TO: Kari Parsons, DSD-Project Manager FROM: Richard Schindler, Core Engineering Group DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General 1. Note: The portions of existing and proposed easements (utility, access, etc.) that overlap with proposed/future public road rights-of-way need to be vacated/terminated at the time of platting of the rights-of-way. Address this specifically in the letter of intent. Response: text is added to letter of intent Construction Plans 1. Revise the County signature block to replace the last sentence with the following: “In accordance with ECM Section 1.12, these construction documents will be valid for construction for a period of 2 years from the date signed by the El Paso County Engineer. If construction has not started within those 2 years the plans will need to be resubmitted for approval, including payment of review fees at the Planning and Community Development Director’s discretion.” 2. Provide complete details on sheet S1 when available. Response: text added. 3. Provide P.E. signature and stamp on all pages with the final submittal. Response: added 4. The proposed alignment of the sanitary sewer is not consistent through Fontaine Blvd. With the future 4-lane principal arterial it appears that the manholes could potentially conflict with the left lane/shoulder line. Verify if the sewer line can all be aligned with the present and future centerline (median). Additional cross-sections on the plan or a separate exhibit showing all proposed and future cross sections (4) would be helpful. Response: the two manholes next to the roundabout are in the center of the road so that the roundabout isn’t blocked during routine maintenance of the sewer. The other three manholes are located 13’ from the centerline. The future lane line will be located 13.5’ from the center of the road. This should be okay. 5. See electronic CD redlines for further minor comments, questions and clarification of these comments. Grading and Erosion Control Plan / SWMP 1. Include all relevant GEC checklist items; missing, incomplete, and unclear items are highlighted on the checklist. Response: Relevant information provided. 2. Include all areas to be graded and/or disturbed with sanitary sewer construction on the GEC plan. Additional GEC sheets appear to be required. Response: detail sheets added. I don’t know what the total disturbed area will be because it depends on methods of construction, i.e, double trench boxes may be used which will reduce footprint of disturbance. We protect the important features like the Etrib and perimeter control is required there as construction progresses. The other areas drain to detention ponds that Lorson owns or to our proposed sediment basin. This is a simple construction plan for sanitary sewer. We will take care of the erosion control and the SWMP will be updated in the field as necessary. 3. SWMP: a. Ensure that all checklist items (attached) are provided. Notation/explanation must be provided for items that are not applicable. Response: added to swmp

Upload: others

Post on 06-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

TO: Kari Parsons, DSD-Project Manager FROM: Richard Schindler, Core Engineering Group DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to

comments

General 1. Note: The portions of existing and proposed easements (utility, access, etc.) that overlap with

proposed/future public road rights-of-way need to be vacated/terminated at the time of platting of the rights-of-way. Address this specifically in the letter of intent. Response: text is added to letter of intent

Construction Plans

1. Revise the County signature block to replace the last sentence with the following: “In accordance with ECM Section 1.12, these construction documents will be valid for construction for a period of 2 years from the date signed by the El Paso County Engineer. If construction has not started within those 2 years the plans will need to be resubmitted for approval, including payment of review fees at the Planning and Community Development Director’s discretion.”

2. Provide complete details on sheet S1 when available. Response: text added. 3. Provide P.E. signature and stamp on all pages with the final submittal. Response: added 4. The proposed alignment of the sanitary sewer is not consistent through Fontaine Blvd. With the

future 4-lane principal arterial it appears that the manholes could potentially conflict with the left lane/shoulder line. Verify if the sewer line can all be aligned with the present and future centerline (median). Additional cross-sections on the plan or a separate exhibit showing all proposed and future cross sections (4) would be helpful. Response: the two manholes next to the roundabout are in the center of the road so that the roundabout isn’t blocked during routine maintenance of the sewer. The other three manholes are located 13’ from the centerline. The future lane line will be located 13.5’ from the center of the road. This should be okay.

5. See electronic CD redlines for further minor comments, questions and clarification of these comments.

Grading and Erosion Control Plan / SWMP

1. Include all relevant GEC checklist items; missing, incomplete, and unclear items are highlighted on the checklist. Response: Relevant information provided.

2. Include all areas to be graded and/or disturbed with sanitary sewer construction on the GEC plan. Additional GEC sheets appear to be required. Response: detail sheets added. I don’t know what the total disturbed area will be because it depends on methods of construction, i.e, double trench boxes may be used which will reduce footprint of disturbance. We protect the important features like the Etrib and perimeter control is required there as construction progresses. The other areas drain to detention ponds that Lorson owns or to our proposed sediment basin. This is a simple construction plan for sanitary sewer. We will take care of the erosion control and the SWMP will be updated in the field as necessary.

3. SWMP: a. Ensure that all checklist items (attached) are provided. Notation/explanation must be

provided for items that are not applicable. Response: added to swmp

Page 2: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

b. Note: some checklist items (including items 5, 6, 10, and 16) may be deferred to the contractor. Provision of the information is required at the time construction begins.

Forms/Financial Assurance Estimate Form

1. Provide a Financial Assurance Estimate for all grading and erosion control items. Account for all necessary BMPs. Response: EGF for grading will be provided with Lorson East since that is where all the material is coming from. No EGF needed for sanitary sewer construction.

Attachments/Electronic Files

1. CD/GEC redlines 2. SWMP redlines 3. GEC Checklist 4. SWMP Checklist 5. Engineering Final Submittal Checklist

El Paso County Grading and Erosion Control Plan Submittal Checklist

1) Vicinity map. 2) North arrow and acceptable scale (1”=20’ to 1”=100’). 3) Existing and proposed Contours 2 feet or less (except for hillside). 4) Standard EPC Grading and Erosion Control Notes included. 5) Delineate mapped FEMA 100-yr floodplain. 6) Construction site boundaries clearly delineated.

Response: boundary added 7) Areas of soil disturbance shown.

Response: boundary added

8) All proposed construction BMPs and Construction BMP details shown. Response: detail sheet added

9) Show existing vegetation. 10) Existing and proposed water courses including springs, streams, wetlands, Detention

ponds, roadside ditches, irrigation ditches and other water surfaces. 11) Show all existing structures. 12) Show all existing utilities. 13) Submit geotechnical investigation from soils engineer. 14) Conclusions from soils report and geologic hazards report incorporated in grading design.

15) Show existing and proposed property lines and site boundary.

Response: property lines added. Lorson owns all property affected 16) All existing and proposed easements (permanent and construction).including required off site

easements. Response: lorson owns all property affected by this construction

17) Any offsite grading clearly shown and called out. 18) Existing and proposed storm drainage facilities as necessary to show all BMPs. 19) Temporary sediment ponds provided for disturbed drainage areas greater than one acre.

20) Proposed slopes steeper than 3:1 with top and toe of slope delineated. 21) Erosion control blanketing shown on slopes steeper than 3:1. 22) Retaining walls greater than or equal to 4ft in height require design by P.E. and building

permit from Regional Building Department. Locations to be shown on the plan (not located in County ROW).

23) Vehicle tracking shown at all construction entrances.

Page 3: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

Response: two vehicle tracking pads shown. 24) The erosion control plan is to be certified by a Colorado Registered P.E. with appropriate

signature blocks for EPC and the Engineer and the statement “The Owner will comply with the requirements of the Erosion Control Plan” signed by the owner.

25) Required Signature blocks:

Page 4: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

Stormwater Management Plan Checklist 1 Applicant (owner/designated operator), Prepared By, SWMP Administrator, and Contractor

information

2 Table of Contents 3 Site description and location to include vicinity map (not just Section, Township, Range) 4 Narrative description of construction activities proposed (e.g., may include clearing and grubbing,

temporary stabilization, road grading, utility / storm installation, final grading, final stabilization, and removal of temporary control measures)

5 Phasing plan – may require separate drawings indicating initial, interim, and final site phases for larger projects. Provide “living maps” that can be revised in the field as conditions dictate.

6 Proposed sequence for major activities: Provide a construction schedule of anticipated starting and completion dates for each stage of land-disturbing activity depicting conservation measures anticipated, including the expected date by which the final stabilization will be completed.

7 Estimates of the total site area and area to undergo disturbance 8 Soil erosion potential and potential impacts upon discharge 9 A description of existing vegetation at the site and percent ground cover 10 The location and description of any other potential pollution sources such as fueling (mobile or

stationary), chemical storage, etc.

11 Material handling to include spill prevention and response procedures 12 Spill prevention and pollution controls for dedicated batch plants 13 Other stormwater pollutant control measures to include waste disposal and cleanup of off-site

soil tracking

14 The location and description of any anticipated non-stormwater components of discharge (springs, irrigation, etc.)

15 The name of ultimate receiving waters; size, type and location of stormwater outfall or storm sewer system discharge

16 SWMP Map to include: a) construction boundaries b) all areas of disturbance c) areas of cut and fill d) areas used for storage of building materials, soils or wastes (stockpiles) e) location of any dedicated asphalt / concrete batch plants f) location of all structural BMPs g) location of all non-structural BMPs h) springs, streams, wetlands and other surface waters 17 Narrative description of all structural BMPs to be used, including: silt fence, straw bales, check

dams, sediment basins, diversion swales, etc. Ensure that methods are ECM/DCM-approved.

18 Description of non-structural BMPs to be used including seeding, mulching, protection of existing vegetation, site watering, sod placement, etc.

19 Technical drawing details for BMP installation and maintenance 20 Procedure for how the SWMP will be revised 21 Description of final stabilization and long-term stormwater quality measures to control stormwater

pollutants after construction operations have been completed

22 Specification that vegetative cover density is to be a minimum of 70% of pre-disturbed levels to be considered stabilized

23 Outline of permit holder inspection procedures to install, maintain, and effectively operate BMPs to manage erosion and sedimentation

24 Record keeping procedures identified to include signature on inspection logs and location of SWMP records onsite

Please note: all items need to be addressed. If not applicable, explain; simply identifying “not applicable” will not satisfy CDPHE requirement of explanation. Response: Items 5&6 already in plan. Item 8-statement added in section 3. Item 12-no batch plants proposed and noted in report. Item 14- section 6.2.7 updated. Items 16b,c,d,f,g added to plans. Item 16e-no batch plants proposed, section 5.9 added. Item 19-detail sheet added. Item 24-location added.

Page 5: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

Engineering Final Submittal Checklist for Electronic Submittals

Check Box Item: Report/Form, Full-Size Plan (F), 11”x17” Plan (H)

Drainage Report (signed)

Traffic Impact Study (signed)

Grading & Erosion Control Plan (signed)

Street Construction Plans (signed)

Deviation Request (signed)

MS4 Post Construction Form and SDI worksheet DPW POC: John Chavez

Proof of embankment/pond submittal to State Engineer

ESQCP (signed) DPW POC: John Chavez

* Financial Assurance Estimate, SIA (signed)

* Pond/BMP Maint. Agreement and Easement (signed)

* Operation & Maintenance Manual

Pre-Development Site Grading Acknowledgement and Right of Access Form (signed)

Other: Offsite Easements, Other Permits (FEMA LOMR, USACE, Floodplain…), Conditions of Approval, etc. _

Pre-Construction Checklist:

Work Within the ROW Permit (DPW or CDOT)

* Stormwater Management Plan (SWMP) Submit to DSD-Inspection 2 weeks prior to precon

* Colorado Discharge Permit (COR:______________________ )

* County Construction Activity Permit

* CDPHE APEN – (if over 25 ac. or 6 mos.)

* Financial Surety (Letter of Credit/Bond/Collateral/Check)

Construction Permit Fee:

Early Grading or Standalone Grading (Verify fees with Inspections Supervisor at time of scheduling)

$ 1,637.00

* - required items to obtain an ESQCP

** - after recordation

Permit Fee and Collateral must be separate checks

Post Construction Submittal Checklist: (ECM 5.10.6)

As-Built Drawings

Pond Certification Letter

Acceptance Letter for wet utilities

COLORADO SPRINGS UTILITIES Gas and Electric Utilities Review Comments Action Items:

Page 6: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

1. All utility line and storm pipe crossings shall be installed above the SDS pipe with clearances approved by CSU. Response: noted 2. The engineer must obtain CSU approval of all utility line and storm pipe construction drawings, which shall show pipe-to-pipe clearances based on pothole data of the SDS water main. Response: added to plans 3. CSU requires that CSU Inspections Department be contacted and be onsite to witness any construction work or potholing within the SDS easement. To coordinate, please contact CSU Inspections Supervisor, Steve Vigil, at (719) 668-4658 ([email protected]). Response: noted 4. A CSU signature block is required on construction drawing sheets showing SDS crossings. See CSU Water Line Extension and Service Standards section 3.6.A for signature block template. Response: added to cover sheet 5. CSU will continue to work with the applicant to address the CSU concerns and comments. Response: noted

Page 7: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Text Box
Provide a GEC details sheet
RSchindler
Callout
sheet added
Page 8: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 9: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 10: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Callout
Include seeding and mulching
dsdrice
Callout
Not found
dsdrice
Cloud+
dsdrice
Cloud+
Does this 3.5 ac. include the diverted area?
dsdrice
Callout
Show pads. Show and label haul roads.
RSchindler
Callout
this is only the disturbed area
RSchindler
Callout
line made bigger. its halfway up the 4:1 slope
RSchindler
Callout
ACCESS ROUTE LABELED. HAUL ROAD PREVIOUSLY LABELED
RSchindler
Callout
MULCH AND SEEDING LABELED
Page 11: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 12: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Callout
Provide copy or reception number
RSchindler
Callout
THIS IS A PROPOSED EASEMENT
Page 13: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Cloud+
dsdrice
Cloud+
See General comment #1
RSchindler
Callout
EASEMENT WILL BE VACATED IN THE FUTURE. ADDED TO LETTER OF INTENT.
Page 14: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 15: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Cloud+
dsdrice
Cloud+
See General comment #1
RSchindler
Callout
EASEMENT WILL BE VACATED IN THE FUTURE. ADDED TO LETTER OF INTENT.
Page 16: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 17: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Length Measurement
16'-3"
dsdrice
Length Measurement
11'-10"
RSchindler
Callout
CALLOUTS ADDED
RSchindler
Callout
CALLOUTS ADDED
Page 18: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Length Measurement
15'-0"
dsdrice
Length Measurement
25'-0"
dsdrice
Callout
Why is the alignment diverging from centerline?
RSchindler
Callout
WE MOVED THIS TO THE CENTERLINE BECAUSE WWSD WILL PUT A VACTRUCK OVER THE MANHOLE TO DO MAINTENANCE AND IT WOULD BLOCK THE ROUNDABOUT
RSchindler
Callout
CALLOUTS ADDED
Page 19: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 20: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 21: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

Markup Summary

Subject: Text BoxPage Label: 1Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:46:06 PMColor:

Provide a GEC details sheet

dsdrice (13)

Subject: CalloutPage Label: 4Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:27:06 PMColor:

Show pads. Show and label haul roads.

Subject: CalloutPage Label: 4Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:18:57 PMColor:

Include seeding and mulching

Subject: CalloutPage Label: 4Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:19:54 PMColor:

Not found

Subject: Cloud+Page Label: 4Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:22:00 PMColor:

Does this 3.5 ac. include the diverted area?

Subject: CalloutPage Label: 6Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/2/2017 4:32:17 PMColor:

Provide copy or reception number

Provide a GEC details sheet

Show pads. Show andlabel haulroads.

Includeseeding and

mulching

Not found

Does this 3.5ac. include thediverted area?

Provide copyor receptionnumber

Page 22: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

Subject: Cloud+Page Label: 7Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:11:23 PMColor:

See General comment #1

Subject: Cloud+Page Label: 9Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:10:54 PMColor:

See General comment #1

Subject: Length MeasurementPage Label: 11Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/3/2017 9:28:15 AMColor:

16'-3"

Subject: Length MeasurementPage Label: 11Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/3/2017 9:28:41 AMColor:

11'-10"

Subject: CalloutPage Label: 12Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/3/2017 9:31:40 AMColor:

Why is the alignment diverging from centerline?

Subject: Length MeasurementPage Label: 12Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/3/2017 9:26:40 AMColor:

15'-0"

See Generalcomment #1

See Generalcomment #1

16'-3

"11

'-10"

Why is the alignmentdiverging from centerline?

15'-0

"

Page 23: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

Subject: Length MeasurementPage Label: 12Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/3/2017 9:27:00 AMColor:

25'-0"

25'-0"

Page 24: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

STORMWATER MANAGEMENT PLAN

FOR EAST JIMMY CAMP CREEK INTERCEPTOR SANITARY SEWER CONSTRUCTION

Stormwater Permit # __________

Certification # __________

Owner/Developer: Lorson, LLC

212 N. Wahsatch Avenue, Suite 301 Colorado Springs, Colorado 80903

Contact: Jeff Mark (719) 635-3200

SWMP Administrator:

TNT Landscaping, Inc

Trevor Terrill 4795 Mark Dabling Rd.

Colorado Springs, Colorado 80918 (719) 659-5619

Engineers:

Core Engineering Group, LLC 15004 1st Avenue S.

Burnsville, MN 55306 Contact: Richard Schindler, P.E.

(719) 570-1100

Page 25: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 2 -

SWMP Location On-site (copy) and Lorson, LLC (original)

Page 26: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

TABLE OF CONTENTS TABLE OF CONTENTS SWMP REPORT REVISION LOG 1.0 INTRODUCTION 1

2.0 SEQUENCE OF MAJOR ACTIVITIES 2

3.0 PRE-DEVELOPMENT CONDITIONS 3

4.0 DEVELOPED CONDITIONS 4

5.0 POTENTIAL SOURCES OF POLLUTION AND CONTROL STRATEGIES 4

6.0 BEST MANAGEMENT PRACTICES 7

7.0 SPILL PREVENTION PLAN 11

8.0 INSPECTIONS 14

9.0 RECORDS MANAGEMENT 14

10.0 FINAL STABILIZATION 15

APPENDIX A: VICINITY MAP APPENDIX B: EASTJIMMY CAMP CREEK INTERCEPTOR SANITARY SEWER CONSTRUCTION PLANS, DATED SEPTEMBER 8, 2017 BY CORE ENGINEERING GROUP

APPENDIX C: STORMWATER INSPECTION REPORTS (BY REFERENCE ONLY

NOT ATTACHED)

APPENDIX D: SPILL REPORT FORM

APPENDIX E: RECORD OF STABILIZATION AND CONSTRUCTION ACTIVITY DATES

APPENDIX F: FEDERAL, STATE, OR LOCAL STORM WATER OR OTHER

ENVIRONMENTAL INSPECTOR SITE VISIT LOG

APPENDIX G: GENERAL PERMIT AND APPLICATION

Page 27: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 4 -

SWMP REPORT REVISION LOG REV. # DATE: BY: COMMENTS Initials

1.

2.

3.

4.

5.

Page 28: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 1 -

1.0 INTRODUCTION The proposed East Jimmy Camp Creek Interceptor Sanitary Sewer Construction is currently farm and ranching land. Approximately 6.25acres will be rough graded and 9 acres (5,200 feet of sewer) will be disturbed with this project. The site is located on the west side of the East Tributary of Jimmy Camp Creek and extends north to Fontaine Boulevard. There is a sanitary sewer lateral extending east but that will be covered under a separate permit. See vicinity map in the appendix. The property drains generally south towards the East Tributary of Jimmy Camp Creek. East Jimmy Camp Creek Interceptor Sanitary Sewer Construction consists of 5,200 feet of sanitary sewer and 6.25acres of rough grading which will be constructed in one phase. Lorson, LLC is the overall developer and will construct major infrastructure. The off-site borrow area will be accessed by a haul road across Lorson Boulevard and is located east of the East Tributary of Jimmy Camp Creek and will be covered under a separate permit for Lorson Ranch East. The off-site borrow area will generate fill necessary to grade the on-site areas. 2.0 SEQUENCE OF MAJOR ACTIVITIES – Exhibit 1 Construction The anticipated date for beginning construction activities is November, 2017 and will be complete in June, 2018. Implementation of the storm water management plan should be in place prior to initiating construction activities. The anticipated sequence of construction is as follows: 1. Installation of perimeter erosion control measures as shown on Exhibit 1 2. Site Clearing/Grubbing and topsoil stockpiling. 3. Construct sediment pond 4. Install erosion control measures along trench excavation as construction progresses 5. Construct underground sewer and rough grading 6. Replace topsoil and final stabilize disturbed areas along sewer lines and rough grading

areas 7. Final erosion control measures as areas are completed 3.0 PRE-DEVELOPMENT CONDITIONS According to the current FEMA Flood Insurance Rate Map (FIRM) number 08041CO957 F, this site is located within the 100-year floodplain. Grading is proposed within the floodplain which is included in CLOMR Case No. 17-08-1043R. Grading shall not occur until the CLOMR has been approved by FEMA. Construction of the sanitary sewer can occur at any time after permits from El Paso County are secured. Existing Vegetation: The site is currently undeveloped and has been used as a farm field (alfalfa) for the past several years. The farm field is currently used a hay field. Ground cover is estimated at 85% coverage Existing Slopes: Existing slopes are around 1% that direct runoff southerly to the East Tributary of Jimmy Camp Creek. No grading will be done in the floodway of the East Tributary of Jimmy Camp Creek.

Page 29: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 2 -

Existing Drainage Patterns: Pre-development drainage patterns include flowing southerly to the East Tributary of Jimmy Camp Creek. The drainage patterns will remain the same after construction. A sediment pond will be constructed downstream of the rough grading area. Existing Soil Types: The following table summarizes the characteristics of the soil type. Table 3.1: SCS Soils Survey

Soil Hydro. Group

Shrink/Swell Potential

Permeability Surface Runoff

Potential

Erosion Hazard

Manzanola Clay Loam (52)

C Moderate to

High Slow Medium Moderate

Nunn Clay Loam (59)

C Moderate to

High Slow Medium Moderate

Based upon the location of the different soil types and type of construction, the contractor shall employ the most appropriate method of erosion control measures based on the El Paso County/City of Colorado Springs Drainage Criteria Manual, Vol. 2 or as directed by the SWMP administrator or his representative. More detailed soils information can be found in the SCS soils survey for El Paso County. 4.0 DEVELOPED CONDITIONS The overall drainage concept for East Jimmy Camp Creek Interceptor Sanitary Sewer Construction will not be changed due to this construction. Proper erosion protection will be installed so no sediment is discharged offsite. No land use changes are proposed with this construction. Construction Site Estimates:

Project Site: 15.25 acres Disturbed Area: 6.25 acres (rough grading), 9 acres (sewer construction)

Percent Impervious before Construction: 0% Runoff Coefficient before Construction: 0.35

Percent Impervious after Construction: 0% Runoff Coefficient after Construction: 0.35

Receiving Waters:

East Tributary of Jimmy Camp Creek Description: The creek channel is a dry creek bed that flow water intermittently after

significant rainfall events in the drainage basin. Description of Storm Sewer System: There is no existing storm sewer system on the

site.

Page 30: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 3 -

Description of impaired waters or waters subject to TMDLs: The site contains no impaired waters or waters subject to TMDLs.

Description of unique features that are to be preserved: There are no known protected plant species within the project limits.

Describe measures to protect these features: N/A

Site Features and Sensitive Areas to be Protected: Portions of this site are located within waters of the state (100-year floodplain) but they contain no other sensitive areas including wetlands or endangered species and no grading will occur in the floodway of the creek. 5.0 POTENTIAL SOURCES OF POLLUTION AND CONTROL STRATEGIES Potential sources of sediment to stormwater runoff include earth moving and concrete activities associated with grading and landscaping. Potential pollutants and sources, other than sediment, to stormwater runoff include Trash, debris, line transfer, Dewatering, fueling and equipment failure. A dewatering permit is not required Construction activities produce many different kinds of pollutants which may cause storm water contamination problems. Grading activities remove rocks, vegetation and other erosion controlling surfaces, resulting in the exposure of underlying soil to the elements. Because the soil surface is unprotected, soil and sand particles are easily picked up by wind and/or washed away by rain or other water sources. The following sections highlight the potential sources of pollution at the Project Site and list the “Best Management” strategies that will be used to prevent migration of pollution offsite. Chemical materials stored indoors or that have no reasonable chance of impacting storm water quality will not be discussed in this plan. Materials of significance stored on the project site include:

Sediment Concrete Washout Cement Trash & Debris Sanitary Wastes Fuels & Oils

5.1 Wind Erosion & Dust Control Pollutant: Sediment Best Management Strategies: Daily inspections will occur for areas experiencing excessive winds, vehicle traffic, or

precipitation events. Water trucks will spray down dust on the project Site as needed to not impact adjacent

properties.

Page 31: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 4 -

Attention will be given to prevent the over use of water in dust control operations to minimize any muddying of the surface and possible sediment transportation.

5.2 Vehicular Transport Pollutant: Sediment Tracking Best Management Strategies: Construct a stabilized construction entrance to provide ingress and egress of the site. Restrict access to the stabilized construction entrance. Fencing will be erected if problems with access control are evident. Maintain track out pads by fluffing up the rock material or by adding additional rock as

needed. Inspect, sweep and clean adjacent streets where track out is evident.

5.3 Stockpiles Pollutant: Sediment Best Management Strategies: Locate stockpiles clear of any water flow paths. Locate stockpiles within the property boundary. Stockpiles will have erosion control devices as needed installed around the base to

prevent the migration of soil. Topsoil stock piles and disturbed portions of the site where construction activity

temporarily ceases for at least 14 days will be stabilized with temporary seed and mulch no later than 14 days from the last construction activity in the area.

5.4 Grading, Trenching, Export/Import Pollutant: Sediment Best management Strategies: Earth moving will be minimized by the engineering balancing of the site. Disturbed portions of the site where construction activity temporarily ceases for at least

14 days will be stabilized with temporary seed and mulch no later than 14 days from the last construction activity in the area.

Seed bed preparation is not required if soil is in loose condition. Prior to seeding, fertilizer shall be applied to each acre to be stabilized in accordance

with the manufacturer’s specifications. If required seeding areas shall be mulched with straw to a uniformed cover. The straw

mulch is to be tacked into place by a disk with blades set nearly straight. A site specific erosion control drawing has been developed showing the location of Best

Management practices to be used during site construction. Where indicated on the erosion control plan, Best Management Practices will be

installed. Material shall be in accordance with the plans and specifications and all construction

shall be provided in accordance with the manufacturer’s specifications. All BMP’s will be inspected bi-weekly and cleaned/maintained as required.

5.5 Waste, Residual Concrete Pollutant: Concrete, paint, and Phosphoric Acid Best Management Strategies: A cleanup and washout area will be designated and posted.

Page 32: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 5 -

Subcontractors will be instructed on the locations and importance of the washout and cleanup areas. No on-site disposal is allowed.

Instruct subcontractors to remove waste for which proper onsite disposal facilities are not provided back to their own facilities for ultimate transport, storage & disposal.

Subcontractors and subcontractor employees are held responsible for improper washout.

5.6 Sanitary Facilities, Trash Containers & Littering Pollutant: Bacteria, Ammonia, Trash Best Management Strategies: Portable facilities will be regularly serviced to prevent excessive waste containment and

overflow. All waste materials will be collected and stored in a container which will meet all local

and any state solid waste management regulations. Trash dumpsters will be emptied prior to becoming 90% full or when debris control

becomes an issue. Employees will be instructed on the importance of recycling and waste management,

and will be held responsible for improper waste management. 5.7 Fueling, Hazardous Materials, Equipment Leakage, Fertilizer Pollutant: Petroleum Hydrocarbons, Ethylene Glycol, Sediment Best Management Strategies: MSDS sheets will be maintained in the project trailer for all onsite materials All dry materials such as cement will be covered and protected from rain. Secondary containment will be provided for stored fuel, oil, paint and any material

classified as hazardous. Subcontractors are responsible for hazardous waste removal back to their own facilities

for ultimate transportation, storage and disposal. Supplies will be kept onsite as necessary to control any potential spill. Employees will be held responsible for any illegal dumping. Seals will be checked by a qualified professional on all equipment and containers

containing significant materials that could contribute potential pollutants and will be replaced as necessary.

Equipment will be inspected by a qualified professional. Drip pans will be available for minor leaks and during fueling operations. Fueling nozzles, gauges, hoses, seals, and emergency shutoff valves will be inspected

for leaks prior to use. Under no circumstances during fueling will the fueling hose/nozzle be left unattended. Fertilizers used will be applied only in the minimum amounts recommended by soil tests. Once applied, fertilizers will be worked into the soil to limit exposure to storm water. Stored fertilizer will be protected from exposure to precipitation and storm water runoff.

5.8 Dewatering – not needed. This shown for information only Pollutant: Sediment, Oil and/or Grease and Phosphoric Acid Best Management Strategies: All dewatering will be filtered through rock and/or woven geo mesh fabric. All dewatering will be tested for Pollutants per state guidelines weekly.

Page 33: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 6 -

6.0 BEST MANAGEMENT PRACTICES (BMP’s) Also refer to attached Erosion and Sediment Control notes and plans included in the site plans 6.1 – Erosion and Sediment Control BMP’s 6.1.1 Minimize Disturbed Area and Protect Natural Features and Soil All work will occur inside the limits of construction per the erosion Control Site Plan. See Exhibit 1 6.1.2 Phase Construction Activity The sequence for the installation and removal of erosion and sediment control measures is as follows:

1. Installation of perimeter erosion control measures as shown on Exhibit 1 2. Site Clearing/Grubbing and topsoil stockpiling. 3. Construct sediment pond 4. Install erosion control measures along trench excavation as construction progresses 5. Construct underground sewer and rough grading 6. Replace topsoil and final stabilize disturbed areas along sewer lines and rough grading

areas 7. Final erosion control measures as areas are completed

6.1.3 Control Stormwater Flowing onto and through the Project Narrative: There is no offsite stormwater flowing onto this project site. On-site runoff flowing across the rough grading area will be directed to a sediment pond so that no sediment enters the downstream receiving waters. 6.1.4 Stabilize Soils No disturbed area which is not actively being worked shall remain denuded for more than 14 calendar days unless otherwise authorized by the director. Temporary cover by seeding or mulching should be provided on areas which will be exposed for a period greater than 14 days before permanent stabilization can be achieved. Permanent cover should be provided on all areas as soon as possible, by means of seeding and mulching, straw or hay mulch is required. All soil stock piles and borrow areas must protected with silt fence within 14 days after grading. All slopes within the project limits that are found to be eroding excessively within two years of permanent stabilization shall be provided additional slope stabilization methods such as seeding and mulching. Water is to be used for dust control. The Contractor will prevent the escape of this water and any sediment it may carry from the construction site. 6.1.5 Protect Slopes Temporary stabilization will include the installation of silt fences on level contours spaces at 10-20 foot intervals. Slopes will be seeded and covered with hay, straw or erosion control blankets on slopes greater than 3:1 as needed to provide for temporary stabilization until vegetation is permanently established. All slopes within the project limits that are found to be eroding excessively within two years of permanent stabilization shall be provided additional slope stabilization methods such as seeding

dsdrice
Cloud+
dsdrice
Cloud+
Include the entire work area on the plan
dsdrice
Cloud+
dsdrice
Cloud+
Verify; plan should reflect this
RSchindler
Callout
now included
RSchindler
Callout
statement updated
Page 34: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 7 -

and mulching. Where slopes are steeper than 3:1 erosion control blankets (per specification requirements) will be utilized for final stabilization. 6.1.6 Protect Storm Drain Inlets Inlet protection will be installed as soon as storm drain inlets are installed and before land-disturbance activities begin in areas with existing storm drain systems. At the Contractor’s discretion, additional temporary erosion control practices to include rock bags and sand bag barriers may be installed to prevent sediment movement. Inlet protection will include rock bags erosion logs curb inlet sediment filters where an overflow capacity is necessary to prevent excessive ponding in front of the curb inlet. Concrete block and wire screen inlet protection if used detail will be included Appendix C prior to installation, will be used where heavy flows are expected and where an overflow capacity is necessary to prevent excessive ponding around the inlet. Inlet protection devices will be inspected and accumulated sediment will be removed as needed. 6.1.7 Establish Perimeter Controls and Sediment Barriers Temporary stabilization will include the installation of silt fences on the downslope perimeter of project area. The silt fence will be trenched in on the uphill side 6 inches deep and 6 inches wide as detailed in the silt fence exhibit. Sediment will be removed when it reaches 1/3 the height of the fence. Silt fence will be inspected and replaced or repaired as needed. 6.1.8 Retain Sediment On-Site Temporary sediment traps shall be installed to detain sediment laden runoff from small watersheds for a period long enough to allow sediment to settle before discharge into receiving waters. For small drainage locations smaller sediment traps should be used. At a minimum, silt fences, vegetative buffer strips or equivalent sediment controls are required for all down-slope boundaries (and for those side slope boundaries deemed appropriate as dictated by individual site conditions) of the construction. The use of a combination of sediment and erosion control measures in order to achieve maximum pollutant removal will be utilized. Sediment traps will be checked regularly for sediment cleanout. Sediments shall be removed and the trap restored to its original dimensions when the sediment has accumulated to one half the design volume of the wet storage. Sediment shall be disposed in suitable areas and in such a manner that will not erode or cause sedimentation problems. The gravel outlets will be checked regularly for sediment buildup which will prevent damage. If the gravel is clogged by sediment, it shall be removed and cleaned or replaced. An alternate to sediment traps are temporary sediment basins. 6.1.9 Establish Stabilized Construction Exits The construction entrance will be established in the entry points of roads. The construction entrance will be at least 50 feet in length and approximately 12 feet wide and graded so runoff does not leave the site. The aggregate will be established at 8 inches thick on top of 4 inch minimum thick free draining material on top of geotextile and will consist of Type G dense graded material. A stabilized stone pad with a filter fabric under liner will be placed at points of vehicular ingress and egress. 6.1.10 Additional BMP’s BMP Schedule:

dsdrice
Cloud+
dsdrice
Cloud+
75
RSchindler
Callout
75'
Page 35: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 8 -

All Sediment and Erosion control BMP’s (detailed below and only on BMP site map and details if utilized onsite) will be installed prior to any excavation or demolition and will be coordinated with the construction schedule. As construction changes and new temporary BMP’s are needed to control sediment and erosion temporary BMP’s will be installed within 24 hours of inspection report.

Recommended BMP’s: ALL RECOMMENDED BMP’S WILL BE INSTALLED PRIOR TO EXCAVATION NEAR ANY SENSITIVE AREAS. Culvert Inlet Protection will be used to protect existing and new culvert inlets. Inlet Protection Detail will be included in Appendix before using onsite. Removal of this BMP will occur only after vegetation is established to a minimum of 70% pre construction coverage and after removal of BMP all sediment builds up will be removed and the area exposed shall be seeded. Silt Fence is to be installed in sensitive areas to protect stream channels, pond, and overland runoff. On this site it will be used to protect runoff from the slip pits. See Silt Fence Detail. Removal of this BMP will occur only after vegetation is established to a minimum of 70% pre construction coverage and after removal of BMP all sediment builds up will be removed and the area exposed shall be seeded. Vehicle Tracking Control is needed at the main construction entrance location. Vehicle tracking control shall be installed at the edge of the construction staging area where construction vehicles regularly exit onto existing asphalt road. If sediment tracking occurs it will be cleaned within 24 hours. See Vehicle Tracking Control Detail in Appendix C. Removal of this BMP will occur only after project is substantially complete and is ready for seeding operations; the area will then be seeded per specification with the rest of the project. Check Dams (rip rap) will be used to reduce storm water velocities in drainage channels during construction as a temporary measure until permanent stabilization can be created and vegetation has been established. Check Dam Detail will be included in the the Appendix before using onsite. Removal of this BMP will occur only after vegetation is established to a minimum of 70% pre construction coverage and after removal of BMP all sediment build-up will be removed and the area exposed shall be seeded. Portable Toilets: Portable toilets are brought in from a service contractor and will be maintained in accordance with standard waste disposal practices using vacuum trucks and place on stable ground to minimize risk of spillage. All portable toilets will be kept a minimum of 500’ from any waterway. Waste Disposal: If needed Roll offs will be utilized for standard construction waste. A qualified contractor will remove waste weekly and take to an appropriate dump site off this project.

6.1.11 Permanent BMP’S:

Re-vegetation:

Page 36: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 9 -

During construction any disturbed area not being currently worked left dormant longer than 14 days will be re-vegetated per specification with native seed and mulched and crimped with weed free straw. Final Stabilization will be considered complete when all disturbed areas have a minimum of 70% preconstruction coverage for the specification requirements. Then all temporary BMP’s will be removed and the exposed areas left behind will be seeded.

6.2 Good Housekeeping BMP’S 6.2.1 Material Handling and Waste Management The site will use a private refuse collector that will remove litter twice weekly. No less than one litter receptacle will be present at the construction site. In the event that unusual items such as tanks, cylinders, unidentified containers, etc. which could contain potentially hazardous materials are discovered or disturbed, the Fire and Rescue services will be notified. Litter and debris will be picked up and disposed of properly daily. Temporary toilet facilities will be located 500 feet away from any storm drain inlets and all waters of the state. 6.2.2 Establish Proper Building Material Staging Areas A designated staging area will be used, location to be determined based on available space in the field and plans will be redline. The staging area will be contained per SWMP guidelines. All Equipment and Materials will be brought into the site as needed. 6.2.3 Designate Washout Areas A concrete washout will be installed to detail as shown in the APPENDIX , and will be placed more than 500 feet away from any waters of the state. 6.2.4 Establish Proper Equipment/Vehicle Fueling and Maintenance Practices During construction the site will be exposed to operation and maintenance of construction equipment. The contractor shall be responsible for all activities such as fueling, oil changing, lubrication and repair which require use of petroleum products. Such products shall be transported to and from the site in special trucks equipped for that purpose. No waste petroleum products, rags, residue, or equipment parts shall be left on site. In the event of a spill or leak, causing soil to be contaminated, that soil shall be excavated placed in sealed barrels and removed from the site for transport to an approved location for disposal. See section 6.2.6 for the Spill Plan. 6.2.5 Control Equipment/Vehicle Washing N/A WILL NOT BE ALLOWED ONSITE 6.2.6 Any Additional BMPs N/A 6.2.7 Allowable Non-Stormwater Discharge Management N/A 6.2.8: SELECTING POST-CONSTRUCTION BMPs

dsdrice
Cloud+
dsdrice
Cloud+
Not found. Provide all applicable standard details.
RSchindler
Callout
added detail sheet
Page 37: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 10 -

Post Construction BMPs. Re-vegetation including seeding, mulching and erosion control blanket will be final BMP’s. Permanent stabilization will be achieved with 70% pre construction vegetative establishment. 7.0 SPILL PREVENTION AND CONTROL PLAN The SITE SUPERINTENDENT will act as the point of contact for any spill that occurs at this jobsite. The project manager will be responsible for implementation of prevention practices, spill containment / cleanup, worker training, reporting and complete documentation in the event of a spill. The ECO shall immediately notify the Owner, /Construction Manager, STATE and the Local Fire Department in addition to the legally required Federal, State, and Local reporting channels (including the National Response Center, 800.424.8802) if a reportable quantity is released to the environment .

7.1 SPILL PREVENTION BEST MANAGEMENT PRACTICES This section describes spill prevention methods Best Management Practices (BMP) that will be practiced to eliminate spills before they happen. 7.1.a Equipment Staging and Maintenance Store and maintain equipment in a designated area Reduce the amount of hazardous materials and waste by substituting non-hazardous or less hazardous materials. Use secondary containment (drain pan) to catch spills when removing or changing fluids. Use proper equipment (pumps, funnels) to transfer fluids Keep spill kits readily accessible Check incoming vehicles for leaking oil and fluids. Transfer used fluids and oil filters to waste or recycling drums immediately following generation. Inspect equipment routinely for leaks and spills Repair equipment immediately, if necessary implement a preventative maintenance schedule for equipment and vehicles. 7.1.b Fueling Area Perform fueling in designated fueling area minimum 50’ away from federal waters Use secondary containment (drain pan) to catch spills Use proper equipment (pumps, funnels) to transfer fluids Keep spill kits readily accessible Inspect fueling areas routinely for leaks and spills Hazardous Material Storage Areas Reduce the amount of hazardous materials by substituting non-hazardous or Less hazardous materials. 7.1. c Hazardous Material Storage Areas Minimize the quantity of hazardous materials brought onsite Store hazardous materials in a designated area away from drainage points. 7.1. d Unexpected Contaminated Soil and Water • Investigate historical site use • Perform all excavation activities carefully and only after the Owner/Construction Manager directed any activities

7.2 SPILL CONTAINMENT METHODS

Page 38: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 11 -

The following discussion identifies the types of secondary containment that will be used in the event of a spill. Table 1 summarizes the containment methods for each potential source.

• Equipment Staging and Maintenance Area. An equipment leak from a fuel tank, equipment seal, or hydraulic line will be contained within a spill containment cell placed beneath all stationary potential leak sources. An undetected leak from parked equipment will be cleaned up using hand shovels and containerized in a 55-gallon steel drum for offsite disposal. • Fueling Area. A small spill during fueling operations will be contained using fuel absorbent pads at the nozzle. The transfer of fuel into portable equipment will be performed using a funnel and/or hand pump and a spill pad used to absorb any incidental spills/drips. Any leaking tanks or drums will have fluids removed and transferred to another tank, drum, or container for the fluids. A spill response kit will be located near the fueling area or on the fuel truck for easy access. The spill response kit will include plastic sheeting, tarps, over pack drums, absorbent litter, and shovels. • Hazardous Material Storage Area. A spill from containers or cans in a hazardous material storage area will be contained within the storage cabinet these materials are kept in. • Unexpected Contaminated Soil. If contaminated soil is encountered during the project, the Owner/Construction Manager will be notified immediately. Small quantities of suspected contaminated soil will be placed on a 6-mil plastic liner and covered with 6-mil plastic. A soil berm or silt fence will be used to contain the stockpile and prevent migration of contaminated liquids in the soil.

Table 1: Spill Prevention and Containment Methods Potential Spill Source Potential Spill Source Equipment Staging and Maintenance Area Spill containment pad, spill kit, pumps,

funnels

Fueling Area (site equipment only Spill containment pad, spill kit, pumps, funnels

Hazardous Material Staging Area Spill containment pad, spill kit, pumps, funnels

Unexpected Contaminated Soil Plastic liner, plastic cover, soil berm, hay bales, lined super sacks

7.3 SPILL COUNTERMEASURES Every preventative measure shall be taken to keep contaminated or hazardous materials contained. If a release occurs, the following actions shall be taken: 1. Stop the Spill: The severity of a spill at the site is anticipated to be minimal as large containers/quantities of Hazardous Materials (HM) are not anticipated. The type of spill would occur while dispensing material at the HM storage facility and would likely be contained in secondary containment. Thus, the use spill kits or other available absorbent materials should stop the spill. 2. Warn Others: Notify co-workers and supervisory personnel of the release. Notify emergency responders if appropriate. For site personnel, an alarm system will consist of

Page 39: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 12 -

three one second blasts on an air horn sounded by the person discovering a spill or fire. In the event of any spill, the Superintendent and Project Manager shall be notified if the spill is 5 gallons or more the STATE will be contacted along with the Fire Department. 3. Isolate the Area: Prevent public access to the area and continue to minimize the spread of the material. Minimize personal exposure throughout emergency response actions. 4. Containment: A spill shall only be contained by trained personnel and if it is safe to do so. DO NOT PLACE YOURSELF IN DANGER. Attempt to extinguish a fire only if it is in the incipient stage; trash can size or smaller. For larger spills, wait for the arrival of emergency response personnel and provide directions to the location of the emergency. 5. Complete a Spill and Incident Report: For each spill of a Hazardous Material a spill and incident report shall be completed and submitted to the Owner/Construction Manager and if applicable to the Engineer and the State of Colorado Department of Public Health and Environment

8.0 INSPECTIONS 8.1 Inspections Inspections will occur at least every 14 days and within 24 hours of a precipitation event producing runoff, which from past experience this occurs with precipitation of 1/4 inch of rain or more , the primary site for tracking weather data and rainfall measurements will be taken from Weather Underground and a rain gauge will be onsite for verification only.

1. Inspection Personnel: The contract Stormwater Inspector will conduct the site inspections as mentioned above in Section 1. 2. Inspection Schedule and Procedures: The inspection schedule will be routinely accomplished every 14 days and after every storm event for the entire site with all BMP's evaluated for performance and need. Any BMP found to be ineffective will be re-accomplished or replaced with a new BMP to provide the level of protection needed. BMP's found to be no longer needed will be removed. Inspections will also be accomplished as soon as practical, but within 24 hours of the end of a precipitation event causing surface erosion, over 1/4” or more. The general procedures for correcting problems when they are identified will be to document the problem in the log and devise a solution utilizing all resources available to formulate BMP's that will correct the problem as soon as possible. A copy of the inspection report to be used for the site is attached. See Appendix.

8.2 Delegation of Authority Duly Authorized Representative(s) or Position(s): Authorized representatives for the SWMP plan will be: Jeff Mark – Primary Contact SWMP INSPECTOR – Trevor Terril 8.3 Revisions to the SWMP The SWMP Inspector and/or the site superintendent have the authority to add/subtract/revise BMP’s as necessary to accommodate construction activities. However, the engineer should be notified when any major redirection of runoff, offsite runoff, pond modifications, or other

Page 40: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 13 -

substantial changes are made to this SWMP. Changes should be documented per Section 9.0. 9.0 RECORDKEEPING AND TRAINING 9.1 Recordkeeping Records will be retained for a minimum period of at least 3 years after the permit is terminated. Major activities will start on 11/2017: Date(s) when construction activities permanently cease on a portion of the site: 06/2018 Date(s) when an area is either temporarily or permanently stabilized: 6/2018 9.2 Changes to the SWMP Any changes will be referenced in APPENDIX. See Section 8.3 for authority to change the SWMP. 9.3 Training Individual(s) Responsible for Training: All personnel on site will trained on the site specific SWMP requirements to be conducted by the SWMP Inspector and/or the site superintendent. 10.0 FINAL STABILIZATION Final stabilization will be accomplished by contractors to re-vegetate the area of disturbance per the approved plans and specifications. Final stabilization will include permanent seeding/mulching of disturbed areas, sediment forebays, erosion control blankets, turf reinforcement mats, and permanent BMP’s. Once 70% of the pre-development vegetative cover has been established and has been accepted, temporary BMP’s will be removed and the permit will be terminated and filed.

Page 41: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 14 -

APPENDIX A

Page 42: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 43: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 15 -

APPENDIX B

Page 44: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 45: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 46: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 47: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
dsdrice
Text Box
See redlined CDs
Page 48: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 49: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 50: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 51: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 52: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 53: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 54: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 55: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 56: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 57: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General
Page 58: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 16 -

APPENDIX C

STORMWATER INSPECTION REPORT

Page 59: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 17 -

Stormwater Inspection Report

Project Name and Location:

Inspector Name and Title: Director:

Date/Time of Inspection: Weather Conditions:

Schedule Completion Date: Construction Stage (circle all that apply):

Clearing/Grubbing Paving Rough Grading Infrastructure Building Construction Final

Grading Final Stabilization Terminate Permit

Type of Control Describe status, identify problems, maintenance needs, or non-conformance with details or temporary alteration

Problem addressed (date and description of corrective action)

Structural: Silt Fence OK N/A

Tears/Holes Burial Sed. Accum. Sediment bypass

Const. Exit OK N/A

Voids Filled Trackout

Check Dam OK N/A

Sediment Accumulation

Inlet Protection OK N/A

Sed. Accum. Sed. Bypass Application not appropriate

DiversionDitch/Berm OK N/A

Erosion Stabilization

Sediment Trap OK N/A

Sediment Accumulation

Sediment Basin OK N/A

Sed. Accumulation Bank erosion Stabilization

Discharge Point OK N/A

Erosion Sediment Discharge

Material Storage/ Secondary Contain. OK N/A

Not shown on Site Map Spills Out of design. area Improper storage: chemicals; solvents; paint; fuels, etc.

Page 60: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 18 -

Other Structural Controls OK N/A

Non-Structural: Good Housekeeping OK N/A

Solid Waste Sanitary Waste Dust Control

Project Name and Location: Date: Page 2

Equip. Wash/Maint. OK N/A

Spills Outside designated area

Concrete Washout OK N/A

Spills out of designated area Not shown on Site Map

Stabilization: Seed/Sod Mulching, Geotextile, Blankets OK N/A

Need Temp. stab. Need final stab. Health of veg.

Record Keeping: Entrance Postings OK N/A

NOI Permits Construction Site Notice

SWPPP Notebook OK N/A

Missing Sections Missing Forms

Site Map/Details OK N/A

Activities not up-to-date Deviate from details BMP Additions Modifications Not up-to-date

Other OK N/A

I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information is, to the best of my knowledge and belied, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. _______________________ Inspector’s Signature Date

Page 61: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 19 -

APPENDIX D

SPILL REPORT FORM

Page 62: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 20 -

Spill Report Form Project Type and Location: Spill Reported by: Date/Time Spill: Describe spill location and events leading to spill: Material spilled: Source of spill: Amount spilled: Amount spilled to waterway: Containment or clean up action: Approximate depth of soil excavation: List Injuries or Personal Contamination: Action to be taken to prevent future spills: Modifications to the SWPPP necessary due to this spill: Agencies notified of the spill: I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. Contractor Superintendent Date

Page 63: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 21 -

APPENDIX E

RECORD OF STABILIZATION AND CONSTRUCTION ACTIVITY DATES

Page 64: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 22 -

SITE STABILIZATION and CONSTRUCTION ACTIVITY DATES A record of dates when BMPs are installed or removed, stabilization measures are initiated, major grading activities occur, and construction activities temporarily or permanently cease on a portion of the site shall be maintained until final site stabilization is achieved.

MAJOR STABILIZATION AND GRADING ACTIVITIES

Description of Activity:_______________________________________________________________________________ Site Contractor: ___________________________________ Begin (date): _____________ End(date):________________ Location:_____________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ Description of Activity:_______________________________________________________________________________ Site Contractor: ___________________________________ Begin (date): _____________ End(date):________________ Location:___________________________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ Description of Activity:_______________________________________________________________________________ Site Contractor: ___________________________________ Begin (date): _____________ End(date):________________ Location:____________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________

Page 65: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 23 -

____________________________________________________________________________

Page 66: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 24 -

APPENDIX F

FEDERAL, STATE, OR LOCAL STORM WATER OR OTHER ENVIRONMENTAL INSPECTOR SITE VISIT LOG

Page 67: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 25 -

Federal, State, or Local Storm Water or other Environmental Inspector Site Visit Log Inspectors Name: Agency: Contractors Representative Present: Others Present: Comments: Time and Date: Report Prepared: Yes No Inspectors Name: Agency: Contractors Representative Present: Others Present: Comments: Time and Date: Report Prepared: Yes No Inspectors Name: Agency: Contractors Representative Present: Others Present: Comments: Time and Date: Report Prepared: Yes No

Page 68: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

- 26 -

APPENDIX G

GENERAL PERMIT

Page 69: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 ...€¦ · DATE: 11/8/2017 SUBJECT: CDR-17-006 Jimmy Camp Creek East Interceptor -Review 1 – response to comments General

Markup Summary

Subject: Cloud+Page Label: 10Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:34:38 PMColor:

Verify; plan should reflect this

dsdrice (5)

Subject: Cloud+Page Label: 10Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:33:36 PMColor:

Include the entire work area on the plan

Subject: Cloud+Page Label: 11Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:51:06 PMColor:

75

Subject: Cloud+Page Label: 13Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:47:39 PMColor:

Not found. Provide all applicable standard details.

Subject: Text BoxPage Label: 24Lock: UnlockedStatus: Checkmark: UncheckedAuthor: dsdriceDate: 10/4/2017 1:41:04 PMColor:

See redlined CDs

6.1 – Erosion and Sediment Control BMP’s 6.1.1 Minimize Disturbed Area and Protect Natural Features and Soil All work will occur inside the limits of construction per the erosion Control Site Plan. See Exhibit 1 6.1.2 Phase Construction Activity The sequence for the installation and removal of erosion and sediment control measures is as follows:

1. Installation of perimeter erosion control measures as shown on Exhibit 1 2. Site Clearing/Grubbing and topsoil stockpiling. 3. Construct sediment pond 4. Install erosion control measures along trench excavation as construction progresses 5. Construct underground sewer and rough grading 6. Replace topsoil and final stabilize disturbed areas along sewer lines and rough grading

areas 7. Final erosion control measures as areas are completed

6.1.3 Control Stormwater Flowing onto and through the Project Narrative: There is no offsite stormwater flowing onto this project site. On-site runoff flowing across the rough grading area will be directed to a sediment pond so that no sediment enters the downstream receiving waters. 6.1.4 Stabilize Soils No disturbed area which is not actively being worked shall remain denuded for more than 14 calendar days unless otherwise authorized by the director. Temporary cover by seeding or mulching should be provided on areas which will be exposed for a period greater than 14 days before permanent stabilization can be achieved. Permanent cover should be provided on all areas as soon as possible, by means of seeding and mulching, straw or hay mulch is required. All soil stock piles and borrow areas must protected with silt fence within 14 days after grading. All slopes within the project limits that are found to be eroding excessively within two years of permanent stabilization shall be provided additional slope stabilization methods such as seeding and mulching. Water is to be used for dust control. The Contractor will prevent the escape of this water and any sediment it may carry from the construction site. 6.1.5 Protect Slopes

Verify; planshould reflectthis

MANAGEMENT PRACTICES (BMP’s)

o attached Erosion and Sediment Control notes and plans included in the site plans

ion and Sediment Control BMP’s

mize Disturbed Area and Protect Natural Features and Soil ll occur inside the limits of construction per the erosion Control Site Plan. See Exhibit

se Construction Activity nce for the installation and removal of erosion and sediment control measures is as

tallation of perimeter erosion control measures as shown on Exhibit 1 e Clearing/Grubbing and topsoil stockpiling. nstruct sediment pond tall erosion control measures along trench excavation as construction progresses nstruct underground sewer and rough grading place topsoil and final stabilize disturbed areas along sewer lines and rough grading as al erosion control measures as areas are completed

rol Stormwater Flowing onto and through the Project

o offsite stormwater flowing onto this project site. On-site runoff flowing across the

Include theentire workarea on theplan

- 7 -

r cause sedimentation problems. vel outlets will be checked regularly for sediment buildup which will prevent damageel is clogged by sediment, it shall be removed and cleaned or replaced.

nate to sediment traps are temporary sediment basins.

stablish Stabilized Construction Exits struction entrance will be established in the entry points of roads. The construction

e will be at least 50 feet in length and approximately 12 feet wide and graded so runt leave the site. The aggregate will be established at 8 inches thick on top of 4 inch

m thick free draining material on top of geotextile and will consist of Type G dense material. A stabilized stone pad with a filter fabric under liner will be placed at pointsr ingress and egress.

Additional BMP’s chedule:

75

sturbed, the Fire and Rescue services will be notified. d up and disposed of properly daily. be located 500 feet away from any storm drain inlets and all

ing Material Staging Areas be used, location to be determined based on available space in ne. The staging area will be contained per SWMP guidelines. All

be brought into the site as needed.

eas stalled to detail as shown in the APPENDIX , and will be placed any waters of the state.

pment/Vehicle Fueling and Maintenance Practices ll be exposed to operation and maintenance of construction

all be responsible for all activities such as fueling, oil changing, quire use of petroleum products. Such products shall be e in special trucks equipped for that purpose. No waste petroleum

uipment parts shall be left on site. In the event of a spill or leak, ed, that soil shall be excavated placed in sealed barrels and sport to an approved location for disposal.

Plan.

Not found. Provide allapplicablestandarddetails.

See redlined CDs