challenges facing performance evaluations of igcc … · thermal performance tests are the “final...
TRANSCRIPT
by
Justin Zachary and Lee SchmoeBechtel Power Corporation
Presented at
© Bechtel 2007. All rights reserved. 8130-10/07-1
Challenges Facing Performance Evaluations of IGCC Power Plants
Coal Gasification ConferenceSan Francisco, California
Thermal performance tests are the “FINAL EXAM”where the guarantees made by suppliers and contractors to owners must be demonstrated. Millions of dollars are at stake, so plan and prepare 4–5 years in advance!Conventional power plant performance tests are guided by ASME codes. To date, the testing procedures for gasification processes have been left to the discretion of the parties to the testA new performance code ASME PTC 47 has been specially developed for an IGCC power plant. Subcomponent procedures are in the works, so get involved now.
© Bechtel 2007. All rights reserved. 8130-10/07-2
8130-10/07-3© Bechtel 2007. All rights reserved.
Outline
Performance Test Code Basics
The Significance of Test Significance
Codes Applicability
Performance Guarantees
Test Tolerance Versus Test Uncertainty
Data Reduction Methodology
Summary and Recommendations
8130-10/07-4© Bechtel 2007. All rights reserved.
Performance Test Code Basics
1. Reach an agreement on the test philosophy and guarantee/test parameters during contract discussions
2. Determine the boundaries of the plant and define all the crossing streams
3. Design of the plant to accommodate accurate permanent and temporary instrumentation to match Step 2
4. Develop performance test procedures on how to collect data and correct to reference conditions
5. Conduct the test, collect data and perform the calculations to determine the guarantees at reference conditions
6. Demonstrate compliance or determine bonuses/ penalties
8130-10/07-5© Bechtel 2007. All rights reserved.
PTC 47 Overall Test Boundary
PowerBlock
GasificationBlock
Air Separation
Unit
MakeupWater and
Condensate
CoolingWater/Air
CoolingWater/Air
ExportSteam
NetPower
Vent N2
Inlet Air
Raw FuelSorbent
SecondaryFuel
ExportSyngas
VentGas
ImportSteam
HRSGExhaust
ByproductsAsh/Spent Sorbent
Sulfur/Sulfuric
ByproductsO2, N2
8130-10/07-6© Bechtel 2007. All rights reserved.
PTC 47.2Gasification
Block
Other IGCC Test Code Boundaries
PTC 47.4(PTC 46)Power Block
PTC 47.1Air
Separation Unit
PTC 47.3Fuel GasCleaning
N2
Raw FuelSorbent
SecondaryFuel
VentGas
Ambient Air
Power
Fuel Gas
Process Steam
Process Water
Condensate
Gasifier Steam
NitrogenAir
Cooling WaterProcess Water
Power
ByproductsAsh
Spent SorbentSulfur
Steam HRSG Exhaust
ByproductsO2, N2 Vent N2
MakeupWater and
CondensateCooling
Water/Air
CoolingWater/Air
ExportSteam
NetPower
O2
Required forTest Calculation
Not Required forTest Calculation
PTC 47.4Test
Boundary
SyntheticGas
8130-10/07-8© Bechtel 2007. All rights reserved.
PTC 47—IGCC Technical Challenges
IGCC plant test procedure differs from any existing codes for conventional power plants by attempting to evaluate in addition to Power Output and Heat Rate:
Direct solid fuel measurement of flow and compositionPoly generation byproducts: Sulfur, O2, N2, syngas
8130-10/07-9© Bechtel 2007. All rights reserved.
Test Significance—It’s Important!Thermal performance evaluation in a power plant is a challenging technical issue with very significant commercial implications. Typical case impact of performance on IGCC liquidated damages
Plant output Test Uncertainty %
LD's Value $/kW $
Power kW 450,000 2200 0.49 1,250 2,750,000
Plant Heat Rate
Test Uncertainty %
LD's Value $/(BTU/kWh) $
Heat Rate Btu/kWh 8,000 80 1 40,000 3,200,000
The Test Uncertainty of 0.5% Power and 1% HR equals $6M
8130-10/07-10© Bechtel 2007. All rights reserved.
Test Uncertainty and Test ToleranceTest Uncertainty is a technical issue dependent on:
Measurement uncertainty • Accuracy of the instrumentation (systematic and random errors) • Proper calibration
Test conductance and corrections methods• Correct conductance of test• Adequate data collection and processing
Test Uncertainty is determined by a well established statisticalanalysis (PTC 19.1)
Test Tolerances are commercial issues negotiated between the parties, to suit the project and financial institutions requirements.Test Uncertainty cannot be zero while Test Tolerance might be set at any value, including zero and equal to Test Uncertainty
8130-10/07-11© Bechtel 2007. All rights reserved.
Typical Test Uncertainties
Corrected ValuesPTC 46
Combined Cycle Example
PTC 46 Steam Cycle
ExamplePTC 47 Power-
Only Case
Input fuel flow 0.75% N/A 3%
Input fuel heating value 0.5% 1% 1%
Plant thermal efficiency 1.3% 1.6% 3.5%
Plant electrical output 0.8% 0.8% 1%
8130-10/07-12© Bechtel 2007. All rights reserved.
IGCC Plant Typical UncertaintiesCorrected Values
Power Only
Multiple Products
Input fuel flow
3%
3%
Input fuel heating value
1%
1%
Export syngas temperature
3 °C (5 °F)
Export syngas pressure (abs.)
½%
Export syngas composition
1%
Export syngas volumetric flow
1%
Export syngas heating value 1%
Export steam temperature 3 °C (5 °F)
Export steam pressure (abs.) ½%
Export steam flow 1%
Plant thermal efficiency 3.5% N/A
Plant electrical output 1% 1%
8130-10/07-13© Bechtel 2007. All rights reserved.
Challenges—Heat Input Evaluation
Due to the nature of the gasification process the direct heat input measurement is commonly used.
Inlet fuel HHV evaluationFuel flow measurement
Indirect method by conducting a carbon balance
Higher Overall Test Uncertainty than conventional coal-fired plants, due to direct measurement of the fuel flow
8130-10/07-14© Bechtel 2007. All rights reserved.
IGCC Plant Dry Coal Measurement
Precision Belt Scale System Claimed Accuracy 0.25% (will use conservatively 1% ) Source: Thermo Electron Ramsey)
8130-10/07-15© Bechtel 2007. All rights reserved.
CQM PGNAA—On-Line Coal Composition
Prompt Gamma Neutron Activation Analysis
PGNAA Measurements
and CalculationsS
AshMoisture
Heating ValueAsh Constituents
SiO2
Al2O3
Fe3O4
CaOTiO2
K2O
8130-10/07-16© Bechtel 2007. All rights reserved.
A B A*B C t*A*CSensitivity Systematic
UncertaintySystematic Uncertainty Contribution
Standard Deviation of the
Mean
student T Coeffcient
Random Uncertainty Contribution
∑((A*B)^2+t*(A*C)^2 )
(% per %, (%) (%) (%, oF, or oC) (%)Primary coal flow
0.951 3.000 2.853 0.300 2.000 0.5718.467
Primary fuel HHV
0.951 1.200 1.141 0.470 2.570 1.1492.622
Total Uncertainty 3.330
Measured Parameter
A B A*B C t*A*CSensitivity Systematic
UncertaintySystematic Uncertainty Contribution
Standard Deviation of the
Mean
student T Coeffcient
Random Uncertainty Contribution
∑((A*B)^2+t*(A*C)^2 )
(% per %, (%) (%) (%, oF, or oC) (%)Primary coal flow
0.951 1.000 0.951 0.300 2.000 0.5711.230
Primary fuel HHV
0.951 1.000 0.951 0.470 2.000 0.8941.704
Total Uncertainty 1.713
Measured Parameter
Current PTC 47 Test Uncertainty
PTC 47 Proposed Methodology to Reduce the Uncertainty
Example Test Uncertainty—Coal Heat Input
Lower Uncertainty = $5.2 Millions
8130-10/07-17© Bechtel 2007. All rights reserved.
Corrections To Reference Conditions
Boundary conditions (corrections)Air pressure, temperature and humidityFuel composition, temperatureHeat sink temperature
Controlled operating conditions (no corrections)Process steam, process heat Byproducts quantities and conditionCondensate return temperature
8130-10/07-18© Bechtel 2007. All rights reserved.
Computer Model or Correction Curves?Tests are almost never conducted at conditions specified in the Contract.Multi-variables curves (developed in polynomial and graphic form) are used to adjust data. The curves generation is done by using simulation program—tedious, expensive, time consuming and not quite correct …PTC 47 correction terms:
30 additive 24 multiplicative
The portable computer have tremendous calculus capability … Why not using the same simulation program directly?
8130-10/07-19© Bechtel 2007. All rights reserved.
Applying computer programs to convert concurrently all the variables to contract conditions, will insure that the mass, momentum, and energy balance are maintained in thermodynamic equilibrium.This method is not commonly implemented due to lack of a commercially acceptable “validation procedure.”Other test codes make reference to this approach as an alternative procedure. To date no real effort has been done to implement it.
Computer Model or Correction Curves
8130-10/07-20© Bechtel 2007. All rights reserved.
Summary and Recommendation
Parties in new IGCC projects should:Tackle the significant commercial challenges of performance testingConfigure the plant for proper testingAllow for special instrumentation in the design and cost
The existence of PTC 47 facilitates the process and provides much needed guidance. We can expect many lessons will be learned when the code recommendations start to be implemented.
Thermal performance of IGCC plants could achieve even lower test uncertainties with better instrumentation—more work is needed.