budget circular 201314
TRANSCRIPT
-
7/31/2019 Budget Circular 201314
1/26
-
7/31/2019 Budget Circular 201314
2/26
will not be allowed to change and will form part of Outcome Budget for the year 2013-14.
These will also form the basis of MOU 2013-14 to be signed with Govt. of India.
III. Budget Heads
The Capex Budgeting is to be implemented through SAP. Budget Head (Fund) (eight digit
code) has been made mandatory field in all the Purchase Documents. Please refer tocircular no.01:FA:Budget:2012 dated 11.04.2012, copy is available on intranet
(Department LinksFinanceBudget). The Budget Head is to be furnished in all thePurchase Document under the tab Account Assignment. The Budget proposal should be
prepared and forwarded strictly in line with the Budget Heads and the same should be
clearly brought out in all the forms.
All sites are requested to use the eight digit (6 digit Budget Head and balance two digits for
reference to stage of the project) Budget Heads available on Intranet. These Budget Headsare to be part of all the budget documents to ensure budget monitoring through SAP.
Completed projects i.e. commissioned prior to 31.03.2011 need to furnish Budget Head
wise details for all the system codes. These stations need not furnish details for works not
having any outlay in RE 12-13 and beyond. However, for outlay of works covered under
Budget Head 16: Ash Handling System, subsystem Budget head-wise details will have tobe provided.
IV. Provision by Corporate Contracts:
The Budget provisions (both financial and physical) for A category contracts ( i.e.
contracts having value exceeding Rs. 50 lakhs ) including the monthly phasing in Form
Nos. C-2, D-2 and E-2 are to be submitted by the Contract coordinator/ Engineer-in-Charge
concerned of Corporate Contracts Deptt., to the projects latest by 15.06.2012 with a copy toCorporate Budget. Utmost care should be taken to ensure that the phasing of expenditure isnot back ended.
V R f S ill O d V i ti
-
7/31/2019 Budget Circular 201314
3/26
required to be made at the time of projecting Outlay(s) in order to realize investment plans
to the fullest extent.
VI Actual Expenditure upto March 31, 2012
Actual expenditure for the year 2011-12 and cumulative expenditure upto 31.03.2012 duly
reconciled with balance sheet should be submitted to Corporate Budget by 14.05.2012.This shall be incorporated by Site Finance in their budget proposals also. The reconciliation
of actual expenditure with balance sheet in Forms 6.1, 6.2 & 6.2 (additional) (revised formsavailable on intranet) should also be submitted by 14.05.2012 along with Actual
expenditure report for the year 2011-12 and cumulative expenditure up to March31, 2012.
Time and again it is found that the cumulative expenditure reported by the site
while sending the balance sheet reconciliation does not reconcile with the figures
indicated in the Construction Budget Proposal. HOD (F) should ensure that thereis no such discrepancy in the reported expenditure.
VII. Actual Expenditure of Q1 of RE 2012 - 13 and phasing of expenditure of RE
2012 - 13 and BE 2013 - 14
Package wise actual expenditure for the Quarter 1.4.2021 to 30.6.2012 (Q1) shall becompiled and circulated by Site finance to all concerned by 02.07.2012 for the purpose of
phasing and preparation of current estimate of RE 2012 - 13.
The budget proposal shall indicate the actual expenditure upto 30.6.2012 in the current year
and monthly anticipated provisions for the period from July 1, 2012 to March 31, 2013 for
arriving at Revised Estimate for the year 2012 13.
In order to facilitate the monitoring of the progress of expenditure, the monthly / quarterly
phasing of expenditure in respect of all schemes should be given in D and E formats tagged
with SAP Budget Heads. Any proposal without these forms shall be considered incomplete
-
7/31/2019 Budget Circular 201314
4/26
Talcher, Gandhar, NCTPP, Dadri Gas, Kahalgaon, Kayamkulam, Faridabad, Rihand-I & II
and Sipat II shall be as per the proforma at Annexure-III. This is in addition to theperformance budget to be submitted by these projects in the prescribed formats. The latest
anticipated cost for those projects commissioned before 31.03.2011 (last unit) should be
reconciled in such a manner that balance expenditure to be incurred beyond 31.03.2014
should be limited to BH 16: Ash Handling System only, unless there are compelling
reasons for providing such expenditure against other Budget Heads as well.
Adequate care must be taken that no new items / commitments are included in the budgetproposal except for:
i) New ash dyke & raising of ash dykeii) Payment of liabilities for remaining worksiii) Provisions for EAP schemesiv) Capital Addition (approved items)v) Ash utilization (Capital Items approved by AUD)vi) Energy Conservation (capital items approved by CEETEM)vii) Expenditure under 5 km schemeviii) Expenditure on Sustainable Development
The provision for new ash dyke, raising of existing dyke and remaining works should be
strictly as per approved/Revised Cost Estimates. No new items/works should be included
merely because provisions are available.
The provision in the budget proposal for items except (i) & (ii) should be sought only after
technical / administrative approval of the item as per DOP Section I clause 2 & 5 remark
(vi) and (xii) and Section II clause 1 remark (iv), (vii) and (ix) has been accorded. The
status of technical / administrative approval should invariably be mentioned in the remarkscolumn of the proposal wherever proposals are not approved at the time of preparation ofbudget proposals but are likely to be approved in due course. In case the approval is in
place, the copies of the approval of the competent authority should be enclosed.
-
7/31/2019 Budget Circular 201314
5/26
b) Contract ClosingThe status of contract closing of all such contracts where physical progress is completed
should be given along with estimated liability and whether any provision has been sought
for these packages in the Performance Budget as per format given at Annexure-IV.
c) Provision of supply of electricity in 5 km area around Central Power Plants -5 km Scheme
Ministry of Power, vide its letter no. 44/7/2010-RE dated 27th April, 2011 notified the
above scheme which covers all existing and upcoming power plants for CPSUs. The cost
of the scheme is to be borne by the CPSUs to which the plant belongs and the same will bebooked under the project cost. Accordingly, the Board of Directors in their 362
ndmeeting
held on 31.01.2011 decided that the above scheme would be implemented for all existing
stations as well as on-going projects of NTPC. Further, the Board decided that Head of
Project/Head of station will enter into agreement with NTPC Electricity Supply Co. Ltd.
(NESCL) for execution of works under the above scheme. The outlays with regard to above
scheme are to be included in RE 2012 - 13 and BE 2013 - 14.
d) New Budget heads for sustainable developmentIn line with External MOU 2012 - 13 signed between Ministry of Power and NTPC Ltd,
expenditure on sustainable development activities need to be reported separately. The
Budget for activities of capital nature will be sought under the head capital addition and
following budget heads have been allocated covering sustainable development activities:
Major Head: Capital Addition 87
Sub-System Head: Sustainable Development 02
Detailed Budget Head:1 W t t 870201
-
7/31/2019 Budget Circular 201314
6/26
IX. Renovation and Modernisation
Renovation and Modernisation (R&M) of operating stations has become an important
activity. Substantial outlays are required to be provided for R&M. Any shortfall in
achievement of target outlays not only has substantial impact on overall achievement of
Budget but may also affect arranging finance for these activities. Substantial shortfalls may
lead to payment of commitment charges for non-drawl of committed amount of loan.Hence, while proposing the outlays, the station maintenance schedule(s) (where ever
required) have to be kept in view and realistic provisions be sought.
X Cost Reconciliation
The exercise of cost updation for on-going projects, new ash dyke, EAP schemes, capitaladdition and R&M schemes shall be carried out in accordance with the MOP letter no. M-
12016/5/97-PAMD dated 27.04.1998 (copy enclosed as Annexure-V). It may be ensuredthat the cost estimates are updated after taking into account balance commitment which
may have to be paid to suppliers/contractors on final settlement and contract closing. Cost
Engineering Department shall intimate latest by 04.06.2012, the cost to be adopted by site.
The representatives of on-going projects must reconcile the cost estimate figures with
Cost Engineering in advance and get the latest cost estimate cleared/accepted by CostEngineering. Only such reconciled figures are to be shown in the budget proposal. A copyof reconciled cost estimate should be submitted to Corporate Budget immediately thereafter
by Cost Engineering.
It may please be noted that proposals with cost figures different from the cost estimate
furnished by Cost Engineering Department shall not be considered.
XI. New Projects: (PP&M Group, Contract Services, New Project Group &Business Development Group)
Budget Outlays & write up
-
7/31/2019 Budget Circular 201314
7/26
XII CERC Tariff Regulation regarding Completion of Works
CERC Terms & Conditions for Tariff period 2009-14 stipulates that capital expenditure
within the original scope of works of a project (other than Ash dyke) cannot be deferred for
execution beyond the cutoff date after the date of commercial operation. Cut Off Date for
this purpose is defined 31st
March of the year closing after two years of the year of
Commercial Operation of the Project, and in case the project is declared under commercialoperation in the last quarter of year, the cut-off date shall be 31
stMarch of the year closing
after three years of the year of Commercial Operation.
In view of above, it is very important that all orders for procurement and execution are
placed well in time for various packages within the scope of works of a project andexpenditure are incurred within the period stipulated by CERC as mentioned above. Aformat has been devised as below which will be filled up by all projects that are completed
in 11th
Plan period.
Project COD oflast unit
Cut-offdate for
incurrenceof
expenditure
LatestEst. Cost
Exp.incurred
upto31.03.11
RE2012 - 13
BE2013 - 14
Est. Exp.2013 - 14
Beyond2013 - 14
1 2 3 4 5 6 7 8 9
NOTE: Only expenditure related to Ash Dyke will be phased beyond the cutoff date.
A detail of the contracts awarded after the commercial operation date is to be furnished asformat in Annexure VIII.
Further, it is seen that while truing up, the capital expenditure projected by various units is
higher than actual expenditure incurred during the years 2009-10, 2010-11 and 2011-12.Please ensure that projections are made accurately since any shortfall in actual capex will
-
7/31/2019 Budget Circular 201314
8/26
-
7/31/2019 Budget Circular 201314
9/26
Distribution
1. RED - ER-I /ER-II/NCR/NR/WR-I/WR-II/SR/Hydro Region2. ED Corporate Affairs/ PP&M /CP/Engineering/CC&M/EMG/ R&R/Commercial/
Fuel Security/ Fuel Transportation/IT/Systems
3. CEO/MD NVVNL/NESCL/NHL/BRBCL / KBUNL/ NSPCL/ NTECL/ RGPPL/APCPL/MUNPL/NPGPCL/BF-NTPC/NBPPPL/NHPTL/TPCL/NPEX/TELK
4. Heads of ProjectAnta/Auraiya/Barh/Barethi/Bilhaur/Bongaigaon/BTPS/Darlipalli/Farakka/Faridabad/Gadarwara/Gajmara/Gandhar/Kahalgaon/Katwa/Kawas/Kargone/Khasia
bara/Kolodyne/Koldam/Korba/Kudgi/Lara/Loharinag Pala/Mouda/NCTPP/ North
Karanpura/Ramagundam/Rihand/Simhadri/Singrauli/Sipat/Solapur/Talcher/TTPS/T
anda/TapovanVishnugad/Vindhyachal/Unchahar/Pakri-Barwadih/Chatti-Bariatu/
Kerandari/Tallaipali/Dulunga
5. Corporate CentreGMs/AGMs - /R&M/PE/CMG/ES/Consultancy/Environment Management/AshUtilisation/ R&R/CS/Cost Engineering/CS/Finance-Commercial/CP/BD/R&M-Engineering/ERP-Finance
6. Heads of P&SAnta/Auraiya/Barh/Barethi/Bilhaur/Bongaigaon/BTPS/Darlipalli/Farakka/Faridabad/Gadarwara/Gajmara/Gandhar/Kahalgaon/Katwa/Kawas/Khargone/
Khasiabara/Kolodyne/Koldam/Korba/Kudgi/Lara/Loharinag Pala /Mouda/NCTPP/North/Karanpura/Ramagundam/Rihand/Simhadri/Singrauli/Sipat/Solapur/Talcher/
TTPS/Tanda/TapovanVishnugad/Vindhyachal/Unchahar/Pakri-Barwadih/Chatti-Bariatu/ Kerandari/Tallaipali/Dulunga
-
7/31/2019 Budget Circular 201314
10/26
Annexure-I
Completion of major activity (Identification Schedule)
S.No. Activity Form No. Responsibility. Target Date
1 Furnishing of actual expenditure
upto end of previous year i.e.March 2012 reconciled with
balance sheet and for 2011-12.
F6.1 & 6.2
& Addl.
HOD( Fin) 14.05.2012
2 Submission of data for uploading in
SAP for generation of CapexBudget report
HOD (Fin) &
HOD( P&S)
21.05.2012
3 Uploading of Data for reportingunder SAP
ERP- Finance 24.05.2012
4 a) Submission of package wiselatest cost estimate to Cost Engg. &
thereafter finalisation &
b) Submission of Latest ProjectCost to Site
Corp. CS/SiteP&S
Cost Engg.
24.05. 2012
28.05.2012
5 Information to Corporate Budget
regarding confirmation of
reconciliation of Cost Estimate with
Cost Engg.
Intimation of accepted package
wise cost estimate to project &Corp. Budget
HOD (P&S)
Cost Engg. &
HOD (P&S.)
28.05.2012
04.06. 2012
6 Review of latest milestone charts & B1,B2 & All Heads of 12.06.2012
-
7/31/2019 Budget Circular 201314
11/26
communication budget to
respective project F&A
11 Submission of construction
materials budget to project P&S
C4,D4,E4 HOD (Material)
site
02.07. 2012
12 Submission of manpower budget to
F&A at CC/Project as required
C7.2 Corp.(HR)
Site (HR)
02.07. 2012
13 Submission of budget & write up
regarding new project to CorporateBudget
ED(PPM)/ 02.07. 2012
14 Submission of detailed budgetaryoutlays and write up about projects
undertaken by JVs and subsidiaries
BD / PPM,Company
Secretary &HOFs of
respective JVs &subsidiaries
02.07.2012
15 Submission of MBOA budgetcommissioning expenditure budget
to project P&S
C3 &2 4,D3&24,E3
& 24
HOD( P&S) 02.07. 2012
16 Submission of establishment
expenses budget to site Finance
C8 to C9,
D8 to D9
All HODs at
Project
02.07. 2012
17 Submission of budget for (a) S&I
identified project; (b) S&I
Unidentified project to Corp.
Budget
C 42,
D42,E42
GM(ES)-NPG 02.07. 2012
18 Compilation of project budget &
approval by Head of project
A, B, C, D
& E
HOD( P&S) 05.07. 2012
19 Submission of final budget
proposals for projects to respectiveEDs
A, B, C,
D&E
GM/AGM(I/c)
of Proj
10.07. 2012
20 Submission of approved budgetproposal to Corp. Budget
ED (Region) 16.07. 2012
-
7/31/2019 Budget Circular 201314
12/26
Annexure II
NTPC Limited
OUTCOME BUDGET MILESTONES FOR 2013-2014
Sl.No.Name of Scheme /
Programme/ProjectObjectiveOutcome
Annual Plan 2013-14 (` crore)Quantifiable
Deliverables/PhysicalMilestones
Processes/Timelines
ProjectedOutcomes
Remarks
1 2 3 4(i) 4(ii) 4(iii) 5 6 7 8
Non-PlanBudget
PlanBudget ComplementaryExtra-Budgetaryresources
i OngoingSchemes
ii New Projects
Total
-
7/31/2019 Budget Circular 201314
13/26
Annexure-III
Summary of budget proposal in respect of (Project name)
BH Particulars ApprovedCost
LatestAnt. cost
Act. Exp.upto
31.03.12
BE12-13
RE12-13
BE13 - 14
Remarks
A. Bal. Expdr. In respect of completed works (such as payment towards final bills/ contract closing)
1
2
3
4
5
Sub-Total (A)B. Ash Dykes and Land for Ash Dykes
1 Land for new ash
dyke2 R&R for new ash
dyke
3 Raising of existing
ash dyke
4 New ash dyke
(supply & erection)
Sub-Total (B)
Grand Total
-
7/31/2019 Budget Circular 201314
14/26
Annexure - IV
Contract Closing
Sl.No
Nameof
Work
LOAno. &
Date
Name ofContractor
Value of Contract TargetDate of
ContractClosing
Status ofwork
completionmonth / yr.
Anticipated amount
PayableOriginalaward
value
LaterAmended
Value
1 2 3 4 5 6 7 8 91
2
3
4
5
67
89
10
-
7/31/2019 Budget Circular 201314
15/26
-
7/31/2019 Budget Circular 201314
16/26
-
7/31/2019 Budget Circular 201314
17/26
-
7/31/2019 Budget Circular 201314
18/26
-
7/31/2019 Budget Circular 201314
19/26
-
7/31/2019 Budget Circular 201314
20/26
-
7/31/2019 Budget Circular 201314
21/26
-
7/31/2019 Budget Circular 201314
22/26
Annexure-VI
Format for Budget Provision in respect of New Projects(Where the Investment Approval has not been accorded)
Project:_______________
Details of Advance Expenditure
Date Amount Approved
(Rs. Lakh)
Approved by Specific Item of Approval
(if any)
Details of Budget Provisions sought
Sl Description Approved Anticipated Expr forthe year2011-12
Cum.Expr.
31.03.12
BE12 - 13
RE12 - 13
BE13 14
A Approved Items
B Items not yet approved
-
7/31/2019 Budget Circular 201314
23/26
Annexure VII
New Schemes
S.No. Name of
Schemes
Latest Est.
Cost/TECcleared cost
Fund tie
up, if any
Expected
date for
Submissionof FR
Investmentapproval
1 2 3 4 5 6
Main PlantAward date
Commissioning Schedule Anticipated Outlay
Unit Date RE 2012 - 13 BE 2013 14
7 8 9 10 11
-
7/31/2019 Budget Circular 201314
24/26
Annexure - VIII
Details of Contract Awarded after Commercial Operation of Last Unit
Sl. No Description of Work Date ofAward
Expected Dateof Completion
Award Value(incl. cost ofOwner Issue
Material)
Latest Statusof Progress
1
2
3
4
5
6
7
89
10
-
7/31/2019 Budget Circular 201314
25/26
Annexure IX
Name ofJV/Subsidiary
EquityContribution by
NTPC
EquityContribution by
JV partner
Loan Total CapitalExpenditure
Cummulative
expenditure upto
31.03.2012
Expenditure forthe month of ------
Expenditure for2012 - 13
(upto the monthof ------
-
7/31/2019 Budget Circular 201314
26/26