chap016.ppt materials requirements planning

Upload: saad-khadur-eilyes

Post on 14-Apr-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    1/25

    McGraw-Hill/Irwin The McGraw-Hill Companies, Inc. 2007, All Rights Reserved

    Materials Requirements

    Planning

    Chapter 16

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    2/25

    16-2

    Chapter 16 Outline

    Definition of MRP Systems

    MRP versus Order-Point Systems

    MRP ExampleMRP Elements

    Operating an MRP System

    The Successful MRP System

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    3/25

    16-3

    Introduction to MRP

    Used to manage dependent demand itemsRaw materials and purchased parts

    Work in process (WIP)

    Driven by the master schedule (which is drivenby S&OP).

    End items exploded into all componentsusing bill of materials (BOM)

    Schedule offset based on lead times

    Is the heart of a larger ERP system

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    4/25

    16-4

    Definitions of MRP Systems

    Developed by Joe Orlicky at IBM, 1975.

    IBM 370 was the first computer with the

    capacity to handle MRP calculations

    Types of MRP: Type I. An inventory control system (MRP)

    Type II. Manufacturing Resource Planning system

    (MRPII)

    Type III. Enterprise Resource Planning (ERP) system

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    5/25

    16-5

    Definitions of MRP Systems

    Three principal functions of MRP (Orlicky):Inventory Order the right part

    Order in the right quantity

    Order at the right time

    Priorities Order with the right due date

    Keep the due date valid

    Capacity

    A complete load An accurate (valid) load

    An adequate time span for visibility of future load

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    6/25

    TR 4-6

    Firm orders from

    Customers

    Sister plants

    Stock replenishment

    Engineering Design changes

    BOM

    Forecast of Demand

    Purchase Orders

    Vendors

    MRP PartsExplosion

    Rough-cutcapacity planning

    Capacity planning

    Shop Orders

    Shop-floor control

    Masterschedule

    S & OP

    Closed Loop MRP System

    Operations ProductRaw Materials

    Inventory Records

    Inv. Transactions

    16-6

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    7/25

    16-7

    Attribute MRP Order Point

    Demand Dependent Independent

    Order philosophy Requirements Replenishment

    Forecast Based on master schedule Based on past demand

    Control concept Control all items ABC

    Objectives Meet manufacturing needs Meet customer needs

    Lot sizing Discrete EOQ

    Demand pattern Lumpy but predictable Random

    Types of inventory Work in process and raw

    materials

    Finished goods and spare

    parts

    Comparison of MRP & Order-Point Systems

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    8/25

    16-8

    MRP Elements

    Inputs

    1. Master Schedule

    2. Bill of Materials (BOM)

    3. Inventory Records

    Capacity Planning (feasibility)

    Planned Order Releases (outputs)

    Purchasing (buy)

    Shop Floor Control (make)

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    9/25

    MRP Inputs

    1. Master schedule

    2. Product structure file (bill of materials or

    BOM)

    1. Parts & subassemblies contained in product

    2. Sequence of operations

    3. Inventory master file

    1. Item master information

    2. Balances & ordering information

    16-9

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    10/25

    1. Master Schedule

    Quantities derived from S&OP production plan(product groups) [input]

    Drives MRP process with a schedule of finished

    products (actual items by week) [output]Quantities may consist of a combination of

    customer orders & demand forecasts

    Quantities represent what needs to be produced,not what can be produced (infinite capacity

    planning)

    16-10

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    11/25

    16-11

    2. MRP Example of BOM

    Top

    Leg

    Long Rail

    Short Rail

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    12/25

    16-12

    BOM (Product Structure)

    Short Rails (2)

    1 week

    Table (End Item)

    1 week

    Long Rails (2)

    1 week

    Legs (4)

    1 week

    Top (1)

    2 weeks

    Leg Assembly (1)

    1 week

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    13/25

    16-13

    Indented BOM

    Level Code Component

    0 Table (end-item)

    1 Leg assembly (1)

    2 Short rails (2)

    2 Long rails (2)

    2 Legs (4)

    1 Top(1)

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    14/25

    16-14

    3. Inventory (item master) File

    Description

    Part number

    Part name

    Safety stockItem classification

    Cost

    Yield

    Lead time

    Group to which itembelongs

    Assemblies in whichitem is used

    Shelf life

    Batch controlrequirements

    Substitutes

    Suppliers and their

    ratingsUnit of measure (SKU)

    Permanent information may include:

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    15/25

    16-15

    Inventory Status File

    Quantities

    Ordered

    Received

    Issued

    Allocated

    Previously allocated that have been issued

    Dates ordered, received, issued, and allocated

    Shipping, production, and purchase numbersOn-hand balance & Available balance

    Batch identification (e.g. lot number)

    Changing information includes:

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    16/25

    MRP Example

    The Alpha Beta Company

    Inventory Position

    Item On Hand Scheduled Receipts Lot Size MPS

    A 10 0 1 100, period 8

    B 5 0 1 200, period 6

    C 140 0 150 - - -

    D 200 250, period 2 250 - - -

    A

    LT=3

    C(3)

    LT=4

    D(2)

    LT=2

    D(3)

    LT=2

    B

    LT=2Level (LLC)=0

    Level (LLC)=1

    BOM

    16-16

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    17/25

    MRP Matrices For A & B

    Item: A LLC: 0 Period

    Lot size: 1 LT: 3 PD 1 2 3 4 5 6 7 8

    Gross requirements 100

    Scheduled receipts

    Projected on hand 10 10 10 10 10 10 10 10 0

    Net requirements 90

    Planned order receipts 90Planned order releases 90

    Item: B LLC: 0 Period

    Lot size: 1 LT: 2 PD 1 2 3 4 5 6 7 8

    Gross requirements 200

    Scheduled receipts

    Projected on hand 5 5 5 5 5 5 0 0 0Net requirements 195

    Planned order receipts 195

    Planned order releases 195

    16-17

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    18/25

    16-18

    Origin of Requirements

    At Level Zero: gross requirements come

    from the master production schedule (MPS)

    Below level zero: gross requirements comefrom planned order releases for the next

    level above.

    Net requirements are gross requirements

    plus scheduled receipts minus inventory on-

    hand

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    19/25

    MRP Matrices For C & D

    Item: C LLC: 1 Period

    Lot size: 150 LT: 4 PD 1 2 3 4 5 6 7 8

    Gross requirements 270

    Scheduled receipts

    Projected on hand 140 140 140 140 140 20 20 20 20

    Net requirements 130

    Planned order receipts 150Planned order releases 150

    Item: D LLC: 1 Period

    Lot size: 250 LT: 2 PD 1 2 3 4 5 6 7 8

    Gross requirements 585 180

    Scheduled receipts 250

    Projected on hand 200 200 450 450 115 185 185 185 185Net requirements 135 65

    Planned order receipts 250 250

    Planned order releases 250 250

    16-19

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    20/25

    Alpha Beta Planned Order

    Release Report

    Period Item Quantity

    1 C 150

    2 D 250

    3 D 250

    4 B 195

    5 A 90

    16-20

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    21/25

    16-21

    Operating an MRP System

    Should MRP carry safety stock?

    How much safety stock should be carried?

    Issue of safety lead time

    Danger of informal system driving out the formal

    system

    Expansion of MRP to other functions (finance, HRM,

    etc.) of business

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    22/25

    16-22

    Operating a Successful MRP

    SystemAccurate Inventory Records

    Stable master production schedule

    Realistic master production scheduleGood control of engineering change orders

    (impacts BOM)

    Good interface with capacity planning (CRP)Reports that are useful

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    23/25

    16-23

    Elements of Successful MRP

    ImplementationAllow enough time (18 months minimum)

    Put materials people in charge of cross-functional team (not IS or accountants)

    Train everyone and train them again!

    Top Management supportAccurate records

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    24/25

    16-24

    Summary

    Definition of MRP Systems

    MRP versus Order-Point Systems

    MRP ExampleMRP Elements

    Operating an MRP System

    The Successful MRP System

  • 7/30/2019 Chap016.ppt Materials Requirements Planning

    25/25

    16-25

    End of Chapter Sixteen