changeover improvement: smed and beyond … dr richard mcintosh
TRANSCRIPT
Changeover Improvement:SMED and beyond …
Dr Richard McIntosh
5 Part Presentation
- Review- Embracing design opportunities- Changeover game- Other important issues- A revised improvement approach
Part I
Review
CHANGEOVER IMPROVEMENT
Copyright Suiko-WCS International
An automotive example
ITBA - July 2007
Another automotive example
CHANGEOVER IMPROVEMENT
CHANGEOVER IMPROVEMENTIndustrial
ITBA - July 2007
CHANGEOVER IMPROVEMENTPurpose
ITBA - July 2007
Why seek better changeovers ?
£ … € …
$ … ¥ …
CHANGEOVER IMPROVEMENT
ITBA - July 2007
Retrospective improvement team
Opportunities
Original equipment manufacturer
ITBA - July 2007
TIME
OUTPUT
(Run down period)
Set up period
Run up period
CHANGEOVER DEFINITION
CHANGEOVER INCLUDING RUN-UPRun-up
0
200
400
600
800
1000
1200
1400Daily Production(‘000s)
Days after Changeover
Target(750,000 units/day)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Set-up period losses
Other losses
Run-up period
Total elapsed changeover period
16 17
Set-up period
ITBA - July 2007
CHANGEOVER DEFINITION
Changeover should be defined as …
• “The activities necessary to ensure manufacture of a new product at a predetermined
production rate and at a predetermined product quality rate.”
and/or
• “The elapsed time between manufacture of an existing product and manufacture of a new product at a predetermined production rate and a predetermined product quality rate.”
CHANGEOVER IMPROVEMENT PRACTICEShingo book: “A revolution in manufacturing”
ITBA - July 2007
Productivity Press
ISBN 0-915299-03-8
‘SMED’
• Stage 0 - Internal and External not distinguished
• Stage 1 - Separate Internal and External
• Stage 2 - Convert Internal to External
• Stage 3 - Streamline
ConceptualStages
Dominant ‘SMED’ methodology
ITBA - July 2007
REVIEWING IMPROVEMENT PRACTICE
Dominant ‘SMED’ methodology
ITBA - July 2007
REVIEWING IMPROVEMENT PRACTICE
SMED concept or stage Assigned technique
Stage 1:Separate internal and external setup
Using a checklistPerforming function checksImproving die transportation
Stage 2:Convert internal to external set-up
Preparing operating conditions in advanceFunction standardisationUsing intermediary jigs
Stage 3:Streamline all aspects of the set-up operation
Improving storage and transportation of dies, etc.Implementing parallel operationsUsing functional clampsEliminating adjustmentsLeast common multiple systemMechanisation
A brief thought …
The use of the SMED methodology to address run-up losses ?
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00 55.00 60.00 65.00 70.00 75.00 80.00 85.00 90.00
Clearing material of old job
Changing jigs (large jigs need two operators)
Loading jigs ready to set + get Material
Change Discs
Untighten Allen Screw on binary decoder
Looking for tools
Finding tools
Changing Electrode
Setting Weld Heat level
Water Off/ Water On
Check on Teach box if program is stopped
Sending Jigs in
Adjusting Decoders
Check Electrode Height Jig 1
Adjusting Weld heat settings Jig 1
Adjusting Electrodes alignment
Check Welds on Panel
Adjusting Weld heat settings Jig 2
Check Welds on Panel
Called away to sorting out problem with other m/c
Reload Jigs
Getting Material
Fasten screws on back side of decoder
Check bolts on electrodes
Putting Teach box away
start running machine
Getting Material
Unloading jig
Reload Jigs
Fasten screws on jig
Act
ivit
ies
time units
start of run-up
CHANGEOVER IMPROVEMENT PRACTICEThe need to measure performance and isolate individual tasks
ITBA - July 2007
Total elapsed changeover time
CHANGEOVER IMPROVEMENT PRACTICEThe ‘post-it note’ method
ITBA - July 2007
Objective: Faster Changeovers(Set-Up Reduction)
Objective 2: Higher Quality Changeovers
CHANGEOVER IMPROVEMENT PRACTICESeeking retrospective improvement: Preconceptions ?
ITBA - July 2007
‘SMED’Kaizen
Low cost>50%
Improvement
CURRENT CHANGEOVER PRACTICESeeking retrospective improvement: Preconceptions ?
ITBA - July 2007
Objective: Faster Changeovers(Set-Up Reduction)
CHANGEOVER IMPROVEMENT PRACTICEOrganisational improvement bias
ITBA - July 2007
CHANGEOVER IMPROVEMENT PRACTICEOrganisational improvement bias
ITBA - July 2007
Before
After
CHANGEOVER IMPROVEMENT PRACTICEOrganisational improvement bias – Standard Operating Procedure
ITBA - July 2007
Organisation-design spectrum
ORGANISATION DESIGN
Range for themajority of
programmes ?
100 % 100 %
ITBA - July 2007
Is adequate guidance and
emphasis provided towards this end of
the spectrum ?
REVIEWING IMPROVEMENT PRACTICE
Part II
Embracing design opportunities
GLOBAL OPPORTUNITIES
ITBA - July 2007
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
The ‘4Ps’
Design
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
Organisation
GLOBAL OPPORTUNITIES
ITBA - July 2007
The ‘4Ps’: Organisation and Design
Design improvement bias
CHANGEOVER IMPROVEMENT PRACTICE
ITBA - July 2007
Changeover time (39 bottle supports) = 60 minutes
Design improvement bias
CHANGEOVER IMPROVEMENT PRACTICE
ITBA - July 2007
Design improvement bias
CHANGEOVER IMPROVEMENT PRACTICE
ITBA - July 2007
Changeover time (39 bottle supports) = 39 minutes
Design improvement bias
CHANGEOVER IMPROVEMENT PRACTICE
ITBA - July 2007
Design improvement bias
CHANGEOVER IMPROVEMENT PRACTICE
ITBA - July 2007
Changeover time (39 bottle supports) = 6 minutes.. and much more precise + much cheaper to make
CHANGEOVER IMPROVEMENT PRACTICECase study conclusions
ITBA - July 2007
• Solution unlikely via SMED
Organisation-design spectrum: alternative opportunity conception
100 % ORG. 100 % DES.
“Do existing things better”
“Do better things”
ITBA - July 2007
CHANGEOVER IMPROVEMENT PRACTICE
“Do fewer, simpler things”
“Prepare better”
Organisation-design spectrum: attributes 2
100 % ORG. 100 % DES.
Achievable gainsSustainability
SkillCost
Implementation difficultyImplementation timeChangeover qualityImpact on run-up
????????
????????
ITBA - July 2007
CHANGEOVER IMPROVEMENT PRACTICE
ITBA - July 2007
• Quick release fasteners
• No tools
• Foolproof (no skill)
• Part count reduction
• Better access
• Modularisation
Retrospective improvement: “doing better things” (design-biased technique guidance)
SOME DESIGN RULES
• Reduction in variety (variability)
• Reduction in effort
• Precision fixed locations
• Pre-setting devices
• Clamping/securing devices
• Standardisation
• Adjustment scales + minimise adjustment
• Lightweight
• Movement/handling aids
• Universality
CHANGEOVER IMPROVEMENT
ITBA - July 2007
‘Universality’: an example
CHANGEOVER IMPROVEMENTBeverage can example ?
ITBA - July 2007
£ … € …
$ … ¥ …
ITBA - July 2007
DOUBLE ACTING CUPPING PRESS - CASE STUDY
Pre-improvement time: 48 hours
(Claimed) Post improvement time: 2 hours
ITBA - July 2007
Rear of the press
Pre-improvement
DOUBLE ACTING CUPPING PRESS - CASE STUDY
ITBA - July 2007
Coil feed assembly
Pre-improvement
DOUBLE ACTING CUPPING PRESS - CASE STUDY
ITBA - July 2007
Pre-improvement
Hard labour
DOUBLE ACTING CUPPING PRESS - CASE STUDY
ITBA - July 2007
Pre-improvement
More hard labour
DOUBLE ACTING CUPPING PRESS - CASE STUDY
ITBA - July 2007
Pre-improvement
Handling / Manipulation
DOUBLE ACTING CUPPING PRESS - CASE STUDY
ITBA - July 2007
Post-improvement
New hardware
DOUBLE ACTING CUPPING PRESS - CASE STUDY
ITBA - July 2007
Post-improvement
Hydraulic lifters / runners
DOUBLE ACTING CUPPING PRESS - CASE STUDY
ITBA - July 2007
Post-improvement
New hardware
DOUBLE ACTING CUPPING PRESS - CASE STUDY
GETTING IT RIGHTHirotec Corporation, Hiroshima
SOURCE: HIROTEC, www.hirotec.co.jp
GETTING IT RIGHTHirotec Corporation, Hiroshima – best in the world
SOURCE: HIROTEC, www.hirotec.co.jp
Part III
Changeover Game
ITBA - July 2007
CHANGEOVER GAME
3 Teams competing against one another
• Marked out of 10 for Changeover Time
• Marked out of 10 for Changeover Quality
--------------------------------------------
What problems ?
What organisational improvement opportunities ?
What design improvement opportunities ?
What time can you get it down to ??
Part IV
Other important issues
ITBA - July 2007
BEYOND SMED ?
Discussed so far …
• Financial benefit
• Appropriate design focus (retrospective and OEM)
• Changeover time and changeover quality
• Run-up as part of changeover (use of SMED ?)--------------------------------------------
Briefly, still to discuss …
• Changeover and maintenance
• Sustaining changeover gains
• A ‘post-SMED’ overall approach ?
ITBA - July 2007
MAINTENANCE 1
In one respect changeover is …
• The removal/replacement/adjustment of alternative part(s).
--------------------------------------------
In one respect maintenance is …
• The removal/replacement/adjustment of the same part(s).
Good changeover practice substantiallyequates to good maintenance practice
ITBA - July 2007
MAINTENANCE 2
All items involved in the changeover must be of requisite quality …
• Consumables
• Exchange machine components
• Fixed machine components
• Incoming product
ITBA - July 2007
MAINTENANCE 2
All items involved in the changeover must be of requisite quality …
ITBA - July 2007
MAINTENANCE 2
All items involved in the changeover must be of requisite quality …
ITBA - July 2007
SUSTAINABILITY
Changeover gains are not necessarily easily sustained …
0
6
4
2
Original changeover
Time
(1989)
Bestchangeover
Time
(1991)
Later changeover
Time
(1994)
ChangeoverTime(Hours)
?
ITBA - July 2007
SUSTAINABILITY
Changeover gains are not necessarily easily sustained …
0
6
4
2
Original changeover
Time
(1989)
Bestchangeover
Time
(1991)
Later changeover
Time
(1994)
ChangeoverTime(Hours)
ITBA - July 2007
SUSTAINABILITY
Changeover gains are not necessarily easily sustained …
0
6
4
2
Original changeover
Time
(1989)
Bestchangeover
Time
(1991)
Later changeover
Time
(1994)
ChangeoverTime(Hours)
“Do fewer, simpler things”
Need to put correct emphasis on design:
THE RATIONALE 1The cigarette company
ITBA - July 2007
An illustration of a demanding marketplace …
• Year 2000
- 47 billion cigarettes per annum – 2 brands
Outcome:Factory closes 2007
Factory prognosis:Not good
• Year 2004
- 24 billion cigarettes per annum > 100 brands
ITBA - July 2007
IMPROVEMENT TOOLS ?
The SMED methodology
• Some in-house design rules
• Some very general published design rules
• Embryonic DfC methodology (University of Bath)
• Cost/benefit analysis ?Contrast with DFMA
ITBA - July 2007
COMPLEXITY ?
“Changeover is typically interwoven with aspects of technical, personnel and behavioral issues (both in the immediate confines of the tasks being undertaken, and beyond).”
How, therefore, is classification of changeover events to be undertaken, in turn potentially guiding where improvement may be sought ?
Are current improvement tools sufficiently capable, or rather are they too blunt ?
GLOBAL OPPORTUNITIES
ITBA - July 2007
‘4Ps’ + Organisation/Design
Design
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
Organisation
GLOBAL OPPORTUNITIES
ITBA - July 2007
Design
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
Organisation
Realm of Improvement TechniquesProblem: complex activity
Requirement: simple, accessible improvement guidance, which embraces all opportunities
GLOBAL OPPORTUNITIES - CONCEPTUAL
ITBA - July 2007
Alter when tasks occur …
Alter what tasks occur …
SMEDDesign
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
Organisation
Realm of Improvement Techniques
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00 55.00 60.00 65.00 70.00 75.00 80.00 85.00 90.00
Clearing material of old job
Changing jigs (large jigs need two operators)
Loading jigs ready to set + get Material
Change Discs
Untighten Allen Screw on binary decoder
Looking for tools
Finding tools
Changing Electrode
Setting Weld Heat level
Water Off/ Water On
Check on Teach box if program is stopped
Sending Jigs in
Adjusting Decoders
Check Electrode Height Jig 1
Adjusting Weld heat settings Jig 1
Adjusting Electrodes alignment
Check Welds on Panel
Adjusting Weld heat settings Jig 2
Check Welds on Panel
Called away to sorting out problem with other m/c
Reload Jigs
Getting Material
Fasten screws on back side of decoder
Check bolts on electrodes
Putting Teach box away
start running machine
Getting Material
Unloading jig
Reload Jigs
Fasten screws on jig
Act
ivit
ies
time units
start of run-up
Total elapsed changeover time
GLOBAL OPPORTUNITIES - CONCEPTUAL
ITBA - July 2007
Alter when tasks occur …
Alter what tasks occur …
Externalise tasks ?
Tasks in parallel ?
Simplify tasks ?
Eliminate tasks ?
Design
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
Organisation
Realm of Improvement Techniques
GLOBAL OPPORTUNITIES - CONCEPTUAL
ITBA - July 2007
Alter when tasks occur …
Alter what tasks occur …
Reduce task complexity …
Reduce variability …(a sub-set of complexity)
Design
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
Organisation
Realm of Improvement Techniques
GLOBAL OPPORTUNITIES 1
ITBA - July 2007
Two fundamental improvement mechanisms – expanded into a useable tool ?
Reduce Complexit
y
Reduce Variabilit
y
Alter when tasks occur
Realm of all available
Improvement Techniques
Design
People Practice
ProcessProducts
Change Elements
ChangeoverActivities
Organisation
GLOBAL OPPORTUNITIES 2
ITBA - July 2007
Two fundamental improvement mechanisms – expanded into a useable tool ?
Reduce Complexit
y
Reduce Variabilit
y
Alter when tasks occur
1. Reduce Complexity (reduce activity count index)
2. Reduce Complexity (reduce activity difficulty index)
3. Optimize Task Sequence (optimise tasks to resources)
4. Optimize Task Sequence (optimise resources to tasks)
5. Reduce Variability (standardize work practices)
6. Reduce Variability (standardize physical entities)
Realm of all available
Improvement Techniques
GLOBAL OPPORTUNITIES 2
ITBA - July 2007
Two fundamental improvement mechanisms – expanded into a useable tool ?
Reduce Complexit
y
Reduce Variabilit
y
Alter when tasks occur
1. Reduce Complexity (reduce activity count)
2. Reduce Complexity (reduce activity difficulty)
3. Optimize Task Sequence (optimise tasks to resources)
4. Optimize Task Sequence (optimise resources to tasks)
5. Reduce Variability (standardize work practices)
6. Reduce Variability (standardize physical entities)
GLOBAL OPPORTUNITIES 2
ITBA - July 2007
Two fundamental improvement mechanisms – expanded into a useable tool ?
Reduce Complexit
y
Reduce Variabilit
y
Alter when tasks occur
1. Reduce Complexity (reduce activity count)
2. Reduce Complexity (reduce activity difficulty)
3. Optimize Task Sequence (optimise tasks to resources)
4. Optimize Task Sequence (optimise resources to tasks)
5. Reduce Variability (standardize work practices)
6. Reduce Variability (standardize physical entities)
Reflect on opportunity merit via the use of indices
Thank you for your attention