project execution plan.pdf

84
Doha Beirut Cairo London ENGINEERING, PROCUREMENT, CONSTRUCTION, TURNKEY CONTRACT FOR THE INTEGRATED DISTRICT COOLING PLANT AT THE PEARL PROJECT DOHA - QATAR PROJECT EXECUTION PLAN Q06024-IDCP-PLN-GT-001-REV A C.A.T. INTERNATIONAL QATAR W.L.L.

Upload: 14102001

Post on 20-Nov-2015

772 views

Category:

Documents


29 download

TRANSCRIPT

  • Doha Beirut Cairo London

    EENNGGIINNEEEERRIINNGG,, PPRROOCCUURREEMMEENNTT,, CCOONNSSTTRRUUCCTTIIOONN,, TTUURRNNKKEEYY CCOONNTTRRAACCTT FFOORR TTHHEE IINNTTEEGGRRAATTEEDD DDIISSTTRRIICCTT CCOOOOLLIINNGG PPLLAANNTT AATT TTHHEE PPEEAARRLL PPRROOJJEECCTT

    DDOOHHAA -- QQAATTAARR

    PROJECT EXECUTION PLAN Q06024-IDCP-PLN-GT-001-REV A

    C.A.T. INTERNATIONAL QATAR W.L.L.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 2 -

    INDEX PAGEPrefacescopeofworks 1.Executionstatement 32.InterpretationsandAbbreviations 33.ProjectExecutionPlan 33.1C.A.T.ApproachPlan 33.2LongLeadItemsProcurement 53.3BulkMaterialProcurement 93.4ConstructionActivities 93.4.1.TemporaryFacilities 93.4.2.OrganizationChart 103.4.3.Subcontractors 103.4.4.FieldCoordinationProcedures 103.4.5.DetailedConstructionSchedule 104.DetailedConstructionSchedule 114.1.DataCollection 114.2.EngineeringandDesign 114.3.ConstructionoftheCoolingPlant 124.4.ConstructionofHEXBuildingsandETSs 184.5.Calibration 184.6.TestingandPrecommissioning 194.7.Commissioning 194.8.Training 195.QualityAssurance(QA) 206.Health,SafetyandEnvironment(HSE) 20Appendix1PROJECTCHART Appendix2ORGANIZATIONCHART Appendix3LONGLEADITEMSLIST Appendix4PROJECTKEYMILESTONES Appendix5TEMPORARYFACILITIES Appendix6LISTOFSUBCONTRACTORS Appendix7CIVILMETHODSTATEMENTLIST Appendix8MECHANICALMETHODSTATEMENTLIST Appendix9E&IMETHODSTATEMENTLIST Appendix10DESIGNINTENTREPORT

  • Q06024-IDCP-PLN-GT-001-REV A

    - 3 -

    1.ExecutionstatementForproperexecutionandtimelycompletionoftheproject,weareplanningtofollowourproposedprojectexecutionplan,whichisinlineandconformstothetargetscopeofworkandcompletiondatesasstipulatedinthecontractdocuments.2.InterpretationsandAbbreviationsIntheprojectexecutionplan,thefollowingwordsandexpressionsshallhavethemeaningherebyassignedtothem,exceptifotherspecifiedorwherethecontextotherwiserequires:EMPLOYER(orClient,Owner,Company)meansQATARCOOLQCwillbecommonlyusedinsteadofQATARCOOL.PMCmeansDARALHANDASAHDARwillbecommonlyusedinsteadofDARALHANDASAH.CONTRACTORmeansC.A.T.INTERNATIONALQATARW.L.LC.A.T.willbecommonlyusedinsteadofC.A.T.INTERNATIONALQATARW.L.L.DESIGNTEAMmeansSTANLEYEngineeringSCIwillbecommonlyusedinsteadofSTANLEYEngineering.3.ProjectExecutionPlan3.1.C.A.T.ApproachTheimplementationofthisprojectExecutionPlanthatcomplieswithQ.CrequirementswillbethemainobjectiveofC.A.T.C.A.T.willbeworkingwithEMPLOYER(QC)personnelandPMC(DAR)personnel,andDesignTeam(SCI)personneltoensurethatthisprincipalobjectiveisaccomplished.Ourexperienceonsimilarprojectshasseasonedourpersonneltocompleteanyandallservicesrequiredwithoptimumperformanceresults.TheC.A.T.ProjectsTeamandseniormanagementarecommittedtoprovidingaprojectthatmeetsEMPLOYERsobjectivesaswellasourownprincipalobjectives.Wetakeprideinourworkandareconfidentthesewillbeaccomplished.TheprincipleobjectivesthattheC.A.T.managementexpectstobemetareasfollows:

    MeetallcriticalmilestonesandcompletetheProjectonschedule

  • Q06024-IDCP-PLN-GT-001-REV A

    - 4 -

    Maintainprojectcostswithinbudget Meettechnicalperformanceobjectives ObtaintotalsatisfactionfromEMPLOYER

    TheproposedProjectChart(seeAppendix1)hasbeendevelopedtoachievetheabovementionedexpectations.Thesuccessfulmanagementoftheprojectrequiresgoodcommunicationsbetweentheengineeringteam and construction team, comprehensivemanagement information systems and a competent,welldirectedprojectteam.Directly upon award, a qualified management and supervisory Project Team was appointed toprepareadetailedstudyoftheprojectrequirementsasfarasengineering,materials,equipmentandlabor force required (seeAppendix 2,ContractorOrganizationChart). This group ofdedicatedprojectpersonnelbeganidentifyingtheprioritiestobecompletedintheearlystagesoftheprojectandplannedfortheinitialkickoffmeetingthatwasheldinQCoffices.ThisinitialmeetingwasimportantinestablishingastrongteamrelationshipwiththeQC,DAR&SCI.Afterawardofthecontract,themanagementpersonnelfromareasbeganmobilizingtofulfillthestaffingneededfortheproject.ThisstaffstartedwithSCIverifyingtheavailabledesign.Basedontheconceptdesign,procurementoftheLLILongleaditems(seelistinAppendix3)startedaspertheprocurementprocedures.Theprojectkeymilestones(seeAppendix4)weretobeconfirmedasperthesuppliers&projectprogress.SCIstartedwiththeconceptdesign,aimingtosubmitthesametoQC&DARforclearanceandtogoaheadwiththedetaileddesign.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 5 -

    3.2. LongLeadItemsProcurement

    FLOWOFPROCUREMENTACTIVITIES

    Data Input

    Requisition Commercial Terms Composite Vendor List

    Project Vendor List Inquiry Concept Design

    Procurement Policy and Procedures

    Material Status Report

    Traffic Operations Arrival at Site

    Expediting and Shop Inspection

    Purchase Order Award

    Negotiation with Vendor

    Client Approval

    Bid Analysis and Tabulation Technical / Commercial

  • Q06024-IDCP-PLN-GT-001-REV A

    - 6 -

    TherequisitionofLLIiscriticalandwillbedevelopedonarushbasis,immediatelyaftercontractawardandapprovalofconceptdesign.Owningtothecriticalmilestonesrequirements,itisessentialthataccelerationpremiumsforspecificequipmentandmaterialstobedevelopedandreflectedC.A.T.sflowprocurementactivities,asshownabove,includethefollowingpolices:AwellscreenedprojectvendorlistwithapreferenceforQCrecommendedvendorswillbeprepared,reflectingC.A.T.recentprocurementexperience;dueconsiderationisgivennotonlytotechnicalcapabilities,commercialcompetitivenessandofferedguaranteeconditions,butalsotodeliveryperformance.Purchaseorderplacementwillbebasedonquotationdevelopmentexceptwheresourceorleadtimeconstraintsdictateotherwise.Fasttrackingproceduresareestablishedtofacilitateearlyprocurementoflongleadtimeitems;closelyknitinterfacingamongQC,DAR,C.A.T.andSCIisexpectedandwillbeimplemented.RigorousexpeditingandfrequenttrackingofmaterialsstatuswillbeperformedintherealizationthatanydelayfromtheConstructionRequiredDates(CRD)ofmaterialsarrivalonthesitewillendangermeetingofthecontractualprojectcompletiondate.Anefficientfieldmaterialscontrolsystemwillbeestablishedandthroughindoctrinationonwarehousingoperationwillbecarriedout.LLIprocurementwillbedoneasperourC.A.T.standardprocurementprocedure,inordertocomplywiththeemployerspecifiedpolicies.3rdPartyValidation(ifrequired)forLLIprocedurewillbeperformedasandwhenrequired.AspartofprocurementactivityC.A.T.&SCIwillcarryoutatechnicalevaluationforeachitemstartingwithtechnicalclarificationandfinalizingwithaTechnicalEvaluationReportC.A.T.&SCIwillcarryoutalsoareviewofvendorsdrawings/documentationaspartoftheabovementionedprocurementactivity.The technicalbidevaluationwillbeundertakenbyeachengineeringdiscipline.The technicalbidevaluationisusedtosummarizethetechnicalaspectsofbidsreceivedforaspecificrequisition,inorder that the bidsmay be compared and evaluated.Proposals (bids) are forwarded to the SCIEngineersandCATConstructionManagersforevaluation.A thorough review of technical data will be made to determine whether bids conform to thespecified technical requirements. Any deviations or inadequate information is identified at thattime.Inaddition,C.A.T&SCIcoordinateanyotherreviewsapplicabletotheparticularevaluation(constructionimpacts,technicalspecialistreview,etc.)andincorporatetheresultsofthesereviewsonthetechnicalbidevaluation.ThetechnicalbidevaluationisthenreviewedandapprovedbytheProjectManager.Atthispoint,C.A.T. area procurement department shall evaluate the bids based on project requirements and

  • Q06024-IDCP-PLN-GT-001-REV A

    - 7 -

    commercial issues.Compliancewithproject requirementswillbe imposed on thevendor for allaspectsofhisequipment.Onceabidisdeterminedtobetechnicallyacceptableandcommerciallyoptimal,C.A.T.willsenditsrecommendation toDAR for approval.C.A.T.will award purchase orders only upon obtainingQC/DARapprovals.Upon receivingCompanys vendor approvals,C.A.T.will issue purchase orders to the selectedvendors.All purchase orders aremonitored. Supplierswill submitmonthly progress reports totracktheequipmentstatus.Similarly,theshopdrawings/productionanddeliveryschedulereportwilldepict,indetails,thestatusofvendordrawings,data,factoryacceptancetestsandinspections,otherrelevantdocumentsasrequested.All LLI will be received on site. All LLI will be checked upon receipt for quality, quantity,conformancewith specifications,damageand tagor identificationnumber,andenteredon stockcards.Areceiptreportand, ifapplicable,anoverage,shortageordamagereportwillbeprepared.Issuewillbemadeonamaterials requisition formsignedbyasignatory froma limited listofpersonsauthorizedbytheprojectmanager.Theprojectprocurementofficerwilloverseealllocallysuppliedmaterial.Receiving,warehousing,reportingandmaterielissuedforconstructionactivitiesshallfollowC.A.T.QA/QCprocedures.Importeditemswillbereceivedbypurchaseordernumber/tagnumberifappropriate,andcheckedfor quantity and evidence of any shipment damage. Contractor will establish a constructionwarehousesystem,whichincludecoveredandopenstoragetocontrolthematerialuntilitisneededfor construction. The Construction Manager will be responsible for issuing material transferauthorizationstoreleasematerialstothevariousConstructionSuperintendents.TheProcurementOfficerwillberesponsibleforprovidingmarkingandtagginginstructionsonallpurchaseorders.Thiseffortwillprovidemeans in the identificationofallmaterials receivedandestablishtraceabilityasrequired.AsprojectLLIarereceived,areportofmaterialsreceivedwillbetransmittedtoupdatetherecordsand generate reports for construction management and QC use. Material inventories will beadjustedascontractor issuesmaterialsandequipment forconstruction throughstandardmaterialtransferdocument.Theprocurementteamwillinterfacewiththequalitycontrolfunctiontoensurethatmaterialsandequipmentareacquiredwithoutdisruptingthedesignandconstructionschedules.Giventhehighcoordinationdemandsofthisfunction,theProjectProcurementOfficerwillserveasakeyfacilitatorbetween thevariouselementsof timelyprocurement.Hewill track theprogressofmaterialsand

  • Q06024-IDCP-PLN-GT-001-REV A

    - 8 -

    equipment throughdelivery to thework site,providingacentralizedpointof information forallprojectmanagement.The project quality and project controls functions will supplement the procurement effort insupport roles. Inherently linked by their common goals of vendor quality and schedule impact,thesetwofunctionswillcloselyinterfacewithProcurementthroughoutthelifeoftheproject.The quality control function monitors the procurement function with each of its supportingpositions. Working to ensure quality from both its subcontractors and vendors, this functionassumes the role of quality assurance for its vendors and quality control for the entire projectthroughcontinuedanalysisofoureffortsaswellasourvendorsandsubcontractors.Where discrepancies are observed, nonconformance reports will be prepared and submitted.ProvisionhasbeenmadeforFATtestedandwitnessedbyQCandC.A.T.TheQA/QCManagerwill verify the technical viability of potential vendors and subcontractors.Throughadocumentedprocessandinspection,thiscoordinatorwillresearchtheabovecriteriaaswellasthequalitysystemsofpotentialsuppliers.TheprojectPlanningEngineerwillpredominantlyassist in the schedulinganddocumentcontrolactivities.Workingwith theExpediteron theareaProcurementDepartment, theprojectPlanningEngineer will develop procurement schedules, linking the relationship between procurement ofspecificequipmentandmaterialswithcriticaldesignandconstructionactivities.TheDocumentControllerwillmaintain the officials vendor data control register, updating andtrackingallvendordataprocessed forreview/approval.TheDocumentControllerwillcoordinatevendor communications, receivingand returningmarkedupand/orapproveddrawingsorothervendordata.Thisdatawill include,but isnot limited to,design calculations,parts lists, specialtools,sparepartsrecommendedbythevendorandvarioussubvendordocuments.Vendor data submissions will include drawings, spare parts data packages, operating andmaintenance manuals/instructions, procedures, and other pertinent data needed to support theequipmentormaterialbeingpurchased.On arrival of products to storage area, the storekeeper with the help of relative department(Mechanical,Electrical, etc)orhisdesignate shall startunloading, checking against thepurchaseorderor the loadingnoteand labelingeach itemwith itscorrectdescription, tally sheetnumber,stocknumber,drawingnumber,andstoreitinitsproperplaceasadvisedbythespecifications.Upon receipt of equipment, each delivery shall be checked for quantity and quality, shortagesvisible or concealed damages. Should there be any damages, shortages, etc then the SiteManagementshallbe informedaccording toapplicableprocedure.Thematerial receivedshallberecordedonstockrecordsaspertheapplicableprocedure.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 9 -

    Toavoiddoublehandlingandonly in theevent that itsuits, liftswillbe initiallyprogrammed toarrive to site after their prospective foundations are ready. The QA/QC Department and thestorekeeper shall ensure that the handling of products is according to vendor specifications,contractualdocuments, safety standardsandproject requirements.Similarly,he shallensure thatconcernedpeopleareproperlyandcurrently informedofmaterial receivedor tobereceived.Allconcernedemployedinmaterialhandlingshallbewellconversantwithvariousprojectsandhavehadpreviousexperiencedealingwithconstructionpermanentmaterial.Specialconsiderationsshallbeappliedtomaterialsandcomponentsthatshouldnothaveunnecessaryhandlingduetoweight,orconfiguration.3.3.BulkMaterialProcurementThematerialsprocurement,other thanLLI,willbedoneasper thesamedescribedprocedure forLLI.3.4.ConstructionActivitiesSoon after N.T.C. a construction group was organized within the Project Team. Based on theconstructionstrategyestablishedandprojectrequirementsidentifiedduringthebiddingstage,thisgroup will develop the Construction Plan, keeping in close contact with the engineering andprocurementgroups.TheConstructionPlanwillbecontinuallyrevisedandupdatedasrequiredtoreflectthelatestinformationaffectingconstructionoperationsandwillcoverthefollowingareas:

    3.4.1.TemporaryFacilities 3.4.2.OrganizationCharts 3.4.3.Subcontractors 3.4.4.FieldCoordinationProcedures 3.4.5.DetailedConstructionSchedule

    3.4.1.TemporaryFacilitiesTemporaryfacilities(seeAppendix5)shallbeerectedincloseproximitytotheworks,aftersecuringM/SUDCs&DARsapprovaltothelayoutandlocationsofsiteoffices,stores,workshops,etc...SitePlotPlanandofficesAreasshallbefencedinaccordancewiththeConstructionRegulations.We shall accommodate our personnel in existing camp in Rayyan& ShahaniyahAreas. Propertransportshallbeprovidedtoensurethetransferofemployeesfromandtositeincomfortableandsuitableconditions.Staffwillbeaccommodatedinfurnishedapartments.QC & DAR requirements for Temporary Facilities shall be completed in accordance with thesupplementaltermsandspecifications.SafetyandEnvironmentalProtectionshallbemaintainedbyourSafetydepartmentasperRequirementsandasperCATSafetyManual.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 10 -

    OurHSEDepartmentpersonnelareaswellfamiliarwiththehandlingandsecuringpassesfromthelocalauthoritiesandUDC;immediately,theprocessofsecuringpassestoallpersonnelenteringthezoneshallproceedtoguaranteethatsuchpasseswillbeavailableontime.3.4.2. OrganizationChartsTheProjectChart(seeAppendix1)andtheContractorChart(seeAppendix2)havebeenstructuredto effectively and economically achieve the project construction objectives. The proposedorganizationaddressesalltheprojecttraderequirementsasfarasmanagementandsupervision.ItisdesignedinawaytoprovideQC&DARwithacomprehensiveandhomogeneousteameffectivein the execution of this type of works and meeting the project milestones. Staff C.Vs, fromSupervisorlevelandabove,shallbesubmittedtoQC&DARforpriorapproval.3.4.3. SubcontractorsThesubcontractors(seeAppendix6.ListofSubcontractors)shallcoverspecificareasandshallbespecializedfortheirexpertisearea.PriorapprovalwillbeobtainedfromDARbeforesubcontractingthework.TheProjectManager,ConstructionManagers,ProjectEngineers,DisciplineEngineers,QCandSafetyEngineershallcontroltheSubcontractorsfieldofactivities.3.4.4. FieldCoordinationProceduresField controlwill be broken down into the following areas,withmanagement coordinating theseparateeffortsintoaneffectiveandefficientfieldorganization: ManpowerControl SafetyandSecurityControl WarehousingandMaterialsManagementPlan ConstructionEquipmentControl FieldChangesControl DocumentControl3.4.5. DetailedConstructionScheduleThedetailedConstructionScheduleiscovering: DataCollection EngineeringandDesign ConstructionofCoolingPlant ConstructionofHEXbuildingsandETSs Calibration TestingandPrecommissioning Commissioning Training WarrantyPeriod

  • Q06024-IDCP-PLN-GT-001-REV A

    - 11 -

    Theconstructionscheduleisdetailedinnextchapter.4. DetailedConstructionSchedule4.1 DataCollectionC.A.T.&SCIwillpreparethecheckliststoidentifytheinformationneededandtheinformationtobeobtainedfromDARandotherparties.Thedatacollectionactivitiesembraceeachofthevariousdisciplinesandwillbestructuredtomeettheneedsforthedesign.CriticaltothescheduleforthisprojectisthedatasitesurveythatwillbeundertakenbyC.A.T.atthestartoftheproject.4.2. EngineeringandDesignSCIwillreviewtheprojectrequirementswithQC,DAR&C.A.T.toconfirmandobtainallrequireddatapertainingtotheprojectdeliverables.Duringthemeetings,themainequipmentsandsystemswill be finalized.Data, such as production rates, physical properties of the products and otherrelevantdatawillbereviewedandagreed.SCIwilldeveloptheconceptdesign,passittoCATfordoublecheckingandreviewingit,andverifyitwithQC/DARpriortodevelopingthedesign.ADesignIntentReportwillbeissued,(Appendixno.10).Based on the verifieddesign, the procurement of theLLILongLead Itemswill start as per theprocurementproceduresalreadydescribed.Theexactsequenceofactivitiesduringtheengineeringand design phase will be dependent on the schedule requirements for construction andconsequently themanufacturing and shipping times forprocurement.Thus, some activitiesmayneedtostartearlierbasedontheinformationprovidedbyQCinthestagepriortoaward.SCIwillperformdetaileddesignensuring thatallprocessrelatedactivitiesdefined in theprojectrequirementswill beundertaken in accordancewith international andQC standards and codes.SCIsexperienceofsimilarprojectswillenablearecognizedandeffectivedesign.Oncethedetaileddesign is substantially completed and approved, the mechanical, instrumentation and electricaldesigns will commence and the finalized specifications and requisitions completed. FollowingQC/DARapproval,thematerialandequipmentwillbetenderedandpurchased.Usingthedataobtainedduringthesurveysandthefinalizedprocessdrawings,theplotplansandlayoutdrawingswillbedevelopedforDARapproval.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 12 -

    Thepipingdrawingsand specificationswill commence,basedupon theapprovedplotplanandlayoutdrawings.Thesewillbe completed once finalizedvendordata is received and approved.Where applicable SCI/C.A.T. will check for compact designs with simplicity of installation butwhich retain easeofaccess foroperation andmaintenance.SCI/C.A.T.will ensure that theplantpiping is laid out in an economical and effective manner to suit the process and operabilityrequirements.SCI/C.A.T. will ensure that all civil engineering will be detailed with due regard to the localconditionsand taking intoaccount thespecificityof thearea.SCI/C.A.T.willalsoensure that fullconsiderationwillbegiventooperationalfunctionality,safetyandaestheticconsiderations.Based upon the equipment & piping arrangements and relevant approved vendor data themechanical,electricalandinstrumentationdrawingswillbecompletedandfinalMTOsestablished.When drawings are finalized and approved by QC/DAR they will be issued as Approved forConstruction(AFC).The constructionof thewholeprojectwillbeperformedaccording toourproposed constructionschedulethatgivesthestartandfinishdateofeachactivity.4.3.ConstructionoftheCoolingPlantTheworks for the plant and administration building shall cover but shall not be limited to thefollowing: Siteclearing Excavationandcompaction

    DewateringWaterProofing

    Raftfoundation&BuildingConcreteWorks PrecastConcreteWorks Equipmentfoundations FinishingWorks EquipmentWorks PipingWorks Fabrication&Erection Electrical&Instrumentationworks Landscape,Roads,curbstoneandsidewalksSiteClearingWeshallcarryonallthenecessaryclearing,grubbingandsoftlandscapinginaccordancewiththespecifications .Excavatedmaterial shallbe removed from the siteand replacedby suitableone ifrequired,allasspecified.Weconfirmthatsuchworksshallstartaftersitepossessionandsecuringtherelatedapprovalandpermitsandagreeingtothelevels.SiteclearingwillbeperformedpartiallybyC.A.T.andmainlybyourexcavationSubContractor.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 13 -

    ExcavationforFoundationandSubstructuresThebuilding shallbedivided into4Areas.Areasare separatedbyconstruction joints.Eachareamighthaveadifferentexcavationlevel.TheselevelswillbecalculatedbySCIandagreedbyDAR.The excavation work shall be executed, by our Subcontractor and under our supervision, inaccordancewithdrawings, specifications and instructions.Thus, excavation shall bedone to thelines and grades or elevation, agreed with QC & DAR during concept Design evaluation andclearedwithUDC.Excavatedmaterial shall beused for backfillingproviding itpasses requiredtests. Unsuitable material shall be removed when encountered and replaced by suitable one.Permanent works blinding concrete membrane or such other protection as specified on thedrawings shallbeplaced,byour concrete subcontractor, followingcompletionofexcavationandcompactionworks, clearing the soil testswithDAR and as soon as it ispractical .AllprecedentworksistobeexecutedtoDARsatisfaction.DewateringDewateringshallbedoneviasubmersiblepumpsinwellsdistributedaroundtheperimeteroftheexcavation.Waterwillbepumpedtothenearbysea.ThepumpsshallbefedfromtwoElectricalsourcesforredundancy.DewateringshallbesubcontractedtoaProfessionalSpecialist.WaterProofingWaterproofingshallbedonebyaProfessionalSpecialistsubcontractorusingMaterialapprovedbyDAR. The water proofing activities are mainly in the Foundation stage, wherever the concretetouchessurroundingsoilandontheroofwherewehavetheCoolingTowers.RaftFoundations&BuildingConcreteworksThebuildingshallbedividedinto4Areas.Areasareseparatedbyconstructionjointsandthereforecanfollowdifferentscheduleofworksoncetheyreachthesuperstructurelevels.Concrete works shall be executed by an approved Concrete Subcontractor. For civil methodstatementlist,refertoAppendix7AQA/QCprocedurecoveringalltheactivitiesrelatedtotheconcreteworksshallbesubmittedtoDAR forapproval.The latterprovide forall thesamplingand testingactivitiescarriedout in thefieldand/or in the laboratory.Sourcesofmaterial i.e.suppliers/manufacturersandmaterial tobeused shall be in prior approved by DAR including working methods and delivery conditions.Transport,transportmeans,protection,delivery,storageandcertificationofcementshallbedoneinaccordancewithspecificationsandapprovedproceduresandtothesatisfactionofDAR.A bar bending schedule shall be submitted to DAR for approval. The number, size, form andpositionofallsteelreinforcingbars,ties,links,stirrupsandotherpartsofthereinforcementaretobe in accordance with the drawings and kept in the correct position in the forms withoutdisplacement during the process of vibrating, tamping and ramming the concrete in place. Theapprovedspacersshallbeusedduring theprocess.Theconcretecovershallnotexceed toleranceunlessparticularlyotherwisespecified.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 14 -

    Duringthepreviouslydetailedactivities,inspectionandtestsshallbeconductedasrequiredinthespecificationsandtoDARsatisfaction.Recordsshallbegenerated,maintainedandkeptforallthedurationof theprocess.Concreteshallbeplaced in thepositionsandsequences indicatedon thedrawingsorinthespecifications.Raft foundations shallbe constructed first,afterwateringproofingand screedingworks isdone.DifferentRaftssizeswillbeconstructed fordifferentareas.Sizeswillbecalculateddependingonloads invarious floorsandequipmentvibrations.Methodstatementsshallbesubmitted for largepouringareas.Backfillingwillbemadeon topof the raft foundations tobring the construction to the requiredlevels,priortoproceedingwiththedifferentfloorplans.Two large Tower cranes will be erected to cover most of the building area and adjacent steelworkshop.MobilecraneswillbeusedtocovertheminorareasunreachablebyTowerCranes.Theworksequencewillfollowourscheduleofworksinordertomatchthedeliveryandinstallationscheduleofmainequipment.Civilcrewsshallbeallocated toFoundations,Structures,andothercrewstoBuildings.Thecrewsshall be scheduled in accordance with the Construction Program. Concrete specified in thedocuments shall be obtained from approved batching plants. For workability and protection ofconcrete,admixturesshallbeused,ifneeded.For all concrete works, ordinary or Medium Sulfate Portland cement shall be used. Concretesurfacesadjacenttosoilshallbecoveredbybituminouspaint.Slumpcontrolshallbeexecutedandsamples shall be taken for strength control during the placing of concrete. Concrete will becompactedwiththeuseofavibrator.Afterwards,thenecessarycuringwillbedone.Foundation,columnandconcretewallFormworkshallbemadeofconventionalwoodenorsteelformwork.Formworks shallbeprepared for concreteplacingafter the controlofaxes,elevation,alignmentand thenecessarystrengtheninghavebeencarriedout.All formworksystemsshallbestrengthenedbyscaffoldingsandworkingplatforms.Theclient/PMCshallapprovethecompletedworks.PrecastConcreteworksPrecast hollow core panels and beamswill be subcontracted to a specialist company, followingapprovalbyDAR.ThiscompanyshallsupplyanderecttheprecastitemswiththeassistanceoftheConcreteSubcontractorsandCAT.Someof theworkswillbeerectedby the largeTowerCranesandtherestwithlongreach,properlysizedMobileCranesConcreteworksshallbeexecutedbyanapprovedConcreteSubcontractor.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 15 -

    A QA/QC procedure covering all the activities related to the precast concrete works shall besubmittedtoDARforapproval.EquipmentFoundationsOnce Material is approved and shop drawings produced and approved, Major Equipmentfoundations shall be designed, coordinated with concrete works and constructed on site inaccordancewithManufacturerrecommendations.FinishingWorksAll Sundry and finishing works shall be executed by C.A.T and by different approvedSubcontractorsinaccordancewithapprovedfinishingschedulesandMaterial.SelectionofFinishingMaterialwillbebasedontherequirementsoftheAcousticStudythatcatersfor thenoise requirementof theProjectandwith theAesthetic requirementsof thespecificationsdetailedinourAlternativeNo.2.EquipmentWorksOnce the major Equipment and Material are approved, manufacturer shop drawings will becoordinated and integrated into the Shop Drawings. C.A.T. shall also prepare the necessaryprocedures/methodstatementsforthemechanicalmaterialandequipmentinstallation,priortoanyInstallation.(SeeAppendix8forMechanicalMethodStatementlist).For the major equipments to be erected by C.A.T. the work is to be executed under the directsupervision of the supplier representative when required and in accordance with providedinstructions and manuals. All necessary measures shall be taken to protect and preserve thesuppliedequipment.C.A.Tshallexecutetheworkswithallnecessarysafetyandsecurityprecautions.Having the concrete foundations properly cured, brushhammered and shimmed to the rightelevation, the chillers,RO equipment, and othermechanical equipment shall be installed as perapprovedmethodstatementsontherespectivefoundationsleveledandproperlycentered.For pumps, preliminary alignment shall be carried out before grouting.All equipment shall beinstalledasperQC/DARrequirementsandvendorsspecificationsandrecommendations.SpecialPlatformonrail/tracksystemwillbemanufactured inourworkshop tobring thechillers,pumps and other equipment into the building and right to the location where they should beinstalled.Hydraulic jacks,telehandlersandspecialtoolswillbeusedtomaneuverinsidetheplantbuilding.Equipmenton the first floorcanbebrought inviaexternalplatformswith thehelpofacraneorfromtheinsideinthegroundfloorwiththeuseofelectricalhoists.Equipmentontheroofwillbeinstalledusingthetowercranesortelescopicexternalmobilecranes.CoolingTowersshall

  • Q06024-IDCP-PLN-GT-001-REV A

    - 16 -

    beassembledbythemanufacturer.AllMajorEquipmentshallbestarted,testedandcommissionedbythemanufacturers.PipingWorksShopDrawingsforpipingfabricationanderectionwillbepreparedandutilizedinthefabricationshop forpreparingspools, ready tobeerected.Allworksshallbecarriedout in linewithabove.Pipingerectionshallcommencewhenbuildingisready.FabricationandErectionPipefabricationworkshallstartinthefabricationshopinthedesignatedareaonsite.AnN.D.T.subcontractorwillbecarryingouttherequiredN.D.T.forC.S.weldsasperspecificationsdoneinthefabricationshopsothatanyrepairsarecarriedoutbeforetransportingthespoolstosite.Prior to fabrication, field checks shall be carried out to ensure that the shop drawings arecompatiblewiththesiteconditions.Copies of the shopdrawingsusedby the fabrication crews shallbegiven to the erection crews.Thesecopiesshallshowthenumbersassignedtotheweldingjointsandshallindicatewhichjointswerealreadytestedinthefabricationshop.Thisshallenablethesitecrewstocorrectlyidentifyandmark the welds performed on site. This shall ensure proper reporting and assist the N.D.T.crews/QCInspectorstoattendandcontrolallthefieldwelds.TheQA/QCofficeralongwiththeforemanresponsibleforthefabricationwillensurethatallweldson thedrawingsare clearlymarked todistinguish the fabricationwelds from the fieldwelds.Arecord of every day welds and N.D.T. will kept. Once fabrication, welding of the spools arecomplete, thespoolsshallbe transported tosite forerection.All thespools tobe taggedproperlypriortotransportationtosite.Allerectionworksshallbeinaccordancewiththedrawingsandspecifications.The fabricated spools shallbe transported to theirdesignatedareaonedayaheadof the startoferectiontoavoidanycongestionintheexistingfacilities.Oncethespoolsbelongingtothesystemareallerected,connectedtotherestoferectedpipesandchecked,thesystemwillbepunchedoutbyustoensurethatinstallationwascarriedoutasperthedrawings,fieldsupportsareallinposition.Oncesatisfied,allrelevantpaperworkwillbesubmittedtoDARandarequesttostarthydrostatictestingwillbeputin.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 17 -

    Electrical&InstrumentationWorksUpondesignapprovaland inaccordancewithmaterialspecifications,manufacturerandsupplierwillbesubmitted toClient forapproval,orderswillbeplaceduponsuppliersandweeklystatusreportswillberequestedtoensuretimelydeliverytosite.Transformers,switchboards,lightfixturesandfloodlightswillallbeinstalledaspermanufacturersrecommendations.Vendorsrepresentativeswillconductthecommissioningoftheswitchgearsandthetransformers.(SeeAppendix9forElectricalMethodStatementlist).AllElectricalSwitchgearsandMCCswillbedeliveredinsectionsandassembledonsitebyC.A.T.except for the 3.3 KV Switchgears and Soft Starters which shall be assembled by theManufacturer/Supplier.Supervision of installation, checking of Bus Bars jointing, Testing and Commissioning will beperformedbythemanufacturer.AllTransformerswillbedeliveredandinstalledonsitebyC.A.T.Supervisionofinstallation,TestingandCommissioningwillbeperformedbythemanufacturer.All raceways, cables, lighting, electrical accessories, lo current systems will be delivered andinstalledonsitebyC.A.T.Cable terminations will be made by C.A.T. except for 11 KV cables which shall be made byapprovedandlicensedsubcontractor.Supervisionofinstallation,TestingandCommissioningofLoCurrentsystemswillbeperformedbytheSuppliers.All electrical cables shallbe laid according to the cable schedules and adhering to the followingsteps:Prior to cable installation,a cablecutting scheduledetailing the cablenumber, type, size, length,and cable drum number shall be established to avoid and minimize any wastage as much aspossible.Thesaidschedulesshallbebasedonthefollowingdata:

    Actualindividualcablelength. Cablelengthonthedrum Placeoninstallationtominimizedoublehandling

    Cable drums shall be transported to their respective site. Actual length of the cable shall bemeasuredonsiteandarecordofeachcablenumbertypeandlengthshallbemade.Alldistributionboards (lighting,smallpower),PushbuttonControlstation,andmarshallingboxwillbe connected in accordancewithElectrical Installation Specification, attached schedules and

  • Q06024-IDCP-PLN-GT-001-REV A

    - 18 -

    drawings.Alllightningandgroundingshallbedoneasperspecificationandwithrelevancetotheapplicabledrawings.Electricalsystemswillbe testedasperrelevant testprocedures thatwillbesubmittedduring thecourseoftheproject.Instrumentation and control will be subcontracted to a nominated subcontractor and systemintegrator.InstrumentationandControlSubcontractorwillinstallallControlsandInstrumentationasperhisapprovedMethodStatement.HeshallalsoinstallandterminatetheinstrumentcablesasperC.A.T.MethodStatement.Absolutelynoprecommissioningshallstartuntilthegroundingsystemiscompletedandtested.Landscape,Roads,CurbstoneandSidewalksWorksOncethebuildingiserectedandmainEquipmentinstalledandtheneedforlargemobilecranesisover,theaboveworkshallstart,notingthatthefinalareatobe landscaped issubjecttoQC/UDCapproval.4.4 ConstructionoftheHEXBuilding&ETSsConstructionofallHeatExchangersbuildingsandETSswillbesimilartomethodologytotheonceoftheplant.Closecoordinationwillbemadewithothercontractors,viaDAR,inordertopossesssitesofHEXsandtocoordinateworksforETSs.4.5 CalibrationQualified technicians will be utilized to carry out the calibration of the instruments. Recordsdocumenting the calibrationwillbekept in ourDocumentControlDepartment.All instrumentsusedforcalibrationshallbecertifiedbyaThirdparty.Ateamshallbeassignedtoremovetheskidmountedinstrumentsandtheirreinstallationalongwiththefieldinstruments.Dedicated instrumentfitterswillberesponsibleforthe installationofthetubingonsiteunderthesupervisionoftheinstrumentandinstrumentsupervisor.Thefitterswillproceedwiththetestingofthetubingaftercompletiontheinstallation.After complete installationof the tubing, instruments, instrument cablesandall required testing,loopcheckingshallstartaccordingtoloopsheetspreviouslypreparedbytheinstrumentengineerandapprovedbytheClient.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 19 -

    4.6 TestingandPreCommissioningUpon thecompletionofconstructionofan individualsystem,a testing /precommissioningcrewshallbeassigned tocarryout the final inspectionbeforeoffering the system to theEmployer forfinalinspection.Thiscrewshallberesponsible:

    Ensuringthattheinstallationwascarriedoutaspertheprojectsspecifications. Makecertainthatalltherequiredtestinghadbeencarriedoutsuccessfully. Confirmthatalltherelateddocumentationisinorder

    During the constructionphase theQA/QC engineer alongwith thediscipline engineers shall beresponsible for maintaining the quality and ensuring that the supervisors are carrying out theinstallationasperthedrawingsandspecifications.Theinspectionfacilitiesutilizedonthisprojectshallinclude:

    HydrostatictestingAscheduleshallbemadeandsubmittedtotheclientapproval.Thisscheduleshallindicatethedateandthelocationinthefieldoftheproposedhydrotest.Pipeflushingandcleaningtobeincluded. LoopCheckingThe loop sheets shall be prepared and submitted to the client for approval.A schedule of loopcheckingshallbemadeandagreedwiththeclienttoavoidanydisruptionsandensurethesmoothcontinuityofwork.

    TestingandinspectionproceduresDetailedtestingandinspectionproceduresshallbepreparedatthebeginningoftheproject.Theseproceduresshallcoveralltheaspectsoftheworksandbeimplementedthroughouttheexecutionoftheproject.Oneverysuccessfultestcompletion,resultsshallbetranscribedontoformats,copiesofwhichshallbesubmittedtothecompanyfortheirrecords.4.7 CommissioningC.A.T.isconsideringemployingasubcontractorfortheTestingandcommissioningactivities.Thissubcontractor shall check the design drawings at the design stage. Commissioning will beperformedfollowingonapprovedMethodStatementwhichshallbesubmittedduringthecourseoftheprojectprovidingelectricityandotherservicesareavailable.4.8Training

    C.A.T.throughitssubcontractorsandsupplierswillprovidetrainingservicesforQCpersonnelasspecifiedinourproposal.Thetrainingprogramwillbesetupformanagers,supervisors,operatorsandmaintenancepersonnel.

  • Q06024-IDCP-PLN-GT-001-REV A

    - 20 -

    A fullprogramwill bedeveloped indetail and in close cooperationwithQC. Such a service isconsidered one of the most important steps for a successful execution of the project includingcommissioningandmaintenance.TheforeseenTrainingAidsarebutnotlimitedto:

    TrainingManual,preparedforthisspecificpurpose.OperationManual.MaintenanceManual.SafetyManual.

    5. QualityAssurance(QA)We confirm that all QC requirements and recommendations shall be adhered to and put intoapplication.TheQAPlan for IDCPhasbeen issued tomeet theEmployerandC.A.T.QAsystemrequirements.6. Health,SafetyandEnvironment(HSE)C.A.T. ensures that all construction employees are aware of and adhere to all safety rules andregulations.C.A.T.ensuresthepromotionofsafety,health,andenvironmentprotectionasamutualobjective for management and employees at all levels, including subcontractors. We will givedetailedsafetyandsecurityinstructionstoeachsubcontractorpriortothecommencementofworkandduringtheconstructionperiod.We confirm that all QC requirements and recommendations shall be adhered to and put intoapplication.TheHSEPlanforIDCPhasbeenissuedtomeettheEmployerandC.A.T.requirements.ListofAppendixes:Appendix1PROJECTCHARTAppendix2ORGANIZATIONCHARTAppendix3LONGLEADITEMSLISTAppendix4PROJECTKEYMILESTONEAppendix5TEMPORARYFACILITIESAppendix6LISTOFSUBCONTRACTORSAppendix7CIVILMETHODSTATEMENTLISTAppendix8MECHANICALMETHODSTATEMENTLISTAppendix9E&IMETHODSTATEMENTLISTAppendix10DESIGNINTENTREPORT

  • PMC DAR AL HANDASAH

    CONTRACTOR C.A.T. INTERNATIONAL QATAR W.L.L

    DESIGN TEAM STANLEY CONSULTANTS INC.

    EMPLOYER QATAR COOL

    APPENDIX 1 PROJECT CHART RELATIONS: FORMAL AUTHORITY / COMMUNICATIONS / REPORTING

    COORDINATION LIMITED AUTHORITY

  • E&I Foreman -HEX & ETS

    B. ShamshadE. Syaiaozy

    E&I Engineer -HEX & ETS

    G.Faraj

    Engineer - HEX & ETS

    R. Ragih

    Mech. Foreman -HEX & ETSA. Farhoud

    Civil Gen. F/M -HEX

    G. Kodoor

    Civil Foreman -HEX

    Civil Foreman -HEX

    QA / QC Engineer

    N. Agtarap

    QA / QC Inspector - HEX

    A. Kumaraswamy

    QA / QC Inspector - HEX B. Mahendran

    Ass. Safety Engineer - HEX &

    ETS

    Safety Inspector -HEX & ETS

    A. Mohd

    Mech. services Eng.

    Y. HamdaniM. Wehbeh

    Bldg. Mech. Foreman

    Bldg. Mech. Foreman

    A. El-Khoury

    Piping Eng.D. HannaE. Engalia

    Piping Foreman

    A. KirubanaJ. Olvida

    R. Mantilla

    S.ST.F/MB. Sayyah

    Instrument Eng.

    A.A Hajjar

    E&I Supervisor

    F. Nassar

    E&I ForemanJ. EspadeliaS. PanikerS. Nassar

    J. Tiakarajan

    Cons. Mang. Mech.

    Z.Nazzal

    Deputy PM -Cons. Mngr

    M,E&IP. Natrajan

    Civil Foreman -B. Fetiluna

    Civil Foreman -

    Civil Engineer K. Wehbe

    Cons. Mngr. Civil

    N. Saba

    S/CNDT

    Ins/Pain

    Civil Gen. F/M

    N. Bou Daher

    N. Reghupathy

    R. Babu

    Proc.CoordintorA. Pacedio

    (**)

    Local Purch.I.A. Kadir

    Sr. Eng. Coord.F. Takieddine

    (**)

    Engineering S/CM/S Stanley

    Shop Drawing S/C

    M/S DEP

    QA/QC Eng.D. Mankikis

    (*)

    QA/QC Insp. CivilA. PeronaS. GeorgeM. Kumar

    QA/QC Insp. Mech.

    R. MarquezA. Mejorada

    J. Obaob

    QA/QC Insp. E&I.F. Medina

    U. MaheshwaranV. Chinnasamy

    Sr. Safety Eng.

    R. Seyouri

    Safety SupervisorG. Felix

    Safety Off.A. TiroJ. Page

    G. Saliba

    Scaff. F/M

    Scaff. F/M

    Ass. Str. KeeperT. Botros

    Store Keeper

    Time KeeperA. Majeed

    A. JacksonM. AhmedS. Riyas

    Wages ClerkA. Kannan

    K. Lal

    C. Imp. HolderJ. KantinalM. Samuel

    AccountantA. Sarkis

    Ins. Off.G. Tabet

    Office BoyA. Devasia

    A. KhanS. Selvaraj

    Sec / TypistJ. MathewV. M. Nair

    A. PrasadanS. Ali

    Transp. OffP. Bala.

    PR/PassportR. KoshyS. Moolya

    Admin. Mngr.

    M. Saadeh

    CampbossN. Asaad

    Watchman

    Watchman

    Project Manager

    Nazih Ghazi

    Cost Eng / Plann Eng

    C. AshkoutiD. Dahwan

    Contract Eng.

    F. Bustani

    QSG. Gobatan

    Project Coord.

    Mohan M.G.

    Sr. Planning Eng.

    N.A. Nahed

    Sr. ELEC. Eng.

    R. Prasad

    Equip. Eng.H. RahhalP. Sarudar

    Equip. Foreman

    R. PrabhuE. E. ElrizzG. Vijayaku

    Fabr. F/MA. Atem

    S/ Contractors

    ELEC. Eng.

    N. Faysal

    AREA PROC. UNIT

    C.A.T. H.OC.O.O

    M. El Hajjar

    SurveyorZ. Daher

    Ass. Eng. - HEX & ETS

    G. Bitar

    T&C - Mech. Eng.H. JumaoA. Basak

    T&C - Elec. Eng.Subramanian K.

    T&C Sub Contractors

    Doc. ControlD. Ramos

    Deepak E.P.

    Expedition / IT Admin

    R. Geryes

    Acc. ClerkJ. Khan

    CAD Operator T. Thomas

    Weld. F/MW.A. Rish

    (*) QA/QC Engineer has the full right to Contact the Area Manager and the Group QA/QC Manager in case he feels a non cooperation om site or he sees a matter that reflects on the Group's global QA/QC system (**) The Sr. Eng. Coordinator & The Procurement Coordinator communicate & interact directly with the Area Procurement office for Design/Procurement related matters.

    Qatar Area ManagerM. Matar

    Qatar CoolN.El- Saadi

    PMC - DARK. Salman

    Civil Engineer -HEX Bldgs

    E. Harb

    Inst & Cntrl S/CM/S CIMAC

    Civil Gen. F/M J. Chalitta

    Civil F/M

    N. Maccagerr

    J. Lukose

    T. Ahmad

    Excavation

    Dewatering

    Concrete

    Precast

    S/CTes./Bal.

    HEX BLDGS & ETS's

    APPENDIX 2

    ORGANIZATION CHART

  • APPENDIX 3

    LONG LEAD ITEMS LIST Item Description Manufactures/Supplier Name 1. HV/MV Switchgears Siemens/ABB/Schneider/ Transformers & Starters Ben Shaw or Approved Equal 2. Chillers Trane/York or Approved Equal 3. Cooling Towers Hamon/BAC or Approved Equal 4. Pumps Goulds/Weir/Flowserve or Approved Equal 5. Heat Exchangers Alfa Laval or Approved Equal 6. R.O. Plant Saudi Berkefeld or Approved Equal

  • APPENDIX 6

    LIST OF SUB CONTRACTORS C.A.T. International Qatar W.L.L proposes to subcontract parts of the works and to supply principal items of the plants as follows: Work Description SubContractor Address

    1. Site Investigation ACTS P.O.Box 22159, Doha, Qatar

    2. Excavation & Backfilling ACI P.O.Box 20040, Doha, Qatar

    3. Dewatering United Equipment P.O.Box 5673, Doha, Qatar

    4. Water Proofing BMC Qatar P.O. Box 24407, Doha, Qatar

    5. Concrete Works Somac Group P.O. Box 7098, Doha, Qatar

    6. Pre Cast Concrete Slabs United Precast Doha, Qatar

    7. Doors, Windows,& Louvres

    8. False Ceiling

    9. Raised Flooring

    10. Painting Hempel/Jotun Doha, Qatar

    11. Elevator

    12. Roads & Pavement

    13. NDT Qatar Inspection Services Doha, Qatar

    14. Controls & SCADA Cimac Or Approved Equal Dubai, U.A.E

    Note: the above names are only for reference. Other Subcontractors will be submitted as applicable. Selection will be based on Compliance to specifications and Milestones

  • Reference No1 Preconstruction Survey Q06024-IDCP-MOS-CI-001

    2 Excavation & Backfilling Q06024-IDCP-MOS-CI-002

    3 Reinforcement Q06024-IDCP-MOS-CI-003

    4 Concrete Receiving, Testing, Placing & Curing Q06024-IDCP-MOS-CI-004

    5 Sub-Structure Waterproofing Q06024-IDCP-MOS-CI-005

    6 Major Concrete Placement for Area (3) Raft Foundation Q06024-IDCP-MOS-CI-006

    7 Erection of Pre-Stressed Beams & Hollow Core Slabs Q06024-IDCP-MOS-CI-007

    APPENDIX 7

    Structural / Civil

    CIVIL METHOD STATEMENT LIST

  • Reference No1 Rigging ,installation and pipe connection of chillers Q06024-IDCP-MOS-ME-001

    2 Rigging , erection and pipe connection of cooling towers Q06024-IDCP-MOS-ME-002

    3 Rigging , installation and pipe connection of chilled water pumps Q06024-IDCP-MOS-ME-003

    4 Rigging , installation and connection of condenser water vertical turbine pumps Q06024-IDCP-MOS-ME-004

    5 Rigging ,installation and connection of plate heat exchangers Q06024-IDCP-MOS-ME-005

    6 Installation and connection of tertiary pumps Q06024-IDCP-MOS-ME-006

    7 Rigging , installation and connection of expansion tanks Q06024-IDCP-MOS-ME-007

    8 Installation and connection of pressurization units Q06024-IDCP-MOS-ME-008

    9 Installation and connection of in line centrifugal solid separators on first floor Q06024-IDCP-MOS-ME-009

    10 Installation and connection of refrigerant silencers on roof Q06024-IDCP-MOS-ME-010

    11 Installation of condenser tube cleaning system including 4 way valves Q06024-IDCP-MOS-ME-011

    Reference No12 Installation of sluice gate valves in cooling tower basins Q06024-IDCP-MOS-ME-012

    13 Installation of process valves Q06024-IDCP-MOS-ME-013

    Reference No14 Rigging , installation and pipe connection of RO system Q06024-IDCP-MOS-ME-014

    15 Installation and connection of transfer pumps Q06024-IDCP-MOS-ME-015

    Reference No

    16 Installation of inserts (pipe connections) in concrete tanks and cooling tower basins Q06024-IDCP-MOS-ME-016

    17 Installation of Overhead cranes Q06024-IDCP-MOS-ME-017

    18 Tagging and labelling of pipe,duct and equipment Q06024-IDCP-MOS-ME-018

    19 Installation of Antivortex fittings in concrete tanks Q06024-IDCP-MOS-ME-019

    20 Pipe handling and storage Q06024-IDCP-MOS-ME-020

    21 Installation of process ,HVAC and domestic water pipes Q06024-IDCP-MOS-ME-021

    22 Insulation of Process , HVAC and domestic water pipes Q06024-IDCP-MOS-ME-022

    23 Jacketing of pipes Q06024-IDCP-MOS-ME-023

    24 Fabrication and installation of pipe supports Q06024-IDCP-MOS-ME-024

    25 Painting of pipes and supports Q06024-IDCP-MOS-ME-025

    26 Hydrotesting of pipes Q06024-IDCP-MOS-ME-026

    27 Installation and connection of diesel tanks Q06024-IDCP-MOS-ME-027

    28 Introducing new equipment into the system at different stages Q06024-IDCP-MOS-ME-028

    Reference No29 SMAW Welding Q06024-IDCP-MOS-ME-029

    30 Installation and soldering of copper pipes Q06024-IDCP-MOS-ME-030

    Reference No1 Installation and pipe connection of electric water heaters ( admin part ) Q06024-IDCP-MOS-PL-001

    2 Installation of cast iron storm water and drainage pipes . Q06024-IDCP-MOS-PL-002

    3 Installation of frames for drainge gratings and manhole covers Q06024-IDCP-MOS-PL-003

    4 Installation of floor drains , roof drains and flower bed drains Q06024-IDCP-MOS-PL-004

    5 Installation of sanitary fixtures , toilet mixers and accessories ( admin part ) Q06024-IDCP-MOS-PL-005

    6 Installation of oil interceptors Q06024-IDCP-MOS-PL-006

    7 Installation and pipe connection of submersible pumps in basement Q06024-IDCP-MOS-PL-007

    APPENDIX 8

    ME Equipment

    MECHANICAL METHOD STATEMENT LIST

    Valves

    RO System

    Common to all Systems

    Welding and Soldering

    Drainage and Plumbing

  • Reference No

    1 Rigging , Installation and connection of fire pump room equipment and components Q06024-IDCP-MOS-FP-001

    2 Installation of preaction ,deluge , alarm zone valves and siamese connections Q06024-IDCP-MOS-FP-002

    3 Installation of fire hose cabinets Q06024-IDCP-MOS-FP-003

    4 Installation of fire fighting grooved pipes and fittings ( vertical and horizontal ) Q06024-IDCP-MOS-FP-004

    5 Installation of diesel pump exhaust with supports up to roof Q06024-IDCP-MOS-FP-005

    6 Installation of FM-200 fire fighting system Q06024-IDCP-MOS-FP-006

    Reference No1 Installation of chemical treatment systems Q06024-IDCP-MOS-WTR-001

    2 Chemical cleaning of pipes Q06024-IDCP-MOS-WTR-002

    Reference No1 Rigging , installation and pipe connection of Air handling units Q06024-IDCP-MOS-AC-001

    2 Installation and pipe connection of fan coil units Q06024-IDCP-MOS-AC-002

    3 Installation and duct connection of fresh and exhaust fans Q06024-IDCP-MOS-AC-003

    4 Galvanised duct and accessories fabrication and installation Q06024-IDCP-MOS-AC-004

    5 Internal and external Insulation of galvanised sheet metal duct Q06024-IDCP-MOS-AC-005

    6 Jacketing of galvanised sheet metal duct Q06024-IDCP-MOS-AC-006

    7 Installation of grilles , diffusers , louvers ,dampers sand trap louvers Q06024-IDCP-MOS-AC-007

    Fire Fighting Systems

    Chemical Treatment

    HVAC

  • Reference No1 11KV Switchgear Q06024-IDCP-MOS-EL-001

    2 3.3KV MCC & Soft Starter Q06024-IDCP-MOS-EL-002

    3 415V MCC & VFD Q06024-IDCP-MOS-EL-003

    4 11KV/3.3KV Transformer Q06024-IDCP-MOS-EL-004

    5 11KV/415V Transformer Q06024-IDCP-MOS-EL-005

    6 Emergency Generator Q06024-IDCP-MOS-EL-006

    7 Battery Charger & UPS Q06024-IDCP-MOS-EL-007

    8 Panel Board & Junction box Q06024-IDCP-MOS-EL-008

    9 Earthing System Q06024-IDCP-MOS-EL-009

    10 Lightning Protection System Q06024-IDCP-MOS-EL-010

    11 Wiring Accessories & Small Power Devices Q06024-IDCP-MOS-EL-011

    12 Interior / Exterior & Emergency Lighting Q06024-IDCP-MOS-EL-012

    13 Wires & Cables Q06024-IDCP-MOS-EL-013

    14 Cable Terminations Q06024-IDCP-MOS-EL-014

    15 Raceways Q06024-IDCP-MOS-EL-015

    Reference No1 Voice & Data System Q06024-IDCP-MOS-LC-001

    2 Security Access Control System Q06024-IDCP-MOS-LC-002

    3 CCTV System Q06024-IDCP-MOS-LC-003

    4 Fire Alarm System Q06024-IDCP-MOS-LC-004

    Reference No1 Instuments Q06024-IDCP-MOS-IC-001

    2 PLC / SCADA System Q06024-IDCP-MOS-IC-002

    APPENDIX 9

    A- HV & MV ELECTRICAL SYSTEM

    B- LOW CURRENT SYSTEMS

    C- INSTRUMENTATION

    E & I METHOD STATEMENT LIST

  • Integrated District Cooling Plant at The Pearl, Qatar

    Design Intent Report -Conceptual Design Edition

    Project Number: Q06024 - IDCP

    FINAL REPORTSeptember 2006

    C.A.T. Qatar International W.L.L.Doha, Qatar

  • Q06024-IDCP-RPT-GT-001-REV 3

    Integrated District Cooling Plant at The Pearl, Qatar Q06024-IDCP-RPT-GT-001-REV 3 Design Intent Report

    C.A.T. Qatar International W.L.L. Doha, Qatar

    Conceptual Design Edition September 28, 2006

  • Q06024-IDCP-RPT-CI-001-REV 3 i Stanley Consultants

    Table of Contents

    Section 1 - Project Description .....................................................................................................1-1 Section 2 - Civil Engineering and Landscaping Design Statement ..............................................2-1

    General......................................................................................................................................2-1 Compliance Statement ..............................................................................................................2-1 Traffic Control ..........................................................................................................................2-2 Paving .......................................................................................................................................2-2 Drainage....................................................................................................................................2-2 Landscaping ..............................................................................................................................2-2

    Section 3 - Architectural Design Statement..................................................................................3-1 General......................................................................................................................................3-1 Compliance Statement ..............................................................................................................3-1 Building Exterior ......................................................................................................................3-1 Accessibility and Maintenance .................................................................................................3-2 Containment Requirements.......................................................................................................3-2 Building Interior .......................................................................................................................3-3 Occupancy ................................................................................................................................3-3

    Section 4 - Structural Design Statement .......................................................................................4-1 General......................................................................................................................................4-1 Compliance Statement ..............................................................................................................4-1 Design Criteria ..........................................................................................................................4-1

    Codes and Standards .............................................................................................................4-1 Design Loads ........................................................................................................................4-2 Material Properties................................................................................................................4-3 Concrete Design....................................................................................................................4-3 Structural Steel Design .........................................................................................................4-3 Material .................................................................................................................................4-3 Structural System..................................................................................................................4-4

  • Q06024-IDCP-RPT-CI-001-REV 3 ii Stanley Consultants

    Section 5 - Mechanical Design Statement ....................................................................................5-1 General......................................................................................................................................5-1 Compliance Statement ..............................................................................................................5-1 Chilled Water Plant Process......................................................................................................5-3

    Codes and Standards .............................................................................................................5-3 General..................................................................................................................................5-4 Chillers..................................................................................................................................5-4 Cooling Towers.....................................................................................................................5-6 Chilled Water Pumping Scheme...........................................................................................5-8 Condenser Water Pumping Scheme......................................................................................5-8 Piping System .......................................................................................................................5-9 Chemical Treatment System .................................................................................................5-9 Miscellaneous .....................................................................................................................5-10

    Reverse Osmosis (R.O.) System.............................................................................................5-10 Energy Transfer Stations.........................................................................................................5-11 Heating, Ventilating, and Air-Conditioning ...........................................................................5-11

    Standards and Codes ...........................................................................................................5-11 Outdoor Design Conditions ................................................................................................5-12 Indoor Design Conditions ...................................................................................................5-12 Minimum Ventilation Requirements ..................................................................................5-12 System Description .............................................................................................................5-13

    Plumbing.................................................................................................................................5-13 Codes and Standards ...........................................................................................................5-13 Water Supply Network .......................................................................................................5-14 Waste Water Drainage ........................................................................................................5-15 Waste Water Drainage ........................................................................................................5-15

    Compressed Air ......................................................................................................................5-16 Standards and Codes ...........................................................................................................5-16 Service Air ..........................................................................................................................5-16

    Fire Suppression System.........................................................................................................5-16 Codes and Standards ...........................................................................................................5-16 Fire Suppression System.....................................................................................................5-16

    Section 6 - Electrical Design Statement........................................................................................6-1 General......................................................................................................................................6-1 Compliance Statement ..............................................................................................................6-1 Extra Low Voltage....................................................................................................................6-2 Applicable Codes and Standards and Basic Design Criteria ....................................................6-2 Ambient Conditions ..................................................................................................................6-3 Electrical Power Distribution....................................................................................................6-3

    Overall System Description ..................................................................................................6-3 Emergency Engine Generators .................................................................................................6-4 415/240-Volt Distribution Network..........................................................................................6-4

    Uninterruptible power Supply UPS ......................................................................................6-4 Lighting and Emergency Lighting ........................................................................................6-4 Boards ...................................................................................................................................6-5 Circuit Breakers, Residual Current Interrupters, Contactors and Disconnect Switches .......6-5 Cables and Wires ..................................................................................................................6-6 Raceways ..............................................................................................................................6-6 Earthing Network..................................................................................................................6-6 Lightning Protection .............................................................................................................6-7

  • Q06024-IDCP-RPT-CI-001-REV 3 iii Stanley Consultants

    Extra Low Voltage....................................................................................................................6-7 Fire Alarm System ................................................................................................................6-7 Voice and Data System.........................................................................................................6-8 Q-Tel GSM Station ...............................................................................................................6-8 Closed Circuit Television System (CCTV) ..........................................................................6-8 Access Control and Door Status System...............................................................................6-9

    Section 7 - Control System Design Statement ..............................................................................7-1 General......................................................................................................................................7-1 Compliance Statement ..............................................................................................................7-1 Control Philosophy ...................................................................................................................7-2

    Chilled Water System ...........................................................................................................7-5 Cooling Towers.....................................................................................................................7-6 Make-Up Water System........................................................................................................7-6 Blowdown System ................................................................................................................7-6 Electrical System ..................................................................................................................7-6

    Instrumentation .........................................................................................................................7-6 Field Instruments ..................................................................................................................7-6

    Section 8 - Utility Services Design Statement ..............................................................................8-1 General......................................................................................................................................8-1 Compliance Statement ..............................................................................................................8-1 Chilled Water ............................................................................................................................8-1

    Codes and Standards .............................................................................................................8-1 System Description ...............................................................................................................8-2

    Potable Water............................................................................................................................8-2 Codes and Standards .............................................................................................................8-2 System Description ...............................................................................................................8-2

    Sanitary Sewer ..........................................................................................................................8-2 Codes and Standards .............................................................................................................8-2 System Description ...............................................................................................................8-2

    Storm Sewer..............................................................................................................................8-2 Codes and Standards .............................................................................................................8-2 System Description ...............................................................................................................8-3

    Section 9 - Maintenance and Accessibility ...................................................................................9-1 General......................................................................................................................................9-1 Compliance Statement ..............................................................................................................9-1 Maintenance and Accessibility .................................................................................................9-1

  • Q06024-IDCP-RPT-GT-001-REV 3 1-1 Stanley Consultants

    Section 1

    Project Description

    The Pearl, Qatar is a 400 hectare man-made island located off the Eastern coast of Qatar approximately 20 kilometers north of the Doha central business district and east of the West Bay Lagoon. The Pearl Island is connected to the mainland by a causeway. This island is being developed (United Development Company) to include residential and commercial usage arranged around three primary marinas, including hotels, shops, and residential villas and apartments.

    The roads and infrastructure for The Pearl Island development were completed under a separate contract to support the entire island. The road work consists of roads, bridges, underpass, culverts, surface water drainage, signage, and roadway lighting. The infrastructure work consists of potable water, sanitary sewer, irrigation transmission, chilled water distribution, telecommunications civil work, and electrical distribution.

    Chilled water has been a primary medium for the transfer of heat from building coils to the refrigeration system since the beginning of heating, ventilating, and air-conditioning design. Providing chilled water from a centrally located plant is an energy efficient and low maintenance means of rejecting heat from air-conditioning systems across a localized campus, whether that campus is a university setting, industrial complex, or large urban site. Over the last five years or more, district energy has exploded on to the scene in the Middle East becoming a necessary utility for new developments.

    The Integrated District Cooling Plant (IDCP) at The Pearl Project includes a new central chilled water plant to serve the cooling needs for the proposed building construction on the island. Qatar Cool will own and operate this plant upon completion and have established a design-build

  • Q06024-IDCP-RPT-GT-001-REV 3 1-2 Stanley Consultants

    contract with C.A.T. International for the construction of this plant. The new development consists of several high-rise buildings and villas, which will use the chilled water from the IDCP to serve their air-conditioning needs in the most efficient manner possible. Each building will include an energy transfer station or heat exchanger as the point of use for chilled water.

    The chilled water generated at this facility will be provided for the following:

    Customer loads at energy transfer stations or heat exchangers.

    Customer loads at valve pits (Take-off Chambers).

    Plant cooling system including, air handling units and fan coil units.

    The IDCP is arranged on site to accommodate the construction of the buildings and the island roads and infrastructure and the plant will architecturally be tied into the aesthetics of the surrounding building structures. The plant will have a guaranteed capacity of 115,000 tons expandable to 120,000 tons (ARI Tolerance) using forty-six (23 pairs) 2,500-ton nominal electric motor-driven centrifugal chillers. Provisions will be incorporated into the design of the IDCP for future expansion using two 2,500-ton nominal electric motor-driven chillers. The chillers will be in a series-series, counter flow arrangement utilizing a direct primary pumping scheme.

    The heat picked up by the chiller refrigeration cycles will be rejected via twenty-four 5,000-ton cooling tower cells. Each cooling tower cell will serve up to two chillers and will be piped in a headered arrangement such that each cell can be used with any combination of chillers. The cooling towers will be constructed of fiberglass and will be field-erected on the roof of the plant to conserve space on the site for other use. Aesthetic enhancements to the new building will visually compliment the architecture of the area per UDC approval.

    Utilities serving the IDCP will be installed by the Infrastructure Contractor under a separate contract with the Owner. The chilled water distribution system will routed to a vault at the limits of the plant site as depicted in the Conceptual Design Drawings.

    The plant will hydraulically operate as two independent facilities; each connected to new underground chilled water distribution systems. Chilled water will be delivered to network through a constant flow, direct primary pumping scheme. The Pearl Chilled Water Distribution System will be a looped, underground distribution network served by the IDCP and installed under a separate infrastructure contract as described above.

    New high-voltage transformers will be provided by the infrastructure contractor and connected to the IDCP to serve the power requirements of the plant.

    The control system will utilize a SCADA control system for monitoring and operation of the new equipment, except for the chillers, which will be started locally. This system will allow control of the new facility from operator workstations, located in the new plant control room. The system will utilize digital communications for remote monitoring and/or control of the various systems within the plant.

  • Q06024-IDCP-RPT-CI-001-REV 3 2-1 Stanley Consultants

    Section 2

    Civil Engineering and

    Landscaping Design Statement

    General This section of the Design Intent Report includes the narrative description of the Civil Engineering and Landscape Site Planning for the Integrated District Cooling Plant (IDCP) at The Pearl, Qatar. Site survey data obtained during the course of this project will form the basis for the development of the grading and paving design. Discussions between the Owner, Qatar Cool, PMC, the Contractor, C.A.T. International (CAT), and the Design-Build Engineer, Stanley Consultants are detailed in Exhibit A Project Correspondence.

    Compliance Statement The Civil Engineering and Landscape Site Planning design will comply with all portions of the Tender Documents prepared for Qatar Cool and issued by DAR during the tender phase. These documents include the general requirements, tender specifications, tender drawings, and the appropriate addendums and tender circulars issued for clarification, except as noted below:

    Plant Arrangement: The IDCP will be based upon the plant arrangement from the Alternate 2 bid proposed by CAT and accepted by Qatar Cool prior to contract award.

    Site Layout: The latest revisions to the U-07 plot limits will form the basis of the site layout and grading and paving design.

    Access Road Width: Service access roads around the plant will be wider than 6 meters at areas designated for equipment installation and removal from the plant building as indicated in Section Q0547/a-SPC-TR-01 REV 1 of the Tender Specifications. Paved equipment staging areas will be provided at these locations to facilitate those operations.

  • Q06024-IDCP-RPT-CI-001-REV 3 2-2 Stanley Consultants

    Traffic Control Construction activities will be coordinated to minimize the impact on traffic flow in the vicinity of Plot U-07. In general, traffic generated by the IDCP is low and as such is not expected to impact the traffic of the area surrounding Plot U-07.

    Paving A new service access drive will be provided to the site from the north and will serve the normal operational traffic of the IDCP as well as to support maintenance and delivery activities for the plant.

    All paving will conform to local codes and standards as well as Section 6 of QCS 2002.

    Drainage The drainage collection system will run along the roads surrounding the site and will consist of storm sewer piping, manholes, gullies, and swails. Storm water run-off will be collected by the gullies and swails. Manholes will be placed not more than 75 meters apart and will be used for inspection of the storm water system.

    Landscaping The soft landscape at ground level will use tree groups in stone mulch (10-cm crushed stone mulch to cover all unplanted and unpaved areas), towards the plot boundaries, providing framed views of the building, with ground cover and shrubs closer to the building, screening the service ring road and providing the first tier of planting to the building. Trees should be of a single, spreading, flowering variety, shrub to comprise a single type of ornamental grass such as Pennisetum alopecuroides, and ground cover of a spreading flowering succulent variety. The same ground cover and ornamental grass shall be used to the planter behind the battered ground floor parapet wall. All planting for the project will be appropriate to the exposed seashore conditions of the site and island. Trees to be minimum 250-cm overall height, shrubs and ornamental grasses grown.

    The IDCP building will include planters as required to meet the agreed upon architectural appearance of the plant relative the surrounding area.

  • Q06024-IDCP-RPT-AR-001-REV 3 3-1 Stanley Consultants

    Section 3

    Architectural Design Statement

    General This section of the Design Intent Report includes the narrative description of the architectural design for the Integrated District Cooling Plant (IDCP) at The Pearl, Qatar. Discussions between the Owner, Qatar Cool, PMC, the Contractor, C.A.T. International (CAT), and the Design-Build Engineer, Stanley Consultants are detailed in Exhibit A Project Correspondence.

    The IDCP will be designed as an attractive, functional, building that acknowledges and expresses the buildings purpose. The new building and cooling towers should be considerate of the appearance, scale, and other features of the surrounding structures and at the same time, minimize the impact of the building on the surrounding visual and aesthetic environment, as well as provide for future horizontal expansion.

    Compliance Statement The Architectural design will comply with all portions of the Tender Documents prepared for Qatar Cool and issued by DAR during the tender phase. These documents include the general requirements, tender specifications, room data sheets, tender drawings, and the appropriate addendums and tender circulars issued for clarification, except as noted below:

    Plant Arrangement: The IDCP will be based upon the plant arrangement from the Alternate 2 bid proposed by CAT and accepted by Qatar Cool prior to contract award.

    Building Exterior The design must consider the buildings physical and visual impact on the site and its relative scale to surrounding structures.

    There are three main components to the proposed building; the operational plant, the cooling towers and the Administration Building.

  • Q06024-IDCP-RPT-AR-001-REV 3 3-2 Stanley Consultants

    The operational plant is a two floor building; ground with a double height, first and partial basement.

    There are two rows consisting of 12 cooling towers each that sit on top of the operational plant.

    The Administration Building is a three floor building; ground, mezzanine and first.

    The exterior is concrete structure and blockwork with grooved plaster and paint finish, in addition to powder coated aluminum louvers at the transformers areas, the Administration Building will have powder coated aluminum curtain walls and windows to allow natural light to filter into the building.

    Accessibility and Maintenance Architectural features will reinforce the functional and maintenance requirements of the facility and will not impede normal operations.

    Overhead doors will be positioned and aligned to provide unimpaired movement through the full width of the door to access aisles. Overhead doors and access aisles will be provided to permit unobstructed removal and replacement of every major piece of equipment and their respective subassemblies.

    A service elevator rated at 1-ton lifting capacity will provide vertical access between the ground, mezzanine and first floors of the Administration Building.

    The roof of the operational plant will be accessible by three individual stair towers.

    Four cranes will be provided at the ground floor of the operational plant to allow handling spare parts and maintenance of the chillers and pumps.

    One crane will be provided at the roof floor of the operational plant to allow handling spare parts and maintenance of the cooling basin pumps.

    Access opening (6000 x 3000 cm) will be provided in the center of the operational plant to handle equipment from the ground floor to the first and roof floors.

    Access hatches will be provided to handle the generators and pumps to the basement.

    Refer to Section 9 for more details on maintenance and accessibility.

    Containment Requirements Electrical areas containing oil-filled transformers will be designed with passive containment provisions as required by the National Electrical Code and Stormwater Pollution Prevention Plan to prevent the accidental release of oil and to facilitate clean up and removal of spilled oil.

  • Q06024-IDCP-RPT-AR-001-REV 3 3-3 Stanley Consultants

    Building Interior The interior of the plant expansion is comprised of the basement, main operating floor, and mezzanine. The basement houses piping, pumps and water tanks related to the plant operations and a generator room containing two generators. Chillers and pumps are located on the main operating floor (ground). The first floor provides RO system as well as space for HVAC and electrical equipment.

    Occupancy The plant will be occupied 24 hours per day.

    The floor, walls, and ceiling of the operational and storage areas are all concrete. The floors have a transparent sealer. The walls and ceilings are painted for better light.

    The lab and control room will have resilient tile. The lab has epoxy resin worktops with integral sinks.

    Life safety features include an automatic sprinkler system and a fire alarm system.

  • Q06024-IDCP-RPT-ST-001-REV 3 4-1 Stanley Consultants

    Section 4

    Structural Design Statement

    General This section of the Design Intent Report includes the narrative description of the structural systems for the Integrated District Cooling Plant (IDCP) at The Pearl, Qatar. Discussions between the Owner, Qatar Cool, PMC, the Contractor, C.A.T. International (CAT), and the Design-Build Engineer, Stanley Consultants are detailed in Exhibit A Project Correspondence.

    This section includes the design criteria, subsurface conditions, foundations, building basement walls, concrete slabs on grade, operating floor over basement, and interior walls within the IDCP.

    Two expansion joints will be provided for the operational plant building and one expansion joint will be provided between the operational plant building and the support space building.

    Compliance Statement The Structural design will comply with all portions of the Tender Documents prepared for Qatar Cool and issued by DAR during the tender phase. These documents include the general requirements, tender specifications, room data sheets, tender drawings, and the appropriate addendums and tender circulars issued for clarification, except as noted below:

    Plant Arrangement: The IDCP will be based upon the plant arrangement from the Alternate 2 bid proposed by CAT and accepted by Qatar Cool prior to contract award.

    Design Criteria Codes and Standards The following codes and standards will be used in conjunction with the structural design:

    BS6399: Code for Loading for Buildings

    BS8110: Structural use of Concrete

  • Q06024-IDCP-RPT-ST-001-REV 3 4-2 Stanley Consultants

    Uniform Building Code (UBC) for Seismic Loads

    Design Loads The Uniform Building Code (UBC) 1997 Edition, with the following criteria:

    Codes: BS 6399: Part 1 for dead and imposed loads CP3 Chapter V, Part 2, for wind loads, UBC for seismic loads.

    Dead Loads:

    - Concrete Unit Wt. = 24.00 KN/m3

    - Floor Covering (Typical Floors) = 2.00 KN/m2

    - Partition Loads (Typical Floors) = 2.50 KN/m2 for block work and 1.00 KN/m2 for Gypsum Partition.

    - Floor Covering (Roof) = 2.50 KN/m2

    Live Loads: The live loads will be based upon the following:

    - Equipment Weight: Location and magnitude of loads will be coordinated with the mechanical design.

    - Pipe Support Loads: Location and magnitude of loads will be coordinated with the mechanical design.

    - Cooling Tower Weight: Location and magnitude of loads will be coordinated with the mechanical design. These loads will include the basin water weight on roof slab.

    - Water Tanks: Location and magnitude of loads will be coordinated with the mechanical design.

    Wind Loads: The wind load will be based upon a basic wind speed of 45 mps.

    Seismic Loads = Zone 2A Seismic Risk

    Load Combinations:

    - 1.40 x D.L. + 1.60 x Live loads

    - 1.40 x D.L. + 1.60 x Lateral Loads

    - 1.20 x D.L. + 1.20 x L.L + 1.20 x Lateral Loads

    Foundations:

    - Foundations will be shallow foundations of raft type.

    - The IDCP will have two levels for the raft foundation. The first will be under the basement floor on rock and the second will be divided into two parts on another raft found