distribution system reliability improvement using
TRANSCRIPT
DISTRIBUTION SYSTEM RELIABILITY IMPROVEMENT USING
DISTRIBUTED GENERATORS.
SITI HAIRANI BINTI JAMAL
A thesis submitted in
fulfillment of the requirement for the award of the
Degree of Master of Electrical Engineering
Faculty of Electrical and Electronic Engineering
Universiti Tun Hussein Onn Malaysia
DECEMBER 2014
v
ABSTRACT
Solar Energy is one of alternative source for rural electrification where no nearest
grid connected available. However, since it is only depending on sun irradiation it
only can feed customers need during day time only. Besides, a standalone solar
energy cannot provide a continuous supply due to seasonal weather and any other
periodic variations. Therefore, to satisfy the customer needs, a hybrid energy source
is a better solution. A combination between solar PV with Battery and Generator set
proposed as the hybrid energy source called Hybrid Distributed Generator.
Investigation will be done on reliability improvement for Distribution system by
using this Distributed Generator. Distributed Generator installed at Station Solar
Hybrid in Tanjung Labian will be investigate. The SAIDI used as the Indices to show
the reliability improvement for distribution system. SAIDI is an importance where
continuity of power is high priority. Besides, SAIDI contributes the amount of time
the customer is affected without power supply.
vi
ABSTRAK
Tenaga solar merupakan salah satu diantara tenaga alternatif untuk digunakan
sebagai tenaga elektrik yang akan membekalkan bekalan elektrik luar Bandar yang
mana kemudahan talian grid terdekat tidak terdapat di kawasan tersebut.
Walaubagaimanapun, oleh kerana tenaga solar ini bergantung sepenuhnya kepada
sinaran solar maka ia hanya dapat menampung beban pengguna pada hari siang.
Disamping itu, tenaga solar sahaja tidak dapat menyambung bekalan elektrik secara
berterusan disebabkan factor perubahan cuaca dan apa – apa variasi berkala. Oleh
itu, untuk memuaskan hati kehendak para pengguna, sumber tenaga hibrid adalah
penyelesaian yang lebih baik. Gabungan antara tenaga solar dengan batteri dan set
penjana dicadangkan sebagai sumber tenagan hybrid yang dipanggil penjana
pengedar. Penjana pengedar yang dipasang di Stesen solar hybrid di Tanjung Labian
akan di siasat. SAIDI akan dijadikan kayu pengukur kebolehpercayaan sistem
pembahagian menggunakan tenaga dari penjana pengedar. SAIDI ini penting dimana
ia kesinambungan bekalan yang berterusan adalah keutamaan yang tinggi. Selain itu,
SAIDI menyumbang jumlah masa pelanggan yang terjejas tanpa bekalan kuasa.
vii
CONTENTS
TITLE i
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
ABSTRAK vi
CONTENT vii
LIST OF TABLES ix
LIST OF FIGURES x
LIST OF SYMBOL AND ABBREVIATION xiii
LIST OF APPENDICES xiv
CHAPTER 1 INTRODUCTION 1
1.1 Project Background 1
1.2 Problem Statements 6
1.3 Project Objectives 8
1.4 Project Scopes 9
viii
CHAPTER 2 LITERATURE REVIEW 10
2.1 Introduction 10
2.2 Theories 10
CHAPTER 3 METHODOLOGY 27
3.1 Project Methodology 27
CHAPTER 4 RESULTS AND DISCUSSION 38
4.1 Introduction 38
4.2 Results and Discussion 39
CHAPTER 5 CONCLUSION RECOMMENDATION 54
5.1 Conclusion 54
5.2 Recommendation 55
REFERENCES 56
APPENDICES 59
VITA 63
ix
LIST OF TABLES
2.1 Strengths and weaknesses of reciprocating engines 12
2.2 Strengths and weakness of microturbines 13
2.3 Strengths and weakness of combustion turbines 14
2.4 Strengths and weakness of Photovoltaic 16
2.5 Strengths and weakness of fuel cell type 17
2.6 Strengths and weakness of Wind Turbines 18
2.7 The strengths and weaknesses of Hybrid system 20
3.1 Type and number of customer for Six (6) Villages 28
3.2 Key Specification of PV Panel 32
3.3 Key Specification of Battery Model 35
4.1 SAIDI tabulated for placing Distributed Generator at existing 48
location
4.2 SAIDI tabulated for placing Distributed Generator at location A 49
4.3 SAIDI tabulated for placing Distributed Generator at location B 50
4.4 SAIDI tabulated for placing Distributed Generator at location C 51
4.5 SAIDI tabulated for placing Distributed Generator at location D 52
x
LIST OF FIGURES
1.1 Rural Electrification : Tanjung Labian Lahad Datu,
Sabah
3
1.2 Distributed Generator connected at Stesen Solar Hibrid
Tanjung Labian, Lahad Datu Sabah
4
1.3 Single Line diagram of Tanjung Laian Lahad Datu 5
1.4 Sabah Map: Location of Tanjung Labian Lahad Datu,
Sabah
7
2.1 Rural Electrification : Tanjung Labian Lahad Datu,
Sabah
11
2.2 Reciprocating engines 12
2.3 Microturbine 13
2.4 Industrial Combustion turbine 14
2.5 Photovoltaic cell, module and array 15
2.6 Solar panel farm 16
2.7 Fuel Cells 17
2.8 Wind turbines 18
2.9 Example of Hybrid system for distributed generator
connected to distribution line
19
2.10 A sample of micro grid application 20
xi
2.11 (a) Radial Structure (b) Loop Structure (c) Meshed
Structure
21
2.12 Sample of Distribution system with Radial Structure 22
3.1 Methodology approach using flow chart 27
3.2 Solar radiation typical data 29
3.3 Annually Solar irradiation 30
3.4 Hybrid System 30
3.5 Symbol of solar cell in SimElectronics 31
3.6 Equivalent circuit of the solar cell 31
3.7 Standalone Photovoltaic as a Distributed Generator 32
3.8 Showing battery block 33
3.9 Showing a thevenin equivalent battery model 34
3.10 Battery as a Distributed Generator 34
3.11 Complete Diagram of Fuel Engine as Distributed
Generator
35
4.1 Tanjung Labian Distribution Network Diagram 39
4.2 Weekdays versus weekend load characteristic 40
4.3 The output waveform of Photovoltaic system 41
4.4 The three phase output voltage inverter after filtering
of all phases
41
4.5 The output waveform of Battery system 42
4.6 The output waveform of Voltage 42
4.7 The output waveform for current 43
4.8 Generator Usage 44
xii
4.9 Irradiation (Solar Usage) 44
4.10 Battery Storage usage 45
4.11 Operation system on 14th
March 2014 45
xiii
LIST OF SYMBOLS AND ABBREVIATIONS
UTHM - Universiti Tun Hussein Onn Malaysia
kW - KiloWatt
km - Kilometer
PV - Photovoltaic
DG - Distributed Generator
xiv
LIST OF APPENDICES
APPENDIX TITLE PAGE
A Data of 16/02/2014 (Super peak Condition) 59
B Data of 14/03/2014 (Normal Condition) 60
C Data of 30/01/2014 (weekdays-Thursday) 61
D Data of 04/01/2014 (weekends-Sunday) 62
CHAPTER 1
INTRODUCTION
1.1 Project Background
Distributed generation is a new approach in electrical industry [1] and has been
gradually increasing in the last few years and will rise even more in near future [2].
Due to high power demand, Utility such as Sabah Electricity Sdn Bhd
(SESB), Tenaga Nasional Berhad (TNB) and Sarawak Energy Berhad (SEB) are
continuously planning the expansion of the electrical networks. One of the methods
used for the expansion of electrical networks is connecting distributed generator in
the distribution system [3].
Distributed Generators is defined as a small-scale generation unit connected
at or near the customer load. The technologies for Distributed Generators are based
on reciprocating engines, photovoltaic, fuel cells, combustion gas turbines, micro
turbines and wind turbines. This technology is also known as alternative energy
system [4].
By connecting distributed generators in the distribution system, the power
demand of the system can be satisfied and also improves the reliability of the
electrical network [3].
Reliability is not a new topic in electric power industry. Yet, it has attracted
interest of professionals in the past decade due to incessant blackouts being
experienced [5].
2
In US, Distributed Generator uses as a sustainable and competitive form of
generation, not just restricted to renewable energy. In light of the recent blackout in
New York, it is proposed as a significant part of the solution to improve both security
and reliability of supply, with islanded operation of distributed generation on
microgrids a real prospect for the future. However, in Europe, it is viewed more
renewable generation, which is given priority dispatch and should be accommodated
where possible [6].
Most independent Distributed Generator such as photovoltaic (PV) as a
generator, weak in stability and sustain the power supply since the source are mostly
dependent on weather condition. Thus, a hybrid Distributed Generator is a solution.
It is more practical and stable since it is based on more than one energy source.
Besides, this hybrid system is suitable to use in remote areas with no access to utility
grid.
In this project, Hybrid Distributed generators installed at Station Solar Hybrid
Tanjung Labian, Lahad Datu Sabah will be explored. Construction of this project
started on October 2011 and the system commissioning on December 2012. This
Station is not connected to an integrated power network. The networks which are not
connected power network constitute an isolated power system. The network currently
supplies 24 hour electricity to 681 household. Figure 1.1 showing rural electrification
using distributed generator for highlighted village.
Figure 1.1
For this station, a hybrid Distributed Generator system development using
solar photovoltaic (PV) combined with fuel generator and
used to serve the village. Reliability of the system can be examined by using
development software called MATLAB/SIMULINK program where this program
will show the reliability impact of Distributed Generator. Figure 1.2 show
connection of the Distributed Generator install at Station Solar Hybrid Tanjung
Labian. The single line diagram of distribution system
Figure 1.1: Rural Electrification : Tanjung Labian Lahad Datu, Sabah
For this station, a hybrid Distributed Generator system development using
solar photovoltaic (PV) combined with fuel generator and battery storage systems
used to serve the village. Reliability of the system can be examined by using
development software called MATLAB/SIMULINK program where this program
will show the reliability impact of Distributed Generator. Figure 1.2 show
nection of the Distributed Generator install at Station Solar Hybrid Tanjung
Labian. The single line diagram of distribution system is shown in Figure 1.3.
3
: Rural Electrification : Tanjung Labian Lahad Datu, Sabah
For this station, a hybrid Distributed Generator system development using
battery storage systems
used to serve the village. Reliability of the system can be examined by using
development software called MATLAB/SIMULINK program where this program
will show the reliability impact of Distributed Generator. Figure 1.2 shows the
nection of the Distributed Generator install at Station Solar Hybrid Tanjung
shown in Figure 1.3.
4
Figure 1.2: Distributed Generator connected at Station Solar Hybrid Tanjung Labian,
Lahad Datu, Sabah
5
Figure 1.3: Single Line diagram of Tanjung Labian Lahad Datu, Sabah
6
1.2 Problem Statements
Nowadays, the electric power industry is facing huge changes with respect to
structure, function, and regulation [3]. The use of distributed generators within
distribution network has drawn attention due to several advantages that small scale
generation can potentially provide to power utilities. The distributed generation has
created a new way for the electric power generation. [3].
The electric power generation that is integrated within the distribution system
is called distribution generation [3]. It is a new approach in electrical industry [1]. In
order to achieve both reliability cost and worth requirement to the company, a study
has been done to select a best possible location for distributed generators.
Thus, a lot of things need to be considered for installing distributed in
distribution system such as impact on power flow, voltages, and reliability indices,
which could be positive or negative [3]. Therefore, maintaining a reliable power
supply is a very important issue for power system design and operation. At planning
stage they faced by difficult problem of deciding how far they are justified in
increasing the investment on their facilities to improve service reliability [6].
Electric demands from rural areas such as Gugusan Tanjung Labian Lahad
Datu Sabah attract Government Malaysia to expand the electrical network to that
area. Thus, Government appoint the consultant to make the survey on how the
electricity can be bring in to the proposed location. Tanjung Labian is situated
between 5° and 10° in North Latitude and 119° and 14° in East Longitude. Figure 1.4
indicates the location of Tanjung Labian Lahad Datu Sabah.
Figure 1.4: Sabah Map
Time constrain versus high demand bring the system are not
planned and dispatch since this is direct negotiation project between Contractor and
Government Malaysia.
is taken as a case study. Estimates of the Statio
resource and actual system data are employed to assess the impact of Distributed
Generated connection.
.
Figure 1.4: Sabah Map: Location of Tanjung Labian Lahad Datu, Sabah
Time constrain versus high demand bring the system are not
planned and dispatch since this is direct negotiation project between Contractor and
Government Malaysia. Distributed Generation install in Tanjung Labian Lahad D
se study. Estimates of the Station Tanjung Labian
resource and actual system data are employed to assess the impact of Distributed
Generated connection.
7
: Location of Tanjung Labian Lahad Datu, Sabah
Time constrain versus high demand bring the system are not centrally
planned and dispatch since this is direct negotiation project between Contractor and
tributed Generation install in Tanjung Labian Lahad Datu
n Tanjung Labian renewable energy
resource and actual system data are employed to assess the impact of Distributed
8
1.3 Project Objectives
General aim of this project is to evaluate power system reliability improvement using
Distributed Generators installed in Station Solar Hybird Tanjung Labian, Lahad
Datu, Sabah
The objectives of this project are:
1. To measure the characteristic such as Generator mode, Photovoltaic mode
and battery mode during normal and super peak condition of Distributed
Generator.
2. To investigate reliability on Station Solar Hybrid, Tanjung Labian by
analyze the performance of existing Station Solar Hybrid, Tanjung Labian.
3. To perform reliability assessment on a distribution system circuit based on
different location of Distributed Generator.
4. To suggest possible location of Distributed Generator for highly distribution
system in Tanjung Labian.
9
1.4 Project Scope
The Scopes of this project are:
1. The study will be conducted at Station Solar Hybrid Tanjung Labian Lahad Datu,
Sabah.
2. The Capacity Electric Power Installed at Station Solar Hybrid Tanjung Labian
Lahad Datu to be investigate
(i) Engines Diesel installed Two (2) unit 500KVA
One (1) unit 350kVA
(ii) Fuel Cell or Battery installed Capacity 4320kWh
(iii) Inverter System installed
900kW Bi-Directional Inverter
750kW ‘Inverter & Control System’
(iv) Photovoltaic Panel installed Capacity 1.2MW
3. Village Coverage and Station Solar Hybrid Tanjung Labian Lahad Datu Sabah as
a Measurement.
No Village Name No of Houses Load Demand
(kW)
1 Kg. Tg. Labian 175 197
2 Kg. Tg. Batu 125 140
3&4 Kg. Tanagian dan Kg. Bahagia 122 137
5 Kg. Sg. Bilis 101 114
6&7 Kg.Lok Sembuang dan Lok Buani 158 178
Total 681 766
CHAPTER 2
LITERATURE REVIEW
2.1 Introduction
In this chapter, the operation or method of the Distribution system using Distributed
generator will be revealed so that this project could be understood easily.
2.2 Theories
Figure 2.1 shows the block diagram or engine of Rural Electrification for Tanjung
Labian Lahad Datu, Sabah. It was made up of three main parts which are Distributed
Generator, Operational Factor and Software. The Distributed Generator used to
produce any electric power to the consumer of Tanjung Labian. Once electric power
produce, a lot of Operational Factor need to consider and a research using
MATLAB/SIMULINK software and one year data obtain from the station used to
get the reliability analysis of the system as the Distributed Generator installed.
11
Rural Electrification:
Tanjung Labian , Lahad Datu
Sabah
Distributed Generator:
√ Batery
√ Photovoltaics
√ Reciprocating engines
Operational Factor:
√ Power Quality
√ Reliability
Software:
√ MATLAB/SIMULINK
Figure 2.1: Rural Electrification : Tanjung Labian Lahad Datu, Sabah
2.2.1 Distributed Generations
Distributed generation (DG) is currently being used by some customers to provide
some or all of their electricity needs. There are many different potential applications
for Distributed Generators technologies. For example, some customers use
Distributed Generators to reduce demand charges imposed by their electric utility,
while others use it to provide primary power or reduce environmental emissions.
Distributed Generators can also be used by electric utilities to enhance their
distribution systems. Several energy sources drive distributed generators including:
2.2.1.1 Reciprocating engines
This Distributed Generators technology was developed more than a century ago, and
is still widely utilized in a broad array of applications. The engines range in size from
less than 5 to over 5,000 kW, and use diesel, natural gas, or waste gas as their fuel
source. Development efforts remain focused on improving efficiency and on
reducing emission levels. Reciprocating engines are being used primarily for backup
12
power, peaking power, and in cogeneration applications [7]. Figure 2.2 showing the
example of Reciprocating engines. The strengths and weaknesses of reciprocating
engines have been listed in Table 2.1[14].
Figure 2.2: Reciprocating engines
Table 2.1: Strengths and weaknesses of reciprocating engines
13
2.2.1.2 Microturbines
A new and emerging technology, microturbines are currently only available from a
few manufacturers. Other manufacturers are looking to enter this emerging market,
with models ranging from 30 to 200 kW. Microturbines promise low emission levels,
but the units are currently relatively expensive. Obtaining reasonable costs and
demonstrating reliability will be major hurdles for manufacturers. Microturbines are
just entering the marketplace, and most installations are for the purpose of testing the
technology [7]. Figure 2.3 presenting a Microturbine. The strengths and weaknesses
of Microturbines have been listed in Table 2.2 [14].
Figure 2.3: Microturbine
Table2.2: Strengths and weakness of microturbines
14
2.2.1.3 Industrial combustion turbines
A mature technology, combustion turbines range from 1 MW to over 5 MW. They
have low capital cost, low emission levels, but also usually low electric efficiency
ratings. Development efforts are focused on increasing efficiency levels for this
widely available technology. Industrial combustion turbines are being used primarily
for peaking power and in cogeneration applications [7]. Figure 2.4 showing an
Industrial combustion turbine. The strengths and weaknesses of Industrial
Combustion Turbines have been listed in Table 2.3[14].
Figure 2.4: Industrial Combustion turbine
Table 2.3: Strengths and weakness of combustion turbines
15
2.2.1.4 Photovoltaic
Commonly known as solar panels, photovoltaic (PV) panels are widely available for
both commercial and domestic use [7]. PV power system converts sunlight into
electricity [8]. Materials that are used for photovoltaic are mono-crystalline silicon,
polycrystalline silicon, microcrystalline sili-con, cadmium telluride and copper
indium selenide [9] [10].
The basic unit of a photovoltaic power system is the PV cell, where cells may be
grouped to form panels or modules. The panels then can be grouped to form large
photovoltaic array that connected in series or parallel, as shown in Figure 2.5[8] [11].
Panels range from less than 5 kW and units connected in parallel increase the current
and connected in series provide a greater output voltage to form a system of any size.
The output characteristics of PV module depends on the solar irradiance, the cell
temperature and output volt-age of PV module [9] [12].They produce no emissions,
and require minimal maintenance. However, they can be quite costly. Less expensive
components and advancements in the manufacturing process are required to
eliminate the economic barriers now impeding wide-spread use of PV systems.
Photovoltaic are currently being used primarily in remote locations without grid
connections and also to generate green power [7]. Figure 2.6 shows a sample of Solar
panel farm. The strengths and weaknesses of Photovoltaic have been listed in Table
2.4 [14].
Figure 2.5: Photovoltaic cell, module and array
16
Figure 2.6: Solar panel farm
Table 2.4 : Strengths and weakness of Photovoltaic
2.2.1.5 Fuel Cells
Fuel cells are not only very efficient but also have very low emission levels. A fuel
cell operates like a battery. It supplies electricity by combining hydrogen and oxygen
electrochemically without combustion. However, while the battery is a storage
device for energy that is eventually used up and/or must be recharged, the fuel cell is
permanently fed with fuel and an oxidant, so that the electrical power generation
continues [7]. Figure 2.7 showing Fuel cell. The strengths and weaknesses of Fuel
cell have been listed in Table 2.5 [14].
17
Figure 2.7: Fuel cells
Table 2.5: Strengths and weakness of fuel cell type
2.2.1.6 Wind turbine systems
Wind turbines are currently available from many manufacturers and range in size
from less than 5 to over 1,000 kW. They provide a relatively inexpensive (compared
to other renewable) way to produce electricity, but as they rely upon the variable and
somewhat unpredictable wind, are unsuitable for continuous power needs.
Development efforts look to pair wind turbines with battery storage systems that can
provide power in those times when the turbine is not turning. Wind turbines are
being used primarily in remote locations not connected to the grid and by energy
18
companies to provide green power [7]. Figure 2.8 below showing wind turbines. The
strengths and weaknesses of Wind Turbine System have been listed in Table 2.6
[14].
Figure 2.8: Wind Turbines
Table 2.6: Strengths and weakness of Wind Turbines
2.2.1.7 Hybrid Systems
A hybrid system is defined as the combination of two or more types of electricity
generation system [8]. A combination energy sources is more effective as compared
to single source system in terms of cost, efficiency and reliability. Properly chosen
combination of renewable power sources will considerably reduce the need and used
for fossil fuel leading to an increase in the sustainability of the power supply [13].
19
This Hybrid system is developed to improve on the performance of an individual
Distributed Generators [7]. Photovoltaic combine with Reciprocating engines and
battery to provide backup supply. This is to ensure a perfect balance exist between
power demand and generated power [8]. Figure 2.9 shows example of Hybrid system
for distributed generator connected to distribution line [14].
Figure 2.9: example of Hybrid system for distributed generator connected to
distribution line.
The advantages of using Distributed Generator based hybrid systems are it increased
the reliability of the hybrid system because it is based on more than one electricity
generation source. Moreover, the hybrid system is suitable to use in remote areas or
isolated locality with no access to utility grid [8] [15] [16].
However, there is also disadvantage of using hybrid systems such as in most cases
the system is over- sized because it contains different types of power generation
20
system [8]. The strengths and weaknesses of hybrid system have been listed in Table
2.7 and a sample of micro grid application in Figure 2.10 [14].
Table 2.7: The strengths and weaknesses of Hybrid system
Figure 2.10: A sample of micro grid application
Distribution Generator rapidly used in rural electrification, it is important to study the
impact on the distribution system operation. The installation of Distributed Generator
may increases the complexity of the system and impacts to the power flow and
voltage condition in the system. Therefore, it is important for the planner of the
electric system comprises of several factors such as type of Distributed Generator
installed, Capacity and number of Distribution Generator units and the Distribution
21
Generator installation location. With depend on this factors, the Distributed
Generator installed can be either positive or negative to the system [17].
For example, when the Distributed Generator is attached downstream, it can confuse
the voltage regulator by setting a voltage lower than the required value. Thus, proper
coordinate installing Distributed Generator can improve the voltage profile of the
system and also improve the power system stability. Beside, placing the Distributed
Generator at optimal location can reduce the losses on the feeder [17].
2.2.2 Electric Power System Structure
Distribution system’ design depending on customer load, cost of installation and
operational and maintenance operation. Generally there are three electric power
structure can be illustrious. There are Radial, Loop and meshed structure. Figure 2.11
below showing (a) Radial Structure (b) Loop structure (c) Meshed Structure [18].
(a) (b) (c)
Figure 2.11 (a) Radial structure (b) Loop structure (c) Meshed Structure
From Figure above, it shows that the radial structure is the simplest structure. Each
substation and customer is connected via a single line to a central point or supply.
The radial power systems are designed for one-way power flow. The complete repair
time if there is any cable or line failure can be considered as a drawback. This
22
structure can be improved by using loop structure. Whereby all substation or
customers are connected via double circuit or line. During a disturbance, the faulted
section can be isolated and the loop is split-up into two parts. The faulted section can
be energizing back once the faulted section recover. For this case, the repair time is
considered the time needed for fault localization and necessary switching actions.
For meshed structure, all substation and consumers are connected via more than two
lines or cable. This design can reduce the losses and also improve the voltage profile
along the feeders [19]. Figure 2.12 showing a sample of distribution system with
radial structure [14].
Figure 2.12: sample of Distribution System with Radial Structure
2.2.3 Operational Factor
Operational Factor is the main technical issues for Distributed Generator connection
to be investigate. Distributed Generator connection related to reliability and quality
of the supply. It involves the operation protocols for connection and disconnection
from the inverter. Protection issues also take part into the operational factor.
Protection arises for both Distributed Generator equipment and network equipment.
It depends on the type of generator and the characteristics of the network. While
network protection issues depending on the type and location of the Distributed
Generator install and network characteristic. Thus protection design requires good
23
interaction between distributed Generator developer and network provider during the
design process.
2.2.3.4 Power Quality
Distributed Generator can have a considerable impact on power quality within the
distribution system. The definition of power quality given in IEEE dictionary in
IEEE std 1100 define as the concept of powering and grounding sensitive equipment
in a matter that is suitable to the operation of that equipment [7].
Some form of Distributed Generator may employ power electronic converters
to interface the system. This can alter the harmonic impedance of the system and care
must be taken at the design and planning stage. In particular, there is the potential for
resonances between capacitors or cables, which may have a detrimental effect on the
operation of the generator [6].
In this research, power quality performance between Solar with Battery mode
and Battery and Generator Diesel mode will be investigate. Impact of the power
quality showed when the feeders are fully loaded during day time and night time.
2.2.3.5 Reliability
Reliability has always been an important issue for system planners and operators.
Reliability can be measured by the indices SAIDI (System Average Interruption
Duration Index), SAIFI (System Average Interruption Frequency Index), which
measure the average frequency and duration of supply interruptions respectively [6].
It is common practices in the electric industry to used the standard IEEE reliably
indices [2][20].
24
SAIDI (System Average Interruption Duration Index) is the average
interruption duration for those customers interrupted during a year. It is determined
by dividing the sum of all customer interruption duration by the number of customers
experiencing one or more interruptions over a one-year period [2].
SAIDI = (2.1)
CAIDI (Customer Average Interruption Duration Index) is calculated by
dividing the sum of total customer interruption durations per year and the total
number of customer affected.
CAIDI = (2.2)
The location for the placement of Distributed Generator is of key importance.
Besides, proper coordination distributed generation can have a positive impact on the
system [17].
In this research, Voltage (V), Current (I), Real power flow (P), Reactive
power flow (Q), frequency (f) is used to calculate reliability indices in normal and
super peak distribution network situation. The result will shows the reliability indices
were highly sensitive to location and number of Distributed Generated install for
distribution network for Gugusan Tanjung Labian Consumer.
Total number of customers’ interruption
Sum of customer interruption durations
Total number of Customers
Sum of Customer Interruption Durations
56
REFERENCES
1. Ackermann, T., Andersson, G. And Soder, L. Distributed generation : a
definition. Electric Power System Research . 2001. 57. pp. 195-204.
2. Pal, J. S. V. and Ghosh, S. Improvement in Reliability Analysis Using
Distributed Generators. International Jurnal of Scientific & Engineering
Research. 2012. Volume 3, Issue 5.
3. Chandrashekar, S. , Prasad, R. , P.V.N and Laxmi, A.J,. Reliability
Improvement of Distribution System : A Hibrid Approach Based on GA
and NN. International Journal of Soft Computing and Engineering ISSN :
2231-2307, .2013. Volume 2, Issue 6.
4. Waseem, I., Pipattanasomporn, M. and Rahman, S. Reliability Benefits of
Distributed Generation as a Backup Source.
5. Adebayo, I.G, Olaomi, A.A. and Buraimoh, E.O..Power System Realibility
Analysis Incorporating Distributed Generator. International Journal
Science & Engineering Research . 2013. Volume 4, Issue 3.
6. Keane, A. Integration of Distributed Generation. Dublin University
Collage, Dublin; 2007
7. Angelopoulos, K. Integration of Distributed Generation in Low Voltage
Networks, Power Quality and Economics. University of Strathclyde in
Glasgow; 2004
57
8. Ng, S. H. Hybrid Wind znd Photovoltaic (Pv) Power Generation System
With Superconducting Magnetic Energy Storage (Smes) Universiti
Teknologi Malaysia; 2012
9. Ghosh, S. K., Shawon, M.H., Rahman A., Abdullah,
R. Modeling of PV
Array and Analysis of Different Parameters International Journal of
Advancements in Research & Technology, . 2013. Volume 2, Issue 5.
10. Narkhede, S, Rajpritam, “Modeling of Photovoltaic Array”, pp. 7-21.
11. SECO, Introduction to Photovoltaic System, T. S. E. C. O. (SECO), Ed.,
ed. Texas, pp. 1-4.
12. Patel, J., Sharma, G., Modeling And Simulation Of Solar Photovoltaic
Module Using MATLAB / Simulink
13. Husain, M.S. , Tariq, A. Modeling of a standalone Wind-PV Hybrid
generation system using MATLAB/SIMULINK and its performance
analysis International Journal of Scientific & Engineering Research,
.2013. Volume 4, Issue11.
14. Gezer, D. A Proposed Rule For The Interconnection Of Distributed
Generation And Its Economic Justification, A Thesis Submitted To The
Graduate School Of Natural And Applied Sciences Of Middle East
Technical University; 2009
15. Rolan, A., Luna, A., Vazquez, G., Aguilar, D., Azevedo, G., Modeling of a
Variable Speed Wind Turbine with a Permanent Magnet Synchronous
Generator. IEEE International Symposium on Industrial Electronics Seoul
Olympic Parktel, Seoul, Korea .2009.July 5-8.
16. Polinder H., de Haan S. W. H., Dubois M. R., Slootweg J., Basic
Operation Principles and Electrical Conversion Systems of Wind Turbines,
NORPIE / 2004, Nordic Workshop on Power and Industrial Electronics,
2004.Paper 069
58
17. Waseem, I Impact of Distributed Generation on the Residential
Distribution Network Operation. Virginia : Virginia Polytechnic Institute
and State University ; 2008
18. Coster, E. J. Distribution Grid Operation Including Distributed
GenerationImpact on grid protection and the consequences of fault ride-
through behaviour. 2010
19. Adebayo, I. G., Olaomi, A. A., and Buraimoh, E. O. Power System
Reliability Analysis Incorporating Distribution Generator, International
Journal of Scientific & Engineering Research .2013. Volume 4, Issue3,
March.
20. Zhu, D., A Thesis on Power System Reliability Analysis with Distributed
Generators , Virginia Polytechnic Institute and State University.
21. O.Beucher and M.Weeks, Introduction to Matlab & Simulink, A project
Approach, Third Edition, Infinity Science Press LLC, Hingham
Massachusetts, New Delhi.
22. PSCAD Circuit Development,
descargas.indielec.com/web/Circuit_Development.pdf
23. Photovoltaic Software. 2014. From http://photovoltaic-
software.com/professional.php
24. VandanaKhanna, Bijoy, K. D., Dinesh B. MATLAB/SIMELECTRONICS
Models Based Study of Solar Cells International Journal Of Renewable
Energy Research Department of Electrical, Electronics & Communication
Engineering, ITM University. 2013
25. Pragya, N., Sayan, D. Feasibility Study of 1 MW Standalone Hybrid
Energy System, For Technical Institutes Department of Electrical
Engineering, Netaji Subhash Engineering College, Kolkata, India; 2012
26. Abdulrahman, Y., Kalbat , PSCAD simulation of Grid-Tied Photovoltaic
Systems and Total Harmonic Distortion Analysis.