Delays in Project Execution
-
7/31/2019 Delays in Project Execution
2/15
Introduction
It is observed that many projects get delayed due todifferent reasons.
Some of the reasons are controllable & some of them
are uncontrollable.
Let us focus on such critical reasons.
-
7/31/2019 Delays in Project Execution
3/15
List of Reasons
1. Statutory Permissions
2. Detailed Engineering
3. Non-availability of Testing/SCADA Engineers
4. Lack of Support Services
5. Poor performance of Civil / Electrical contractor / sub-contractor
6. Non-availability of necessary outages
7. Lack of detailed Scheduling/Monitoring
8. Attitude
9. No leanings from previous similar projects/activities
10. Delay in enquiries / order placement / material delivery11. Organizational structure of project execution team
-
7/31/2019 Delays in Project Execution
4/15
1. Statutory Permissions
Cable Projects-
Permissions fromBMC/MCGM/MMRDA/TRAFFIC
Transmission Line Projects-
Road crossings/Railway crossingsForest/private property/mangroves
GIS Projects-
Building/development permission
-
7/31/2019 Delays in Project Execution
5/15
2. Detailed Engineering
Non availability of approved drawings/ layouts.E.g. Approved ICS
Non Standardization
Scope not defined
Change in scope in between
-
7/31/2019 Delays in Project Execution
6/15
3. Non-availability of Testing/SCADA Engineers
Since Testing/SCADA engineers are busy with their
current schedule, they are not available during the
test-charging/commissioning activities of project.
-
7/31/2019 Delays in Project Execution
7/15
4. Lack of Support Services
Lack of support from operating division.
Role clarification.
-
7/31/2019 Delays in Project Execution
8/15
-
7/31/2019 Delays in Project Execution
9/15
6. Non-availability of necessary outages
This is major uncontrollable factor.
-
7/31/2019 Delays in Project Execution
10/15
7. Lack of detailed Scheduling/Monitoring
Use of Project planning soft wares such as
MS-Projects/SAP for detailed scheduling, update/
tracking of project activities can solve the problem.
Review of progress at site level.
-
7/31/2019 Delays in Project Execution
11/15
8. Attitude
Absence of Rigor
Communication Gap
Ownership
Targeting End-dates
-
7/31/2019 Delays in Project Execution
12/15
9. No leanings from previous similarprojects/ activities
Share/Seek the knowledge across/from the similarproject groups.
Evaluate the similar problems & plan alternatesolutions for them.
-
7/31/2019 Delays in Project Execution
13/15
10. Delays in enquiries /Order placement/Material delivery
Delay in
Supply-chain Management
Bids-EvaluationMaterials Receipt
-
7/31/2019 Delays in Project Execution
14/15
11. Organizational structure of projectexecution team
Organizational structure of project execution team &
support services should be under one umbrella, so that it
can help in better co-ordination of the project-activities.
-