building failure case study
TRANSCRIPT
Source-Kirsten Jørgensen, The Technical University of Denmark, Lyngby, DK (email [email protected])
020ANALYSIS OF FAILURE IN A
BUILDING PROJECT
Science Art Religion Politics Scholarly Articles For Mathematics and Productivity
http://www.twitlonger.com/show/n_1sp9pjo?new_post=true
MICROSOFT OneDrive PPT’s PDF’s BOOK LESSONS Dr f Dejahang BSc CEng, BSc (Hons) Construction Mgmt, MSc, PhD
THE BOW TIE – AN ANALYTICAL METHOD
THE BOW TIE – AN ANALYTICAL METHOD
The bow-tie analysis of failure (ceasing to function)
ANALYSIS OF FAILURE IN A BUILDING PROJECT
Just-In-Time(JIT)
Supply ChainManagement
(SCM)
LeanConstruction
maximizes valuereduceswaste
Based on LeanManufacturing, of the Toyota
Production system
High productivity
LAST PLANNERSYSTEM
SCM route
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
The bow-tie analysis of failure (ceasing to function)
Poor management of the preparation of the site for construction
Wrong man set to manage the work
The work not checked by a project leader
The size and extent of the work underestimated
Slow handling of the case by the authorities
Delays in the start of the construction
Chose 10 grades of pollution classification,which takes time
The track for the crane was laidbefore the piles were cut to the right heights
Complicated methods for the excavation
The use of time and resources not optimal
Focus on cost-benefit optimisation of own task
Poor planning of the sequence of the process, especially for bungs and piles
Slow decision-making when unforeseen problems arise
Too few employees for the job
Poor focus on deadlines
Complication in the pile cuts and economic losses
1
Figure 3
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
Slow excavation and preparation of the ground for the construction
Slow respons from authorities
More polution in the ground than expected
Choose to sort the poluted earth into 10 classes of polution instead of 4
Poor management of the project
For cost obtimisation for this specific task
Incompetentmanager for the job
The pre test was not sufficient
Delayed of the starting point for the construction site
Delayed of diving the piles
The tracks for the cranes places before the piles is cutted
Complications for cutting the piles
Increase the time pressure for the rest of the construction process
13
Figure 4
ANALYSIS OF FAILURE IN A BUILDING PROJECT
Figure 5 illustrates the bow-tie analysis of another consequence of the incompetent management
the bungs were driven in too early in the process, which had serious consequences for later stages.
This shows that the reason for driving the bungs early was quite reasonable – but also that there was no adequate process analysis.
ANALYSIS OF FAILURE IN A BUILDING PROJECT
Too early driving the bungs
It is best to drive the bungs in before the excavation process
The entrepreneur had free capacity of manpower at an early stage
The consequences were not evaluated
The excavation went on to be most complicated
The early placement of the bungs obstructed access for cutting the piles
Delayed the preparation of the site
This forced theentrepreneurs to use an inconvenient method for cutting the piles
14
Figure 5
ANALYSIS OF FAILURE IN A BUILDING PROJECT Figure 6 illustrates that pile driving came too late in the process, with the result that other process stages, e.g. laying the crane tracks, occurred before the piles were cut, with consequences for the pile cutting.
ANALYSIS OF FAILURE IN A BUILDING PROJECT
Delayed driving in the piles
The preparation of the ground was more complicated than expected
Poor management of the preparation of the ground
The tracks to the crane couldn´t wait and were laid before the piles had been cut
This delayed the start of the construction
15Figure 6
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
B. Overview of mutual relationships between critical events
Time delayingCost consuming
Resource requiring
The client The design process The foundation The shell Ext. accommodation Int. accommodation Delivery
4.Unrealistic timeframe forthe delivery
2.Overload of the site manager for the shell
1.Poor manage-ment of the preparation of the site for constrution
3.Acceptance of additional choice at the wrong moment
5. Lack of iron in fil igree slab
6.Filigree slab arethicker than on drawrings
10.Instalations overlapping
11.Outlet put in same place as a pile
12. Achitectural ironmongery problem in dobbelt walls
13. Slow excavationand preparation of the ground
14.Too early driving in of the bungs
15. Delayed driving in of the piles
16. Broken piles
17. Damage to the iron in the piles
18.Excavation filled with water
19. Employment problems
20. Lacks of props up to fil igree elements
21.Poor erection of concrete elements
22. Lopsidedness of walls
23.The width of the fil igree elements too small
24. Wrong placement of wall in the entrance
25. Slow and poor finish
26. Poor mainte-nance, cleaning
27. Delivery failure of concrete elements
28. Failure in outlet at the cubicle
29. Wrong chock up at the cubicle
44.Water in the corrugated pipes
45.Uneven and slope of surface
46. Too small room for batten
47. Wrong masking-off in wall
48. Few socket outlet in rooms
49. Damage of wall in cubicle
50. Diffuculties in mounting of kitchin elements
51. The crew for painting too small
52. A simple accident
53. Oil pollution
54. Late delivery of floor materials
55. Defects at the time for delivery of the building
7. Lacks in the design of elect. installations-
30.Poor coordina-tion of agreements
31.The buildingcan´t be cloosed
32.Placement of the crane track
33. Damage to windows
34. Water intrusion from the roof
37. No space for window
36.Humidity of the plaster
35.Many cut outs are needed
38. Lacks of plates
39.Isolations prob.
41. Water in penth.
42. Damaged pipe
43.Late deliveries
40. The plates on the roof too high
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
ANALYSIS OF FAILURE IN A BUILDING PROJECT
It was also possible to clarify the link between deficient electrical planning and a number of critical events later in the construction phase during the internal fitting out.
NETWORK PROGRAMMING
Start
Excavate section -1 Pipe bed section- 1 Lay pipe section-1 Back fill section- 1
Excavate section- 2 Pipe bed section- 2 Lay pipe section-2 Back fill section -2
Excavate section 3 Pipe bed section 3 Lay pipe section 3
3 1 1
Back fill section-3
3 1 1 2
4 6