department of state development, infrastructure and planning · department of state development,...
TRANSCRIPT
So What Is Aquis?
• Mr Fung’s vision is an “Iconic first class unique modern piece of man made infrastructure” that is a compelling reason to come from there to here and most importantly to refer and return
• A “must see” man made “wonder of the world”
• iconic enough and big enough to be “must see“ or the people will not come
• The complete package is a – A first class iconic man made asset in conjunction with world class natural tourism assets in conjunction with high quality services (accommodation; casino; food and beverage; retail shopping; entertainment) and a focused and directed relevant marketing campaign
• Omit one part of the package and the offering will not be competitive at all
10
WHOLE of Phase 1 of Stage 1
• Construction Cost of whole of Phase One $3.6B
• Total cost $4.2B
• 3000 rooms across 3 Hotels
• Casino
• Retail over 3000 sqm
• Food & Beverage total just under 7000 sqm
• Operational 3 years 6 months from start
• Commence construction May 2016 and finish
construction and ready to open in early 2020 for 2020
Chinese New Year – earlier if we do as two sub phases
18
EIS
• Initial Advice Statement July 2013
• Coordinated Project designation under SDPWO Act August
2013
• Draft TOR issued August 2013
• Public and Agency submissions on Tor September 2013
• Final TOR October 2013
• EPBC referral 1 April 2014
• Controlled action decision 5 May 2014
• Assessment under State Process as an accredited process
• Revised TOR incorporating Controlling provisions
issued May 2014
• EIS submitted 12 June 2014
• Public Notice 21 June to 5 August 2014
19
EIS Process
• Impact Avoidance/assessment
1. Community engagement (displays, surveys, social
media,) Community and stakeholder reference groups as part
of SIA
2. Site Values (Native veg, flora and fauna surveys, Matters of
SES & NES, geotechnical/ground investigations, Water Quality
sampling, Cultural heritage surveys, Visual amenity values,
ambient noise and air quality surveys)
3. Site constraints (flooding, Coastal Processes, SCL, Native Veg
mapping, OLS and Airport operations)
4. Project refinement
5. Infrastructure demands
6. Residual impacts on site values
7. Management and Mitigation Plans
20
Community and Agency Response
• Submissions received from 220 Individuals and
organisations in the community
• Submissions received from 30 State Agencies, Gov
Corporations and Local Governments
• Responses to Community Issues and Agency
submissions submitted on 2 September 2014
• Request for further information issued by COG 16
September 2014
• Supplementary Information Report submitted 7 October
2014
21
Cultural Facilities
• Significant commitment to indigenous culture, events,
locations and facilities
• Significant commitment to local arts, cultural and
entertainment events, locations and facilities
• Sponsorship of indigenous sport and sporting events
• Sponsorship of local sports clubs and events
• With Cairns Regional Council - a Cairns CBD
“Chinatown” cultural precinct
23
Education
• Working with James Cook University concerning
courses and educational programs in:
– Tourism and Hospitality Management and services
– Gaming management and services
– Languages
• Indigenous training and employment is an absolute
imperative of AQUIS
24
Infrastructure - Transport
• SCR (CCH, CWAR upgrades required with or
without Aquis)
• Local Road Network (Dunne Road, YK road to
be upgraded)
• Port (spare capacity to cater for anticipated
demands)
• Rail (spare capacity to cater for anticipated
demands)
• Airport (spare capacity to cater for anticipated
demands)
25
Infrastructure - Services
• Water Supply (Bulk Water , Water treatment, Distribution
and storage) – Minimise Potable water use, Treated water
Reuse to minimise potable demand
• Wastewater – adjacent to MCWWTP , Plant augmentation
required - increased capacity, improved quality (A+ for
reuse). Will reuse more treated water than waste water
produced
• Gas – No reticulated gas in Cairns – Possible on site storage
of gas as energy sources
• Energy – Connection to ERGON network – Major Customer
Agreement- Smithfield Switchyard and HV supply. On site
generation (wind , solar, centralised chilled water)
• Comms – NBN in place prior to operations
26
Approvals
• Section 242 (SPA) application to Cairns Regional
Council following COG Evaluation Report
• CRC decision to approve or reject Land use application
• CRC decision open to 3rd party appeal to P&E Court by
anyone who made a submission on EIS
• MCU Code assessable applications to follow for
development permits fro Resort Complex, Environmental
facilities and Sports and Recreation facilities
• Operational works applications required for site works,
external works for road upgrades and service connections
• ERA applications for excavation of Lake
• Tidal works applications required for Lake inlet/outlet
works
27
Programme
• Design / Construction
• Concept Design commenced
• Design development - May 2015 onwards
• External Works design – May 2015 onwards
• Site works / External works - commence July
2015
• Building works - May 2016
• Construction complete - July 2019
Services / Products Opportunities
• Design
– Architect
– Interior design
– Landscaping
– Engineering (Civil, Structural, Hydraulics,
Geotechnical, Acoustics, Building Services
Electrical, Communications)
– Quantity Surveying / Cost Control
– Design Co-ordination / Management
– Golf Couse design
– Specialist design services (Stadium, Water Park)
Services / Products Opportunities
• Construction
– Civil works
– Earthworks, Road construction, Paving
contractors, Drainage,
– Services connections (sewerage and water
supply)
– Landscapers
– Irrigation
Services / Products Opportunities
• Construction
– Building Works (all construction trades)
– Concreters, Formwork, Steel Fixers,
Plumbers, Carpenters, Joiners, Carpet
Layers, Flooring Contractors, Electrical
Contractors, Steel Painters, Tilers, Steel
Fabricators, Joinery Manufacturing,
Plumbing Supplies
– Transport Services, Accommodation, etc
etc
Services / Products Opportunities
• Operations
– Food and beverage suppliers
– Staff uniforms
– Transport services (guests and staff)
– Security
– Laundry
– Waste removal
– Repairs and maintenance services
– Professional services / administration support / office supplies
Project Policies
• Local Content and Participation – Aquis considers the encouragement of local employment and
business opportunities within its operations as a critical corporate
value in the delivery and operation of the Aquis Resort Project
– Develop processes to ensure local business opportunities are
considered in project procurement practises
– Allow competitive local business to be given fair and reasonable
opportunities to provide goods or services to the project
– Encourage contractors to source local goods and services where
possible
– Encourage businesses who provide goods and services to the
project to consider Indigenous employment in order to maximise
Indigenous employment opportunities
– Continue to engage with key business bodies regarding appropriate
opportunities for local businesses to supply goods and services to
the project.
Project Policies
• Local Content and Participation – Facilitate the communication of the Local Procurement Policy to
local service providers by ongoing communication of project
procurement requirements, regular project updates during
construction and overview of goods and services packages and
supply chain
– Participate in existing programs that provide technical assistance
and briefings to potential local and regional businesses about
opportunities and requirements
– Collaborate with the existing job service providers to advertise for
local positions, allowing applicants to choose between industry and
non industry jobs
– Liaise with training providers to inform them of business solutions
and programs are available to provide goods and services to the
project
Opportunities for NQ Businesses
• Substantial Opportunities for NQ Businesses
in design construction and Operations
• FNQ/Cairns supply chains will be capacity
limited and challenged
• Opportunity to add capacity to Cairns based
businesses through strategic alliances and
collaborative partnerships
• Expanded population in Cairns is an
opportunity for the supply of goods and
services
Register Your Interest
http://aquisgreatbarrierreefresort.com/lcc-business-register
MAJOR PROJECTS FORUM TOWNSVILLE
Hon Keith DeLacy AM
Chairman INTEGRATED FOOD AND ENERGY DEVELOPMENTS (Ifed)
Page 37 Decemberr 2014
Page 38
A NEW MODEL FOR THE TROPICS
A greenfield development of a privately funded, large-scale, world-class, vertically integrated and sustainable agribusiness.
THE IFED PROPOSAL
ETHERIDGE INTEGRATED AGRICULTURE PROJECT
(EIAP)
December 2014
IFED has secured long-term options over the key properties required for water diversion, water storage, cropping and infrastructure.
Project area comprises: 5 properties – 326,000 ha Cropping land – 65,000 ha Water storage – 18,000 ha Infrastructure – 2,000 ha Grazing – 241,000 ha
5,400,000 (Ord River =3,870,000)
PROJECT LOCATION AND SIZE
Einasleigh R
Gilbert R
Page 39
Flow rate in megalitres /year
December 2014
Water is flood harvested into lakes and gravity fed to the co-located farming and processing facilities.
PROJECT DESIGN
December 2014 Page 40
Existing cattle operations
Existing cattle operations
Off-river Water
Storage
Cogen – 90MW Bagasse/biogas
Gum Plant
Sugar Mill 700 kt/y of sugar
Farm Sugar - 40,000 ha Guar – 25,000 ha
Hull and germ 65 kt/y
Cane 4.8 Mt/y
Raw sugar – 535 kt/y Ethanol – 100 ML/y
Steam and Electricity - 43MW
Guar gum - 32 kt/y
Meat Processing Plant
ng cattle operations
Existing cattle operations
Existing cattle operations
200,000 hd/y Cattle from local
graziers
Meat products 53 kt/y Hides and offal
Pellet Mill Biomass Pellets - 400 kt/y
Cane Tops 120 kt/y
Aquaculture Redclaw ponds
Redclaw 7.5 kt/y
OVERVIEW: Integration of Water, Farm and Processing Activities.
December 2014
Feed Mill 400 kt/y
Molasses 61kt/y
Page 41
PROJECT COST ESTIMATE:
Page 42
Item Cost Estimate -
$M
Land acquisition plus costs 67 Water Infrastructure & Allocation 497
Farm - Land Preparation 123 Farm - Irrigation Development 367
Sugar mill 371
Ethanol refinery 126
Guar mill 52
Stock feed plant 36
Power station 159
Meat processing 63 Infrastructure & Accommodation 62
Plant & Equipment 54
Capital expenditure $1,977
December 2014
The vertically integrated farming and processing model delivers revenue diversity and high EBITDA. Typical year from 2020:
Products Units Quantity
Sell price
$/unit
Revenue $M
Cost $M
EBITDA Margin
$M Farming
sugar cane Tonnes 4,800,000
109 -109
guar bean Tonnes 98,000
25 -25
Raw sugar Tonnes 535,000 487
261
66 195
Ethanol Litres 100,000,0
00 1.15
115
25 90
Guar gum Tonnes 32,000 4,871
156
33 123
Stock feed Tonnes 404,000 173
70
17 53
Electricity MWH 358,000 106
38
15 23 Meat & co-products Head 200,000 1,140
228
208 20
Indirect Overheads 22 -22
Total
868
520 348
Page 43
PROJECT FORECAST FINANCIALS
December 2014
• Reaching negotiated agreements with five land owners that secures 326,000 hectares under long term options;
• Completion of detailed technical and commercial feasibility analysis;
• “Development Protocol” for a water allocation agreed with the Queensland Government;
• Declaration of a “Co-ordinated Project” by the Queensland government; and
• Well progressed with Pre-Construction Phase capital raising.
Page 44
PROJECT MILESTONES
December 2014
After the failures, what’s changed this time?
A NEW MODEL - WHY EIAP IS DIFFERENT
• SCALE
• BIO-MASS = ENERGY
• INTEGRATION
• DE-RISKED CLIMATE
• INNOVATIVE WATER STORAGE
• OFF-THE SHELF AGRICULTURE AND PROCESSING
Page 45 December 2014
PROJECT VALUE
Revenue is $868 million
Capital cost is $1.977 billion
Value-added during: • Construction is $3.78B over 3 years
• Operations is $2.75B each year
Value added multipliers in NQ
December 2014 Page 46
Water facilities (Area 100)
PARTIAL FLOW DIVERSION and OFF-RIVER STORAGE
2 x Off-river storages
• Dagworth lake – 1.6M megalitres, 8 km of embankment
• Dismal Lake – 0.4M megalitres, 0.6 km of embankment
• 8 million cubic metres of earth and rock embankments with sand filter and clay core
Channels (mainly in-cut)
• 72 km of channels
• 33.5 million cubic metres
• Under-river syphons
December 2014 Page 47
FARM FACILITIES (Area 200)
Farm and Irrigation System Installed and Operated by Contractors
• 100 km of channels, 12.5million m3
• 180 pump stations
• 1,625 x 40 ha farm blocks
• 6,600 valves and in-line filters
• 630 km of 650 mm dia mainline
• 2,300 km of 150 mm dia sub-mains
• 1,760 km of flushing manifold
• 540,000 km of sub-surface drip
• Instrumentation and control system
• Fertiliser injection system
• Water recovery and reuse ponds
• Drains and roads
• 150 Tractors, 26 cane harvesters, 75 haulout bins, 8 headers, etc
• 86 road trains
• Implements
• Farm sheds
• Maintenance workshop equipment
• 200 km of Fences
• Aerial monitoring equipment
December 2014 Page 48
PROCESSING FACILITIES BULK QUANTITIES
Steel structures
• 15,000 t of structural steel
Civil Work
• 60 to 80,000 m3 of concrete
• 7 to 8,000 tonnes of reinforced bars
• 80 to 100,000 m2 of cladding
•
Mechanical and piping
• 15 to 20,000 tons of steel structure
• 20 to 25,000 tons of equipment
• 40 km of pipes to be installed
December 2014 Page 49
PROCESSING FACILITIES Process and Process Packages
Area 300 – Process
• Sugar mill
• Guar mill
• Biogas plant
• Biomass pellet plant
• Stockfeed mill
• Meat processing plant
• Cogeneration plant
AREA 400 - Process Packages
• Cane fibre separation plant
• Guar bean silos
• Chemicals storage eg C3H6O, NH3,H2SO4
• Lime handling
• Molasses storage
• Bagasse stockpile
• Cane tops stockpile
• Cane trash stockpile
• Tallow-based biodiesel plant
December 2014 Page 50
Processing facilities Process Water, Services and Utilities
Area 500
• Process raw water supply
• Process filtered water supply
• Process RO water
• Process demineralised water
• Process potable water
• Process gland seal water
• Process cooling water
• Process run-off water sediment pond
• Process sewage treatment
• Process fire water
• Process treated water discharge
• Farm and Process diesel tank farm
• Auxiliary boiler
• Electricity transmission lines off-site
• Plant air
• Process air
• Instrument air
• Process mobile equipment
December 2014 Page 51
Processing facilities Process Plant Infrastructure
AREA 600
• Plant roads and drainage
• Precinct Bulk earthworks and drainage
• Office - admin and engineering, lab, control room
• Canteen and change room
• Workshops
• Spare parts storage shed
• Process maintenance facilities
• Vehicle, truck and tractor maintenance facilities
• Chemical storage
• Raw sugar shed
• Guar bean storage shed
• Lab fitout
• Control room fitout
• Maintenance equipment fit-out
• Truck weighbridge
• Fire truck station and fire truck
• Container holding yard
• Truck Stop
• Diesel load-out
• Truck fueling station
• Vehicle fueling station
December 2014 Page 52
Site Facilities General Infrastructure – off site
AREA 700
• Bulk earthworks and drainage for the village
• Roads off-site
• Village units including admin office, mess hall
• Construction camps x 2 incl power, water, sewage
• Social and community
• Communications and data infrastructure
• Water assets, Farm and Process Plants control system
• Village fire water system
• Village sewage
• Municipal Waste disposal
• Security building, fences, process plant and village
• Truck loadout at Port
• Port warehouse
• Conveying and shiploading
December 2014 Page 53
Site Facilities Construction Service Support
AREA 800
• Construction offices
• Common contractor facilities
• Survey
• Medical Services
• Geotech , soil testing
• Warehouse operations
• Project security
• Vendor rep costs
• Major construction cranage
• Road and building maintenance
• Camp management and catering
• HSE
• Commissioning support
• Fuel for construction
December 2014 Page 54
• Bulk Water Package delivered by a single EPC Contract:
– channels, embankments, syphons
– Andy’s Earth Movers
• Land Clearing and Preparation:
– Preliminary site visit completed
• Pipelines, pipe fittings and pipeline installation:
– Manufacturer driven pipeline and fittings supply
– Installation contractor/s required
• Pump and field valve stations
– Off-site (shop) fabrication, test, haul and site install
• Process Plants:
– EPC for Major process package (discussions underway)
– Meat processing plant (in discussion)
– Biogas plant (ADI selected)
• Utilities - various contracts:
– On-farm/site HV distribution
– Roads, etc
December 2014 Page 55
Project Implementation Contact [email protected]
Page 56
ETHERIDGE INTEGRATED AGRICULTURE PROJECT • TRANSFORMING AGRICULTURE • BRINGING GOVERNMENT POLICY TO LIFE • DEVELOPING THE NORTH • CREATING JOBS AND OPPORTUNITIES IN AN ISOLATED REGION • CREATING WEALTH AND GOVERNMENT REVENUE • POSITIONING AUSTRALIA IN THE ASIAN CENTURY • FEEDING A HUNGRY WORLD
December 2014
JOINT LOGISTICS COMMAND
JLU(NQ) Presentation to
Townsville Industry Breakfast 02 Dec 14
Lieutenant Colonel Matt Patching and Mr Larry Staggs
JOINT LOGISTICS COMMAND
Scope
• JLU(NQ)
– Who, where, and what
– Logistics Transformation
• Regional changes
– Plan Beersheba
– Land 121
• Industry opportunities
• Accessing JLU(NQ)
JOINT LOGISTICS COMMAND
Who, where, what – JLU(NQ) • Lavarack Barracks, Ross Island Barracks, RAAF Base Townsville,
Macrossan
• Logistics support to international and domestic operations and training activities, including:
– Warehousing & Distribution
– Loan Pool (Vehicle, Construction and ‘Party Equipment’ Hire)
– Maintenance - minor through to heavy grade repair • Land materiel
• Army Marine Craft
– Explosive Ordnance Services
– Clothing Stores
• Achieved primarily through prime contractors:
– Linfox –Warehousing and Distribution
– Transfield Services - Land Materiel Maintenance
– Serco Sodexo Defence Services – Clothing and Operational Kitting
– Drake and Skilled – Labour Hire
– Thales – Explosive Ordnance Management
– Local Industry (Maintenance and Local Procurement)
JOINT LOGISTICS COMMAND
Defence Logistics Transformation
• Infrastructure development: – New $150m site to be completed mid-16
• Delivery of facilities commenced May 14
• Land Materiel Maintenance: – Trade repair is an important part of the Business
Model
– Trade repair is managed by Commonwealth maintenance planning staff at JLU(NQ)
– Investment in North Queensland providing a sustainable, flexible, long term regional maintenance footprint
• FY 13/14 approx $6M to trade houses, $4M to labour hire companies employing Townsville residents
JOINT LOGISTICS COMMAND
Regional Changes
• Plan BEERSHEBA – Rebalance of Army’s combat force to make Brigades more alike
– Generation of Armoured Cavalry Regiments in Townsville, Darwin, and
Brisbane
– 2014 - re-introduction of armoured vehicles to NQ
• Australian Light Armoured Vehicle (ASLAV)
• M113AS4 Personnel Carrier
– Late 2015 – introduction of M1A1 Abrams Tank to NQ
• Land 121
– Replacement of light and medium vehicle fleets
– G Wagon slowly replacing Landrover 110
• Mercedes Benz Australia endorsed repairer for G-Wagon
• Large Landrover 110 fleet remains
– Critically managing Unimog / Mack fleets for 5-8 years
• Industry opportunities likely limited to non-armoured fleets
JOINT LOGISTICS COMMAND
Industry opportunities
• Fleets expected to be supported by trade repair using local
industry:
– Plant / Construction Equipment
– Materiel Handling Equipment
– B Vehicles (light and medium trucks)
– Bulk Liquid Distribution assets, (Fuel/Water tankers & pumps)
– Fire fighting equipment
– Canvas repairs
JOINT LOGISTICS COMMAND
Accessing JLU(NQ)
• Small to Medium Enterprise assessments can be arranged
through:
– Fleet and Maintenance Manager – Mr Larry Staggs
[email protected] / (07) 4411 8598
– Trade Repair Supervisor – Mr Mick O’Brien
Mike.o’[email protected] / (07) 4411 6796
– Queensland Government
• Qld Govt Department of State Development, Infrastructure and Planning
Melissa Anderson
QLD State Director
AusIndustry – Entrepreneur Development
2 December 2014
Entrepreneurs’ Infrastructure
Programme
Five Growth Sectors
Advanced Manufacturing
Food and Agribusiness
Medical Technologies and Pharmaceuticals
Mining Equipment, Technology and Services, and
Oil, Gas and Energy Resources
Enabling Industries (ICT and Digital, Professional Services, Transport and Logistics, Infrastructure Construction)
What does Entrepreneur Infrastructure Programme
offer?
Three streams with a phased
delivery:
Business Management
Research Connections, and
Commercialising Ideas.
Practical support for businesses
includes:
Advice from people with relevant
private sector experience
Small co-contributions for re-
engineering or growth
opportunities for businesses, and
Connection and collaboration
opportunities
The Three Streams
Business Management
• Business Evaluation
• Business Growth Grant
• Business Growth Services
• Supply Chain Services
Research Connections
Facilitation and Advice
Research Connections
Grant
Commercialising Ideas
Department of Industry | Business
Melissa Anderson
QLD State Director
AusIndustry – Entrepreneur Development
Level 13, 100 Creek St
QLD 4000 Telephone +61 7 3227 4752
For more information about Australian
Government Business services visit
business.gov.au or call 13 28 46.
Next Townsville Industry Breakfast
• 17 March 2015 – Townsville RSL
• Full details will be sent out closer to the date – so keep a watch in your emails!
Thank you! The Townsville Industry Breakfast team would like to thank you
all for your on-going support and attendance.
We all look forward to 2015 and the continuing success of the Townsville Industry Breakfast.
Merry Christmas and a fabulous New Year!