ConFire Engineering Pvt. Ltd
1358,13 th lane,Zone 5,Millenium City,Athurugiriya
1
Learning objectives
How to build up a company with registration documents Learn how to act as consultant as well as contractor As contractor our company have managed to build a pedestrian bridge As consultant we have inspected a wind turbine Identify the different bridge designs and construction materials used in
modern day engineering To learn about management process in engineering field
3 OUTLINECONSULTATION
S • Wind Turbine
CONSTRUCTION• Pedestrian
Bridge• Specifications• Design• Time schedule• Cost analysis• Problems
faced
4 Organization Chart of ConFire Engineering Pvt(Ltd)
Board of Directors1. Fernando W.N.M (Mechanical Engineer)2. Thennakoon T.M.N.D (Civil Engineer)
CEO
Fernando W.N.M
(Mechanical Engineer)
Secretary
Mapa M.M.D.A.B
CTO
D.B.Pandithasekara(Charted
Engineer-Mechanical)
Design and Engineering Division
G.R.L.Vinod( Mechanical Engineer)
5 Timeline
Pre- Proposal conference 20th July 2015
RFP due date 27th July 2015
Shortlist interviews 10th August 2015
Planning 17th August 2015
Finalize the design & complete the final design development 24th August 2015
Symposium 31st August 2015
Complete final construction documents
18st September 2015
6 ConsultationContractor-BRANDOUT
Design-Wind Turbine
7 ConstructionClient-Sri Lanka Institute of Information Technology
Design-Pedestrian Bridge
Consultant-Omega Engineering PVT. Ltd
8
Pedestrian Bridge
EQUIPMENTS ENVIRONMENT USES
Drill Machine Sun Shine
Rainy
Helps people to walk across
Connects to locations in a elegant style
Timber(Rubber and Pinus)
MATERIALS PROCEDURE
Decrease the curvature of the arc
AMENDMENTS
ISHIKAWA DIAGRAMMetal cutting Hack Saw
Hammer
Brass Nuts and Bolts
Cutting wood Draw and cut the arc shape
Shaping and grindingAssembling and connect all parts together
Use quality timber and paints
Grinder Machine
9 Pedestrian Bridge details and specifications.
10
11Items Cost
Timber(Rubber and Pinus) Rs. 6000/=
8mm,4 inch brass nut and bolts-24 Rs. 900/=
Steel washers Rs. 60/=Timber Smoothing Process Rs. 500/=
Varnish,thinner,grinding papers and other
Rs. 1000/=
FINAL COST Rs. 8460/=
Cost Analysis
12 Prototype
13 Problems we faced…
To find appropriate and economical timber
To align both arcs
How to cut the arc shape correctly
Which type of nuts should use
Balance of the base stands
14
Phase I
• Collecting the necessary materials for the construction
• Assembling the components• Completed on the 12th September,2015
Phase II
• Testing and development stage: Testing if the bridge is capable of carrying a load of 700N Completed on 21st September,2015
Time schedule
In future…
We can use this technology and the experience we gained in future constructions as engineers
As real engineers we can manage a project according to a given documentation
To design projects such as highways, buildings, bridges and all type of structures for the benefit of humanity and our world
Engineering principles are very useful to communicate with fellow engineers as well as clients
16 Suggestions
As engineering students we would like to suggest more reflective modules like engineering principles
Through out modules like this undergraduates can gain more learning outcomes about management process
Would like to suggest modules like this in future for give an idea about what leadership and group work is?
17
Thank youThennakoon T.M.N.D : EN15549532Vinod G.R.L : EN15550736Fernando W.N.M : EN15552648D.B.Pandithasekara : EN15554314Mapa M.M.D.A.B : EN15555922