilization, deliver faster and better services, and to improve transparency and accountability of public expenditure was a priority for the government from the outset of reconstruction.   2. The Government had made progress in establishing its Public Financial Management (PFM) system by the time of project design. The legal framework underpinning financial management was established with the adoption of the PFM law in 2005. Over the period that followed, international firms were engaged to support the Treasury Department, the former Afghanistan Reconstruction and Development Services (ARDS), and the Control and Audit office (CAO) in the areas of treasury operations, procurement, and audit.  

     3. While  this  progress  was  encouraging,  Public  Expenditure  and  Financial  Accountability  (PEFA) Assessments  in 2006 and 2007 highlighted  important PFM weaknesses. Critical actions were proposed  in the following areas: (i) development of PFM capacity in the line ministries (outside MOF); and (ii) strengthening of internal  and  external  audit  capacity,  including  formal  academic/professional  training;  and  revision  of  legal foundation based on international standards. 

     4. The macroeconomic context provided a significant challenge during project implementation. Economic growth averaged 9.4 percent per year from 2003 to 2012 and key social and infrastructure indicators, including school enrollment, life expectancy, and access to water improved. However, economic growth fell sharply to 1.5 percent in 2014 following an international military transition and a fiscal crisis unfolded with declining revenues leading to depleted cash reserves and accumulation of arrears.   Rationale for the Project  5. During the reconstruction period, support for the PFM was coordinated between multiple donors. The Bank led provision of technical assistance in Treasury, Procurement, and Audit. USAID, US Treasury, DFID, UNDP, and  ADB  provided  assistance  for  budget,  revenue management,  and  decentralization.  The  government  and donors requested that the project be financed under ARTF with IDA providing supervision and implementation support  as  it  represented  a  natural  continuation  and  deepening  of  reforms  supported  by  prior  IDA  grant operations. After another donor concluded financing for support for revenue management, this component was added to the project.   6. Building  core  PFM  capacity  in  the  government was  a  key  component  of  the  Bank’s  interim  support strategy for Afghanistan. The Bank had gained valuable insight on PFM issues in Afghanistan through the IDA‐funded  technical  assistance  projects  and  through  extensive  analytical  work  on  PFM.  The  Bank  was  well‐positioned  to  assist  the  government  in  implementing  the  PFM  Roadmap  that  called  for  reforms  to  ensure efficient, transparent and accountable use of public resources, increase aid absorption capacity and secure on‐budget donor aid, and improve development outcomes. 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 7 of 68

    Theory of Change (Results Chain) 

    7. The  original  project  development  objective  was  “to  strengthen  the  efficiency  and  effectiveness  of Afghanistan’s procurement,  treasury, and audit  systems  to ensure  transparent use of public  resources.” The project was  divided  into  four  components  to meet  this  overall  objective:  procurement,  treasury,  audit,  and reform  management.  This  fourth  component  supported  improvement  in  monitoring  and  management  of technical assistance and human resources in the MOF. Addressing these areas of reform together was seen as a complementary approach that would strengthen PFM throughout the budget cycle within the context of support provided by other donors. Consequently, a Results Framework was prepared which articulated project’s pathway from planned interventions to the intended outcomes. The logic of this results chain was valid and prudential. See diagram below: 

     Theory of Change 

    PDO: to strengthen public financial management through effective procurement, treasury and audit structures and systems Strengthen Procurement Efficiency   

    Activities  Outputs  PDO/Outcomes o Consultancy Services for PFC to 

    assist ARDS o Capacity Building in line 

    ministries and Provinces o Institutional Development for 

    legal framework 

    o Procurement Law passed by the Parliament  

    o Procurement rules of procedures approved, including debarment, appeal and review, domestic and foreign preference policy, and zero corruption tolerance policies 

     

    o Implementation of Procurement Reform Framework to achieve more economical public procurement and greater transparency 

    o Ministries fully capable of independent procurement processing and facilitating transparent utilization of donor resources for reconstruction and development 

    o Procurement capacity built in Line Ministries and Provinces o Procurement regulation and oversight strengthened;  o Procurement responsibility transferred to all Line Ministries 

    Underlying Assumptions: These outcomes will result in more economical public procurement and greater transparency Strengthen Treasury 

    Activities  Outputs  PDO/Outcomes o Treasury Operations Support and 

    System Development Activities o Treasury HR Capacity Building 

    Activities  o Professional Accounting 

    Organizations Development 

    o FMIS Maintenance and Enhancement in all line ministries and provinces 

    o Production of Qatia (statutory govt. FM statements) 

    o Moving to web based freelance Version 7 

    o Improved Treasury procedures to achieve full benefits of enhanced AFMIS  

    Underlying Assumptions: These outcomes will result in High level PFM performance with improved capacity Strengthen Audit System 

    Activities  Outputs  PDO/Outcomes o Capacity Building Activities o Institutional Development o IT Support 

    o Professional Certifications:  o 50 Internal Auditors o 20 Fraud Examiners o 10 IS Auditors o 20 Project Mgmt. Professionals 

    o Improved "Internal” and “External” Audit coverage   

    Underlying Assumptions: These outcomes will result in sound standards of monitoring, reporting and control  

    Project Development Objectives (PDOs) 

    8. The original project development objective was “to  strengthen public  financial management  through effective procurement,  treasury and audit  structures and  systems”  in  line with  sound  financial management standards of monitoring, reporting and control. 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 8 of 68

    Key Expected Outcomes and Outcome Indicators Indicator Name  Baseline  End of Project Target 1.  Donors shift 20% of their off‐budget official development assistance to Afghanistan to on‐budget 

     0% (at $1.8 billion) 

     20% cumulative increase 

    2.  PEFA ratings for internal audit improve to B  Rating of C: coverage under 50%, not done to recognized standard and no action by management 

    75% cumulative coverage of expenditure and 75 % revenue done to recognized standard and responses given to all audits done by MoF and action taken on most 

    3.  PEFA ratings for external audit improve to B  Rating of C: coverage under 50%, not done to a recognized standard and no evidence of follow‐up 

    75% cumulative coverage of expenditure done to an acceptable standard and evidence presented of follow‐up 

    4.  At least 50% of procurement under the budget is done by line ministries conducting stand‐alone procurement  

     Two ministries  

    Procurement under these should equal 50% of procurement   

    5.  Increased number of functions carried out by regular ministry staff that were previously carried out by contracted staff 

     0 

     20 separate functions in MOF   

     

    Components 

    9. Component 1: Procurement Reform (Original estimated cost: $21.47 million; actual cumulative cost $32.46 million): The component provided support to build procurement management capacity throughout the government and institutional capacity in the public and private sectors.  There were three sub‐components: 

     Sub‐component 1.1  ‐ Procurement Facilitation:  The activities  included consultancy services of a Procurement Facilitation  Consultant  (PFC)  to  assist  the  ARDS  in:  (i)  processing  civilian  on‐budget  public  procurement;  (ii) completing procurement regulatory and institutional frameworks; and (iii) capacity building through knowledge transfer to staff in the Line Ministries.    Sub‐component 1.2 ‐ Capacity Building: The activities included (i) support to the former Procurement Policy Unit (PPU) and Afghanistan Civil Service Institute (ACSI) to lead capacity building and institution building activities; and (ii) deployment of three groups of procurement specialists in the Line Ministries to: (a) liaise with the central authorities on training and support the application of training in operations; (b) act as procurement controllers to  contribute  to  the  preparation  of  procurement  plans,  report  on  progress  and  coordinate  input  into  the procurement management  information system (PMIS); and (c) as procurement facilitators, assist on complex procurement and accelerate budget execution.   Sub‐component  1.3  ‐  Institutional  Development:  Support  was  provided  to  complete  the  legal  framework, preparing a collection of all relevant legal documents and for operation of the Appeal & Review Committee, and training on dispute resolution. Support was also provided for designing an effective and strategic communication and procurement disclosure policy to raise awareness, and to enhance and operate PMIS. 

     10. Component  2:  Financial  Management  Reform  (Original  estimated  cost:  $23.88  million;  actual cumulative cost $39.84 million): The component supported high level PFM performance; and building staff and institutional PFM capacity throughout government through training, systems development and process renewal. There were four sub‐components: 

     

  • The World Bank Public Financial Management Reform II (P120427)

    Page 9 of 68

    Sub‐component  2.1  ‐  Treasury  Operations  and  Systems  Development:  Through  the  services  of  a  Financial Management Consultant, support was provided to develop treasury functions and strengthen internal controls and to provide counterpart training. Specific activities included establishment of a disaster recovery plan and equipping the Afghanistan Financial Management Information System (AFMIS) IT back‐up facility.  Sub‐component  2.2  ‐  Human  Resource  Capacity Development:  Support was  provided  to  develop  job‐specific certifiable finance and general skills of treasury and finance staff of MOF and the line ministries. Support was also provided to develop a Treasury Communications Plan and to implement support reforms.  Sub‐component 2.3  ‐  Professional Accountants Organization Development:  The activities  included  support  to establish the  legal  framework and structures  for development and regulation of  the accounting and auditing profession and for training of professional accountants in Afghanistan.  Sub‐component 2.4 ‐ Line Ministry PFM Assessments: This sub‐component financed a detailed review of internal control and PFM performance of seven line ministries. 

     11. Component  3:  Audit  Reform  and  Performance  (Original  estimated  cost:  $24.70  million;  actual cumulative  cost:  $34.27  million).  The  component  improved  public  sector  governance  through  nine  sub‐components, grouped under the following Internal and External Audits: 

     Internal Audit: Through three sub‐components, support was provided for  institutional reforms in the internal audit and capacity building activities to improve management oversight. Support was also provided to develop information systems and training in automated auditing tools.  External Audit:  Through six  sub‐components,  support was provided  for  capacity building and  carrying out of independent reviews of on‐budget donor‐funded operations, including all operations under the budget of nine line ministries over the project period. Additional support was provided for the Public Accounts Committee and the purchase of the office and IT equipment for the new Chief Audit Officer. 

     12. Component 4: Reform Management (Original estimated cost: $2.95 million; actual cumulative cost: $3.72  million).  The  component  supported  activities  to  improve    monitoring  and  management  of  technical assistance  and  human  resources  in  MOF,  through:  (i)  strengthening  monitoring  and  evaluation  (M&E);  (ii) strengthening MOF Human Resources (HR) Management Department; (iii) project management; and (iv) other institutional strengthening and capacity building to strengthen M&E, HR management development, and project executive management  functions  in  the MOF  in addition  to other  related  technical assistance and analytical work. 

    B. SIGNIFICANT CHANGES DURING IMPLEMENTATION 

      Revised PDO, Results Framework, and PDO Indicators 

    13. Revised Project Development Objective: The PDO was revised to make it more specific and measurable by  linking  it  to  the  PFM  Strategy  as  follows:  “To  further  strengthen  the  efficiency  and  effectiveness  of Afghanistan’s procurement, treasury, and audit systems.”   14. Revised  Results  Framework:  During  implementation,  the  Results  Framework  was  revised  to  reflect organizational  changes  in  the  government.  Most  notably,  the  National  Procurement  Authority  (NPA)  was 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 10 of 68

    included  as  the  successor  organization  to  ARDS/PPU.  Changes  were  also  introduced  to  enhance  results monitoring to reflect citizen engagement and gender issues.   15. Revised PDO Indicators: Revisions were introduced to audit reform indicators to eliminate any reference to the Public Expenditure and Financial Accountability methodology. The new wording of the indicators focused more on the quality and scope of audit coverage that was in the spirit of the original PDO indicators. A new, more relevant indicator related to the Procurement Reform component, was introduced to replace the one that had become irrelevant and difficult to measure. Another indicator was introduced on the theme of accountability and  transparency  in  publishing  procurement  decisions.  The  indicator  pertaining  to  the  increased  number  of functions  carried  out  by  regular  ministry  staff  was  further  refined  to  focus  on  the  development  and implementation  of  plans  to  transit  posts  to  programs  such  as  Capacity  Building  for  Results.  The  Results Framework and monitoring indicators were revised and updated as below: 

     Indicator Name  Baseline  End Target (2017) Donors shift their off‐budget official development assistance to Afghanistan to on‐budget. 

     0% 

     20% 

    Reduction in number of days taken by the National Procurement Commission to dispose of cases presented to it.  

     10 days 

     7 days 

    Establish a database of, and publicly disclose, National Procurement Commission decisions. 

     2 days 

     1 day 

    The Supreme Audit Office commences development of a mechanism for citizen participation in audit. 

    No Citizen participation in audit 

    Preparation for citizen participation in audit during FY16 leading to development of mechanism for citizen participation in audits and issuance of policy governing citizen participation in public oversight of public funds by June 30, 2017. 

    Increased number of functions carried out by regular ministry staff that were previously carried out by contracted staff. 

    Plans currently work in progress 

    Plan in place for FY17 to modify Tashkeel to include functions currently undertaken by national consultants. FY16 Plan implemented. 

    Improved coverage and quality of internal audit  49  50 Improved coverage and quality of external audit  49  75 

     16. Revised Components: The original  components were not  revised during  implementation. However, a new component related to ‘Revenue Mobilization’ was added to the project design. DFID‐financed support for revenue concluded  in 2015, and  follow‐on assistance was  requested by Government and donors  in  this area following a significant decline in revenues. This component complemented revenue mobilization targets under the ARTF incentive program and the IMF program. The activities supported were related to the maintenance of computerized tax systems (SIGTAS), the implementation of risk‐based compliance, preparation for value added tax  (VAT), and establishing a new organizational structure. The new Revenue Mobilization component  ($3.85 million) was added under the Additional Financing when another donor concluded its program in this area.  

    Other Changes: 

    17.  Additional  Financing  (AF):  Additional  Financing  of  $41.13  million1/  was  provided  to  finance  costs associated  with  scaling  up  of  successful  activities  and  to  sustain  achieved  results  under  the  project.  The government requested the Bank to develop a follow‐on project to support the implementation of key aspects of the new PFM Strategy. The AF acted as a bridge to avoid any gap in the Bank’s PFM support and losing momentum 

    1 Effective on January 27, 2017 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 11 of 68

    on key results that had been achieved under the project. The AF was also utilized to finance the new component (Revenue Mobilization), which was at the top of the government’s priorities, requiring around $3.85 million.  18. Extension of Grant Closing Dates: The project was extended three times: (i) from the original December 31, 2014 closing to December 31, 2015, to provide the government more time to complete implementation of ongoing activities; (ii) from December 31, 2015 to June 30, 2017 to give additional time to complete ongoing activities, and to prepare AF for the project; and (iii) from June 30, 2017 to December 31, 2017, as some activities were still unfinished and required additional time to be completed while a follow‐on project was prepared.   19. Revised Cost Estimate: With the inclusion of AF, the original costs were revised as below:  

    Comparison of Original Amount vs. Revised Costs by Component (US$ Million) 

     Components 

     Original Amount 

     % of Total   AF 

    %  of Total with AF 

     Revised  Total 

    Overall Percentag

    e Financing 

    1: Procurement Reform   21.47  29.4%  11.00  26.8%  32.47  28.4% 2: Financial Management Reform   23.88  32.7%  15.96  38.8%  39.84  35.0% 3: Audit Reform and Performance       Comprising:         Internal Audit         External Audit  

    24.70  

    09.60 15.10 

    33.8%  

    13.2% 20.6% 

    9.57  

    4.07 5.50 

    23.2%  

    9.8% 13.4% 

    34.27  

    13.67 20.60 

    30.0%  

    12.0% 18.0% 

    4: Reform Management   2.95  4.1%  0.77  1.9%  3.72  3.3% 5: Revenue Mobilization   ‐  ‐  3.84  9.3%  3.84  3.3% Total   73.00  100%  41.13  100%  114.13  100% 

    Rationale for Changes and their Implication on the Original Theory of Change 

    20. The provision of AF did not have any major  implication on  the  theory of  change.  In  fact,  it  provided additional resources that contributed to more effective linkages in the result chains. It also addressed a shift in complementary financing from other donors, as revenue was moved from DFID support into PFMR‐II.  

     II. OUTCOME  A. RELEVANCE OF PDOs 

    21. The relevance of the project development objective is rated as High. The PDO was relevant to the Bank’s goals and donor‐supported PFM reform objective. It reflected government’s key priorities as given in the PFM Roadmap presented at the Kabul Donor Conference in June 2010. The PDO remains highly relevant to the Country Partnership Framework (2017‐20). The PDO was also in line with the government’s Strategic Plan, prepared by MOF (as custodian of PFM), that proposed reforms to produce greater efficiency in managing public resources and maintaining  standards  for oversight and governance.  The  strategy  called  for  a participatory process and regular  support  to MOF decision‐makers  to ensure alignment of actions,  improved management of  technical assistance (TA), and regular contact and communications with partner ministries and agencies. However, two gaps were identified in the coverage of PDO indicators. Treasury operations were not sufficiently covered by the indicators and the addition of support for revenue mobilization with additional financing did not result  in the addition of any indicators.  

  • The World Bank Public Financial Management Reform II (P120427)

    Page 12 of 68

    B. ACHIEVEMENT OF PDOs (EFFICACY) Assessment of Achievement of Each Objective/Outcome  

    22. Since  the  original  PDO  and  some  of  its  associated  outcome  targets  were  formally  revised  through restructuring, separate outcome ratings have been weighted in proportion to the share of actual disbursements made in the periods before and after the restructuring. Based on the two ratings, as shown Annex 7, the overall achievement  of  the  project  is  rated Moderately  Satisfactory.  The  project’s  achievements  in  terms  of  PDO indicators before and after restructuring are given below: 

     PDO Indicators  Original Project   After Restructuring/AF Target  Actual  Target  Actual 

    1.  Increased number of functions carried out by regular ministry staff that was previously carried out by contracted staff 

    20 separate functions in MOF 

     

    Plans work in progress 

    Plan in place for FY17 to modify Tashkeel to include functions that are currently undertaken by national consultants. Equivalent FY16 Plan implemented. 

    Plans currently work in progress.  On target: Treasury has succeeded in transitioning some key functions from advisors to civil servants; NPA now carries out key managerial functions through civil servants and number of Tashkeel staff now exceed the number of TAs.  

    2.  Donors shift their off‐budget official development assistance to Afghanistan to on‐budget 

    20% cumulative increase 

    62% cumulative increase  20% cumulative increase  65% cumulative increase 

    3.  The Supreme Audit Office commences development of a mechanism for citizen participation in audit (New Indicator) 

    N/A  N/A 

    Preparation for citizen participation in audit during FY16 leading to development of mechanism for citizen participation in audits and issuance of policy governing citizen participation in public oversight of public funds by June 30, 2017.  

    SAO has developed a mechanism for citizen participation in audit / issued a policy governing citizen participation in public oversight. SAO has also developed the annual work plan for public participation in audit process, and is organizing a one‐day seminar for relevant stakeholders 

    4.  Establish a database of, and publicly disclose, National Procurement Commission (NPC) decisions (New Indicator). 

    N/A  N/A  One  One 

    5.  Reduction in number of days taken by the National Procurement Commission to dispose of cases presented to it (New Indicator).  

    N/A  N/A  10 Days  to dispose of cases 7 Days 

    to dispose of cases 

    6.  Improved coverage and quality of internal audit (Revised) 

    75% cumulative coverage of expenditure and 75% revenue done 

    50 Audits 

    MOF IAD audits 50% of budgeted expenditure & (for entities which collect) revenue 25%, 

    56% coverage of expenditure and 42% coverage of revenue completed. 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 13 of 68

    to recognized standard and responses given to all audits done by MOF and action taken on most. 

    within its mandate, as per recognized standards such as International Standards for the Professional Practice of Internal Auditing, issued by the Institute of Internal Auditors.  Unit of Measure = % 

    7.  Improved coverage and quality of external audit (Revised) 

    75% cumulative coverage of expenditure done to an acceptable standard and evidence presented of follow‐up 

    74%  75%  71% 

    8.  % of procurement done by LM using stand‐alone procurement (Deleted) 

    50  48  N/A  N/A 

    9.  Number of functions carried out by regular ministry staff (Deleted) 

    20  17  N/A  N/A 

     23. Project outcomes before Restructuring: The original PDO had  three components.  “To strengthen  the efficiency  and  effectiveness  of  Afghanistan’s  (1)  procurement,  (2)  treasury,  and  (3)  audit  systems  to  ensure transparent use of public  resources.”  The overall  theory of  change was  that  these  reforms would have more impact when implemented together, in concert with budget and revenue support provided by other donors.   24. Since effectiveness, the project performed well and disbursed nearly $68.72 million (94%) out of the total original commitment of $73 million. Satisfactory progress was made on three of the five PDO Indicators. Overall, the indicator on donor contributions to the budget was satisfactory (62% of baseline off‐budget ODA was shifted on‐budget, against 20% targeted).  25. Outcome 1 – Procurement – Substantial: Standalone procurement capacity was satisfactory. Although the NPC had 28 days to decide on a case in law, it was taking on average one week for a case to go NPC against seven days targeted. NPA was carrying out key managerial functions through civil servants, meeting its planned target in 2017. The NPA began posting all procurement on a single website, improving transparency.  

     26. Outcome 2 – Treasury – Substantial:  PDO indicators did not cover the implementation of the upgraded treasury systems. However, Treasury was successful  in  transitioning some key  functions  from advisors  to civil servants, albeit civil servants paid a special premium (the National Technical Assistance (NTA) pay scale) leading to gains in cost efficiency. Transaction time was reduced as ministries and agencies have been able to directly access Treasury systems.  

     27. Outcome 3 – Audit – Modest: Only moderate progress was made on the internal and external audits2/ and on the development of  the professional accountancy organization. The Professional Accountants Organization  2 Mainly due to the change in the legal framework on internal audit and a delay in mobilizing technical assistance for the external audits of the line ministries 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 14 of 68

    Development sub‐component faced considerable challenges in establishing a legal framework and structure for development and regulation of the profession and training of professional accountants. The draft Accountancy Law  remained  pending  with  the Ministry  of  Justice  for  approval  as  it  stayed  with  the  President’s  office  for extensive discussions. Furthermore, the change of mandate of the Internal Audit Department adversely affected the prospect of achievement of the PDO Indicator for internal audit.3 Regarding the external audit subcomponent, while good progress was observed, there were delays in mobilizing TA for the external audits of the Line Ministries.  

     28. The project results framework and component activities were amended through restructuring and for Additional Financing to accommodate the performance issues discussed above. Project performance was rated ‘Moderately Satisfactory’ for PDO and Implementation Progress.  29. Project  outcomes  after  Restructuring:  After  restructuring,  PDO  had  three  components.  “To  further strengthen the efficiency and effectiveness of Afghanistan’s (1) procurement, (2) treasury, and (3) audit systems.” The overall theory of change remained the same ‐‐ these reforms would have more impact when implemented together. 

     30. Progress after restructuring improved and most targets have been met. Overall, the indicator on shifting off‐budget  official  development  assistance  on‐budget met  its  target  ‐  65%  achieved  against  65%  targeted. Additionally,  the  increased number of  functions  carried out by  regular ministry  staff previously  carried out by contracted staff (consultants) met its target. Many functions of the MOF previously carried out by consultants are now performed by civil servants. However, many positions continue to require special pay arrangements, and consultants  continue  to  advise  on  key  functions  in  the ministry.  It  is  not  clear  from  the  PDO  indicator what percentage of key functions of the MoF have been transitioned. This issue is discussed further in Lessons Learned.  

     31. Outcome 1 – Procurement – Substantial: The targets for procurement were met. Establish a database of, and  publicly  disclose,  National  Procurement  Commission  (NPC)  decisions.  This  target  is  fully  met.  The  NPC decisions are reported immediately after each session, against one day targeted. The NPA has made substantial progress  in  improving  transparency  through  the publication of  tenders, awards,  standard bidding documents, debarments, decisions, and laws on a comprehensive website. Decision forms are available on the NPA website within  the  same day.  Reduction  in number of days  taken by  the NPC  to dispose of  cases presented  to  it.  This indicator has exceeded its target. On average now, seven days is taken against seven days targeted. By law, NPC has 28 days to decide on a case unless the package is submitted incomplete. In FY2017, the NPC held 51 weekly meetings, approving 446 projects with a total value of $2.2 billion.   

     32. Outcome  2  –  Treasury  –  Substantial:  In  Treasury,  the  presence  of  civil  servants  has  increased  for  all functions including FM activities, allotment and commitment, cash management, debt management as well as AFMIS operation. Hiring of local Tashkeel staff is ongoing. As Treasury Department capacity increased, reliance on external firms was reduced. No external firms have been contracted for treasury operations since 2014. However, many civil servants with technical capacity in these areas continue to be paid special premiums. This is discussed further  in  Lessons  Learned.  Development  partners  have  received  the  AFMIS  dataset  for  seven  fiscal  years, providing for a detailed review of transactions (over 400,000 lines of data) and increased confidence in on‐budget financing. This data has been used to improve third‐party monitoring such as employment verification to improve public perceptions of the use of public resources. The web‐based system allows for real‐time access to live data  3 As a consequence of the amendment of Article 61, responsibility for internal audit remains a subject of discussion between MoF and SAO.  

  • The World Bank Public Financial Management Reform II (P120427)

    Page 15 of 68

    eliminating previous delays in relaying information to ministries and agencies.   33. Outcome  3  –  Audit  –  Substantial:  The  Supreme  Audit  Office  (SAO)  commences  development  of  a mechanism for citizen participation in audit. This target is fully met. The SAO has issued a policy in this regard. Improved coverage and quality of “internal audit”. This target is fully met. The progress was initially slower than expected as  limited audits were performed in the provinces due to factors outside of the control of the Bank; however,  the  improved  expenditure  coverage  is  now 56% and  improved  revenue  coverage  is  42%.  Improved coverage and quality of “external audit”. This target is not fully met. The improved audit coverage now stands at 71% against 75% targeted. The SAO is presently working to increase the audit coverage. 

     34. Rating Before Project Restructuring (August 9, 2011 ‐ January 1, 2016):  The Efficacy before restructuring is  rated as Modest. While  there was satisfactory progress on three of  the  five PDO  Indicators, only moderate progress was achieved on internal and external audit aspects due to a change in the legal framework on internal audit procedures and delay in mobilizing TA for external audits of the Line Ministries. As a result, the project team continued  to  rate  the  project’s  performance  as  ‘Moderately  Satisfactory’,  for  both  PDO  and  Implementation Progress. 

     35. Rating After Project Restructuring (January 2, 2016 – December 31, 2017): The Efficacy after restructuring is rated Substantial. Despite political challenges, the project responded well by keeping its focus on developing PFM systems in the Line Ministries and providing intensive training in procurement, financial management and audit, across various government departments. Targets were mostly fully met, and in few areas, exceeded goals. 

     Justification of Overall Efficacy Rating   

    36. The overall efficacy is rated as Substantial. This is based on individual ratings of Relevance of PDO (High), and Achievement of PDO (Substantial).  

    C. EFFICIENCY Assessment of Efficiency and Rating 

    37. The  Efficiency  is  rated  as  Substantial.  The  implementation  of  the  project  is  considered  efficient.  An economic analysis was not performed at appraisal and there is no original projection for the Net Present Value (NPV)  or  Economic  Rate  of  Return  (ERR).  This  limits  the  extent  to  which  a  comprehensive  analysis  can  be performed at the ICR stage. Credible economic benefit calculation leading to NPV and external rate of return is challenging  with  broad‐based  PFM  reforms,  as  it  is  difficult  to  claim  attribution  to  all  downstream  benefits. Nevertheless, an estimate of project costs and benefits is estimated in Annex 4. The main benefits of the project include efficiencies gained from shifting ODA on‐budget and savings from efficiency of public procurement. The shift  in ODA depended on  implementation of  all  project  components.  The NPV of  the project  at  a  5  percent discount rate is $1,021 million and at a 12 percent discount rate is $832 million. The EIRR is calculated at 236.5 percent. As discussed in the annex, this approach provides an indicative analysis only, as the outcomes supported in this project cannot be solely attributed to project activities.  38. The project also yielded non‐financial benefits. Line Ministries are increasingly able to execute budget and deliver services more efficiently and Government is increasingly empowered to manage and direct development partner  resources  through  the budget  cycle. Procurement  is more  transparent,  treasury management  is more 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 16 of 68

    efficient and  is accessible within  line ministries, and audit  coverage and quality has  increased. Data access  in AFMIS is now real‐time, with no delays after data entry. These reforms have supported increased use of national systems by donors with a higher proportion of ODA flowing through the budget. Capacity building of civil servants to operate PFM systems has contributed to the sustainability of these systems. Below are the benefits realized under various components: 

     Procurement Efficiency  39. Structural Efficiency: The procurement structure in the MoF and the Ministry of Economy was scattered prior to initiation of reform. The of functions under the NPA, as one single regulatory body, resulted in an efficient structure. Also, NPA acting as the Secretariat of the NPC has further strengthened the efficiency.  40. Efficiency in Accountability (Cultural Efficiency): Because of NPC oversight and the follow up activities by NPA, there is more responsiveness and accountability within procurement entities and the Line Ministries. 

     41. System/Process  Efficiency:  By  law,  the  service  standard  for  NPC  to  decide  on  award  of  a  project submission of documents is 28 days; however, track records show that award decisions are made more efficiently and in less than 28 days. Moreover, Bid Evaluations are now done by procurement entities, which in the past were an open‐ended process, which generally took more than two years. After the reform, the service standard is set to be 30 days plus one‐time possibility of extension. 

     42. Savings,  Safeguarding  and  Contribution  to  Revenue:  The  establishment  of  the  NPA  has  resulted  in increased confidence in national procurement systems. The use of unified Rules of Procedures required vendors who participate in the bidding to settle their tax arrears as a condition of participation. This has positively affected revenues. 

     43. NPA is also in early stage of initiating the assessment of Afghanistan’s readiness for, and implementation of,  Electronic  Government  Procurement  (eGP)  as  part  of  the  government’s  vision  and  efforts  toward  e‐governance.   

     Treasury Efficiency  

    44. The upgraded AFMIS is providing real‐time access to financial data which allows organizations to keep track  of  their  budgets  and  financial  transactions.  The  web‐based  AFMIS  system  was  implemented  in  all  34 provinces  and  all  line ministries  in  Kabul.  The  system was built  and deployed  around  a  centralized payment‐processing model, where all budget executions are managed at the Central Treasury in Kabul and the ‘Mustofiats’ in the provinces.  45. Based on the continued efforts of Treasury General Directorate, local banks have been able to integrate their systems with communication companies, which provide their customers with access to their salary accounts by using mobile banking facility. This is particularly helpful in areas that do not have access to the bank branches.  

     46. The Pilot project of mobile banking started in Kapisa province in north of Kabul in July 2015, and the first payment of salary to Afghan Local Police through mobile took place in August 2015. The new payment mechanism is  greatly  appreciated  by  Afghan  Local  Police  leadership  and  the  funding  donor,  and  the  Combined  Security 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 17 of 68

    Transition Command Afghanistan (CSTCA), as the process helps remove ghost employees and strictly limits the payment of salary to a second party by capturing the employees fingerprint into the system.  

     Audit Reform and Performance Efficiency  

    47. The  project  supported  the  adoption  of  good  practices  in  internal  audit  through  the  adoption  of  the Institute of  Internal Auditors  (IIA)  standards. Manuals,  guidelines and  similar materials have been developed, resulting in a common approach to internal audit amongst audit professionals employed at the Ministries and the Independent Directorates. Skills were improved through the Professional Certification Program (PCP) provided to around  100  staff,  including  cadres  of  Internal  Auditors  of  the  MOF,  all  the  Line  Ministries  and  the  State Administered Directorates.4/  

     48. This program has resulted  in  immediate cost savings  for government.  In 2017, 962 staff were  trained against 500 envisaged and 175 internal audits were performed per standards as compared with 34 envisaged. As a result, out of $11.2 million collectable revenue, around $0.9 million was already recovered and deposited into the government’s account. Similarly, 52 civil servants were terminated due to fraudulent activities.  

       Revenue Mobilization Efficiency  49. The revenue component was introduced to the project in 2016. Following a significant reduction during the military transition, revenues recovered during project implementation, increasing 18% in 2016. In percent of GDP, the revenues increased from 8.7% in 2014 to over 11% in 20165/, which may be attributed to the revenue administration reforms, simplified returns filing requirements (5 steps to 3), functional appeals department, as well  as  some  policy  reforms  undertaken  by  ARD  (increase  in  Business  Receipts  Tax  from  2%  to  4%,  and introduction of a 10% fee on telecommunications in 2015). The decline and recovery of revenues is presented in the chart below.  

    4 (i) Certified Internal Auditors (50); (ii) Certified Fraud Examiner (20); (iii) Certified Information Systems Auditor (10); and (iv) Project Management Professionals (20). 5 Afghanistan’s fiscal year runs from approximately December 21 to December 20. https://www.usip.org/publications/2017/02/revenue‐growth‐afghanistan‐continues‐strong‐future‐uncertain 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 18 of 68

     50. Notable achievements under this component are:  

    A  clear  strategy  and  roadmap  developed  for  its reorganization to sustain reforms; 

    SIGTAS  implementation  in  all major  tax  offices  in Kabul  and  the provinces  has helped progressively increase transaction volume as core  functions are automated; 

    Fast‐track filing system completed to facilitate large taxpayers; 

    Risk‐based audit implemented;  Local  capacity  built  in  ICT,  audit,  legal  and  HR 

    reforms;  Taxpayers’  awareness  and  education  program 

    conducted.  

    Other Factors  51. There were only two Task Team Leaders (TTLs) for the implementation period of the project. Both were based in Kabul, which enabled them to maintain regular contact with the government and stakeholders.   This factor  was  critical  for  providing  the  client  with  timely  and  consistent  technical  and  operational  support  and capacity building, as well as facilitating project implementation significantly. 

     D. JUSTIFICATION OF OVERALL OUTCOME RATING 

    52. The overall outcome is rated as Moderately Satisfactory.  This is based on: (i) High rating for Relevance of PDO (based on relevance at closing); (ii) Modest rating for Efficacy before restructuring; (iii) Substantial rating for Efficacy after restructuring; (iv); Substantial rating for Efficiency (based on efficiency at closing). Using the ICR Guidelines Annexes H and I, the overall outcome rating is (v) Moderately Unsatisfactory before restructuring; (v) Satisfactory after restructuring. Annex 8 of this report presents the split rating calculation.  

     Split 

    Ratings Relevance of 

    Development Objectives Efficacy 

    Assessment Efficiency Assessment 

    Overall Outcome Rating 

    Before Restructuring High 

    Modest Substantial 

    Moderately Unsatisfactory 

    After Restructuring  Substantial  Satisfactory 

    Overall Outcome Rating        Moderately Satisfactory 

     E. OTHER OUTCOMES AND IMPACTS 

    Gender 

    53. The  original  project  did  not  specifically  target  women,  however  during  restructuring;  changes  were introduced in the Results Framework to include monitoring of gender involvement. Under the Audit Reform and Performance component, internship programs targeting women were offered to 60 female graduates from the MOF, four Line Ministries, and various Directorates. Under the Procurement Reform component, tailored courses 

    0%1%2%3%4%5%6%7%8%9%

    10%11%12%

    Domestic Revenues as  Percentage of GDP

    Direct taxes Sales tax (BRT)

    Customs duty Non‐tax revenues

  • The World Bank Public Financial Management Reform II (P120427)

    Page 19 of 68

    were offered to 3,024 personnel in the National Procurement Institute (NPI), which included 329 women (10%). Similarly, under Financial Management Reform component, 527 Treasury employees were offered Masters and Bachelor level courses of which 77 were female (15%).  

    Institutional Strengthening 

      Procurement 

    54. The  NPA  is  implementing  reforms  to  professionalize  and  digitize  public  procurement  to  address corruption and enhancing accountability. These efforts are divided into the restructuring of procuring entities, the  recruitment  of  procurement  professionals  and  the  professionalization  of  procurement  cadres  through training.   55. Restructuring procurement entities ‐ Under the leadership of the Presidency, the NPA and the National Procurement Institute (NPI) were established to lead these reforms. The NPA is the main body for strengthening of procurement systems in Afghanistan. NPA staff, many of which are consultants, are being moved into the civil service. The NPI works with 56 procuring entities to focus on capacity building activities.   56. Recruiting  procurement  professionals  ‐  To  professionalize  the  procurement  profession,  a  mass recruitment of civil service staff was completed in 43 procuring entities of the government agencies. Out of 36,787 applicants, 8,175 completed written exams and 697 procurement professionals were hired.   57. Professionalization ‐ To build the capacity of the procurement profession, an intensive capacity building program has been undertaken. The NPA staff was trained on World Bank procurement procedures. Key staff have been selected to complete master’s degree in sustainable procurement contract management, e‐procurement, and  supply  chain management  in  various  countries  including  India,  Italy,  and Afghanistan.  The NPI  has  been established  to  sustainably  continue  capacity  building  in  Afghanistan  by  providing  institutional  support  and Training,  developing  a  training  curriculum  and  training  trainers.  Training  of  Trainers  has  been  completed  on training techniques, procurement skills enhancement, and selected procurement topics. The NPI plans to conduct regular  and  special  procurement  training  for  the  newly  hired  procurement  personnel  through  the  mass recruitment. 

      Treasury 

    58. AFMIS has been upgraded and a web‐based payroll system was developed. Study visits were organized to Timor‐Leste  and  Kosovo,  countries  which  have  upgraded  Free‐balance  system  to  the  web‐based  version. Subsequently, MoF implemented the upgraded system in Afghanistan. Additionally, an electronic payroll system was implemented. All 34 provinces now have unified payroll data for Treasury, including all the Line Ministries, except the Ministry of Education.  59. Treasury  coverage extended  to Kabul Municipality. The extension of AFMIS  to Kabul Municipality has improved efficiency and compliance. Payroll calculations have been automated. It now takes only a day to process all  salaries  as  compared  to  ten  days  previously.  Legal  changes  to  rates  of  pay  have  now been  implemented. Workers who were not present were removed from the payroll, resulting in cost savings.  

     60. A capacity building program has been introduced for employees. Treasury employees can pursue their Bachelor’s  and Master’s  degrees  in  Accounting,  Finance,  Business Management  and  Computer  Science  after working hours, with reimbursement of tuition costs. The scheme aims to increase self–reliance,  confidence and 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 20 of 68

    skills of government staff and decrease the organization’s dependency on outside consultants. Over the past five years, more than 600 employees have enrolled in the program and 260 employees have successfully completed their course at universities across Afghanistan. As a result of this program, employees have been able to take on progressively higher responsibilities. Under civil service rules, employees at Grade 5 and above require a degree in  relevant  field. As a  result of  this  program,  capacity within  the Treasury Department  is  improving and  core functions have been carried out by staff (rather than consulting firms) since 2014.   

    Employees moving to higher positions within treasury/ MoF  40 Employees gaining higher positions in other ministries  10 Employees retaining positions post‐graduation course  210 

     61. Technical Support to Develop Afghanistan Accountancy law: The Accounting Law was developed and approved with technical support from the project. The Afghanistan CPA was formed under the Professional Accountants Organizations Development component.  62. Scholarship  programs  for  Association  of  Chartered  Certified Accountants  (ACCA)  students: MOU were signed with the Kabul University to establish an Accounting Department for curriculum development. A long‐term contract with the University of Malaysia has also been signed for capacity development of lecturers.  So far, more than 1,000 people have begun  the process of qualifying  (around a  third of  them women)  for  the  scholarship program, which  is encouraging  in a country where  less than fifth of the women over the age of 15 are  in the workforce. 

    Audit 

    63. Internal  Audit  ‐  Establishment  of  Internal  Audit  Committee:  The  Internal  Audit  Department  has established an Audit Committee in the MOF. Technical Audit Manuals, Audit Tool Kits, step‐by‐step guidelines on performing audits, including audit planning, programming, risk assessment, and preparing reports were provided. Audit  report  template  based  on  5‐Cs  (criteria,  conditions,  cause,  consequence,  and  corrective  actions)  were developed. Digitized audit reports were also introduced. 

     64. External Audit ‐ Institutional Development for SAO: Auditing standards with baseline for all audits were provided; professionalized audit unit were set‐up in each department – grant audit, specific audit, local budget audit, municipal audit. Twelve departments now have their own audit units; Audit follow‐up unit were established to follow‐up on compliances issues; Citizen engagement in audit; Information dissemination, citizen consultation, reporting fraud and investigation units have been established. 

     65. Support to Public Accounts Committee (PAC): The project supported establishment of PAC, which meets daily. Once SAO submits report, PAC must approve it before the next budget.  66. The SAO has completed the entire audit of World Bank projects for the fiscal year 2015, and submitted the report to World Bank and MOF. The SAO has completed the audit of Grants project and issued nine audit reports for various line ministries.   

     Revenue 

    67. IT  System  Operational  Nationally:  The  implementation  of  Standard  Integrated  Government  Tax Administration System (SIGTAS) has been completed in all major tax offices in Kabul and the provinces. Together with the installation of the new system and procurement of the required IT equipment (laptops, desktops etc.), the field staff were provided on‐the‐job training  in effectively using the system. This has helped progressively 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 21 of 68

    increase transaction volume as core functions are automated. As a result of this system, the reliability of taxpayer information  has  increased  and  audit  and  enforcement  measures  have  been  reinforced  while  simplifying procedures for taxpayers. This has underpinned an increase in revenues while supporting an improved business climate.   68. Risk‐based  Audit  Introduced  in  the  Revenue  Department:  During  the  project,  operating guidelines/manuals were developed; risk criteria were established; and compliance improvement plan and risk register  were  finalized.  A  compliance  improvement  committee  was  established  to  provide  guidance  in  case selection for audits. Performance Indicators have been developed to monitor performance over 3‐year period. As a result of this reform, audit resources can be targeted on high‐risk taxpayers. This is supporting increased revenue while supporting an improved business climate.  

    Other 

    69. The PFMR‐II Reform Implementation Management Unit (RIMU) supported initialization of good practices: Since the outset of the project, the RIMU has supported training and policy development to institutionalize good practices developed under  the project. At  the provincial  level,  human  resource policies and procedures were developed  and  training  on  these  policies  was  completed.  Policies  included  code  of  conduct;  merit  based appointment; leave management; guidelines relatives’ employment; occupational health and safety; job rotation; overseas  training  management;  performance  appraisal;  employment  incentives;  internship  policy;  policy  for contracted staff employment; and policy for scholarship committee. Induction Manuals were prepared in three languages – Dari, Pashto, and English. A “Questions Bank Book” was also prepared which was comprised of 2,700 questions on various subject matter, along with “answer‐key” from the MOF. 

    Poverty Reduction and Shared Prosperity 

    70. It is difficult to attribute the effect of the project on poverty reduction as it is an enabling function for service delivery. The project provided tools to the government to better plan, execute and monitor the budget. Improvements in internal and external audits provide better assurance on the use of budget and address waste and abuse. The SAO has also started performance audits that evaluate economy, efficiency and effectiveness of government  spending.  In  the  long  run,  the  project  would  benefit  the  poor  with  improved  public  finance performance and investment in social sectors. 

    Other Unintended Outcomes and Impacts 

    71. The  number  of  approved  learning  providers  and  institutions  for  the  courses  offered  by  ACCA  has increased from one to seven during project period, which is mainly attributed to the scholarships provided by the project to ACCA students, which has led to more demand for this course. This increase in the supply of training is likely to support the nascent accounting profession in Afghanistan.   

     III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME  A. KEY FACTORS DURING PREPARATION 

    72. In the context of weak public sector governance, the project preparation team recognized the challenges of  implementation  and  prepared  the  project  design  with  sound  background  analysis  and  comprehensive assessment of the government’s commitment. Lessons learned during the PFM operations in other jurisdictions as well as from the ongoing operations, at the time, were also considered to assess potential risks and mitigation measures. 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 22 of 68

    Lessons Learned during project preparation  

    73. The ICR of the Public Administration Capacity Building Project (IDA‐H1440) highlighted several issues that persisted under the then ongoing PFMR project that were considered in the design of this project. The issues and lessons learned are as follows: 

     (i)  Inadequate  Human  Resources  Capacity  in  PFM:  Engaging  international  firms  and  local  consultants  to perform basic PFM functions was a default strategy. Sustainability was difficult as local specialized advisors moved from the ministries to work on projects outside the budget or in the private sector while civil servants could not take over related duties.   (ii)  Durability of  PFM Reforms:  The Government, while  generally  dedicated  to making  improvements,  has taken unilateral action to reverse or restrain progress in the legal framework. Donor coordination around the ARTF Incentive Program and consultations on the PFM Roadmap have led to firm commitments to maintain and improve the legal framework.  (iii)    Limited Automation of PFM Processes:  The prevailing  systems  to  support  service delivery were  largely manual, and lacked some basic functions. The project supported the development of the related service delivery administrative processes.   (iv)   Corruption  Risk:  The  country  environment  carries  high  risk  to  perceived  corruption.  Strengthening  of procurement and audit of Public Accounts Committee should reduce this risk.   (v)  Internal  Audit:  Management  oversight  is  constrained  by  lack  of  effectively  operating  internal  audit function, except in the MOF. Building internal audit capacity cannot be done in the short term so implementing the approach  provided  in  the  Public  Expenditure  and  Finance  Law which  entrusts MOF  to  establish  internal  audit throughout the government would be the most effective and expeditious route to establish the function across government, while at the same time supporting the development of  internal audit  in the  line ministries, where feasible.   (vi)  External Audit: The external accountability of the executive must be strengthened. Many achievements in PFM are discounted because there is little independent oversight or assurance that the reports and decisions of the executive deserve credibility, particularly given the perception of  rising corruption. A new  legal  framework, training for members of a public accounts committee and training and technical support to the CAO are needed.   (vii)  Accounting Profession: There is a limited accounting and audit profession in Afghanistan due to an acute shortage of qualified professionals. There  is no  recognized body  that  represents or promotes  the profession  in Afghanistan,  nor  regulation  of  the  profession.  Accounting  and  auditing  services  are  provided  by  expatriate accountants,  without  any  oversight.  Support  is  needed  to  develop  the  capacity  of  accounting  and  auditing  in Afghanistan and establish a sustainable structure of effective regulation and oversight of the profession.  

     74. Risks and Risk Mitigation Measures: During project preparation, the Bank’s task team identified key risks and adopted appropriate mitigation measures. The overall risk rating for implementation was considered high. Based on the experience of the then ongoing IDA projects in Afghanistan, major challenges the project could face were related to the capacity and coordination within the government and among donors, as well as delays in procurement  or  mis‐procurement.  The  deteriorating  security  could  also  slow  down  implementation  and discourage contractors from bidding, and agencies may not be able to source high  level TA on a timely basis and/or at reasonable cost. The project oversight and adequate Bank supervision helped address the issues that 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 23 of 68

    arose  and  specific  steps,  including  long  lead‐times  and  engagement  of  specialist  support  for  procurement addressed potential delays were considered. The project was designed to specifically address capacity issues in accounting, auditing in general and PFM specifically. 

     75. Adequacy of government commitment: After decades of wars and civil strife, building an effective state ‐ one that could provide security and services to the people ‐ was at the heart of the reconstruction effort in Afghanistan. The government in this context made significant progress in establishing a functioning PFM system under the direction of MOF, which is the single most crucial enabling factor for the budget implementation. The legal framework underpinning PFM (Public Finance and Expenditure Management Law and Public Procurement Law)  was  established.  Through  a  series  of  IDA  grant  operations,  the  government  had  engaged  specialized international  firms  to provide direct operational  support  to  the Treasury of MOF,  the ARDS  for public  sector procurement management, and the CAO for carrying out external audits for all IDA and ARTF funded operations in Afghanistan. 

     B. KEY FACTORS DURING IMPLEMENTATION 

    Positive Factors 

    76. The government’s ownership of PFM reform program was noteworthy. Effective PFM remained of key importance to the government as it openly promoted the reform agenda, proclaiming this was the backbone of the country and that the government would support the agenda. Despite challenges of fragility, the government was successful in making significant progress in establishing a functioning PFM system under the direction of the MOF. In particularly, the support from the President of Afghanistan, as the head of the National Procurement Commission, was a major positive factor during implementation.   77. As a follow‐on project, the agencies involved in the implementation of each component had experience in implementing Bank projects and following Bank procedures.  78. The two task team leaders were based in Kabul, which enabled them to maintain regular contacts with the government and the stakeholders. This facilitated project implementation significantly.  

     Negative Factors 

     79. Delays were experienced in the procurement of goods and consultancy packages as the government was not able to prepare a timely and comprehensive procurement plan. Requests for procurement plan revisions were made  only  on  ad  hoc  basis  which  resulted  in  duplication  of  procurement  of  similar  items.  Had  these packages been combined, the benefit from the economy of scale could have been realized.  80. In the NPA, staff faced implementation challenges because of non‐familiarity with Bank’s procurement policies and procedures, which improved with time as the staff gained experience. Implementation was by close coordination between the Bank and the RIMU and hiring of competent and professional staff familiar with Bank’s procurement guidelines.   81. Because of the country’s unstable and volatile security concerns, field visits outside of Kabul were difficult or impossible. Similarly, because of fragile country environment, interest from foreign contractors for bidding contracts  remained  limited  which  resulted  in  the  Bank  adjusting  procurement  methodology  aligning  to  the 

  • The World Bank Public Financial Management Reform II (P120427)

    Page 24 of 68

    market realities during implementation.  82. Revenue mobilization was relatively a new component and experienced implementation delays because of  inadequate  coordination  between  MOF  and  ARD;  staff  turnover;  and  low  capacity  of  staff  in  handling procurement complexities. 

     IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME  A. QUALITY OF MONITORING AND EVALUATION (M&E) 

    M&E Design 

    83. M&E Design:  The project’s  Results  Framework was prepared  as  per  the Bank’s  guidelines.  The PDO indicators and targets were compatible with the government’s approach, donor inputs, and overall PFM reforms agenda. This approach ensured that M&E framework was grounded  in reality and ev