chapter 2 _ ipm _ developing project plan

Upload: zeeshan-bhatti

Post on 08-Jul-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    1/72

    IT PROJECT MANAGEMENT Dr. Zeeshan Bhatti

    MPhil (IT)

    Lecture 3

    Institute of Information and Communication TechnologyUniversity of Sindh, Jamshoro

    Developing the Project Plan

    BY: DR. ZEE SHAN BHATT I 1

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    2/72

    • Introduction to PM

    • Project planning

     – Gantt chart and WBS

    • Project planning

     – Network analysis I

    • Project planning

     –Network analysis II

    PLAN

    Project planning Resource analysis

    Risk management

    Quality

    Budgets and cost control

    Project teams

    BY: DR. ZEE SHAN BHATT I 2

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    3/72

    WHAT IS A PROJECT?

    “Unique process consisting of a set of coordinated andcontrolled activities with start and finish dates,

    undertaken to achieve an objective conforming tospecific requirements, including constraints of time, cost,quality and resources”

    A Project is a planned set of activities

    A Project has a scope

    A Project has time, cost, quality and resource constraints

    3

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    4/72

    WHAT IS PROJECT MANAGEMENT?

    The art of organising, leading, reporting and completinga project through people

    4

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    5/72

    WHAT IS PROJECT MANAGEMENT?

    A project is a planned undertaking

    A project manager is a person who causes things tohappen

    Therefore, project management is causing a plannedundertaking to happen.

    5

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    6/72

    CHARACTERISTICS OF A GOOD IT

    PROJECT MANAGER

    BY: DR. ZEE SHAN BHATT I 6

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    7/72

    EXERCISE 1

    Write down three attributes of a good Project Manager

    BY: DR. ZEE SHAN BHATT I 7

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    8/72

    PROJECT MANAGER ROLE

    A Good Project Manager Takes ownership of the whole project

    Is proactive not reactive

    Adequately plans the project

    Is Authoritative (NOT Authoritarian) Is Decisive

    Is a Good Communicator

    Manages by data and facts not uniformed optimism

    Leads by example Has sound Judgement

    Is a Motivator

    Is Diplomatic

    Can Delegate 8

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    9/72

    PERSONAL CHARACTERISTICS

    · Is technically qualified

    · Is a decision maker

    · Is honest and creates a relaxed atmosphere

    · Possesses the art of saying no without offending others

    · Believes in managing time and people

    BY: DR. ZEE SHAN BHATT I 9

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    10/72

    PROJECT−RELATED CHARACTERISTICS

    Achieves the objectives and goals of the project within the established schedule, budget,and procedures

    Develops IT projects on budget and on time to the complete satisfaction of the users

    Has experience in related or similar projects

    Can control project outcomes by measuring and evaluating performance against establishedobjectives and standards

    Develops and executes contingency plans to meet unforeseen circumstances and problems

    Develops and implements decisions relating to planning

    Is willing to redefine goals, responsibilities, and schedules as necessary to get the projectback on track in case the schedule slips or the project is over budget

    Establishes and meets real priorities and deadlines

    Believes in good planning to reduce pressure and stress and increase productivity

    Establishes long−term and short−term planning

    BY: DR. ZEE SHAN BHATT I 10

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    11/72

    TEAM−RELATED CHARACTERISTICS

    Has good communication and managerial skills

    Is able to plan, organize, lead, motivate, and delegate proper responsibilitiesto team members

    Respects team members and has their confidence and respect

    Shares success with the team members

    Selects the right person for the right job

    Shows appreciation to good workers

    Gets others in the organization to accept his or her ideas and carry out his orher plans

    Delegates duties and maintains control

    Believes in professionally training people for their delegated jobs

    BY: DR. ZEE SHAN BHATT I 11

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    12/72

    Considers himself or herself as a part of the team

    Creates structured discipline

    Recognizes individual differences and takes advantage of individualstrengths

    Provides work that stimulates a feeling of personal respect andprofessional growth

    Allows sufficient time for ideas to develop and mature

    Allows free time and encourages openness

    Understands the team members and creates effective communication

    Monitors his or her team members on a regular basis for and takesnecessary actions

    BY: DR. ZEE SHAN BHATT I 12

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    13/72

    PROJECT MANAGEMENT CHECKLIST

    A good IT project manager must do the following:

    · Identify users, stakeholders, and customers

    · Communicate with users, stakeholders, and customers throughout the project

    · Educate and train users, stakeholders, and customers about the project

    · Understand the requirements of users, stakeholders, and customers

    · Set up the project book

    · Plan the project

    · Staff the project

    · Establish project phases

    · Allocate the budget for various phases and activities

    · Estimate resources

    · Estimate the level of efforts

    · Model and simulate the project

    · Establish standards and controls

    BY: DR. ZEE SHAN BHATT I 13

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    14/72

    · Form project tasks teams

    · Staff task teams

    · Provide necessary training

    · Staff support groups· Provide a team concept

    · Establish a schedule and milestones

    · Provide a guideline to implement success

    · Provide state−of−the−art tools

    · Encourage the reuse of assets, the Internet, and telecommunications

    · Track the deliverables

    · Measure the success

    · Create effective communication among the members of the projectteam

    · Gain the users' confidence

    · Show results

    · Document the products

    · Provide a smooth transition of the product to the usersBY: DR. ZEE SHAN BHATT I 14

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    15/72

    STAKEHOLDER ENGAGEMENT

    BY: DR. ZEE SHAN BHATT I 15

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    16/72

    STAKEHOLDER

    “A person or group of people who have a vested

    interest in the success of an organization and the

    environment in which the organization operates”

    BY: DR. ZEE SHAN BHATT I 16

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    17/72

    EXERCISE 2

    Write down three typical project stakeholders

    BY: DR. ZEE SHAN BHATT I 17

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    18/72

    EXERCISE 2 - TYPICAL STAKEHOLDERS

    Sponsor

    Funding Body

    Customer

    Suppliers

    End User

    HSE/Environmental Agency

    Maintenance Team

    Neighbours/Community/Shareholders

    Fusion Community

    Interfaces

    BY: DR. ZEE SHAN BHATT I 18

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    19/72

    STAKEHOLDER ENGAGEMENT PROCESS

    Identify Stakeholders

    Assess needs

    Define actions

    Establish communication channels

    Gather feedback

    Monitor and review

    BY: DR. ZEE SHAN BHATT I 19

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    20/72

    THE PROJECT PROCESS

    Projectset-up

    MajorProject

    Proposals

    ProjectDefinition Conceptual

    Design SchemeDesign Detailed

    DesignTender

    Invitation &Assessment

    ManufactureEquipment Install

    EquipmentConfirm

    Completion

    Test &Commission

    ProjectReview

    Appoint Project SponsorAssess Project PriorityAssess Budget ImplicationsEst. Proj. Deliverables and ObjectivesAppoint Project LeaderApprove Project Set-up

    Draft Statement of Requirements (SoR)Review & Approve SoR IdentifyResources Appoint ProjectTeam Produce & MaintainProcurement PlansUndertake Project Risk AssessmentPrepare Project Boundary DocumentDevelop Project Management Plan (PMP)*Raise initial TCD-R/PERF**Prepare Preliminary Conceptual Design**

    Raise/Extend/Update initial TCD-R/PERFPrepare Outline Conceptual DesignDefine Design Constraints PrepareInterface Requirements Spec. (IRP)Finalise Conceptual DesignHold Conceptual Design Review (CDR)Clear CDR IssuesInitiate Modification Safety CaseUpdate PMPApprove Proceed to Detailed Design

    Raise/Extend Sub-system TCD-Rs/PERFsAgree Classifications & InterfacesPrepare Sub-system Scheme DesignHold Sub-system Scheme Design Review (SDR)Clear Sub-system SDR IssuesUpdate PMPUse TCD-I/MMAC for Sub-system SD Approval

    Extend TCD-Rs/PERFsPrepare Sub-system Detailed Design HoldDetailed Design Review (DDR)Clear Sub-system DDR IssuesUse TCD-I/MMAC for Sub-system DD ApprovalPrepare Final D ocuments including:- Design Documents., Machine CompatibilityDocuments., Safety Case Modification

    Compile Tender Docs.***Send out Invitations (ITTS)Hold Clarification MeetingsReceive TendersEvaluate TendersArrange site visitsApprove changes to Specs.Choose preferred Company

    Raise Contract DocumentationPlace ContractHold Kick off Meeting (KOM)Clarify Issues (Quality Plan)Monitor ProgressWitness key ProceduresComplete Release NoteApprove Complete Package****Approve Release NotePack & Dispatch Equipment

    Receive EquipmentPre-test Equipment

    Install equipment

    Test Equipment against Test ScheduleCommission Complete System

    Confirm Technical CompletionReview Project Records Complete

    Handover Documents ResolveReservations ObtainAcceptance of Completed Project

    Initiate Project

    Undertake Design

    Implement Project

    Complete Project

    EFDA/CSU/JOC Management

    Project Leader/Project Team/EFDA/CSU

    Project Team/IRP/EFDA/CSU/JDC

    Project Team/Interfaces

    Project Team/Interfaces/EFDA/CSU/JDC

    Project Team/ICM

    Project Team/ICM/EFDA/CSU

    Project Team/EFDA/CSU

    Project Team/CSU

    Undertake PostProject Review

    Project Team/Contracts/EFDA

    Project Team/Contractor/ICM

    Prepare Technical DesignEnsure Machine Compatibility Prepare

    Safety Case Modification

    *** These will comprise:

    - Technical Specification- Drawings- Contractual Requirements

    Note: Overall Project

    Management and Reporting willbe as defined in the ProjectManagement Plan (PMP)

    **** This includessupporting documentation

    Gate 4

    Gate 1 Gate 2 Gate 3

    Gates (Formal Decision Points)See accompanying notes

    Gate 0Project Justification- Approve Project Definition

    Design Approval- Approval ofFinal Documents

    Readiness forManufacture- Approval toplace Contract

    Readiness for Operation- Acceptance of System

    Strategic and BudgetaryApproval

    Undertake Tender

    * This will include:

    - Initial WBS, OBS and CBS- Project Plan- Risk and Procurement Strategies

    ** These will only take place herefor large projects demanding DOeffort for preliminary Conceptualwork

    UNCONTROLLED

    WHEN PRINTEDBY: DR. ZEE SHAN BHATT I 20

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    21/72

    VARIOUS PHASESOF THE IT

    PROJECT

    BY: DR. ZEE SHAN BHATT I 21

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    22/72

    KEY POINTS IN PROJECT SET-UP AND DEFINITION

    Create Project Management Plan (PMP)

    Be clear of scope and objectives Establish clear statement of what is to be

    done (WBS)

    Establish Risks to be Managed

    Establish Costs and Durations

    Establish Resources Required

    BY: DR. ZEE SHAN BHATT I 22

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    23/72

    PROJECT MANAGEMENT PLAN - PMP

    Master Document for Project

    Defines the following:-

    Project Objectives, Scope, Deliverables

    Stakeholders (Internal & External)

    Work to be done (WBS)

    Project Organisation and Resources (OBS)

    Project Costings (CBS)

    Project Schedule

    Procurement/Contract Strategy

    Risk Management

    Quality management

    Change Management BY: DR. ZEE SHAN BHATT I 23

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    24/72

    PROJECT PLANNING

    BY: DR. ZEE SHAN BHATT I 24

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    25/72

    PROJECT PLANNING

    Adequate planning leads to the correct completion of

    work

    25

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    26/72

    PROJECT PLANNING

    “The larger, more complex or uncertain an endeavour is,

    the more important planning becomes”

    Lockyer & Gordon

    What measures would you use to determine thecomplexity of a project?

    BY: DR. ZEE SHAN BHATT I 26

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    27/72

    PLANNING

    Inadequate planning leads to frustration towards the end of the project & poorproject performance

    Project Start Project End

    27

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    28/72

    WHY PLAN?

    IS development is complex and time consuming

    There are usually a number of people involved with a

    project

    Communication Informs Project Manager/Team of the state of the project

    Customer confidence

    BY: DR. ZEE SHAN BHATT I 28

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    29/72

    WHY PLAN?

    Projects are unique and therefore there will always beuncertainties

    Need to plan for these (Plan B)

    So… For anything more than the smallest project, planning must be a formal

    process

    BY: DR. ZEE SHAN BHATT I 29

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    30/72

    PROJECT PLANNING FOR IS

    Requires knowledge drawn from: Development techniques

    Application domain

    Project planning techniques

    Skills abilities and motivation of developers

    Business and organisational environment

    BY: DR. ZEE SHAN BHATT I 30

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    31/72

    PROJECT PROPOSALS

    Project planning starts with the project proposal -Result of Conception Phase

    Maybe a response to a project brief prepared by an external or internal customer

    BY: DR. ZEE SHAN BHATT I 31

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    32/72

    PROJECT INITIATION

    Project initiation document Internal or external

    Project manager needs a good appreciation ofrequirements This may require extra work

    Customer needs report on unknowns

    protects both the project team and the customer

    BY: DR. ZEE SHAN BHATT I 32

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    33/72

    THE PROJECT PLAN – SIMPLE FORM

    The project plan is an attempt to timetableall the activities that make up a project

    How will the project be divided

    Who does what

    When are tasks carried out

    BY: DR. ZEE SHAN BHATT I 33

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    34/72

    THE PROJECT PLAN

    More detail can be added to the plan to indicate: Level of performance and quality

    Costs

    Further detail indicates: availability of the resources required to carry out each task

    BY: DR. ZEE SHAN BHATT I 34

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    35/72

    THE PROJECT PLAN

    Summary plan Shows key tasks, events and milestones in the systems project

    Primarily used for reporting progress

    Detailed plan Task plan

    Time control plans

    Resource plan Cost plans

    Primarily used as a working tool

    BY: DR. ZEE SHAN BHATT I 35

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    36/72

    Project Planning

     A word about Scheduling

     –Schedules (task durations) can have a wide

    variation

     –There is no unique answer. Rather, there is a

    statistical variation depending on assumptions

     –Need to understand the basis of scheduling

    (Most challenging; Most likely; Absolute certainty

    - bet your life on it!) –Most people are very optimistic/naive

    BY: DR. ZEE SHAN BHATT I 36

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    37/72

     

    Monitor &

    Review

    PLANNING AND CONTROL CYCLE 

    Plan

    BY: DR. ZEE SHAN BHATT I 37

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    38/72

    ITERATIVE PROCESS

    The plan will evolve as the project evolves

    The plan is reviewed and updated as more informationbecomes available and uncertainties become less uncertain

     

    Monitor &

    Review

    Plan

    Monitor &

    Review

    Plan

    Monitor &

    Review

    Plan

    BY: DR. ZEESHAN BHATTI 38

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    39/72

    THE PROJECT PLAN – SIMPLE FORM

    How will the project be divided?Work breakdown structure

    Product breakdown structure

    When will the work be carried out? Gantt Chart

    Who does what?

    BY: DR. ZEE SHAN BHATT I 39

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    40/72

    WORK BREAKDOWN STRUCTURE

    Work broken down in a hierarchical manner until: Each task is “atomic”

    Duration can be estimated with reasonable accuracy

    Can be carried out by one person

    Each task : Has a well defined beginning and end Will consume resources

    May be dependant on other tasks

    BY: DR. ZEE SHAN BHATT I 40

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    41/72

    WORK BREAKDOWN STRUCTURE (WBS)

    The Work Breakdown Structure is the foundation foreffective project planning, costing and management.

    It is the most important aspect in setting-up a Project

    It is the foundation on which

    everything else builds

    41

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    42/72

    WORK BREAKDOWN STRUCTURE - DEFINITION

    “A Work Breakdown Structure (WBS) is ahierarchical (from general to specific) tree

    structure of deliverables and tasks that need tobe performed to complete a project.”

    BY: DR. ZEE SHAN BHATT I 42

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    43/72

    WBS EXAMPLE  Project

    ConductInvestigation

    ProduceReport

    InvestigateOther Systems

     AnalyseRequirements

    InvestigatePackages

    InvestigateHardware

    ConductInterviews

    FinanceDirector

    StoresManager

    Sales Manager Etc.ManagingDirector

    Write Notes Review Notes Create DFD’s  Review DFD’s ConductInterview

    BY: DR. ZEE SHAN BHATT I 43

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    44/72

    EXAMPLE WBS - TOP LEVEL PROJECT A

    Be

    Recycling1.1.1.0.0

    Bulk WDivertor 1.1.2.0.0

    W Coatings

    1.1.3.0.0

    Markers

    1.1.4.0.0

    R&D

    Management1.1.5.0.0

    Research &

    Development1.1.0.0.0

    Sliced Be

    Tiles1.2.1.0.0

    Bulk MetalTiles1.2.2.0.0

    W Coated

    CFC Tiles1.2.3.0.0

    Embedded

    Diagnostics1.2.4.0.0

    Engineering D&M

    Management1.2.5.0.0

    Bulk W

    Tiles1.2.6.0.0

    Component Inspect

    & Re-pack1.2.7.0.0

    Engineering

    Design & Manufacture1.2.0.0.0

    Remote

    Handling1.3.1.0.0

    Torus InstallationGroup1.3.2.0.0

    Waste Man.

    Group1.3.3.0.0

    Vacuum

    Group1.3.4.0.0

    ILW Tile Removal

    & Replacement1.3.5.0.0

    EP2 Shutdown

    Management1.3.6.0.0

    EP2

    Shutdown1.3.0.0.0

    Overall Project

    Management1.4.1.0.0

    ContractualManagement1.4.2.0.0

    Safety & HP

    Management1.4.3.0.0

    Quality

    Management1.4.4.0.0

    FZJ Contract

    Management1.4.5.0.0

    Project

    Management1.4.0.0.0

     Assess JET

    Be Stocks1.5.1.0.0

    Prepare & ShipJET Be1.5.2.0.0

    Be

    Recycling1.5.0.0.0

    Sliced Be Tiles

    Install Prep.1.6.1.0.0

    Bulk Metal TilesInstall Prep.1.6.2.0.0

    W Coated CFC

    Install Prep.1.6.3.0.0

    Embed. Diag.

    Install Prep.1.6.4.0.0

    Install Prep.

    Management1.6.5.0.0

    Install Prep.

    Bulk W1.6.6.0.0

    Install Prep.

    Other Activities1.6.7.0.0

    Installation

    Preparation1.6.0.0.0

    Engineering

    Design & Manuf.1.7.1.0.0

    Erosion/Deposition Assemby & Calib.1.7.2.0.0

    Erosion/Deposition

    Installation1.7.3.0.0

    Erosion/Deposition

    Management1.7.4.0.0

    Erosion/Deposition

    for ILW1.7.0.0.0

    ITER-Like

    Wall Project

    1.0.0.0.0

    BY: DR. ZEE SHAN BHATT I 44

    EXAMPLE WBS TOP LEVEL PROJECT B

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    45/72

    EXAMPLE WBS - TOP LEVEL PROJECT B

    Key ProjectMilestones1.1.1.0.0

    Key Project

    Deliverables1.1.2.0.0

    Key ITERMilestones & IPL

    1.1.3.0.0

    OverallManagement

    1.1.4.0.0

    Safety & HP

    Management1.1.5.0.0

    RiskManagement

    1.1.6.0.0

    Quality

    Management1.1.7.0.0

    LIDAR ProjectManagement

    1.1.0.0.0

    Overall Cluster Co-ordination

    1.2.1.0.0

    Performance

     Analysis1.2.2.0.0

    LIDARNeutronics1.2.3.0.0

    ScatteringTheory

    1.2.4.0.0

    R&D

    Tasks1.2.5.0.0

    RadiationEffects Data

    1.2.6.0.0

    Remote

    Handling1.2.7.0.0

    ItemTest Unit1.2.8.0.0

    Engineering Analysis1.2.9.0.0

    LIDAR SystemConcepts1.2.0.0.0

    Lasers1.3.1.0.0

    Laser 

    Layout1.3.2.0.0

    Laser BeamCombiner 1.3.3.0.0

    Laser Systems1.3.0.0.0

    Collection Optical Design

    1.4.1.0.0

    Collection

    Windows1.4.2.0.0

    In-VacuumCollection Mirrors

    1.4.3.0.0

    Ex-VacuumCollection Optics

    1.4.4.0.0

    Collection Optics

    Mechanical Design1.4.5.0.0

    Spectrometer System

    1.4.6.0.0

    Detectors

    1.4.7.0.0

     AlignmentSystem

    1.4.8.0.0

    CalibrationSystem

    1.4.9.0.0

    CollectionOptics

    1.4.0.0.0

    Laser PathOptical Design

    1.5.1.0.0

    Laser 

    Windows1.5.2.0.0

    Plasma FacingLaser Mirrors

    1.5.3.0.0

    Other Laser Mirrors

    1.5.4.0.0

    Laser Path

    Mechanical Design1.5.5.0.0

    BeamDump

    1.5.6.0.0

     Alignment

    System1.5.7.0.0

    CalibrationSystem

    1.5.8.0.0

    Laser PathOptics

    1.5.0.0.0

    Control SystemInterface Definition

    1.6.1.0.0

    Control

    System1.6.2.0.0

     AcquisitionSystem

    1.6.3.0.0

    LIDARInstrumentation

    1.6.4.0.0

    Safety

    Interlocks1.6.5.0.0

    SafetySystem

    1.6.6.0.0

    Control & Acquisition

    1.6.0.0.0

    Shutters1.7.1.0.0

    Labyrinth

    1.7.2.0.0

    Extension Tubes &Mirror Mounting

    1.7.3.0.0

    External Port OpticsMounting

    1.7.4.0.0

    Bioshield

    1.7.5.0.0

    BSMPenetrations

    1.7.6.0.0

    EM Analysis for 

    In-Port Comp.1.7.7.0.0

    LIDARPort Engineering

    1.7.0.0.0

    Water Services1.8.1.0.0

    Interspace

    Vacuum1.8.2.0.0

    LIDARPower 

    1.8.3.0.0

    Spectrometer  Area

    1.8.4.0.0

    Laser 

    Room1.8.5.0.0

    Port Cell/Interspace

    1.8.6.0.0

    LIDARServices1.8.0.0.0

    LIDARInterfaces1.9.1.0.0

    Mock-up

    Facility1.9.2.0.0

    Basic Mock-upTests

    1.9.3.0.0

    TokamakTests

    1.9.4.0.0

    Final System

    Testing1.9.5.0.0

    System Assembly& Dis-assembly

    1.9.6.0.0

    Interfaces &Integrated Testing

    1.9.0.0.0

    Thomson ScatteringCore (LIDAR)5.5.C.1.0.0.0.0

    OpticalSystems

    5.5.C.0.0.0.0.0

    BY: DR. ZEE SHAN BHATT I 45

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    46/72

    Project Planning – WBS (1)

    Lowest Level of WBS is the Work Package (WP)

    WP can be clearly defined allowing package to be

    costed, scheduled and resourced

    WP contains a list of Tasks to be Performed that

    form the basis for the Schedule

    WP allows assignment of responsibilities (Work

    Package Manger, WPM)

    BY: DR. ZEE SHAN BHATT I 46

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    47/72

    Project Planning – WBS (2)

    WBS allows hierarchical build-up of costs and

    schedule

    Cost and Schedule can be reported at any level of

    the WBS

    WBS facilitates strong management during project

    execution (Cost and Schedule control)

    WBS can be used for many other things -

    Document Management, Risk Management etc.BY: DR. ZEE SHAN BHATT I 47

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    48/72

    PRODUCT BREAKDOWN STRUCTURE

    Concentrates on what is to be done, rather than how it isto be done

    More difficult to forget a product/element

    Easier to assign quality measures/procedures

    Process is more likely to fit if developed after product

    Example {http://www.gifpa.co.uk/news/6/plans.html}

    BY: DR. ZEE SHAN BHATT I 48

    http://www.gifpa.co.uk/news/6/plans.htmlhttp://www.gifpa.co.uk/news/6/plans.html

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    49/72

    PBS EXAMPLE

     

    Project

    DesignDeliverables

    DatabaseDeliverables

    GUIDeliverables

    FunctionalDeliverables

    ProjectManagementDeliverables

     

    BY: DR. ZEE SHAN BHATT I 49

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    50/72

    PBS EXAMPLE 

    Project

    Design

    Deliverables

    Database

    Deliverables

    GUI

    Deliverables

    Functional

    Deliverables

    Project

    ManagementDeliverables 

    Produce ClassDiagrams

    Produce UseCases

    Produce ActivityDiagrams

    BY: DR. ZEE SHAN BHATT I 50

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    51/72

    THE PROJECT PLAN – SIMPLE FORM

    • How will the project be divided?

     – Work breakdown structure

    • When will the work be carried out?

     – Gantt Chart

    • Who does what?

    BY: DR. ZEE SHAN BHATT I 51

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    52/72

    GANTT CHART (SOURCE : WW.GANTT.COM)A Gantt chart, commonly used in project management, is one of the mostpopular and useful ways of showing activities (tasks or events) displayedagainst time. On the left of the chart is a list of the activities and along thetop is a suitable time scale. Each activity is represented by a bar; theposition and length of the bar reflects the start date, duration and end date

    of the activity. This allows you to see at a glance:

    What the various activities are

    When each activity begins and ends

    How long each activity is scheduled to last

    Where activities overlap with other activities, and by how much

    The start and end date of the whole project

    To summarize, a Gantt chart shows you what has to be done (the activities)and when (the schedule).

    BY: DR. ZEE SHAN BHATT I 52

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    53/72

    EXAMPLE GANTT CHART

    BY: DR. ZEE SHAN BHATT I 53

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    54/72

    EXAMPLE GANTT CHART

     Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14

     AB

    C

    D

    E

    F

    G

    Week Number 

    BY: DR. ZEE SHAN BHATT I 54

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    55/72

    EXAMPLE GANTT CHART

    BY: DR. ZEE SHAN BHATT I 55

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    56/72

    EXAMPLE GANTT CHART

     Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14

     AB

    C

    D

    E

    F

    G

    Week Number 

    BY: DR. ZEE SHAN BHATT I 56

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    57/72

    GANTT CHART COMPONENTS

     An Activity/Task is represented as follows:

    The length of the bar is proportional to theduration time of the activity

    Start Finish

    BY: DR. ZEE SHAN BHATT I 57

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    58/72

    GANTT CHART COMPONENTS

    Progress on an Activity/Task can be shown as follows:

    The length of the bar is proportional to theamount of work completed.This example is approx 50% complete

    Start Finish

    BY: DR. ZEE SHAN BHATT I 58

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    59/72

    EXAMPLE GANTT CHART

     Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14

     AB

    C

    D

    E

    F

    G

    Week Number 

    BY: DR. ZEE SHAN BHATT I 59

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    60/72

    EXAMPLE GANTT CHART

     Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14

     AB

    C

    D

    E

    F

    G

    Week Number 

    BY: DR. ZEE SHAN BHATT I 60

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    61/72

    EXERCISE

     Activity Start (Week No) Duration (Weeks) % Complete

     A 1 5 100

    B 2 3 100

    C 1 8 75

    D 3 4 100

    E 5 5 60

    F 2 4 25

    G 10 6 0H 6 6 100

    I 7 2 50

    J 8 6 50

    BY: DR. ZEE SHAN BHATT I 61

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    62/72

    EXERCISE

     Activity Start (Week No) Duration (Weeks) % Complete

     A 1 5 100

    B 2 3 100

    C 1 8 75

    D 3 4 100

    E 5 5 60

    F 2 4 25

    G 10 6 0H 6 6 100

    I 7 2 50

    J 8 6 50

    BY: DR. ZEE SHAN BHATT I 62

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    63/72

    GANTT CHART ADVANTAGES

    It is good at showing timing

    It shows project progress clearly

    It is therefore an ideal tool for the summary plan

    BY: DR. ZEE SHAN BHATT I 63

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    64/72

    GANTT CHART DISADVANTAGES

    Not ideal for showing inter-relationships MS Project does do this

    Locating an activity requires three simultaneousdecisions: Method

    Time

    Resources

    BY: DR. ZEE SHAN BHATT I 64

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    65/72

    • How will the project be divided?

     – Work breakdown structure

    • When will the work be carried out?

     – Gantt Chart

    • Who does what?

    THE PROJECT PLAN – SIMPLE FORM

    BY: DR. ZEE SHAN BHATT I 65

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    66/72

    BENEFITS OF PLANNING

    Avoids the cost of the chaos that would ensue ifthe project was unplanned

    Filters out projects that would provide a negativereturn

    Being able to resolve problems in advance

    Being able to allocate resources in advance

    BY: DR. ZEE SHAN BHATT I 67

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    67/72

    TWO VIEWS TO A PLAN

    The Plan is a straight-jacket Very Precise

    Focus on data

    The Plan is a working tool Very Accurate

    Focus on information

    BY: DR. ZEE SHAN BHATT I 68

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    68/72

    WHO DOES PLANNING

    Developing the project plan is an iterativeprocess that involves: Project manager Project team

    Project sponsor

    Customer

    Other stakeholders

    BY: DR. ZEE SHAN BHATT I 69

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    69/72

    LECTURE SLIDE REFERENCES

    Slides Material By:

    Dr Martin [email protected]

    Slide Reference Book:

    IT Project Management Handbook

    By: Jag Sodhi, Prince Sodhi

    BY: DR. ZEE SHAN BHATT I 70

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    70/72

    REFERENCES BOOKS USED

    IT Project Management Handbook

    By: Jag Sodhi, Prince Sodhi

    Project Management Nation: Tools,Techniques, and Goals for the Newand Practicing IT Project Manager

    By: Jason CharvatISBN: 0471139262

    BY: DR. ZEE SHAN BHATT I 71

    THANKYOU

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    71/72

    THANKYOU

    Q & A

    BY: DR. ZEESHAN BHATTI

    For Course Slides and Handouts

    Blog:http://zeeshanacademy.blogspot.com/

    Facebook:

    https://www.facebook.com/drzeeshanacademy

    72

    http://zeeshanacademy.blogspot.com/http://zeeshanacademy.blogspot.com/

  • 8/19/2019 Chapter 2 _ IPM _ Developing Project Plan

    72/72