    Code of Construction Practice Part A:General Requirements

    Track Changes

    December 2013

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    2/118

    Code of Construction PracticePart A: General Requirements

    This page left intentionally blank

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    3/118

    Code of Construction PracticePart A: General Requirements

    i

    Thames Tideway Tunnel

    Code of Construction Practice

    Part A: General RequirementsList of contents

    Page number

    1 Introduction ...................................................................................................... 11.1 General .................................................................................................... 1

    2 General requirements ...................................................................................... 52.1 Environmental impact assessment .......................................................... 52.2 Environmental management system ....................................................... 52.3 Construction environmental management plan ....................................... 52.4 Enforcement ............................................................................................ 8

    3 Communications and community/stakeholder liaison ............................... 114 General site operations ................................................................................. 15

    4.1 Construction process ............................................................................. 154.2 Working hours ....................................................................................... 154.3 Worksite layout ...................................................................................... 204.4 Controls for works outside main site areas ............................................ 224.5 Cranes ................................................................................................... 224.6 Site lighting ............................................................................................ 234.7 River works ............................................................................................ 234.8 Security.................................................................................................. 254.9 Emergency preparedness plan .............................................................. 264.10 Pollution incident response .................................................................... 274.11 Fire prevention and control .................................................................... 284.12 Electromagnetic interference ................................................................. 284.13 Unexploded ordnance ........................................................................... 294.14 Utility works ........................................................................................... 294.15 Worker access ....................................................................................... 304.16 Clearance of site on completion of activities .......................................... 304.17 Considerate Constructors Scheme ........................................................ 30

    5 Public access, the highway and river transport .......................................... 335.1 Traffic management and control ............................................................ 335.2 Lorry management and control .............................................................. 35

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    4/118

    Code of Construction PracticePart A: General Requirements

    ii

    5.3 Works within the highway or on a Public Right of Way .......................... 365.4 Road cleanliness ................................................................................... 375.5 Highway and public right of way reinstatement ...................................... 385.6 River transport and works ...................................................................... 385.7 References ............................................................................................ 39

    6 Noise and vibration ........................................................................................ 416.1 General .................................................................................................. 416.2 Working hours ....................................................................................... 426.3 Section 61 consent applications ............................................................ 446.4 Noise and vibration control measures ................................................... 456.5 Noise insulation and temporary re-housing ........................................... 486.6 Noise and vibration monitoring .............................................................. 506.7 Suitably qualified persons ...................................................................... 506.8 References ............................................................................................ 51

    7 Air quality........................................................................................................ 537.1 General .................................................................................................. 537.2 Vehicle and plant emissions .................................................................. 537.3 Dust emissions ...................................................................................... 547.4 Dust control ........................................................................................... 547.5 Dust and particulate monitoring ............................................................. 557.6 Odours ................................................................................................... 567.7 References ............................................................................................ 56

    8 Water resources ............................................................................................. 598.1 General .................................................................................................. 598.2 Site drainage ......................................................................................... 598.3 Protection of watercourses .................................................................... 608.4 Control of pollution of surface water ...................................................... 618.5 Control of pollution to groundwater ........................................................ 628.6 Management of impact on abstraction boreholes .................................. 638.7 Flooding ................................................................................................. 648.8 Dewatering ............................................................................................ 658.9 Ground treatment .................................................................................. 658.10 Monitoring .............................................................................................. 668.11 Dredging ................................................................................................ 668.12 References ............................................................................................ 67

    9 Land quality .................................................................................................... 699.1 General .................................................................................................. 69

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    5/118

    Code of Construction PracticePart A: General Requirements

    iii

    9.2 Site assessment and remedial practice ................................................. 699.3 Site works .............................................................................................. 719.4 References ............................................................................................ 72

    10 Waste management and resource use ......................................................... 7510.1 Excavated material options assessment and Excavated material and

    waste strategy ....................................................................................... 7510.2 Duty of care ........................................................................................... 7710.3 Asbestos waste management................................................................ 7810.4 Resource use ........................................................................................ 7910.5 References ............................................................................................ 80

    11 Ecology (aquatic and terrestrial) .................................................................. 8111.1 General .................................................................................................. 8111.2 Procedures ............................................................................................ 8111.3 Detailed provisions ................................................................................ 8211.4 Habitat and species considerations ....................................................... 8211.5 Aquatic ecology receptors (marine mammals, fish and invertebrates) .. 8511.6 Protection of trees ................................................................................. 8611.7 Reinstatement landscaping ................................................................... 8711.8 References ............................................................................................ 88

    12 Historic environment ..................................................................................... 8912.1 General .................................................................................................. 8912.2 Procedures ............................................................................................ 8912.3 Detailed provisions ................................................................................ 9012.4 References ............................................................................................ 91

    13 Third-party impact and asset protection process ....................................... 9313.1 Protection of existing infrastructure and buildings ................................. 9313.2 Monitoring and action plans ................................................................... 94

    Glossary .................................................................................................................. 95Appendix A : Section 61 application guidance .................................................. 101Appendix B : Construction Environmental Management Plan Template ........ 107

    List of tables

    Page number

    Table 4.1 Classification of different types of working hours ..................................... 16Table 6.1 Noise trigger levels .................................................................................. 49

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    6/118

    Code of Construction PracticePart A: General Requirements

    iv

    List of abbreviations

    AURN Automatic Urban and Rural Network

    BPG Best practice guidance

    BPM Best practicable meansCEMP(s) Construction environmental management plan(s)

    CIRIA Construction Industry Research and Information Association

    CoPA Control of Pollution Act 1974

    CoCP Code of Construction Practice

    CSO(s) Combined sewer overflow(s)

    DCO Development Consent Order

    EA Environment Agency

    EH English Heritage

    EIA Environmental impact assessment

    EMS Environmental Management System

    EPP(s) Emergency preparedness plan(s)

    ES Environmental Statement

    FRA Flood risk assessment

    GLA Greater London Authority

    HBMCE Historic Buildings and Monuments Commission for England

    HSSE Health, Safety, Security and Environment

    MMO Marine Management Organisation

    OAWSI Overarching Archaeological Written Scheme of Investigation

    PLA Port of London Authority

    PPG(s) Pollution Prevention Guidelines(s)

    SPZ Source protection zone

    SRN Strategic Road Network

    TBM(s) Tunnel boring machine(s)

    TfL Transport for London

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    7/118

    1 Introduction

    Code of Construction PracticePart A: General Requirements

    1

    1 Introduction

    1.1 General

    1.1.1 All works covered in this document are to be managed and performed tothe culture within the Thames Tideway Tunnel projectsvision of ZeroIncidents, Zero Harm, Zero Compromise.

    1.1.2 This Code of Construction Practice(CoCP) is submitted as part of theapplication for development consentapplication (the application) for theThames Tideway Tunnel project (the project). The development consentorder (DCO) is an order under the Planning Act 2008 approving adevelopment; it is the statutory instrument defining the terms under whichdevelopment consent would be granted.

    1.1.3 The principles and requirements within this CoCPrelate to themanagement of construction impacts and are to be read in conjunctionwith safety legislation and the employers Health, safety, security andenvironment standard( the HSSE Standardi) for contractors.

    1.1.4 The CoCPhas been carefully developed to reduce and minimisetheeffectsof the projectduring construction. It aims to provide appropriateand clear means of monitoring and enforcing compliance with a widerange of good practice measures and sets out a series of measures andstandards of work, which will be applied by the contractor throughout theconstruction period to:a. provide effective planning, management and control duringconstruction to manage and mitigatepotential impacts on people,

    businesses and the natural and historic environment

    b. provide the mechanisms to engage with the local community and itsrepresentatives throughout the construction period.

    1.1.41.1.5 The employer is the party responsible for the delivery of the project, (ie,the party in whom the powers of the DCOare vested or transferred,todeliver the project). The employeris responsible for all of the works, whichincludes overseeing the contractor. The employerwill have a projectmanagement organisation in place,which will be suitably skilled and

    resourced to undertake this duty.1.1.51.1.6 The term construction in the CoCPincludes all physical works undertaken

    to implement the project: utility diversions, site preparation, demolition,material delivery, removal of excavated material removal,andwasteremoval, tunnelling and shaft construction, interception of existingcombined sewer overflows (CSOs), installation of equipment, landscaping,commissioning, and all related engineering and construction activities asdefined in Schedule 1 of to theDCO).

    i

    This will be produced for the project to achieve outstanding arrangements for health, safety, security andenvironment.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    8/118

    1 Introduction

    Code of Construction PracticePart A: General Requirements

    2

    1.1.61.1.7As the project extends across 14 local authoritiesLondon boroughs, theCoCPestablishes the basis for a consistent approach to the managementof construction impacts across local authority boundaries,and with arange of key stakeholders. Any construction codes or guidancedocuments relating to construction that have been produced by the local

    authorities were considered during the preparation of this document.1.1.71.1.8 The CoCPcomprises of two parts:

    a. Part A: General requirements. These measures are applicableproject wide.

    b. Part B: Site-specific requirements. These are minimum site-specificmeasures,identifying or deviations from the general requirementsindicated in Part Athat will be implemented by the contractor.

    1.1.81.1.9 The CoCPsets out a series of measures to be applied throughoutconstruction to mitigate the potential impact of site activities. Significant

    effects from construction insofar as they may affect onthe natural andhuman environment, amenity and safety of local residents, road users andtraffic flow, businesses and the public,. Anysignificant effects fromconstruction will be limited in the vicinity of the works by implementation ofthe code.

    1.1.91.1.10 The CoCPsupports the planning and delivery of the project in asustainable, efficient and cost-effective manner to meet the objectives ofthe Sustainability Statement,. It also andpromotes co-operation with otherprojects in the vicinity, as far as practicable, in order to reduce combinedimpacts.

    1.1.101.1.11 The contractor will adhere to a works contract, which thatwill referenceUK water industry standards, Thames Water requirements for capitaldelivery standards and Sewers for Adoption,as appropriate.

    1.1.111.1.12 Requirements within the DCOstate that the project shall will be carriedout in accordance with both Parts A and Part B of theCoCPunless agreedotherwise with therelevantlocal authority. Further specific measures foreach site may be made through amendments to the CoCP Part Bs, inagreement with the relevant local authority and in consultation with therelevant key stakeholders including Transport for London (TfL), theEnvironment Agency (EA), the Port of London Authority (PLA), the Historic

    Buildings and Monuments Commission for England (HBMCE, formerlyreferred to as English Heritage), and the Marine ManagementOrganisation(MMO).

    1.1.121.1.13 When an agreement or approval is sought from the relevant localauthority and not obtained (or obtained on terms that are not satisfactoryto the employer), then it will be open to the employer to appeal to theSecretary of State under the appeal mechanism set out in the DCO(Sschedule 17, para.4). Applications made further to rRequirements areto be regulated by virtue of Schedule 17,paras.1 to3); and any otherapplications or requests made under the DCO are to be regulated by DCOarticle 53(2).

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    9/118

    1 Introduction

    Code of Construction PracticePart A: General Requirements

    3

    1.1.131.1.14 Within this document, the terms reasonable and practicable meansare used. Any decision of what is reasonable or practicable will be madeby the employer in accordance with the terms of the works contracts.

    1.1.15 Within this document,the term consultation is used to describe theprocess of sharing and discussing draft information with stakeholders. ThecConsultation will take have due regard to any comments received,wherever practicable. If no comments are returned within the consultationperiod,this will be deemed as to mean tacit acceptance. The length ofconsultation periodsof consultation may vary.

    1.1.16 Throughout the CoCPa number of plans, procedures and reports arereferenced. For the purposesof this document,the following terms aredefined as:

    a. Approved: When a plan, procedure, report or other item is to beapproved, this means that it needs to be signed-off by a regulatorybody that itasmeetsingthe legislative and project requirements by theapprovinga regulatory body and/or by the employer as specified withinthis document

    b. Agreed: When a plan, procedure, report or other item is to be agreed,this means that the relevant 3rdthirdparty is informed and/or satisfiedthat the submission meets the intended and/or specifiedrequirements;.Ttypically this is a non-regulatory authority, eg,.utility orland owner

    a.c.Accepted: When a plan, procedure, report or other item is accepted, itmeans that it is provided for information and meets the specified

    requirements with respect to content. Typically this is for works underthe contract between the employerand the contractor,and is part ofthe employers supervision of the project.supervision by the employer

    1.1.17 Where the CoCPstates approved or agreed by the employer,thistheplan, procedure, report or other itemwill be implemented via the NEC3contract between the employerand the Ccontractor and is administered bythe acceptance procedures of the Project Manager, as defined within thecontract.

    1.1.141.1.18 The contractor will comply with the terms of the DCO,including thisCoCPand any other relevant legislation referenced in this document or

    otherwise, or any legislation amending or replacing it.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    10/118

    1 Introduction

    Code of Construction PracticePart A: General Requirements

    4

    This page left intentionally blank

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    11/118

    2 General requirements

    Code of Construction PracticePart A: General Requirements

    5

    2 General requirements

    2.1 Environmental impact assessment

    2.1.1 An environmental impact assessment (EIA) has been undertakenwascarried outfor the project and an Environmental Statementhas beenprepared in accordance with the Infrastructure Planning (EnvironmentalImpact Assessment) Regulations 2009, as amended. Through the EIAprocess, mitigation identified with respect to construction effects hasbeenwasembedded within the CoCPin order to form part of the proposalsfor the construction of the project. The findings of the EIA are reported intheEnvironmental Statement.

    2.1.2 The employerwill ensure that the residual environmental effects of theconstruction and operation of the project are not worse than those

    described in the Environmental Statement. In line with this duty, thecontractorswill have to implementthe mitigation measures described inthe Environmental Statement, or any other appropriate or equivalentmitigation measures.

    2.1.3 The Environmental Statementis, therefore, a worst case assessment interms of adverse environmental effects,which the employerandcontractor will seek to improve on within those bounds.

    2.1.22.1.4 The contractor will comply with and provide implement the mitigationmeasures described in the CoCP.

    2.2 Environmental management system

    2.2.1 The contractor will be required to develop and implement anenvironmental management system (EMS) consistent with BritishStandard (BS)EN ISO 14001: Environmental Management. This will bealigned with the employers EMS,and will set out:

    a. the contractors environmental policy

    b. the procedures to be implemented to deliver and monitor compliancewith environmental legislation

    c. the procedures to be implemented to deliver and monitor compliancewith the environmental provisions in this CoCP.

    2.2.2 The contractors EMS will ensure and demonstrate that all theenvironmental requirements of the contract and all relevant legislation,standards, regulations and consents are being met.

    2.3 Construction environmental management plan

    2.3.1 The contractor for each work package shall will produce and implementsite-specific construction environmental management plans (CEMPs) foreach site,in full accordance with the CoCP,for approval by the employer,in consultation with the local authority, the EA and HBMCEand the EA.The CEMPswill demonstrate how the CoCPwill be implemented by the

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    12/118

    2 General requirements

    Code of Construction PracticePart A: General Requirements

    6

    contractor through by means of the contractorsitsEMS. The CEMPswillbe produced as part of and supporting in support of the constructionphasesplan that will define how works and associated risks will bemanaged in compliance with the HSSE Standard.

    2.3.2 The CEMPswill be form the overarching environmental management planfor each site,covering general site operations and overall management ofthe construction works. It They will include, but is not be limited to, detailsof the controls with regard to general site layout and operations, workinghours, site lighting, security, emergency planning and response, fireprevention and control, utility works and worker access and welfare. TheCEMPswill include the following specific management plansincluding:

    a. Pollution incident response plan (refer to Section4): to include detailsof controls to be adopted and procedures to be followed to manageany pollution incidents.and procedures to be followed in the event ofany pollution incidents.

    b. Emergency preparedness plan (refer to Section4): this willtoincludeprocedures to deal with hazards and incidents,and will to take intoaccount ofthesecurity requirements.

    c. Lighting management plan (refer to Section4.6): to provide designlayouts and to demonstrate how the requirements are met by thedesign.

    d. Traffic management plan (refer to Section5): to include details oftraffic (and lorry) control measures, site access points, access for non-motorised users (eg, cyclists and pedestrians), public roads that will be

    used during construction and control of construction traffic, togetherwith advertising and notification procedures regarding planned roadworks. Highway and Public Right of Way reinstatement and rivertransport and navigational controls will also be included. Rivertransport management will include river transport and navigationalcontrols.

    e. Noise and vibration management plan (refer to Section6): to includedetails of measures to control and mitigate noise and vibration duringconstruction,theSection 61 consent application process, together withdetails regardingandmonitoring systems to be employed during theconstruction works.

    f. Air quality management plan (refer to Section7): to include details ofcontrol measures for dust and air pollutioncontrol measures, vehicleand plant emissions,and odour.

    g. Water management plan (refer to Section8 and Section10.4): toinclude details of water use, site drainage, protection of watercourses;,controls to prevent contamination of surface water and groundwaterresources, flooding, dewatering, dredging;,and together withmonitoring systems to be employed during the construction works.

    h. Land quality (refer to Section9): although not a management plan, this

    will include details of site assessment and remedial practices.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    13/118

    2 General requirements

    Code of Construction PracticePart A: General Requirements

    7

    i. Site waste management plan (refer to Section10): to include detailsfor of the handling, storage, transfer and removal of waste materialsand contaminated materials, as well as measures to be implementedfor the reuse or recycling of excavated material and waste.

    j. Ecology and landscape management plan (refer to Section11): toinclude details of procedures and mitigation measures relating tolegally protected and notable species, as well as habitat protection andreinstatement.

    k. Heritage management plan(HMP)(refer to Section12): to includedetails of measures for protecting listed structures,and archaeologicalfindsand , as well as controls to be put in place to protect heritageassets adjacent to the construction workssites.

    l. Community liaison plan (refer to Section3): to includeplans forengagement withcommunities, local authorities and otherstakeholders as well as y engagement,helpline/website information,as well as local authority and other stakeholder engagement. A and amechanism for dealing with complaintswill also be detailed.

    m. Resource management plans (refer to Section 10.4): these will includedetails for resource use management (water, energy and materials).

    2.3.3 The CEMPs, its the subsidiary plans and other management plans,will belive documents that are subject to updating and refinementwill be updatedand refinedby the contractor as required necessary, in response to thechanging needs of the works during construction. The contractor shall willagree gainobtainapproval for alterations in to the scope of the CEMPs

    with from the employer,and in consultation with relevant stakeholders,including the relevant local authority. See Appendix B for the structure ofthe CEMP.

    2.3.4 The CEMPswill set out the contractors arrangements to for providingesupervisory and site personnel with relevant, adequate training relevant totheir roles prior to being before they are employed on the a constructionsite, including project induction and site-specific environmental induction.Supervision, training and competency requirements are set out in theconstruction phasesplan.

    2.3.5 The CEMPswill include details of those responsible for theireffective

    implementation of the plan and will also set out the procedures to beimplemented in order to monitor compliance with the plan CEMPs duringconstruction.

    2.3.6 The contractorswill manage sites and achieve formal certification underthe Considerate Constructors Scheme operated by the ConstructionFederation (refer to Section4.3).

    2.3.7 The Ccontractorsresponsible for tunnelling will be required to follow theAssociation of British Insurers/British Tunnelling Societys,Code ofPractice for Risk Management in Tunnelling.

    2.3.72.3.8 The CEMP will set out the environmental mitigation that mustbe

    embedded into the working methods.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    14/118

    2 General requirements

    Code of Construction PracticePart A: General Requirements

    8

    2.4 Enforcement

    2.4.1 Compliance with the provisions of this CoCPwill be enforceable by virtueof a number of mechanisms.

    2.4.1 A breach of the Code of Construction PracticeCoCPwould effectively be abreach of a DCOrRequirement (project-wide Requirement PW6 requirescompliance with the CoCPPart Aand Bs).

    2.4.2 Project-wide requirement PW4 requires the details of the body or bodiesresponsible for undertaking each of the works at a site to shallbe providedto the local planning authority. Both the contractor and the employer wouldbe potentially be open to enforcement action under Section 161 of thePlanning Act 2008 and, in theevent offailure to comply with the terms of aSection 61 notice, under the Control of Pollution Act1974 ( the CoPA).

    2.4.22.4.3 Compliance with the provisions of this CoCPwill be enforceable by virtue

    of a number of mechanisms.2.4.3 Compliance will be enforceable against the employer by virtue of project

    wide requirement PW6, which requires compliance with the CoCPPart A(as well as those site specific requirements addressing the CoCPPart Bfor that site).

    2.4.4 The employer will be able to enforce the contractors compliance throughthe construction contracts. Compliance will be enforceable by theemployer against the contractor through the construction contracts whichbetween the employer and the contractor will enter into.

    2.4.5 In addition, tThe CoCPobliges the contractor to seek and obtain consent

    pursuant to sSection 61 of the Control of Pollution Act 1974 (CoPA)for theway in which certain works are to be carried out., and l Local authoritieswill have the power to serve a notice under Section 60 of the CoPA in theevent that the terms of the consent are not adhered to. Contravention ofthe requirements of such a notice without a reasonable excuse is anoffence.

    2.4.6 Similarly, the CoCPidentifies certain other consents, licences and permitsthat will bearerequired by under other legislation, and thesewhichprovidea further means of ensuring that the works are carried out in the way thatisasdescribed in the CoCP.

    2.4.7 Each contractors project manager will be responsible for ensuring that thework is planned and managed to be undertaken in accordance with allrequirements of theisCoCP. Each contractors project manager willrequire their its environment manager to undertake a programme ofmonitoring and auditing to confirm compliance.

    2.4.8 Site inspections and audits will be carried out by the employer todetermine the ensurecompliance with the CoCP. Regulating authoritiesmay also attend site to confirm ensure compliance with relevant permitsand consents.

    2.4.9 The construction contract will require the contractor to ensure that all sub-contractors and suppliers meet the requirements of the CoCP.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    15/118

    2 General requirements

    Code of Construction PracticePart A: General Requirements

    9

    2.4.10 The following compensation policies will be secured by way of a sSection106 obligation given to all relevant local planning authorities:

    a. Exceptional hardship procedure

    b. Non-statutory mitigation compensation procedure

    c. Non-statutory disturbance compensation procedure

    d. Settlement Information Paper(but not including the Settlement Deed,since Thames Water is offering that already)

    e. Noise insulation and temporary re-housing policy.

    2.4.11 Documents (a) and (d) were appended to the last version of the CoCP.Theyhave now been removed as they will be updated and secured via adifferent mechanism.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    16/118

    2 General requirements

    Code of Construction PracticePart A: General Requirements

    10

    This page left intentionally blank

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    17/118

    3 Communications and community/stakeholder liaison

    Code of Construction PracticePart A: General Requirements

    11

    3 Communications and community/stakeholderliaison

    3.1.1 The employerand contractor will provide community/stakeholder relationspersonnel, who will be focussed on engaging with thecommunity/stakeholder to provide appropriate information and be the firstline of response to resolve issues of concern. The employerandcontractor will take reasonable steps to engage with nearby residents,including those who may be detrimentally affected by constructionimpacts. The contractor employerwill ensure thatthe contractor informsoccupiers of nearby properties are informed in advance of works takingplace, including the type and duration of the activity. In the case of workrequired in response to an emergency, the local authority and localresidents will be advised as soon as reasonably practicable that short

    notice work is taking place. This will comply with the HSSEcommunication procedure (refer to HSSE Standard, Section8.1).

    3.1.2 The contractor will develop, in conjunction with the employer, acommunity liaison planwith, and for approval by the employer, which willinclude the following:

    a. Monitoring of contractor and subcontractor compliance withundertakings and performance against relevant commitments, localagreements and specific community requirements throughout theproject. (These will be defined in the Sustainability StrategyStratementand in the project environmental management plan).

    b. Maintenance of regular communication with the community, otherstakeholders and affected parties to ensure they are all kept informedof the scope of works being undertaken, and the progress of the worksand programme. The contractor will be required to produceinformation sheets of the works to be carried out, detailing expecteddisruptions and the measures being taken to minimise or mitigateadverse impacts of these works, at least two weeks prior toconstruction activity taking place. A liaison plan will be issued inadvance to the employer and appropriate local authorities, detailingthe information to be supplied, for acceptance approval by the

    employer. The plan will include details and a map of properties to benotified directly with information sheets.

    c. For tunnel boring, a website will be established (by the employer) thatwill provide information on the forecast and actual passage of thetunnel boring machines (TBMs). The contractor will be required todistribute leaflets along the route of the tunnel drives, giving notice ofthe forecast passage of the TBMs as the work progresses.

    d. Liaison with appropriate local community projects, employment andeducational initiatives.

    e. Provision of a point of contact for a small claims procedure, relating to

    claims of physical damage to property, or minor injuries. The

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    18/118

    3 Communications and community/stakeholder liaison

    Code of Construction PracticePart A: General Requirements

    12

    contractor will assist in enabling any claims to be progressed promptlyin co-ordination with the employer and insurer.

    f. Co-ordination of preconstruction defect surveys in properties whichhave been identified. Liaison, in conjunction with the employer, withthe building surveyor employed to carry out the surveys, and also tomaintain a dialogue with the relevant property owners throughout theduration of the works.

    3.1.3 Appropriate meetings will be held with residents (or their representatives),businesses and other local occupiers to keep them informed about theworks, and to provide a forum for them to express their views. Therelevant local authority will be invited to participate.

    3.1.4 The employer will maintain a telephone helpline service during theprogramme construction period to handle enquiries and concerns from thegeneral public. It will also act as a first point of contact for information inthe case of any emergency. All calls will be logged, together with a recordof the responses and action taken. Appropriate contacts and responsetimes will be the subject of a detailed procedure to be agreed prior to thecommencement of construction. Potentially affected occupiers will benotified of the helpline number and it will be widely advertised.

    3.1.5 A confidential reporting line will be operated by the employer which links tothe HSSE and Project Incident Plan.

    3.1.6 A complaints register will be maintained by the employeror the contractor,and a copy will be provided to the relevant local authority each month (orsuch other interval as is agreed with the local authority). The contractor

    will notify the employer of complaints when they are received, along withthe event and any on-going actions.

    3.1.7 Onsite communications, such as daily shift and activity briefings will beused to advise the site workforce of health, safety, environmental, andcommunity matters. This will include information obtained from communityliaison on items such as noise generation and access issues, together withconstraints detailed in the contracts (eg, working hours). Thiscommunication will be given to all relevant workforce, including newstarters and sub-contractors, before they commence work. Furtherinformation can be found in the health and safety documentation. Toolboxtalks will be used as a means to disseminate information to the workforce

    on a routine basis.

    3.1.8 The employer will establish a framework of coordination andcommunication meetings with key stakeholders. The contractor will attendmeetings as required and arrange other meetings where required. Anyother meetings identified by the contractor will be notified to the employer.Meetings will include a regular traffic/transport liaison meeting with TfL,EA, PLA, and Natural England where relevant, and the associatedborough to consider all sites in that borough.

    3.1.9 The employer will also establish project-wide coordination meetings withlocal authorities, TfL, the EA, PLA, and Natural England at critical phases

    throughout the works for the scheme as a whole.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    19/118

    3 Communications and community/stakeholder liaison

    Code of Construction PracticePart A: General Requirements

    13

    3.1.9 Any plans which have been consulted on and approved by the employerwill be notified to the relevant stakeholders (eg,emergency preparednessplan).

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    20/118

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    21/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    15

    4 General site operations

    4.1 Construction process

    4.1.1 The construction of the project will extend across central London andrequire a number of major construction sites as well as smallerconstruction sites.

    4.2 Working hours

    General

    4.2.1 The activities at the worksites are varied and include construction of majorshafts, tunnels and other activities that will be constructed over extendedperiods of time and will include periods of working on a continuous 24-

    hour, seven days a week basis.

    4.2.2 There will be variations in the hours of working between different siteswhich will be dependent on the ability to mitigate the potential effects ofsite working. The specific land uses and potential receptors surroundingthe sites will also influence the working hours. The working hours by typeof site are described in paras.4.2.11 to4.2.13.

    4.2.3 Working hours are identified in the CoCP Part B for each site.Requirements within the DCOprovide that the project will be carried out inaccordance with both Part AandPart Bsof theCoCP,unless agreedotherwise with the local authority. The contractor may apply pursuant toSection 61 of the Control of Pollution Act 1974 to vary these working hourswhich will have been fixed and approved by virtue of the CoCPPart B inthe light of the contractorsdetailed working methods. Further Section 61application guidance is contained in Appendix A.

    4.2.4 The Section 61 application process will include submitting noise andvibration predictions and associated mitigation, as appropriate and agreedwith the local authority. This is detailed in Section 6 of this document.Whenimplementing best practicable means(as defined in the CoPA)forthe control of noise and vibration, as defined in CoPAmeasureswill beconsistent with the recommendations of BS5228 (2009): Code of practice

    for noise and vibration control on construction and open sites.

    4.2.5 This section provides details of the working hour classifications, as well asthe flexibility to enable detailed agreement of the works between thecontractors and local authorities through Section 61 consents,dispensations or variations to ensure that the construction activities aremitigated in order to protect local sensitive receptors.

    Classification of working hours

    4.2.6 The working hours at the worksites will depend on the constructionactivities. The following table classifies the types of working hours that will

    be applied.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    22/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    16

    Table 4.1 Classification of different types of working hours

    Classification Description

    Standard working hours

    8am 08:00 to 6pm 18:00

    weekdays

    8am 08:00 to 13:00 6m Saturday

    Plus up to one hour before andafter for mobilisation, ie, 7am07:00 to 7pm 19:00 weekdays,7am 07:00 to 2pm14:00Saturdays

    Plus maintenance periods1pm 13:00 to 5pm 17:00Saturdays

    10am 10:00 to 4pm 16:00Sundays

    These hours consist of:

    a. standard working hours

    b. mobilisation period

    c. maintenance period.

    These are the standard hours that will apply tothe majority of worksites and constructionactivities.

    These hours are the same as those that aredefined by most local authorities within theirindividual boroughs.

    Mobilisation period: Mobilisation activities will

    comprise the following: arrival and departure ofworkforce and staff at site and movement to andfrom place of work (if parked up, engines to beturned off, staff to remain considerate ofneighbours, no loud music or raised voices);general refuelling (from jerry cans only, use offuel tractors/bowsers to be limited to standardworking hours); site inspections and safetychecks; site meetings (briefings and quietinspections/walkovers); site clean-up (sitehousekeeping that does not require the use ofplant); site maintenance; and low keymaintenance and safety checking of plant andmachinery (provided this does not require orcause hammering or banging etc).

    Mobilisation does not include lorry movementsinto and out of the sites.

    Maintenance period: The activities allowed inthis period are limited to those that do not causesignificant noise or vibration. Maintenanceactivities will comprise general mechanical

    maintenance to construction machinery andplant such as cranes, excavators, compressors,grouting equipment and dewatering pumps.Only essential maintenance works will beundertaken on Sundays.

    Extended working hours

    6pm 18:00 to 10pm 22:00weekdays

    1pm 13:00 to 5pm17:00Saturdays

    These are intermittent and are required to covercertain construction activities that will not becompleted during standard working hours.

    These activities comprise works for majorconcrete pours and piling/diaphragm wall works.

    The number of work activities that require theseextended working hours are limited, and are not

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    23/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    17

    Classification Description

    necessarily on consecutive days.

    The detail of the duration and frequency of theintermittent requirement for extended working

    hours will be included within the Section 61application.

    Where these works are not defined within theCoCP Part B, they will be agreed with the localauthority through a Section 61 consent,dispensation, or variation, and notified torelevant stakeholders (eg, TfL).

    Continuous working hours

    12am 00:00 to 0012:00pmMonday to Sunday

    For the tunnel construction activities, theunderground work andessentialsurfacesupport activities will be undertaken on a

    continuous 24-hour, seven days a week basis.Underground work includes maintenance ofunderground machinery and plant.

    Essential Surface surface support activitiescomprise works required to support tunnellingincluding excavated material processing andhandling, shaft lifting operations, tunnel liningsupply, grout and concrete batching plantoperation, barge loading and movements.

    Out of hours/possession working

    It is beneficial to undertake a number ofactivities outside of the standard working hours.These are required:

    a. for utilisation of periods of low traffic flowsfor items such as abnormal loads/construction plant delivery; works within thehighway or footpaths; works affectingoperational railways

    b. for utilisation of periods with low demand orflows for utility diversions and works on theexisting sewer system

    c. to ensure minimum disruption to thirdparties who may have on-going operationsduring the day.

    This will be agreed with the local authoritythrough a Section 61 consent, dispensation orvariation, and in consultation with relevantstakeholders.

    Tidal working Certain works are located in the foreshore andthe construction activities will be required to beundertaken at high or low tides. Any tidal

    working outside of standard working hours willbe agreed with the local authority through a

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    24/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    18

    Classification Description

    Section 61 consent, dispensation or variation,and notified to relevant stakeholders.

    River and rail transport hours

    As continuous working hours12am 00:00 to 12pm00:00Monday to Sunday

    Main tunnel construction sites have the

    opportunity for excavated material to beremoved by barge or train. At these sites bargeand/or train loading and transfer will be on acontinuous 24-hour, seven days a week basis.

    The movement of barges from constructionsites is linked to the state of the tide and will beundertaken when the tide suits bargemovement. Small CSO sites using the river willbe dealt with on a site-by-site basis in Part B ofthe CoCP.

    Short notice working On a major project such as this, there is thepotential for works that need to be completed orundertaken to secure and make safeconstruction operations that will be outside thestandard working hours.

    At the commencement of the works, theprocess for notifying and coordinating theseworks with the local authorities and relevantstakeholders will be agreed with the localauthority through a Section 61 consent,dispensation or variation, and notified to

    relevant stakeholders.

    4.2.7 Key support activities are required for safeguarding the works and arerequired to be in operation and maintained on a continuous 24-hour,seven days a week basis. This includes items such as site security,pumps, ventilation fans, cranes and compressors. Such equipment will beshielded to provide noise attenuation, as appropriate (refer to Section6).

    4.2.8 Suitably qualified staff will be required to undertake monitoring and collectdata and samples outside the standard hours, both within the worksite andin the surrounding areas.

    Deliveries and lorry movements

    4.2.9 Deliveries will be arranged to limit impacts on the road system. Deliveriesand all vehicle movements will be restricted to standard working hours, orextended hours, unless agreed with the local authority through a Section61 consent, dispensation or variation, or site specific requirements in theCoCPPart B. Abnormal and special loads (as defined in the RoadVehicles (Authorisation of Special Types) (General) Order 2003 (S.I.2003/1998) may be delivered outside standard working hours, subject tothe requirements of the highways authority and the police. Any furtherrequirements for a specific site will be included in the CoCP Part B. Lorry

    movements during extended working hours must relate to the activity thatrequires the extension.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    25/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    19

    4.2.10 Deliveries by lorry at night may be allowed subject to agreementwithapproval fromthe local highway authority in accordance with relevantlegislation on a site-specific basis; for example, in areas away fromsensitive noise receptors.

    Description of site types and associated working hoursMain tunnel construction sites

    4.2.11 The main tunnel (including Greenwich and Dormay connection tunnels)will be constructed from a number of worksites. The construction phasesundertaken on each worksite will include associated development works,site establishment, shaft construction, tunnel construction, shaft and tunnellining, surface works and commissioning.

    4.2.12 The tunnel construction phases (including secondary lining) will beundertaken on a continuous working hour basis. The other constructionphases will be undertaken within the standard working hours unless

    otherwise agreed with the local authority through either a Section 61consent, dispensation or variation, and notified to relevant stakeholders.

    4.2.13 There are practicality considerations that necessitate the construction ofdiaphragm walls, and for other major concrete pours for the main shafts tobe undertaken beyond extended working hours.

    CSO sites

    4.2.14 The construction phases, activities and durations for the CSO interceptionworks and shafts will vary depending on the location; the working hourswill depend on the construction phase.

    4.2.15 The majority of the construction phases and activities will be completedwithin the standard working hours.

    4.2.16 Certain activities cannot be completed within the standard working hoursand will require extended hours. These activities comprise majorconcrete pours and piling/diaphragm wall works during shaft construction.

    4.2.17 A number of the construction sites will operate as connection tunnel drivesites, where the tunnelling works will be undertaken on a continuousbasis. This applies to both short and long connection tunnels.

    CSO interception works

    4.2.18 A number of construction sites require connections to existing sewers andoutfalls outside of the shaft construction sites. These works includerequirements for traffic management (where works require temporaryclosure of the carriageway) and may be appropriate to be undertakenoutside the standard working hours.

    Associated development works

    4.2.19 Associated development works are required, including traffic managementand utility diversions. The working hours for these activities will aim tominimise disruption to traffic and the local environment. Any works givingrise to any significant noise effect will be captured under the Section 61

    process, and as such approved by the local authorityand will be agreedwith the local authority in consultation with the highway authority. It may

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    26/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    20

    be appropriate for certain work, such as works within existing highways, tobe undertaken in out of hours/possession working hours.

    4.3 Worksite layout

    4.3.1 The contractor will ensure that the site layout and appearance will bedesigned using the following principles:

    a. All sites will be fully secured with appropriate hoardings or fences, asdefined in the employers specification.

    b. Noise generating activities will be sited away from noise sensitivereceptors or screened so as not to exceed agreed levels.

    c. Storage sites, fixed plant and machinery equipment and temporaryoffices will be located to limit environmental impacts, and have dueregard to neighbouring properties and the constraints of each site.

    d. The site layout will also consider and limit where practical, potentialimpacts from restrictions to natural light to adjacent property.

    e. Site lighting will be located and directed so as to minimise intrusioninto occupied residential properties and on sensitive areas includingthe river, and will not constitute a road, rail or river hazard.

    f. River sites will have appropriate lighting to assist river navigation inaccordance with relevant legislation, such as the Port of London Act1968.

    g. Internal vehicle routes will be arranged to minimise the risk of mudbeing carried out of the site.

    h. Site drainage will be carefully considered to minimise areas of mud inone part of the site contaminating other areas.

    i. Security cameras will be sited and directed so that they do not intrudeinto occupied residential or commercial properties.

    j. Site plant and facilities will be powered from mains electrical sources,where reasonably practicable.

    k. Where required temporary fencing will include appropriate noiseattenuation.

    l. Pedestrian access to and from adjacent residential and commercialpremises will be maintained.

    4.3.2 The contractor will display an information board containing contact names,telephone number and address, and the helpline number at appropriatelocations on the boundaries of the sites (refer to Section3 for more detail).This will be in accordance with the employers specification.

    4.3.3 The type of hoarding or fencing is required to comply with the followingprinciples:

    a. Meet the employersspecification and standard detailed drawings.

    b. The standard hoarding will be 2.4m high unless specified otherwise.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    27/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    21

    c. The extent and height of hoarding or fencing at a particular locationwill be selected to maintain effective security and achieve appropriatenoise attenuation, dust containment and visual screening.

    d. Hoardings will be maintained in good condition throughout thecontract.

    e. Measures will be used for tree protection (refer to Section11.6).

    f. Where reasonably practicable, existing walls, fences, hedges andearth banks will be retained (also to aid in site security wherepracticable).

    g. Notices will be displayed on all site boundaries, where appropriate, towarn of hazards onsite such as deep excavations and constructionaccess.

    h. Appropriate sight lines/visibility splays will be maintained to ensuresafety of both vehicles and pedestrians is preserved (refer to the

    HSSE Standard).

    i. Temporary fences may be used in certain areas, such as forshort-term occupation of sites or at more remote locations. Whereindicated in the CoCP Part Bs, temporary fencing will includeappropriate noise attenuation.

    4.3.4 Hoardings where required will be of a design appropriate to the characterof the surrounding townscape. This may include one or more of thefollowing:

    a. incorporation of art work visualising the proposed development or

    photographic views of the local area or incorporating art work,mounted onto standard well maintained hoardings

    b. incorporation of viewing windows into standard well maintainedhoardings to preserve important views and provide opportunities toobserve construction activity

    c. incorporation of a full cover of climbing plants on dark green paintedhoardings, with the plants trimmed back only to allow for essentiallighting and health and safety signage.

    4.3.5 Vehicle access and egress points will have gates positioned such that nogate will open outwards onto the highway where possible. As far as isreasonably practicable, gates will be located to allow vehicles to drive intothe site, clear of any public highway. Where provided for noise control,gates will be of a similar material and construction to the boundary inwhich they are situated, and will be closed except when being used foraccess (refer to theHSSE Standard, Section 9).

    4.3.6 The contractor will obtain any required hoarding licences from theappropriate highway authority if the hoarding has to be placed on highwayland. Where the area of works is stopped up and the hoarding falls withinthe stopped up area, a licence will not be required.

    4.3.7 The contractor will promote and enforce good housekeepingarrangements on all the construction sites to ensure that clean, tidy andsafe sites are provided. Arrangements will be implemented to provide

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    28/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    22

    effective preventative pest and vermin control and prompt treatment of anypest and vermin infestation. The contractor will ensure that the risk ofinfestation by pests and vermin is minimised. Adequate arrangements fordisposing of food waste or other attractive material must be implemented.If infestation occurs the contractor must take action to eliminate the

    infestation and prevent further occurrence. Measures will be implementedto protect ecologically sensitive areas or legally protected and/or notablespecies (refer to Section11 for further details). This will be assessed aspart of the Considerate Constructor Scheme, where applicable.

    4.3.8 The contractor will ensure that welfare facilities appropriate to the type ofsite (eg, drive site) are provided. The facilities will be connected to mainsservices and drainage, where reasonably practicable. Alternativearrangements will be provided when connection to the mains is notpossible (refer to theHSSE Standardfor further details).

    4.3.9 Where there is potential for crane arcs to impact on trees and other

    ecology, suitable protection measures will be implemented (refer toSection11).

    4.4 Controls for works outside main site areas

    4.4.1 This includes work activities around existing sewer systems andconnection or construction works to existing CSOs.

    4.4.2 In general, the principles detailed within this CoCPwill apply, asappropriate, to other works, having regard to size, location, duration andscope of works being undertaken.

    4.4.3 Each site requires appropriate method statements, risk assessments andconsultation and approval withfromthe employer, the local authority andrelevant stakeholders.

    4.5 Cranes

    4.5.1 Crane arcs will be confined within the site boundary or limits of land to beacquired, unless agreed otherwise with the local authority in accordancewith statutory legislation for use of cranes which over-sail the publichighway, and property owners/occupiers whose air space is affected (eg,London Underground, Docklands Light Railway, TfL, Network Rail, PLA).The contractor will obtain the relevant permissions (eg. Licence for use ofcrane which over-sails the public highway), in accordance with therelevant legislation, from TfL or the local authority, as appropriate, forcranes located adjacent to roads. Cranes will be operated in accordancewith the requirements of BS7121, Code of Practice for Safe Use ofCranes.

    4.5.2 Where there is potential for crane arcs to impact on trees and associatedecology, suitable protection measures will be implemented (refer toSection11).

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    29/118

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    30/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    24

    Construction activities in the river of foreshore

    4.7.2 Prior to construction activities starting (including temporary works), thecontractor will provide further information to the MMO, the PLA and the EAabout proposed river works including:

    a. construction methodologies

    b. materials to be used, including backfill to cofferdams

    c. timings to construction activities

    d. details of environmental mitigation measures

    a.e.details of contractors and vessels to be used.

    Dredging activities

    4.7.3 Prior to dredging activities starting, the contractor will provide furtherinformation to the MMO, the PLA and the EA including:

    a. dredging methodologies

    b. descriptions of dredge materials, including sediment quality sampleanalysis where appropriate ( e.g. for the determination of the presenceor otherwise of contaminants within those sediments to be dredged)

    c. timings of the dredging activities

    d. dredging volumes

    e. waste disposal locations and quantities

    f. details of environmental mitigation measures

    g. details of contractors and vessels to be used.

    Removal of temporary works

    4.7.4 Prior to removal of any temporary works from the river of foreshore, thecontractor will provide further information to the MMO, the PLA and the EAincluding:

    a. removal methodologies

    b. waste disposal locations and quantities for backfill materials

    c. timing of removal activities

    d. details of foreshore reinstatement measures and material to be used

    e. details of environmental mitigation measures

    f. details of contractors and vessels to be used.

    Removal of in-river piles

    4.7.24.7.5 The contractor willdesign in river piling to facilitate removal, and makereasonable effort to remove all piles completely from the bed of the riverupon will make reasonable effort to remove all temporary piles completelyfrom the bed of the river prior to completion of the works.

    4.7.34.7.6 With the prior written agreement of the PLAandin accordance withrelevant legislation,or as part of the River Works Licence,, tthe contractor

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    31/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    25

    will ensure any piles which prove impossible to fully extract on applicationof the confirmed minimum crane pull of 40 tonnes, are driven down, cut offor removed to a depth of a least 1 metre below the adjacent riverbed levelunless advised otherwise.

    4.7.44.7.7As the works are carried out the contractor will compile and makeavailable for inspection by the PLA a survey report and plan, with plottedcut-off piles, a suitable permanent reference point, a note of the top levelof each pile and adjacent riverbed level relative to chart datum. Uponcompletion of the works the contractor will provide a copy of the completedsurvey report and plan to the PLA.

    4.7.8 The top of any cut-off piles will be retained and kept available forinspection by the PLA during the progress of the works and each one willbe marked with the reference given to its pile stump in the survey so thatby using the survey and plan the PLA can identify which stump it camefrom.

    Cofferdam construction

    4.7.9 The temporary and permanent material used for fill within cofferdams andtemporary construction within the foreshore is to be suitable for use withinthe river environment and not cause any potential contamination to theriver.

    Scour and accretion

    4.7.54.7.10 Prior to commencement of any part of the works which would be withinthe river, a scour monitoring and mitigation plan for that part of the works

    shall be prepared by the contractor in consultation with the MarineManagement Organisation, the Environment Agency, the Port of LondonAuthority and English Heritage and submitted to and approved by theMMO. The scour monitoring and mitigation plan shall be prepared inaccordance with the Scour and accretion monitoring and mitigationstrategy for temporary and permanent works in the foreshore.

    4.8 Security

    4.8.1 Site security is a significant issue, particularly for central London, and withhighly visible construction sites. The contractor will comply with the HSSE

    Standardrelating to security details full requirements including thefollowing:

    a. The contractor will ensure that all construction sites are secure andhave manned security on a 24-hour basis (swipe card access may beconsidered). Access to the site will be limited to specified entry pointsonly and all personnel entries/exits will be recorded and monitored forsecurity, health and safety purposes.

    b. The contractor has a statutory duty to prevent unauthorised access tothe site and will carry out site-specific assessments of the security andtrespass risk at each site, and implement appropriate control

    measures.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    32/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    26

    c. The site boundary will be secured and constructed such that itminimises opportunities for unauthorised entry. The boundary will bemonitored remotely by CCTV at relevant locations. These locationswill be determined in consultation with the local authority or local policeas appropriate. Should the site boundary suffer damage, it will be

    immediately rectified by the contractor.d. The contractor will consult with local crime prevention officers to

    determine security proposals for each site and to identify any securityissues at particular sites with regular liaison to review securityeffectiveness and response to incidents.

    4.9 Emergency preparedness plan

    4.9.1 The employer will put in place an emergency preparedness plan(refer tothe HSSE Standardfor further details) at each site location, which the

    contractor will be required to adhere to. The procedures will bestandardised, as far as possible, across the worksites and will be adaptedto be appropriate to the anticipated hazards and the specific layout. Theplan will include emergency pollution control measures that will take intoaccount EA guidelines. The emergency procedure will contain emergencyphone numbers and the method of notifying local authorities, statutoryauthorities and local community representatives. Contact numbers for thekey employer and contractors staff will also be included. The approvedEmergency preparedness plan will be notified to relevant stakeholders.

    4.9.2 Consideration will also be given to vulnerable buildings and elements oftransport infrastructure.

    4.9.3 The contractor will ensure that the legislative requirements will be followedfor the provision of safe site access points. This might include forums withrelevant emergency services where appropriate. In all cases, thearrangements put in place will also be suitable for and in consultation withthe emergency services (London Ambulance Service, London FireBrigade, and the Metropolitan Police).

    4.9.4 The contractor will need to have standby equipment readily available (eg,road diversion signs).

    4.9.5 The contractor will ensure procedures are in place for awareness of flood

    warning and preparation for a potential flood event relevant to the floodrisks of each site. This will include the identification of an evacuation routeand potential refuge areas in the event of a flood to enable egress andaccess from the site.

    4.9.6 The plan will need to cover key areas of monitoring and mitigationactivities. This includes for buildings, transport and utility infrastructure,and riverbed monitoring for scour. Any separate plans for these areasneed to be identified and referenced.

    4.9.7 Suitable spill kits will be provided and positioned in vulnerable areas andstaff will be trained in their use and a record will be kept of all pollution

    incidents or near-misses, to ensure appropriate action is taken andlessons are learned. Regular toolbox talks will be held to raise staff

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    33/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    27

    awareness of incident prevention and share lessons learned. There willbe written procedures in place for dealing with spillages and pollution (thepollution incident control plan). The plan will contain the following as aminimum:

    a. guidance on the storage and use of hazardous materials with the aimof preventing and containing spills and releases

    b. guidelines on the degrees of containment which take account of thenature of the materials and the sensitivity of the environment

    c. procedures to be adopted in the event of an environmental incident, tocontain and limit any adverse effects

    d. procedures and appropriate information required in the event of anyincident such as a spillage or release of a potentially hazardousmaterial

    e. process in place to link into the incident management plan of the

    project.

    f. systems for notifying appropriate emergency services, the EA andother relevant authorities, the employer and the contractor'spersonnel.

    4.10 Pollution incident response

    4.10.1 This will be intrinsic to the above emergency preparedness plan. Workswill be carried out in such a way as to avoid pollution incidents. However,should any occur, incident response procedures, including appropriate

    equipment, materials and resources, will be implemented to contain andlimit the effects.

    4.10.2 The site procedures, methods of working and selection of materials willconsider the risk of pollution incidents, and include mitigation measures toreduce the likelihood and impact of any incident. Preventativecontainment measures will also be considered.

    4.10.3 Such procedures and measures will cover atmospheric, aquatic or landpollution and procedures in the event of fire.

    4.10.4 The correct storage, handling, use, and disposal of any potentially

    hazardous materials will be carried out in accordance with the relevantstatutory provisions and EA and Health and Safety Executive codes ofpractice and guidance notes, together with any manufacturersrecommendations.

    4.10.5 The relevant statutory bodies, including the Health and Safety Executive(Construction), Fire Authority, the EA, PLA and the local authority(Emergency Planning) will be consulted during the process of developingthe pollution incident control plan. This plan will cover the procedures tobe followed to limit the spread of pollution in the event of an incident. Thepollution incident control plan will complement and be consistent with therelevant emergency preparedness plans, as required by health and safety

    legislation, other environmental management and health and safety

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    34/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    28

    procedures. The approved pollution incident control plan will be notified torelevant stakeholders.

    4.10.6 The pollution incident control plan (refer to the HSSE Standardfor furtherinformation) will contain:

    a. an assessment of the type of materials to be used and the risk ofcontamination

    b. guidance on the storage and use of hazardous materials, with the aimof preventing and containing spills and releases

    c. guidelines on pollution prevention for sites on or adjacent to the riverand watercourses

    d. guidelines on the degrees of containment which take account of thenature of the materials and the sensitivity of the environment

    e. procedures to be adopted in the event of a pollution incident, to

    contain and limit any adverse effectsf. procedures and appropriate information required in the event of any

    incident such as a spillage or release of a potentially hazardousmaterial

    g. systems for notifying appropriate emergency services, authorities, theemployer and the contractor's personnel

    h. arrangements for notifying appropriate statutory bodies and localauthorities of pollution incidents, where required to by legislation

    i. standby equipment and materials

    j. specific arrangements for sites on or adjacent to the river

    k. relevant procedures and contacts for each work site for forwarding tothe emergency services and appropriate authorities.

    4.10.7 Where pollution is likely to affect an environmentally designated site,safeguards will be included in the ecology and landscape managementplan.

    4.11 Fire prevention and control

    4.11.1 All construction sites and associated accommodation and welfare facilitieswill have in place appropriate plans and management controls to preventfires (refer to the HSSE Standard, Section 8.7, for further information).

    4.12 Electromagnetic interference

    4.12.1 The contractor will consider the effects of electromagnetic interference onwireless telecommunication systems (and including traffic and railsignalling equipment) during the design and construction of the project,which will include site-specific impacts from the demolition of buildings andthe installation of tower cranes and, where appropriate, will employ best

    practice technology to ensure that levels of Radio Frequency Interferenceassociated with the project are low and at acceptable levels.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    35/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    29

    4.13 Unexploded ordnance

    4.13.1 A risk assessment will be completed by the contractor for the possibility ofunexploded ordnance being found on all sites (particularly those within theforeshore) and a response process will be included in the emergency

    response procedures.

    4.13.14.13.2 Unexploded ordnance (UXO)surveys will be undertaken using a"magnetomer survey" carried out by an accredited specialists. Anymagnetic contacts that model as an UXO will be investigated to confirmidentity. Any confirmed UXO will be managed and made safe by a suitablyqualified specialist.

    4.14 Utility works

    4.14.1 The utility diversions and new works required by the design will be

    identified, and schedules produced and agreed with the utility owners inaccordance, where appropriate, with the protective provisions.

    4.14.2 Account will be taken of any outages in planning the utility diversions.

    4.14.3 Where further changes in utility infrastructure cannot reasonably beavoided, the contractor will agree make arrangements with the employerand owner of the equipment to be relocated, either temporarily orpermanently, outside the area of the project works, and in accordance,where appropriate, with the protective provisions. In some instances, theapparatus may be surplus to requirements and can be decommissioned.

    4.14.4 When the work is carried out, the new equipment will be installed andcommissioned before the existing infrastructure is disconnected, but theremay be circumstances where a period of disconnection will be essential toallow safe completion of the work. In these circumstances, the contractorwill agree appropriate arrangements (such as planned night time orweekend closures) with the relevant utility operator, and in accordance,where appropriate, with the protective provisions.

    4.14.5 The contractor will locate, identify and protect (or divert if necessary) allutility plant and equipment reasonably expected to be materially adverselyaffected by the project works. Methods will include the use of groundpenetrating radar and vacuum excavation. On a site-specific basis, this

    will include preliminary site investigations to confirm the extent and exactlocation of underground infrastructure, to confirm the accuracy of existingand provided records. Even with these precautions, there is a risk thatunrecorded infrastructure will be encountered unexpectedly, in a city asdensely developed as London. Before starting construction, the contractorwill establish procedures with the utility operators for the management andmitigation of unforeseen events, and in accordance, where appropriate,with the protective provisions. Information from the EnvironmentalStatementand site investigations work will be made available.

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    36/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    30

    4.15 Worker access

    4.15.1 The employer willcontractor shallproduce a construction workforceguidance and requirement for the contractor to produce a green travel planfor the project. The plan will be developed in accordance with the Draft

    Project Framework Travel Plan to encourage the use of public transport bythose working on the project.

    4.15.2 The contractor will only allow site vehicles necessary to undertake theworks on site. No worker parking will be allowed unless specificallyidentified in the CoCPPart B, or unless agreed with the local authority.Site parking will be limited to operational vehicles such as mini buses,management and maintenance vehicles. The contractor will put measuresin place to monitor and eliminate fly-parkingby workers in the vicinity ofthe site.

    4.15.3 No temporary living accommodation is permitted on site.

    4.16 Clearance of site on completion of activities

    4.16.1 The contractor will clear and clean all working areas and accesses as workproceeds and when no longer required for the works.

    4.16.2 At the completion of the construction activity plant, temporary buildings orvehicles not required during subsequent construction works will beremoved from the site. All land, including highways, footpaths, publicopen spaces, river embankments/waterways, loading facilities or otherland occupied temporarily will be made good to the satisfaction of the

    employer. This will be in accordance with the ecology and landscapemanagement planand the approved landscape design for the site.

    4.16.3 Temporary working areas within the foreshore will be reinstated to asimilar condition and material as was presented prior to the works asagreed with the EA prior to start of the works in accordance with anyapplicable part of the protective provisions. This is detailed in Section 11Ecology.

    4.17 Considerate Constructors Scheme

    4.17.1 The contractor will be required to manage sites and achieve formalcertification under the Considerate Constructors Scheme. contractors willbe required to attain certification under the following five areas (or asamended):

    a. enhancing the appearance

    b. respecting the community

    c. protecting the environment

    d. securing everyones safety

    e. caring for the workforce.

    4.17.2 For each site, contractors will be required to achieve a minimum score(eight out of ten) for each of the above sections (maximum score = 50).

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    37/118

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    38/118

    4 General site operations

    Code of Construction PracticePart A: General Requirements

    32

    This page left intentionally blank

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    39/118

    5 Public access, the highway and river transport

    Code of Construction PracticePart A: General Requirements

    33

    5 Public access, the highway and rivertransport

    5.1 Traffic management and control

    5.1.1 The CoCPtogether with the Transport Assessmentsets out the frameworkwithin which the project related traffic will be controlled and the basis forthe production of further site specific level information. The CoCPPart Bidentifies any site-specific requirements and constraints, such asaccess/egress points for the worksites, and temporary and permanentclosures and diversions of highways.

    5.1.2 The contractor will comply with the legislation as amended by the DCO(including but not limited to the Highways Act 1980, the Road Traffic

    Regulation Act 1984, the New Roads and Street Works Act 1991 and theTraffic Management Act 2004). Articles 18, 55 and 56 of the DCO modifyand, in some cases exclude, relevant highways legislation and thecontractor must also comply with these Articles. The contractor willundertake the works in such a way as to maintain, as far as is reasonablypracticable, existing public access routes and rights of way duringconstruction (refer to the HSSE Standard). Alternative signposted routingwill be provided where required and feasible.

    5.1.3 The transportation of materials (including hazardous materials) willconsider the risk of incidents, and include mitigation measures to reduce

    the likelihood and impact of any incident. Preventative containmentmeasures will also be considered in advance.

    5.1.4 The contractor will carry out the works in such a manner as to limitinconvenience to the public arising from increased traffic flows anddisruptive impacts of construction traffic.

    5.1.5 For each worksite, a site-specific traffic management plan will beproduced, co-ordinated and then implemented by the contractor. The planwill be prepared in consultation with highway and traffic authorities and theemergency services. The plans will need to be approved by the relevantlocal authority in consultation with the relevant highway and traffic

    authority. The plans will include:a. site boundaries and the main access/egress points for the worksites

    b. temporary and permanent closures and diversions of highways(including programme and/or phasing)

    c. how the contractor will meet the requirements of the transportassessment

    d. the strategy for traffic management such as the use of parkingmeasures and/or site operatives to manage how construction vehicleswill enter and exit the sites

    e. local routes to be used by lorries, cranes and abnormal loadsgenerated by construction activity including, where required, the

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    40/118

    5 Public access, the highway and river transport

    Code of Construction PracticePart A: General Requirements

    34

    timings of use of such routes, lorry holding areas, lorry route signingstrategy, means of monitoring lorry use and any routes prohibited fromuse

    f. a schedule and programme of the planned traffic managementschemes and measures required to undertake the works

    g. required bus diversions and bus stop locations

    h. requirements for amendments to traffic signal infrastructure or timingmodifications that need to be agreed with and provided by TfL

    i. interfaces and effects with adjacent developments and other projectconstruction sites, including measures to coordinate and reducecombined impacts

    j. arrangements for lorry management as detailed in Section5.2

    k. measures (including notification to suppliers) to address potential risk

    to residents and activities on local roads adjacent to the constructionsite. These will include where appropriate restrictions on deliveryhours where practical, and strict enforcement of speed limits

    l. procedures for carrying out regular full safety audits on all permanenthighway works and temporary diversion routes

    l.m. a mechanism to monitor the assumptions within the travel plan.

    5.1.6 Traffic management schemes to control, divert or amend traffic flowsduring the works will be submitted for approval to the relevant localhighway authority in consultation with TfL. The submission will include:

    a. scheme details and layouts including drawings and any traffic signalamendments

    b. phasing and programming of scheme including control measures

    c. fully validated traffic modelling and reports for the traffic managementand control measures where necessary and specified in the CoCPPart B. The reports will be produced in accordance with the relevantguidance as issued by TfL

    d. safety audits on all permanent highway works, temporary diversionroutes and accesses and as required in the CoCPPart B

    e. details of mitigation measures to reduce impacts on traffic(buses,cyclists and pedestrians) including traffic signal amendments,temporary diversion routes and measures to minimise duration ofscheme

    f. proposed publicity to notify and inform users before and during theimplementation of all traffic management and control measures.

    5.1.7 In conjunction with the Traffic Management Plan the contractor willproduce a separate Construction Logistics Plan for each site. This detailsthe efficient and sustainable management of material, and material vehicleand vessel movements to and from the site. The plan will be prepared in

    consultation with the PLA and local traffic authorities. The plans will be

  • 8/13/2019 CoCP Part a General Requirements Track Changes

    41/118

    5 Public access, the highway and river transport

    Code of Construction PracticePart A: General Requirements

    35

    submitted and approved by the local planning authority in liaison with thePLA and relevant local traffic authorities before commencement of work.

    5.1.8 The planning of the works will include consideration of the access andservicing requirements of affected residential and commercial premises.The contractor will be required to undertake regular communications withparties affected by the works, as detailed in Section3. Local residentsand businesses will be informed in advance of the dates and durations ofclosures, and will be provided with details of diversion routes at least twoweeks in advance of the works. Access and servicing requirements will bemaintained, within the constraints of the works and the need to ensure thesafety of the public.

    5.1.9 Some traffic management proposals may require traffic regulation ordersunder the Road Traffic Regulation Act 1984 to cover measures such asthe introduction of one-way streets, road closures, banned turns, andtemporary speed limits. Where these have not been identified within

    schedules to the Draft DCO, applications will be made to the relevanthighway authority in advance of the works.

    5.1.10 The employer will assess overall traffic impact from the project and ensurethat where required, traffic management is coordinated between theworksites and contractors.

    5.2 Lorry management and control

    5.2.1 The contractor will have the following lorry management requirements andvehicle measures applied to his own vehicles and those of sub-contractors

    and suppliers:a. Membership of the