deck example

Upload: denis

Post on 06-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/16/2019 Deck Example

    1/100

    SIMPLE

    BRIDGE

    DESICN

    USING

    PR

    ESTRESSED

    BEAMS

    ON

    p

    pp

  • 8/16/2019 Deck Example

    2/100

    Simple

    Bridge

    Design

    using

    Prestressed

    Beams

    An introduction to

    the

    design

    of

    simply-supported

    bridge

    decks

    using prestressed

    concrete

    bridge

    beams

    B

    A

    NICHOLSON

  • 8/16/2019 Deck Example

    3/100

    11

    ISBN

    0

    95000347 2

    X

    ©

    Prestressed Concrete Association

    1997

    Prestressed Concrete Association

    60

    Charles Street

    Leicester

    LE

    11

    FB

    Typeset

    by

    B. A.

    Nicholson.

    Design

    by

    G. Ballantyne.

    Printed

    by

    Uniskill

    Ltd.

  • 8/16/2019 Deck Example

    4/100

    CONTENTS

    FOREWORD

    1

    STANDARD

    BEAMS 2

    1.1

    History

    2

    1.2

    Bridge

    deck

    ypes

    4

    1.3

    Choice

    of

    section

    6

    1.4

    Standard sections

    6

    1.5 Practical site

    considerations 8

    2

    BEAM & SLAB DECKDESIGN EXAMPLE

    12

    3 GRILLAGE MODEL

    14

    3.1

    Introduction 14

    3.2

    Suitability

    of

    Grillage Analysis

    14

    3.3

    Grillage

    models or

    prestressed

    beamdecks 16

    3.4

    Deck idealisation

    18

    3.5 Section

    properties

    20

    3.6 Edge stiffening

    22

    3.7 Torsion

    24

    4

    CALCULATIONOFLOADS

    26

    4.1 Introduction

    26

    4.2 Definitions

    26

    4.3

    Highway loading

    28

    4.4 Wind load

    32

    4.5 Pedestrian liveload

    32

    4.6

    Temperature

    effects

    32

    4.7

    Shrinkage

    36

    5

    APPLICATION OF

    LOADS

    38

    5.1 Load

    Combinations

    38

    5.2 Selection

    of

    Critical LoadCases

    38

    5.3

    Input

    to

    Grillage Analysis

    40

    6

    PRESTRESSED BEAMDESIGN

    44

    6.1

    General

    44

    6.2 Design Bending Moments 44

    6.3

    Serviceability

    Limit State

    46

    6.4 Prestress losses

    50

    6.5 Ultimate limit

    state 56

    6.6

    Shear

    60

    6.7

    Longitudinal

    shear

    66

    111

  • 8/16/2019 Deck Example

    5/100

    iv

    7

    FINISHINGS

    68

    7.1

    Introduction

    68

    7.2

    Bearings

    68

    7.3

    Waterproofing

    and

    surfacing

    80

    7.4 Joints

    82

    7.5

    Parapets

    84

    8 SOLID SLAB DECK DESIGN

    EXAMPLE 86

    8.1

    Introduction

    86

    8.2

    Grillage analysis

    88

    8.3

    Design

    of ransverse reinforcement 90

  • 8/16/2019 Deck Example

    6/100

  • 8/16/2019 Deck Example

    7/100

    2 SIMPLE BRIDGE DESIGN

    USING PRESTRESSEDBEAMS

    STANDARD BEAMS

    1.1 HISTORY

    The

    use

    of

    precastprestressed

    beams in

    bridge

    decks in the

    post

    World

    War

    II

    era

    owes its success in he main o the

    foresight

    of he Prestressed Concrete

    Development

    Group,

    which n the 1950's

    developed

    the firststandard

    beamsections

    to

    beavailable

    fromthebeam

    manufacturers.

    This enabled

    factory production

    of

    he

    beams

    on

    a

    large scale, and,

    with the dawnof

    major

    road construction

    in

    the late 1950'sand its

    philosophy

    of

    grade

    separation for

    motorways

    and trunk

    roads,

    it

    gave bridge engineers scope

    to

    rationalise

    design

    procedures usingup-to-date

    load distribution theories.

    The standard beam sections available

    at that time have ofcourse themselves been

    developed

    and

    modified,

    and in essence

    only

    one

    really

    remains

    today

    with

    any

    significant usage.

    This

    beam,

    he inverted

    T

    beam,

    s

    used n

    bridge

    decks in

    spans up

    to

    about 20 metres.

    With herapid

    development

    of

    he

    UK

    motorway

    network

    n the

    1960's,

    it

    wasclear

    that here

    was

    scope

    for

    a

    standardbeam hatwould enable

    larger spans

    tobe

    achieved.

    Consequently,

    at

    the end of he decade

    a

    new beam was

    introduced

    for

    spans

    from

    about

    15 to 30metres. This was

    designated

    the

    M

    beam,

    due o itswidth and ntended

    spacing.

    These

    beams were intended

    for

    use

    in

    pseudo-slab bridge

    decks with

    a

    contiguous

    concretebottom

    flange

    using

    transverse reinforcement located

    hrough

    lower

    web holes at 600mm centres

    along

    the beams.

    Eventually engineers

    realised that he Mbeamcould

    be

    used more

    efficiently

    in

    beam

    and slabdecks

    by eliminating

    the bottom in-situ concrete and

    by

    spacing

    hebeams

    apart

    at

    up

    to

    1.5

    metre centres. The limitation

    on thistype

    of

    use

    proved

    to be

    the

    shear

    capacity

    of he

    beams,

    whichhave

    a

    web thickness of

    only

    160mm.

    Other

    beams

    developed

    around this time were the

    U

    beam

    for

    beam and slabdecks

    up

    to about30 metre

    spans,

    anda

    U

    shaped

    variation

    of he

    M

    beam

    foruse

    as

    edge

    beams

    in M

    beam

    decks.

    Eventually,

    with the

    very popular

    M

    beam

    being

    used in

    a

    manner somewhat different

    from its intended

    use,

    and

    bearing

    in mind the various

    problems

    and

    limitations his

    presented,

    a

    newbeamwas

    developedby

    the Prestressed

    Concrete Association

    in the late 1980's. This was

    designated

    theY

    beam.

    The

    Y

    beam now has three

    variants: the

    TYbeam,the

    Y

    beam,and the SY

    beam.

    Together

    these cover all

    span ranges up

    to

    45m. It

    is

    expected

    that

    in

    due course

    inverted T beams and

    M

    beams

    will cease

    to

    be used

    in

    favourof he enhanced

    properties

    of he

    Y

    beam

    anges.

  • 8/16/2019 Deck Example

    8/100

    H

    M beam

    Inverted T beam

    U beam

    STANDARD BEAMS 3

    TY beam Y

    beam SY

    beam

  • 8/16/2019 Deck Example

    9/100

    4 SIMPLE BRIDGEDESIGN

    USING PRESTRESSED BEAMS

    1.2

    BRIDGE DECK TYPES

    Concrete

    bridge

    superstructures

    using precast

    prestressed

    concretebeams fall

    into

    threedistinct

    ypes:

    slab

    decks, pseudo-slab

    decks,

    andbeam and slabdecks.

    Slab Decks

    Slab decks can be solid or

    voided,

    and

    provide simplysupported spans

    of

    up

    to

    20

    metres. Thesedecksusestandard TY or inverted

    T

    beams

    placed

    side

    by

    side. The

    space

    between them is then filled with in-situ

    concrete,

    and an overall

    covering

    of

    75mm

    completes

    the deck.

    Continuity

    of

    hese

    decks

    canquiteeasilybe

    achieved

    by

    using

    einforcement

    in

    the

    in-situ concrete

    over the

    supports. Suspended

    spans using

    TYbeams or inverted

    T

    beamscanbe

    lightened

    by

    introducing

    voidformers into the

    space

    between the beams.

    Pseudo-slab

    Decks

    This

    type

    of

    bridge

    structure

    is

    currently

    not

    quite

    so

    popular.

    Precast

    beams are

    incorporated

    intoavoidedslab

    ype

    ofdeck

    by

    either

    adding

    an in-situ bottom

    flange

    and

    op flange,

    aswith the

    original

    Mbeam

    decks,

    or

    by using

    voidedbeams

    e.g.

    box

    beams).

    A voided slab deck is thus created without the inconvenience

    of

    emporary

    works

    andsoffit

    shutters,

    and

    provides

    a

    torsionally

    stiffer deck than

    ordinary

    beam andslab

    decks.

    Spans

    for this

    type

    of

    bridge

    deck are

    usually

    imited

    by

    the

    length

    of

    precast

    beams

    that canbe

    transported

    to

    site,

    and thereforeare

    rarely

    more than 30 metres.

    BeamandSlab Decks

    The mostcommon

    type

    of

    uperstructure

    for small

    o

    medium

    spanbridges,

    this

    ype

    ofdeck

    comprises

    individual

    precast

    beams

    at

    discrete centreswith anin-situ concrete

    top flange.

    M

    beams,

    TY

    beams,

    Y

    beams,

    SY

    beams,

    and Ubeams can all be used

    inthis form

    ofconstruction.

    Withmost

    of

    hestandard

    range

    of

    precast

    beamsthe in-situ

    concrete

    top

    slab

    is

    cast

    into

    permanent

    formwork whichislocated nrecesses formed

    n he

    edges

    of he

    top

    flanges

    of he beams.

    Typical spans

    for this

    type

    ofdeckare similar

    o the

    pseudo-

    slabdecks

    above, being

    imited

    in the main

    bytransportable

    beam

    components.

    Standard

    edge

    beams are available to

    complement

    the

    Y

    beam,

    TY

    beam,

    and

    M

    beam

    anges.

    These

    provide

    avertical visible

    face,

    and

    have he

    capacity

    to

    carry

    he

    extraloads from

    the

    parapet

    cantilever.

  • 8/16/2019 Deck Example

    10/100

    STANIAiu

    BEAMS

    5

    This solid

    slab

    deck uses

    19

    T2

    beams.

    Service

    ducts are included in

    the

    infihl

    concrete

    between

    he

    beams.

    This

    bridge

    deck uses nine

    US

    beams

    at a

    spacing

    of1

    .72m.

    Service ducts

    run under

    the

    footpath.

    A

    carrier drain

    runs

    through

    one

    of

    he

    U

    beam

    cells.

    This

    bridgedeck uses

    seven Y8

    internalbeams

    at a

    spacing

    of

    1

    .275m,

    and

    YE8

    edge

    beams on

    each

    side.

    Service ducts

    run under

    the

    footpath.

  • 8/16/2019 Deck Example

    11/100

    6

    SIMPLE

    BRIDGE DESIGN USING PRESTRESSED

    BEAMS

    1.3 CHOICE

    OF SECTION

    For the

    types

    of

    superstructure indicated above,

    the beam

    manufacturers provide

    standard details

    of

    he

    individual sectionsand their

    anges together

    with anindication

    of

    ypical span ranges

    for

    decks

    incorporating

    these beams

    and

    carrying

    standard

    highway

    loads.

    Therewill

    obviously

    besituations

    where the choiceofdeck

    type

    isnot

    clearly

    indicated

    by

    the available

    span,

    and itisalso inevitable

    that herewill beareas

    of

    overlap

    where

    the choice between

    invertedTbeams in a slab

    deckor ndividual M or Y beams

    n a

    beam and slab deck

    may

    not be

    clear cut.

    In this

    situation

    it

    may

    be

    necessary

    to

    evaluate more than one

    solution,

    and hestandard sections enable aswift

    selection of

    the

    available ranges

    for

    comparative design exercises

    to

    be

    undertaken

    and cost

    comparisons

    made.

    It is also

    possible

    within

    thestandard

    range

    of

    each beam

    ype

    to be in a

    span

    range

    that is covered

    by

    more hanone

    specific

    beamunit. In thissituation

    it

    is

    usually

    cost

    effective

    o

    select the

    larger

    unit where

    there arenorestrictive imitationsonheadroom.

    1.4

    STANDARD SECTIONS

    Design

    Although

    he various

    types

    ofstandard

    beam

    sections are

    well

    documented

    interms

    ofdimensions

    andstructural

    properties,

    it is

    mportant

    to

    point

    out that these

    factory

    produced

    beams are standard

    only

    to the extent

    that

    they

    are manufactured

    using

    standard

    shaped

    sections. The amount

    and

    magnitude

    of

    prestress

    applied

    to

    each

    beam is

    dependent

    on its

    individual

    situation,

    and mustbe

    determined

    by

    the

    designer

    prior

    to

    manufacture. The standard sectionsshow

    where

    prestressing

    strands

    may

    be

    located,

    but

    it isthe

    responsibility

    of he

    designer

    todetermine which

    of

    hese are

    to

    be

    used.

    Intheir

    literature,

    themanufacturers

    givesuggestions

    for

    gooddesign

    details. These

    should be adhered

    to,

    as

    they

    leadto

    economy

    and

    good workmanship.

    Manufacture

    Precast

    prestressed

    beams

    aremanufactured n

    long

    lines

    of

    everal

    units

    using

    straight

    strands.

    These

    are debonded

    for

    varying

    distances

    at

    the ends

    of

    each beam

    within

    the

    mould. Thisis

    necessary

    tomaintain the

    stress inthebeam atan

    acceptable

    level

    as the

    self-weight bending

    moment educes

    approaching

    the

    supports.

    Once theconcrete

    in

    the moulds reaches the minimum

    transfer

    strength, detensioning

    can take

    place,

    the strands between the beamcan

    be

    cut,

    and the beamsremoved

    to

    the

    storage

    area

    prior

    to

    delivery

    o site.

  • 8/16/2019 Deck Example

    12/100

    Standard

    positions

    for

    prestressing

    strands inaY8 beam.

    It is

    up

    to

    the

    designer

    to

    decidewhichof hese strand

    positions

    o

    use.

    STANDARD

    BEAMS 7

    Span

    in

    metres: 12

    14 16 18 20 22

    24 26 28 30

    32

    Beams

    at im

    centres

    Beams

    at

    2m centres

    £

    Beam

    selection chart for the

    Y

    beam

    range,

    takenfrom PCA

    literature.

    -1-4-

    4--I-

    -4--I-

    4--I-

    -4-4-

    -4--I-

    -I--I-

    -I--I-

    -4--I-

    1300

    1200

    1100

    1000

    900

    800

    +4--I--I-

    -4- -4-

    4-

    260

    210

    160

    -

    110

    60

    0

  • 8/16/2019 Deck Example

    13/100

    S SIMPLE BRIDGE

    DESIGNUSING PRESTRESSED BEAMS

    1.5 PRACTICAL SITE

    CONSIDERATIONS

    Handling

    Beamsare

    usually

    manufactured

    with

    lifting loops,

    hus

    enabling

    on site

    lifting

    to

    be

    achieved

    witheither

    single

    or twin cranes

    o suit he site

    requirements.

    However,

    TY

    beams and

    inverted T beams are

    usually

    lifted

    using

    a

    sling

    through

    the end web

    holes.

    Access

    to

    Site

    Itisof

    obvious

    importance

    that there

    is

    suitable access

    to

    the

    bridges

    in order forthe

    beams o

    be

    delivered

    and

    lifted

    off

    he trailerby

    suitably located cranes.

    Of

    course,

    this also

    applies

    to

    the route to the

    construction

    site

    which

    must

    allow

    the

    delivery

    lorries

    omanoeuvre

    their

    engthy

    loads.

    There s

    generally

    no

    problem

    in he

    transportation

    ofbeamsof he

    lengths

    described

    in thisbook.

    Camber

    Variation in camberof

    prestressed

    beams

    is

    nevitablewhenoneconsiders

    he olerance

    in

    prestress

    force and

    ocation,

    togetherwithpossible

    variation

    in concrete

    properties

    with

    maturity

    andclimatic conditions.

    It

    would

    thereforebe

    impracticable

    o

    specify any

    limitationon

    camber

    values, although

    a

    olerance

    oncamber variation between beamshasbeen

    adopted.

    However,

    it

    should

    been

    borne

    in mind

    by

    the

    designer

    that an

    occasional failure

    to meet

    the

    specified

    tolerance

    on

    soffit level variation does

    not result n

    impossible

    constructionconditions.

    Thecareful

    positioning

    of

    adjacent

    beams

    n adeckshould

    nearly

    always

    result n an

    evening

    outofdifferential camber.

    Edge

    Details

    On

    site,

    construction

    of

    parapet

    tring

    courses

    in one

    or

    more

    stages generally

    follows

    the construction

    of

    he central deck slab area.

    This necessitates the formation

    ofa

    construction

    joint

    along

    the

    edge

    beam

    prior

    to

    constructing

    thefascia.

    Alternatively,

    it

    is sometimes

    possible

    to

    construct

    thefasciaas

    a

    second

    stage casting

    in the

    manufacturer's

    yard, prior

    to

    delivery

    to site

    as

    analmost

    complete

    unit. One

    advantage

    of

    this

    is

    that

    the

    beam can

    be

    propped quite easily

    at the

    works,

    thus

    enabling

    stresses

    nthe

    precast

    beamsection tobeminimised.

  • 8/16/2019 Deck Example

    14/100

    /

    STANDARD BEAMS 9

    This section

    can be

    cast on

    site

    as

    a

    second

    stage

    after

    the

    rest of

    the deck,

    or

    alternatively can

    be

    cast

    onto

    the UM beamby

    the

    manufacturer

    so that

    the

    edge

    beam and

    parapet

    can

    be

    brought

    to

    site

    as

    a

    single

    unit.

    Two

    examples

    of

    edge

    details

    Second

    stage

    in-situ

    concrete

    in-situ

    concrete

    Cast

    by

    manufacturer

  • 8/16/2019 Deck Example

    15/100

    10 SIMPLE BRIDGEDESIGN

    USING PRESTRESSED BEAMS

    Skew

    Although

    it

    is

    possible o

    manufacture

    precast

    beams

    with skew

    ends,

    he increase in

    cost for each unit and

    the

    problems

    that skew

    presents

    should be considered

    in detail

    at the

    design

    stage.

    Firstly,

    it

    should

    be

    remembered

    thatevena

    very

    small

    change

    inskew

    angle equires

    anew

    stop

    end for the mould. A

    change

    from

    say

    300

    to

    31° increases the width

    by

    12mmfor an

    M

    beam.

    To rationalise a

    range

    of

    angles

    with a variation

    of

    10°, say,

    would be auseful

    andeconomic

    possibility

    Structural

    problems

    created

    by

    skew

    in the endsof

    precast

    beamsrelate

    specifically

    to

    the acute corner,

    where the

    formation

    of

    cracks can cause the

    corner

    of

    he flange

    to

    spall

    whenthe beamcambers

    during

    transfer.

    Although

    not

    structurally significant,

    this is

    undesirable,

    and isbest

    prevented by blocking

    out the corner to

    give

    a local

    square

    end.

    An additional

    problem

    that

    presents

    itselfwith skew beams is hatof

    ocating

    ransverse

    reinforcement

    through

    thewebholes. Itisrecommended that thestandard

    webholes

    permit

    reinforcementtobe

    placed

    forskews

    up

    to about 35°.

    Higher

    skewshan this

    would

    require

    special

    non-standard

    web

    holes,

    whichwould increase the costof he

    beams

    significantly,

    and

    may

    evenaffect

    the shear

    capacity

    of hesection. For

    high

    skew

    bridges,

    it

    is

    normallybetter

    to

    place

    thetransverse

    deck

    reinforcement

    at

    ight-

    angles

    o the beams rather han

    parallel

    to the

    abutments.

    Transverse Reinforcement

    For the transverse

    reinforcement

    through

    the webholes of

    precast

    beams,

    it is

    usually

    betterto use

    anumberof mallerbars rather thana

    single large

    diameter

    bar,

    as

    lap

    lengths

    are reduced

    and

    handling

    becomes easier. For some awkward skew situations

    it

    may

    even be sensible

    to use untensioned

    prestressing

    strand threaded

    through

    the

    web

    holes

    instead of

    einforcing bars,

    as it ismore flexible.

    The

    positioning

    of ransverse deck

    reinforcementwhen

    using

    solid

    edge

    beams

    may

    require

    the useof

    couplers

    atthe

    edge

    beaminterface.

    Temporary Support

    Itis

    mportant

    to ensure

    that the beamsarc

    supported

    so that

    they

    cannot

    topple

    over

    on site.

    Deeper

    beams,

    particularly

    when

    beingjacked

    to their final level and

    during

    bearing

    installation,

    mustbe

    assessed to eliminatethis risk.

  • 8/16/2019 Deck Example

    16/100

    STANDARD BEAMS 11

    Local

    square

    end

    to M

    beam

    330

    wide

    Diaphragm

    800 wide

    M

    beam

    bridge

    deck

    with

    45°

    skew.

    Diagrams

    show

    endsof

    M

    beams

    embedded

    in

    a

    diaphragm.

    tDecks1ab

    M

    beam

    Web

    hole at end

    ofM

    beam,

    for

    diaphragm

    reinforcement

    Diaphragm

    I

    L

  • 8/16/2019 Deck Example

    17/100

    12

    SIMPLE BRIDGE

    DESIGN USING PRESTRESSED BEAMS

    2 BEAM

    & SLAB DECK DESIGN

    EXAMPLE

    Sections 3 to

    7

    of

    his book

    consist

    of

    a

    design example

    of

    a

    beam and slab

    deck.

    This

    design

    example

    shows the

    typical sequential

    calculations

    necessary

    for thefull

    design

    of

    a

    precast

    pretensioned

    concreteY beam

    in a

    simply supported

    beam

    and

    slab

    bridge

    deck.

    The

    right

    hand

    pages

    show the numerical

    calculations involved ateach

    stage,

    and the

    left hand

    pages

    contain

    explanatory

    comments

    andfurther information.

    The

    example bridge

    has the

    following design requirements:

    Span

    26.6lm

    single

    span

    Width

    7.3m

    carriageway, plus

    I

    .0m

    hard

    strip

    each side

    1

    .5m

    footpath

    eachside

    Loading

    HA

    plus

    37.5 units HB

    Surfacing

    100mm

    thick

    (minimum) plus

    20mm

    waterproofing

    The

    following

    materials

    willbeused:

    Precast concrete

    =

    50N/mm2

    fd

    =40N/mm2

    In-situ concrete

    f

    =

    40N/mm2

    Prestressing

    strand 15.2

    mmdiameter

    Dyform

    strand

    f

    =

    1820 N/mm2

    Area

    =

    165 mm2

    per

    strand

    The

    edge

    detailwas chosen

    foraesthetic

    reasons,

    and the outerbeams

    placed

    as near

    tothe

    edges

    of he

    bridge

    within his

    limit. This ledtothe beam

    spacing

    of1 275m.

    The

    span

    charts for Y beams

    give spans

    for beams

    at I and 2 metre

    spacings.

    It is

    straightforward

    to

    interpolate from

    this

    information

    to

    make an initial

    selection

    of

    beam

    size,

    in thiscase Y8.

    Clearly

    alternatives would have been

    possible,

    for

    example

    eleven Y6 beamscould

    have been

    used,

    atabout 1 metre

    spacing.

    However,

    ithas been found hatunless it

    is

    necessary

    to make the deck as shallow as

    possible,

    it

    is

    usuallypreferable

    to use

    fewer but

    larger

    beams.

  • 8/16/2019 Deck Example

    18/100

    DESIGN

    EXAMPLE

    13

    13350

    Overall

    llatdstn'p

    £rniagew

    fw

    540 1500 1000

    7300

    1000 1500 540

    1275 1275

    Cross

    se/

    f ridge

    decfordes#/,

    xgir/e

  • 8/16/2019 Deck Example

    19/100

    14 SIMPLE BRIDGE

    DESIGNUSING PRESTRESSED BEAMS

    3 GRILLAGE MODEL

    3.1 INTRODUCTION

    Early

    bridge

    decks were

    analysed

    ona

    strip

    basis. Abnormal

    and wheel loads were

    crudely

    distributed and conservative

    designs

    resulted.

    Experimental

    data became

    available

    todeterminethe ransverse load

    carrying

    characteristicsofdeckstodetermine

    thecorrect

    level of ransverse

    strength provision

    and

    todistribute loadmore

    ogically

    to the

    longitudinal

    members. For

    example,

    in the

    1950'sMoriceand Little

    developed

    a Distribution Coefficient

    method which was a

    simple

    hand method based on

    experiments

    which

    allowed

    for

    the

    overall distribution

    of

    oads

    on

    a

    plate structure

    such

    as

    a

    bridge

    deck.

    It was

    satisfactory

    for skews

    up

    to200. This method was one

    of everal similar

    echniques

    extensively

    usedin

    design

    offices

    for

    approximately

    15

    years,

    until the adventof

    omputer techniques

    which enabled

    larger

    andmore

    complex

    structures

    to be

    analysed

    more

    accuratelyusinggrillage,

    finite

    strip

    and

    finite element

    methods. Of hese threemethods

    grillages

    offer the widest

    range

    of tructures

    which

    can

    be

    analysed.

    Popular opinion suggests they

    are also the easiest

    to use and

    understand.

    No

    analysis

    method

    gives

    a

    rigorous

    solution,

    and some

    degree

    oferror must

    be

    accepted, usually

    angingup

    to

    10%

    or

    20%

    depending

    on

    complexity.

    These

    errors

    come

    fromseveral

    sources, including

    the idealisation

    of he

    geometry

    andmaterial

    properties,

    and idealisation of he structural

    behaviour.

    Grillage analysis

    has

    found favour as a

    bridge engineer'sdesign

    tool because it is

    perceived

    to have

    the

    following

    advantages:

    Grillage

    beams

    can be

    positioned

    to

    correspond

    with

    physical

    beams

    n

    the real

    structure,

    or

    wheremaximum effects are

    anticipated.

    Modern PC versions

    have 'user

    friendly' input,

    often

    designed

    by

    engineers,

    and use

    pre-

    and

    post-processors

    to

    ease

    subsequent checking,

    searching

    and

    analysis.

    Familiarity

    of

    use in the

    design

    office

    enables

    rapid analysis

    and

    checking,

    which isvital ina

    competitive

    market.

    Programs

    are

    relatively cheap,

    thus

    making analysis

    economic.

    3.2 SUITABILITY

    OF GRILLAGE

    ANALYSIS

    The

    method

    can

    be

    used for

    structures with

    beamand slabs

    decks,

    voided slabs or

    solid slabs.

    Itcan be usedfor

    simple

    andcontinuous

    bridges,

    and allow for elastic

    supports

    andsettlement.

    It issuitable for

    right,

    skew

    and curveddecks. This

    range

    covers hundredsifnot housands

    of

    bridge

    decks

    designed

    inrecent

    times,

    and

    certainly

    covers

    all

    bridges

    with

    prestressed

    beams.

  • 8/16/2019 Deck Example

    20/100

    GRILLAGE

    MODEL 15

    NILLAfi

    ANAL

    418/8

    This

    km/ge

    wi/Ike

    aira/ysed

    with

    a

    gill/agea#a/qsiS.

    The

    an'a/qsiS

    wY/be

    etformedasitig

    he

    conipaterprogram

    "STAN)

    111/181)8

    "

    from'

    T

  • 8/16/2019 Deck Example

    21/100

    16

    SIMPLE BRIDGE DESIGN USING PRESTRESSED

    BEAMS

    3.3 GRILLAGE MODELS FOR PRESTRESSED

    BEAM

    DECKS

    Longitudinal grillagebeams areplaced

    on he

    line

    of

    hephysicalbeams,

    and

    represent

    the

    composite

    action

    of

    he beam and its

    associated section

    of slab.

    Longitudinal

    beams arealso

    positioned

    along

    the

    parapet edge

    beam. Transverse elements

    represent

    the

    top

    slab. Thereare no end

    diaphragms

    in this

    bridge,

    but whenthese are

    present

    they

    must also

    be

    represented

    by

    appropriate

    transverse elements.

    This

    type

    of

    grillage

    model

    is

    suitable for beam

    and slabdecks

    using

    M-beamsand

    Y-beams.

    Because

    of

    he

    usually arge

    numberofbeams naT-beam

    deck,

    it

    may

    be

    preferable

    to

    model

    two or three

    beams

    by

    onegrillage

    member. Transverse elements represent

    transverse solid

    infill

    elements.

    Because of henon-uniform

    shape

    of

    hese elements

    as

    they pass

    over and

    through

    he beams their

    depth

    is

    normally

    taken to the centre

    lineof he ransverse holes. Thewider

    spacing

    of

    model elementsdoes not

    materially

    affect the transverse element idealisation since the structure acts

    as

    a

    true slab.

    However,

    care

    isneeded

    when

    evaluating design

    moments

    shearsand

    reactions due

    to

    thecombination

    of

    everal

    physical

    elements into

    single

    model elements.

    U-beam

    decks,

    although basically

    beam and slab

    decks,

    behave

    differently

    because

    the

    transverse stiffness

    alternates across the

    deck

    between stiff

    hrough

    the

    beams

    and

    flexible between

    the

    beams.

    The

    beams

    are

    positioned

    to

    try

    and

    equalise the top

    slab

    spans

    between

    and acrossbeams. Onemethod

    of

    modelling

    a

    U-beamdeck

    is

    o

    place longitudinal

    elements

    on

    hecentrelineof ach

    web. The

    longitudinalproperties

    for

    each

    grillage

    beam are then

    taken as

    half

    hat of he

    composite

    box section. As

    with the inverted T-beam

    decks,

    care

    is

    required

    in

    evaluating

    the

    output

    since here

    are now two

    longitudinal

    elements

    representing

    one

    physical

    beam.

    r n

    •1

    n

    \U/ \U/

    \

    p p p p p

  • 8/16/2019 Deck Example

    22/100

    GRILLAGE MODEL

    17

    oft/re

    deck

    The

    bridge

    looks

    like

    thi;

    Their-s/tii

    dowHskHdfa'sck7

    aNd

    tkearetbeevi,

    reboM

    d,cot/,gog

    a,rdso do rot

    co#tribite

    10te

    S

    Theci

    s-sec1lo,r

    oft/re

    strgctiiral

    elemeirts

    oft/rebridge

    I

    t/reremre'

    ri/lage

    eams

    willbe

    /aced

    o

    ire

    ites

    oft/re

    t/ire

    preteirsioired

    beams,

    airdirom4ra/edge

    beams

    wi/Ibe

    p/aced

    a/oirg ireparapetke'ams.

    Thustire

    grit/age epreseirtatA'r

    ft/re

    cross-sectloiti

    p

    Traitsverse memberswillbe

    provided

    at

    1. 9Osr

    4rtetva/s

    o

    epreseirt

    ireslab.

    Thi

    diVides ire

    leiigtir

    oft/re

    deck4rto

    14

    eqjialsectiirs.

    The rodes

    of

    ire

    grit/age

    will

    geiret-a/ly

    beoit

    a

    grid

    of

    1900

    .

    1275,

    wir/ciri e//belowa

    2,'l

    aspect

    atio aird

    lireref

    re

    satifactorq.

  • 8/16/2019 Deck Example

    23/100

    18

    SIMPLE

    BRIDGEDESIGN

    USING PRESTRESSED

    BEAMS

    3.4 DECK IDEALISATION

    Grillage analysis

    idealises

    a

    deck into

    a

    grid

    of

    interconnected beams. The real

    dispersed

    effects of

    bending,

    shearand

    torsion

    are assumed

    o

    be

    concentrated

    in the

    nearest

    equivalent

    grillage

    beam.

    Variations from

    the

    true behaviour

    arise because

    the real slabs

    element

    equilibrium

    requires torques

    and wists o be identical

    and n

    orthogonal

    directions,

    but

    in

    grillages

    the

    joints

    can

    rotate

    differently.

    However,

    if

    a

    slab

    is

    modelled

    by

    a

    sufficiently

    fine

    grillage

    mesh

    these anomalies are smoothed

    out

    tobecome almost

    insignificant.

    Again,

    moments

    in

    grillage

    beams

    are

    proportional

    to

    the

    beam

    curvature

    in that

    direction.

    In real

    slabs,

    moments

    also

    depend

    on the

    orthogonal

    direction

    curvature,

    but

    this

    error

    is

    also

    sufficiently small

    to

    be

    ignored.

    There are

    a few

    fundamental

    requirements

    for

    competent

    grillage

    modelling:

    Place the

    grillage

    beams coincident

    with

    the

    physical

    beams or

    ines of

    designed

    strength.

    Where

    possible, lay

    out

    the

    grillage

    o

    capture

    all

    the

    load,

    and for

    ease

    of

    hape generation

    and

    section

    property

    calculations.

    Transverse elements

    should be

    spaced

    to

    try

    and reflect

    the

    aspect

    ratio

    (length/width)

    of he

    whole

    deck.

    Skew decks

    can

    be

    analysed

    by

    orthogonal

    or skew

    meshes.

    If

    he

    skew

    exceeds

    20°,

    the

    model should

    be laid out

    within 5° of he real

    skew.

    Generally,

    transverse members should be

    orthogonal

    to the

    longitudinal

    members,

    particularly

    when

    skew exceeds 20°.

    Bearing

    positions

    should

    be

    represented

    faithfully,

    and

    in

    skew

    bridges

    the verticalstiffnessmust

    be

    modelled with care

    as

    hey

    can have

    significant

    effect

    on

    theoretical distribution

    of

    oad.

    Once

    the

    grillage

    model has beenset

    up,

    it is

    recommended

    that an initial est load

    is

    applied

    (such

    as

    auniform

    UDL),

    to

    verify

    hat it

    is

    behaving correctly.

    The test

    load

    case

    should

    be

    checked

    against some simple hand calculations (e.g. wL2/8)

    o

    make

    sure

    that the results

    are reasonable.

  • 8/16/2019 Deck Example

    24/100

    n//aae

    mvde/

    The

    gill/age

    wode/is/towit

    be/ow

    GRILLAGE

    MODEL 19

    The

    (fr-stdkgcast

    s/tows he

    ,ode

    rHmbers,

    aitdfrtdicates

    sti/'orts

    a cfrc/e.

    The

    secoirddhigram

    s/tows he

    tenrbern#mbethrg.'

    15

    30

    45

    60

    75

    90

    105

    120

    135

    150

    165

    15

    50

    1

    ———-

    38

    1

    46i

    53

    61

    91

    106

    121

    136

    68

    76-

    151

    t5t

    152 164

    1 5

    ———--

    16

    1

    ii

    18 19

    — —

    ——

    ——

    249

    262

    263

    290

    156 ISP 158 159

    304

    130

  • 8/16/2019 Deck Example

    25/100

    20

    SIMPLE

    BRIDGE DESIGN USING PRESTRESSEDBEAMS

    3.5

    SECTION

    PROPERTIES

    Since

    he precast

    and n-situconcrete

    trengths

    do not differby

    more

    than

    10N/mm2,

    Clause

    7.4.1

    permits

    a modular

    ratio

    of1.0

    to be used.

    However

    inthe

    example

    a

    more

    accurate

    valuehas been

    calculated

    taking

    into accountof

    he

    different concrete

    strengths.

    The

    Y

    beams

    have

    standard notches

    50 mm

    deep along

    he

    top

    edges.

    These allow

    formwork

    tobe

    placed

    between

    the beams o

    support

    the deck concrete. In

    this

    case,

    20 mm hick

    permanent

    formwork

    is

    used,

    sothat he beam

    protrudes

    30 mm

    into the

    deck

    slab.

    The

    overall

    height

    of he section

    is

    1.590

    m.

    The

    composite

    section

    properties

    are calculated

    by

    assuming

    the

    section is

    made

    up

    from the Y8

    beam,

    a

    rectangular

    slab

    which overlaps

    it

    by

    30mm,andthe small

    overlap

    area

    which must

    be subtractedas it hasbeen

    counted twice.

    The code

    permits

    stiffnesses

    tobe

    represented

    on

    the

    gross

    concrete

    ection

    ignoring

    the

    reinforcement or strand.

    This is the

    most

    straightforward,

    since

    the

    amount of

    reinforcement

    and

    strand

    hasnot

    yet

    been

    accurately

    determined

    at he

    analysis stage.

    In

    some

    situations,

    such as

    continuous

    bridges

    at

    supports,

    the

    transformed section

    may

    be

    important

    and

    should

    be

    used.

    Under

    transient

    applied

    forces

    the short term

    elastic

    modulus should

    be

    used,

    and

    under

    applied deformations

    or

    long

    term

    loads

    the

    long

    term

    modulus should

    be

    used.

    To save

    analysis

    time

    for

    hese

    two

    situations

    a

    value

    between

    long

    and

    short

    may

    be

    chosen,

    ideally

    reflecting

    the

    proportion

    of

    permanent

    to

    transient

    effects.

    Almost

    all

    analyses

    are

    executed

    on

    elastic

    models,

    even

    though

    the

    code

    allows

    plastic

    methods with

    the

    approval

    of he

    bridge authority.

    An

    elastic

    analysis

    is

    appropriate

    for

    he

    serviceability

    limit

    state,

    which

    s

    the

    most

    important

    for

    the

    design

    of

    he

    pretensioned

    beams.

    The use

    of

    an

    elastic

    model

    for

    he ultimate limit state is

    simple

    and

    conservative. It

    is

    a lower bound solution

    in

    which

    the

    structure

    is

    in

    equilibrium

    and

    yield

    isnot

    reached.

  • 8/16/2019 Deck Example

    26/100

    $ectloir

    Propemes

    &am

    lo,,e.'

    S

    ean,,

    prg'erns

    rom'

    data sheet

    74rea

    =

    0.5847m2

    9=0.639

    m'

    I

    =

    0,1188s,

    Comt'os/te

    8/ab

    cocretef,

    =40

    N/nrm'2,

    =31

    tN/m'nr

    &an,

    cocretef

    =50

    N/mwr,

    =34

    N/m'm't

    Mod#/ar atio

    =

    31/3

    4 =0.91

    The

    actual

    area

    i

    e4jiiredor

    a/cu/at/oil

    of

    he

    seiwe,'ht

    othetwie Memodularratiowillbe

    applied

    o theslab.

    GRILLAGE

    MODEL 21

    The

    values

    forA('y-?

    irMi able ca,,

    oit/q

    be

    fl//ed

    4r

    afterq

    has

    bee,,ca/cilIated

    94/M

    =0.737/0.829 =0.889m'

    (from'bottomofbean,)

    I

    =0.2429si

    $ectioirmoduilicait

    ow

    e

    calculated'

    Thi ast

    value

    i

    asedoi, the

    ra

    formed

    sectiw

    properns,

    so

    willot

    ive

    the

    rue

    stresses4 heslab, The

    modit'lar

    atio iiruistbediVided

    ot

    of

    h/

    value

    o

    ind

    the ruesect/onmvduiluis

    for

    heslabi

    Zk

    Q,

    347

    /

    .91

    =0.381m

    (for

    actual

    stresses

    ?t

    slab)

    0220

    1.370

    Actual

    area

    ffect,Ve

    area

    q

    A(i-7

    I

    8/ak

    Overlap

    '/8

    0.280

    -0.012

    0.585

    0.255

    -0.011

    0.585

    1,480

    1.385

    0.639

    0,378

    -0.015

    0.374

    0.0891

    -0.0027

    0.0366

    0.0011

    0.0000

    0.1188

    Totals 0.853m'

    0.829sr

    O.737m O.2429m'

    &ttom

    of

    eam',

    Top

    of

    ean,,

    Top

    of

    lab,

    Zbb =1/9

    =0.273

    n,3

    Z

    =

    "(1400-7,)

    =

    0.475

    ,3

    Z

    =I/(l.590-9)

    =0.347m3

  • 8/16/2019 Deck Example

    27/100

    22 SIMPLE BRIDGE DESIGN USING PRESTRESSED

    BEAMS

    3.6 EDGE STIFFENING

    Most

    decks

    haveedge

    stiffening

    for the

    parapets.

    Manydeck

    arrangements cause

    the

    edge

    beam to

    be

    the most

    heavily

    loaded.

    In

    many

    instances

    these

    effects are

    complementary,

    he

    extra stiffness

    reducing

    stresses from the

    extra

    oading.

    However,

    the

    combined

    stiffliessof he

    edge

    beamwith he

    parapet upstand

    may

    be

    significantly

    higher

    than the

    stiffness

    of

    the internal

    beams,

    and

    so

    may

    attract

    high

    unwanted

    loads

    into

    the

    parapet upstand.

    Care must be taken in

    the

    computer

    modelling

    to

    ensure

    that the

    stiffness

    allocated o

    the

    edge

    beamisnot

    unrealistically high,

    as

    this

    would

    aggravate

    the

    problem.

    To counteract

    this

    'overloading'

    henomenon,

    the

    following approaches

    canbe

    taken

    when he

    apparent

    edgebeam nertia

    s

    significantly

    higher han

    internal elements:

    model

    the

    edge

    upstand

    as

    a

    separate

    element

    (usually

    with

    less

    inertia

    than the main

    elements).

    This reverses

    the trend

    ofattraction.

    calculate

    the

    whole

    deck

    nertia

    including

    he

    upstands,

    and also

    excluding

    the

    upstands.

    Then

    allocate

    half

    he

    difference

    to

    each

    edge

    member.

    This is

    likely

    to be

    significantly

    less

    than the inertia

    calculated

    for

    the

    discrete

    edge

    shape.

    make he

    edge upstand

    discontinuous. This

    is

    becoming

    more

    popular

    as

    it also

    reduces

    thermal and

    differential

    shrinkage

    cracking.

    It

    does,

    however,

    require

    careful

    detailing.

    In the

    design example,

    the

    third

    method

    has

    been

    adopted.

    The

    downstand fascia

    and

    parapet

    are cast

    after the deck has been

    completed,

    and are

    both

    cast in

    sections

    about

    2.5m

    long

    separated

    by

    a narrow

    gap.

    The stiffness of

    he

    parapet

    cantilever

    is

    included with

    the outer

    Y

    beam.

    Edge

    longitudinal

    elements are included

    in the

    model

    along

    he

    line

    of

    he

    parapet

    support

    upstand.

    These

    elements are

    given

    very

    small

    section

    properties

    so

    that

    they

    do

    not

    contribute structurally

    to the

    grillage.

    They

    are

    only

    included

    to

    give

    the

    grillage

    model

    a

    idy

    appearance

    the same

    size

    and

    shape

    as the

    bridge

    deck.

    They

    could be

    omittedwithout

    affecting

    the resultsof

    he

    analysis.

    Ifnominal members are

    used

    n

    this

    way,

    however,

    loads should

    notbe

    applied

    directly

    o

    these members.

  • 8/16/2019 Deck Example

    28/100

    dge

    &am

    GRILLAGE MODEL 23

    ,4n

    ir-sltii

    coircrete

    dowirstan'd

    asck

    i

    eift'ed

    ortiri

    'ndge.

    To

    acir/eve

    aH

    ecoiromia'al

    edge

    beam

    des/gM,

    a wo

    stage

    ct/OH

    se'eirce

    wi/Ike

    ised

    1n

    tiref tstage,

    tire

    deci

    ast

    tj

    toiitside

    tire

    edge

    beams.

    The

    weihtof

    he

    stage

    wo

    coirstriict/o.'ri

    iq'poned

    b'

    ire

    dec(-

    wil-ir

    edge

    beams

    atst

    ge

    o/,e,

    am/a

    ri//age

    a/ra4fs/

    cabecarried

    out

    accord/irg4'.

    Thi

    ana/qsi

    ,

    ot

    preseilted

    ere,

    but

    ire

    secM'npropenies

    oft/re

    stage

    oire

    edge

    beams obeused4r

    tirI

    aira4'si

    are;

    effectiVe

    Area

    =

    O,O2m

    9

    =O.875m

    I

    =O.24Om

    Iii

    tage

    two,

    tireca,rti/everi

    addea

    as

    well

    as

    the

    dicoirt4uuous

    parapet

    OH

    downstairdfascki.

    The

    of

    ire

    cross-sect/oir

    i

    haded

    OH

    tire

    dkigrarn

    asedoir

    M'i

    cross-sectiw,

    the

    sectioH

    to beused

    for

    irema4r

    gri//ageaira4,s,

    caH

    becalculatedas

    or

    ire

    ,rteriral eam

    oir

    ire

    revious

    page,

    airclare

    as

    ollows;

    Actual

    area =1.044

    m2

    effectiVe

    Area

    =

    1,003m

    7

    =l,022m

    I

    =0.316m4

    Parapetedge

    member'

    Alt/rough

    he

    gri//age

    wi//41cluide

    members

    ruiir#r4rgalo/ig

    the

    verq'

    edgesof

    he ecA

    these

    are

    Hot

    struictut'rat

    aird

    verq

    smallva/lieswi//be

    iisedfortire

    sect4'irpropemes.

    slab

    members;

    These

    represeirta

    1.900m

    sect/oir

    of

    lab;

    I

    =mbt/12= 0.911.9000.2203/12

    =

    0.00153m4

    There

    is

    Ho eNd

    dkiphragm,

    so theeHdslabmembers

    s41rplq

    epreseirt

    0.950m

    of

    lab;

    I

    =

    mbd/L2

    =

    0.91

    x

    0.950

    x

    0.

    220

    12

    =0.

    00077m4

  • 8/16/2019 Deck Example

    29/100

    24 SIMPLE BRIDGE DESIGN USING PRESTRESSED BEAMS

    3.7 TORSION

    Torsional

    inertia

    can

    be

    difficult

    to

    calculateprecisely.

    A

    reasonable estimate can

    be

    made

    by

    dividing

    the

    section

    up

    into

    rectangles.

    The torsional inertiaof

    he

    section is

    approximately

    given by

    the

    sum of

    he

    inertiasof

    he

    individual

    rectangles.

    In

    beam

    and slab

    bridges,

    the

    torsional inertia is

    normally

    small

    compared

    to the

    bending

    inertia,

    so

    this

    approximate

    method

    ofcalculation is

    sufficiently

    accurate.

    For

    rectangular

    ections,

    C

    =

    k1b3d

    where

    b is

    the

    length

    of

    he shortside

    d is

    the

    length

    of he

    long

    side

    and

    k1

    is a

    factor

    depending

    on the ratio

    d/b

    If d/b>

    2,

    then

    k1

    can

    be

    approximated by:

    k1

    =

    1/(1

    -0.63

    b/d)

    This formula should

    not

    be

    used for

    elements which

    represent

    sectionsof

    a

    wide slab.

    In this

    case,

    the valueused

    fork1

    must

    bereflect

    the

    whole

    slab

    action,

    and

    should

    not

    be

    calculated

    for

    he individualelements. Slabs wist

    in

    both longitudinal

    and

    ransverse

    directions,

    so

    the value

    ofC ishalved

    for each

    direction to

    reflect his double

    action.

    Additionally,

    he slab

    elements shouldbetransformed

    in

    accordance with the modular

    ratio. The torsional

    inertia

    of

    slab

    elements is

    thus

    given

    by:

    C

    =

    '/6mb3d

    Torsionless

    Design

    For

    many composite

    beams,

    as

    here,

    the

    torsional inertia is

    an

    order of

    magnitude

    less than the

    bending

    inertia.

    The

    analysis

    of

    uch

    bridges

    can

    be

    simplified

    by

    ignoring

    the torsion

    constraints.

    In

    other

    words,

    torsionless

    design

    can

    be

    used.

    The

    resulting

    load

    distributionis

    less

    effective

    and his

    gives

    rise o

    slightly

    increased

    bending

    moments.

    The

    correspondingly

    increased

    design strength

    is considered

    adequate

    to

    carry

    the

    torques

    which

    would

    be

    associated

    with

    a

    full torsion

    model.

    Torsionless

    designs

    should

    not be used for

    significant

    skews

    or boxbeam

    decks which

    may

    bechosen

    for their

    high

    torsion stiffness

    properties

    or

    where torsional

    strength

    is

    a

    significant requirement.

    Torsion should

    also not

    be

    ignored

    in UM beams and thick

    edge

    beams such

    as YE

    beams,

    evenif nternal beams are considered orsionless.

    Edge

    beams can

    be

    subjected

    to considerable torsion

    due

    to loads from the

    parapet

    cantilever,

    and

    cracking

    of

    these beams couldoccur

    if orsion is

    ignored

    in the

    design.

  • 8/16/2019 Deck Example

    30/100

    GRILLAGE

    MODEL 25

    of

    secMi,

    bq dea/iiiig

    Me

    ect

    o#i

    as

    ree

    I

    -

    I127.5x

    0.220

    2

    0.540x

    1,080

    T

    7

    0.,50x

    0.290

    fi$ca/cii/ate

    i'rern's

    for

    e

    iidMdia/rectaiig/es;

    1. Th,

    of

    a wider

    wo

    waq

    s/a

    80 6

    frfb3d/6

    =O.91OL203xL2P5/6

    =0,0021,?

    2

    d/b

    =

    L080/0.34o

    =3.18

    '1

    =(1-0.631'/d)/3

    =(1-0.63/3.18)/3

    =0.26,

    6

    =i(1b3d

    =0.26P0,34O31,080

    =Q,Qjf3j4

    3.'

    d/b

    =

    0.P5o/o.29o 2,59

    ,

    =(1-0.63k/d)/3

    =

    (1-0.63/2.59)/3

    =0252

    C

    ='1b5d

    =O,252x0.29OO,750

    =00046i?

    Total

    s/o#ali',ern,,

    C=00021

    0.0113

    +

    0.0046

    =0.018,?

    for

    costparisoir,

    1=0.255,?

    The

    ken'd4rg

    lerthT

    i

    learlf

    ver,'

    mwcli

    larger

    MallMe oii,talbiertki.

    To,%#

    wi/I

    Merefore

    be

    #regleced

  • 8/16/2019 Deck Example

    31/100

    26 SIMPLE BRIDGE DESIGN

    USING PRESTRESSED BEAMS

    4 CALCULATION

    OFLOADS

    4.1

    INTRODUCTION

    The

    Departmental

    Standard BD 3

    7/88,

    Loads

    for

    Highway Bridges,

    is

    currently

    used

    to determine

    the

    loading

    on UK

    bridges.

    BD

    37/88

    effectively

    supersedes

    BS

    5400

    Part2 in he

    UK, pending

    revisionof

    his

    Standard,

    andit isused

    hroughout

    this

    design example.

    The

    loads

    generally specified

    in the

    Standard

    are

    nominal

    loads

    appropriate

    to

    a

    returnperiod

    of

    120

    years. Design loads

    will be obtained

    ater

    by

    multiplying the

    nominal

    oads

    by

    load factors

    y

    given

    in the

    Standard.

    An

    additional

    factor,

    y0,

    is

    also

    introduced

    to

    obtain

    the

    design

    load effects

    (moments,

    shears,

    etc.)

    from the

    design

    loads. Valuesof

    are

    given

    in

    BS

    5400Part4

    for

    concrete

    bridges.

    4.2 DEFINITIONS

    It

    is

    worthwhile

    clarifying

    afew

    definitions,

    as

    they may

    differ rom

    those

    used

    with

    other

    structural

    design

    work:

    Dead Load

    the

    weight

    of tructural materials

    in the

    bridge.

    Superimposed

    the

    weight

    ofnon-structural materials

    on

    the

    Dead Load

    bridge,

    such as road

    surfacing, parapets,

    etc.

    Live

    Loads loads

    due o

    vehicular

    and

    pedestrian

    traffic.

    Primary

    Live Loads vertical

    live

    loads

    dueto

    weight

    of

    raffic.

    Secondary

    horizontal loads

    due to

    change

    in

    direction

    of

    Live

    Loads traffic

    (eg.

    centrifugal

    forces,

    braking,

    urching).

    Permanent

    those

    loads considered

    to be

    acting

    at all

    times

    Loads

    (i.e.

    DL,

    SDL,

    and

    any

    loads

    due to

    fill).

    Transient

    all

    loads

    other

    than

    permanent

    loads

    Loads

    (i.e.

    wind,

    temperature,

    and live

    loads).

  • 8/16/2019 Deck Example

    32/100

    C7ILCUL74TIONOTLOAD

    CALCULATIONOF Los

    27

    Dead

    Load

    Dead oad

    wY/be

    car/iedbq

    hebeasts

    acf-l'tg

    %n'e,

    with/to

    cosipos/te

    acz'Ion'.

    /f3

    &ast

    a/oit

    e

    /irterna/beam'

    idge

    beam

    74ra

    =

    0.584,m2

    (frost

    data

    s*eet)

    Weig'kt

    =0,584x24kN/st

    =

    14.03k/V/st

    =

    Q584P(f8,)+Q,2c5Q5(s/ab)-

    0.

    0120(oven'ap)

    =0,85325,2

    We/g.*t

    =0,c5532st224kN/st3

    =20.48k/V/st

    Area

    =0.

    5848)

    +0.

    4592(s/ab+caitt#ever)

    =1.044st2

    We,kt

    =1,044s,224kN/sr5

    =25.05

    k/V/st

    Thi

    oad4rg

    i

    pp/led

    o

    the

    costposie

    beast

    &

    s/ak

    strkc$Hre.

    Carrkigewa; Aspñaltsiirfach'ig

    -f

    siip//cltq

    assume

    stax/st

    ist

    hi'kness

    of

    165mst

    over

    wñole

    carnigewai.

    ThA

    'rc/udesa/b

    waitce

    for

    waterprooflHg rotect/on

    boards.

    $DL

    =0.165st24 /V/st3 =4.0k/V/rn2

    =

    4.Ok/V/st2

    x.

    1.275rn =5,1

    k/V/st

    perbeast

    Verge.'

    The

    wei,t

    of

    ire

    ootpath,

    andnon-structural

    (d/scontzsruouis)

    str4tg

    courseand

    fasck

    wi/I

    all

    be

    taken

    as $DL

    Total

    we,ht

    =14.6k/V/st

    eack

    side

    of ridge

    8uperh'rposedDeadLoad

  • 8/16/2019 Deck Example

    33/100

    28

    SIMPLE BRIDGEDESIGNUSING PRESTRESSED

    BEAMS

    4.3

    HIGHWAYLOADING

    Notional lanes

    For

    the

    purposes

    of

    calculating

    the loads to be

    applied

    to

    the

    bridge

    deck,

    the

    carriageway

    is

    split

    into

    notional

    anes.

    In this

    context,

    the

    carriageway

    is

    taken

    as

    the

    distance between

    raised

    kerbs,

    thus

    including

    the hard

    shoulders

    (see

    Clause

    3.2.9.1).

    Clause 3.2.9.3 then defines how

    the

    carriageway

    should

    be

    split

    into notional

    lanes.

    Note that inthis

    example

    there

    are

    three

    notional

    lanes

    for

    loading

    purposes,

    even

    though

    he deck will be

    marked

    out for

    only

    two

    lanes of

    raffic.

    HA

    Loading

    HA

    loading

    is

    a formula

    loading representing

    normal

    traffic

    in Great

    Britain.

    It

    comprises

    a

    uniformly

    distributed

    load

    (UDL)

    and

    aknife

    edge

    load

    (KEL)

    combined,

    or

    alternatively

    a

    single

    wheel

    oad.

    For

    loaded

    lengths

    up

    to and

    including

    50

    m,

    the

    UDL

    expressed

    in kN

    per

    linear

    metreofnotional

    laneis

    given

    by

    the

    equation:

    W

    =

    336(IIL)°67

    where

    Listhe

    loaded

    length

    (in

    metres)

    andW isthe load

    per

    metreofnotional lane.

    The KEL

    per

    notional

    lane

    is

    always

    taken

    as

    120 kN.

    The UDL

    and

    KEL

    are

    uniformly

    distributed

    over the full width

    of

    he

    notional lane

    to

    which

    they

    apply.

    However,

    not all lanes

    carry

    the

    full

    HA oadatthe

    same

    time,

    and this isdealt

    with

    by

    means

    of

    ane

    factors.

    These

    are functions of

    he

    loaded

    length

    and the lane

    width,

    and

    are

    specified

    in

    Table 14 of

    he

    Standard.

    The

    single

    100 kN wheel

    load

    alternative

    to

    the UDL

    and

    KEL

    canbe

    placed anywhere

    on

    he

    carriageway,

    and

    occupies

    eithera

    circular

    areaof

    340mm

    diameterora

    square

    area

    of300mm side.

    The

    single

    wheel oadis

    only

    significant

    in the

    local

    analysis

    of

    the

    deck

    slab,

    which

    isnot

    covered

    inthis

    design example.

  • 8/16/2019 Deck Example

    34/100

    CALCULATION OF LOADS

    29

    l-/iahwat

    oads

    6am'gewa.i

    width

    =

    1,0

    (*ardstr')

    +

    7

    3

    traffic

    aNes)

    +1,0

    =93m

    Three

    iot/ona/Iawes

    are

    rei/red'

    Not/offal

    aMe

    width,

    kL

    =95

    n/S

    =5,1 n

    /174 load'

    Loaded

    eirgt/r

    =

    26.61 m'

    /1AUDL

    =336(1/L)°6'

    =

    536(1/26.61)°

    k/V/rn

    HAAL=120k/V

    Wheel oad

    =

    100

    k/V

    'si'rgIe oad)

    LaMe

    factors

    kasedoit

    L)

    3,/&s

    Thkle

    14.'

    a2

    =

    °157(k

    40-L)

    +3,

    65(L-20))

    =

    0

    013,(3,

    1(40-26.61)

    +

    3.65(26.61-20))

    =0,90

    &st

    aMe

    factoi

    /3

    =

    a2

    =0.90

    $ecoffd

    aNe

    factoi

    /2

    =

    a2

    =090

    ThIrd aNe

    factoi

    133

    =

    0.60

  • 8/16/2019 Deck Example

    35/100

    30 SIMPLE BRIDGEDESIGN

    USING PRESTRESSED BEAMS

    HB

    Loading

    HB

    loading represents

    abnormal vehicle

    loading.

    An

    example might

    bea low load

    trailer

    carrying

    a

    power

    station transformer,

    with tractor

    units

    at

    front

    and

    rear.

    For all

    public highway bridges

    in GreatBritain theminimum

    numberofunits of

    ype

    HB

    loading

    that

    must

    normally

    beconsideredis

    30,

    but this number

    may

    be

    increased

    up

    to 45 units.

    For this

    design

    example,

    the client has

    specified

    37.5 units

    ofHB load.

    TheHB vehicleas

    defined in the Standard

    represents

    fouraxleswith fourwheels

    per

    axle.

    One unit

    of

    oad

    represents 10

    kNperaxle. Thus he full 45 units

    maximum is

    equal

    to 450 kN

    per

    axle

    or

    112.5

    kN

    per

    wheel.

    Thedistancebetween he central

    woaxles isvariable. For

    simply

    supported spans,

    the smallest

    igure

    is

    obviously

    the mostcritical.

    As

    with the HA wheel load the contactsurface

    may

    be taken

    as circular or

    square

    with a contact

    pressure

    of1.1 N/mm2.

    Note

    thatin this

    example

    theHBwheel load isless than the

    HA

    wheel

    load. Forslab

    design

    theHA wheelwill

    therefore

    be

    critical.

    Longitudinal

    and ransverse

    loading

    Thisis

    only required

    for

    design

    of he

    bearings.

  • 8/16/2019 Deck Example

    36/100

    CALCULATION OFLos 31

    /15

    oad'

    Thi

    bridge

    ,

    esig',ed

    for

    37,5 iwits

    of/-IS

    oad

    AyJeload=37,5xl0kN =375k/V

    Total/-IS

    vehicle

    weight

    =4

    x.375k/V

    =

    1500k/V

    W4'eel

    load

    =

    375

    kN/4 =9375

    k/V

    for

    hi

    s4ii4siippon'ed

    ridge,

    theshonest

    wheelbasewi/Ike critical

    Thus

    ditance

    bet

    wecir

    cdiltral

    x/es

    of

    Me 15

    vehicle

    wi//be

    aken'

    as

    6rn

    Jorion'ta/Loads,'

    Clause

    6,1

    0

    iVes

    the

    norn4ra/Ion'gi'tuid4ra//oads.'

    HA

    /on'gituda/

    load

    =250k/V

    +8

    k/V/rn

    of/oaded/en'gth

    =250kA/+(8k/V/rnx2á.6rn)

    =463k/V

    Thi

    i

    pplied

    o

    on'e n'otion'a/lan'e,

    /13

    lon'gituidin'a/

    load

    =25%

    of

    'orn4ral

    /15

    wei,ght

    =25%

    1500k/V

    =375k/V

    Thii

    qp'all.i

    ditr,butedbet

    ween

    the8

    wheels

    ofapaitof

    xles,

    butwi/I

    Hotbe criticalasiti ess han' the HA

    on'gituidin'al

    load

    Clause

    6.11

    giVes

    the

    ornin'altran'sverse oads/

    The

    n'orn4ral tran'sverse

    load

    due to

    skidd4rg

    i

    s4tglepo4tt

    oad

    of300

    k/V

    acti.Yg

    4,

    an'q

    d,tecti'n

    'parallel

    o the oad

    surface)

  • 8/16/2019 Deck Example

    37/100

    32

    SIMPLE BRIDGE

    DESIGN

    USING PRESTRESSED BEAMS

    4.4 WIND LOAD

    Methods

    of

    calculating

    wind oads are

    given

    in

    Clause 5.3

    of

    he

    Standard.

    Combination

    2

    loading(seepage38)

    is

    not

    significant

    n

    itseffectona

    argeproportion

    of

    bridges,

    such asconcreteslabor

    beamand slabstructures 20mor ess

    in

    span,

    1Om

    or more in width and

    at

    normal

    heights

    above

    ground.

    Wind

    load thereforedoes not

    need

    to

    be calculated

    for

    most

    bridgesdesignedusingprestressed

    beams.

    4.5 PEDESTRIAN LIVE LOAD

    For

    oaded

    lengths

    of

    36m and

    under,

    the

    nominal

    pedestrian

    ive load

    is a

    uniformly

    distributed live load of5.0 kN/m2.

    For

    superstructures carrying

    both

    highway

    and

    pedestrian loading,

    a

    reduction factor

    of0.8

    is

    applied

    to thenominal

    pedestrian

    live

    loading specified

    for

    footbridges

    alone.

    Thus,

    in

    this case

    the

    pedestrian

    ive load

    is

    4.0 kN/m2.

    4.6

    TEMPERATURE EFFECTS

    Temperature

    effects

    produce

    two

    aspects

    of

    oading,namely

    therestraint

    tothe overall

    bridge

    movement due

    to the

    temperature range,

    and the effects of

    temperature

    differences

    (or gradients) through

    he

    depth

    of he

    bridge

    deck.

    Temperature Range

    The

    temperature range

    for

    a

    particular bridge

    is

    obtained

    by

    first

    determining

    the

    maximum andminimum shade air

    temperatures

    for the location of he

    bridge

    from

    isotherms

    plotted

    on

    maps

    of he

    UK,

    andshown in

    Figures

    7

    and8

    in

    the Standard.

    As these

    isotherm

    maps

    are

    derived from

    Meteorological

    Office

    datarelating

    to a

    return

    period

    of120

    years

    (the

    bridge

    design life),

    it

    may

    be

    necessary

    to

    adjust

    the

    temperatures

    for

    a

    return

    period

    of50

    years

    forcertain

    applications

    such as

    footbridges

    and

    carriagewayjoints.

    Thisis achieved

    by

    a

    straightforward

    increaseorreduction in

    temperature

    as indicated

    in

    Clause5.4.2of he Standard.

    Maximum andminimum

    effective

    bridge emperatures

    are then derived from Tables

    10 and 11 in the Standard. Prestressed

    beam

    bridges

    will

    always

    be

    type

    4.

    The

    effective

    bridge

    temperature

    range

    is

    then used for

    designing

    the

    bearings

    and

    expansion joints,

    or

    if

    this movement

    is

    restrained then in

    determining

    the stress

    resultants in the structure.

  • 8/16/2019 Deck Example

    38/100

    CALCULATION OF LOADS

    33

    WZ'td oad

    Wi,d

    oad

    speci%'al/i

    calcø/ated

    for

    t*i

    'ridge.

    assHnted

    Mat

    Load

    6omk/itat/on

    2wi//notbe

    critical

    footpath

    Loads

    Nom4ya//,Veoad

    for

    ootpaths

    giVen

    it Clause6.5,1,1as

    5

    ('N/m.

    h'ice

    his

    bridge

    carr,skikwa.i

    oad/itg

    as

    we//as he

    ootpath,

    the eduction

    factorof

    0.8

    app/is.

    Neduced

    nom/iuaload

    be

    applied

    =

    0.8

    x

    5.0

    =

    4.0

    kN/m

    Temperature Nange

    from

    D

    37/88,

    hgures

    7

    and

    &

    Miuimuim

    hade ait

    eli,t'eratgre

    =

    18

    0

    Max/mum

    shadealt +3606

    from

    #uire

    9,

    bridge

    construction

    i

    ype

    4.

    from

    Tab/es

    10and11,

    M/iu/'ium

    effectiVe bridge emperature

    =

    11°C

    Ma/iuuim

    effectiVebridge temperatuire=

    +36°C

    Temperatureange

    =

    47°C

    Coefficient

    of

    hermal

    e.q.'ansiin

    =

    12x1

    Ct6/°C

    Length

    between

    eansi'nj/iuts

    =

    27m

    (approx)

    Nange

    of

    movement

    =

    47x

    (121O6,)

    x

    27=0.

    0152m

    Nange

    of

    movement

    fromcentra/posi'tt'n

    =

    ±76mm

  • 8/16/2019 Deck Example

    39/100

    34

    SIMPLE BRIDGE

    DESIGN USING PRESTRESSED BEAMS

    Temperature

    Difference

    Positive

    temperature

    differences

    occur

    within he

    superstructure

    when

    conditions are

    such

    that

    solar

    radiation

    and other

    effects cause

    a

    gain

    in heat

    hrough

    the

    top

    surface

    of he

    deck.

    Conversely,

    reverse

    temperature

    differences

    occur

    when

    conditions are

    such hat heatis

    lost

    from the

    top

    surfaceof he

    bridge

    deck as

    aresultof

    e-radiation

    and other

    effects.

    Temperature gradient

    diagrams

    for each

    of

    hese states are

    shown

    on

    Figure

    9 in the

    Standard.

    For

    surfacing

    of hickness

    other

    than

    100mm

    these

    can

    be

    modified

    by

    reference

    to

    Appendix

    C.

    The

    coefficient

    of

    hermal

    expansion

    for

    concrete

    and

    steel is

    takenhere as

    I

    2x

    106.

    For

    concrete with limestone

    aggregates,

    a

    reduced coefficient

    of

    hermal

    expansion

    of

    9x10-6

    can

    be

    used.

    If he deck

    were

    fully

    restrained

    ateach

    end,

    stresses

    proportional

    to the

    temperature

    at each

    point

    in the

    deck would arise.

    These

    emperatures

    and stressesare

    shown in

    the

    top

    line

    of

    diagrams opposite.

    The

    stress

    at the

    top

    of he

    slab,

    for

    example,

    is

    calculated as:

    Stress

    =

    E

    ci.

    T

    =

    (31,000 N/mm2)

    x

    (12x106/°C)

    x

    (13.5°C)

    =

    5.02 N/mm2

    In a

    simply

    supported

    deck

    there

    is

    no

    axial

    restraint

    at the

    ends,

    and no

    moment

    restraint.

    The

    axial

    and

    moment

    components

    of

    hese stresses will be relieved

    by

    overall

    lengthening

    and

    hogging

    of he deck.

    A

    self-equilibrating

    et

    of nternal stresses

    will

    remain;

    they

    will exist

    without

    any

    external forces or reactions

    on the

    deck.

    These

    nternal stresses

    are calculated

    by

    subtracting

    he

    axial

    and

    moment

    components

    from

    the

    stresses calculated

    for the

    fully

    restrained

    condition.

    Stresses

    due to

    negative temperature

    differences

    also need to be

    calculated. These

    are not

    presented here,

    but

    exactly

    he

    same

    procedure

    is

    followed.

    It isworth

    noting

    that the

    serviceability

    limit state stresses

    determined from these

    temperature

    difference

    diagrams

    are

    subject

    to a load factor

    of0.8.

  • 8/16/2019 Deck Example

    40/100

    TestfleratureD/fferen'ce

    CALCULATION OF LOADS

    35

    Temeratiire

    d/tr/iiz/'M

    through

    thecross

    ect/oH

    igiVei,4i iwre

    9

    ofD

    37/88

    k,

    =0Jim

    15.5CC

    0,25mfl

    Ca/cu/ate

    am/force

    a#dmoment

    omponents

    of

    hesestresses.

    $tress

    has

    keen

    diVideduip

    Z#o

    fiVe

    blocks, 4rd/catedon

    dkigram

    bove,

    jtreaseof

    a/cu/at/on.

    A

    1

    1,275x0.15

    2

    1,275x0J5

    3

    1,2,75x0,07

    4

    0.4.zx0.18

    5

    0.75x0.20

    //

    74Y

    0.626

    0214 0154

    0651 0.375 0.245

    0516 0.086 0,044

    0391 0.037 0015

    -0.822 0.077 -0.063

    Am/force

    = =

    0787MN

    I,,

    st'/q

    supported

    ridge,ne/theraxia/force

    ormoment re

    4i

    act

    estra4rea

    so

    ocked

    4t

    stresses

    are

    ca/cui/atedbqsuiktract/ng

    these

    effects rom'

    he

    stress

    diigram

    above.'

    Ax/a/re/ease

    stress

    =

    (0.

    787

    MN)/(0.

    829

    mi')

    =0.95

    N/mm

    Moment

    e/easestress

    =

    (0.373

    M/V&/Z

    =

    (0.373

    MNm)/(0. 475m)

    =0.79

    N/mm2

    at

    op'of

    eam',

    etc.

    502

    N/mm

    PositiVe

    teratu1red7ereHce/

    Cross

    *3

    =020m

    .5CC

    Temperature

    Difference

    JOiN/mm'

    $tresses

    41

    fui/4i

    estrained

    deck

    =iaT

    1,12

    1.95

    0.96

    0.44

    0.51

    Moment about

    centroidal

    ax/s

    =

    =

    o.S7SMNm

    098N/mm'86N/mm'

    095

    N/mm'

    095

    3,18

    /mm'

    1,02N/mm'

    Nestrained

    tresses

    Moment

    from

    op

    dhtgram

    re/ease

    re/ease

    j37d

    144N/m.w'

    $eif-

    eqii/ibrat4ig

    temperature

    stresses

  • 8/16/2019 Deck Example

    41/100

    36

    SIMPLE

    BRIDGE DESIGN USING PRESTRESSED BEAMS

    4.7 SHR[NKAGE

    When he in-situ

    op

    iscast on the

    precast

    beams

    some

    of

    he

    shrinkage

    of he beams

    has

    already

    occurred. Hence differential

    shrinkage

    occurs

    between he

    precast

    and

    in-situ

    concretes,

    and his

    results

    in the

    development

    of

    a

    pattern

    of nternal stresses.

    Clause 7.4.3.4 states

    that

    he Table

    29

    shrinkage

    values

    may

    be

    adopted.

    It

    is reasonable

    (and usual)

    to

    assume

    thathalf

    of

    he beam

    shrinkage

    has

    occurred

    at the time of

    casting

    the

    top

    slab. Hence

    the

    differential

    shrinkage

    assumed

    in the

    calculation is

    half

    of

    he

    Table

    29

    shrinkage

    value.

    The

    effects

    of

    differential

    shrinkage

    will

    be

    reduced

    by

    creep.

    Allowance

    ismade

    or

    this n the

    calculations

    byusing

    a

    eduction coefficient,4.

    A

    value

    of

    0.43 isnormally

    usedforthis

    coefficient,

    as

    given

    in

    Clause 7.4.3.4.

    The

    differential

    shrinkage

    stresses

    can be

    determined

    in

    a

    similar

    manner

    to

    the

    differential

    temperature

    stresses.

    The

    restrained stresses are

    calculated,

    and he

    axial

    force

    and moment

    component

    are

    subtracted

    to

    give

    the

    actual internal stresses.

  • 8/16/2019 Deck Example

    42/100

    CALCULATION OF LOADS

    37

    $ñrirkage

    DftreHt/a/shr4tk.age

    bet

    ween

    slab

    and

    dec,('

    creates

    itterna/stresses.

    /tZ

    assiimed/a4

    the

    otal

    hithikageoft/re

    beam'has

    aI(en

    p/ace before

    thes/ak

    i

    ast;

    Different/al

    kr4t.(-age

    stra4r,

    =

    0.5

    x.

    (-300x106)

    =

    -150x106

    __________________

    15ot

    I&I

    I

    Nest

    a/nirg

    orce

    =

    £

    . x

    A

    ..

    =

    -15010

    '

    x

    31000

    x.

    (L2,5

    x

    0.220)

    x

    0.43

    =

    -0,561 MN

    (tensi2w)

    Nestra/n4rg

    stonrent

    =

    -0.561

    x

    eccentric/tJ,f

    =-0.561X('1,480-

    0.889)

    =-0,332MNm'

    Ca/ri/at/on

    of

    nternal

    stresses

    i

    i'tri/arto he

    calci/ati#r

    fortestperatiire

    difference.

    Nestrai'redstress

    =

    x. x.

    0

    =

    -2.0

    N/m'm

    Ax/al

    re/ease

    =

    ('0.561M

    N,)/1"O.

    829nr,)

    =

    -0.68

    N/mnr

    Montent elease

    =

    A4/Z1,

    =

    -0.332/0.381

    =

    -0,

    5,

    N/m'm'

    at

    op

    of

    slab,

    etc.

    Total4,terna/stresses

    ares/townon he

    ri/tt

    and

    digram;

    -2.0

    N/,m -062

    N/mi,r -067

    I

    4N15ôN/mm054

    N/mm-

    -0,66 N/mi

    Nestra,'red

    Ax/al

    Mom'ent

    &/f-eii/likrat4rg

    stresses

    re/ease re/ease

    skr4rtage

    stresses

  • 8/16/2019 Deck Example

    43/100

    38

    SIMPLE

    BRIDGE DESIGN USING PRESTRESSED

    BEAMS

    5

    APPLICATIONOF

    LOADS

    5.1

    LOADCOMB1NATIONS

    BD 37/88 considers

    fivecombinationsof oads. These are

    listed in detail

    in

    Table 1

    of he

    Standard,

    which

    also

    gives

    load factors to be used in each case.

    The five

    combinations can be summarised

    asfollows:

    Comb.

    1:

    Permanent loads

    plusprimary

    live oads.

    (For railway bridges,

    secondary

    live

    load

    is

    also

    ncluded.)

    Comb. 2: Wind

    load,

    plus

    loads

    in Comb. 1

    (but

    with some reduced load

    factors).

    Comb. 3:

    Temperature

    effects,

    againcombined

    with

    loads from

    Combination

    1.

    Comb. 4:

    Secondary

    live loads

    (each

    considered

    separately),

    in

    combination with

    permanent

    loadsand theassociated

    primary

    live oad.

    Comb. 5:

    Bearings

    friction,

    together

    with

    permanent

    loads.

    Load combinations

    1

    to

    3 are the

    primary

    combinationsto

    be

    considered

    inthe overall

    analysis

    of he

    bridge

    deck. In

    pretensioned

    beam

    bridge

    decks,

    Combination

    2

    (including

    wind

    loading)

    is

    rarely

    critical,

    and

    is

    gnored

    in the

    design example.

    This

    leavesCombinations 1 and3

    to

    be

    analysed.

    For

    bridges

    in the

    UK,

    the

    requirements

    of

    BS 5400:Part

    4

    mustbemodified

    according

    to

    Departmental

    StandardBD

    24/92,

    The

    Design

    ofConcrete

    Highway Bridges

    and

    Structures,

    Use ofBS 5400:Part 4: 1990. Themost

    important change

    this ntroduces

    relates to the Combination

    1

    loading.

    The beams must

    comply

    with Class 1 SLS

    stresslimits foramodified

    version ofCombination 1. BS 5400: Part

    4

    calls

    for

    a

    maximum of25 units

    ofHB load for this

    condition,

    but BD 24/92 reduces the live

    loading

    to HA alonefor hiscondition.

    This

    design example

    follows the

    requirements

    ofBD 24/92.

    5.2

    SELECTIONOF

    CRITiCAL LOAD CASES

    In this

    example,

    maximum

    midspan

    moments will

    obviously

    be obtained

    by

    concentrating

    the loads as near

    to

    midspan

    as

    possible.

    This means

    putting

    the HA

    KEL

    at

    midspan

    in

    the lanes

    to

    which

    it

    applies,

    and also

    putting

    the HB vehicle at

    midspan.

    Positioning

    of heloads to obtain

    maximum

    bending

    momentelsewhere in the

    span,

    oron skew

    bridges,

    is

    not so

    easy.

    The

    arrangement

    of oads which

    give

    maximum

    effects in the various

    beams can be found

    by

    trial and error.

    Alternatively,

    some

    software

    packages

    will

    automatically

    analyse

    a

    multitude

    of

    different

    possibilities

    and

    report

    themaximum effects.

    The

    temperature

    loads in Combination

    3

    do not cause

    any bending

    moments

    in

    the

    beams,

    andso

    will nothave

    a

    significant

    effect

    at

    ULS.

    Only

    Combination

    1 therefore

    needs to be

    analysed

    at ULS.

  • 8/16/2019 Deck Example

    44/100

    APPL/CA /ON

    Of

    L

    O74D

    TO

    5N/LM

    APPLICATION OF

    LOADS

    39

    Load Cases

    Loadcasesmast eselected

    forhe'at

    the

    gri/lageana4sis.

    forhe

    designof

    he

    estressed

    beams,

    onli

    he

    maxi,wm

    moments

    (wh'ith

    will

    occarat

    midspan,),

    and

    he

    max/mi/rn

    shear

    at

    theends

    of

    hebeamsandat are

    needed Moments are

    reqjiired

    othat$L$

    and

    at

    WL'.

    On4

    WL is

    equiredfor

    he

    shear

    ca/calat4ns,

    bat

    he

    cond/tiwWi//a/so be

    ana4'sed

    to

    giVe

    mac'wrn

    oadson

    the

    bearings.

    &/ow

    s

    a

    sammary

    of

    he

    oadcases

    o

    be

    analqsed

    This

    has

    been

    basedon

    fiare

    13

    of

    ,])

    37/88.

    Note

    that

    he

    /-/

    ye/ride

    s

    wider han

    a

    rothna/

    ane, When

    the

    /1

    ye/ride

    straddles

    the

    adjicent

    ane,

    the

    K.L

    isomitted

    from

    hat

    ane,

    and

    he ane

    factorfor

    he 14

    IIDL

    s

    basedonanot/9na/ ane width

    of

    2.

    Sm,

    giving

    a ane

    factor

    of

    0.

    7S9

    see

    C/aase

    6.4.2(b))

    HA with

    37.5anitsH

    Combiratin 1

    atL'

    nd

    11L

    Combi'tat,kn3at

    HAwith37.5anitsH

    Combination1 atãL

    ndUL

    Combi',at,n

    3 at

    HA

    with37.5an/tsH

    to

    max/mise

    hearand

    eactins

    in ane

    1.'

    Combination1

    at

    $L nd

    UL$

    HA,

    /14

    HA,

    J3,=O.9,

    iL

    130.9

    iL

    /330.6,

    iL

    HA,

    132=0.789

    H vehicle

    HA,

    /3=O.9,

    AL

    H,

    ye/ride

    HA,

    132=0.789

    H4

    J3=0.9,

    /(.zL

    HA

    alone'

    Combination1 at

    and

    11L

    Combinati'on

    3

    at

    L,neJ

    Le2

    krne3

    f

    HA,

    HA,

    I

    vehicle

    132=0.789

    /3=O.9

    AL

    1

    I

  • 8/16/2019 Deck Example

    45/100

    40

    SIMPLE BRIDGE