copyright by sean michael donahue 2016

150
Copyright by Sean Michael Donahue 2016

Upload: others

Post on 12-Mar-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

             

Copyright

by

Sean Michael Donahue

2016

The thesis committee for Sean Michael Donahue

certifies that this is the approved version of the following thesis:

Proposed Test Program for Evaluating the Progressive Collapse

Capacity of Steel Framed Composite Buildings

APPROVED BY

SUPERVISIING COMMITTEE:

_________________________________

Michael D. Engelhardt, Supervisor

_________________________________

Howard Liljestrand, Co-Supervisor

_________________________________

Eric Williamson

Proposed Test Program for Evaluating the Progressive Collapse

Capacity of Steel Framed Composite Buildings

by

Sean Michael Donahue, B.S.

Thesis

Presented to the Faculty of the Graduate School

of the University of Texas at Austin

in Partial Fulfillment

of the Requirements

for the Degree of

Master of Science in Engineering

The University of Texas at Austin

August 2016

iv

Proposed Test Program for Evaluating the Progressive Collapse

Capacity of Steel Framed Composite Buildings

by

Sean Michael Donahue, M.S.E.

The University of Texas at Austin, 2016

SUPERVISORS: Michael Engelhardt and Howard Liljestrand

The threat of progressive collapse has been an increased concern for structural

engineers in recent history. Current practice when designing structures to resist

progressive collapse has focused on local strengthening of members and connections, and

the addition of extra structural elements to “tie” the structure together. However, typical

structures have a degree of inherent robustness that is not currently counted on by

designers, which may lessen the need for these additional elements. Many of these

elements that add integrity to the structure have not seen extensive experimental testing,

and their strength and ductility are not fully understood. In an effort to fill this gap, a test

program was designed and implemented to study the response of steel-framed composite

buildings to the loss of a column.

A prototype building was designed by Walter P. Moore to be consistent with current

construction standards and practices. A test building was designed based on this

prototype building, with spans and members scaled down slightly to accommodate the

test frame. Test specimens consisted of a 2-bay by 2-bay section of the test building (in

the case of an interior column loss) or a 2-bay by 1-bay section of the test building (in the

case of a perimeter column loss). The effect of the surrounding building was simulated by

the construction of a heavy restraining beam that circumscribed the test specimen,

providing the restraint that would be present due to neighboring bays. A loading system

and test protocol were designed to allow a uniform floor load to be applied to the test

v

specimen while the column support is removed quasi-statically, with the potential for

further uniform floor load to be added if the specimen survived column loss.

vi

Table of Contents

1  INTRODUCTION 1 

1.1  Progressive Collapse .......................................................................................1 

1.2  Research Objectives ........................................................................................2 

1.3  Scope of Thesis ...............................................................................................3 

2  BACKGROUND 5 

2.1  Gravity-Framed Steel Buildings .....................................................................5 

2.1.1 Components of Gravity Framing ...........................................................5 

2.1.2 Design of Gravity Framing ....................................................................9 

2.2  Design for Progressive Collapse ...................................................................13 

2.2.1 History of Progressive Collapse Design ..............................................13 

2.2.2 Current Approaches to Progressive Collapse Design ..........................16 

2.2.3 Behavior of Gravity Framing under Column Loss ..............................21 

2.3  Previous Research .........................................................................................21 

2.3.1 Connection Behavior ...........................................................................22 

2.3.2 Floor Systems.......................................................................................34 

3  TEST SETUP AND SPECIMEN 46 

3.1  Test Concept .................................................................................................46 

3.2  Prototype Building ........................................................................................48 

3.3  Scaling of Test Specimen..............................................................................50 

3.4  Test Specimen Design ...................................................................................51 

3.4.1 Primary Structural Members ................................................................51 

3.4.2 Connections..........................................................................................53 

3.4.3 Floor Slab .............................................................................................54 

3.4.4 Additional Specimen Detailing ............................................................57 

vii

4  TEST FRAME DESIGN 61 

4.1  Foundation Design ........................................................................................61 

4.2  Ring Beam Design ........................................................................................62 

4.3  Additional Design Considerations ................................................................70 

5  TEST PROCEDURE 72 

5.1  Actuator Removal .........................................................................................72 

5.2  Loading System ............................................................................................73 

5.3  Instrumentation .............................................................................................75 

5.4  Test Matrix ....................................................................................................78 

5.5  Interior Column Loss ....................................................................................79 

5.6  Exterior Column Loss ...................................................................................80 

6  CONSTRUCTION OF TEST FRAME AND FIRST TEST SPECIMEN 82 

6.1  Foundation Pour ............................................................................................82 

6.2  Loading System ............................................................................................83 

6.3  Test Frame ....................................................................................................85 

6.4  Floor System .................................................................................................88 

6.5  Concrete Casting ...........................................................................................93 

7  SUMMARY AND CONCLUSIONS 95 

7.1  Summary of Work .........................................................................................95 

7.2  Accuracy of Boundary Conditions................................................................95 

7.3  Effect of Scale on Results .............................................................................96 

APPENDIX A: TEST SPECIMEN AND FRAME DRAWINGS 98 

APPENDIX B: PROTOTYPE BUILDING PLANS 118 

viii

WORKS CITED 133  

 

ix

List of Tables

Table 2-1 Moment-Rotation Parameters of Composite Shear Tabs ................................. 28

Table 2-2 Enhancement from Tensile Membrane Action with Orthotropic Reinforcement............................................................................................................................... 39 

    

x

List of Figures

Figure 2-1 Simple Shear Connections (a) shear tab (b) clip angle (c) end-plate (d) tee (e) seated connection (f) stiffened seated connection .................................................. 6

Figure 2-2 Composite Floor Slab Detail ............................................................................. 8

Figure 2-3 Embossments on Composite Decking ............................................................... 9

Figure 2-4 Rotational Ductility of Clip Angle Connection .............................................. 11

Figure 2-5 Tensile Catenary Action .................................................................................. 18

Figure 2-6 Catenary Action of Edge Panel Enhanced by Peripheral Tie ......................... 20

Figure 2-7 Shear Tab Column Loss Test Setup ................................................................ 23

Figure 2-8 Reduced Rotation Demand on Shear Tabs ...................................................... 25

Figure 2-9 Composite Shear Tabs under Hogging Moment ............................................. 26

Figure 2-10 Composite Shear Tabs under Cyclic Load Test Setup .................................. 27

Figure 2-11 Clip Angles under Cyclic Load Test Setu ..................................................... 30

Figure 2-12 Moment Rotation Hysteresis of Clip Angle .................................................. 31

Figure 2-13 Compressive Membrane Action in Concrete Slabs ...................................... 35

Figure 2-14 Tensile Membrane Action in Highly Deflected Slabs .................................. 35

Figure 2-15 Compression Rin ........................................................................................... 36

Figure 2-16 Load Deflection Relationship for Restrained and Unrestrained Slabs with Span to Depth Ratio of 20 ..................................................................................... 37

Figure 2-17 Parametric Study of Deck Thickness Effect on Composite Floor Robustness............................................................................................................................... 41

Figure 2-18 Parametric Study of Connection Strength on Composite Floor Robustness. 42

Figure 2-19 Deck Fasteners under Cyclic Load Test Setup ............................................. 43

xi

Figure 2-20 Floor Plan of Composite Floor Column Loss Test Setup ............................. 45

Figure 3-1 Test Setup Floor Plan ...................................................................................... 47

Figure 3-2 Actuator in Test Setup ..................................................................................... 48

Figure 3-3 Floor Plans for WPM Prototype Building ....................................................... 49

Figure 3-4 Clip Angle Detail and Constructed ................................................................. 54

Figure 3-5 Shear Tab Detail and Constructed ................................................................... 54

Figure 3-6 Deck with Wire Reinforcement Detail and Constructed ................................. 55

Figure 3-7 Reinforcement over Girder Detail and Constructed ........................................ 56

Figure 3-8 Shear Stud Detail over (a) Secondary Beams and (b) Girders ........................ 57

Figure 3-9 Connection from Deck to Beam using Puddle Welds and Tek Screws .......... 58

Figure 3-10 Tek Screw Layout for (a) Floor Beams and Sidelaps and (b) Girders .......... 59

Figure 3-11 Constructed Detail of (a) Girder and Sidelap Tek Screws and (b) Floor Beam............................................................................................................................... 59

Figure 3-12 Longitudinal Seam Detail and Constructed .................................................. 60

Figure 4-1 Foundation....................................................................................................... 62

Figure 4-2 Load-Slip Relationship of Steel Deck-Concrete Composite Bond ................. 64

Figure 4-3 Restraining Beam Detail and Constructed ...................................................... 65

Figure 4-4 Load-Deflection Response of Floor Slab with Ring Beam and Adjacent Bays............................................................................................................................... 66

Figure 4-5 Restraining Beam Connection Drawing and Constructed .............................. 67

Figure 4-6 Restraining Beam Boundary Parallel to Deck Ribs Detail and Constructed .. 68

Figure 4-7 Restraining Beam Boundary Perpendicular to Deck Ribs Detail and Constructed ........................................................................................................... 69

xii

Figure 5-1 Irrigation System ............................................................................................. 75

Figure 5-2 Instrumentation Plan ....................................................................................... 76

Figure 5-3 Floor System Displacing as (a) Rigid Plates and (b) Flexural Shapes ............ 77

Figure 5-4 String Pot Layout at Center Column ............................................................... 78

Figure 5-5 Interior and Exterior Column Test Setup ........................................................ 79

Figure 6-1 Coupler Attachment to Accommodate Short Anchor Rods ............................ 83

Figure 6-2 Constructed Loading Boxes ............................................................................ 85

Figure 6-3 Erection of Restraining Beams ........................................................................ 86

Figure 6-4 Temporary Frame Supporting Central Column .............................................. 87

Figure 6-5 Screw Jacks Supporting Floor System ............................................................ 88

Figure 6-6 Slab Closures (a) Parallel to Deck Ribs and (b) Perpendicular to Deck Ribs . 89

Figure 6-7 Pour Stop Closures and Insulation Sealing ..................................................... 90

Figure 6-8 Reinforcement Layout along Restraining Beam Parallel to Deck Ribs .......... 91

Figure 6-9 Reinforcement Layout along Restraining Beam Perpendicular to Deck Ribs 92

Figure 6-10 Stiffeners Added to (a) Restraining Beam Supports and (b) Middle Column............................................................................................................................... 94

Figure A-1 Test Frame Plans-Specimen Level ................................................................. 99

Figure A-2 Test Frame Plans-Top Level ........................................................................ 100

Figure A-3 Test Frame Elevation ................................................................................... 101

Figure A-4 Test Frame Elevation-Section View ............................................................ 102

Figure A-5 Test Specimen Detail-Column Connection .................................................. 103

Figure A-6 Test Specimen Details-Column Connection-Section View ......................... 104

xiii

Figure A-7 Test Specimen Details-Clip Angle to Ring Beam Connection .................... 105

Figure A-8 Test Specimen Details-Shear Tab to Ring Beam Connection ...................... 106

Figure A-9 Test Specimen Details-Deck Connection ..................................................... 107

Figure A-10 Test Specimen Details-Deck Details .......................................................... 108

Figure A-11 Test Frame Details-Restraining Beam to Corner Column Connection ...... 109

Figure A-12 Test Frame Details-Midspan Column-Ring Beam Connection, Lateral Brace Center Connection .............................................................................................. 110

Figure A-13 Test Frame Details-Column Top Level Connections ................................. 111

Figure A-14 Test Frame Details-Central Actuator Support, Lateral Brace to Ring Beam Connection .......................................................................................................... 112

Figure A-15 Test Frame Details-Corner Column Base Plate ......................................... 113

Figure A-16 Test Frame Details-Corner Footing Foundation Design ............................ 114

Figure A-17 Test Frame Details-Midspan Column Base Plate and Footing Detail ....... 115

Figure A-18 Test Frame Details-Central Actuator Base Plate and Footing ................... 116

Figure A-19 Test Frame Details-Top Level Brace Connections .................................... 117

Figure B-1 Prototype Building-Floor Plan ..................................................................... 119

Figure B-2 Prototype Building-Column and Brace Schedule ......................................... 120

Figure B-3 Prototype Building-Column Splice and Beam to Girder Connection .......... 121

Figure B-4 Prototype Building-Beam to Column Flange Connection............................ 122

Figure B-5 Prototype Building-Spandrel to Column Flange Connection ....................... 123

Figure B-6 Prototype Building-Girder to Column Flange Connection .......................... 124

Figure B-7 Prototype Building-Beam to Column Web Connection ............................... 125

xiv

Figure B-8 Prototype Building-Spandrel to Column Web Connection .......................... 126

Figure B-9 Prototype Building-Girder to Column Web Connection .............................. 127

Figure B-10 Prototype Building-Reinforcement Details ................................................ 128

Figure B-11 Prototype Building-Shear Stud Details ...................................................... 129

Figure B-12 Prototype Building-Decking Perimeter Details .......................................... 130

Figure B-13 Prototype Building-Deck Closure and Sidelap Details .............................. 131

Figure B-14 Prototype Building-Brace Connection Detail ............................................. 132

1

1 INTRODUCTION

This thesis discusses a proposed test procedure for evaluating the resistance of

steel framed composite buildings to progressive collapse. This research was undertaken

as part of a larger project to test the resistance of such buildings to multiple collapse

scenarios with the intent of developing computational models to predict their behavior.

This chapter briefly describes progressive collapse, the response of steel framed

composite buildings to progressive collapse, and outlines the scope of this thesis.

1.1 Progressive Collapse

Progressive collapse occurs when an initiating event causes a collapse that is

disproportionate to the magnitude of the initial event (Starossek 2007). For this reason, it

is also often referred to as disproportionate collapse. Historically, the threat of

progressive collapse was not heavily considered by designers, but events such as the

collapse of Ronan Point Towers in 1968 in London, and more recently the attacks of

September 11 in New York City have spurred engineers to create integrity provisions to

prevent against such failures (Foley 2007). These provisions are often based on tying the

structural elements of a building together, to better enable redistribution of a building’s

loads around the damaged area. The use of these tie forces in resisting progressive

collapse was originally based on research done on reinforced concrete buildings, and

there are still many unanswered questions about how other structures respond to collapse

scenarios, in particular, steel framed composite buildings.

Most elements in a steel framed building are constructed with “gravity framing”,

so called because it is designed only to resist vertical gravity loads. Thus it is not

2

explicitly designed for the high rotations, moments, and lateral forces common in

progressive collapse scenarios. Thus, the current philosophy used when designing such

buildings to resist progressive collapse requires the strengthening of members and

connections, or the placement of additional structural components (typically additional

reinforcing steel in the floor slab). It is recognized that steel gravity framing does have

some inherent resistance to collapse that may lessen or remove the need for this

strengthening, but currently there is insufficient experimental data for engineers to rely

on this inherent robustness (Stevens 2008)

1.2 Research Objectives

The goal of this research is to increase the available experimental data on the

performance of gravity framed steel buildings under collapse scenarios. There are many

components present in these buildings with the potential to contribute significant

robustness to the structure, but their behavior is not sufficiently well understood to be

incorporated into current codes. In particular, the ductility of composite floor slabs is not

fully understood. The strength of the steel decking used in those slabs is also poorly

understood, particularly because of the very limited testing done on the strength and

ductility of the connections used on that decking. The performance of common flexural

connections, particularly when working compositely with a concrete slab, has also

undergone very limited testing.

This project hopes to answer many of those questions by simulating the response

of a typical gravity framed steel building that has not been designed to resist collapse

under a variety of column loss scenarios. The results of these tests will enable us to

evaluate the inherent robustness of this type of construction. By documenting the

response of the structure and the points of failure of each component (if any), the project

3

also hopes to increase our understanding of the behavior of many of the components

counted on to provide robustness. By identifying the most critical points of failure in

typical construction, the project also aims to design and test alternative construction

details that could be used in future structures to improve the robustness of such buildings.

A full understanding of the behavior of all of these components is beyond the

scope of this paper, and beyond this project. Many more tests will be needed before the

response of floor systems under column loss scenarios can be predicted with confidence.

To that end, this thesis details the design and construction of a test frame and procedure

that can be used to test the behavior of gravity framed composite-steel floor systems

subjected to column loss.

1.3 Scope of Thesis

The experimental portion of this research project consists of multiple large scale

tests conducted on the response of a section of a steel framed composite building under

an interior and exterior column loss scenario. The results of these tests, as well as the

computational models developed based on the results, will be discussed in future papers.

This thesis covers the design and construction of the test setup used to simulate the

boundary conditions and loading present in a full structure subjected to a collapse

scenario.

Chapter 2 provides background information on gravity framing and previous

research into its response to column loss scenarios, and background on the history of

progressive collapse design as well as current philosophy. Chapter 3 discusses the design

of the prototype building used for testing, and the test specimens based upon it. Chapter 4

discusses the design of the testing frame. Chapter 5 discusses the test procedure for

4

simulating column loss and the proposed test matrix. Chapter 6 discusses the construction

of the test setup and first test specimen. Conclusions are presented in chapter 7.

5

2 BACKGROUND

This chapter gives an introduction into the typical design and construction of

gravity framed steel buildings with composite floors and discusses the primary

components that affect their behavior. This chapter also summarizes some of the past

research into the behavior of these individual components under collapse conditions.

Finally, the chapter examines the existing empirical and analytical research on full floor

systems.

2.1 Gravity-Framed Steel Buildings

2.1.1 COMPONENTS OF GRAVITY FRAMING

In typical U.S. design practice for steel buildings, lateral loads (wind, seismic,

frame stability) are resisted by a small number of lateral force resisting frames, normally

moment frames, braced frames, shear walls, or some combination of these. The

remainder of the structural system is designed to resist gravity loads (dead, live, snow,

etc.) and normally consists of columns, beams and girders with a composite floor system,

wherein beams are connected to girders, and girders and beams are connected to columns

using “simple shear” connections. There are many connections commonly used in steel

design that are considered simple shear connections including shear tabs, clip angles,

endplates, tees, and seated connections (See Figure 2-1). While there are many different

types of simple shear connections, in conventional design they are all modeled as “perfect

pin” connections, possessing no rotational strength of stiffness. Thus they cannot

contribute to the lateral strength of the structure, which must be provided by moment

frames, braced frames or shear walls placed throughout the structure.

regar

dema

types

on th

single

(typic

called

Fig

Although

rdless of the

and scenario

s of shear co

he performan

e plate con

cally a girde

d web cleat

gure 2-1 Sim

simple she

type used, t

o, such as th

onnections is

nce of shear

nnection) is

er or column

ts) are a sin

mple Shear C(e) seated

ear connectio

the true beh

he loss of a

s beyond the

tabs and cli

a thin plat

n) and then

ngle angle o

Connections connection

6

ons are typi

avior of suc

column) can

e scope of th

ip angles. A

te of steel

bolted to th

or pair of s

(a) shear tab(f) stiffened

ically mode

ch connectio

n vary. Stud

his research

shear tab (a

welded to

he supported

steel angles

b (b) clip angseated conn

eled in the s

ons (particula

dying the re

, so this rese

also called a

the suppor

d beam. Clip

attached to

gle (c) end-pnection

same manne

arly in a hig

esponse of a

earch focuse

a side plate o

rting membe

p angles (als

o the flexura

plate (d) tee

 

er

gh

all

es

or

er

so

al

7

member and the supporting member. The connections to the flexural member and

supporting member can both be done with bolts or welds. While clip angles are typically

more expensive to construct than shear tabs, they are often used in beam to column

connections, as they can exhibit greater strength and ductility than shear tabs, and their

geometry allows easier attachment to a column web.

These simple shear connections make up the majority of a structure’s framing,

while the structure’s lateral force resisting systems are placed at only a few locations, as

they are significantly more expensive to construct and erect. Their lateral strength must

then be transferred to the rest of the building by use of the floor diaphragm, often

provided by a concrete slab. This slab is typically constructed by placing corrugated

metal decking down over the beams, to which it is usually attached through either puddle

welds or self-drilling tek screws. A concrete slab is then poured on top of it. Through the

use of shear studs welded to the floor beams and extending into the concrete slab, the

concrete also acts compositely with the frame of the structure, enabling it to distribute the

strength of the building’s lateral frames, and enhancing the flexural capacity of the

beams. Figure 2-2 shows a schematic view of a composite floor system.

slab m

is typ

formw

with

slab c

length

flexu

2-3).

inclu

this r

In additio

must also be

pically done

work is non

reinforcing b

can be built

h to prevent

ural reinforce

To control

ded (approx

reinforcemen

on to provid

e designed to

in one of tw

-composite,

bars placed

with compo

t slip betwe

ement for th

shrinkage a

ximately 1%

nt is not cou

Figu

ding compos

o carry the f

wo ways. If

the concrete

in the slab t

osite metal d

en the deck

he slab, rem

and limit cra

by area), us

unted on in

re 2-2 Comp

8

site strength

floor loads to

the corrugat

e slab is des

to provide its

decking. Thi

king and con

moving the n

acking, a sm

sually in the

the analysis

posite Floor

h to the buil

o the beams

ted metal de

signed as a t

s flexural ca

s decking ha

ncrete, which

need for rein

mall amount

e form of a r

s of the struc

Slab Detail

ding frame,

s and girders

ecking used

typical cast

apacity. Alte

as embossm

h enables it

nforcing bars

t of reinforc

reinforced w

cture. The c

the concret

s. This desig

for the slab

in place slab

ernatively, th

ments along it

to act as th

s (See Figur

cement is sti

wire mesh, bu

concrete itse

 

te

gn

’s

b,

he

ts

he

re

ill

ut

elf

can b

has h

codes

struct

still f

2.1.2

frami

simpl

stiffn

they

the s

be made of

higher therm

s. The thinn

ture, but the

frequently us

DESIGN O

There are

ing, one of

le shear con

ness, and thu

support. Inst

supported m

normal weig

mal resistanc

ner slabs, and

e low cost a

sed (SDI 201

OF GRAVITY

e several as

which is th

nnections of

us do not ex

tead, they ar

members. Sim

Figure 2-

ght concrete

e, allowing

d lower den

and higher av

12).

FRAMING

ssumptions

he “perfect p

a gravity fra

xperience an

re designed o

mple shear

-3 Embossm

9

e, or lightwe

the use of t

nsity of the c

vailability o

that go int

pin” assump

amed buildin

ny flexural d

only to carry

connections

ments on Com

eight concre

thinner slab

concrete, res

of normal we

to the desig

ption of the

ng are assum

demand from

y the shear f

s can also b

mposite Deck

ete. Lightwe

s while still

sult in lowe

eight concre

gn of comp

e shear conn

med to have

m the beam

force impose

be designed

king

eight concret

l meeting fir

er load on th

ete mean it

posite gravit

nections. Th

no rotationa

ms and girder

ed on them b

d to handle

te

re

he

is

 

ty

he

al

rs

by

a

10

beam’s axial force if used in a braced frame, but that scenario is not within the scope of

this research. Although the connections are typically modeled as perfect pins, all simple

shear connections have some rotational stiffness (particularly after the concrete slab has

been poured), and will experience some flexural demand during the life of the structure.

Thus, shear connections are designed with a minimum rotational ductility, so that the

rotation of the beam does not lead to rupture of the connection. This ductility is typically

provided by prescriptive guidelines on the connection geometry. In the case of

conventional (i.e. not extended) shear tabs, this ductility is assumed to be inherently

present in the bolted connection to the supported member. In the case of clip angles (and

similar connections such as endplates, or tee connections), this ductility can be provided

by bolting the angles to the supporting member. If the connection is welded to the

supporting member, short weld returns are used at the top of the connection, instead of

placing a continuous weld (AISC 2005). Either of these procedures allows the angle to

deform under negative moment, preventing rupture. Note that welding the angle in this

manner allows ductility for negative moment rotation, but does not necessarily provide

ductility for positive moment rotation (which can occur in a column loss scenario) (See

Figure 2-4).

using

suppo

contin

can b

memb

thoug

not c

gravi

over

const

resist

and t

The flexu

g the perfect

orted memb

nuously ove

be counted o

bers are som

gh most com

counted on in

ity framing i

a lost suppo

The desig

truction, wh

t all loads, a

the building

F

ural member

pin assump

bers, with

er multiple b

on to span g

metimes des

mmonly this

n the memb

is designed

rt, either thr

gn of a comp

en the concr

and during th

frame can r

igure 2-4 Ro

rs of a grav

tion, with th

a few exce

beams, will t

greater distan

signed with

is done for

ber’s load ca

as a statical

ough flexura

posite floor s

rete floor sl

he service li

rely on its c

otational Du

11

vity framed

he beams, gi

eptions. Th

take into acc

nces (Canam

negative mo

r serviceabili

arrying capa

lly determina

al or catenar

system can b

ab has not b

ife of the st

composite st

ctility of Cli

building are

irders and sla

he corrugate

count negati

m 2010). Ad

oment reinfo

ity concerns

acity (Ashcra

ate system,

ry action.

be split into

been added

tructure, onc

trength. Wh

ip Angle Con

e also typica

ab all design

ed decking,

ive moment

dditionally, t

forcement at

s to reduce c

aft 2006). O

with no abi

two main p

and the stee

ce the concr

hile the assum

nnection

ally designe

ned as simpl

if it span

capacity an

the composit

t connection

cracking, an

Otherwise, th

ility to bridg

phases: durin

el frame mu

rete has cure

med buildin

ed

ly

ns

nd

te

ns,

nd

he

ge

ng

st

ed

ng

12

loads are typically greatest during the service life of the building, the design of the

flexural members is often controlled by the construction phase of the building, when they

must support the weight of the floor system without relying on composite action. This

weight comes primarily from the concrete while it is being poured, before it has cured.

The Steel Deck Institute recommends a load of 1.6 times the weight of the concrete plus

1.4 times the construction live load (usually assumed to be 20 psf) plus 1.2 times the

weight of the steel decking (SDI 2012). In addition to strength requirements, the beams

must be stiff enough to prevent excessive deflection during pouring of the concrete, as

large beam deflections could lead to an increased weight of concrete being poured to

reach the designed deck thickness. Though there are no explicit specifications limiting

the deflection during concrete pouring, AISC Design Guide 3 recommends limiting dead

load deflections (which includes deflection during concrete pouring) to span length/360.

Modern structures are often built with beams pre-cambered upwards (or, more rarely,

shored at mid-span) to control this deflection while using lighter members (AISC 2003).

The design of the steel decking is similarly controlled by the demands during placement

of the concrete. As with the beams, this design is sometimes controlled by stiffness rather

than strength, with deflections during concrete pouring limited to span length/180 (SDI

2012).

After pouring of the concrete, the composite members must then have the

capacity to carry the building’s service loads. Though there are a variety of load cases,

the controlling case is usually 1.2 times the dead load plus 1.6 times the live load (ASCE

2010). Through the use of shear studs, the steel beams and girders act compositely with

the concrete slab, increasing their strength and stiffness. Due to this large increase, it is

common for a fully composite beam to significantly exceed the capacity demanded by the

design loads (AISC 2003). Thus, the beams and girders are often designed to be partially

13

composite, with the erectors only installing enough shear studs to mobilize a portion of

the concrete deck, usually the minimum portion needed to provide the required flexural

capacity. In some buildings, the percentage of the slab needed to achieve the required

flexural capacity is very small, and in those cases a minimum percentage of composite

action is imposed to prevent excessive slip between the concrete and steel beams. This

percentage varies between engineers, but the engineers consulted on this research

suggested a lower limit of 25%.

The concrete slab must also be designed with sufficient strength and stiffness to

distribute the floor loads to the floor beams. However, the design of the concrete slab is

typically controlled by fire codes (Ashcraft 2006). For floor systems to achieve sufficient

fire resistance (without requiring the addition of supplemental fire proofing to the deck)

a minimum thickness of concrete is needed (typically 3-1/2” above the deck flutes for

lightweight concrete and 4-1/2” above the deck flutes for normal weight concrete) (UL

2015). In most cases, this minimum thickness of concrete provides sufficient stiffness to

span typical distances allowed by the corrugated metal decking. In the case of composite

metal decking, the flexural reinforcement provided by the decking is also usually

sufficient to enable the concrete slab to carry the expected service loads on the floor

without any additional reinforcement (Canam 2010). In non-composite decking, where

the decking cannot provide reinforcement to the slab, reinforcing bars must be added to

the slab to give it the needed strength to carry the building’s service loads.

2.2 Design for Progressive Collapse

2.2.1 HISTORY OF PROGRESSIVE COLLAPSE DESIGN

An early incident that motivated the study of progressive collapse was the

collapse at Ronan Point (A tower block in England) in May 1968. An explosion in the

14

building’s gas line knocked out one of the concrete load bearing walls, leading to the

collapse of a corner of the building (Pearson and Delatte 2005). Due to the location of the

incident, much of the immediate response from the structural engineering community

happened in the United Kingdom. A report filed shortly after the collapse (Griffiths et al,

1968) found that the collapse was partially due to poor workmanship in the construction

of the building, with joints that were not properly constructed. However, the overall

design of the building (and many others in full compliance with then-current building

standards) was deemed incapable of withstanding local damage without the risk of

disproportionate collapse. In response to this report, provisions were added to the U.K.

Building Regulations that required structural members to be able to withstand a pressure

of 34 kN/m2 (4.9 psi) acting on the member (and any cladding attached to it). If the

member cannot withstand this pressure, the provisions required the structure be designed

to remain stable if that member is removed. However, the provisions give relatively little

guidance on how this design is to be carried out (Hendry 1979). The use of member

removal as a method for progressive collapse design will be explained further in section

2.2.2. Later Building Regulations also allowed for the use of horizontal and vertical ties

placed throughout the building in place of the need to design for removal of structural

members, enabling the building to resist collapse through catenary action (Khabbazan

2005). The use of tie forces and catenary action to resist collapse will be explained in

greater detail in section 2.2.2.

The development of progressive collapse provisions in the United States was

less immediate, and focused more on the performance of precast concrete structures (the

style of construction used in Ronan Point), instead of general structural performance

(Foley 2007). The U.S. approach also focused more on utilizing the robustness already

present in existing design. Initial ACI integrity provisions required continuity of column

15

reinforcement and temperature and shrinkage reinforcement in the slab to tie the structure

together, and provide a minimum level of catenary action (Popoff 1975). Later work by

Hawkins and Mitchell (1979) and Mitchell and Cook (1984) looked more closely at the

formation of catenary action in concrete slabs, and came up with continuity provisions

that form the basis of the current ACI integrity provisions. These require a minimum

portion of reinforcement in beams and slabs be continuous (or spliced to develop their

full tensile capacity) throughout the floor system, and this reinforcement must be

anchored to supports at the perimeter of the structure (ACI 2008).

Comparatively little research has been done in the U.S. on the resistance of steel

buildings to progressive collapse. It was primarily in response to the collapse of the

World Trade Center in 2001 (as well as attacks on U.S. owned buildings outside the

country in previous years) that significant provisions were created to provide integrity

requirements in steel structures, but these provisions are still limited (Geschwindner

2010). The American Society of Civil Engineers (ASCE) Standard 7-10: Minimum

Design Loads for Buildings and Other Structures includes general integrity provisions.

These provisions are primarily designed to provide a continuous load path in the

structure, requiring (among other things) all members to be connected to the rest of the

structure with connections capable of handling a lateral load equal to 5% of the vertical

load imposed on the connection. The International Building Code (2009) also provides

structural integrity provisions that require beam and girder connections to have a tensile

capacity equal to 2/3 of the connection’s required shear strength. The use of these

provisions will likely provide some robustness to steel structures, but leave out

considerations that could be relevant to the collapse resistance of steel buildings.

While integrity provisions for general steel structures are currently limited, more

developed guidelines are currently in place for many federal buildings constructed in the

16

U.S. or by U.S. interests abroad. In 2003, the General Services Administration (GSA)

published the Progressive Collapse Analysis and Design Guidelines for New Federal

Office Buildings and Major Modernization Projects (GSA 2003). These guidelines

(originally published in 2000 as a guide for designing robustness in concrete structures,

expanded to include steel in this edition) provided two methods for designing structures

to resist progressive collapse. One method was a series of exemptions, where a structure

could be considered not at risk of progressive collapse if it possessed certain structural

characteristics, primarily a high degree of connection ductility and axial strength. If it

was not exempt, the building’s response to multiple column loss scenarios would need to

be analyzed, and the performance of its components compared against failure criteria

established by the Guidelines. In 2005, the Department of Defense published the Unified

Facilities Criteria (UFC) document Design of Buildings to Resist Progressive Collapse

(UFC 2005). This document (later updated in 2009) has many similarities to the GSA

Guidelines, but also outlines other approaches to designing buildings to prevent

progressive collapse, including the use of tie forces seen in the Building Regulation and

ACI provisions. While the UFC guidelines only currently apply to certain federal

buildings, they are (in the author’s opinion) the most comprehensive set of standards in

use in the U.S. today, and they will be used as a basis for discussing current approaches

to progressive collapse design in the next section.

2.2.2 CURRENT APPROACHES TO PROGRESSIVE COLLAPSE DESIGN

In the time period immediately following the Ronan Point collapse, some

guidelines tried to address the risk of progressive collapse by subjecting the building

components to blast loads that were deemed representative of what would be seen in a

collapse scenario (Griffith et al 1968). Such provisions are still in place in the UK

17

Building Regulations. However, many engineers have raised the objection that such loads

are inherently arbitrary, as a determined attacker can almost always attack with a load

slightly more than the design load (Foley 2007). Current approaches to progressive

collapse design more commonly try to achieve general robustness with an event-

independent approach, typically designing the structure to withstand the loss of a single

key structural member (usually a column) without the collapse of a disproportionate

portion of the structure. There are two approaches commonly used to design structures to

resist collapse in the event of member removal: the indirect design approach, which

provides general robustness to the structure through ensuring high degrees of continuity

and ductility in the building components, and the direct design approach, where a full

analysis is carried out on a model of the structure with one column removed, and the

response of the structure is evaluated to determine if a disproportionate percentage of the

structure collapses.

An example of indirect design for progressive collapse is the Tie Force approach

in the UFC Guidelines. Though this section discusses the UFC guidelines, most of the

conclusions are based on Assessment and Proposed Approach for Tie Forces in Framed

and Load-bearing Wall Structures, the 2008 report by David Stevens that formed the

basis for the 2009 UFC Guidelines (Stevens 2008). This approach relies on the formation

of catenary action to allow the building to bridge over a removed column. Catenary

action (also called membrane action in the case of plane elements) is the ability of a

structural element to resist transverse loads using purely axial tension forces by

undergoing large deflections, behaving similar to an cable (see Figure 2-5). Such

displacements are too large to be permissible under service conditions, but in collapse

scenarios, large deflections can be tolerated if the structure remains stable. If large

deflections are allowed, the use of catenary action can be very beneficial, as it allows thin

eleme

larger

floor

preve

axial

system

ducti

rotati

shape

defle

These

these

span.

bays.

to a p

calcu

These

the ti

ents (such a

r than they

slab, if pro

enting collap

capacity un

m must pos

lity at the en

While it

ion capacity,

e and maxim

ction is bas

e tests will b

tests, the au

Note that du

The guideli

parabola). U

ulated for an

e assumption

e forces mus

as the floor s

would typic

operly reinf

pse of the st

nder very la

sess a high

nds of the ele

is possible

, tie force pr

mum deflec

ed on a ser

be discussed

uthors of the

ue to the rem

ines also ass

Using this ass

ny regularly

ns on displac

st be provide

Fi

slab of a bu

cally be abl

forced with

tructure. Thi

arge displace

degree of bo

ement).

to calculate

rovisions, to

ction. In the

ries of tests

d in greater

e UFC guide

moval of the

sume the for

sumed shape

framed bui

ced shape ar

ed by elemen

gure 2-5 Ten

18

uilding) to ef

le to span u

horizontal

is capacity i

ements, whi

oth strength

the needed

remain simp

e case of t

done on co

detail in sec

elines decide

column, thi

rmation of a

e, the needed

lding, using

re critical to

nts that have

nsile Catena

fficiently sp

under purely

ties, can sp

is dependent

ich means t

h and ductilit

d catenary s

ple, will typ

the UFC gu

oncrete slabs

ction 2.3.2.1

ed on a defle

is span length

a true catenar

d horizontal

g simply its

the calculati

e the ductilit

ary Action

pan large dis

y flexural ac

pan over a

t on the slab

that an effic

ty (particula

strength for

ically assum

uidelines, th

s under high

1. Based on

ection limit o

th consists of

ry shape (ro

tie forces ca

bay size an

ion of tie for

ty to achieve

stances, muc

ction. Thus,

lost column

b retaining it

cient catenar

arly rotationa

any arbitrar

me a displace

his maximum

h deflection

the results o

of 10% of th

f two framin

oughly simila

an be quickl

nd floor load

rces, and thu

e the assume

ch

a

n,

ts

ry

al

ry

ed

m

ns.

of

he

ng

ar

ly

d.

us

ed

19

shape. Concrete slabs (cast in place, composite decks, or topping slabs) that are

traditionally reinforced are assumed to have this minimum ductility. Any other element

that is intended to provide a tie force must be shown capable of carrying the tie force

while undergoing a 0.2 radian rotation.

For catenary action to function effectively, vertical and lateral restraint must be

provided at the perimeter of the affected area. In some instances, this lateral restraint can

be provided by the slab itself, through a “compression ring” mechanism, discussed

further in section 4.2. However, for certain locations of column removal, sufficient

restraint cannot be provided by the undamaged portion of the structure. If an edge column

is lost, restraint can be provided in the direction parallel to the edge by the surrounding

beams, but the tensile membrane cannot form in the direction perpendicular to the edge.

To improve the catenary capacity of the structure, a peripheral tie is also placed around

the perimeter of the structure. This peripheral tie provides limited restraint to the tensile

membrane perpendicular to the edge of the building, improving the efficiency of the tie

forces. (See Figure 2-6) In the case of column loss at the corner of the structure or

immediately next to the corner (i.e. the penultimate column), it is prohibitively difficult to

provide sufficient restraint to effectively support the catenary action of the slab. Thus,

design for tie forces typically also involves Enhanced Local Resistance, strengthening the

corner and penultimate columns, and designing them for ductile failures.

altern

remo

this a

speci

The

colum

guide

allow

ampl

non-l

of the

force

behav

the st

Fig

The other

nate path app

ved, and red

approach has

ific guideline

UFC guide

mns must be

elines are sim

w for the a

ification fac

linear effects

e structural e

-controlled

viors) specif

tructure can

ure 2-6 Cate

r approach t

proach, anal

designing an

s been ackno

es on how t

elines provid

e removed an

milar to the

analysis of

ctors applied

s, a non-line

elements are

behaviors)

fied by the g

withstand th

enary Action

to progressiv

lyzing the re

ny componen

owledged as

this analysis

de specific

nd the analy

procedure c

the structu

d to forces

ear static mo

e then compa

or rotation

guidelines. A

he loss of the

n of Edge Pa

20

ve collapse

esponse of th

nts that are

s a method o

should be c

procedures

ysis of the st

created in th

ures with a

and displac

odel, or non-

ared to their

limits (in

Any compone

e column wit

anel Enhance

design in th

the structure

overloaded

of creating r

carried out a

and accept

tructure after

he GSA guid

an elastic

ements to a

-linear dynam

load-carryin

the case o

ents that fail

thout ruptur

ed by Periph

he UFC Guid

e if one of th

in that scen

robustness fo

are compara

tance criteri

r member re

delines). The

model, wit

account for

mic model.

ng capacity (

f deformati

l must be red

re of its elem

heral Tie (Ste

delines is th

he columns

nario. Thoug

or some time

atively recen

ia for whic

emoval (thes

ese guideline

th prescribe

dynamic an

The respons

(in the case o

on-controlle

designed unt

ments.

evens 2008)

he

is

gh

e,

nt.

ch

se

es

ed

nd

se

of

ed

til

21

2.2.3 BEHAVIOR OF GRAVITY FRAMING UNDER COLUMN LOSS

The typical design approach to gravity framing results in a building with limited

redundancy against the loss of a support. The connections are assumed to have no

flexural strength, and thus a lost column would result in the formation of a mechanism in

the beam. Although the connections do have some axial capacity, the rotational capacity

of the connections is believed to be relatively limited, and thus not able to deflect enough

to provide meaningful catenary support. The composite decking used to support the

concrete during casting also has significant axial capacity, but the continuity of the

decking (primarily its ability to carry axial load over seams in the deck) and the rotational

capacity of the deck have not been sufficiently investigated to be relied on in design

(Stevens 2008). Despite these limitations, there is some inherent robustness in gravity

framed steel structures. However, the experimental data on this robustness is limited.

Further research is needed to better understand the response of these elements under a

column loss scenario, so the collapse performance of gravity framed steel building can be

better understood.

2.3 Previous Research

Few researchers have looked at the total system response of steel framed

composite buildings under column loss scenarios. However, there has been testing done

on many of the components of such buildings under conditions similar to those in a

building experiencing a column loss. A summary of many of these tests, and how their

findings may impact such a structure’s robustness, is presented below.

22

2.3.1 CONNECTION BEHAVIOR

2.3.1.1 Shear Tabs

There has been limited experimental testing done on the behavior of shear tabs

under progressive collapse scenarios. Shear tabs are usually assumed to be too brittle to

add to a building’s robustness. The UFC guidelines specify a maximum rotation of

approximately 0.05 radians for shear tabs that are expected to contribute to a buildings

collapse resistance, significantly less than the .2 radians assumed for catenary action.

Despite their limited rotation capacity, neglecting their contribution to a building’s

collapse response may be an overly conservative assumption.

Testing done by Thompson (2009) at the Milwaukee School of Engineering

simulated the response of shear tabs in a column loss scenario. Beams were attached to

opposite sides of a central column by shear tabs of various depths, and pinned at their

opposite end. The column was then pulled down, to induce the displacements present

after column loss, and the load-deflection responses of the connections were recorded

(See Figure 2-7). These tests showed that shear tabs could develop flexural and catenary

capacity in a highly displaced floor system, but that these capacities are limited. Using

this research’s prototype building (discussed in section 3.2) as a typical building, the

expected flexural and axial demands using the UFC alternate path and tie force

provisions, respectively, are greater than any of the observed capacities. Additionally,

the connections exhibited limited flexural ductility, with moment capacities typically

reaching their peak at rotations of approximately .07 radians, and quickly dropping off at

higher rotations. This limited ductility means the flexural capacity likely cannot work in

conjunction with the catenary capacity of the system, as the connections only exhibited

significant axial load after the flexural capacity began to drop off. The shear tabs’ axial

response exhibited higher rotational capacity, supporting large tensile loads until its

failur

withs

ducti

to the

depth

signif

failin

rotati

The d

more

incre

streng

of lar

loss s

re due to bo

stand a colum

le enough to

e building’s

The tests

hs on the c

ficant effect

ng at lower f

ions of 0.13

deeper conne

bolts. The

ased connec

gth or ductil

rger, stronge

scenario.

Figu

olt tear-out i

mn loss scen

o contribute

robustness.

done by Th

onnections’

t on the beh

final rotation

radians, dro

ections also

flexural cap

ction depth,

lity to contri

er shear tabs

re 2-7 Shear

n the shear

nario on its

to the floor

hompson als

behavior. T

havior, with

ns. The shall

opping off to

exhibited lit

pacity of the

but, as state

ibute signific

s may actual

r Tab Colum

23

tab. While

own, the sh

system’s me

so examined

This varying

h deeper con

lowest conne

o 0.9 radians

ttle gain in a

e connection

ed earlier, th

cantly to the

lly lead to a

mn Loss Test

this capacity

hear tab’s ca

embrane act

d the effect

g depth of

nnections th

ection (with

s for the deep

axial capacit

n did show s

his capacity

e building’s

a reduced ab

Setup (Thom

y is likely n

atenary behav

tion, and cou

of different

connections

hat have mo

h three bolt r

per five bolt

ty despite th

significant in

likely does

robustness.

bility to surv

mpson 2009

not enough t

vior could b

uld contribut

t connection

s did have

ore bolt row

rows) reache

t connection

he presence o

ncreases wit

not have th

Thus, the us

vive a colum

9)

to

be

te

 

ns

a

ws

ed

ns.

of

th

he

se

mn

24

Though the use of deeper shear tabs may not improve a building’s robustness, it

may be possible to increase the collapse performance of shear tabs through other

methods. In particular, the shear tabs tested all failed through tear-out of the shear tab,

where the shear tab did not have enough horizontal edge distance to fully develop the

bolt’s bearing capacity. By slightly extending the shear tab, its ability to support tension

along its axis could be greatly improved, significantly raising its catenary contribution,

with negligible increase in construction cost. This could also change the failure mode

however, causing the connections to fail via bolt fracture, resulting in a more brittle

failure that cannot work compositely with the rest of the system. Shear tab performance

could also be improved through the use of slotted holes, or other methods not yet

considered. While looking at all of these parameters is beyond the scope of the project,

there is potential for the use of different details in future tests.

An important facet when considering the contribution of shear tabs to the

behavior of a floor system is their location in typical floor systems. While typical practice

varies from designer to designer, shear tabs are more commonly used in beam-to-girder

connections, and less frequently used to connect flexural members to columns (Waggoner

2012). This means that in a column loss scenario, shear tabs are typically located away

from the point of greatest deflection, and are subsequently called upon to undergo less

rotation than the column connections, which may enable them to continue contributing

capacity through catenary action even if the floor system undergoes a greater total

rotation (See Figure 2-8)

2.3.1

collap

the c

respo

Alter

conne

the fl

comp

Xiao

mom

conne

ends

did n

but s

perfo

.2 Compos

Another v

pse scenario

concrete slab

onse of the

rnatively, by

ection more

loor’s system

To the au

posite shear

et al (199

ments. Two

ections, and

of the beam

not include th

still reveal

ormance.

site Effects

very importa

os is the effe

b above the

e shear tab

y stiffening

brittle, caus

ms strength u

uthor’s know

tab connect

4) studied

cantilever b

d a composit

ms were then

he effect of c

some insig

Figure 2-8

on Shear T

ant compone

ct of compo

e connection

b, by addin

g the conne

sing it to fai

under collaps

wledge, there

tions under

the respons

beams were

te concrete

loaded dow

catenary forc

ghts into th

Reduced Ro

25

abs

ent of the re

osite behavio

n has the po

ng strength

ection, the

l at a lower

se scenarios

e has been l

progressive

se of compo

e framed in

slab was ca

nward until

ces, or exam

he effect o

otation Dem

esponse of s

or on the con

otential to s

and stiffn

composite

rotation, red

.

limited expe

e collapse co

osite shear

nto a centra

ast over the

failure of th

mine the resp

of composite

mand on Shea

shear tabs to

nnection. Th

significantly

ness to the

action coul

ducing its co

erimental tes

onditions. T

connections

al column b

beams. The

he connection

ponse to posi

e action on

ar Tabs

o progressiv

he presence o

improve th

e connection

ld make th

ontribution t

sting done o

Tests done b

s to hoggin

by shear ta

e cantilevere

n. These test

itive momen

n connectio

 

ve

of

he

n.

he

to

on

by

ng

ab

ed

ts

nt,

on

impro

streng

brittle

Signi

reinfo

rotati

to ac

desig

perfo

to ser

the c

large

Astan

The prese

oved the sti

gth of the c

e behavior,

ificant impr

orcement to

ions several

chieve this i

gners to con

ormance wer

rve as addit

onnections w

st rotation c

neh-Asl (200

Figure 2-9

ence of a ty

ffness of th

connections.

failing at

rovements i

o the concr

times larger

improvemen

ntrol crackin

re achieved b

ional reinfor

was still no

capacity rec

00) on the pe

Composite S

ypical comp

he tested con

Additionall

.026 radian

n connectio

rete slab, w

r than that of

nt is minima

ng (Ashcraf

by orienting

rcement. De

oticeably sho

corded was

erformance o

Shear Tabs u

26

posite slab (

nnections, bu

ly, the conn

ns due to fr

on behavior

with such c

f the unmod

al, and is so

ft 2006). Si

the decking

espite this im

ort of the .2

.08 radians)

of composite

under Hoggi

(with only s

ut did not s

nection with

fracture of t

r were achi

connections

dified slab. T

ometimes in

imilar impr

g ribs paralle

mprovement

2 radians ass

). Tests wer

e shear tabs

ng Moment

shrinkage re

significantly

h a typical s

the reinforc

ieved by ad

reaching m

The reinforce

ncluded in fl

rovements in

el to the beam

t, the rotatio

sumed for ti

re also done

under cyclic

(Xiao et al 1

einforcemen

y improve th

slab exhibite

cement mesh

dding furthe

moments an

ement neede

floor slabs b

n connectio

m, allowing

on capacity o

ie forces (th

e by Liu an

c loads whic

1994)

nt)

he

ed

h.

er

nd

ed

by

on

it

of

he

nd

ch

studie

tests

respo

on a

centr

of th

beam

allow

to th

appli

the ro

and r

tabs e

and c

capac

Fi

ed moment

also did not

onse of conn

series of bea

al column w

e beam. Th

m size, and pr

wed the speci

e column, i

ed cyclically

otation reach

rotation in th

The conn

exceeding .1

crushing of

city decrease

igure 2-10 C

and rotation

include the

ections to bo

am “strips”,

with shear ta

e parameter

resence and

imen to have

inducing rot

y, with gradu

hed .15 radia

he connection

nections exhi

1 radians of r

f the concre

ed as the con

Composite Sh

n capacity o

axial forces

oth positive

consisting o

abs, with an

rs investigate

reinforceme

e a gravity l

tations in th

ually increas

ans (the max

ns was moni

ibited signif

rotational ca

ete around t

nnection dep

hear Tabs un

27

of these conn

s present in a

and negative

of two floor b

8 foot wide

ed by the te

ent of concre

load imposed

he shear tab

sing displace

ximum perm

itored throug

ficant rotatio

apacity befor

the column.

pth increase

nder Cyclic L2000)

nections und

a collapse sc

e moments.

beams attach

e composite

esting includ

ete. The test

d on it while

b connection

ements, unti

mitted by the

ghout testing

on capacity,

re failing via

As in prev

d, but there

Load Test Se

der high rot

cenario, but

The tests we

hed to oppos

concrete sla

ded depth o

t frame (See

e lateral drif

ns. This late

il the connec

e test setup).

g.

with all com

a fracture in

vious tests,

are not eno

etup (Liu an

tations. Thes

did study th

ere conducte

site sides of

ab cast on to

of connection

e Figure 2-10

ft was applie

eral drift wa

ction failed o

The momen

mposite shea

the shear tab

this rotatio

ough points t

nd Astaneh

se

he

ed

f a

op

n,

0)

ed

as

or

nt

ar

b,

on

to

estim

incre

studie

shear

mom

prese

enoug

capac

the a

under

Howe

conne

durin

flexu

the s

reduc

than

mate the prec

ase in rotati

ed exhibited

r tabs studie

ment (see Err

ent in the do

gh to suppo

city of the bu

Whether

available dat

r small rotat

ever, this w

ections only

ng a monoton

ural capacity

ystem (due

cing its ducti

the Thomp

Table

ise nature of

ion capacity

d significant

ed, this capa

ror! Referen

ouble span s

rt the floor

uilding if it c

or not these

ta though. T

tions, with th

weakening ef

y reached h

nic loading s

would unde

to catenary

ility. It is us

pson test (w

e 2-1 Mome

f this relation

over the te

moment cap

acity was be

nce source

cenario crea

loads by its

can act in tan

e mechanism

The connect

he moment

ffect could b

high rotation

scenario (su

ergo less deg

y forces) cou

seful to note

which includ

nt-Rotation

28

nship. It is n

sts done by

pacity under

etween 36 a

not found.)

ated by a los

self, but cou

ndem with th

ms can work

tions exhibit

capacity dro

be due to th

ns after bein

ch as would

gradation. C

uld damage

that these te

ded axial e

Parameters o

not clear at th

Xiao. Addi

the high rot

and 45 perce

. Due to the

st column, t

uld provide a

he building’

k together is

ted much h

opping off a

he cyclic na

ng repeatedl

d be seen in

Conversely, t

e some elem

ests showed

effects), thou

of Composit

his point wh

itionally, the

tations. For t

ent of the b

e very high f

this capacity

a significant

s catenary re

difficult to

higher mome

as the rotatio

ature of the

ly loaded. I

a column lo

the presence

ments in the

d greater flex

ugh the rea

te Shear Tab

hat caused th

e connection

the composit

eam’s plasti

flexural load

y is likely no

t boost to th

esponse.

discern from

ent capacitie

ons increased

e tests, as th

It is possibl

oss event), th

of tension i

connection

xural ductilit

ason for th

bs

is

ns

te

ic

ds

ot

he

m

es

d.

he

le

he

in

ns,

ty

is

29

difference is not clear. Thus, the true ductility of composite shear tabs in column loss

scenarios is difficult to predict at this point.

Also of note, the reduction in moment capacity at high rotations was much higher

in instances where the beam connected to the column’s web, rather than to the column’s

flanges. When connected to the column web, the concrete is forced to primarily react

against only the edge of the column flanges, reducing the available bearing area. This

could cause it to crack earlier, leading to the reduction in moment capacity. Conversely,

when oriented so the concrete could bear against the full column flange, the reduction in

moment capacity was much lower, losing approximately 25% of their max capacity, as

opposed to the 50% reduction seen in the other orientation. If the shear tabs are used to

connect flexural members to girders (as it is in our prototype building) the concrete slab

would be continuous between the connections. This would likely provide sufficient

bearing area to exhibit this favorable behavior. Alternatively, the loss in capacity could

be an artifact of the different maximum rotations. The shear tab connections used in the

column web connections in this test had shorter connection depths than those in the

flange connections, and thus reached a larger rotation before failing. This increased

rotation could account for the higher reduction in moment capacity. Thus, although these

connections have the potential to increase a structure’s robustness, there are still many

questions that need to be answered before their capacity can be counted on by practicing

engineers.

2.3.1.3 Clip Angles

Like shear tabs, clip angles are often assumed to have insufficient strength and

stiffness to contribute more than shear resistance to most steel framed structures. Thus,

their performance under collapse conditions has undergone limited testing. Work done by

Astan

angle

doub

was t

conne

tear o

that f

speci

longe

speci

great

the pl

deter

F

neh et al (19

e connection

le angle con

then rotated

ection or the

The conne

out, or failur

failed via bol

imens that fa

er common i

imens conne

er strength a

lastic mome

ioration in c

Figure 2-11

989) at the U

ns under cycl

nnection wel

d through cy

e test maxim

ections exhib

e of the angl

lt tearing exh

ailed via bolt

n modern co

cted with A3

and ductility

nt of the atta

apacity up to

Clip Angles

University o

lic loading.

lded to the

ycles of unif

mum of .06 ra

bited two m

les by fractu

hibited limit

t tear-out we

onstruction p

325 bolts all

. The conne

ached beam,

o their failur

s under Cycl

30

of Berkeley l

Different be

beam web a

formly incre

adians.

ajor failure m

ure at points

ted ductility,

ere connecte

practice). Th

l failed throu

ections achie

, and maintai

res at rotatio

ic Load Test

looked at th

eams were a

and bolted t

easing rotati

modes: failu

of high yield

, but it is imp

d with ribbe

he specimens

ugh angle fra

eved between

ined that lev

ons of approx

t Setup (Ast

he performan

attached to a

to the colum

ions, up to f

ure of the bol

ding. The co

portant to no

ed bolts (a fa

s with thinne

acture after e

n 10 and 20

vel with min

ximately .05

taneh-Asl et

nce of doubl

a column by

mn. The beam

failure of th

lts via thread

onnections

ote that all

astener no

er angles and

exhibiting

percent of

imal

5 radians

al 1989)

le

a

m

he

d

d

(see)

high

conne

tighte

typic

highe

welde

tests,

eccen

incre

result

angle

that

conne

F

. While this

load, and fat

ections were

ened, which

al gravity fra

er rotation ca

Similar re

ed-bolted do

with a can

ntric actuato

asing displa

ted in a brit

e yielding th

failure of t

ection, impr

Figure 2-12 M

rotation cap

tigue likely c

e all pre-tens

can improve

aming in a m

apacities, an

esults were o

ouble angle c

ntilever beam

r first throug

acement step

ttle connecti

he connectio

the angle c

roving duct

Moment Rot

acity is limit

contributed t

sioned, while

e their rotati

monotonic lo

d contribute

obtained from

connections

m attached t

gh a series o

ps. The tes

ion failure a

on exhibited

could be fo

tility with m

tation Hyster

31

ted, the failu

to their failu

e typical gra

on capacity

oading scena

meaningful

m cyclic test

. A similar t

to a fixed c

of increasing

sts again sh

at low rotati

higher duct

orced by in

minimal de

resis of Clip

ures occurred

ure. Also of n

avity framed

(Fleischman

ario (like col

lly to a build

ts done by A

test setup wa

column and

g load steps,

howed that

ion, but if t

tility. The te

creasing the

ecrease in u

p Angle (Ast

d after sever

note is that t

connections

n et al 1991)

lumn loss), c

ding’s robust

Abolmaali et

as used as in

then loade

, then throug

failure via

the connecti

est program

e column g

ultimate stre

taneh-Asl et

ral cycles of

the tested

s are snug-

). Thus,

could exhibit

tness.

t al (2003) o

n the Astane

d through a

gh a series o

bolt fractur

ion failed vi

also showe

gauge of th

ength of th

al 1989)

t

on

eh

an

of

re

ia

ed

he

he

32

connection. As before, despite the connections exhibiting significant strength and

ductility, these values might not be sufficient to withstand a column loss scenario. The

ultimate moment capacity of the connections was approximately 10 to 15 percent of the

demand that would be seen on such a connection in a column loss event (based on the

floor loads and spans in our prototype building). The connections also failed at rotations

less than .04 radians, although it should be noted that failure was defined as the point

when further cycles did not result in an increase in connection moment, not a complete

loss in connection capacity. This rotation at maximum moment is consistent with the

rotation at maximum moment seen in the shear tab tests mentioned previously, which

exhibited significantly more rotational capacity before failure. It is possible that the clip

angles could continue to carry load under much higher rotations and exhibit more

ductility in a true collapse scenario.

While these results tell us a great deal, it is difficult to compare these findings

directly to those present in a progressive collapse scenario. First, the tests were done on

the cyclic response of the connections. Since the angles yielded several times before

fracture occurred, it is likely fatigue played a significant role in the final failure point of

the connections, and an angle subjected to the monotonic load present in column loss

scenarios could exhibit significantly more rotation capacity. Conversely, the testing done

does not include the tensile forces that would be imposed on the connection by the

membrane action of the deflected system. The addition of that tensile force could place

more stress on the connection leading to it fracturing at an earlier point.

Unfortunately, this is only one of the many unknowns encountered when studying

the response of double angles under collapse conditions. In particular, the presence of a

concrete slab above the clip angle connection will likely provide a significant increase in

moment capacity. Whether this moment capacity is retained at high enough rotations to

33

contribute significantly to the building’s collapse response, and whether the slab has a

significant effect on the ductility of the connections response are both unknown, as they

have never been empirically tested to the author’s knowledge. Likewise, the effect of

catenary forces on the connection could also play a large role in the connection’s

behavior, but has not been experimentally investigated.

2.3.1.4 Composite Effects on Clip Angles

Leon (1990) examined the rotational strength and stiffness of various composite

shear connections under cyclic loads. While most of these tests focused on different types

of seat angle configurations, one test on clip angle behavior was conducted. Due to the

limited size of the test matrix, it is difficult to draw many conclusions from this series of

tests, but the results can be compared with non-composite clip angles tested by Astaneh-

Asl and Abolmaali. The presence of a composite slab seems to significantly increase the

moment capacity of the connection, achieving up to twice the moment capacity of

similarly sized bare steel connections, with similar increases in stiffness. While this

increased capacity is likely not enough to support the significant increase in flexural

demand in a typical column loss scenario, it does possess the potential to contribute

significantly to the building’s robustness if it can act in concert with the rest of the floor

system. Unfortunately, the rotational ductility of composite clip angles is still unknown,

as the tests done by Leon were stopped at 0.3 radians, while the connections appeared to

have some residual capacity. It is also important to note the connections tested by Leon

were very heavy clip angles, with a heavily reinforced slab. Whether their high moment

capacity is present in lighter connections, with less reinforced slabs is still unanswered.

34

2.3.2 FLOOR SYSTEMS

2.3.2.1 Membrane Theory

It had long been observed that concrete floor slabs loaded to collapse can exhibit

significantly higher capacities than those predicted by flexural theory (Park 1964). As

floor slabs are loaded, the shape created by their deflection tends to push the bottom

edges of the slab outward. In slabs with ends restrained against lateral movement, this

outward movement will create a compressive arch in the slab, adding to its load carrying

capacity through compressive membrane action (See Figure 2-13). If the slab is loaded

even further, the slab can snap through to a tensile membrane, where the deflection

becomes large enough that it pulls the edges of the slab inward (See Figure 2-14). If the

detailing of the slab is sufficient to provide high ductility, this tension membrane capacity

can significantly exceed the capacity predicted by flexural theory.

restra

affect

(1965

latera

memb

will b

the p

memb

The load

aint, which

ted area is

5), Brotchie

al restraint s

brane action

be pulled inw

erimeter of t

brane forces

Figu

Figur

carrying ca

may not be

near the b

and Holley

still had the

n. If the slab

ward by the

the structure

s, allowing th

ure 2-13 Com

re 2-14 Tens

apacities pre

e present in

building’s pe

y (1971), an

potential to

bs are vertic

deflection at

e. This comp

he slab to fu

mpressive M

sile Membra

35

edicted by m

n a gravity

erimeter). H

nd others sh

o carry signi

cally suppor

t the middle

pression ring

unction as a s

Membrane Ac

ne Action in

membrane th

framed buil

However, te

howed that

ificantly gre

rted along th

e of the slab,

g can resist t

self-equilibra

ction in Con

n Highly Def

heory assum

lding (partic

esting done

slabs with l

eater loads d

heir perimet

inducing co

the tension c

ating system

ncrete Slabs

flected Slabs

me full latera

cularly if th

by Sawczu

limited or n

due to tensil

ter, the edge

ompression i

created by th

m.

s

al

he

uk

no

le

es

in

he

fully

testin

loade

series

was p

aroun

partia

unres

the e

highe

such

restra

and s

Testing d

restrained s

ng was cond

ed via hydra

s of slabs th

provided to

nd the slab,

ally restrain

strained slab

nds. For sla

er initial stre

as would b

aint decrease

stiffness und

one by Brot

slabs, partia

ducted on 1

aulic pressur

hrough a clam

one series o

which also

ned slab wa

bs were simp

abs with a sp

ength and sti

e present in

es, up to the

der tensile m

Figure 2-1

chie and Ho

lly restraine

5” square s

re. Full later

mping force

of slabs by t

allowed the

as placed o

ply placed on

pan to depth

iffness. How

n the slabs o

point where

embrane act

5 Compressi

36

olley (1971)

ed slabs and

slabs of vary

ral and rota

e around the

the placeme

e monitoring

on rollers to

n the rollers

h ratio of 10

wever, for sla

of composite

e the unrestra

tion if suffic

ion Ring (Ja

compared th

d slabs with

ying depth

ational restra

e edges. Com

ent of load c

g of the resu

o allow rot

, with no lat

0 or lower,

abs with a h

e buildings,

ained slab ca

ciently reinfo

ahromi et al 2

he membran

no lateral r

and reinfor

aint was pro

mpressive la

cells at frequ

ultant archin

tation at th

teral restrain

the restraine

higher span t

the enhanc

an exhibit hi

orced. The re

2012)

ne response o

restraint. Th

cement ratio

ovided to on

ateral restrain

uent interva

ng force. Th

he ends. Th

nt provided a

ed slabs hav

to depth ratio

ement due t

igher strengt

eason for th

of

he

o,

ne

nt

ls

he

he

at

ve

o,

to

th

is

is no

cause

flexu

and c

due t

the p

no fo

fully

slab s

likely

loadin

F

ot definitivel

es them to re

ural action le

causes earlier

However,

o tensile me

artially restr

orce in the re

self-equilib

should have

y some mat

ng, which i

Figure 2-16 L

ly known, b

esist loads th

eads to a loc

r cracking.

, in the case

embrane acti

rained slabs

estraints at th

brating syste

e been effect

terial degrad

impaired its

Load Deflectw

but it is like

hrough a com

cal concentra

e of lightly

on was not s

(which did

he time of te

em. Thus, th

tively identic

dation occur

ability to c

tion Relationwith Span to

37

ely the restra

mbination of

ation of tens

reinforced u

seen. The rea

exhibit sign

ensile memb

he unrestrain

cal once ten

rred in the

carry catena

nship for Reo Depth Rati

aint provide

f flexural an

sile strain at

unrestrained

ason for this

nificant tensi

brane action

ned slab and

nsile membra

unrestrained

ary forces. T

estrained andio of 20

ed to the res

nd membrane

t points of h

d slabs, the

s is difficult

ile membran

, implying th

d the partia

ane action o

d slab durin

Thus, while

d Unrestraine

strained slab

e action. Th

high momen

enhancemen

to discern, a

ne action) ha

he slab was

lly restraine

occurred. It

ng the initia

unrestraine

ed Slabs

bs

is

nt,

nt

as

ad

a

ed

is

al

ed

38

slabs have the potential to carry significant load through catenary action, it is likely the

system will need significant ductility to achieve that capacity.

The enhancement due to the presence of tensile membrane effects is dependent on

a variety of factors besides lateral restraint, including the orthotropic nature of the slab,

strength and ductility of reinforcement, and span to depth ratio of the slab. Many of these

factors have not been heavily investigated at the scale typical in composite floor slabs.

For instance, in a column loss scenario, the composite floor slab in our prototype building

would have a span to depth ratio of approximately 55, significantly higher than what has

been tested. Since the ability of a slab to carry a given load under tensile action is

significantly less dependent on its span length than under flexural action, these very long

span slabs have the potential to show even greater benefit from the presence of membrane

action. Conversely, the shape of the steel decking that constitutes most of a slab’s

reinforcement (if composite decking is used) could lead to very orthotropic behavior,

which could lead to diminished effectiveness of membrane action. Tests by Hayes and

Taylor (1969) studied the effect of different reinforcement distribution on the

enhancement gained from membrane action. The testing indicated that increasing

orthotropy resulted in lower effectiveness of membrane action (See Table 2-2). While

this does suggest a diminished ability of composite slabs to carry membrane forces, there

was still noticeable enhancement from membrane action. Additionally, the orthotropic

nature of the floor slab may be less significant than the decking’s shape would indicate.

The presence of the concrete slab and the secondary beams may serve to stiffen the deck

along its weak axis enough to cause the floor to behave almost isotropically, enabling it

to receive the full enhancement from in plane forces, and help it survive a collapse

scenario.

2.3.2

been

place

corru

to de

loss

analy

condu

under

respo

is sig

to cre

studie

collap

studie

floor

.2 Analyti

The abilit

used by de

ement of rein

ugated deckin

evelop tensil

scenario (S

ytically. Yu

ucted very

r column lo

onse of such

gnificant robu

eate a tensile

es looked at

pse loads st

es’ authors a

load.

Table 2-2

cal Studies

ty of floor sy

esigners, but

nforcing ste

ng already i

e membrane

Stevens 200

et al (2010)

detailed fin

oss scenario

systems to

ustness in su

e membrane

suggested t

tatically. On

all conclude

2 Enhancem

of Membra

ystems to sp

t to date it

el in the con

in place in c

e action, wh

08). A varie

), Sadek et a

nite element

os. These an

collapse con

uch structure

e spanning ov

that this robu

nce amplific

ed the analyz

ent from TenRei

39

ane Action in

pan large dis

has been d

ncrete slab.

composite fl

hich could al

ety of resea

al (2010), A

analyses o

nalyses rev

nditions. In p

es, due prima

ver the affec

ustness is su

cation for dy

zed structure

nsile Membrinforcement

n Composit

stances throu

done almost

Many engin

loor systems

llow the sys

archers hav

Alashker et a

f steel fram

eal many im

particular, th

arily to the a

cted area. H

ufficient at m

ynamic effe

es were una

rane Action

te Floor Sys

ugh membra

exclusively

neers have n

s has signific

stem to surv

ve studied t

al (2010) and

med compos

mportant as

hese studies

ability of the

owever, all

most to carry

cts is accou

able to carry

with Orthot

stems

ane action ha

y through th

noted that th

cant potentia

vive a colum

this potentia

d others hav

site structure

spects of th

suggest ther

e floor system

the analytica

y the resultan

unted for, th

y the resultan

tropic

as

he

he

al

mn

al

ve

es

he

re

m

al

nt

he

nt

40

The true significance of these findings is hard to determine at this stage, as there

is little experimental data to validate the models created by the various researchers. In

particular, the researchers all make several assumptions about the response of the steel

decking, and the accuracy of these assumptions is unknown. The decking is modeled

without any discontinuities taken into account, which could significantly reduce its ability

to carry tensile membrane forces. Additionally, slip between the decking is either

prevented or modeled with a simple friction coefficient. While it is difficult to say

whether these assumptions produce significant error in the final results, the likely effect is

an unconservative result. Thus, while steel framed buildings may have significant

redundancy, the analysis done suggests that this is not enough for such structures to

survive a collapse scenario without additional reinforcement.

The researchers also conducted various parametric studies to examine which

aspects of the floor system were most significant to the structural response, and the most

effective areas to add further structural robustness. The results of those parametric studies

were highly dependent on the nature of loading imposed on the system. Studies done with

load applied at the location of column loss were primarily dependent on the strength of

the flexural connections, as the failure of those connections resulted in the failure of the

system. Connections with more bolts (Alashker et al 2010) or more rigid elements (Yu et

al 2010) all experienced significant increases in strength and slight increases in ductility.

Slabs with additional reinforcement placed near the lost column also exhibited improved

performance (Yu et al 2010). However, in floor systems loaded through a distributed

floor load, the floor system was more sensitive to the strength of the steel decking, with a

doubling of deck thickness resulting in a 40% increase in maximum strength (See Figure

2-17). As this loading is more consistent with what would be expected in a collapse

scenario, it is likely the decking that is the most significant factor in the performance of

real s

still

conne

displa

2010

work

structures. It

sensitive to

ections exhi

acements aft

). This sugg

king together

Figure 2-17

is importan

o the nature

ibited notice

ter the conne

gests that the

r, and none o

7 ParametricR

nt to note how

e of the fle

eable increas

ections had u

e full strengt

of their contr

Study of DeRobustness (A

41

wever, that t

exural conn

ses in streng

undergone si

th of the sys

ributions sho

eck ThickneAlashker et a

the response

nections. Flo

gth, (See Fi

ignificant de

stem is a res

ould be negle

ess Effect onal 2010)

e under distr

oor systems

igure 2-18)

egradation (A

ult of all the

ected.

n Composite

ibuted load

s with large

even at larg

Alashker et a

e component

Floor

is

er

ge

al

ts

2.3.2

one o

based

assum

streng

behav

inves

scena

in roo

plates

One

little

mann

.3 Experim

While the

of the most

d on several

mptions is c

gth and duc

vior of the c

stigated, as th

ario. Work d

of decking u

s and subjec

of the most

load and in

ner, able to c

Figure 2-1

mental Testi

e analytical s

significant c

assumption

currently un

ctility of cor

connections

hose connec

done by Roge

under cyclic

cted to mon

commonly

n a very br

continue hol

18 ParametriR

ing on Deck

studies previ

components

ns about deck

nknown. To

rrugated dec

used to atta

ctions are no

ers and Trem

loading. 20

notonic loads

used deckin

rittle manner

ding load at

ic Study of CRobustness (A

42

k Performan

iously discu

of a floor’s

k behavior.

date, there

cking placed

ach decking

ot expected t

mblay (2003

and 22 gage

s, as well as

ng connectio

r. Self-drilli

t the maximu

Connection SAlashker et a

nce

ussed sugges

collapse re

Unfortunate

has been v

d under axia

sheets toget

to carry any

) studied the

e sheet deck

s cyclic load

ons, puddle

ing screws

um displacem

Strength on Cal 2010)

st that the ste

sponse, thos

ely, the accu

very little te

al load. In p

ther has not

load in a gr

e response o

king was atta

ds of a set d

welds, faile

failed in a

ment impos

Composite F

eel decking

se models ar

uracy of thos

esting on th

particular, th

been heavil

ravity loadin

of connection

ached to stee

displacemen

ed under ver

more ductil

ed by the te

Floor

is

re

se

he

he

ly

ng

ns

el

nt.

ry

le

st

(5 m

conne

load

that d

as th

despi

conne

neede

fasten

signif

decki

memb

of co

direct

conne

Fi

mm), but also

ections, whi

at the full 5

displacemen

ere is usuall

ite the pres

ections, in a

ed to develo

ner at each lo

These tes

ficant tensil

ing. Howev

brane forces

oncrete on to

tly to the te

ections. In a

igure 2-19 D

o failed at v

ch showed a

5mm displac

t. However,

ly no cause

sence of re

all cases, the

p the deck’s

ow flute of t

sts suggest

le membran

ver, there ar

s in a collaps

op of the de

ensile capaci

almost all tes

Deck Fastene

very low lo

a comparativ

cement impo

weld-with-w

for stronger

easonable d

e connection

s full capacit

the decking (

that it may

e action if

re a variety

se scenario.

ecking. Whil

ity of the sy

sts, the deck

ers under Cy

43

oads. Tests

vely high lev

osed by the

washer conn

r connection

ductility in

s exhibited

ty using stan

(Ashcraft 20

y not be po

that tension

y of factors

The most si

le it is unlik

ystem, it cou

king connect

yclic Load Te2003)

were also r

vel of load a

test, despite

nections are

ns in compo

the screws

capacities si

ndard fastene

006).

ossible for

n has to bri

s that could

gnificant fac

kely that the

uld improve

tions failed b

est Setup (R

run on weld

and were also

e undergoing

rare in com

osite decks.

s and weld

ignificantly

er spacings,

the decking

idge over a

d help the

ctor is likely

e concrete c

e the perform

by tearing o

Rogers and T

d-with-washe

o able to hol

g softening a

mposite deck

Additionally

d-with-washe

less than tha

typically on

g to underg

seam in th

deck suppo

y the presenc

can contribut

mance of th

of the deckin

Tremblay

er

ld

at

ks,

y,

er

at

ne

go

he

ort

ce

te

he

ng

44

around the fastener. The concrete deck could reinforce this connection by requiring the

fastener to also crush the concrete around it. Additionally the slab reinforcement, while

very small, can help to transfer tension forces across the seam of the decking. Finally, the

shear studs used to attach the concrete to the beam are also attached to the decking, and

could help attach the decking sheets together. The strength and ductility of this

connection is something that, to the author’s knowledge, has never been tested. Whether

any or all of these effects is enough to allow the decking to achieve significant membrane

action is still unknown.

Full scale testing on the ability of decking to form a tensile membrane in a

column loss scenario has so far been limited. Researchers at the University of California

at Berkeley (Astaneh-Asl et al 2002) built a 60-ft. by 20-ft. steel structure with composite

floors and subjected it to a column loss scenario. The support at one column was

removed, and then additional load was applied to the slab through actuators at the

location of the removed column. (See Figure 2-20) The floor system was able to support

a maximum of 62.8 kips of static load. While it is difficult to exactly predict the uniform

load corresponding to this point load, the researchers calculated it as approximately 300

pounds per square foot of distributed load. Even accounting for dynamic effects, this

implies that typical composite construction can support a column loss scenario without

the need for additional reinforcing.

conne

throu

the re

test, s

obser

the s

surm

accep

this

conne

data i 

Also imp

ection betw

ugh the colum

esearchers in

still seemed

rved at a colu

span length.

ised from th

pted value of

test did no

ections used

is needed be

Figure

ortant to no

een the colu

mn, this me

ndicted that

to have furt

umn displac

Thus, whi

hese tests, i

f 10% for co

ot have a l

d in that seam

efore the duc

2-20 Floor P

ote is that th

umn and be

ant no more

the steel dec

ther deforma

cement of 35

ile the full

it is possibl

oncrete slabs

longitudinal

m could sign

ctility of such

Plan of Com

45

he failure of

eam failed.

e load could

cking, thoug

ation capacit

5 inches, corr

deflection

le it is as h

s. It is impo

seam in t

nificantly lim

h systems ca

mposite Floor

f the floor sy

As the spec

d be applied

gh it had sust

ty and load c

responding t

capacity of

high, or hig

rtant to note

the affected

mit the duct

an be predict

r Column Lo

ystem occur

cimen was

to the syste

tained dama

carrying abil

to approxim

f the deckin

gher, than th

e that the de

d area howe

tility of the

ted with con

oss Test Setu

rred when th

being loade

em. Howeve

age during th

lity. This wa

mately 7.3% o

ng cannot b

he commonl

cking used i

ever. As th

system, mor

nfidence.

up

he

ed

er,

he

as

of

be

ly

in

he

re

46

3 TEST SETUP AND SPECIMEN

As discussed in Chapter 2, a major goal of this project is to experimentally

investigate the response of typical composite gravity-framed floor systems to column loss

scenarios. This chapter briefly outlines the test set up and procedure, which will be

further expanded on in chapters 4 and 5 respectively. The chapter then discusses in depth

the design of the test specimen. The prototype building used as a basis for the test

specimen is introduced. The chapter then goes into the design of the test specimen based

on this prototype building, discussing the decisions made to accommodate the smaller

scale of the test specimen, while still representing common practice as accurately as

possible.

3.1 Test Concept

The purpose of the project is to test how composite gravity-framed floor systems,

designed for normal loading without any consideration to progressive collapse, respond

to a column loss scenario, and see if sufficient robustness is inherent in these floor

systems to survive such an event. Testing a full building to collapse is impractical for a

number of reasons, so the initial plan for the test involved constructing a 2 bay by 2 bay

section of building, with the effects of the surrounding floor bays simulated by a

restraining ring beam circumscribing the specimen (See Figure 3-1). This made testing

much more economical, and allowed for the testing of multiple collapse scenarios. Apart

from the use of the ring beam to simulate the effect of surrounding bays, all details of the

specimen were designed to represent current construction practice to the extent possible.

suppo

once

the a

respo

point

collap

the fu

the te

To simula

orted by a te

the initial lo

actuator is sl

onse of the f

t where it no

psed, the ac

ull LRFD fl

est specimen

ate a column

elescopic act

oad (consist

lowly lower

floor system

o longer pro

ctuator will b

oor load the

n.

F

n loss event,

tuator before

ent with UF

red, removin

m component

ovides suppo

be fully retr

e building w

Figure 3-1 Te

47

the central c

e testing of t

FC collapse l

ng the suppo

ts is monitor

ort to the flo

racted. Then

was designed

est Setup Flo

column of th

the specimen

load) has be

ort of the c

red. If the a

oor system,

n additional

d to withstan

oor Plan

he 2 bay by 2

n (See Figur

een imposed

entral colum

actuator is lo

and the slab

load will be

nd to achiev

2 bay panel

re 3-2). Then

d on the floo

mn, while th

owered to th

b has not ye

e added up t

ve collapse o

is

n,

or,

he

he

et

to

of

P Mo

with

stand

build

of bu

Austi

desig

seism

Desig

latera

differ

behav

seism

In order t

oore designe

layout, mem

dards and pr

ding are prov

uildings pres

in, Texas. T

gn category

mic forces, s

gn Category

al force res

rent than th

vior of the g

mic lateral fo

o ensure the

ed a compos

mbers, conn

ractices of c

vided in App

sent through

This determin

of the stru

since the Au

A (ASCE 2

sisting syste

he prototype

gravity floor

orce resistin

Fi

3.2 Prot

e test specim

site building

nections, and

construction

pendix B). W

hout the coun

ned the win

ucture. The

ustin locatio

2010). For hi

em (braced

e building. H

r system, the

ng system sh

igure 3-2 Ac

48

totype Bu

men resemble

g for use as

d floor syste

(See Figure

While the des

ntry, the bu

nd load prese

prototype s

n meant the

igher seismi

frames for

However, s

e type and d

hould have

ctuator in Te

ilding

ed a real stru

a basis for t

ems consiste

e 3-3). (Full

sign of the s

uilding was a

ent on the s

structure wa

e building w

c design cat

the prototy

ince the fo

design requir

little influe

est Setup

ucture, the fi

the test spec

ent with cur

l plans for t

structure is r

assumed to

structure, and

as designed

was classifie

tegories, the

ype buildin

cus of this

rements for

ence on the

firm of Walte

cimen design

rrent industr

the prototyp

representativ

be located i

d the seismi

for minima

ed as Seismi

design of th

ng) would b

study is th

the wind an

gravity floo

er

n,

ry

pe

ve

in

ic

al

ic

he

be

he

nd

or

system

gravi

and 1

floor

in ad

Struc

Desig

Hum

m design, o

ity load syst

100 psf dead

As stated

system is c

ddition to the

ctural Steel B

gn Consider

an Activity

ther than dia

em (floor an

d load.

in the previ

ontrolled by

e structural d

Buildings, W

rations for S

(AISC 1997

Figure 3-3

aphragm des

nd columns)

ious chapter

y serviceabil

design of th

WPM also us

Steel Buildi

7), to determ

Floor Plans

49

sign conside

), the buildin

, the design

ity and fire

he building, b

sed AISC De

ngs (AISC

mine the nec

for WPM Pr

erations for

ng was desig

of many co

concerns, ra

based on th

esign Guides

2003) and

cessary stiffn

rototype Bui

the floor sy

gned for 50

mponents of

ather than st

e AISC Spe

s 3 and 11, S

Floor Vibra

ness for the

ilding

stem. For th

psf live loa

f a composit

trength. Thu

ecification fo

Serviceabilit

ations due t

floor system

he

ad

te

us,

or

ty

to

m,

50

which controlled much of the design. Additionally, the floor system, to comply with the

Underwriter’s Laboratories fire rated design UL D916, was constructed with a thicker

deck than was necessary to carry the expected floor loads.

3.3 Scaling of Test Specimen

The prototype building provided by WPM was designed with 30 ft. x 32 ft. bay

sizes. Performing the intended test program on a full-scale portion of the prototype

building floor system proved to be impractical with the budget available to the project.

Thus, the decision was made to scale the building down to a size that was achievable with

the funding and laboratory infrastructure available, while still being large enough to

capture behaviors under investigation.

There were two possible approaches to scaling the building down to an

economically achievable level. The building elements designed by Walter P Moore could

be directly scaled down by a reduction factor based on the ratio between the bay size of

the prototype building and the bay size of the test structure. Alternatively, the plans

provided could be used as a basis for designing a different building with smaller spans,

with the same standards for strength, stiffness and constructability used. The concern

with the former method was the difficulty in determining how to scale the member sizes.

Since the system response depended on both the axial and flexural response of many

components, determining a reduction factor that could provide an accurately scaled

representation of all the relevant behaviors was difficult. The concern with the latter

method was that since some of the elements were designed with respect to prescriptive

codes (or other standards independent of size/span length) a short span building designed

51

to typical practice may be stronger for some loading conditions than an equivalent larger

span building.

A compromise between the two ideas was used. The structural elements of the

building that are typically controlled by strength and serviceability were designed as they

would be in a short span building. The assumed live load was left at 50 psf, while the

assumed dead load was decreased from 100 psf to 75 psf to account for the reduced

weight of the thinner concrete deck. For structural components and details that are

governed by common practice, and not a calculated limit state, such as the reinforcement

placed around the perimeter and over girders as crack control, the components were

scaled directly off the prototype building’s details. As these components predominantly

exhibited an axial response, they could be reduced by a linear ratio of the prototype’s and

test specimen’s respective sizes, and still accurately mirror the response expected in an

actual structure. For codes not directly related to the buildings structural response

(particularly fire codes), these limit states were ignored, in order to ensure the building

was not stronger (relative to its size) than a building of typical bay sizes. The design of

individual components is discussed further in the following section.

3.4 Test Specimen Design

3.4.1 PRIMARY STRUCTURAL MEMBERS

The girders used in the test specimen were W12x14s, whose design was

controlled by the strength demands during construction. The secondary beams used were

W6x9s. These beams were capable of handling the full strength requirements during

concrete placement and building occupancy. However, the deflections induced in these

beams by the placement of concrete were slightly higher than typical serviceability limits.

While it is common for serviceability to control these beams, due to the limited number

52

of beam sizes available at this small scale, increasing to the smallest available beam that

could meet deflection limits would have still resulted in a significant increase in beam

strength. Not only would this result in an uncharacteristically strong structure, but due to

the small size of the structure, it would have made it very difficult to achieve a minimum

level of composite action with the floor slab (discussed further in part 3.4.3). Thus, the

W6x9s were used despite their slight flexibility. During construction of the interior

column loss specimen, this deflection, combined with the decking deflection, resulted in

an unexpectedly high amount of additional concrete being poured to achieve a level slab

(discussed further in 6.5). While it is not believed that this had a significant effect on the

final capacity of the structure, it did add additional dead load. For the subsequent exterior

column loss specimen, temporary wood shoring was used to support the secondary beams

during concrete placement

For the exterior column loss specimen, spandrel girders and spandrel secondary

beams needed to be designed as well. When designing the spandrel elements of the

structure, the serviceability requirements and imposed loads are heavily dependent on the

choice of façade attached to the flexural members. For instance, the prototype building

included significantly stiffer and stronger spandrel girder sizes on the brick façade face

than on the curtain wall façade face. As the test program did not allow for sufficient tests

to investigate the effects of different sizes of spandrel member, a single design needed to

be selected. For many of the potential facades that could be used in the design, the

required spandrel members were identical in size to their interior counterparts. Thus the

decision was made to use identical members for both configurations. This enabled more

effective comparison between the interior and exterior column removal tests.

The central column was designed to support the same 5 floors as the prototype

building, with the floor area based on the test specimen’s bay sizes. The column design is

53

also controlled by the floor-to-floor height of the building, which could have been

assumed to be consistent with the prototype building, or scaled down in conjunction with

the floor slab. The column was designed with the more conservative assumption of 15-ft.

floor-to-floor heights, requiring a W8x31 shape to carry the gravity loads. This larger

column allowed more room for the clip angle connections to be attached, enabling easier

constructability. As the column’s strength likely has minimal impact on the collapse

response of the structure, this design should still give an accurate estimation of the

behavior of floor systems under a column loss scenario.

3.4.2 CONNECTIONS

All connections (girder-to-column, beam-to-column, beam-to-girder) in the test

specimens were designed as simple shear connections. The connection components were

primarily controlled by typical construction practice, or available components. For

instance, the angles used for the clip angle connections are all 3/16” thick, as that is the

smallest commonly available size, despite that being significantly stronger than needed to

carry the required shear loads (AISC 2005). The shear tabs used are also 3/16” thick, to

enable better comparison of their behavior with the clip angles. Similar constraints

occurred in the selection of the connections’ bolts. Typical construction practice requires

at least two bolts in a given shear tab, and two bolts in each connecting angle (for a total

of four bolts for a double angle connection) (AISC 2005). Given that structural bolts are

not commonly available in sizes less than 1/2”, this meant the shear tabs and clip angles

had significantly more capacity than the loads demanded. The use of smaller connecting

elements, while perhaps more accurate on a relative strength basis, would be inconsistent

with typical construction practice, and was thus decided against for our project.

3.4.3

2006

spaci

vary

corre

speci

truly

most

FLOOR SL

Typical c

). The steel

ing of second

significantl

lated with th

imen that is

“representat

representati

LAB

concrete floo

decking use

dary beams.

y in actual

he column sp

scaled accur

tive” buildin

ive method

Figure 3

Figure 3

or slab thic

ed is primar

As the num

buildings,

pacing of a b

rately to our

ng to compa

that could b

3-4 Clip Ang

3-5 Shear Ta

54

cknesses are

rily controlle

mber of secon

the strength

building. Th

r specimen’s

are to. Given

be found wa

gle Detail an

ab Detail and

e controlled

ed by the co

ndary beams

h of the flo

hus, designin

s small size

n the small s

as to use the

nd Construct

d Constructe

by fire cod

oncrete thick

s in between

oor slab is

ng a floor sla

is difficult,

size of our s

e lightest ste

ted

ed

des (Ashcra

kness and th

n columns ca

not strongl

ab for our te

as there is n

specimen, th

eel composit

aft

he

an

ly

st

no

he

te

decki

suppo

the pr

shear

1/2”

load,

and c

concr

addit

This

locati

reinfo

under

the r

reinfo

could

ing common

orted by that

The decki

roject by Va

r studs while

was needed

the concret

cracking co

rete slab.

Additiona

ional steel r

improves th

ions due t

orcement wa

r collapse sc

relatively we

orcement w

d not be desi

Figur

nly offered b

t deck, ignor

ing used was

alley Joist In

e maintainin

. As this dep

te slab was d

ontrol, WWR

ally, while it

reinforcemen

he serviceab

to the flex

as included

cenarios, by

eak shear c

as based on

igned for the

e 3-6 Deck w

by U.S. ma

ring fire code

s WVC2-22

nc. In order t

ng the minim

pth of concr

designed wit

R 6x6x1.6

t is not expl

nt to the de

bility of the

xibility of t

in the test s

enabling the

connections.

n historical p

e test specim

with Wire R

55

anufacturers,

es or other n

, a 2” tall, 22

to accommod

mum clear c

rete was suff

th the 4-1/2

welded wir

licitly requir

eck spanning

structure an

the seconda

specimen as

e floor syste

In the pro

practice rath

men’s reduce

Reinforcemen

, and design

non-structura

2 gage comp

date the nec

cover, a deck

ficient to car

” minimum

re reinforcem

red by any c

g over the g

nd further re

ary beams

s this detail

em’s membr

ototype build

her than a s

ed scale. In

nt Detail and

n the concre

al restriction

posite deckin

cessary reinf

k thickness

rry the build

thickness. F

ment was p

code, some e

girders (See

estrains crac

(Ashcraft

could be ve

rane action t

ding, the d

specific lim

order to app

d Constructe

ete slab to b

ns.

ng donated t

forcement an

of at least 4

ding’s servic

For shrinkag

placed in th

engineers ad

e Figure 3-7

cking at thes

2006). Th

ery beneficia

o bridge ove

esign of th

mit state, so

proximate th

d

be

to

nd

4-

ce

ge

he

dd

7).

se

is

al

er

is

it

he

relati

reinfo

reinfo

with

neede

comp

load.

signif

carry

and s

studs

recom

of se

presc

degre

ive strength

orcement we

orcement rat

Shear stud

the steel be

ed to carry

posite, addin

Due to the

ficantly stro

y the building

slab, a minim

were de

mmendations

econdary b

criptive stand

ee of compo

Fig

of this co

ere scaled do

tio, respectiv

ds were also

ams. In typi

the expect

ng only the n

e very small

onger than th

g loads. How

mum degree

signed to

s from Walt

eams, seco

dard of placi

site action th

gure 3-7 Rein

omponent fo

own to posse

vely.

o included in

ical practice

ted floor lo

needed numb

l beams use

he girders,

wever, in or

e of composi

achieve 2

ter P Moore

ondary beam

ing one shea

han structura

nforcement o

56

or our spec

ess a similar

n the floor sy

e, fully comp

oads, so the

ber of shear s

ed in the te

and very lit

rder to preve

ite action is

25% compo

. While this

ms are mo

ar stud at eve

ally required

over Girder D

cimen, the

r ratio of reb

ystem to ena

posite beam

e girders ar

studs to carr

st specimen

ttle composi

ent excessive

often used.

osite action

s limit somet

re common

ery low flute

d (Waggoner

Detail and C

length and

bar length to

able it to act

s are much

re designed

ry the maxim

n, the concre

ite action w

e slip betwe

. Thus, the g

n with th

times contro

nly designe

e, which cre

r 2012). As

Constructed

area of th

bay size, an

t compositel

stronger tha

d as partiall

mum expecte

ete deck wa

was needed t

een the beam

girders’ shea

e slab, pe

ols the desig

ed using th

eates a greate

this provide

he

nd

ly

an

ly

ed

as

to

ms

ar

er

gn

he

er

ed

suffic

mirro

3.4.4

build

desig

const

attach

must

girde

or pu

attach

studs

weld

need

cient strengt

ored in our sp

ADDITION

Typical d

ding’s design

gn engineer

truction vary

hed to the s

also be att

rs, at a spac

uddle welds,

hed to the se

. As the stu

can be used

for more

Figure 3

th and degr

pecimen.

NAL SPECIM

design and c

n, leaves ma

. In particu

y from proje

steel frame a

tached at al

cing no more

or button p

econdary be

ud welding p

d as the con

fasteners. H

-8 Shear Stu

ree of comp

MEN DETAILI

construction

any decision

ular, many

ct to project

at every low

ll side-laps

e than 36”. T

unches in th

eams at only

process also

nnection betw

However, as

ud Detail ove

57

posite action

ING

n practice, w

ns in the ha

details of

t. For instanc

w flute over

between adj

This attachm

he case of si

y a few locat

o forms a w

ween the lo

s tek screw

er (a) Secon

n for our sy

while contro

ands of the

f the floor

ce, the steel

each secon

djacent sheet

ment can be p

ide laps. Occ

tions prior t

weld between

ow flute and

ws and pud

dary Beams

ystem, this

olling many

contractor

deck’s pla

decking is r

ndary beam.

ts of deckin

provided wi

casionally, t

to the placem

n the stud a

d the beam, r

ddle welds

and (b) Gird

practice wa

aspects of

or individua

acement an

required to b

The deckin

ng and alon

ith tek screw

the decking

ment of shea

and deck, th

removing th

are typicall

ders

as

a

al

nd

be

ng

ng

ws

is

ar

is

he

ly

inexp

better

over

along

evenl

these

screw

beam

is mo

depen

uncer

F

pensive and

r secure the

The test s

all secondar

g the girders

ly fit in the

connection

ws are used,

m cover plate

ore consisten

nding on the

rtainty to the

Figure 3-9 C

fast to inst

deck, as wel

specimen fo

ry beams. T

s (and corres

7-1/2’ secon

ns are prim

as scaled te

es. Tek screw

nt and pred

e quality of

e results (Ro

Connection fr

all, many c

ll as placing

llowed this

ek screws w

sponding rin

ndary beam

arily contro

ek screws wo

ws were chos

ictable. Pud

weld and le

gers and Tre

rom Deck to

58

ontractors w

shear studs

practice, usi

were also pla

ng beams) at

spacing) (S

olled by dec

ould be mor

sen over pud

ddle welds o

evel of cont

emblay 2003

o Beam using

will place th

afterwards (

ing #10 tek

aced along a

t a 30” spaci

ee Figure 3-

cking thickn

re difficult t

ddle welds b

often have a

tact between

3).

g Puddle We

hem at each

(SDI 2012).

screws at e

all decking s

ing (reduced

-10 and Figu

ness, standa

to attach to t

because their

a wide range

n deck and b

elds and Tek

h low flute t

ach low flut

side laps, an

d from 36” t

ure 3-11). A

ard sized te

the thick rin

r performanc

e in behavio

beam, addin

k Screws

to

te

nd

to

As

ek

ng

ce

or

ng

into t

spans

this l

seam

of fai

seam

F

Fi

The decki

the column.

s long. Engin

imits deflect

m could incre

ilure. As ma

m in the affec

Figure 3-10 T

igure 3-11 C

ing also incl

This resulte

neers often

tions during

ease the spec

any column

ted area, its

Tek Screw L

Constructed D

luded a long

ed in the dec

try to provid

pouring of

cimen’s stre

loss location

inclusion wa

Layout for (a

Detail of (a)

59

gitudinal seam

cking on eit

de at least th

the concrete

ength, by rem

ns would res

as deemed n

a) Floor Beam

Girder and Beam

m over the s

ther side of

hree spans o

e. However,

moving the s

sult in the p

necessary.

ms and Side

Sidelap Tek

secondary be

the seam be

of continuou

omitting the

seam as a p

presence of a

elaps and (b)

k Screws and

eams framin

eing only tw

us decking, a

e longitudina

otential poin

a longitudina

) Girders

d (b) Floor

ng

wo

as

al

nt

al

width

decki

at the

them

sheet

throu

conne

allow

minim

weak

Howe

can a

result

failur

Due to th

h of the flang

ing included

e location of

together (Se

t seams usua

ugh multiple

ections betw

w the deckin

mal impact

k or brittle

ever, it is po

achieve mor

ts of testing

re of the spec

he small size

ge to avoid w

d a 4” overla

f the longitu

ee Figure 3-

ally butting

e layers of

ween the dec

ng to achiev

on the final

to meaning

ossible that th

re effective

g may indica

cimen.

Figure 3-12

e of the beam

web cripplin

ap between s

udinal seam w

12). While t

against each

deck is typ

cking and b

e its full str

l result. It is

gfully contri

his change w

tensile mem

ate whether

2 Longitudin

60

m flanges, th

ng at the ends

sheets, and s

went throug

this is somet

h other with

ically avoid

beams, as w

rength, and

s also possib

ibute to the

will strengthe

mbrane acti

this discrepa

al Seam Det

he decking n

s. Thus, the

subsequently

gh both sheet

times done i

h no overlap

ded (AISC 2

well as the p

the shear st

ble the shea

e catenary c

en the seams

on than a t

ancy has a s

tail and Con

needed to re

longitudinal

y the shear s

ts of decking

in practice, i

p, as weldin

2005). It is

presence of

tud connecti

ar stud conn

capacity of

s to the poin

true building

significant i

nstructed

est on the fu

l seams of th

studs attache

g, connectin

it is rare, wit

g shear stud

possible th

concrete wi

ion will hav

nection is to

the decking

nt that the sla

g could. Th

impact on th

ull

he

ed

ng

th

ds

he

ill

ve

oo

g.

ab

he

he

61

4 TEST FRAME DESIGN

This chapter details the design of the test frame supporting the tested floor system.

The foundation built for the test frame is first described. Then, the design of the ring

beam and the connections between the ring beam and floor system is explained, and the

accuracy of the ring beam’s modeling of a full building’s response is discussed. Finally,

the bracing used to restrain the test frame and central column is detailed.

4.1 Foundation Design

Due to the large size of the test specimen, the lab could not accommodate the full

test frame, and the project had to be moved outside. A 24 ft. by 56 ft. concrete slab was

already present at the proposed test frame location. However, the existing slab was too

small to accommodate the test frame’s full size and too weak to accommodate some of

the column loads. Thus, the foundation needed to be expanded and strengthened to

support the test, as shown in Figure 4.2 Additional 8-ft. wide, 8” deep concrete slabs

were added to both long sides of the existing 24 ft. by 56 ft. foundation. Reinforcement

was post installed in the existing slab at the interface between the new and existing slabs

to create a connection between slabs. Three 16” deep, 42” square footings were included

in each extended slab to accommodate the loads from the test frame’s columns. The test

frame also had columns located on the existing foundation, which induced loads greater

than the slab could withstand. Thus, a 5-ft. square section of slab was removed at each

column location, and the soil dug out to accommodate 16” deep footings, which were

also bonded to the existing slab through the use of post-installed rebar. The actuator was

located over an existing footing in the slab, and could be supported without additional

strengthening.

restra

beam

close

restra

force

prese

the c

circum

bays

ment

The respo

aint and supp

m around the

ly as possib

aint present

s that will p

ent in compo

collapsing b

mscribing b

is likely u

ioned previo

onse of a fl

port provide

e test specim

ble. The prim

in a full bui

potentially su

osite building

bays, one w

beam. Howe

unnecessary

ously in Cha

4.2 Rin

loor system

ed to it from

men is inten

mary aspect

ilding, which

upport load a

gs has the po

which may

ever, providi

due to the

apter 2.

Figure 4

62

ng Beam D

under colla

m the surroun

nded to sim

t the ring be

h will enabl

after column

otential to pr

not be pra

ing the full

e presence

4-1 Foundat

Design

apse conditi

nding bays o

mulate the ef

eam needs t

e the floor t

n removal. T

rovide a ver

actical to m

l lateral stre

of the “co

tion

ions is depe

of the struct

ffects of thi

to replicate

to develop th

The large flo

ry large later

match accur

ength of the

ompression

endent on th

ture. The rin

is restraint a

is the latera

he membran

or diaphragm

ral strength t

rately with

e surroundin

ring” effec

he

ng

as

al

ne

m

to

a

ng

ct,

63

While the compression ring effect suggests that the system will have sufficient

lateral strength to support the membrane forces placed on it, whether it has sufficient

lateral stiffness is harder to predict. The lateral stiffness of compression rings relative to

fully restrained slabs has not been investigated at depth, and likely depends on a wide

variety of factors which are not fully understood. Tests have shown slabs relying on

compression rings can have less stiff load-deflection relationships than slabs with full

lateral restraint, but have also been observed displaying higher stiffness under certain

conditions (See Figure 2-16) (Brotchie and Holley 1971). Thus, the difference in

response of a system that relies on the compression ring effect, and one that has lateral

restraint is currently unclear.

Additionally, the amount of lateral restraint that would be provided to a damaged

floor in a full structure is difficult to calculate. Depending on the location of the missing

column, there could be many floor bays around the perimeter of the damaged area, or

none (if the lost column is one bay from the building’s edge). Not only is the restraint

dependent on the lost column location, the restraint provided to the floor slab is

dependent on the connection between the floor slab and the surrounding structures, and

thus is reduced by slip between the decking and concrete, as well as deformation of the

shear studs. Thus, many column loss situations will occur on floor slabs that have

significantly less than full lateral restraint at their perimeter.

Testing has been done by a variety of researchers, including Ferrer et al (2006)

and Marimuthu et al (2007) on the slip of composite decking in pull-out tests. While the

observed load-deflection responses varied significantly due to the decking used and shear

span of the test specimen (See Figure 4-2), the stiffnesses were all orders of magnitude

lower than that of the floor diaphragm. Therefore, the lateral restraint of a composite slab

undergoing membrane action is likely controlled primarily by that stiffness, and not the

latera

stiffn

frame

build

shear

be ac

the re

lab p

flexu

from

stiffn

defle

Fig

al restraint

ness provided

e will also b

ding.

In order t

r stud deform

chieved give

estraining be

projects, and

ural stiffness

the beam’s

ness to ensu

ctions. To p

gure 4-2 Loa

provided by

d by the rin

be controlle

to ensure the

mation, the d

n the econom

eam were tw

d freely avai

, the membr

s centerline.

ure that twi

provide this

ad-Slip Relat

y the comp

ng beam is s

ed primarily

e lateral rest

decision was

mic constrai

wo W27x94

ilable for us

rane loads fr

Thus, the b

isting of th

torsional s

tionship of S

64

ression ring

sufficiently l

y by deck sl

traint was c

s made to ch

ints of the pr

and two W2

se. While th

rom the floo

beams also

e beam did

tiffness, the

Steel Deck-C2006)

g or surroun

large, the la

lip, matchin

controlled pr

hoose the stif

roject. The p

27x84 beam

hese beams p

or system wi

needed to h

d not allow

e restraining

Concrete Com

nding floor

ateral restrai

ng the respo

rimarily by d

ffest ring bea

primary w-sh

ms left over f

possess a hi

ill be acting

have signific

w for excess

g beam was

mposite Bon

bays. If th

nt of our te

nse of a rea

deck slip an

am that coul

hapes used i

from previou

igh degree o

eccentricall

cant torsiona

sive in plan

made into

nd (Ferrer

he

st

al

nd

ld

in

us

of

ly

al

ne

a

close

comp

bay,

exper

Analy

slip a

build

curve

failur

slight

the s

agree

overa

progr

d shape, by

pact) to each

The chose

is still (ba

rimentally o

ysis done by

at the perime

ding with one

e (See Figure

re displacem

tly higher ve

significantly

ement betwe

all behavior

ram.

welding full

h side, creatin

en ring beam

ased on exp

bserved stif

y Imperial C

eter suggest

e surroundin

e 4-4). The l

ment of 218 m

ertical stiffn

higher vert

een the two s

closely, w

Figure 4-3

l depth half

ng a large bo

m design, w

pected latera

ffnesses of th

College of Lo

ts that the sy

ng bay on ea

line at 11.4 k

mm. The ana

ness than one

tical restrain

scenarios wo

while still en

Restraining

65

inch plates (

ox section.

while signific

al load dist

he concrete-

ondon, as pa

ystem is com

ach side, and

kN/m^2 ind

alysis sugge

e restrained

nt provided

ould be idea

nsuring sign

g Beam Deta

(chosen to e

cantly more

tribution) se

-steel deck s

art of this pr

mparable in

d has a simil

dicates the fa

ests that the t

by adjacent

by the rin

al, the curren

nificant stren

ail and Const

ensure the be

flexible tha

everal times

shear bond (

roject, incorp

stiffness to

ar overall lo

ailure load at

test prototyp

t floor bays,

ng beam. W

nt test design

ngth to sup

tructed

eam remaine

an a full floo

s stiffer tha

(Ferrer 2006

porating dec

that of a fu

oad-deflectio

t the assume

pe will have

likely due t

While stronge

n matches th

pport the te

ed

or

an

6).

ck

ull

on

ed

a

to

er

he

st

beam

place

the c

accom

expen

latera

small

mom

F

The restra

ms at their c

e was unfeas

connections

mmodate th

nsive connec

al strength to

l. Thus, the c

ment, resultin

igure 4-4 Lo

aining beam

connections.

sible, so the

needed to b

e entire cap

ctions. As th

o the system

connections

ng in a re

oad-Deflectio

’s stiffness i

Due to acc

connections

be attached t

pacity of the

he compressi

, the demand

were design

elatively eco

on Response

66

is based on t

cess issues,

s had to be b

to, designing

e ring beam

ion ring effe

d on the ring

ned to suppo

onomic det

e of Floor SlBays

the assumpti

welding the

bolted. Due

g fully fixed

m resulted in

ect should pr

g beam conn

ort half of th

tail, while

lab with Rin

ion of fixity

e ring beam

to the smal

d connectio

n prohibitive

rovide the m

nection will l

he ring beam

still provid

ng Beam and

between rin

ms together i

ll flange size

ns that coul

ely large an

majority of th

likely be ver

m’s full plasti

ding strengt

d Adjacent

 

ng

in

es

ld

nd

he

ry

ic

th

signif

Impe

the d

induc

crack

force

needs

direct

conne

ribs o

to dev

caten

ancho

frame

shoul

paral

decki

appro

ficantly in e

rial College)

In additio

decking’s an

ced by the

king occurs v

will need to

s to be firm

tly with mec

ection betwe

of the steel c

velop the ax

nary load tha

ored through

e. In the dir

ld be more

lel to the d

ing. Accord

oximately 28

Figure

excess of th

).

on to the nee

nchorage ne

membrane

very early at

o be transfer

mly attached

chanical or w

een the steel

could be atta

xial capacity

at could be

h the compo

rection perp

than suffici

decking ribs

ding to dec

8” of develo

e 4-5 Restrai

he predicted

ed for the rin

eeded to be

action. As

the perimet

rred almost e

to the test

welded faste

l decking an

ached in this

of the top ri

transferred

osite bond b

pendicular to

ent to ancho

, this bond

ck slip test

opment leng

ining Beam C

67

d demand (b

ng beam to p

strong eno

experiment

ter of the dam

exclusively t

frame. Atta

eners would

d test frame

s way, such

ibs of the dec

to the test f

etween it an

o the deckin

or the decki

must be ac

ts done by

gth is neede

Connection

based on an

provide the n

ough to with

tal tests ha

maged area (

through the

aching the d

likely have

. Additional

a connectio

cking, signif

frame. Instea

nd the concr

ng, the corr

ing to the c

chieved by

y Abdullah

d for the st

Drawing and

nalytical mod

necessary lat

hstand the

ave shown t

(Bailey 2000

steel deckin

decking to th

e resulted in

lly, since on

on would like

ficantly redu

ad the steel

rete above th

rugations of

concrete. In

the emboss

and Easter

eel decking

d Constructe

dels done b

teral strength

lateral force

that concret

0), this latera

ng, and it thu

he ring beam

a very brittl

ly the bottom

ely be unabl

ucing the tota

decking wa

he restrainin

f the deckin

the directio

sments in th

rling (2009

used on th

ed

by

h,

es

te

al

us

m

le

m

le

al

as

ng

ng

on

he

9),

is

proje

lower

of co

ancho

concr

concr

were

paral

threa

concr

(See

bolte

Refer

Fig

ct to develo

r due to the

oncrete arou

ored, enabli

rete could th

rete deck an

designed to

lel to the de

ded rods we

rete deck to

Figure 4-6)

d to the en

rence sourc

gure 4-6 Res

p its full ten

presence of

und the perim

ing the floo

hen be tied t

nd ring beam

o be reusable

ecking, as th

ere connecte

function as

. Along the

nd at each r

ce not found

straining Bea

nsile capacit

f the compre

meter of the

or system t

to the ring b

m. Due to th

e to simplify

he connector

ed to the rin

shear studs,

ring beams

rib, and she

d.Figure 4-7)

am Boundary

68

y (the actua

ession ring e

e test frame

to achieve t

beam throug

he need to re

y demolition

rs needed to

ng beam suc

, while still

s perpendicu

ear studs we

).

y Parallel to

al tensile dem

effect). Addi

e enabled th

the maximu

gh composite

euse the test

between tes

o pass throu

ch that their

allowing ea

ular to the d

ere welded

o Deck Ribs D

mand will lik

ing this add

he steel dec

um catenary

e connectors

t frame, thes

sts. Along th

ugh the entir

r shaft exten

sy removal

decking, 1/4

to those pl

Detail and C

kely be muc

ditional lengt

k to be full

y effect. Th

s between th

se connector

he ring beam

re ring beam

nded into th

after collaps

" plates wer

lates (Error

Constructed

ch

th

ly

he

he

rs

ms

m,

he

se

re

r!

flexu

the c

edges

span

along

overl

mode

suppo

build

action

the ri

poten

fixity

restra

comp

beam

The other

ural restraint

ompression

s. In additio

over the dam

g the perime

loaded, parti

e for the sys

ort was des

ding. That wa

n without th

ing beam, th

ntial for failu

In a full

y to the floor

aining beam

ponents that

m only need

Figure 4-7 R

r behavioral

around the

ring effect

on, the mem

maged colum

ter of the da

icularly the

tem, it is a f

igned to be

ay, it would

he surroundi

he load tran

ure of those b

structure, th

r system by

m must also

attach to the

s to resist t

Restraining B

aspects the

perimeter. T

is dependen

mbrane action

mn will resu

amaged area

smaller seco

failure mech

e significant

be possible

ing structure

sferred to th

beams check

he surroundi

continuity b

provide fle

e ring beam

the moment

Beam BoundCo

69

e ring beam

The vertical

nt on the pr

n that we be

ult in a large

a. This transf

ondary beam

hanism that i

tly more tha

to observe t

e failing firs

he perimeter

ked indirectl

ing floor ba

between adja

xural restrai

have very w

t imposed b

dary Perpenonstructed

needs to sa

restraint is

resence of v

elieve will a

e load being

fer could res

ms. While th

is well unde

an what wo

the connecti

st. With suff

r beams cou

ly.

ays also can

acent bays.

aint to the s

weak flexural

by simple s

ndicular to D

atisfy are the

particularly

vertical supp

allow the flo

g transferred

sult in those

his is an imp

erstood. Thu

ould be pres

ion failure an

ficient instru

uld be calcul

n provide pa

To mimic th

system. How

l behavior. T

hear connec

eck Ribs De

e vertical an

y important a

port along th

oor system t

to the beam

e beams bein

portant failur

s, the vertica

sent in a fu

nd membran

umentation o

lated, and th

artial flexura

his effect, th

wever, all th

Thus, the rin

ctors and th

etail and

nd

as

he

to

ms

ng

re

al

ull

ne

of

he

al

he

he

ng

he

70

moment capacity of the deck under negative moment, both of which are limited. As the

ring beam was designed as a very torsionally stiff closed shape to resist the torsion from

the eccentric in-plane forces, the existing shape has enough torsional strength and

stiffness to be treated as a nearly rigid boundary for the comparatively weak elements

attached to it.

4.3 Additional Design Considerations

As the full gravity load experienced by the entire structure was relatively small,

the load demand on the columns supporting the test frame was minimal. The corner

columns were thus chosen based on the lab’s availability of pre-existing columns that

were at least 20 ft. long, to accommodate the height of the test frame and top bracing.

Thus, surplus W12x58 columns were chosen as the corner supports of the test frame. The

middle columns were chosen specifically for the project. W4x13 columns proved

sufficient to carry the needed mid-span loads from the gravity loads. Cross bracing was

provided on all sides of the structure and along the top plane of the system. Due to the

small vertical loads on the structure, designing these braces to meet the structure’s

expected demands resulted in very small members. Thus the cross-braces were designed

instead to meet a nominal 10 kip lateral load, to ensure the structure had significant

redundancy against stability failures.

The top cross braces, in addition to providing further stability to the structure, also

provided lateral restraint to the central column. In a column loss scenario, the column

below the affected floor system is assumed to be completely destroyed, but the column

above the floor is fully intact, and still attached to the floor above. Thus, the column will

be laterally restrained by the floor above it, and can provide rotational restraint where it

frames into the damaged floor. In the case of the interior column loss, this will likely

71

have minimal effect, as the symmetry of the system should prevent any significant

rotation at the column. However, in the case of the exterior column loss, the rotational

restraint of the column could enable the beam framing into it to develop its full moment

capacity, improving the performance of the system.

In a true building, the top end of the column would be restrained by the shear

stiffness of the full floor diaphragm. Mimicking the full stiffness at the column top would

be prohibitively expensive. However, if the column is sufficiently stiff, it can act as an

effectively rigid boundary to the connection framing into it. The stiffness of the

composite clip angle that frames into the column connection has been minimally

investigated. Liew et al (2003) looked at the behavior of composite partial depth

endplates under positive moment, which deform in a manner similar to web cleat, and

likely have similar stiffness. For connections of similar depth to the ones used in our

setup, the rotational stiffness is more than an order of magnitude less than that of the

stiffness provided to the column by the braces. Therefore, the column should function

effectively as pinned at the top and mirror the restraint provided by a full structure.  

72

5 TEST PROCEDURE

This chapter discusses the procedures for testing the collapse capacity of the floor

system in this experimental program. The procedure for simulating column loss is

explained, as well as the procedure for adding additional load to the structure if

necessary. The matrix of proposed tests is then introduced and detailed.

5.1 Actuator Removal

The most commonly used method for evaluating the robustness of a structure is

subjecting the floor system to a sudden loss of a primary member, usually a column.

Thus, the test setup was designed to simulate a column-loss scenario. In a true collapse

event, the “sudden” loss of a column induces significant dynamic effects. For this test

program, however, column support for the floor system was removed gradually by slowly

retracting the actuator that represented the lost column. This was done because of cost

and safety concerns associated with sudden removal of a column in the test specimen.

Since this was one of the first times such a collapse test has been undertaken, the decision

was made to provide for gradual column removal. This allows for more thorough

observations of structural behavior during the column removal process, and also permits

the opportunity to stop the column removal process, should safety concerns arise during

the course of testing. Also, by monitoring the load-deflection response of the structure,

the energy the structure absorbs can be calculated, and an appropriate dynamic

amplification factor can be calculated and applied to the load to estimate the capacity of

the structure under sudden column removal (Dusenberry and Hamburger 2006).

Nonetheless, gradual column removal is a limitation of this test program that must be

considered when interpreting the test results. In the future, similar tests that include

sudden column removal would be useful.

73

In the test specimen, the effect of column loss is simulated by supporting the

central column through a hydraulic actuator. This actuator can then be lowered, removing

the vertical support provided to the floor system. Teflon sheets are placed between the

actuator and central column to minimize any lateral restraint provided to the floor by the

actuator during initial lowering. Because the ductility of the structure is difficult to

predict, the actuator needed to have a very large stroke capacity so it could be fully

retracted to the point where it was no longer supporting the floor system. To the author’s

knowledge, no empirical testing has taken composite floor slabs to failure in this type of

test, but the upper bound deflection limit for traditionally reinforced slabs is often around

15% of the full span (Stevens 2008), corresponding to a deflection of 4-1/2 feet for our

test specimen. To accommodate this high deflection capacity, a three stage telescopic

actuator was used which allowed the floor system to displace seven feet before hitting the

limits of the test frame. The actuator would then collapse into a steel cage erected under

the floor system to protect it from the collapsing structure, so that the slab could be

loaded further if it survives the initial column removal.

5.2 Loading System

For LRFD design of floor systems under gravity load, ASCE 7 (ref) requires a

factored load of 1.D +1.6L, where D is the nominal deal load, and L is the service live

load. However, for the extreme loading conditions of a column loss scenario, UFC

progressive collapse guidelines recommend designing the structure to withstand a gravity

load of 1.2D+0.5L. Given the assumption of 75 psf nominal dead load and 50 psf service

live load used in the design of the structure, this required a total imposed floor load of

115 psf on the test specimen. While the system’s response to the UFC design load is of

importance, determining the full collapse capacity of the structure was also of interest in

74

this research. Thus, the loading system needed to be able to apply additional load in the

event that the structure survived the full removal of the central column. To design the

loading system, an upper limit for this additional load needed to be chosen. Due to the

many unknowns in the behavior of the test specimen, the true collapse load was difficult

to predict, so the decision was made that a reasonable upper bound for capacity was the

full gravity load the structure was designed for. This load, based on the ASCE

requirement of 1.2D+1.6L resulted in a distributed load of 170 psf.

The loading system chosen would need to apply these loads in a reasonably

uniform manner over the floor slab to match the loading assumptions of typical design.

Thus, the loading system needed to be flexible enough to conform to the structure’s

deflected shape, and not simply span over the slab and apply its load primarily to the

floor beams. This uniform distribution needed to be maintained for both the initial load

and the added load after removal of the column. Given access issues of the test specimen,

the most feasible way to add load was through the use of water added on top of the slab.

Given the potential for significant deflection of the slab, if the water was placed into a

large receptacle, it would drift toward the center of the slab, and lead to the load

concentrating in that area. Thus, the elements of the loading system needed to be small to

keep the water uniformly distributed, and enable the flexibility of the loading system.

The design chosen for the loading system was a set of 40”x40” plywood

formworks, with a 6” layer of concrete placed in the bottom of the formworks to impose

the full UFC collapse load on the floor slab. The formworks are 24” tall, and left in place

after the concrete is poured, so that 18” of available space is left over the concrete for

water to be added. 64 vessels were needed to cover the entire floor slab, which would

have been logistically difficult to place individually. To simplify placement, the

reinforcement in the concrete blocks was placed continuously between adjacent buckets,

to tie

betwe

suffic

throu

bubb

allow

is the

study

decki

sheet

most

dama

struct

memb

e them toget

een buckets

cient flexibi

ugh an irriga

lers are des

wing the adde

The behav

e role of cate

ying this dir

ing, as well

ts would req

critical part

aged area. Th

ture, can g

brane respo

ther in grou

s, to maintai

lity to defle

ation system

signed to a

ed load to be

vior we belie

enary action

rectly is ver

as its comp

quire a prohi

t of the cate

his response

ive a very

nse. Additio

ups of four.

in the unifo

ect with the

which inclu

add water to

e accurately

5.3 Ins

eve to be mo

n in the floor

ry difficult.

lex geometr

ibitive amou

enary respon

e, if examine

accurate e

onally, the l

Figure 5-1

75

This also p

ormity of lo

floor slab.

udes a “bubb

o each indiv

calculated (

strumenta

ost significan

r system’s u

Given the v

ry, an accura

unt of instru

nse is the fo

ed in conjun

estimate of

load the flo

Irrigation S

provided for

oad, while s

To add load

bler” nozzle

vidual buck

See Figure 5

ation

ant to the resp

ultimate load

very large s

ate picture o

umentation t

orce it exerts

nction with th

the load su

oor system e

System

r a consisten

still allowin

d, water wa

over each b

ket at a pre

5-1).

ponse of the

d capacity. U

surface area

of the strain

to achieve. H

s on the per

he displaced

upported by

exerts on th

nt 6” spacin

g the system

as be pumpe

bucket. Thes

escribed rate

e floor system

Unfortunately

a of the stee

across all th

However, th

rimeter of th

d shape of th

y the floor

he rest of th

ng

m

ed

se

e,

m

y,

el

he

he

he

he

’s

he

struct

surro

typic

from

beam

place

beam

determ

isolat

capac

displa

centr

of the

Figur

ture will sug

unding stru

al composite

the floor sy

ms and their

ed on the top

m, so the resp

mine the ax

ted and studi

The overa

city of the s

acement the

al column c

e beams, cau

re 5-3a). If

ggest whethe

ucture, or w

e constructio

ystem will pr

connections

p and bottom

ponse could

xial force pr

ied.

all displacem

structure’s m

floor system

onnections i

using the flo

the connect

F

er the catena

whether the

on. Finally,

rovide an ind

s as catenar

m of the ring

d be monitor

resent in it,

ment of the f

membrane re

m, and the s

is low, their

oor system t

tions are stif

Figure 5-2 In

76

ary response

compression

the demand

dication of t

ry action is

beam’s flan

red. Addition

so the axia

floor system

esponse is h

shape of the

r rotation wi

to deform as

ffer, they m

nstrumentati

imposes a s

n ring effec

d placed on t

the demands

developed.

nges at the m

nally, the gi

al contributi

m is also imp

heavily depe

deflected sl

ill significan

s a group of

may cause th

ion Plan

significant d

ct can be co

the surround

s placed on t

Thus, strain

mid and end p

irder was str

on of the d

portant to m

endent on th

lab. If the st

ntly exceed t

f largely rigi

he system to

emand on th

ounted on i

ding structur

the secondar

n gages wer

points of eac

rain gaged t

deck could b

monitor, as th

he maximum

tiffness of th

the deflectio

id plates (Se

o deflect in

he

in

re

ry

re

ch

to

be

he

m

he

on

ee

a

shape

gover

determ

used

ends

the fl

occur

shear

impa

dissip

the d

To st

attach

colum

rotati

mom

F

e more simil

rn the rotatio

mines the e

to measure

of the beam

loor system.

rs between t

r connection

Additiona

ct of dynam

pate in a tru

ductility can

tudy the resp

hed to moni

mn connecti

ion. The gir

ment in the b

Figure 5-3 F

lar to that o

on at the end

ffectiveness

vertical dis

ms framing in

String pots

the central c

s.

ally, the duc

ic amplificat

ue “sudden c

be determin

ponse of the

itor the hor

ion, allowin

rder flanges

eam. By stu

Floor System

of a long bea

ds of the slab

of the cate

placement o

nto the centr

were also at

column and

ctility of the

tion on the s

column loss”

ned by comp

e beam and g

izontal disp

ng measurem

s were also

udying the r

m Displacing

77

am (See Fig

b, which (alo

nary action.

of all floor b

ral column, t

ttached to th

floor system

system will

structure, and

” scenario. F

paring the ap

girder conne

placement at

ment of the

strain gage

esponse of t

as (a) Rigid

gure 5-3b). T

ong with the

. Thus, large

beams at the

to capture th

he central col

m, particular

l play a larg

d how much

For the deck

pplied load

ections to th

t the top an

axial displ

ed at the m

the connecti

d Plates and (

This deflecte

maximum d

e stroke stri

eir mid poin

he full displa

lumn, to det

rly after the

ge role in det

h energy it ca

king’s caten

to the overa

he column, st

nd bottom fl

lacement as

mid-point to

ions to the c

(b) Flexural

ed shape wi

displacemen

ing pots wer

nts and at th

aced shape o

termine if sli

failure of th

termining th

an effectivel

nary response

all deflection

tring pots ar

lange at eac

s well as th

estimate th

collapse load

Shapes

ill

nt)

re

he

of

ip

he

he

ly

e,

n.

re

ch

he

he

d,

the st

determ

collap

on th

simul

system

an int

exter

tiffness of th

mined, givin

pse conditio

The abilit

he boundary

lation of mu

m responds

terior colum

ior column l

he connectio

ng further in

ns.

ty of a system

conditions i

ultiple colum

to collapse e

mn loss, with

loss with onl

Figure 5

ons (both axi

nsight into th

5.4 T

m to carry lo

imposed on

mn loss scena

events. The

the full 2 ba

ly one half o

5-4 String Po

78

ial and rotat

he strength a

Test Matr

oad through

it. Thus, the

arios to bett

proposed tes

ay by 2 bay

of the floor c

ot Layout at

tional) and th

and ductility

rix

catenary ac

e proposed t

ter understan

st matrix inc

floor cast, a

constructed o

Center Colu

he point of f

y of these el

ction is heavi

test program

nd how a co

cludes three

and three tes

on the test fr

umn

failure can b

ements unde

ily dependen

m includes th

mposite floo

tests done o

sts done on a

rame.

be

er

nt

he

or

on

an

colum

under

evalu

condi

ring,

been

direct

exert

comp

mode

on th

deck

does

The first

mn (i.e. with

r the ideal

uation of so

itions in the

while it has

studied in h

tions, the ef

ed by the m

pletion of th

els the behav

he restraining

will crack u

not allow fo

5

series of pr

h a floor slab

conditions

ome of the

test frame si

been observ

heavily ortho

ffectiveness

membrane o

he first test,

vior of com

g beam will

under minim

or torsional d

Figure 5-5

5.5 Interi

roposed test

b in all bays s

for membra

test assum

imulate thos

ved in many

otropic slabs

of the comp

on the restr

to determin

mposite floor

l need to be

mal negative

deflections th

5 Interior and

79

ior Colum

ts are intend

surrounding

ane action.

mptions, in

se present in

y experiment

. Due to the

pression ring

aining beam

ne how accu

decks. Add

e studied, to

moment is

hat would no

d Exterior C

mn Loss

ded to study

the column

In addition

particular h

an actual str

ts, has not (to

different de

g could be r

m will need

urately the

ditionally, th

o ensure that

valid, and t

ot be present

Column Test

y the loss o

), to evaluat

n, these test

how well t

ructure. The

o the author

eck propertie

educed. The

d to be stud

compression

he torsional

t the assump

that the rest

t in a full str

Setup

of an interio

te its respons

ts will allow

the boundar

e compressio

rs knowledge

es in differen

e lateral forc

died after th

n ring theor

force exerte

ption that th

training beam

ructure.

or

se

w

ry

on

e)

nt

ce

he

ry

ed

he

m

80

The first proposed test is on the unmodified building design, with no

modifications made to improve robustness. The results of this test will significantly

improve understanding of the robustness of typical composite construction. In particular,

the failure sequence observed (if any) will indicate the ductility of the system, and the

components most critical to the performance of the structure. Using the results of this

test, a new design will be created, consisting of revised details to improve the

performance of the critical components, and hopefully increase the robustness of the

structure. This new design will then be constructed and tested under a column loss

scenario, to determine if the collapse performance of the structure can be improved. A

third interior column test is also planned, where the central column will first be lifted,

forcing the floor system to deflect upward. In the case of an interior column loss resulting

from an explosion, the pressure of the blast can produce an initial uplift on the system,

before the blast dissipates and the floor system deflects downward. This uplift has the

potential to damage some components of the structure (particularly the concrete around

the column), leading to a possible loss of stiffness and strength in the later response of the

structure. By applying an initial upward force to the central column before removing it,

we can simulate this damage and see whether it plays a significant role in the final load

carrying capacity of the structure.

5.6 Exterior Column Loss

The second series of tests will simulate the loss of an exterior column. Without

the presence of an undamaged building section on all sides of the slab, the system’s

ability to form a two-way membrane is likely to be heavily compromised. In this

scenario, the slab’s response will be a primarily one-way membrane spanning between

the opposite undamaged sides. Because of this, and because of the orthotropic nature of

81

the composite decking, the orientation of the decking can have a significant effect on the

ability of the slab to carry collapse loads. Thus, specimens will be tested with the decking

ribs parallel to the exterior wall, and with decking ribs perpendicular to the exterior wall.

In addition to the reduced load carrying capacity of the slab when forming a one-

way membrane, there is an additional concern of load redistribution to the undamaged

members. As stated previously, the flexural members around the perimeter of the

damaged area experience significant increases in load in collapse scenarios, which could

lead to their failure. This increase is even more significant in the case of one-way

membrane action, as fewer flexural members are mobilized to carry the redistributed

load. However, there is the possibility for the slab to still be able to form a two-way

membrane even without the presence of an undamaged section on one side of the affected

area. Analysis done by Stevens (2008) showed that the placement of a peripheral tie

along the perimeter of the structure could enable the formation of membrane forces in

both directions, though the membrane action is larger in the direction that provides lateral

restraint (See Figure 2-6). This could reduce the increased demand on the surrounding

structure, improving its robustness, though the effect may be small. The peripheral ties

examined in the study were also subjected to very large tensile forces, likely larger than

those that could be supported by existing composite construction.

The third proposed exterior column loss test will examine whether this behavior is

something that can be readily achieved in composite construction. Depending on the

results of the earlier tests, a new detail will be created to allow the structure to carry a

significant peripheral tie force, allowing the formation of a two-way membrane. The

ability of this tie force to carry tensile loads, as well as the effect of the tie force on the

floor system’s capacity and the demand on the surrounding structure will be evaluated for

their potential to improve the building’s robustness.

82

6 CONSTRUCTION OF TEST FRAME AND FIRST TEST SPECIMEN

This chapter discusses the construction of the test set-up and the first interior

column loss test specimen. The expansion of the foundation and the revisions to the test

frame after expansion are detailed. Construction of the loading system is explained. The

erection of the test frame and specimen is discussed, and the casting of the concrete floor

slab is shown.

6.1 Foundation Pour

The test frame was constructed outside of the University of Texas at Austin

Ferguson Laboratory. The test frame was constructed outside of the laboratory, as space

constraints precluded constructing the test frame inside of the laboratory. The area of

outside of the laboratory chosen for the test frame construction already had an existing

slab on grade that could be used as the foundation for the test setup. However, the

existing foundation in place at the location of the test set-up lacked the size and strength

to support the columns of the test frame. Thus, the foundation needed to be expanded,

and footings needed to be added at the locations of all test columns. For the middle

columns supporting the long restraining beam, there was an existing concrete slab under

them, which did not have the capacity to withstand the expected gravity loads that would

be imposed at that location. Thus, the existing slab needed to be removed to allow the

pouring of a stronger footing under the column. Due to problems during placement of

anchor rods in the expanded foundation, there was less exposed length of anchor rod than

initially designed. This meant that the W4x13 columns could not be attached directly to

the foundation, as there would not be sufficient threads in the anchor rods to secure them.

Couplers were added to the existing anchor rods, and additional threaded rods were

conne

short

colum

the sl

Addit

locati

spaci

frame

geom

with

were

ected to the

ened slightly

mn base plat

lab and base

tionally, dur

ion due to i

ing between

e and speci

metry.

The loadi

a concrete s

constructed

Figure 6

m, so that t

y to allow f

te did not be

e plate to pr

ring placeme

nterference

footings alo

imen were

ing system f

slab at the b

d of 23/32” p

6-1 Coupler

the columns

for this addi

ear directly o

revent exces

ent, some an

with the reb

ong the add

shortened

6.2 Lo

for the test

bottom, and

plywood sh

Attachment

83

s could be a

itional conne

on the slab,

ss flexibility

nchor rods w

bar in the sl

ed slab strip

to ensure c

oading Sys

setup was m

room abov

eets to have

t to Accomm

attached to t

ection length

so spacer pl

y due to dist

ere unable to

lab. This res

ps. The relev

compatibility

stem

made of larg

ve it to add

e outside dim

modate Short

those. The c

th. Due to th

lates were ad

tortion of th

o be placed

sulted in a s

vant membe

y with the

ge square ply

18” of wate

mensions of

t Anchor Ro

columns wer

his detail, th

dded betwee

he base plate

in the desire

slightly lowe

ers of the te

new ancho

ywood boxe

er. The boxe

f 40” x 40”

ds

re

he

en

e.

ed

er

st

or

es

es

x

84

24”. The bottom sheet was attached to the walls with 7-2” exterior screws along each

side. The walls of the boxes would have to stand significant outward pressure from the

water added during testing, and due to the small thickness of the plywood, end screwing

between sheets was unlikely to be able to sustain the resultant load. Thus, 2-ft. long

sections of 2x2 dimensioned lumber were added at each corner, and the walls were

attached to those pieces with 6 2” long exterior screws at each end. To further reinforce

the connections, and seal the boxes, silicone caulking was applied along all seams

between pieces of the formwork. Though constructed of exterior grade plywood, there

was concern that the boxes (as they would be left outside when not in use) would degrade

if rainwater was trapped in them for extended periods of time. Thus, 6 mil plastic

sheeting was used to line the interiors of each bucket, to protect the plywood from the

elements. Unfortunately, the plastic sheeting proved very sensitive to UV radiation, and

broke down rapidly under sun exposure, removing the benefit to the boxes.

Five 7/16” holes were drilled into each wall of the formwork at an 8” spacing to

allow the passage of #3 bars into the formwork, to tie the boxes together in groups of

four, with a 6” spacing between all boxes. The reinforcement chosen was the minimum to

resist shrinkage and cracking of the concrete (to improve water retention ability of the

system), while allowing the maximum flexibility of the system, so it could deform in

tandem with the collapsing floor slab. Additional #2 bars were bent into 180⁰ hooks with

a 4” radius, and placed through the existing drilled holes such that 6” of rebar protruded

from the boxes, ensuring that neighboring groups of buckets still maintained the 6”

spacing between boxes. 1/2" steel tendons were placed that spanned from the center of

one box to the center of the adjacent box, to allow easy movement by either the lab

forklift or a crane during placement of the boxes. Finally, 6” of concrete was added to

each bucket to achieve the desired floor load. Due to uncertainty in exact placement of

concr

asses

attach

of the

woul

stabil

impa

place

were

restra

The r

rete, the bo

sment of the

The colum

hment of the

e restraining

d be in typ

lity purposes

ct on the fi

ed on the gus

left only sn

aining beam

restraining b

oxes were e

e floor load t

mns were a

e restraining

g beam, the

ical constru

s, any additio

nal behavio

sset connect

nug-tight. A

and the col

eam’s conne

Figur

each weighe

they imposed

6.3

all erected an

g beam to th

plumbness

uction. Due

onal out-of-p

or of the fra

tions to the c

laser range

lumns were

ections were

re 6-2 Const

85

ed after cas

d could be c

Test Fram

nd plumbed

e columns a

of the colum

to the signi

plumbness in

ame during t

corner colum

finder was u

shimmed u

e then fully ti

tructed Load

sting was c

calculated.

me

d. Due to th

and the attac

mn was not

ificant over

n the column

testing. The

mns and bolt

used to mea

until the ring

ightened wh

ding Boxes

complete so

he tight toler

chments betw

enforced as

rdesign of th

ns should ha

e restraining

ted together,

asure the dia

g beam was

hile in this co

o an accurat

rances of th

ween section

s strictly as

he braces fo

ave negligibl

g beams wer

, but the bolt

agonals of th

fully square

onfiguration

te

he

ns

it

or

le

re

ts

he

e.

.

centr

sides

adjus

along

beam

held b

the b

girde

the b

were

could

with

The perim

al column b

and the to

stment durin

g the west w

ms. The centr

by the bracin

bottom by an

rs and floor

eams were a

adjusted thr

d be plumbe

a shorter fr

meter top c

bracing chor

op of the re

ng placemen

wall was left

ral column o

ng chords at

n existing fr

beams were

attached and

rough tighten

ed. Next, th

rame, allowi

Figur

hords were

rds attached

estraining fr

nt of the cen

disconnecte

of the specim

t the top of t

rame present

e attached to

d laterally bra

ning of the h

e frame sup

ing sufficien

re 6-3 Erectio

86

then attach

to them. Th

rame. The t

ntral column

d to allow a

men was then

the test fram

t at the lab

o the restrain

acing the co

horizontal cr

pporting the

nt clearance

on of Restra

hed to the c

he cross bra

top braces w

n, and the lo

access for th

n raised into

me. The colum

to within 1”

ning beam a

olumn, the to

ross braces s

column wa

for screw j

aining Beam

corner colum

aces were at

were left lo

ower south

he forklift to

place so tha

mn was then

” of its fina

and central c

op column br

so that the ce

as removed

jacks to be

s

mns, and th

ttached to a

oose to allow

bracing stra

move furthe

at the top wa

n supported a

al height. Th

column. Onc

racing chord

entral colum

and replace

placed unde

he

all

w

ap

er

as

at

he

ce

ds

mn

ed

er

each

heigh

beam frami

ht.

Fi

ng into the

igure 6-4 Te

column, so

emporary Fra

87

the column

ame Support

could be ra

ting Central

aised to its p

Column

precise desiggn

were

disco

along

instal

and f

cover

mode

perim

Once the

laid and c

ontinuities. O

g all beams a

lled in mem

floor beams.

r plates, pilo

el of tek scre

meter of the

flexural me

cut in place

Once all dec

and side lap

mbers up to .

For the atta

ot holes of

ew. Once th

specimen t

Figure 6-

6.4 F

embers were

e to fit aro

cking sheets

ps. All tek sc

345” thick,

achment betw

13/64” were

e decking w

to serve as

-5 Screw Jac

88

Floor Syste

e all in plac

ound the ce

s were in p

crews were s

which accom

ween the dec

e drilled to a

was in place,

the perimet

cks Supportin

em

ce, the deck

entral colum

place, #10 te

special teks/

mmodated t

cking and rin

allow easier

18 gage an

ter formwor

ng Floor Sys

king was laid

mn and oth

ek screws w

/2 screws, d

the flanges o

ng beam, wh

r installation

ngles were at

rk for the co

stem

d. The sheet

her necessar

were installe

designed to b

of our girder

hich had 1/2

n of the sam

ttached to th

oncrete pou

ts

ry

ed

be

rs

2”

me

he

ur.

These

to the

to en

to the

with

angle

attach

the u

Fig

e angles wer

e deck ribs.

sure the stud

e deck ribs,

tek screws a

e, and place

hed with tek

se of sprayab

gure 6-6 Slab

re installed w

This increas

ds could dev

the angle w

at a 12” spac

ed at all ope

k screws. Any

ble foam ins

b Closures (a

with a 2” ove

sed the lengt

velop their fu

was installed

cing. Pour sto

en ends of t

y observable

sulation.

a) Parallel to

89

erhang along

th of concret

ull capacity.

with no ove

op closures w

the decking

e gaps remai

o Deck Ribs

g the restrain

te the shear

Along the r

erlap. Both f

were created

g ribs to sto

ining in the f

and (b) Perp

ning beams p

studs could

restraining b

formworks w

d out of the s

op concrete

floor were se

pendicular to

perpendicula

d bear agains

beams paralle

were attache

same 18 gag

seepage, an

ealed throug

o Deck Ribs

ar

st,

el

ed

ge

nd

gh

direct

reinfo

were

reinfo

bars w

to the

was p

and 9

bendi

exten

reinfo

lower

The weld

tion of deck

orcement. O

placed unde

orcement rol

were placed

e deck ribs a

placed aroun

9” from the

ing of the r

nded higher

orcement, th

ring the max

ded wire rein

k span. Each

Once the wel

er the reinfo

lls were tied

d at 12” spac

and tied to th

nd the perim

edge perpen

reinforcemen

than the ex

he chairs we

ximum heigh

Figure 6-7 P

nforcement w

roll was lai

ded wire wa

orcement at

d to each oth

cing over the

he welded wi

meter of the fl

ndicular to th

nt between p

xpected 4” m

ere manually

ht of the reba

Pour Stop Cl

90

was laid in

id overlappin

as placed, 4-

4-ft. spacing

her at 3-ft. sp

e girders and

ire reinforce

floor at 3” fro

he deck ribs

points of su

maximum h

y shortened

ar to a more

losures and I

5-ft. wide r

ng the previ

-ft. long 3-1/

g. Once the

pacing. Add

d along the r

ment (See F

om the edge

s (Figure 6-8

upport, sectio

height. To im

to an appro

appropriate

Insulation S

rolls perpend

ous roll by o

/2” tall cont

chairs were

ditional 3-ft.

restraining b

Figure 6-8). A

e parallel to

8 and Figure

ons of the r

mprove the

oximate heig

position.

ealing

dicular to th

one square o

tinuous chair

e in place, th

lengths of #

beams paralle

A final #3 ba

the deck rib

e 6-9). Due t

reinforcemen

cover of th

ght of 3-1/4”

he

of

rs

he

#3

el

ar

s,

to

nt

he

”,

FFigure 6-8 RReinforcemennt Layout al

91

ong Restrainning Beam PParallel to Deck Ribs

floor

were

into t

neede

Thus

locati

so the

the d

above

above

F

3-1/2” lon

beams, alw

also installe

the restrainin

ed to be atta

, the small fl

ion of shear

e shear stud

eck ribs, 5/8

e the restrai

e. The fricti

Figure 6-9 Re

ng, 1/2” dia

ays in the “s

ed at the firs

ng beam. Al

ached at the

flute at the ce

r stud placem

would fully

8” threaded r

ning beam a

ion of this c

einforcemen

ameter shear

strong” posi

st low rib ov

ong the gird

center of th

enter of the l

ment. This en

bond with t

rods were pl

and tightene

connection sh

nt Layout alo

92

r studs were

ition away fr

ver the ring b

der, due to th

he low rib to

low rib was

nabled full c

he girder. A

laced throug

ed with 4” o

hould preve

ong RestrainiRibs

e installed a

rom the beam

beams wher

he thin flang

o ensure a go

flattened wi

contact betw

Along the rest

gh the restra

of their lengt

ent slip betw

ing Beam Pe

at each low

m centerline

re the floor b

ges of the gir

ood bond wi

ith a sledgeh

ween the dec

training beam

aining beams

th extended

ween the rod

erpendicular

rib along th

e. Shear stud

beams frame

rder, the stud

ith the girde

hammer at th

ck and girde

ms parallel t

s and deckin

into the sla

d and deckin

r to Deck

he

ds

ed

ds

er.

he

er,

to

ng

ab

ng

93

and function approximately as a stud weld. An additional nut was attached to the

threaded rods and positioned at 3-1/2” above the decking, to function as the “head” of a

shear stud and allow the threaded rod to develop composite action with the concrete slab

in a comparable fashion (See Figure 6-8). Along the restraining beams perpendicular to

the deck ribs, 4” wide, 10” long 1/4” plates were attached at each low rib to the

restraining beam with a 5/8” bolt. The decking was cut back in areas where it extended to

the location of this bolt, to ensure consistency in boundary conditions along the length.

Shear studs were then attached to this plate through the decking (See Figure 6-9).

6.5 Concrete Casting

Before pouring of the concrete, two potential areas of instability were noted in the

test frame. The gusset plates used in the restraining beam to column connections, due to

their large size, had the potential to buckle out of plane, and lose their ability to support

the floor system. Thus, 2 1/2” plates, 10” wide by 14” long, were welded to the ends of

the gusset plates, to serve as a diaphragm tying the plates together (See Figure 6-10a). As

an additional concern, the lateral cross bracing parallel to the deck ribs framed into the

center of the restraining beam cover plate, as did the W4x13 column that provided the

needed vertical support to make the bracing system functional. Due to the relatively thin

cover plate used, and the large distance between the flanges of the restraining beam, the

out of plane flexibility of the cover plates significantly reduced the stiffness of the

bracing system as a whole. Thus, 2 5” wide, 3/4” plates were welded to the bottom side

of the restraining beam between the column and cross brace connections to serve as

transverse stiffeners, preventing local distortions, and improving the effectiveness of the

bracing system (See Figure 6-10b).

throu

pump

build

streng

each

the te

defle

and t

slab.

defle

Due to th

ugh the use

per truck, a

ding specified

gth mix avai

truck so that

est day. Due

ctions occur

thus more de

Mid-span s

ctions. A res

Figure 6-10

he difficult

of a concret

7” slump,

d 3.5 ksi con

ilable from t

t an accurate

e to the flexi

rred during

eflections. T

shoring of t

sin curing co

0 Stiffeners A

access of th

te pumper tr

3/8” aggreg

ncrete, a 4 k

the concrete

e estimate of

ibility of the

concrete cas

This resulted

the beams is

ompound wa

Added to (a)

94

he slab, the

ruck. To en

gate concret

ksi concrete m

supplier. Six

f the true con

e floor beam

sting, o lead

d in the slab

s recommen

as then appli

RestrainingColumn

concrete sl

nsure an unin

te was used

mix was use

x concrete c

ncrete streng

ms mentioned

ding to more

b being heav

nded in futu

ed over the s

g Beam Supp

lab needed

nterrupted f

d. Though t

ed, as that w

cylinders we

gth could be

d in chapter

e concrete b

vier than a t

ure tests to

slab.

ports and (b)

to be poure

flow from th

the prototyp

was the lowe

re taken from

e measured o

3, noticeabl

being poured

typical 4-1/2

control thes

) Middle

ed

he

pe

st

m

on

le

d,

2”

se

95

7 SUMMARY AND CONCLUSIONS

7.1 Summary of Work

This thesis has detailed the design and construction of a test program for

evaluating the response of steel framed composite buildings to a column loss scenario. A

prototype building was designed to match current construction practice and test

specimens were designed based on that prototype building, and scaled down to

accommodate the constraints of the test setup. A test frame was designed and constructed

to simulate the boundary conditions that would be provided by the neighboring bays of a

full structure. A loading system and protocol was detailed to simulate the removal of a

column while providing gravity load, with the option to provide further uniform gravity

loading if necessary to cause failure of the test specimen. As this thesis does not cover the

results of the experimental testing, it is difficult to draw definitive conclusions on the

accuracy of the test program, however, preliminary observations based on literature

review and analysis are summarized below.

7.2 Accuracy of Boundary Conditions

One significant assumption made in the design of this test program was that the

response of a building to a column loss scenario could be modeled accurately looking at

an isolated section of the building, with the effect of neighboring bays simulated by the

presence of a heavy restraining beam around the specimen’s perimeter. This assumption

introduces significant uncertainty into the test program, both in the ability of the ring

beam to provide sufficient restraint, and in the restraint that should be present in a full

96

structure. Depending on the location of the lost column, and the layout of the structure,

the number of neighboring bays around the damaged area can vary widely, changing the

restraint provided to the affected floor. Additionally, the stiffness of the lateral restraint

provided by the neighboring bays could be significantly reduced by local deformation

(particularly deformation in the shear studs and bond slip between the concrete and

composite deck), although there is insufficient experimental data to definitively conclude

this. Thus, the necessary lateral restraint that must be provided by a perimeter beam to

accurately simulate the response of the rest of the structure is not precisely known at this

point. It is the opinion of the author that providing a restraining beam of high flexural and

torsional stiffness (such as the one used in this research) will mirror the response of an

actual structure with reasonable accuracy, as both responses will be dominated by local

flexibility of the shear studs and decking. Testing of a larger section of building, with

neighboring bays present is likely necessary to confirm this assumption.

7.3 Effect of Scale on Results

While the test specimens constructed as part of this research program are of a

large size, many of the components are smaller than what would typically be seen in

modern construction. The precise effect of this scaling down is unknown. The gravity

connections, (both shear tab and clip angle) are made of thinner plates or angles than are

commonly used, and are less deep than common connections. Both of these changes have

been shown in other research to significantly increase the ductility of the connection,

possibly allowing the specimens tested in this project to achieve greater maximum

deflections than could be counted on in a larger span structure. The floor slab is also

made of thinner deck than is often used, and has slightly smaller spans. However,

previous testing on tie forces suggests that this scaling has limited effect on the ductility

97

of the system, with slabs of varying reinforcement ratios and spans all achieving similar

rotations before failure. Unfortunately this testing has been limited primarily to

reinforced concrete slabs, and its applicability to composite slabs is not known.

Nevertheless, it is the opinion of the author that the floor slab used in this test will behave

in a manner similar to the larger span floor slabs typically seen in practice, albeit with the

magnitude of the tie forces scaled down due to the smaller area of steel in the thin deck.

The applicability of this test to larger span structures thus will likely depend on which

system dominates the response. If the specimen’s robustness is provided primarily by the

flexural system (beams, girders and shear connections), the increased ductility of the

smaller connections may lead to an over-prediction in strength if extrapolated to other

structures. If the response is dominated by the floor slab, then the small scale will have

less impact on the results, and the response of the test specimen will likely be similar to

that of a larger span structure, allowing us to draw reasonable conclusions as to the ability

of steel framed composite building to withstand column loss.  

98

APPENDIX A: TEST SPECIMEN AND FRAME DRAWINGS

99

 

 

100

 

 

101

 

 

102

 

 

 

103

 

104

 

 

105

 

 

106

 

 

107

 

 

 

108

 

109

 

 

110

 

 

111

 

 

Figure A

-14 Test F

rame D

etails-Central A

ctuator Support, L

ateral Brace to R

ing Beam

Connection

 F

igureA

-14T

estFram

eD

etails-CentralA

ctuatorS

upportL

ateralBrace

toR

ingB

eamC

onnection

112

 

 

 

113

 

114

 

 

115

 

 

116

 

 

 

117

 

118

APPENDIX B: PROTOTYPE BUILDING PLANS

   

119

 

 

120

 

 

121

 

 

122

 

 

123

 

124

 

 

125

 

 

126

 

 

127

 

 

 

128

 

129

 

 

130

 

 

 

131

 

   

Figure B

-14 Prototype B

uilding-Brace C

onnection Detail 

Figure

B-14

Prototype

Building-B

raceC

onnectionD

etail

132

 

133

WORKS CITED

Abdullah, Redzuan, and W. Samuel Easterling. "New Evaluation and Modeling Procedure for Horizontal Shear Bond in Composite Slabs." Journal of Constructional Steel Research 65.4 (2009): 891-99 Abolmaali, A., A.R. Kukreti, and H. Razavi. "Hysteresis Behavior of Semi-rigid Double Web Angle Steel Connections." Journal of Constructional Steel Research 59.8 (2003): 1057-082

ACI. Building Code Requirements for Structural Concrete: (ACI 318-08); and Commentary (ACI 318R-08). Farmington Hills, MI: American Concrete Institute, 2008. Alashker, Yasser, Sherif El-Tawil, and Fahim Sadek. "Progressive Collapse Resistance of Steel-Concrete Composite Floors." Journal of Structural Engineering 136.10 (2010): 1187-196

AISC. Steel Construction Manual. Chicago, IL: American Institute of Steel Construction, 2005 Thirteenth Edition American Institute of Steel Construction. Steel Design Guide 3. Serviceability Considerations for Steel Buildings. 2003. Second Edition American Institute of Steel Construction. Steel Design Guide 11. Floor Vibrations Due to Human Activity. 1997. ASCE. Minimum Design Loads for Buildings and Other Structures. ASCE/SEI 7-10 Reston, VA: American Society of Civil Engineers/Structural Engineering Institute, 2010. Ashcraft, Douglas. “Steel Deck Design, Specifications, and Details.” Engineering Skills and Development Program. Nov. 2006. Astaneh, Abolhassan, Marwan N. Nader, and Lincoln Malik. "Cyclic Behavior of Double Angle Connections." Journal of Structural Engineering 115.5 (1989): 1101-118.

Astaneh-Asl, Abolhassan, Brant Jones, Yongkuan Zhao, Ricky Hwa, David McCallem and Charles Noble (2001), “Progressive Collapse Resistance of Steel Building Floors”, Report No. UCB/CEE-Steel-2001/03, Department of Civil and Environmental Engineering, University of California, Berkeley.

Bailey, Colin G. "Membrane Action of Unrestrained Lightly Reinforced Concrete Slabs at Large Displacements." Engineering Structures 23.5 (2001): 470-83

134

Brotchie, John F., M.J. Holley. (1971) “Membrane Action in Slabs.” American Concrete Institute Publication SP-30-16. 343-355.

Dusenberry, Donald O., and Ronald O. Hamburger. "Practical Means for Energy-Based Analyses of Disproportionate Collapse Potential." Journal of Performance of Constructed Facilities 20.4 (2006): 336-48 DoD (2009). UFC 4-023-03: Design of Buildings to Resist Progressive Collapse, Department of Defense, Washington, DC.

Ferrer, Miquel, Frederic Marimon, and Michel Crisinel. "Designing Cold-formed Steel Sheets for Composite Slabs: An Experimentally Validated FEM Approach to Slip Failure Mechanics." Thin-Walled Structures 44.12 (2006): 1261-271 Fleischman, R. B., Chasten, C. P., Lu, L. W., & Driscoll, G. C. (1991). Top-and-seat-angle connections and end-plate connections: snug vs. fully pretensioned bolts. Engineering Journal, 28(1), 18-28. Foley, Christopher, Kristine Martin and Carl Schneeman (2007), “Robustness in Structural Steel Framing System”, Report No. MU-CEEN-SE-07-01, Department of Civil and Environmental Engineering, Marquette University, Wisconsin. Geschwindner, Louis F. and Kurt D. Gustafson. “Single-Plate Shear Connection Design to Meet Structural Integrity Requirements.” Engineering Journal. Vol. 3 (2010): 189-202 Griffiths, H., Pugsley, A., and Saunders, O. (1968). Report of the Inquiry into the Collapse of Flats at Ronan Point, Canning Town. Her Majesty's Stationary Office, London, U.K. GSA (2003). Progressive Collapse Analysis and Design Guidelines for New Federal Office Buildings and Major Modernization Projects, U.S. General Services Administration Washington, DC. Hawkins, N. M., and Mitchell, D. (1979). "Progressive Collapse of Flat Plate Structures." ACI Journal, 76(8), American Concrete Institute, Detroit, MI, 775-808. Hayes, B., and R. Taylor. "Some Tests on Reinforced Concrete Beam-slab Panels." Magazine of Concrete Research 21.67 (1969): 113-20

Hendry, A. W. "Summary of Research and Design Philosophy for Bearing Wall Structures." ACI Journal Proceedings JP 76.6 (1979): 723-37

135

IBC. 2009 International Building Code. Washington, DC: International Code Council, 2009 Jahromi, Hamed Zolghadr, Bassam Izzuddin, David Nethercot, Sean Donahue, Michalis Hadjioannou, Eric Williamson, Michael Engelhardt, David Stevens, Kirk Marchand, and Mark Waggoner. "Robustness Assessment of Building Structures under Explosion." Buildings 2.4 (2012): 497-518 Khabbazan, Medhi M. "Progressive Collapse." The Structural Engineer (2005): 28-32 Leon, Roberto T. "Semi-rigid Composite Construction." Journal of Constructional Steel Research 15.1-2 (1990): 99-120.

Liew, J.Y. Richard, T.H. Teo, and N.E. Shanmugam. "Composite Joints Subject to Reversal of Loading—Part 2: Analytical Assessments." Journal of Constructional Steel Research 60.2 (2004): 247-68.

Liu, Judy, and Abolhassan Astaneh-Asl. "Cyclic Testing of Simple Connections Including Effects of Slab." Journal of Structural Engineering 126.1 (2000): 32-39. Marimuthu, V., S. Seetharaman, S. Arul Jayachandran, A. Chellappan, T.k. Bandyopadhyay, and D. Dutta. "Experimental Studies on Composite Deck Slabs to Determine the Shear-bond Characteristic Values of the Embossed Profiled Sheet." Journal of Constructional Steel Research 63.6 (2007): 791-803 Mitchell, Denis, and William D. Cook. "Preventing Progressive Collapse of Slab Structures." Journal of Structural Engineering 110.7 (1984): 1513-532 Park, R. (1964). "Tensile Membrane Behaviour of Uniformly Loaded Rectangular Reinforced Concrete Slabs with Fully Restrained Edges." Magazine of Concrete Research, 16(46), London, England, 39-44. Pearson, Cynthia, and Norbert Delatte. "Ronan Point Apartment Tower Collapse and Its Effect on Building Codes." Journal of Performance of Constructed Facilities 19.2 (2005): 172-77 Popoff, J., A. (1975). "Design Against Progressive Collapse." PCI Journal, March-April, Prestressed Precast Concrete Institute, Chicago, IL, 44-57. Rogers, Colin A., and Robert Tremblay. "Inelastic Seismic Response of Side Lap Fasteners for Steel Roof Deck Diaphragms." Journal of Structural Engineering 129.12 (2003): 1637-646

136

Rogers, Colin A., and Robert Tremblay. "Inelastic Seismic Response of Frame Fasteners for Steel Roof Deck Diaphragms." Journal of Structural Engineering 129.12 (2003): 1647-657 Sadek, Fahim, Sherif El-Tawil, and H. S. Lew. "Robustness of Composite Floor Systems with Shear Connections: Modeling, Simulation, and Evaluation." Journal of Structural Engineering J. Struct. Eng. 134.11 (2008): 1717-725 Sawzuck Antoni. (1965) “Membrane Action in Flexure of Rectangular Plates with Restrained Edges.” Flexural Mechanics of Reinforced Concrete, ACI/ASCE, SP. 12, Detroit, 347–358. Starossek, Uwe. "Typology of Progressive Collapse." Engineering Structures 29.9 (2007): 2302-307 Steel Deck Catalog. Canam Buildings. 2010 Steel Deck Institute. Standard for Composite Steel Floor Deck-Slabs. 2012 ANSI/SDI C-2011 Stevens, David. (2008). “Assessment and Proposed Approach for Tie Forces in Framed and Loadbearing Wall Structures.” Protection Engineering Consultants. Dripping Springs, TX Thompson, S. L. (2009). “Axial, shear and moment interaction of single plate ‘shear tab’ connections.” M.S. thesis, Milwaukee School of Engineering, Milwaukee, WI.

Underwriters Laboratories. Design for Fire Resistance. ANSI/UL D916:2015. Northbrook, IL: Waggoner, Mark. Personal Communication, June 6th, 2012 Xiao, Y. B.S. Choo and D.A. Nethercot. (1994). "Composite Connections in Steel and Concrete. 1. Experimental Behavior of Composite Beam-Column Connections," Journal of Constructional Steel Research. Vol. 34, p. 3-30 Yu, Min, Xiaoxiong Zha, and Jianqiao Ye. "The Influence of Joints and Composite Floor Slabs on Effective Tying of Steel Structures in Preventing Progressive Collapse." Journal of Constructional Steel Research 66.3 (2010): 442-51