cutting room project

Upload: nishkarsh-maurya

Post on 14-Apr-2018

232 views

Category:

Documents


2 download

TRANSCRIPT

  • 7/30/2019 Cutting Room Project

    1/30

    Objective

    Main objective:To study and increase total cutting room efficiency

    Sub-objectives:

    a) Time & Motion Study of different operations in

    spreading & cutting leading to:

    1) Determination of efficiency of the worker:

    The purpose is to optimize on manpower utilization. Put the best person

    to best use and avoid multitude of workforce wherever not required.

    2) Identification of bottleneck operations:

    Bottlenecks increase the throughput time, which is a significant loss on the critical

    time. Bottlenecks should be identified and taken care of immediately to save on

    cost and time.

    3) Reduction of idle times whenever possible:

    Huge expenditure is incurred on machinery. The interest of that investment

    should always be kept in mind. As such, machine idle time is a disguised

    expenditure in form of loss of interest on investment. Continuously running machine

    is an investment justified.

    4) Maximum utilization of automatic spreading & cutting systems:

    Automation is justified only if it is used to the fullest extent. The intention is to de-

    skill and increase production, and wherever possible economize on cost. All the

    three purposes should be achieved; otherwise the advantage of automation may

    not be one hundred percent.

  • 7/30/2019 Cutting Room Project

    2/30

    b) Study of the existing layout with reference to material flow & explore

    scope of improvement:

    Layout affects production flow. It should be conducive to material movement,

    and at the same time technically correct. Haphazard layout may obstruct

    movement thus costing on time and fatigue, and in turn resulting in loss of time and

    energy.

    c)To utilize the variable resources manpower efficiently in the cuttingsection:

    It will help in target setting and work monitoring for the activities of cutting room.

    Our project, thus attempts to strike at a balance in the production activity-

    cutting department. And the balance is of the most critical components - Man,

    Machine andMaterial

  • 7/30/2019 Cutting Room Project

    3/30

    CUTTING DEPARTMENT

    Cutting is the very first process in garment manufacturing. The cutting

    department receives the fabric from the fabric department after inspection.

    Objectives of the department

    Cutting according to the master patterns with 100% accuracy.

    Ensuring 100% quality in cutting.

    100% issue of all the parts to sewing section.

    The cutting floor is a combined unit for spreading, cutting, ticketing and bundling.

    The work of cutting department starts right from the point of order being receivedfrom the buyer by the merchandising department. The CAD department preparesthe marker using the patterns prepared by the Sampling Department. It alsoprepares the CAD-Consumption Worksheet and makes estimation for theconsumption of the fabric for that particular order. The results are thencommunicated to merchandiser.

    The cutting department at Arvind mills limited; Vadsar unit is an advanced cutting

    unit. It uses advanced Gerber technology for spreading and cutting. Manual

    spreading is also done here. Cutting department also has straight knife and band

    knife. The model no. of these machines has been mentioned later in this section.

    Band knife is used to cut small components like moon patch, placket, sleeves

    etc. The capacity of the cutting department is 13000-16000 pieces per day. The

    department head is Mr. Mittal.

  • 7/30/2019 Cutting Room Project

    4/30

    Hierarchy of the cutting department

    Head supervisor

    Preparatorysupervisor

    Cutting supervisor

    Operator Operator

    Cutting head

  • 7/30/2019 Cutting Room Project

    5/30

    MATERIAL FLOW

    Issue of fabric from knits store

    Cutting

    Sorting & stickering

    Spreading

    Laying of patterns (if manualspreading)

    Issue to the sewing department

    Bundling

    Relaxation

    CPI (cut panel inspection)

  • 7/30/2019 Cutting Room Project

    6/30

    Total number of lights:41

    Total number of ventilators:24

    Shift wise manpower of cutting department for Gerber:

    Process

    1st Shift 2nd Shift 3rd Shift

    Total

    Excess/short

    Req. Actual Req. Actual Req. Actual

    Spreader 8 7 8 7 8 7 21 -3

    Gerber 3 3 3 3 3 3 9 0

    Ticketing 3 3 3 3 3 3 9 0

    Bundling 5 5 5 5 5 5 15 0

    Collar lay 2 3 2 3 2 3 9 3

    Cuff lay 2 3 2 3 2 3 9 3

    Band knife 2 1 2 1 2 1 3 -3

    Cuff overlock 3 2 3 3 3 3 8 -1

    Parts mix 2 2 2 2 2 2 6 0

    Heat parts mix 2 2 2 2 2 2 6 0

    Fusing 5 3 5 4 5 4 11 -4

    RBK parts mix 6 5 6 6 11 -1

    Manual cut,recut

    5 6 5 6 5 4 16 1

    Total 48 45 48 48 42 40

  • 7/30/2019 Cutting Room Project

    7/30

    The cutting department is divided into two parts one for spreading and cutting ofsolids and other for stripes. For stripes both spreading and cutting is donemanually. For solids automatic spreader and CAM do spreading and cutting. Thefabric that has to go for washing is spread manually and cut into panels. Forstripes 2 contractors have been employed. First with 13 labors and second with

    18 labors.

    Working procedure

    Issue of fabric

    Easing process.

    Spreading of lay

    Marker laying (in case of manual cutting)

    Cutting of cakes

    Sorting & stickering

    Bundling

    Issue to sewing room

    For a particular order the amount of fabric, which is required for the order, is

    determined by the PPC. In Arvind mills limited no extra fabric is ordered like in

    other garment industries generally 5-10% extra is ordered. Since the fabrics

    presently were all from Arvind mills textile unit only so no checking is being done.

    If fabric is taken from some other unit then 10% random inspection is done .if

    three roles simultaneously is found to be defective then the whole lot is rejected.

    The fabric is kept in shelves according to lot wise, roll wise and a report of the

    fabric received is generated which contains information like lot number ,style

    number. The information is kept with the store in charge.

  • 7/30/2019 Cutting Room Project

    8/30

    Various Stages in Cutting Room of Arvind:

    When a particular order is approved from the buyer planning is made by PPCdepartment to execute the job. PPC sends batch order in knitting room for the

    fabric according to buyers demand. All the information related to fabric like GSM,dia, shade, and quantity etc. is given in batch order form.

    A batch of knitting room is complete order requirement that consists of everythingsuch as fabric, trims (collar, cuff).

    Knitting department completes the order and sends fabric rolls to the stores incutting room.

    Process flow of solids cutting:

    Spreading on automatic spreader

    CAM cutting

    Ticketing

    Bundling

    Work on Cut parts (optional)

    Inspection

    Cut parts send to warehouse

    The cut parts before inspection are also sent to embroidery, heat transferprinting, fusing and in some cases bottom hem.

    Process flow of stripes cutting:

    Opening of fabric roll

  • 7/30/2019 Cutting Room Project

    9/30

    Cutting of blocks

    Making of pattern on block

    Cutting

    3 straight knifes are used for cutting of laid blocks. Shears are used for cutting ofpanels. A piece of stripes is on the pattern given for matching by the Samplingdepartment.

    Fabric Stores:

    Receiving of fabrics:

    Fabric comes to stores directly from knitting house. For every particular batchsamples comes with audit report from audit department in process house of knits.

    Audit report contains all information regarding the fabric and trims of thatparticular batch.

    Storing of fabric:

    Fabric; is stored according to the buyers name. Every buyer is allocated aspecific rack in storeroom, so batch for that particular buyer is stored in that rack.

    There is no further segregation in the warehouse area.

    Issuing of Fabric:

    Cut plan department sends the required k&p no. of fabric with other data to thestore incharge. Required fabric is then allocated to cutting room from the stores.

    Fabric rolls are received in trolley. It is ensured that all fabric rolls are loadeduniformly. One trolley carries a max of 15 rolls.

    Easing Of The Fabric (Relaxation)

    After the issue of fabric if fabric is single jersey it is taken for relaxation

    process.

    Here fabric is simply unrolled by the machine.

  • 7/30/2019 Cutting Room Project

    10/30

    In this section handling of fabric is done manually bare handed.

    Marker planning and marker making:

    Marker planning is done in other unit. In this unit, just arrangement of marker isdone according to the width of the fabric and gsm of the fabric. New marker isthen uploaded in the cam machine.

    Lay planning:

    Lay planning is done in data-entry department according to the marker plan andthe order of the customer.

    Spreading

    The main objective of spreading is to spread the fabric lay accurately as per the

    length of the maker with minimum waste at end of a lay.

    Types of fabric laying:

    Face to face alternative plies: For symmetrical pattern pieces, and fabric

    which is stable spread face to face, the fabric can be spread along face upand immediately back again face down.

    Face up alternative plies: For asymmetrical as well as symmetrical pattern

    pieces and fabric which is stable spread all the same way up, the fabriccan be spread along and immediately back again.

    Face up all plies in the same direction: For asymmetrical as well assymmetrical pattern pieces and fabric which is stable all the same way up,the spreader spreads in one direction only.

    Face to face all plies in the same direction: For symmetrical pattern

    pieces, and fabric, which is stable face to face, the spreader spreads inone direction only.

  • 7/30/2019 Cutting Room Project

    11/30

    Types of laying methods

    Automatic spreading: Automatic spreader is used to lay honeycomb, pique, andsingle jersey fabrics of both open width and tubular.

    1. Automatic spreading

    2. Manual spreading

    Automatic Spreading:

    Automatic spreading is done for the solid dyed fabric only. After relaxation offabric; fabric is kept on the spreading tables. From here they are loaded onautomatic spreader.

    Features of automatic spreader

    MODEL: GERBER spreader SY101

    Preset: it sets no of plies required 0 point: sets the position of the machine beyond which it cannot move

    Allows zigzag and face one way laying

    Has a sensor which stops the machine if it runs out of fabric

    Dancing bar: checks the tension of the fabric while being laid

    Distance to be traveled by the spreader i.e. the length of the marker is

    fed into the spreading machine system.

    Maximum speed of the machine 100mtrs/min

  • 7/30/2019 Cutting Room Project

    12/30

    Manual Spreading:

    Manual spreading is done for the yarn died fabric and for the fabric that has to

    Off

    stndr

    dtime

    TOTA

    7-

    6-

    6-

    4-jun

    4-

    3-

    3-

    Date

    Gerber

    offstandardtime

    A B A B A B A S h

    if

    t

    1 1 1 1 1 1 1 Gerb

    erno.

    0.00

    % 0 Marke

    rnot

    read

    6.48%

    560

    225

    65

    30

    Machin

    ebrea

    k

    down

    0.00%

    0 Marker

    width

    issues

    12.04

    % 1040

    45

    105

    170

    90

    No

    feedin

    0.0

    0%

    0 Power

    failure

    18.52

    % 1600

    225

    45

    105

    65

    170

    30

    90

    Total

    off

    time

    8640

    1440

    Total

    min

    worked

  • 7/30/2019 Cutting Room Project

    13/30

    be sent for washing. After the fabric is issued from warehouse, it is first blocked,then two persons lay fabric according to the length of marker.

    Generally lay is of length of one full piece of t-shirt. A layer of 65-100 pieces ismade according to the cut plan. During spreading all the plies are matched stripeto stripe on both the sides by workers.

    A separate room is allotted to stripe spreading, cutting and bundling the fabricswhich were yarn dyed.

    Bundle checklist & Bundle card generation:

    Bundle card is generated after the spreading of the lay is done. Bundle card isspecifically the information about that certain bundle viz; k&p no., roll no., piecesin that bundle, size etc. this bundle card is made on the basis of the lay data.

    Cutting:

    Cutting is done by automatic CAM machine for all the fabrics except yarn dyedfabric. For the yarn dyed fabric manual cutting process is used. In manual cuttingmachine lay is cut by straight knife fabric.

    Trims are cut on the band knife machine in a separate area according to the cutplan. Trims are cut in accordance to the main body material of required piece.

    Cutting on Automatic Machine :

    First the lay is transferred from spreading table to cutting area.

    First required cut program is selected form the CAD machine

    Particular parameter is set on Gerber cutting machine according to

    requirement; it consists of speed of blade, area for movement etc.

    The lay is cut in cakes of required

    Numbering & Bundling:

    After the layer is cut the cut pieces are sorted out according to the different rolls.The sleeves, back, front, and placket pieces of one roll are kept together and thesticker which was used during the laying of the layers is sticked on the cut piecesaccordingly and the pieces are bundled.

  • 7/30/2019 Cutting Room Project

    14/30

    A job card is attached to every bundle. This job card contains all the informationabout the bundle and plays an important role till the packing of the garment isdone.

    Fusing/Heat seal:

    Fusing is done for the placket, cuff, collar of the shirts. Different companies/brands have different requirement for fusing and heat sealing.

    Heat sealed machine

    Parameters required for the M&STime - 8 to 10 secondsTemperature- 185 0C

    Pressure 6 bar

    Parameters required for Reebok international And Reebok DomesticTime - 8 secondsTemperature - 180 0CPressure - 6 bar

    Slit making fusing machine

    In slit making fusing machine folders are attached. Canvas and bone both arepassed together through the folder.Bone width = 2.4 cmCanvas width = 0.8 cmReady width of the slit = 1 cm

    Machine nameHASHIMA HPM 600B

    Parameters for fusing machine (slit making)

    Temperature - 140 0CPressure - 2kg/cm2

    Maximum pressure that can be used is 5kg/cm2

    Pressure gauge starts from

  • 7/30/2019 Cutting Room Project

    15/30

    1kg/cm2

    2kg/cm2

    3kg/cm2

    4kg/cm2

    5kg/cm2

    Fusing machine for placket , collar etc.

    Parameters areTime - 5 secondsTemperature - 150 0CPressure 5 kg

    Cut parts inspection:

    After all the parts are introduced in a bundle with the bundle card the bundle ischecked randomly. In cut parts inspection pieces are checked for the sizes fabricfault and cutting fault. Nearly 10% of the bundles are checked.

    Tally of the bundle with information on the job card regarding k&p no., shade,size and no. of pieces is done. 10% visual audit is done. Check list is made here.

  • 7/30/2019 Cutting Room Project

    16/30

    Observations & Suggestions

    Fabric inspection department:

    Fabric inspection is done for each and every roll from a batch. Inspection is donefor the fabric faults and to check the width of each roll of fabric.

    But it was observed that every bundle was not being checked for the

    width.

    Mostly due to workers being uneducated about faults many times roll with

    faults are passed over to audit department.

    Sometimes due to lac of knowledge defected fabric is passed and for the

    same reason less defected fabric is bundled under defected category.

    No humidity and temperature measuring instruments are available.

    GSM of fabric is taken without drying it.

    No instruction is given to rolling operator about the dimension of fabric to

    be cut for GSM measurement.

    GSM of roll is taken from very localized fabric area.

    Suggestion:

    Each and every fabric roll must be checked for width at least two times; atstart of roll and at middle of it.

    Correct information regarding roll must be fed in slip.

    It must be tried to check the GSM of each roll of fabric.

    Employee education is very necessary here.

    Samples of defected fabrics or photographs of them should be made

    available to operator.

    Due to excess humidity and temperature,there is more relaxationallowances for worker which decreases overall on standard time.

    Due to moisture contamination observed GSM of fabric may vary from

    actual one.

    Due to unspecified dimension of cut part which is utilized for GSM

    measurement leads to fabric wastage.

  • 7/30/2019 Cutting Room Project

    17/30

    Fabric audit department:

    In fabric audit department 3-4 rolls are checked for width and gsm of the fabricalong with the fabric fault.

    Many time GSM of the fabric changes from roll to roll and also in the same

    roll.

    Same thing happens with the width of the fabric.

    But as each bundle is not checked these faults pass unnoticed to cutting

    room

    Suggestion:

    Cut part which is choosen for GSM measurement should be taken from

    different location of fabric roll and avg of different measurement should bemarked as GSM of fabric.

    Width of the fabric should be taken from different phases of fabric roll ie 1 st

    check when 15 mts are roll is finish.

    2nd measurement should be taken at middle of rolling process and third atlast.

    Fabric Warehouse:

    There is no check of fabric prior to storage in the warehouse.

    Fabric is not segregated according to width or gsm of fabric.

    Relaxation of the fabric:

    No proper relaxation machine.

    Machine that is used does not have proper attachments.

    Fabric handle is done manually. This causes fabric disturbance and

    relaxed fabric is gets ruffled.

    No accountability in this department.

  • 7/30/2019 Cutting Room Project

    18/30

    Suggestion:

    Spiral rollers should be used instead of plain rollers.

    Tray should be used in which fabric is collected and loaded to spreadingmachine along with the tray.

    Spreading:

    Automatic Spreading

    Running speed of the machine is higher than required

    Used speed of machine is very low in the range of 7m/min.

    Spreading machine uses more workers than needed.

    Spread of single jersey is very difficult due to above operations.

    Achievable target is not achieved even after excess operators being

    implied on spreader.

    Optimum lay length is 7-8m but here lay length sometimes is more than

    10m.

    Lack of attachments in the spreading machine.

    Change in width and lack of data regarding the variation of roll width there

    is frequent machine stoppage; and sometimes even two or three plieshave to be removed after being laid.

    Manual Spreading:

    Excessive manpower allocated in this department.

    Hand shears is used instead of end cutters leading to increase of

    manpower need.

    In yarn dyed spread length is generally for a single piece of shirt leading in

    the need of excessive manpower for laying.

    Shifting of the lay to cutting table:

    While shifting of lay from spreading table to the cutting table air floatation

  • 7/30/2019 Cutting Room Project

    19/30

    table is not used properly.

    Suggestion:

    Decrease running speed of spreader,to avoid turning of plies upside down.

    Keep length of spread between 7-8 m.this will help in faster and preciselay.

    One operator should always travel along with the machine to fix any

    blockage in the passage of laying. At the beginning itself.

    Spiral rollers should be used instead of plane surface rollers. To insure

    even lay .

    Two diiffrent lays of tubular knits can be spread at a time to utilize

    maximum width laying capacity of spreader.

    Spreading operator have no data about width of roll which causes

    spreading of rolls with different widths ,this will create loss of fabric asmarker is made according to roll of minimum width.

    Replace hand shears with end cutters.this will decrease labour

    requirement from 4 to 2.and will also increase efficiency of lay.

    Instead of laying for single piece one can make a block for two piece and

    after laying block can be cut and operated separately.

    Before shifting of lay make sure that air flotation is on and running at

    highest level.this will decrease tension in lay due to pulling and alsodistortion in lay.

    Problems faced in the cutting department

    Bowing

    This is a major problem faced in the cutting department while spreading.Variation in the width of the fabric, which form an arc shape during spreading issaid to be bowing effect.

    Leaning

  • 7/30/2019 Cutting Room Project

    20/30

    Leaning is occurred during manual spreading. In leaning the top ply of the fabricwill be slightly inside the previous ply. It is occurred due to improper laying.

    Edging

    It is also a problem faced in the cutting room. On every spread there is aplus/minus variation of the edge of the fabric from the below lay of the fabric.

    End loss

    The fabric that extends beyond the marker patterns end is called as end loss.This occurred due to improper laying of fabric lays.

    End bits

    Here in the cutting room we are getting end bits almost for all fabric Takas. Aftercomplete laying of one fabric Taka, at the end we get a small piece of fabric thatcannot be used for laying which is said to be end bits.

    Uneven tension

    It is a spreading defect that arisen only when the layers lay fabric under impropertension and creases are formed on spread surface.

    Misalignment of pliesIt is a spreading defect that arises when all the plies of the lays are of differentlength and not lay exactly of same length as per table marker.

    Now comes last but not the least:

    Spirality:

    Spirality of knitted fabric is obtained when wales is not perpendicular tocourse,forming an angle of spirality with vertical direction of the fabric.it affectsgenerally single jersey knits and produce serious problem during garment

    confection and use.Problems occur due to Spirality are:

    Mismatched patterns.

    Sewing difficulty.

    Displacement of side seams to the back and front of the body

    Garment distortion.

  • 7/30/2019 Cutting Room Project

    21/30

    How to measure spirality???...

    For the measurement of spirality angle, plain knitted fabric samples

    having 10x10 cm dimensions were prepared. Digital photographs were

    taken by a digital optical microscope using a software (Motic images

    plus 2.0) permitting to acquire and save images with 10 to 40 times

    magnifying. These images were taken

    from the back side of the plain knitted fabric because stitch edges from

    this side were easier to distinguish than those from right side (Figure

    1).

    Right side Back side

    Figure 1. Aspect of right and back side of plain knitted fabric.

    The images were then treated by Microsoft Visual Basic VB 6.0

    software. The image processing consists to improve the image quality

    (brightness, contrast)

  • 7/30/2019 Cutting Room Project

    22/30

    and to draw two lines by clicking on four points belonging to a wale

    edges and calculate the mean straight line equation .

    . Microsoft Visual Basic programme for spirality angle

    measurement.

    The same procedure is applied to a fabric course. The two mean

    straight lines equations allow the determination of the spirality angle ?.

    All measurements were performed under standard textile testing

    conditions of 21C 1C, and 65% 2% relative humidity. No

    tension was applied to samples under microscope. Seven specimen of

    each sample were tested and the mean spirality angle and the

    corresponding CV% were calculated. We produced a series of 16

    cotton plain knitted fabric (100% combed cotton yarn) commonly used

    in the clothing industry by using an industrial single jersey circular

    knitting machine. (Diameter = 23 inch, gauge = 24, total number of

    feeders = 74).

    The influence of four parameters linked to yarn, fabric structure and

    machine were studied. The knitted specimen covered a large range ofyarn twists, yarn tension, loops length and feeders density. When

    studying one parameter the three other ones were kept constant. Yarn

    tension was measured by using an electronic tensiometer and loop

    length was obtained by using a yarn debimeter. Feeder density

    corresponds to the number of feeders per inch of machines diameter.

  • 7/30/2019 Cutting Room Project

    23/30

    For the variation of this parameter, we performed specific machine

    setting by using interchangeable miss cams in order to be able to

    cancel some feeders and to vary progressively the number of working

    feeders on the single jersey machine.

    Results

    Average spirality angles obtained in the different knitting conditions

    are summarised in Table below.

  • 7/30/2019 Cutting Room Project

    24/30

    Variation of spirality angle with Yarn twist.

    shows plot of averages spirality angle versus stitch length. The degreeof fabric spirality increases linearly with stitch length. The relationship

    between fabric spirality and stitch length is again strong (correlation

    coefficient R = 0.98).

    Variation of spirality angle with stitch length. Relationship between

    fabric spirality and yarn tension during knitting is shown Fabric

  • 7/30/2019 Cutting Room Project

    25/30

    spirality decreases linearly with yarn tension with a quite strong

    (correlation coefficient R = 0.97).

    Variation of spirality angle with yarn tension. shows the influence of

    the number of feeders and fabric spirality. Linear correlation cannot betested in this case since the number of feeders is not a continuous

    variable, but spirality increases strongly when increasing the number

    of working feeders on the machine.

    Variation of spirality angle with number of feeders. A very common

    finishing process, typically used for fine gauge cotton knitted

    structures was applied to the fabric presented in the first line of Table

    1. First, the plain knitted fabric was washed and dyed. After squeezing,

    the fabric was dried and relaxed by using a tumbler drier. Finally, thefabric was stabilised and ironed by using a tubular compactor.

    Corresponding average spirality angle are presented in Table . We can

    easily observe that finishing reduces fabric spirality. The fabric shrank

    and stitch wales were straightened.

    Fabric aspect before and after finishing.

    Spirality angle

    Mean(degree)

    CV%

  • 7/30/2019 Cutting Room Project

    26/30

    Before

    Finishing

    11.5 7.13

    After

    Finishing

    3.82 7.18

    Various causes of Spirality

    Yarn twist:

    The strong linear dependence obtained between fabric spirality and

    yarn twist show that the main source of spirality is yarn twist. When

    a twisted yarn is knitted into a loop, it will have a tendency to rotate

    inside the fabric in order to release its torsional strain during

    relaxation.

  • 7/30/2019 Cutting Room Project

    27/30

    Stitch length

    Stitch length expresses the tightness of knitting construction. The

    fabric is as tight as stitch length is low. The observed proportionality

    between fabric spirality and stitch length can be explained by the fact

    that compared to tight fabrics, slack fabrics have higher stitch length

    and then the yarn composing the loop has a higher tendency to rotate

    inside the fabric after relaxation in knitted fabric construction. In a

    more tightly knitted fabric, the movement of a knitted loop is

    restricted, and thus spirality is reduced.

  • 7/30/2019 Cutting Room Project

    28/30

    Yarn tension

    The influence of yarn tension during knitting on fabric spirality has not

    been studied in literature. The observed linear dependence between

    these two parameters is linked to yarn deformation. During knitting,yarn undergoes an important tension. At high tensions, the viscoelastic

    nature of the yarn causes yarn fibres to slip inside the structure. This

    slippage straightens fibres and reduce yarn twist and then yarn

    tendency to rotate inside the fabric after relaxation. This explains why

    at high yarn tensions, the fabric spirality is reduced.

    Number of knitting feeders:

    The observed increase of fabric spirality with the number of knitting

    feeders at a constant machine diameter is due to the nature of weft

    circular knitting. A fabric course knitted in a given feeder has to be

    inclined with a certain angle in order to permit the knock over of the

    row of stitches knitted in the following feeder. This angle depends on

    the number of feeders per machine diameter. The increase of the

    feeder density in circular knitting machines is the subject of high

    competition between machines manufacturers because of its impact on

    machines productivity. Mayer & Cie holds the record in this matter with

    the single jersey machine Relanit 4.0 which has 4 feeders per inch of

  • 7/30/2019 Cutting Room Project

    29/30

    machine diameter [10]. These technological advances will certainly

    increase the importance of fabric quality problems linked to spirality.

    Effect of the number of feeders on fabric spirality

    The observed reduction of fabric spirality after a typical cotton

    finishing process is due two main obligatory operations: Squeezing and

    compacting. During wet treatments (ie, washing and dyeing) fabric is

    relaxed and fabric spirality increases, but during squeezing, stitch

    wales are straightened thanks to the air injection device equipping the

    squeezing machine. Fabric compacting contribute also to the reduction

    of spirality by correcting mechanically wale direction and fixing this

    correction with a thermal treatment. Finishing reduces fabric spirality

    but a residual spirality angle always remains. Generally a spirality

    angle under 4 is tolerated before garment confection. It is then

    important to reduce fabric spirality from knitting process in order to

    make spirality correction during finishing possible.

    Following are the factors causing delay in cutting department

    Spreader stoppage because of nap direction

    Defect marks

    Splicing

    Utilizing end bits

    Paper work

    Measure length and width of ply

    Roll change

  • 7/30/2019 Cutting Room Project

    30/30

    Conclusion

    The project has been very useful in giving a practical knowledge of the cuttingroom and particularly knits in the garment industry.

    The project has given us a detailed knowledge about the process flow andprocedures followed in industry.