  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    1/83

    Round C2

    IPMA Certification Level CCertified Project Manager

    Candidates Manual

    cPMDAN, Suite A6, Zone 'D' Plaza, No.1, Adeyinka Adebayo street,

    Apo Quarters, Zone 'D', Abuja, Nigeria

    Tel./Fax: +234702 541 6594

    www.pmdan,org

    [email protected]

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page1

    of83

    http://www.pmdan%2Corg/http://www.pmdan%2Corg/mailto:[email protected]:[email protected]:[email protected]://www.pmdan%2Corg/
  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    2/83

    Contents and program

    1. Introduction to IPMA Level CCertification

    Stage 1: Self-assessment, application,

    2. CV on education, career etc.

    3. Basis for competence assessment

    4. Description of experience applications

    5. Self-assessment

    6. Application for Level C Certification

    Stage 2: People to be contacted forreferences, Examination

    7. People to be contacted for references(Referees)

    8. Written examination

    Stage 3: Report9. Project Short Report

    10. Competence development plan

    Stage 4: Interview

    11. Interview

    Stage 5: Final evaluation12.Final evaluation and recommendation

    Further orientation

    13.General information

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page2

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    3/83

    1.Introduction toIPMALevel CCertification

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page3

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    4/83

    Purpose of

    Introduction Session

    Guidehow to succeed in

    demonstrating your

    competences in project

    management to the assessors

    during the certification process.

    Inspire

    to the fact that participation in

    the process gives a further lift

    of yourcompetences inproject

    management.

    Topics of the introduction sessionFollowing the content of this manual, all topics

    laid down here will be further explained wherenecessary and the questions of the candidates willbe answered.

    This session will be offered to all interested personsin the form of a webinar.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page4

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    5/83

    Programme for introduction session

    1. Introduction to IPMA Certification

    2. CV on education, career etc.

    3. Basis for competence assessment

    4. Description of experience application

    5. Self-assessment

    6. Application for Level C Certification

    7. People to be contacted for references

    8. Written examination

    9. Project report,

    10.Competence development plan

    11.Interview

    12.Final evaluation

    13.General information

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page5

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    6/83

    The certification - in brief

    1.

    Test the project managers competence tolead a project by applying knowledge andexperience in an appropriate way

    2.

    Assesses PM-Behavioural, PM-Technicaland PM-Contextual competencesand theability to make thesepart competences tostrengthen each other by managing projects

    3.

    Assessed by two assessors who themselveshold an IPMA certificate in projectmanagement and act independently, justbound to the rules and regulations set for allIPMA organisations

    4.

    Certification in four levels which reflectsand supports a career with project

    management

    5.

    Participation in the certification is a self-learning process which gives a characteristiclift of competences

    6.

    Managed by the PMDAN

    7.

    The certification is recognisedinternationally by certification organisationsin more than 50 countries

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page6

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    7/83

    Requirements for Level C (1)CertifiedProject Manager

    Competent to

    to manage projectswith limited complexity,

    and/or to assistthe managerof a complex

    project in all competence elements of projectmanagement.

    Implies that the candidate can manage a project

    with limited complexityin all its aspects, or formanaging a sub-project of a complex project.

    Implies that the candidate applies appropriateproject management processes, methods,techniques and tools.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page7

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    8/83

    Requirements for Level C (2)Certified Project Manager

    Experience application

    At least 36 man-monthsof project managementexperience in a responsible leadership role ofprojects with limited complexity.

    The 36man-monthsshould not be older than 6

    years, but upon request a period up to 9 yearscan

    be accepted (with appropriate justification)

    The complexityof the assessed projects shall be

    evaluated against the following criteria: Objectives, assessment of results Interested parties, integration

    Cultural and social context

    Degree of innovation, general conditions Project structure, demand for coordination Project organisation

    Leadership, teamwork, decisions Resources, including finance Risks and opportunities

    Project management methods, tools and

    techniques.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page8

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    9/83

    Requirements for Level C (3)Certified Project Manager

    Knowledge

    knowledgeof a few methods and tools for most of

    the competence elements of the ICB in lesscomplex project management situations, includingevaluating the methods and tools appliedin the

    project managed by the candidate.

    Practical experience

    Practicalexperiencefrom applications withseveral participants, in several situations withinprojects with limited complexity. The project shall

    be complex enough that the reporting andinterview is possible on all competence elements.

    Reflecton own behaviour and make improvementsfrom time to time.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page9

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    10/83

    IPMA Level CCertification Procedure (1)

    Stage 1: Application, Self-assessment1.1Preparation

    Get familiar with the application documentsand/or collect questions on these (to be

    answered in the introduction session)1.2Introduction session

    Webinar for applicants (28 October 2013)

    14.00-17:001.3Application, Self-assessment

    To be submitted at the latest (25 November2013)

    1.4Report proposal

    To be submitted at the latest (25 November2013)

    1.5First feedbackBy 7 January 2014

    Stage 2: Referees, Exam

    2.1 People to be contacted for references

    By 25 November 20132.2 Written exam (3 hrs)- 10 January 2014

    (13.00-16:00)

    Venue:Best Western Premier Port Harcourt HotelKm 16, Aba expressway, opposite Intels camp,Port Harcourt, Rivers State.

    Mobile: +234 803-871-8302, +234-810-209-0401

    Tel:+234 (084) 465 700

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page10

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    11/83

    IPMA Level CCertification Procedure (2)

    Stage 3: Report, Competence development planBy 10 February 2014

    3.1 Report3.2 Competence development plan

    Stage 4: Interview

    4.1 Interview- 9 January 2014(9.00-17:00).

    Venue:Best Western Premier Port Harcourt HotelKm 16, Aba expressway, opposite Intels camp,Port Harcourt, Rivers State.

    Mobile: +234 803-871-8302, +234-810-209-0401Tel:+234 (084) 465 700

    Stage 5: Final evaluation

    5.1 Final evaluation and recommendation11 January 2014(9.00-17:00) afterinterview

    5.2 Decision and issue of certificate

    5.3 Feedback from the candidate

    5.4 Appeal

    Within 30 Working days after the decision, inwriting

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page11

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    12/83

    Change between levels

    If the assessment indicates that the candidates

    competences seem to be suitable for Level B, youcan change the level upon request.

    If the candidate passes Stage 1 (written exam) but

    not the following Stages, you can change toIPMA Level D upon request.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page12

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    13/83

    2.

    CV on education, career etc.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page13

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    14/83

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page14

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    15/83

    Guidelines for filling in the CV Part 1

    The candidate Insert your name at the first page in the file. Insert your photo in the document

    Explanation

    Specify both motivation for yourcompany and your personal motivation

    Basic education(s) Fill in your long term education(s)

    Career

    Start with your latest employment.

    State both year and month: YY/MM

    If you have changed function in a corporation

    use a new line in the form. Function/responsibility stated by three lines

    about project related roles.

    Extra line(s) with leave maternity or other

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page15

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    16/83

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page16

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    17/83

    Courses/seminars/conferences/network

    Also education in project management as apart of basic education

    Number of days at training modules and possiblypractice periods as a part of the education

    Practice periods include self-study, coaching, useat own project etc.

    The three statements reflect your personalgainings and should not summarise the

    content.Literature on project management and otherrelevant issues

    Internal guidelines can also be included if sosupply with keyword on content

    The three statements reflect your personalgainings summarising the content

    Slides from courses are to be filled in undercourses not as literature

    Own articles

    Both internal and external presentations

    Reference persons

    You specify 2 (and only 2) reference persons

    The reference persons has to have insight inyour management effort not only the results ofthe projects

    State projects, where the reference person hasan insight or the period for the co-operation

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page17

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    18/83

    The reference persons may not be a member ofthe IPMA assessor corps

    This is a separate document

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page18

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    19/83

    3.Basis for competence

    assessment

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page19

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    20/83

    Total use of the IPMA Competence

    Baseline for ProjectManagement

    1. Introduction meetingGet an overview of the tools and an opportunity topractice selectedelements.

    2. Self-assessment

    Work out the main steps describing knowledge andexperience applications of the Technical,

    Behavioural and Contextual competences.

    Remember to use the guidelines for each step.

    3. Development plan

    Plan a further development of your general

    competences in management of project and/orspecific initiatives in the current project to improvethe project management.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page20

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    21/83

    4.Description of experience

    application

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page21

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    22/83

    The purpose of describing Experience

    Application

    1. Your experiences in project managementaredocumented.

    Useful for your career as project manager

    - and a requirement for certification

    2. A chronological consideration of your

    career in project management establishesa solid basis for the next step of the

    competence assessment, where we decideon your experiences in using chosenproject methods.

    3. Specifications of experiences give anopportunity to reflect and learn aboutmanaging projects.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page22

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    23/83

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page23

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    24/83

    Guidance to description of

    management experience (1)

    The number of projects are not limited Formally not older than 6 years, but we can

    accept up to 9 years, with reasons

    Informative project name

    Max. 3 lines of description

    Organisation of employment + other major

    organisations involved

    Max. 3 organisations and max. 3 lines

    Own organisation, customer organization orothers

    Start- and close

    For the part of the project you were involved in.That is not necessarily the whole projects startand close

    Total resources

    For the part of the project you were involved in

    Active participants

    Active participants are those who use aconsiderable part of their time on the project(eg. permanent project participants, sub-projectmanagers, project co-ordinators, working groupleaders etc.)

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page24

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    25/83

    Guidance to description of

    management experience (2)

    Other participants

    The number who has contributed to the result ofthe project in short periods or in minor degree(eg. members of reference groups, testers,specialists etc.)

    Type of project task

    BD Business Development BF Building Facilities, etc

    OD Organisational Development

    PD Product Development

    SD Systems Development

    SI Systems Supply/Implementation

    TF Technical Facilities

    Own role in project

    PrM Program Manager

    PfM Portfolio Manager

    SPM Senior Project Manager

    PM Project Manager

    SubPM Sub-Project Manager

    PMA PM Associate

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page25

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    26/83

    Manager of phases

    Covers the phases where you were involved

    Entire lifecycle from idea to operation/application

    Developing the project ideas into a definedconcept

    Further developing the concept into detailedspecification of project results

    Transferring specifications into finalresults/products and operation/application

    Level A, B, C complexity

    Level A complexity - complex portfolios orprogrammes

    Level B complexity - complex projects

    Level C complexity projects of limited

    complexityNumber of man-months

    The time spent on project management orparticipation in managing projects

    Per year only a maximum of 12 man months can

    be earned

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page26

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    27/83

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page27

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    28/83

    Requirements as to extent and

    character of experience

    At least 36 man-monthsof project managementexperience in a responsible leadership role ofprojects with limited complexity.

    The 36man-monthsshould not be older than 6years, but upon request a period up to 9 yearscan be accepted (with appropriate justification)

    The 36person-monthsare in a responsible

    leadership function ofprojects with limitedcomplexity

    All projects that are part of the assessmentshould be included in the form.

    Only 12 man-months effort can be earnedas experience per year overtime should notbe included.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page28

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    29/83

    Complexity of portfolio, programme

    and projects (1)

    Level A complexity (complex portfolios orprogrammes)

    The main criteria for the complexity of a portfolio or

    programme are:

    Number, importance, variety and complexity ofactive projects in the programme or portfolio and

    number of project managers directed. Proposals to the overseeing body for decision and

    own decisions.

    Selection and development of project

    management requirements, processes, methods,techniques, tool, regulations and guidelines in theorganisation.

    Influence on the selection, training andemployment of project managers. Coordination of all projects of their portfolios or

    programmes and ensuring compliance to

    strategy.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page29

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    30/83

    Complexity of portfolio, programme

    and projects (2)

    Level B complexity (complex projects)

    At Level B the complexity of the assessed projectsshall be evaluated against the following criteria:

    1. Objectives, Assessment of Results

    Mandate and objective (uncertain, vague),Conflicting objectives (many), Transparency of

    mandate and objectives (low), Interdependenceof objectives (high), Number and assessment ofresults (multi-dimensional)

    2. Interested Parties, Integration

    Interested parties, lobbies (numerous),

    Categories of stakeholders (many, different),Stakeholder interrelations (unknown), Interests

    of involved parties (divergent)3. Cultural and social context

    Diversity of context (diverse), Cultural variety(multicultural), Geographic distances (distant,

    distributed), Social span (large)

    4. Degree of innovation, general conditions

    Technological degree of innovation (unknown),Demand of creativity (innovative), Scope fordevelopment (large), Significance on public

    agenda (large interest)

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page30

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    31/83

    Complexity of portfolio, programme

    and projects (3)

    5. Project structure, demand forcoordination

    Structures to be coordinated (numerousstructures), Demand of coordination (large),Structuring of phases (overlapping), Demand forreporting (multidimensional)

    6. Project organisation

    Number of interfaces (many), Demand for

    communication (indirect, manifold), Hierarchicalstructure (matrix, multi-dimensional), Relationswith permanent organisations (intensive,

    mutual)

    7. Leadership, teamwork, decisionsNumber of sub-ordinates (many, large controlspan), Team structure (many, dynamic),Leadership style (variable, adaptive), Decision-making processes (many important decisions)

    8. Resources including finance

    Availability of people (uncertain, changing),

    Financial resources (many investors and kinds ofresources), Capital investment (large), Quantityand diversity of staff (large)

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page31

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    32/83

    Complexity of portfolio, programme

    and projects (4)

    9. Risk and opportunities

    Predictability of risks and opportunities (low),

    Risk probability (high), significance of impacts(large), Potential of opportunities (large),Options for action to minimise risks (large)

    10. PM methods, tools and techniques

    Variety of methods and tools applied (manifold),Application of standards (few), Availability of

    support (low), Proportion of PM to total projectwork (high)

    Level C complexitySame as level B, but of limited complexity

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page32

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    33/83

    Evaluation of project management

    complexity for Level C (1)

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page33

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    34/83

    Evaluation of project management

    complexity for Level C (2)

    The evaluation is done in separate Excel spread sheetComplexity_Evaluation_form:

    C.2_Name_Surname_Complexity_Evaluation_form_Date

    This scheme is used to assess the complexity ofproject management in a project.

    Each indicator is rated according to four levels of

    complexity (4 = very high complexity, 3 = highcomplexity, 2 = low complexity, 1 = very lowcomplexity).

    If the total complexity value is equal or exceeding18 points, a project is appropriate to be used in acertification process on IPMA Level C.

    Ratings between 16 and 20 points need a carefulverification. For a complete evaluation all criteriahave to be rated.

    For a complete evaluation all criteria have to berated.

    On completing the scheme the Totalcomplexityscore is calculated.

    When complexity is evaluated the projectmanagement complexityis in focus not thecomplexity of the project task.

    Just forward complexity evaluation of the projectwhich you later, in the application, report onexperiences but do use the form for assessingmore/all projects.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page34

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    35/83

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page35

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    36/83

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page36

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    37/83

    Reporting on experience from

    managing chosen project (1)

    You choose a newer project with limited

    complexity, which you use to demonstrateyour

    competencesin project management and your

    abilityto extract learning.

    In the first form copy the information on the

    chosen project from the form Extent and characterof PM Experience

    At the upper half of the page give a further

    descriptionof the project bullet-form preferred.

    May clarify its context, goals, resources, deadlines

    and the organization incl. own role.

    On the following pages of the application form you

    explain three (3) managementchallengesincl.

    initiatives, resultsand gainedlearning.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page37

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    38/83

    Reporting on experience from

    managing chosen project (2)

    You analyse threemanagement tasks using thefollowing steps:

    1. Describing the challengefocusing on what

    should be achieved from managing the project

    2. State your factual managerial initiativesand

    applications to cope with the challenge

    3. Summarize the managerial outcomesof the

    initiatives and/or lack of outcome

    4. Describe what you have learnedand how this

    learning has been applied later

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page38

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    39/83

    Reporting on experience from

    managing chosen project (3)

    The situation, initiatives, outcomes and learning

    shall be about managing projects.

    Under initiatives and learning refer in the column to

    the right to a maximum of two elements of the ICB.

    The more specificthe challenges are formulated

    the more specific you can formulate the learning.

    One form must be a maximum of one A4 page

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page39

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    40/83

    Example of Report experience from

    managing chosen project

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page40

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    41/83

    5.

    Self-assessment

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page41

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    42/83

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page42

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    43/83

    Procedure for self-assessment (1)

    The applicant shall assess their knowledge and

    experiencefor all competence elementsof theICB.

    As an aid for the applicant, the self-assessment

    form includes a rationale for the scores, particularly

    for the high and low ones.

    The applicants assess their competence by

    reflecting on their activities in projects and lessons

    learned.

    After completing their self-assessment, the

    applicant should discuss the results with another

    person who knows them well. The outcome of such

    a discussion may result in an adjustment of thescores.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page43

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    44/83

    6.Application for

    Level C Certification

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page44

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    45/83

    Requirements to contents of

    application

    The document shall be forwarded by e-mail [email protected]. Word-format is recommended

    Electronic file-name:

    C.1_First name_Surname-ApplicationForm_Date

    Date is stated as: YY-MM-DD

    At new versions the date is changed.

    On request from the Certification Body an

    updated application has to be submitted e.g. if

    the application is not complete

    Relevant documentation shall be archived in hard

    copy and/or electronically for at least six yearsfrom the date of certification.

    The CB undertakes to keep confidential all

    information from the application and

    certification process

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page45

    of83

    mailto:[email protected]:[email protected]
  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    46/83

    The candidates documents from stage 1

    Document content Number

    ofpages

    CV incl. photo and application 3

    Extent and character of projectmanagement experience

    1-2

    Distribution of own man monthper year

    1

    Evaluation of projectmanagement complexity (only

    for one project)

    1

    Report experience frommanaging chosen project

    4

    Self-assessment 1

    Report (Body, pages) 5-15

    Report (Appendices, maximumpages)

    10

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page46

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    47/83

    7.People to be contacted for

    references

    Contact details of at least two referees

    are to be provided by the candidate.

    The assessors shall contact as manyreferees, named by the applicant, as isdeemed necessary to assist in the

    assessment of the applicants eligibilityand competence.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page47

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    48/83

    8.

    Written exam

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page48

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    49/83

    Practical information of the

    examination (1)

    Examination on paper:

    The examination will be conducted in writing

    on paper. Each candidate should thereforecarry proper writing utensils to theexamination place.

    The examination will take place 10th

    January 2014(13:00-16:00)

    Venue:Best Western Premier Port Harcourt Hotel

    Km 16, Aba expressway, opposite Intels camp,

    Port Harcourt, Rivers State.Mobile: +234 803-871-8302, +234-810-209-0401Tel:+234 (084) 465 700

    Duration:

    3 hours

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page49

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    50/83

    Practical information of the

    examination (2)

    Aids:

    No further aids (books, scripts etc.) are

    allowed at the examination.

    No own note paper is to be brought to the

    examination. Note paper will be made

    available by the assessors, if needed. This has

    to be returned together with the examination

    papers and the task sheets at the end of the

    examination to the assessors.

    Certification fees:

    Only applicants with paid fees shall beadmitted to exams

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page50

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    51/83

    Structure of exam (1)

    17 Direct questions

    14 Open essays and/or Intellectual tasks

    Duration at least 3 hours.

    35% of the competence elements will be covered

    with the direct questions and at least 2 competence

    elements per range will be covered in the open

    essays and / or intellectual tasks.Direct questions are multiple choice or single

    questions.

    Open essays are proposals, calculations or

    process descriptions.

    Intellectual tasks are case studies (may be withseveral questions).

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page51

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    52/83

    Structure of exam (2)

    Part 1

    30 multiple choice tasks

    Each correct answer gives 1 point

    (Max. of 30 points could be achieved)

    Part 2

    12 single questions,

    Each correct answer gives 5 points

    Answer in about 2 to 3 lines or 3 to 6 list items

    (Max. of 60 points could be achieved)

    Part 3

    Project case with 14 questions

    14 x 5 points = 70 points,

    (Max. of 70 points could be achieved)

    20 minutes for rework and final check of answers.

    A maximum 160 points could be achieved.

    To Pass 100 points should be achieved

    (corresponding to 62,5% of accepted answers)

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page52

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    53/83

    Examples for part 1: Multiple choice

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page53

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    54/83

    Examples for part 2: Single questions

    Question 1:

    Mention four typical project phases.Question 2:

    Elaborate the answers by giving a brief

    description of the contents and result of each

    of the phases.

    Question 3:

    Describe briefly: What is a risk analysis?

    Question 4:

    When is a risk analysis to be carried out?

    Question 5:

    What are the four most important steps of a

    risk analyses and what is the substance ofeach of the steps?

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page54

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    55/83

    Introduction to Part 3: Project

    example

    The framework for the task is an example of

    project with limited complexity, in which 'the

    application of the knowledge in the project

    management competence elements to a

    practical case should be treated within the

    framework of the example e.g. tasks of objective description, planning

    and follow-up of the project example.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page55

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    56/83

    9.Project short report

    See separate sampleProject short report:

    C.2_Name_Surname_Project_short_report_Date

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page56

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    57/83

    Outline description of Project short

    report

    Project

    Description of project stakeholders, resource

    frame, total duration and role in the project

    organization incl. own place and role. Attach

    project organisation chart and project time

    schedule with project phases on one sheet each.Project Characteristics

    Main characteristics of management complexity set

    of management efforts during the project.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page57

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    58/83

    Guidance for Project short report p.1The report has two objectives:

    The final report should show the candidate'scompetence in managing a project of limited

    complexity in each of the competence elements

    described.

    Work on the development will contribute to

    development of the candidate's competence.

    The font size should be 10 point, and the report

    must not exceed 15 pages plus 10 pages

    appendices.

    If the report is longer than 15 pages plus 10

    pages appendices,it will be rejected.

    Report should highlight own role in the project. TheSTAR method(situation, taskof the applicant

    (the challenge/problem), actiontaken, result of

    the action, what the applicant learnt and how this

    learning has been applied in subsequent projects

    for each element described)should be used for

    describing the project management of thecandidate.

    It is also expected that the report will be a

    presentation of the project results / benefits /

    dividends.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page58

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    59/83

    Guidance for Project short report p.2

    It is recommended to supplement the report with

    up to 10 pages of appendices, which illustratesthe applicationof methods and techniques.

    The STAR method (situation, task, action, results)

    should be used for describing the project

    management of the candidate for each element

    described.

    It is recommended you use personal form in the

    description and clarify own role when handling

    management tasks.

    One competence elementshould be described in

    not more than 3/4 of one A4 page

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page59

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    60/83

    Scope of Project short report at

    IPMA Level C

    Body, pages 5-15

    Appendices, maximum pages 10

    M in im u m n u m b e r o f co m p e t en c e e l e m e n t s

    a d d r e s se d ( I CB )

    Technical 12

    Behavioural 5

    Contextual 4

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page60

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    61/83

    10. Competence development

    plan

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page61

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    62/83

    Managing competence development

    Practice management of projects with limited

    complexity

    Reflect on experience, gained from own practice,

    maybe with sparring partner, team

    Use practice, theory, expert opinion within ownorganisation, PM quality management, developmentof standards and guidelines

    Use feedback from lecturing and trainings, preparenew modules

    Evaluate performance of professionals on same levelor level of direct subordinates (assessments,discuss their professional development)

    Use practice, theory, expert opinion of third parties,

    network, external assessment, development ofstandards and guidelines

    Participate in seminars and conferences

    Study professional books, journals, magazinesyourself

    Participate in continuing professional education andtrainings

    Maintain own competence and update own self-

    assessment sheetfor renewing your IPMA Level Ccertificate

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page62

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    63/83

    Guidelines for competence

    development

    It is recommended that you prepare a personalplan for developing your competences in managingprojects with limited complexity for the year tocome.

    The plan is based on the assessment of yourcurrent competences. As a first step you record

    your competence development of the current year.You update your self-assessment sheet.

    Then you identify your development potentialand establish the most important objectives for

    your next year's development.

    The achievement record for the current year andthe plan for the next year shall be documented withspecific and quantitative facts. The following tablecan be useful

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page63

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    64/83

    Description of development initiatives

    Name Period Date:

    Description of professional developmentinitiatives

    Numberofdays

    Achieved competenceselement(s)

    PM-technical

    co

    mpetence

    PM-behavioural

    co

    mpetence

    PM-contextual

    co

    mpetence

    Practice Project management:specific

    competence development activities youwere / plan to be engagedReflect on experience, gained from own

    practiceUse competence development in ownorganisation

    Use feedback and new modules from lecturing

    and trainings

    Evaluate performance on same level or ofsubordinate level

    Use competence of third parties

    Participate in seminars and conferences

    Study professional literature yourself

    Participate in PM continuous education andtrainings

    Update own self-assessment sheet

    Number of days in total:

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page64

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    65/83

    11. Interview session

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page65

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    66/83

    Organising of Interview Session

    Based on self-assessment, workshop and

    report, an interview with the candidate is

    carried out.

    The candidate must bring his application

    forms.

    The candidate is encouraged to bring

    examples of using the methods

    Uncertainties from the self-assessment

    should be elaborated.

    Behaviour competence elements are also

    assessed at the interview. The guideline isto assess about 6 PM-technical, about 2

    PM-behavioural and about2 PM-

    contextualcompetence elements in the

    interview.

    The interview takes not less than. 1 hour.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page66

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    67/83

    Program for Interview

    Participants

    The candidate and at least two assessors.

    Dialogue on competence

    In the interview the assessors shall ask

    questions they have previously prepared

    related to the self-assessment, the report andthe workshop. The questions may include:

    A check of statements in the documentation

    submitted.

    An exploration of gaps, strengths and

    weaknesses in the knowledge andexperience of the candidate.

    A demonstration of the competence of the

    candidate related to managing projects,

    Dialogue on competence development

    Feed-back from assessors - which is not apart of the formal exam shall be delivered

    by e-mail or after the interview

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page67

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    68/83

    12. Final evaluation

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page68

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    69/83

    Final assessment

    Upon completion of the interview, the

    assessors determine if the candidate hassatisfactorily met all required criteria for the

    IPMA Level applied for. Their recommendation

    with supporting documentation is then

    forwarded to the CB operational management

    for decision. Both assessors are required to

    verify the evaluation report. The self

    assessment score is not part of the final

    evaluation.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page69

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    70/83

    Issuing of certificate (1)

    On behalf of the CB, the operational

    management of the CB shall make the

    decision about granting a pass or fail based

    upon the recommendation of the assessors.

    Certificates shall be issued in English

    language.

    Certificates shall be registered in both CB and

    IPMA databases. The information is published

    on the IPMA website as public information

    unless the applicant has explicitly expressed a

    wish not to.

    The CB shall use the IPMA standard certificate

    and the Accompanying Sheet with the

    summary of the certification scheme for all

    certificates.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page70

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    71/83

    Issuing of certificate (2)

    The certificate will be issued on the final day

    of the certification process.

    The names of the certified in project

    management are published:

    On www.pmdan.org

    (2-6weeks after the certificate is issued)

    On www.ipma.ch(will be updated 4 times a year)

    If the candidate does notwant to have the

    name published, written announcement

    together with the CV mustbe given.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page71

    of83

    http://www.pmdan.org/http://www.ipma.ch/http://www.ipma.ch/http://www.pmdan.org/
  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    72/83

    Appeal against CBdecisions

    An applicant who is not accepted or candidate

    who fails the initial certification process can

    file an appeal to the CB. Such an appeal shall

    be made in writing to the CB within 30

    working days of the decision and shall include

    reasons for the appeal.

    The candidate should give a writtenreasoningfor the appeal to the

    Certification Secretariat not to exceed 2

    A4-pages.

    It mustbe stated that it is a formal

    appeal.

    The secretariat forwards the appeal to the

    AppealCommitteetogether with relevant

    documents from the certification in question

    The Appeal Committee assesses the appeal

    and decides if a new assessorassessmentshould be done.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page72

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    73/83

    13. General information

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page73

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    74/83

    IPMA Level C Certification Procedure

    Stage 1: Application, Self-assessment

    1.6PreparationGet familiar with the application documentsand/or collect questions on these (to beanswered in the introduction session)

    1.7Introduction session

    Webinar for applicants (28 October 2013)

    14.00-17:00

    1.8Application, Self-assessmentTo be submitted at the latest (25 November

    2013)1.9Report proposal

    To be submitted at the latest (25 November

    2013)1.10 First feedback

    By 7 January 2014Stage 2: Referees, Exam

    2.1 People to be contacted for references

    By 25 November 20132.2 Written exam (3 hrs)- 10 January 2014

    (13.00-16:00)Venue:

    Best Western Premier Port Harcourt HotelKm 16, Aba expressway, opposite Intels camp,Port Harcourt, Rivers State.Mobile: +234 803-871-8302, +234-810-209-0401

    Tel:+234 (084) 465 700

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page74

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    75/83

    IPMA Level CCertification Procedure (2)

    Stage 3: Report, Competence development planBy 10 February 2014

    3.1 Report3.2 Competence development plan

    Stage 4: Interview

    4.1 Interview- 9 January 2014(9.00-17:00).

    Venue:Best Western Premier Port Harcourt HotelKm 16, Aba expressway, opposite Intels camp,

    Port Harcourt, Rivers State.Mobile: +234 803-871-8302, +234-810-209-0401Tel:+234 (084) 465 700

    Stage 5: Final evaluation

    5.5 Final evaluation and recommendation

    11 January 2014(9.00-17:00) afterinterview

    5.6 Decision and issue of certificate

    5.7 Feedback from the candidate

    5.8 Appeal

    Within 30 Working days after the decision, inwriting

    Certification fees:

    Certification Fees shall be paid no later than 25November 2013. Only applicants with paidfees shall have their application forms

    reviewed

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page75

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    76/83

    IPMA 4 Level Certification personal effort

    The following figures indicate the average personaleffort of the candidate to be reserved for proper

    preparation of the assessment:

    IPMA Level D 30 hours

    IPMA Level C 60 hours

    IPMA Level B 90 hours

    IPMA Level A 120 hours

    PMDAN recommends seeking for professionalsupport in preparing yourself for the examination.

    Further information can be obtained by contactingus directly.

    Assessors Level CCurrently, the following assessors are appointed by

    PMDAN CB to conduct Level B certifications:

    Mr. Per Frank Povlsen

    Foreign First Assessor to PMDAN

    Dr. Chinwi Obari MgbereNational First Assessor to PMDAN

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page76

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    77/83

    Introduction to re-certification (1)

    When the certificate has been achieved it

    should be maintained.

    After 5 yearsa report an application and

    report should be forwarded concerning re-

    certification. The report should document

    that the certificate is still competent

    It is expected, that the candidate

    was activein project management in

    the last 5 years and

    developedhis/her competence in

    project management in the past 5

    years

    The current guidelines for the reporting aim

    at forwarding a new version of the material

    from the first stageof the certification.

    The candidate can also be asked to forward

    further documentation as part of the re-

    certification and/or be summoned to an

    interview meeting.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page77

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    78/83

    Introduction to re-certification (2)

    It is the responsibility of the certificate holder

    to monitor the expiry date of their certificate

    and to initiate the recertification process.

    Recertification focuses on a candidates

    development and professional experience

    since obtaining their initial certification or

    latest recertification.

    The recertification candidate shall be

    assessed by two assessors. If there is any

    doubt as to the result, then the assessors

    shall propose an interview via the CB. A

    recommendation is then made regardingrenewal. If non-renewal is recommended,

    supporting documentation shall accompany

    the recommendation.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page78

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    79/83

    Introduction to re-certification (3)

    The recertification process steps are

    1. Stage 1: Application, CV, Self-

    Assessment, List of projects

    2. Stage 2: References, eventual complaints

    3. Stage 3: Competence development Plan

    4. Stage 4: Interview if necessary

    5. Stage 5: Final Evaluation andRecommendation, Decision and issue of the

    certificate, Feedback from the candidate

    The Application shall include all necessary

    personal details and the recertification level

    applied for.

    The certificate holder shall confirm that they

    agree to abide by the conditions and

    obligations of the IPMA recertification process

    including, but not limited to: recertification

    fees, code of conduct, publication of their

    name (unless they have explicitly expressed awish not to do so).

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page79

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    80/83

    Introduction to re-certification (4)

    In addition to that specified in the CV, it shall

    be supplemented with information about the

    individuals Continuous Professional

    Development since the initial certification or

    recertification.

    If the assessors, having evaluated the

    documents, consider it necessary torecommend an interview, the CB shall make

    the decision as to whether it will take place.

    The candidate shall be entitled to present

    additional evidence to support their claim of

    competence, professional development and

    their professional conduct at the interview.

    A recertification candidate who has been

    denied renewal of the certificate may file an

    appeal for reconsideration of the decision.

    Such an appeal must be made in writing to

    the CB within 30 working days of the decisionand must include reasons for the appeal.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page80

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    81/83

    Assessment (1)

    The candidates self-assessment has to be

    considered in the assessment and has to bechecked by the assessors for consistency and

    credibility.

    For the candidate to pass the recertification

    process, the CB must fulfil the administrative

    requirements of the recertification process(e.g. correct assignment of assessors to

    candidates, ensures fees are paid) and the

    candidate:

    Attains a minimum for both professional

    project management activities/assignments of50%.

    Has evidence of Continuing Professional

    Development of 35 hours per annum, during

    the last 5 years.

    Has complied with the code of professionalconduct.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page81

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    82/83

    Assessment (2)

    The following outcomes are possible as a

    result of the recertification assessment:

    Renewal of certificate.

    Renewal of certificate following satisfactory

    interview/ and/or references/ and/or review of

    complaints/ and/or an enquiry for additional

    information from the candidate for

    clarification.

    Non-renewal of certificate following

    unsatisfactory interview and/or references

    and/or review of complaints/ and/or an

    enquiry for additional information from thecandidate.

    If any doubt exists, the CB shall invite the

    candidate to an interview with the assessors.

    A determination will then be made pending

    the outcome of the interview.

    Cert_Cp_Version 1.1_130917 Candidates Manual Level C page82

    of83

  • 8/10/2019 C.2 Candidates Manual Version 1.1-131017

    83/83

    Change control

    Issue Status Author Page Date Comme

    nts

    Version 1.0 Released Dr. Chinwi Mgbere 13.05.01

    Version 1.1 Released Dr. Chinwi Mgbere 13.10.17 Released

    for C2