![Page 1: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/1.jpg)
Ansaldo STS Sweden
COMBINED SE-DKATP SYSTEM
FORØRESUND LINK
05/10/2009
![Page 2: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/2.jpg)
05/10/2009
Ansaldo STS Sweden
2
BACKGROUND• History• Characteristics Swedish ATP – Danish ATP• Strategic Considerations• Decision
PRINCIPLES• Combined ATP• Automatic Switch-Over• Scenarios• Units
CONCLUSIONS• Experience• The future
TOPICS
![Page 3: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/3.jpg)
05/10/2009
Ansaldo STS Sweden
3
SWEDISH ATP• Introduced late 70’s• Updated ‘ATC2’ early 90’s• Wayside equipment supplied by Bombardier (Ebicab 700
~98%) and Ansaldo (L10000 ~2%)• Onboard equipment supplied by Bombardier (Ebicab 700
~10%) and Ansaldo (L10000 ~90%)• Full brake profile monitoring, based on the train’s individual
braking characteristics
DANISH ATP• Introduced late 80’s• Wayside equipment supplied by Siemens (ZUB123 100%)• Onboard equipment supplied ny Siemens (ZUB123 100%)• Full brake profile monitoring, based on the train’s individual
braking characteristics
HISTORY
![Page 4: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/4.jpg)
05/10/2009
Ansaldo STS Sweden
4
SWEDISH ATP• Balises located between rails• Minimum two balises at one
location (balise group)• Signal info and civil speeds from
separate groups• Frequency range 27 / 4.5 MHz• Digital DMI display without
speedometerDANISH ATP• Balises located on the right hand
side of running rails• Only one balise at a location• Signal info and civil speeds from
same balise• Frequency range 100 / 850 kHz• Analogue and digital DMI display
with speedometer
SYSTEM CHARACTERISTICS
![Page 5: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/5.jpg)
05/10/2009
Ansaldo STS Sweden
5
DMISWEDISH ATP
DANISH ATP
![Page 6: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/6.jpg)
05/10/2009
Ansaldo STS Sweden
6
A. ERTMS?
B. DUAL WAYSIDE?
C. DUAL ON-BOARD SYSTEMS?
D. DUAL WAYSIDE / DUAL ON-BOARD?
CONSIDERATIONS
![Page 7: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/7.jpg)
05/10/2009
Ansaldo STS Sweden
7
A. ERTMS?• Not a mature system 1997• No STM:s available
B. DUAL WAYSIDE?• Requires whole section
to be fitted with both systems
C. DUAL ON-BOARD SYSTEMS?• Requires all trains on
the link to be fitted with combined ATP
D. DUAL WAYSIDE / DUAL ON-BOARD?• Same as C, but with the possibility for
future upgrade to dual wayside• Requires some means of system
selection when in ‘dual wayside’ area
CONSIDERATIONS
![Page 8: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/8.jpg)
05/10/2009
Ansaldo STS Sweden
8
D. DUAL WAYSIDE / DUAL ON-BOARD!
• Initially, all trains operating on the link will be fitted with a dual system
• In the future, the link Copenhagen- Malmö can be fitted with both systems
• Once this step has been taken, then trains fitted with Swedish ATP can operate to Copenhagen and trains fitted with Danish ATP can operate to Malmö
• Trains fitted with the dual system can operate beyond these without constraints
DECISION
![Page 9: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/9.jpg)
05/10/2009
Ansaldo STS Sweden
9
• Capable of operating on Danish lines without constraints• Capable of operating on Swedish lines without constraints• Capable of operating on a line equipped with both ATP
systems• Capable of switching from one mode of operation to the other
at speeds up to 200 km/h
REQUIREMENTS
![Page 10: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/10.jpg)
05/10/2009
Ansaldo STS Sweden
10
BLOCK DIAGRAM
![Page 11: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/11.jpg)
05/10/2009
Ansaldo STS Sweden
11
SYSTEM SELECTIONPANEL (SSP)
![Page 12: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/12.jpg)
05/10/2009
Ansaldo STS Sweden
12
TRACK LAYOUT
![Page 13: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/13.jpg)
05/10/2009
Ansaldo STS Sweden
13
• DRIVING FROM SWEDEN TO DENMARK
• DRIVING FROM DENMARK TO SWEDEN
• CHANGING PRIORITY
• SELECTING DANISH ATP EXCLUSIVELY
• SELECTING SWEDISH ATP EXCLUSIVELY
SCENARIOS
![Page 14: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/14.jpg)
05/10/2009
Ansaldo STS Sweden
14
DRIVING FROM SWEDEN TO DENMARK (Startup)
• Activate Cab• Both systems startup• Self test and enter train data in both
systems• Both Systems start supervising default startup conditions• SSP: Indicates priority• SE ATP reads first signal balises and speed board balises• Drive train length• SE DMI will light up and SE ATP will commence full
supervision• SE ATP sends ‘Supervising’ flag to DK-ATP• DK ATP extinguishes all displays and ‘Max Speed’ indicator
is set to zero• DK ATP ceases supervision and enters ‘F’ state• SSP: DK ‘state’ lamp will change green > yellow
SCENARIO — SE > DK
![Page 15: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/15.jpg)
05/10/2009
Ansaldo STS Sweden
15
DRIVING FROM SWEDEN TO DENMARK (Switch-over)
• DK ATP reads first DK balise• DK ATP lights up and starts monitoring• SSP: DK ‘state’ lamp will change yellow > green• DK ATP sends ‘Supervising’ flag to SE ATP• SE ATP will extinguish all displays• SE ATP ceases supervision and enters ‘F’ state• SSP: SE ‘state’ lamp will change green > yellow• SE ATP reads ‘system switch-over’ balises and ‘border’
balises (ignored, because SE ATP is now in ‘F’ state)
NB: The changeover is slightly different, pending which system is prioritized
SCENARIO — SE > DK
![Page 16: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/16.jpg)
05/10/2009
Ansaldo STS Sweden
16
DRIVING FROM DENMARK TO SWEDEN (Startup)
• Activate Cab• Both systems startup• Self test and enter train data in both
systems• Both Systems start supervising default
startup conditions• SSP: Indicates priority• DK ATP reads first balise• DK DMI will light up and DK ATP will commence full
supervision• DK ATP sends ‘Supervising’ flag to SE-ATP• SE ATP extinguishes all displays• SE ATP ceases supervision and enters ‘F’ state• SSP: SE ‘state’ lamp will change green > yellow
SCENARIO — DK > SE
![Page 17: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/17.jpg)
05/10/2009
Ansaldo STS Sweden
17
DRIVING FROM DENMARK TO SWEDEN (Switch-over)
• DK ATP reads last DK balise, which includes information on the upcoming system switch-over
• SE ATP reads first SE signal balises and speed board balises• Drive train length• SE ATP lights up and starts monitoring• SSP: SE ‘state’ lamp will change yellow > green• SE ATP sends ‘Supervising’ flag to DK ATP• DK ATP will extinguish all displays and ‘Max Speed’ indicator
is set to zero• DK ATP ceases supervision and enters ‘F’ state• SSP: DK ‘state’ lamp will change green > yellow
NB: The changeover is slightly different, pending which system is prioritized
SCENARIO — DK > SE
![Page 18: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/18.jpg)
05/10/2009
Ansaldo STS Sweden
18
FROM PRIORITY SWEDISH ATP TO PRIORITY DANISH ATP
• Both systems have information for full supervision• SE ATP is prioritized• SSP: ‘Priority SE’ illuminated• SSP: Press ‘Priority DK’ button until it illuminates• SSP: ‘Priority SE’ is extinguished• DK ATP illuminates and starts monitoring• SSP: DK ‘state’ lamp will change yellow > green• DK ATP sends ‘Supervising’ flag to SE ATP• SE ATP ceases supervision and enters ‘F’ state• SSP: SE ‘state’ lamp will change green > yellow
NB: Changing priority from Danish ATP to Swedish ATP follows a similar procedure
SCENARIO— CHANGING PRIORITY
![Page 19: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/19.jpg)
05/10/2009
Ansaldo STS Sweden
19
SELECTING DANISH ATP
• This procedure may only be undertaken at standstill• Danish ATP must not be selected when the train is in an area
not fitted with Danish ATP• SSP: Press ‘DK’ button until it illuminates• SSP: Other buttons are extinguished• DK ATP illuminates and starts monitoring• SSP: DK ‘state’ lamp will change yellow > green• DK ATP isolates SE ATP• SE ‘state’ lamp is extinguished
NB: Selecting SE ATP follows a similar procedure, but requires breaking a seal.
SCENARIO— SELECTING EXCLUSIVE ATP
![Page 20: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/20.jpg)
05/10/2009
Ansaldo STS Sweden
20
SIGNAL EQUIPPED WITHBOTH ATP SYSTEMS
![Page 21: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/21.jpg)
05/10/2009
Ansaldo STS Sweden
21
DRIVER’S CABEMU
![Page 22: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/22.jpg)
05/10/2009
Ansaldo STS Sweden
22
DRIVER’S CABFREIGHT LOCO
![Page 23: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/23.jpg)
05/10/2009
Ansaldo STS Sweden
23
SYSTEM SELECTION PANEL
![Page 24: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/24.jpg)
05/10/2009
Ansaldo STS Sweden
24
ATP CABINET
![Page 25: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/25.jpg)
05/10/2009
Ansaldo STS Sweden
25
INTERFACE BOX
![Page 26: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/26.jpg)
05/10/2009
Ansaldo STS Sweden
26
• The combined SE – DK ATP system has now been in service since 2000
• Over 200 systems supplied• Very reliable, including safe switch-over up to 200 km/h• Can be upgraded to dual wayside, should the need arise• Will most probably be replaced by ERTMS in the future
CONCLUSIONS
![Page 27: COMBINED SE-DK ATP SYSTEM FOR ØRESUND LINK · 2015. 10. 7. · Ansaldo STS Sweden. 4. SWEDISH ATP • Balises located between rails • Minimum two balises at one location (balise](https://reader035.vdocuments.mx/reader035/viewer/2022071404/60f7d90594bf18044c5f99e5/html5/thumbnails/27.jpg)
Ansaldo STS Sweden
THANK YOU FOR YOUR ATTENTION