charleston dam recreational precinct masterplan
TRANSCRIPT
C h a r l e s t o n D a m R e c r e a t i o n a l P r e c i n c t M a s t e r p l a nDocument reference: PR140639-1 [B]
rpsgroup.com.au
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 2
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
Prepared for:
etheridge shire Council
Prepared by:
RPs australia east
level 5, Central Plaza, 370 Flinders street, townsville, QlD, australia
telephone: +61 7 4724 4244 Facsimile: +61 74724 4144
www.rpsgroup.com.au aBn 81 591 046 588
[B]
[a]
Revision
2018-08-31
2018-08-24
Date
DKG
Kes
Prepared by
tFC
tFC
approved by
© RPs 2018
the information contained in this document produced by RPs is solely for the use of etheridge shire Council for the purpose for which it has been prepared and RPs undertakes no duty to or accepts any responsibility to any third party who may rely upon this document.
this document offers preliminary design information only, based on information provided by etheridge shire Council and an assumed dam water level of 392m.
all rights reserved. no section or element of this document may be removed from this document, reproduced, electronically stored or transmitted in any form without the written permission of RPs.
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 3
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
1 . 0 R e c r e a t i o n a l M a s t e r p l a n
RPs was engaged by etheridge shire Council to develop a concept masterplan to pro-vide a recreation area of local significance which builds amenity for community along the edge of the proposed Charleston Dam. the Charleston Dam Recreational area has been recognised by the local council as a significant opportunity to contribute to the enhancement of the local lifestyle and amenity and enhance the shire’s overall tourism appeal.
the proposed concept masterplan provides a recreational precinct with swimming beach, open ‘kick-about’ parkland, playground, barbeques, picnic shelters and public amenities positioned on the eastern edge of a natural peninsula to take full advantage of cooling easterly breezes while providing ample shade from the western afternoon sun.
the recreation precinct offers centralised parking and amenities for the two boat ramps – eastern and western – which together offer boat access to the greater Charleston Dam and provide a launching option protected from the prevailing east-erly breezes. Beyond the central recreation precinct visitors can use the proposed bushwalking tracks to access a series of smaller swimming bays or access the two proposed lakeside boating/camping locations, ideal for social water skiing or short stays.
R e c r e a t i o n a l M a s t e r p l a n1 : 2 0 0 0
Recreation Precinct (refer to page 4)
l o c a t i o n P l a n1 : 6 0 0 , 0 0 0
l e g e n d
1
2
3
4
5
6
7
8
9
Western boat ramp
eastern boat ramp
Boat and trailer car park
lakeside camping and boat parking
swimming and paddlecraft area
Bushwalking track
lookout
Unsealed road
Forsayth-Cemetery Road 1
23
4
4
5
6
7
8
9
5
5
Georgetown
Forsayth
Charleston Dam
Fors
ayth
Roa
d
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 4
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
R e c r e a t i o n M a s t e r p l a n1 : 1 0 0 0
l e g e n d
1/1000 @ a3
1
12
12
13
13
13
16
16
17
14
15
13
13
11
2
34
5
6
78
8
8
9
10
1011
6
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
entry statement and gate
Western boat ramp
eastern boat ramp
Boat and trailer car park
Car park
lakeside camping and boat parking
Man-made beach
swimming and paddlecraft area
Walking loop
Bushwalking track
lookout
BBQ shelter
shelter
Playground
amenities block
open recreation ‘kick-about’ space
Unsealed road
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 5
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
2 . 0 R e c r e a t i o n P r e c i n c t P e r s p e c t i v e sP r o p o s e d R e c r e a t i o n P r e c i n c t
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 6
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
P r o p o s e d M a n - m a d e B e a c h a n d F o r e s h o r e
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 7
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
P r o p o s e d C h a r l e s t o n D a m R e c r e a t i o n P r e c i n c t
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 8
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
3 . 0 P r o p o s e d P l a n t i n g P a l e t t e
eucalyptus crebra
terminalia aridicola
heteropogon contortus themeda triandra Dianella caerulea lomandra longifolia
Petalostigma banksii Melaleuca leucadendra erythrophleum chlorostachys
Cupaniopsis anacardioides Flindersia australis Corymbia pocillum
the proposed planting palette for the Charleston Dam Recreational Precinct incorporates plants that are endemic to the area and readily available. the palette also proposes some additional species that will thrive in the estab-lished micro environment and complement the surrounding flora.
DATE:ISSUE:
Item Description Unit Qty Rate Total (Ex GST)Preliminaries
.01.01 Including costs associated with contractor to establish on site. Cost may include site sheds,
signage or security. General health and safety requirements associated with workplace.
Compliance with 'General' and 'Preliminaries' sections of specificationPC Sum 1 100,000.00$ 100,000.00$
Earthworks.02.01 Earthworks - Garden Areas (Sub-soil prep, Amelioration, Soil, Fertiliser, Mulch) m² 1920 10.00$ 19,200.00$
.02.02 Earthworks - Turf Areas (Sub-soil prep, Amelioration, Soil, Fertiliser) m² 13643 10.00$ 136,430.00$
Pavements/Surface Treatments.03.01 Pavement Type 1 (PT1) - Standard Pathway Plain Grey Broom Finished Concrete m² 1235 120.00$ 148,200.00$
.03.02 Pathways (PT1) around playground m² 225 120.00$ 27,000.00$
.03.03 Softfall Area Type 1 (SF1) - Sand Softfall m² 135 150.00$ 20,250.00$
.03.04 Boat Ramp m² 315 150.00$ 47,250.00$
.03.05 Boulevard (from carpark to beach) m² 280 150.00$ 42,000.00$
.03.06 Jetty item 1 15,000.00$ 15,000.00$
.03.07 Walking Track m² 1055 50.00$ 52,750.00$
.03.08 Beach m² 1045 50.00$ 52,250.00$
.03.09 Asphalt - Carpark area m² 1430 65.00$ 92,950.00$
.03.10 Asphalt - Carpark to boat ramp and road to camp site m² 940 65.00$ 61,100.00$
.03.11 Asphalt - Road to west boat ramp m² 162 65.00$ 10,530.00$
.03.12 Asphalt - Road around northern camping area m² 526 65.00$ 34,190.00$
.03.13 Asphalt - Main Entry Road m² 2015 65.00$ 130,975.00$
.03.14 Road shoulder to main entry road m² 1415 20.00$ 28,300.00$
Garden Edging.04.01 Concrete Edging - Garden to turf lin m 300 30.00$ 9,000.00$
PlantingSupply and plant including all excavation, backfill, fertilizer etc. the following plants:
.05.01 140mm Container (4 per square meter of garden) item 7680 10.00$ 76,800.00$
.05.02 45 Ltr Bag Trees item 100 300.00$ 30,000.00$
.05.03 400 Ltr Bag Trees item 25 600.00$ 15,000.00$
Turf.06.01 Camping Area turf m² 13643 2.00$ 27,286.00$
.06.02 Large main areas of turf m² 7600 20.00$ 152,000.00$
.06.03 Small main area of turf m² 2750 20.00$ 55,000.00$
Street Furniture.07.01 Seat item 4 2,500.00$ 10,000.00$
.07.02 Picnic Setting item 7 3,500.00$ 24,500.00$
.07.03 Wheelie Bin item 2 1,500.00$ 3,000.00$
.07.04 Entry Walls item 2 5,000.00$ 10,000.00$
.07.05 BBQ (Wood only) item 2 1,500.00$ 3,000.00$
.07.06 Shelters along walking track item 3 10,000.00$ 30,000.00$
Structures.08.01 Shade Shelter - 3 x 3 item 5 10,000.00$ 50,000.00$
.08.02 Shade Shelter - 6 x 3 item 2 30,000.00$ 60,000.00$
.08.03 Toilet Block item 1 250,000.00$ 250,000.00$
.08.04 Shade Sail 130m2 item 1 25,000.00$ 25,000.00$
.08.05 Shade Sail 73m2 item 1 25,000.00$ 25,000.00$
Irrigation.09.01 Pump assembly to lake PC Sum 1 50,000.00$ 50,000.00$
.09.02 Irrigation to Garden Areas m² 1920 3.00$ 5,760.00$
.09.03 Irrigation to Turf Areas m² 13643 3.00$ 40,929.00$
Civil Services.10.02 Power Connection PC Sum 1 50,000.00$ 50,000.00$
.10.03 Septic System to Toilet Block PC Sum 1 20,000.00$ 20,000.00$
.10.04 Water provision for balance of site. PC Sum 1 25,000.00$ 25,000.00$
Establishment/On MaintenanceE1 Maintain all hardscape and softscape landscaping works including pavements, trees, shrubs,
groundcovers and turf areas. Maintenance to include minimum 20 visits during the initial and
minimum 13 week maintenance period as per a maintenance program and schedule in order to
obtain On-Maintenance with TCC
weeks 13 500.00$ 6,500.00$
E2 Maintain all hardscape and softscape landscaping works including pavements, trees, shrubs,
groundcovers and turf areas. Maintenance as per the specified maintenance program and schedule
leading to Off-Maintenance certification and handover with TCCmonths 9 500.00$ 4,500.00$
2,076,650.00$
1
2
3
4
RPS Australia East has compiled the information in the above table from varying tenders received by it from third parties for the provision of landscape goods and
services over the past 6 months. The information is not intended to be an exact estimate of costs of the landscape works or specifically refer to the goods and
services required by the Client. The information is provided by third parties and RPS Australia East does not provide an opinion nor make any representation or
warranty as to the accuracy, suitability or reasonableness of any of the prices or information contained in the above table.
The information in the above table is intended to provide an initial and general estimate of costs only. Due to the number of variables involved in construction and
structural works, the information should only be used as a general guide to costs. Prior to proceeding with any work the Client should obtain an exact estimate of
costs from a licensed Quantity Surveyor.
RPS Australia East will not be liable (in negligence or otherwise) for any direct or indirect loss, damage, liability or claim arising out of or incidental to the Client or
a Third Party using or relying on information contained in the above table without obtaining a further estimate from a Quantity Surveyor, nor in any case where
RPS Australia East has used or relied on information provided to it by the Client or a Third Party where the information is incorrect, incomplete, inaccurate, out-of-
date or unreasonable.
TOTAL CONTRACTED ITEMS PRICE (excluding GST)
DISCLAIMERS FOR ESTIMATES OF PROBABLE COSTSThe information set out in the above table was prepared for the sole purposes of Etheridge Shire Council (“Client”) for the purpose of providing general
information about the cost of landscape goods and services to be provided by third parties and which are contemplated in the attached) (“Purpose”). The
information is strictly limited to the Purpose and does not apply directly or indirectly and will not be used for any other application, purpose, use or matter. The
information is presented without the assumption of a duty of care to any other person (other than the (Client) (“Third Party”) and may not be relied on by Third
Party.
Charleston DamOpinion of Probable Costs
201808311 - Initial issue
DATE:ISSUE:
Item Description Unit Qty Rate Total (Ex GST)Preliminaries
.01.01 Including costs associated with contractor to establish on site. Cost may include site sheds,
signage or security. General health and safety requirements associated with workplace.
Compliance with 'General' and 'Preliminaries' sections of specificationPC Sum 1 100,000.00$ 100,000.00$
Earthworks.02.01 Earthworks - Garden Areas (Sub-soil prep, Amelioration, Soil, Fertiliser, Mulch) m² 1920 10.00$ 19,200.00$
.02.02 Earthworks - Turf Areas (Sub-soil prep, Amelioration, Soil, Fertiliser) m² 13643 10.00$ 136,430.00$
Pavements/Surface Treatments.03.01 Pavement Type 1 (PT1) - Standard Pathway Plain Grey Broom Finished Concrete m² 1235 120.00$ 148,200.00$
.03.02 Pathways (PT1) around playground m² 225 120.00$ 27,000.00$
.03.03 Softfall Area Type 1 (SF1) - Sand Softfall m² 135 150.00$ 20,250.00$
.03.04 Boat Ramp m² 315 150.00$ 47,250.00$
.03.05 Boulevard (from carpark to beach) m² 280 150.00$ 42,000.00$
.03.06 Jetty item 1 15,000.00$ 15,000.00$
.03.07 Walking Track m² 1055 50.00$ 52,750.00$
.03.08 Beach m² 1045 50.00$ 52,250.00$
.03.09 Asphalt - Carpark area m² 1430 65.00$ 92,950.00$
.03.10 Asphalt - Carpark to boat ramp and road to camp site m² 940 65.00$ 61,100.00$
.03.11 Asphalt - Road to west boat ramp m² 162 65.00$ 10,530.00$
.03.12 Asphalt - Road around northern camping area m² 526 65.00$ 34,190.00$
.03.13 Asphalt - Main Entry Road m² 2015 65.00$ 130,975.00$
.03.14 Road shoulder to main entry road m² 1415 20.00$ 28,300.00$
Garden Edging.04.01 Concrete Edging - Garden to turf lin m 300 30.00$ 9,000.00$
PlantingSupply and plant including all excavation, backfill, fertilizer etc. the following plants:
.05.01 140mm Container (4 per square meter of garden) item 7680 10.00$ 76,800.00$
.05.02 45 Ltr Bag Trees item 100 300.00$ 30,000.00$
.05.03 400 Ltr Bag Trees item 25 600.00$ 15,000.00$
Turf.06.01 Camping Area turf m² 13643 2.00$ 27,286.00$
.06.02 Large main areas of turf m² 7600 20.00$ 152,000.00$
.06.03 Small main area of turf m² 2750 20.00$ 55,000.00$
Street Furniture.07.01 Seat item 4 2,500.00$ 10,000.00$
.07.02 Picnic Setting item 7 3,500.00$ 24,500.00$
.07.03 Wheelie Bin item 2 1,500.00$ 3,000.00$
.07.04 Entry Walls item 2 5,000.00$ 10,000.00$
.07.05 BBQ (Wood only) item 2 1,500.00$ 3,000.00$
.07.06 Shelters along walking track item 3 10,000.00$ 30,000.00$
Structures.08.01 Shade Shelter - 3 x 3 item 5 10,000.00$ 50,000.00$
.08.02 Shade Shelter - 6 x 3 item 2 30,000.00$ 60,000.00$
.08.03 Toilet Block item 1 250,000.00$ 250,000.00$
.08.04 Shade Sail 130m2 item 1 25,000.00$ 25,000.00$
.08.05 Shade Sail 73m2 item 1 25,000.00$ 25,000.00$
Irrigation.09.01 Pump assembly to lake PC Sum 1 50,000.00$ 50,000.00$
.09.02 Irrigation to Garden Areas m² 1920 3.00$ 5,760.00$
.09.03 Irrigation to Turf Areas m² 13643 3.00$ 40,929.00$
Civil Services.10.02 Power Connection PC Sum 1 50,000.00$ 50,000.00$
.10.03 Septic System to Toilet Block PC Sum 1 20,000.00$ 20,000.00$
.10.04 Water provision for balance of site. PC Sum 1 25,000.00$ 25,000.00$
Establishment/On MaintenanceE1 Maintain all hardscape and softscape landscaping works including pavements, trees, shrubs,
groundcovers and turf areas. Maintenance to include minimum 20 visits during the initial and
minimum 13 week maintenance period as per a maintenance program and schedule in order to
obtain On-Maintenance with TCC
weeks 13 500.00$ 6,500.00$
E2 Maintain all hardscape and softscape landscaping works including pavements, trees, shrubs,
groundcovers and turf areas. Maintenance as per the specified maintenance program and schedule
leading to Off-Maintenance certification and handover with TCCmonths 9 500.00$ 4,500.00$
2,076,650.00$
1
2
3
4
RPS Australia East has compiled the information in the above table from varying tenders received by it from third parties for the provision of landscape goods and
services over the past 6 months. The information is not intended to be an exact estimate of costs of the landscape works or specifically refer to the goods and
services required by the Client. The information is provided by third parties and RPS Australia East does not provide an opinion nor make any representation or
warranty as to the accuracy, suitability or reasonableness of any of the prices or information contained in the above table.
The information in the above table is intended to provide an initial and general estimate of costs only. Due to the number of variables involved in construction and
structural works, the information should only be used as a general guide to costs. Prior to proceeding with any work the Client should obtain an exact estimate of
costs from a licensed Quantity Surveyor.
RPS Australia East will not be liable (in negligence or otherwise) for any direct or indirect loss, damage, liability or claim arising out of or incidental to the Client or
a Third Party using or relying on information contained in the above table without obtaining a further estimate from a Quantity Surveyor, nor in any case where
RPS Australia East has used or relied on information provided to it by the Client or a Third Party where the information is incorrect, incomplete, inaccurate, out-of-
date or unreasonable.
TOTAL CONTRACTED ITEMS PRICE (excluding GST)
DISCLAIMERS FOR ESTIMATES OF PROBABLE COSTSThe information set out in the above table was prepared for the sole purposes of Etheridge Shire Council (“Client”) for the purpose of providing general
information about the cost of landscape goods and services to be provided by third parties and which are contemplated in the attached) (“Purpose”). The
information is strictly limited to the Purpose and does not apply directly or indirectly and will not be used for any other application, purpose, use or matter. The
information is presented without the assumption of a duty of care to any other person (other than the (Client) (“Third Party”) and may not be relied on by Third
Party.
Charleston DamOpinion of Probable Costs
201808311 - Initial issue
rpsgroup.com.au
2018-08-31 [B] | PR140639-1 - Charleston Dam Recreational Precinct Masterplan | Page 9
G:\0140000\140639 ChaRleston DaM\140639-1 - la\C_teChniCal\C4_inDesiGn\MasteRPlan\ChaRleston DaM.inDD
4 . 0 e s t i m a t e o f P r o b a b l e C o s t s