design report a water generator water - calvin · pdf filei executive summary the goal of this...

61
© 2012 Team 5: Water from Air, Calvin College DESIGN REPORT ATMOSPHERIC WATER GENERATOR WATER FROM AIR: TEAM 5 Ben Niewenhuis - EE Chris Shepperly - ME Ryan Van Beek - ME Eric Van Kooten ME 9 May 2012

Upload: hangoc

Post on 31-Jan-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

© 2012

Team 5: Water from Air, Calvin College

DESIGN REPORT

ATMOSPHERIC WATER GENERATOR

WATER FROM AIR:

TEAM 5

Ben Niewenhuis - EE

Chris Shepperly - ME

Ryan Van Beek - ME

Eric Van Kooten – ME

9 May 2012

Page 2: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

i

Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator,

a device which produces drinkable water from humid air. Special emphasis is given to energy

efficiency and compatibility with renewable energy sources.

This project is the culmination of the engineering program at Calvin College. It is conducted

within the context of a two-semester course which covers all aspects of project development and

management. The following report explores the feasibility of the proposed design as well as

specifying components of the design.

After careful research and testing, Team 5 has concluded that wet desiccation is not a practical

process for atmospheric water generation. The prototype works and is capable of producing 0.72

liters of water per day with significant potential for improvement. However, one of the metrics

used to compare this unit to comparable units is the water per unit energy. Water From Air can

produce 72.1 mL of water per kW-hr; Ecoloblue, a leading competitor, can produce 1031 mL of

per kW-hr. Given this factor of 10 difference, Team 5 has concluded that this design is

impractical for atmospheric water generation.

Page 3: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

ii

Table of Contents

Introduction ............................................................................................................................. 1 1.

1.1. Background ...................................................................................................................... 1

1.2. Team Members ................................................................................................................. 1

1.2.1. Ben Niewenhuis ........................................................................................................ 1

1.2.2. Chris Shepperly ......................................................................................................... 1

1.2.3. Ryan Van Beek ......................................................................................................... 1

1.2.4. Eric Van Kooten ....................................................................................................... 2

1.3. Problem Statement ........................................................................................................... 2

Constraints ............................................................................................................................... 2 2.

2.1. Requirements .................................................................................................................... 2

2.2. Design Objectives ............................................................................................................ 3

2.3. Deliverables ...................................................................................................................... 3

Design Norms .......................................................................................................................... 3 3.

3.1. Transparency .................................................................................................................... 4

3.2. Stewardship ...................................................................................................................... 4

3.3. Integrity ............................................................................................................................ 4

3.4. Trust ................................................................................................................................. 4

Design Evaluation.................................................................................................................... 4 4.

4.1. Dehumidification .............................................................................................................. 4

4.1.1. Refrigeration ............................................................................................................. 5

4.1.2. Pressure ..................................................................................................................... 5

4.1.3. Combination .............................................................................................................. 8

4.1.4. Wet Desiccation ........................................................................................................ 8

4.1.5. Decision .................................................................................................................. 11

4.2. Brine ............................................................................................................................... 12

4.2.1. Corrosion................................................................................................................. 12

4.2.2. Cost ......................................................................................................................... 12

4.2.3. Safety ...................................................................................................................... 13

Page 4: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

iii

4.2.4. Decision .................................................................................................................. 14

System Architecture .............................................................................................................. 14 5.

5.1. System Structure ............................................................................................................ 14

5.1.1. Frame ...................................................................................................................... 14

5.1.1. Air Blower Shelf ..................................................................................................... 15

5.1.2. Upper and Lower Shelves ....................................................................................... 15

5.2. Process ............................................................................................................................ 15

5.2.1. Airflow Loop .......................................................................................................... 16

5.2.2. Brine Loop .............................................................................................................. 17

5.2.3. Condensation Loop ................................................................................................. 20

5.1. Electronics ...................................................................................................................... 21

5.1.1. Power ...................................................................................................................... 21

5.1.2. Sensor ...................................................................................................................... 23

5.1.3. Control .................................................................................................................... 26

Prototype Operation ............................................................................................................... 26 6.

6.1. Description of Operation ................................................................................................ 26

6.1.1. Batch Process .......................................................................................................... 26

6.1.2. Manual Switches ..................................................................................................... 27

6.2. Operating Instructions .................................................................................................... 27

6.2.1. Start-Up Routine ..................................................................................................... 27

6.2.2. Shutdown Routine ................................................................................................... 28

Project Expenses .................................................................................................................... 28 7.

Testing ................................................................................................................................... 30 8.

8.1. Absorption Rate.............................................................................................................. 30

8.2. Evaporation Rate ............................................................................................................ 31

8.3. Prototype ........................................................................................................................ 32

8.3.1. Envirotronics ........................................................................................................... 32

8.3.2. Steelcase Inc............................................................................................................ 34

8.3.3. Produced Water Quality .......................................................................................... 35

8.3.4. Power Requirements ............................................................................................... 35

8.4. Control System ............................................................................................................... 36

Page 5: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

iv

8.5. Further Testing ............................................................................................................... 36

8.5.1. Envirotronics ........................................................................................................... 36

8.5.2. Steelcase Inc............................................................................................................ 37

Project Design Improvements ............................................................................................... 37 9.

9.1. Financial-Based Improvements ...................................................................................... 37

9.2. Time-Based Improvements ............................................................................................ 38

Conclusion ......................................................................................................................... 39 10.

Acknowledgements ............................................................................................................ 39 11.

Appendix ............................................................................................................................ 42 12.

12.1. Competitor Summary ................................................................................................. 42

12.2. Decision Matrix .......................................................................................................... 42

12.3. Experiment Setup ....................................................................................................... 43

12.4. Experiment Data ......................................................................................................... 44

12.5. EES Calculations for Pressure Dehumification .......................................................... 45

12.6. EES Calculations for Desiccation Model ................................................................... 46

12.7. Complete Project Expenses Table .............................................................................. 47

12.8. Capacitive Sensor Circuit Reference .......................................................................... 48

12.9. Temperature Sensor Circuit Reference ....................................................................... 50

12.10. Envirotronics Validation Certificate ........................................................................... 54

Table of Acronyms

PPFS Project Proposal Feasibility Study

AWG Atmospheric Water Generator

WHO World Health Organization

CaCl2 Calcium Chloride

WBS Work Breakdown Schedule

MDF Medium Density Fiberboard

CFM Cubic Feet per Minute

EES Engineering Equation Solver

Table of Figures

Figure 1: Dehumidification by Refrigeration Cycle ....................................................................... 5

Figure 2: Dehumidification by Pressurization ................................................................................ 6

Figure 3: Power Requirements for Pressure Dehumification. ........................................................ 8

Page 6: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

v

Figure 4: Dehumidification by Desiccation .................................................................................... 9

Figure 5: Research-Based Model .................................................................................................. 10

Figure 6: Results of the FEA analysis for the system’s frame ...................................................... 15

Figure 7: Block diagram of wet desiccation process .................................................................... 16

Figure 8: Candidate Locations for Sensor Placement ................................................................... 23

Figure 9: Humidity Sensor Circuit ................................................................................................ 24

Figure 10: Temperature Sensor Circuit......................................................................................... 25

Figure 11: Sensor Circuit Board Layout ....................................................................................... 25

Figure 12: Brine solution mass gain over time ............................................................................. 31

Figure 13: Temperature Curve for the Upper Tank ...................................................................... 32

Figure 14: Validation Graph of Envirotronics' Testing ................................................................ 34

Figure 15: Brine Concentration during Steelcase Testing ............................................................ 35

Figure 16: Experimental Setup ..................................................................................................... 43

Figure 17: EES Display for Pressure Dehumidification ............................................................... 45

Figure 18: EES Display for Desiccation Model ........................................................................... 46

Figure 19: PSpice Parametric Capacitive Sweep of Sensor Circuit ............................................. 48

Figure 20: Humidity Sensor Capacitance Response ..................................................................... 49

Figure 21: Sensor Capacitance Calculation .................................................................................. 49

Figure 22: Frequency to Relative Humidity Reference Chart ...................................................... 50

Figure 23: PSpice Voltage Sweep Simulation of Temperature Circuit ........................................ 50

Figure 24: Output Voltage vs. Ambient Temperature .................................................................. 51

Figure 25: Temperature Probe Calibration Results ...................................................................... 52

Figure 26: Temperature Circuit Calibration Mathcad Sheet (Screenshot) ................................... 53

Table of Tables

Table 1: Energy Values from Compression Condensation Base Case ........................................... 7

Table 2: Reported Nominal Operating Conditions and Performance ........................................... 10

Table 3: EES Model Results for Representative Conditions ........................................................ 11

Table 4: Salt Cost Comparisons .................................................................................................... 13

Table 5: Brine Decision Summary ................................................................................................ 14

Table 6: Component-wise Power Requirements of Prototype ...................................................... 22

Table 7: DC Power Supply Option Comparison .......................................................................... 22

Table 8: Main System Expenses. .................................................................................................. 28

Table 9: Breakdown of System Loop Expenses. .......................................................................... 29

Table 10: Summary of Design Features for Prominent Competition ........................................... 36

Table 11: Competitor Summary.................................................................................................... 42

Table 12: Desiccant Decision Matrix ........................................................................................... 42

Table 13: Recorded Project Expenses. .......................................................................................... 47

Table 14: Temperature Probe Calibration Data ............................................................................ 51

Page 7: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

1

Introduction 1.

1.1. Background

Calvin College is a Christian Liberal Arts institution located in Grand Rapids, MI. It is one of the

few Christian colleges in America that offers a full engineering major. Integrating Christian

values and the Liberal Arts into engineering, Calvin’s program has a strong reputation for

producing thoughtful and well-rounded engineers.

This senior design project is the capstone course for the Calvin Engineering program. Two

courses, Engineering 339 and 340, are coordinated around the project, covering various aspects

of project management and design.

1.2. Team Members

1.2.1. Ben Niewenhuis

Ben Niewenhuis hails from Battle Creek, Michigan, a product of St Phillip Catholic High School

and the Battle Creek Area Math and Science Center. Active as a student and an athlete, Ben was

particularly interested in the realms of math and science. He entered the Calvin College

Engineering program in the fall of 2008, and has chosen Electrical Engineering as his field of

study. He is an active leader of the Calvin Chess Club and has taken two summer research

positions; one at Calvin College concerning polystyrene recycling and the other at Carnegie

Mellon University on improvements in Monte Carlo analysis. He looks forward to continuing his

studies at the graduate level in Electrical Engineering at Carnegie Mellon University.

1.2.2. Chris Shepperly

From Battle Creek, Michigan, Chris Shepperly chose to attend Calvin and pursue an engineering

degree. At Calvin Chris chose to concentrate in mechanical engineering because of his interest in

thermodynamics and mechanics of materials. Apart from engineering Chris spent a lot of time as

a swimmer for Calvin and was the captain for two years. His current plans are to enter the

workforce as a Systems Engineer at Dematic Corp. in Grand Rapids.

1.2.3. Ryan Van Beek

Ryan Van Beek is from Lansing, Illinois, where he graduated from Illiana Christian High

School. In the fall of 2008, Ryan began attending Calvin College and upon entering into his

junior year of college, Ryan began his focused study of mechanical engineering primarily in the

fields of machine design, thermodynamics, and heat transfer. Ryan’s engineering internship

experiences have been in both the aerospace industry at Woodward and HVAC modification

industry with Trane. After graduation in December of 2012 with a B.S.E. mechanical

concentration with a business minor, Ryan plans to work as a sales engineer for Trane while

continuing to live in the Grand Rapids Area.

Page 8: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

2

1.2.4. Eric Van Kooten

Eric Van Kooten is a native of the Grand Rapids Area. He was born and raised in Kentwood,

Michigan and attended South Christian High School where he fostered his love for athletics,

being outdoors, and engineering. After South Christian Eric choose Calvin College and in order

to pursue engineering. Eric will graduate from Calvin College in January 2013 with a B.S.E.

mechanical concentration and International designation with a business minor. After Calvin, Eric

will work at Gentex and plans to utilize his international experience in industry and has a goal of

continuing his education with a dream of obtaining his doctorate and someday becoming

Professor Van Kooten.

1.3. Problem Statement

The initial problem statement for Team 5 was posed by Michael Harris, Executive Director of

the Calvin College Enterprise Center. The original statement was as follows:

“Design and develop a prototype system for removing clean (potable) drinking water from air

using a wind turbine. Use a wind turbine to generate electricity; use electricity to cool air (or

increase pressure) resulting in condensation of water; capture water vapor from air that

condenses into water. Self-contained system (no external connections required). Basic human

need (especially valuable for remote areas).”

Upon adoption of this project, Team 5 adapted the problem statement to better reflect the

realities of atmospheric water generation. Atmospheric water generators already exist as products

on the market; thus there is a need for this design to differentiate itself, through some innovation

or better utility in order to justify the expenditure of time and money on this project.

Furthermore, atmospheric water generation is an energy intensive process. Existing

implementations aren’t capable of producing significant amounts of water at a decent price. In

light of these considerations, Team 5 formulated the following problem statement:

“To design and prototype a system for obtaining clean drinking water from air, focusing on

improvements in the energy requirement with the end goal of powering the device with

renewable energy.”

Constraints 2.

2.1. Requirements

When designing the atmospheric water generator Team 5 identified three requirements they

needed meet to ensure that the final project would effectively fulfill its intended purpose.

Potability of Water - Water produced by the design must conform to the World Health

Organization (WHO) drinking water quality standards.

Simplicity of Use - Design must be operable by persons of limited technical experience.

Safety - Design must not pose a hazard to users at any point during its normal operation.

Page 9: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

3

Potability of Water

The first requirement is that the water produced is safe to drink. This requirement is vital because

engineers must be socially responsible and take precautions so that society is not harmed by any

products they design. The World Health Organization (WHO) spends significant time working

globally to keep people safe from disease and other illnesses. Team 5 worked hard to follow

these standards so the end users are not harmed by the device they made.

Simplicity of Use

The second requirement is that the design is simple for people with limited technical experience

to use. The interface is designed to have approximately the same complexity level as standard

household appliances such as stoves, dishwashers, and washing machines.

Safety

In addition to the first two requirements, Team 5 also designed the AWG so that it is not

hazardous to users at any point of its standard operation. This third requirement is similar to the

first in that it seeks to protect the end users and society in general; however, this requirement

focuses on ensuring safety across all aspects of operating the system.

2.2. Design Objectives

When starting the project Team 5 developed several goals or objectives that the design will meet.

Flexibility in Power Source - The design should be able to utilize a variety of power

sources, including (but not limited to) solar, wind, and the traditional power grid.

1 Liter of Water Production per Day - The design should produce at least one liter of

drinkable water per day.

Maximize Efficiency - The design should maximize the water produced per unit energy.

Minimize Cost - The design should minimize the cost per unit water production for both

capital cost and production cost.

2.3. Deliverables

The final prototype of the atmospheric water generator will be a device that accomplishes the

requirements Team 5 established at the onset of the project within the scope and budget set forth

by the Senior Design Class. Team 5 will additionally provide a final design report, this

document, detailing the design process and specifications for the final design.

Design Norms 3.

For this project, Team 5 kept several design norms in mind as they planned to create this wet

desiccation system. This involved taking an honest look at the goals of the project and thought

on how the final product should interact with the users and other people who would be affected

by it.

Page 10: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

4

3.1. Transparency

Throughout the design process we worked to make our process understandable, consistent, and

reliable. Someone will be using this so we should make sure that users without a technical

background can understand the process and make use of the product in everyday life.

3.2. Stewardship

The second design norm considered was stewardship. This norm is important for the project

because in using the earth’s resources, we must remember to take care of the world God has

given us. Using economic, environmental, and human resources in a manner that clearly

demonstrates a high value on stewardship shows we care about the world we live in and the

people we share it with.

3.3. Integrity

The design norm of integrity involves looking at the harmony between form and function,

completeness, promotion of human values and relationships, and is pleasing and intuitive to use.

Developing this AWG so that it accomplishes and reflects integrity in design meshes well with

the other design norms of trust and transparency. Our goal is to accomplish all of these design

norms to effectively make a better product that takes into consideration the rights of others.

3.4. Trust

The final design norm important for this project is trust. We want people to feel comfortable

using our AWG so that they use it to its fullest potential and their maximum benefit. Our desire

is to make a good product that is dependable and reliable. Making an unreliable product would

drive up user costs for repair and maintenance, our goal is to have a trustworthy design,

something that our customer can rely on.

Design Evaluation 4.

The system can be divided into four primary aspects: dehumidification, brine, control, and

power, each of which is discussed in detail below.

4.1. Dehumidification

When approaching the problem of atmospheric water generation it is clear that the heart of the

system is dehumidification, which is the removal of water from a stream of air. In this

application we seek to capture this water and utilize it for drinking purposes. Three common

psychometric methods of dehumidification stood out during preliminary research; a temperature

drop below the dew point (refrigeration condensing), pressure condensing, or a combination of

the two. In addition to these three psychometric methods, the team came upon an alternative

chemistry-related method called wet desiccation.

Page 11: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

5

4.1.1. Refrigeration

Traditional refrigeration cycle dehumidification remains the most prevalent method for

generating water from atmospheric humidity. This method circulates air over cooling coils

connected in a refrigeration cycle to bring the water in the air below its dew point. The dew point

of the water is dependent on the vapor pressure and humidity and tends to be a relatively low

temperature compared to the ambient conditions. To reach the dew point the air running through

the unit will have to be cooled a considerable amount.1 This process requires a constant energy

supply that is used as the maximum allowable energy demand for the system. This approach is

expressed in Figure 1 below:

Figure 1: Dehumidification by Refrigeration Cycle

There are several advantages to this approach. First, it is founded on decades of technical work

and innovation. Furthermore, it is a very direct approach and relatively simple to evaluate given

psychometric theory and the latent heat of condensation. A primary disadvantage to this

approach is the magnitude of the heat transfer needed to generate a significant quantity of water.

Virtually all commercial atmospheric water generators utilize this approach to dehumidification.

4.1.2. Pressure

It is possible to compress humid air so much that it will condense at the ambient temperature. As

pressure increases the dew point rises; thus, enough compression will force the dew point above

the ambient temperature resulting in spontaneous condensation; heat will transfer from the

pressurized humid air to the ambient air. Compressing air to extract water could potentially

require pressures up to five times the ambient pressure. This will require a very sturdy tank that

can handle high amounts of stress in its walls. This method has great potential for low energy

1 Cengel, Yunus. Engineering Thermodynamics: Heat Transfer. Calvin College ed. Vol. 1. N.p.: McGraw-Hill,

2011. 192-202. 2 vols. Print.

Evaporator

Water

Humid Air Dehumidified

Air

Condenser

Warm Exhaust

Air

Compressor

Refrigerant

Cycle

Page 12: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

6

demands, especially if one was able to recapture some of the energy in the compressed air using

a turbine or piston. The energy efficiency of this design option has great promise but it is heavily

dependent on compressor and decompressor efficiency and humidity. Figure 2 below is a

representation of this approach.

Figure 2: Dehumidification by Pressurization

The primary advantage of pressure dehumidification is the low energy requirement; the only

unavoidable loss is the pressure applied to the water vapor. However, any inefficiency in the

compression/decompression cycle is amplified by the large volume of air processed per unit

water produced. Additionally, the rate of production when driven by natural convection cooling

to the atmosphere is too slow for significant production; some mechanism to speed up this heat

transfer needs to be implemented, increasing the energy cost. No existing atmospheric water

generators utilize this approach.

Pressure assisted condensation was the first idea investigated in this project. Team 5 saw

potential in the alternate method of condensing because of the theoretical energy savings.

Because the team saw such promise for this approach thorough energy calculations were used to

evaluate the feasibility of the system. The system is deemed feasible if the energy per unit of

water is less than the competition. Several assumptions were made for the base case feasibility

calculations:

The incoming air has a relative humidity of 1 kgwater /kgdry air (ω1 =1) and the outgoing air

has a relative humidity of 0 kgwater /kgdry air (ω2 =0). This is a simplification because all air

will not come in with a humidity of 1 nor will it leave with no water vapor left in the air,

so this is an ideal humidity removal situation.

The compressor has a constant volume that does not change. A standard home

compressor has a volume of approximately 25 liters, which was used as the constant

volume for the base case.

Decompressor

Humid Air

Ambient Air

Dehumidified

Air

Pressure

Vessel

Compressor

Water

Heat

Page 13: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

7

The mass of the water vapor removed from the air does not decrease the pressure in the

system at all. This is not reality because when the water is condensed out and then it is

pumped out of the control volume there will be less mass within the control volume and

the gas will be less dense. Since we have a constant volume the pressure will decrease to

account for the loss of mass.

The efficiency of the compressor was assumed to be 80%. This number is based on

preliminary findings from the internet.

The efficiency of the turbine was assumed to be 80%. The turbine and compressor were

assumed to be the same for simplicity but in reality they will vary.

The density of water is assumed to be 1000 kg/m3

for all temperatures. This was assumed

because the density variance over the small range of temperatures analyzed in this system

was negligible. Likewise the density of air was assumed to be 1.2 kg/ m3

for all

temperatures, for the same reasons.

Compression would not cause any change in temperature and the system would only have

to remove the energy required to condense the water, the latent heat of condensation. It

was also assumed that the heat could be removed in a perfectly efficient process.

For these assumptions Team 5 was able to calculate the amount of energy that was required per

mass of water. This unit mass of energy was found using Equation 1:

(Equation 1)

In is the electrical energy required and is the mass of the water. The total energy

required, energy recovered, and the energy required from the grid are related in Equation 2.

(Equation 2)

With all of the assumptions, Team 5 found that for each gram of water produced the system

would require 20,670 Joules from the grid which is more than the competition. Table 1 shows the

values for the energy calculations of the pressure condensing system along with basic

comparisons of the competitor’s energy requirements.

Table 1: Energy Values from Compression Condensation Base Case

Total Energy Required 57416 kJ/kg

Energy Recovered 36747 kJ/kg

Energy Required from Grid 20669 kJ/kg

Ecoloblue 3500 kJ/kg

Page 14: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

8

After the base case calculations were complete, Team 5 was able to vary several parameters to

determine the minimum efficiency required in the compressor and turbine to equal the best

competitor’s energy requirement. First by varying the efficiency of the compressor and turbine as

one component, an average component efficiency of 92% is required to match Ecoloblue. When

the final pressure is lowered the average efficiency decreases up until a certain point. This shows

that there is an ideal pressure at which to operate the system. This ideal pressure is 190 kPa and

requires a minimum average component efficiency of 85%, Figure 3 shows the decreasing power

requirements for increasing average component efficiencies. Calculations for the compression

condensing system can be found in section 12.5 of the appendix.

Figure 3: Power Requirements for Pressure Dehumification.

4.1.3. Combination

The third alternative is a combination of compression and cooling. When humid air is

pressurized the dew point of the water vapor is increased. This is beneficial for an atmospheric

water generator because pressurizing the air a small amount so that less cooling is required could

lower energy requirements. By combining the two approaches it minimizes the work needed for

each to achieve the same desired result; however this would significantly increase the system

cost and complexity.

4.1.4. Wet Desiccation

The final design option considered is the most abstract, but has gained recognition recently as a

valid design for atmospheric water generation. Wet desiccation is a process where a brine

solution is exposed to humid air in order to absorb water vapor from that air. The solution is then

sent into a regenerator where the water vapor is extracted from the solution.2 This method has

2 Ramachandran, Balakrishnan. 10 Eco-Friendly Gadgets that Procude Water from Air. N.p., 10 Aug. 2011. Web. 8

Dec. 2011. <http://www.ecofriend.com/entry/10-eco-friendly-gadgets-produce-water-air/>.

0.76 0.8 0.84 0.88 0.92 0.96 10

1000

2000

3000

4000

5000

6000

7000

8000

hcompressor

kJ

/kg

qgridqgrid

qcompetitorqcompetitor

Page 15: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

9

grown in popularity because of its efficiency and the ease with which it can be adapted to

renewable energy, particularly solar. Figure 4 below is a basic representation of this approach.

Figure 4: Dehumidification by Desiccation

A primary advantage to this approach is that the desiccant accomplishes the most difficult part of

dehumidification, extracting the water from the air, without a direct expenditure of energy. The

problem is thus recast into terms of regenerating the desiccant and capturing the resultant water.

The main disadvantage of wet desiccation is the complexity that is introduced, both in terms of

system and materials.

Actual implementation of wet desiccation dehumidification depends largely upon the desiccant

used. Two atmospheric water generators that utilize desiccation have been identified, each of

which utilizes a different material as its desiccant. The first is in development at the Interfacial

Engineering and Biotechnology IGB in Stuttgart, Germany and uses a highly concentrated brine

solution. The solution adsorbs water from humid air and is then cycled into the interior of the

device, where the water is extracted under low pressure conditions3. The other device uses a

solid-state desiccant and a day-night cycle; by night humid air is circulated, by day solar heat is

used to extract the water and regenerate the desiccant4.

Wet desiccation originally appeared to be a daunting task; however, as more research was

performed; wet desiccation became more appealing as a design alternative due to its potential for

low energy operation and room for innovation. The biggest difficulty was establishing the

feasibility of this approach, especially concerning the rate at which the water was absorbed by

the desiccant. Research yielded several useful articles that described the performance and

implementation of wet desiccation systems. Of these, one article in particular was best suited to

our purposes. This article described a cross-flow liquid desiccant dehumidification system and

reported the performance of the system across a variety of experimental conditions. The

operation of the system under nominal conditions was highly encouraging, a state summarized in

Table 2.

3 Fraunhofer-Gesellschaft. "Drinking Water From Air Humidity." ScienceDaily, 5 Jun. 2009. Web. 8 Dec. 2011.

<http://www.sciencedaily.com/releases/2009/06/090605091856.htm> 4 Ellsworth, Joe. Solar Thermal Air to Water. N.p., 28 Aug. 2011. Web. 8 Dec. 2011. <http://a2wh.com/>.

Humid Air Dehumidified Air Dehumidifier

Regenerator

Desiccant

Cycle

Water

Page 16: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

10

Table 2: Reported Nominal Operating Conditions and Performance5

Parameter Value

Solution Temperature 30C

Solution Concentration (mass %) 43%

Solution Flow Rate 0.175kg/s

Air Temperature 30C

Air Relative Humidity 78%

Air Flow Rate 204.4cfm

Water Absorption Rate 79.49kg/day

Several observations can be made from these reported results. First, the rate of water production,

almost 80kg of water per day, translates into a volume much greater than our stated goal of 1L

per day. This is particularly encouraging considering the second observation: the operating

points of the reported system are tailored to provide maximum dehumidification performance.

Thus, in adapting the results of this system to our design one can only expect the absorption rate

to fall as compromises are made to reduce energy cost and maximize the water produced in the

regenerator system; the initial figure of 80kg per day gives good reason to believe that the

original goal can still be achieved in a similar system.

The next step was to construct a model using the relationships reported in this article between the

various operating conditions and the water absorption rate. Four key factors were identified: the

size of the contact surface, the rate of air flow, the concentration of the brine exposed to the air

stream, and the temperature of the brine. Linear approximations were developed for each of these

factors using the reported data. Additionally, it was assumed that each of these factors has an

independent effect on the system. Figure 5 below is a representation of the resultant model.

Figure 5: Research-Based Model

This model takes the four input variables noted above and returns a predicted rate of water

absorption and a nominal brine flow rate (flow rates below this nominal value fall off due to

incomplete wetting of the packing tower). This model was implemented in Engineering Equation

5 C. Moon, P. Bansal, S. Jain, “New Mas Transfer Performance Data of a Cross-Flow Liquid Desiccant

Dehumidification System,” International Journal of Refrigeration 32, 2009, p. 524-533.

Packing Dimension l

Brine Concentration C

Brine Temperature T

Air Flow

Model Water Absorption

Brine Flow

Page 17: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

11

Solver (see section 12.6) and used to evaluate an operating condition representative of our

system design. Table 3 below summarizes the results of this simulation.

Table 3: EES Model Results for Representative Conditions

Parameter Value

Solution Temperature 30 C

Solution Concentration (w%) 32%

Packing Dimension 30cm

Air Flow Rate 93.5cfm

Water Absorption Rate 18.06kg/day

Nominal Brine Flow Rate 0.171kg/s

The critical change between the operating conditions and those used in the article is the solution

concentration: we will be dehumidifying with a concentration much less than that used in the

article. In this calculation 32% was the estimate used. Additionally, airflow was reduced to save

energy and lower noise. According to this model, even with these changes, 18kg of water can be

absorbed per day. Given that components supplying the required flow rates and packing

dimensions are available within the budget range (see Table 13), it is concluded that this

approach is feasible from a research perspective.

4.1.5. Decision

After careful consideration, Team 5 chose the wet desiccation system as the best option for

atmospheric water generation. Teams 5’s initial inclination was to work with independent

compression, but after performing energy calculations and going through careful consideration of

the alternatives it no was no longer favored. A main difficulty with compression is that in order

to make it competitive, in terms of energy usage, a prohibitively expensive high efficiency

compressor is required. Because of the pricey compressor Team 5 faced a tradeoff between an

energy efficient system and a relatively inexpensive system with pure compression; therefore it

was passed up as the design of choice.

Another factor in the design decision is the fact that no patents or reports of an atmospheric

water generator that runs only on compression could be found. Even though we had calculations

to support that it is possible, the fact that no one uses that method made the team hesitant to

pursue the process. We decided against cooling coils because currently every main stream

atmospheric generator uses them. To achieve the goal of making this technology more available

and to prepare for the future of this market, the technology designed needs to be new and

possibly better than the current competitors. All of these factors are quantified in a decision

matrix located in the appendix in section 12.2.

Page 18: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

12

4.2. Brine

In the desiccation process there are several different salts that will work in the brine solution.

Lithium bromide (LiBr), lithium chloride (LiCl), and calcium chloride (CaCl2) are all common

salts used in this process. To determine the best option, they were compared by several factors:

corrosion, cost, and safety. Each of the considerations is explained below.6

4.2.1. Corrosion

Salt solutions can cause accelerated corrosion on many different materials. Because it is

unavoidable for us to use a salt solution, corrosion must be minimized corrosion by choosing

corrosive resistant components and choosing a relatively non-corrosive salt. All three of the salts

that Team 5 is considering are fairly non-corrosive, but the nature of a salt solution will cause

accelerated corrosion compared to pure water.

To minimize corrosion, inhibitors can be added to the brine. Inhibitors are commonly used in

lithium solutions in which they are effective. No matter how effective the inhibitor is, if it

introduces toxic or harmful chemicals into the system Team 5 can’t use it (For more details refer

to the safety section); unfortunately, most inhibitors are harmful to humans. CaCl2 requires

inhibitors as frequently as the lithium-based brines, but uninhibited CaCl2 is more corrosive than

either LiBr or LiCL with inhibitors.

No matter which salt or which inhibitor is used, corrosion will occur with most metals. Because

of this as many plastic components will be used as possible.

4.2.2. Cost

Cost is important when selecting the brine because the system will require a significant amount

of brine in order to run. Cost prices for all three salts were found online and are reported in Table

4. Looking at the table it is clear that CaCl2 is the clear favorite. The design will require more

than one kilogram or salt so using either of the lithium salts would be a significant burden on

Team 5’s budget.

6 Studak, Joseph W., and John L. Peterson. "A Preliminary Evaluation of Alternative Liquid Desiccants for a Hybrid

Desiccant Air Conditioner." Austin, Texas: Center for Energy Studies, The University of Texas, 1988. N. pag. Print.

Page 19: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

13

Table 4: Salt Cost Comparisons

Component Price Amount

Unit Price

($) (g) ($/kg)

LiCl7 19 100 190

LiBr8 59 100 590

CaCl29 23 22680 1.01

4.2.3. Safety

Team 5 is creating an AWG with the final goal of producing drinkable water. If this system is to

be effective the final output must be safe for humans to consume and safe to operate. The brine

solution has the potential to cause the design to be unsafe in both of these areas.

In this design the brine will be regenerated using evaporation; this means that no salt should

remain in the water vapor because it will not evaporate out of the brine. Even so, we do not want

to bring water into contact with a compound that is harmful to humans if ingested. The general

public would not understand that the design is safe and the resulting negative image would

hinder any hope of having a marketable product. Of the three salts considered above, CaCl2 is

the safest. Both lithium based compounds are safe to minor ingestion and exposure but repeated

exposure could cause harmful side effects. Because of this it is a great risk to use either LiCl or

LiBr.

The brine can cause the design to be unsafe during operation if the brine mist gets out of the

packed tower. Once in the air, it is hazardous if users inhale the mist or it comes into contact

with their eyes. All three of the salts considered will cause irritation to the eyes and lungs if they

exit the AWG apparatus. Since this is unavoidable with all three alternatives, Team 5 has

decided to minimize the chance of escaped brine mist by putting air filters over the air intake and

outlet of the packed tower. These filters have been chosen to minimize and eliminate the

possibility of escaping brine mist.10

11

12

7 "Lithium Chloride, 100gr." Science Company. N.p., 2011. Google. Web. 8 Dec. 2011.

<http://secure.sciencecompany.com/Lithium-Chloride-100g-P6357C670.aspx>. 8 "Acros Organics, Lithium Bromide, Anhydro 100gr." Neobits. N.p., 2009. Google. Web. 8 Dec. 2011.

<http://www.neobits.com/acros_organics>. 9 "Cargill Salt 50850 Calcium Chloride Pellets - 50lb." Ace Hardware. N.p., 2010. Google. Web. 8 Dec. 2011.

<http://www.acehardwareoutlet.com/>. 10

The Dow Chemical Company. "PELADOW* DG Calcium Chloride." Material Safety Data Sheet. N.p.: n.p.,

2009. N. pag. MSDS Solutions Center. Web. 7 Dec. 2011. <http://msds.com/>. 11

FMC Lithium. "Lithium Bromide Solution, Uninhibited." Material Safety Data Sheet. N.p.: n.p., 2010. N. pag.

MSDS Solutions Center. Web. 7 Dec. 2011. <http://msds.com/>. 12

Anachemla. "Lithium Chloride." Material Safety Data Sheet. N.p.: n.p., 2004. N. pag. MSDS Solutions Center.

Web. 7 Dec. 2011. <http://msds.com/>.

Page 20: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

14

4.2.4. Decision

After considering the various factors for all three components, the chosen brine solution will be

composed of CaCl2. The considerations are shown in Table 5. Although it was not the best

option in all of the categories, CaCl2 is the safest and cheapest. If the design of the AWG is

unsafe to use then it is worthless; using harmful brine is not an option on this project. The design

must be cheap enough for customers to afford and with the amount of salt needed the lithium

salts our design price would inflate quickly.

Table 5: Brine Decision Summary

Consideration LiCl LiBr CaCl2

Corrosion Low Low Medium

Cost High High Low

Safety Poor Poor Good

System Architecture 5.

The wet desiccation system can be divided into three overall sections: system structure, process

and electronics.

5.1. System Structure

The system structure is the physical components that go into the system not including any

electrical components.

5.1.1. Frame

The entire system needed to be supported by some kind of frame; this frame was designed and

built to carry the load of all of the equipment for water generation. Calvin College’s Metal Shop

had an abundance of 1” hollow square tubing with 1/8” thickness walls. The entire frame was

fabricated with this material and strength tests were simulated using Autodesk Algor to assure

structural integrity. An image of the Algor test is shown Figure 6 where a uniform load of 40 lbf

was applied to the upper frame. The corresponding stress to the AISI 1005 steel was only 550

psi, which is well below its maximum strength. Therefore this frame is sufficient to support all

equipment necessary for the system and has a safety factor of roughly 70.

Page 21: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

15

Figure 6: Results of the FEA analysis for the system’s frame

5.1.1. Air Blower Shelf

This shelf was added to the system to support the air blower, chimney, and condensation coils of

the system. This addition was made out of the same 1” hollow square tubing as the frame and

attached to the lower side of the frame outside of the primary supports (It is not shown in Figure

6).

5.1.2. Upper and Lower Shelves

The shelves were added to hold all of the equipment for the system between the supports of steel

frame. They were made out of medium density fiberboard (MDF) which was chosen because of

its availability and high strength.

5.2. Process

The process section is composed of the mechanical and chemical methods that generate water.

The process is divided into three loops: airflow, brine flow, and condenser. Figure 7 is a block

diagram showing all of the necessary parts for the system to help visualize the process portion of

the design.

Page 22: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

16

Figure 7: Block diagram of wet desiccation process

5.2.1. Airflow Loop

The airflow loop begins with the blower pulling ambient air into the condenser chimney. This air

is channeled over a series of condenser coils and then blown through a diffuser into the packed

tower assembly. This is where the air comes into contact with brine from the brine flow loop.

The air then exits the packed tower assembly and returns to the environment. Stages in this loop

are denoted by the letter “A” in Figure 7 above.

5.2.1.1. Air Blower

The key stage for absorption comes as the brine is flowing down the packed tower while the

water vapor filled air is blown over it. Initial calculations determined the blower would need to

be capable of pushing at least 190 cfm (cubic feet per minute) into the packed tower in order to

meet the water production target. After extensive research to find the lowest cost unit that would

provide the necessary airflow, a Stanley blower fan was purchased that had three settings ranging

from 1280 cfm to 2180 cfm. Even though these flow rates are much higher than we need, the fan

Page 23: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

17

will be a good fit because the large increase in the cross-sectional area of the air flow path will

lower the volumetric flow rate.

5.2.1.2. Inlet Fan Diffuser

The selected air blower had a limited distribution range which had to be increased to cover the

entire 32 inch by 12 inch face of the packed tower. A diffuser was designed in Autodesk Inventor

to fit the dimensional requirements of the air blower and the packed tower. The diffuser consists

of a shell built out of sheet metal with cardboard air dividers. The air dividers break the diffuser

shell into seven sections and each divider was made out of cardboard, covered in packaging tape

to protect the cardboard, and reinforced with duct tape to increase the rigidity of the dividers.

This simple design was chosen because the time needed to make and attach sheet metal dividers

was far too much. Cardboard is much less permanent, but this prototype is meant to be a proof-

of-concept and not a long term use unit. A production quality AWG would utilize a corrosion

resistant diffuser constructed with plastic and designed with higher strength and longer use in

mind.

5.2.1.3. Air Outlet Slats

With the fan blowing across the flow path of the brine loop, it is important to keep the brine

inside of the packed tower casing. The initial design had an air filter on the outside of the packed

tower case to capture any brine that would be blown out of the loop. This filter was insufficient

and was quickly destroyed when brine came into contact with it. The second iteration of the

design was to place fiberglass screens in front of the air outlet hole. This worked well but the

screen was blown out of the packed tower case when the air blower was turned on. This caused

the screen to be useless.

To contain all of the brine, outlet slats were created so that any droplets blown through would be

caught on these angled polycarbonate slats and allowed to fall back into the lower tank while the

air moved up and out of the tower casing. Minimizing the escape of brine from the tower casing

was also accomplished by creating a small square fence around the sprayer to direct brine flow

into the packed tower instead of towards the sides where it could flow down and out of the tank.

5.2.2. Brine Loop

Brine flow begins in the upper tank where it is released from the upper tank directly into the

lower tank. The brine pump then circulates the brine up to the spray nozzle at the top of the

packed tower assembly. Once the brine has gone through the packed tower several times and has

absorbed water from the air it is re-circulated to the upper tank; this is done with the brine pump

as well. There is an electronically controlled T-valve directing the brine flow between the spray

nozzle and the upper tank. Once in the upper tank again the brine is dried using two 100 watt

light bulbs as heating elements. Stages in this loop are denoted by the letter “B” in Figure 7

above.

Page 24: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

18

5.2.2.1. Upper Tank

This portion of the AWG is for the evaporation of pure water from the brine solution. One of the

most important design considerations for this part was insulation. Since energy conservation is

one of the goals of this project, the energy put into this tank needs to be saved and reused

throughout operation. Adequate insulation also lowers the time needed to fully evaporate the

solution in the upper tank. This tank needs to be air tight, but accessible for maintenance so foam

weather stripping was attached to the top edges so that the top layer of the tank can be pressed

against it tightly. The top layer is anchored down by ratchet straps which were a great solution to

making the tank air tight, but still accessible.

The lid of the upper tank is where the brine inlet and outlet tubes, air inlet and outlet tubes and

both light sockets for the heating element enter the top tank. Because the top tank needs to be air

tight all of these holes need to be sealed. The top is made of acrylic with holes drilled into it.

5.2.2.2. Packed Tower

The design of this component greatly affects the efficiency of the entire AWG. Its function is to

maximize the surface area of contact between the brine and the air, this allows them to interact

more and increase the absorption. Therefore the more tightly the tower is packed, the greater the

contact surface area, the more humidity is absorbed out of the air flow through the system.

In addition to the packed tower, a shell was built to encase it fully so that no brine could leave

the system. This shell was made out of clear polycarbonate so the process will be more

transparent for education and observation of the system.

5.2.2.3. Lower Tank

This part of the design is only for short-term storage of the brine as it cycles through the packed

tower. To fulfill the two main functions of brine storage and packed tower support, the tank was

designed to hold a maximum of ten gallons and two supporting bridges were put into the lower

tank to hold the packed tower above the liquid’s maximum height. This tank and the packed

tower supports were all constructed out of polycarbonate and carefully sealed to make sure the

tank would not leak any of the stored brine onto the lower shelf.

5.2.2.4. Brine Pump

The brine pump is one of the main mechanical components of our system because it is used to

circulate our working fluid through the packed tower and up to the top tank. To meet the target

water output, the system model in EES (Engineering Equation Solver) required the pump be able

to pump at least two gallons per minute. Since the system frame was constructed with the upper

tank approximately five feet higher than the lower tank the pump also needed to be able to

maintain that flow rate while overcoming the head pressure. A third required characteristic of the

pump was that it be corrosion resistant. Product research and conversations with a pump

salesman determined that the March Magnetic Drive Pump was the solution for this application.

Page 25: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

19

This pump is constructed to have only corrosion resistant materials (polypropylene, ceramic, and

Viton) in contact with the fluid. It also has a maximum head of thirteen feet and maximum flow

of five gallons per minute (gpm). This pump will provide more than four gpm of flow at five feet

of head based on the pump curve provided by the manufacturer. This unit more than fulfills the

specifications determined as sufficient for this system.

5.2.2.5. Brine Distributer

This portion of the AWG will play a pivotal role in the operation of the brine circulation. There

must be a minimum of 2 gallons per minute flowing over the packed tower at any time.

Initially a spray nozzle was chosen, it was an in-ground sprinkler head that has a continuous

stream in a circular area large enough to cover the packed tower. This was effective except for

leaving a large dry section in the middle of the packed tower and getting a lot of overspray on the

walls of the packed tower encasement. This was a problem because we did not have even

distribution and the overspray lead to brine getting out of the encasement.

To determine the optimal brine distribution over the packed tower, a grid of ice cube trays was

placed beneath the packed tower. The ice cube trays allowed us to determine where the brine was

falling and where it was missing. Using this we were able to determine the optimal brine

distribution method. The first method used to address the problem was to drape a towel over the

top of the packed tower. The spray nozzle would saturate the towel and the brine would then

flow down through the towel evenly flow down the walls of the packed tower. The towel worked

well at distributing the brine more consistently, there was however still a small dry spot in the

middle of the packed tower directly below the spray nozzle.

Adding the towel greatly increased the overspray that was landing on the packed tower

encasement and there was a need to address this. We decided to make a 3 inch high square that

would sit atop of the towel on the packed tower. This contained all of the spray from the spray

nozzle so that none of it reached the packed tower encasement.

After adding the towel to the top of the packed tower the flow was dangerously close to falling

below the minimum of 2 gallons per minute. By removing the spray nozzle completely and just

having the open tube letting brine flow openly onto the towel, which is now folded in half to

make it twice as thick, the flow rate is enough to consistently remain above this minimum flow

rate. Also with the thicker towel the flow does not go right through, a slight poop builds up on

top of the towel, contained by the square, until enough head builds up to equilibrate the flow rate

from the hose and the brine flowing down the packed tower. Because there is pool on top of the

packed tower we are ensuring even brine distribution. The towel also acts as a brine filter

collecting and large contaminates floating through it.

Page 26: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

20

5.2.2.6. Heating Element

To evaporate the pure water out of the brine solution in the upper tank, a significant amount of

heat needs to be added. The final design was concluded as two 100 watt light bulbs. Testing has

gone into verifying that these bulbs will provide sufficient heat to evaporate the water (see

section 8.2 Evaporation Rate). They also keep the project cheap and help minimize energy

requirements. If this AWG were to be coupled with solar panels, these light bulbs as heating

elements could be entirely replaced by solar heat.

To fill this requirement, a solar water heater would be the best substitution of direct heat from a

200 Watt source. Solar water heaters generally are bought to contain up to 100 gallons in a loop,

but for this system only 5 gallons are needed. A small solar water heater could be used by

cycling the brine solution from the upper tank through the solar panels to heat the liquid easily to

50 degrees Celsius. This would require a new system design, but would be the best application

of renewable energy for this system.

5.2.2.7. System Tubing

Originally, the tubing meant for the entire system was 1/4 inch, but it was quickly realized that

this size restricts the flow of brine and brings the flow below two gallons per minute. The

solution was to implement 1/2 inch tubing to allow for greater flow. The 1/4 inch tubing is still

used, but only in the condensation loop.

5.2.2.8. T-Valve

The T-Valve selected for this system is a three way valve that can be toggled electronically. It

has two different flow settings; the default setting is when power supply is cut off. Brine is

always being pumped into the T-Valve by the brine pump; at the default position the brine leaves

the T-Valve and goes to the brine distributer to travel through the packed tower. When power is

applied to the T-Valve, the flow switches so that all of the brine is being pumped to the upper

tank. Most of the time the system will need to be pumping brine to the top of the packed tower

assembly and by making this orientation of the T-Valve the default, we are saving energy.

5.2.3. Condensation Loop

The condenser loop begins in the upper tank. The air within the tank is saturated with the water

that has been evaporated with the heating elements. This air is pumped out of the tank and

through condenser coils. In these coils heat is removed from the air causing the moisture to

condense out and into the water storage unit. The air is then pumped back into the tank and is

bubbled through the brine so that it can pull more water out of the brine. The condenser coils are

placed in an airflow chimney. The chimney is located at the inlet of the blower for the airflow

loop, this is done so that air will flow across the condenser coils and heat transfer will occur at an

accelerated rate due to forced convection. Stages in this loop are denoted by the letter “C” in

Figure 7 above.

Page 27: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

21

5.2.3.1. Condenser Coils

The evaporated pure water that came out of the brine must be condensed so that it is useful and

can be captured. To do this effectively, twenty feet of copper tubing was purchased and shaped

into a helical coil. The copper tubing’s heat transfer properties are the reason it was chosen.

These coils are located inside the chimney and the pure water condensate is pumped through the

cycle using the air pump. This coil ends inside the water storage which doubles as a

condensation trap.

5.2.3.2. Air Pump

This pump was chosen because it is powerful enough to force the air from the upper tank through

the entire 20’ of copper tubing into the condensation trap and back to its source.

5.2.3.3. Chimney

The air chimney was added later in the design process, but it will improve the condensation cycle

greatly. Having the blower fan’s inlet air come through the chimney will increase the airflow

across the condenser coils and increase the heat rejection from the hot condenser air to the cooler

inlet air. This forced convection will improve the condensation rate and because it is close to the

frame and supported partly by the blower shelf, it provides a convenient way to support the

copper tubing.

5.2.3.4. Water Storage Condensation Trap

To capture the water that condenses inside condenser coils, the condensation trap has a vertical

drop from the coil inlet. This drop will let gravity take the condensed water to the bottom of the

storage tube and allow uncondensed water and air to return to the upper tank to repeat the cycle.

This water storage container is a clear PVC tube with an inlet and outlet on the top and a water

release valve on the bottom. Clear pipe was used for this component so that the final step of the

process can be visualized, and so that the water level can be monitored.

5.1. Electronics

The electronic section covers the power, sensor, and control systems necessary for the operation

of the design.

5.1.1. Power

The power systems are responsible for two primary functions. First, they must supply the

necessary voltages and currents to all of the design’s various components. Second, the power

systems need to be safe: electrocution is one of the greater hazards associated with this design,

and as such, safe power system design can significantly reduce this danger. Additionally, one of

the goals of this project is to produce a device that is compatible with renewable energy sources.

Unfortunately, it is outside of the scope and budget of this project to implement this design

consideration in our prototype. Table 6 below contains all of the power requirements for the

prototype.

Page 28: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

22

Table 6: Component-wise Power Requirements of Prototype

Component Voltage (V) Current (A) AC/DC

Air Blower 120 0.9 AC

Brine Pump 120 1.0 AC

Air Pump 120 1.8 AC

Heating Element 120 2.4 AC

Brine Routing Valve 120 1.6 AC

Brine Return Valve 12 1.7 DC

Sensors 5 / ±12 0.2 DC

Given the component requirements listed in the table above, the prototype’s power systems will

need to provide one AC voltage and three distinct DC voltages. The AC voltage is easily

accessible from the grid. The DC voltages, however, require the inclusion of a DC power supply.

Two options were explored for this power supply: a standard computer power supply unit and a

board designed and assembled for this specific application. Table 7 below lists the estimated

costs and labor hours required for each option.

Table 7: DC Power Supply Option Comparison

Power Supply Option Estimated Cost Estimated Labor (Hours)

Computer $25 2

Custom $15 20

Not only was the computer power supply significantly more time effective without a prohibitive

increase in cost, the computer power supply was of better quality than any realistic custom

design, came in a self-contained unit, and was guaranteed to provide the required voltages and

currents. In light of these considerations, a computer power supply was purchased and used in

the prototype.

The other primary consideration in the power system was the safety of the user. Given the

voltages supplied to the prototype and the fact that the prototype would be filled with a highly

conductive fluid, the threat of shock to the user is not insignificant. In light of this, several design

decisions were made to minimize this risk. First, all power was routed through the air blower,

which had a built-in 10A breaker. Thus, in the event of a short, the breaker would throw and

prevent electrical fires. Second, the entire frame was tied to ground to prevent the possibility of

the frame going live and shocking any user who came into contact with it. Finally, a GFCI

(Ground Fault Current Interrupter) was incorporated in the power supply lines upstream of the

prototype. This device interrupts the current if any imbalance is detected between the in and out

power lines (i.e. if any current is leaking to the ground). All of these features taken together

ensure that the user is in no way at risk of dangerous electrical shock during the normal operation

of the prototype.

Page 29: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

23

5.1.2. Sensor

Sensor systems allow the user and/or controller of the prototype to determine the operational

conditions of the process. Sensor systems are particularly vital for determining and keeping

within optimal control patterns. Looking at the prototype system diagram, there are six locations

where sensors would provide useful data, as shown below in Figure 8.

Figure 8: Candidate Locations for Sensor Placement

Every significant aspect of the system can be characterized by sensors placed at each of these

locations. The difference between the temperature and humidity readings at (I) and (II) would

provide the rate of absorption of water into the brine. A similar difference in readings between

(V) and (VI) would give the rate of water production. Brine temperature and conductivity

readings at (III) and (IV) would provide the basis for determining when to cycle the brine

solutions.

Limited resources, however, prevented the inclusion of sensors at every locations noted above in

the prototype. In particular, accurate conductivity sensors were prohibitively expensive ($67.95

II

I

III

IV

V

VI

Page 30: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

24

for Hanna Instruments HI76128513

). In light of these restrictions, sensor placement was

prioritized. Temperature probes were placed in three locations (I, III, and IV above), and a

humidity sensor was placed at (I). These four measurements are sufficient for control of the

system once a control scheme has been determined, and establish a basis for inclusion of further

sensors if needed.

Components were chosen to meet these sensor requirements. Two specific components were

selected based on accuracy and cost: the temperature sensor integrated circuit MCP9701-E and

the capacitive humidity sensor HCH-1000-002, by Honeywell. A circuit was designed to accept

the output from each of these sensors and convey it to the user. In the case of the humidity sensor

such a circuit was necessary: the capacitance was on the order of 300 to 500 pF, meaning that a

highly accurate capacitance meter would otherwise be required. Figure 9 below is a PSpice

schematic of the circuit designed for this purpose.

Figure 9: Humidity Sensor Circuit

This circuit uses a 555 timer to translate minute differences in sensor capacitance into

measureable differences in output frequency. Refer to Appendix p. 48 for the relevant pages of

the component datasheet, PSpice simulation results, calculations, and the final reference chart for

the humidity sensor system.

The temperature probes, alternatively, did not require any additional circuitry; the voltage output

from the selected component was designed to be linearly dependent on the temperature.

However, because sensor output would be read by the user in the prototype, a circuit was

designed to scale and adjust the output voltage such that the conversion from voltage to

13

http://www.neobits.com/hanna_instruments_hi761285_conductivity_probe_with_built_in_temperature_sensor_for_

hi8730_p1829307.html?atc=gbs

0

X1

555D

GN

D1

TRIGGER2

OUTPUT3

RESET4

CONTROL5

THRESHOLD6

DISCHARGE7

VC

C8

V1

5Vdc

RA

100k

RB

100k

C_Sensor

{CSense}

C2

1u

R3

1k

PARAMETERS:

CSense = 300p

Page 31: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

25

temperature could be performed without a reference chart. Figure 10 below is a PSpice

schematic of the circuit designed for this purpose.

Figure 10: Temperature Sensor Circuit

This circuit utilizes a follower circuit succeeded by an inverting amplifier, implemented using

operational amplifiers, to apply a gain and offset to the temperature IC output. Refer to Appendix

p. 50 for relevant pages of the component datasheet, PSpice simulation results, calculations, and

calibration data for the temperature sensor systems.

Three copies of the temperature sensor circuit and one copy of the humidity sensor circuit were

printed onto a custom circuit board, with layout shown below in Figure 11.

Figure 11: Sensor Circuit Board Layout

0

U2

uA741

+3

-2

V+7

V-

4

OUT6

OS11

OS25

V1

12Vdc

V2

12Vdc

VCC

VEE

VCC

VEEV5

0

V4

0Vdc

R1

799

R2

4201

R3

4664

R4

336

U3

uA741

+3

-2

V+7

V-

4

OUT6

OS11

OS25

VCC

VEE

V3

5Vdc

V5

Temperature Sensor

Potentiometer

Potentiometer

Page 32: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

26

The above board was fabricated by members of Team 5 at Calvin’s facilities. This circuit board

and the corresponding sensors were successfully integrated into the final prototype.

5.1.3. Control

Control systems are responsible for making decisions as to the operation of the prototype. Team

5 has opted not to implement full electronic control in the prototype. Instead, the user will be

responsible for engaging the various valves and pumps in the prototype to achieve operating

conditions. This decision was motivated by several factors. First, electronic control is an

additional layer of complexity; user-based control simplifies the prototype electronics

considerably. Second, the exact nature of the required electronics is dependent on the desired

control. As Team 5 had no experience with controlling a wet desiccation process, the

requirements were unknown prior to prototype construction. Finally, Team 5 was limited

resources in terms of expertise (given only one electrical engineer on the team) and budget.

Electronic control would, however, be required in future versions of this system, particularly to

meet the Simplicity of Use requirement. Because of this, Team 5 designed the prototype with

future control improvements in mind. The current design brings together many of the sensors and

switches at a single location (the electronics faceplate) in the prototype. This would be the

location for any electronic controller in future versions. Manipulation of the various pumps and

valves would be achieved via relays controlled by a single microcontroller. This microcontroller

would have all of the sensors as inputs, along with a single on/off power switch from the user.

The microcontroller would thus be able to monitor and control the process via the sensors and

relays according to its programming, which would be determined based on optimizations of the

process. Finally, an LCD screen could be implemented in order to make the sensor data and

operating state of the system available to the user, increasing the transparency of the design.

Prototype Operation 6.

The prototype is constructed to be a proof-of-concept and it requires certain considerations while

it is operating.

6.1. Description of Operation

The following section of the report describes the prototype operation.

6.1.1. Batch Process

The brine loop operates in a batch process which requires the condenser loop to operate in a

batch process as well. This was chosen because space constraints on the packed tower meant the

brine would not absorb enough water in one cycle to justify circulating it to the upper tank.

Therefore the brine needs to be circulated for up to two hours through the packed tower assembly

until it is saturated enough to be sent to the upper tank for drying.

Page 33: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

27

The actual times needed for each cycle were determined by testing the prototype and finding an

optimal use time. The brine loop requires a total of 2.5 hours to fully saturate. This cycle time

was determined at test conditions so actual cycle time would most likely be longer than 2.5

hours. Entirely independent of environmental conditions, the condensation loop is most effective

if run for 13.5 hours. This cycle much slower relative to the brine loop and requires an ample

amount of time to heat the brine solution and condense the water vapor back into liquid.

6.1.2. Manual Switches

Since the brine loop is operating as a batch process, switches must be flipped by hand at the

correct time to allow brine to stay in the packed tower cycle or pump to the upper tank. This

process could be automated and electronically controlled after extensive testing, but automation

is outside the scope of this project.

With time not available this semester, the prototype could be run through many different

operating conditions and flow rates to determine the time it would take to saturate brine. With

this optimization an electronic clock could be set to control the valves throughout system

operation. This clock or a concentration sensor would need to adapt to changing operating

conditions during operation. Once the concentration of the brine in the tank was diluted to a

specific level, the switch could flip automatically and send brine to the upper tank.

6.2. Operating Instructions

The following information is a step by step process of turning on and turning off the AWG.

6.2.1. Start-Up Routine

All components must start in an off position or unplugged, the following is a list of all switches

and plugs in the appropriate position.

Brine Return (Missile Switch) OFF (flipped up, cover up)

Brine Routing (Square Toggle) UP Position

Air Pump (Pin Toggle) UP Position

Power Supply OFF

Power Strip OFF

Lights Unplugged

Brine Pump Unplugged

The next list shows the order of turning on all systems assuming that the system has been set

according to the section above.

1. Plug in Air Blower

2. Turn on Power Strip

3. Turn on Power Supply

4. Plug in Brine Pump

Page 34: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

28

5. Plug in Lights

6.2.2. Shutdown Routine

The following set of instructions shows the step by step instructions for shutting down the

system.

1. Unplug Brine Pump

2. Unplug Lights

3. Turn all Routing Switches to their OFF position (see above)

4. Turn OFF Power Supply

5. Turn OFF Power Strip

6. Unplug Air Blower

Once these steps have been accomplished, the entire system has been shut down and is safe to be

maintained.

Project Expenses 7.

In order to determine the overall expense of building an atmospheric water generator, the team

developed an original budget for the prototype by researching what components were available

both online and in the Calvin College metal shop. This budget served as a baseline to guide part

ordering and prototype construction. Primary component sizes were determined based on the

necessary performance levels as determined by the system model developed in EES (Engineering

Equation Solver). The brine pump, air blower, and packed tower were the three main

components and also the three highest individual expenses. More detailed descriptions of these

parts and others are included in the System Architecture section..

Table 8: Main System Expenses.

Main Systems

System Cost

Brine Loop $342.89

Air Loop $54.92

Condenser Loop $32.80

Electrical Systems $81.72

Other $0.00

Total Cost $512.33

The final overall expenses for this system are shown in Table 8. The original budget for Team 5

was five hundred dollars and after purchasing all of the parts for the project, the final expenses

exceeded the original budget by twelve dollars and thirty-three cents.

In Table 8, several main systems are mentioned; the more detailed system costs are shown in

Table 9. The sizes, manufacturers, and quantities of each component are specified in the

Appendix in Table 13. Donated components are listed as costing $0.00 in all expenses tables.

Page 35: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

29

Table 9: Breakdown of System Loop Expenses.

Brine Loop

Components Cost

Magnetic Drive Pump $159.18

Packed Tower $67.10

Packed Tower Case $0.00

Lower Tank $0.00

Upper Tank $11.12

Insulation $0.00

CaCl2 $0.00

Spray Nozzles $3.60

Funnels $4.48

Fittings $35.57

System Tubing $25.89

Miscellaneous $18.27

Upper Tanks Straps $17.68

Total System Cost $342.89

Air Loop

Blower Fan $53.95

Air Filter $0.97

Diffuser $0.00

Total System Cost $54.92

Condenser Loop

Air Blower Pump $0.00

Copper Coils $18.14

Air Column Duct $0.00

Collector Tube Parts $5.19

Light Bulbs $9.47

Total System Cost $32.80

Electrical System

Humidity and Temperature Sensors $33.01

GFI Outlet $16.94

Switches and Power Supply $31.77

Total System Cost $81.72

Other

Metal Frame $0.00

MDF Shelves $0.00

Total System Cost $0.00

Page 36: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

30

Testing 8.

Testing and experimentation allowed Team 5 to understand the relationship between different

process variables and how the system reacts to environmental changes.

8.1. Absorption Rate

In order to use wet desiccation it is essential to know the rate at which a brine solution can

absorb water. Team 5 met with Mr. Glenn Remelts and Professor Vander Griend to answer this

problem. Mr. Remelts helped lead the search for scholarly articles regarding brine absorption and

experimental setups. Professor Vander Griend helped the team develop the set up for several

experiments that will help to determine the absorption rate of a concentrated brine solution.

In the first experiment executed, a small mouth mug and a wide mouth mug (40% concentration

of CaCl2 by mass) were placed on a plate with water on it and covered with a larger pot. With

both mugs under the dome the atmosphere would remain unchanged except when measurements

were made. The water in the plate would evaporate into humidity which would then be absorbed

by the brine in the mug. A picture of the experiment is included in Appendix 12.3. The water

was held in a plate instead of a mug so that the test would not be limited by the speed at which

the water came out of the mug but by the rate at which it could get into the brine. This test took

place from December 1, 2011 to December 5, 2011 with the two different sized mugs so two

different absorption rates could be obtained based on each different mug. The data collected is

included in Appendix 12.4. The contact surface area between the brine solution and the

controlled atmosphere for the small mouth mug was 0.00422 m2 and 0.00633 m

2 for the wide

mouth mug. For each mug a function was developed for the change in mass over time. Looking

at Figure 12 shown below this relationship was different for the different surface areas. The

wide mouth mug has an absorption rate of 1.92 grams of water per day and the small mouth mug

has a rate of 1.00 grams of water per day.

Page 37: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

31

Figure 12: Brine solution mass gain over time

Because there were two different surface areas, each mug gained different amounts of water over

the time of measurement, and a mass flux rate was calculated to compare the two more

accurately. The wide mouth mug had a flux rate of 303.2 g/day-m2 and the small mouth mug’s

flux rate was smaller at a rate of 235.8 g/day-m2. This comparison clearly shows that increasing

the surface area increases the rate which water is absorbed. Through research a company was

found who made a similar device with a 16.4 m2 absorption surface made of a cross corrugated

cellulose pad.

8.2. Evaporation Rate

The upper tank is designed to use heat sources to evaporate the excess water from the brine so

the vapor can be condensed down to liquid water. It is important to test this rate under operating

conditions to determine the effectiveness of the design.

Figure 13 shows the temperature curve of the upper tank during a test that was run on the

condenser loop with pure water in the tank. Temperature probes were placed in the upper tank to

record the change in temperature over time. The light heat source was turned on and the water in

the upper tank was allowed to heat up to 45 °C, this took roughly 150 minutes. At this point the

∆mass = 1.00t R² = 0.9998

∆mass = 1.92t R² = 0.9987

0

1

2

3

4

5

6

7

8

9

0:00:00 12:00:00 24:00:00 36:00:00 48:00:00 60:00:00 72:00:00 84:00:00 96:00:00 108:00:00

Mas

s G

ain

(g)

Time Elapsed, t (days)

CaCl2 Brine Solution Absorption Rate

Small Mouth Mug (Area = 0.00422 m^2)

Wide Mouth Mug (Area = 0.00633 m^2)

Page 38: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

32

air pump was turned on and the air was bubbled through the water in the tank. As seen in Figure

13, this caused the temperature to jump nearly 5 °C, this leads us to believe that the temperature

probe was not taking accurate measurements and that the water needed to be stirred. The test was

run for another hour to condense water out of the air in the tank. In one hour of having the air

pump running 59.8 grams of water were produced. This gave us a baseline to work from.

Because this test was run with pure water we can expect the water production rate to be slightly

decreased but not significantly.

Figure 13: Temperature Curve for the Upper Tank

8.3. Prototype

The goal of our project is to generate water using the air surrounding the device. Temperature

and humidity are key variables that influence the rate of water production and testing them in a

measureable way is essential.

8.3.1. Envirotronics

Through a string of contacts beginning with Professor Harris and Steve Beukema, we were

connected with Dwayne Botruff who is the engineering manager at Envirotronics. Envirotronics

Page 39: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

33

is an industry leader in the design, manufacture, and service of environmental test chambers

based in Grand Rapids14

. Dwayne provided Team 5 with the opportunity to use a test chamber to

manage the humidity and temperature during testing. Using this room for testing allowed the

team to subject the prototype to varying temperatures and humidity cyclically to simulate day

and night conditions. Testing the AWG in this room enabled the team to gather a much wider

range of performance data to develop a model for predicting system performance given various

atmospheric conditions. The result will be a greater ability to analyze the prototype and optimize

it to achieve maximum water production at a minimum cost.

In the visit that Team 5 made to Envirotronics, the only test conducted was on the brine loop.

The environmental test chamber that was used for testing was just larger than the size of the

prototype and it was impractical for the condenser loop to be run because of these size

limitations. The brine loop was run for six hours and every two hours three 50 mL samples of the

brine were collected. This was done in order to determine the concentration change of the brine

over the time of testing. These samples were weighed before testing and then were placed in an

oven to evaporate all of the water. Once this process is complete the mass of the sample, which is

now just salt, is measured again and this determines the change in concentration. Three samples

were taken each time to get an effective average.

The samples that were taken at Envirotronics were placed in the oven with a temperature that

was too high. All of the samples boiled over and were ruined, none of the testing from

Envirotronics can be measured but the testing was still valuable, Team 5 was able to see the

brine loop work for an extended period of time.

The final piece of documentation that Envirotronics left with us is validation certificates. Figure

14 shows the humidity and temperature inside the test chamber during the time of our testing.

This graph and the supporting validation certification (found in 12.10 Envirotronics Validation

Certificate) show that our tests were performed under the conditions specified and are accurate.

The sharp downward spikes in humidity correspond with us opening the door of the chamber

take data and samples, these humidity spikes correspond with a spike in temperature that is less

dramatic but still significant.

14

"About Us: Overview." Envirotronics: Environmental Test Chambers & Services. N.p., 2012. Web. 20 Apr. 2012.

<http://envirotronics.com>.

Page 40: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

34

Figure 14: Validation Graph of Envirotronics' Testing

8.3.2. Steelcase Inc.

Through several more contacts Team 5 was connected with Marty Bender, manager of the

product development test labs at Steelcase Incorporated. Steelcase offered the use of their

humidity controlled chamber, a large room that is maintained at 85% relative humidity and 80

degrees Fahrenheit. With this chamber the entire prototype could be tested contrasting the tests

conducted at Envirotronics where only absorption was possible.

Like at Envirotronics, Team 5 took periodic brine samples in order to determine the brine

concentration in the lower tank. These were placed in the oven at a much lower temperature and

were correctly processed in order to determine the change in concentration. These samples were

dried for two days and then weighed. The results are graphed in Figure 15. This graph shows that

the brine becomes more concentrated as the tests move forward. This goes against what the

graph should show and what actually happens in reality. There are several possibilities as to why

this data seems to be incorrect. One idea is that the brine samples were not completely dry when

they were weighed and there is still some water trapped in the salt causing the sample to weigh

more and skew the results. Another possibility is that brine which had been dried in the upper

0

10

20

30

40

50

60

70

80

90

100

9:2

6:2

2 A

M

9:4

1:2

2 A

M

9:5

6:2

2 A

M

10

:11

:22 A

M

10

:26

:22 A

M

10

:41

:22 A

M

10

:56

:22 A

M

11

:11

:22 A

M

11

:26

:22 A

M

11

:41

:22 A

M

11

:56

:22 A

M

12

:11

:22 P

M

12

:26

:22 P

M

12

:41

:22 P

M

12

:56

:22 P

M

1:1

1:2

2 P

M

1:2

6:2

2 P

M

1:4

1:2

2 P

M

1:5

6:2

2 P

M

2:1

1:2

2 P

M

2:2

6:2

2 P

M

2:4

1:2

2 P

M

2:5

6:2

2 P

M

3:1

1:2

2 P

M

3:2

6:2

2 P

M

deg

."c"

& %

rh

date & time

Calvin College

tempsetpoint

actualtemp.

humiditysetpoint

actual%rh

Page 41: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

35

tank was released to the lower tank. This brine is at a different concentration and will change the

overall the concentration of the lower tank.

Figure 15: Brine Concentration during Steelcase Testing

During testing the temperature in the upper tank and lower tank as well as the relative humidity

in the test chamber were taken every half hour. Using these measurements a time cycle was

determined.

The best cycle was run at Steelcase where 45 mL of water was produced in roughly 1.5 hours.

This was a significant production amount for Team 5 and it helped set some base values for

comparison of further improvements.

8.3.3. Produced Water Quality

Using evaporation and condensing processes will produce pure water by definition. Team 5 will

test the water produced to make sure there is no remaining Calcium Chloride in it. This is the

main concern with the drinking water. A secondary concern is the taste, smell and appearance of

the water.

8.3.4. Power Requirements

It is important to measure the power requirements of the prototype so that Team 5 can evaluate

the energy performance. One of the objectives of the project is to maximize efficiency, and Team

5 will measure this efficiency in units of water produced per unit energy. The basis for this

comparison is competitor models as described in Table 10. The energy use will be measured

using a watt meter. The watt meter measures the electrical power supplied to the system. This

watt meter can be used to measure the energy of the overall system but also the energy of several

of the components individually.

0.26

0.265

0.27

0.275

0.28

0.285

0.29

0.295

9:30 10:18 11:01 11:30 12:30

Bri

ne

Co

nce

ntr

atio

n

Time

Brine Concentration during Steelcase Testing

Page 42: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

36

Table 10: Summary of Design Features for Prominent Competition

Device Manufacturer Production

(L/day) Power

(W)

Water Filtration

Stages

Unit Cost

Ecoloblue 2615 Ecoloblue 26 1050 11 $1,199

Dolphin116 Air2Water 22.8 500 5 $1,799

Atmos 2817 Atmos H2O 28 500 5 $1,545

8.4. Control System

One of the critical areas of testing will be determining what manner of control the system

requires for optimum operation. Mass production plans are to implement a series of control

statements using simplistic analog circuitry. The first order of business will be to determine the

thresholds required for good control on the system. From there, the most effective means of

applying the control signals will be determined, beginning with an assessment of the delays

inherent in the system process. Once these issues have been addressed, the overall performance

of this type of control will be examined, and further improvements added as necessary.

8.5. Further Testing

Team 5 wishes to perform further testing on the prototype and possibly revised prototypes. Some

of these tests are modifications to the tests that were performed and others are new tests that

were determined as valuable after the prototype was created.

8.5.1. Envirotronics

Testing improvements that Team 5 would like to make to the testing that was performed at

Envirotronics include a concentration sensor and humidity sensors at the air outlet of the packed

tower assembly.

The concentration sensor would allow for instantaneous reading of the brine concentration in the

bottom tank. It would eliminate the need to take samples and evaporate them later. This

eliminates some of the risk involved with the samples and would eliminate the steps that led to

ruining them. An accurate, instantaneous concentration measurement system would also make it

possible to modify the test while running it to improve the overall results.

15

Home and Office Products. Ecoloblue, 2011. Web. 9 Dec. 2011. <http://www.ecoloblue.com/home-office.html>. 16

Home/Office Products. Air2Water, 2011. Web. 9 Dec. 2011. <http://www.air2water.net/homeoffice.html>. 17

Atmos 28. Atmos H2O, 2011. Web. 9 Dec. 2011. <http://www.atmosh2o.com/docs/59/atmos_28/>.

Page 43: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

37

The humidity sensor at the air outlet of the packed tower would allow Team 5 to measure the

change in humidity over the packed tower assembly. This would allow us to determine how

much water the air is losing to the brine while it is traveling down the packed tower. We could

make changes to the rate of air travel or brine travel according to this reading to maximize the

absorption that occurs.

8.5.2. Steelcase Inc.

Improvements that relate directly to the testing performed at Steelcase Inc. include timing the

different cycles more accurately, taking temperature measurements on the condenser coils and

having a concentration sensor in the upper tank.

The timing on the cycles is important to determine when and how often brine should be

circulated up to the top tank and released down into the bottom tank. The timing of when to turn

on the air pump, starting the condenser loop, and when to let the top tank heat is not accurately

known at this time; running more extensive tests to determine the optimal timing of this process

will allow a higher production of water.

Temperature measurements on the condenser coils will give a temperature gradient as the hot

and humid air passes through the condenser loop and will enable the optimal number of coils and

the optimal surface area for heat removal to be determined.

A concentration sensor in the upper tank will allow for an accurate reading of how much water is

in the upper tank. The optimal time to release the brine into the lower tank and when to pump

fresh brine up into the upper tank can be found with a concentration sensor.

Project Design Improvements 9.

Upon finishing the project prototype and performing initial testing, the results obtained are less

than the goal Team 5 set out to accomplish. However, the team recognized several areas of

weakness that could be improved to yield better final results. These improvements can be

separated by whether they would be accomplished with a higher budget or if more time would

make them a reality.

9.1. Financial-Based Improvements

Financially-based improvements would be accomplished by investing more money into the

prototype. Spending more on parts would improve the capabilities of the absorption loop, heating

loop, and condensation loop to maximize water production. Purchasing larger pumps, stronger

fans, more effective heating elements, a more densely packed tower, and improving how these

components are connected would raise the efficiency of the system and enable the atmospheric

water generator to produce more water for a given energy input. Since the working fluid (brine

solution) is a corrosive liquid, making the system with more corrosion resistant materials would

improve product life. Many of the materials in the system are also not very water resistant; the

Page 44: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

38

MDF rots when exposed to too much water and the steel frame beams showed oxidation after

only short periods of testing in the humid conditions.

Since the top of the upper tank showed significant warping after being ran at temperature and the

seals for tubes running through the lid leaked frequently, Team 5 would strongly recommend a

custom top tank lid that has the necessary ports formed into it so that tubing connection leaks are

completely eliminated or running the tubes through the side of the tank with high quality seals.

This custom lid would also be heat resistant and provide a way for the safer, more efficient

heating elements to be mounted at the top of the tank. Since heat rises, it might also be a good

idea to implement heaters on the bottom surface of the tank instead of the top. The packed tower

casing and lower tank are also to components that would greatly benefit from custom one-piece

construction. The polycarbonate used for this prototype is expensive and would not have been

used if it was not donated by the Calvin College metal shop. Forming a one-piece lower tank and

a one-piece tower casing and diffuser would also prevent any leaks and alleviate any need to seal

the bottom tank.

The electrical system could also be improved by adding LCD readout screens for the

temperature, humidity, water level, and power consumption monitoring probes. These easier to

understand output screens would also be mounted on a housing for the electrical components.

The housing would not only provide an easier way to mount various sensors and switches to the

frame, but it would also protect all of these components from any brine splashed out of the upper

heating tank. Various switches for the blowers, pumps, and heating elements would also be

installed on this housing to enable easier modulation of those various mechanical components.

9.2. Time-Based Improvements

Time-based improvements are best described as work Team 5 would do if there was enough time

to design and implement them in a second round prototype. Re-wiring the system to keep the

solenoid valves closed when the power is off and re-routing the power to send the most power to

the upper tank in a way that produces the best results of water output.

The heating and condenser loops are both much less efficient than desired; future design work

would involve spending significant time narrowing down exactly how to maximize these

components’ cycle time, physical size, and increase the phase change rate to the fastest point

possible. Adding a third tank that would serve as a buffer tank between the dry, hot, top tank

liquid and the wet, cool, bottom tank liquid would allow the system to cycle faster because hot

brine in the cool brine loop would no longer negatively impact humidity absorption that occurs

there.

To further improve the overall water output and energy consumption numbers, substantial testing

would need to be performed at both of the humidity chambers to ascertain precisely where the

optimum operation points of the system were. Upon determining these optimum points, the

various cycles can be turned on as needed and subsequently operated only when it is beneficial to

Page 45: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

39

do so instead of all the time. This optimization process would also open the door for automating

the system and eliminating the need for an operator to flip switches to change cycle operations. It

is unlikely that any of these improvements would increase the water efficiency number (mL/kW-

hr) by a factor of 14 to reach the levels of our competitors, but Team 5 does believe that a little

work will make it easy to meet the goal of 1 liter per day.

Conclusion 10.

After testing in ideal conditions it was found that this wet desiccation system could produce 0.72

liters of water in one day. The system operates at an average of 416 Watts and produces 72.1 mL

per kW-hr. As reference, Ecoloblue 26 produces 1031 mL per kW-hr. This result shows that the

system created by Team 5 is 14 times less efficient at producing water than the competition.

Therefore, after researching, designing, building, and testing a wet desiccation based

atmospheric water generator, Team 5 has determined it is not a practical method of water

generation. In comparison to other atmospheric water generators it is not an improvement on

energy efficiency. While many of aspects of the prototype could be improved, Team 5 doubts

such a system could reach the efficiencies and production rates of current AWGs.

This project has not, however, been a failure; through this project Team 5 hopes to have

promoted development and understanding of wet desiccation technology and has learned

valuable lessons about design and prototyping. Through the extent of this year long design

project each member of Team 5 has had the opportunity to take charge of a portion of this

design. They have cultivated essential skills for managing large projects and meeting important

deadlines. All of this had been done in the context of a technical project which requires

collaboration with others, grounded in design norms and Christian principles. All of these things

will help the members of Team 5 as they move on from Calvin College on the paths that God has

lain before them.

Acknowledgements 11.

Professor Ned Nielsen

Professor Nielsen was the faculty advisor for Team 5. He consistently took opportunities to teach

each member through the different steps of the design process. He encouraged Team 5 to keep a

realistic scope and reminded them that failure happens in the design process, but it isn’t the end

of the road. A change of direction occasionally leads to a better solution.

Professor Michael Harris

Professor Harris proposed the idea of designing an AWG to the senior design class. When Team

5 decided to take on this project, he was valuable in offering preliminary insights and support,

including putting the team in contact with Mr. Steve Beukema. He helped to define an initial

scope and customer. With his help Team 5 was also able to get in contact with several other

people that were willing to help.

Page 46: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

40

Mr. Ren Tubergen

Mr. Tubergen is Team 5’s industrial consultant. He provided valuable insight and direction

during the meeting he had with Team 5 as well as through emails. He encouraged the team to

focus on specifying the absorption rate which is the “lynch pin” to designing the system. Without

his honest evaluation we would not have produced the document being set forth.

Professor Douglas Vander Griend

Professor Vander Griend met with Team 5 on several different occasions and he helped design

several experiments through which the absorption rate could be specified. He was instrumental in

procuring some CaCl2 from the Calvin College chemistry department in order for the team to

run the experiments. He set up room in one of the chemistry labs and allowed Team 5 to use

some lab equipment. Without his willingness to help Team 5 would not have been able to

perform these experiments.

Mr. Steve Beukema

Mr. Beukema provided valuable insight into the advantages and disadvantages of filter

technology, particularly as compared to atmospheric water generators. He also offered

encouragement to the team and provided connections to Envirotronics for testing the prototype.

Envirotronics

The company allowed Team 5 to test their prototype in one of their test chambers. This allowed

the team to set a baseline for operation and validate safe operation was possible. Special thanks

go out to Dwayne Botruff and Tim Koenigsknecht who were the contacts at the company.

Steelcase

Steelcase allowed Team 5 to use their humidity chamber which allowed us to test the entire

system and produce water for the first time. A special thanks to Mark Heidmann who connected

us with Steelcase and Kurt Heidmann, Jeff Musculus, and Marty Bender who helped us gain

access to the humidity chamber.

Mr. Phil Jasperes

Phil was considered to be the unofficial 5th

member of Team 5. His expertise was utilized almost

daily and he always offered it willingly. He provided valuable insight on constructing the

prototype as well as insightful ideas as to how the prototype could be improved. We cannot

express our gratitude to Phil enough and we are indebted to him for his assistance.

Page 47: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

41

Calvin College Engineering Staff

Bob DeKraker helped Team 5 order all of the parts that were necessary for the prototype. He was

also instrumental in getting the team’s work area set up and established with all of the computers

and technology that was necessary for the project to succeed.

Chuck Holwerda helped Team 5 by offering advice and wisdom whenever he could. He also

helped assist and support many of the tests that were performed.

Michelle Krul was instrumental in organizing and managing all of the teams and the activities

that were involved in this course. She is a master scheduler and organizer.

Rich Huisman, a member of Calvin College’s Chemistry Department, provided Team 5 with

several essential pieces of equipment needed to perform experiments and tests.

Class Advisors

Professor Steven VanderLeest, Professor David Wunder and Professor Wayne Wentzheimer all

helped Team 5 through various assignments and collectively were a vital asset throughout the

senior design class.

Page 48: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

42

Appendix 12.

12.1. Competitor Summary

Table 11: Competitor Summary

Model Performance Testing

Conditions

Additional

Features

Cost Water

(L/day)

Power

(W)

Energy

(kJ/L)

Energy

(kJ/kg)

Temp

(C)

Rel.

Hum.

Water

Filters

Hot/

Cold

Water

Dolphin118

$1,799 27.5 500 1570.9 1577.8 30 0.8 5 Y

Ecoloblue

2619

$1,199 26 1050 3489.2 3501.4 28 0.8 11 Y

AirJuicer

401020

$1,499 19 500 2273.7 2281.5 26.7 0.6 5 Y

12.2. Decision Matrix

Table 12: Desiccant Decision Matrix

18

Home and Office Products. Ecoloblue, 2011. Web. 9 Dec. 2011. <http://www.ecoloblue.com/home-office.html>. 19

Home/Office Products. Air2Water, 2011. Web. 9 Dec. 2011. <http://www.air2water.net/homeoffice.html>. 20

Atmos 28. Atmos H2O, 2011. Web. 9 Dec. 2011. <http://www.atmosh2o.com/docs/59/atmos_28/>.

Page 49: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

43

12.3. Experiment Setup

Figure 16: Experimental Setup

Page 50: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

44

12.4. Experiment Data

Dat

e: 1

2/1/

2011

Exp

eri

me

nt

1

Dat

e o

f

Me

asu

rem

en

ts

Tim

e o

f

Me

asu

rem

en

ts

Tim

e E

lap

sed

(hr)

Ro

om

Tem

p (

°C)

Ro

om

We

t B

ulb

Tem

p (

°C)

Me

asu

red

Mas

s (g

)

Mas

s o

f

Solu

tio

n (

g)

Ch

ange

in

Mas

s (g

)C

on

c. (

w%

)M

eas

ure

d

Mas

s (g

)

Mas

s o

f

Solu

tio

n (

g)

Ch

ange

in

Mas

s (g

)C

on

c. (

w%

)D

ata

coll

ect

ed

by:

12/1

/201

111

:05

0:00

:00

23.5

1846

9.67

60.5

30

0.39

8858

6.90

60.0

30.

000.

4022

EVK

12/1

/201

112

:00

0:55

:00

23.5

1946

9.69

60.5

50.

020.

3987

587.

0460

.17

0.14

0.40

12EV

K

12/1

/201

113

:03

1:58

:00

2312

.546

9.75

60.6

10.

080.

3983

587.

1460

.27

0.24

0.40

06B

TN

12/1

/201

115

:04

3:59

:00

2318

.546

9.83

60.6

90.

160.

3978

587.

3060

.43

0.40

0.39

95R

VB

12/1

/201

115

:58

4:53

:00

2318

469.

8660

.72

0.19

0.39

7658

7.37

60.5

00.

470.

3990

RV

B

12/2

/201

113

:45

26:4

0:00

2315

.547

0.81

61.6

71.

140.

3915

589.

2062

.33

2.30

0.38

73EV

K

12/2

/201

115

:29

28:2

4:00

22.5

13.5

470.

8861

.74

1.21

0.39

1058

9.32

62.4

52.

420.

3866

BTN

12/2

/201

117

:00

29:5

5:00

2218

470.

9361

.79

1.26

0.39

0758

9.43

62.5

62.

530.

3859

RV

B

12/5

/201

112

:00

96:5

5:00

2318

473.

6964

.55

4.02

0.37

4059

4.60

67.7

37.

700.

3564

RV

B

12/5

/201

113

:10

98:0

5:00

2316

473.

7164

.57

4.04

0.37

3959

4.66

67.7

97.

760.

3561

EVK

9.81

5

236.

546

526.

876.

592

409.

14

3.53

5

2.88

7

0.00

633

0.00

422

1.92

1.00

303.

2

235.

8

Surf

ace

Are

a (W

M)

(in

^2)

Surf

ace

Are

a (S

M 1

) (i

n^2

)

Fin

din

g th

e B

rin

e S

olu

tio

n A

bso

rpti

on

Rat

e o

f W

ate

r

Po

t 1

Po

t 2

Dat

a C

oll

ect

ion

Info

rmat

ion

Ro

om

Co

nd

itio

ns

Flu

x R

ate

(SM

) (g

/day

-m2)

Surf

ace

Are

a (W

M)

(m2)

Init

ial C

on

dit

ion

s:

ID S

mal

l Mo

uth

Mu

g (S

M)

(in

)

ID W

ide

Mo

uth

Mu

g (W

M)

(in

)

Mas

s o

f Em

pty

Sm

all M

ou

th M

ug

(g)

Mas

s o

f Em

pty

Wid

e M

ou

th M

ug

(g)

Ro

om

Te

mp

(°C

)

Surf

ace

Are

a (S

M 2

) (i

n^2

)

Flu

x R

ate

(W

M)

(g/d

ay-m

2)

Bri

ne

Ab

sorp

tio

n R

ate

(W

M)

(g/d

ay)

Bri

ne

Ab

sorp

tio

n R

ate

(SM

) (g

/day

)

Surf

ace

Are

a (S

M)

(m2)

Page 51: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

45

12.5. EES Calculations for Pressure Dehumification

omega[1]=HumRat(AirH2O,T=28,r=0.8,P=P[1]) dp[1]=DewPoint(AirH2O,T=28,w=omega[1],P=P[1]) omega[2]=HumRat(AirH2O,T=28,D=28,P=P[2]) rh[2]=RelHum(AirH2O,T=28,w=omega[2],P=P[1]) {dp[2]=DewPoint(AirH2O,T=28,w=omega[2],P=P[2])} dp[2]=28[C] P[1]=101 {P[2]=150*convert(psi,kPa)} P[2]=190 rho_water=1000 vol=25 rho_air=density(air,T=20,P=P[1]) eta_compressor=0.80 eta_turb=eta_compressor latent_heat_cond=2257[kJ/kg] e_compress=(P[2]-P[1])*Vol*convert(J,kJ) m_air=rho_air*Vol/convert(m^3,L) m_water=m_air*(omega[1]-omega[2]) q=e_elec/m_water eta_compressor=e_compress/e_elec e_recovered=eta_turb*e_compress e_elec=e_recovered+e_grid q_grid=e_grid/m_water q_recovered=e_recovered/m_water Heat=e_compress+latent_heat_cond*m_water q_competitor=3500[kJ/kg]

Figure 17: EES Display for Pressure Dehumidification

Page 52: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

46

12.6. EES Calculations for Desiccation Model

"Model for Peformance of Wet Desiccation AWG" "Specified:" L = 0.3 [m] "Dimension of cubic packing tower" C = 32 "Concentration of the brine solution" m_dot_air = 0.05138 [kg/s] "Mass flow rate of air" T_brine = 30 [C] "Brine temperature in packing tower" "State Points" T[0] = 30 [C] P[0] = 101.325 [kPa] "Assumptions:" m_dot_nominal = 0.00096 [kg/s] "Nominal mass flow rate" j_brine_nominal = 1.9 [kg/m^2*s] "Nominal flux rate" "Calculations:" Factor_SA = (L^3) / ((0.3[m])^3) "Surface area factor" Factor_air = 0.38 + ((0.5[m^2*s/kg]) * (m_dot_air / L^2)) "Air factor" Factor_C = (-1.02 + (0.042 * C)) "Concentration factor" Factor_Brine = (2.6 - (0.053 [1/C] * T_brine)) "Brine factor" m_dot_water = Factor_SA * Factor_air * Factor_C * Factor_Brine * m_dot_nominal m_dot_brine = j_brine_nominal * (L^2) m_dot_waterperday = m_dot_water / convert(s,day) "Mass flow rate of water (kg/day)" "Pump Work Calculations:" h_return = 3 * L "h_return = height from pump to return valve" W_dot_pump_in = m_dot_brine * h_return * g# "Volumetric Flow Rate (air)" rho_air = density(air, T = T[0], P = P[0]) V_dot_air = m_dot_air / rho_air * convert(m^3/s,cfm)

Figure 18: EES Display for Desiccation Model

Page 53: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

47

12.7. Complete Project Expenses Table

Table 13: Recorded Project Expenses.

Co

mp

on

en

tM

anu

fact

ure

rP

art

Nu

mb

er

Dis

trib

ute

rSi

zeC

ost

($)

Qu

anti

tySh

ipp

ing

Tota

l Co

st (

$)

Mag

Dri

ve P

um

pM

arch

6305

.201

Rya

nH

erc

o5

GP

M, 1

3 ft

max

he

ad$1

42.8

01

$16.

38$1

59.1

8

Blo

we

r Fa

nLa

sko

(St

anle

y®)

6557

02b

uy.

com

2180

CFM

max

, 8.7

5 lb

s$4

8.96

1$4

.99

$53.

95

Pac

ked

To

we

rC

oo

lin

g To

we

r D

ep

ot

CTD

-ILI

DO

P-1

0C

oo

lin

g To

we

r D

ep

ot

1'x1

'x6'

$40.

211

$26.

89$6

7.10

Air

Blo

we

r P

um

pG

ast

Man

ufa

ctu

rin

gM

OA

-V11

2-A

EM

eta

l Sh

op

1/16

HP

, 115

/110

V, 1

.8/2

.2 A

mp

s$0

.00

1$0

.00

$0.0

0

Co

ils

& C

ou

pli

ng

--23

051

Low

e's

1/4"

x 3

0' c

oil

ed

co

pp

er

tub

ing

$18.

141

$0.0

0$1

8.14

Spra

y N

ozz

les

Orb

it54

020

Low

e's

8' s

pra

y ra

diu

s$1

.80

2$0

.00

$3.6

0

CaC

l 2--

--P

hys

ical

Pla

nt

50 lb

$0.0

01

$0.0

0$0

.00

Low

er

Tan

kM

akro

lon

--M

eta

l Sh

op

1/4"

x 4

' x 6

' $0

.00

1$0

.00

$0.0

0

Bri

ne

Tu

b--

7944

1004

02M

eij

er

14"x

20"x

6"$6

.35

1$0

.00

$6.3

5

Up

pe

r Ta

nk

Insu

lati

on

----

Tran

e2'

x6'x

1"$0

.00

1$0

.00

$0.0

0

Up

pe

r Ta

nk

--47

4971

5002

Me

ije

r5

gal f

ish

tan

k$1

1.12

1$0

.00

$11.

12

Gra

vel

Este

s34

6524

0506

Me

ije

r5

lbs

$4.0

21

$0.0

0$4

.02

Up

pe

r Ta

nk

Stra

ps

--31

7655

Low

e's

12' x

1"

De

sert

Cam

o S

trap

s$1

7.68

1$0

.00

$17.

68

Fitt

ings

U.S

. Pla

stic

Co

rp.

vari

ou

sU

.S. P

last

ic C

orp

.va

rio

us

$12.

161

$9.1

8$2

1.34

Fitt

ings

U.S

. Pla

stic

Co

rp.

vari

ou

sU

.S. P

last

ic C

orp

.va

rio

us

$7.8

01

$6.4

3$1

4.23

Fun

ne

ls--

9559

1Lo

we

's1

pin

t$2

.24

2$0

.00

$4.4

8

Me

sh--

2996

81Lo

we

's36

"x84

"$7

.90

1$0

.00

$7.9

0

Syst

em

Tu

bin

g W

atts

2227

4 &

249

48Lo

we

's3/

4"x3

' an

d 1

/2"x

15' c

lear

vin

yl$1

1.00

1$0

.00

$11.

00

Syst

em

Tu

bin

g W

atts

2227

4Lo

we

's1/

2"x1

0' c

lear

vin

yl$3

.92

1$0

.00

$3.9

2

Syst

em

Tu

bin

g W

atts

24

948

Low

e's

3/4"

ID x

4' c

lear

vin

yl$6

.84

1$0

.00

$6.8

4

Syst

em

Tu

bin

g W

atts

2227

1Lo

we

's3/

8"x1

/4"x

20' c

lear

vin

yl$4

.13

1$0

.00

$4.1

3

Tow

er

Cas

ing

Mak

rolo

n--

Me

tal S

ho

p1/

4" x

4' x

6'

$0.0

01

$0.0

0$0

.00

Syst

em

Fra

me

----

Me

tal S

ho

p1"

x8' s

qu

are

ho

llo

w s

tee

l tu

bin

g$0

.00

8$0

.00

$0.0

0

She

lve

s--

--W

oo

d S

ho

p4'

x6'x

1" m

df

she

et

$0.0

01

$0.0

0$0

.00

Dif

fuse

r--

--M

eta

l Sh

op

4'x4

' ste

el s

he

et

me

tal

$0.0

01

$0.0

0$0

.00

Air

co

lum

n d

uct

ing

----

Me

tal S

ho

p8"

x6' h

oll

ow

pvc

pip

e$0

.00

1$0

.00

$0.0

0

Air

fil

ter

Ene

rgy

Air

e31

2777

Low

e's

1" x

14"

x 2

4" p

leat

ed

air

fil

ter

$0.9

71

$0.0

0$0

.97

Co

lle

cto

r Tu

be

Par

ts--

--Lo

we

's2"

cap

an

d 1

/8"x

11/2

nip

ple

$5.1

91

$0.0

0$5

.19

Ligh

t b

ulb

sG

E--

Low

e's

2x 1

00W

an

d 2

x 40

W$9

.47

1$0

.00

$9.4

7

Ele

ctro

nic

sD

igik

ey

$2

6.34

1$6

.67

$33.

01

Ele

ctro

nic

s--

--R

adio

Sh

ack

--$1

0.78

1$0

.00

$10.

78

GFI

Ou

tle

tC

oo

pe

r24

5864

Low

e's

20 a

mp

, 125

vo

lt$1

6.94

1$0

.00

$16.

94

Ele

ctro

nic

sTi

gerD

ire

ct$1

0.99

1$1

0.00

$20.

99

Tota

l Sys

tem

$512

.33

(Var

iou

s p

arts

are

incl

ud

ed

in t

his

est

imat

e)

(Var

iou

s p

arts

are

incl

ud

ed

in t

his

est

imat

e)

Bu

dge

t fo

r W

ate

r fr

om

Air

(Te

am 5

)

Page 54: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

48

12.8. Capacitive Sensor Circuit Reference

Figure 19: PSpice Parametric Capacitive Sweep of Sensor Circuit

CSense

300p 310p 320p 330p 340p 350p 360p 370p 380p 390p 400p

1/period(V(X1:OUTPUT))

11.5K

12.0K

12.5K

13.0K

13.5K

14.0K

14.5K

15.0K

15.5K

16.0K

Page 55: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

49

Figure 20: Humidity Sensor Capacitance Response21

Figure 21: Sensor Capacitance Calculation

21

HCH-1000 Series Datasheet, Honeywell International Inc., 2011. Figure 2 in original document.

Page 56: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

50

Figure 22: Frequency to Relative Humidity Reference Chart

12.9. Temperature Sensor Circuit Reference

Figure 23: PSpice Voltage Sweep Simulation of Temperature Circuit

0

10

20

30

40

50

60

70

80

90

100

13.5 13.7 13.9 14.1 14.3 14.5 14.7 14.9 15.1 15.3 15.5 15.7 15.9 16.1 16.3 16.5

Re

lati

ve H

um

idit

y (%

)

Measured Frequency (kHz)

V_V4

0.4V 0.6V 0.8V 1.0V 1.2V 1.4V 1.6V 1.8V 2.0V 2.2V 2.4V

V(R2:2)

-12V

-10V

-8V

-6V

-4V

-2V

0V

Page 57: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

51

Figure 24: Output Voltage vs. Ambient Temperature22

Table 14: Temperature Probe Calibration Data

Short Lead Medium Lead Long Lead

Temp (C)

Vout (V)

Temp (C)

Vout (V)

Temp (C)

Vout (V)

22.7 0.818 22.7 0.809 22.7 0.834

4.8 0.675 5.8 0.483 5.4 0.545

2.6 0.675 2.6 0.429 2.6 0.456

22

MCP9700/9700A and MCP9701/9701A Datasheet, Microchip Technologies Inc., 2009. Figure 2-16 in original

document.

Page 58: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

52

Figure 25: Temperature Probe Calibration Results

y = 0.019x + 0.3764 R² = 0.9997

y = 0.0181x + 0.4268 R² = 0.9904

y = 0.0075x + 0.6479 R² = 0.99

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

0 5 10 15 20 25

Raw

Ou

tpu

t V

olt

age

(V

)

Temperature (C)

Medium Lead

Long Lead

Short Lead

Linear (Medium Lead)

Linear (Long Lead)

Linear (Short Lead)

Page 59: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

53

Figure 26: Temperature Circuit Calibration Mathcad Sheet (Screenshot)

Page 60: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

54

12.10. Envirotronics Validation Certificate

Page 61: DESIGN REPORT A WATER GENERATOR WATER - Calvin · PDF filei Executive Summary The goal of this senior design project is to design and prototype an atmospheric water generator, a device

55