council rock middle schools construction bid review

Upload: buckslocalnewscom

Post on 07-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    1/41

    Newtown 

    and 

    Holland 

    Middle 

    Schools 

    Construction Project Bid Review

    Facilities Committee

     Meeting

    March 30, 2016

    (Updated March 31, 2016)

    *Includes clarifications requested  at  

    30MAR16 FACCOM Meeting (italicized)

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    2/41

    AGENDA

    Facilities Improvements Update   Newtown Middle School Bid Review/Recommendations

      Holland Middle

     School

     Bid

     Review/Recommendations

    Capital Improvements Project Update

    (20APR16 FACCOM

     Agenda

     Items)

      Final Accounting of  NOC Construction

      2016 Summer Projects Bid Review/Recommendations

      Holland ES Toilet Room Floor Tile Repairs

      Aramark Custodial Fees 1, 3, and 5 Year Proposal 

    Public Comments

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    3/41

    Facilities 

    Improvements

    Update

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    4/41

    Newtown Middle School

    Site 

    Plan 

    Sketch

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    5/41

    Newtown 

    MS 

     – 1st 

    Floor 

    Plan 

    Sketch

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    6/41

    Newtown MS

      – 2nd

     Floor

     Plan

     Sketch

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    7/41

    Newtown Middle School 

    Construction 

    Project 

    Bid 

    Review

    •   Bids opened March 1 & 3, 2016

    •   Good competition

     ‐ Minimum

     4 bids

     for

     each

     of 

     the

     major

     

    contracts

    •   Project under budget and on schedule

    •   LEED Gold, sustainable, energy efficient building

    •   Value added alternates incorporated for durability and 

    maintainability

    •   On track to receive $2M in ACE Grant Funds

      On 

    track 

    to 

    receive 

    PDE 

    reimbursement

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    8/41

    Newtown Middle School Project 

    Bid 

    Results

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    9/41

    Newtown Middle School Project 

    Budget vs. 

    Bid 

    Results

    Budget Actual

     

    Construction 

    Costs 49,704,672$ 

    46,298,250$ 

    Financing Costs 1,148,673$  917,899$ 

    Contingency for unforeseens 2,274,562$  2,191,275$ 

    Fees, Permits, Testing, etc. 5,054,403$  4,713,027$ 

    FF&E 400,000$ 

    1,700,000$ Project

     

    Budget 

    without 

    ACE 

    Grant 58,582,310$ 

    55,820,451$ 

    LEED Gold ACE Grant achievable though 

    project design and construction 2,000,000$  2,000,000$ 

    Total 

    Project 

    Cost, 

    Excluding 

    Financing 55,433,637$ 

    52,902,552$ 

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    10/41

    Bid Alternates Review ‐

    Recommended 

    AlternatesEngineered stone fill for building pad  ‐Construction activities can continue following storm events. Clean, compacted fill beneath building slab.

     $ 

    320,000 

    Alternate Garland roof  w/ 25 yr. warranty  ‐Upgraded roof  with additional 5 year warranty; LEED compliance

     $  288,000 

    Alternate building monitoring system controls and HVAC equipment

      ‐BMS controls and equipment by JCI in lieu of  Trane/Siemens

     $  (110,000)

    Solar roof 

     panels

      ‐Offset 3% of  building's electric use, teaching tool

     $ 

    198,000 

    Extended warranty (all primes)

      ‐Increase period from 1 year to 2 years ‐ value as there is complex equipment and BMS

     $  102,000 

    Install sod in lieu of  grass in select areas

      ‐

    Eliminates 

    earth 

    from 

    entering 

    the 

    building 

    and 

    establishes 

    lawn 

    at 

    building 

    front 

    where 

    foot 

    traffic 

    is 

    most 

    anticipated

     $  58,000 

    Upgrade locker doors  ‐Durability and extended life of  lockers

     $  2,800 

    Outdoor cafeteria seating  ‐Additional outdoor seating for students; program requirement that will provide for opportunities for the students

     $  83,000 

    Mill and Overlay Green Lane

      ‐

    Road 

    is 

    deteriorated 

    and 

    will 

    likely 

    continue 

    to 

    do 

    so 

    during 

    construction

     $  87,000 

    Sanitary line replacement (required)

      ‐Required in order to obtain the proper approvals for the Project

     $  32,000 

    Lightning protection system  ‐Protection for the building and expensive rooftop equipment

     $  99,000 

    Total 

    Alternates 

    1,159,800 

    Recommended Alternates

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    11/41

    Bid Alternates Review ‐

    Alternates 

    Not 

    Recommended

    Delete Four (4) Classrooms

      ‐Base bid  includes District  requirement   for  7  Learning teams $  (391,000)

    Alternate Floor Finishes

      ‐Less

     durable/lesser

     quality

     floor

     finishes

     with

     a shorter

     life

     cycle

      Varies 

    Alternate Light Fixtures

      ‐Added cost with little value $  19,900 

    Total 

    Alternates 

    Not 

    Being 

    Recommended 

    (371,100)

    Alternates 

    Not 

    Being 

    Recommended

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    12/41

    General Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    13/41

    Mechanical Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    14/41

    Electrical Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    15/41

    Plumbing Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    16/41

    Environmental Abatement Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    17/41

    Newtown Middle School Project 

    Budget vs. 

    Bid 

    Results

    Budget Actual

      Construction Costs 49,704,672$  46,298,250$ 

    Financing Costs 1,148,673$  917,899$ 

    Contingency for unforeseens 2,274,562$  2,191,275$ 

    Fees, Permits, Testing, etc. 5,054,403$  4,713,027$ 

    FF&E 400,000$ 

    1,700,000$ Project

     

    Budget 

    without 

    ACE 

    Grant 58,582,310$ 

    55,820,451$ 

    LEED Gold ACE Grant achievable though 

    project design and construction 2,000,000$  2,000,000$ 

    Total 

    Project 

    Cost, 

    Excluding 

    Financing 55,433,637$ 

    52,902,552$ 

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    18/41

    Newtown Middle School Project 

    Summary 

    of  

    Square 

    Foot 

    Costs

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    19/41

    Newtown Achievements

    •   Project under budget and on schedule

    •   LEED Gold, sustainable, energy‐efficient building

    •  Value

     added

     alternates

     incorporated

     for

     durability

     and maintainability

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    20/41

    Newtown MS  –

    Next 

    Steps•   March 31, 2016:

     –    Award bids and alternates

     –    Approve PlanCon

     F,

     Attachment

     C,

     PlanCon

     G,

     and

     PlanCon

     H

     documents

     –    Award Construction Testing and Construction Waste Management Contracts

    •   May 2016  – Ground breaking

    •   June 2016

      – Construction

     begins

    •   June 2018  – New building complete

    •   August 2018  – Students occupy new school

    •   June 2019  – Demolition and fields complete

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    21/41

    Newtown Discussion

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    22/41

    Holland Middle School

    Site Plan Sketch

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    23/41

    Holland MS  – 1st Floor Plan Sketch

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    24/41

    Holland MS  – 2nd Floor Plan Sketch

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    25/41

    Holland Middle School 

    Construction Project Bid Review

    •   Bids opened March 29, 2016

      Good competition

      – Minimum

     5 bids

     for

     each

     of 

     the

     major

     

    contracts

    •   Project under budget and on schedule

    •   LEED Gold, sustainable, energy efficient building

    •   Value added alternates incorporated for durability and 

    maintainability

    •   On track to receive $2M in ACE Grant Funds

    •   On track to receive PDE reimbursement

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    26/41

    Holland Middle School Project 

    Bid Results

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    27/41

    Holland Middle School Project 

    Budget vs. Bid Results

    Budget Actual

      Construction Costs 43,488,168$  40,827,400$ 

    Financing Costs 1,045,526$  785,077$ 

    Reserve Contingency for unforeseens 3,482,930$  2,482,930$ 

    Reserve Fees, Permits, Testing, etc. 4,905,178$  4,905,178$ 

    FF&E   400,000$ 

    1,700,000$ 

    Project 

    Budget 

    without 

    ACE 

    Grant 53,321,802$ 

    50,700,585$ 

    LEED Gold ACE Grant achievable though 

    project design and construction 2,000,000$  2,000,000$ 

    Total 

    Project 

    Cost, 

    Excluding 

    Financing 50,276,276$ 

    47,915,508$ 

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    28/41

    Bid Alternates Review ‐

    Recommended Alternates

    Alternate Garland roof  w/ 25 yr. warranty  ‐Upgraded roof  with additional 5 year warranty; LEED compliance

     $  (50,000)

    Alternate building monitoring system controls and HVAC equipment

      ‐BMS controls and equipment by JCI in lieu of  Trane/Siemens

     $  (115,000)

    Solar 

    roof  

    panels  ‐Offset 7% of  building's electric use, teaching tool

     

    450,000 

    Engineered stone fill for building pad  ‐Construction activities can continue following storm events. Clean, compacted fill beneath building slab.

     $  150,000 

    Install sod in lieu of  grass in select areas

      ‐

    Eliminates 

    earth 

    from 

    entering 

    the 

    building 

    and 

    establishes 

    lawn 

    immediately

     $  22,000 

    Upgrade locker doors  ‐Durability and extended life of  lockers

     $  1,200 

    Outdoor cafeteria seating  ‐Additional outdoor seating for students; program requirement that will provide for opportunities for students

     $  32,000 

    Delete Wood Paneling at Lobby Area

     ‐More

     durable,

     sustainable

     wall

     finish,

     with

     accessibility

     to

     utilities

     located

     in

     ceiling

     $  (191,000)

    Use of  Steel Railing System at Learning Stair

      ‐More durable and less susceptible to damage/vandalism

     $  (45,000)

    Crosswalk at Buck Road  ‐Must be accepted as this is a part of  Land Development requirements

     $  82,000 

    Lightning protection system

      ‐Protection

     for

     the

     building

     and

     expensive

     rooftop

     equipment

     $  75,800 

    Total 

    Alternates 

    412,000 

    Recommended Alternates

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    29/41

    Bid Alternates Review ‐

    Alternates Not Recommended

    Delete Four (4) Classrooms

      ‐

    Base 

    bid  

    includes 

    District  

    requirement  

     for  

    7  

    Learning 

    teams

     $  (416,300)

    Alternate Floor Finishes  ‐Less durable/lesser quality floor finishes with a shorter life cycle

      Varies 

    Reduce the Size of  Front Canopy

      ‐Provides a dry zone for student drop‐off, demarcation for car stacking, and defines the school entry $  (175,000)

    Remove Tablet Arms from Mezzanine Seating/LGI

     ‐Area serves LGI ‐ keep tablet arms to provide a desk surface for students

     $  (7,400)

    Salvage Existing Bleachers for Auxiliary Gym  ‐Bleachers are over 40 years old and at the end of  their useful life

     $  (7,000)

    Alternate Auditorium Seating

      ‐Physical samples were unavailable for seating ‐ can be reconsidered at a later date

     $  (14,000)

    Total 

    Alternates 

    Not 

    Being 

    Recommended 

    (619,700)

    Alternates Not Being Recommended

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    30/41

    General Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    31/41

    Mechanical Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    32/41

    Electrical Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    33/41

    Plumbing Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    34/41

    Environmental Abatement Construction Bids

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    35/41

    Holland Middle School Project 

    Budget vs. Bid Results

    Budget Actual

      Construction Costs 43,488,168$  40,827,400$ 

    Financing Costs 1,045,526$  785,077$ 

    Reserve Contingency for unforeseens 3,482,930$  2,482,930$ 

    Reserve Fees, Permits, Testing, etc. 4,905,178$  4,905,178$ 

    FF&E   400,000$  1,700,000$ 

    Project 

    Budget 

    without 

    ACE 

    Grant 53,321,802$ 

    50,700,585$ 

    LEED Gold ACE Grant achievable though 

    project design and construction 2,000,000$  2,000,000$ 

    Total 

    Project 

    Cost, 

    Excluding 

    Financing 50,276,276$ 

    47,915,508$ 

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    36/41

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    37/41

    Holland Achievements

    •   Project under budget and on schedule

    •   LEED Gold, sustainable, energy‐efficient building

      Value added

     alternates

     incorporated

     for

     durability

     and maintainability

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    38/41

    Holland MS  –

    Next Steps

    •   March 31, 2016:

     –    Award bids and alternates

     – 

      Approve PlanCon

     F,

     Attachment

     C,

     PlanCon

     G,

     and

     PlanCon

     H

     documents

     –    Award Construction Testing Contract

    •   May 2016  – Ground breaking

    •  June

     2016

      – Construction

     begins

    •   June 2016 to August 2018  – Phased completion of  building 

    renovations and additions

    •   August 2018

      – Students

     occupy

     all

     new

     areas

    •   October 2018  – Final sitework complete

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    39/41

    Holland Discussion

    T t l P j t C i

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    40/41

    Total Projects Comparison

    Budget vs. Bid ResultsNewtown Middle School Budget Actual

      Construction Costs 49,704,672$  46,298,250$ 

    Financing Costs 1,148,673$  917,899$ 

    Contingency for unforeseens 2,274,562$  2,191,275$ 

    Fees, Permits, Testing, etc. 5,054,403$  4,713,027$ 

    FF&E   400,000$ 

    1,700,000$ 

    Project 

    Budget 

    without 

    ACE 

    Grant 58,582,310$ 

    55,820,451$ 

    LEED Gold ACE Grant achievable though 

    project design and construction 2,000,000$  2,000,000$ 

    Total 

    Project 

    Cost, 

    Excluding 

    Financing 55,433,637$ 

    52,902,552$ 

    Holland Middle School Budget Actual

     Construction

     Costs 43,488,168$

     40,827,400$

     

    Financing Costs 1,045,526$  785,077$ 

    Reserve Contingency for unforeseens 3,482,930$  2,482,930$ 

    Reserve Fees, Permits, Testing, etc. 4,905,178$  4,905,178$ 

    FF&E   400,000$  1,700,000$ 

    Project 

    Budget 

    without 

    ACE 

    Grant 53,321,802$ 

    50,700,585$ 

    LEED Gold

     ACE

     Grant

     achievable

     though

     

    project design and construction 2,000,000$  2,000,000$ 

    Total 

    Project 

    Cost, 

    Excluding 

    Financing 50,276,276$ 

    47,915,508$ 

    Budget Actual

    GRAND TOTAL: 105,709,913$  100,818,060$ 

    Difference: 4,891,853$ 

    Contingency 

    Available 

    for 

    Both 

    Projects:   4,674,205$ 

  • 8/18/2019 Council Rock Middle Schools Construction Bid Review

    41/41