deep soil mixing for underground construction · tunnel section –9.6 km, 60m below sea bed bridge...

52
Deep Soil Mixing For Underground Construction Alan R. Ringen, P.E. September 12, 2018

Upload: others

Post on 22-Feb-2020

9 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixing

For Underground ConstructionAlan R. Ringen, P.E.

September 12, 2018

Page 2: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Presentation Outline

• Introduction• Soil mixing equipment• Installation procedure• QC/QA• Engineering properties of soil-cement• Applications

Page 3: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixing

Deep Soil Mixing is the in situ mechanical mixing of a cement grout with soil to produce an a variety of engineered geometries and soil properties to suit the application

Page 4: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixing(DMM, CDM, CDSM, DSM)

• Deep Soil Mixing (DSM) is an in situ soil treatment technology whereby native soils are blended in situ with cementitious materials, typically Portland cement.

• Geotechnical - The soil-cement mixture created by DSM has increased strength, lower permeability and reduced compressibility

• Environmental – In situ solidification and stabilization; Groundwater barrier for containment

Page 5: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixing EquipmentTwo and three axis rigs & mixing tools

Page 6: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixing Equipment Four & six axis rigs & mixing tools

Page 7: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Backhoe Mounted Soil Mixing Tool

Page 8: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Mixing tool for cohesive soil Mixing tool for granular soil

Conventional mixing tool WILL mixing tool

Backhoe Mounted Soil Mixing Tool

Page 9: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Soil Mixing Support Equipment

Water Supply Generator Grout Pump

Cement Silo

Soil Mixing RigBatch Plant

Page 10: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Slurry batch plant

QC system

Soil Mixing Support Equipment

Page 11: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Installation procedurePositioning . Grout injection and soil mixing . Completion

Page 12: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Installation procedure - Alternating

Installation Procedure for Cutoff Wall and Shoring WallAlternating, i.e. Primary & Secondary sequence

Page 13: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Installation procedure – Proceeding

Proceeding installation procedurefor ground improvement cells

Proceeding installation procedurefor cutoff & shoring walls

Page 14: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixed Wall Plan

Page 15: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Factors affecting soil-cement properties

▪ Soil type

▪ Mix design

▪ Mixing Energy

Page 16: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Quality controlMix design▪ Cement factor▪ Water cement ratio

Mix energy▪ Rotation speed▪ Penetration &

withdrawal rate

Page 17: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Real-time QC monitoring & recording system Mixing Tool Location, Amendment, & Treatment

Real-time monitoring & control on:• Depth / Location• Penetration rate• Mixing tool rotation rate• Grout flow / dosage rate

Quality control

Page 18: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Core sampling & testing

Page 19: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Engineering propertiesUCS vs curing age

Sources: 1. CDIT 2002, “The Deep Mixing Method, Principal, Design and Construction”, edited by Coastal Development Institute of Technology (CDIT), Japan, published by A.A. Balkema Publisher. 2. Saitoh 1988, “Experimental study of engineering properties of cement improved ground by the deep mixing method. Ph.D. Thesis, Nihon University .

Laboratory Mix Designs

Page 20: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Engineering properties Tensile strength

Tens

ile s

treng

th, σ

t(M

N/m

2)

Unconfined compressive strength, qu (MN/m2)

Sources: 1. CDIT 2002, “The Deep Mixing Method, Principal, Design and Construction”, edited by Coastal Development Institute of Technology (CDIT), Japan, published by A.A. Balkema Publisher. 2. Terashi, Tanaka, Mitsumoto, Niidome & Honma 1980. “Fundamental properties of lime and cement treated soils (2nd

report)”, Report of the Port and Harbour Research Institute, 1980.

Page 21: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixing Applications

• Increased Bearing Capacity

• Settlement Reduction

• Support of Excavation

• Liquefaction Mitigation

• Seepage Control

Page 22: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

DSM for Tunnel Construction

▪ DSM walls and slabs for excavation support and groundwater control

▪ DSM for support of launching & receiving of TBM machine

▪ DSM ground improvement outside launching & receiving shafts

Page 23: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

DSM Applications

Block

Cell

Page 24: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

DSM Applications

Shear wall&

columns

RingCIDHPile

Page 25: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

DSM Product and ApplicationsExposed soil-cement produced by WILL Method Core Samples

Ground improvement for tunnel shaft Ground improvement adjacent to structures

Page 26: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Top of soil-cement elements

Top of exposed DSM elements

Page 27: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

DSM Foundation Support

Page 28: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Infrastructure & industrial facility

Soil-cement cells for • Bearing capacity• Settlement control• Liquefaction mitigation

Page 29: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep Soil Mixed Shaft Wall

Page 30: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Excavation support & groundwater control

Cypress Freeway Replacement Project, Oakland, CA

Page 31: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Boston Central Artery/Tunnel (CA/T)Mass DOT

• I-93 – To expand existing six-lane highway to an eight-to-ten-lane underground expressway, constructed directly beneath existing roadways, buildings, and subways in downtown Boston.

• I-90 - To extend I-90 from its existing terminus south of downtown Boston to Logan Airport through the Ted Williams Tunnel under Boston Harbor and a tunnel beneath the Fort Point Channel.

Courtesy of Dr. T.D. O’Rourke and A.J. McGinn, Cornell University; Massachusetts Turnpike Authority;Federal Highway Administration and Bechtel/Parsons Brinckerhoff (illustration)

1-1 Bird Island Flats (C07A1) – DSM was use to install excavation support wall for construction of cut-and-cover tunnel.

1-2 Fort Point Channel Crossing (C09A7) – DSM was used for ground improvement for the construction of cut-and-cover tunnel and boat sections

Page 32: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Installation of DSM (SMW) Wall at Bird Island Flats

Source: 1) Taki and Yang 1991; 2) Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central Artery T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture

Page 33: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Subsurface profiles at BIF

East Wall West WallSource: Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central ArteryT. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture

Page 34: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Base stabilization scheme

Source: Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central Artery T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture

Page 35: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Cross section of BIF base stabilization

1. DSM buttress2. Jet grouting3. Final subgrade

Source: Lessons Learned for Ground Movements and Soil Stabilization from the Boston Central Artery T. D. O’Rourke, M.ASCE1; and A. J. McGinn, M.ASCE2, 2005 Ralph B. Peck Award Lecture

Page 36: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

DSM Work at Fort Point Channel (FPC), C09A7Tunnel and boat sections

Courtesy of Dr. T.D. O’Rourke and A.J. McGinn, Cornell University; Massachusetts Turnpike Authority;Federal Highway Administration and Bechtel/Parsons Brinckerhoff (illustration)

The interchange at FPC consists of a network of tunnels and depressed roadway (boat section), viaducts and bridges requiring braced excavations as deep as 18.3 m in very soft to soft soils.

Page 37: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Subsurface conditions

▪ Fill

▪ Organic Deposits▪ Sand/Inorganic silt

▪ Marine clay

▪ Glacial deposits

Source: Haley & Aldrich, 1995a “Summary Report of April, 1995 Fact Finding Trip on Soil Mixing Methods”, Excavation Support/I-90 Marine Tunnels

The critical junction between jacked and immersed tube tunnels islocated in deep, low strength deposits of Marine Clay and Organics.

Page 38: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Representative construction conditions at Ramp D

Sources: 1) Lambrechts, J.R., P.A. Roy, and E.J.Wishart (1998), “Deign Conditions and Analysis Methods forSoil-Cement Buttress in Fort Point Channel”, GSP No. 83, ASCE, Reston, VA, pp. 153-174. 2) Performance ofdeep Mixing method at Fort Point Channel by A.J. McGinn & T.D. O’Rourke, Cornell University, 2003

Page 39: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Representative long-term conditions at Ramp D

Sources: 1) Lambrechts, J.R., P.A. Roy, and E.J.Wishart (1998), “Deign Conditions and Analysis Methods forSoil-Cement Buttress in Fort Point Channel”, GSP No. 83, ASCE, Reston, VA, pp. 153-174. 2) Performance ofdeep Mixing method at Fort Point Channel by A.J. McGinn & T.D. O’Rourke, Cornell University, 2003

Page 40: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Fort Point Channel DSM construction

Courtesy of Dr. T.D. O’Rourke and A.J. McGinn, Cornell University;Massachusetts Turnpike Authority;Federal Highway Administration and Bechtel/Parsons Brinckerhoff

Page 41: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

DSM equipment at FPC siteDSM rig on barge

Photos by Jakiel (2000) and McGinn Source: Performance of deep Mixing method atFort Point Channel by A.J. McGinn & T.D. O’Rourke, Cornell University, 2003

M250 DSM rig on land Triple shaft mixing tools

Page 42: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

TokyoTokyo Bay

Chiba

Trans-Tokyo Bay Highway Project

Tunnel section – 9.6 km,60m below sea bed

Bridge section – 4.4 km

Kisarazuman-made island

Kawasakiman-made island

Ukishimaaccess

Plan

SectionKisarazuCity

KawasakiCity

Trans-Tokyo Bay HWY = 15.1 kmMarine zone = 14.3 km

Courtesy of Dr. Masaki Kitazume, Tokyo Institute of Technology, Tokyo, Japan

Page 43: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Kawasaki man-made island Kisarazu man-made island Bridge section

Bridge sectionKisarazuman-made island

Kawasaki man-made islandUkishima access

Courtesy of Dr. Masaki Kitazume, Tokyo Institute of Technology, Tokyo, Japan

Trans-Tokyo Bay Highway Project

Page 44: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Kisarazu man-made island

Ground improvement

• Deep soil mixing• Sand compaction pile• Premix soil-cement fill

Sheet pile cells for control of lateral deformation

Premix soil-cement fill

to Kisarazuto Kisarazuto Kawasaki

Premix fill

Sheet pile cell

Sheet pile cell

Courtesy of Dr. Masaki Kitazume, Tokyo Institute of Technology, Tokyo, Japan

Page 45: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Kisarazu man-made island

Ramp section Flat section

Ramp section Flat section

Plan

Section

Shield tunnel advanced through soil-cement zones installed by premixing and deep soil mixing

Source: Ground improvement by cement-treatment in Trans-Tokyo Bay Highway Project,K. Uchida , K. Imai, F. Tatsuoka and Y. Kohata; Grouting and Deep Mixing, published by A.A. Balkema 1996

Page 46: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Ukishima access

Shield tunnel advanced through soil-cement zones installed by premixing anddeep soil mixing (DSM)

DSM

Premix fill

DSM

Premix fill

Source: Ground improvement by cement-treatment in Trans-Tokyo Bay Highway Project, K. Uchida ,K. Imai, F. Tatsuoka and Y. Kohata; Grouting and Deep Mixing, published by A.A. Balkema 1996

Page 47: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Deep mixing barge and mixing tool for sea bed stabilization

Courtesy of Dr. Masaki Kitazume, Tokyo Institute of Technology, Tokyo, Japan

Page 48: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Kawasaki man-made island

Ground improvement

• Deep soil mixing• Sand compaction pile

Sheet pile cells for control of lateral deformation

Soil mixing wallDSM

DSM Soil mixing wall

DSM

Courtesy of Dr. Masaki Kitazume, Tokyo Institute of Technology, Tokyo, Japan

Page 49: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Kawasaki Man-made island

Courtesy of Dr. Masaki Kitazume, Tokyo Institute of Technology, Tokyo, Japan

Page 50: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Questions?

Thank You!

Page 51: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Company history

▪ JAFEC (Japan Foundation Engineering Company, Ltd.) was established in 1953. The U.S. subsidiary, JAFEC USA, Inc., was established in 2009.

▪ Ground improvement technologies: Deep soil mixing Deep power compaction Sand compaction piles / Stone columns Grouting

Page 52: Deep Soil Mixing For Underground Construction · Tunnel section –9.6 km, 60m below sea bed Bridge section –4.4 km Kisarazu man-made island Kawasaki man-made island Ukishima access

Alan R. Ringen, P.E.Senior Vice President

JAFEC USA, Inc.2025 Gateway Place, Suite 180

San Jose, CA 95110408.472.6175