digitalplant case studies – part 2. power – owner operators

12
DigitalPlant Case Studies – Part 2

Upload: brent-rayner

Post on 31-Mar-2015

220 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: DigitalPlant Case Studies – Part 2. Power – Owner Operators

DigitalPlant

Case Studies – Part 2

Page 2: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Power – Owner Operators

Page 3: DigitalPlant Case Studies – Part 2. Power – Owner Operators

KOPEC – Korean Fossil and Nuclear

• Shin Kori 1&2 Nuclear Power Plant is located in the southeastern coast of the Korean Peninsula.

• The power plant is a two-loop light-water moderated and cooled pressurized water reactor system rated at 2,825MWt, and an electrical output of 1,000MWt.

• The construction permission of the project was approved on April 1 2002. The completion of Shin Kori Unit 2 will be October 31, 2011.

• The Approximate size of each reactor is: − 3,300 Equipment Items− 250,000 feet of piping − 5,400 piping supports in each unit.

• The Engineering and Construction management budget for KOPEC (A/E) was approximately $200 million dollars.

• And 3D modeling technique is used A/E design for the first time for Kopec on a Nuclear Power Plant

• New techniques will be applied for construction, operation and maintenance to reduce construction and check out time.

Page 4: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Foster Wheeler – United Kingom• Two new CFB power plants, the largest Circulating Fluidized Beds (CFB’s) in the

world were installed at the existing JEA Northside Station Units 1 & 2 to repower existing steam turbines with more efficient and cleaner technology.

• Each CFB was designed to burn solid fuels including a range of petroleum coke as primary fuel and a diverse range of coals; each CFB is capable of combusting 100% petroleum coke or 100% coal or any proportionate combination of both.

• Each unit consists of two CFB Boilers exhausting through independent dry scrubbers and fabric filters to a common stack.

• Foster Wheeler’s scope of supply included the critical piping to interconnect the new boilers to the existing steam turbines, a limestone preparation system, ash handling system and supply of the fuel crushers. Each boiler is designed to produce 1,994,000 lbs/hr of steam at 2,635 psia.

• The CFB Boiler technology in combination with the flue gas scrubbers will allow JEA to meet their commitment to reduce Sulfur Dioxide (SO2) and nitric oxide and nitrogen dioxide, (collectively referred to as NOx) emissions from the plant by 10%.

• Foster Wheeler’s scope of work included; assessment of existing plant equipment and systems, environmental permitting, preliminary design and engineering, extensive plant performance calculations, and execution of the project under a lump sum turnkey contract. The contract overall schedule from Notice to Proceed to Substantial Completion was 33 months and 36 months respectively on the first and second unit.

Page 5: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Intergen - United Kingdom

• Rocksavage & Coryton Power Plants – United Kingdom• The project goal was to enable plant data to be sourced in the

simplest and most expedient way by both office based staff and plant based staff in Operations and Maintenance.

• We needed to interact with the information held in ProjectWise to source drawings and information, and also to create an accurate tag database for access to information based on the plant tags of items such as equipment, Valves, Instruments etc.

• In short, some staff know the plant information by document name and some need to find information based on the item's tag name and number.

Page 6: DigitalPlant Case Studies – Part 2. Power – Owner Operators

2 SAL Yoke Systems (SYS) for Bohai Bay, China

• For CFD11, the FPSO and SPM are owned by China Offshore Oil Bohai Corporation (COOBC) and operated by Kerr-McGee China Petroleum Limited, whereas BZ25 The FPSO and SPM are owned by China Offshore Oil Bohai Corporation (COOBC) and operated by CNOOC/Chevron Texaco.

• The SYS is of the Single Point Mooring (SPM) type. The purpose of the SYS is to provide the fixed weather vaning mooring for the FPSO, and to provide the interface between the subsea pipelines and cables allowing the transfer of well fluids from, and injection water and HV power to the wellhead platforms.

• The FPSO’s are new-build of approximately 200,000 DWT vessel. The mooring system and vessel of both systems are designed to withstand the 100-year typhoon of 5.0 meter significant wave height. The water depth is approximately 24m for CFD11 and 18m for BZ25. The field life of both projects is 25 years.

Page 7: DigitalPlant Case Studies – Part 2. Power – Owner Operators

WorleyParsons Services Pty Ltd Victoria Platform Development • Victoria Platform DevelopmentClient: Apache EnergyOverview:Apache has a number of marginal oil

fields with recoverable reserves of between 2~4mbbs. In order to exploit these reserves a cost effective Wellhead Facility was developed by WorleyParsons to ensure the projects remained viable.

• The entire project was designed and fabricated within Western Australia and has set a benchmark for the exploitation of marginal Oil and Gas fields. Both the substructure and deck were fabricated in Kwinana and transported to Dampier by road, then loaded onto a cargo barge for shipment to the offshore site for installation.

• The project was completed within a near impossible design and construct schedule of ten weeks. In order to meet the schedule, WorleyParsons entered into an alliance arrangement with local fabricator Ausclad to provide the detailed engineering, piping design and fabrication support for the construction of the minimum facilities platform.

• The Victoria Development is a further extension of the Simpson and Gibson pipeline, extending south from Apache’s hub on Varanus Island, off the north-west coast of Western Australia. The design and fabrication schedule was linked in to the exploration-drilling program, which meant minimum time for design. The design team worked solidly for 10 weeks from mid June to the end of August to achieve AFC issue of all documentation.

• The fast track nature of the project meant that drawings were progressively issued to the fabricator, who successfully completed fabrication within time and delivered the jacket and topsides to Dampier wharf for loadout. Engineering

Page 8: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Engineering Companies

Page 9: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Warehouse

FacilityManager

ReportWeb FacilityManager

ClassManager

PipingManager

P&IDs

DIGITALPLANT (eWarehouse)

CARDS+INTOOLS DashboardPortal

FM, CM Reports

PEGSAXSYS

DDEDOCUMENTUMIPMS CMS

Central SchemaObject Engineering.

Deliverables

Ma

jor

Equ

ipm

ent

No

zzle

s a

nd T

P’s

Lin

es

Inst

rum

ents

eWa

reho

use

ID

’s

Ma

jor

Equ

ipm

ent

No

zzle

s a

nd T

P’s

Lin

es

Inst

rum

ents

eWa

reho

use

ID

’s

Inst

rum

ent T

ags

Lin

es

Inst

rum

ent

Cab

les

Fire

an

d G

as

Ta

gs

Loop

s

Te

leco

m D

evi

ces

Ma

nufa

ctu

rers

Cab

le C

ode

s

Ele

ctric

al C

abl

es

Ele

ctric

al M

oto

rs

Ele

ctric

al E

quip

Inst

rum

ent

Cab

les

Fro

m/T

o E

quip

men

t

Ta

gged

Ite

m D

ata

Ob

j. E

ng.

Da

ta

Do

c/T

ag

Ref

ere

nce

s

Lin

es

Spo

ols

Are

a P

ipe

s an

d S

poo

ls

Are

a P

ipe

Sta

tus

Equ

ip S

tatu

s

Ob

ject

His

tory

Are

a P

ipe

Sta

tus

Equ

ip S

tatu

s

Ob

ject

His

tory

Are

a P

ipe

Sta

tus

Equ

ip S

tatu

s

Ob

ject

His

tory

Do

cum

en

t Lin

ks

Do

cum

en

ts

Ta

g A

wa

rd D

ata

Re

lea

sed

Ta

gs

Ob

ject

s and

Pro

p

Warehouse

FacilityManager

ReportWeb FacilityManager

ClassManager

PipingManager

P&IDs

DIGITALPLANT (eWarehouse)

CARDS+INTOOLS DashboardPortal

FM, CM Reports

PEGSAXSYS

DDEDOCUMENTUMIPMS CMS

Central SchemaObject Engineering.

Deliverables

Ma

jor

Equ

ipm

ent

Ma

jor

Equ

ipm

ent

No

zzle

s a

nd T

P’s

No

zzle

s a

nd T

P’s

Lin

es

Lin

es

Inst

rum

ents

Inst

rum

ents

eWa

reho

use

ID

’seW

are

hou

se I

D’s

Ma

jor

Equ

ipm

ent

Ma

jor

Equ

ipm

ent

No

zzle

s a

nd T

P’s

No

zzle

s a

nd T

P’s

Lin

es

Lin

es

Inst

rum

ents

Inst

rum

ents

eWa

reho

use

ID

’seW

are

hou

se I

D’s

Inst

rum

ent T

ags

Inst

rum

ent T

ags

Lin

es

Lin

es

Inst

rum

ent

Cab

les

Fire

an

d G

as

Ta

gs

Loop

sLo

op

s

Te

leco

m D

evi

ces

Te

leco

m D

evi

ces

Ma

nufa

ctu

rers

Ma

nufa

ctu

rers

Cab

le C

ode

sC

able

Cod

es

Ele

ctric

al C

abl

es

Ele

ctric

al C

abl

es

Ele

ctric

al M

oto

rsE

lect

rica

l Mo

tors

Ele

ctric

al E

quip

Ele

ctric

al E

quip

Inst

rum

ent

Cab

les

Fro

m/T

o E

quip

men

t

Ta

gged

Ite

m D

ata

Ob

j. E

ng.

Da

ta

Do

c/T

ag

Ref

ere

nce

s

Lin

es

Lin

es

Spo

ols

Spo

ols

Are

a P

ipe

s an

d S

poo

ls

Are

a P

ipe

Sta

tus

Are

a P

ipe

Sta

tus

Equ

ip S

tatu

sE

quip

Sta

tus

Ob

ject

His

tory

Ob

ject

His

tory

Are

a P

ipe

Sta

tus

Are

a P

ipe

Sta

tus

Equ

ip S

tatu

sE

quip

Sta

tus

Ob

ject

His

tory

Ob

ject

His

tory

Are

a P

ipe

Sta

tus

Are

a P

ipe

Sta

tus

Equ

ip S

tatu

sE

quip

Sta

tus

Ob

ject

His

tory

Ob

ject

His

tory

Do

cum

en

t Lin

ksD

ocu

men

t Lin

ks

Do

cum

en

tsD

ocu

men

ts

Ta

g A

wa

rd D

ata

Ta

g A

wa

rd D

ata

Re

lea

sed

Ta

gsR

ele

ase

d T

ags

Ob

ject

s and

Pro

p

Concurrent Engineering with State Based Components

Access Control at the Component Level – Status based management

Page 10: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Bechtel – Waste Treatment Facility• Department of Energy – Waste Treatment Plant• Bechtel - $14.5 Billion

• Bentley DigitalPlant - MCS Oracle Database− 25gb in size− 844 Equipment components− 340,000 piping components− 52,000 pipe supports− 15,000 Conduit components− 5,000 Electrical Tray components

• Bentley DigitalPlant - ProjectWise Database− 131gb in size− Over 100 existing workflows− Over 200,000 files stored (including non-engineering deliverables)

Page 11: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Benefits Summary – Coopers & Lybrand

10-30% Concept development time15-28% Engineering hours30% Engineering productivity10-30% Quality cost/change management time15-20% Commissioning engineering hours60% Hand-over/start-up costs10-20% IT costs10-20% Operational costs

Page 12: DigitalPlant Case Studies – Part 2. Power – Owner Operators

Proven Benefits of DigitalPlant

• Proven• Reduction in handover costs - $1m-$4m /project• Reduction in spare parts costs – 20%• Saving in total engineering hours – 15%• Elimination in commissioning delays due to lack of information

• Estimated• Reduction in TCO - 1-5% • Reduced number of unscheduled shutdowns• Savings of 20% maintenance labour costs• Savings of 20% project material costs