  • ITEM DESCRIPTION UNIT QTY RATE (N)* COST(N)

    1 Detailed Engineering L/S 1 94,010,000.00 94,010,000.000.00

    2Mobilization and Demobilization of materials,personnel and equipment L/S 1 309,791,350.00 309,791,350.00

    0.00

    3

    Excavation works (16000mm x 6500mm x 3050mm) -dimensions to be frozen after detailed engineeringdesign (for the Skimmer Pit) M3 317 7,000.00 2,220,400.00

    0.00

    4Construction of Concrete Walls and Base of 250mmthick M3 46.5 120,000.00 5,580,000.00

    0.00

    5Provision of all required accessories for the SkimmerPit L/S 1 37,043,512.00 37,043,512.00

    0.00

    6

    Provision and installation of two (2) nos. PneumaticPumps for pumping the Skimmed Oil back forprocessing and recycling of the effluent water PCS 2 25,605,008.00 23,277,280.00

    7

    Provision and installation of two (2) nos. Pumps forpumping the Oily water from the Skimmer Pit to theENVIRO-CELL unit for further Treatment. PCS 2 28,878,608.00 26,253,280.00

    0.00

    8

    Provision and installation of inter pipingconnections, valves, other accessories and ancillarywork L/S 1 49,502,475.00 49,502,475.00

    0.00

    9Provision and installation of 10,000 BLD ENVIRO-CELLunit L/S 1 120,798,568.00 120,798,568.00

    0.00

    10Provision of two (2) nos. Pumps for pumpingtreated water to water body 8km away PCS 2 28,878,608.00 26,253,280.00

    0.00

    11Provision and installation of Quality meter and Three(3) way valve to ensure specified water quality is met L/S 1 34,059,080.00 34,059,080.00

    0.00

    12

    Provision of all the associated Flowlines andaccessories from the skimmer Pit to the Oily WaterTreatment facility and from the Treatment Facility todisposal 8km away. L/S 1 152,009,000.00 152,009,000.00

    0.0013 Testing and commissioning L/S 1 34,237,897.10 34,237,897.10

    14 Hook up of Cathodic Protection System L/S 1 5,000,000.00 5,000,000.00

    SUB TOTAL 826,026,122.10CASHES 1 5,000,000.00 5,000,000.00

    5% VAT 49,861,567.33

    GRAND TOTAL 880,887,689.43*Note - 158 Naira/US$

    BILL OF ENGINEERING MEASUREMENTS & EVALUATIONS (BEME) FOR:

    THE PROVISION OF ENGINEERING, PROCUREMENT AND CONSTRUCTION OILY WATER TREATMENT FACILITIES