bureau of reclamation - j...as studies progressed, it became evident that it would be feasible to...

31
r '� I t · I a < BHR:\U OF R''C,:. ! l�·mTmT HYDHAUJ,IC LABCJHA'l'tJ1lY WH BORRO� RETUf PiiOi,1FTLY HYDRAULICS BRANCH OFFICIAL FILE COPY HYDRAULIC DESIGN FEATURES OF THE CANADIAN RIVER AQUEDUCT by Harvey C. Olander Head, Canals and Bridges Section Office of Chief Engineer Bureau of Reclamation Denver, Colorado A paper presented at the fall meeting of the Texas Section of the American Society of Civil Engineers, Fort Worth, Texas, October 7-9, 1965

Upload: others

Post on 24-Aug-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

r

'�

(\j

I

Q_

<(_ Q_

t'"'i ·..O

I

a..

< �

BHR!I:\U OF R'i!'Ci:,:.!l�·mTmT

HYDHAUJ,IC LABCJHA'l'tJ1lY

WHEN BORRO� RETUfuf PiiOi,1FTLY

HYDRAULICS BRANCH

OFFICIAL FILE COPY

HYDRAULIC DESIGN FEATURES

OF THE

CANADIAN RIVER AQUEDUCT

by

Harvey C. Olander

Head, Canals and Bridges Section Office of Chief Engineer

Bureau of Reclamation

Denver, Colorado

A paper presented at the fall meeting

of the Texas Section of the American

Society of Civil Engineers, Fort Worth, Texas, October 7-9, 1965

Page 2: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

HYDRAULIC DESIGN OF CANADIAN RIVER AQUEDUCT

The 320-mile Canadian River Aqueduct is the Bureau of Reclamation's longest pipeline system. It delivers municipal water from Lake Meredith at Sanford Dam to 11 Texas cities. In the Northern System, water is raised approxi­mately 720 ft in 4 lifts to a regulating reservoir at Amarillo. Detailed cost comparisons dictated pipeline sizes of 72 and 78 in. Surge and water hammer problems were solved by use of open surge tanks and careful timing of valve and pump operation. Automatic controls at each of the pumping plants were designed to reduce surge problems and coordinate the electric power demand with local power supply. Pipe sizes from 96 to 54 in carry the gravity flow through the Centrel System. The hydr�ulic gradient was made parallel to the ground surface, resulting in low head pipe and the most economical pipe sizes. "Pipe check" and "pipe stand" control struc­tures were placed at strategic points along the line, practically eliminat­ing pressure transients and surges. A computer program using elastic water column theory evaluated the design and location of these controls and closely confirmed laboratory test results. For the Southern System below Lubbock, a thin-wall type of pipe with embedded steel cylinder and cement mortar lining and coating was used. Flow is by gravity in a closed system with the static head being reduced in a series of steps by pressure­reducing stations.

DESCRIPTORS-- *aqueducts/ *pipelines/ hydraulic structures/ *pumping plants/ reservoirs/ forebays/ cost comparisons/ operation and maintenance/ *surges/ surge tanks/ valves/ *water hanmer/ *automatic control/ air traps/ timing circuits/ standpipes/ electric power demand/ hydraulic gradients/ computer programing/ check structures/ water pressures/ design data/ pumps/ flow control/ laboratory tests IDENTIFIERS-- Canadian Riv Aqueduct, Tex/ *hydraulic design/ Canadian River Proj, Tex/ water column separation/ Texas

Page 3: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

HYDRAULIC DESIGN FEA'I1JRES OF THE CANADIAN RIVER AQUEDUCT

The Canadian River Aqueduct is a series of pipelines totaling

about 320 miles in length. The aqueduct, a principal feature of the

Bureau of Reclamation's Canadian River Project in northwestern Texas,

is the Bureau's longest pipeline system. It serves the cities of

Amarillo, Borger, Pampa, Lubbock, Plainview, Brownfield, Levelland,

Slaton, Tahoka, O'Donnell, and Lamesa with water from the Canadian

River, which is stored in Lake Meredith, the reservoir impounded by

the project's Sanford Dam near Sanford, Texas. Many types of pipe

are used, largely of reinforced concrete. The aqueduct also has

many types of hydraulic structures, including pumping plants and the

large regulating reservoirs at Amarillo and Lubbock.

For the purposes of this paper, the aqueduct is divided into

three main divisions, as the basic operations of each are distinctly

different from a hydraulic standpoint. These divisions are desig­

nated Northern, Central, and Southern Systems, as shown in Figure 1.

The Northern part extends from Sanford Dam to Amarillo and includes

the East Aqueduct serving Borger and Pampa. The Central part extends

from Amarillo to Lubbock, and the Southern System extends south and

southwest of Lubbock.

Northern System

As it is simpler to treat each division separately, I will

begin with the Northern System. The main part of this system is

the pipeline bringing water from the dam to a regulating reservoir

Page 4: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

at Amarillo. To accomplish this, under normal operation, the water

must be raised approximately 720 feet. This is done in four lifts

by that many pumping plants. For reference, these plants, starting

at the dam, are consecutively numbered 1, 2, 3, and 4. See Figure 2.

Plants No. 2, 3, and 4 are of equal capacity, 160 cfs. Plant No. 1,

which must provide the extra amowtt required for the East Aqueduct

serving Borger and Pampa, has a capacity of 183 cfs.

Each plant, except No. 1, is preceded immediately by forebays

that are small concrete-lined reservoirs. Plant No. 1 is located at

the dam and draws directly from Lake Meredith. The forebay for Plant

No. 2, in addition to supplying East Aqueduct, also serves as after­

bay for Plant No. 1. A similar arrangement follows for the other

plants with the regulating reservoir at Amarillo serving as after­

bay for Plant No. 4. The pipelines between plants vary in length

from 1. 9 to 14.3 miles with internal diameters 72 and 78 inches.

The 72-inch sizes are used in regions of higher heads. These sizes

were determined by economic considerations, including first costs,

interest on the investment, and pumping costs.

Concerning cost studies, a graphical method introduced by Julian

Hinds in the Engineering News-Record, January 28, 1937, and March 25,

1937, was used for the preliminary economic studies. These proved

quite accurate. When the layouts of the pipelines were fairly well

established, detailed cost comparisons of various pipe sizes were

made. These confirmed the preliminary results by graphical methods

in every instance.

2

Page 5: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

As studies progressed, it became evident that it would be

feasible to make all pump units at Plants No. 2, 31

and 4 of equal

size. Since this was considered desirable, especially from mainte­

nance standpoint, the final locations of pumping plants were slightly

adjusted to complement this consideration.

The next step was to determine control of operations and most

economical ways of dealing with water-hammer and surge problems.

Operations of controls greatly influence transient pressures and

surges, which in turn can be minimized by judicious use of valves,

surge tanks, air chambers, etc. The schematic drawing shown in

Figure 3 illustrates the operation of the Northern System. We found

this drawing invaluable for coordination of the five branches involved

in·this design.

The best means of achieving economy in pipe costs usually dic-

tates types of controls, valves, timing, size of pwnps, etc. This

drawing serves as a working scheme for controls as we work out our

pipe design, and it also serves as design data for the other branches

involved. Each branch then contributes to developing the final

schematic which will provide the basis of the designers' operating

criteria.

Now in the type of system shown here, it is apparent that a

control valve must be used on the discharge side of each pump to

keep the pipes full. These should be automatically controlled to

close individually when their attendant pump stops and to open

when the pump starts. The timing must be adjustable so as to open

3

Page 6: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

or close at prescribed rates. The time of closure will greatly

affect water hammer and this in turn depends on the pump charac­

teristics, in particular the inertia of the pump and motor and the

pump's specific speed. In the Northern System, hydraulically

operated square-bottom gate valves were selected that open and

close at a wiiform rate of speed. In some cases it is advantageous

to specify variable rates of opening or closing. Sometimes check

valves are used where sudden closure is permissible, as in the

East Aqueduct and Southwest Aqueduct.

Beyond the control valve, the pipeline must be protected

against excessive transient pressures, particularly those that

could be brought about by water column separation, This consider­

ation is usually met most positively and economically by simple

open surge tanks located at carefully selected points in the line.

In some instances, open surge tanks are not feasible because

topographic conditions would require an excessively high tank. A

one-way surge tank may then be used in conjunction with an open

tank. A one-way surge tank provides water so as to prevent water

column sep3ration but does not protect against high-pressure tran­

sients. Another disadvantage of one-way surge tanks is that they

must depend upon the operation of valves; therefore, the valves

must be given the very best continuous maintenance to insure their

operation at all times. For safety, the Bureau has always provided

duplicate valves in parallel. Figure 4 gives a comparison of result­

ing pressure waves and design gradients using open and one-way surge

tanks.

4

Page 7: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

Air chambers often serve effectively where an open surge tank

cannot be built economically. These also require careful mainte­

nance, and in addition to valve problems, a supply of compressed

air must be maintained.

Surge suppressors and pressure relief or pressure reducing

valves are to be used when all else is not feasible, We have always

found that these valves respond too slowly to give instantaneous

relief and are uneconomical to use when resulting pressure tran­

sients are considered in the pipeline. In fact, where possibilities

of water column separation exist, and the profile of the pipeline

is such that the points of separation cannot be pinpointed, we can­

not predict the magnitude of the pressure transients, It must be

borne in mind that in long, large diameter pipelines, such as I am

now speaking of, a slight increase in design head greatly affects

the cost of the pipeline. This is quite different from small lines

where even nominal standard pipe usually provides strengths far in

excess of design heads and pressure transients often are not critical.

As mentioned before, timing of the controls is most critical

and therefore limitations must be imposed on timing. The frequency

at which motors are started and stopped affects their life. Sudden

changes in power load must be kept within the capabilities of the

power system to respond. Our pumps are controlled by float switches

in forebays and afterbays which start or stop pumps as water surfaces

rise or fall, You can visualize that the capacity of the forebays

5

Page 8: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

controls the timing of operation of pumps; or vice versa, the

capacity of the control reservoirs are determined by timing.

The Amarillo Regulating Reservoir, mentioned earlier, is

different from the other afterbays. The reservoir was placed at

the end of the Northern Branch where the flow of the aqueduct

changes from pumped to gravity flow. It is also near a point

where the capacity of the aqueduct changes considerably because of

deliveries made to Amarillo.

We originally considered this reservoir to have a smaller

capacity. However, after considering the scheme that the power

company proposed for supplying economical power, the capacity was

increased to 750 acre-feet; 250 acre-feet are for emergency use for

Amarillo, and the remaining 500 acre-feet are to provide flexibility

in the operation of pumps. Some shutdown time of the pumps is neces­

sary because the power company is not required to furnish power

during periods of peak load or when generating economies are affected,

The power company therefore is allowed to control pump operation,

This is done by remote manual operation of Plant No. 2, All other

pumps at the other plants are automatically controlled,

The East Aqueduct, a part of the Northem System, takes water

from Forebay No. 2 and delivers it to Borger and Pampa. Its opera­

tion involves features common to the Main Aqueduct just discussed

and features that will be discussed later under the Southern System,

6

Page 9: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

Central System

Proceeding south along the aqueduct, the Central System of

Canadian River Aqueduct will occupy our attention. As shown on the

condensed profile, Figure 5, the aqueduct proceeds by gravity flow

to Lubbock where another regulating reservoir receives the flow.

This stretch is 115 miles long. Only one small delivery is made

before reaching Lubbock, and that is at Plainview. The maximum

capacity of the Central System is 92 cfs.

As you can see, pipe sizes range from 96 to 54 inches with the

predominant size 66 inches. The hydraulic gradient has been made

parallel to the general ground surface, which results in low head

pipe and the most economical pipe sizes. You will notice also that

the design gradient is the same as the hydraulic gradient, which

means that controls are such as to practically eliminate pressure

transients and surges. This is accomplished by controlling the

flow at the upstream end. Such a system of controls would present

no problems if the flow were always steady, but it must be remembered

that the entire aqueduct must operate on a demand basis. The demand

is not as immediate as in a city distribution system; nevertheless,

it must meet requirements.

For example let us consider two extremes of meeting demand: If

the flow in the pipeline from Amarillo to Lubbock were controlled at

the upper end and the pipe allowed to drain whenever it was shut

down, it would take many days to refill the line and bring it up to

7

Page 10: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

full flow. On the other hand, if control of the line is at the

lower end, at Lubbock, flow could be started immediately, but the

design head for the pipe would be the static head established by

the water elevation in Amarillo Reservoir.

Obviously, neither of the above schemes are the solution to the

problem. The first one is too slow and the second one is too expen­

sive. The increased design head would have cost the project some

2-1/2 million dollars extra.

The solution used is to control the flow at the upper end but to

make provisions to keep the pipe full at all times. To do this, a

series of structures were placed at strategic points along the line

so as to establish a series of pools, as shown in Figures. These

structures are not all the same because, as we shall show later,

some had to perform other functions as well as establish a pool

elevation.

The simplest structure is the one shown in Figure 6. We have

called it a pipe check. This structure gives the smallest hydraulic

losses, and is least expensive to construct. However, there is

practically no room for storage of water, which would limit the use

of the structure.

Combined with the pipe check, we used the structure shown in

Figure 7. For convenience, we designate this a pipe stand. It also

holds the water upstream in the line at a certain pool elevation,

but in addition it has storage capacity. The size of the tanks was

varied as required by hydraulic considerations.

8

Page 11: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

At all the pipe check and pipe stand structures along the line,

a vent was placed immediately downstream as shown. It is imperative

that most of the air be removed from the system to prevent accumula­

tion of air pockets; otherwise an analysis to determine surges would

be nearly impossible.

It may appear that we are talking about the most simple type

water conveyance system, or simply, "turn the water on whenever you

want it and let it run." Many years ago, however, the Bureau had an

unfortunate experience with this very type of system for an irriga­

tion project. A series of check structures were used, and it was

found that under certain operating conditions, the surges at the

various checks came into resonance resulting in surges that literally

blew the lid off structures and discharged water high in the air.

This phenomenon is difficult to explain in a short discussion, but

if one runs through a simple graphical solution of the surge problem,

it becomes clear.

The problem resolves itself basically into a solution of Newton's

law; force is equal to mass times acceleration. In an individual

reach of pipe, the accelerating force is established by the difference

in heads at the structures at each end of the reach. You can visualize,

however, that when several such reaches are placed in series, the

surges that are taking place in one affect those in another and the

problem becomes compounded.

Figure 8 shows a graphical solution for a hypothetical problem

consisting of three reaches. The solution is based on rigid water

9

Page 12: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

column theory, which is accurate enough when surging alone is being

considered. Surges at the three structures are plotted against flows,

but time is also involved. You will notice that surging at the first

structure is relatively mild or the water rises in this structure at

a fairly unifonu rate. However, at points farther down the line,

surging progressively increases and becomes unmanageable at Pipe

Check No. 4. A more detailed drawing of this particular solution

is shown in Figure BA. This demonstrates the complexity of a graph­

ical solution for a rather simple system.

Our first study of the Central System surging was done graph­

ically. There are 21 reaches, and needless to say, it was very

difficult and extremely time consuming. It did show that we had

problems even in the one and only case considered, and that there

was a definite need to study many other conditions that may be

expected to arise in ordinary operation of the project. Therefore,

since considerable money was involved, it was decided to develop a

computer program for surge studies. It was also decided that some

experimental verification of the program should be attempted. All

this was carried out, but it became evident that in order to check

experimental results, considerable refinement would be required in

the computer program. Therefore, a very precise program was needed,

using elastic water column theory. We decided also to develop a

very flexible program.

In Volume 218, Part 1, 1963, of the Transactions of the ASCE,

a paper was published entitled "Water Hammer Analysis Including

10

Page 13: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

Fluid Friction" by Victor L. Streeter and Clinton Lai. This paper

outlines a theoretical analysis of water har.imcr with the inclusion

of hydraulic friction losses by a set of nonlinear, partial differ­

ential equations. These equations are transformed into character­

istic equations that are then organized into difference equations,

suitable for high-speed digital computers of fairly large storage

capacity.

The program has been written for the Bureau's H-800 Honeywell

computer (32, 000 words), and laboratory tests have verified the

theoretical analysis. Figure 9 shows the laboratory setup, and

Figure 10 shows a comparison of test results with theoretical

results. Surging is plotted against time for the last two struc­

tures in the laboratory setup.

Our studies show, that by using some pipe stand structures

interspersed with pipe check structures and a prescribed rate of

operation of the control valve at the upper end, the overall opera­

tion of the Central System becomes virtually problem free.

The pipe stand structures, by virtue of their storage capacity,

have the effect of placing small reservoirs at various points along

the pipeline, which tend to break the system up into many smaller

systems. Now one could proceed along this line and arrive at a

solution to the problem by using large pipe stand structures or

even regulating reservoirs spaced periodically with pipe check

structures between, and analyze the separate reaches individually

by graphical methods. However, we were able to keep the size of

11

Page 14: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

structures down and obtain considerable savings in the cost of this

system of the aqueduct.

There probably are an infinite number of modifications of the

Central System that could be used, but this is most economical. The

pipe is minimum size, minimum head, and no valves whatever are

required below the control valve near Amarillo. It takes several

hours to increase flow from zero to full capacity, but this is

rapid enough considering the large regulating reservoir at Lubbock.

Southern System

There were many factors that influenced selection of type of

hydraulic system used south of Lubbock. Nearly all considerations

of economy and operation lead to the same conclusion; namely, that

this should be a pressure system.

You may know that the City of Lubbock has entered into agree­

ment with all the other cities served by the Canadian River Aqueduct

south of Lubbock to treat their water. Each city will probably

wish to take their delivered water almost directly into the mains.

Therefore, the entire Southern System will function best as a demand

system, with each city operating independently of the demands of the

others. Any other type of system would be very difficult to operate.

Pipe sizes were to be small as compared with the Northern and

Central Systems; furthermore, we were persuaded that a thin wall

type of pipe with embedded steel cylinder and cement mortar lining

and coating would be economical in the area. This was because

coarse aggregate for thick wall pipe is not available in the near

12

Page 15: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

vicinity. Minimum designs for this type of pipe are good for rather

high heads, and therefore design pressures would not be as critical

as in the other two systems. This factor made it economically

feasible to use some form of pressure system which would satisfy

most requirements.

On Figure 1 you will notice that the main aqueduct proceeds

due south and a branch called the Southwest Aqueduct takes off just

north of Lubbock. The main aqueduct flows by gravity, whereas the

first part of the Southwest Aqueduct requires pumping. Four pumping

plants are required all together with open surge tanks and forebays.

The forebays are concrete tanks unlike the open concrete-lined

reservoirs on the Northern System, but aside from such differences,

the two pumping systems are very much alike. Therefore, I will not

talk any more about the Southwest Aqueduct, but will devote the

remainder of my discussion to the Main Aqueduct.

As mentioned before, flow is by gravity in a closed system,

but the full static head is not imposed on the entire pipeline.

The static head is reduced in a series of steps by means of struc­

tures that essentially amount to pressure-reducing stations, as

shown in Figure 11.

The locations of the pressure-reducing stations were first

detemined by turnouts. For hydraulic reasons regarding surges

and pressure transients, it is desirable to have a regulating tank

at all such points. Fortunately, placing regulating tanks at these

points could be used to advantage for pressure regulation, and the

13

Page 16: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

spacing was good as regards the resulting static heads on the various

reaches of pipe. That is, the maximum heads in all the various reaches

of pipe were fairly equal. Furthermore, each reach was in the head

range where the nominal strength of pipe would generally not be

exceeded.

I believe a little more detail about the pressure-reducing

stations would be of interest. Figure 12 shows the controls at

regulating Tank No. 6, the one at the turnout for the South Lubbock

Lateral. The three valves shown are installed in parallel but act

in series; that is, they open and close at different times, but one,

two, or all three may be open at the same time. Each valve is con­

trolled by a float in the regulating tank. As shown, one 16-inch

valve begins to open when the water surface drops below elevation

3200. 6. As the water continues to drop, the valve opens wider and

becomes fully open after the water surface has dropped 1 foot. The

next 16-inch valve begins to open at this point, and the process

continues, if the water surface continues to drop, until all three

valves are open.

The valves open or close through a limited range of water level

variation in the tank. Each valve will remain at a constant position

if the water surface in the tank remains constant. Therefore, if the

demand downstream from the regulating tank remains constant, the

valves will adjust themselves to maintain an equal amount of steady

flow into the tank. This valve feature is described as a modulating

feature. The three valves, two 16-inch and one 20-inch, are the

14

Page 17: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

main controls, and each is equipped with a rate-of-flow controller

which is set to limit the maximum flow so that the total flow from

the three valves is limited to a predetermined amount. This is to

insure that no part of the system may take more than their allotted

share of water and possibly rob another part.

The valves themselves are hydraulically operated, pneumatically

controlled butterfly valves. In some cases, where the difference

in head across the valves is great and cavitation may r�sult when

the valves are operating in a nearly closed position, air is intro­

duced through the valve on the downstream side. This has proven

very effective in reducing cavitation. There are different schemes

for introducing the air; sometimes through the valve disc and some­

times through the body of the valve around the perimeter just down­

stream from the disc-seating area. The latter method seems to be

most effective, especially for smaller valves.

You will notice a fourth large 30-inch butterfly valve just

upstream from the three controlling modulating valves. This large

valve is fully opened or fully closed by float switches in surge

Tank No. 10 upstream. When the water at the surge tank drops to a

predetermined low, the valve closes so as to prevent draining any

part of the pipeline upstream. The other valves shown are merely

shutoff valves to be used for servicing the control valves.

At each delivery point along the main aqueduct, a pressure­

reducing station has been set up featuring the type of control just

described.

15

Page 18: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

This briefly covers the hydraulic features of the Canadian

River Aqueduct. I am sure you would find it interesting to visit

the project, now under construction, to see completed parts and

view the work in progress. You will find personnel of the Bureau

of Reclamation very cooperative and eager to help you.

16

Page 19: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

.N SANFORD DAM,, ,--------- - -- ----�

:=JJb - 11r

' I

NORTHERN CONTROL STAT ION---, ,'

' 1 .... --,---· cANADJA../\l --- -

.,__ Borge rp •

-----.a a mpa '--EA ST

I I

I

�I Q:: I �

1.u:1.u :c:, ...... ...... I

(/)

a::)... C)1(/)

<!' I

AQUEDUCT� -- - -----·-- - -------x..

MAIN AQUEDUCT---

CONTROL STAT ION---- -----

(SOUTHWESTERN PUBLIC SERVICE COMPANY)

--

MAIN AQUEDUCT--

I

I

I

I I

I

._JI

q::� Q:: 11.u ..,_1..,_

<! :(/) l.aJ I)-.

(_) :(/) SOUTHERN

CONTROL STATION---,

I

I I I

I I

Abernathy ' ' ____ . ---------------! Level land >--.....--�;:() Lubbock :

SOUTHWEST __ Slaton �: AQUEDUCT-4&�- a::� IJJ1 laJ Brownf i e Id u----... l:: ..,_ t--,(/) :::, I:>­C) I(/)

Tahoka O'Donnel I MA IN AQUEDUCT---- (/)I

I Lamesa y_ ------ - - ---------- -- - --

MAP OF MAJOR SYSTEMS FIGURE I

Page 20: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

->-i Q:183 r- -- -------- -- - --- -- -------Q = 160 C. f.s.--- ----- --- -- - - - - --- - --->-1 I I I

II I 1 7 II I - II II p 7 II I . II Pl PE - I - II I 72->1 �- 8->+<-72->+<-- 78 Pl E--->-t<-- 2-->-<-- - -- 78 --- - - - -->+<.-- - - --72 Pl PE- - - - -->, I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I

¥91 /"--7DESIGN GRADIENT I

I I ' 1 I I I , I : : : : ,--------J.oESIGN GRADIENT

I ! / rHYDRAULIC GRADIENT: I I I I I / I I

:

1 : DESIGN � // : SURGE TANK #4,,_ 1

1�

I I ,.-, I : / I 0:: 1 l : //if GRADIENT 1 __ ... --HYDRAULIC GRADIENT 0: : I t_L I I

\ >I l I II I : ,HYDRAULIC I '-STATIC W.S. ffi: I : I : I I : GRADIENT I (/)I I I I ' , I w 1 I I Cle�!::::::::::::::;=:�5iiiii--JJ ' I ct: I I I I I 170, G. I I <.!)I 1''

I ' I ;zl

HG .. �\ 1 'STATIC W.S. 1� 1-' . . J. I \I ' I

, .,. <[ I } II""> v 1 1- .....J I

I

I I I I

::c I t-1 Cl �1-LLJ I# :Ela.:

I CL,; LLJI �, <C1 .....J1

--:tF�--s. W. S. t------S T :11: I IC\J ..

1:tt C\J l l­

.&&. lz

'fl' I <C >-1.....J <ela.. all LLJ I <.!:> a::,z o,­u.. a.. I� I:::> la..

W.S� 1# # I z =>I I <C <.!:> I 1"">11- >-1 .....J w, =II: IZ <CICl.. ct: 1 l<C all >-1.....J w1 <.!:> o l

<C l a.. ,..,,, Z .....JI al �, .....J wl <.!:> o1a: _1 ct:lz U..l:E ct:I 01- I::> <Cl u.. l

a.. la.. �, I� <C 1

I a..

PROFILE - NORTHERN SYSTEM FIGURE 2

Page 21: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

.------'--f-_..----Horizontal

I SIMPLE SURGE ---------�ESIGN GRADIENT\

TANK--, _ ___,_1..-\ ___ L'---Surge I -r _.._

I

' --,=-J

,,20Max. 1 ) , ------ -------I I I

I I \

\ permissible 1 , l HYDRAULIC GRADIENT-----r- -

\ / '--STEADY-STATE

\ ,Valve � WATER SURFACE I I / ' AFTERBAY __ .,.,

Pump-, . \ \ /'. ,, '· ll� '-Negative pressure wave

SIMPLE SURGE TANK {a)

'\ ' '---DESIGN GRADIENT

--STEADY-STATE ONE - WAY // WATER SURFACE . . SURGE TAN:)/ ,.--HYDRAULIC GRADIENT c20' Max. perm1ss1ble

t-+ -, --,- -,- -, -,- ,- ,- M r- ,-, I ----, ----i -==- -

.1 ' / / / l-<---1-<, I I I I I I I I I -

I�-,___- I I I I __j_J _j_ I �__..._.......__ I ----'-��� ·, 20, Max

'

. · "ble ... -Check valve / ---- AFTERBAY-,,/ perm, ss1 ... , �__, \ ,/ '-Negative pressure wave fronts

Pump-, , , ' I , ' \, I

''--Negative pressure wave 'I' ,valve

ONE-WAY SURGE TANK (b)

FIGURE 4

Page 22: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

1-o 1- 1-0 1" 1- 1-0 lfTI 1-0 I-l(J) I fTI 1-0 1-1 I ,,,, 1l> I ("') I ,2 l::C 1n

In, ,:c 10 In rri I I A I("') I I

I I A

I I I

I I I I

I

9 3�n£l1.:1

W31SAS 7'1�.LN3�-371.:IO�d

1-0 l>lr zll> c,1:z I -01< -I r,, -01

:E 1-u

l'Tll 1-I 1-U 1,:, cn1-1 ln,1- I,:, I -0 -11c I ,:, I- 1- I -0

1>1 :::0 'nlni ,-u 1-U ,-212 l::c lcn 1ni In, 1

-0 010 In, 1-1

lcn l(J) I fTI

1C 1--i In ll> 1--1 1-1 ,en 1Al2 ll> 1l> 1-I I I IOIZ: 11> I ,2 I I l 10 )0 12 I

l, 1 ( 10 ') I I ( I I I I I I I I I

l> 3:: l> ::0 r r 0

Page 23: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

UPSTREAM

POOL LEVEL',

-----Vent

LO

I

DOWNSTREAM

POO L L EVEL-," \ )

i)

I , .

I 1 - • --::---- ·. ::.; _ : · : ... -� . -1 � I- ·{ ;h , · . · . o . · . · . . · . . . . · . - :<:> . o · · · o · ·j i/M/1@\, ,,w s _ + 000 / - iJiiid�r ,

I - - •

_,, 1

1'-S = - .087 L-- - - - - - - - -- - - - - - - - - - - - ----o , 6 + 'V )- - - - - - - - - -- - -- - - - - - - - - - �

P I PE CHECK VENT D = I. D. of p i pe in feet

Y = Veloc i ty of wate r in p i pe in feet

P l PE CH ECK AND V E N T F I G U R E 6

Page 24: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

,, -U PSTREAM : POOL LEVEL \ \ \ \ I

�� .

I

:a! :1 (1.

11° -lO

I

/DOWNSTREAM ! POOL LEVEL I.

I I . . ,-r: . . ' / :j · l : I • J"#� . o: , ·.� . · . · . · ·O· . . �· . . -�� I · · -J;;-:.� mtil@\w · . . . . . -hi��h S = ± .QQQ-... " @E.\ � \ S 087 : i '

= -:

�- - - - - - - - - - - - - - - - - - - - - - D ( 6 + 'V ) -- - - - - - - - - - -- - - - - - - - - -�

P I PE STAND D = I . D . of p i pe i n feet

VENT

'V= Ve l oc ity of water i n p i pe i n feet

P I P E STAND AN D V E NT F I G U R E 7

Page 25: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

J.­�

a <( w :::c

I I I 1

I

VA LV E -- - ---

CD

-<- - - - - - - - - - - - Q - - - - - - - - -::.>-->-

CD

®

g fltA 2L

-----1 1, /-<-- ll t '< 2A

®

® GRAPH I CA L SU R G E A N A LYS I S

F I G U R E 8

©

Page 26: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

LLJ :i � u. 0 LLJ C (/)

::E ct LLJ ct:: t-(/)

r�:�; :2

::0

,�� �- - - -T�-�-G l::o

�:�-:7-1:,:�

_�i�: �

-

-

- - - - 40,ooo'- - - - - - - - - - - - -Tr ______ _ _ -- - - 40,ooo'- - - - - - - - -- - -1- -

- - - - -- - - --- -40.000'1 _ _ _ _ __ - - - - - ---7

-._:,,:_-.,_.,,...-4-_ / ' ,-Point B � :.,.,·H G El 103 45 ,,--H G El 93 02

/ Pool El 86 0---, A· · _ ,,·Po int C

,,--H. G. El 65 30 , 66' Rote of flow contro l ler va lve Volve opening I hour.

-----'

66' Pipe-----•

o,o 10 20 30 40 50 60 70 ao 90 100 .1_'W S E l . 120.0

1 20 · -r -

1 10

: J-Hv = head loss across ,- 1 flow control ler valve

---T l ine for t ime interva l 16.

I \ I \

I \ I \

I \ I \

I \ I \

I \ I \

\ 1-c- --,,-

- - -r·.>, I ' ' \

I : __ ,/ \ / /' '

11 '-·tan e =0 . 573

I I I

·;;A,-Ent. loss+ pipe <i loss: Res. to -;- va lve .

I I

_ _ )'.

,,-·H.G. E l . 37 58

1

,--W.S. E t . 10.0

� '··Pipe check c

a:, t­z

60

0 50 Q. t-ct

� i

cnl.!! Q.>•.O

·i:: I Pool E l . 58.o----� <!l.!� ,r·� I I , 7 ,

, , I I I I I \ I \

,-Q ot point B, time inter_vol 12. 1

I ,. "i,/

1

I,... , I I / ,., I : ,-0 ot point c, time intervo I 12 . \ r / I

' I

/' A

/ '/3 / I -- ------l ' . ' .

' 8 'v'' \

4' �0.287 '

I

: _1-·E I . D0

I ,< I 1-- l- - -

...

I I

: I I : : I I I I I

-� ,--·Pipe loss + bend Z 1 00 z

0 _ j_ __ � -j - - ->-t I ,_ -'---ton _ _

__ .r_ _ _ _ ._ : ,·Water surface elevation downstream

io 0 u 1:12.

�� loss: From point N e to point c. 3:

0 C z 0 j:: � UJ ...J w 0 :c

90

90

- -f ' '

· � ,A',-P,pe loss + bend ci loss: From valve : to point A.

[/t,,IM-w IVIV •y ·· y •• I . I I I I '- . I I I :

·-Crot ,col depth for I L I·· Pool E l .86.0

flow at Point A.

FLOW AT VA LVE .. FLOW AT A

Pool E l . 86.o - · · -

� �

(I) I _!:! "' •..c - , o 5 1� > , .., en.:�

� "' : : / leg of pipe check B.

12' , '�_i C � Li:f 40

I

I I I

I "' (!) ct:: ::, (/)

' VI • • �i=:-r: I ,v I I I I I I I 1. . .t 9� ;'·Cri t ica l depth for ;, Pool E t . 31 .0·-·-·'

flow at point c. FLOW AT POINT B11:1 FLOW AT POINT C

4 - -f I

I

0

:

C o � 100 ..... --....---------, � o 0 �

fj ·- 75 ... �i '15 °S 't �0 t-----t-+---t----1

::: 0' �

� 3 g. 25 1----+----+-----t ;:> ... _

15 � -' 0 o � &o "eo Vot,o cloaed

Rotation of valve leaf in degrees FLOW CHARACTERIST IC CHART

FOR BUTTERFLY VALVE

HYDRAULIC PROPERTIES OF PIPE LINE a .. 100 c. f . s . A m 23 . 76 sq . ft. v .. 4.2 1 ft. I sec. S • .000686

Va lues of 't" obtained from flow characteristic chart for butterfly va lve. Hv a � 2g T2 Ar/-

ton s • g l!.t A/2L

a • Quantity of water g .. 32. 16 ft. / sec. Ao .. Area of fully apened vol

.ti.fa 30 sec. interval assumed A .. Area of pipe L • Length of pipe

• 32 . 16 l 30 I 23. 76 / 2 1 20Q()()a .573

ton rf, • g.t.tA /2L - 32.16 1 30 1 23.76 / 2 1 40000 m .287

ton 8 .. .t.t / 2A1

.. 30/ 2 1 23.76 = .63 1

8 obove E t . D

<, ,., - - - - - -- A !-.:..vent

C :::::,., - - --- -- 1 ,,. ' : I

:-,ir, I • ' I

A, .. Area of vertical pipe in check structure

AVE . AREA

12.1 sq. ft.

, I

I

- -x : /-El. 0• I- �..::... __ __::::a,_ �-=---�=-�:.....!:=�::.._----------== --+--� : z

·�---- : - :30�===t�t�;r=�t1j::--,-7,---=�===�===�===�=.;J�z===j 0 a. �===tj�:4=J�d=�";;-r---+----+===+====1=j��c==j ,

Pool E 1 .---� .....__--+ --t/ I \

18.3 47. t 63.8 64.7 27.4 24.3

tan P 1 . 194

.819

.3 1 8 .235 .232 .547 . 6 1 7

-ct 1-z � � z 0

> LLJ ...J LLJ LLJ (!) ct:: :) (/)

80

,--Q at point A. t ime interva l 16 ,' I I I ,' ,-a at point B, time in terval 16

10 r _ J _ _ _ J _ _ _ _ I Js.

I , , I \ I \ I \ I I I \ I \

I r,: I I ' ,..\ I ', � \ I J / \ I J' \

'·-ton 4> =0 287 I

I I /

IA_

·

/ 13, I · · ·*

_ _ _ _ _ _ _ f ' · -Water surface e levation-11ownstream leg of p ipe check°'A.

'·-Cri t ica l depth for flow at point B.

I

' ' ' '

FLOW AT PO I N T A1• FLOW AT PO I N T B

--+---F----1· . � -J_

Pool E l . 58.0 · ·- '

I I I I ...

<D ci II <!l. C: 0 +-

I I I I I I

I I : I

I

I I I

-,.'., ,-·Pipe loss + bend �- loss : From point N A to point B.

I

1- r---t,\71--,-lH--:?K�r---+------f===+===����=t==j : ,-·El . De

ct

-+-t I

I

z I :

0

I I I I

j::

� -�...,_.,

,-·Pipe loss � bend

ct io � loss: From point

> /

o i c to reservoir

LLJ 20 / :

� /4

w / )

(!) / I

it: - -------1

::, ' '

' /J (/)

' '

"' ' ' '

C

n I f 11 J1a' � /,ZJ'b :; , ___ t

,---Downsurge would cause U11watering of pipe ,�' downstream from po int c� (Failure)

FLOW AT POINT C1 •

FLOW AT R ESERVO I R

Pool Et . 10.0-----'

G R A P H I C A L S U R G E A N A L Y S I S

'·-6 Equo I spaces used

F I G U R E 8A

Page 27: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered
Page 28: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

C) <( w ::r:

T h eoret i ca l

M od e l

T I M E

C H E C K N O. 5

C) <( w ::r:

Theoret i c a l

M o d e l

T I M E

C H EC K N O. 6

C O M PA R I S O N O F T H E O R E T I C A L A N D M O D E L R E S U LTS

F I G U R E 1 0

Page 29: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

I r I J> 1 3: I n, I U> 1 l> I --4 I n, I ::0 I � 1 -1 Z 1 l> I r I I I I

I I 3 H n 8 1 .:I

W3.LSAS N�3H.L nos - 37 1.:JO�d

1N3 10V�9

Page 30: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

� 2o" Rate - of-f l ow contro l ler,. \

I

1 6" Rate -of-f low c on1ro l ler.,,

FLOW INTO

M A I N

1 : , 1 r---FLO W TO SO. Y LUBBOCK T.O. PLA N

E I . 3200 . 6 ---,, E l. 3 1 9 9 . 6 ---, \ ' \ E I. 3 1 98 . 6--... , 'i l

\ I I F LOAT M ODULATI ON RANG ES E I . 3 1 9 7 . 1 --.. \ : \ : I I I I

1 st. 1 6 " f l ow control ler range-- -- ------

1• · · · 1 y i i Y::!:I_ 2nd 1 6" f I ow control ler ra nge- ------ 1::_7°'1/i. A

_ _ _ Y =lo 20" f low contro l ler ra nge -------- . - -/ ' / �, /

Al l th ree rate -of-flow control l ers �;[ / .,, .,,/

a re fu l l y open when water surface �> .. ....--is at or be l ow E l. 3 1 97. 1 - --- - - - -- - - - �,

R EGULA T l N G TAN K NO. 6-- - - --- --

E L E VAT I O N

I I

. · . . . ·o . • I> · • • • •

PRESSURE REDUC I NG STAT ION AT

REG U LAT I NG TAN K NO. 6 F I G U R E 1 2

Page 31: Bureau of Reclamation - j...As studies progressed, it became evident that it would be feasible to make all pump units at Plants No. 2, 31 and 4 of equal size. Since this was considered

afg

Oa

z17, 1

.• zg J

m

CO

m

z.

do

D.= FOREBAY NO.4

n2

Z Ul

zz

40

as

0

0,

an

2'

o

EXPLANATIO

lot or 2nd pump a t

01

ter leve l contro ls

E :=

44

,..... '

O

-L-- -az

10 °E

0

I

,-- ..E.'-' I 2 F.,

I :'.47.,,

,,:ia k"

__

__

__,

6%

11 4

t,

0) FOR OPERA TION

ICI

N W

0

DI A G RAM

AMARILLO REGULATING RESERVOIR High level alarm sounds at control station when water level rises to elevation 3659. 7.

Water level to be transmitted to control station. For normal operation, water level should not be allowed to drop below elevation 3649.5.

N O

N ,IN

V.L

g

oo

ns

--Mad. W S El. 3721.8

YIO

AY

35

3V

1 9

N1

.1V

-10931d 07718V

WV

02

66

£ /3

'SM

N IO

W

0661 , f 1

3 Jia

m m

Olp

an0

'ON

iNV

- Id O

NId

WIld

V 'O

N A

V9

3N

Od

Reset 2 uni ts El 3491. 32

E SYMBOLS

N;

O

W.S. El 3560 8

0

0

FOREBAY NO. 2

z17,

zz

<0

J.

Z .

0

2 '

ao

FLOAT S WI TCH

o

at

l'ON

YN

Vi 3

9a

0s

I ON

1N

Vld

9N

1dV

eld

Wv0

Ge

tOd

NV

S

Max W S Et 3 180.0

0

O

O

N

0.

1900

T.tt

2g'

ttf!

2.

Zt"

44440

ji 41

SAN FORD RESE RVOIR

4E

41,1

!

i141 l'7

2t1

2.0

;,

g.

.2

. 1'4

0

!g

.!

18i

tze.1.2-vg. tt,.g

Ifc,n5

2

'8 .2

C 1

:!1

4! "1

11

:

44.

4.4

, ;1

7:

!,::11.°1211

T9

ial .°1.lp I '4E gi

t

m.4

4t

q snEg

ovoz.„

2"41:2

!!:!!!4i,

2 4t

N't! !n1154!!T

om-

2. 401,I

EuOO

tz i!>

gg

i:fAif2t42

li

.

slj.7.E4 il'A it2,0

8z T

Attr.40,740

'1"

1;14iiFi:s

L,

„„385

1:r°°g

'-'3

""

82ttV

."

9

""E

w m

A4

4W

.f..g

tg

',9

2.S

HO

1in!;e 'aliV

4""4""12

11

t tl

e!. h

'''''

'j-

al p

!TI.:

Cgc.:A

30:ii 4%

iq

n 1

1°9

M

i .i.. 4ii;f4

i trn

t:!-!, 0

011! f,,,2" 2t,,T

11E' t:§i8 asf:

i02 ::

!1-7:5. ia

OAg

!;1=1sAT

V -!

; g1,.

,il ;i

li

EE

Jili

;"

l

12T

!

-i

t

I

g:

.m+ o

w

:2:°1

1 :;1

r! !1!!:

g d

t7.

P2

.2-. .‹.

!-i!

_;

_,

F.Ti 111.:1 .0.%12h4t1412!tpqpvt!s<1;g.4...

F.-w

3t03.50.?,

Ig`e.

-4.tvt4

0.

i.rtlili

1 0"g

:""2

1iit

&

ueod

^n!Eiff71 1

gn

1

1'4'112:p:1.11

t.2

'9.. .L

.,

0

ogF-'

Y t r

0

.

th r:r

4-:

E.t

i'.

027.'7. 1;!fe0.

-04

kl

VtIlil:!

7-ilig

'M'''.:..

046

712-;3.2,

40°.;

IT.I!,Z if

'°r..:q;"

g5:4 gt ,In:It;t41 f''1

:'

.'

.'

t

iijile92

4P

39

1

42

2f!

: E

ri9

N

P

j 141 ;

c:4! , ',‘:°

! !

4'

. - ,.! . ! !

, :12 ! 2

!Ii.:::! v , , , ,:

it2

:t" !

"1

-"4:2 ..i t S,, .43 :! :I:.

.Z4 10

I.W01 ;i1A;M-1

I'lltil:MH:q

,!"-1,

. s.t.......,1

.

Off'sdiN

"'''''4'P2

:..t0-0

w8ENumi

:t, ti

74, 17

4:7;

".4....„-zw

g

42.4 ilhf, ,,,,,

.:

21

:'1:;

. ;7:7

pilqii h114,0, 1.1A

2L

-A

nlp..

COMMUNICATIO N ROUTES - PUMPING SYSTE MS

tt-

;44 s4

4

4E

B

t!

d A

m liz: .34.;

11411: :ilpijI

If

;11

U

1,1 7,1s.TL

.07.'

1!

t,%tr

4101

02P4g'`"27A2tP>oTitI"n=g.iE.

ma

W1h

tr:'121

-9

,"°jt

28

E um

PAVA

ITcn1Aa

N o 00 U

0 004

P0

9.stli

4lq

!E

"I'q

4

fltN.f!;;IfflV4-04

C

g 2%

5, =

N 2

c„

.2.

m Y

tt'4

10

EE 2

:4 4

.

6.1

4415044

?-:1

0W

1,11

2E

8T

:

4'25

007,'"" g".'

t1°''gt.'':'"'

'`''45

3sEW;

P!i02:gg7444

0T

-Ag

'tt5t'ffl4r

t""

.1Sz-2."

nn

-

. o

CO

N M

NV

1 3

080S

FOREBAY NO. 3

1131SA

S

PIILS

AS

N

8 3H.LH

ON

>

1V8.1.N

33 o

214 I 2

0

a

A

!

,

cv2

Zy

z=

dri

E3

' D

S

0.0

8 -4111

-2

',

P.O

l044].O

Iu

CN

L

15

01

Hm

L 6

A S

A

0.H

01

0

ca m

mu

w° 10544°m

o0

.4

n

"4

4'5

1''=

""ct2

t!1

1!till

"9

G+

I1

°E

7174

70R

2E

0ii:°,

12

-1

11

giltg

:1

::-.4

"7

4v

2E

1 H

Ny

11

;1122'71P

Pf:git2,2 m

y

u8A

7

.. !' .!;1,5,4 -51 ....:A1.74t1 1317

07'. 0i! 'f

int

-F4A2 !

oYm

- 02tos N

i! , 11

;'.! 9W

MP

.; t'!!:!H!

Aqi1215

grIE

4vA

rtliwgIO

l

S

'

25

q

q .W

SIg

aY

.L

A

94

L .°a

".V

:A

:524P

`52

!T

?S

+P

t'tn

r,':A

00

8.0

04

,;!1W

,14

4h

Og

rag

.:. - E !M

ilg;i6

V84

41 0

10

PA

1. E

il..-741K

4

C E

t '

W Itttg

lii121161.1T

:"P

"4;

:'8!

4:34

..8

EO

N IN

Vld

9N

1,1

1N

nd

: 4

frO4

F O

N A

VG

3d0g i

om

S

g.

, ,,;0.4

mw

4N a

Zaz m

u E m

t2t

!.' I. IteoThEe5.4

66

u

C1741 11d!Ajl .1P.;;IWAra

g

'11 1;r2

'407

01

:4"

I,t,',E

. 7W

A2w1-01

.t ail

.4

,d„

"'"0

7 0

4 g

:tE

7;0

,:t=

4:f

sT

igg:tt't11.

2

EL

1302`126172;t8W

S'g

E:!>

g.C

2t 44 .:!:2

Restart lst or 2nd. Pump E1. 3332.50

O

4444

1 R

OW

WW

- vt

ow

"'

tWt'os,p4

:;rgrfl e

!.q31,P

!MP

4'8

Fg" 344

"zA3ww

4f;g0 ""4

""T

44 l2

E1

22

32

8.

!T

in

7°1:,

""

tV

T,

Z- 0

::

3

.1"0:‘t:2]

"'g:g

.2

2

'T

"'w

"""''

2g

"gg›.,w

3""5211!

wc0wW 00 W

34q,-10,ww

.;;w4J

t„ ' Ii

Millg NA U!''d-

12-2.-52„2nE:d .2.13 .1.,9 1-.P.:-:

I L,,.,A: g..., :-g;.-.7,, EttJ5-2:5 2..L:v..5

" --7

:::::!:::::::7: ,.

: ::1:1; ;;;:;::!:::;;;;;°:;; i i.

_.m.,.„,.

.;. t -,,.. „.,y,,,, ,,t,32.11g§t-gl-s2.,,-._0q,2-1 ,

,

ii ."::11-d2U

3,22'igiL4„1

..", 2

;'2. "2

11

11

t 44 7

.,Eg' .2

gz2

,,,A

2, ,,

i2.,,-;:;;

L

41

;i;;;til`;:;2;;;;aii;ii M

fl!!

w3uw

0.W

ww

4 u

w,w

,wco

Tve.4,7.0',5

5-,,,,m1,-;

WI°781ial*:i!! 4.4 11 !t: 1!!i!i!lh1DP,.

'"""t"''''''

..' .22.:Zt,, .7 .,..1=

4.st.E,3t,,3

W5

.A

M1

V0

12

1g

2.58

gp

tg

gt:w

s..

,33

.0,

Z O

N N

NV

.L 3

9e

i0S

Z 'O

N .I.N

Vld

9N

1dV

i0d

Z O

N A

VN

3N

Od

.°4'1