Can Traditional Highway Asset Management

Strategies Be Adapted To Waterway Infrastructure

Analysis?

Bruce LambertInstitute For Water Resources

US Army Corps of Engineers

Page 2: Can Traditional Highway Asset Management Strategies Be

2

Presentation Objectives

What are traditional Asset Management Strategies for Highways?

Asset management within the CorpsA Condition and Needs Report?

Disclaimer: These views represents those of the author and not the policies of the U.S. Army Corps of Engineers.

Page 3: Can Traditional Highway Asset Management Strategies Be

3Why examine linkages across modes?

More State DOT’s have a navigation roleAll states have other waterway resource

considerationsGeneral concerns over future of

transportation activities and infrastructure demands

Will a national dialogue on all public investment in infrastructure emerge?

Page 4: Can Traditional Highway Asset Management Strategies Be

4

How Can One Look At A System?

Inventory Functions – physical characteristics, numbers of facilities, labor, equipment

Engineering – structural integrity, deteriorationOperational Reliability – delay, closuresEconomical and Financial – Cost/Benefit

Analysis, capital and financial resourcesDemand - Traffic volumes and flowsSafety and Security Sharing resources across different users with

conflicting goals

Page 5: Can Traditional Highway Asset Management Strategies Be

5

Highway Asset Management

Focus – strategic assessment of economic tradeoffs between alternative infrastructure investments

Recognizing:Increased demand on system“Mature” network of roads and bridgesIncreased competition for funding and supportNon-traditional players in decision processMore focus on maintenance and meeting user

expectations

Page 6: Can Traditional Highway Asset Management Strategies Be

6Evolution in Highway Asset Management

Began with engineering criteriaStructures were gauged on risk of structural

“failure” or conditionDecision makers were not financially

constrained to make tough “economic” trade-off analysis

In 60’s/70s, began linking economic concepts to “optimize” roadway investment

Most Asset Management models developed from legacy systems

Page 7: Can Traditional Highway Asset Management Strategies Be

7Data Elements in Highway Infrastructure

Traffic patterns (truck, car, weight, etc.)Structural composition and conditionHistorical condition and maintenance logsMethodology to determine different

alternatives – incremental analysisGIS with system attributes“Customer” responsive attributes

Page 8: Can Traditional Highway Asset Management Strategies Be

8

A Generic Asset Management System

Goals Asset Inventory

Condition Assessment and

Performance Modeling

Alternatives Evaluation and

Program Optimization

Short and Long Range Plans

Project Implementation

Performance Monitoring

Budget

Page 9: Can Traditional Highway Asset Management Strategies Be

9

Performance Measures

Performance Measures provide mechanism for understanding system performance

Some approaches for HighwaysLevel of ServiceTraffic Volume DelaysReliability

Page 10: Can Traditional Highway Asset Management Strategies Be

10

The C&P Report

Use HPMS Data submitted by StatesUse HERS Model – peer reviewed and

checkedOngoing research effort that has been peer

reviewedForecasts of traffic patterns by various typesScenarios of different operational and

performance strategiesSample of road networks (links)

Page 11: Can Traditional Highway Asset Management Strategies Be

11

Corps Navigation Mission

Provide safe, reliable, efficient, effective and environmentally sustainable waterborne transportation systems for movement of commerce, national security needs, and recreation.

Page 12: Can Traditional Highway Asset Management Strategies Be

12

USACE – Overview

Projects are authorized by CongressLocal cost share formulas exist for various

project types for new constructionCorps maintains projects into perpetuity

once competed Competition from other business lines

within Corps budgetShift from Construction to Operating and

Maintenance (O&M) of navigation projects

Page 13: Can Traditional Highway Asset Management Strategies Be

13Maritime Infrastructure Conditions and Concerns

25,000 miles of waterway and harbor channels handle 2.4 billion tons of cargo vital to economy

Half of locks exceed 50-year design life and lock maintenance downtime has doubled

Maintenance backlog increased to nearly $700 million under FY 2005 Budget

Harbor improvements are needed to handle new larger vessels

Lock Construction Projects underway to meet these needs have been delayed by 5-10 years due to funding shortfall

Page 14: Can Traditional Highway Asset Management Strategies Be

14

The Corps is Examining Performance Measures for O&M Budgeting

Developing new measures use and economic measures to balance issues of scale, geography, and use

Seeking comparability with other USACE business lines:

Flood Damage ReductionHydropowerEnvironmental Stewardship (Natural Resources)Recreation

Page 15: Can Traditional Highway Asset Management Strategies Be

15Current Asset Management Process at USACE

Districts determine projects based on HQ criteria, mostly Remaining Benefit/Cost Ratios

Information supplied to HQ and sorted into various groups based on B/C and other factors

Determinations based on actual budgets for upcoming year

Strategic planning is a different function

Page 16: Can Traditional Highway Asset Management Strategies Be

16Repair, Evaluation, Maintenance and Rehabilitation (REMR)

For lock componentsDeveloped Condition Index

0 Extremely Poor 90-100 Excellent Condition

Was linked to FHWA research on concreteLimitations:Did not satisfy all needsNo economic cost benefit ratiosNo linkage to user expectations

Page 17: Can Traditional Highway Asset Management Strategies Be

17Asset Management Models being used or reviewed by Corps

Maximo – detailed Hydroamp – industry standard in

hydropowerNASA Deferred ModelDepartment of the Interior – Locks and

DamsAd Hoc analysis – “inventory” featuresLife Cycle Costs – PIANC, COPRI, USACE

Question on levels of aggregation or components

Page 18: Can Traditional Highway Asset Management Strategies Be

18Recent USACE workshop on Asset Management:

Held end of August50+ peopleThird of series of meetings

Five Critical ProblemsLack of standards and criteriaCondition assessmentRisk and uncertaintyBusiness line processInadequate models and tools

Page 19: Can Traditional Highway Asset Management Strategies Be

19

Can We Help People Make Better Decisions?

Page 20: Can Traditional Highway Asset Management Strategies Be

20Previous Studies That Addressed Maritime Needs and Conditions

AASHTO – “Freight Bottom Line” FHWA Condition and Needs– 1995 TRB – “Global Intermodal Freight:

State of Readiness for the 21st Century” Marad – Several studies on large ships

at ports Trade and Transportation: A Study of

North American Port and Intermodal Systems, US Chamber of Commerce, March 2003.

Water Transportation, Ports, and International Trade, TRB Transportation Research Record, No. 1820, 2003.

Latin America Trade and Transportation Study, Mississippi DOT & Wilbur Smith Associates, 2001.

The Importance of the U.S. Port System – USACE - IWR 1997

Inland Waterway Review, IWR, various editions.

National Waterways Study: A Framework for Decision Making, IWR, January 1983.

National Dredging Needs Study, IWR, Dec 2002, Updated May 2003.

The Marine Transportation System and the Federal Role: Measuring Performance, Targeting Improvement, TRB, Special Report 279, 2004.

Freight Capacity for the 21st Century, TRB Special Report 271, 2003.

Maritime Trade and Transportation, USDOT, 2002

Page 21: Can Traditional Highway Asset Management Strategies Be

21Where Does One Estimate Port or Maritime System Productivity?

Terminal Capacity? System Capacity?

Origination

Port

Destination

Truck, Water, Rail

Truck, Water, Rail

Page 22: Can Traditional Highway Asset Management Strategies Be

22

Age of Lock as One Measure?

Page 23: Can Traditional Highway Asset Management Strategies Be

23

A Generic Asset Management System

Goals Asset Inventory

Condition Assessment and

Performance Modeling

Alternatives Evaluation and

Program Optimization

Short and Long Range Plans

Project Implementation

Performance Monitoring

Budget

Page 24: Can Traditional Highway Asset Management Strategies Be

24Research gaps related to adopting asset management models

Lack of consistent performance measures Linguistic differences Lack of network effects (operational)No consistent long term view of waterways Emphasis – accounting, engineering, economical,

reliable? Striking a balance?Engineering standards for different componentsChanging vessel sizes and configurations –

operational characteristicsLack of portable models and tools

Page 25: Can Traditional Highway Asset Management Strategies Be

25Potential Lessons on Applying HERS type methodology

Accepted time horizons and scenarios in incremental analysis

Elasticity concepts consistent with waterway studies

Many of same elements – traffic, throughput, economic and engineering concepts

Page 26: Can Traditional Highway Asset Management Strategies Be

26Limitations on Applying HERS type methodology

Induced Demand in the original design, but no post plan review

Background traffic concept different Stronger seasonality changing peak/off peak

design considerationsWaterway studies are justified on travel savingsNetwork effects strongerNo functional class structure in U.S. databasesWaterways more prone to discrete changesNo national forecasts of water activitiesDifferences of links (highways) vs. Nodes

(waterways)

Page 27: Can Traditional Highway Asset Management Strategies Be

27

Implementation Challenges?

Projects have multiple uses No framework to determine and track user expectations Competing and changing commercial interests Determining or guaranteeing a minimum standards Planning and defining current and future needs Data integration – GIS and data warehousing Can process transparency be developed? Education No long term strategic view of transportation needs Public-Private Partnerships?

Page 28: Can Traditional Highway Asset Management Strategies Be

28

Conclusion

Some highway activities could be applied, such as process and data integration

Waterway system is too diverse to simply rely upon highway tools

Need to look at more collaboration, especially for non-traditional relationships

Page 29: Can Traditional Highway Asset Management Strategies Be

29

Institute For Water ResourcesUS Army Corps of Engineers

http://www.iwr.usace.army.mil

Bruce Lambert