chapter 1 introduction -...
TRANSCRIPT
Environmental Impact Assessment Report 2014
1 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER 1
INTRODUCTION
Environmental Impact Assessment Report 2014
2 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
1.0 INTRODUCTION
1.1 BACKGROUND OF THE PROPOSED PROJECT
This is a proposal for expansion of Sugar cane crushing capacity from 10000TCD to
20,000 TCD, Co-generation power plant from 44 MW to 75 MW & Molasses based
Distillery from 75 KLPD to 200 KLPD in the premises of M/s UGAR SUGAR WORKS
LTD.(USWL) Ugar Khurd, Tal: Athani, Dist: Belgaum, State: Karnataka.
Image 1.1: The Ugar Sugar Works Ltd. Ugar Khurd
USWL has distillery, IML section and Co-generation plant. The company has expanded
its capacity from time to time and the present capacity is 10000TCD and 44 MW co-
generation, out of which 28 – 30 MW is exportable. The factory started Distillery in the
year 1963 & the present capacity of the distillery is 75 KLPD (30 KLPD batch type & 45
KLPD continuous type). Consisting of 20 KLPD Ethanol Plant & 50 KLPD ENA Plant with
blending & bottling of 9 different IML varieties. The company has provided fully fledged
effluent treatment plant which includes bio-digesters, concentration & spray drying of
spent wash, treatment of sugar factory effluent etc. The company has also provided
biogas plant where filter cake is used for domestic fuel requirement. The gas is provided
to 170 residential quarters. Filter cake is a by-product of sugar factory.
Environmental Impact Assessment Report 2014
3 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
1.2 BACKGROUND OF PROJECT PROPONENT OF THE PROPONENT
The Ugar Sugar Works Ltd. is one of the pioneers in sugar production in the state of
Karnataka; the Company was incorporated on 11th September 1939, under the able
guidance and kind patronage of his late highness. The Rajasahab of Sangli with a
crushing capacity of 500 tons per day. Vaidya and Company was the first Managing
Agents. In the year 1940, M/s. Shirgaokar Brothers were called to manage the affairs of
the Company and they were the Managing Agents till 31st December 1969. M/s.
Shirgaokar Brothers who had by then made the Kolhapur Sugar Mills outstanding and
notable success proved to be successful in bringing up the Ugar Sugar Works Ltd., also.
Under the overall supervision and control of M/s. Shirgaokar Brothers the crushing
capacity of the factory has been increased from time to time.
The company has introduced number of irrigation schemes for the development of
sugarcane in the area. The company has started its own distillery during the year 1962-
63 and liquor section in the year 1967-68. New distillery plant unit with production
capacity of 45000 liters of rectified spirit has been commissioned in March 1995.
Present Director board of the company is as follows:
Ø Shri. R.V.Shirgaokar’ (C & M)
Ø Shri. P.V. Shirgaokar (E V C)
Ø Shri. S.S. Shirgaokar (MD)
Ø Shri N. S. Shirgaokar (Jt. MD)
Ø Shri C. S. Shirgaokar (Jt. MD)
Ø Shri M. R. Desai (Director)
Ø Shri V. Balasubramanyam (Director)
Ø Shri S. N. Inamdar (Director)
Ø Shri M. G. Joshi (Director)
Ø Shri D. B. Shah (Director)
1.3 PURPOSE OF THE ENVIRONMENTAL IMPACT ASSESSMENT
Industrial activities such as invariably involve utilization of natural resources and
generation of waste substances and they may have adverse consequence to the
environment. However, mankind as it is developed today cannot live without taking up
these activities for his food, security or other needs. Hence, there is a need to
harmonious developmental activities with the environmental concern. EIA is one of the
Environmental Impact Assessment Report 2014
4 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
tools available with the planners to achieve the above goal. It is desirable to ensure that
the project activity is sustainable. Hence, the environmental consequence must be
characterized early in the project cycle and accounted for in the project design.
The objective of EIA is to foresee the potential environmental problems that would arise
out of the proposed development and address them in the project planning and design
stage. The present EIA report incorporates the environmental consequence of the
proposed ethanol project along with the measures adopted in the distillery for control of
pollution and enhancement of environmental quality.
Before establishment of any project, under Environmental Protection Act (EPA) 1986, it
is mandatory for the project proponents to obtain clearance on environmental angle from
State pollution control board. The industries seeking consent for establishment have to
make application to state pollution control board in the prescribed forms along with
Environmental Management Plan (EMP) and other details related to pollution control and
environmental protection.
Further, the proposed project is listed under EIA Notification dated 14-09-2006 of
Ministry of Environment and Forests (MoEF). As per the above notification, prior
environmental clearance from MoEF is mandatory before establishment of this industry.
Hence, the industry is to follow due course of procedure to secure EC including
application to MoEF for EC, Terms of References for conduct of EIA studies, Public
hearing/consultation and deliberation of the project at Expert Appraisal Committee of
MoEF. Accordingly, the project proponents have submitted prescribed application along
with pre feasibility report to the MoEF New Delhi seeking Terms of Reference (TOR) for
conduct of EIA studies. MoEF, New Delhi has deliberated the project ‘Terms of
Reference (TOR)’ during the 5th reconstituted Expert Appraisal Committee (Industry)
held during 31st January, 2013– 1st February, 2013. The ToR granted by MoEF as per
MoEF letter no. J-11011/315/2012-1AII (I) dtd. 22 March 2013. Accordingly the EIA
studies were conducted and the present report is prepared for submission to authorities.
With EIA report and other documents the industry has to approach KSPCB to conduct
Public Hearing/ Consultation.
Environmental Impact Assessment Report 2014
5 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
1.4 BRIEF DESCRIPTION OF NATURE, SIZE AND LOCATION OF PROJECT
Table 1.1: Description of Project
Sr.
No.
Project
Requirement Details
1 Proposed Project
expansion of Sugar cane crushing capacity from 10000
TCD to 20,000 TCD, Co-generation power plant from 44
MW to 75 MW & Molasses based Distillery from 75
KLPD to 200 KLPD in the existing premises of M/s
UGAR SUGAR WORKS LTD.(USWL) Ugar Khurd, Tal:
Athani, Dist: Belgaum, State: Karnataka.
2 Location
Survey nos.1, 1A, 45 A, 267, 267 A, 268,373, 376,376A.
Village - Ugar Khurd, Tal - Athani, Dist-Belgaum,
Karnataka.
Latitude: 16°39'0.90"N
Longitude: 74°49'14.71"E
3 Plot Area Total Plot area - 251.31 acres
4 Total Factory Area Present factory area – 55 acres
5 Total Water
requirement 14310 m3/day
6
RAW MATERIAL EXISTING PROPOSED
Cane 10000TCD 20,000 TCD
Lime 24 MT/day 40 MT/day( Rajasthan)
Sulphur 6 MT/day 10 MT/day.(Indian/Imported)
7
PRODUCTS EXISTING PROPOSED
Sugar 10,000 TCD 20, 000 TCD
BY PRODUCTS EXISTING PROPOSED
Bagasses
3000 MT/Day 6000 MT/Day
Environmental Impact Assessment Report 2014
6 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Filter cake 400 MT/Day 800 MT/Day
Molasses 400 MT/Day 800 MT/Day
8 Nearest City Miraj City is 25 Kms
9 Nearest Railway
Station Ugar khurd Railway Station: 2 Kms.
10 Nearest
Headquarters The Belgaum district headquarter is 100 kms.
11 Nearest Highway
1. The National highway No.4 is 70Kms
2. State highway Sankeshwar to Bijapur is 10 km away
from the sugar factory.
12 Wildlife Sanctuary,
Eco Sensitive Zone Does Not Exist
1.5 NEED FOR THE PROJECT
All the nearby plants are going for the expansion and the forecast is total crushing days
will be reduced. Previously it was only one sugar factory in Athani taluka, now there are
6-7 sugar factories in the radius of 20 to 30 KM.
Athani farmers sugar factory is going for expansion to 5000 TCD, Krishna SSK is going
for expansion to 5000 TCD, Renuka Sugar Kokatnur is going for expansion to 15000
TCD, Renuka Sugar Raibag SSK is going for expansion to 5000 TCD, Mohanrao Shinde
Arag is 2500 TCD and Shirguppi sugar has commissioning with capacity of 5000 TCD.
The new plant Shivshakti sugar is coming up with capacity 2500 TCD.
To achieve maximum crushing in minimum crop days with maximum sugar recovery it is
essential to go for expansion. Present overheads at Ugar are already high, which leads
to face difficulties in arriving at competitive cane price. Hence Ugar Sugar management
is proposing to expand the sugar plant capacity to 20000 TCD.
Ugar Sugar has already taken steps to overcome the bottlenecks faced to crush 416.66
TCH (10000 TCD in 24 hrs) and during last season USWL has crushed almost 416.66
TCH. One of the bottlenecks is still exists i.e.at cane unloading station of 42 x 84 mill.
Due to space constraint and lower capacity cane un-loaders they are unable to maintain
Environmental Impact Assessment Report 2014
7 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
uniform cane feeding. Bagasse moisture will be on higher side, which leads to
fluctuations in boiler steam working parameters and in turn affects the crushing. Along
with cane unloading station the other parameters, i.e. reduction in crop days in future,
higher overheads per ton of cane and competitive cane price, sugar plant expansion
seems to be essential. Hence USWL proposing to expand the crushing capacity.
Along with the expansion of the sugar plant capacity to 20000 TCD it is also proposed to
expand cogen power plant capacity to 75 MW with distillery of 200 KLPD capacity.
1.6 Terms of Reference (TOR) Compliances:
Draft Terms of Reference (TOR) have been discussed and finalized during the 5th
Reconstituted Expert Appraisal Committee (Industry) held during 31st January, 2013–
1st February, 2013 for preparation of EIA/EMP report. Following are the ‘TORs’:
Table 1.2: ToR Compliance
Sr. no Terms of References
1 Executive summary of the project.
2 Compliance of environmental conditions prescribed by the SPCB for the existing sugar & Distillery unit
3 Detailed breakup of the land area along with latest photograph of the area.
4 Present land use based on satellite imagery.
5 Details of site and information related to environmental setting within 10 km radius of the project.
6 Location of national park/Wild life sanctuary/Reserve forest within 10 km radius of the project.
7 Permission from the forest department regarding the impact of the proposed plant on the surrounding reserve forest.
8 List of existing distillery units in the study area along with their capacity.
9 Number of working days of the distillery unit and CPP
10 The cost of the project along with total capital cost and recuring cost/annum for environmental pollution control measures.
11 Manufacturing process details of sugar plant and CPP along with process flow chart.
12 Details of raw materials and source of raw material molasses,bagasse etc.
Environmental Impact Assessment Report 2014
8 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
13 Sources and quantity of fuel (coal etc)for the boiler.Measures to take care of SO2 emission.A copy of memorandum of Understanding(MoU)signed with the coal suppliers should be submitted,in case coal is uesd.
14 Action plan prepared by the SPCB to control ambient air quality as per Standards for PM10 PM2.5 SO2&NOX as per GSR 826(E) dated 16 th
November,2009.
15 One season site-specific micro-meterological data using temperature,relative hourly wind speed and direction and rainfall and AAQ data(except monsoon)for PM10 ,SO2&NOX and HC(methane&non methane) should be collected.the sensitive receptors including reserved forests.Data for water and noise monitoring should also be included.
16 Mathamatical modeling for calculating the dispersion of air pollutents and ground level concentration along with emission from the boiler.
17 An action plan to control and monitor secondary fugitive emission from all the sources.
18 Details of boiler & its capacity.Details of the use of steam from the boiler.
19 Ground water quality around existing spent wash storage lagoon and the project area.
20 Details of water requirement,water balance chart for sugar & co-generation plant Measures for conservation water by recycling and reuse to minimize the fresh water requirement.
21 Prior’permission’ from competent Authority for the drawl of the total fresh water source of water supply.
22 Hydro-geological study of the area for availability of ground water.
23 Proposed effluent treatment system for sugar unit as well as CPP and scheme for achiving ‘zero’ discharge
24 Logoon capacity for sugar unit and spent wash as well measures to be taken to control ground water contamination.
25 Details of solid waste management including management of boiler ash.submit ash management plan.MoU with cement for the use of fly ash.
26 Green belt development as per the CPCB guidelines .
27 List of flora & fauna in the study area.
28 Noise levels monitoring at five locations within the study area.
29 Detailed Environment management plan(EMP)with specific reference to details of pollution control system,water & waste water management,monitoring
Environmental Impact Assessment Report 2014
9 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
responsibility and time bound implementation plan for mitigation measure provided.
30 EMP should also include the concept of waste-minimization, recycle/reuse techniques,Energy conservation,and natural resource conservation.
31 Details of bagasse storage.Details of press mud requirement.
32 Action plan for rainwater harvesting measures at plant site should be included to harvest rainwater from the roof tops & storm water drains to recharge the ground water
33 Details of occupational health programme
34 Details of socio-economic welfare activities to be provided.
35 Traffic Study of the area for the proposed projects in respect of existing traffic,type of vehicles for transportation of materials,additional traffic due to proposed project,parking arrangement etc
36 Action plan for post-project environmental monitoring
37 Corporate Environmental Responsibility
38 Any litigation pending against the project and/or any direction/order passed by any court of law against the project ,if so,details thereof.
39 Public hearing issues raised & commitments made by the project proponent on the same should be included seperately in EIA/EMP Report in the form of tabular chart with financial budget for complying with the commitments made.
1.7 Scope of EIA Study:
The study envisages characterization of the existing status of physical environment such
as air, water, soil, land use, meteorology, socio-economic and heritage etc. as well as
biological environment such as flora and fauna of the study area of 10 km radius and
quantifying impacts on the environmental parameters. Based on the study, the EIA
evaluates the proposed control measures by the project and prepares an environment
management plan, outlining additional proposed activities and delineates the
requirements of environmental monitoring program. EIA study shall cover the following
aspects:
Ø Evaluation of present environmental factors through analysis of generated
and collected baseline data for one complete dry season (3 months).
Ø Assess the probable impact on the environmental factors due to
implementation of the project with respect to existing scenario.
Environmental Impact Assessment Report 2014
10 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø Analyze the predicted impact with respect to the regulatory environmental
standards.
Ø Assess the probable risk at the proposed plant.
Ø Develop an Environmental Management Plan and on site Disaster
Management Plan for the proposed project to mitigate the negative
significant impacts that would arise from the proposed project.
Ø Report shall help to obtain No Objection Certificate for consent to operate
from the State Pollution Control Board.
The baseline data has been collected for the following environmental components,
during September – November 2013:
· Air Quality
· Meteorology
· Noise Environment
· Water Use & Quality
· Soil Quality
· Land Use, Crop Pattern, Agricultural Practices
· Demographic & socio-economic aspects
· Terrestrial & Aquatic ecology
Baseline data on parameters of the above-mentioned aspects over a season provides
means for identifying possible impact-positive as well as adverse. An environmental
impact assessment and environment management plan comprising an overall
assessment of the impact due to project activity over baseline condition of the existing
environment and a mitigating action plan to counter the adverse impact as defined. An
environmental monitoring program is also prepared to provide scientific support to future
actions of environmental protection.
Methodology
A study area of 10 km radius with the proposed plant site of USL at the center was
considered for the present study. This study will help to determine the present
environmental status and likely impacts of the proposed unit’s operations, if any in the
region. The most predominant wind direction during study period was considered for
various facts of establishing and the monitoring stations were finalized.
Table: 1.3 Scope of Work for EIA report
Environmental No of Observations
Environmental Impact Assessment Report 2014
11 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Attributes Locations
Meteorology 1
Hourly observations for Temperature, Relative
Humidity, Wind direction, wind speed & Rain fall
during 3 month study period
AAQ 8
For PM10, PM2.5, SO2, NO2,Total Hydro carbon for
24 hours duration, 2 times in each week during 12-
week study period
Water 6
3 Surface water Locations
3 Ground water locations (including the place near to
the plant site), Parameters that are analyzed are as
per Analysis of Drinking Water Quality had been
carried out
Noise 8 Day and night noise levels once in every location
Ecology
Flora- Fauna &
Ecosystem
Total study period is 90 days. However predicted flora
– fauna also included for non-seasonal plant species
(ephemerals) based on existing secondary data and
field conditions
Land use
10 km Radius study area
Land use data based on satellite imagery of 10 km
radius study area.
Socio-economic data
Demography & Occupational
Details
Secondary data from the existing literature (Census
2001 & 2011)
Organisation of Report
The Generic structure of EIA is given in EIA notification dated 14th September, 2006 is
maintained. The EIA report has been divided into following chapters:
Chapter-1 Introduction
This chapter provides background information of the project, brief description and
objectives of the project, description of the area, scope and organisation of the EIA
study.
Environmental Impact Assessment Report 2014
12 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Chapter-2 Project Description
This chapter deals with the process and specifications of the project. This also deals with
the sources of pollution for the proposed project and proposed control measures.
Chapter-3 Description of the Environment
This chapter presents the methodology and findings of field studies undertaken w.r.t to
meteorology, ambient air, water, soils, noise, and ecology to define the existing
environmental status in the area. Details on land use, socio-economic and hydro-
geology which are presented from published secondary data.
Chapter-4 Anticipated Environmental Impacts
This chapter highlights the inferences drawn from the environmental impact assessment.
It describes the overall impact of the proposed integrated project and underscores the
areas where applicable environmental standards are expected to be violated. The
impact is assessed after considering both pre-project and post-project scenario.
Chapter- 5 Environmental Monitoring Program
The Environmental monitoring requirements for determining the efficiency of the
environmental protection and mitigation measures are delineated in this Chapter along
with required institutional arrangements for ensuring their implementation.
Chapter- 6 Additional Studies
This chapter describes studies carried out as per the specified TOR of the EIA. This
includes a Risk Assessment for the proposed unit along with Social-Economic study,
review of the Safety and Disaster Management Plan proposed for the proposed power
plant.
Chapter- 7 Project Benefits
This Chapter highlights the expected benefits of the proposed plant to the socio-
economic scenario in the study area and to the country as a whole.
Chapter -8 Environmental Management Plan
This Chapter consolidates the proposed and recommended environmental protection
and mitigation measures and the required institutional structure that ensures its proper
implementation during the construction as well as operational phase of the project.
Environmental Impact Assessment Report 2014
13 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
The assessment will cover the baseline data generation, predictions and evaluation of
impact on various environmental components and preparation of adequate
Environmental Management Plan.
* * * * *
Environmental Impact Assessment Report 2014
14 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER 2
PROJECT DISCRIPTION
2.1 INTRODUCTION
M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum, State:
Karnataka have Proposed Expansion of Sugar cane crushing capacity
f rom 10000TCD to 20,000 TCD, Co-generation power plant f rom 44 MW to
75 MW & Molasses based Dist i l lery from 75 KLPD to 200 KLPD.
Environmental Impact Assessment Report 2014
15 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
The site is well connected by Road, so that both the raw materials and
f inished goods can be convent ional ly handled. Total land available with
sugar factory is about 255 Acres. Bagasse is available from the sugar
plant wi l l be uti l ized as inputs in the proposed project. Land required for
the project is avai lable in the exist ing industry. Procurement of addit ional
land for the project is not needed. Water requirement wi l l be managed
within the avai lable l imits.
2.2 LOCATION OF THE PROJECT
M/s. Ugar Sugar Works Limited, Ugar khurd, Tal- Athani, Dist-Belgaum,
Karnataka. Survey nos.1, 1A, 45 A, 267, 267 A, 268,373, 376,
376A.Vil lage - Ugar Khurd, Tal - Athani, Dist-Belgaum, Karnataka
Table- 2.1 Salient features of site location
1. Project site M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal:
Athani,Dist: Belgaum, State: Karnataka
2. Latitude & longitude Latitude : 160 38’ 58. 42” N
Longitude: 740 49’14. 34” E
3. Nearest town/city
Miraj City is 25 Kms away from factory site. The
Belgaum district headquarter is 100 kms away from the
site.
4. Nearest Highway
The National highway No.4 is 70 Kms from the
proposed site and state highway sankeshwar to Bijapur
is 10km away from the sugar factory
5. Nearest Railway Junction Ugar khurd Railway Station: 2 Kms. From the sugar
factory.
6. Nearest Airport Belgaum airport is 100 Kms from the factory site.
Environmental Impact Assessment Report 2014
16 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
7. Topography
· The factory site has leveled area.
· The elevation of about 554 meter above the sea
level.
· Climate : Semi - arid
8. Surroundings · The site is 1 km from Krishna river.
Image 2.1: Google Earth image
The proposed co-gen power unit will be associated activity of the existing sugar unit. The
proposed plant will utilize bagasse available in the sugar plant. The land, water and
other infrastructural facility is available in the existing sugar industry. Hence, the project
is essentially to be located in the premise of the existing sugar industry.
The selection of site location for the industry depends mainly on the availability of
resources such as raw materials, fuel, power, water, manpower, connectivity for
Environmental Impact Assessment Report 2014
17 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
transportation of man and material, market for the product and more important is
environmental compatibility and sustainability.
2.3 COMPONENTS OF PROJECT
USWL proposes to enhance Proposed Expansion of Sugar cane crushing capacity from
10000 TCD to 20,000 TCD, Co-generation power plant from 44 MW to 75 MW &
Molasses based Distillery from 75 KLPD to 200 KLPD. At Ugar Khurd, Tal: Athani,Dist:
Belgaum, State: Karnataka. The raw material of sugar cane is available in the vicinity of
the project site and the bagasse will be used as fuel for cogeneration power plant. The
project involves:
a. SUGAR UNIT
Numbers of new sugar factories have increased in the nearby area of The Ugar Sugar
Works ltd., and also existing sugar plant expansions are taking place in the nearby area.
Hence the total cane crushing capacity is increasing in the same cane growing area,
which in turn reduces the duration of crushing days. To maintain the ultimate sugar
production target it is essential to increase the crushing capacity of USWL. At the same
time expansion of cogeneration and distillery is also essential to balance the by-
products. In this line of action management of ugar sugar have decided to go for Sugar
Plant expansion in phased manner. It is proposed to expand sugar plant capacity to
20000 TCD and cogeneration 75 MW.
Environmental Impact Assessment Report 2014
18 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
The main activity of the company is to manufacture white crystal sugar, Electrical
power, ENA, ethanol & IML
The daily Sugar cane crushing capacity of the plant after expansion will be 20000 TCD,
which means the production as follows.
Table- 2.2 Capacity of Sugar unit
Product Production per Annum in MT
Maximum
Sugar cane crushing MT 27,00,000 to 30,00,000
Sugar in QT 31,05,000 to 34,50,000
Proposed Power Generation
During season 75 MW
Proposed power export 52 MW
The raw material for manufacturing the above is Sugarcane i.e. 25 to 30 lakh MT which
is sufficient for 120 to 150 days @ 20000 TCD. The productivity of the sugar cane &
yield depend on water supply & hence, the cane can be grown in & around the
Ugar. Which is on the bank of river Krishna, has full & sufficient irrigation facility. It is
expected that yield will be 40 to 50 MT per Acre with recovery of sugar as 11% to 12%.
b. CO-GEN POWER PLANT
The co-gen plant is configured keeping in view that the sugar factory operations & also
to meet peak steam & power requirement. The installed capacity of co-gen plant is 44
MW with 4 numbers of boilers having 310 TPH capacities @ 62 bar 490 deg C temp.
Environmental Impact Assessment Report 2014
19 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Image 2.2 for the entire Boilers Wet Scrubbers Are Provided and the Stack Heights Are Maintained As Per KSPCB Norms
Image 2.3: 22.8 MW x 2 Nos SHIN NIPPON Turbine (Back)
Environmental Impact Assessment Report 2014
20 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Image 2.4: 18 MW SIEMENS Turbine Extraction Cum Condensing)
Image 2.5: Cogeneration Plant Control Room
Environmental Impact Assessment Report 2014
21 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
C. DISTILLERY
The factory started Distillery in the year 1963 & the present capacity of the distillery is 75
KLPD (30 KLPD batch type & 45 KLPD continuous types). Consisting of 20 KLPD
Ethanol Plant & 50 KLPD ENA Plant with blending & bottling of 9 different IML varieties.
The company has provided fully fledged effluent treatment plant which includes bio-
digesters, concentration & spray drying of spent wash, aerobic treatment of sugar factory
effluent etc.
There are two distilleries available with the USWL. One is of very old with the capacity of
30 KLPD and another one is of 45 KLPD. Total existing capacity is 75 KLPD. USWL is
having IML section also wherein bottling with their own brand are being manufactured.
There is a separate effluent treatment plant i.e. evaporation and drying effluent to the
recover potash powder is available with USWL.
Image2.6: Distil lery Plant No.2
Environmental Impact Assessment Report 2014
22 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
2.4 PRODUCTS:
Table 2.3: List of product and by products
Product Particulars Maximum Quantity
A)Products
Existing Proposed
Activity
Sugar 10,000 TCD 20, 000 TCD
B) By products
Bagasses 3000 MT/Day 6000 MT/Day
Filter cake 400 MT/Day 800 MT/Day
Molasses 400 MT/Day 800 MT/Day
C) Co-generation Power 44 MW 75 MW
D) Distillery Spirit, IML, Absolute
alcohol, ENA 75 KLPD 200 KLPD
2.5 RAW MATERIAL:
Table2.4: List of raw material
RAW MATERIAL EXISTING PROPOSED
Cane 12,000 TCD 20,000 TCD
Lime 24 MT/day 40 MT/day( Rajasthan)
Sulphur 6 MT/day 10 MT/day.(Indian/Imported)
In Belgaum district where the plant is located, sugar cane is available from the month of
October to April even many times the season has to extend up to the end of May.
Typically, sugar cane availability is for a period of 7 to 8 months in a year. The registered
area under sugar cane cultivation allocated to Ugar Sugar Company is 60000 acres. The
Environmental Impact Assessment Report 2014
23 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
important factor with regard to the operation of USWL is that the cane arrival is fairly
uniform and the plant reaches the maximum crushing rate within a month of season
commencement. The total cane availability during a season is approximately 40 Lakh
tonnes and most of it reaches the plant during the crushing season. But now, due to new
sugar plants installed in the nearby area, crushing season days have reduced from 8
months to 5 to 6 months.
2.6 Manufacturing Process:
The manufactur ing process of integrated sugar industry is given in below
given chart:
2.6.1 Sugar unit
The process of manufacturing involves the following steps:
I. Extraction of cane juice from cane
II. Purification of cane juice
III. Evaporation of cane juice to facilitates crystallisation
IV. Crystallisation of Sugar
V. Separation of sugar and liquid by Centrifugal force
VI. Re-Boiling of Liquid
VII. Drying
· Brief Description of The Above Process Steps Are Given Below:
24 M/s Ugar Sugar Works Ltd.Ugar Kh
Figure 2.1 Manufacturing process flow of integrated sugar industry
· The sugar industry is a chemical based industry, where different of process
involved in it .Sugar manufacturing process in brief is as under.
· The sugar cane received at the factory is weighed and then it i
with the help of cane unloader or tippler on the feeder table which is fed into the
cane carrier. The feed cane is passed through
cutter, cane levelers, fibrizer for fine participation. The prepared cane is f
through mill tandem for extraction of juice. The bagasse is removed from the last
mill in the mill tandem 95% juice is extracted with approximate 20% imbibitions
water % on cane and bagasse is send to boilers as fuel for steam production and
balance bagasse is sent for baling and storage.
Environmental Impact Assessment Report
M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
ring process flow of integrated sugar industry
The sugar industry is a chemical based industry, where different of process
involved in it .Sugar manufacturing process in brief is as under.
The sugar cane received at the factory is weighed and then it is unloaded either
with the help of cane unloader or tippler on the feeder table which is fed into the
cane carrier. The feed cane is passed through preparatory devices like cane
cutter, cane levelers, fibrizer for fine participation. The prepared cane is f
through mill tandem for extraction of juice. The bagasse is removed from the last
mill in the mill tandem 95% juice is extracted with approximate 20% imbibitions
water % on cane and bagasse is send to boilers as fuel for steam production and
gasse is sent for baling and storage.
2014
urd, Tal: Athani, Dist: Belgaum
ring process flow of integrated sugar industry
The sugar industry is a chemical based industry, where different of process
s unloaded either
with the help of cane unloader or tippler on the feeder table which is fed into the
preparatory devices like cane
cutter, cane levelers, fibrizer for fine participation. The prepared cane is feed
through mill tandem for extraction of juice. The bagasse is removed from the last
mill in the mill tandem 95% juice is extracted with approximate 20% imbibitions
water % on cane and bagasse is send to boilers as fuel for steam production and
Environmental Impact Assessment Report 2014
25 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
· Extracted juice form mill tandem is called mixed juice or raw juice. The raw juice
is weighed by mass flow meter and then it is send to raw juice heater. Here the
juice is heated up to 70°C to 75°C temperature. After raw juice heating the
heated juice is sent to sulphitation tank to remove non sugar and coloring matter
by using SO gas and milk of lime (Ca (OH) ). This juice is called as sculptured
juice. This sculptured juice is heated up to 100°C to 105°C temperature and this
juice is clarifier for settling, in this process the muddy juice is sent to raw juice
tank for reprocess.
· The clear juice from clarifier is sent to evaporator bodies for further boiling. Here
the juice is concentrated up to 55-60 Brix. This concentrated juice is called
unsulphured. This unsulphured syrup is sent to sulphitation tank for bleaching by
SO gas. This sulphur is sent to pan section for crystallization process.
· On pan section three masscult boiling system is followed. A-masscult and B-
masscult. In the pan sulphur syrup is boiled and mixture of crystals and mother
liquor called as masscult prepared. This masscult is stored in crystallizer. Then it
is sent to centrifugal section through pug mill at centrifugal section, sugar crystals
and molasses are separated, final molasses is sent to storage tank and other
molasses is re-used in process. Sugar crystals are in wet condition, dried on
hoppers with hot and cold air blowers. Dried sugar crystals are separated grade
wise through sugar grader and graded sugar.
I. Extraction of Cane Juice from Cane
The cane which is brought from fields by carts/trucks/tractors, weighed and unloaded in
the cane carrier for extraction of juice from sugarcane. The unloaded cane will pass
through preparatory devices (Chopper, leveller and fibrizer). The preparatory devices will
cut the cane stalks into pieces.
The prepared cane enters mills consist of multiple units of three roller combination
through which the prepared cane. To aid in the extraction of juice spraying thin juice
from previous mills and water before last mill, directed on the blanket of Bagasse as it
emerges from each mill help to leach out the sugar.
Environmental Impact Assessment Report 2014
26 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Use of Bagasse
The residue that leaves the last mill is called bagasse contains un-extracted sugar,
woody fibre and water. The bagasse will be used as fuel to produce steam and power as
co-generation. The generated steam will be used to run turbines for power generation.
The outlet of the turbine i.e., low pressure steam will be used for mill juice processing.
The condensed water will be sent back to boiler for steam generation during crushing
season.
II. Purification of Cane Juice – Clarification
The extracted juice from mills is strained to remove bagasse particles before sending for
process. This juice is sent through a mass flow meter and the quantity automatically
recorded. The dark green juice from mills is acidic and turbid. The universal process
employed to remove both soluble and insoluble impurities is called Sulphitation process.
The juice will be heated up to 70oC to 75oC to avoid inversion. In sugar plant as a
measure of steam economy primary heating will be done by tubular heat exchanger
using heat energy available from the condensates of evaporators and pans.
III. Evaporation
The clarified juice obtained in the clarifiers constitutes 75% water. The first stage of
concentration is carried out in equipment called the evaporator, which operates
continuously. The evaporator consists of five bodies, connected in series so that the
juice undergoes progressive concentration from the first effect to the last effect to
evaporate 75% of water which is present in the juice; for that we require steam, hence
exhaust steam from turbines at a pressure of 1.5 kg/cm2 at 125oCwill be fed to the effect
of evaporator. Subsequently due to the evaporation of the water in the first effect will
yield the same amount of vapour, which will be fed to the succeeding bodies. Due to the
difference in the pressure and the vacuum in the bodies the evaporation of juice will
takes place in all the evaporators. Initially clarified juice will have a brix of 14-160C,
reaching 55-60oC Brix from the outlet of the V body. This syrup is passed through a
tower consists of absorption of the SO2 (Sulphurdioxide) by the syrup, lowering its
original pH from 6.4 -6.8 to 4.6 -5.2. The water vapour generated from 1st evaporator will
Environmental Impact Assessment Report 2014
27 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
be used in subsequent bodies and the generated condensate will be utilised for cane
juice extraction at mills, muddy juice filtration at vacuum filters, milk of lime preparation,
pan washing and centrifuge. The excess condensate will be cooled and used for plant
utilities and on land irrigation.
IV. Crystallization
Crystallization takes place in single effect vacuum pan. The syrup obtained from the
evaporator will be boiled until saturated with sugar. At this point “seed grain” is added to
serve as nuclei for the sugar crystals and more syrup is added as the water evaporates.
Continuing the above process the pans are filled up till the desire size crystals are built
up and dropped in mixers called crystallizers. The sugar and syrup forms a dense mass
known as Massecuite.
V. Separation of sugar and liquid by centrifugal force
From the crystallizers, the massecuite will be cured in the centrifugal machines. In
centrifugals the sugar and molasses will be separated. In centrifugals there are two
types of machines
I. Continuous centrifugal Machines
II. Batch Type centrifugal machine
The continuous centrifugal machines will be used for low grade massecuites like B and
C Massecuites. The separated molasses will be taken back to the process for extracting
the dissolved sugar which is present in molasses. The separated sugar having low purity
is made as a magma minglers and it will be melted in the sugar melter and will be taken
back to the A massecuite boiling. High grade massecuite i.e., A- Massecuite will be
cured in the batchtype centrifugals. The sugar discharged from the batch centrifugal has
a high moisture level with temperature of around 60 to 65 degree centigrade.
VII. Drying
The separated sugar from ‘A’ centrifugals cooling and drying of the sugar is carried out in
a multi tray hopper, in the hopper the cold and hot air will be pass in co-current direction
to bring down the moisture and temperature of the marketable sugar. From the drier, the
28 M/s Ugar Sugar Works Ltd.Ugar Kh
sugar passes through grader where the separation of sugar of various grades depending
on the size and colour like: L-30, M
sugar will be collected in bins. The
weighing scale, stitched and will be sent to the sugar godown. Sugar is stored in 50 kg
PP bags and 50kgs “A” twill gunny bags in sugar godown.
2.6.2 COGENERATION POWER PLANT BRIEF DESCRIPTION OF PROCESS
USWL proposes to implement the Cogeneration of 75 MW power plant by installation of
50 TPH to 55 TPH and temp up-gradation from 380 to 500 deg C. The scheme of Co
generation is designed to operate plant at the rated capacity of 20000 TCD.
Fig 2.2: Manufacturing process of Cogen power plant
Selection of Pressure and Temperature for the proposed Cogeneration Power
Cycle
Environmental Impact Assessment Report
M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
sugar passes through grader where the separation of sugar of various grades depending
30, M-30, S-30 and SS-31 will takes place. The graded
sugar will be collected in bins. The sugar from the bins will be weighed in automatic
weighing scale, stitched and will be sent to the sugar godown. Sugar is stored in 50 kg
PP bags and 50kgs “A” twill gunny bags in sugar godown.
COGENERATION POWER PLANT BRIEF DESCRIPTION OF PROCESS
USWL proposes to implement the Cogeneration of 75 MW power plant by installation of
gradation from 380 to 500 deg C. The scheme of Co
generation is designed to operate plant at the rated capacity of 20000 TCD.
cturing process of Cogen power plant
Selection of Pressure and Temperature for the proposed Cogeneration Power
2014
urd, Tal: Athani, Dist: Belgaum
sugar passes through grader where the separation of sugar of various grades depending
31 will takes place. The graded
sugar from the bins will be weighed in automatic
weighing scale, stitched and will be sent to the sugar godown. Sugar is stored in 50 kg
COGENERATION POWER PLANT BRIEF DESCRIPTION OF PROCESS
USWL proposes to implement the Cogeneration of 75 MW power plant by installation of
gradation from 380 to 500 deg C. The scheme of Co-
Selection of Pressure and Temperature for the proposed Cogeneration Power
Environmental Impact Assessment Report 2014
29 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
While going for Sugar Unit of 20000 TCD, the factory has proposed 50 TPH to 55 TPH
and temp up-gradation from 380 to 500 deg C. The adaptation of pressure and
temperature are very suitable for obtaining the maximum power generation for proved
technology available for bagasse based cogeneration. Therefore, while implementation
of the cogeneration project; the parameters adopted shall be based on minimum 45 ata
pressure and 450C temperature of the boilers. Further, various parameters viz. optimum
cycle efficiency, metallurgy of pressure parts, standard range of turbine, operability,
maintainability and working performance of similar bagasse based cogeneration plants
recently commissioned have been taken into account
Operation of the Cogeneration Plant during Crushing Season
USWL proposes to implement the Cogeneration of 75 MW power plant by installation of
50 TPH to 55 TPH and temp up-gradation from 380 to 500 deg C. The scheme of Co-
generation is designed to operate plant at the rated capacity of 20000 TCD.The steam
balance, Bagasse balance and Power balance during the season operation of the
Cogeneration Plant are described as below
I. Steam Balance
Fig. 2.3: Steam balance non crushing season flow sheet
Bagasse 40.82 TPH
110 ata
540 Degree C
Steam at 2.5 ata Steam at 0.1 ata for
condenser
Steam at 8 ata
for Dist & SSP
& HP heater
12.04 TPH 61.11 TPH 26.35 TPH
100 TPH
Environmental Impact Assessment Report 2014
30 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Fig 2.4: PROPOSED STEAM BALANCE
130
Bagasse Production 254.55 TPH
Bagasse Saving 46.72 TPH
140 TPH 110 ata
22.8 MW SNM 1 Turbine
New DEC 22 MW TG
Sugar process @ 8 ata-13.64 Tph
HP heater @ 8 ata-15.55 Tph
Distillery @ 8 ata 25 TPH
12 MW Turbine
Sugar process @ 2.5 ata 363.64 TPH
1 x 55 TPH, 32 ata
& 480 Deg C
130 TPH
50 TPH 130.48 TPH
207.83 TPH
46.72 TPH
22.72 TPH 53.25 TPH
115 TPH
80 TPH
70 TPH @ 2.5 ata
Condenser 15 TPH
48 TPH
22.8 MW SNM 2Turbine
PRDS
80 TPH
15 TPH 15 TPH
115 TPH
310 TPH, 62 ata
131.81 TPH
290 TPH
DS
1.19Tp
DS
6.1Tph
Environmental Impact Assessment Report 2014
31 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
II. Bagasse Balance
Fig 2.5: PROPOSED BAGASSE BALANCE
Crushing per day 20000 TPD
Average Cane Crushed 909 TPH
909 TPH Bagasse Production
(At 29%) 263.6 TPH
263.6 TPH
Bagasse for Oliver filter & Spillage
(Losses at 1%) 9.09 TPH
254.5 TPH
Bagasse required for Old Boiler to generate steam – 22.72 TPH
Bagasse required for other boilers to generate Steam – 131.81 TPH
Bagasse required for new boiler – 53.25 TPH
46.72 TPH Bagasse Saving per Hour 46.72 TPH
Environmental Impact Assessment Report 2014
32 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
III. Power Balance
Fig 2.6: PROPOSED POWER BALANCE
Power export
v Total power generation: 52 MW
2.6.3 DISTILLARY
I. FERMENTATION SECTION:
In Fermentation process, fermentable sugars in juice/syrup/molasses are converted into
ethanol. This reaction is carried out by the yeast. This is basically metabolic activity of
yeast which converts sugar into ethanol. During the reaction Carbon-di-oxide is also
POWER GENERATION
From SNM TG Set – 44 MW
From New TG Set – 11.75 MW
From New DEC TG Set – 19.25 MW
POWER CONSUMPTION
Captive for Sugar Plant –17.55 MW
Captive for Cogen Plant –5.45 MW
EXPORTABLE POWER to
Grid – 52. MW
52. MW
75 MW
33 M/s Ugar Sugar Works Ltd.Ugar Kh
generated which is vented into atmosphere after scrub
loss.
Fig 2.7: Flow sheet of Distillery Process
Environmental Impact Assessment Report
M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
generated which is vented into atmosphere after scrubbing with water to prevent alcohol
Fig 2.7: Flow sheet of Distillery Process
2014
urd, Tal: Athani, Dist: Belgaum
bing with water to prevent alcohol
Environmental Impact Assessment Report 2014
34 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Being a exothermic reaction, heat is generated during the production of alcohol. To
maintain the Fomenter temperature constant, this heat is removed by means of external
cooling system arrangement. This system consists of Plate Heat Exchanger (PHE)
through which fermented wash is continuously recirculated by Recirculation Pumps and
heat is removed by cooling water passing through the PHE.
Air Spargers are provided in the fermenters to provide air (Oxygen) supply to the
growing yeast cells. Provision of air supply to fermenters is always better to keep yeast
cells active all the time. The air supply is regulated through flowmeters provided to each
fermenters. It also ensures suspension of the mass. Agiataors are also provided to keep
entire mass in suspension and proper mixing to have uniform temperature throughtout
the fermenter.
Fermentation System is designed to operate on both the modes
1) Continuous Fermentation
2) Batch fermentation
Depending upon the feed quality mode of operation can be selected. Yeast culturing &
prefermentation system provides active cell mass to fermenters for each batch of
fermenter or when required for continuous fermentation.
Wash Clarification System provided is exhaustive, comprising of Wash Settling Tank,
Sludge Settling Tank & Decanter removes sludge effectively from fermented wash. Clear
Fermented wash is stored in Beer well and continuously fed to distillation.
II. DISTILLATION SECTION:
WASH TO RECTIFIED SPIRIT
Multi pressure vacuum Distillation:
Environmental Impact Assessment Report 2014
35 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
The system comprises of 4 columns operating under different pressures and is designed
to produce Rectified Spirit either in liquid or vapor form.
Following columns are considered.
1. Analyzer Column – under vacuum
2. Degasifying Column – under vacuum
2. Aldehyde Column- under vacuum
3. Rectification cum Exhaust Column- under pressure
Fermented Wash from Beer Well is first passed through Beer Heater, then to
Degasifying Column top through wash Preheater where is it is heated by spent wash
from Analyser Column bottom.
Degasser Column :
In Degasser column, non condensables like CO2 and low boiling impurities are
separated and fed to Aldehyde column in the form of vapors.
Analyser Column :
From fermented wash coming down from Degasser column alcohol is stripped off and
vapors from the Analyser top are condensed in the condensers. This condensate is fed
to Rectifier Column. Spent wash is taken out from the column bottom.
Heat is supplied to the column by rectifiers vapors through reboiler.
Aldehyde Column:
In aldehyde column, the noncondensables & low boiling impurities are concentrated and
taken out as Impure Cut from the top.
Remaining alcohol water mixture from the bottom is fed to Rectifier Column.
Rectifier cum Exhaust Column:
Liquid streams from two columns i.e. Analyzer condensate & Aldehyde bottoms are fed
to the Rectifier Column. In Rectifier column alcohol is concentrated at the top. Heavy &
Light Fusel oils are taken out from the tapping provided to this column. Spent Lees is
taken out from the bottom of the column.
Environmental Impact Assessment Report 2014
36 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Rectified Spirit is taken out from the tray which is few trays below the top tray.
Here additional provision is kept for taking out direct vapors to MSDH section for
production of ethanol.
Other Equipments:
Other equipments like Condensers, Coolers, Pumps, PHE, Vapor-Liquid Separator etc
are provided as per process requirement.
III. MOLECULAR SIEVE DEHYDRATION SYSTEM
This is basically adsorption operation where water from Rectified Spirit is removed by
molecular sieves (size – 3A).
This section can be operated in two modes
1) As Stand-alone – Ethanol production from RS in liquid form
2) Integrated – Ethanol production from RS vapors from Rectifier Column in
distillation section.
In first mode RS is fed to Evaporation column where it is vaporized.
Either these vapors or vapors from Rectifier Column are first superheated in
Superheater and fed to Molecular Sieve beds filled with molecular sieve and support
balls.
Molecular Sieve Beds (2 Nos) System
This beds operates on Pressure Swing Adsorption operation. Out of two, one bed
operates as Active (Adsorption) bed where water from RS is adsorbed by the molecular
sieve and dry ethanol is produced. At the same time another bed is in regeneration
(Disorption) mode where adsorbed water is removed from the bed. These beds operates
in cycles which are entirely controlled by the control system provided. The liquid
Environmental Impact Assessment Report 2014
37 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
removed from beds contains alcohol in low concentration which is recycled back to
column.
The heat of ethanol vapor produced is used to preheat the regeneration liquid (low
strength alcohol) and the RS feed. Then the ethanol is cooled and sent to storage.
IV. BIO-METHANATION
The effluent from distillery unit is received into a receiving tank (Two day holding
capacity), where it is allowed to settle for 48 hrs. Suspended solids settled in this tank
can be removed from time to time, and clear effluent is pumped to bio digester.
The effluent after getting mixed with recycled biomass from Lamella Clarifier to maintain
a feed temperature of 36-380C is fed in to the digester. The feed rate is controlled by a
manual control valve and a flow meter provided in the feed line and the sludge recycling
line.
In the digester the effluent mixed with the recycled biomass from the Lamella Clarifier
gets further mixed with contents of the digester with the help of Central and Lateral
agitators, which provide homogeneous mixing in the digester. The digester has about
14-15 days retention capacity. Anaerobic digestion takes place in the Digester, as a
result of which BOD/COD is reduced and biogas is evolved.
The digested effluent/biomass mixture overflow into a degassing pond where entrapped
gases are released. Degassed effluent flows to Lamella Clarifier for separation of active
biomass from outgoing treated effluent.
The clarified effluent leaves the Lamella Clarifier for disposal or to secondary effluent
treatment plant, while the separated biomass is pumped back continuously into the
Digester. The excess biomass is removed form the bottom of digester regularly to
sludge during beds for disposal, or to be used as farm manure.
The biogas produced in the Digester accumulates in digester roof, from where it flows to
the gasholder. The gasholder acts as intermediate gas storage as well as a Pressure
Control Vessel (PCV).
The biogas is pumped to the boiler house by a biogas blower. Surplus gas, if any, is
burnt in a gas flare unit whenever gas is not being utilised in the boiler.
Environmental Impact Assessment Report 2014
38 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
‘Flame Arresters’ are provided in gas lines to protect the digester from backfire from the
flare and/or the boiler burner. ‘Over/Under’ pressure release device is provided on
biogas digester for its safety from over pressure/v
2.7 UTILITIES
Utilities will be provided for smooth and efficient functioning of the enhanced project of
20000 TCD Sugar Unit and 75 MW Cogeneration Plant.
In addition to raw material and product details, utilities like Land, water, power etc. also
the essential aspects, which are discussed in below given sections:
A) Water
The Continuous fermentation based 200 KLPD Ethanol Plant with multi-product
integrated project requires water maximum to 14130m3/day. Company would be drawing
water from Krishna River. Sufficient water storage facility will be created for uninterrupted
water supply. USWL has obtained the requisite permission from State Govt. for lifting of
water.
To achieve better efficiency and to maintain the plant and machinery in good condition, it
is necessary to have proper water treatment system. Raw water will be treated in water
treatment unit before using it for the process. Cooling tower make-up water will be used
after treatment in a water-softening unit. By having proper water supply system as clear
water pump etc. the Ethanol Plant can have good water supply arrangements.
B) Land Requirement
The project is identified in a non-agricultural revenue land of 50 acre. The Land Use
break up is given in the following:
Environmental Impact Assessment Report 2014
39 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
The proposed expansion will be carried out in existing premises of sugar industry having
total area of 50 acre.
Table 2.5: Land Use Break up of Project Area
S. No. Description In Square meters
1. Built Up Area 1150
2. Vacant / open land 625
3. Area for Green Belt 200000
Total Area 201775
The detailed layout plant is given as f igure 2.8.
Environmental Impact Assessment Report 2014
40 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Fig 2.8: Plant Layout
Environmental Impact Assessment Report 2014
41 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Environmental Impact Assessment Report 2014
48 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
C) FUEL:
Fuel requirement is mainly for generat ion of steam in the boiler.
Bagasse generated from the Sugar Plant and it wi l l be used as fuel for
operation of the boi ler. The fuel character ist ics are given as under:-
Table 2.6: Characteristics of Bagasse
S.No. Particulars Value
1 Calorif ic Value 4400 Kcal/kg (dry)
2250 Kcal/kg (wet)
2 Moisture content 45 – 55%
3 Ash Content 2 – 10 %
4 In sugar mill the crushed cane forms
bagasse 27 -32%
Table2.7: Characteristics of Diesel Fuel (IS: 1448)
S.No. Particulars Value
1. Acidity Nil
2. Ash%, by mass 0.01
3. Carbon residue %, by mass 0.30
4. Pour point, Max 030C for winter, 150C
for summer
5. Flash point 350C
6. Kinematic Viscosity, cSt at 40C 2.5-5.0
7. Sediment %, by mass (max) 0.05
8. Sulphur content by mass (max.) 0.05%
Environmental Impact Assessment Report 2014
49 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
9. Water content, % by volume, Max. 0.05
D) DETAILS OF MACHINERY
Table2.8: Sugar Plant Machinery
Mill Section
S.No. Description of Equipment
1 Cane loader
2 Cane unloader
3 Feeder table
4 First cane carr ier
5 Cane chopper
6 Cane level ler
7 Swing Hammer Fibrizer
8 Rake type carr ier
9 Belt conveyor with tramp iron separator
10 Cane equalizer
11 Intermediate Rake carr ier
12 Mil l ing Plant
13 Mil l house Crane
14 Belt Conveyor
15 Rake type bagasse elevator
16 Lubrication System
17 Juice Tray
Environmental Impact Assessment Report 2014
50 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
18 Donnelly Chute
19 Pumps
20 Lubricants for Mil l House Package
21 Rotary screen juice
Table2.9: Boiling House Machinery:
S.No. Particulars
1. Raw juice
2 Juice heaters
3 Juice sulphitor
4 Sulphur burner
5 Air blowers
6 Milk of l ime preparation
7 Juice clar if ier
8 Vacuum f il ter
9 Evaporator Quintuple
10 Syrup sulphitor
11 Syrup & molasses storage tanks
12 Batch type & Cont inuous vacuum pans
13 Crystal l izers
14 Condensers and injection pump station
15 Sugar melter
Environmental Impact Assessment Report 2014
51 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
16 Sugar drying
17 Mild steel fabricated vapour pipe
18 Insulation
E) MAN POWER REQUIREMENT / EMPLOYMENT
The total number of employees (including off ice staff and contract
labour) wi l l be 1800 nos. (Permanent, seasonal & temporary).
F) PROJECT COST
The total project cost is estimated Rs.38367.48 lakhs; out of this Rs.
199 Crs are proposed for expansion.
G) BUILDING MATERIALS
The majority of construct ion work is in fabricat ion f rom Mild steel
structural. The or ientat ion is so kept as to balance near ly the cutt ing and
f i l l ing. The small requirements are avai lable systemat ical ly. The
construct ion –erect ion t ime wil l be smal l and wil l be done in day t ime.
Labour camp is not necessary.
2.8 CASCADING POLLUTION
There wil l not be any signif icant pol lut ion during the construction
phase. Adequate provisions wil l be made available during operat ional
phase.
2.8.1 AIR
Air quality around the project site will not be impacted dur ing
construction phase.
Further to minimize any impact fol lowing measures shall be taken:
Environmental Impact Assessment Report 2014
52 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø The raw material handling wil l be located as per the predominant
wind direction, in such a way that the fugit ive dust generated
from the site wil l be primari ly contained within the construction
si te only.
Ø The raw material handling yard wil l be suitably enclosed so as to
generate minimum air born dust.
Ø Al l the loose material either stacked or transport wil l be provided
with sui table covering such as tarpaulin, etc.
Ø Water sprinkl ing wil l be done at the locations where dust
generation is anticipated.
Ø To minimize the occupat ional health hazard, proper personal
protective gears i .e. mask wil l be provided to the workers who
are engaged in dust generation activity.
Emission Control Equipments (ECE)
The air pollut ion caused by this industry is mainly from dust as
suspended part iculate matter (SPM) from Cogenerat ion power plant –
boi lers and fuel of diesel generat ing set (DG set).
USWL knows from which unit operat ion or process, air pol lutants are
expected. For the purpose of arresting and captur ing the pollutants,
measures are proposed and designed. The detai led note on Design
basis of boi lers along with f low sheet is enclosed as Annexure 13 &
14.
Sources of Air Pollutants
1. Boiler
The industry have proposes to cont inue the efforts of air pol lut ion
control and remain inside the limits.
Table no. 2.10 Existing Emission details
Source of Air pollution
Type of fuel Quantity of fuel
Height APC equipment
Environmental Impact Assessment Report 2014
53 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
MYS 1736 50TPH
Bagasse 25 T/hr. 45.5 mtr Wet Scrubber
MR 8597 MR 8598 60TPH
Bagasse 60 T/hr 60 mtr. Wet Scrubber
KTK 2272 70TPH
Bagasse + coal
35 T/hr 50 mtr. ESP
KTK 2404 80TPH
Bagasse 40 T/hr 52 mtr. ESP
12 TPH Boiler Biogas &
Furnace oil 800 kg/hr 52 mtr. -
DG sets
1000KVA * 2 nos. HSD 230 Ltr/hr 12 mtr. -
2000KVA HSD 375 Ltr/hr 12 mtr. -
5 KVA * 2 nos. HSD 60 Ltr/hr & 80 Ltr/hr
12 mtr. -
The material of construct ion is RCC and shape is round. Adequate
facil i ty for collect ion of samples in the forms of ladder, platform, and
port-hole etc. is provided.
The industry also proposed the 2 nos.* 35TPH of slop f ired travel grate
incinerat ion boiler with ESP faci l ity.
2. Burning of fuel in standby DG set
Fugitive
# Source Pollutant In-plant
Measures
Control Equipment
1 Standby DG
set
SO2 Feed low
sulphur diesel
-
2 Process HCl Close container Fume hood vents
shal l be provided
with scrubber system
Environmental Impact Assessment Report 2014
54 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
A number of mit igation measures wil l be taken to control fugit ive
emissions, the presence of which wi ll be noticeable by plain vision if
not controlled. The measures are thus taken seriously and
continuously such as:
Ø Rubber wheel carts / trucks to bring in raw materials wil l not be
f i l led high, side’s cladded, slow speed travel, avoiding vibrat ions
en-route.
Ø Engineering the plant layout wil l be in such a way so as to
vi rtual ly el iminate need of using heavy equipment for material
handl ing.
Ø Tree plantation on surrounding available area.
Ø The industry proposes to continue the efforts of air pol lution
control and remain inside the l imits.
2.8.2 WATER and WASTE WATER
There wil l not be any signif icant pol lution during the construct ion &
Operat ion phase as the development wi l l take place in exist ing building
structure. Adequate provisions wil l be made available to col lect the
runoff f rom the site, so that runoff wil l not be allowed to stand or enter
into the roadside or nearby drain.
Raw Water
The water used for the USWL plant wil l be supplied by Irr igat ion
department. The water wil l be treated ful ly to standard character ist ics.
The samples wi l l be tested & conf irmed. The details of required water
are given in table no. 2.7.
Table no. 2.11 Water Consumption (m3/day)
Sr. no. Existing capacity
Proposed capacity
1 Sugar Factory 2592 6600
2 Co-generation 2433 2388
Environmental Impact Assessment Report 2014
55 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3 Domestic 1920 2332
4 Distillery 1155 3000
Total 8100 14310
Disposal
Total ef f luent generated during the operation wil l be about 4960
M3/day from sugar & cogen unit. An eff luent treatment plant has been
provided which is cont inuously in operat ion and the results obtained
wil l be within the permissible l imits as prescribed by KSPCB.
Table no. 2.12 Waste water generation (m3/day)
Sr. no. Existing capacity
Proposed capacity
1 Sugar Factory 1000 2000
2 Co-generation 174 -
3 Domestic 500 500
4 Spent leese 250 960
5 Condensate - 1500
5 Distillery 900 3000
Presently, the sugar and cogenerat ion waste water are disposed
through 1750 m3/day capacity of full f ledge Eff luent treatment plant
and for dist i l lery waste water i.e. 900 m3/day are disposed through
closed biomethanation system (RCC digesters 4 nos.) as a primary
treatment. Bio gas is being used for Hot Air generator or Package
/55TPH Boi lers. After biomethanat ion eff luent fol lowed by Evaporator &
Dryer Plant to generate powder i e Zero Pollut ion.
Environmental Impact Assessment Report 2014
56 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
For proposed expansion, the total quant ity of waste water wi l l be
generat ing from sugar and cogen unit is 4950m3/day and same will be
disposed through combined ETP & send for irr igation. In dist i l lery, out
of 2400 M3/day the 900 M3/day eff luent wil l send for closed
biomethanat ion system (RCC digesters 4 nos.) & one MS digester.
Total 5 No.digesters,as a primary treatment. The generated Bio gas is
being used for Hot Air generator & Package /55 TPH Boilers.
The Eff luent 1500 M3/day, wil l be treated in Evaporat ion &
concentration & the slop wil l be burnt along with bagasse in Cheema
Boilers 2 Nos. Condensate wil l be treated in combined ETP & send for
irr igat ion.
Brief ly:
Ø For exist ing sugar factory & domestic eff luent have been treated
in combined ETP, equalizat ion tank fol lowed by aeration system
where diffused aeration system is provided, followed by pr imary
clarif iers and secondary clarif iers, fol lowed by di lut ion with low
pollutant and cooling tower, over f low & f inal treated eff luent
with less than 100mg/l BOD is being sent for irr igat ion.
Ø For proposed sugar factory & domestic eff luent being treated in
combined ETP, Anaerobic lagoon followed by equalization tank
fol lowed by aerat ion system where diffused aerat ion system is
provided, fol lowed by primary clar if iers and secondary clar if iers,
fol lowed by di lut ion with low pollutant and cooling tower, over
f low & f inal treated eff luent with less than 100mg/l BOD is being
sent for irr igat ion.
Ø For exist ing dist i l lery, the waste water quantity is being sent to
biomethantion unit (bio-digesters) fol lowed by evaporat ion &
drying i .e. Zero pollut ion. Spent less is treated into combined
ETP.
Ø For proposed disti l lery, addit ional evaporation systems followed
by Chima boilers wi l l be instal led to achieve the zero pollut ion.
Environmental Impact Assessment Report 2014
57 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
There wil l be no discharge of ef f luent outside. The detai led note on
ETP along with f low sheet is enclosed as Annexure 17 & 18.
Mitigation measures
As addit ional mit igat ion measures, USWL proposes to take-up
fol lowing measures:
Ø To spread awareness to the workers about the importance of
water quantity measurements and resource conservation.
Ø The treated domest ic waste water wil l be applied judiciously on
land for gardening so that there wil l not be any f looding of
excess water either to migrate to ground water table or get away
as runoff to join surface water drains.
Ø The industrial waste water is subjected to thermal treatment
result ing in hazardous sol id waste being sent to CHWTSDF &
evaporating the moisture.
2.8.3 SOLID WASTE
Minimum amount of sol id waste wil l be generated as there wi l l be
construction work. Following mit igat ion practice is the pol icy for future:
Ø Minimization at all levels need be attempted for discarded
products, empty containers, packing surpluses, incoming raw
material unloading spil lages and fugit ives.
Ø The sol id in process generate only as Ash from cogeneration
plant, ETP sludge and domestic waste.
Ø Other wi l l be empty drums which can be used for ref i l l or may be
disposed to original vendors
The solid waste generation from Sugar and dist i l lery units are
tabulated in table 2.13.
Table 2.13 Solid Waste Generation from Sugar Plant with disposal
Environmental Impact Assessment Report 2014
58 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Source Quantity Treatment & Disposal
CANE CRUSHING SEASON
Mill House Bagasse – 6000
T/day
Use in Boiler of Cogen plant
Process House Press Mud – 800
T/day
Disposed to Dist i l lery units by
product ion of potash powder
fert i l iser.
Boiler House –
Cogen Plant
Ash – 200 T/day The ash being r ich in nutr ient
composit ion, the same will be
disposed as fert i l izer for soi l
condit ioning.
Eff luent
treatment Plant
Sludge – 80-100
T/day
Disposed as Manure.
Evaporator &
Dryer plant
powder
10-12 MT/day Sold to farmers & fert i l izer
companies as a manure
2.8.4 NOISE
Mitigation measures:
During the construction stage, expected noise levels shall be in the
range of 75-80 dB. Al l the construction act ivit ies shal l be carried out
during the dayt ime. To prevent any occupational hazard, ear muff / ear
plug wil l be given to the workers working around or operat ing plant and
machinery emitt ing high noise levels. Use of such plant or machinery
wil l not be al lowed during night hour. Careful planning of machinery
operation and scheduling of operat ions shall be done to minimize such
impact.
Environmental Impact Assessment Report 2014
59 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
No signif icant amount of noise wil l be generated during the operat ion
phase.
2.9 Mitigation Measures (Brief)
Every human act ivity creates some side-effects. This can make
signif icant adverse impact if lef t unattended. It is proposed to reduce
the impact by prevention, abatement and control and mit igation
mechanism. These are described in detai ls later in Chapter Four. Brief
resume can be indicated as fol lows.
Table no. 2.14 Mitigation measures
# Facets of
Environment
Mitigation & Impact Thereafter
1. Air The emissions from Boiler only. DG Set as stand by. Stack
attached to wet scrubber boiler and ESP boiler with 45.5 mtr,
60 mtr and meter & 50 mtr & 52 mtr heights respectively
provided as per the pollution control board guideline. The
CO2 from fermentation will be converted to liquid CO2. The
effluent treatment will be fully aerobic.
2. Fugitive Internal roads paved, leveled, no undulations, no sharp
curves, slow speed. Press-mud, compost yard and compost
not involved. Tree plantation on surrounding available area.
3. Water and
Waste Water
The waste water generated will be treated through methane
bio-digester and evaporators. Spent wash will be converted
to Fuel and moderate will be treated aerobically with disposal
on seed/ demonstration plot or recycled.
4. Solid Waste Collection 100% every day. Segregated and treated/
disposed per SPCB norms.
Environmental Impact Assessment Report 2014
60 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
5. Odour Limited source of odour. Controlled by keeping closed
regime during initial treatment. Use of heat exchanger for
cooling. Small capacity ETP for moderate and sober BOD
effluent will be aerobic and away with a barrier. No cess
pools in disposal area. Bio-digester is fully covered.
6. Noise Smooth roads, sturdy foundation and No Vibrations. Acoustic
enclosures to all DG Set as per manufacturers’ design. Use
as standby only. Trees are planted around. Side cladding.
Large No. of tree barriers. Factory placed away from
boundary.
2.10 CHAPTER CONCLUSION
After introducing the subject of study in Chapter One, in this Chapter
Two addit ional points are covered. Type of the project is underl ined.
The locat ion is described after ment ioning what cr iter ia of select ion
were kept before eyes. The Process is ful ly described and it may be
seen that best environmental opt ion is selected. Al l alternatives having
considered, i t is seen that “No Project” opt ion or abandoning the
project is not proper.
* * * * *
Environmental Impact Assessment Report 2014
61 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER 3
DESCRIPTION OF THE ENVIRONMENT
Environmental Impact Assessment Report 2014
62 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3.1 Introduction:
Information is first assembled for the Region-District and then narrowed down to
10 km radius with the Project as Centre. In both the areas, both the components
of Environment (i.e. Natural and Man-made) are covered. The baseline
environmental quality has been assessed as per the TOR and all the studies
have been conducted from month of September 2013 to November 2013. The
standard methodology is adopted and discussed in this chapter.
Table No.3.1: Summary of Sampling
All the samples were collected by Standard Practices and analyzed as per Indian
Standard Specifications or by APHA (USA).
3.2.1 Materials:
The work involves three activities viz. (1) collection of dry data and statistics by
literature survey, interviewing resource institutes and general public, (2) wet
studies by sampling and laboratory analysis of ambient air, surface water, ground
water, noise, soil, etc. and (3) logically analyzing the findings of dry and wet
studies for interpretation, extrapolation and inference.
No. Media Stations Parameters Frequency
1 Surface Water 2 26 1
2 Ground Water 3 21 1
3 Ambient Air 6 12 Twice a week
4 Ambient Noise 5 2 1
5 Soil Study 4 12 1
Environmental Impact Assessment Report 2014
63 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
A number of officers/offices were contacted in the course of this study. Samples
were collected in the month of September 2013 to November 2013; as follows,
vide Table No.3.1
3.2.2 Approach For a streamline work, a standard six-step model of working is adopted for this
Project study. The six generic steps associated with environment impacts are:
(1) Identification of pollutant emissions and impact concerns related to the
construction and operation of the development project,
(2) Description of the environmental setting in terms of existing environmental
quality, emission inventory, and natural data in the project study area,
(3) Procurement of relevant laws, regulations or criteria related to environmental
quality and/or pollution emission effluent standards,
(4) Conduction of impact prediction activities, including the use of simple dilution
calculations, qualitative predictions based on case study and professional
judgments.
(5) Use of pertinent information from step 3, along with professional judgment
and public input to assess the significance of anticipated beneficial/ detrimental
impacts, and
(6) Identification, development and incorporation of appropriate mitigation
measures for the adverse impacts.
3.3 The Region
The base line data has been collected within the 10 km radius surrounding the
project site of M/s. Ugar Sugar Works Ltd. Ugar Khurd. The Google image of the
study area showing 5 Km & 10 km radius area is given below as Image - 3.1.
Environmental Impact Assessment Report 2014
64 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Belgaum district is a district in the state of Karnataka, India. The city
of Belgaum is the district headquarters in North Karnataka. According to the 2011
Census of India, it has a population of 4,778,439 of which 24.03% live in urban
areas.
Image- 3.1 Google Image showing project site and 10km circle considering
project site at centre
3.3.1 Geographical Location and area The district of Belgaum is located east of the Western Ghats and is situated in
the northwestern part of Karnataka state. It is bordered by the state of Goa on its
southwest and Maharashtra state towards its west and north. The districts of
Bijapur and Bagalkot of Karnataka state lie towards its northeast and east
respectively whereas; the districts of Dharwar and Uttar Kanara lie towards its
Environmental Impact Assessment Report 2014
65 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
south and southwest, respectively (Figure-1). The district lies between 15°00’
and 17°00’ north latitudes and between 74°00 and 75°30’ east longitudes. It
covers an area of 13,444 Sq. Km.
3.3.2 Physical Setting The state is situated in the Deccan Plateau and is bordered by the Arabian Sea
to the west, Goa to the northwest, Maharashtra to the north, Andhra Pradesh to
the east, Tamil Nadu to the east and southeast, and Kerala to the southwest. It is
situated at the angle where the Western Ghats and Eastern Ghats of South India
converge into the Nilgiri Hills. The state has three principal physical zones:
The coastal strip, between the Western Ghats and the Arabian Sea, which is
lowland, with moderate to high rainfall levels. This strip is around 320 km in
length and 48-64 km wide.
The Western Ghats, a mountain range inland from the Arabian Sea, rising to
about 900 m average height, and with moderate to high rainfall levels.
The Deccan Plateau, comprising the main inland region of the state, which is
drier and verging on the semi-arid. The humidity in these plains or maidans never
exceeds 50%.
3.3.3 Water Phase of Environment: 3.3.3.1 Rivers
The entire district falls in the Krishna river basin except small catchments of
Khanapur, Belgaum and Bailhongal taluks that fall in the catchments of Mahadayi
and Kalinadi rivers that flow towards the west. The river Krishna, along with its
tributaries Ghataprabha and Malaprabha are perennial and effluent in nature and
flow in easterly direction. The drainage density varies from 0.80 to 3.4km/sq.km
3.3.3.2 Irrigation in Belgaum District
The district has registered 1,73,684 irrigation pump sets out of which 173,452 are
electrified. Lift irrigation pumps are mostly located in the vicinity of the rivers, thus
providing surface water irrigation. Canals also contribute substantially to
Environmental Impact Assessment Report 2014
66 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
irrigation. Out of the total irrigated area, about 50% is being irrigated by ground
water sources alone. The area irrigated by surface and ground water resources
is 3,72,497 hectares which is about 44% of the net sown area. Irrigation by the
ground water resources alone covers an area of 1,86,126 hectares, which is
about 22% of the ‘Net sown’ area.
3.4 Meteorology
Micro-meteorological data within the study area during the air quality survey period
is an indispensable part of air pollution studies as the micro-meteorological
parameters regulate the transport and diffusion of pollutants released into the
atmosphere. The meteorological data recorded during the monitoring period is
useful for the interpretation of the baseline condition and it can be compared with
the historical data in order to identify changes, which may have taken place in the
area.
3.3.1 Secondary Meteorological Data
The secondary data w.r.t. wind speed, wind direction, Special weather
phenomena, Temperature, Relative humidity and Rainfall collected from
climatological table of IMD, Pune for Miraj (Sangli) station, which is nearby
factory site than the Belgaum station and the same is presented in the below
given tables.
Table: 3.2 Mean Wind Speed
Month Mean Wind Speed
Km/Hour
January 7.4
February 7.7
March 8.9
April 10.6
Environmental Impact Assessment Report 2014
67 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
May 14.2
June 16.3
July 18.0
August 15.4
September 12.2
October 8.4
November 8.5
December 8.4
Annual 11.3
Winds are light to moderate except in the south-west monsoon season when
they are stronger. In the south-west monsoon season, winds are from directions
between south-west and north-west, the westerlies being more frequent. In the
post-monsoon season they are predominantly from the north-east or east.
Easterlies and south-easterlies are common in the cold season. By February
westerlies and north-westerlies appear and these predominate in the summer.
Table: 3.2 Special Weather Phenomena (Miraj Station)
Mean No.
of days
with
Jan. Feb. Mar. Apr. May June July Aug. Sep. Oct. Nov. Dec. Annual
Thunder 0.0 0.0 1.7 4.4 6.1 3.1 0.1 0.9 2.0 4.0 0.9 0.4 23.6
Hail 0.0 0.0 0.1 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2
Dust-
Storm 0.1 0.0 0.1 0.2 0.4 0.2 0.0 0.0 0.0 0.0 0.0 0.0 1.0
Squall 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Fog 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Environmental Impact Assessment Report 2014
68 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Thunderstorms occur in the hot season and in the post- monsoon season. In the
beginning and end of the south-west monsoon season rainfall is often associated
with thunder. The climate of this district is on the whole agreeable and is
characterised by general dryness in the major part of the year. The cold season
is from December to about the middle of February. The hot season which follows,
lasts till the end of May. June to September is the south-west monsoon season
and the two months, October and November, constitute the post-monsoon or
retreating monsoon season.
The only meteorological observatory in the district is at Miraj. The records of this
observatory may be taken as representative of the climatic conditions over the
district in general. The cold weather starts by about the end of November and
lasts till about the middle of February, December being the coldest month. In this
month the mean daily maximum temperature is 29.50C, while the mean daily
minimum is 14.30C. The minimum temperature may sometimes go below 70C.
The period from about the middle of February to the end of May is one of
continuous increase of temperature. In May, the hottest month, the mean daily
maximum temperature is 37.50C and the mean daily minimum 22.70C. The heat
is intense and the maximum temperature may sometimes go up to 42.00C.
Afternoon thundershowers bring welcome relief from the heat on some days.
Table: 3.3 Mean Daily Maximum and Minimum Temperature and Relative
Humidity (Miraj Station)
Month
Mean daily maximum
temperature (0C)
Mean Daily minimum
temperature (0C)
Highest maximum
ever recorded
(0C)
Lowest maximum
ever recorded
(0C)
Relative Humidity
(%)
0830 1730
January 30.5 14.1 33.9 5.0 62 35
February 32.8 15.2 37.2 6.7 56 31
Environmental Impact Assessment Report 2014
69 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
March 36.1 18.5 40.6 11.1 54 27
April 37.9 21.5 42.2 15.0 64 30
May 37.5 22.7 42.2 18.9 73 40
June 31.5 22.3 42.2 19.4 82 66
July 27.9 21.7 35.0 17.2 86 79
August 28.2 21.2 34.4 17.8 87 76
September 29.2 20.2 35.6 15.6 86 68
October 31.0 20.1 36.1 12.2 74 51
November 30.1 17.3 34.4 8.3 65 45
December 29.5 14.3 34.4 7.2 61 37
Annual 31.9 19.1 -- -- 62 35
The highest maximum temperature recorded at Miraj was 42.20C and the lowest
minimum temperature recorded at this station was 5.00C. In the south-west
monsoon months the air is highly humid. In the post-monsoon, summer and cold
seasons the air is dry particularly in the afternoons. Skies are generally clear or
lightly clouded during the months November to March. Cloudiness begins to
increase progressively from April and afternoons are more clouded than the
mornings. During the monsoon months the skies are heavily clouded to overcast.
Records of rainfall in the district are available for nine stations for periods ranging
from 15 to 83 years. The average annual rainfall in the district is 692.4 mm
(27.26"). The rainfall in the western portion of the district, near the Western Ghats
is considerably higher than in the rest of the district. The rainfall generally
decreases from the Western Ghats towards the eastern portions of the district;
Madhavpur (Vadgaon) near the western border of the district getting 1,225.8 mm
(48.26") and Jath in the eastern part getting only 528.2 mm (20.80"). Some
rainfall in the form of thunder-showers occurs in May but the main rainy season is
from June to September. The rainfall in the south-west monsoon months is about
68% of the annual total. July is the month with the heaviest rainfall.
Environmental Impact Assessment Report 2014
70 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
About 19% of the annual rainfall is received in the post-monsoon season. The
rainfall at individual stations shows considerable variations from year to year. It
will be seen from table 3.4 that at some stations the rainfall has been as much as
double the normal in some years while in some other years rainfall has been
about half the normal. In the fifty year period 1901—1950 the annual rainfall in
the district was the highest in 1932 when it amounted to 140% of the normal.
Both 1918 and 1923 were years with the lowest rainfall which was only 57% of
the normal. In the same fifty year period, the annual rainfall was less than 80% of
the normal in 14 years. There were three occasions when consecutive two years
had rainfall less than 8/% of the normal. Consecutive four years of such low
rainfall occurred during the period 1923—1926. It will be seen from table 3.4 that
in 33 years out of fifty the rainfall in the district was between 500 and 800 mm
(19.69" and 31.50").
3.3.2 Primary Meteorological Data
Site-specific primary meteorological data was collected in the project site for the
month of September 2013 to November 2013. Meteorological station was installed
at Sugar Factory site 10 meters from the ground level to monitor parameters of
wind speed, wind direction, temperature, relative humidity and rainfall. The data
is recorded as the maximum, minimum, instantaneous value. Monitoring was
done as per IS: 8829: Micro-meteorological Techniques in Air Pollution.
The details of parameters monitored, equipment used and the frequency of
monitoring are given in Table.
Table 3.5 Meteorological Parameters monitored at Site
SR.
NO.
PARAMETERS INSTRUMENTS FREQUENCY
1. Wind Speed Counter Cup
Anemometer
Hourly/Continuous
2. Wind Direction Wind Vane Hourly/Continuous
Environmental Impact Assessment Report 2014
71 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3. Temperature Thermo-sensor Hourly/Continuous
4. Relative
Humidity
Thermo-hygro sensor Hourly/Continuous
5. Rainfall Rain gauge (automatic) Hourly/ Continuous
Temperature
It was observed that the temperature ranged from 16.2 °C to 36.8 °C. The
maximum temperature of 36.8 °C recorded in the month of November and
minimum temperature of 16.2 °C was observed to be in the month of November.
The monthly variations in the temperature are presented in Table 3.1.
Relative Humidity
During the monitoring period of three months, the relative humidity ranges from 35
% to 98 %. The maximum humidity (98%) was recorded in the month of October
whereas minimum humidity i.e. 35 % was observed in the month of October. The
monthly variations in the relative humidity are given in Table 3.1.
Table 3.6: Meteorological Data monitored at the Project Site
Month
Temperature (OC) Relative Humidity (%)
Max Min Avg. Max Min Avg.
September 34.00 19.60 26.8 97 41 69
October 32.2 18.6 25.4 98 35 66.5
November 36.8 16.2 26.5 87 43 65
Wind Speed and Direction
Winds are light to moderate throughout the study period. The month-wise and
season-wise pattern is discussed below. The monthly and seasonal wind roses are
presented in Figure 3.2 to 3.5.
Figure 3.1 : Windrose for the Month of September 2013
Environmental Impact Assessment Report 2014
72 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Figure 3.2 : Windrose for the Month of October 2013
Environmental Impact Assessment Report 2014
73 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Figure 3.3 : Windrose for the Month of November 2013
Figure 3.4: Windrose for the study Period September - November 2013
Environmental Impact Assessment Report 2014
74 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Wind pattern during September 13
A review of the wind pattern shows that predominant winds are mostly from west
and followed by North West as shown in Figure 3.1. Wind speed observed during
the whole month of September was 1.21m/s whereas calm winds are found to be
19.61%
Wind pattern during October 13
Wind pattern for the month of October shows that predominant winds are from
North and North East direction (Figure 3.2). Wind speed and calm winds observed
to be 1.26m/s and 15.65% respectively.
Wind pattern during November 13
Wind pattern for the month of November, shows that the predominant winds are
mostly from East North East direction (Figure 3.3). Wind speed and calm winds
observed to be 1.11m/s and 16.04% respectively.
Wind pattern during the Study Period (September to November 13)
Predominant wind found to be from the direction of ENE as shown in Figure 3.4.
Wind speed observed to be 1.19 m/s where as calm condition are found to be
17.08 %
3.5 AIR ENVIRONMENT
The baseline studies for air environment cover reconnaissance, identification of
specific air pollutants expected to have significant impacts and assessment of
their prevalent levels in atmosphere at representative locations (within the site
and the buffer zone).
3.5.1 Ambient Air Quality
The ambient air quality status with respect to the specific (identified) pollutants
across the study zone of 5 km radial distance from the project site during study
Environmental Impact Assessment Report 2014
75 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
period will form the base line information over which the predicted impacts due to
the proposed project can be superimposed to find out the net (final) impacts
(post-project scenario) on air environment. If the final impacts due to the project
activities are known at the planning stage of the project, a viable Environmental
Management Plan (EMP) can be prepared based on impact assessment for the
air environment. The ambient air quality monitoring was carried out in
accordance with guidelines and National Ambient Air Quality Standards
(NAAQS) of MoEF & CPCB.
3.5.2 Procedure for Sampling and Analysis
Sampling location is shown in Map below and the monitoring data from 8 stations
at various directions is presented in table 3.7. Reconnaissance survey was
undertaken to establish the baseline status of air environment in the study region.
Keeping in view the nature and size of the proposed site and various guidelines
available, an area of 10 km radius from the proposed site, was covered for the
purpose of Environmental Impact Assessment. During study period, the study
region has predominating wind direction from ENE to WSW.
To establish the existing baseline air quality status of the air basin, around the
IFL plant, Seven ambient Air Quality Monitoring (AAQM) stations were selected
in different directions of project site as per guidelines of network siting criteria.
The identified locations of AAQM are shown in Figure 3.5.
Based on the nature of industries existing and various other activities within the
study area, the conventional air pollutants such as Suspended Particulate Matter
(SPM), Respirable Particulate Matter (RPM) and gaseous pollutants such as
Sulphur dioxide (SO2), and Oxides of nitrogen (NOx), were identified as
significant pollutants for ambient air quality monitoring.
Environmental Impact Assessment Report 2014
76 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Air quality was monitored with eight samplers, for 24 hours, twice a week, for a
total of 13 weeks as per the guidelines specified by the MoEF. The volumetric
flow rate of each sampler was maintained at 1.1-1.2 L/min. Air samples are
analyzed by using standard procedures prescribed by Central Pollution Control
Board (CPCB), Indian Standards: IS 5182. Details of techniques used for
analysis of air samples are given in
Table 3.6: Techniques Used for Analysis of Air Quality
Sr.
No. Parameter
Code of
Practice Sampler
Equipment/
Instruments for
Analysis
Methodology
Adopted
1
Suspended
Particulate
Matter (SPM)
IS: 5182
(Part IV) HVS
Balance, Oven
and Desiccators
Gravimetric
Method
2
Respirable
Particulate
Matter (RPM)
IS: 5182
(Part IV)
Respirable
Dust Sampler
with Cyclone
Separator
Balance Gravimetric
Method
3 SO2 IS: 5182
(Part V) HVS Colorimeter Colorimetric
4 NOx IS: 5182
(Part V) HVS Colorimeter Colorimeter
5
Carbon
Monoxide
(CO)
IS: 5182
(Part X)
Bladder and
Aspirator
Gas
Chromatograph
with Methaniser
Flame
Ionization
Detector
Figure 3.5 Air monitoring site map of 10 km radius area around Project Site
Environmental Impact Assessment Report 2014
77 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Table- 3.7 Ambient Air Quality Monitoring Locations
Sr.
No.
Code No.
Station Name Direction w.r.t. site
Distance w.r.t. site
km Description
1. AAQ1 Project Site -- -- Industrial
2. AAQ2 Ugar Khurd East 1.4 Residential / Rural area
3. AAQ3 Ugar Budruk West 2.0 Residential / Rural area
4. AAQ4 Ugar Khurd (Kudachi)
South East 3.8 Residential / Rural area
5. AAQ5 Ugar Khurd North East 3.2 Residential / Rural area
6. AAQ6 Kusnal South West 4.1 Residential / Rural area
The ambient air quality monitoring has been done twice in week for every location.
The baseline data of air environment is generated for the following parameters:
Environmental Impact Assessment Report 2014
78 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
· Total Suspended Particulate Matter (TSPM);
· PM10 : Respirable Particulate Matter (RPM);
· Sulphur dioxide (SO2); and
· Oxides of Nitrogen (NOx)
· Carbon monoxide (CO);
· Lead (pb); and
· Hydrocarbons (HC)
3.4.2 Sampling Duration
Ø Twenty-four hourly samples, twice a week at all air-monitoring stations.
3.4.3 Instruments Used
Respirable Dust Samplers (APM-451) of “Envirotech” make are used for
sampling SPM, PM10 and gaseous pollutants like SO2, NOx. The gases are
collected in a sampling tray attached to the Respirable Dust Sampler.
3.4.4 Methodology for Analysis
The air samples are analyzed as per IS: 5182 "Method for Measurement of Air
Pollution".
· SPM/ PM10: Gravimetric Method (IS: 5182, Part IV)
· SO2: Modified West and Gaeke Method (IS: 5182, Part II)
· NOx: Jacobs and Hochheiser Method (IS: 5182, Part VI)
· CO: NDIR spectroscopy method
· pb: Atomic Absorption Spectroscopy (AAS) method
3.4.5 Presentation of Results The ambient Air quality monitoring data analysed and tabulated in the Table -
3.3.3 which is compared with National Ambient Air Quality Standards as tabulated
in Table - 3.3.2.
Table- 3.8 Ambient Air Quality Monitoring Results Village
(Location) Parameters
SO2
(mg/m3) NOx
(mg/m3) SPM
(mg/m3) PM10
(mg/m3) CO
(ppm)
Environmental Impact Assessment Report 2014
79 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
AAQ1 Minimum 4.0 9.1 126.4 29.6 0.40
Maximum 9.0 16.6 184.2 54.6 1.20
Average 6.6 11.5 153.7 43.5 0.80
Std. Deviation
1.24 2.12 15.10 7.30 0.20
98th percentile
8.96 16.18 181.4 54.4 1.20
AAQ2 Minimum 4.0 8.1 106.1 28.1 0.51
Maximum 7.2 12.9 170.1 57.1 1.26
Average 4.9 9.8 141.4 42.0 0.80
Std. Deviation
0.81 1.09 17.1 7.4 0.20
98th percentile
7.1 12.5 166.2 56.4 1.16
AAQ3 Minimum 4.0 9.0 121.3 36.4 0.52
Maximum 7.1 12.9 185.3 65.4 1.11
Average 5.1 10.1 157.4 50.5 0.73
Std. Deviation
0.8 1.1 17.05 7.51 0.17
98th percentile
6.9 12.5 181.4 64.7 1.06
AAQ4 Minimum 6.7 13.6 106.8 34.4 0.87
Maximum 13.0 21.7 163.6 72.3 1.93
Average 9.5 17.8 145.4 48.8 1.22
Std. Deviation
1.5 2.2 15.9 8.4 0.33
Environmental Impact Assessment Report 2014
80 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
98th percentile
8.8 17.7 163.4 66.9 0.92
AAQ5 Minimum 4.0 9.0 140.9 45.1 0.47
Maximum 7.2 14.6 168.8 55.2 1.20
Average 5.3 10.3 151.0 50.5 0.77
Std. Deviation
1.0 1.5 6.0 2.5 0.21
98th percentile
7.1 14.1 164.7 55.1 1.15
AAQ6 Minimum 4.0 9.0 107.9 29.6 0.52
Maximum 8.4 16.2 164.7 61.2 1.11
Average 5.6 11.6 146.5 45.4 0.73
Std. Deviation
1.1 1.9 15.9 9.2 0.17
98th percentile
7.9 15.6 164.5 60.6 1.06
Ambient air quality analysis results for the six monitoring locations which were
selected to represent baseline conditions of the region are given below.
AAQ1
The location comes under Industrial zone. The concentration of SPM ranged
from 126.4-184.2 µg/m3 while that of PM10 was in the range of 29.6-54.6 µg/m3,
SO2 and NOx were in the range of 4-9 µg/m3 and 9.1-16.6 µg/m3 respectively.
The CO values were observed in the range of 0.40-1.20 ppm.
AAQ2
The location comes under Non-Industrial zone. The concentrations of SPM and
PM10 at this location were in the range of 106.1-170.1 µg/m3 and 28.1-57.1
µg/m3 respectively. While the values of SO2 and NOX were observed in the range
Environmental Impact Assessment Report 2014
81 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
of 4-7.2 µg/m3 and 8.1-12.9 µg/m3 respectively. The CO values were observed in
the range of 0.51-1.26 ppm.
AAQ3
The location comes in the residential /semi urban zone. Here the SPM and PM10
concentrations were in the range of 121.3-185.3 µg/m3 and 36.4-65.4 µg/m3
respectively. The concentrations of SO2 and NOX were observed in the range of
4-7.1 µg/m3 and 9-12.9µg/m3 respectively. The CO values were observed in the
range of 0.52-1.11 ppm.
AAQ4
This location comes within the residential zone. The concentrations of SPM and
PM10 at this location were in the range of 106.8-163.6 µg/m3 and 34.4-72.3
µg/m3 respectively. While the values of SO2 and NOX were observed in the range
of 6.7-13 µg/m3 and 13.6-21.7 µg/m3 respectively. The CO values were observed
in the range of 0.87-1.93 ppm.
AAQ5
The location comes under Non-Industrial Zone. The concentration of SPM
ranged from 140.9-168.8 µg/m3 while that of PM10 was in the range of 45.1-55.2
µg/m3. SO2 and NOx concentrations were in the range of 4-7.2 µg/m3 and 9-14.6
µg/m3 respectively. The CO values were observed in the range of 0.47-1.20 ppm.
AAQ6
The location comes under Non-Industrial Zone. The concentration of SPM
ranged from 107.9-164.7 µg/m3 while that of PM10 was in the range of 29.6-61.2
µg/m3. SO2 and NOx concentrations were in the range of 4-8.4 µg/m3 and 9-16.2
µg/m3 respectively. The CO values were observed in the range of 0.52-1.11 ppm.
The summary of the monitoring results including minimum, maximum and
average levels along with the 98th percentile values are presented in Table 3.8.
The results obtained were compared for 24 hrs average standards for residential
areas prescribed by the National Ambient Air Quality Standards (NAAQS). The
National Ambient Air Quality Standards are presented in Table 3.9.
Environmental Impact Assessment Report 2014
82 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Table 3.9: National Ambient Air Quality Standards (NAAQS)
Sr.
No
.
Pollutant Time Weighted
Average
Concentration in Ambient Air
(µg/m3 except indicated)
Industri
al Area
Residential,
Rural and
Other Areas
Sensitive
Area
1 Sulphur
Dioxide (SO2)
Annual Average
* 80 60 15
24 Hours** 120 80 30
2 Oxides of
Nitrogen (NOx)
Annual Average
* 80 60 15
24 Hours** 120 80 30
3
Suspended
Particular
Matter (SPM)
Annual Average
* 360 140 70
24 Hours** 500 200 100
4
Respirable
Particular
Matter (RPM)
Annual Average
* 120 60 50
24 Hours** 150 100 75
5 Carbon
Monoxide (CO)
8 Hourly
Average*
5.0
mg/m3 2.0 mg/m3 1.0 mg/m3
1 Hour
Average**
10.0
mg/m3 4.0 mg/m3 2.0 mg/m3
* Annual arithmetic mean of minimum 104 measurements in a year
taken twice a week 24 hourly at uniform interval
** 24 hourly/8 hourly values should be met 98% of the time in a year.
However, 2% of the time it may exceed but not on two consecutive
days
On the above observations of the results and their compliance to the 24 hourly
averages of NAAQ standards are well within the limits.
3.6 NOISE ENVIRONMENT
Environmental Impact Assessment Report 2014
83 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Noise is defined as unwanted sound, interferes with speech, communication,
sleep, causes annoyance and results in deterioration of the quality of human
environment. Perception of noise varies with a number of factors including
natural sensitivity and hearing ability, past experience, cultural factors and the
time of day at which the sound is experienced. Continuous sound is perceived
quite differently from intermittent sound at the same level. High or continuous
noise levels may cause permanent loss of hearing ranging from reduced
perception at certain frequencies to total deafness. Even at comparatively lower
levels, noise may have psychological effects including disturbance of sleep,
annoyance and irritation.
Monitoring of noise levels in the proposed site during summer season was
carried out to assess the present baseline levels. Impact of noise generated due
to propose Foundry activity was studied and also to know the impact of vehicular
traffic on human settlements. Studies pertaining to noise environment were
conducted in the following order:
Ø Reconnaissance survey
Ø Measurement of equivalent noise levels
Ø Impact of noise exposure on the communities
Noise Levels
The noise levels measured at the existing plant facility, proposed plant site and
villages located within 10 Km. radius are in Table 3.18
Table 3.9 Noise Monitoring Locations
Sr.
No.
Code No.
Station Name Direction w.r.t. site
Distance w.r.t. site
km Description
1. N1 Project Site -- -- Industrial
2. N2 Ugar Khurd East 1.4 Residential / Rural area
3. N3 Ugar Budruk West 2.0 Residential / Rural area
4. N4 Ugar Khurd South East 3.8 Residential / Rural area
Environmental Impact Assessment Report 2014
84 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
(Kudachi)
5. N5 Ugar Khurd North East 3.2 Residential / Rural area
Fig 3.6: Noise monitoring site map of 10 km radius area around Project Site
Table 3.10 Noise Monitoring Scenario
Name of
Station
Noise Levels (dBA) Ambient Noise Standard (dBA)
Day Night Day Night Category
of area
Project Site 60.8 55.3 75 70 Industrial
Ugar Khurd 45.6 41.7 55 45 Residential
Ugar Budruk 48.4 42.2 55 45 Residential
Ugar Khurd (Kudachi)
50.3 43.9 55 45 Residential
Ugar Khurd 52.5 40.5 55 45 Residential
Environmental Impact Assessment Report 2014
85 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
From the monitoring survey of noise levels it was observed that the day time
noise levels were observed in the range of 45.6-60.8 dB (A). The night time noise
levels observed at the 5 locations were found to be in the range of 41.7 – 55.3 dB
(A). Noise Levels are found to be within the day and night time standards
prescribed for residential, commercial, industrial zone.
3.7 WATER ENVIRONMENT
Water environment consists of water resources such as river, ponds, streams,
etc. The water quality forms the essential component of EIA that helps to identify
and evaluate critical impacts / issues with a view to suggest appropriate
mitigation measures for implementation. Water quality of ground water has been
studied in order to assess various uses of water such as during construction, in
process, drinking, horticulture, etc. with respect to the proposed project.
Approach Reconnaissance Survey for ground and surface water bodies in the study region
shows that both ground and surface water are important sources of drinking
water found in the study region.
3.7.1 Surface Water Environment
The district falls in the Krishna river basin except small catchments of Khanapur,
Belgaum and Bailhongal taluks that fall in the catchments of Mahadayi and
Kalinadi rivers that flow towards the west. The river Krishna, along with its
tributaries Ghataprabha and Malaprabha are perennial and flow in easterly
direction.
Sampling and Analysis
Water samples were collected in the month of September 2013 to November
2013 from bore/open wells located within 10 Km. radius from the proposed site.
The water samples collected were analyzed for pH, COD, BOD, Suspended
Solids, Oil and Grease, Chlorides, Sulphates and Total Hardness. The results
are presented in Table 3.12. Methodologies adopted for analyzing the samples
Environmental Impact Assessment Report 2014
86 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
for the parameters mentioned above were according to the APHA prescribed
methods. 3.11 Surface water Sampling Locations:
Sr.
No. Sampling Location Name
Direction from
project site
Distance from
project site
SW1 Krisna river at Kudachi SE 1 Km
SW2 Krisna river at Kudachi SE 1 Km
Fig. 3.8: Surface water sampling site map
Surface Water Quality Scenario
Surface water samples analyzed during the study period indicate that the water is
free from the industrial pollution. Water from these wells is used for drinking,
gardening, industrial and agricultural purposes. Concentrations of suspended
solids and dissolved solids were low. BOD, COD levels which indicate organic
pollution are also low. All the other parameters are within the prescribed limits.
Table: 3.12 Surface Water Analysis results
Environmental Impact Assessment Report 2014
87 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Sr. No
Parameter Unit Limits as
per IS:2296-C
SW1 SW2
1 pH - - 7.7 8.0
2 Electrical Conductivity mmhos/cm NS 317.6 969.2
3 Chlorides (Cl-) Mg/l 600 68.3 101.9
4 Total Hardness mg/l NS 99.2 139.2
5 Total Alkalinity mg/l NS 117.4 412.2
6 Total Dissolved Solids mg/l 1500 250.3 630.6
7 Sulphate (SO4-) mg/l 400 45.5 93.7
8 Iron (Fe+) mg/l 50 0.1 0.2
9 Fluoride (F-) mg/l 1.5 0.7 0.7
10 Calcium (Ca+) mg/l NS 31.9 43.7
11 Magnesium (Mg+) mg/l NS 10.5 11.6
12 Nitrates (NO3-) mg/l 50 7.0 5.6
13 Total suspended solids
mg/l NS 76.4 83.7
14 B O D mg/l 3 1.1 1.3
15 Dissolved Oxygen mg/l 4 (min) 4.9 4.4
16 Copper (Cu) mg/l 1.5 BDL BDL
17 Manganese (Mn) mg/l NS BDL BDL
18 Mercury (Hg) mg/l NS BDL BDL
19 Selenium (Se) mg/l 0.05 BDL BDL
20 Cyanide (CN) mg/l NS BDL BDL
21 Chromium (Cr+6) mg/l NS BDL BDL
Environmental Impact Assessment Report 2014
88 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
22 Lead (Pb) mg/l NS BDL BDL
23 Zinc (Zn) mg/l NS BDL BDL
24 Aluminum (Al) mg/l NS BDL BDL
25 Cadmium (Cd) mg/l NS BDL BDL
26 Arsenic (As) mg/l 0.2 BDL BDL
For the monitoring of surface water quality, three surface water samples have
been analyzed once during the study period. The results of analysis are given in
Table - 3.12. Which are compared with the standards for Class-C water of IS:
2296 (Water quality fit for drinking after conventional treatment).
A perusal of the table reveals that the results of all parameters are well within the
specified limits. The pH values are in the range of 7.7 to 8.0 throughout the study
period, which shows that the surface water of the study area is slightly alkaline in
nature, which may be due to carbonates and bicarbonates. The concentration of
the total dissolved solids and total alkalinity are in the range of 250 to 630 mg/lt
and 117 to 412 mg/lt. The DO values at all locations are found to be appreciable
which indicates self-purification capacity of the surface water body. The heavy
metal concentrations at all the three locations during the study period were found
below detectable limits.
3.7.2 Ground Water Quality
Ground water is the accumulation of water below the surface of earth, caused by
the portion of rainfall that percolates through the soil pores and rock crevices,
flown by natural gravity till it reaches an impervious stratum. The study area
receives limited rains, but has considerable groundwater presence. The quality of
groundwater is examined by drawing samples from open dug wells as well as
from deep wells from the study area. Analysis was done by Standard methods.
Environmental Impact Assessment Report 2014
89 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
The results are summarized below in tabular form, and compared with limits of
IS:10500
3.13 Ground water sampling Locations
Sr.
No.
Sampling Location
Name
Direction from
Project site
Distance from project
site
1 Ugar khurd (GW1) NE 3.5Km
2 Ugar budruk (GW2) W 3.5 Km
3 Kudachi (GW3) SE 3.5 Km
Fig 3.9 Groundwater sampling site map
Ground Water Quality Scenario:
Ground water samples analyzed during the study period indicate that the water is
free from the industrial pollution. Water from these wells is used for drinking,
gardening, industrial and agricultural purposes. All the other parameters are
within the prescribed limits. The results of the analysis of ground water are
tabulated in Table 3.14
Environmental Impact Assessment Report 2014
90 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Table 3.14: Ground Water analysis results
Sr. No.
Parameter Unit
Limits as per IS:10500
(Desirable/ permissible)
Ground Water
GW1 GW2 GW3
1 pH 6.5 –8.5 6.5 6.9 6.4
2 Conductivity mmhos/c
m NS 108.5 112.8 284
3 Chlorides (Cl-) ppm 250/ 1000 92.8 137.6 19.6
4 Total Hardness ppm 300/ 600 236.8 310.4 64.6
5 Alkalinity as CaCO3 ppm 200/600 448.0 284.8 69.6
6 Total Dissolved Solids ppm 500/ 2000 704.0 736.0 211
7 Sulphate (SO4-) ppm 250/ 400 176.0 116.0 64.2
8 Iron (as Fe) ppm 0.3/1.0 0.1 0.1 0.1
9 Fluoride (F-) ppm 1.0/ 1.5 1.5 1.3 0.4
10 Calcium (Ca+) ppm 75/ 200 67.2 89.6 23.34
11 Magnesium (Mg+) ppm NS 16.8 20.8 8.96
12 Nitrates (NO3-) ppm 45/100 2.9 3.0 4.8
13 Copper (Cu) ppm 0.05/1.5 BDL BDL BDL
14 Manganese (Mn) ppm NS BDL BDL BDL
15 Mercury (Hg) ppm 0.001/NR BDL BDL BDL
16 Selenium (Se) ppm 0.01/NR BDL BDL BDL
17 Cyanide (CN) ppm 0.05/NR BDL BDL BDL
18 Chromium (Cr+6) ppm 0.05/NR BDL BDL BDL
19 Lead (Pb) ppm 0.05/NR BDL BDL BDL
Environmental Impact Assessment Report 2014
91 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
20 Zinc (Zn) ppm 5.0/15.0 BDL BDL BDL
21 Cadmium (Cd) ppm 0.01/NR BDL BDL BDL
22 Arsenic (As) ppm 0.05/NR BDL BDL BDL
23 Total Coliform, Nos./100
ml Absent 8 5 6
24 Faecal Coliforms. Nos/100m
l Absent 0 0 0
The ground water analysis results are compared with the drinking water quality
standards of IS: 10500-1991. The observed values of ground water analysis
during the study period are given in Table - 3.13. The pH value ranges within 6.4
to 6.9 which are found to be slightly towards the lower limit.
The electrical conductivity ranges 284 to 1314 mmhos/cm at all sampling
locations during the study period. Total dissolved solids (TDS) ranges between
211 to 872 ppm. The fluoride concentrations are between 0.4 to 1.5 ppm. These
values are due to the existing geological structure of the area and cannot be
attributed to industrial causes.
The total hardness during study period observed in the ranges 64.4 to 345.6
ppm. It was observed that the total hardness is found to be within the desirable
limits. The concentrations of heavy metals are below detectable limits throughout
the study period.
3.8 Flora and Fauna Objectives of study Flora and Fauna around the 10 km area was recorded. The study was undertaken with a view to understand the status of ecosystem along the following line
Environmental Impact Assessment Report 2014
92 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø To assess nature and distribution of the vegetation in the area Ø Preparation of checklist of flora and fauna. Ø Generation of primary data to understand baseline status of floral and faunal
elements, sensitive habitats and rare species Methods adopted for the study To achieve the objectives, general ecological survey covering an area around the proposed project site was carried out in the month of November. Ø General field visit on site and closed vicinity area Ø Reconnaissance Survey Ø Information from local peoples and forest department
Observations and Results
Flora: The floral study was conducted in the study area during the month of
September 2013 to November 2013. The floral diversity in the area is described
in Table. During this survey total 36 plant species comprising of 15 Tree species,
5 climber species, 3 shrub species and 13 herb species were recorded. These
plants are the common habitant in the project area.
Table3.15: List of flora available in study area
Sr.
No
Name of
Species
Vernacular
name Family
Phenology
Habitat
Distribution
1. Mangifera
indica Amba Anacardiaceae
January -
May
Evergreen
and semi-
evergreen
forests and
also widely
cultivated
Indo-Malesia
2. Terminalia
arjuna Arjun Combrataceae
November
- June
Dry
Deciduous
forests
India and Sri
Lanka
3. Bridelia
retusa Asana Euphorbiaceae
August –
December
Semi-
evergreen Indo-Malaya
Environmental Impact Assessment Report 2014
93 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
and
deciduous
forests,
also in the
plains
4. Morinda
tinctoria Ashi Rubiaceae
March -
June
Moist and
dry
deciduous
forests,
also in the
plains
Indo-Malesia
5. Thespesia
populnea Bhendi Malvaceae
March -
June
Grown as
fence-
posts and
avenue
tree, also
in
mangrove
forests
Pantropical
6. Ziziphus
mauritiana Bor Rhamnaceae
February –
April
Dry
deciduous
forests,
also
planted in
the plains
Paleotropics
7. Tamarindus
indica Chinch Fabaceae
February –
April Cultivated
Native of
Tropical
Africa;
introduced
and widely
grown in
India and
other parts
Environmental Impact Assessment Report 2014
94 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
of tropics
8. Terminalia
catapa
Deshi
badam Combrataceae
March –
January
Grown as
ornamental
tree
Malaysia to
North
Australia
and
Polynesia,
commonly
planted in
the tropics
9. Grewia
tiliaefolia Dhaman Tiliaceae
February -
June
Moist
deciduous
forests
Tropical
Africa, India
to Indo-
China
10. Acacia
auriculiformis Kadambo Fabaceae
Throughout
the year
Grown as
avenue
tree, also
raised in
plantations
Native of
Tropical
Australia
11. Azadiracta
indica Kadulimb Meliaceae
February –
September
Dry
deciduous
forests,
also widely
planted
Indo-Malesia
12. Cocus
nucifera Naral Arecaceae
Throughout
the year Cultivated
Cultivated
throughout
the tropics
13. Ficus
religiosa Pimpal Moraceae
November
- February
Widely
planted in
tem
ple
premises
East
Himalayas;
planted and
naturalised
in India and
neighbouring
14. Samanea Rat-shirish Fabaceae March – Grown as Native of
Environmental Impact Assessment Report 2014
95 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
saman May avenue
tree
Central and
South
America;
widely
planted in
the tropics
as avenue
tree
15. Tectona
grandis Sag Verbanaceae
May –
January
Moist
deciduous
forests,
also raised
in
plantations
South and
South East
Asia
CLIMBERS
Sr.
No.
Name of
Species
Vernacular
Name Family
Phenology
Habitat
Distribution
1. Mikania
micrantha
Bittervine Asteraceae
February –
April
Forest
plantations
and also in
the plains
in moist
localities
Pan-tropical
2. Ipomia
muricata Bhovari convolvulaceae October
Cultivated
as
vegetable
Native of
tropical
Africa and
Asia
3. Momordica
dioica Kantoli Cucurbitaceae
July -
December
Deciduous
and semi-
evergreen
forests,
also in the
Indo-
Malesia and
China
Environmental Impact Assessment Report 2014
96 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
plains
4. Mucana
prurita Khaj-kuili Fabaceae
October –
February
In
secondary
forests at
low
altitudes,
also in the
plains
India,
Myanmar
and Sri
Lanka
5. Vigna
radiata
Jungle
moong Fabaceae
August -
December
Mostly
under
cultivation,
also
naturalised
in the
plains
Paleotropics
SHRUBS
Sr.
No.
Name of
Species
Vernacular
Name Family
Phenology
Habitat
Distribution
1. Lantana
camera Lantana Verbenaceae April - June
Introduced
as
ornamental
plant; now
naturalised
as weed
Native of
Tropical
America,
widely
naturalised
in the tropics
and
subtropics
2. Calotropis
gigantea Rui Aslepiadaceae
Throughtout
the year Wastelands Tropical Asia
3. Hibiscus
subdariffa ambadi Malvaceae
December -
February
Cultivated
as
vegetable,
Native of
Tropical
Africa;
Environmental Impact Assessment Report 2014
97 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
but now
naturalised
widely
cultivated in
all tropics
regions
HERBS
Sr
No
Name of
Species
Vernacular
Name Family
Phenolo
gy
Habitat
Distributio
n
1. Achyranthe
s aspera Aghada
Amaranthace
ae
October -
March
Dry
deciduous
forests
and forest
plantations
, also in
the plains
Pantropical
2. Solanum
surattense Bhuiringani Solanaceae
August -
Novembe
r
Degraded
forest
areas,
also along
roadsides
and
wasteland
s
India,
Himalaya,
South East
Asia,
Malesia,
Australia,
Polynesia
3. Physalis
minima
Choti
phulwa Solanaceae
July –
Decembe
r
Degraded
forests
and waste
places
Tropical
Asia, Africa
and
Australia
4 Ephorbia
hirta Dudhi
Euphorbiacea
e
Througho
ut the
year
Degraded
forest
areas and
forest
plantations
Native of
Tropical
America;
now
Pantropical
Environmental Impact Assessment Report 2014
98 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
, also in
the plains
5. Alternanthra
sessilis Kacheri
Amaranthace
ae
Througho
ut the
year
Along
sides of
water
courses
and
marshy
areas
Pantropical
6. Triumfetta
rhomloidea Jhinjhira Tiliaceae
August -
January
Degraded
deciduous
forests,
also in the
plains
Pantropical
7. Aeschyomm
ene indica Bhatsola Fabaceae
August -
Decembe
r
Moist
deciduous
forests
and
waterlogg
ed areas
in the
plains
Pantropics,
probably
native in
South East
United
States
8. Tridax
procumbens kambarmodi Asteraceae
Througho
ut the
year
Deciduous
forests,
also waste
lands in
the plains
Native of
Tropical
America;
now
widespread
throughout
tropics and
subtropics
9. Aerva
lanata
Kapurmadh
uri
Amaranthace
ae
Sepetmb
er – April
Deciduous
forests
and waste
Widespread
in the
tropics and
Environmental Impact Assessment Report 2014
99 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
lands in
the plains
subtropics
10
Commelina
benghalensi
s
kena Commelinace
ae
July -
Novembe
r
Wasteland
s, also in
deciduous
forests
Africa,
India,
China,
Japan and
Malesia
11 Celosia
argentea kurdu
Amaranthace
ae
Novembe
r -
Decembe
r
Weed in
cultivated
areas and
wasteland
s
Cosmopolit
an
12 Mimosa
pudica Lajalu Fabaceae
July -
January
Weed in
the plains
Native of
South
America;
now
Pantropical
13 Urena
lobata vanbhendi Malvaceae
August -
Decembe
r
Degraded
forests,
also in the
plains
Pantropical
Conclusion: - There is no flora species existing at site which are in the red list
species category.
Fauna: The faunal study was conducted in the study area during the month of
September 2013 to October 2013 The faunal diversity in the area is described in
Table. Inquiry was made with the villagers in the concerned cluster regarding
availability of wildlife fauna in the study area. The faunal diversity is very meager,
only common species of mammals, birds and reptiles are available in the study
area. No any wildlife Sanctuary or National Park is present in this study area.
Table 3.16: List of fauna available in study area
Environmental Impact Assessment Report 2014
100 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
1. Mammals:
Common Name Scientific Name Habitat IUCN Status
Indian palm squirrel Funambulus palmarum Plantation Least
Concern
2. Avian Fauna
Common Name Scientific name Habitat IUCN Status
House crow Corvus splendens Plantation, habitation Least
Concern
Common myna Acridotheres tristis Plantation Least
Concern
Black drongo Dicrurus
macrocercus
Plantation Least
Concern
Black-headed oriole Oriolus xanthornus Tropical moist-
deciduous biotope:light
forest, plantations,
village groves, gardens
Least
Concern
Lesser coucal Centropus
bengalensis
Scrub jungle and tall
grassland
Least
Concern
Common myna Acridotheres tristis Plantation Least
Concern
Common buzzard Buteo buteo Sailing flight over tree
top
Least
Concern
Red whiskered bulbul Pycnonotus jocosus Plantation, shrubs Least
Concern
Red-vented bulbul Pycnonotus cafer Cultivation, Scrubs Least
Concern
Black kite Milvis migrans Urban localities Least
Concern
Large pied wagtail Motacilla
maderaspatensis
Streams, grasses,
irrigation reservoirs
Least
Concern
Environmental Impact Assessment Report 2014
101 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3. Butterfly/insects
Species Observed Scientific name Habitat
Dot dash sergent Athyma kanwa Scrub, plantation, habitation
Blue tiger Tirumala limniace Hills, plains, not in desserts and at
high altitude, gardens
Common Indian
crow
Eupoloea core Among milkweed butterflies, this
is most abundantly found,
Mountains till 8000 feet,
occasionally it swarms in the low,
wet, jungles
Common evening
brown
Melanitis leda Very common throughout India,
except in the arid northwest
Common grass
yellow
Eurema hecabe Scrub, plantation, habitation
4. Reptilian fauna
Species Observed Scientific name Habitat Status
Common garden
lizard
Calotes versicolor Occupies all
biotopes from dry
desert to thick
forest, Indian
subcontinent
It is commonest agamid
lizard of India
5. Amphibian fauna
Common name Scientific name Habitat Status
Asian Common Toad Bufo melanostictus Home in almost all
biotopes found in
India, commonest
among Indian
species
commonest
among Indian
species and also
the amphibian
most likely to be
seen
Conclusion: - There is no fauna species existing at site which are in the red
list species category.
Environmental Impact Assessment Report 2014
102 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Reference:
1. “The Book of Indian Birds” Thirteenth Edition 2012 by Salim Ali,
Bombay Natural History Society
2. “The Book of Indian Reptiles and Amphibians” 2002 by J. C. Daniel,
Bombay Natural History Society.
3. Discussions with local people
3.9 SOIL ENVIRONMENT
Soil Quality
The soil in and around the proposed site is formed due to weathering of rocks
and can be classified as reddish gray / brown silty type. Rocks underneath are of
volcanic origin. The rocks are dark colored of basaltic composition and mainly
comprise of plagioclase, pyroxenes iron ores, primary glass and some secondary
minerals.
Table 3.17 Soil Quality Sampling Location:
Sr.
No.
Sampling Location
Name
Direction from
project site
Distance from
project site 1. Ugar khurd NE 2.7 km
2. Ugar Budruk W 1.5 km
3. Ugar khurd SE 1.7 km
Fig 3.10 Soil sampling site map of 10 km radius area around Project Site
Environmental Impact Assessment Report 2014
103 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Table 3.18 Soil Monitoring Scenario
Sr.
No. Parameters
Project
Site
Ugar
Khurd
(1.7 km)
Ugar
Budruk
Ugar
Khurd
(1.7
km)
Unit
1. pH 7.92 8.03 8.1 7.7 -
2. Conductivity 0.85 0.69 0.92 1.01 Ms/sec
3. Chlorine(Cl) ND ND ND ND Mg/ltr
4 Nitrogen(N) 102 111 100 124 Kg/Ha
5 Phosphorous(P2O5) 22.2 19.4 20.2 18.0 Kg/Ha
6 Potassium(K2O) 241 320 329 237 Kg/Ha
Environmental Impact Assessment Report 2014
104 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
7 Iron(Fe) 6.2 7.4 6.9 7.0 ppm
8 Calcium(Ca) 26.0 21.2 23.4 20.8 Kg/Ha
9 Manganese (Mn) 8.1 10.2 9.3 8.9 ppm
10 Zinc (Zn) 0.62 0.72 0.69 0.70 ppm
11 Copper (Cu) 0.88 0.86 0.94 1.03 ppm
12 Organic Carbon 0.82 0.74 1.03 0.97 %
3.10 Remote Sensing and GIS Study
Remote Sensing is a process of identification and demarcation of various earths’
objects from a distance without directly coming into contact with them. Remote
sensing is largely concerned with the measurement of electromagnetic radiation
from the sun, which is reflected, scattered, and emitted by the objects on the
surface of the earth. Different objects on the surface of the earth reflect different
amounts of the electromagnetic spectrum. The potential of remote sensing in
natural resources mapping basically depends on spatial, radiometric and
temporal resolution of the sensor. Thus the satellite remote sensing with its
capability of repetitive coverage, multi-spectral imaging, synoptic view and low
cost can play an important role in the delineation of various landuse landcover
classes.
Land cover is a fundamental parameter describing the Earth’s surface. This
parameter is a considerable variable that impacts on and links many parts of the
human and physical environments. Remote sensing technique has ability to
represent of land cover categories by means of classification process. With the
availability of multispectral remotely sensed data in digital form and the
developments in digital processing, remote sensing supplies a new prospective
for land-cover/land-use analysis. Geographical Information Systems have
already been used for assessing environmental problems, since they provides a
Environmental Impact Assessment Report 2014
105 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
flexible environment and a powerful tool for the manipulation and analysis of
spatial information for land cover feature identification and the maps of all
variables were combined to extract information to better understand analyzing.
Satellite remote sensing, in conjunction with geographic information systems, has
been widely applied and been recognized as a powerful and effective tool in
analyzing land cover/use categories This study made use of remotely sensed
data and GIS technologies; to evaluate qualitatively and quantitatively outcome
of part of dist. Pune land cover/use distribution. Obtained results were
compared, visualized and analyzed, in Geographic Information System.
The project site is having latitudes 16°39'0.90"N and longitudes 74°49'14.71"E.
The 10 km radius area around project site is having latitudes 16°33'35.452"N to
16°44'26.361"N and longitudes 74°43'37.116"E to 74°54'52.303"E.
Software and Hardware
Satellite Data: RESOURCESAT-2 cloud free data has been used for Landuse /
landcover analysis.
Satellite Sensor – RESOURCESAT-2 LISS- III
Path and Row – Path 97 Row 61 Resolutions - 23.5 m.
Date of Pass: 29 Apr 2013
Ancillary Data:
PC based GIS and image-processing software’s are used for the purpose of
image classification and for delineating drainage and other features in the study
area. Number of peripheral devices such as scanner, plotter, printer etc. has also
been interfaced with the system.
Objectives:
· Delineation of Landuse/ Landcover categories at 10 km radius area
around Project site.
· Generation of digital cartographic database using secondary data sources.
Environmental Impact Assessment Report 2014
106 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Fig.3.11. Toposheet map of 10 km radius area around Project Site.
Methodology:
The multispectral data obtained from sensors, due to its synoptic view and revisit
capability, can effectively be used for continuous monitoring of land surface. The
spatial, spectral and radiometric resolutions are the three primary factors in the
estimation of various landuse/landcover classes.
The satellite data is then taken into a hard disk and then converted in the
standard false colour composite by assigning blue, green and red to green, red
and near infra red band respectively. Image enhancement has been done by the
technique called histogram stretching between the ranges of 0-255, as the data
content is 8-bit. Applying formulae derived by modeling the sources of distortions
in order to correct the systematic distortions such as earth curvature carried out
rectification and registration of satellite data. The random distortions were
corrected using well distributed ground control points occurring in raw data. To
achieve planimetric accuracy, the remote sensing scene was rectified with
Environmental Impact Assessment Report 2014
107 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
respect to SOI maps on 1: 50,000 scales. The GCP’s in the scene such as
railroad intersections, corners of water reservoirs, bunds, etc. were identified on
the image as well as on the reference map. Third order model was constructed
and finally registration of image was carried out with nearest neighborhood
resampling taking map as reference and one map registration was achieved.
Then the subset of image has been taken according to the boundary of the study
area. The digital classification technique has been used for the extraction of the
landuse/landcover information from the imagery. Eight different
landuse/landcover classes have been identified in the area under study. Table
shows the information about the extent of landuse/landcover classes in the study
area.
Environmental Impact Assessment Report 2014
108 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Fig.3.12. Satellite Image of 10 km radius area around Project Site.
Environmental Impact Assessment Report 2014
109 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Landuse/ Landcover Classes Details:
Satellite data for Rabi season was classified using supervised classification
technique. Maximum likelihood algorithm classifier was used for the analysis.
The scenes were individually classified and then were integrated to get a
composite classified output where information from Rabi season is available. A
truth table was generated taking 0.95 as the conversion threshold. After
aggregation, the final classified output was converted in raster format. The image
was then converted in raster format, which is understood by GIS. Eight landuse /
landcover classes identified in total 10 km radius area around Project Site. The
area under each class has been calculated and given below.
Table 1: Landuse/ Landcover Statistics of the Ten Km radius Area.
Sr. No.
LAND USE AREA (Ha)
AREA (%)
1 Built-Up Land
Settlements 599.52 1.9 2 Water Bodies
Tank/River/Dry Reservoir etc.
455.4 1.44
3 Forest
Vegetation 537.66 1.7 4 Crop Land
Irrigated crop land 8198.68 26.05 Fallow land 8501.12 27.07
5 Waste Lands
Land with scrub 6691.23 21.23 Land without scrub 6488.37 20.61
Total 31471.98 100.00
Environmental Impact Assessment Report 2014
110 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Fig.3.13. Landuse/landcover map of 10 km radius area around Project Site.
Environmental Impact Assessment Report 2014
111 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Digital Cartographic Database preparation in GIS
GIS is an integrated information system having capability to capture, store, edit,
manipulate, analyze and retrieve all types of spatial and non-spatial information
about a particular area. The advent of electronics and computing techniques coupled
with the development of GIS has increased the potential of creating and maintaining
databases using geographical space as the key field. The database can be used for
speedier monitoring, assessment, planning, and management of various aspects of
natural resources.
Comprehensive GIS based database was generated for the study area that
comprises of the following data sets. Resource data such as landuse from remote
sensing data, soil map, geology, water bodies, surface and ground water sampling
locations, drainage, contour.
The methodology used for database preparation involves the following steps
Data Input:
The function of data input is to convert the existing data from one into another that
can be used in GIS. Georeferenced data are commonly provided as maps, satellite
images, and associated attributes.
Environmental Impact Assessment Report 2014
112 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
· Drainage Map: Drainage layer, which was generated after scanning the
thematic manuscripts, was edited for line the errors. Two different layers were
made separately for line drainage. Drainage order was given to all the drain
lines in the layer‘s. Strahler method of ordering was used for giving order to
drainage. Whenever two drains of any order joined the order of next drain was
increase by one. The study area has an order of fourth. River name also
attached as attribute to drainage layer. All the water bodies and river with
sufficient width were put in polygon layer.
The area shows not much of undulating topography thus it shows the
Dendritic drainage patterns.
Fig. 3.14: Drainage map of 10 km radius area around Project Site.
· Contour – Thematic manuscript for contour layer was generated from Survey
of India toposheet at 1:50,000 scale. After scanning coverage was generated.
Environmental Impact Assessment Report 2014
113 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Coverage was edited to remove all errors of dangle. Attribute value was given
to each contour in the coverage.
Fig.3.15: Contour map of 10 km radius area around Project Site.
3.11 Socio-Economic Environment: Social and economical consideration is basic in the man-made environment. Any
human activity is undertaken for a sole objective of economic benefit to the human
society. In other words if the socio-economic impact is not positively beneficial, one
will not enter into that activity at all. It is, therefore, worthwhile to make a socio-
economic impact assessment (SIA) in advance before deciding on commencement
of the activity. SIA is done honestly, keeping the following framework.
• SIA is a systematic effort to identify, analyze, and evaluate social impacts due to a
proposed project or policy change on the individuals and social groups within a
community or on an entire community in advance of the decision making process in
order that the information derived from the SIA can actually influence decisions.
Environmental Impact Assessment Report 2014
114 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
• SIA increase knowledge on the part of the project proponent and the impacted
community.
• SIA raises consciousness and the level of understanding of the community and
puts the residents in a better position to understand the broader implication of the
proposed action.
• SIA includes within it a process to mitigate the social impacts likely to occur, if that
action is desired by the impacted community. For further discussions this study area
which is fully of rural component will be considered.
· Village Map: Village layer was prepared from SOI toposheet at 1:50,000
scale, 10 km radius area around the project site. After scanning the
manuscript layer was prepared. The point layer was prepared. Errors were
removed after editing the layer.
Fig. 3.16: Village map of 10 km radius area around Project Site.
Environmental Impact Assessment Report 2014
115 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
· Accessibility Map: Major Road and Railway network layer was prepared
from SOI toposheet at 1:50,000 scale 10 km radius area around the project
site. After scanning the manuscript layer was prepared. Errors were removed
after editing the layer. Attributes were given to different types of road and
railway.
Fig. 3.17: Accessibility map of 10 km radius area around Project Site.
3.12 HYDROGEOLOGY
Water table generally follows the topography of the area and is at greater depths in
the water divides and topographic highs, but becomes shallower in the valleys and
topographic lows and therefore, groundwater moves down and follows the gradient
from the higher to lower elevations, that is, from recharge area to discharge area.
Therefore, locally direction of flow from higher elevations is towards the rivers.
Overall, the general flow direction of ground water in the district is generally towards
the east.
Environmental Impact Assessment Report 2014
116 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
The district is underlain by gneisses, schist, limestone, sandstone, basalts, alluvium
etc. of Archaean to Recent age. Deccan basalts cover an area of 7,650 Sq.Kms. in
the northern part of the district and have a maximum thickness of around 256 m,
which gradually thins out in the southern direction.
Hard rocks occupy a major part of the district; majority of which are basaltic lava
flows. Most of these rocks have poor capacity of storing and transmitting water,
except through favourable zones and at favourable locations. Aquifer systems
encountered are therefore limited in nature. Ground water occurs both in weathered
and fractured zones. Ground water occurs in all weathered formations of the district
under phreatic conditions and in fractured and jointed formations under semi-
confined conditions.
Deccan basalts act as a multilayer aquifers having low to medium permeability. In
Deccan basalts that comprise different flows, fractures and interstitial pore spaces of
vesicular zones, are good repositories of ground water. Groundwater occurs under
phreatic conditions in weathered zone of these basalts and under semi-confined to
confined conditions in inter-trapeans and also in joints and fractures at deeper levels.
In limestone, solution cavities are considered to be more potential than weathered
and fractured ones. In gneisses and schist, weathered zone varies from 7 to 12 m
and water-bearing zones extend down to 80m.
The aquifers occurring within the shallow depth range of 0 to 20 m bgl are mainly
weathered and fractured formations. Groundwater occurs in these formations under
phreatic conditions and the average thickness of these aquifers ranges from 5 to
15m. In general, 60% area of the district is having the weathered thickness in the
range of 5 to 10 m. About 25% of the district area has weathered thickness in the
range of 10 to 15m and 15% in the range of 15 to 20m.
In the major parts of the district, the decadal mean of depth to water level generally
ranged between 5 to 20 m bgl (Figure-3). During pre-monsoon period i.e. May 2006,
8%, 28%, 37%, and 27% of the wells had depth to water level ranges between 0-2,
2-5, 5-10 and 10-20m bgl respectively (Figure-4). There was a rise of water level in
Environmental Impact Assessment Report 2014
117 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
30%, 20% and 30% of the wells during post monsoon period i.e. November 2006 in
the range of 0-2, 2-4 and more than 4m respectively.
On the other hand 12%, 5% and 3% of the wells showed a fall in water levels in the
ranges of 0-2, 2-4 and more than 4m respectively. Therefore, more than half of the
district had depth to water level between 2-5m bgl during post-monsoon period i.e.
November 2006 and the overall depth to water level in the district was between 0 to
10m bgl, except in a small strip towards southern part of Ramdurg taluk where it is
more than 10m bgl.
The long-term pre-monsoon water level trend (1996-2005) shows a rise in 53% of
the wells, while there is a fall in 47% of the wells. On the other hand during post-
monsoon period, 68% of the wells show falling trend, while there is a rising trend in
32% of the wells. Over all the annualised trend shows a fall in 61% of the wells and
rise in 39% of the wells.
Based on the pumping test data of the dugwells, it is inferred that there is a
progressive increase in the permeability exceeding >100m/ day in the water table
phreatic zones of basaltic aquifers towards the east, even though the area falls in the
northern dry and transitional zone having low to moderate rainfall. Similar is the case
with other lithologic units. On the other hand in Khanapur taluk, though it falls in high
rainfall hill zone agro-climatically, the permeability of the principle water table
aquifers of schists and gneisses range from < 25 to 50m/ day.
Analyses of Pumping test data of exploratory borewells show that wells have yielded
discharges in the range of 0.02 to 7.58 lps and the draw down ranged between 0.068
to 32.44 m. The transmissivity (T) computed was between 1 and 2,220 m2/day.
Environmental Impact Assessment Report 2014
118 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Fig 3.18: Hydrogeology of Belgaum district, Karnataka
Source: Central Ground Water Board South Western Region Bangalore August 2007
3.13 SEISMICITY Based on the tectonic features and records of earthquake, a Seismic Zoning map
has been developed for the country by Bureau of Indian Standard (BIS). Seismic
Zoning Map of India is placed as Figure 3.13
Environmental Impact Assessment Report 2014
119 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Figure 3.19 : Seismic Zone Map
The area under study falls in Zone-II, according to the Indian Standard Seismic
Zoning Map. Suitable seismic coefficients in horizontal and vertical directions
respectively, have to be adopted while designing the structures.
* * * * *
Environmental Impact Assessment Report 2014
120 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER 4
ANTICIPATED ENVIRONMENTAL
IMPACTS & MITIGATION
MEASURES
Environmental Impact Assessment Report 2014
121 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4.0 Identification of Impacts
Identification, prediction and assessment of potential impacts of the proposed expansion
project on the surrounding environment during construction and thereafter during
operation stage have been discussed in this section. In line with any industrial
development, the Sugar, cogen & distillery expansion project have environmental
impacts during construction and operational phases. By and large the impacts are local
and there are no major sub regional or regional negative impacts.
The proposed expansion of integrated project installation will involve activities such as
erection of plant and machinery, creation of infrastructure to transport raw material and
finished products as the main activities during construction phase. These activities
during construction phase will have impacts on air & water quality, noise levels, socio-
economic conditions. However the impact on environment will be limited to construction
phase. Following paragraphs give a brief description of the environmental impacts of
proposed of sugar, cogeneration & Distillery projects during construction and operational
phases.
· During construction phase: These may be regarded as temporary or short term
and ceases with implementation of the project.
· During operation phase: These impacts are continuous warranting built in
permanent measures for mitigation and monitoring.
Construction and operation phase of the project comprises of various activities, each of
which will have an impact on some or other environmental parameters. Impacts on
environmental parameters during construction and operational phase have been studied
to estimate the impacts on environment as below.
4.1 Impacts during Construction Phase and Mitigation Measures
Construction activity includes foundation works, fabrication of storage tanks and erection
of plant-machineries. The construction phase is expected to be about three months. The
major activities during construction phase include
1. Site preparation and development
2. Civil construction work
3. Vehicular movement
4. Loading and unloading civil items and plant machineries
5. On site storage of civil items & plant machineries.
Environmental Impact Assessment Report 2014
122 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
6. Erection of plant and civil structures
7. Power supply
8. Maintenance of construction machinery
9. Disposal of solid wastes
Probable environmental impacts during construction phase are typically due to activities
related to clearing of vegetation, leveling of site, civil constructions erection of structures
and installation of equipment.
The activities will have impact on land environment, water environment, air environment,
noise level and socio-economics of the region and these are discussed below.
4.1.1 Air Environment
Impact on Air Quality
During construction phase, suspended particulate matter will be the main pollutant,
which will be generated from site development activities and movement of vehicles. The
impact will be mostly confined within the project boundary and is expected to be
negligible outside the plant boundary. The transportation and construction activity is for a
limited period and therefore the air emissions due to vehicles or construction equipment
will be for a limited period only. The impact of such activities would be temporary and
restricted to construction phase.
The main sources for impact of air quality during construction period is due to movement
of vehicles and construction equipment at site, dust emitted during leveling, grading,
earthmoving, foundation works, transportation of construction material etc. Hence,
during the construction phase, particulate matter (PM10 & PM2.5) would be the main
pollutants. The emissions from vehicles and construction equipment could also be of
some concern on a local level. The internal roads will be paved or tarred. Proper upkeep
and maintenance of vehicles, sprinkling of water on roads and construction site are
some of the measures that would greatly mitigate the impacts on air environment during
the construction phase.
All the vehicles permitted at the project site will be possessing Pollution under Control
certificate. All the contractors will be instructed to carry out regular maintenance of
vehicles in order to keep pollution under check.
Environmental Impact Assessment Report 2014
123 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Air Pollution Mitigation Measures
The dust generated will also be fugitive in nature, which can be controlled by sprinkling
of water. The impacts will be localized in nature and the areas outside the project
boundary are not likely to have any major impact with respect to ambient air quality.
The construction of proposed units would result in the increase of SPM concentrations
due to fugitive dust. Frequent water sprinkling in the vicinity of the construction sites
would be undertaken and will be continued after the completion of plant construction as
there is scope for heavy truck mobility. It will be ensured that diesel powered vehicles
will be properly maintained to comply with exhaust emission requirements.
4.1.2 Noise Environment
Impact on Noise Levels
Noise will be generated during the construction phase due to vehicular traffic, movement
and operation of construction equipment like dozers, scrapers, concrete mixer, cranes,
generators, compressors, vibrators etc. The operation of these equipments will generate
noise ranging between 70-85 dB (A). Major construction work will be carried during the
day time. Personnel protective devices such as ear muffs will be provided to the
operators of this machinery to prevent harm due to noise.
Since noise levels reduce @ square of distance, effect of construction activity noise shall
not be significant on surrounding areas.
Noise Levels Mitigation Measures
The noise control measures during the construction phase include provision of caps on
the construction equipment and regular maintenance of the equipment. Equipment will
be maintained appropriately to keep the noise level within 75 dB(A). Wherever possible,
equipment will be provided with silencers and mufflers. High noise producing
construction activities will be restricted to daytime only. Further, workers deployed in
high noise areas will be provided with necessary protective devices such as ear plug,
ear-muffs etc. Overall, the impact due to increase in noise on the environment would be
insignificant, localized and confined to the day hours.
Environmental Impact Assessment Report 2014
124 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4.1.3 Water Environment
Impact on Water Resources and Quality
Due to civil construction activities, during rainy season the surface run off may contain
more of eroded soil and other loose matter. Construction activities may be avoided
during rainy days to mitigate the small impacts on soil quality caused due to construction
activity. Segregation of construction area and proper drainages facilities will prevent the
contamination of water due to construction activity. Proper garland drains will be
provided so as contaminants like oil and grease, diesel fuel, paints etc do not mix with
soil. Water after washing will be collected in drain in an impervious pond, filtered and
used for irrigation.
Proper drinking and sanitation facilities will be constructed first for workers. The sewage
will be collected in a septic tank with overflow as well as sludge will be used for irrigation.
Water Pollution Mitigation Measures
Toilets with septic tanks will be constructed at site for workers and it will be ensured that
domestic wastewater generated in worker colonies does not flow to water bodies. The
overall impact on water environment during construction phase due to expansion
activities is likely to be short term and insignificant. By adopting necessary mitigation
measures the overall impact on water environment during construction phase of the
project will be temporary and insignificant.
4.1.4 Land Environment
Impact on Land use
Additional construction will be carried out on barren lands which are already available
with USWL. It is a plain land almost in level. No major earth moving / leveling will be
involved. There is no vegetation or trees or water bodies present on factory land. Most of
the land will be open with storage sheds, roads, effluent treatment systems installed.
Construction will be only in small portion.
33% of open land and belt around the factory premises will be developed as green belt.
Plant sampling suiting local conditions will be planted
Environmental Impact Assessment Report 2014
125 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Impact on Topography
Topographically, the area forms slightly elevated land and general elevation is from
North to South. Most of the area forms plain land covered with mixed soil. Adequate
storm water drains will be provided to collect and carry the surface runoff during
monsoon to the natural drainage system of the project area.
4.1.5 Socio-economic Environment
The socio-economic impacts during the construction phase of the proposed
Enhancement Sugar plant with Cogeneration Plant & distillery unit could result due to
migrant workers, worker camps, induced development etc. Increase in floating
population. The local population will have employment opportunities in related service
activities like petty commercial establishments, small contracts/sub-contracts and supply
of construction materials for buildings and ancillary infrastructures etc. consequently, this
will contribute to economic up liftment of the area. Normally, the construction activity will
benefit the local population in a number of ways, which include the increase in
requirement of construction skilled, semi-skilled and un-skilled workers, tertiary sector
employment and provision of goods and services for daily needs including transport.
Ø Local people will be given preference for employment depending on their
suitability;
Ø All the applicable guidelines under the relevant Acts and Rules related to labour
welfare and safety will be implemented during the construction phase;
Ø The contractor has been advised to provide fire wood/kerosene/LPG to the
workers to prevent cutting of nearby trees for firewood; and
Ø The construction site will be secured with fencing and is having guarded entry
points.
4.1.6 Storage of Hazardous Material
The hazardous materials used during construction may include diesel and lubricating
oils.. These materials will be stored and handled carefully under applicable safety
guidelines. Some of the precautions of storage include the following:-
Environmental Impact Assessment Report 2014
126 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø Dyked enclosures will be provided so as to contain complete contents of the
largest tank;
Ø Diesel and other fuels will be stored in separate dyke enclosures;
Ø Tanks having large storage capacity for will be separated by fire insulating walls
from other storage tanks; and
Ø The distance between the storage tanks will be maintained half their height.
4.1.7 Facilities to be provided by Labour Contractor
The contractor will be made to provide the following facilities to construction work force:
First Aid
At work place, first aid facilities will be maintained at a readily accessible place where
necessary appliances including sterilized cotton wool etc. Ambulance will be kept at the
site and made available at workplace to take injured person to the nearest hospital.
Potable Water
Sufficient supply of water fit for drinking will be provided at suitable places.
Sanitary Facility
Sanitary facilities will be provided at accessible place within the work zone and kept in a
good condition. The contractor will conform to requirement of local medical and health
authorities at all times.
Canteen
The canteen will be provided for the benefit of workers.
Security
USWL will provide necessary security to work force in co-ordination with State
authorities.
Environmental Impact Assessment Report 2014
127 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4.2 Impacts during Operation Phase
During the Operation Phase the establishment of the project, results in emissions,
generation of wastewater and solid waste.
4.2.1 Air Pollution
The proposed project will use own generated bagasse, available bagasse from nearby sugar
mills for the proposed Boiler of the Integrated Sugar plant. The unit will use bagasse for
which steam turbine has been envisaged. In extreme emergency, Diesel Generator will be
used for running the important equipment and street light. This will be limited to a few hours
only. As such, the pollutants expected to be released in the emission will mainly be the
Particulate Matter (PM).
The concerning emission will be only from Point Source i.e. from Stack of Boiler, which
will be released through a stack of 75 m. height.
Mitigation Measures
The measures to minimize air pollution have been envisaged as under:
v Providing adequate stack height as per norms of MoEF & KSPCB for wider
dispersion of pollutants, resulting in lower ground level concentration.
v Stacks of Boiler will be equipped with ESP.
Environmental Impact Assessment Report 2014
128 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Electro Static Precipitator (ESP) Details
Ø A suitable ESP so that the fly ash contents of flue gases leaving the chimney
confirm to the rules and regulations of the pollution act as applicable to the
factory and as outlet concentration below 100 mg/Nm3.
Ø A certificate to this effect should be obtained from pollution control board under
whose jurisdiction this mills falls.
Ø The ESP shall be installed on the suction side of the I.D. fan and shall to be
complete with rotary airlock valve with drive provided with local and remote push
button control, and a side manual gate. The minimum elevation of discharge
flange of the rotary airlock valve shall be at + 2500 mm.
Ø Suitable platform, ladder, inspection and poking holes etc., shall be provided to
facilitate regular inspection and cleaning of the ESP.
Ø Even with one field of ESP out of service the ESP must remain in operation. The
ESP with only one field in service at 100% boiler MCR with bagasse as fuel.
Ø All electrical including MCC, rectifiers, panels, electrical & control cables, earthing
will be in place. ESP control shall be from control room
Ø The design & supply will suitable flue gas cleaning system to ensure that the flue
gases entering the chimney do not contain SPM in excess of 100 mg/Nm3.
The exhausts of DG set will be provided with adequate height as per norms prescribed
by Central Pollution Control Board.
Impact Assessment
The impact on air quality has been assessed considering the following:
Environmental Impact Assessment Report 2014
129 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
a) The air quality impacts have been predicted for the release of emissions
from Stack of Boiler.
b) Plume Rise and Effective Stack Height
Brigg’s modified equation as suggested by Central Pollution Control Board
has been used for calculation of effective Stack Height.
c) Dispersion Coefficient: Brigg’s dispersion coefficients have been used to
determine sy and sz for rural conditions.
d) Particulate Matter (SPM) has been considered taking maximum limit of 150
mg/Nm3 for Stack as prescribed by Central Pollution Control Board for stack
in general.
Air Quality Modeling
The air dispersion model used is Industrial Source Complex Short Term (ISCST 3),
Version 02035 developed by the US Environmental Protection Agency (US EPA) and
recommended by Ministry of Environment & Forests (MoEF).
The main air pollutant from the operations would be Particulate Matter and for the same
short term 24-hourly GLC’s has been computed. The GLC’s are estimated using the site-
specific meteorological data. The details of stack and emissions for the proposed project
are presented in Table 4.2.
AIR POLLUTION MODELLING
Prediction of impacts on air environment has been carried out employing mathematical
model based on a steady state Gaussian plume dispersion model designed for multiple
point sources for short term. In the present case, AERMOD View version 8.0.0
dispersion model based on steady state Gaussian plume dispersion, designed for
multiple point sources for short term and developed by Lake Environment has been used
for simulations from open pit source.
Presentation of results
The maximum GLCs for Particulate Matter after implementation of the stone quarry are
likely to be within the prescribed standards for industrial areas. The impact on ambient
air quality due to the proposed plant has been assessed by estimating the maximum
Environmental Impact Assessment Report 2014
130 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ground Level Concentrations (GLC's). Site specific meteorology data recorded for the
period September 2013 to November 2013. In the Short-term simulations, the
concentrations were estimated around 441 receptor points chosen to obtain an optimum
description of variations in concentrations over the site in an area of 10 km radius
around plant centre.
The highest predicted results for each pollutant are tabulated. The incremental
concentrations are estimated at ambient air quality monitoring locations and are
superimposed over the baseline concentrations to know the likely resultant
concentrations and are depicted below in Table.
TABLE 4.1 RESULTANT CONCENTRATIONS
Pollutant Maxi AAQ Conc. Recorded during study period (µg/m3)
Max incremental Conc. Due to project (µg/m3)
Resultant Conc (µg/m3)
PM10 72.3 0.00062 72.30062
SO2 9.1 0.20966 9.30966
NOx 16.6 0.20912 16.80912
Maximum incremental concentration was obtained at project site, when added with
baseline values resultant concentration was obtained which is below NAAQ standards.
The isopleaths obtained were presented in figure 4.1 to 4.3.
Environmental Impact Assessment Report 2014
131 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Environmental Impact Assessment Report 2014
132 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Environmental Impact Assessment Report 2014
133 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Environmental Impact Assessment Report 2014
134 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Input Parameters
For modeling purposes Particulate Matter (PM) have been considered. The emission of
SO2 & NOx has not been considered because of its insignificant concentration in
Emission.
The PM has been taken maximum 150 mg/Nm3 (as prescribed by CPCB for Stack
Emission). The details are presented in Table 4.2 as under.
Table – 4.2 Stack & Emission Details
Source of Air pollution
MYS 1736 50TPH
MR 8597 MR 8598 60TPH
KTK 2272 70TPH
KTK 2404 80TPH
Type of fuel Bagasse Bagasse
Bagasse + coal
Bagasse
Quantity of fuel 25 T/hr. 60 T/hr 35 T/hr 40 T/hr
Height 45.5 mtr 60 mtr. 50 mtr. 52 mtr.
APC equipment Wet Scrubber
Wet Scrubber ESP ESP
Gas quality m3/hr 36.3 42.4 20.7 19.3
Temp 0C 11 140 100 110
Exit gas velocity m/sec
10.3 13.6 5.9 6.2
SPM (mg/Nm3) 11.4 7.9 17.3 10.2
SO2 (µg/Nm3) 41.1 42.2 39.2 40.1
NOx (µg/Nm3) 42 40.7 46.0 44
Results & Discussions
The predictions have been made for the summer season i.e. September 13 – November
13. The hourly data on wind speed, direction, atmospheric stability, temperature have
been used.
Environmental Impact Assessment Report 2014
135 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
For the short-term simulations, the concentration was estimated around 396 receptors to
obtain an optimum description of variations in concentrations over the site in 10 km.
covering 36 directions for the monitoring period. For each time scale i.e. for 24 Hrs. the
model computes the 50 highest concentrations observed during the period over all
measurement points.
The resultant concentration after the commissioning of the proposed boiler on the GLC
of SPM as predicted and super imposing the predicted values on the maximum baseline
concentrations recorded during the study period respective to the direction and distance
of the monitoring location . The predicted GLCs for SPM after commissioning of the
proposed project are not found to be significant to add up on the existing ambient air
quality. However, the proposed air pollution control system for boiler, Electro Static
Precipitator (ESP) will be installed for further improving the existing ambient air quality
and help in bringing down the ambient air quality.
The estimated cumulative GLCs for SPM after commissioning of the proposed project
are found to be well within the ambient air quality standards prescribed by CPCB.
Hence it can be concluded that the impact on Air Quality by the proposed project will be
negligible. The environment around the proposed site has enough buffers to assimilate
these insignificant values. The favorable wind and the proposed height of stack will
disperse these pollutants in different directions fast to longer distance with negligible
concentrations.
4.2.2 Impact on Water Quality
There will not be any significant pollution during the construction & operation phase as
the development will take place in existing building structure. Adequate provisions will be
made available to collect the runoff from the site, so that runoff will not be allowed to
stand or enter into the roadside or nearby drain.
The water used for the USWL plant will be supplied by Irrigation department. The water
will be treated fully to standard characteristics. The samples will be tested & confirmed.
Environmental Impact Assessment Report 2014
136 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Total effluent generated during the operation will be about 4960 M3/day from sugar &
cogen unit. An effluent treatment plant has been provided which is continuously in
operation and the results obtained will be within the permissible limits as prescribed by
KSPCB.
This will be achieving ‘Zero Discharge’ plant to meet the guidelines of MoEF. The
effluent from the sugar mill will essentially be subjected to the effluent treatment plant
and then will be utilized for irrigation and other horticultural uses. The domestic effluent
will be treated into STP followed by Gardening. The details of water budget and process
of ETP are enclosed as Annexure.
4.2.3 Solid Waste
Minimum amount of solid waste will be generated as there will be construction work.
Following mitigation practice is the policy for future:
Ø Minimization at al l levels need be attempted for discarded products,
empty containers, packing surpluses, incoming raw material
unloading spi l lages and fugit ives.
Ø The solid in process generate only as Ash from cogenerat ion plant,
ETP sludge and domestic waste.
Ø Other wi l l be empty drums which can be used for ref i l l or may be
disposed to original vendors
The solid waste generation from Sugar and dist i l lery units are tabulated in
table 2.9.
Table 2.9 Solid Waste Generation from Sugar Plant with disposal
Source Quantity Treatment & Disposal
CANE CRUSHING SEASON
Mil l House Bagasse – 6000
T/day
Use in Boi ler of Cogen plant
Process House Press Mud – 800
T/day
Disposed to Dist i l lery units by
product ion of potash powder.
Environmental Impact Assessment Report 2014
137 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Boiler House –
Cogen Plant
Ash – 200 T/day The ash being r ich in nutr ient
composit ion, the same will be
disposed as fert i l izer for soil
condit ioning.
Eff luent
treatment Plant
Sludge – 80-100
T/day
Disposed as Manure.
Evaporator &
Dryer plant
powder
10-12 MT/day Sold to farmers & fert i l izer
companies as a manure
Hazardous wastes such as waste oil from machinery would be generated from the
proposed project. Such waste oils shall be collected, stored safely at a designated
area. The waste oils would further be sold to oil recyclers, duly approved by Central
Pollution Control Board (CPCB).
4.2.4 Impact on Ecology
The enhanced project will not have any significant impact on ecology as there are no
reserve forests in the study area and in addition to that the project will implement an
effective environmental management plan to control the emissions from the project.
Green belt development
Out of the total project area 33% will be used for green belt development. Local species
will be preferred for green belt development.
4.2.5 Demography and Socio-economics
The impacts due to enhanced project on demography and socio economic condition are
as follows:-
Ø Increase in employment opportunities and Reduction in migrants to outside for
employment.
Ø Increase in literacy rate.
Ø Growth in service sectors
Environmental Impact Assessment Report 2014
138 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø Increase in consumer prices of indigenous produce and services, land prices,
house rent rates and Labour prices.
Ø Improvement in socio cultural environment of the study area.
Ø Improvement in transport, communication, health and educational services.
Ø Increase in employment due to increased business, trade commerce and service
sector.
Ø The overall impact on the socio economic environment will be beneficial.
4.2.6 Impact on Health
Adequate air pollution and noise control measures will be provided. The environmental
management and emergency preparedness plans will be prepared to ensure that the
probability of undesired events and consequences would be reduced, and adequate
mitigation measures will be provided in case of an emergency. The overall impact on
Human health is negligible during operation of plant.
4.3 MITIGATION MEASURES AGAINST ENVIRONMENTAL IMPACTS
The main objective of mitigation measures is to conserve the resources, minimize the
waste generation, treatment of wastes, recovery of by products and recycling of material.
It also incorporates greenery development and landscape of open area and also the
post project monitoring of environmental quality. The measures under mitigation plan are
classified as,
· Measures built in the process
· Measures during construction phase
· Measures during operation phase.
4.3.1 MEASURES BUILT IN THE PROCESS
Built in measures for resource conservation and pollution control in the industry are
discussed along with project. The main objective is to follow environments friendly
process, with efficient utilisation of resources, minimum waste generation and built in
waste treatment and operation safety. The measures adopted are,
Co-Gen Power Unit
Environmental Impact Assessment Report 2014
139 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø Boilers will be fired with multi fuels having low sulphur content.
Ø Boilers are provided with ESP and chimney of 50 m height to control the impact
of gaseous emissions.
Ø Bagasse is Conveyed through covered mechanical conveyors in the plant.
Distillery Unit
Ø Continuous fermentation to improve alcohol yield and recovery and thereby
Ø molasses consumption reduced.
Ø Separation, recovery and recycle of yeast present in fermenter wash for reuse
Ø in fermenter. This reduces the use of fresh culture and nutrients in the fermenter
and also improves ethanol yield.
Ø Use of live steam is avoided by employing re-boiler in distillation columns. This
reduces the generation of wastewater.
Ø Multi pressure distillation system is used to reduce the consumption of steam and
quantity of effluent.
Ø Use of pumps with mechanical seals to avoid liquid leakages.
Ø Scrubbing of fermenter vent gases containing CO2 to recover traces of alcohol
present in it.
Ø Water utilization reduced by
a. Evaporation of spent wash with recovery of condensate water for use in cooling
tower,
b. Re-boiler reduces water utilization,
c. Recycle of lees water for dilution of molasses and
d. Decanter centrifuge and recycle of thin yeast slurry saves water and improves
alcohol recovery.
Ø Bio recovery from spent wash for use as fuel.
Ø Concentrated spent wash is used as fuel in boiler.
* * * * *
Environmental Impact Assessment Report 2014
140 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER– 5
ENVIRONMENTAL MONITORING
PROGRAM
Environmental Impact Assessment Report 2014
141 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Environmental Monitoring Program
5.0 Introduction:-
The Objective of this Study is to minimize or off-set the adverse impacts that might be
created due to this project. Various mitigation measures are designed and described. In
operation phase we shall have to check continuously as to (1) whether our measures are
being operated as per design and (2) whether the resultant impacts are coming inside
the tolerance limits. This can happen only if we have a specialized cell, higher
management support for the cell, adequate funding, support of library- laboratory, open
dialogue corridor with all the stakeholders and authorities, and if the success indicators
are in agreement with our findings. Documentation is necessary along with periodic
Reporting to factory management and statutory authorities such as MoEF, KSPCB,
Factory inspectorate etc.
It is proposed to frame an Environmental Monitoring programme both in Construction
and Operational stages to monitor the effectiveness of the mitigation measures by
judging the impact on environment. A separate budget is proposed for the same as also
a dedicated Cell. A transparent approach will be kept with documentation and Reporting
with statistical treatment to the data. Checklist of Statutory Obligations will be maintained
and compliance with it will be monitored.
A chemical or process industry in general produces solid, liquid and gaseous wastes,
which are discharged to the environment. These discharges pollute receiving media
such as air, water and land which in turn harm living beings and property. The waste
product may contain one or more chemical constituents. It is the responsibility of the
industries to prevent or minimize the discharges of waste products by adopting suitable
control measures in the factory to avoid harm to the environment. The effectiveness of
such measures is ascertained by systematic monitoring of discharges at factory level
and at receiving level. Systematic monitoring of various environmental parameters is to
be carried out on regular basis to ascertain the following.
1. Pollution status within the plant and in its vicinity.
2. Generate data for predictive or corrective purpose in respect of pollution.
3. Effectiveness of pollution control measures and control facilities.
Environmental Impact Assessment Report 2014
142 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4. To assess environmental impacts.
5. To follow the trend of parameters which have been identified as critical;
Pollution Monitoring and Surveillance Systems
For Proposed Enhanced Sugar, Cogeneration power plant and Distillery unit, the Indian
Emission Regulations stipulate the limits for particulate matter emissions and
appropriate stack heights will be maintained for keeping the emission levels in the
ambient within the air quality standards. The characteristics of the effluent from the plant
would be maintained so as to meet the requirements of the State Pollution Control Board
and the National Standards for Sugar Plant stipulated by the Central Board for
Prevention and Control of Water Pollution.
5.1 Environmental cell
An Environmental Cell will be established in the industry to implement and monitor
environmental policy and program. Environmental management Environmental cell
consisting of Managing director and departmental heads will be created to effectively
manage the environmental activities in the industry.
5.2 Environmental Department
Environmental department will be formed with environmental scientist, laboratory
chemists and operators to implement and operate pollution control and environmental
protection measures.
5.3 Environmental Monitoring Plan
Self monitoring system consisting of well equipped laboratory and manpower will be
established in the industry with facilities to analyze wastewater, soil, stack emissions,
ambient air etc. to ascertain the compliances of environmental norms and standards.
The routine monitoring program as indicated below is already practiced in the existing
industry. The same facility and system is adequate even after expansion of the proposed
power plant. However additional monitoring facility will be provided for stack emissions
of the boiler.
Regular monitoring of important and crucial environmental parameters is of immense
importance to assess the status of environment during plant operation. The knowledge
of baseline status and monitored data is an indicator to ascertain for any deterioration in
environmental conditions due to operation of the plant. Based on these data, suitable
Environmental Impact Assessment Report 2014
143 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
mitigation steps could be taken in time to safeguard the environment. Monitoring is as
important as that of pollution control since the efficiency of control measures can only be
determined by monitoring. A comprehensive monitoring system in the industry is
parented below.
5.4 Environmental Records
Environmental department will maintain log sheets and records for operation and
maintenance of pollution control and related facilities. Self monitoring system will be
established in the industry with manpower and facilities to ascertain the compliances of
environmental norms and standards. A laboratory is established to analyze wastewater,
soil, stack emission, ambient air etc. The parameters are monitored as per
MoEF/KSPCB guidelines. The quality and quantity of wastes discharged from the
industry and the significant parameters of environment will be regularly monitored during
operation of the industry.
Air Quality monitoring programme
The purpose of air quality monitoring is acquisition of data for comparison against
prescribed standards, thereby ensuring that the quality of air is maintained within the
permissible levels. It is proposed to monitor the following from the stack emissions:-
v Particulate Matter (SPM, PM10& PM2.5)
v Sulphur dioxide
v Oxides of Nitrogen
It is proposed to monitor particulate emission qualitatively and quantitatively in the stack
and with the aid of a continuous particulate stack monitoring system. The stack
monitoring data would be utilized to keep a continuous check on the performance of
ESPs and Scrubbers. Further it is proposed to monitor and record the weather
parameters such as temperature (maximum & minimum), Relative humidity, wind
direction, wind speed, rainfall etc. on daily basis, for this purpose, it is proposed to install
Weather Monitoring Station with necessary gadgets.
5.5 Post Project Environmental Monitoring
Environmental monitoring will be conducted on regular basis to assess the pollution level
in the plant as well in the surrounding area. Therefore, regular monitoring program of the
Environmental Impact Assessment Report 2014
144 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
environmental parameters is essential to take into account the changes in the
environment. The objectives of monitoring are:-
Ø To verify the result of the impact assessment study in particular with regards to
new developments;
Ø To follow the trend of parameters which have been identified as critical;
Ø To check or assess the efficacy of the controlling measures;
Ø To ensure that new parameters, other than those identified in the impact
assessment study, do not become critical through the commissioning of new
installations or through the modification in the operation of existing facilities;
Ø To check assumptions made with regard to the development and to detect
deviations in order to initiate necessary measures; and
Ø To establish a database for future Impact Assessment Studies for expansion
projects.
The attributes, which merit regular monitoring, are specified below:-
v Air quality;
v Water and wastewater quality;
v Noise levels;
v Soil quality;
v Ecological preservation and afforestation; and
v Socio Economic aspects and community development
The post project monitoring will be carried out at the industry level is discussed below:
5.6 Monitoring and Reporting Procedure
Regular monitoring of important and crucial environmental parameters has an immense
importance to assess the status of environment during plant operation. With the
knowledge of baseline conditions, the monitoring programme can serve as an indicator
for any deterioration in environmental conditions due to operation of the plant and
suitable mitigation steps could be taken in time to safeguard the environment. Monitoring
is as important as that of control of pollution since the efficiency of control measures can
only be determined by monitoring. The following routine monitoring programme would
therefore be implemented. A comprehensive monitoring program will be implemented is
given in the Table 5.1.
Table 5.1 Post Project Monitoring Source
Source Location Parameters to Frequency Responsibility
Environmental Impact Assessment Report 2014
145 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
be monitored
Meteorology At the project
site
Wind speed,
direction,
temperature,
relative
humidity
rainfall
Hourly M/s USWL
(MoEF
recognized Lab)
Ambient Air
Quality
Within plant
and
surrounding
10km radial
zone.
PM10, PM2.5
SO2, NOx
Monthly M/s USWL
(MoEF
recognized Lab)
Water Quality Within the plant
and
surrounding
10km radial
zone Surface
Water As well
as Ground
Water
As per IS:
10500
Monthly M/s USWL
(MoEF
recognized Lab)
Noise Levels Within the plant
and
surrounding
10km radial
zone.
Noise levels Monthly M/s USWL
(MoEF
recognized Lab)
Soil quality Within the plant
and 10 km
radial zone
Soil
parameters
Monthly M/s USWL
(MoEF
recognized Lab)
Boilers & DG
sets
Individual Units Particulate
matter, SO2,
NOx
Monthly M/s USWL
(MoEF
recognized Lab)
Wastewater Inlet and outlet
of ETP Steam–
Generator
pH, TDS, COD,
SS and others .
pH, SS, Oil,
Monthly M/s USWL
(MoEF
recognized Lab)
Environmental Impact Assessment Report 2014
146 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Blow down
Cooling Tower
Grease, Cu,
Iron
Phosphates
5.7 Environmental Laboratory Equipment
The plant will have an in-house environmental laboratory for the online monitoring of air,
noise, water and soil. For all non-routine analysis, the plant may utilize the services of
external accredited laboratory facilities. The laboratory equipment required for
monitoring and analysis are given below:
Table-5.2 List of Equipment for the Environmental Laboratory
Name of the Equipment Nos.
Automatic Weather Station, which can record wind speed, wind
direction temperature, relative humidity, rainfall, Solar radiation
Sunshine
1
a) Online Automatic gaseous stack monitoring kit for SO2, NOx,
O2, Flue gas volume, Temperature etc. b) On line dust monitor
1
Fine Particulate Matter samplers with PM10& PM2.5 provision 5
Portable Flue Gas Combustion Analyser 1
Atomic Absorption Spectrophotometer 1
Mercury analyzer 1
Portable Noise level meter (Dosimeter) 2
Portable Waste Water Analysis Kit 1
BOD Incubator 1
COD Digester 2
Electronic Balance 1
Calorimeter 1
Conductivity Meter 2
Different micron sieves (set) 1 set
Dissolved Oxygen Meter – Brief case size 2
Electronic colony counter 1
Flask Shaker 1
Environmental Impact Assessment Report 2014
147 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Hot Air Oven 2
Laboratory Water Distillation and 147emineralization (DM) unit 2
5.9 Environmental Management Group
A separate environmental management group will be established to implement the
management plan. The group will be headed by a Superintending Engineer. The group
will ensure the suitability, adequacy and effectiveness of the Environment Management
Program. The management review process will ensure that the necessary information is
collected to allow management to carry out its evaluation. This review will be
documented. Functions of Environmental Management Group (EMG) at Site will be:-
Ø Obtaining consent order from State Pollution Control Board.
Ø Environmental monitoring.
Ø Analysis of environmental data, reports, preparations and transmission of report
to statutory authorities, Corporate Centre etc.
Ø Co-ordinate with statutory bodies, functional groups of the station, head office
etc.
Ø Interactions for evolving and implementation of modification programs to improve
the availability / efficiency of pollution control devices / systems.
Ø Environmental Appraisal (Internal) and Environmental Audit.
5.10 Expenditure and Environmental Measures
The budget for Environmental Protection Measures in Lakhs is given as under:-
The investment of Rs.70.50 crs/annum is earmarked for environmental monitoring plan
& auditing & Rs.14.95 crs for laboratory facilities.
Table 5.3: Budget provision for Environmental Management plan
S.
No.
ITEM Capital
Cost in Crs.
Recurring Cost per
Annum in Crs.
1 Air Pollution Control 15.00 6.00
2 Water Pollution Control 50.00 6.00
Environmental Impact Assessment Report 2014
148 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3 Noise Pollution Control 0.50 0.10
4 Environment Monitoring and
Management
1.00 0.10
5 Solid waste management 2.00 1.00
6 Occupational Health 0.50 0.05
7 Green Belt 1.00 0.05
8 Safety management. 0.50 0.05
9 Laboratory and chemicals -- 0.10
10 Salaries and wages of workers. -- 1.50
Total 70.50 14.95
* * * * *
Environmental Impact Assessment Report 2014
149 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER– 6
ADDITIONAL STUDIES
(RISK ASSESSMENT AND DISASTER
MANAGEMENT PLAN)
Environmental Impact Assessment Report 2014
150 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Risk Assessment
General Assessment:
The environment is at risk of exposure during transportation, storage, disposal, or
destruction of ethyl alcohol. In almost every scenario, the threat of environmental
exposure is contingent upon the proper handling of the chemical substance. Accidental
spills, large or small, can result in fire, explosion, and possible contamination of the
surrounding environmental mediums (water, soil, and air).
1. Introduction
The word 'disaster' is synonymous with 'emergency' as defined by the Ministry of
Environment and Forests (MoEF). An emergency occurring in the proposed
Enhancement plant is one that may affect several sections within it and/ or may cause
serious injuries, loss of lives, extensive damage to environment or property or serious
disruption outside the plant. It will require the best use of internal resources and the use
of outside resources to handle it effectively. It may happen usually as the result of a
malfunction of the normal operating procedures. It is imperative to conduct risk analysis
for all the projects where hazardous materials, fuels are handled.
The following have been addressed as part of the risk analysis.
ü Introduction
ü Hazard Identification and Risk Analysis
ü Risk Reducing Measures
The Introduction deals with the objective and methodology of carrying out the risk
analysis. Hazard Identification and Risk Analysis discusses about the various types of
hazards associated with the operation of the Plant due to process, storage & handling,
human errors, electric failures and natural calamities. It also presents the calculated
frequencies of occurrence of different accident scenarios for the identified potential
hazard occurrence in the proposed plant and the details of consequence modelling/
analysis for the identified potential accidents/disaster scenarios in the plant. Risk
Reducing Measures based on the calculated frequencies and consequences.
An industry with its complex nature of activities involving various plant machineries, raw
materials, products, operations, intermediates and environmental discharge has a
number of associated hazards. A minor failure can lead to major failure resulting into a
Environmental Impact Assessment Report 2014
151 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
disaster causing heavy losses to life, property and environmental. Risk assessment
studies are being conducted to ensure safety and reliability of any new plant, through a
systematic and scientific methods to identify possible failures and prevent their
occurrences before they actually cause disasters and production loss.
Accidents can occur in any industry despite of taking efforts to prevent them. The
suffering and damage as a result of the accident is determined by the potential for loss
surrounding the event, but by taking correct action at the time of the occurrence of the
incidence the full potential loss can largely avoided and effective action will be possible if
a pre-planned and practiced procedure for handling major emergencies utilizing the
combined resources of factory and the outside emergency services is in existence.
The best way of managing an emergency lies in its prevention it is recognized that in
spite of our best efforts to prevent emergencies by good engineering design and
construction, reliable safety system careful selection of personnel & training, audits and
inspections, use of state of art technology and sophisticated equipments etc. things can
still go wrong therefore it is essential to properly prepare, develop and update
emergency plans and rehearse them and be prepared for emergencies. The objective of
the emergency plan is to contain and control incidence to safe guard the employees and
any one nearby who might be affected and to minimize property loss & to protect the
environment.
2. Safety, Health & Environment Policy:
Safety Policy:
01. We believe that accidents are preventable and health hazards can be minimized by
Training and Retraining of the employees.
02. We will comply all the legislation & rules regarding Safety & Health.
Environmental Impact Assessment Report 2014
152 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
03. We are committed to provide safe machinery, equipment, methods & tools and to
continual improvement in Health and Environment (HSE) performance.
04. Our Policy is to maintain Safety beyond compromise.
05. We believe that rules are sacred and must be observed.
06. While on duty, we will concentrate on our job.
07. Care & Caution is our guide in the life.
08. Safety, Security & Punctuality keep us always happy.
09. Our Motto – No Accidents due to human failure.
10. Our employees are more valuable than anything and we expect the employees to
follow the HSE norms.
Environment Policy:
We shall –
1. Conduct our operation in an environment friendly manner and to comply with the
relevant regulation and prevent pollution.
2. Strive for continuous improvement in our environmental performance by setting
Environmental Impact Assessment Report 2014
153 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
challenging targets.
3. Conduct necessary programmes to enhance environmental awareness amongst
our employees and the general populace around plant and site.
4. Strive to conduct industrial and commercial operation in such a way that the
quality of the environment now and in the future is preserved.
5. Make wastes and effluents value added products in an environment friendly
manner.
6. Demonstrate our commitment through involvement of all employees for
achievement of environmental performance.
3. Identification of Hazards Sugar and Co generation Plant :
Sl.
No
.
Operatio
n /
Process /
Departme
nt
Hazards
Identification.
Precautionary measures taken.
Remark.
1 Cane
yard /
sugar
cane
milling
1) Movement of
trucks and tractors
in haphazard
manner may
cause accident.
1) For smooth movement of vehicles
route marking is done properly and
two-way traffic is arranged separately
for incoming and outgoing of cane and
controlled by adequate security staff.
Driving license & other legal
documents are checked strictly at
entry gate.
In case of
any
emergency
the units will
be tripped
immediately
by using
tripping
devices.
Environmental Impact Assessment Report 2014
154 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
2) The sugar cane
is lifted through
crane & there are
chance of cane
bundle being
dropped.
2) Safety Helmets and training is
provided to the workers working near
cane lifting area.
3) Collapse of
EOT crane due to
damaged wire
rope and improper
clamping
3) Cranes,wire ropes and lifting
tackles are tasted once in a year by
competent Authority and routine
preventive maintenance will carried
out.
4) Miss-operation
of cranes due to
defect in eyes of
crane operators
may cause of
accident.
4)Eye testing of cane operators will be
done periodically.
5) Unguarded
machinery
5) All rotating dangerous machines in
mill section are provided with
adequate guards.
6) Slippery floor 6) Floor washing is done regularly.
7) Flying of
Bagasse particles
7) Suitable face mask are provided
and flying of Bagasse will be
minimized at possible extent.
8) Electrical short
circuiting
8) Suitable fire extinguisher are kept
and loose electrical connections are
avoided.
Environmental Impact Assessment Report 2014
155 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
2 Clarificati
on
section
1) Leakage of So2
gas
1) All sulphur Burners and related
pipelines are tested properly during
off-season and necessary preventive
maintenance will be taken to avoid
any damage in season. Workers are
provided with necessary PPEs.
Safety
shower cum
Eye wash
fountain is
installed at
working
area.
2) Contact with
lime dust & milk of
Lime.
2) Workers are provided with
necessary PPEs.
Sufficient
ventilation is
provided.
3) Slippery floor 3) Leakage of juice and water will be
avoided.
4) Heat stress at
sulphur furnace
4) Necessary ventilation is provided
and workers are provided with
suitable PPEs.
3 Evaporati
on and
Pan
boiling
section.
1) Slippery floors
and walk ways.
As explained above.
Sufficient
free air flow
is
maintained
& air cooler
& pedestal
fans are
installed at
pan floor &
at
evaporator
section
2) Juice leakage
from valves.
3) Heat stress in
surrounding area.
4) Un-guarded
crystallizer units.
4 Centrifug
al section
1) Machine
operators are
exposing to
noise,vibration and
1) All operators are provided with
necessary PPEs
Environmental Impact Assessment Report 2014
156 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
heat stress.
2) Leakage of
steam,hot water
due to which
slippery floor
causes.
2) As explained above.
3) Unguarded
machineries.
3) All rotating dangerous machines
are well guarded and properly
covered with inter locking
arrangement.
4) All
centrifugal
machines
are tested
once in a
year from
competent
authority.
4) Collapse of
centrifugal
machines due to
imbalance of
basket & shaft.
4) During off-season and season
preventive maintenance will be
prepared for testing of shafts &
baskets.
5) Electrical short
circuiting.
5) As explained above.
Environmental Impact Assessment Report 2014
157 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
5 Sugar
drying
and
cooling /
packing
Godown.
1) Lot of dust,
noise and
vibration.
As explained above.
2) Fire hazards
due to loose wiring
/ defective
electrical
appliances.
As explained above.
3) Un-guarded
Hopper drives.
As explained above.
4) Back injury due
to improper
handling of bags.
Training to the workers regarding
safe handling of sugar bags.
5) Entanglement
of persons on the
moving conveyors.
Pull card system provided.
6) Slippage and
falling of bags in
sugar Godown.
The pyramid system of bag stacking
is followed
Proper ventilation will be provided. 7) Ventilation
6 Boiler
section.
1) Failure of
pressure parts &
explosion.
As sugar industry is a seasonal one
during off-season all the pressure
parts are tested for its thickness, and
if necessary replacement of tubes
and other pressure parts will be
carried out with the permission of
statutory bodies.
Boiler are
manufacture
d by reputed
manufacture
s registered
with
statutary
authorities
and repair
work if any
2) High Temp work
area.
Lagging of all high temperate lines
and steam lines to avoid heat
dissipation in working area.
Environmental Impact Assessment Report 2014
158 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3) Fire at Bagasse
yard.
Separate high pressure fire hydrant
line is provided.
will be
carried out
by IBR
approved
contractors.
7 Co-
generatio
n Plant (
Turbine &
Power
House)
1) Noise
Less noise equipment are selected
and regular preventive maintenance
to keep the noise level to minimum.
2) Fire
The sound proof control room panel
is provided and minimum numbers of
workers with minimum duration with
PPE's like ear plugs and Muffs.
Sand buckets and fire extinguisher
are provided and workers are
trained.
3) Shock
Operators are issued Shock
resistance rubber hand gloves &
safety shoes. Electrical grade rubber
Mat is also provided to all panel
board control room. Also chart is
displayed regarding First-aid if
person got electrical shock.
Environmental Impact Assessment Report 2014
159 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
8 Switch
Yard
1) Fire
In Switch Yard only hazard is Fire &
Electrical Shock. Suitable and
Sufficient Fire extinguishers are kept
near Transformer. Person’s are also
trained in fire extinguisher operation.
Total switch yard area is barricaded
to avoid unauthorized entry inside the
premises. Caution boards are also
displayed. Electrical grade rubber
mat is provided wherever necessary.
2) Electrical Shock
9 Diesel
Storage
tank.
1) Fire
We have storage of 130 KL of HSD
inside the factory for power house
use during emergency.
1) Suitable and sufficient fire
extinguisher are kept and person's
are trained.
2) Sand buckets are also provided
near HSD tanks.
2) Leakage of
HSD.
3) Suitable Dyke wall with proper
drainage arrangement is provided.
4) Permission / License is obtained
from legal authorities & it is get
Renewed time to time.
5) Storage area is completely
barricaded to avoid unauthorized
entry of person.
6) Smoking is strictly prohibited &
sign boards are also displayed.
7) Tanks are properly Earthed to
avoid static electricity.
8) Tanks is constructed as per
Environmental Impact Assessment Report 2014
160 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
applicable IS standards.
10 Molasses
Tanks
1) We have
storage of 34000
MT of molasses in
tanks. There is
source of ordinary
fire hazards;
Molasses when
stored for a long
time without being
turned over there
is likelihood of
spontaneous
combustion. No
flame or smoke
will be seen but
whole content
becomes solid
mode of ashes.
Hence it should
not be allow to be
stored for a long
time and it should
be always kept in
semisolid
condition.
External water cooling arrangement
is done so that during summer,
Molasses temperature will be kept
normal.
2) Spillage due to
failure of Tanks
overflow and
. Dyke walls are provided so that
spilled molasses will be collected in
that Dyke wall.
. Constructed as per applicable IS
Standard by the reputed fabricators.
Environmental Impact Assessment Report 2014
161 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
leakages. . Hydro static test is carried out
periodically during off-season and
any leakages found will be rectified.
Safety Precautions During Storage and Handling of Hazardous Material
Bagasse & Coal :
Bagasse & coal are the main sources of fire in sugar factory especially dried Bagasse is
highly combustible in nature. It catches fire automatically by way of spontaneous
combustion without external sources if it is stored for a long time. The fine bagasse will
accumulate in all workplace like electrical cables,steam pipes. If they are not cleared
periodically they will catch the fire and lead to big loss to industry. The bagasse and coal
will come under Class ' A ' fire which needs to be extinguished by water spray method
only. We propose to store coal in separate coal yard and separate fire hydrant system
will be made after storage of coal in coal yard.
Existing Control Measures at Bagasse Yard.
Bagasse yard is open area where large amount of bagasse being stored. At present we
are having two bagasse yard one is outside the factory premises & another one is inside
factory premises at boiler section.
1) At outside factory premises we are having storage capacity of 40000 MT of baled
bagasse.
a) We are having two fire hydrant 10HP pumps with 50 mt head connected to water
well.
b) Water is sprayed through hydrant points total 36 points with fire hose & fire
Environmental Impact Assessment Report 2014
162 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
hydrant valve.
c) In summer season one separate fire fighting team will be formed to keep
continuous watch and for spraying water near bagasse stack so that surrounding
area is kept cool.
d) Round the clock security is working to avoid unauthorized entry inside premises.
e) Smoking is strictly prohibited & sign boards are also displayed.
f) Water well is connected to both river water & bore well water.
g) Lighting arrestors are also provided to protect against Lighting.
h) Telephone arrangement is made during emergency. Telephone no 407
i) Security persons are with full fledged communication system.
2) In boiler area also where small amount of bagasse is being stored, we are having two
Separated fire hydrant line covering entire bagasse yard & belt conveyors. One line is
having 6 hydrant points connected to delivery of +ve section of four pumps having
capacity 45 lit / sec pressure 5 kg/cm2 & head of 50mtr. Another high pressure fire
hydrant pump line is having 14 hydrant points connected to pump of 7 kg pressure.
Discharge 2000LPM & head 70 mtrs with + ve section. Both pumps are connected to
water reservoir of capacity 5 Lakh Lit used for both fire fighting and process & water is
supplied to reservoir directly from river water through high pressure pumps. Also we are
having DG set to run the pumps during power failure. Same precautionary measure
taken as at out side bagasse yard area.
Environmental Impact Assessment Report 2014
163 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Health Hazard:
Bagasse is very hazardous especially dried & fine bagasse for health of the workers
working there. Due to prolonged inhalation of fine bagasse a disease may occur i.e
Bagassosis. Hence due attention must be given to health of the workers.
Measures:
1) Suitable face masks & goggles will be provided to workers working in that place,
strict use will be enforced.
2) Periodical medical checkup of workers will be done & health records will be
maintained.
Sulphur storage & preparation of SO2 gas:
Sulphur will be used in our industry for the manufacture of SO2 gas. The oxygen present
in the air reacts with sulphur & SO2 is formed. This gas is used for clarification of juice &
syrup.
Hazards of SO2 Gas:
So2 is one of the most widely encountered contaminants in the workplace.So2 is an
irritant gas. It may enter the body through the respiratory tract and cause respiratory
problems. In sugar industry So2 poisoning will be of chronic in nature. The substance
has local irritant action & produces a sensation of burning & pain in nose & throat.
Environmental Impact Assessment Report 2014
164 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Safety & Health Measures:
1) Sufficient ventilation is maintained in this work.
2) Workers are provided with gas mask to prevent inhalation of So2 gas.
3) Safety shoes, goggles, hand gloves & aprons are provided to the workers to
protect from the heat & fire.
4) Periodical medical checkup of the workers will be done and health records will be
maintained.
5) Smoking & eatables will be strictly avoided in that area.
6) Safe operating procedures will be displayed.
7) Eye wash fountain is installed at work area.
Hazards in Sulphur Storage:
Sulphur is highly combustible material. It comes under class ' A ' fire. we are having
200mt of sulphur storage in godown.
Measures taken:
1) Full fledged fire hydrant system will be provided.
2) Suitable fire extinguishers are kept in godowns.
3) Smoking is strictly prohibited.
4) Godown is kept with locking arrangement.
5) Suitable PPE's (Personal Protective Equipment) are provided those handling sulphur.
6) Adequate ventilation and natural lighting is provided.
7) Cautionary boards are displayed.
Environmental Impact Assessment Report 2014
165 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
HCL Storage:
We are having storage capacity of 30 MT for boiler make up water treatment & HCL is
required is stored in FRP storage tanks. The only hazard in this area is release toxic
vapor.
The following remedial measures are taken.
1) Storage of HCL in FRP tanks, which will be located in the area free from all
ignition sources.
2) Sufficient water is provided during emergency.
3) All vents are taken to open area where there is no danger to workers.
4) People working in this area will be fully trained during emergency.
5) Handling of HCL is totally by mechanical system. So that there should be no
spillage all joints are leak proof.
6) Cautionary notices & instructions will be displayed.
7) Smoking & eatables are strictly avoided in this area.
8) Dyke wall is provided to storage tank.
9) Eye wash fountain is provided at working area.
H2So4 STORAGE:
We are storing H2so4 at D.M.Plant for water treatment purpose.H2so4 is stored in
carboys and kept in a separate room and carboys are kept on sand. Total storage
capacity 5MT.
Measures will be taken:
1) H2so4 is highly corrosive chemical and it is kept in separate room.
2) Sufficient ventilation is provided.
3) Cautionary boards are displayed.
Environmental Impact Assessment Report 2014
166 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4) All required PPE's are provided for handling H2so4.
5) Eye wash fountain is provided near D. M. plant area.
6) Safe operating procedures are displayed.
Sugar Godowns:
Since sugar is combustible material due importance is to be given for fire safety in sugar
storage godown. Sugar is packed in gunny bags and PP bags and stored in sugar
godown. We are having 19 sugar godowns of storing capacity 15 lakhs of sugar bags.
Falling of sugar bag bunches on workers is a major concern. Hence due importance is
given while stacking of sugar bags so that there is no slippage of bags from stack.
Precautionary Measures:
1) Suitable fire extinguishers are kept in sugar godown.
2) Smoking is strictly prohibited.
3) All electrical arrangement is flame proof.
4) Sufficient ventilation will be provided to godowns.
5) Sugar is stacked properly to avoid slippage of bags.
6) Sugar bags are stacked in pyramid shape. Only well experienced contractor is
engaged in sugar bag stacking work.
7) Training is given to concerned workers regarding safety precautions to be taken
while handling of sugar bags in sugar godowns.
Noise & hazards & control measures.
Noise is one of most common health hazards found in the work place. Exposure to
excessive noise can cause noise induced hearing loss. In Sugar Industry high level
noise areas are
1) Generator room.
2) Turbine house.
3) Boiler house.
Environmental Impact Assessment Report 2014
167 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4) Centrifugal Machines.
5) Noise due to steam leakages.
6) Compressor room.
Noise control measures are divided into the following categories:
1) Elimination
2) Substitution
3) Isolation
4) Engineering control at source and in transmission path.
5) Personal Protection Equipments.
All above methods will be tried to reduce the noise level in the factory and ensured that
there will be no bad effects noise in the work place.
In addition to this following steps will be taken-
1) Suitable Personal Protective Equipments are provided for workers expose to
noise like Ear plugs,Ear Muffs etc.
2) Acoustic measures will be provided wherever necessary.
3) Periodical medical checkup of workers is being done and necessary action will be
taken.
4) Noise aspects are taken care in the design process of the plant.
5) Noise level departments layout is designed in such way that noise will not effect
other departments.
6) Noise level is measured periodically and if exceeds prescribed normal then
necessary action will be taken.
7) Training and Education of workers.
Safety Precautions while Operating ESP (Electrostatic Precipitator)
Environmental Impact Assessment Report 2014
168 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
We have installed two numbers ESP for 80T & 70T Krupp boilers for controlling
environment pollution. The only hazard present is Fire & Explosion.
Causes:
1) Unburnt % in fly ash
2) Prolong accumulation / storage of fly ash.
3) Air ingress
4) Excess Carbon Monoxide generation during upset conditions
Control Measures:
1) Control over combustion
2) Periodic checking of ash
3) In order to ensure the air tightness each of the by-pass chute opening should
have air tight blanks. The blank will be allowed to open only after I D fan stops.
4) Carbon Monoxide monitoring kit to be installed at upstream and well ahead of
ESP.
5) Fix a carbon monoxide monitor well upstream of ESP- with a tripping logic for all
T/R sets while carbon monoxide set point goes above the set point.
6) Main equipment (boiler) operation should be efficient so that proper combustion
happen and reducing the risk of carbon monoxide generation.
7) The ESP should be maintained properly for all tightness so that ambient air
ingress can be controlled within permissible limit. Regular checking door
gasket will reduces the chances of such air ingress by 85%.
Do's & Don’t of ESP operation of boiler:
Many of times ESP cannot be commissioned at boiler because of low temperature
interlock, which is associated to lower boiler load. in that situation you cannot start up T /
R sets because of low temperature interlock, but you need to run all ESP auxiliaries at
Environmental Impact Assessment Report 2014
169 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
all the time including the ash handling system and the bypass chute remains closed at
all time please note that during start up the chances of accident are more due to process
instability & high carryover of unburnt. For more details of operation and safety
measures please refer operation and maintenance manual given by the manufacture
and kept at boiler section.
Identification of Hazards in Distillery Plant:
Sl
.
N
o
Operation
/ Process /
Departmen
t
Hazards
Identification.
Precautionary measures
taken.
Remark.
1 Fermentati
on section
1) Fire
2) Fermentation
1.All electrical appliances are
flame proof like motors,lighting
etc,.
2.Suitable fire extinguisher are
kept in section
3.Smoking and using of mobile
is strictly prohibited.
4) Unauthorized person's entry
is restricted.
5) No smoking boards are
displayed.
7) Full fledged fire hydrant
system is provided to cover the
entire area.
1. Adequate ventilation is
In case of any
emergency
the units will
be tripped
immediately
by using
tripping
devices.
Environmental Impact Assessment Report 2014
170 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
odour
3) Slippery floor
4)Un- guarded
machinery
5) Noise
6)Leakage of
fermentation wash
provided.
2.Workers are provide suitable
PPE
3. Good housekeeping is
maintained.
1. All pumps, pipelines, are well
maintained. And are checked
periodically to avoid leakages.
2. Necessary gutters are
provided to avoid overflow.
3. Floor washing is done in every
shift.
All rotating dangerous
machineries in this section's are
provided with adequate guards.
Workers are provided with
suitable PPE's.
1. Suitable dye wall will be
provided. So that spilled
fermented wash will be collected
in dye wall.
2. All tanks are constructed as
per IS standard by the reputed
Safety shower
cum Eye wash
fountain is
Environmental Impact Assessment Report 2014
171 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
7) Static electricity
fabricators.
3. Every year thickness testing
will be done & necessary action
will be taken. Proper earthing is
provided to all tanks, to avoid
static electricity Hazards.
installed at
working area.
Sl
.
N
o
Operation
/ Process /
Departmen
t
Hazards
Identification.
Precautionary measures
taken.
Remark.
2 Distillation
section
1) Fire
2) Noise
3)Leakage of
Distillation
As explained above.
3 Ware
House
1) Fire
2) Leakage of
Denatured spirit.
As explained above.
Environmental Impact Assessment Report 2014
172 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3) Static electricity
4) Loading
/unloading of spirit.
1. Proper earthing is done to
vehicles & tans before filling.
2.Proper checking of pipeline
tanks and pumps
3. Before transfer, take
approval from Electrician &
using flame proof pump, tube
light, No naked light, No
smoking zone.
4. Keeping fire extinguisher,
water line ready at ware
house.
4 R.S./ N.S.
ware
house
1) Fire
2) Leakage of
Rectified spirit.
3) Leakage of
Neutral spirit.
4) Static electricity
5) Slippery floor
As explained above.
Environmental Impact Assessment Report 2014
173 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
5 Ethanol
ware
house
1) Fire
2) Leakage of
Ethanol
3) Static electricity
4) Slippery floor
As explained above.
Sl.
No
Operation /
Process /
Department
Hazards Identification.
Precautionary measures taken.
Remark.
6 Cask ware
house
1) Fire
2) Leakage of Malted
spirit.
As explained above.
Environmental Impact Assessment Report 2014
174 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
3) Static electricity
4) Slippery floor
7 IML Section/
Bottling ware
house.
1)Fire hazards due to
loose wiring / defective
electrical appliances.
2)Back injury due to
improper handling of box.
3)Entanglement of
persons on the moving
conveyors.
4) Ventilation
5)Flying/strucking of
glass pieces due to
broken bottles.
6)Leakage of blending
vat
Routine preventive maintenance will
be carried out.
Suitable fire extinguisher are kept
and loose electrical connections are
avoided.
Training to the workers regarding
safe handling of box.
Pull card system& Emergency
switches are provided.
Proper ventilation will be provided.
Workers are provided with safety
goggle,hand gloves & gumboots for
handling bottles.
As Explained above
Environmental Impact Assessment Report 2014
175 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
8 Packed
liquor ware
house
1) Fire
2)Leakage of alcohol
As Explained above
4. Risk Involved Through Risk Analysis.
1) Fire & explosion.
2) Electrical Shock.
3) Bursting of boiler.
4) Electrical short circuiting.
5) Collapse of tall structures.
6) Failure of machinery.
7) Leakage of Hazardous / toxic materials like Co2 gas
5. Severity / severity mapping:
If any emergency occur, the severity of the incident will be within factory premises & not
outside the premises at any cost.
6. Identification of emergency in each hazard activity:
It is already defined in this on site emergency plan in heading “ Identification of hazards
in sugar & cogen plant.”
7. Mitigation measures required:
It is already defined in this on site emergency plan in heading “ Identification of hazards
in sugar & co-generation plant.”
8. Mitigation measures possessed by industry:
Environmental Impact Assessment Report 2014
176 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
We are having following mitigation measures in our industry.
1) Full fledged fire fighter of capacity 4500 lit & additional Foam tank of 500lit
Capacity.
2) Fire hydrant system at bagasse yard, belt conveyors, Entire distillery & IML
section.
3) Suitable PPE's like safety shoes, helmet, goggles, mask.
4) We are having separate Ambulance facility round the clock.
5) Emergency siren.
6) Emergency organization.
7) Well trained fire fighters & first aider.
8) Full fledged occupational health centre.
9. Identification of Mutual aid partners:
We have not defined any mutual aid partners; we have sufficient resources at our own to
mitigate the emergency. if at all required we will call nearest Fire stations like Athani,
Chikkodi etc.
10. Identification of resource suppliers:
We have not identified the resources suppliers. We are having our own.
11. Alert Action plan (Action on site):
1. The effective handling of an emergency will depend on the decision and
action taken at the time, based on the situation and seriousness of the
incident. Each and every incident cannot be foreseen and hence it is not
practicable to include every action which may be required to be taken in a
given situation, however certain actions which are of general nature must be
considered in the emergency management plan. Hence suitable guidelines for
all major foreseeable incidences must be included in the emergency
management plan.
Environmental Impact Assessment Report 2014
177 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
2. Incident controller shall initiate all such actions as essential on the shop floor.
3. Evacuate all the personal on the shop floor not required for controlling the
situation or hazard.
4. Shall immediately grasp the problem / hazard and shall give instructions to
the concerned teams to act in a manner required to control the situation.
5. In case of fire, shall ring up the fire force.
6. Simultaneously shall call the workman in the fire fighting procedures and
organize controlling / extinguishing the fire.
7. With the view to ensure that declarer / controller of emergency shall have
assistance from the teams former.
12. Control room :
The security office shall function as the control room since security office is ideally
situated nearer to the main gate and away from the plant there shall be no problem with
regard to vapor / smoke of any toxic substances affecting security office. However,
should there be a situation where/ when entire premises have to be declared as
emergency the control room shall operate from the FSS office which is outside the main
gate. Required communication facility like walky talkies, mobiles & telephone facility is
provided. Required resources like PPE's, fire extinguishers, firefighting equipments like
fire hose, valves are kept in security office. Important telephone numbers list is displayed
at control room.
13. Site Plan:
Site plan is enclosed.
14. MSDS:
Major chemical MSDS are enclosed.
15. List of Important Telephone Numbers:
Environmental Impact Assessment Report 2014
178 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Fire fighter 265 / 273
Ambulance 265 / 273
Telephone operator 09
Hospital / Medical Officer 277
Chief engineer 250
Manager Administration 205
Safety officer 434
Security 267
Distillery I / c 261
Shift engineer / chemist
Boiler Engineer
268
423
16. ON SITE EMERGENCY STRUCTURE:
Sl.
No.
Designation Personnel Responsible Scope of responsibilities
1. INCIDENT
CONTROLLER
(In charge of the
scene of the
incident)
CHIEF ENINGEER will be
the incident controller
during the general shift and
whenever present in the
works.
1) As soon as he has been
made aware of an
incidence, the incident
controller should decide
whether a major
emergency exists or is
likely. If so he should
Environmental Impact Assessment Report 2014
179 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
SECURITY OFFICER
/SECURITY WATCHMAN.
will be the incident
controller during all 24 hrs &
holidays also.
immediately activate the
onsite emergency plan
2) He should assume duties
of the site main controller
pending the latter’s arrival,
in particular to:
1. Ensure the emergency
services have been
called.
2. Direct the shutting
down and evacuation
of the areas likely to be
affected.
3. Ensure the key
personal have been
summoned
3) His main function,
however, is to direct all
operations at scene of the
incident as follows.
Ø Rescue and fire
fighting operations
until the arrival of fire
brigade.
Ø Search for casualties
Ø Evacuation of non-
essential workers to
assembly areas.
Ø Set up a
communications point
with telephone or in
case of failure of
telephone
communication use
Environmental Impact Assessment Report 2014
180 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
walky-talky messenger
contact with the
emergency control
center.
Ø Give advice and
information as
requested to the
emergency services.
Sl.
No.
Designation Personnel Responsible Scope of responsibilities
2. SITE MAIN
CONTROLLER
Managing Director: Will be
site main controller during
general shift.
SECURITY OFFICER/
WATCHMAN SECURITY:
Will be site main controller
during all 24 hrs & holidays
also.
Ø The Site main
controller should go to
the emergency control
center and take charge
from the incident
controller for over all
control
Ø If he decides that a
major emergency
exists or is likely, he
should ensure that the
emergency services
have been called and
the on site plan is
activated.
Ø He shall take over the
situation and shall start
in such a manner as to
control the situation
and curb it as soon as
possible.
Ø Control the traffic
Environmental Impact Assessment Report 2014
181 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
movement within the
works.
Ø Issue authorized
statements to the news
media.
Ø Control rehabilitation of
affected areas after
emergency.
Ø Ensure that proper
consideration is given
to the preservation of
evidence.
Emergency organization:
Communication Team
Team A Team B Team C
Team D
SITE MAIN CONTROLLER – Managing Director
INCIDENT CONTROLLER – CHIEF ENGINEER
Environmental Impact Assessment Report 2014
182 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Communication Team:
1) Manager (Administration)
2) Security officer
3) Shift Telephone Operator
4) Head Timekeeper
Team A
1) Shift Engineer/Boiler Engineer
2) Shift Chemist
3) Electrical Engineer.
4) Fire fighting team
1) Shri R.T.Patil
2) Shri M.G.Mataguli
3) Shri L.S.Ganennavar
4) Shri D.V.Gharge
5) Shri C.S.Khurd
6) Shri B.H.Jagli
7) Shri M.R.Hukkeri
8) Shri R.T. Visapure
9) Shri A.L.Mallewade
Team B
1) Chief Chemist
2) Workshop I/c
3) Dy. Manager (P)
4) Timekeeper
5) Distillery & IML Incharge.
Team C
1) Factory Manager
Environmental Impact Assessment Report 2014
183 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
2) Safety Officer
3) Medical Officer
4) Environment Engineer
5) Motor Department I/c
Team D
Personnel’s which are not included in emergency action team.
Role of communication team:
Manager (Administration)
Ø Proceed to control center and take orders from main site controller.
Ø Arrange mutual aid/fire brigades as requested by main site controller.
Ø Inform police if advised by main site controller.
Ø Inform neighbouring factories.
Ø Requisition vehicles and ambulance as required.
Security Officer/Watchman
After getting information activate the siren.
Control Traffic at the gate.
Arrange a guard at gate to inform incoming essential personal of the nature of
emergency.
Prevent unauthorized entry.
Depute guard to control traffic and block roads at the scene of emergency.
Inform about location of emergency to mutual aid / city fire brigade.
Assemble all the victims at assembly point.
Telephone operator.
On receipt of information in case of siren is not yet actuated, inform security personal to
blow siren.
Inform security so that guards are released to control traffic around the emergency-
visitors are kept out.
Await further instructions from site main controller and keep telephone free from
incoming calls.
Inform others as directed by site main controller.
Environmental Impact Assessment Report 2014
184 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
ROLE OF ACTION TEAM A:
Inform site main controller / telephone operator of location and nature of emergency.
Switch off electrical supply.
Alert every occupant to leave the area to reach the assembly point safely.
Simultaneously trained employees to start fire fighting and rescue operation
Follow instruction of incident controller / site main controller.
Ensure that fire hydrant systems / pumps are in good condition.
Provide engineering assistance to incident controller/ site main controller.
Proceed to scene of emergency.
Consult area supervisor regarding special precautions if any.
Decide line of action in consultation with incident controller/ site main controller.
Keep stock e.g. water, personal protective equipments.
ROLE OF ACTION TEAM B:
Ensure that fire pumps are operating normally.
Shut off power.
Shut down the plant in consultation with incident controller/ site controller.
Evacuate to assembly points in a single line by the safest route without panic
Stand in lines assembly point for ease of head count.
Section in charge has to take head count and locate missing persons if any.
Follow instruction from incident controller/ site main controller.
Get back to your work place (if safe) and when all clear signal is received from site main
controller.
ROLE OF ACTION TEAM C:
Safety/Environment Officer.
Approach the site of incidence immediately
Be in contact with incidence controller/ site main controller.
Coordinate between incidence controller/ site main controller and other key personal.
Check evacuation and head count is done properly at assembly point near the affected
area.
Follow instructions from main site controller.
Environmental Impact Assessment Report 2014
185 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Notify evacuation squad if required.
Medical Officer
Keep ambulance ready to proceed to scene of emergency at short notice.
Priorities casualties for treatment.
Considered casualties for special treatment.
Arrange hospitalization, additional ambulances.
Call trained first aid members for assistance.
M.T.D. In charge
Arrange transport as required.
Arrange driver for ambulance.
Requisition vehicles, drivers as necessary for evacuation.
First aid team:
1) Shri D V Patil
2) Shri D.D.Datar
3) Shri P.A.Herawade
4) Shri M.B.Kumbhar
5) Shri R.Y.Shirgannavar
6) Shri S.B.Patil
8) Shri R.B.Vasawade
9) Shri R.M.Billur
10) Shri N.P.Savant
Proceed to affected area / medical center as requested and render all assistance.
ROLE OF ACTION TEAM D:
Leave the site immediately by the safest route to assembling point.
Assist in head count at assembly point.
Avoid panic.
Do not go to scene of emergency unless specifically instructed by site main controller
Do not re enter site unless directed personally or announced.
17. Types of emergencies considered:
Environmental Impact Assessment Report 2014
186 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
A major Emergency or disaster occurring at works is the one that may affect several
departments within works and may cause serious injuries, loss of life, extensive damage
to property or serious disruption outside the works. Usually a major emergency is the
result of malfunctioning or bypassing of inbuilt safety devices and systems. Deviation
from the normal operating procedure. Emergency disasters could be due to natural
causes or manmade causes they include.
1) Fire and explosion
2) Bursting of Boiler
3) Leakage/Spillage of Effluent/molasses/chemicals ( Spent wash/ Effluent)/
chemicals/spirit/flammable materials/Alcohol ( Spent wash/ Effluent)
4) Malfunctioning of E.T.P
5) Plane crash over the works
6) War (affecting works e.g. Bombing over the works)
7) Over flow of E.T.P (Discharge Pumps failure)
8) Toxic releases like Methane & Co2 gas
18. Objectives:
The main objective of the emergency plan should be to make optimum use of all
available resources both internal and external to achieve the followings.
Ø Contain the extent of emergency and cascading effects of the original
emergency and bring the incident under control with priority to saving life and
preventing further injury.
Ø Controlling the original incident and prevent an onsite emergency from turning
in to an offsite emergency report.
Ø Mitigate the consequences of the emergency by arranging rescue and
treatment casualties.
Ø Safe guard over the people.
Ø Minimize the damage to environment property.
Ø Identify any fatalities and notify the relatives.
Ø Provide for the need of relatives.
Ø Secure the safe rehabilitation of affected areas.
Provide authentic and authoritative information to the news media through the
Environmental Impact Assessment Report 2014
187 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Companies authorized person.
19. Safe Assembly Points and Emergency Exits:
We have marketed and identified assembly points at following Work places where
nearby workers can gather safely during emergency.
1) Main gate.
2) In front of distillery section.
3) In front of civil department.
4) Sugar cooling tower (i.e. In front of Godown No.7)
5) Co generation Cooling tower.
6) Co generation ash bed area.
7) M.T.D. Front area.
Also we have marked and identified section wise emergency exits and gangways and
shown in annex II. We have trained all workers in respect of above points.
20. Notification of Emergency/Duties of employee during emergency:
1) If the employee notices the symptoms of fire, leakage of chemical or any other
unusual occurrences he has to inform the Security Department through
Telephone No 273 and Safety Department Telephone No 434, Electrical
Department Telephone No 256, Workshop Incharge Telephone No 259, If the
telephone is out of order send a special messenger to the Security Department.
Also he has to specify the exact location and cause for the first inform the shift
Incharge who is at all times on the shop floor shall identify the same, he shall
report to the chief engineer.
2) Use the suitable fire extinguisher available in the department if there is leakage of
chemicals do not allow anybody to touch or smoke nearby and flush with water
and in case of electrical short circuit use appropriate fire extinguisher don’t use
water in case of electric short circuit.
3) If the fire seems to be uncontrollable call fire brigade/fire fighting team & also
inform them exact location & causes of fire so that they will come with right type
of fire extinguishers.
Environmental Impact Assessment Report 2014
188 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4) Immediately arrange for removing the combustibles nearby.
5) Cool the surrounding area with the help of fire hydrant water.
6) Fire fighting operations or approach should be from the opposite direction of
smoke.
7) In case anybody trapped must wear breathing apparatus before enter into the
smoke for rescue.
8) Clear the public gathering.
Security Department:
a) Order the fire crew to reach the spot at shortest possible time.
b) Arrange to start the fire hydrant pump.
c) Barricade the area.
d) Instruct the main gate person to keep open the gate full for fire brigade entry.
e) Instruct one security guard to come along with the fire brigade from the gate to
avoid searching the spot.
f) Arrange to remove the nearby fire prone wastes.
Safety Department:
a) Visit the spot immediately has quick check over the spot for explosives
combustible Materials etc.
b) Arrange for switching off the electrical mains pertaining to that area.
c) If the area is covered with dense smoke, see that the people must wear
respirators.
d) If anybody falls down on the ground because of the suffocation arrange for the
medical treatment.
21. Declaration of Emergency:
Under this plan the Chief Engineer is identified and nominated as the
DECLARER/CONTROLLER OF EMERGENCY. No sooner he gets information from
shift in-charge ,he shall move to the place of hazard/calamity & he shall assess the
situation & decide to declare emergency either in particular section or in the entire plant.
If the Emergency is to be declared in one section the other plant will work normally.
Environmental Impact Assessment Report 2014
189 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
He shall start functioning in such a manner as to control the situation & curb it as soon
as possible. Only the site main controller should declare the end of emergency and such
declaration should be made only after his fully satisfied the following things.
· All fires have been extinguished.
· There is no risk of re-ignition.
· Source of emission of hazardous gas has been effectively isolated.
· All gas clouds have been disposed and
· No toxic contamination exists.
· After considering all these aspects and satisfying him that the site is safe to
enter the emergency reader may order entry to restore the normalcy. he shall
then arrange for blowing the siren three times which indicates an all clear
signal.
22. Warning system:
· One electrical operated hooter siren & steam blown siren installed on the top
roof of the Factory. It can be heard throughout the factory premises and
nearby outside area also. The siren will be blown to indicate the emergency.
· Internal telephones & Walky –Talkies and Mobiles are available from all
places to inform emergency at a time at any time.
· On getting the warning all those should act as per the role mentioned in the
action team.
23. Emergency Shutdown of Various Sections:
The only hazards i.e. expected in the factory are fire: immediate action to be taken in
each of the sections for the purpose of emergency shutdown would be as under.
1) MILL SECTION
Stop D.C. Drives.
Environmental Impact Assessment Report 2014
190 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
2) BOILER SECTION
Stop the Boiler.
3) CLARIFICATION SECTION
Switch of the pumps & steam Valves.
4) BOILING HOUSE & PAN SECTION:
Switch of the Machines, Valves & pumps.
5) Turbine House.
Stop the Turbines.
At Distillery / IML Section
1) CUT OF MAINS SUPPLY
2) DISTILLERY SECTION
Stop all distillations.
3) BOILER SECTION
Stop the Boilers.
4) BOTTLE FILLING SECTION:
Environmental Impact Assessment Report 2014
191 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Switch off the filling lines and stop filling.
5) PACKING SECTION:
Stop packing.
6) STOP ETHNOL PROCESS.
24. Evacuation of Personnel:
Siren will blown within short note many times in addition to the shouting for evacuation
and security staff] runs to each department to drive out the person safe place. When a
major accident occurs and if there is case of workmen has supervisory personnel
fainting or losing consciousness any other type of accident, it shall be the responsibility
of Team-B to evacuate them in the vehicle to our dispensary after providing necessary
First Aid in the office. The well laid out roads in around the plant in factory premises and
they should choose the safest road to come out from the plant.
25. Accounting of personal:
Accounting of personnel will be done at each assembly point by timekeeper & section
Incharge. Total strength will be tallied with actual attendance at timekeeper office. If
anybody is missing immediately inform to any one of emergency team for necessary
action. When persons engaged in the department or in emergency the section in
charges are responsible to bring out the employee to safe place and make arrangement
for their medical treatment, department head also visits the site of emergency to ensure
that nobody has been trapped. The persons who have trained in the First Aid and
Firefighting also quick check up for ensuring that nobody has been trapped. It shall be
the responsibility of Team B to immediately take stock of the personnel on duty and
Environmental Impact Assessment Report 2014
192 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
cross check with the personnel who have come out of the plant / have got stuck-up. This
team shall co-ordinates with team D and ensure that all personnel are accounted for. It is
also essential for team ' B ' to counter check with the security if any visitors or transport
workers have entered the plant and if so they should also be accounted for.
26. Controlling of Emergency:
The declarer / controller of emergency shall take steps to train all the teams & shall draw
up an action plan forthwith. The maintenance in charge is marked as Work incident
controller and he shall act as the Incharge at the site of the hazard to control the entire
operations.
27. Arrangements for medical treatment:
We have full fledged own occupational health center with all facilities & required staff to
treat injured during emergency & also we will shift the injured persons to nearby
hospitals & if higher treatment is required we can arrange to shift the injured persons to
Miraj city hospital which we have close contact.
28. Information to the relatives of injured:
Chief engineer & Dy. Manager (Personal) will inform the relatives of injured through
phone & messengers.
29. Information to the government authorities:
Environmental Impact Assessment Report 2014
193 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Manager (A& P), CE & Dy. Manager (Personal) will communicate govt. authorities
regarding emergency occurred and status.
30. Law and Order:
We have close contact with the Kagwad Police station to meet our emergency
requirement.
The Dy. Director of Factories & Director of Factories, Member secretary and State
Pollution Control Board, shall also be informed.
31. All Clear Signals:
Once the emergency is controlled and normalcy regained completely and the
DECLARER / CONTROLLER OF EMERGENCY is of the opinion that there is no further
hazard involved there and the work can go on normally, he shall then arrange for
blowing the siren three times which indicates an all clear signal.
32. Emergency Transport Facility:
We have sufficient vehicles to transport injured persons. We are having separate motor
department of our own & they have the facility to control the situation also we have one
full fledged ambulance ready round the clock.
33. Drawing of fire hydrant and Extinguishers:
Details are enclosed in (Annexure II & III) & location of fire extinguishers is given below
Location wise Fire Extinguisher Details
Sr.
No.
Location Type Capacity Qty.
1 Sulphur House CO2 4.5 kg. 2 Nos.
2 -do- D.C.P. 10 kg. 1 No.
3 Boiling House CO2 4.5 kg. 2 Nos.
Environmental Impact Assessment Report 2014
194 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
4 -do- D.C.P. 10 kg. 1 No.
5 Sugar House CO2 4.5 kg. 2 Nos.
6 -do- D.C.P. 10 kg. 1 No.
7 Shift In-charge Cabin. CO2 4.5 kg. 2 Nos.
8 -do- D.C.P. 10 kg. 2 Nos.
9 Mill Turbine CO2 4.5 kg. 2 Nos.
10 -do- D.C.P. 10 kg. 1 No.
11 -do- CO2 22.5 kg. 1 No.
12 Workshop CO2 4.5 kg. 1 No.
13 -do- D.C.P. 10 kg. 2 Nos.
14 Store Water type
CO2
9 Ltr. 3 Nos.
15 Civil CO2 4.5 kg. 1 No.
16 -do- D.C.P. 10 kg. 1 No.
17 Main Gate CO2 4.5 kg. 2 Nos.
18 -do- D.C.P. 10 kg. 1 No.
19 Weighbridge CO2 4.5 kg. 1 No.
20 -do- D.C.P. 10 kg. 1 No
21 Material Godown Water type
CO2
9 Ltr. 1 No.
22 Sulphur Godown Water type
CO2
9 Ltr. 3 Nos.
23 M.T.D. CO2 4.5 kg. 1 No.
Environmental Impact Assessment Report 2014
195 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
24 -do- D.C.P. 10 kg. 1 No.
25 Sugar Godown Water type
CO2
9 Ltr. 2 Nos.
26 Belt Conveyor CO2 4.5 kg. 1 No.
27 -do- D.C.P. 10 kg. 1 No.
28 Diesel Tank Foam type 9 Ltr. 5 Nos.
29 Switch yard D.C.P. 22 kg. 2 Nos.
30 -do- CO2 22.5 kg. 1 No.
31 Cogen Cooling Tower CO2 9 Ltr. 1 No.
32 Back TFR D.C.P. 22 kg. 1 No.
33 Triveni Turbine down side. CO2 22.5 kg. 2 Nos.
34 Centrifugal CO2 22.5 kg. 1 No.
35 80 T. Boiler CO2 22.5 kg. 1 No.
36 TFR D.C.P. 22.5 kg. 2 Nos.
37 33x66 Mill TFR CO2 22.5 kg. 2 Ns.
38 42x84 Mill TFR CO2 22.5 kg. 1 No.
39 42x84 Mill CO2 22.5 kg. 1 No.
40 D.C. Drive D.C.P. 10 kg. 1 No.
41 Power House CO2 4.5 kgs. 2 Nos.
42 -do- D.C.P. 10 kg. 1 No.
43 Paras Boiler CO2 4.5 kg. 1 No.
44 -do- D.C.P. 10 kg. 1 No.
45 70 T. Boiler D.C.P. 10 kg. 1 No.
Environmental Impact Assessment Report 2014
196 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
46 Boiler Compressor CO2 4.5 kg. 1 No.
47 Paras Boiler I.D. CO2 4.5 kg. 1 No.
48 70 T. Boiler I.D. CO2 4.5 kg. 1 No.
49 Cogen. TFR CO2 22.5 kg. 1 No.
50 Cogen. Turbine CO2 4.5 kg. 1 No.
51 -do- D.C.P. 22.5 kg. 5 Nos
At Distillery & IML Section:
Location wise Fire Extinguisher Details
Sr.
No.
Location Type Capacity Qty.
1 Distillery (old) D.C.P. 10 kg. 1 No.
2 Distillery (old) D.C.P. 5 kg. 1 No.
3 Distillery (old) Main Panel
Board. D.C.P. 4.5 kg. 1 No.
4 Distillery (old) Pump House D.C.P. 5 kg. 1 No.
5 Distillery (old) D.N.S.
Warehouse D.C.P. 5 kg. 1 No.
6 Praj Distillery Panel Board CO2 4.5 kg. 2 Nos.
7 Praj Distillery warehouse Water type 9 Ltr. 1 No.
8 Distillery Column No. 2 D.C.P. 10 kg. 1 No.
9 Distillery Col. No. 4 D.C.P. 5 kg. 1 No.
Environmental Impact Assessment Report 2014
197 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
10 Fermentation House D.C.P. 5 kg. 2 Nos.
11 Packed liquor ware house D.C.P 5kg 2Nos
12 Packed liquor ware house Water Type 9lit 2Nos
13 IML bottling CO2 22.5kg 2Nos
14 IML bottling D.C.P 10 kg. 2Nos
34. Location of First Aid Boxes.
We have kept and maintained First Aid Boxes with prescribed medicines in all sections.
Location of First Aid Boxes is given below.
Sl No. Location
1 T. K. OFFICE
2 DISTILLERY (PRAJ)
3 DISTILLERY (IMFL)
4 SULPHUR HOUSE / CHEMICAL
5 PAN SECTION (CHEMICAL)
6 SUGAR HOUSE
7 BELT
8 M.T.D.
9 KRUPP BOILER
10 PARAS BOILER
11 POWER HOUSE
12 D. M. PLANT
Environmental Impact Assessment Report 2014
198 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
13 SWITCH YARD
14 CIVIL
15 COGEN. TURBINE
16 42”x 84” Mill
17 33”x 66” Mill
18 WORKSHOP – Welder
19 WORKSHOP – Moulder shop
20 FIRE FIGHTER
21 AMBULANCE
22 ENVIRONMENT DEPT.
23 TRAINING CENTRE
35. Electrical drawings:
Details are enclosed in (Annexure IV)
36. Display of prominent telephone numbers of at least:
Deputy Commissioner (0831) 2407200
Superintendent of / Local Police (0831) 2405204
Local Police Kagawad (08339) 264633
Fire Services Athani
Chikkodi
Sadalga
(08289) 251740
(08338) 273333
(08338)251900
Hospitals – Ugar sugar hospital
Wanless Hospital Miraj
(08339) 272230
(0233) 222329
Occupier / Manager (08339) 272230
Environmental Impact Assessment Report 2014
199 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Directorate of Factories & Boilers (080) 26531201
Karnataka State Pollution Control
Board Bangalore, Belgaum
(080) 25581383
(0831)2459121
Blood Bank – Dr.Shirgaokar Blood
Bank Sangli.
(0233) 2372376
Vasantdada Blood Bank Miraj (0233) 2222319
37. Key personal of the industry:
Name of the Person Designation Telephone number
P.V.Shirgaokar Executive VC 9972022205
S.S.Shirgaokar Managing Director 9972022206
N.S.Shirgaokar Joint Managing Director 9972024447
C.S.Shirgaokar Joint Managing Director 9972024448
G.N.Bellary DGM (A&P) 9900559181
S.N.Gurav Dy. Manager (P) 7259186058
D.K.Pendse DGM(Sugar) / Factory
Manager
9900559190
R.B.Shegunshi Safety Officer 9972372425
S.S.Sardesai DGM El ( Sugar
&Cogen)
9900559160
C.G.Pimpalkar DGM ( Process) 9900559188
B.N.Akiwate DGM (Cogen) 9900559162
N.B.Kagwade Dy.CE (cogen) 9972372423
M.B.Joshi CE El (Sugar & Cogen) 9900559177
Environmental Impact Assessment Report 2014
200 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Dr.B.V.Zadbuke Medical Officer 9740979188
Dr.S.M.Pattanshetty Chief Env. Manager 9900559179
D.B.Patil Distillery I / c 9972372427
B.T.Viapure
S.V.Shula
IML Manager
IML Incharge
9900559168
9972372428
Namdev Kharade Security Officer 9740083842
38. Waste disposal:
Waste should be disposed off in scientific manner. Debris should be collected in tractor
and trailers and dumped for land filling purpose. For this state rules and regulations
regarding waste disposal will be considered.
*****
Environmental Impact Assessment Report 2014
201 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER– 7
PROJECT BENEFITS
Environmental Impact Assessment Report 2014
202 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Project Benefits
7.0 Benefits
M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani,Dist: Belgaum, State: Karnataka
have Proposed Expansion of Sugar cane crushing capacity from 10000 TCD to 20,000
TCD, Co-generation power plant from 44 MW to 75 MW & Molasses based Distillery
from 75 KLPD to 200 KLPD. This project development will give rise to social and
economic development measures in the study area.
7.1 Improvement in Physical Infrastructure
The Enhancement project is expected to yield a positive impact on the socio-economic
environment. It helps in sustainable development of this area including further
development of physical Infrastructural facilities. The following physical infrastructure
facilities will improve due to proposed project:-
Ø Road Transport facilities
Ø Educational facilities
Ø Water supply and sanitation
7.2 Improvement in Social Infrastructure
The Enhancement project will lead to direct and indirect employment opportunity.
Employment is expected during civil construction period, in trade, garbage lifting,
sanitation, plantation works and other ancillary services. Employment in these sectors
will be primarily temporary or contractual and involvement of unskilled labour will be
more. This will enhance their income and lead to overall economic growth of the area.
The following changes in socio-economic status are expected to take place with this
project.
The project will have a strong positive employment and income effect, both direct as well
as indirect because of better indirect employment opportunities due to this project. The
project is going to have positive impact on consumption behavior by way of raising
average consumption and income through multiplier effect. The project is going to bring
about changes in the pattern of demand from food to non-food items and sufficient
income is generated. Following development of social infrastructures will be carried out.
Environmental Impact Assessment Report 2014
203 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
ü Education facilities
ü Banking facilities
ü Post offices and Communication facilities
ü Medical facilities
ü Recreation facilities
ü Business establishments
ü Community facilities
7.3 Places of Historical Importance
There is no historical or archaeological monument within 10 km of the area. Industrial
development and consequent economic development will lead to improvement in the
living standards of the people and enhanced social awareness. On the other hand, the
Enhancement project is likely to have several benefits like improvement in indirect
employment generation and economic growth of the area, by way of improved
infrastructure facilities and better socio-economic conditions.
7.4 Other Tangible Benefits
The Expansion project is likely to have other tangible benefits as given below:-
Ø Indirect employment opportunities to local people in contractual works like housing
construction, transportations, sanitation, for supply of goods and services to the
project and other community services;
Ø Additional housing demand for rental accommodation will be increased;
Ø Market and business establishment facilities will be also increased; Cultural,
recreation and aesthetic facilities will be improved;
Ø Improvement in communication, transport, education, community development and
medical facilities.
7.5 Project benefit:
Sugar is an essential food product. The by-products such as bagasse, molasses, and
press mud produced from sugar plant will be profitably utilized in the industry itself.
Bagasse is used as fuel in production of electrical power. Surplus power exported to
public distribution system will reduce the power scarcity in the region. The bagasse is
obtained from renewable source and is a substitute to fossil fuels such as coal or
petroleum.
Environmental Impact Assessment Report 2014
204 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Molasses is a raw material for production of ethyl alcohol which gains importance for its
use as fuel and as a starting material for various organic chemicals. The molasses is
thus a renewable resource and dispense the use of petroleum for fuel and organic
chemicals.
Press mud produced from sugar plant is composted along with spent wash generated
from the distillery plant to produce enriched bio-manure. It will be supplied to farmers for
use in cultivation of sugarcane and other crops. The composted bio-manure is rich in
nutrients and use of the same will reduce the need for chemical fertilizer.
Sugarcane cultivated in the region is presently transported through 30-60 km and
supplied to existing factories. Sugarcane cultivation gives higher economical returns to
the farmers. It will improve the economic status of the farmers growing sugarcane.
Hence more land will be brought under sugarcane cultivation.
The industry is established in the backward region of the state. The presence of the
industry helps to develop road and transportation facilities in the region. Commencement
of this industry will create direct and indirect employment opportunities to more than
2000 persons in terms of factory employment, transportation, vehicle maintenance, petty
shops etc. It will also benefit more than 500 sugarcane growing farmers in the region.
The expansion of integrated sugar industry will thus meet the national interest of
economical power and food through sustainable development without adverse effects to
the environment. Further it helps in the up-liftment of rural mass.
* * * * *
Environmental Impact Assessment Report 2014
205 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER– 8
ENVIRONMENTAL MANAGEMENT
PLAN
Environmental Impact Assessment Report 2014
206 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Environmental Management Plan
8.0 Introduction
The proposed project involves utilization of natural resources and generation of waste
and polluting substances. Depletion of natural resources will affect the competitive
users. The waste and polluting materials if discharged with out control and treatment is
likely to have adverse consequence to the environment parameters including water, air,
soil, flora and fauna. Further, it may exert stress to the existing infrastructural and other
facilities and also to the existing socio economic status of the region. It is the
responsibility of the project proponents to control the utilization of resources and
discharges of waste products by adopting suitable control measures in the factory to
avoid adverse consequence of industrial activities on the environment and inturn to
enhance the quality of the existing environment.
The Environment Management Plan describes both generic good practice measures and
site-specific measures so as to mitigate potential impacts associated with the proposed
activities. The Environmental Management Plan (EMP) of the Expansion plant with
respect to noise, air quality, water quality, solid waste, ecology, landscape socio-
economic measure are summarized below:- The EMP provides a delivery mechanism to
address potential adverse impacts and to introduce standards of good practice to be
adopted for all project works. For each stage of the program, the EMP lists all the
requirements to ensure effective mitigation of every potential environmental attribute and
socio-economic impacts. For each impact type during construction and operation the
following information is presented:-
v A comprehensive listing of the mitigation measures (actions) that are needed to
implement;
v The parameters that will be monitored to ensure effective implementation of the
action;
v The timing for implementation of the action to ensure that the objectives of
mitigation are fully met.
8.1 Environmental Management Plan during Construction Phase
8.1.1 Air Environment
The setting up of enhanced project from 10000 to 20000 TCD of Sugar Plant and 44MW
to 75 MW of Cogeneration power plant would result in increase of dust concentrations
Environmental Impact Assessment Report 2014
207 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
due to fugitive dust. Frequent water sprinkling in the vicinity of the construction sites
would be undertaken and will be continued after the completion of plant construction, as
there is scope for heavy truck mobility. It will be ensured that both petrol and diesel
powered vehicles are properly maintained to comply with exhaust emission
requirements.
The sources of particulate emissions from the Sugar Unit and Co-generation plant shall
be controlled to less than 150 mg/N m3 by the use of high efficiency ESP/ wet scrubber.
Stacks with suitable heights will be provided for long term distance travel of pollutant and
wide dispersion as per norms
8.1.2 Noise Environment
There will be marginal increase in noise levels during construction phase, which is
temporary and intermittent.
· Adequate measures taken to keep noise and vibrations under control
· The noise will be < 75 dB and these will be fleeting noise sources noise sources.
For the workers personal protective equipments will be provided viz. earmuffs,
earplugs.
· Processing will be under closed system, so no noise pollution will be controlled.
8.1.3 Water Environment
During construction, provision for infra-structural services including water supply,
sewage, drainage facilities and electrification will be mad Proper measures will be taken
to reduce the water consumption. The waste water shall be treated in an elaborate ETP
consisting of two stage activated sludge process which will be used for gardening/
irrigation purpose. For distillery there is a separate ETP i.e. evaporation and drying
effluent to form powder. In anaerobic digestion of spent wash, methane gas is produced
which can be used as a fuel in boiler. Hence, there will not be any adverse impact on the
environment.
8.1.4 Land Environment
Any hazardous material required for constructional activity will be stored as per safety
norms. Further construction site will be provided with suitable toilet and treatment
facilities etc for maintaining hygienic conditions.
Environmental Impact Assessment Report 2014
208 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
8.1.5 Socio-economic Environment
Any construction activity will benefit the local population in a number of ways. The
company management will give preference to local eligible people through both direct
and indirect employment. It will provide ample opportunity to the locals to up-lift their
living standards by organizing events that propagate mutual benefits to all, such as
health camps, awareness campaigns, donations to poorer sections of society and down-
trodden.
8.1.6 Safety and Health
Adequate space will be provided for construction of temporary sheds for construction
workers mobilized by the contractors. M/s USWL will take care of supply of potable
water for the construction workers. The safety department will supervise the safe
working of the contractor and their employees. Work spots will be maintained clean,
provided with optimum lighting and enough ventilation to eliminate dust/fumes. A
comprehensive Occupational Health and Safety management plan is put in place to
address any sort of eventuality.
8.2 Environmental Management Plan during Operations Phase
8.2.1 Air Environment
The major pollutants emerged due to Sugar Plant and Cogeneration Plant operations
are suspended particulate matter (SPM), fine particulate matter (PM10& PM2.5),
Sulphur dioxide (SO2) and Oxides of Nitrogen (NOx).
Ø All sources of dust generation in the Sugar Plant with Cogeneration Plant shall be
well designed for producing minimum dust and shall be provided with high
efficiency ESP and Wet Scrubber.
Ø Particulate Matter emission level from the stack chimney will be less than 50
mg/Nm3 and the stack height is proposed to 75 m.
Ø SO2 concentration will be negligible as the bagasse will be used as fuel for boiler.
Ø The periodic evaluation for the efficiency performance of Wet Scrubber will be
carried out.
Ø For controlling fugitive dust, in hopper, reclaimer, conveyors, silos etc. bag filters
shall be installed.
Ø Fugitive emissions due to storage, transportation, etc. and the leakages and
spillages shall be continuously monitored and controlled.
Environmental Impact Assessment Report 2014
209 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø Water conservation measures shall be undertaken for effective implementation.
Cooling water is put into closed circuit to minimize the evaporation losses.
Ø Thermal insulation will be provided wherever necessary to minimize heat
radiation from the equipment, piping etc., to ensure protection of personnel.
8.2.2 Noise Environment
ü All rotating items are well lubricated and provided with enclosures as far as
possible to reduce noise.
ü The design features of machineries shall be provided to ensure low noise levels
in the working areas.
ü Extensive vibration monitoring system will be provided to check and reduce
vibrations. Allfans, compressors etc., are provided with vibration isolators to
reduce vibration and noise.
ü Noise generating equipment including fans, blowers, pumps, motors etc., will be
running with speed less than 1500 rpm and reduce noise levels.
ü Provision for silencers wherever possible.
ü Green belt development will be done and it will act as noise reducers.
ü Requisite enclosures will also be provided on the working platform/areas to
provide local protection in high noise level areas.
ü All heavy earthmoving equipment will be kept in a well maintained condition.
ü Proper lubrication and house equipment will be kept in better condition
ü Necessary PPE will be provided such as ear plugs, ear muffs etc.
By these measures, it is anticipated that noise levels in the plant will be maintained
within the permissible limits at the boundary of the plant premises. Plantation on the
periphery of the plant would further attenuate noise levels.
8.2.3 Solid Waste Management
Dry fly ash and furnace bottom ash
Fly ash collected from the ESP hoppers and the air heaters hoppers and the ash
collected from the furnace bottom hoppers can be used as landfill. The high potash
content in the bagasse ash makes the ash as good manure. Filter cake will be sold to
farmers as manure. The liquid molasses will be sent to distillery for manufacture of
alcohol.
Environmental Impact Assessment Report 2014
210 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Sewage from various buildings in the plant
Sewage from various buildings in the plant area will be conveyed though separate drains
to the septic tank. The effluent from septic tank will be disposed in soil by providing
disposing trenches. There will be no ground pollution because of leaching due to this.
Sludge will be used as manure for green belt development.
8.2.4 Water and Wastewater Management
Continuous efforts would be made to reduce the water consumption and thereby to
reduce the wastewater generation. Flow meters would be installed for all major water
inlet and the flow rates would be continuously monitored. Periodic water audits would be
conducted to explore the possibilities for minimization of water consumption. Water will
be drawn from Krishna River to meet the plant consumptive water requirement.
Considering the quality of water, the Cycle of Concentration (COC) of the cooling tower
is considered as 1.5.
Waste water Management
The treated water quantity will be used for dust suppression. Water Pollution control
measures to be undertaken are given as under:-
v No trade effluent shall be discharged from the Plants
v Cooling water is put into closed circuit to minimize the evaporation losses
v The domestic sewages from the Plants, Sugar Plant with Cogeneration Unit and
Township shall be treated in the Sewage Treatment Plant to meet the Statutory
Norms and the treated sewage shall be used for Green Belt;
v No percolation of treated water to deep ground water table is done.
v Periodical monitoring for specific parameters shall be done regularly.
v Rainwater harvesting structures shall also be developed as proposed from the
roof tops of Plants as well as Township areas to supplement the water supply
from the river.
Wastewater treatment
Waste water treatment for the plant will be based on discharges of the various effluents
to ponds for clarification and filtration. Oily water will be treated separately to remove
oil/grease before discharge into effluent ponds. The oily water collection in the plant is
Environmental Impact Assessment Report 2014
211 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
basically due to floor cleaning, leaky oil filters, etc. Clarification is used to settle out large
suspended particles and condition smaller colloidal particles to make them settle. A
pond, reservoir tank or tank is used to allow larger particles to settle in a matter of hours.
The finer particles overflow and are made to settle more quickly by the addition of
chemical agents, coagulants and polymers that cause agglomeration to sizes large
enough to settle out of suspension. As required and with approvals from appropriate
regulating bodies, final waste stream pH is controlled by combining various plant
streams to provide a neutral pH product. Where needed, acid or alkali addition will be
used to achieve the final pH.
Final Disposal of the wastewater
The treated effluent from the effluent tank will be used for horticulture and green belt
development within the plant.
Monitoring of Wastewater Treatment
The treated effluent would be monitored regularly for the flow rate and quality to identify
any deviations in performance of Effluent treatment plant.
Thermal Pollution Management
A closed circuit cooling water system with cooling towers is present in the existing area.
This eliminates the letting out of high temperature water into the canals and prevents
thermal pollution. Blow down from the cooling tower will be trenched out and ultimately
conveyed to the effluent ponds. Hence, there is no separate pollution on account of blow
down from cooling water system.
8.4 Rain Water harvesting System
Rain Water harvesting System The rain (storm) water from the building roofs, non-
process area and grade level surfaces will be directed through the rain water harvesting
structures and excess water will be directed through open drains to the storm drainage
Environmental Impact Assessment Report 2014
212 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
system. The storm water from the storm drainage system will be discharged outside the
plant boundary. All drains will be lined and will be arranged to provide the shortest
possible drainage path for efficient drainage.
8.5 Housekeeping
Salient features of housekeeping will be adopted are as follows:-
v Mechanized cleaning of roads and floor area inside the plant premises by using
road sweeper and mobile vacuum cleaner on regular basis;
v Training on regular basis to all workers and staff about the importance of
cleanliness;
v Careful garbage transportation to dumping site and disinfection of transport
vehicles body;
v Decorative plantation and gardening to improve aesthetics of the plant; and
v Construction of suitably designed drains all along the roads and boundary of the
plant premises.
8.6 Occupational Health & Safety
During operation stage, dust causes the main health hazard. Other health hazards are
due to gas cutting, welding, noise and high temperature and micro ambient conditions
especially near the boiler and platforms, which may lead to adverse effects (Heat
cramps, heat exhaustion and heat stress reaction) leading to local and systemic
disorders.
The occupational health surveillance program is to address pre employment health
examination and periodic health examination. Every employee on his appointment for a
job with a possibility of exposure to airborne asbestos shall get the pre-employment
medical examination done within stipulated days of his employment, by the employer.
Scheme for health surveillance shall include exposure data at each pertinent work place,
periodical examination of workers, X-ray examination for radiological changes, lung
function test for digestive disorder and clinical examination for early detection of signs of
Environmental Impact Assessment Report 2014
213 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
asbestosis. These tests are to be recorded for pre-employment, periodic surveillance
and at cessation of employment as per the concerned state government regulations.
Occupational health surveillance is to be carried out by occupational physician or chest
physician trained in occupational medicine. The occupational health surveillance
program is to be drawn for all the employees potentially exposed to asbestos dust and it
is to be provided free of cost.
The medical records is to be maintained and stored for period of 15 years following the
termination of employment or for 40 years after first day of employment, whichever is
later. The medical records is to be maintained covering the details of pre-employment
examination, the periodical medical examinations, medical examination done at other
times, if any and the medical examinations conducted at cessation of employment and
further follow-up examinations, where done. The records shall also be maintained of the
individual employee’s occupational exposure profile to asbestos, specific work practices,
and preventive measures prescribed, if any.
The occupational health surveillance program is to address the following aspects
· Pre-employment medical examination
· Periodic medical examination
· Medical employment at cessation of employment
· Maintenance of medical records and
· Health education
Scheme for occupational health monitoring is to be prepared in detail [BIS code of
practices IS: 11451-1986 (Reaffirmed 2005) (Recommendations for safety health
requirements relating to occupational exposure to asbestos)]
Table – 8.1 Health Evaluation schedule: Frequency of Periodical Examination of
Occupational Health
Occupation Type of evaluation Frequency
Pre-placement
Cane Crushing Area Chest X-ray, spirometry
and vision testing
Every 5 years to age <30;
Every 4 years to age 31-
Environmental Impact Assessment Report 2014
214 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
40; and every 2 years to
age 41-50;
Sugar Process Area &
Cogeneration Area
Chest X-ray, spirometry
and vision testing
Every 5 years to age <30;
Every 4 years to age 31-
40; and every 2 years to
age 41-50;
Noise prone areas Audiometry Annually
Main Control Room Far & Near Vision; Colour
Vision; and Hearing tests
Every 5 years to age <30;
Every 4 years to age 31-
40; And every 2 years to
age 41-50;
Ash Handling Area&
Bagasse Handling Area
Chest X-ray, spirometry,
Vision; and Hearing tests
Every 5 years to age <30;
Every 4 years to age 31-
40; And every 2 years to
age 41-50;
Ø All workers engaged in material handling system will be regularly examined for
lung diseases such as PFT (Pulmonary Function Test) tests;
8.7 Design of Green Belt
Green belt development in around 33 % of the total plant area will be developed. Green
belt of around 50 m width will be provided throughout the periphery of the existing
project site.
8.7.1 Green Belt and Plantation Plan
Green belt development in an industry is one of the most effective environmental
pollution control measures. Trees play vital role in keeping the ground level
concentrations in control within the plant premises and also in preventing the horizontal
dispersion of the pollutants to the surrounding areas. They are very effective in trapping
the pollution causing agents viz. dust and gaseous pollutants. They are also considered
to be excellent indicators of excessive ground level concentrations. The green belt is
being proposed for the following objectives.
Environmental Impact Assessment Report 2014
215 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Out of the total 251 acres of land, green belt will be developed 33% in 95.20 acres. Apart
from the bulk plantation around the boundaries, Roadside avenue plantations will also
be taken up. Based on the agro-climatic conditions of the region, location of the Sugar
Plant with Cogeneration Unit, physico-bio-chemical properties of the soil strata, nature of
the pollutants and their rate of dispersion, it is suggested to develop greenbelt around
the plant. Such green areas would improve the floral status and serve the dual purpose
of arrest of any fugitive dust from unpaved or open areas and also help to abate the
noise effects through dampening effects.
Table-8.2 Suggested Plant Species for Road Side Plantation
S.
No.
Scientific Name Vernacular name
1 Bauhimapururea Kachnar
2 Leucaenaleucocephala Subabool
3 Delonixregia Gulmohar
4 Cassia fistula Amaltas
5 Pongamiapinnata Karanj
6 Samaniasaman Rain tree
Table-8.3 Plant Species Suggested for Green Belt Development suggested by
CPCB
S.No
.
Botanical name of the
plant
Size of the
grown up tree
Type and suitable site,
where the plants are to be
plotted
1 Acacia auriculaeformis Medium Semi-evergreen fragrant white
flowers suitable in green belts
and on road sides
Environmental Impact Assessment Report 2014
216 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
2 Adina corodifolia Large Deciduous, a light demander,
suitable on open areas and
near flares
3 Aeglemarmelos Medium Deciduous, good for green
belts near temples.
4 Anogeissuslatifolia Medium Deciduous, Suitable for green
belts
5 Artabotryshexapetaius Small Evergreen shrub with fragrant
flowers good for gardens and
inside boundary wall and long
canals
6 Averrhoacarambola Small Semi evergreen, good in
narrow green belts along the
ash pond
7 Azadirachtaindica Large Evergreen, suitable in green
belts along the boundary and
outside office & sensitive
buildings like hospitals.
8 Bauhinia variegate Medium Deciduous, good in green belts
in garden and as a second row
avenue tree
9 Borassusflabellifer Large A tall deciduous palm can be
used as wind break when of
different age.
10 Boswelliaserrata Medium Deciduous suitable on green
belt on willow soils
11 Bureraserrata Medium Evergreen, suitable on willow
soils as a green belt or avenue
tree
12 Buteamonosperma Medium Deciduous for green belt and
as a second row avenue tree
13 Caesalpiniapulcherrima Small A large shrub, suitable for
gardens outside offices and
along channels
Environmental Impact Assessment Report 2014
217 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
14 Callistemon lanceolatus Medium Deciduous for some time,
ornamental plant in garden
15 Carevaaroborea Large Deciduous, good in green belts
16 CarrisaCarandas Small Semi evergreen large bushy
shrub good as a hedge to
protect against noise.
17 Carhotaurents Large A lofty palm, good as a wind
break
18 Cassia fistula Medium Deciduous, good ornamental
tree in green belts.
19 C.siamea Large Evergreen, good as an avenue
tree.
20 Casuarinaequisetifolia Medium Evergreen suitable for covering
low lying area and in green
belts and along ponds.
21 Cedrelatoona Large Deciduous, good in open
spaces, in green belts and
along ponds.
22 Ficusbengalensi Large Deciduous, widely spaced
avenue tree (15 m apart)
23 Ficusreligiosa Large Deciduous, widely spaced
avenue tree also as a single
tree in isolated sites.
24 Maducaindica Medium Deciduous, good in green
belts.
25 Peltophoruminerme Medium Semi evergreen, suitable on
road sides, in gardens and
outside office buildings.
26 Saracaindica Medium Evergreen tree good on road
sides within campus
27 Tamarindusindica Large Evergreen tree good along
boundary and road sides.
28 Terminaliacatappa Large Deciduous tree
29 Terminaliaarjuna Large Evergreen tree for road sides
Environmental Impact Assessment Report 2014
218 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
and in green belts
30 Zanthoxyium Medium Deciduous in green belts
8.8 Measures to Improve Socio-Economic Conditions
For the benefit of the community in the vicinity of the project, USWL will take several
measures to develop various amenities in an effort to improve standard of living, some of
which are; Capital budget of Rs.199.52 Crs will be allotted for the following works in
consultation with local administration.
ü Providing drinking water
ü Construction of schools
ü Construction of community centres
ü Construction of roads and drainage
ü Construction of health centres
Table – 8.4 Corporate Social Responsibility (CSR) Budget
S. No. Description Amount in
Rs. Lakhs
1 Donations 10.00
2 Krishi melas 1.00
3 Medical Aid 35.0
4 Sports /recreation 5.0
5 Road repairs 25.0
6 Aid to School 20.0
7 Aid to places of worships 5.0
Total 101.00
Environmental Impact Assessment Report 2014
219 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
8.9 Landscaping
The various services I utility areas within the plant will be suitably graded to different
elevations. Natural features of the plant site will be retained as far as possible to
integrate with the buildings to form pleasant environment. Areas in front of various
buildings and the entrance of Sugar Plant with Cogeneration Unit will be landscaped with
ground cover, plants, trees based on factors like climate, adaptability, etc. The green belt
will consist of native perennial green and fast growing trees. Trees will also be planted
around the plant boundary to minimize the dust pollution. Adequate afforestation will be
carried out as per the guidelines of MoEF.
8.10 Fire Fighting & Protection System
Safety Policy and Regulations
Keeping in view of the safety requirement during construction, operation and
maintenance phase, M/s USWL has formulated safety policy with the following
regulations:-
v To allocate sufficient resources to maintain safe and healthy conditions at work
place.
v To take, steps to ensure that all known safety factors are taken into account in
the design, construction, operation and maintenance of plants, machinery and
equipment.
v To ensure that adequate safety instructions are given to all employees.
v To provide wherever necessary, protective equipment, safety appliances and
clothing and to ensure their proper use.
v To inform employees about materials, equipment or processes review for making
necessary changes from the point of view of safety in the light of experience and
up to date knowledge.
v To provide appropriate instruction, training and supervision in health and safety,
first aid and to ensure that adequate publicity is given to these matters.
v To ensure proper implementation of fire prevention and an appropriate fire
fighting service together with training facilities for personnel involved in this
service.
v To ensure that professional advice is made available wherever potentially
hazardous situations exists or might arise.
Environmental Impact Assessment Report 2014
220 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
v To organize collection, analysis and presentation of data on accident, sickness
and incident involving personal injury to health with a view to taking corrective,
remedial and preventive action.
v To prepare safety rules for each type of occupation/process involved in a project.
v To ensure regular safety inspection by a competent person at suitable intervals of
all buildings, equipment, work places and operations
Fire Protection System
v The plant has proposed adequate number of wall/column mounted type portable
fire extinguishers in various strategic areas of the plant including the control
room, administration building, stores, pump house etc. These portable fire
extinguishers are basically of carbon dioxide and dry powder type.
v Fire hydrants at suitable locations for TG building, boiler area, & storage area.
v Medium velocity water spray system for the cable gallery
v Necessary electric driven, Jockey pumps with piping valves & instrumentation for
safe operation.
8.11 Corporate Environment Policy: Corporate Responsibility for Environmental
Management
Ø The plant has an Environmental Management Committee headed by the Director
& Chief Operating Officer and comprises of key personnel in the plant. The
Committee meets regularly to review the status of various aspects of pollution
control measures will be implemented in the plant.
Ø The unit has also initiated improvement measures to get ISO14001 certification.
Ø Suggestion scheme has been launched and various suggestions given by the
workers and employees have been implemented in order to improve safety and
protect environment.
Ø The unit has resolved to become a zero waste integrated agro business sugar
complex and in its commitment to ensure zero discharge. Measures will be
implemented to recycle and reuse waste water to avoid effluent discharge into
the environment.
Ø The unit complies with the various requirements and standards stipulated by
Ministry of Environment & Forests, Central Pollution Control Board and
Maharashtra Pollution Control Board.
Environmental Impact Assessment Report 2014
221 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Ø The unit recently commissioned a new mist cooling system with automation for
cooling the evaporator and pan condenser water.
Ø Involvement of workmen in Safety Management through the Safety Committee
which is empowered to review accidents and initiate corrective and preventive
action.
Ø Ensuring high standards of housekeeping in the factory premises, resulting in a
Safe Shop floor,
Ø All personnel are trained on First Aid and basics of Safety Management.
* * * * *
Environmental Impact Assessment Report 2014
222 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER 9
SUMMARY AND CONCLUSIONS
Environmental Impact Assessment Report 2014
223 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
SUMMARY AND CONCLUSIONS
M/s. Ugar Sugar Works Ltd. Ugar Khurd, Tal: Athani, Dist: Belgaum, State: Karnataka
have Proposed Expansion of Sugar cane crushing capacity from 10,000 TCD to 20,000
TCD, Co-generation power plant from 44 MW to 75 MW & Molasses based Distillery
from 75 KLPD to 200 KLPD. This project development will give rise to social and
economic development measures in the study area.
1. The proposed agro based sugar industry has national priority to overcome energy
and food crisis. Sugar industry also has export potentials to earn foreign
exchange. Commencement of this industry will create employment opportunities
and improve the economic status of the farmers of this rural under-developed
region.
2. Wastewater generated from co-gen sugar unit is treated and used for irrigating
agricultural land for growing sugarcane.
3. The by-products such as bagasse, molasses, press mud produced from the
sugar plant will be profitably utilized in the industry itself in the production of
electrical power, alcohol and bio-manure respectively.
4. The project activity is an example as sustainable development as the resources
used from the nature are sent back to the environment by recycling process. The
concept of reduce, reuse and recycle is practiced in the industry as per the eco-
policy of Govt. of India.
5. This industry does not produce any toxic products and does not have significant
adverse effect on the quality of land, water and air. The industry has taken all the
necessary preventive measures to mitigate even the small effects which may be
caused by industrial activities.
6. There are no protected forests, sanctuary, archeological important structures or
other sensitive locations in the vicinity of the factory except the rivers Krishna &
Don rivers. Therefore, the proposed industry will not have adverse effect on the
environment or the eco system.
7. This industry does not have significant adverse effect on environment. The
industry proposes to adopt an effective environment management system and
environment management plan to protect the environment. Due priority is given
for greenery development and rainwater harvesting in the factory premises.
Environmental Impact Assessment Report 2014
224 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Environmental management plan and suggested measures for pollution control are
adequate for protection of environment and to seek environmental clearance to the
project.
Conclusion
The potential environmental, social and economic impacts have been assessed. The
proposed Sugar Unit, Cogeneration plant and distillery unit will have certain levels of
marginal impacts on the local environment. Implementation of the project will have
beneficial impact in terms of providing direct and indirect employment opportunities.
There will be a positive socio-economic development in the region. Quality of life of the
people will be improved. Recommendations made in the CREP for Sugar Plant will be
implemented. USWL will also undertake various community welfare measures for the
upliftment of the villages of the study area.
.
* * * * *
Environmental Impact Assessment Report 2014
225 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
CHAPTER 10
DISCLOSURE OF CONSULTANT
Environmental Impact Assessment Report 2014
226 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
Chapter 10
DISCLOSURE OF CONSULTANT
This EIA report is prepared on behalf of the proponents, taking inputs from
proponent’s office staff, their R & D wing, Architects, Project Management
Professionals etc. by Environmental Consultants M/s. Ultra-Tech Environmental
Consultancy & Laboratory, Thane, Mumbai , who have been accredited by QCI-
NABET vide official memorandum of MoEF S.N. 93 of LIST ‘A’ of MoEF - O.M. No. J
11013/77/2004/IA II(I) dated September 30, 2011, S. No.157 of list of Consultants
with Provisional Accreditation * (Rev.23) of dated 07th August, 2014.
M/s Ultra-Tech Environmental Consultancy & Laboratory:
Ultra-Tech Environmental Consultancy & Laboratory [Lab Gazetted by MoEF – Govt.
of India] not only give environmental solutions for sustainable development, but
make sure that they are economically feasible. With innovative ideas and impact
mitigation measures offered, make them distinguished in environmental consulting
business. The completion of tasks in record time is the key feature of Ultra-Tech. A
team of more than hundred environmental brigadiers consists of engineers, experts,
ecologists, hydrologists, geologists, socio-economic experts, solid waste and hazard
waste experts apart from environmental media sampling and monitoring experts and
management experts , strive hard to serve clients with up to mark and best services.
Ultra-Tech offers environmental consultancy services to assist its clients to obtain
environmental clearance for their large buildings, construction, CRZ, SEZ, high rise
buildings, township projects and industries covering sugar and distilleries from
respective authorities. Ultra-Tech is in the process of getting QCI-NABET final
accreditation for its EIA organization.
Ultra-Tech also provide STP/ETP /WTP project consultancy on turn-key basis apart
from Operation and Maintenance of these projects on annual contract basis. Also,
having MoEF approved environmental laboratory, Ultra-Tech provide laboratory
services for monitoring and analysis of various environmental media like air, water,
Environmental Impact Assessment Report 2014
227 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
waste water, stack, noise and meteorological data to its clients all over India and
abroad.
Functional area experts and assistance to FAE involved in the EIA study for “M/s
Indian Sugar Manufacturing Co. Ltd. Turk Pimpri, Barshi Tehsil, Solapur District,
Maharashtra,” is as follows:
* EIA COORDINATOR : NAME : MR. A.K.MHASKAR
* PERIOD OF INVOLVEMENT : September 2013 – November 2013
* CONTACT INFORMATION : ULTRA-TECH Environmental consultancy & Laboratory,
EIA TEAM MEMBERS
S/ No.
Name of Sector
Name of Project
NAME OF EIA
COORDINATOR
FUNCTIONAL AREA EXPERTS
INVOLVED
1 Distilleries 5 (g), Sugar 5 (j) & Co- Gen 1 (d)
Indian Sugar Mfg co. Ltd. (Industrial Project)
Mr. A.K. Mhaskar Associates: Mr. Kishor Sawant, Dr. Prashant Banne
FA Names AP Mr. Akshay Kulkarni WP Ms. Pardnya Parkhi EB Ms. Bharti Khairnar SE Mr. Shrikrishna Kulkarni
SHW Ms. Pradnya Parkhi LU Associate: Mr. Amogh Bodas
LABORATORY FOR ANALYSIS
S/ No. Name of
Laboratory Scope of Services ACCREDITATION
STATUS 1 Green Circle INC. Monitoring and Analysis of:
1. Ambient Air Quality Monitoring 2. Ground and Surface Water Quality Monitoring 3. Noise Level Monitoring and 4. Soil Quality Monitoring 5. Metrological data collection
Gazetted by MoEF- Govt. of India
* * * * *
Environmental Impact Assessment Report 2014
228 M/s Ugar Sugar Works Ltd.Ugar Khurd, Tal: Athani, Dist: Belgaum
List of Annexure
Annexure
No.
Title of Annexure
1 Site Layout Plan
2 Existing unit MPCB consent to Operate Under Air act
3 Existing unit MPCB consent to Operate under Water act
4 Licence for Manufacture of Sugar
5 Distil lery Licence
6 Brief note on Sugar Manufacture Process
7 Schematic flow diagram of Sugar Manufacturing Process
8 A short note on Extra Neutral Alcohol Process
9 Flow Diagram of Disti l lery Plant
10 Flow Diagram of Disti llation Plant
11 Flow sheet for ENA process
12 Flow chart of IML Plant
13 Design basis of Single- Drum, Slop fired (TG) Boiler
14 Cogeneration – Package Boiler f low sheet
15 General Arrangement of Diesel power house
16 Data on Air quality modell ing
17 Note on Eff luent Treatment Plant (ETP)
18 Site plan of ETP
19 Note on Agriculture management plan
20 Map showing that irrigated area by disti llery effluent
21 Environmental Monitoring reports
22 Lab recognition & NABET accreditation certif icates
23 Copy of ToR (Terms of Reference) received from MoEF