capacity planning

47
Capacity Planning

Upload: divyakaushal

Post on 25-Nov-2014

710 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Capacity Planning

Capacity Planning

Page 2: Capacity Planning

Schedule

• Understanding of capacity planning – line – factory section (attendance/efficiency)

• Operation breakdowns, independent and dependent processes, flow diagrams.

• Machine, equipment and manpower requirements.

• Line and production balancing.• Production control• Role of the supervisor

Page 3: Capacity Planning

Factory capacity

• 500 operators working 48 hour week.• Work content of 30 minutes per garment

Therefore

capacity = 500 x 48x 60 = 48000 garments/week 30

Ok? Any problems?

Page 4: Capacity Planning

Reasons for lost output• Absenteeism

• Poor work methods (affects performance & efficiency)

• Low operator performance

• Poor operator utilisation

• Style change (not only a cause of lost output itself, but can cause all or some of the above!!)

Page 5: Capacity Planning

Definitions• On – Standard : Time the operator spends

on “measured” work, earning standard minutes (SM).

• Off – Standard : Time the operator spends on “un-measured” work or “measured” work that is classified as “off-standard”.

Page 6: Capacity Planning

Definitions- “Measured work”• That work to which a standard measure

(SMV, SAM) has been applied.

• Example of “measured work” that may be classified as “off-standard”. An operator may whilst learning a new operation be taken off standard for payment purposes but will still be contributing SMS as the operation they complete will have SMV applied.

Page 7: Capacity Planning

Off standard time

• Should be reported on “Labour cost control sheet”

• Waiting for work• Machine breakdown• Unmeasured work –

operation not yet allocated SMV.

• Sampling

• Repairs (not known)• Paid average (for

balancing)• Under re-train• Indirect work –

covering for supervisor

• Supervisor/manager should be targeted to stay within budget.

Page 8: Capacity Planning

SMV/SAM?

• Standard Minute Value (S.M.V.) is the time allocated through work measurement for an operation to be completed at a 100 rating. (Basic Work Content)

• Standard Allocated (Allotted) Minute (S.A.M.) is an S.M.V. + any policy allowances added.

Page 9: Capacity Planning

Definitions: Operator Performance

• Primarily a measure of the effectiveness of the individual operator

• SM’s earned “on standard” x 100 Time spent “on standard”

Sometimes referred to as “Pay” performance as it is usually measured within an incentive scheme.

Page 10: Capacity Planning

Definitions Operator Utilisation

• A measure of how well the supervisor manages to keep the operators “on – standard”

= time “on-standard” x 100

time attended

Page 11: Capacity Planning

DefinitionsEfficiency

• A measure of how well the section/factory is run.

SM’s earned x 100 time attended.• A measure of both the operator and

the supervisor• Incorporates elements of operator

performance & utilisation into the single measure

Page 12: Capacity Planning

Definitions Absence / attendance

total operator time attended x 100

total contracted time

= attendance.

• Absence = 1/attendance

Page 13: Capacity Planning

Measures factor/section/operator

• Standard hours (minutes) produced.

• Operator performance

• Operator utilisation

• Section efficiency

• Off – standard time

• Absence (attendance)

Page 14: Capacity Planning

MeasuresExamples

• Section = 20 operators working 9 hour/540 minute day

• 2 operators are absent all day• Attendance = 18 x 540 x 100 20 x 540

= 9720 = 90% (or) 10% absence 10800

Page 15: Capacity Planning

Measures Examples

• An operator attends for 540 minutes

• Produces 1500 pieces @ SMV of 0.30

• Waits 60 minutes for work

• Waits 20 minutes machine breakdown

Page 16: Capacity Planning

MeasuresExamples

• Sms produced = 1500 x 0.30 = 450.

• Time “on-standard” = 540 – (60+20) = 460 minutes

• Performance = 450 x 100 460= 97.8 or 98%

Page 17: Capacity Planning

MeasuresExamples

• Operator Utilisation

= 460 x 100 = 85.2%

540

Not acceptable ?

Page 18: Capacity Planning

MeasuresExamples

• Efficiency = 450 x 100

540

= 83%

Borderline ?

Page 19: Capacity Planning

ExerciseSection 1Operator cont Att op. production SMV offStd Perf Uti Eff min minAlison 540 540 1. 1000 0.37 30 Betty 540 480 2 1120 0.30 charlie 540 0 3 0 0.26 Dorothy 540 540 4 950 0.23 3 350 0.26 75 Ethel 540 540 5 1070 0.45 15 Freda 540 540 6 1250 0.40 30 Gail 540 540 7 1200 0.21 3 880 0.26 Heather 540 540 8 600 0.85 30 Irma 540 540 8 600 0.85 45 June 540 540 9 1275 0.38 30 Totals

Page 20: Capacity Planning

Exercise

• Section 1Operator cont. Att op production SMV OffStd Perf Uti Eff mins Alison 540 540 1. 1000 0.37 30 72.5 94 68.5Betty 540 480 2 1120 0.30 70 100 70charlie 540 0 3 0 0.26 Dorothy 540 540 4 950 0.23 66.5 86 57.3 3 350 0.26 75 Ethel 540 540 5 1070 0.45 15 91.7 97 89.2Freda 540 540 6 1250 0.40 30 98 94 92.5Gail 540 540 7 1200 0.21 89 100 89 3 880 0.26 Heather 540 540 8 600 0.85 30 100 94 94.4Irma 540 540 8 600 0.85 45 103 92 94.4 June 540 540 9 1275 0.38 30 95 94 89.7Totals 5400 4800 3.22 255 87.6 94.7 83

Page 21: Capacity Planning

Exercise

• Attendance = 4800/5400 = 89%

• total sms earned = 3982.30

Page 22: Capacity Planning

Capacity planning

• Factory

• Department

• Section

• Machine

• Skill

• Restricting or defining factor

Page 23: Capacity Planning

Capacity planning

• What is the starting point?

• How many garments can a section produce?

• How many operators/machines do we need to produce a given number of garments?

• Same calculation – just reversed!

Page 24: Capacity Planning

Information!!

• Labour content (SMVs/SAMs/Std. hrs)

• Available operators

• Contracted hours

• Absenteeism levels

• Efficiency levels

Page 25: Capacity Planning

Capacity planning

• Information• Information• Information• Obvious but where does it

come from?• How accurate is it?

Page 26: Capacity Planning

Work content. SAMs, SMVs

• Are they accurate? (can self correct in capacity planning)

• What operations do they cover?

• What operations are unmeasured or performed by indirect operators. Be clear!

Page 27: Capacity Planning

Capacity planning - people

• How many garments can a given number of people produce?

• Number of operators

• SMV (Labour content)

• Absenteeism

• Efficiency/ inefficiency!

Page 28: Capacity Planning

Capacity planning - people

• 500 direct operators working 48 hours/week• S.M.V. = 25 per garment• Absence level of 8%• Average efficiency of 85%• Contracted time

1. Calculate standard hour/minutes that can be produced by operators.

2. Calculate how many garments that represents

Page 29: Capacity Planning

Capacity planning - people

• 500 operators x 48 hours = 24000 contracted hours

• 24000 – 8% (1920 hours) absence = 22080 attended hours (absence costs 40 operators)

• At efficiency of 85% std. hours produced = 22080 x 85% = 18768 std hrs.

• 5232 hours lost to absence & inefficiency.=

21.8% of original contracted hours

Page 30: Capacity Planning

Capacity planning - people

• 18768 std hrs produced

• S.M.V. = 25 mins. or 0.417 std. hrs.

• Garment capacity = 18768

0.417

= 45007 garments.

Page 31: Capacity Planning

Capacity planning

• Under the same conditions how many people are need to produced 70000 garments per week.?

• 70000 x 0.417 = 29190 standard hours required.

• Each operator will produce 39 hours @ 85% efficiency

= 39 x 85% = 33.15 std. hrs/week

Page 32: Capacity Planning

Capacity planning

• 29190 standard hours required.

• Each operator will produce 33.15 std. hrs/week

• Number of operators = 29190

33.15

= 880.54 people.

• + Absence of 8% = 880.54 +8%.= 951

Page 33: Capacity Planning

Capacity planning

• Capacity planning is only as accurate as the information it is based upon!

Page 34: Capacity Planning

Capacity planning

• Limiting factors

• People X

• Machines?

• Department?

Page 35: Capacity Planning

Capacity planning-machines

• Auto pocket set machine

• S.M.V. 0.60

• Efficiency = 95%

• 15 machines available

• 8.50 hour day

• How many garments can they supply to sections?

Page 36: Capacity Planning

Capacity planning-machines

• 15 machines x 8.50 hours = 127.50 hours/day.• @95% efficiency std. hrs produced = 121.13 hrs• SMV = 0.60 = 100 per hour at standard• Output = 100 x 121.13 = 12113 garments• Absence ignored as decision taken to ensure

absence cover (15 machines + 8* absence = 17 operators. 1 spare shared with pressing

Page 37: Capacity Planning

Capacity planning-machines

• Capacity must be increased to 25000 per day.

• Each machine does 100 x 95% = 95 per hour. 25000/95 = 263.15 hours. In 8.5 hour day = 31 machines

• However machines cost $75000 each and have a six month delivery lead time.

• Try again!!!

Page 38: Capacity Planning

Capacity planning-machines

• Each machine will produce 95 per hour worked.

• 25000/95 = 263.15 hours

• 263.15 hours / 15 machines = 17.54 per machine per day

• 2 shifts

Page 39: Capacity Planning

Capacity planning

• Limiting factors

• People X

• Machines X

• Department?

Page 40: Capacity Planning

Capacity planning- Department

• Cutting room using semi-auto spreading machines and computerised cutting head.

• SMV for spreading = 0.1584 per metre• SMV for cutting = 0.050 per metre• Average fabric content per gmt. = 90 cms.• Standard working day= 8.50 hours (39 week)• 3 spreading machines on 4 tables• 1 cutting machine.• Department runs at 90% efficiency and 8%

absence

Page 41: Capacity Planning

Capacity planning- Exercise

• How many people are needed to supply the factory with 50000 garments per week?

• What is machine requirement for 50000 garments per week?

• What do you recommend if production cut to 24000 garments per week?

• All operators are able to use both spread and cut equipment.

Page 42: Capacity Planning

Capacity planning-spreading

• 50000 garments x 0.90 metres = 45000 metres to be cut each week.

• Each metre Smv = 0.1584 therefore 45000 x 0.1584 = 0.1584 x 45000

60

= 118.80 std.hrs required

@ 90% efficiency = 132 operated hours./ 3machines = 44 hour week

Page 43: Capacity Planning

Capacity planning- cutting

• 50000 garments x 0.90 metres = 45000 metres to be cut each week.

• Each metre Smv. = 0.05 therefore 45000 x 0.05 = 0.05 x 45000

60

= 37.5 std.hrs required

@ 90% efficiency = 41.70 operated hours

Page 44: Capacity Planning

Capacity planning –cutting room

• Spreading 132 hours needed over 3 machines• Cutting 41.70 hours needed.• Total operating hours = 173.9• Absence = 8% = 187.18 contracted hours

needed = 4.8 (5) people at 39 hour week.• 4 operators work 8.50 hours (when all

attending). 1 operator works 2 hours early

and through lunch break = 14 hour extra machine time per week. Helps on non-machine elements.

Page 45: Capacity Planning

Capacity planning-spreading

• 24000 garments x 0.90 metres = 21600 metres to be cut each week.

• Each metre Smv = 0.1584 therefore 21600 x 0.1584 = 0.1584 x 21600

60

= 61.60 std.hrs required

@ 90% efficiency = 68.40 operated hours./ 3machines = 22.80 hour week

Page 46: Capacity Planning

Capacity planning- cutting

• 24000 garments x 0.90 metres = 21600 metres to be cut each week.

• Each metre Smv = 0.05 therefore 21600 x 0.05 = 0.05 x 21600

60

= 18.0 std.hrs required

@ 90% efficiency = 20 operated hours

Page 47: Capacity Planning

Capacity planning –cutting room

• Spreading 68.4 hours needed over 3 machines

• Cutting 20 hours needed.• Total operating hours = 84.4• Absence = 8% = 91.2 contracted hours

needed = 2.3 (3) people at 39 hour week.• 2 operators to be released.• Can 1 operator be redeployed for part of

the day?