complications in financing new nuclear power plants lynn rubow, director, business development...
TRANSCRIPT
Complications inFinancing New Nuclear Power Plants
Lynn Rubow, Director, Business DevelopmentLazarina Bataklieva, Lead Economic Analyst
BULATOM 2011
What we all know….
Large Capital Investment Complex Licensing and Permitting Process Long Term Implementation Nuclear is Exceptionally Safe Long Life with Very Low Production Cost Required Strong Regulatory Platform Required Large Community of Qualified Experts Small Community of Large Gen III or III+ NPP Suppliers Virtually No Air Quality Issues, including CO2 Special Public Sensitivities to Nuclear Technology
WorleyParsons Recent NPP Economic/ Financing Evaluation Experience
Kozloduy Modernization Belene NPP New-Build “Far East” NPP New-Build (Russia) Armenia NPP Unit Replacement Jordan First NPP New-Build Egypt First NPP New-Build Baltic NPP New-Build (Russia)
Historical Financing Approach
For many years, nuclear was a quite conservative investment:– Lower investment costs; – Monopoly (or Franchise) utility, guaranteed electricity offtake; – Long-term (30+ years), low-interest loans, on balance sheet; – Risks generally passed to consumers; – Sovereign financing or sovereign guarantees on financing; and – Generally, reasonable level of public support, or public not entering
the picture.
And now??
Recent Financing Complexities
Higher investment costs Significant impact on company rating and balance sheet Economic crisis Lending terms less attractive (for several reasons) Lack of security for electricity sales
– Secure PPA– No balance sheet– Competition
Governments desire to shed some risk Public opposition more “organized”
Project Funding
Government Domestic banks
Local investors Foreign banks/ Governments
Sources of Equity Sources of Debt
Investors, with Vendors Export credit agencies
Other large utility companies Development Finance Institutions
FinancingFinancing
structurestructure
Critical: Critical:
• Split of Equity (Majority In-Country)Split of Equity (Majority In-Country)
• Maximize ECA and Government LoansMaximize ECA and Government Loans
Technical Developments
50+ years “Lessons Learned” Multiple Redundant Active Safety Systems Extensive Passive Safety Design Continuing Materials Development Improved Operational Reliability/ Availability Long design life However……..
– Limited number of NPP suppliers– Limited number of large “qualified” international investors– Technological development actually restricted by the requirement for
extensive qualification and/ or reference plant support
Time: A Fundamental Issue
0
2
4
6
8
10
12
GT-Simple
GTCC Coal Nuclear PoliticalTerm
Yea
rs Elected Term
Des & Construction
Development
Financing Drivers
Characteristics of a Project Finance (non-recourse) Model: – Reliance on strong PPA; however, in conflict with “free market” that
is theoretically open to competition– Reliance on fuel supply agreement, also somewhat in conflict with
“free market” concept (though less critical for nuclear)– Reliance on strong, more expensive, EPC-LSTK contract
Unbundled market, with associated free market for electricity purchase/ sale is not supportive of the Project Finance Model
Goal of NPP Financing is to strike a balance between free market principles, and the required security to achieve reasonable finance terms. How??
Conflicting Goals
Paths of Development:– Government only– Private entity only– Public-Private Partnerships (PPPs) as a Special Purpose Company
(SPC)…..today’s common approach
Issues of Nuclear Public-Private Partnerships (PPPs)– General difficulty to form PPPs – As a special purpose company, while effective for projects organized
under a “Project Finance” approach, secured by PPA, FSA, EPC-LSTK Agreement, it is more difficult for nuclear projects considering their need for stringent security, and their long-lead nature.
– The SPCs must still have backing – Goals of partnerships can be in conflict
Different Motivation/ Values: Public vs. Private
Public (i.e. Government) Private
Expectation of Benefits over the Long Term;
Expectation of Investment Return in Short Period, signified by high Discount Rate in analysis, but also to capture “cash cow” benefits after debt is paid;
Electricity is a base need of the society. Responsibility to provide reliable electricity supply to population;
Electricity is a “market good”; Plant is responsible to satisfy terms of PPA, and also motivated to participate in the Market, as applicable, to maximize returns;
Highly motivated to achieve acceptable tariff, for Political, Social, and Economic reasons;
Interest is in setting maximum acceptable tariff to achieve return on investment;
Responsibility to Insure Safety, far above required insurance limit;
Responsible to meet insurance requirements;
Motivated to build technical expertise within country.
Satisfy contract requirements for “Capacity Building”.
In the end, there will likely be compromises on both sides to blend long- and short-term needs, and find agreement.
Consider Cash Flows through the Plant Life
Cost of Electricity Escalated and Not Discounted
When you reach year 15 or 20, the “revenue vs. cost” of the plant becomes insignificant
Cost of electricity by Components, annual basis
0
10
20
30
40
50
60
70
80
90
100
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Year of plant operation
EU
R/M
Wh
Loan Repayment
Fuel Costs
O&M Costs
Cost of electricity by Components, annual basis
01020
3040506070
8090
100
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Year of plant operation
EU
R/M
Wh
Loan Repayment
Fuel Costs
O&M Costs
Cost of Electricity Escalated and Discounted at 10%/year
Consider Cash Flows through the Plant Life Cost of electricity by Components, annual basis
01020
3040506070
8090
100
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Year of plant operation
EU
R/M
Wh
Loan Repayment
Fuel Costs
O&M CostsCost of Electricity Escalated and Discounted at 10%/year
Cost of Electricity Escalated and Discounted at 4%/year
Cost of electricity by Components, annual basis
0
10
20
30
40
50
60
70
80
90
100
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Year of plant operation
EU
R/M
Wh
Loan Repayment
Fuel Costs
O&M Costs
Consider IRR Requirements
Higher IRR “Demands” will result in different required tariffs through the plant life
Tariff Path at Different IRR
0
50
100
150
200
250
2010 2015 2020 2025 2030 2035 2040
Ta
riff
, E
ur/
MW
h
IRR 15%
IRR 12%
IRR 10%
IRR 8%
The Case for In-Country Ownership
Many nuclear projects seeking “complex” arrangements involving foreign investment due to: – Lack of equity– Lack of borrowing capacity– Lack of development/ operational expertise
More Issues (in addition to Public-Private issues): – Ultimate responsibility lies within the Project Country– Criteria for quality of investment are different:
Country wants security of long-term power supply Investor wants return on investment as soon as possible BOO model quite expensive to consumer, generally
– Typically, “Earned Equity” is undervalued
100% In-Country Ownership retains both costs and benefits within the border.
Consider Small, Low GDP Country Issues
Many smaller countries are pursuing nuclear as their best option, and now interested in joining nuclear power “club”; however, it is a large undertaking without precedent
Financing security issues of smaller countries: – GDP– Cash– Lending limits– Country rating– Technical base (also a financing issue)
Generally, the primary issue is “affordability”
Some Possible things to Consider
Stronger involvement of Government Stronger involvement of offtakers as investors:
– Large industrial entities– Utilities/ Distribution companies– Smaller, aggregated industrial entities
Return to corporate finance model (e.g. balance sheet based on existing operating assets)
More creative BOO(T) structures EPCM project execution structures Better communication with outside stakeholders, i.e.,
why nuclear is best option
Discussion Items
Can nuclear plant financing be structured as a normal power project??
How to Simultaneously Satisfy Requirements of Public and Private Investors??
What kind of requirements should be imposed on outside investors in NPPs??
How can Lenders become more a part of the process??
How can Public become more a part of the process??