How to create a Change
Request in Remedy
-
7/29/2019 CM How to Create a CR in Remedy v1.1
2/12
1
Change Control Table
Date Version Number Amendment by Summary of Changes
26th July 2012 1.0 Kavitha Chalapathy Initial Draft for Instructions
for requesting a change
2nd of February2013
1.1 Kavitha Chalapathy Updated with details onrelation to various
departments within
Wegener.
Approval Control Table
Date Approver Comments
2nd
February 2013 Sander van Knippenberg Approved by Change manager
-
7/29/2019 CM How to Create a CR in Remedy v1.1
3/12
2
Log in to the Remedy Change Management console
http://remedy.platina.intra/arsys/forms/remedy-
app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Man
ager%29/
And select New Change
Determine what class change is requiredIf your change requires a single team, isnt complicated and poses a zero to none risk
and minimum impact it is a candidate for a Class A change. In order to find out if your
change fits this categorization please see if there is an applicable template. Otherwisego for a class B (1 team), or Class C (multiple teams involved and building required).
Standard Change (Class A)1. Select the appropriate Standard change template.
2. Add the abbreviation WEG or MEC or BEM to the summary field
a) WEG, if the change is only relevant to the Wegener division
b) MEC , if the change is relevant to both Wegener and Berlingske Media divisons
c) BEM, if the change is only relevant to the Berlingske Media division
http://remedy.platina.intra/arsys/forms/remedy-app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Manager%29/http://remedy.platina.intra/arsys/forms/remedy-app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Manager%29/http://remedy.platina.intra/arsys/forms/remedy-app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Manager%29/http://remedy.platina.intra/arsys/forms/remedy-app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Manager%29/http://remedy.platina.intra/arsys/forms/remedy-app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Manager%29/http://remedy.platina.intra/arsys/forms/remedy-app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Manager%29/http://remedy.platina.intra/arsys/forms/remedy-app.platina.intra/CHG%3AChange+Management+Console/Default+User+View+%28Manager%29/ -
7/29/2019 CM How to Create a CR in Remedy v1.1
4/12
3
Please ensure to keep a meaningful summary after starting the Summary* with WEG,
BEM or MEC
3. Customer Company has to be filled, If the change is specific to Wegener then ensure
that you select Wegener, If the change is related to Berlingske select BEM. If the change
is related to Wegener and Berlingske ensure that Mecom is selected.
4. If you request the change on behalf of the client then please ensure to update the
Requested For+ field to reflect the same. The same applies if you request a change for
someone else within HCL.
-
7/29/2019 CM How to Create a CR in Remedy v1.1
5/12
4
a. Click on the delete button on the right side of Requested For+
b. Type a in the now empty field and hit the enter-button.
Now you can search for the person you are requesting this change for.
5. Complete the Notes field by putting something meaningful in here to complete the
template provided.
Please note this should be a laymans description on what this change is trying to
achieve.
6. Set the Urgency
Change urgency has to initially be set correctly during the draft stage because urgency
cannot be changed once the change has moved to approval stage.
-
7/29/2019 CM How to Create a CR in Remedy v1.1
6/12
5
7. Fill the details for Requested Start Date, Requested End Date.
Please note that a Class A change requires a 2 business days lead time starting from
12:00 CET (noon).
If you need to do this change outside of the regular maintenance window then please
add a General information & Work Notes Work Info with a Summary* field of:Not in regular maintenance window. Then in the Notes part describe why you
feel this change needs to take place outside of the regular maintenance window.
This will however require firm justification.
Please note: An attached e-mail with relevant client approval normally gets approved by
the change manager. In case of doubt please contact the change management team.
-
7/29/2019 CM How to Create a CR in Remedy v1.1
7/12
6
8. Select the Change coordinator as Kavitha Chalapathy
Select Add work Info and then Fill the Implementation and Backout Plan.
Please ensure to complete the Summary field as Implementation Plan or Backout
Plan to reflect the same.
In the Implementation plan you can write the steps you are planning to take to achieve
the goal described in the notes field.
If required you can attach files to it.
NOTE: If you select [Locked: Yes] you cannot make any alterations and will have to add
an additional Implementation plan with summary field Additional Implementation Plan
to make any alterations.
Click on Classification tab and check if the for a class A autopopulated fields are correct
Operational Categorization Tier1 and Tier2
Product Categorization Tier1 and Tier2Otherwise ensure yourself to complete these.
-
7/29/2019 CM How to Create a CR in Remedy v1.1
8/12
7
1. Adding tasks for various teams to completClick the Task Tab Create Task In General tab provide the required details under the task location, in the bottom
of the page change the site status to ACTIVE
2. Click Assignment Tab and provide the details as required
-
7/29/2019 CM How to Create a CR in Remedy v1.1
9/12
8
3. Click Dates Tab and provide the scheduled start and End date.
4. Click Save Button , Task will be created. If needed you can add multiple Task.
-
7/29/2019 CM How to Create a CR in Remedy v1.1
10/12
9
Relationship Tab
For example if there is a incident, The incident is raised to perform a change, In that case we
use the relationship tab. Will can close the incident and create a new change and relate the
incident in the created CR.
Select the request type as Incidentsearch, new window opens, Provide the Incident Number
click enter.
5. Check and Save the Change Request. Now the change will be in draft Status. Click
Next Stage the CR will go for necessary approvals.
-
7/29/2019 CM How to Create a CR in Remedy v1.1
11/12
10
For Class B and Class C change we need to follow below additional steps6. Under Initiate Tab Risk and impact Assessment details has to be filled.
7. IA form needs to be attached for all Class B and C changes. The template to be used is
found on the Sharepoint environment.
Change urgency has to initially be set correctly during the draft stage because urgency
cannot be changed once the change has moved to approval stage
-
7/29/2019 CM How to Create a CR in Remedy v1.1
12/12
11
8. Select the change model accordingly