ch. 15 managing service projects

25
1 Ch. 15 Managing Service Projects

Upload: jalila

Post on 22-Jan-2016

45 views

Category:

Documents


0 download

DESCRIPTION

Ch. 15 Managing Service Projects. 常見的專案問題. 畢專:開學前完成計畫書( Gantt 圖) 畢旅,或系學會規劃運管營及交通盃 借鏡:訪談本系主辦運輸年會之經驗,老師提國科會計畫案 包括哪些 activity ? Critical path ?. Learning Objectives. 1. the nature of project management ( PM ) 2. project network and critical path analysis - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Ch. 15 Managing Service Projects

1

Ch. 15 Managing Service Projects

Page 2: Ch. 15 Managing Service Projects

2

常見的專案問題

1. 畢專:開學前完成計畫書( Gantt 圖)2. 畢旅,或系學會規劃運管營及交通盃3. 借鏡:訪談本系主辦運輸年會之經驗,老

師提國科會計畫案4. 包括哪些 activity ? Critical path ?

Page 3: Ch. 15 Managing Service Projects

3

Learning Objectives

1. the nature of project management (PM)

2. project network and critical path analysis

3. activity crashing: Cost-time Tradeoff

4. incorporating uncertainty in activity times

Page 4: Ch. 15 Managing Service Projects

4

1. The Nature of PM

Characteristics purpose, life cycle, interdependencies, uniqueness,

and conflict.

Process planning (work breakdown structure, WBS),

scheduling, and controlling.

Selecting the Project Manager credibility, sensitivity, ability to handle stress, and

leadership.

Page 5: Ch. 15 Managing Service Projects

5

1. The Nature of PM

Building the Project Team Forming, Storming, Norming, and Performing.

Principles of Effective PM direct people individually and as a team, reinforce excitement,

keep everyone informed, manage healthy conflict, empower team, encourage risk taking and creativity.

Project Metrics Cost, Time, Performance

Page 6: Ch. 15 Managing Service Projects

6

1. PM Questions (4W1H)

What activities are required to complete a project and in what sequence?

When should each activity be scheduled to begin and end?

Which activities are critical to completing the project on time?

What is the probability of meeting the project completion due date?

How should resources be allocated to activities?

Page 7: Ch. 15 Managing Service Projects

7

2. Techniques for PM

1. Gantt chart

2. Project network

Page 8: Ch. 15 Managing Service Projects

8

2. Tennis Tournament Activities

ID Activity Description Network Immediate Duration Node Predecessor (days)1 Negotiate for Location A - 22 Contact Seeded Players B - 83 Plan Promotion C 1 34 Locate Officials D 3 25 Send RSVP Invitations E 3 106 Sign Player Contracts F 2,3 47 Purchase Balls and Trophies G 4 48 Negotiate Catering H 5,6 19 Prepare Location I 5,7 310 Tournament J 8,9 2

Page 9: Ch. 15 Managing Service Projects

9

Notation for Critical Path Analysis

Item Symbol Definition

Activity duration t The expected duration of an activity

Early start ES The earliest time an activity can begin if all previous activities are begun at their earliest times

Early finish EF The earliest time an activity can be completed if it is started at its early start time

Late start LS The latest time an activity can begin without delaying the completion of the project

Late finish LF The latest time an activity can be completed if it is started at its latest start time

Total slack TS The amount of time an activity can be delayed without delaying the completion of the project

Page 10: Ch. 15 Managing Service Projects

10

Scheduling Formulas

ES = EFpredecessor (max) (1)

EF = ES + t (2)

LF = LSsuccessor (min) (3)

LS = LF - t (4)

TS = LF - EF (5)

TS = LS - ES (6) or

Page 11: Ch. 15 Managing Service Projects

11

Activity on Node Diagram

J2

B8

START

A2 C3 D2 G4

E10 I3

F4 H1

TS ES EF

LS LF

Page 12: Ch. 15 Managing Service Projects

12

Early Start Gantt Chart

ID Activity Days Day of Project Schedule 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20A Negotiate for 2 LocationB Contact Seeded 8 PlayersC Plan Promotion 3

D Locate Officials 2

E Send RSVP 10 InvitationsF Sign Player 4 ContractsG Purchase Balls 4 and TrophiesH Negotiate 1 CateringI Prepare Location 3

J Tournament 2

Personnel Required 2 2 2 2 2 3 3 3 3 3 3 2 1 1 1 2 1 1 1 1

Critical Path ActivitiesActivities with Slack

Page 13: Ch. 15 Managing Service Projects

13

Resource Leveled Schedule

ID Activity Days Day of Project Schedule 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20A Negotiate for 2 LocationB Contact Seeded 8 PlayersC Plan Promotion 3

D Locate Officials 2

E Send RSVP 10 InvitationsF Sign Player 4 ContractsG Purchase Balls 4 and TrophiesH Negotiate 1 CateringI Prepare Location 3

J Tournament 2

Personnel Required 2 2 2 2 2 2 2 2 2 2 2 2 2 3 2 2 2 2 1 1

Critical Path ActivitiesActivities with Slack

Page 14: Ch. 15 Managing Service Projects

14

3. Costs for Hypothetical Project

Cos

t

(0,0)

Schedule with Minimum Total Cost

Duration of Project

Total Cost

Indirect Cost

Opportunity Cost

Direct Cost

Page 15: Ch. 15 Managing Service Projects

15

Cost-Time Estimates

Time Estimate Direct Cost Expedite CostActivity Normal Crash Normal Crash Slope A 2 1 5 15 10 B 8 6 22 30 4 C 3 2 10 13 3 D 2 1 11 17 6 E 10 6 20 40 5 F 4 3 8 15 7 G 4 3 9 10 1 H 1 1 10 10 - I 3 2 8 10 2 J 2 1 12 20 8 Total 115

Page 16: Ch. 15 Managing Service Projects

16

Activity Cost-time Tradeoff

C

C*

D* D Activity Duration (Days)

Normal

CrashSlope is cost to expedite per day

Cost

Page 17: Ch. 15 Managing Service Projects

17

Progressive Crashing

Project Activity Direct Indirect Opportunity TotalDuration Crashed Cost Cost Cost Cost 20 Normal 115 45 8 168 19 41 6 18 37 4 17 33 2 16 29 0 15 25 -2 14 21 -4 13 17 -6 12 13 -8

Normal Duration After Crashing ActivityProject Paths DurationA-C-D-G-I-J 16A-C-E-I-J 20A-C-E-H-J 18A-C-F-H-J 12B-F-H-J 15

Page 18: Ch. 15 Managing Service Projects

18

4. Incorporating Uncertainty in Activity times

A M D B

F(D)P(D<A) = .01

P(D>B) = .01

optimistic most pessimistic likely

TIME

Page 19: Ch. 15 Managing Service Projects

19

Formulas for Beta Distribution of Activity Duration

1. Expected Duration

DA M B_

4

6

2. Variance

VB A

6

2

Note: (B - A )= Range or 6

Page 20: Ch. 15 Managing Service Projects

20

Activity Means and Variances

Activity A M B D V A 1 2 3 B 5 8 11 C 2 3 4 D 1 2 3 E 6 9 18 F 2 4 6 G 1 3 11 H 1 1 1 I 2 2 8 J 2 2 2

Page 21: Ch. 15 Managing Service Projects

21

Uncertainly Analysis

Assumptions1. Use of Beta Distribution and Formulas For D and V2. Activities Statistically Independent3. Central Limit Theorem Applies ( Use “student t” if less than 30 activities on CP) 4. Use of Critical Path Activities Leading Into Event Node

ResultProject Completion Time Distribution is Normal With:

For Critical Path Activities

For Critical Path Activities

D_

2 V

Page 22: Ch. 15 Managing Service Projects

22

Completion Time Distribution

Critical Path Activities D V A 2 4/36 C 3 4/36 E 10 144/36 I 3 36/36 J 2 0

= 20 188/36 = 5.2 = 2

Page 23: Ch. 15 Managing Service Projects

23

Question

What is the probability of an overrun if a 24 day completion time is promised?

24

P (Time > 24) = .5 - .4599 = .04 or 4%

Days

2 5 2 .

ZX

Z

Z

24 20

52175

..

Page 24: Ch. 15 Managing Service Projects

24

Discussion: Applying Theory of Constraints (TOC) to PM

Why does activity safety time exist and is subsequently lost?1. The “student syndrome” procrastination phenomena.2. Multi-tasking muddles priorities.3. Dependencies between activities cause delays to accumulate.

Buffer: Reduce by ½ all activity durations > 3 days to eliminate safety time

Software: Project 2000

Page 25: Ch. 15 Managing Service Projects

25

Exercise

Prepare a work breakdown structure (WBS) for a homecoming dance.