Current Meter Maintenance Model OSS-B1. ‘Hydrographic Basics’ Training Course No. 27743. Section 1 Prior To Discharge Measurements. Prior To Discharge Measurements. Remove fan assembly from carry case Turn fan carrier anti-clockwise. Anti-Clockwise. Prior To Discharge Measurements. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Current Meter Maintenance Model OSS-B1

Current Meter MaintenanceModel OSS-B1

‘Hydrographic Basics’ Training

Course No. 27743

Page 2: Current Meter Maintenance Model OSS-B1

Section 1Prior To Discharge Measurements

Page 3: Current Meter Maintenance Model OSS-B1

Prior To Discharge Measurements

• Remove fan assembly from carry case

• Turn fan carrier anti-clockwise

Anti-Clockwise

Page 4: Current Meter Maintenance Model OSS-B1

Prior To Discharge Measurements

• Separate fan carrier from shaft assembly (keep away from contact with any dirt particles)

• Hold the fan upright and ‘fill’ with approved HS current meter oil

Use Lint Free Tissue

Page 5: Current Meter Maintenance Model OSS-B1

Prior To Discharge Measurements

• Replace axle and fan carrier, excess oil will be forced up through the capillary gap around the axle, ensure fan carrier is tightened

• Wipe the excess oil of

the meter using lint free paper towel

Clockwise

Page 6: Current Meter Maintenance Model OSS-B1

Prior To Discharge Measurements

• Do not forget to close the oil bottle straight after usage to avoid contamination of the oil

• Slide the fan assembly into the body and use the stubby screwdriver to tighten the retaining screw to lock the fan assembly in place

Page 7: Current Meter Maintenance Model OSS-B1

Prior To Discharge Measurements

• Prior to spin test hold the current meter in the horizontal position and spin by hand for approx. one minute to get rid of the hydraulic pressure

• Spin test the meter against time to test the performance of the shaft and bearings

Page 8: Current Meter Maintenance Model OSS-B1

Prior To Discharge Measurements

• Spin test results are dependent on the fan type

• Connect your current meter to the counter using the lead provided (this will test that the lead, reed switch and counter are working prior to use)

• If the current meter fails the spin test, disassemble and clean all components again.

• If the current meter continues to fail the test, replace bearings

OSS-B1 Spin Test

Fan No. Minimum Time (secs)

1 90

A 110

2 90

4 90

Page 9: Current Meter Maintenance Model OSS-B1

Section 2During and After Discharge

Measurements

Page 10: Current Meter Maintenance Model OSS-B1

During and after Discharge Measurements

After every discharge measurement, (or one hour of use), the current

meter should be cleaned and refilled with oil, if continuing a discharge

measurement.

Page 11: Current Meter Maintenance Model OSS-B1

During and after Discharge Measurements

• Undo the cleaning jar cap and ‘¾ fill’ with white spirit

• Remove fan assembly from meter body by undoing the retaining screw and separate the body from the fan

Cleaning Jar

Page 12: Current Meter Maintenance Model OSS-B1

During and after Discharge Measurements

• Remove fan carrier and shaft assembly (do not place in contact with dirt particles)

• Empty the old oil in a recycling container and dispose (do NOT re-use)

Page 13: Current Meter Maintenance Model OSS-B1

During and after Discharge Measurements

• Put the shaft and bearing assembly into the cleaning jar.

• Agitate the jar • Fill up the fan with white

spirit, place your thumb over the hole and shake vigorously for a few seconds.

• Current meter body should be wiped clean with white spirit (there is no need to immerse)

Page 14: Current Meter Maintenance Model OSS-B1

During and after Discharge Measurements

• Blow dry the shaft assembly, fan carrier and fan.

• Re-assemble the fan, coat bearings with a small amount of oil if discharge measurement is complete

Page 15: Current Meter Maintenance Model OSS-B1

During and after Discharge Measurements

• Wipe box clean and return the fan assembly to the case

• If continuing a discharge measurement, refill the fan with oil

Page 16: Current Meter Maintenance Model OSS-B1

During and after Discharge Measurements

• Spin test the current meter against time as shown in section 1

• After the spin test is performed connect your current meter to the counter using the lead, to test the lead, reed switch and counter.

Page 17: Current Meter Maintenance Model OSS-B1

Section 3Office Cleaning

Page 18: Current Meter Maintenance Model OSS-B1

Office Cleaning

Office cleaning should be performed on a monthly basis or whenever the

meter is dirty

Page 19: Current Meter Maintenance Model OSS-B1

Office Cleaning

• Separate fan carrier from shaft assembly

• Current meter body should be wiped clean with soapy water (there is no need to immerse)

Anti-Clockwise

Page 20: Current Meter Maintenance Model OSS-B1

Office Cleaning

• Separate fan carrier (1) from shaft assembly (2)

1 2

Page 21: Current Meter Maintenance Model OSS-B1

Office Cleaning

Remove Nut Remove Bearing

Page 22: Current Meter Maintenance Model OSS-B1

Office Cleaning

Remove Outer Spacer

Remove Inner Spacer

Page 23: Current Meter Maintenance Model OSS-B1

Office Cleaning

Remove Bearing Fan assembly fully dismantled ready to clean

Page 24: Current Meter Maintenance Model OSS-B1

Office Cleaning

Place items in sink, filled with hot soapy water, soak for at least 5 minutes

Clean items with a bottlebrush cleaner

Page 25: Current Meter Maintenance Model OSS-B1

Office Cleaning

Cleaning Fan Cleaning Fan Carrier

Page 26: Current Meter Maintenance Model OSS-B1

Office Cleaning

Cleaning outer spacer

Rinse full assembly with tap water

Page 27: Current Meter Maintenance Model OSS-B1

Office Cleaning

• Place full assembly on lint free tissue

• Ready to dry and re-assemble

• Rinse all items in white spirit prior to re-assembly

Page 28: Current Meter Maintenance Model OSS-B1

Office Cleaning

Dry Fan Carrier Dry Fan

Page 29: Current Meter Maintenance Model OSS-B1

Office Cleaning

Dry Outer Spacer Dry Inner Spacer

Page 30: Current Meter Maintenance Model OSS-B1

Office Cleaning

Blow Dry Bearing & Nut

Page 31: Current Meter Maintenance Model OSS-B1

Office Cleaning

Start Shaft Assembly, Bearing First

Assemble Inner Spacer

Page 32: Current Meter Maintenance Model OSS-B1

Office Cleaning

Assemble Outer Spacer

Assemble Bearing

Page 33: Current Meter Maintenance Model OSS-B1

Office Cleaning

Assemble axle nut Dip shaft assembly in white spirit to lubricate

bearings

Page 34: Current Meter Maintenance Model OSS-B1

Office Cleaning

Blow Excess White Spirit

Assemble Axle With Fan Carrier

Page 35: Current Meter Maintenance Model OSS-B1

Office Cleaning

• Re-assemble fan and place in carry case Clockwise

Page 36: Current Meter Maintenance Model OSS-B1

Section 4Calibration

Page 37: Current Meter Maintenance Model OSS-B1

CalibrationAS 3778 ‘Measurement of water flow in open channels, Part 6.1, Section 7.6 ‘Recalibration’ states:      

“Meters shall be recalibrated whenever their performance is suspect. In practice, for

individually rated meters, recalibration is sometimes carried out at yearly intervals or after

300 h of use, whichever is the shorter.”

Page 38: Current Meter Maintenance Model OSS-B1

Questions?