deck example
TRANSCRIPT
-
8/16/2019 Deck Example
1/100
SIMPLE
BRIDGE
DESICN
USING
PR
ESTRESSED
BEAMS
ON
p
pp
-
8/16/2019 Deck Example
2/100
Simple
Bridge
Design
using
Prestressed
Beams
An introduction to
the
design
of
simply-supported
bridge
decks
using prestressed
concrete
bridge
beams
B
A
NICHOLSON
-
8/16/2019 Deck Example
3/100
11
ISBN
0
95000347 2
X
©
Prestressed Concrete Association
1997
Prestressed Concrete Association
60
Charles Street
Leicester
LE
11
FB
Typeset
by
B. A.
Nicholson.
Design
by
G. Ballantyne.
Printed
by
Uniskill
Ltd.
-
8/16/2019 Deck Example
4/100
CONTENTS
FOREWORD
1
STANDARD
BEAMS 2
1.1
History
2
1.2
Bridge
deck
ypes
4
1.3
Choice
of
section
6
1.4
Standard sections
6
1.5 Practical site
considerations 8
2
BEAM & SLAB DECKDESIGN EXAMPLE
12
3 GRILLAGE MODEL
14
3.1
Introduction 14
3.2
Suitability
of
Grillage Analysis
14
3.3
Grillage
models or
prestressed
beamdecks 16
3.4
Deck idealisation
18
3.5 Section
properties
20
3.6 Edge stiffening
22
3.7 Torsion
24
4
CALCULATIONOFLOADS
26
4.1 Introduction
26
4.2 Definitions
26
4.3
Highway loading
28
4.4 Wind load
32
4.5 Pedestrian liveload
32
4.6
Temperature
effects
32
4.7
Shrinkage
36
5
APPLICATION OF
LOADS
38
5.1 Load
Combinations
38
5.2 Selection
of
Critical LoadCases
38
5.3
Input
to
Grillage Analysis
40
6
PRESTRESSED BEAMDESIGN
44
6.1
General
44
6.2 Design Bending Moments 44
6.3
Serviceability
Limit State
46
6.4 Prestress losses
50
6.5 Ultimate limit
state 56
6.6
Shear
60
6.7
Longitudinal
shear
66
111
-
8/16/2019 Deck Example
5/100
iv
7
FINISHINGS
68
7.1
Introduction
68
7.2
Bearings
68
7.3
Waterproofing
and
surfacing
80
7.4 Joints
82
7.5
Parapets
84
8 SOLID SLAB DECK DESIGN
EXAMPLE 86
8.1
Introduction
86
8.2
Grillage analysis
88
8.3
Design
of ransverse reinforcement 90
-
8/16/2019 Deck Example
6/100
-
8/16/2019 Deck Example
7/100
2 SIMPLE BRIDGE DESIGN
USING PRESTRESSEDBEAMS
STANDARD BEAMS
1.1 HISTORY
The
use
of
precastprestressed
beams in
bridge
decks in the
post
World
War
II
era
owes its success in he main o the
foresight
of he Prestressed Concrete
Development
Group,
which n the 1950's
developed
the firststandard
beamsections
to
beavailable
fromthebeam
manufacturers.
This enabled
factory production
of
he
beams
on
a
large scale, and,
with the dawnof
major
road construction
in
the late 1950'sand its
philosophy
of
grade
separation for
motorways
and trunk
roads,
it
gave bridge engineers scope
to
rationalise
design
procedures usingup-to-date
load distribution theories.
The standard beam sections available
at that time have ofcourse themselves been
developed
and
modified,
and in essence
only
one
really
remains
today
with
any
significant usage.
This
beam,
he inverted
T
beam,
s
used n
bridge
decks in
spans up
to
about 20 metres.
With herapid
development
of
he
UK
motorway
network
n the
1960's,
it
wasclear
that here
was
scope
for
a
standardbeam hatwould enable
larger spans
tobe
achieved.
Consequently,
at
the end of he decade
a
new beam was
introduced
for
spans
from
about
15 to 30metres. This was
designated
the
M
beam,
due o itswidth and ntended
spacing.
These
beams were intended
for
use
in
pseudo-slab bridge
decks with
a
contiguous
concretebottom
flange
using
transverse reinforcement located
hrough
lower
web holes at 600mm centres
along
the beams.
Eventually engineers
realised that he Mbeamcould
be
used more
efficiently
in
beam
and slabdecks
by eliminating
the bottom in-situ concrete and
by
spacing
hebeams
apart
at
up
to
1.5
metre centres. The limitation
on thistype
of
use
proved
to be
the
shear
capacity
of he
beams,
whichhave
a
web thickness of
only
160mm.
Other
beams
developed
around this time were the
U
beam
for
beam and slabdecks
up
to about30 metre
spans,
anda
U
shaped
variation
of he
M
beam
foruse
as
edge
beams
in M
beam
decks.
Eventually,
with the
very popular
M
beam
being
used in
a
manner somewhat different
from its intended
use,
and
bearing
in mind the various
problems
and
limitations his
presented,
a
newbeamwas
developedby
the Prestressed
Concrete Association
in the late 1980's. This was
designated
theY
beam.
The
Y
beam now has three
variants: the
TYbeam,the
Y
beam,and the SY
beam.
Together
these cover all
span ranges up
to
45m. It
is
expected
that
in
due course
inverted T beams and
M
beams
will cease
to
be used
in
favourof he enhanced
properties
of he
Y
beam
anges.
-
8/16/2019 Deck Example
8/100
H
M beam
Inverted T beam
U beam
STANDARD BEAMS 3
TY beam Y
beam SY
beam
-
8/16/2019 Deck Example
9/100
4 SIMPLE BRIDGEDESIGN
USING PRESTRESSED BEAMS
1.2
BRIDGE DECK TYPES
Concrete
bridge
superstructures
using precast
prestressed
concretebeams fall
into
threedistinct
ypes:
slab
decks, pseudo-slab
decks,
andbeam and slabdecks.
Slab Decks
Slab decks can be solid or
voided,
and
provide simplysupported spans
of
up
to
20
metres. Thesedecksusestandard TY or inverted
T
beams
placed
side
by
side. The
space
between them is then filled with in-situ
concrete,
and an overall
covering
of
75mm
completes
the deck.
Continuity
of
hese
decks
canquiteeasilybe
achieved
by
using
einforcement
in
the
in-situ concrete
over the
supports. Suspended
spans using
TYbeams or inverted
T
beamscanbe
lightened
by
introducing
voidformers into the
space
between the beams.
Pseudo-slab
Decks
This
type
of
bridge
structure
is
currently
not
quite
so
popular.
Precast
beams are
incorporated
intoavoidedslab
ype
ofdeck
by
either
adding
an in-situ bottom
flange
and
op flange,
aswith the
original
Mbeam
decks,
or
by using
voidedbeams
e.g.
box
beams).
A voided slab deck is thus created without the inconvenience
of
emporary
works
andsoffit
shutters,
and
provides
a
torsionally
stiffer deck than
ordinary
beam andslab
decks.
Spans
for this
type
of
bridge
deck are
usually
imited
by
the
length
of
precast
beams
that canbe
transported
to
site,
and thereforeare
rarely
more than 30 metres.
BeamandSlab Decks
The mostcommon
type
of
uperstructure
for small
o
medium
spanbridges,
this
ype
ofdeck
comprises
individual
precast
beams
at
discrete centreswith anin-situ concrete
top flange.
M
beams,
TY
beams,
Y
beams,
SY
beams,
and Ubeams can all be used
inthis form
ofconstruction.
Withmost
of
hestandard
range
of
precast
beamsthe in-situ
concrete
top
slab
is
cast
into
permanent
formwork whichislocated nrecesses formed
n he
edges
of he
top
flanges
of he beams.
Typical spans
for this
type
ofdeckare similar
o the
pseudo-
slabdecks
above, being
imited
in the main
bytransportable
beam
components.
Standard
edge
beams are available to
complement
the
Y
beam,
TY
beam,
and
M
beam
anges.
These
provide
avertical visible
face,
and
have he
capacity
to
carry
he
extraloads from
the
parapet
cantilever.
-
8/16/2019 Deck Example
10/100
STANIAiu
BEAMS
5
This solid
slab
deck uses
19
T2
beams.
Service
ducts are included in
the
infihl
concrete
between
he
beams.
This
bridge
deck uses nine
US
beams
at a
spacing
of1
.72m.
Service ducts
run under
the
footpath.
A
carrier drain
runs
through
one
of
he
U
beam
cells.
This
bridgedeck uses
seven Y8
internalbeams
at a
spacing
of
1
.275m,
and
YE8
edge
beams on
each
side.
Service ducts
run under
the
footpath.
-
8/16/2019 Deck Example
11/100
6
SIMPLE
BRIDGE DESIGN USING PRESTRESSED
BEAMS
1.3 CHOICE
OF SECTION
For the
types
of
superstructure indicated above,
the beam
manufacturers provide
standard details
of
he
individual sectionsand their
anges together
with anindication
of
ypical span ranges
for
decks
incorporating
these beams
and
carrying
standard
highway
loads.
Therewill
obviously
besituations
where the choiceofdeck
type
isnot
clearly
indicated
by
the available
span,
and itisalso inevitable
that herewill beareas
of
overlap
where
the choice between
invertedTbeams in a slab
deckor ndividual M or Y beams
n a
beam and slab deck
may
not be
clear cut.
In this
situation
it
may
be
necessary
to
evaluate more than one
solution,
and hestandard sections enable aswift
selection of
the
available ranges
for
comparative design exercises
to
be
undertaken
and cost
comparisons
made.
It is also
possible
within
thestandard
range
of
each beam
ype
to be in a
span
range
that is covered
by
more hanone
specific
beamunit. In thissituation
it
is
usually
cost
effective
o
select the
larger
unit where
there arenorestrictive imitationsonheadroom.
1.4
STANDARD SECTIONS
Design
Although
he various
types
ofstandard
beam
sections are
well
documented
interms
ofdimensions
andstructural
properties,
it is
mportant
to
point
out that these
factory
produced
beams are standard
only
to the extent
that
they
are manufactured
using
standard
shaped
sections. The amount
and
magnitude
of
prestress
applied
to
each
beam is
dependent
on its
individual
situation,
and mustbe
determined
by
the
designer
prior
to
manufacture. The standard sectionsshow
where
prestressing
strands
may
be
located,
but
it isthe
responsibility
of he
designer
todetermine which
of
hese are
to
be
used.
Intheir
literature,
themanufacturers
givesuggestions
for
gooddesign
details. These
should be adhered
to,
as
they
leadto
economy
and
good workmanship.
Manufacture
Precast
prestressed
beams
aremanufactured n
long
lines
of
everal
units
using
straight
strands.
These
are debonded
for
varying
distances
at
the ends
of
each beam
within
the
mould. Thisis
necessary
tomaintain the
stress inthebeam atan
acceptable
level
as the
self-weight bending
moment educes
approaching
the
supports.
Once theconcrete
in
the moulds reaches the minimum
transfer
strength, detensioning
can take
place,
the strands between the beamcan
be
cut,
and the beamsremoved
to
the
storage
area
prior
to
delivery
o site.
-
8/16/2019 Deck Example
12/100
Standard
positions
for
prestressing
strands inaY8 beam.
It is
up
to
the
designer
to
decidewhichof hese strand
positions
o
use.
STANDARD
BEAMS 7
Span
in
metres: 12
14 16 18 20 22
24 26 28 30
32
Beams
at im
centres
Beams
at
2m centres
£
Beam
selection chart for the
Y
beam
range,
takenfrom PCA
literature.
-1-4-
4--I-
-4--I-
4--I-
-4-4-
-4--I-
-I--I-
-I--I-
-4--I-
1300
1200
1100
1000
900
800
+4--I--I-
-4- -4-
4-
260
210
160
-
110
60
0
-
8/16/2019 Deck Example
13/100
S SIMPLE BRIDGE
DESIGNUSING PRESTRESSED BEAMS
1.5 PRACTICAL SITE
CONSIDERATIONS
Handling
Beamsare
usually
manufactured
with
lifting loops,
hus
enabling
on site
lifting
to
be
achieved
witheither
single
or twin cranes
o suit he site
requirements.
However,
TY
beams and
inverted T beams are
usually
lifted
using
a
sling
through
the end web
holes.
Access
to
Site
Itisof
obvious
importance
that there
is
suitable access
to
the
bridges
in order forthe
beams o
be
delivered
and
lifted
off
he trailerby
suitably located cranes.
Of
course,
this also
applies
to
the route to the
construction
site
which
must
allow
the
delivery
lorries
omanoeuvre
their
engthy
loads.
There s
generally
no
problem
in he
transportation
ofbeamsof he
lengths
described
in thisbook.
Camber
Variation in camberof
prestressed
beams
is
nevitablewhenoneconsiders
he olerance
in
prestress
force and
ocation,
togetherwithpossible
variation
in concrete
properties
with
maturity
andclimatic conditions.
It
would
thereforebe
impracticable
o
specify any
limitationon
camber
values, although
a
olerance
oncamber variation between beamshasbeen
adopted.
However,
it
should
been
borne
in mind
by
the
designer
that an
occasional failure
to meet
the
specified
tolerance
on
soffit level variation does
not result n
impossible
constructionconditions.
Thecareful
positioning
of
adjacent
beams
n adeckshould
nearly
always
result n an
evening
outofdifferential camber.
Edge
Details
On
site,
construction
of
parapet
tring
courses
in one
or
more
stages generally
follows
the construction
of
he central deck slab area.
This necessitates the formation
ofa
construction
joint
along
the
edge
beam
prior
to
constructing
thefascia.
Alternatively,
it
is sometimes
possible
to
construct
thefasciaas
a
second
stage casting
in the
manufacturer's
yard, prior
to
delivery
to site
as
analmost
complete
unit. One
advantage
of
this
is
that
the
beam can
be
propped quite easily
at the
works,
thus
enabling
stresses
nthe
precast
beamsection tobeminimised.
-
8/16/2019 Deck Example
14/100
/
STANDARD BEAMS 9
This section
can be
cast on
site
as
a
second
stage
after
the
rest of
the deck,
or
alternatively can
be
cast
onto
the UM beamby
the
manufacturer
so that
the
edge
beam and
parapet
can
be
brought
to
site
as
a
single
unit.
Two
examples
of
edge
details
Second
stage
in-situ
concrete
in-situ
concrete
Cast
by
manufacturer
-
8/16/2019 Deck Example
15/100
10 SIMPLE BRIDGEDESIGN
USING PRESTRESSED BEAMS
Skew
Although
it
is
possible o
manufacture
precast
beams
with skew
ends,
he increase in
cost for each unit and
the
problems
that skew
presents
should be considered
in detail
at the
design
stage.
Firstly,
it
should
be
remembered
thatevena
very
small
change
inskew
angle equires
anew
stop
end for the mould. A
change
from
say
300
to
31° increases the width
by
12mmfor an
M
beam.
To rationalise a
range
of
angles
with a variation
of
10°, say,
would be auseful
andeconomic
possibility
Structural
problems
created
by
skew
in the endsof
precast
beamsrelate
specifically
to
the acute corner,
where the
formation
of
cracks can cause the
corner
of
he flange
to
spall
whenthe beamcambers
during
transfer.
Although
not
structurally significant,
this is
undesirable,
and isbest
prevented by blocking
out the corner to
give
a local
square
end.
An additional
problem
that
presents
itselfwith skew beams is hatof
ocating
ransverse
reinforcement
through
thewebholes. Itisrecommended that thestandard
webholes
permit
reinforcementtobe
placed
forskews
up
to about 35°.
Higher
skewshan this
would
require
special
non-standard
web
holes,
whichwould increase the costof he
beams
significantly,
and
may
evenaffect
the shear
capacity
of hesection. For
high
skew
bridges,
it
is
normallybetter
to
place
thetransverse
deck
reinforcement
at
ight-
angles
o the beams rather han
parallel
to the
abutments.
Transverse Reinforcement
For the transverse
reinforcement
through
the webholes of
precast
beams,
it is
usually
betterto use
anumberof mallerbars rather thana
single large
diameter
bar,
as
lap
lengths
are reduced
and
handling
becomes easier. For some awkward skew situations
it
may
even be sensible
to use untensioned
prestressing
strand threaded
through
the
web
holes
instead of
einforcing bars,
as it ismore flexible.
The
positioning
of ransverse deck
reinforcementwhen
using
solid
edge
beams
may
require
the useof
couplers
atthe
edge
beaminterface.
Temporary Support
Itis
mportant
to ensure
that the beamsarc
supported
so that
they
cannot
topple
over
on site.
Deeper
beams,
particularly
when
beingjacked
to their final level and
during
bearing
installation,
mustbe
assessed to eliminatethis risk.
-
8/16/2019 Deck Example
16/100
STANDARD BEAMS 11
Local
square
end
to M
beam
330
wide
Diaphragm
800 wide
M
beam
bridge
deck
with
45°
skew.
Diagrams
show
endsof
M
beams
embedded
in
a
diaphragm.
tDecks1ab
M
beam
Web
hole at end
ofM
beam,
for
diaphragm
reinforcement
Diaphragm
I
L
-
8/16/2019 Deck Example
17/100
12
SIMPLE BRIDGE
DESIGN USING PRESTRESSED BEAMS
2 BEAM
& SLAB DECK DESIGN
EXAMPLE
Sections 3 to
7
of
his book
consist
of
a
design example
of
a
beam and slab
deck.
This
design
example
shows the
typical sequential
calculations
necessary
for thefull
design
of
a
precast
pretensioned
concreteY beam
in a
simply supported
beam
and
slab
bridge
deck.
The
right
hand
pages
show the numerical
calculations involved ateach
stage,
and the
left hand
pages
contain
explanatory
comments
andfurther information.
The
example bridge
has the
following design requirements:
Span
26.6lm
single
span
Width
7.3m
carriageway, plus
I
.0m
hard
strip
each side
1
.5m
footpath
eachside
Loading
HA
plus
37.5 units HB
Surfacing
100mm
thick
(minimum) plus
20mm
waterproofing
The
following
materials
willbeused:
Precast concrete
=
50N/mm2
fd
=40N/mm2
In-situ concrete
f
=
40N/mm2
Prestressing
strand 15.2
mmdiameter
Dyform
strand
f
=
1820 N/mm2
Area
=
165 mm2
per
strand
The
edge
detailwas chosen
foraesthetic
reasons,
and the outerbeams
placed
as near
tothe
edges
of he
bridge
within his
limit. This ledtothe beam
spacing
of1 275m.
The
span
charts for Y beams
give spans
for beams
at I and 2 metre
spacings.
It is
straightforward
to
interpolate from
this
information
to
make an initial
selection
of
beam
size,
in thiscase Y8.
Clearly
alternatives would have been
possible,
for
example
eleven Y6 beamscould
have been
used,
atabout 1 metre
spacing.
However,
ithas been found hatunless it
is
necessary
to make the deck as shallow as
possible,
it
is
usuallypreferable
to use
fewer but
larger
beams.
-
8/16/2019 Deck Example
18/100
DESIGN
EXAMPLE
13
13350
Overall
llatdstn'p
£rniagew
fw
540 1500 1000
7300
1000 1500 540
1275 1275
Cross
se/
f ridge
decfordes#/,
xgir/e
-
8/16/2019 Deck Example
19/100
14 SIMPLE BRIDGE
DESIGNUSING PRESTRESSED BEAMS
3 GRILLAGE MODEL
3.1 INTRODUCTION
Early
bridge
decks were
analysed
ona
strip
basis. Abnormal
and wheel loads were
crudely
distributed and conservative
designs
resulted.
Experimental
data became
available
todeterminethe ransverse load
carrying
characteristicsofdeckstodetermine
thecorrect
level of ransverse
strength provision
and
todistribute loadmore
ogically
to the
longitudinal
members. For
example,
in the
1950'sMoriceand Little
developed
a Distribution Coefficient
method which was a
simple
hand method based on
experiments
which
allowed
for
the
overall distribution
of
oads
on
a
plate structure
such
as
a
bridge
deck.
It was
satisfactory
for skews
up
to200. This method was one
of everal similar
echniques
extensively
usedin
design
offices
for
approximately
15
years,
until the adventof
omputer techniques
which enabled
larger
andmore
complex
structures
to be
analysed
more
accuratelyusinggrillage,
finite
strip
and
finite element
methods. Of hese threemethods
grillages
offer the widest
range
of tructures
which
can
be
analysed.
Popular opinion suggests they
are also the easiest
to use and
understand.
No
analysis
method
gives
a
rigorous
solution,
and some
degree
oferror must
be
accepted, usually
angingup
to
10%
or
20%
depending
on
complexity.
These
errors
come
fromseveral
sources, including
the idealisation
of he
geometry
andmaterial
properties,
and idealisation of he structural
behaviour.
Grillage analysis
has
found favour as a
bridge engineer'sdesign
tool because it is
perceived
to have
the
following
advantages:
•
Grillage
beams
can be
positioned
to
correspond
with
physical
beams
n
the real
structure,
or
wheremaximum effects are
anticipated.
•
Modern PC versions
have 'user
friendly' input,
often
designed
by
engineers,
and use
pre-
and
post-processors
to
ease
subsequent checking,
searching
and
analysis.
•
Familiarity
of
use in the
design
office
enables
rapid analysis
and
checking,
which isvital ina
competitive
market.
•
Programs
are
relatively cheap,
thus
making analysis
economic.
3.2 SUITABILITY
OF GRILLAGE
ANALYSIS
The
method
can
be
used for
structures with
beamand slabs
decks,
voided slabs or
solid slabs.
Itcan be usedfor
simple
andcontinuous
bridges,
and allow for elastic
supports
andsettlement.
It issuitable for
right,
skew
and curveddecks. This
range
covers hundredsifnot housands
of
bridge
decks
designed
inrecent
times,
and
certainly
covers
all
bridges
with
prestressed
beams.
-
8/16/2019 Deck Example
20/100
GRILLAGE
MODEL 15
NILLAfi
ANAL
418/8
This
km/ge
wi/Ike
aira/ysed
with
a
gill/agea#a/qsiS.
The
an'a/qsiS
wY/be
etformedasitig
he
conipaterprogram
"STAN)
111/181)8
"
from'
T
-
8/16/2019 Deck Example
21/100
16
SIMPLE BRIDGE DESIGN USING PRESTRESSED
BEAMS
3.3 GRILLAGE MODELS FOR PRESTRESSED
BEAM
DECKS
Longitudinal grillagebeams areplaced
on he
line
of
hephysicalbeams,
and
represent
the
composite
action
of
he beam and its
associated section
of slab.
Longitudinal
beams arealso
positioned
along
the
parapet edge
beam. Transverse elements
represent
the
top
slab. Thereare no end
diaphragms
in this
bridge,
but whenthese are
present
they
must also
be
represented
by
appropriate
transverse elements.
This
type
of
grillage
model
is
suitable for beam
and slabdecks
using
M-beamsand
Y-beams.
Because
of
he
usually arge
numberofbeams naT-beam
deck,
it
may
be
preferable
to
model
two or three
beams
by
onegrillage
member. Transverse elements represent
transverse solid
infill
elements.
Because of henon-uniform
shape
of
hese elements
as
they pass
over and
through
he beams their
depth
is
normally
taken to the centre
lineof he ransverse holes. Thewider
spacing
of
model elementsdoes not
materially
affect the transverse element idealisation since the structure acts
as
a
true slab.
However,
care
isneeded
when
evaluating design
moments
shearsand
reactions due
to
thecombination
of
everal
physical
elements into
single
model elements.
U-beam
decks,
although basically
beam and slab
decks,
behave
differently
because
the
transverse stiffness
alternates across the
deck
between stiff
hrough
the
beams
and
flexible between
the
beams.
The
beams
are
positioned
to
try
and
equalise the top
slab
spans
between
and acrossbeams. Onemethod
of
modelling
a
U-beamdeck
is
o
place longitudinal
elements
on
hecentrelineof ach
web. The
longitudinalproperties
for
each
grillage
beam are then
taken as
half
hat of he
composite
box section. As
with the inverted T-beam
decks,
care
is
required
in
evaluating
the
output
since here
are now two
longitudinal
elements
representing
one
physical
beam.
r n
•1
n
•
\U/ \U/
\
p p p p p
-
8/16/2019 Deck Example
22/100
GRILLAGE MODEL
17
oft/re
deck
The
bridge
looks
like
thi;
Their-s/tii
dowHskHdfa'sck7
aNd
tkearetbeevi,
reboM
d,cot/,gog
a,rdso do rot
co#tribite
10te
S
Theci
s-sec1lo,r
oft/re
strgctiiral
elemeirts
oft/rebridge
I
t/reremre'
ri/lage
eams
willbe
/aced
o
ire
ites
oft/re
t/ire
preteirsioired
beams,
airdirom4ra/edge
beams
wi/Ibe
p/aced
a/oirg ireparapetke'ams.
Thustire
grit/age epreseirtatA'r
ft/re
cross-sectloiti
p
Traitsverse memberswillbe
provided
at
1. 9Osr
4rtetva/s
o
epreseirt
ireslab.
Thi
diVides ire
leiigtir
oft/re
deck4rto
14
eqjialsectiirs.
The rodes
of
ire
grit/age
will
geiret-a/ly
beoit
a
grid
of
1900
.
1275,
wir/ciri e//belowa
2,'l
aspect
atio aird
lireref
re
satifactorq.
-
8/16/2019 Deck Example
23/100
18
SIMPLE
BRIDGEDESIGN
USING PRESTRESSED
BEAMS
3.4 DECK IDEALISATION
Grillage analysis
idealises
a
deck into
a
grid
of
interconnected beams. The real
dispersed
effects of
bending,
shearand
torsion
are assumed
o
be
concentrated
in the
nearest
equivalent
grillage
beam.
Variations from
the
true behaviour
arise because
the real slabs
element
equilibrium
requires torques
and wists o be identical
and n
orthogonal
directions,
but
in
grillages
the
joints
can
rotate
differently.
However,
if
a
slab
is
modelled
by
a
sufficiently
fine
grillage
mesh
these anomalies are smoothed
out
tobecome almost
insignificant.
Again,
moments
in
grillage
beams
are
proportional
to
the
beam
curvature
in that
direction.
In real
slabs,
moments
also
depend
on the
orthogonal
direction
curvature,
but
this
error
is
also
sufficiently small
to
be
ignored.
There are
a few
fundamental
requirements
for
competent
grillage
modelling:
•
Place the
grillage
beams coincident
with
the
physical
beams or
ines of
designed
strength.
•
Where
possible, lay
out
the
grillage
o
capture
all
the
load,
and for
ease
of
hape generation
and
section
property
calculations.
•
Transverse elements
should be
spaced
to
try
and reflect
the
aspect
ratio
(length/width)
of he
whole
deck.
•
Skew decks
can
be
analysed
by
orthogonal
or skew
meshes.
If
he
skew
exceeds
20°,
the
model should
be laid out
within 5° of he real
skew.
•
Generally,
transverse members should be
orthogonal
to the
longitudinal
members,
particularly
when
skew exceeds 20°.
•
Bearing
positions
should
be
represented
faithfully,
and
in
skew
bridges
the verticalstiffnessmust
be
modelled with care
as
hey
can have
significant
effect
on
theoretical distribution
of
oad.
Once
the
grillage
model has beenset
up,
it is
recommended
that an initial est load
is
applied
(such
as
auniform
UDL),
to
verify
hat it
is
behaving correctly.
The test
load
case
should
be
checked
against some simple hand calculations (e.g. wL2/8)
o
make
sure
that the results
are reasonable.
-
8/16/2019 Deck Example
24/100
n//aae
mvde/
The
gill/age
wode/is/towit
be/ow
GRILLAGE
MODEL 19
The
(fr-stdkgcast
s/tows he
,ode
rHmbers,
aitdfrtdicates
sti/'orts
a cfrc/e.
The
secoirddhigram
s/tows he
tenrbern#mbethrg.'
15
30
45
60
75
90
105
120
135
150
165
15
50
1
———-
38
1
46i
—
53
—
61
91
106
121
136
68
76-
—
151
t5t
152 164
1 5
———--
16
1
ii
—
18 19
— —
——
——
—
249
262
263
290
156 ISP 158 159
304
130
-
8/16/2019 Deck Example
25/100
20
SIMPLE
BRIDGE DESIGN USING PRESTRESSEDBEAMS
3.5
SECTION
PROPERTIES
Since
he precast
and n-situconcrete
trengths
do not differby
more
than
10N/mm2,
Clause
7.4.1
permits
a modular
ratio
of1.0
to be used.
However
inthe
example
a
more
accurate
valuehas been
calculated
taking
into accountof
he
different concrete
strengths.
The
Y
beams
have
standard notches
50 mm
deep along
he
top
edges.
These allow
formwork
tobe
placed
between
the beams o
support
the deck concrete. In
this
case,
20 mm hick
permanent
formwork
is
used,
sothat he beam
protrudes
30 mm
into the
deck
slab.
The
overall
height
of he section
is
1.590
m.
The
composite
section
properties
are calculated
by
assuming
the
section is
made
up
from the Y8
beam,
a
rectangular
slab
which overlaps
it
by
30mm,andthe small
overlap
area
which must
be subtractedas it hasbeen
counted twice.
The code
permits
stiffnesses
tobe
represented
on
the
gross
concrete
ection
ignoring
the
reinforcement or strand.
This is the
most
straightforward,
since
the
amount of
reinforcement
and
strand
hasnot
yet
been
accurately
determined
at he
analysis stage.
In
some
situations,
such as
continuous
bridges
at
supports,
the
transformed section
may
be
important
and
should
be
used.
Under
transient
applied
forces
the short term
elastic
modulus should
be
used,
and
under
applied deformations
or
long
term
loads
the
long
term
modulus should
be
used.
To save
analysis
time
for
hese
two
situations
a
value
between
long
and
short
may
be
chosen,
ideally
reflecting
the
proportion
of
permanent
to
transient
effects.
Almost
all
analyses
are
executed
on
elastic
models,
even
though
the
code
allows
plastic
methods with
the
approval
of he
bridge authority.
An
elastic
analysis
is
appropriate
for
he
serviceability
limit
state,
which
s
the
most
important
for
the
design
of
he
pretensioned
beams.
The use
of
an
elastic
model
for
he ultimate limit state is
simple
and
conservative. It
is
a lower bound solution
in
which
the
structure
is
in
equilibrium
and
yield
isnot
reached.
-
8/16/2019 Deck Example
26/100
$ectloir
Propemes
&am
lo,,e.'
S
ean,,
prg'erns
rom'
data sheet
74rea
=
0.5847m2
9=0.639
m'
I
=
0,1188s,
Comt'os/te
8/ab
cocretef,
=40
N/nrm'2,
=31
tN/m'nr
&an,
cocretef
=50
N/mwr,
=34
N/m'm't
Mod#/ar atio
=
31/3
4 =0.91
The
actual
area
i
e4jiiredor
a/cu/at/oil
of
he
seiwe,'ht
othetwie Memodularratiowillbe
applied
o theslab.
GRILLAGE
MODEL 21
The
values
forA('y-?
irMi able ca,,
oit/q
be
fl//ed
4r
afterq
has
bee,,ca/cilIated
94/M
=0.737/0.829 =0.889m'
(from'bottomofbean,)
I
=0.2429si
$ectioirmoduilicait
ow
e
calculated'
Thi ast
value
i
asedoi, the
ra
formed
sectiw
properns,
so
willot
ive
the
rue
stresses4 heslab, The
modit'lar
atio iiruistbediVided
ot
of
h/
value
o
ind
the ruesect/onmvduiluis
for
heslabi
Zk
Q,
347
/
.91
=0.381m
(for
actual
stresses
?t
slab)
0220
1.370
Actual
area
ffect,Ve
area
q
A(i-7
I
8/ak
Overlap
'/8
0.280
-0.012
0.585
0.255
-0.011
0.585
1,480
1.385
0.639
0,378
-0.015
0.374
0.0891
-0.0027
0.0366
0.0011
0.0000
0.1188
Totals 0.853m'
0.829sr
O.737m O.2429m'
&ttom
of
eam',
Top
of
ean,,
Top
of
lab,
Zbb =1/9
=0.273
n,3
Z
=
"(1400-7,)
=
0.475
,3
Z
=I/(l.590-9)
=0.347m3
-
8/16/2019 Deck Example
27/100
22 SIMPLE BRIDGE DESIGN USING PRESTRESSED
BEAMS
3.6 EDGE STIFFENING
Most
decks
haveedge
stiffening
for the
parapets.
Manydeck
arrangements cause
the
edge
beam to
be
the most
heavily
loaded.
In
many
instances
these
effects are
complementary,
he
extra stiffness
reducing
stresses from the
extra
oading.
However,
the
combined
stiffliessof he
edge
beamwith he
parapet upstand
may
be
significantly
higher
than the
stiffness
of
the internal
beams,
and
so
may
attract
high
unwanted
loads
into
the
parapet upstand.
Care must be taken in
the
computer
modelling
to
ensure
that the
stiffness
allocated o
the
edge
beamisnot
unrealistically high,
as
this
would
aggravate
the
problem.
To counteract
this
'overloading'
henomenon,
the
following approaches
canbe
taken
when he
apparent
edgebeam nertia
s
significantly
higher han
internal elements:
•
model
the
edge
upstand
as
a
separate
element
(usually
with
less
inertia
than the main
elements).
This reverses
the trend
ofattraction.
•
calculate
the
whole
deck
nertia
including
he
upstands,
and also
excluding
the
upstands.
Then
allocate
half
he
difference
to
each
edge
member.
This is
likely
to be
significantly
less
than the inertia
calculated
for
the
discrete
edge
shape.
•
make he
edge upstand
discontinuous. This
is
becoming
more
popular
as
it also
reduces
thermal and
differential
shrinkage
cracking.
It
does,
however,
require
careful
detailing.
In the
design example,
the
third
method
has
been
adopted.
The
downstand fascia
and
parapet
are cast
after the deck has been
completed,
and are
both
cast in
sections
about
2.5m
long
separated
by
a narrow
gap.
The stiffness of
he
parapet
cantilever
is
included with
the outer
Y
beam.
Edge
longitudinal
elements are included
in the
model
along
he
line
of
he
parapet
support
upstand.
These
elements are
given
very
small
section
properties
so
that
they
do
not
contribute structurally
to the
grillage.
They
are
only
included
to
give
the
grillage
model
a
idy
appearance
the same
size
and
shape
as the
bridge
deck.
They
could be
omittedwithout
affecting
the resultsof
he
analysis.
Ifnominal members are
used
n
this
way,
however,
loads should
notbe
applied
directly
o
these members.
-
8/16/2019 Deck Example
28/100
dge
&am
GRILLAGE MODEL 23
,4n
ir-sltii
coircrete
dowirstan'd
asck
i
eift'ed
ortiri
'ndge.
To
acir/eve
aH
ecoiromia'al
edge
beam
des/gM,
a wo
stage
ct/OH
se'eirce
wi/Ike
ised
1n
tiref tstage,
tire
deci
ast
tj
toiitside
tire
edge
beams.
The
weihtof
he
stage
wo
coirstriict/o.'ri
iq'poned
b'
ire
dec(-
wil-ir
edge
beams
atst
ge
o/,e,
am/a
ri//age
a/ra4fs/
cabecarried
out
accord/irg4'.
Thi
ana/qsi
,
ot
preseilted
ere,
but
ire
secM'npropenies
oft/re
stage
oire
edge
beams obeused4r
tirI
aira4'si
are;
effectiVe
Area
=
O,O2m
9
=O.875m
I
=O.24Om
Iii
tage
two,
tireca,rti/everi
addea
as
well
as
the
dicoirt4uuous
parapet
OH
downstairdfascki.
The
of
ire
cross-sect/oir
i
haded
OH
tire
dkigrarn
asedoir
M'i
cross-sectiw,
the
sectioH
to beused
for
irema4r
gri//ageaira4,s,
caH
becalculatedas
or
ire
,rteriral eam
oir
ire
revious
page,
airclare
as
ollows;
Actual
area =1.044
m2
effectiVe
Area
=
1,003m
7
=l,022m
I
=0.316m4
Parapetedge
member'
Alt/rough
he
gri//age
wi//41cluide
members
ruiir#r4rgalo/ig
the
verq'
edgesof
he ecA
these
are
Hot
struictut'rat
aird
verq
smallva/lieswi//be
iisedfortire
sect4'irpropemes.
slab
members;
These
represeirta
1.900m
sect/oir
of
lab;
I
=mbt/12= 0.911.9000.2203/12
=
0.00153m4
There
is
Ho eNd
dkiphragm,
so theeHdslabmembers
s41rplq
epreseirt
0.950m
of
lab;
I
=
mbd/L2
=
0.91
x
0.950
x
0.
220
12
=0.
00077m4
-
8/16/2019 Deck Example
29/100
24 SIMPLE BRIDGE DESIGN USING PRESTRESSED BEAMS
3.7 TORSION
Torsional
inertia
can
be
difficult
to
calculateprecisely.
A
reasonable estimate can
be
made
by
dividing
the
section
up
into
rectangles.
The torsional inertiaof
he
section is
approximately
given by
the
sum of
he
inertiasof
he
individual
rectangles.
In
beam
and slab
bridges,
the
torsional inertia is
normally
small
compared
to the
bending
inertia,
so
this
approximate
method
ofcalculation is
sufficiently
accurate.
For
rectangular
ections,
C
=
k1b3d
where
b is
the
length
of
he shortside
d is
the
length
of he
long
side
and
k1
is a
factor
depending
on the ratio
d/b
If d/b>
2,
then
k1
can
be
approximated by:
k1
=
1/(1
-0.63
b/d)
This formula should
not
be
used for
elements which
represent
sectionsof
a
wide slab.
In this
case,
the valueused
fork1
must
bereflect
the
whole
slab
action,
and
should
not
be
calculated
for
he individualelements. Slabs wist
in
both longitudinal
and
ransverse
directions,
so
the value
ofC ishalved
for each
direction to
reflect his double
action.
Additionally,
he slab
elements shouldbetransformed
in
accordance with the modular
ratio. The torsional
inertia
of
slab
elements is
thus
given
by:
C
=
'/6mb3d
Torsionless
Design
For
many composite
beams,
as
here,
the
torsional inertia is
an
order of
magnitude
less than the
bending
inertia.
The
analysis
of
uch
bridges
can
be
simplified
by
ignoring
the torsion
constraints.
In
other
words,
torsionless
design
can
be
used.
The
resulting
load
distributionis
less
effective
and his
gives
rise o
slightly
increased
bending
moments.
The
correspondingly
increased
design strength
is considered
adequate
to
carry
the
torques
which
would
be
associated
with
a
full torsion
model.
Torsionless
designs
should
not be used for
significant
skews
or boxbeam
decks which
may
bechosen
for their
high
torsion stiffness
properties
or
where torsional
strength
is
a
significant requirement.
Torsion should
also not
be
ignored
in UM beams and thick
edge
beams such
as YE
beams,
evenif nternal beams are considered orsionless.
Edge
beams can
be
subjected
to considerable torsion
due
to loads from the
parapet
cantilever,
and
cracking
of
these beams couldoccur
if orsion is
ignored
in the
design.
-
8/16/2019 Deck Example
30/100
GRILLAGE
MODEL 25
of
secMi,
bq dea/iiiig
Me
ect
o#i
as
ree
I
-
I127.5x
0.220
2
0.540x
1,080
T
7
0.,50x
0.290
fi$ca/cii/ate
i'rern's
for
e
iidMdia/rectaiig/es;
1. Th,
of
a wider
wo
waq
s/a
80 6
frfb3d/6
=O.91OL203xL2P5/6
=0,0021,?
2
d/b
=
L080/0.34o
=3.18
'1
=(1-0.631'/d)/3
=(1-0.63/3.18)/3
=0.26,
6
=i(1b3d
=0.26P0,34O31,080
=Q,Qjf3j4
3.'
d/b
=
0.P5o/o.29o 2,59
,
=(1-0.63k/d)/3
=
(1-0.63/2.59)/3
=0252
C
='1b5d
=O,252x0.29OO,750
=00046i?
Total
s/o#ali',ern,,
C=00021
0.0113
+
0.0046
=0.018,?
for
costparisoir,
1=0.255,?
The
ken'd4rg
lerthT
i
learlf
ver,'
mwcli
larger
MallMe oii,talbiertki.
To,%#
wi/I
Merefore
be
#regleced
-
8/16/2019 Deck Example
31/100
26 SIMPLE BRIDGE DESIGN
USING PRESTRESSED BEAMS
4 CALCULATION
OFLOADS
4.1
INTRODUCTION
The
Departmental
Standard BD 3
7/88,
Loads
for
Highway Bridges,
is
currently
used
to determine
the
loading
on UK
bridges.
BD
37/88
effectively
supersedes
BS
5400
Part2 in he
UK, pending
revisionof
his
Standard,
andit isused
hroughout
this
design example.
The
loads
generally specified
in the
Standard
are
nominal
loads
appropriate
to
a
returnperiod
of
120
years. Design loads
will be obtained
ater
by
multiplying the
nominal
oads
by
load factors
y
given
in the
Standard.
An
additional
factor,
y0,
is
also
introduced
to
obtain
the
design
load effects
(moments,
shears,
etc.)
from the
design
loads. Valuesof
are
given
in
BS
5400Part4
for
concrete
bridges.
4.2 DEFINITIONS
It
is
worthwhile
clarifying
afew
definitions,
as
they may
differ rom
those
used
with
other
structural
design
work:
Dead Load
the
weight
of tructural materials
in the
bridge.
Superimposed
the
weight
ofnon-structural materials
on
the
Dead Load
bridge,
such as road
surfacing, parapets,
etc.
Live
Loads loads
due o
vehicular
and
pedestrian
traffic.
Primary
Live Loads vertical
live
loads
dueto
weight
of
raffic.
Secondary
horizontal loads
due to
change
in
direction
of
Live
Loads traffic
(eg.
centrifugal
forces,
braking,
urching).
Permanent
those
loads considered
to be
acting
at all
times
Loads
(i.e.
DL,
SDL,
and
any
loads
due to
fill).
Transient
all
loads
other
than
permanent
loads
Loads
(i.e.
wind,
temperature,
and live
loads).
-
8/16/2019 Deck Example
32/100
C7ILCUL74TIONOTLOAD
CALCULATIONOF Los
27
Dead
Load
Dead oad
wY/be
car/iedbq
hebeasts
acf-l'tg
%n'e,
with/to
cosipos/te
acz'Ion'.
/f3
&ast
a/oit
e
/irterna/beam'
idge
beam
74ra
=
0.584,m2
(frost
data
s*eet)
Weig'kt
=0,584x24kN/st
=
14.03k/V/st
=
Q584P(f8,)+Q,2c5Q5(s/ab)-
0.
0120(oven'ap)
=0,85325,2
We/g.*t
=0,c5532st224kN/st3
=20.48k/V/st
Area
=0.
5848)
+0.
4592(s/ab+caitt#ever)
=1.044st2
We,kt
=1,044s,224kN/sr5
=25.05
k/V/st
Thi
oad4rg
i
pp/led
o
the
costposie
beast
&
s/ak
strkc$Hre.
Carrkigewa; Aspñaltsiirfach'ig
-f
siip//cltq
assume
stax/st
ist
hi'kness
of
165mst
over
wñole
carnigewai.
ThA
'rc/udesa/b
waitce
for
waterprooflHg rotect/on
boards.
$DL
=0.165st24 /V/st3 =4.0k/V/rn2
=
4.Ok/V/st2
x.
1.275rn =5,1
k/V/st
perbeast
Verge.'
The
wei,t
of
ire
ootpath,
andnon-structural
(d/scontzsruouis)
str4tg
courseand
fasck
wi/I
all
be
taken
as $DL
Total
we,ht
=14.6k/V/st
eack
side
of ridge
8uperh'rposedDeadLoad
-
8/16/2019 Deck Example
33/100
28
SIMPLE BRIDGEDESIGNUSING PRESTRESSED
BEAMS
4.3
HIGHWAYLOADING
Notional lanes
For
the
purposes
of
calculating
the loads to be
applied
to
the
bridge
deck,
the
carriageway
is
split
into
notional
anes.
In this
context,
the
carriageway
is
taken
as
the
distance between
raised
kerbs,
thus
including
the hard
shoulders
(see
Clause
3.2.9.1).
Clause 3.2.9.3 then defines how
the
carriageway
should
be
split
into notional
lanes.
Note that inthis
example
there
are
three
notional
lanes
for
loading
purposes,
even
though
he deck will be
marked
out for
only
two
lanes of
raffic.
HA
Loading
HA
loading
is
a formula
loading representing
normal
traffic
in Great
Britain.
It
comprises
a
uniformly
distributed
load
(UDL)
and
aknife
edge
load
(KEL)
combined,
or
alternatively
a
single
wheel
oad.
For
loaded
lengths
up
to and
including
50
m,
the
UDL
expressed
in kN
per
linear
metreofnotional
laneis
given
by
the
equation:
W
=
336(IIL)°67
where
Listhe
loaded
length
(in
metres)
andW isthe load
per
metreofnotional lane.
The KEL
per
notional
lane
is
always
taken
as
120 kN.
The UDL
and
KEL
are
uniformly
distributed
over the full width
of
he
notional lane
to
which
they
apply.
However,
not all lanes
carry
the
full
HA oadatthe
same
time,
and this isdealt
with
by
means
of
ane
factors.
These
are functions of
he
loaded
length
and the lane
width,
and
are
specified
in
Table 14 of
he
Standard.
The
single
100 kN wheel
load
alternative
to
the UDL
and
KEL
canbe
placed anywhere
on
he
carriageway,
and
occupies
eithera
circular
areaof
340mm
diameterora
square
area
of300mm side.
The
single
wheel oadis
only
significant
in the
local
analysis
of
the
deck
slab,
which
isnot
covered
inthis
design example.
-
8/16/2019 Deck Example
34/100
CALCULATION OF LOADS
29
l-/iahwat
oads
6am'gewa.i
width
=
1,0
(*ardstr')
+
7
3
traffic
aNes)
+1,0
=93m
Three
iot/ona/Iawes
are
rei/red'
Not/offal
aMe
width,
kL
=95
n/S
=5,1 n
/174 load'
Loaded
eirgt/r
=
26.61 m'
/1AUDL
=336(1/L)°6'
=
536(1/26.61)°
k/V/rn
HAAL=120k/V
Wheel oad
=
100
k/V
'si'rgIe oad)
LaMe
factors
kasedoit
L)
3,/&s
Thkle
14.'
a2
=
°157(k
40-L)
+3,
65(L-20))
=
0
013,(3,
1(40-26.61)
+
3.65(26.61-20))
=0,90
&st
aMe
factoi
/3
=
a2
=0.90
$ecoffd
aNe
factoi
/2
=
a2
=090
ThIrd aNe
factoi
133
=
0.60
-
8/16/2019 Deck Example
35/100
30 SIMPLE BRIDGEDESIGN
USING PRESTRESSED BEAMS
HB
Loading
HB
loading represents
abnormal vehicle
loading.
An
example might
bea low load
trailer
carrying
a
power
station transformer,
with tractor
units
at
front
and
rear.
For all
public highway bridges
in GreatBritain theminimum
numberofunits of
ype
HB
loading
that
must
normally
beconsideredis
30,
but this number
may
be
increased
up
to 45 units.
For this
design
example,
the client has
specified
37.5 units
ofHB load.
TheHB vehicleas
defined in the Standard
represents
fouraxleswith fourwheels
per
axle.
One unit
of
oad
represents 10
kNperaxle. Thus he full 45 units
maximum is
equal
to 450 kN
per
axle
or
112.5
kN
per
wheel.
Thedistancebetween he central
woaxles isvariable. For
simply
supported spans,
the smallest
igure
is
obviously
the mostcritical.
As
with the HA wheel load the contactsurface
may
be taken
as circular or
square
with a contact
pressure
of1.1 N/mm2.
Note
thatin this
example
theHBwheel load isless than the
HA
wheel
load. Forslab
design
theHA wheelwill
therefore
be
critical.
Longitudinal
and ransverse
loading
Thisis
only required
for
design
of he
bearings.
-
8/16/2019 Deck Example
36/100
CALCULATION OFLos 31
/15
oad'
Thi
bridge
,
esig',ed
for
37,5 iwits
of/-IS
oad
AyJeload=37,5xl0kN =375k/V
Total/-IS
vehicle
weight
=4
x.375k/V
=
1500k/V
W4'eel
load
=
375
kN/4 =9375
k/V
for
hi
s4ii4siippon'ed
ridge,
theshonest
wheelbasewi/Ike critical
Thus
ditance
bet
wecir
cdiltral
x/es
of
Me 15
vehicle
wi//be
aken'
as
6rn
Jorion'ta/Loads,'
Clause
6,1
0
iVes
the
norn4ra/Ion'gi'tuid4ra//oads.'
HA
/on'gituda/
load
=250k/V
+8
k/V/rn
of/oaded/en'gth
=250kA/+(8k/V/rnx2á.6rn)
=463k/V
Thi
i
pplied
o
on'e n'otion'a/lan'e,
/13
lon'gituidin'a/
load
=25%
of
'orn4ral
/15
wei,ght
=25%
1500k/V
=375k/V
Thii
qp'all.i
ditr,butedbet
ween
the8
wheels
ofapaitof
xles,
butwi/I
Hotbe criticalasiti ess han' the HA
on'gituidin'al
load
Clause
6.11
giVes
the
ornin'altran'sverse oads/
The
n'orn4ral tran'sverse
load
due to
skidd4rg
i
s4tglepo4tt
oad
of300
k/V
acti.Yg
4,
an'q
d,tecti'n
'parallel
o the oad
surface)
-
8/16/2019 Deck Example
37/100
32
SIMPLE BRIDGE
DESIGN
USING PRESTRESSED BEAMS
4.4 WIND LOAD
Methods
of
calculating
wind oads are
given
in
Clause 5.3
of
he
Standard.
Combination
2
loading(seepage38)
is
not
significant
n
itseffectona
argeproportion
of
bridges,
such asconcreteslabor
beamand slabstructures 20mor ess
in
span,
1Om
or more in width and
at
normal
heights
above
ground.
Wind
load thereforedoes not
need
to
be calculated
for
most
bridgesdesignedusingprestressed
beams.
4.5 PEDESTRIAN LIVE LOAD
For
oaded
lengths
of
36m and
under,
the
nominal
pedestrian
ive load
is a
uniformly
distributed live load of5.0 kN/m2.
For
superstructures carrying
both
highway
and
pedestrian loading,
a
reduction factor
of0.8
is
applied
to thenominal
pedestrian
live
loading specified
for
footbridges
alone.
Thus,
in
this case
the
pedestrian
ive load
is
4.0 kN/m2.
4.6
TEMPERATURE EFFECTS
Temperature
effects
produce
two
aspects
of
oading,namely
therestraint
tothe overall
bridge
movement due
to the
temperature range,
and the effects of
temperature
differences
(or gradients) through
he
depth
of he
bridge
deck.
Temperature Range
The
temperature range
for
a
particular bridge
is
obtained
by
first
determining
the
maximum andminimum shade air
temperatures
for the location of he
bridge
from
isotherms
plotted
on
maps
of he
UK,
andshown in
Figures
7
and8
in
the Standard.
As these
isotherm
maps
are
derived from
Meteorological
Office
datarelating
to a
return
period
of120
years
(the
bridge
design life),
it
may
be
necessary
to
adjust
the
temperatures
for
a
return
period
of50
years
forcertain
applications
such as
footbridges
and
carriagewayjoints.
Thisis achieved
by
a
straightforward
increaseorreduction in
temperature
as indicated
in
Clause5.4.2of he Standard.
Maximum andminimum
effective
bridge emperatures
are then derived from Tables
10 and 11 in the Standard. Prestressed
beam
bridges
will
always
be
type
4.
The
effective
bridge
temperature
range
is
then used for
designing
the
bearings
and
expansion joints,
or
if
this movement
is
restrained then in
determining
the stress
resultants in the structure.
-
8/16/2019 Deck Example
38/100
CALCULATION OF LOADS
33
WZ'td oad
Wi,d
oad
speci%'al/i
calcø/ated
for
t*i
'ridge.
assHnted
Mat
Load
6omk/itat/on
2wi//notbe
critical
footpath
Loads
Nom4ya//,Veoad
for
ootpaths
giVen
it Clause6.5,1,1as
5
('N/m.
h'ice
his
bridge
carr,skikwa.i
oad/itg
as
we//as he
ootpath,
the eduction
factorof
0.8
app/is.
Neduced
nom/iuaload
be
applied
=
0.8
x
5.0
=
4.0
kN/m
Temperature Nange
from
D
37/88,
hgures
7
and
&
Miuimuim
hade ait
eli,t'eratgre
=
18
0
Max/mum
shadealt +3606
from
#uire
9,
bridge
construction
i
ype
4.
from
Tab/es
10and11,
M/iu/'ium
effectiVe bridge emperature
=
11°C
Ma/iuuim
effectiVebridge temperatuire=
+36°C
Temperatureange
=
47°C
Coefficient
of
hermal
e.q.'ansiin
=
12x1
Ct6/°C
Length
between
eansi'nj/iuts
=
27m
(approx)
Nange
of
movement
=
47x
(121O6,)
x
27=0.
0152m
Nange
of
movement
fromcentra/posi'tt'n
=
±76mm
-
8/16/2019 Deck Example
39/100
34
SIMPLE BRIDGE
DESIGN USING PRESTRESSED BEAMS
Temperature
Difference
Positive
temperature
differences
occur
within he
superstructure
when
conditions are
such
that
solar
radiation
and other
effects cause
a
gain
in heat
hrough
the
top
surface
of he
deck.
Conversely,
reverse
temperature
differences
occur
when
conditions are
such hat heatis
lost
from the
top
surfaceof he
bridge
deck as
aresultof
e-radiation
and other
effects.
Temperature gradient
diagrams
for each
of
hese states are
shown
on
Figure
9 in the
Standard.
For
surfacing
of hickness
other
than
100mm
these
can
be
modified
by
reference
to
Appendix
C.
The
coefficient
of
hermal
expansion
for
concrete
and
steel is
takenhere as
I
2x
106.
For
concrete with limestone
aggregates,
a
reduced coefficient
of
hermal
expansion
of
9x10-6
can
be
used.
If he deck
were
fully
restrained
ateach
end,
stresses
proportional
to the
temperature
at each
point
in the
deck would arise.
These
emperatures
and stressesare
shown in
the
top
line
of
diagrams opposite.
The
stress
at the
top
of he
slab,
for
example,
is
calculated as:
Stress
=
E
ci.
T
=
(31,000 N/mm2)
x
(12x106/°C)
x
(13.5°C)
=
5.02 N/mm2
In a
simply
supported
deck
there
is
no
axial
restraint
at the
ends,
and no
moment
restraint.
The
axial
and
moment
components
of
hese stresses will be relieved
by
overall
lengthening
and
hogging
of he deck.
A
self-equilibrating
et
of nternal stresses
will
remain;
they
will exist
without
any
external forces or reactions
on the
deck.
These
nternal stresses
are calculated
by
subtracting
he
axial
and
moment
components
from
the
stresses calculated
for the
fully
restrained
condition.
Stresses
due to
negative temperature
differences
also need to be
calculated. These
are not
presented here,
but
exactly
he
same
procedure
is
followed.
It isworth
noting
that the
serviceability
limit state stresses
determined from these
temperature
difference
diagrams
are
subject
to a load factor
of0.8.
-
8/16/2019 Deck Example
40/100
TestfleratureD/fferen'ce
CALCULATION OF LOADS
35
Temeratiire
d/tr/iiz/'M
through
thecross
ect/oH
igiVei,4i iwre
9
ofD
37/88
k,
=0Jim
15.5CC
0,25mfl
Ca/cu/ate
am/force
a#dmoment
omponents
of
hesestresses.
$tress
has
keen
diVideduip
Z#o
fiVe
blocks, 4rd/catedon
dkigram
bove,
jtreaseof
a/cu/at/on.
A
1
1,275x0.15
2
1,275x0J5
3
1,2,75x0,07
4
0.4.zx0.18
5
0.75x0.20
//
74Y
0.626
0214 0154
0651 0.375 0.245
0516 0.086 0,044
0391 0.037 0015
-0.822 0.077 -0.063
Am/force
= =
0787MN
I,,
st'/q
supported
ridge,ne/theraxia/force
ormoment re
4i
act
estra4rea
so
ocked
4t
stresses
are
ca/cui/atedbqsuiktract/ng
these
effects rom'
he
stress
diigram
above.'
Ax/a/re/ease
stress
=
(0.
787
MN)/(0.
829
mi')
=0.95
N/mm
Moment
e/easestress
=
(0.373
M/V&/Z
=
(0.373
MNm)/(0. 475m)
=0.79
N/mm2
at
op'of
eam',
etc.
502
N/mm
PositiVe
teratu1red7ereHce/
Cross
*3
=020m
.5CC
Temperature
Difference
JOiN/mm'
$tresses
41
fui/4i
estrained
deck
=iaT
1,12
1.95
0.96
0.44
0.51
Moment about
centroidal
ax/s
=
=
o.S7SMNm
098N/mm'86N/mm'
095
N/mm'
095
3,18
/mm'
1,02N/mm'
Nestrained
tresses
Moment
from
op
dhtgram
re/ease
re/ease
j37d
144N/m.w'
$eif-
eqii/ibrat4ig
temperature
stresses
-
8/16/2019 Deck Example
41/100
36
SIMPLE
BRIDGE DESIGN USING PRESTRESSED BEAMS
4.7 SHR[NKAGE
When he in-situ
op
iscast on the
precast
beams
some
of
he
shrinkage
of he beams
has
already
occurred. Hence differential
shrinkage
occurs
between he
precast
and
in-situ
concretes,
and his
results
in the
development
of
a
pattern
of nternal stresses.
Clause 7.4.3.4 states
that
he Table
29
shrinkage
values
may
be
adopted.
It
is reasonable
(and usual)
to
assume
thathalf
of
he beam
shrinkage
has
occurred
at the time of
casting
the
top
slab. Hence
the
differential
shrinkage
assumed
in the
calculation is
half
of
he
Table
29
shrinkage
value.
The
effects
of
differential
shrinkage
will
be
reduced
by
creep.
Allowance
ismade
or
this n the
calculations
byusing
a
eduction coefficient,4.
A
value
of
0.43 isnormally
usedforthis
coefficient,
as
given
in
Clause 7.4.3.4.
The
differential
shrinkage
stresses
can be
determined
in
a
similar
manner
to
the
differential
temperature
stresses.
The
restrained stresses are
calculated,
and he
axial
force
and moment
component
are
subtracted
to
give
the
actual internal stresses.
-
8/16/2019 Deck Example
42/100
CALCULATION OF LOADS
37
$ñrirkage
DftreHt/a/shr4tk.age
bet
ween
slab
and
dec,('
creates
itterna/stresses.
/tZ
assiimed/a4
the
otal
hithikageoft/re
beam'has
aI(en
p/ace before
thes/ak
i
ast;
Different/al
kr4t.(-age
stra4r,
=
0.5
x.
(-300x106)
=
-150x106
__________________
15ot
I&I
I
Nest
a/nirg
orce
=
£
. x
A
..
=
-15010
'
x
31000
x.
(L2,5
x
0.220)
x
0.43
=
-0,561 MN
(tensi2w)
Nestra/n4rg
stonrent
=
-0.561
x
eccentric/tJ,f
=-0.561X('1,480-
0.889)
=-0,332MNm'
Ca/ri/at/on
of
nternal
stresses
i
i'tri/arto he
calci/ati#r
fortestperatiire
difference.
Nestrai'redstress
=
x. x.
0
=
-2.0
N/m'm
Ax/al
re/ease
=
('0.561M
N,)/1"O.
829nr,)
=
-0.68
N/mnr
Montent elease
=
A4/Z1,
=
-0.332/0.381
=
-0,
5,
N/m'm'
at
op
of
slab,
etc.
Total4,terna/stresses
ares/townon he
ri/tt
and
digram;
-2.0
N/,m -062
N/mi,r -067
I
—
4N15ôN/mm054
N/mm-
-0,66 N/mi
Nestra,'red
Ax/al
Mom'ent
&/f-eii/likrat4rg
stresses
re/ease re/ease
skr4rtage
stresses
-
8/16/2019 Deck Example
43/100
38
SIMPLE
BRIDGE DESIGN USING PRESTRESSED
BEAMS
5
APPLICATIONOF
LOADS
5.1
LOADCOMB1NATIONS
BD 37/88 considers
fivecombinationsof oads. These are
listed in detail
in
Table 1
of he
Standard,
which
also
gives
load factors to be used in each case.
The five
combinations can be summarised
asfollows:
Comb.
1:
Permanent loads
plusprimary
live oads.
(For railway bridges,
secondary
live
load
is
also
ncluded.)
Comb. 2: Wind
load,
plus
loads
in Comb. 1
(but
with some reduced load
factors).
Comb. 3:
Temperature
effects,
againcombined
with
loads from
Combination
1.
Comb. 4:
Secondary
live loads
(each
considered
separately),
in
combination with
permanent
loadsand theassociated
primary
live oad.
Comb. 5:
Bearings
friction,
together
with
permanent
loads.
Load combinations
1
to
3 are the
primary
combinationsto
be
considered
inthe overall
analysis
of he
bridge
deck. In
pretensioned
beam
bridge
decks,
Combination
2
(including
wind
loading)
is
rarely
critical,
and
is
gnored
in the
design example.
This
leavesCombinations 1 and3
to
be
analysed.
For
bridges
in the
UK,
the
requirements
of
BS 5400:Part
4
mustbemodified
according
to
Departmental
StandardBD
24/92,
The
Design
ofConcrete
Highway Bridges
and
Structures,
Use ofBS 5400:Part 4: 1990. Themost
important change
this ntroduces
relates to the Combination
1
loading.
The beams must
comply
with Class 1 SLS
stresslimits foramodified
version ofCombination 1. BS 5400: Part
4
calls
for
a
maximum of25 units
ofHB load for this
condition,
but BD 24/92 reduces the live
loading
to HA alonefor hiscondition.
This
design example
follows the
requirements
ofBD 24/92.
5.2
SELECTIONOF
CRITiCAL LOAD CASES
In this
example,
maximum
midspan
moments will
obviously
be obtained
by
concentrating
the loads as near
to
midspan
as
possible.
This means
putting
the HA
KEL
at
midspan
in
the lanes
to
which
it
applies,
and also
putting
the HB vehicle at
midspan.
Positioning
of heloads to obtain
maximum
bending
momentelsewhere in the
span,
oron skew
bridges,
is
not so
easy.
The
arrangement
of oads which
give
maximum
effects in the various
beams can be found
by
trial and error.
Alternatively,
some
software
packages
will
automatically
analyse
a
multitude
of
different
possibilities
and
report
themaximum effects.
The
temperature
loads in Combination
3
do not cause
any bending
moments
in
the
beams,
andso
will nothave
a
significant
effect
at
ULS.
Only
Combination
1 therefore
needs to be
analysed
at ULS.
-
8/16/2019 Deck Example
44/100
APPL/CA /ON
Of
L
O74D
TO
5N/LM
APPLICATION OF
LOADS
39
Load Cases
Loadcasesmast eselected
forhe'at
the
gri/lageana4sis.
forhe
designof
he
estressed
beams,
onli
he
maxi,wm
moments
(wh'ith
will
occarat
midspan,),
and
he
max/mi/rn
shear
at
theends
of
hebeamsandat are
needed Moments are
reqjiired
othat$L$
and
at
WL'.
On4
WL is
equiredfor
he
shear
ca/calat4ns,
bat
he
cond/tiwWi//a/so be
ana4'sed
to
giVe
mac'wrn
oadson
the
bearings.
&/ow
s
a
sammary
of
he
oadcases
o
be
analqsed
This
has
been
basedon
fiare
13
of
,])
37/88.
Note
that
he
/-/
ye/ride
s
wider han
a
rothna/
ane, When
the
/1
ye/ride
straddles
the
adjicent
ane,
the
K.L
isomitted
from
hat
ane,
and
he ane
factorfor
he 14
IIDL
s
basedonanot/9na/ ane width
of
2.
Sm,
giving
a ane
factor
of
0.
7S9
see
C/aase
6.4.2(b))
HA with
37.5anitsH
Combiratin 1
atL'
nd
11L
Combi'tat,kn3at
HAwith37.5anitsH
Combination1 atãL
ndUL
Combi',at,n
3 at
HA
with37.5an/tsH
to
max/mise
hearand
eactins
in ane
1.'
Combination1
at
$L nd
UL$
HA,
/14
HA,
J3,=O.9,
iL
130.9
iL
/330.6,
iL
HA,
132=0.789
H vehicle
HA,
/3=O.9,
AL
H,
ye/ride
HA,
132=0.789
H4
J3=0.9,
/(.zL
HA
alone'
Combination1 at
and
11L
Combinati'on
3
at
L,neJ
Le2
krne3
f
—
HA,
HA,
I
vehicle
132=0.789
/3=O.9
AL
1
I
-
8/16/2019 Deck Example
45/100
40
SIMPLE BRIDGE