Blueprint Columbus Southeast District AWWA Conference November 4, 2016

Page 2: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Agenda • Consent Order

background

• Blueprint Plan

• Gray Plan

• Costs

• Benefits of Blueprint

Page 3: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Columbus’ Wet Weather Timeline

August 2002

September 2004

July 2010

September 2010

July 2012

January 2013

September 2015

July 2005

Page 4: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Columbus’ Wet Weather Timeline

August 2002

September 2004

July 2010

September 2010

July 2012

January 2013

September 2015

July 2005

SSO Consent

Order

CSO Consent

Order

Wet Weather Management

Plan

Page 5: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Columbus’ Wet Weather Timeline

August 2002

September 2004

July 2010

September 2010

July 2012

January 2013

September 2015

July 2005

WWTP Expansion Complete

OARS Construction

Begins

Page 6: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

25

35

45

55

65

75

85

95

105

115

1250

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

2007 2008 2009 2010 2011 2012 2013 2014

Rain

fall

(in)

Tota

l Ove

rflo

w (M

G) Total Overflow

WWTP Bypass and Overflow from the Largest SSO and CSO

Total Overflow (MG) Rainfall (in)

2011 is the wettest year on record.

Page 7: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Columbus’ Wet Weather Timeline

August 2002

September 2004

July 2010

September 2010

July 2012

January 2013

September 2015

July 2005

Request to Explore

Integrated Planning

OEPA Approval of

Request

Blueprint Columbus

Report Delivered

Page 8: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Delivered to Ohio EPA on Sept. 15, 2015 • The Integrated Plan and 2015 WWMP

Update – Both plans have to meet functional requirements

• Four schedules for completing plan – Original schedule (30 more years), plus 5, 10 and

15 years shorter

– Blueprint to be completed by 2035

• Affordability analysis – demonstrating plan is fast but affordable

Page 9: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

What is the Blueprint Approach?

• Blueprint has four pillars

– Mandatory lateral lining

– Selected roof redirection

– Voluntary sump pump

– Green infrastructure

• Vacant lot repurposing

Gree

n In

fras

truc

ture

Late

ral L

inin

g

Volu

ntar

y Su

mp

Pum

p

Roof

Red

irect

ion

Page 10: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Pre-Blueprint Condition • Directly connected roof drains and ineffective

splash blocks contribute rain to the foundation drain

• The foundation drain is connected to the lateral • Lateral may be cracked or leaking

Page 11: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Roof Drain Redirection and Lining • Roof drain redirection will direct water

away from the foundation drain • Laterals and mainlines lined

Page 12: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Voluntary Sump Pump Program and GI Sump pumps and lateral lining will disconnect foundation drains from the lateral and direct the water to green infrastructure

Page 13: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Blueprint Clintonville – Green Infrastructure

• Do No Harm

– Street flooding will not get worse

– Green infrastructure will be sized to receive redirected flow

• 20% reduction in Total Suspended Solids

• Do not expect any infiltration into the soil

– Infiltration testing shows average infiltration at 0.006 inches per hour

– Provide treatment and some detention prior to release to storm system

Page 14: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Blueprint Map

18,400 acres

Page 15: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Gray Improvements Needed in Both Plans

• It was determined that the Blueprint Plan would need to have some gray infrastructure included

– Tunnel on the west side known as Lower Olentangy Tunnel

• The tunnel needed in the Blueprint Plan for two reasons

– Completion of the CSO program

– Certain areas not solved with Blueprint alone

• The gray plan will include this tunnel, plus more tunnels

Page 16: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

The Blueprint Plan

• Applied modeling assumptions on all of the map areas

• Checked to make sure SSOs and WIBs are eliminated

– (this is when the need for LOT was identified)

• Checked to make sure not making things worse outside Columbus

• Determined that Blueprint could be successful without any participation from suburban areas

• Some areas solved with just Blueprint, some required additional solutions

• Includes green infrastructure (not depicted on maps yet)

Page 17: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

X X X X

1 WIB

Columbus area reduced from 928 acres to 432 acres

X = DSR or Connection Closed

0 = Weir Raised/Reconfigured

= New Pipes Installed

X

No work in Upper Arlington or Franklin County

To LOT/FM

WIBs DSRs

Base 103 10

BLU 1 0

Fifth by Northwest

Page 18: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

2. LOT1 provides free boundary condition

1. Oxley Rd Relief is closed

Fifth by Northwest

WIBs DSRs

Base 103 10

GRY 0 0

X = DSR or Connection Closed

0 = Weir Raised/Reconfigured

= New Pipes Installed = Pipes Upsized

Page 19: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Blueprint Plan

Page 20: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Gray Plan

Page 21: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Functional Requirements

• All plans meet the following functional requirements:

– 10 year level of service for SSOs

– 10 year level of service for WIBs

– 10 year level of service for downtown CSOs

– Typical year level of service for other CSOs

– 4 overflows in a typical year for the OARS CSO

– 1.4 year level of service at Southerly WWTP bypass

Page 22: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Costs • The cost of the Blueprint plan and the Gray plan are similar

– Blueprint $1.77B

– Gray $1.61B (2015 WWMP)

• Both are lower than the remaining cost of the 2005 WWMP, which is $2.47B

• Rates are based on the Total Capital

• The new plan is cheaper!

Blueprint Gray 2005 WWMP

Consent Order $1.77 B $1.61 B $2.47 B

Non-Consent Order $1.88 B $2.02 B $2.02 B

Total Capital $3.64 B $3.63 B $4.49 B

Page 23: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

0

500

1,000

1,500

2,000

2,500

3,000

2005 2010 2015 2020 2025 2030 2035 2040 2045 2050

Aver

age

Annu

al O

verf

low

(M

G)

Blueprint Projects

BWARI, Headworks, WWTP Peak Capacity Expansion

CEPT, OARS Completion

SMR, DSR 83, Sluice Gates

How Does Blueprint Impact Overflows?

Page 24: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Technology Volume Reduced (MG)

Peak Reduced (MGD)

Sewer Lining 17.5 0.3 Lateral Lining 26.2 0.6 Sump Pump 12.1 2.0 Downspout Redirection 6.4 1.3 All 4 Technologies Combined

67.0 3.3

Note that each row is a separate model run. Approximately this amount will be routed to the stormwater system.

I/I Reduced by Technology: Typical Year of Rain Clintonville Pilot Area

Page 25: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Benefits of Blueprint Plan

• Water Quality - Stormwater

– Removes 342 tons of sediment from local rivers and streams annually once all 18,000 acres are constructed

– That’s 44 Hanks!

– $373 M in Green Infrastructure

• Regional Economic Impact

– Keeping money local compared to out-of-town tunneling companies

– Products and services provided by the community

Columbus Zoo’s Hank weighs 15,600 pounds

Page 26: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Benefits of Blueprint Plan

• Job Creation

– GI maintenance jobs

– Smaller construction projects

• Neighborhood Impacts

– Green amenities

– Renewed laterals

• Addressing the problem rather than the symptom

Page 27: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Benefits of Blueprint Plan

• Blueprint includes $959 M in renewed infrastructure – Approximately half of this will go towards lining laterals

– Solving the source of the problem that will only get worse if left alone

• The gray plan only includes $390 M in renewed infrastructure – Gray depends on building new assets rather than fixing the existing

assets

– Does not include the liability that homeowners face with lateral failures

– Rates will be the same but homeowners will incur more costs

Page 28: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Where can you find the report?

http://www.columbus.gov/blueprint/

Page 29: Blueprint Columbus Southeast District AWWA Conference · – Original schedule (30 more years), plus 5, 10 and 15 years shorter ... • Roof drain redirection will direct water away

Questions? Jason Sanson, P.E.