CVE 4073/5073. Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE. Estimating defined…. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/1.jpg)
Construction Cost EstimatingClass #2: Concept Estimating
Prof. Ralph V. Locurcio, PE
![Page 2: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/2.jpg)
A complex process involving the collection of available information on the scope of a project, the expected resource consumption, and future changes in resource costs.
This information is synthesized in a visualization of the construction process and translated into an approximation of the final cost.
![Page 3: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/3.jpg)
Extensive knowledge of: Construction processes & methods Materials & methods Contracts & work practices Construction documents & details Background business factors Design & code requirements Verbal & written communications Good common sense & judgment
![Page 4: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/4.jpg)
KickoffMeeting
WorkPlan
EstablishStandards
UpdateDatabase
PrepareEstimate
DocumentEstimate
ReviewEstimate
Adjust Estimate?
SubmitBid
ProjectExecution
ProjectCompletion
Yes
No
Revise
Lessons Learned
Feedback to improve data base
Reality C
heck Yes
No
![Page 5: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/5.jpg)
Read the Plans, Specs & Contract
Conduct Site Visit
Decide Construction
MethodPrepare Schedule
Plan for SubcontractsPlan for EquipmentMaterial Take-Offs
Estimate costs
Determine contingency
Analyze Risk Factors
Finalize Bid
![Page 6: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/6.jpg)
Systematic analysis of: Project components Equipment needed Construction methods Temporary work items Support activities Externalities
![Page 7: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/7.jpg)
Conceptual Used for early decisions & feasibility Rough estimate using minimal data Relies heavily on past data Level of accuracy about 70%
Detailed Used for major decisions; i.e. bids & budgets Based on final design documents Level of accuracy up to 95%
![Page 8: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/8.jpg)
% Accuracy
% D
esig
n
0 25 50 90 100
100
90
60
30
![Page 9: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/9.jpg)
Based on prior experience: Weight check… weight of equipment Cost-capacity factor- ratio of Q/$ Comparative cost of structure – $/unit
Feasibility estimates Appropriations estimates Time & location adjustments
![Page 10: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/10.jpg)
Basis is cost per unit based on past experience with similar units. Compare structures of like construction, (e.g.
school: steel, concrete, quality, local labor, weather) Develop cost per unit, e.g.
A$/pupil = A Cost/A pupils Apply to new construction:
B Cost = B pupils x A$/pupil
![Page 11: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/11.jpg)
Schools: $/pupil Bridges: $/feet of span Stadium: $/seat Hospital: $/beds Offices: $/ft2
Warehouses: $/ft3
![Page 12: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/12.jpg)
Plant cost ratio… process plant ratiodifferentiates machine ft2 from admin ft2
Floor area… cost/ft2 … but Total horizontal area… all floors equal Finished floor area… $ based on type finish Cubic foot of volume… floor height varies
![Page 13: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/13.jpg)
Used for capital budgeting Expect 80-90% accuracy Based on historical data base Methods:
Panel… hist data on “typical” panels Bay… hist data on “typical” bays Plant component… equip cost + other TPC = ET/(1-PT)
Where ET=tot equip cost/(1-% all other cost items) ET = $$$ equip/(1-70%)
![Page 14: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/14.jpg)
Cost indexing Based on similar “group” of key items Compare “group” over time or location Final cost based on ratio x calculated cost:
Est Cost = T2/T1 x Calc Cost Est Cost = (T2/T1)(L2/L1) x Calc Cost
![Page 15: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/15.jpg)
“The future ain’t what it used to be”…Yogi Berra
Need to project costs to mid-point of the construction year for budgeting
Generally average past 3-5 years cost data & project forward
![Page 16: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/16.jpg)
Based on three primary factors:
A. Scope… quantitiesB. Constructability… methods
C. Risk… externalities
![Page 17: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/17.jpg)
Technology in project - complexity Milestone deadlines for work - timing Material & equipment - availability Staffing needed – skill & availability Contract terms – allocation of risk Amount of competition - markets
![Page 18: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/18.jpg)
Construction quality – skill required Allowable tolerances – productivity Complexity of design – learning curve Flexibility of methods – special terms
![Page 19: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/19.jpg)
Unspecified material or workmanship Differing site conditions Error in bidding Changes in cost over time Subcontractor error or failures Weather & environmental issues Strikes & labor issues Utilities & support issues
![Page 20: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/20.jpg)
1. Determine project characteristics:Scope, constructability, risk
2. Examine the project design & site3. Structure the estimate 4. Determine elements of cost 5. Calculate estimate
![Page 21: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/21.jpg)
Technical specifications Referenced standards Project drawings Testing and performance Special methods or procedures Physical elements & site characteristics Errors & omissions
![Page 22: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/22.jpg)
Structure often follows specification template
Ensure nothing left out Need a plan for completing the project Logical flow of resources & materials Productivity factors
![Page 23: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/23.jpg)
Labor- craft & skill resources; sub-contractors; union labor; wage rates; training; “effective” labor rates; productivity factors (weather, complexity, experience, management)
Material- price, shipping, availability, storage, relation to specifications
Equipment- purchase vs. lease, single use, down time, cost of maintenance
Capital- interest rates, payment flow, retainage Time- overhead costs, required completion date,
![Page 24: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/24.jpg)
Material take-off from plans1. Quantities of all construction materials2. Compare with specifications
Labor cost for construction or installation1. Effective labor rates2. Team composition & duration
Construction equipment schedule1. On hand vs. lease or purchase2. Time on job
Follow elements of cost1. Ensure all items are covered
![Page 25: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/25.jpg)
Calculate the estimated cost Solution in class
![Page 26: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/26.jpg)
Based on historical data Accuracy = +30% Used for planning purposes when no
design exists Used to check validity of detailed
estimate
![Page 27: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/27.jpg)
Assumes cost of equipment is dominant factor in plant cost
Estimate based on % of cost allocated to equipment relative to total cost of facility
Estimated cost is proportional to known cost
Must adjust for time & location
![Page 28: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/28.jpg)
Assume that the equipment portion of a chemical processing plant constructed in 2006 cost $1.2M and the total plant cost was $2.5M. Therefore the equipment portion of the total cost was 46%. Estimate the cost of a new plant with the same processes if the equipment for the new plant has been determined to cost $2.7M. Assume time and location factors are negligible in this case.
Solution:
![Page 29: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/29.jpg)
Assume that the equipment portion of a chemical processing plant constructed in 2006 cost $1.2M and the total plant cost was $2.5M. Therefore the equipment portion of the total cost was 46%. Estimate the cost of a new plant with the same process if the equipment for the new plant has been determined to cost $2.4M. Assume time and location factors are negligible in this case.
Solution: C2/E2 = C1/E1 … solve for C2
C2 = [C1/E1] x E2
C2 = [$2.5M/$1.2M] x $2.4MC2 = [2.08] x $2.7 = $5,625,000M
![Page 30: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/30.jpg)
Similar to comparison of $/sf unit measure Used when facility has differing ceiling
heights Calculate the $/cf of known facility Determine $/cf of known facility Calculate total cf of new facility Using known $/cf calculate cost of new
facility Adjust for time and location
![Page 31: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/31.jpg)
Determine the cost of a new warehouse which will have 3 distinct storage areas with differing ceiling heights. Area 1 = 12’; Area 2=14’ and Area 3 = 10’. The floor area of all three areas is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14’. Assume time and location factors are negligible in this case.
Solution:
![Page 32: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/32.jpg)
Determine the cost of a new warehouse which will have 3 distinct storage areas with differing ceiling heights. Area 1 = 12’; Area 2=14’ and Area 3 = 10’. The floor area of each area is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14’. Assume time and location factors are negligible in this case. Solution: Existing Building
A = 8000sf x 14’ = 112,000 cfCost/cf = $2,400,000 / 112,000 cf = $21.43/cfNew BuildingA1 = 4000sf x 12’ = 48,000 cf A2 = 4000sf x 14’ = 56,000 cfA3 = 4000sf x 10’ = 40,000 cfTotal = 144,000 cfCost = 144,000 cf x $21.43/cf = $3,085,714
![Page 33: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/33.jpg)
Prices “escalate” over time due to inflation Must adjust estimated cost to “mid-point” of
construction. Determine period of construction Determine start date of construction Determine mid-point of construction =
average cost Determine “escalation rate” = given index Multiply estimated cost by “escalation rate” Note: escalation is compounded, ie. increase is
cumulative over number of years of escalation
![Page 34: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/34.jpg)
Prices differ by region of the country Must consult a reliable index to determine
“relative” cost of construction between regions RS Means Cost Data or Engineering News
Record are examples Adjustment is a simple ratio multiplied times the
estimated construction cost. So… C2/C1 = L2/L1 X Estimated Construction Cost
and C2 = C1 x L2/L1
![Page 35: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/35.jpg)
You have been asked to prepare a conceptual cost estimate for the construction of a new university dormitory at Florida Tech to open in 2010. You have 2005 RS Means data that provides a cost of $30,000/bed for similar dormitories in the northeast of the US, and a construction period of 2 years. The Means data states that construction costs escalate at 10% per year in the southeast. If the dorm is to house 200 students at Florida Tech and the Means Cost Comparison Index between the northeast and southeast is 0.80, what is the estimated cost for the new library at Florida Tech at the mid-point of construction? Estimated Florida Tech cost:______________________
![Page 36: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/36.jpg)
1. $30,000 per bed x 200 beds = $6,000,000… in the northeast in
20052. In the southeast in 2005…
$6,000,000 x 0.80 = $4,800,0003. Construction start is…
Occupancy – 2 years = 2010 – 2 = 2008
4. Mid-point of construction is =2008 + 1 = 2009
5. Years of escalation…2009 – 2005 = 4 yrs
![Page 37: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/37.jpg)
6. Escalation: $4,800,000 x 1.10 = $5,280,000
(2005-06) $5,280,000 x 1.10 = $5,808,000
(2006-07) $5,808,000 x 1.10 = $6,388,800
(2007-08) $6,388,800 x 1.10 = $7,027,680
(2008-09)
![Page 38: CVE 4073/5073](https://reader036.vdocuments.mx/reader036/viewer/2022062305/568150d3550346895dbef65f/html5/thumbnails/38.jpg)
Therefore… the estimated cost of the new dormitory for Florida Tech at the mid-point of construction in 2009 is:
$7,027,680