comparison of alternative retrofitting … · fema 273. (1997), guidelines to the seismic...
TRANSCRIPT
1 İnş. Yük. Müh.,Promer Müş. Müh. Ltd. Şti., Ankara
2 İnş. Yük. Müh.,Promer Müş. Müh. Ltd. Şti., İstanbul
3 Dr.İnş. Müh.,Buehler &Buehler Eng. Sacramento/California
4 Principal Str. Eng. Buehler & Buehler Eng. Sacramento California
Email: [email protected]
1
COMPARISON OF ALTERNATIVE RETROFITTING TECHNIQUES
FOR A TYPICAL R/C SCHOOL BUILDING
S. Yıldırım2, A. Sümer
3 , E.Fuller,
4 Y.İ. Tonguç
1
ABSTRACT:
This study consist of 4 different retrofitting techniques on a 4 storey typical school building.
Moreover comparison result of classical retrofitting technique and seismic damper application is
included for an 8 storey administrative reinforced concrete building. All mentioned retrofitting
techniques were technically applicable. The building performance has reached to the level which The
aim of this study was to compare them economically. Compered retrofitting techniques were classical
(adding R/C shear walls and R/C jacketing of columns), Adding Braced Steel Frames, Adding
Buckling Restrained Bracing Frames (BRBF) and Base Isolation. Shear Wall addition and R/C
jacking of columns is studied using Turkish Earthquake codes (TEC) whereas Other 3 techniques are
studied using ASCE 41 due to lack of necessary criterias in TEC.
ANAHTAR KELİMELER : Retrofitting, Base Isolation, Inovative Retrofitting Techniques.
1. EXISTING BUILDING INFORMATION
Figure 1: Google Earth view. Photo 1: Front view.
District : Kadıköy Total Construction area : 3020m2
Campus Name : Gözcübaba High School Number of students : 600
Construction time : 1994 Concrete Quality : A Bl: 8.5 MPa; B
Bl: 7.1 MPa
Number of storey : 4
2
2. RETROFITTING WITH SHEAR WALL ADDITION
The reason of using conventional techniques were;
Being more familier for engineers,
No need for high skilled workers,
Matearials can be found from Turkish Market.
More economical for this kind of typical buildings.
Disadvantages;
Building need to be evacuated,
8-10 months for construction,
High Architectural disturbance,
The following additions were done in this alternative.
Interior and Exterior R/C shear wall additions were done respectively,
4 Shear walls added and 2 existing shear walls were reconstructed for x-direction
4 Shear walls were added for y-direction
29 of 44 columns were jacketed at the Ground and 1 st Floor
14 of 42 columns were jacketed at the 2 nd Floor
4 of 42 columns were jacketed at the 3 rd Floor
Typical plan view of retrofitted building can be seen in Figure 2.
Figure 2: Typical Retrofitted Plan view.
Table 1: Compartive Results of Retrofitted Building.
Assessment of the retrofitted building using Shear walls and column jacketing can be seen in table 2.
There can be seen some beams in collapse and heavy damage region in both X and Y direction.
Because αs were higher than 75%, beams are considered as secondary members and not retrofitted as
per Ismep Guidelines 2008. Displacement, natural periods are decreased while mass and shear force
are increased as it is expected for Retrofitted Building. Retrofitted building satisfied conditions of
Turkish Earthquake Code (TEC 2007).
Approximate total structural cost for retrofitting with additional shear walls and R/C column jacketing
can be seen in table 4.
Table 2: Assessment of Retrofitted Building Using Additional Shear Walls X-Direction
Table 3: Assessment of Retrofitted Building Using Additional Shear Walls Y-Direction
Table 4: Structural Retrofitting Cost With Shear Wall Addition
4
3. ALTERNATIVE RETROFIT SOLUTIONS
3.1 BRACED FRAME RETROFIT
A Preliminary Design and analysis that details can be seen in Figures 3,4,5 were performed by
Eric Fuller in order to get cost estimation of Braced Frame (OCBF) and Buckling Restrained
Bracing Frame (BRBF) Retrofitting.
Solution originally based on equivalent displacement to
concrete solution
Displacement requirements of this solution
reduced building functionality to the point where
it was unreasonable
Shifted to force based solution
Deleted all existing shear walls to eliminate
displacement compatibility issues
Design threshold at 75 percent of total base shear per
guidelines section 4.5.2.2
Beam performance ignored
Due to larger drifts jacketing of many columns required
Photo 2: OCBF Installation
Photo 3: OCBF Installation Photo 4: BRBF Installation
Ordinary Concentric Braced Frame solution (OCBF)
Buckling Restrained Braced Frame solution (BRBF)
Brace locations at perimeter when possible
Grade beam foundations kept linear
Minimizes demolition
Existing columns remain stable
Design Criteria:
R=4.0 , I=1.4, Cd=3.0
Interstory Drift:
1.6 cm OCBF
3.0 cm BRBF
0.6 cm Concrete (for comparison)
Figure 3: Section 1 OCBF Figure 4: Section 2 OCBF
6
Figure 5: Foundation Plan View of Braced Framed Building
Figure 6: Details of Beam at Braced Frame Figure 7: Details of Brace Frame Footing
Table 5: Steel Bracing Addition Retrofitting Cost Summary Table.
3.2 BUCKLING RESTRAINED BRACING FRAME (BRBF) RETROFIT
Application of Buckling Restrained Bracing Frames are
very similar to OCBF. Differences are:
Core plate is allowed to yield without buckling
in both tension and compression
BRB elements are specified by core plate area
which defines capacity
Advantages of BRBF solutions over OCBF are
lower system demand and increased
predictability
Table 6: Buckling Restrained Bracing Frame Retrofitting Cost Summary Table
3.3 BASE ISOLATION RETROFITTING
A Preliminary Design which is seen at Figure 8 was done by Ian Aiken (Siecorp) in order to get cost
estimation for base isolation retrofitting.
8
38 SLİDER 18 LEAD
RUBBER
Figure 8: LRB and Slider Application
Figure 9: Assumed Section of Base Isolation Application
Table 7: Base Isolation Application Cost Summary Table
Although Base Isolation Application has some advantages such as;
Minimum architectural disturbance,
Having minimum acceleration for upper structure
System has some disadvantages for this kind of typical school buildings in Turkey such as;
High cost,
Completely imported material,
Long time period and high cost for testing (No qualified, certified test center in Turkey).
Technical difficulties and cost of installing isolators under an existing building.
4. CONCLUSSIONS
Comparison Parameters of Retrofitting techniques are not only the cost for sure. The following
parameters can be considered in choosing retrofitting technique.
Total Cost,
Construction Time,
Material availability in Turkish Market,
Special conditions of the building such as historical buildings,
Possibility of evacuating the building.
Amount of architectural disturbance
For typical school buildings which is considered in this study the most important parameter between
these is the cost. Economical comparison chart can be seen in Figure 10.
Figure 10: Economical Comparison Chart of Alternative Retrofitting Techniques
10
5. RESOURCES
Turkish Earthquase Code 2007.
ASCE 41-06. (2006), Seismic Rehabilitation of Existing Buildings. American Society of Civil
Engineers.
FEMA 273. (1997), Guidelines to the Seismic Rehabilitaion of Existing Buildings. Federal
Emergency Management Agency.
FEMA 356. (2000), Prestandard and Commentary for the Seismic Rehabilitation of Buildings.
Federal Emergency Management Agency.