document control sheet - zitholele – zitholele websitezitholele.co.za/projects/12810 - wml for...
TRANSCRIPT
Zitholele Consulting
Reg. No. 2000/000392/07 PO Box 6002 Halfway House 1685, South Africa Building 1, Maxwell Office Park, Magwa Crescent West c/o Allandale Road & Maxwell Drive, Waterfall City, Midrand Tel + (27) 11 207 2060 Fax + (27) 86 674 6121 E-mail : [email protected]
Directors: S Pillay (Managing Director); N Rajasakran (Director); Dr AM Van Niekerk (Director)
DOCUMENT CONTROL SHEET
Project Title: Conceptual Engineering Design Report for the Continuous Ashing at Kendal Power Station
Project No: 12810
Document Ref. No: 12810-REP-ENG-001-Conceptual Design Report
DOCUMENT APPROVAL
ACTION FUNCTION NAME DATE SIGNATURE
Prepared Project Engineer N Rajasakran 25-08-2014
Reviewed Project Reviewer D Jansen van
Rensburg 25-08-2014
Approved Project Director S Pillay 25-08-2014
RECORD OF REVISIONS
Date Revision Author Comments
05-05-2014 0 N Rajasakran Concept Design Report Issued for Comments.
25-08-2014 1 J Heera Updated Concept Design Report Issued for Comments.
Zitholele Consulting
Reg. No. 2000/000392/07 PO Box 6002 Halfway House 1685, South Africa Building 1, Maxwell Office Park, Magwa Crescent West c/o Allandale Road & Maxwell Drive, Waterfall City, Midrand Tel + (27) 11 207 2060 Fax + (27) 86 674 6121 E-mail : [email protected]
Directors: S Pillay (Managing Director); N Rajasakran (Director); Dr AM Van Niekerk (Director)
REPORT ON
CONTINUOUS ASHING AT KENDAL POWER STATION
CONCEPTUAL ENGINEERING REPORT
Report No : 12810
Submitted to:
Eskom Holdings SOC Ltd
P O Box 1091 Johannesburg
2000
DISTRIBUTION:
2 Copies - Eskom Holdings SOC Ltd
1 Copy - Zitholele Consulting (Pty) Ltd – Library
05 September 2014 12810
05 September 2014 i 12810
ZITHOLELE CONSULTING
EXECUTIVE SUMMARY
Kendal power station was commissioned in the mid 1980’s, with a 40 year operating life. The initial
dry ash dump site was designed to have a capacity for the operating life with an eight year
contingency period. The life of the power station has since been upgraded to 60 years and with
some other contributing factors, such as the dry density and the load factor, the initial dry ash
dump is now under capacity. The power station is therefore expected to be decommissioned at
the end of 2053. This means that area to accommodate the additional ash generated during this
operational period will need to be extended. The area to the north of the existing facility will need
to be optimised in order to receive this ash. The Conceptual Engineering designs indicate that ash
may be accommodated here until early 2030 and thereafter an alternative site will need to be
licenced to receive ash up to the end of 2053. The supplementary site up to the end of 2053 is a
separate submission for Environmental Authorisation and is not addressed within this report.
Eskom has appointed Zitholele Consulting (Pty) Ltd (Zitholele) to start with the environmental
impact assessment (EIA) to extend the existing Kendal dry ash dump into the northerly direction.
Zitholele are also responsible for the conceptual engineering design for the options identified and
to recommend a preferred option. These engineering designs will be used to underpin and inform
the EIA.
The Conceptual Engineering Report discusses the following:
Continuation of the Ash Disposal Facility (ADF) with the extended footprint being lined in
compliance with DEA’s Norms and Standards as promulgated on 23 August 2013;
Design of pollution control dams and stormwater management infrastructure in compliance with
GN704
Diversion of a natural stream to accommodate the extended footprint of the ADF
Remedial works to an existing dam within Eskom’s property boundary but not part of their
water management system which addresses the mixing of flow from the final voids of the
adjacent mining operations.
Several options were considered for determining the go-forward option on the ADF and stormwater
management philosophy. The “piggyback” options described in both the determination of air space
on the ADF and stormwater management philosophy is not deemed feasible currently from a
mechanical perspective. This option was therefore not considered for implementation in this
report. Further investigation is currently underway here and will be reported on a separate project
that has been commissioned by Kendal Power Station.
Trade-off studies were conducted in order to determine the optimised go-forward scheme for the
continuation of the current Kendal Ash Dump and stormwater infrastructure. Environmental,
Technical and Financial aspects are considered in the trade-of studies when making the decision
on which option to proceed with to the next stage of design. Six options for the ADF layout and
nineteen options for the stormwater management philosophy were assessed. This was supported
by:
05 September 2014 ii 12810
ZITHOLELE CONSULTING
Conceptual airspace modelling of each alternative;
A daily time-step water balance model over a 50 year period for run-off determination and PCD
sizing, as well as sizing of clean and dirty water conveyances. From the trade-off study,
Scenario 2 option 3B was identified at the preferred option
Conceptual development of dump infrastructure including surface drainage structures,
hydraulic structures, leachate and sub-surface drainage, lining and cover materials;
Cost estimation;
Trade-off study workshop.
From the trade-off study held the preferred option is identified as Option 2A, which is to divert the northern stream to get the maximum dump volume on the current site;
Option 2A provides a ashing capacity of 98 Mm3 at a density of 0.85t/m3
This provides a remaining life of 15 years from January 2015 until December 2029;
The preferred option as selected through the trade-off study analysis is based on a preliminary design. All fundamental aspects were addressed to inform the EIA study.
It is recommended to progress with the preferred option through a feasibility study and detailed design phase.
The requirements that are raised as issues and concerns through the EIA and stakeholder engagement process should be addressed during the feasibility and detailed design phase and the impacts should be mitigated through engineering solutions.
Based on the trade-off study work, it can be stated that the proposed facility extension is a feasible solution.
Following the workshops, it was proposed that Option 2A, for the ADF layout of diverting the
northern stream with no Piggy Backing, and Scenario 2 Option 3B, for the stormwater
management philosophy, be taken to the next stage of design. Scenario 2 being the scenario with
an optimum open ash area of 82 hectares, and Option 3B being the option where Dam 1 & 5 are
considered dirty, Dam 2, 3 and 4 are considered clean, dust suppression is done from Dam 5 to open ash
areas, irrigation is done from Dam 4 to rehabbed areas and irrigation is done from the existing Clean Water
Dam to the power station terrace. A Waste Management Licence (WML) and Water Use Licence
(WUL) need to be applied for the infrastructure and activities as described in the aforementioned
options.
05 September 2014 iii 12810
ZITHOLELE CONSULTING
TABLE OF CONTENTS
SECTION PAGE
1 INTRODUCTION ................................................................................................ 1
2 BASIS OF DESIGN ............................................................................................ 2 2.1 Assumptions and limitations............................................................................. 2 2.2 Ash characteristics ........................................................................................... 2
2.2.1 Grading and Specific gravity .............................................................. 2 2.2.2 Stability .............................................................................................. 3 2.2.3 Permeability ....................................................................................... 3
2.3 Annual tonnages .............................................................................................. 3 2.4 Capacity requirements ..................................................................................... 4 2.5 Dust suppression ............................................................................................. 4 2.6 Stormwater Management ................................................................................. 4 2.7 Stream Diversion ............................................................................................. 5
3 ADF OPTIONS MODELLED .............................................................................. 6 3.1 Description of options ...................................................................................... 6
3.1.1 Option 1A: Minimum volume .............................................................. 6 3.1.2 Option 1B & 1C: Minimum volume with staged (1B) or concurrent
piggybacking (1C) .............................................................................. 7 3.1.3 Option 2A: Maximum volume ............................................................. 8 3.1.4 Option 2B & 2C: Maximum volume with staged (2B) or concurrent
piggybacking (2C) .............................................................................. 9 3.2 Trade-off study for ADF Preferred Option ...................................................... 10 3.3 Approach to the trade-off study ...................................................................... 10 3.4 Trade-off study .............................................................................................. 12 3.5 Results of the trade-off study ......................................................................... 13
4 ADF CONCEPTUAL DESIGN .......................................................................... 14 4.1 Ash disposal .................................................................................................. 14
4.1.1 Option 1A &2A: Minimum & Maximum volume deposition strategy .. 15 4.1.2 Option 1B & 2B: Staged piggyback deposition strategy .................... 15 4.1.3 Option 1C & 2C: Concurrent piggyback deposition strategy ............. 16
4.2 Liner system .................................................................................................. 16 4.2.1 Liner System Installation .................................................................. 17 4.2.2 Leachate collection system .............................................................. 17 4.2.3 Sub-soil drainage system ................................................................. 18
4.3 Capping system ............................................................................................. 19 4.4 E-Dump ......................................................................................................... 20
5 STORMWATER MANAGEMENT PHILOSOPHY ............................................ 21 5.1 OBJECTIVES ................................................................................................ 21 5.2 EXISTING STORMWATER MANAGEMENT SYSTEM .................................. 21
5.2.1 Power Station Terrace ..................................................................... 22 5.2.1.1 Impacted Areas ................................................................................ 23 5.2.1.2 Clean Areas ..................................................................................... 23 5.2.2 Cross over plant ............................................................................... 24 5.2.3 Silt Traps .......................................................................................... 24 5.2.4 Dirty Water Dam............................................................................... 24 5.2.5 Emergency Dirty Water Dam ............................................................ 25 5.2.6 Clean Water Diversion Berm and Channel ....................................... 26 5.2.7 Clean Water Dam............................................................................. 26 5.2.8 Coal Stockyard Attenuation Basin .................................................... 26 5.2.9 E-dump Stormwater Management .................................................... 27 5.2.10 Pumps and Pipelines ....................................................................... 27
5.3 OBJECTIVES OF PROPOSED STORMWATER MANAGEMENT SYSTEM . 27
05 September 2014 iv 12810
ZITHOLELE CONSULTING
5.4 MODELING APPROACH AND ASSUMPTIONS ............................................ 28 5.4.1 Rainfall data ..................................................................................... 28 5.4.2 Operating flows ................................................................................ 29 5.4.3 Description of catchment areas at ADF ............................................ 29 5.4.3.1 Open Ash Areas ............................................................................... 29 5.4.3.2 Rehabilitated Areas .......................................................................... 30 5.4.3.3 Transfer House F and Surrounding Areas ........................................ 30 5.4.3.4 Ash conveyor from E-dump .............................................................. 31 5.4.4 Stormwater runoff calculations ......................................................... 32
5.5 OPTIONS MODELLED .................................................................................. 34 5.6 MODELLING RESULTS ................................................................................ 35 5.7 TRADE-OFF ASSESSMENT ......................................................................... 36 5.8 PROPOSED INFRASTRUCTURE ................................................................. 39
5.8.1 Pollution Control Dams .................................................................... 39 5.8.2 Clean Water Dams ........................................................................... 41 5.8.3 Toe Paddocks .................................................................................. 44 5.8.4 Storage Reservoirs .......................................................................... 44 5.8.5 Conveyance infrastructure (pumps, pipelines and channels) ............ 44
5.9 1 IN 100 YEAR FLOODLINES ....................................................................... 45 5.9.1 Methodology .................................................................................... 45 5.9.2 Results ............................................................................................. 53
5.10 Suppression Abstraction Philosophy .............................................................. 58 5.11 Hydraulic Analysis ......................................................................................... 58
5.11.1 Sizing of “Clean” stormwater diversion drains and berms ................. 58 5.11.2 Sizing of “Dirty” stormwater conveyance drains ................................ 58
5.12 WATER BALANCE ........................................................................................ 60 5.13 OPERATIONAL REQUIREMENTS ................................................................ 60
5.13.1 Monitoring of Quality in Clean Water Dams ...................................... 61 5.13.2 Maintaining Open Ash Areas for Dust Suppression .......................... 61 5.13.3 Maintaining Silt Traps ....................................................................... 61
5.14 WAY FORWARD FOR STORMWATER MANAGEMENT .............................. 61 6 STREAM DIVERSION ...................................................................................... 62 7 PHASED APPROACH TO ADF ....................................................................... 63
7.1.1 Option 1A & 2A ................................................................................ 63 7.1.2 Option 1B & 2B ................................................................................ 63 7.1.3 Options 1C & 2C .............................................................................. 63
8 FARM DAM SYSTEM ....................................................................................... 64
9 OPERATION AND MAINTENANCE PLAN ...................................................... 66 9.1 Code requirements in terms of SABS 0286 .................................................... 66
10 DISCUSSION .................................................................................................... 67 11 RECOMMENDATION AND CONCLUSION ..................................................... 68
LIST OF FIGURES
Figure 1: Option 1A ............................................................................................................ 7
Figure 2: Option 1B & 1C ................................................................................................... 8
Figure 3: Option 2A ............................................................................................................ 9
Figure 4: Option 2B & 2C ................................................................................................. 10
Figure 5: Layout of conveyor system used to deposit ash ................................................ 14
05 September 2014 v 12810
ZITHOLELE CONSULTING
Figure 6: Typical Class C Landfill Barrier System............................................................. 17
Figure 7: Proposed Class C Barrier System ..................................................................... 17
Figure 8: Leachate collection system for Option 2A ......................................................... 18
Figure 9: Layout of the sub-soil drainage system ............................................................. 19
Figure 10: Section through rehabilitated ADF ................................................................... 19
Figure 11: Existing E-Dump ............................................................................................. 20
Figure 12: Current Stormwater System ............................................................................ 22
Figure 13 : Power Station Clean and Dirty Area Demarcation .......................................... 23
Figure 14: Concrete lined silt trap with adjustable overflow weir ....................................... 24
Figure 15: Dirty Water Dam with spillway in background .................................................. 25
Figure 16: Emergency Dirty Water Dam overflow channel ............................................... 26
Figure 17: Open Ash Area on ADF .................................................................................. 29
Figure 18: Rehabilitated Area on ADF .............................................................................. 30
Figure 19: Transfer House F ............................................................................................ 30
Figure 20: Stormwater Management at Transfer House F ................................................ 31
Figure 21: Maintenance at Low Point on Conveyor .......................................................... 31
Figure 22: Dirty Water Dam Levels for Simulation Period ................................................. 39
Figure 23: Emergency Dirty Water Dam Levels for Simulation Period .............................. 40
Figure 24: Proposed Dam 1 Levels for Simulation Period ................................................ 40
Figure 25: Proposed Dam 5 Levels for Simulation Period ................................................ 41
Figure 26: Existing Clean Water Dam Levels for Simulation Period ................................. 42
Figure 27: Proposed Dam 2 Levels for Simulation Period ................................................ 42
Figure 28: Proposed Dam 3 Levels for Simulation Period ................................................ 43
Figure 29: Proposed Dam 4 Levels for Simulation Period ................................................ 43
Figure 30: Positioning of Temporary Toe Paddocks ......................................................... 44
Figure 31: 1 in 100 Year Floodlines Pre- and Post-Development ..................................... 53
Figure 32: Resulting Longitudinal section of Three Dams Water Course .......................... 54
Figure 33: Cross Section of Diversion Channel ................................................................ 55
Figure 34 Resulting Longitudinal Section of Farm Dam Water Course, Pre-Development56
Figure 35: Resulting Longitudinal Section of Farm Dam Water Course, Post-Development57
Figure 36: Toe Line Drain ................................................................................................ 59
Figure 37: Outlet Drain ..................................................................................................... 59
05 September 2014 vi 12810
ZITHOLELE CONSULTING
Figure 38: Proposed Stream Diversion ............................................................................ 62
Figure 39: Proposed changes at Farm Dam System ........................................................ 65
LIST OF TABLES
Table 1: Ash grading .......................................................................................................... 3
Table 2: Weightings for the options analysis workshop .................................................... 11
Table 3: Trade-off Study Workshop Delegates and Designations .................................... 12
Table 4: Results from the Trade-off matrix ....................................................................... 13
Table 5: Recorded rainfall statistics ................................................................................. 28
Table 6: Operating flows used in time-step model ............................................................ 29
Table 7: Catchment areas ................................................................................................ 32
Table 8: C values calculated according to catchment characteristics ............................... 33
Table 9: C values obtained from adjustment factors ......................................................... 34
Table 10: Options modelled ............................................................................................. 34
Table 11: Modelling results .............................................................................................. 36
Table 12: Option Analysis Criteria and Weighting ............................................................ 37
Table 13: Results of Trade-off Study Workshop ............................................................... 38
Table 14: Sub-Catchment Surface Areas ......................................................................... 45
Table 15: Resulting Time of Concentration for the sub-catchments ................................. 47
Table 16: Resulting Storm Depths, Storm Durations and Rainfall Intensities .................... 47
Table 17: Run-off Coefficients with regard to Surface Slope Classifications ..................... 48
Table 18: Run-off coefficients with regard to Permeability ................................................ 48
Table 19: Run-off coefficient with regard to Vegetation .................................................... 48
Table 20: Adjustment Factors for c1 with regard to Return Period: .................................. 49
Table 21: Resulting c-values ............................................................................................ 49
Table 22: Results of Hydrology Calculations .................................................................... 50
Table 23: Output from the Three Dams Water Course Pre-Development Model .............. 51
Table 24: Output from the Farm Dam Pre-Development Model ........................................ 52
Table 25: "Dirty" Water Channels Concept Design Parameters ....................................... 60
05 September 2014 vii 12810
ZITHOLELE CONSULTING
LIST OF APPENDICES
Appendix A: Geotechnical Report
Appendix B: Waste Classification Report
Appendix C: Conceptual Engineering Drawings
Appendix D: Water Balance Diagram
Appendix E: Trade-off study matrix
Appendix F: Tech Memo Selection for barrier System
05 September 2014 1 12810
ZITHOLELE CONSULTING
1 INTRODUCTION
Kendal power station was commissioned in the mid 1980’s, with a 40 year operating life. The initial
dry ash dump site was designed to have a capacity for the operating life with an eight year
contingency period. The life of the power station has since been upgraded to 60 years and with
some other contributing factors, such as the dry density and the load factor, the initial dry ash
dump is now under capacity. The power station is therefore expected to be decommissioned at
the end of 2053. This means that area to accommodate the additional ash generated during this
operational period will need to be extended. The area to the north of the existing facility will need
to be optimised in order to receive this ash. The Conceptual Engineering designs indicate that ash
may be accommodated here until early 2030 and thereafter an alternative site will need to be
licenced to receive ash up to the end of 2053. The supplementary site up to the end of 2053 is a
separate submission for Environmental Authorisation and is not addressed within this report.
Eskom has appointed Zitholele Consulting (Pty) Ltd (Zitholele) to start with the environmental
impact assessment (EIA) to extend the existing Kendal dry ash dump into the northerly direction.
Zitholele are also responsible for the conceptual engineering design for the options identified and
to recommend a preferred option. These engineering designs will be used to underpin and inform
the EIA.
05 September 2014 2 12810
ZITHOLELE CONSULTING
2 BASIS OF DESIGN
2.1 Assumptions and limitations
The following assumptions were made in developing the conceptual designs presented herewith;
The requirements for the clean and dirty water systems stipulated in Regulation 704 and
Regulation 1560 of the National Water Act, 1998 will be adhered too;
The Pollution Control Dam (PCD) will be a Stormwater Dam; classified in terms of the National
Water Act, 1998 and will operate empty;
The life of the Power station was taken up to the year 2053 excluding final rehabilitation and
closure.
Ashing on an extended lined facility will start in July 2017; this timeline provides for
Authorisation, Further design, tender and construction project steps will be required to
commission the extended facility.
Conveyor system will move radially around existing pivot point and can extend to the required
dimension
The existing area of the ash facility that has been rehabilitated is seen as a final rehabilitation
and no other additional rehabilitation is needed except in the areas where the piggyback
options may be placed.
The Volume of ash per annum stays constant through the whole life of power station.
All volumes, remaining life and timelines are subject to the dump models that are produced.
2.2 Ash characteristics
2.2.1 Grading and Specific gravity
The fly ash varies from silty sand to silty clay using a triangular soil classification chart (US corps of
Engineers). The grading curve exhibits a uniform particle size distribution. According to ASTM
D422-63:
Clay sized particle is larger than 1 micrometre and smaller than 5 micrometre.
Silt sized particle is larger than 5 micrometre and smaller than 75 micrometre
Sand sized particle is larger than 75 micrometre and 425 micrometre
Thus using the above mentioned envelopes the grading of ash are as follows:
05 September 2014 3 12810
ZITHOLELE CONSULTING
Table 1: Ash grading
Particle size Weathered fly ash Median Fly ash
Clay-sized (%) 5-77 16 14
Silt sized (%) 23-83 60 59
Sand sized (%) 0-64 30 27
D50 (µm) 3-120 23 27.5
Specific Gravity (Gs) 2-2.2 2.2
Data used from : J.S. Mahlaba et al. Fuel 90 (2011)
2.2.2 Stability
The Stability of the final ash dump was not investigated in this phase as the already rehabilitated
slopes are at 1V:5H which has been assessed through an observational approach as stable
slopes. There is however a concern for the advancing ash face which is at angle of repose of
1V:1.2H. On the site visit held on 9 April 2013, some cracks have already formed close to the edge
of the ash disposal facility.
There are measures to mitigate the stability concerns of the ash face on the base liner; a textured
geomembrane can be used, this will increase the interface friction angle between the critical friction
interfaces. Other measures such as terracing the natural ground can also be considered. Further
investigations during the detailed design will have to be done to confirm the stability of the
advancing face when it is placed on the liner.
2.2.3 Permeability
The permeability is largely dependent on the density of the ash on the facility. A value of
11.5 m/year for medium dense ash was assumed. This is the mean of 3 m/y (dense ash) to
20 m/year (loose ash) (Brackley et al, 1987) (6.34*10-7 m/sec). This is required for calculating
seepage pool to the leachate collection system.
2.3 Annual tonnages
The indicated annual tonnage of ash placed on the ash disposal facility is 5500 kt/ annum. This
information is from a previous report (Report nr: 11613601-10981-2) in which Golder Associates
Africa did the development of an industry waste management plan for Eskom where all the waste
type and quantities of all the power stations were considered.
The density of the ash is 850kg/m3 and thus the annual airspace required for the continuous
ashing facility is approximately 6.5 Mm3/ annum. Based on this the remaining life for the continuous
ashing site is determined.
Refer to Eskom document number: 240-71273834 for coal quality used and Eskom Consistent
Data Set (CDS) – 36-623 for remaining life and coal burn plan utilised for coal consumption values.
05 September 2014 4 12810
ZITHOLELE CONSULTING
2.4 Capacity requirements
The existing ash disposal facility was commissioned in the 1980’s for a 40 year life span and an 8
year contingency period. The operating life of the ash disposal facility has since then been
increased to 60 years and with a number of other design and material changes the existing dump
geometry is grossly under capacity.
The total additional capacity required for the ash disposal facility is 291 Mm3 from January 2015
until December 2058. With the current boundary and operating machinery limitations this capacity
will not be reached on the current site. The remaining area between the western and northern
streams does not have sufficient capacity to allow a new facility to be established. If the northern
stream is diverted, the continuous ash dump will only provide 98 Mm3 capacity, requiring a new
“30”year ADF of 193 Mm3. There are current investigations to identify a suitable site for the
remaining ash to be deposited. The size and commissioning date of this new site is dependent on
the Continuous ADF site capacity.
2.5 Dust suppression
The current approach is to use water from the three dam system (Dirty Water Dam, Emergency
Dirty Water Dam and Clean Water Dam) that is located on the Eastern side of the site and then via
irrigation, spray the exposed ash areas to minimise the mobilisation of the ash. Key operational
staff members in Eskom, are of the opinion that the current system is not fulfilling its intended
purpose and that the system will have to be modified so that the ash mobilisation is minimal.
There are a number of techniques and products that can be used such as:
Using a dust suppression chemical
Using a self-propelled spraying system; using pressure to propel itself forward
Upgrading the current system with better controls in place
50mm subsoil cover
The above mentioned options will have to be investigated further in the following phase of design
as there might be a lot of other innovative approaches that can be followed.
2.6 Stormwater Management
The management philosophy for the routing and capturing of stormwater is summarised as follows:
The separation of the runoff draining south-easterly towards the extended ash disposal facility
(i.e. from the area upslope of the ash dump) and runoff generated from within the footprint of
the extended ash dump;
The diversion of “clean” surface runoff generated from the upslope contributing catchments
away from the extended ash disposal facility, thereby isolating the ash dam as “dirty areas” in
accordance with the requirements GN 704 in terms of the National Water Act, 1998;
05 September 2014 5 12810
ZITHOLELE CONSULTING
Containment of all “dirty” surface runoff generated from within the “dirty” catchment,
conveyance and discharge into a dedicated pollution control dam sized in accordance with the
requirements GN 704 in terms of the National Water Act, 1998.
The current and proposed stormwater management philosophy is discussed in depth in Section 1
of this report.
2.7 Stream Diversion
The current extent of the ash dump is bordered by one perennial stream to the east and one non-
perennial stream to the west. The stream to the East flows in a north-westerly direction whilst the
stream to the West flows northerly. The two (2) streams converge north of the existing ash dump.
Flood management philosophy is as follows;
Diversion of the stream forming the eastern border of the ash dump in a northerly direction.
The diversion channel will be sized to match the discharge capacity of the existing clean water
dam spillway upstream of the culvert system across the district road adjoining the R555 and R50
national roads, and the stormwater runoff to the east below the culverts. The stream diversion
design will be carried out in accordance with the provision of the water use licence.
05 September 2014 6 12810
ZITHOLELE CONSULTING
3 ADF OPTIONS MODELLED
The Kendal Power Station Continuous Ashing project had to ensure the continued operations of
the Power Station when considering the options for the extended ashing facility. Any option that
involved the temporary stoppage of production was considered fatally flawed. The advancing face
of the current ashing operations is in a northerly direction and options were considered for this area
only as it did not involve major configuration changes of the conveyors and stackers. The vacant
area to the south of the existing ADF between the rehabilitated area and the National Road R545
was considered as being fatally flawed with respect to aforementioned conditions and was not
considered further as a feasible option.
Two broad options, and the respective sub-options, were considered in determining the air space
required for the extended facility. The broad options are as follows:
Option 1 Minimum Dump – The ADF is positioned between the two streams as previously
described.
Option 2 Maximum Dump – The positioning of the ADF requires the northern stream to be
diverted.
The sub-options for the above includes for a piggybacking option which may be done concurrently
with the current operations or done once the existing footprint is exhausted at the prevailing levels.
3.1 Description of options
3.1.1 Option 1A: Minimum volume
The minimum volume option stays within the original footprint area and is lined from the set
timeline of early 2017 as shown in the figure below. Physical parameters of the options are:
Total Footprint Area: 480 ha
Remaining dump volume: 32.5 Mm3
Remaining life: 5 years from January 2015
Maximum height: 60 m
05 September 2014 7 12810
ZITHOLELE CONSULTING
Lined area: 114 ha
Figure 1: Option 1A
3.1.2 Option 1B & 1C: Minimum volume with staged (1B) or concurrent piggybacking
(1C)
These options are have the same footprint and piggyback area, the definitive difference is the way
in which they are constructed and the specific areas that were lined. The physical parameters of
these options are as follows:
Option 1B & 1C
Total Footprint Area: 480 ha
Remaining dump volume: 47 Mm3
Remaining life: 7 years from January 2015
Maximum height: 80 m
Only Option 1B
Lined area: 275 ha
The method of construction for this option is the footprint will first be totally completed before the
piggyback can be constructed the piggyback area will also be lined in this option.
Only Option 1C
Lined area: 114 ha
05 September 2014 8 12810
ZITHOLELE CONSULTING
The method of construction for this option is the footprint area and the piggyback area will be
constructed concurrently by moving the conveyors back into the required position and not lining the
piggyback area.
Figure 2: Option 1B & 1C
3.1.3 Option 2A: Maximum volume
The maximum volume option falls outside the existing footprint and entails that the north eastern
stream be diverted up against the slope. The physical parameters are:
Total Footprint Area: 583 ha
Remaining dump volume: 98 Mm3 from January 2015
Remaining life: 15 years from January 2015
Maximum height: 60 m
Lined area:224 ha
05 September 2014 9 12810
ZITHOLELE CONSULTING
Figure 3: Option 2A
3.1.4 Option 2B & 2C: Maximum volume with staged (2B) or concurrent piggybacking
(2C)
These options again have the same footprint and piggyback area as well as the stream
diversion.The most significant difference is the way in which they are constructed and the specific
areas that were lined. The physical parameters of these options are as follows:
Option 2B & 2C
Total Footprint Area: 583 ha
Remaining dump volume: 114 Mm3
Remaining life: 18 years from January 2015
Maximum height: 80 m
Only Option 2B
Lined area: 385 ha
The method of construction for this option is the footprint will first be totally completed before the
piggyback can be constructed the piggyback area will also be lined in this option.
05 September 2014 10 12810
ZITHOLELE CONSULTING
Only Option 2C
Lined area: 224 ha
The method of construction for this option is the footprint area and the piggyback area will be
constructed concurrently by moving the conveyors back into the required position and not lining the
piggyback area.
Figure 4: Option 2B & 2C
3.2 Trade-off study for ADF Preferred Option
The objective of the trade-off study is to select a preferred option from those considered (refer 3.1),
with which to go forward to subsequent development stages of the project. Selection of an
alternative does not render it inflexible to improvement opportunities, but instead provides a broad
engineering framework for the development of the ash disposal facility.
3.3 Approach to the trade-off study
Six possible alternatives for the deposition of ash were conceptualised for consideration in the
trade-off study (refer 3.1).
Three broad criteria were selected for analysis of the options, namely:
Environmental influences;
Engineering aspects;
Financial considerations.
05 September 2014 11 12810
ZITHOLELE CONSULTING
Each of these criteria was given a weighting in terms of perceived importance or influence on the
project. Each criterion was also subdivided into sub-categories which were deemed to be relevant
to the project. The table below shows the overall criteria and weighting matrix used for evaluating
and comparing the options:
Table 2: Weightings for the options analysis workshop
ENGINEERING ENVIRONMENTAL
CONSIDERATIONS
FINANCIAL
50% 30.0% 20%
Airspace won 15.0% Level of impact of the
footprint size
15.0% Lowest Cost in terms of R/m3
70%
Does the airspace
model provide
sufficient capacity to
reach the required
timeline of 2020
1.0% Impact on the 30 year
scheme
15.0% Least Total Capital Spent
30%
What is the
complexity of the
operations for the
Spreader and Stacker
20.0% Significance of
encroachment on
current land uses and
natural habitat (Zone
of Influence)
15.0%
What is the
complexity of the
phase construction
5.0% Influence of proximity
to water course
20.0%
Complexity of
disposal facility
geometry
12.0% Complexity of
disposal facility
geometry for closure
5.0%
What is the size and
complexity of the
leachate collection
system
5.0% Level of impact that
the proposed option
has on the ground
water system
20.0%
What is the
complexity of the
Stormwater
management system
on the dump
7.0% Visual impact
assessment of post
closure landform
5.0%
What is the
complexity of the
proposed Stormwater
management system
around the dump
5.0% Impact of exposed
ash body on air
quality
5.0%
05 September 2014 12 12810
ZITHOLELE CONSULTING
What is the impact on
the proposed height
10.0%
What is the impact of
the required capping
system
10.0%
Impact on slope
erosion and resulting
sediment transport
10.0%
A trade-off study workshop was conducted on 9 May 2013 with the following representatives
present:
Table 3: Trade-off Study Workshop Delegates and Designations
ESKOM ZITHOLELE GOLDER
ASSOCIATES
NUT AIRSHED
Andre Kreuiter N Rajasakran D Hattingh Mina Cilliers Dr. Terri Bird
Tobile Bokee Virginia
Ramakuwela
C McLuckie
Eddie Setei Mathys Vosloo Dieli Mesoabi
Warren Kok Gerhard Coetzer
Jan-Dirk Brak Johan Jordaan
Andre Zinn
Francois Marias
Eddie van Wyk
Danie Brink
Warren Aken
3.4 Trade-off study
All delegates present participated in critically discussing each criteria and subcategory. The result
is that the ranking and rating matrix was modified and agreed to by the meeting.
Following the above process, each cell in the matrix was populated by robust debate between all
representatives and disciplines present. Financial criteria were not discussed at the trade-off
workshop because the workshop was seen as a qualitative workshop in where only the technical
feasibility and the environmental impacts were evaluated.
Financial comparison was conducted by analysing capital and closure costs associated with each
option and calculating the cost-benefit in terms of a rate – Rands paid per m3 airspace won or
R/m3. The total costs and the cost benefit rates were shown in the trade-off matrix and rated
accordingly. Costs were determined by measurements from the CADD models and using rates
obtained from previous work done on similar projects.
05 September 2014 13 12810
ZITHOLELE CONSULTING
3.5 Results of the trade-off study
The trade-off study matrix is shown in Appendix E. The results are shown in the table below:
Table 4: Results from the Trade-off matrix
OPTION DESCRIPTION ENVIRONMENTAL ENGINEERING FINANCIAL TOTAL
Weighting
30.0% 50% 20% 100.0%
Option 1A Minimum dump 3.6 Fatally Flawed 0 FF
Option 1B Minimum dump and lined piggybacking (staged piggybacking)
3.25 2.23 1.3 2.35
Option 1C Minimum dump no lined piggyback concurrent piggybacking
2.9 2.61 4.3 3.04
Option 2A Maximum dump 1.75 3.85 4 3.25
Option 2B Maximum dump and lined piggybacking (staged piggybacking)
1.65 2.23 1.7 1.95
Option 2C Maximum dump no lined piggyback concurrent piggybacking
1.5 2.71 4.7 2.75
Option 1A is the preferred option for the environmental influences criteria; this result is a defensible
outcome, as this option has the smallest influence on the surrounding environment. Option 1A is
deemed fatally flawed in the engineering aspects criterion as it does not meet the timeline required.
Option 2A is the preferred option from an engineering perspective. The financial consideration was
based on the principal of the best return on investment; option 2C is the preferred option in this
case.
Taking all these considerations into account and looking at the criteria as a whole, Option 2A is the
preferred option and is recommended to be taken forward to the next phase of design.
05 September 2014 14 12810
ZITHOLELE CONSULTING
4 ADF CONCEPTUAL DESIGN
4.1 Ash disposal
The ash is deposited onto the ash disposal facility by means of a conveyor system. The transfer
conveyors moves the ash from the power station to transfer house E, the emergency ash dump (E-
dump) is located just to the north of the transfer house and was initially designed to provide a
capacity of five days of ashing for emergencies such as maintenance to the overland conveyors
etc.
From transfer house E the ash is transported via the overland conveyors which cross a provincial
road and the north eastern stream to transfer house F. The extendable conveyors transfer the ash
from transfer house F to the shiftable conveyors. The extendable conveyors were initially designed
to extend in the direction of its current bearing as soon as the shiftable conveyors are
perpendicular to the extendable conveyors this method of deposition is called parallel shifting, but
this deposition strategy cannot be implemented due to the new boundary extents of the existing
area.
The shiftable conveyors are the stacker shiftable conveyor (Primary system) and the spreader
shiftable conveyor (Standby system). This is used to deposit the ash onto the ash disposal facility.
The current deposition strategy is to place ash only via radial shifting. In the figure below the layout
and naming for the conveyor system is shown.
Figure 5: Layout of conveyor system used to deposit ash
There are some limitations to these shiftable conveyor systems as the ash is only placed radially.
Some of the limitations are:
The maximum gradient the system can traverse is 1V:20H
As the conveyor cannot bend the advancing face as well as the final face position cannot have any kinks or bends as this meant that the conveyor had a bend in place
The maximum height the of the spreader system is approximately 45m and 62m for the stacker system
05 September 2014 15 12810
ZITHOLELE CONSULTING
The spreader system can only place a front stack where the stacker system can place a front stack and back stack.
Shift intervals needs to be kept to a minimum, between 4-6 months per shift.
The estimated time it would take to get all the authorisation in place as well as providing detailed
designs, tender and construction would take up to September 2015, During this time the ash facility
still needs to continually ash and thus there is still a certain amount of ashing that will take place
while the authorisation is being considered on virgin ground which would then be impractical to line
the area. Refer to drawings 13615205-100-D-D100 and D102 for Options 1A,B and C and
13615205-100-D-D101 and D103 for options 2A,B and C for the section that will be lined.
The deposition strategies are explained in the sections below, the same philosophy was followed
for the various maximum and minimum options numbered A, B and C thus where the deposition
strategy explanations were combined
4.1.1 Option 1A &2A: Minimum & Maximum volume deposition strategy
The Minimum & Maximum volume options will be constructed in the same manner as currently
used. The ash is deposited radially while the stacker and spreader systems are pivoting around its
own fixed point on the extendable conveyors. The split that is designed for is 80:20 split which
means the stacker system is depositing 80% of the ash and the spreader only 20%.
This is currently not the case as the split is closer to 60:40 resulting in the front spreader system
running away from the stacker system. This is a major problem as this means that the backup
system will run its route a lot faster than anticipated with the result that the backup system will
become redundant because there is no designated area left to ash. This would have to be taken
into account in the following phases of design.
4.1.2 Option 1B & 2B: Staged piggyback deposition strategy
These options have the same final footprint as either option 1A or 2A but with another lift
constructed on the already placed ash called a piggyback. The deposition strategy for these
options is to first construct the initial dump which is again either 1A or 2A as described in the
previous section and then move the conveyor system back to where the piggyback section will
start and only then start constructing the piggyback section. It was assumed that the piggyback
would also be lined in these options.
There are some major limitations to this deposition strategy. If the initial option is first constructed
with both the spreader and stacker, the spreader would be on a level approximately 14m lower
than that of the stacker level. This means that as the stacker is moved back to the piggyback
starting point and that the spreader has run its route there is no means of depositing ash except at
the E-dump, which has only five days of storage. This is not sufficient capacity of the required
operation.
The stacker face next to the spreader needs to be shaped to an acceptable gradient so to be able
to pull the stacker shiftable conveyors up the slope. While the spreader is moved into position no
05 September 2014 16 12810
ZITHOLELE CONSULTING
lining can be done as the spreader first needs to move across the area to be lined and ashing still
needs to take place, the spreader would have to be used and ash will be deposited on an unlined
area.
Once both the systems are in place the floor would have to be lined as that was the assumption for
these options. The lining of the piggyback area would have to happen concurrently with the
deposition as stopping the operations on the ash disposal facility is not an option. As the piggyback
liner is constructed the 300mm top soil cover layer placed on the initial option will become a
sacrificial layer as this topsoil is contaminated and other topsoil will be needed for the capping of
the system. These options are very complex and can be impractical to construct.
4.1.3 Option 1C & 2C: Concurrent piggyback deposition strategy
These options again have the same final footprint as either 1A and 2A and another lift the same as
described in the above section is constructed, the only differences are that the piggyback and initial
footprint will be constructed concurrently and that the piggyback area is not lined. It is impractical to
line the piggyback area if the initial footprint is not constructed first.
The stacker system will be moved back to the piggy back starting point while the spreader system
is used to deposit ash at its current position. When the stacker system is in place the spreader
system can be pulled back to the stacker shiftable conveyor position and extended to allow it to
place the full width of the initial frontstack.
Once both systems are in place ashing from both systems can be accommodated. Thus the
spreader will then deposit ash from the initial stacker position with the stacker system placing a
front stack and a back stack on the ash placed by the stacker.
This is a much easier deposition strategy and is fairly straight forward compared to the staged
piggyback strategy.
4.2 Liner system
A waste classification was carried out on the ash and it was classified as a Type 3 waste – low
hazard waste (Report no: JW030/13/D121-Rev3) which requires disposal on a landfill with a Class
C barrier system. A Class C barrier system entails the use of clay or a feasible alternative. Tests
were done on a Geosynthetic Clay Liner (GCL) to determine whether the GCL is compromised due
to cation exchange. The test proved inconclusive on the short term but was recommended not to
be used without doing long term testing. Due to time constraints, a Benonite Enriched Soil (BES)
is proposed as an alternative. Tests were done on similar projects and proved successful. Testing
is currently underway using in-situ soils from the ADF footprint.
05 September 2014 17 12810
ZITHOLELE CONSULTING
Figure 6: Typical Class C Landfill Barrier System
Figure 7: Proposed Class C Barrier System
4.2.1 Liner System Installation
The construction timeline allowed for is twelve months; this includes the earthworks and liner
installation and will start approximately in July 2015 depending on the Environmental Authorisation
for the construction works. The liner system would be constructed with best practice in relation to
manufacturing, transport, storage and installation. The liner system will be installed according to
the manufacturer’s specifications where applicable.
4.2.2 Leachate collection system
As discussed in the liner system (section 4.2) the leachate collection layer is substituted with a
finger drain system. The finger drain system consists of perforated HDPE pipes110mm or 160mm
in diameter placed in 19mm washed stone and wrapped in a geotextile.
Filter sand Washed river sand
6mm Stone 19mm
Stone Leachate collection
drain Protection
geotextile
1.5mm Double
texture
geomembrane
*Clay layers
100mm Filter sand Excavatio
n line 19mm
Stone
Washed river
sand
6mm Stone
Filter sand Subsoil drain
Separation geotextile
05 September 2014 18 12810
ZITHOLELE CONSULTING
The expected horizontal spacing of the drains is 20m. It is best practice to keep the pipes to a
reasonable length. This helps to avoid the severity of blockages if they occur. The finger drain
system has a herringbone layout and daylights into the dirty water drains on either side of the
footprint where it reports in the pollution control dam.
In Option 2A, B and C the leachate collection system of Cell 1 is constructed by having the
collector drains discharge into the dirty water channel every 400 metres. With Cell 2 the existing
stream bed is used as a drain and then has only two discharge points that daylight into the
channel. In the figure below the leachate collection system of Option 2A is shown:
Figure 8: Leachate collection system for Option 2A
4.2.3 Sub-soil drainage system
The subsoil drainage system is installed to prevent hydrostatic pressures on the liner system and
to convey clean ground water away from the site. The subsoil drain consists of a110mm or 160mm
perforated pipe enclosed in 19mm washed stone. The drains are at 20m horizontal spacing.
In Option 2A, B and C the subsoil drains are placed in a parallel layout for Cell 1, collecting the
perched ground water and conveyed to the outer perimeter of the access road outside the dirty
water footprint. Cell 2 has the same pipe system layout as the leachate collection; a main pipe is
placed in the existing river bed and feeder drains are connected to form the herringbone layout.
This option has only one outlet and special care needs to be taken to prevent blockages from
occurring. In the figure below the layout of Option 2A is given:
05 September 2014 19 12810
ZITHOLELE CONSULTING
Figure 9: Layout of the sub-soil drainage system
4.3 Capping system
It is proposed that the current system of topsoiling and grassing be continued on the continuous
ashing site.
Figure 10: Section through rehabilitated ADF
Waste body
Soil saver
300mm Topsoil
Grass/hydroseed
Soil saver
05 September 2014 20 12810
ZITHOLELE CONSULTING
4.4 E-Dump
The Emergency Dump or commonly known as E- Dump” is located between the Power Station and
the existing ash dump, on the Power Station terrace. The facility operates as an emergency
storage of ash if the spreaders or stacker at the dump is inoperable. Once the equipment is
operable, the ash is loaded onto the conveyor reporting to the ADF. Currently, this area is cleared
by means of trucking the ash to the ADF, which will be the emergency method of removal of the
ash in the event that the onloading conveyor is not available, in order to clear the emergency dump
area as quick as possible.
The current area comprises of a reinforced concrete surface bed with an area of approximately
5,500m². The facility includes for a silt-trap and stormwater impoundment facility, approximately
1,000m³ in capacity. The surface bed is currently unbunded. Currently less than 2 days ash
production may be accommodated on the surface bed.
It is proposed to increase the storage capacity of E-dump to accommodate 7 days ash production.
The total footprint area of the surface bed will increase to 31,141 m² and will accommodate a total
volume of 190,000 m3. The area will be bunded within a 1 metre high reinforce concrete wall. The
existing stormwater impoundment dam will not be upgraded. Water from the impoundment facility
will be used in that area for washwater and dust suppression Excess water from this area will
gravitate to the Dirty Water Dam.
The surface bed will be cast in 25 m2 panels, with expansion joints in between the panels. The
expansion joints will comprise of an expandable polypropylene filler and will be sealed off at the
surface with a two component polyurethane sealant. This will render the joint water tight. The
surface beds will be cast with a floor slope of 1 in 200 to facilitate the drainage of stormwater off
the beds.
It is proposed to use fibre reinforced concrete due to the ease of construction. The strength and
durability of the concrete and its functionality will not be compromised by this choice of material.
An access road around the facility will facilitate the removal of ash.
Figure 11: Existing E-Dump
Convey
or to
ADF
Conveyor from
Station
Silt traps
PCD
Emergency ash dump
05 September 2014 21 12810
ZITHOLELE CONSULTING
5 STORMWATER MANAGEMENT PHILOSOPHY
Eskom is busy applying for an Environmental Authorisation to continue disposing of dry ash on
their existing facility located at Kendal Power Station. Conceptual engineering is undertaken at this
stage to underpin the Environmental Assessments. The following structures have been
conceptualised at this stage:
Continuation of ashing on the existing ashing facilities;
Pollution control dam(s) and canals to contain the dirty water runoff;
Stream diversions to facilitate the construction of the continuous ashing facility footprint.
The pollution control dams as indicated above will need to be designed in compliance with
Government Notice 704. More specifically, Clause 6 (d) of the regulation indicates that:
Design, construct, maintain and operate any dirty water system at the mine or activity so that it is
not likely to spill into any clean water system more than once in 50 years.
In order to achieve the above, a continuous model needs to be set-up to simulate the duration as
mentioned in the regulation in order to determine the performance of the proposed stormwater
impoundment infrastructure under normal operating conditions. Following the finalisation of the
model, the water balance may be derived for the facility once all proposed stormwater
infrastructure has been determined.
5.1 OBJECTIVES
In order to understand the stormwater management system and the relevance of each of the
proposed impoundment and conveyance structures, an integrated water balance needs to be
consulted.
This also informs the design of any facility that needs to comply with Government Notice 704.
Kendal Power Station does not have an integrated water balance therefore a conceptual water
balance is being proposed here for the stormwater management system.
5.2 EXISTING STORMWATER MANAGEMENT SYSTEM
Clean water and impacted water are separated within the power station terrace and handled
separately. The clean water reports to the Clean Water Dam and the impacted water reports to the
Dirty Water Dam via a water Crossover Plant and Silt Trap. Surface runoff within the catchment
draining naturally to the above Dirty Water Dams are diverted around it to the Clean Water Dam by
means of a berm, located to the north of the dams, and conveyed via a concrete channel located to
the south of the dams.
The Farm Dam, located to the west of the existing ashing facility, does not form part of Kendal
Power Station’s water balance and is therefore not included in this report.
05 September 2014 22 12810
ZITHOLELE CONSULTING
The current stormwater management is summarised in Figure 12 below and is described in detail thereafter.
Figure 12: Current Stormwater System
The Layout of the current infrastructure is shown on Figure 2.
5.2.1 Power Station Terrace
The power station terrace is predominantly considered to be clean with most of the impacted water
coming from the process drains. Figure 2 below gives an overview of the clean and impacted areas
demarcation on the power station terrace.
05 September 2014 23 12810
ZITHOLELE CONSULTING
Figure 13 : Power Station Clean and Dirty Area Demarcation
5.2.1.1 Impacted Areas
The impacted area within the power station terrace is located centrally, in the vicinity of the Boiler
and Turbine houses. An underground dirty water pipe system, located centrally within the plant,
conveys dirty wash water and some runoff to the cross-over plant, where the water is treated, the
sludge removed and then the treated water is conveyed to the dirty water dam.
The Coal Stockyard is also classified as an impacted area. Concrete channels constructed along
the boundary of the coal stock yard discharge storm water into an existing settling and attenuation
basin located at the coal stockyard. At the settling basin the solids settle out of suspension and the
liquid is then conveyed via a pipe to the Dirty Water Dam.
Stormwater runoff from the emergency dump is contained locally within a pollution control facility.
5.2.1.2 Clean Areas
Clean surface water runoff from the power station terrace is collected in an underground clean
water pipe system, located centrally within the plant, conveying clean storm water runoff to the
cross-over plant then to the Clean Water Dam. Clean storm water runoff that is not collected in the
central underground clean water pipe system is collected in concrete channels constructed along
the boundary of the plant. On the southern side of the plant the water collected in the channels is
discharged and is collected in the Clean Water Dam and on the northern side of the plant the clean
water is discharged into the surrounding veld area.
Clean Veld Discharge
Clean Area to Clean Water Dam
Dirty Area to Dirty Water Dam
05 September 2014 24 12810
ZITHOLELE CONSULTING
Clean Stormwater runoff from the surrounding veld area on the southern side of the plant is caught
by an existing earth berm which directs the storm water runoff to a canal that conveys the water to
the clean water dam. This berm is not currently effective as it has been eroded over time and also
removed in areas for access.
5.2.2 Cross over plant
No information was available for the design capacity of this facility as well as the process flow. All
information contained within the attached Water balance is assumed based on the diameter of the
clarifiers. Percentage of sludge produced was assumed as approximately 2%.
5.2.3 Silt Traps
Before discharging into the Dirty Water Dam, silt is first settled out at the silt trap located in close
proximity to the dam. The silt trap is divided into two compartments to facilitate maintenance.
Each compartment is concrete lined. An adjustable weir controls the outflow from each
compartment to the Dirty Water Dam which is assumed to be designed to attenuate the outflow to
settle out the solids.
Figure 14: Concrete lined silt trap with adjustable overflow weir
No information was provided for this facility. Assumptions on functionality were based on the
footprint area of it.
5.2.4 Dirty Water Dam
The Dirty Water Dam is a licenced facility (DWA Licence No: 04/B20E/BCEG/1048) with an annual
waste throughput of 1,095 Mℓ. The approved size of the facility is not given in the licence.
According to the latest (June 2013) hydrographic survey conducted by Kendal Power Station, the
capacity of this dam was found to be 226,900 m3.
05 September 2014 25 12810
ZITHOLELE CONSULTING
Impacted water is conveyed to the facility at an average rate of 35 ℓ/s via a 1500 mm diameter
concrete pipeline. The current licence for this facility does not require it to be lined. In-situ
weathered granite and felsite underlays the site and acts as a natural barrier.
The dam has an earth wall with a concrete weir spillway which overflows into the Emergency Dirty
Water Dam. A filter drain is located within the dam wall. Upstream and downstream faces of the
dam wall, constructed at slopes of 1:2.5 (v:h), are lined with rip-rap for erosion protection against
wave action. The base of the dam wall is keyed into the in-situ stiff residual material to prevent
against sliding.
Figure 15: Dirty Water Dam with spillway in background
5.2.5 Emergency Dirty Water Dam
The Emergency Dirty Water Dam is a licenced facility to receive a maximum of 55 Mℓ of impacted
water (duration not specified in the Water Use Licence) as an overflow from the Dirty Water Dam
when the Dirty Water Dam is full. The approved size of the facility is not given in the licence.
According to the latest (June 2013) hydrographic survey conducted by Kendal Power Station, the
capacity of this dam was found to be 83,242 m3.
Design and construction of the dam wall is as per the Dirty Water Dam. However, the overflow
spillway is a trapezoidal channel approximately 20 metres wide, lined with reno-mattresses. The
spillway discharges to the Clean Water Dam.
05 September 2014 26 12810
ZITHOLELE CONSULTING
Figure 16: Emergency Dirty Water Dam overflow channel
5.2.6 Clean Water Diversion Berm and Channel
An earth berm was designed to divert clean stormwater run-off around the dirty water dams and
discharge it to a concrete lined channel which discharges to the Clean Water Dam. However, only
remnants of this berm remain due to erosion and removal to open vehicular accesses.
The concrete lined stream diversion trapezoidal channel, approximately 23 metres wide at the top,
discharges to the Clean Water Dam. In order to prevent erosion at the discharge point to the
Clean Water Dam, a still basin was constructed at the discharged end. This drains to the dam via
a reno-mattress lined chute.
5.2.7 Clean Water Dam
The Clean Water Dam is a licenced facility and is contained within the same licence as referenced
previously. Design and construction of the dam is the same as the Dirty Water and Emergency
Dirty Water Dams. It is licenced to have a storage capacity of 90 Mℓ. According to the latest (June
2013) hydrographic survey conducted by Kendal Power Station, the capacity of this dam was
found to be 87,262 m3. A concrete overflow spillway discharges to the natural watercourse.
5.2.8 Coal Stockyard Attenuation Basin
The coal stockyard is located to the south east of the power station terrace and covers an area of
approximately 48 hectares. This area comprises of the following infrastructure:
Coal stockpile
Concrete lined channels intercepting stormwater run-off and discharging it to the settling basin
Settling and attenuation basin with a combined capacity of 10 Mℓ
05 September 2014 27 12810
ZITHOLELE CONSULTING
The surface runoff is conveyed via concrete lined open drains located to the west of the coal
stockyard. Two sets of drains, one running in a southern direction and the other northerly, drain to
an attenuation dam located centrally to the western boundary of the site.
Upstream of the attenuation basin is a settling basin. The settling basin is concrete lined and
facilitates the settlement of solids mobilised from the coal during the storm event. The combined
structure is not sized in compliance with the requirements of GN 704 and excess flow reports to the
Dirty Water Dam via a 1.2 metre diameter concrete pipe.
Mixing of water in the settling basin and attenuation basin is allowed in the current design. This will
need to be modified. Excess flow exits the facility via the settling basin. It is proposed that the
excess flow exits the facility via the attenuation basin.
5.2.9 E-dump Stormwater Management
“E- Dump” is located between the Power Station and the existing ash dump, on the Power Station
terrace. The facility operates as an emergency storage of ash if the spreaders or stacker at the
dump is inoperable. The current area comprises of a reinforced concrete surface bed with an area
of approximately 5,500m². The facility includes for a silt-trap and stormwater impoundment facility,
approximately 1,000m³ in capacity. The impoundment facility has not been designed to comply
with GN704 and will need to be addressed when the area is expanded.
5.2.10 Pumps and Pipelines
The pumps serving the Dirty Water Dam, Emergency Dam and Clean Water Dam are located
downstream of the Clean Water Dam. These pumps deliver water to the ash dump, for dust
suppression, and to the power station for wash water and ash conditioning. Ten (10) pumpsets are
provided for this of which four (4) are dedicated to the ash dump and the remainder to wash water
at the power station terrace. The combined flow to the ash dump is 60 ℓ/s on average and 80 ℓ/s
on average to the power station terrace.
Two dedicated sets of steel pipelines leave the pump station, a 150mm diameter in a westerly
direction to the ash dump and a 350mm diameter in a north-easterly direction to the power station
terrace. Currently, the latter pipeline is in the process of being replaced. Both pipelines, painted in
conspicuous colours as per the conditions of the WUL, are located above ground and fixed onto
concrete plinths.
5.3 OBJECTIVES OF PROPOSED STORMWATER MANAGEMENT SYSTEM
The new system will need to manage the stormwater run-off from the Ash Disposal Facility (ADF)
as well as manage the impacts that this has on the existing three dam system. All dams proposed
on this system will need to be in compliance with GN704. This will entail the following:
Confine any unpolluted water to a clean water system, away from any dirty area;
05 September 2014 28 12810
ZITHOLELE CONSULTING
Design, construct, maintain and operate any clean water system so that it is unlikely to spill into
any dirty water system more than once in 50 years;
Collect the water arising within any dirty area, including seepage;
Design, construct and maintain all stormwater systems in such a manner as to guarantee the
serviceability of such conveyances for flows up to and including those arising as a result of the
maximum flood with and average period of recurrence on once in 50 years;
Design, construct, maintain and operate any dirty water system so that it is unlikely to spill into
any clean water system more than once in 50 years.
In order to determine the optimum solution for stormwater management around the extended ADF
to meet the above objectives, various possible options will need to be considered. These options
are modelled and trade-off against each other in order to find the “go-forward” option.
5.4 MODELING APPROACH AND ASSUMPTIONS
A fifty (50) year daily time-step model was built using Microsoft Excel for the different scenarios
and options as described in the subsequent sections of this report.
5.4.1 Rainfall data
The model takes into consideration daily recorded rainfall closest to the site under investigation.
An uninterrupted data set could not be found for Kendal so the one for Cologne in Mpumalanga
(Station No. 0478008_W) was used to make-up the required rainfall data. Cologne is located
approximately six (6) kilometres south-east of Kendal PS. Data for the period May 1963 to August
2000 was used from Cologne. Recorded data for Kendal PS was used for the period September
2000 to May 2013. The combined data set represents fifty (50) years of recorded rainfall.
The table below gives the statistics of the data set used.
Table 5: Recorded rainfall statistics
Recurrence Interval
(1 in)
1 Day Rainfall
Depth (Cologne)
1 Day Rainfall
Depth Range (mm)
No. of Occurrences
in Data Set
2 54 50 - 65 24
5 74 66 – 85 16
10 90 86 – 100 4
20 106 101 – 124 1
50 131* 125 - 135 1
* A rainfall value of 106mm was changed to 131mm to simulate the 50 year 24 hour rainfall depth
05 September 2014 29 12810
ZITHOLELE CONSULTING
5.4.2 Operating flows
Table 6: Operating flows used in time-step model
Use Quality Description Ml/a m3/d
Process Waste Dirty Power station to
dirty water dam
4350 11918
Process Waste Clean Power station to
clean water dam
88 241
Washwater Dirty Dirty Water Dam to
SSC + Washwater
1570 4301
Ash Conditioning Dirty Dirty Water Dam to
Ash Conditioning
630 1726
5.4.3 Description of catchment areas at ADF
The connectivity of the catchment areas and the dams that they drain to are captured in the layout
drawings attached to the appendices. Brief descriptions are given below for each of the catchment
areas envisaged in the model.
5.4.3.1 Open Ash Areas
The open ash area is the most sensitive variable in the model. It was for this reason that different
Scenarios for this area were modelled. For all Scenarios, the open ash area is the area between
the toe of the standby stacker up to the crest of the main stacker. This run-off goes to the
proposed Dam 1.
Figure 17: Open Ash Area on ADF
OPEN ASH AREA
05 September 2014 30 12810
ZITHOLELE CONSULTING
5.4.3.2 Rehabilitated Areas
The rehabilitated area is the top-soiled and grassed area which is behind the crest of the main
stacker. This run-off goes to Dams 2, 3 and 4.
Figure 18: Rehabilitated Area on ADF
5.4.3.3 Transfer House F and Surrounding Areas
The slab that the extendable conveyor is fixed to, from Transfer House F to the dump, is washed
on a daily basis. This water drains to two unlined earth dams located adjacent to Transfer House F
at the base of the embankment. This run-off is proposed to drain to Dam 5 in future which will be
located at a lower elevation on the existing stream. This stream is proposed to be diverted.
A portion of the rehabilitated area also drains to this area and mixes with the impacted run-off. It is
recommended to construct a diversion channel alongside the road at Transfer House F and divert
this clean run-off to Dam 4.
Figure 19: Transfer House F
REHABILITATED AREA
05 September 2014 31 12810
ZITHOLELE CONSULTING
Figure 20: Stormwater Management at Transfer House F
5.4.3.4 Ash conveyor from E-dump
The conveyor route between E-dump and Transfer House F has its lowest point as it crosses the
national road. During abnormal conditioning of the ash, a slurry forms and drains to this point. It is
recommended that this area be concrete lined and a “V” drain be constructed from this point to
Dam 5, downstream of this point, to facilitate washing.
Figure 21: Maintenance at Low Point on Conveyor
DAMS HANDLING RUN-OFF
FROM TRANSFER HOUSE F
PROPOSED POSITION
OF CLEAN DAM 4 PROPOSED CUT-OFF DRAIN TO CHANNEL CLEAN
RUN-OFF AWAY FROM TRANSFER HOUSE F
TRANSFER HOUSE F
TRANSFER HOUSE F
E-DUMP
LOW POINT ON CONVEYOR AT
NATIONAL ROAD CROSSING
PROPOSED POSITION
OF DIRTY DAM 5 PROPOSED CHANNEL TO
FACILITATE CLEANING
AT CONVEYOR LOW
POINT
05 September 2014 32 12810
ZITHOLELE CONSULTING
5.4.4 Stormwater runoff calculations
The steps for calculation of stormwater runoff volumes for areas and dams are given below.
Step 1: Catchment areas are calculated for each area and dam.
Table 7: Catchment areas
Catchment Hectares
Power Station Clean Area 75.5
Power Station Dirty Area 1.1
Coal Stockyard 48
Dirty Water Dam 15
Emergency Dirty Water Dam
5
Clean Water Dam 330
Dam 3 114
Dam 2 328
Dam 4 47
Dam 1 82
Dam 5 11
Step 2: The Run-off coefficient (C) for each catchment area is calculated. The c-values are
calculated as per the SANRAL Drainage Manual. Table 3.7 in the manual provides a description of
recommended values of C.
The recommended values are selected according to 3 characteristics of the catchment under
consideration. They are namely:-
a) Surface slope classification
b) Permeability classification
c) Vegetation classification
A C-value for each characteristic is selected and the sum of which is the overall C-value, known as
C1, for a particular catchment. C1 is then multiplied by adjustment factors for each return period, i.e.
2, 5, 10, 20, 50, 100 years. The return period for each storm event was determined using the
rainfall depth and comparing it against the one day depth as contained in Table 5. Table 3.8 in the
aforementioned Manual provides adjustment factors for the value of C1.
05 September 2014 33 12810
ZITHOLELE CONSULTING
Table 8: C values calculated according to catchment characteristics
Catchment Area (m²)
Surface Slope Classification
Cs Permeability Classification
Cp Vegetation Classification
Cv C1
Power Station Clean Area
755 000 Flat Areas (3-10%)
0.08 Semi-permeable
0.16 Grasslands 0.21 0.45
Power Station Dirty Area
11 000 Flat Areas (3-10%)
0.08 Impermeable 0.26 No vegetation
0.28 0.62
Coal Stockyard
480 000 Hilly (10-30%)
0.16 Semi-permeable
0.16 No vegetation
0.28 0.6
Dirty Water Dam
150 000 Flat Areas (3-10%)
0.08 Permeable 0.08 Grasslands 0.21 0.37
Emergency Dirty Water Dam
50 000 Flat Areas (3-10%)
0.08 Permeable 0.08 Grasslands 0.21 0.37
Clean Water Dam
3 300 000
Flat Areas (3-10%)
0.08 Permeable 0.08 Grasslands 0.21 0.37
Dam 1 820 000 Flat Areas (3-10%)
0.08 Permeable 0.08 No vegetation
0.28 0.44
Dam 2 3 280 000
Flat Areas (3-10%)
0.08 Permeable 0.08 No vegetation
0.28 0.44
Dam 3 1 140 000
Flat Areas (3-10%)
0.08 Permeable 0.08 No vegetation
0.28 0.44
Dam 4 470 000 Flat Areas (3-10%)
0.08 Permeable 0.08 No vegetation
0.28 0.44
Dam 5 110 000 Flat Areas (3-10%)
0.08 Permeable 0.08 No vegetation
0.28 0.44
05 September 2014 34 12810
ZITHOLELE CONSULTING
Table 9: C values obtained from adjustment factors
RP PS
Clean Area
PS Dirty Area
CSY Dirty
Water Dam
Emerg Dirty
Water Dam
Clean Water Dam
Dam 1
Dam 2
Dam 3
Dam 4
Dam 5
0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1 0.21 0.23 0.26 0.18 0.18 0.18 0.23 0.23 0.19 0.19 0.19
2 0.23 0.31 0.30 0.19 0.19 0.19 0.26 0.26 0.22 0.22 0.22
5 0.25 0.34 0.33 0.20 0.20 0.20 0.28 0.28 0.24 0.24 0.24
10 0.27 0.37 0.36 0.22 0.22 0.22 0.30 0.30 0.26 0.26 0.26
20 0.30 0.42 0.40 0.25 0.25 0.25 0.33 0.33 0.29 0.29 0.29
50 0.37 0.51 0.50 0.31 0.31 0.31 0.40 0.40 0.37 0.37 0.37
100 0.45 0.62 0.60 0.37 0.37 0.37 0.48 0.48 0.44 0.44 0.44
Step 3: The adjusted C-values for Dam 1 is increased by 3.5% to take leachate into account. Only
half the facility will be line as this meets the requirements of the prevailing legislation therefore an
amount of 3.5 percent was utilised opposed to a norm of 7 percent.
Step 4: Rainfall, catchment area and C-values are multiplied to obtain a volume of runoff for each
area and dam.
5.5 OPTIONS MODELLED
Nineteen (19) Options under three (3) scenarios were modelled. The table below describes each
of the options.
Table 10: Options modelled
OPTIONS MODELLED
SCENARIO 1: Minimum open ash working area = 63 hectares
SCENARIO 2: Optimum open ash working area = 82 hectares
SCENARIO 3: Piggyback open ash working area = 98 hectares
OPTION 1 OPTION 2 OPTION 3 OPTION 4
• Status Quo
• Proposed system – Five (5) new dams.
• Proposed system – Five (5) new dams.
• Proposed system – Five (5) new dams.
• All dams considered to be dirty. Spills from Dams 2, 3, 4 & 5 over flow to Dam 1.
• Dam 1 & 5 considered dirty. Dam 2, 3 and 4 considered clean.
• Dam 1 & 5 considered dirty. Dam 2, 3 and 4 considered clean.
• Dust suppression from • Dust suppression from • Dust suppression from
05 September 2014 35 12810
ZITHOLELE CONSULTING
Dam 1, DWD & EDWD. Dam 1, DWD & EDWD. Dam 1, DWD & EDWD.
• Spills from e-dump overflow to DWD.
• Spills from e-dump overflow to DWD.
• Spills from e-dump overflow to DWD.
• Upper catchment not bypassed. (Total catchment area = 330 hectares)
• Spills from Dam 5 over flow to Dam 1.
• Spills from Dam 5 over flow to Dam 1.
• No irrigation to rehabbed areas.
• Upper catchment not bypassed. (Total catchment area = 330 hectares)
• Upper catchment bypassed. (Total catchment area = 4 hectares)
• Irrigation from existing CWD to power station terrace. (20mm)
• Irrigation to rehabbed areas. (20mm)
• Irrigation to rehabbed areas. (20mm)
Dam capacities for Dams 2, 3 & 4 determined for 50 year storm event. Dam 2 = 166,000 m
3, Dam 3 =
57,000 m3, Dam 4 = 32,000
m3
Irrigation from existing CWD to power station terrace. (20mm)
Dam capacities for Dams 2, 3 & 4 sized to spill once in 50 years.
Resultant Dam 1 sized to GN704 to only spill once in 50 years.
Dam capacities for Dams 2, 3 & 4 sized to spill once in 50 years.
Resultant Dam 1 sized to GN704 to only spill once in 50 years.
Resultant Dam 1 sized to GN704 to only spill once in 50 years.
CWD becomes process dam, i.e. EDWD spills into CWD
OPTION 2a OPTION 3a OPTION 4a
EDWD spills into Dam 5, Dam 5 spills into Dam 1
EDWD spills into Dam 5, Dam 5 spills into Dam 1
CWD spills into Dam 5, Dam 5 spills into Dam 1
OPTION 2b OPTION 3b OPTION 4b
Water treatment plant at EDWD
Water treatment plant at EDWD
Water treatment plant at CWD
5.6 MODELLING RESULTS
The results of the modelling exercise are contained in Table 10 below.
05 September 2014 36 12810
ZITHOLELE CONSULTING
Table 11: Modelling results
OPTIONS
2A 2B 3A 3B 4A 4B
SCEN
AR
IO 1
Dam 1 57,600,000 371,500 10,623,000 312,000 22,388,500 390,000
Dam 2 166,000 166,000 282,000 282,000 282,000 282,000
Dam 3 57,000 57,000 76,000 76,000 76,000 76,000
Dam 4 32,000 32,000 32,000 32,000 32,000 32,000
Dam 5 76,000 76,000 76,000 76,000 76,000 76,000
WTP(ML/d
)ay)
0 12.25 0 2.75 0 8.75
SCEN
AR
IO 2
Dam 1 17,368,623 371,500 120,000 120,000 297,000 120,000
Dam 2 166,000 166,000 257,000 257,000 257,000 257,000
Dam 3 57,000 57,000 76,000 76,000 76,000 76,000
Dam 4 32,000 32,000 32,000 32,000 32,000 32,000
Dam 5 76,000 76,000 76,000 76,000 76,000 76,000
WTP(ML/d
)ay)
0 9.25 0 0 0 1
SCEN
AR
IO 3
Dam 1 1,150,000 371,500 111,000 111,000 200,000 111,000
Dam 2 166,000 166,000 257,000 257,000 257,000 257,000
Dam 3 57,000 57,000 76,000 76,000 76,000 76,000
Dam 4 32,000 32,000 32,000 32,000 32,000 32,000
Dam 5 76,000 76,000 76,000 76,000 76,000 76,000
WTP(ML/d
)ay)
0 8.5 0 0 0 1
5.7 TRADE-OFF ASSESSMENT
The objective of the trade-off study is to select a preferred option from those considered in Section
5.5, with which to go forward to subsequent development stages of the project. Selection of an
alternative does not render it inflexible to improvement opportunities, but instead provides a broad
engineering framework for the development of the ash disposal facility. The nineteen (19) possible
alternatives for the stormwater management system around the ADF were conceptualised for
consideration in the trade-off study. Three broad criteria were selected for analysis of the options,
namely:
Environmental and social influences;
Engineering aspects;
Financial considerations.
The following approach was adopted:
Each of the above criteria was given a weighting in terms of perceived importance or
influence on the project.
05 September 2014 37 12810
ZITHOLELE CONSULTING
Each criterion was also sub-divided into sub-categories which were deemed to be relevant
to the project. Table 12 below shows the overall criteria and weighting matrix used for
evaluating and comparing the options:
Table 12: Option Analysis Criteria and Weighting
Category Description Category Weight
Engineering (Overall Weight = 35%)
No and size of dams required 10.0%
What is the complexity of the proposed Stormwater management system
around the dump
7.5%
Ease of maintenance of stormwater management infrastructure 7.5%
Complexity of operational philosophy 12.5%
Experienced human resources to run facility (controlled release, water
treatment plant)
10.0%
Infrastructure requirements (more pipelines to divert spillages, erosion control
at multiple discharge points, etc.)
10.0%
Air space lost due to larger PCD requirements 12.5%
Management of excess water (dust suppression, irrigation and WTP
optimisation)
10.0%
Dam safety requirements due to higher dam walls 5.0%
Security risk to stormwater management equipment 5.0%
Construction and monitoring complexity to ensure clean and dirty water
separation
10.0%
Environmental (Overall Weight = 35%)
Encroachment on wetlands and floodlines 15.0%
Level of impact that the proposed option has on the surface water system 20.0%
Regulatory process risks 15.0%
Groundwater impacts 10.0%
Compliance with GN704 30.0%
Multiple points of discharge from dams to receiving waters 10.0%
Financial (Overall Weight = 30%)
Net Present Value (Rands) 100%
A workshop was convened with all stakeholders involved in this project. Delegates present at this
workshop participated in critically discussing each criteria and sub-category. The result is that the
ranking and rating matrix was modified and agreed to by the meeting.
Following the above process, each cell in the matrix was populated by robust debate between all
representatives and disciplines present. Financial criteria were not discussed at the trade-off
workshop because the workshop was seen as a qualitative workshop in where only the technical
feasibility and the environmental impacts were evaluated.
05 September 2014 38 12810
ZITHOLELE CONSULTING
Financial comparison was conducted by analysing net present value of the capital costs associated
with each option. The total costs and the cost benefit rates were shown in the trade-off matrix and
rated accordingly. Costs were determined by measurements from the CAD models and using rates
obtained from previous work done on similar projects.
The summary of the results of the rating and ranking workshop are shown in Table 13. Full details
for all criteria are given in the appendices.
Table 13: Results of Trade-off Study Workshop
OPTION DESCRIPTION ENVIRONMENTAL CONSIDERATIONS
TECHNICAL FINANCIAL
Weighting 40.0% 30% 30% Score Rank
SCENARIO 0 STATUS QUO
0.00 0.00 5.00 0.00 14
SCEN
AR
IO 1
OPTION 2A 2.95 0.00 0.10 0.00 14
OPTION 2B 2.95 1.98 0.10 1.80 13
OPTION 3A 3.85 0.00 0.10 0.00 14
OPTION 3B 3.70 2.28 0.10 2.19 10
OPTION 4A 3.90 0.00 0.10 0.00 14
OPTION 4B 3.60 2.38 0.10 2.18 11
SCEN
AR
IO 2
OPTION 2A 3.10 0.00 0.10 0.00 14
OPTION 2B 2.95 2.63 0.10 2.00 12
OPTION 3A 4.30 3.53 4.93 4.26 4
OPTION 3B 4.30 3.53 4.98 4.27 3
OPTION 4A 4.20 2.80 4.35 3.83 6
OPTION 4B 3.90 2.88 0.10 2.45 9
SCEN
AR
IO 3
OPTION 2A 4.20 0.00 1.92 0.00 14
OPTION 2B 4.20 2.63 0.10 2.50 8
OPTION 3A 4.60 3.33 4.95 4.32 2
OPTION 3B 4.60 3.33 5.00 4.34 1
OPTION 4A 4.30 3.25 4.83 4.14 5
OPTION 4B 4.30 3.08 0.10 2.67 7
Option 3B, Scenario 3 is the preferred option following the technical, environmental and financial
scoring. However, this Scenario assumes that piggybacking is feasible. This has not been proven
as yet and cannot be considered at this stage. If proven feasible in future, the proposed
infrastructure will need to be sized adequately to accommodate the potential flows during this
Scenario. Since Scenario 3 is the best case scenario, it is proven that the infrastructure
implemented under the other Scenarios will accommodate flow generated under Scenario 3.
05 September 2014 39 12810
ZITHOLELE CONSULTING
Taking all these considerations into account and looking at the criteria as a whole, Option 3B
Scenario 2 is the preferred option and is recommended to be taken forward to the next phase of
design.
5.8 PROPOSED INFRASTRUCTURE
Option 3B Scenario 2 is the preferred option following the Trade-off Assessment and will be taken
forward to the Conceptual Design Phase. The proposed infrastructure is detailed below. Layout
drawings of the proposed infrastructure for the options modelled as well as the preferred option are
attached to the appendices.
5.8.1 Pollution Control Dams
The two (2) existing pollution control dams, dirty water dam and emergency dirty water dam,
remain in place. Additional Dams 1 and 5 are proposed. The capacity of Dams 1 and 5 is 120 Mℓ
and 76 Mℓ (+ 2 days storage for dust suppression water) respectively. The performance (dam
levels) of these four pollution control dams for the fifty (50) year simulation period is shown on the
respective graphs below.
Figure 22: Dirty Water Dam Levels for Simulation Period
0%
20%
40%
60%
80%
100%
120%
16
-May
-63
16
-May
-66
16
-May
-69
16
-May
-72
16
-May
-75
16
-May
-78
16
-May
-81
16
-May
-84
16
-May
-87
16
-May
-90
16
-May
-93
16
-May
-96
16
-May
-99
16
-May
-02
16
-May
-05
16
-May
-08
16
-May
-11
Dam Level Dam Max Capacity
05 September 2014 40 12810
ZITHOLELE CONSULTING
0%
20%
40%
60%
80%
100%
120%
Dam Level Dam Max Capacity
Figure 23: Emergency Dirty Water Dam Levels for Simulation Period
Figure 24: Proposed Dam 1 Levels for Simulation Period
0%
20%
40%
60%
80%
100%
120%
Dam Level Dam Max Capacity
05 September 2014 41 12810
ZITHOLELE CONSULTING
Figure 25: Proposed Dam 5 Levels for Simulation Period
5.8.2 Clean Water Dams
In addition to the existing Clean Water Dam, three (3) more dams are proposed for clean water
containment. These dams will be operated on a controlled release principle which is based on the
receiving water quality. It is not the intention to impound clean water if not required provided that
the discharge quality is acceptable. If the water in these dams are deemed impacted, it will be
irrigated onto the areas that it emanated from or utilised in the power station water balance if
possible.
The following are the proposed Clean Water Dams:
Dam 2 257 Mℓ
Dam 3 76 Mℓ
Dam 4 32 Mℓ + two day storage for irrigation water
The performance (dam levels) of these four (including the existing Clean Water Dam) clean water
dams for the fifty (50) year simulation period is shown on the respective graphs below
0%
20%
40%
60%
80%
100%
120%
Dam Level Dam Max Capacity
05 September 2014 42 12810
ZITHOLELE CONSULTING
0%
20%
40%
60%
80%
100%
120%
16
-May
-63
16
-May
-66
16
-May
-69
16
-May
-72
16
-May
-75
16
-May
-78
16
-May
-81
16
-May
-84
16
-May
-87
16
-May
-90
16
-May
-93
16
-May
-96
16
-May
-99
16
-May
-02
16
-May
-05
16
-May
-08
16
-May
-11
Dam Level Dam Max Capacity
Figure 26: Existing Clean Water Dam Levels for Simulation Period
Figure 27: Proposed Dam 2 Levels for Simulation Period
0%
20%
40%
60%
80%
100%
120%
16
-May
-63
16
-May
-66
16
-May
-69
16
-May
-72
16
-May
-75
16
-May
-78
16
-May
-81
16
-May
-84
16
-May
-87
16
-May
-90
16
-May
-93
16
-May
-96
16
-May
-99
16
-May
-02
16
-May
-05
16
-May
-08
16
-May
-11
Dam Level Dam Max Capacity
05 September 2014 43 12810
ZITHOLELE CONSULTING
Figure 28: Proposed Dam 3 Levels for Simulation Period
Figure 29: Proposed Dam 4 Levels for Simulation Period
0%
20%
40%
60%
80%
100%
120%
Dam Level Dam Max Capacity
0%
20%
40%
60%
80%
100%
120%
Dam Level Dam Max Capacity
05 September 2014 44 12810
ZITHOLELE CONSULTING
5.8.3 Toe Paddocks
The slope available to facilitate self-cleansing velocities in the western dirty water channel
discharging to the pollution control Dam 1 could not be achieved. In order to prevent siltation within
the channels and reduce the required velocities, it is proposed that paddocks be constructed at the
toe of the advancing face to intercept run-off from the disposal facility and allow this to overflow to
the discharge channels. The temporary structures will facilitate siltation. It is envisaged that the
paddocks will be constructed from ash and will be located on top of the lined portion of the facility.
The paddocks will be covered over when dozing the side slope down to the final 1:5 slope for
rehabilitation of that section of the facility.
Figure 30: Positioning of Temporary Toe Paddocks
5.8.4 Storage Reservoirs
Apart from capturing runoff from its respective areas, dust suppression and irrigation water will be
stored in Dam 5 and Dam 4 respectively. It is proposed that additional two days storage be
allowed for in the capacity of these dams.
5.8.5 Conveyance infrastructure (pumps, pipelines and channels)
The proposed operational philosophy around stormwater management will involve the construction
of new infrastructure. Apart from the dams as mentioned in the previous sections of this report,
conveyance infrastructure will be required for the following reasons:
Conveyance of spills from one facility to the next;
Conveyance of dust suppression water from the relevant dams to the dedicated storage
reservoirs;
Conveyance of rehabilitated irrigation water from the relevant dams to the dedicated storage
reservoirs;
Dust suppression from storage reservoir to open ash area of the ADF;
Irrigation from storage reservoir to the rehabilitated area of the ADF;
Irrigation of the power station terrace grassed areas from the Clean Water Dam
CLEAN WATER CUT-OFF BERM
ACCESS ROAD
CHANNEL TO PCD
TEMPORARY TOE PADDOCK
CONSTRUCTED FROM ASH
ON TOP OF LINER
ADVANCING FACE OF ADF
REHABILITATED FACE OF ADF
ASH BODY
LINER UP TO DIRTY
WATER CHANNEL
05 September 2014 45 12810
ZITHOLELE CONSULTING
5.9 1 IN 100 YEAR FLOODLINES
5.9.1 Methodology
Delineation of Catchment Areas
The 0.5m interval contours were obtained from the topographical survey. The contours and 1 in 50
000 topographical maps were studied to divide the area into smaller sub-catchments. Water
courses, streams and rivers were identified using the maps. Two separate water courses were
identified, namely the Three Dams Water Course and the Farm Dam Water Course. The surface
area of each sub-catchment was determined as well as the ground cover and the average slopes
and distances of overland flow and average slopes of water courses. The surface area of the sub-
catchments are shown in Table 14.
Table 14: Sub-Catchment Surface Areas
Water Course Sub-catchment Surface Area (ha)
Three Dam System A 436
Three Dam System B 408
Farm Dam System C 3 617
Flood Hydrology
The Rational Method as described in the document Drainage Manual, Sixth Edition (2013) as
published by SANRAL (South African National Roads Agency Limited) was used to determine the
magnitude of the 1 in 100 year floods.
The peak flow rate is calculated with the following formula:
Where Q = peak flow (m3/s)
c = run-off coefficient (dimensionless)
i = average rainfall intensity over the catchment (mm/hour)
A = effective area of catchment (km2)
3.6 = conversion factor
05 September 2014 46 12810
ZITHOLELE CONSULTING
Rainfall data was obtained for the Cologne rainfall station (Number 0478008_W). The rainfall
record for this station is 97 years long. The rainfall station is located approximately 3.7km west of
Kendal Power Station. The Mean Annual Precipitation (MAP) was found to be 675 mm/year.
The Time of Concentration was determined for each sub-catchment in accordance with the
following formulas. Refer to Drainage Manual, Sixth Edition (2013):
For overland flow:
Where Tc = time of concentration (hours)
r = roughness coefficient = 0.4 for medium grass cover
L = length of the catchment from the boundary to where the flood needs to be
recorded (km)
S = slope of the catchment (m/m)
For defined water courses:
Where Tc = time of concentration (hours)
r = roughness coefficient = 0.4 for medium grass cover
L = length of the water course from the boundary to where the flood needs to be
recorded (km)
S = average slope of the catchment (m/m)
The total time of concentration is the sum of the time of concentration for overland flow plus the
time of concentration for water course flow, namely Tc1 plus Tc2. The time of concentration for
overland flow, flow in water courses and the total time of concentration is presented in Table 15.
05 September 2014 47 12810
ZITHOLELE CONSULTING
Table 15: Resulting Time of Concentration for the sub-catchments
Water Course Sub-catchment Calculated time
of
concentration
for overland
flow (minutes)
Calculated time
of
concentration
for flow in a
water course
(minutes)
Total Time of
Concentration
(minutes)
Three Dam
System
A 7 22 29
Three Dam
System
A and B
together
7 66 73
Farm Dam
System
C 3 173 176
The storm duration is taken as the total time of concentration. The rainfall intensity is determined
from Figure 3.8 in the Drainage Manual, Sixth Edition (2013) as published by SANRAL.
The resulting storm depths, storm durations and rainfall intensities are shown in Table 16.
Table 16: Resulting Storm Depths, Storm Durations and Rainfall Intensities
Water Course Sub-catchment Storm Depth
(mm)
Storm Duration
(hours)
Rainfall
Intensity, i
(mm/hrs)
Three Dam
System
A 75 0.49 152
Three Dam
System
A and B
together
130 1.22 106
Farm Dam
System
C 160 2.93 55
The Run-off coefficient (c) for each sub-catchment must now be calculated.
The recommended values are selected according to 3 characteristics of the catchment under
consideration, namely:-
a) Surface slope classification
b) Permeability classification
c) Vegetation classification
05 September 2014 48 12810
ZITHOLELE CONSULTING
The run-off coefficients with regard to surface slope classification are presented in Table 17.
Table 17: Run-off Coefficients with regard to Surface Slope Classifications
Description Run-off coefficient (cs) for rural
areas with an MAP between 600
and 900mm/year
Steep areas (slopes > 30%) 0.03
Hilly (10 to 30%) 0.08
Flat areas (3 to 10%) 0.16
Vleis and pans (slopes < 3%) 0.26
The run-off coefficients with regard to permeability are presented in Table 18.
Table 18: Run-off coefficients with regard to Permeability
Description Run-off coefficient (cp) for rural
areas with an MAP between 600
and 900mm/year
Very permeable 0.04
Permeable 0.08
Semi-impermeable 0.16
Impermeable 0.26
The run-off coefficients with regard to vegetation classification are presented in Table 19.
Table 19: Run-off coefficient with regard to Vegetation
Description Run-off coefficient (cv) for rural
areas with an MAP between 600
and 900mm/year
Thick bush and plantation 0.04
Light bush and farmlands 0.11
Grasslands 0.21
No vegetation 0.28
The overall c-value for a catchment, also known as the c1 is the sum of the c-values for the three
characteristics, as shown by the following equation:
Where c1 = Overall run-off coefficient for a catchment
05 September 2014 49 12810
ZITHOLELE CONSULTING
cs = Run-off coefficient with regard to slope
cp = Run-off coefficient with regard to permeability
cv = Run-off coefficient with regard to vegetation
The overall run-off coefficient c1 is multiplied by an adjustment factor with regard to the return
period, as presented in Table 20:
Table 20: Adjustment Factors for c1 with regard to Return Period:
Return Period (years) 2 5 10 20 50 100
Factor (Ft) for steep
and impermeable
catchments
0.75 0.80 0.85 0.90 0.95 1.00
Factor (Ft) for flat and
permeable
catchments
0.50 0.55 0.60 0.67 0.83 1.00
The magnitude of the 1 in 100 year flood can now be determined for exact locations within the two
water courses. Generally, the larger a catchment area contributing to the run-off at a specific point,
the larger the magnitude of the flood at that point will be.
The resulting c-values are presented in Table 21.
Table 21: Resulting c-values
Description c-value
cs 0.26
cp 0.12
cv 0.16
c1 0.54
The magnitude of the 1 in 100 year flood can now be determined for exact locations within water
courses, streams and rivers.
The results of the hydrology calculations are presented in Table 22.
05 September 2014 50 12810
ZITHOLELE CONSULTING
Table 22: Results of Hydrology Calculations
Water Course
Catchment or Sub-Catchment
Area (ha)
i (mm/hours)
c1-value Maximum 1 in 100 Year
Flood (m3/s)
Three Dam
System
A 436 152 0.54 99.3
Three Dam
System
A and B
together
408 106 0.54 134.4
Farm Dam
System
C 3 617 55 0.54 296.8
Hydraulic Simulation
The 0.5m interval contours were obtained from the topographical survey. The software Autodesk
Civil3D 2013 was used to extract longitudinal sections of the two water courses. Cross sections
were also extracted at intervals of approximately 250m. The length of typical cross sections was
approximately 1.2km.
The geometry was imported into the software HEC-RAS, a backwater model, which was developed
by the United States Army Corps of Engineers.
A Manning’s “n” hydraulic roughness value of 0.045 was assumed for all sections, which
corresponds to natural straight water courses.
Normal water flow depths were assumed for the upstream position and downstream position of the
river section. Normal flow depth here means the calculated water depth for a certain roughness, a
certain flow and a certain longitudinal slope. The software does the hydraulic calculations for each
cross section. The output from the software are flow depths, flow velocities, cross sectional area,
wetted perimeter etc. Four separate models were produced, namely:
Three Dam Water Course Pre-Development
Three Dam Water Course Post-Development
Farm Dam Water Course Pre-Development
Farm Dam Water Course Post-Development
The outputs from the Three Dams Water Course Pre-Development Model are presented in Table
23. An output longitudinal section of this model is presented in Figure 5-11.
05 September 2014 51 12810
ZITHOLELE CONSULTING
Table 23: Output from the Three Dams Water Course Pre-Development Model
River Station
(m)
Maximum Channel
Depth (m)
Velocity (m/s)
Cross Sectional
Area (m2)
Hydraulic Depth
(m)
5815.29 0.67 2.1 63.96 0.44
5692.63 0.86 0.82 164.91 0.67
5500.75 0.68 1.61 83.22 0.48
5264.58 1.19 0.93 144.28 0.72
4992.33 1.04 2.23 60.15 0.51
4714.41 1.66 1.44 93.22 1.12
4559.7 0.84 2.62 51.24 0.69
4380.86 1.99 0.61 221.22 1.61
4164.74 2.45 0.26 525.01 2.2
4084.26 2.44 0.21 632.53 2.29
4002.2 2.62 4.31 31.19 1.87
3916.36 4.82 0.14 948.05 3.57
3851.62 1.42 2.66 50.47 0.71
3775.49 3.14 0.24 561.42 2.48
3699.91 1.63 2.99 44.95 0.91
3628.32 6.86 0.25 540.42 3.19
3442.92 2.26 3.21 41.9 1.05
3333.43 1.75 3.84 35.03 0.76
3233.58 1.59 3.14 42.86 0.99
3133.43 1.88 4.21 31.92 0.96
3012.8 2.47 3.61 37.25 1.06
2901.17 2.16 3.1 43.36 1
2749.19 2 4.06 33.13 0.84
2564.16 1.13 2.75 48.81 0.77
2348.07 1.07 1.99 67.68 0.81
2142.4 1.32 2.38 56.5 0.63
1912.37 1.58 1.84 73.11 0.63
1698.17 1.11 1.8 74.66 0.77
1399.16 0.95 2.35 57.09 0.56
1000.06 0.86 1.31 102.35 0.64
742.81 0.99 1.08 124.55 0.7
501.76 0.8 1.98 67.88 0.49
222.11 0.89 1.1 122.2 0.63
0 1.63 1.84 72.86 0.34
A new diversion channel was designed for the Three Dams Water Course Post-Development
scenario. The new diversion channel will be lined with reno-mattresses and seeded with
indigenous grasses. The new diversion channel was designed to contain the 1 in 100 year flood
without overflowing. The minimum longitudinal slope of the new channel is 0.192% or 1 in 522
05 September 2014 52 12810
ZITHOLELE CONSULTING
(m/m). A Manning’s “n” hydraulic roughness value of 0.035 was assumed for the new channel,
which corresponds to long grass growing in the diversion channel. The normal flow depth in the
channel was calculated to be 2.9 m, and the critical depth is 1.8m deep. Flow will therefore be sub-
critical. A cross section of the channel is presented in Figure 5-12.
The outputs from the Farm Dam Water Course Pre-Development Model are presented in Table 24.
An output longitudinal section of this model is presented in 5-13Error! Reference source not
ound..
Table 24: Output from the Farm Dam Pre-Development Model
River Station
(m)
Maximum Channel
Depth (m)
Velocity (m/s)
Cross Sectional
Area (m2)
Hydraulic Depth
(m)
5336.07 1.97 2.92 101.48 0.87
5005.81 2.68 5.91 50.23 1.22
4695.89 3.3 1.62 183.1 1.21
4343.33 3.11 1.94 152.6 1.08
4004.85 3.04 1.1 270.8 1.2
3740.42 1.83 1.72 172.86 0.91
3406.65 1.23 1.84 161.25 0.8
3149.75 2.09 1.68 176.47 1.59
2839.08 1.82 1.7 174.68 1.34
2550.1 3.2 0.37 792.46 2.34
2227.47 3.19 0.27 1104.32 2.95
1977.23 2.84 2.34 126.64 1.16
1802.67 3.01 0.21 1420.39 2.6
1556.71 3.01 0.25 1170.21 2.79
1331.24 3 0.2 1452.15 2.79
1164.38 1.4 2.14 138.79 0.45
946.45 1.06 1.48 201.2 0.71
624.74 1.88 0.79 374.08 0.84
441 1.11 1.57 189.17 0.45
176.53 0.8 0.89 335.31 0.66
0 2.26 1.99 148.9 0.39
The wall of the Farm Dam will be lowered by 3 m in elevation for the Post-Development scenario.
The post-development output longitudinal section of this model is presented in Figure 5-13.
05 September 2014 53 12810
ZITHOLELE CONSULTING
5.9.2 Results
The resulting 1 in 100 year floodlines are shown in Figure 5-10.
Figure 31: 1 in 100 Year Floodlines Pre- and Post-Development
05 September 2014 54 12810
ZITHOLELE CONSULTING
Figure 32: Resulting Longitudinal section of Three Dams Water Course
05 September 2014 55 12810
ZITHOLELE CONSULTING
Figure 33: Cross Section of Diversion Channel
05 September 2014 56 12810
ZITHOLELE CONSULTING
Figure 34 Resulting Longitudinal Section of Farm Dam Water Course, Pre-Development
05 September 2014 57 12810
ZITHOLELE CONSULTING
Figure 35: Resulting Longitudinal Section of Farm Dam Water Course, Post-Development
05 September 2014 58 12810
ZITHOLELE CONSULTING
5.10 Suppression Abstraction Philosophy
The Stormwater Management Philosophy proposed below is for the preferred option, Option 3B,
Scenario 2. Impacted (dirty) stormwater will be contained in four (4) pollution control dams,
namely:
1. Dirty Water Dam (existing)
2. Emergency Dirty Water Dam (existing)
3. Dam 1 (proposed)
4. Dam 5 (proposed)
The operating philosophies of these dams are interlinked with respect to abstraction of water for
dust suppression and will need to be managed effectively to ensure peak performance. The
relationship between these dams is as follows:
The Emergency Dirty Water Dam will need to always have 55 Mℓ available storage capacity
therefore it should be given priority for dust suppression to maintain this volume.
If the Emergency Dirty Water Dam has the available storage available, then water for dust
suppression will have to be abstracted from either the Dirty Water Dam or Dam 1 (proposed).
Water will be abstracted from the dam with the highest volume by percentage of its storage
capacity.
Dam 5 is used as a storage reservoir for dust suppression. Water from the three (3) other
pollution control dams are pumped here for dust suppression.
5.11 Hydraulic Analysis
5.11.1 Sizing of “Clean” stormwater diversion drains and berms
The topography of the area earmarked for the extension of the existing ash dump has a natural rolling terrain
in a north-westerly direction. Consequently, “clean” surface runoff can only be expected from the contributing
sub-catchments located to the east of the study area. This resultant runoff will be managed as part of the
river/stream diversion discussed in section 1 of this report.
The river diversion will be sized to convey the peak discharge generated during a 1:100yr storm event from
the contributing catchment downstream of the spillway and the clean water dam spillway capacity of
100m3/s. The spillway is used as a control point from the contributing catchments upstream.
5.11.2 Sizing of “Dirty” stormwater conveyance drains
Surface runoff generated from within the footprint of the extended ash dump will ultimately report into toe-
drains running northerly along the western toe line. This system comprises of two (2) types of drains (Toeline
drain & Outlet Drain) in series leading into the new PCDs shown in figure below.
05 September 2014 59 12810
ZITHOLELE CONSULTING
Figure 36: Toe Line Drain
Figure 37: Outlet Drain
05 September 2014 60 12810
ZITHOLELE CONSULTING
Preliminary design parameters for the “dirty” stormwater drains are indicated in Table 25:
Table 25: "Dirty" Water Channels Concept Design Parameters
Design
Parameter
“Dirty” Water Channel
Toe line
Drain (D1)
Outlet Drain
(O1)
Channel Type Trapezoidal Trapezoidal
Lining Type Concrete Concrete
Friction
Calculation
Method
Manning’s
Formula
Manning’s
Formula
Flow Rate
Q(m3/s)
33 46
Bed Slope S
(m/m)
0.005 0.005
Manning’s N
(s/m1/3
)
0.016 0.016
Velocity V(m/s) 4.1(to be
optimised at
detailed
design stage)
4.4(to be
optimised at
detailed
design stage)
Side Slopes
(m/m)
0.5 0.5
Bottom Width
(m)
2 2.5
Normal Depth
(m)
1.5 1.7
5.12 WATER BALANCE
The Water Balance for the preferred option is shown in Appendix D. Normal
operating levels for the dams, both existing and proposed, are shown on the
graphs in Section 5.8.
5.13 OPERATIONAL REQUIREMENTS
In sizing the proposed infrastructure, several assumptions were made for the
operational philosophy surrounding the ADF and its infrastructure. These
assumptions need to be realised during operation in order to ensure the
performance of the new infrastructure.
05 September 2014 61 12810
ZITHOLELE CONSULTING
5.13.1 Monitoring of Quality in Clean Water Dams
The clean water dams, Dams 2, 3 and 4, have been sized not to spill more than
once in fifty years which takes into consideration irrigation onto the rehabilitated
areas. These dams will need to be monitored for water quality on a continuous
basis. If the water is deemed clean with respect to the discharge quality of the
receiving environment, then it may be released. However, if the quality does not
meet the discharge quality, then this water must be irrigated onto the rehabilitated
areas or utilised in the station water balance.
5.13.2 Maintaining Open Ash Areas for Dust Suppression
Option 3B Scenario 2 recommends an optimum open ash area of 82 hectares to
be maintained during operations, to balance the dirty water system using dust
suppression without the need for a Water Treatment Plant. The respective dams
have been sized accordingly. If significantly smaller areas are maintained, the
dams recommended is this report will be too small to ensure that we do not spill
more than once in fifty years from the pollution control dams.
5.13.3 Maintaining Silt Traps
The storage capacity of the proposed dams does not assume a continuous influx of
silt into it as it is equipped with a silt trap. If these silt traps are not maintained as
per their design requirements, the performance of the dams will be compromised.
The silt traps will be finalised during detailed design and the operations thereof
need to be communicated to the power station operators.
5.14 WAY FORWARD FOR STORMWATER MANAGEMENT
The trade-off study was conducted and finalised to inform the permitting process in
order to determine the optimised go-forward scheme for the implementation of
stormwater management infrastructure surrounding the extension of the current
Kendal Ash Dump. Option 3B Scenario 2 is the preferred option and conceptual
designs will need to be finalised for this.
It is also recommended that a Water Use Licence Application be made for the
water uses as described in this report.
05 September 2014 62 12810
ZITHOLELE CONSULTING
6 STREAM DIVERSION
The perennial stream located to the East of the existing ash dump currently runs
through the proposed footprint of Options 2A, 2B and 2C. Consequently, this
stream will be diverted to run northerly, parallel to the extended footprint of the ash
dump.
This stream serves as a receptor for discharge from the existing clean water dam
located up-slope. This dam serves as a primary source of flow for the stream. The
maximum discharge over the dam’s spillway is 100m3/s. The diversion channel will
be sized to cater for this flow, plus the runoff from the area below the spillway,
while incorporating an additional freeboard of 1m. A preliminary sizing has been
done; the bottom width of the stream diversion is 10m wide and a depth of 2m the
left and right side slopes are 1V:2.5 and 1V:3H respectively., on the lower left bank
side a berm is constructed to provide the 1m freeboard. In the figure below a
typical section is provided for the stream diversion. There are a number of aspects
listed below that needs to be investigated in the following phase of design to
provide an optimal solution for the stream diversion:
Investigating impact of stream diversion downstream of the stream diversion ,
Establishing similar vegetation in new stream
Erosion mitigation in initial stages
Probability of leachate of the existing facility migrating towards the stream
diversion
Design of this stream diversion channel will be carried out at a later stage of the
project, only a preliminary river section is provided in Figure 38
Figure 38: Proposed Stream Diversion
Berm constructed from suitable
excavated material
Reno-mattress lining
05 September 2014 63 12810
ZITHOLELE CONSULTING
7 PHASED APPROACH TO ADF
7.1.1 Option 1A & 2A
All the constraints where identified in terms of site boundaries, stream 100m lines
(Stream diversion lines for 2A) machinery and equipment used. Within these
options the maximum footprint was identified within these constrains. And a
maximum height was determined to be 60m.
For Option 1A the capacity of the site gives a remaining life of 5 years from
January 2015. This gives us time to 2019. If construction of the liner only finishes
at the end of 2015 the remaining life is only 4 years which means it would be
impractical to have phase development for this option
For Option 2A the capacity gives a remaining life of 15 years from January 2015.
This is triple the capacity of option 1A. It was assumed that the minimum cell life for
this option would be 5 years. Thus after construction there is only life for 11 years.
Thus a two cell approach is considered on which Cell 1 will have a life of six years
and Cell 2 a life of five years.
7.1.2 Option 1B & 2B
These options have the same footprints as option 1A and 2A therefore their
footprint cells will be the same. As the idea here is to do staged piggybacking the
piggybacked area is seen as another lined cell on its own. Option 2B has a
remaining life of 18 years which provides another three years of capacity. The
piggyback cell will only have a capacity of three years and will also involve moving
the suitable conveyor systems regularly if the piggyback is constructed solely
which can be an operational flaw.
7.1.3 Options 1C & 2C
These options again have the same footprint as option 1A and 2A, but due to the
piggyback section being constructed concurrently the piggyback area will not be
lined and the majority of it will be placed on the existing dump as the shiftable
conveyor system will be moved back and then covered with topsoil and grassed.
Option 1 C will have the same footprint cell and will thus have a capacity of 5
years, this means that 2 years for this option will be placed on the existing footprint
which will then be topsoiled and grassed.
Option 2C will also have the same footprint as Option 2A and thus have two
footprint cells with a capacity for 11 years. Thus 5 years of ashing will take place
on the existing ash dump and will then be topsoiled and grassed.
05 September 2014 64 12810
ZITHOLELE CONSULTING
8 FARM DAM SYSTEM
To the west of the existing ADF, there exists a farm dam on Eskom’s property
which does not form part of the water management philosophy. The dam is
currently used by a farmer to irrigate two centre pivots, located on the footprint of
the proposed extension. His activities will cease once the ADF is extended and the
dam will no longer be required to serve its intended purpose. However, the dam
sustains a wetland located at the toe of the dam wall and will pose a significant
environmental impact if removed in its entirety. The wetland is sustained via
seepage through the dam wall, which was not designed or constructed to
acceptable engineering standards and poses a risk of failure.
The height of the dam wall poses a significant institutional challenge for Eskom as
the top water level reaches at times the level of the final open cast coal mine voids
located adjacent to the farm dam. This is not ideal as clean water flow enters the
final voids when the level in the dam is high, resulting in contamination of the clean
water in the dam. However, the mine may decant uncontrollably into the farm dam.
The latter should be addressed by the mining house as it is outside the control of
Eskom.
The farm dam is in-stream downstream of a diverted watercourse created by the
mine in order to undertake open cast mining on its original course.
The following work is proposed in order to make this system environmentally
acceptable:
New earth dam wall to be built to prevent overflow into mining voids and
vice-versa
Existing dam wall to be removed
Engineered seepage from the dam to downstream of wall taken into
consideration for wetland sustainability
Upstream approach channel and outlet channel to dam to be lined using
reno mattress – flat gradients
Channel designed for the 1:2 year stormflow velocities
It should be noted that a portion of the upstream approach channel falls within the
property of Side Minerals. This is portion 1 of Leeuwfontein 219 IR. Side Minerals
(or Shanduka Coal) are the mining right holders of the Lakeside and Stuart
Collieries which are no longer operational.
05 September 2014 65 12810
ZITHOLELE CONSULTING
The proposed works are shown on the figure below.
Figure 39: Proposed changes at Farm Dam System
Reline stream diversion with
reno mattress
Lower dam wall to
below final void
decant level
Final voids
Reline dam outlet channel
with reno mattress
05 September 2014 66 12810
ZITHOLELE CONSULTING
9 OPERATION AND MAINTENANCE PLAN
There is currently an operational manual in place for the existing Kendal facility
which provides insight into all current activities on site.
9.1 Code requirements in terms of SABS 0286
The Following needs to be in accordance with SABS 0286
Management
Operational phase appointment
Facility audit
Hazard classification
Operating manual
Operation of the ash dump
Operation of silt trap/s and pollution control dam
Monitoring and maintenance requirements
Rehabilitation and environmental considerations
05 September 2014 67 12810
ZITHOLELE CONSULTING
10 DISCUSSION
Trade-off studies were conducted in order to determine the optimised go-forward
scheme for the expansion of the current Kendal Ash Dump and stormwater
infrastructure. Six options for the ADF and nineteen options for the stormwater
management philosophy were assessed. This was supported by:
Conceptual airspace modelling of each alternative;
A daily time-step model over a 50 year period for run-off determination and
PCD sizing, as well as sizing of clean and dirty water conveyances;
Conceptual development of dump infrastructure including surface drainage
structures, hydraulic structures, leachate and sub-surface drainage, lining and
cover materials;
Cost estimation;
Trade-off study workshop.
From the trade-off study held the preferred layout option is identified as Option 2A and the preferred water balance option is identified as Scenario 2, Option 3B
Option 2A provides a ashing capacity of 98 Mm3 at a density of 0.85t/m3
This provides a remaining life of 15 years from January until 2029
The preferred option as selected through the trade-off study analysis is based on a preliminary design. All fundamental aspects were addressed to inform the EIA study.
It is recommended to progress with the preferred option through a basic and detailed design phase.
The requirements that are raised as issues and concerns through the EIA and stakeholder engagement process should be addressed during the basic and detailed design phase and the impacts should be mitigated through engineering solutions.
Based on the trade-off study work, it can be stated that the proposed facility extension is a feasible solution.
05 September 2014 68 12810
ZITHOLELE CONSULTING
11 RECOMMENDATION AND CONCLUSION
Several options were considered for determining the go-forward option on the ADF
and stormwater management philosophy. The “piggyback” options described in
both the determination of air space on the ADF and stormwater management
philosophy are not deemed feasible currently from a mechanical perspective. This
option was therefore not considered for implementation in this report. Further
investigation is currently underway here and will be reported on a separate project
that has been commissioned by Kendal Power Station.
The go-forward option as proposed for the ADF layout is Option 2A and for the
stormwater management philosophy is Scenario 2 Option 3B. A Waste
Management Licence (WML) and Water Use Licence (WUL) need to be applied for
the infrastructure and activities as described in the aforementioned options.
ZITHOLELE CONSULTING (PTY) LTD
N Rajasakran Pr.Eng J Heera
Project Manager Project Reviewer
ZITHOLELE CONSULTING
APPENDIX A
Geotechnical Report
ZITHOLELE CONSULTING
APPENDIX B
Waste Classification Report
ZITHOLELE CONSULTING
APPENDIX C
Conceptual Engineering Drawings
ZITHOLELE CONSULTING
APPENDIX D
Water Balance Diagram
ZITHOLELE CONSULTING
APPENDIX E
Trade-Off Study Matrix
ZITHOLELE CONSULTING
APPENDIX F
Technical Memo: Selection of Barrier System