before a board of inquiry basin bridge proposal - … · 24089825_7.docx before a board of inquiry...
TRANSCRIPT
24089825_7.docx
BEFORE A BOARD OF INQUIRYBASIN BRIDGE PROPOSAL
UNDER the Resource Management Act 1991
IN THE MATTER OF applications for resource consents and notice of requirement in relation to the Basin Bridge Proposal
BY NZ Transport Agency
EVIDENCE OF MICHELLE CONLAND ON BEHALF OF GREATER WELLINGTON REGIONAL COUNCIL
Planning
DATE: 17 December 2013
Barristers & Solicitors
M G Conway / M D LeslieTelephone: +64-4-499 4599Facsimile: +64-4-472 6986E-mail: [email protected] SX11174PO Box 2402Wellington
Page 1
24089825_7.docx
CONTENTS
Page
Introduction 2
Scope of evidence 3
Executive summary 4
WRC's submission and outstanding issues 5
Consistency with the Regional Policy Statement, Regional Plans and Part 2 of the RMA
6
Adequacy of mitigation measures and conditions 11
Recommendations 12
Conclusion 17
Annexure: Suggested wording of consent conditions 18
Page 2
24089825_7.docx
INTRODUCTION
1. My full name is Michelle Andrea Conland. I am a resource management
consultant, contracted to Environmental Regulation, Greater Wellington Regional
Council (WRC).
2. I have a Bachelor of Science and a Master of Science degree in Physical
Geography, from Victoria University of Wellington. I have worked in the field of
resource management for approximately 15 years.
3. From 1998 to 2000, I was employed by the Wellington City Council, assisting
hearing panels writing notified resource consent decisions and then as a Policy
Advisor. From 2000 to 2008, I was employed by the Otago Regional Council, as a
Resource Adviser and then Senior Resource Adviser. From 2008 to 2010, I
managed the Consents Team at Hawke’s Bay Regional Council. Since April
2010, I have been a self-employed resource management consultant, undertaking
various projects for regional councils, including processing resource consent
applications.
4. In 2012 and 2013, I carried out pre-lodgement and lodgement checks under
section 88 of the Resource Management Act 1991 (RMA) and produced a section
149G(3) Key Issues Report for the Environmental Protection Authority (EPA) on
behalf of WRC, in relation to New Zealand Transport Agency’s (NZTA) MacKays
to Peka Peka and Peka Peka to Otaki Roads of National Significance (RoNS)
Expressway projects.
5. My involvement to date in the Basin Bridge Proposal (Proposal) has comprised a
meeting with the EPA, NZTA and Wellington City Council (WCC) on 12 December
2012, at which NZTA provided an overview of the Proposal. In addition, while
preparing this evidence, I have reviewed the planning matters for the Proposal
which are relevant to WRC’s submission. I participated in expert witness
conferencing on planning matters on 3 December 2013.
6. In preparing this evidence I have reviewed the following:
(a) WRC’s s149G(3) Key Issues Report;
(b) Relevant application documents;
Page 3
24089825_7.docx
(c) Relevant statements of evidence prepared by witnesses for the
applicant, including the evidence of Mr Alistair Aburn (Planning), and Mr
Lindsay Daysh (Planning Matters and Conditions), both dated 25
October 2013;
(d) The section 42A report “Planning Report, First Edition”, prepared by
Mitchell Partnerships Limited, dated 25 October 2013;
(e) Joint Statements of Expert Witnesses for Erosion and Sediment Control
dated 10 December 2013 and Groundwater dated 12 December 2013;
and
(f) All statements of evidence prepared by witnesses on behalf of WRC.
7. I am authorised by WRC to present this evidence on its behalf.
8. I have read and am familiar with the Code of Conduct for Expert Witnesses in the
Environment Court Practice Note 2011. I agree to comply with that Code. Other
than where I state that I am relying on the advice of another person, this evidence
is within my area of expertise. I have not omitted to consider material facts known
to me that might alter or detract from the opinions that I express.
SCOPE OF EVIDENCE
9. WRC made a submission supporting the applications but raising a number of
issues relating to:
(a) Groundwater;
(b) Erosion and sediment control; and
(c) Transport.
10. The groundwater and erosion/sediment control matters have largely been
resolved through NZTA’s evidential response to WRC’s submission and through
expert conferencing. The transport issues are addressed in more detail in the
evidence of:
(a) Mr Nick Sargent (transport modelling);
(b) Mr Alex Campbell (public transport operations); and
Page 4
24089825_7.docx
(c) Mr Luke Troy (regional transport).
11. Drawing on the evidence of WRC's advisers, my evidence addresses the following
matters:
(a) WRC's submission points and outstanding issues;
(b) Consistency with the regional policy statement, regional plans and Part 2
of the RMA;
(c) Adequacy of mitigation measures and conditions; and
(d) Recommendations.
EXECUTIVE SUMMARY
12. WRC generally supports the Proposal due to the overall benefits to the region’s
transport network. However, there remain some outstanding concerns identified
in this evidence and that of other witnesses on behalf of WRC. Suggested
amendments to the draft conditions prepared by the applicant have been
identified.
13. WRC’s Public Transport Group seeks a substantial degree of engagement with
the Proposal project team to enable input into the detailed design of the Proposal
and the development of the CTMP and SSTMPs, to achieve better outcomes for
public transport. It is also recommended that the detailed design of the Proposal
provide for consistency with the preferred option of the PT Spine Study. I
recommend a new condition that requires that a Network Integration Plan be
prepared in collaboration with WCC and WRC (in respect of the public transport
elements). This plan would demonstrate how the Project integrates with the
existing local road network and with future improvements identified in the Public
Transport Spine Study.
14. In addition, amendments are required to some conditions to clarify the
requirements of the management plans, the groundwater monitoring requirements
and the provision of data. Changes to the conditions relating to the review of the
consents, dispute resolution, and the notification of incidents or complaints are
also recommended.
Page 5
24089825_7.docx
15. Subject to addressing WRC’s outstanding concerns in the manner set out in my
evidence, in my opinion, the Proposal is generally consistent with all of the
relevant provisions of the applicable planning and policy documents, and Part 2 of
the RMA.
WRC'S SUBMISSION AND OUTSTANDING ISSUES
16. WRC supports the Proposal overall, subject to refinements to the proposed
designation and resource consent conditions to address the matters raised in the
submission. In its submission, WRC requested the following:
(a) further involvement in the public transport operational planning and
implementation phases of the Proposal to ensure future compatibility and
to maximise the efficiency and effectiveness of public transport
movements through this area;
(b) involvement in all stakeholder and associated meetings relating to the
operational traffic management planning during the construction phase of
the project;
(c) consultation with WRC on the development of the Construction Traffic
Management Plan (CTMP) and Site-specific Transport Management
Plans (SSTMPs);
(d) further consultation and involvement in the planning of post construction
operational issues, including bus stop location, merging of bus traffic and
bus priority measures;
(e) appropriate monitoring of groundwater flows and levels to help manage
potential effects and contingency measures for excessive flows;
(f) treating discharged groundwater in accordance with the draft NZTA
Erosion and Sediment Control Standard for State Highway Infrastructure
as well as the WRC Erosion and Sediment Control Guidelines;
(g) certification by WRC of management plans and any changes to these
plans; and
(h) well structured, easily interpreted, certain, defensible and enforceable
conditions.
Page 6
24089825_7.docx
17. While some of these matters have been addressed through the statements of
evidence prepared by witnesses for the applicant, including the evidence of Mr
Daysh, and the Joint Statements of Expert Witnesses for Erosion and Sediment
Control, and Groundwater, some of these matters remain of concern. Further
details of the outstanding concerns are provided below.
CONSISTENCY WITH THE REGIONAL POLICY STATEMENT, REGIONAL PLANS AND
PART 2 OF THE RMA
18. The statutory framework for the Proposal is set out in Part E, Chapter 7 (Statutory
Considerations) and Part I, Chapter 36 (Approach to the Assessment) of the
Assessment of Environmental Effects (AEE). To avoid unnecessary duplication I
will adopt their description except where indicated in my evidence.
19. An assessment of the Proposal against the provisions of national and regional
planning and policy documents is provided in Part E, Chapter 7 (Statutory
Considerations) and Part I, Chapter 37 (Planning Assessment of the Project) of
the AEE. I consider the following statutory documents and provisions are relevant
to this Proposal with regard to GWRC’s submission:
(a) National Policy Statement for Freshwater Management 2011 (NPS FM),
but only with regard to groundwater;
(b) The Regional Policy Statement 2013 (RPS);
(c) The Regional Freshwater Plan for the Wellington Region 1999 (RFWP);
(d) The Regional Plan for Discharges to Land for the Wellington Region
1999 (RPDL);
(e) The Resource Management (Measurement and Reporting of Water
Takes) Regulations 2010 (MRWT); and
(f) Other relevant matters, listed at paragraph 31 below.
20. I consider that the New Zealand Coastal Policy Statement 2010 is not relevant to
this Proposal, as there are no direct discharges to, or effects on, the coastal
marine area.
21. Policies 1-34 of the RPS are listed in Chapter 37 and Technical Report 18 as
being relevant to the Proposal. However, these policies direct provisions to be
Page 7
24089825_7.docx
included in the District Plan, Regional Plans and the Regional Land Transport
Strategy, and so are not directly relevant to the consideration of the designation
and resource consent applications. Policy 42 of the RPS (‘Minimising
Contamination in Stormwater from Development – Consideration’) has not been
identified in Chapter 37 or Technical Report 18.
22. Mr Aburn in his evidence has not included the RFWP or the RPDL as having a
role to play in establishing the strategic planning framework for the Proposal, and
no assessment of the Proposal against the objectives and policies of these plans
is provided in his evidence.1 In my opinion, while these plans may not relate
directly to the overall transportation outcomes sought by the applicant, they do,
nonetheless, have a role in managing the adverse effects of the Proposal on the
environment. I note the relevant provisions of these plans below.
23. With the exception of the matters noted above in paragraph 16, and setting aside
the lack of reference to the RFWP and RPDL in Mr Aburn’s evidence, it is my
opinion that the relevant provisions of the regional and national planning
documents have been identified by the applicant in Chapters 7 and 37 of the AEE
and Technical Report 18.
24. However, until the concerns raised in WRC’s submission and evidence regarding
involvement in the operational traffic management planning, and appropriate
conditions for the water permit, land use consent and discharge permit have been
addressed satisfactorily, I consider that it is not appropriate to conclude at this
time that the proposal is entirely consistent with the provisions of all of these
documents.
25. With regard to the concerns relating to WRC’s involvement in operational traffic
management planning, consistency is required with the following policies of the
RPS in particular:
Policy 57 Integrating land use and transportation;
Policy 54: Achieving the region’s urban design principles; and
Policy 58: Co-ordinating land use with development and operation of
infrastructure.
1 Alistair Aburn evidence, paragraph 4.2.
Page 8
24089825_7.docx
26. Policy 57 states that when considering an application for a notice of requirement,
particular regard shall be given to certain matters, in making progress towards
achieving the key outcomes of the Wellington Regional Land Transport Strategy.
Those matters which relate to the outcomes that WRC is seeking include (a) in
relation to the impacts on the efficiency, reliability or safety of the network, (c) in
relation to good access to the strategic public transport network and (e) which
notes that particular regard be given to whether new or upgrades to existing
transport network infrastructure have been appropriately recognised and provided
for.
27. Policy 54 relates to achieving the region’s urban design principles which are set
out in Appendix 2 of the RPS. There are seven principles and those of relevance
to the matters that WRC is seeking include:
Context – which states that quality urban design provides for public
transport, roading, cycling and walking networks that are integrated with
each other and the land uses they serve
Choice – which states that quality urban design allows people to choose
different modes of transport
Connections – which states that quality urban design places a high priority
on walking, cycling and public transport; and anticipates travel demands
and provides a sustainable choice of integrated transport modes
Collaboration – which states that quality urban design uses a collaborative
approach to design that acknowledges the contributions of many different
disciplines and perspectives.
28. Policy 58 states that when considering an application for a notice of requirement,
particular regard shall be given to whether the proposed development is located or
sequenced to coordinate with the development and operation of new
infrastructure. As noted below Mr Luke Troy recommends that the detailed design
of the Proposal provide for consistency with the preferred option of the PT Spine
Study.
Page 9
24089825_7.docx
29. With regard to the concerns relating to the conditions of the resource consents,
consistency is required with the objectives and policies of the RFWP and the
RPDL, and in particular:
Policies 4.2.35 and 4.2.36 of the RFWP in relation to consent conditions;
Policy 5.2.7 of the RFWP in relation to adverse effects on groundwater
quality as a result of discharges to groundwater;
Policy 5.2.14 of the RFWP in relation to the treatment of stormwater
discharges;
Policy 5.2.16 of the RFWP in relation to minimising the adverse effects of
accidental spills on water quality; and
Policy 4.2.21(2) of the RPDL in relation to the potential for any
contaminants to enter groundwater, surface water or coastal water,
including the risks of any accidental discharges, and any effects on water
quality and aquatic ecosystems.
30. In my opinion, these policies support the changes sought to the conditions, as
recommended below.
Other relevant regulations and matters
31. The Resource Management (Measurement and Reporting of Water Takes)
Regulations 2010 (MRWT) are unlikely to be relevant to the Proposal, as these
regulations only apply to water takes where the abstraction is at a rate of more
than 5 litres per second. However, an upper limit on the volume of water to be
abstracted has not been provided in the application so it is difficult to be certain
about whether the MWRT are relevant. Non-consumptive takes are not subject to
the regulations (irrespective of the rate of that take), which are described in the
regulations as takes where the same amount of water is returned to the same
water body at or near the location from which it was taken; and there is no
significant delay between the taking and returning of the water. Any water taken
and discharged via the WCC’s stormwater system would be classified as a
consumptive take.
Page 10
24089825_7.docx
32. Witnesses on behalf of WRC also refer to ‘other matters’ of relevance to the
Proposal, including:
(a) Wellington Regional Land Transport Strategy 2010-2040;
(b) Wellington Regional Land Transport Programme 2012-2015;
(c) Wellington Regional Land Transport Plan 2011-2021;
(d) Public Transport Spine Study (June 2013) (PT Spine Study); and
(e) Ngauranga to Airport Corridor Plan 2008.
33. The other witnesses on behalf of WRC make statements about the relevance and
consistency of the proposal with these documents and I rely upon their
assessments.
Additional matters for discharge permits
34. Section 105 of the RMA lists additional matters that a consent authority must have
regard to when considering applications for discharge or coastal permits to do
something that would contravene section 15 of the RMA. Resource consents
have been sought for the discharge of contaminants to groundwater and land in
relation to the construction of bridge piles and ground improvement works. Section
107(1) of the RMA places restrictions on the grant of resource consents for the
discharge of contaminants into water if they cause certain adverse effects in
receiving waters after reasonable mixing.
35. I consider that provided appropriate conditions of consent are in place to manage
the potential adverse effects of these discharges during construction, including the
recommended changes to the conditions of the discharge permit and in relation to
the erosion and sediment control measures, the Proposal will meet the
requirements of Section 105 and 107 of the RMA.
Part 2 RMA Assessment
36. Mr Aburn in his evidence concludes that the Project is consistent with the
applicable statutory and planning instruments.2 Mr Daysh concludes in his
2 Alistair Aburn evidence, paragraphs 9.2 and 9.12.
Page 11
24089825_7.docx
evidence that the Project meets the statutory tests of the RMA and is consistent
with the purpose and principles of Part 2 of the RMA.3
37. In my opinion, provided that the conditions are amended as proposed below, the
Proposal is generally consistent with Part 2 of the RMA. However, a lack of
involvement in the construction and operational traffic planning matters and of
consistency with the PT Spine Study, could result in the Proposal being
inconsistent with Section 7(b) of the RMA (‘the efficient use and development of
natural and physical resources’), and to a lesser extent may also have impacts on
whether the Proposal is consistent with Section 7(f) (‘the maintenance and
enhancement of the quality of the environment’). Robust consultation and input
from WRC Public Transport Group into the planning and design of the Proposal
will help to ensure the efficient use and development of all affected physical
resources, and the maintenance and enhancement of the quality of the
environment.
ADEQUACY OF MITIGATION MEASURES AND CONDITIONS
38. WRC will be responsible for monitoring ongoing effects of the Proposal and
ensuring compliance with the conditions of the four resource consents sought
under WRC’s regional plans for the Proposal, if granted. This includes
certification of management plans and undertaking physical compliance
inspections during and after construction. As such, WRC has an interest in
ensuring that consent conditions are clear, certain and enforceable, with
appropriate performance standards.
39. In my opinion it is important that conditions have sufficient detail so that all parties
have certainty of expected outcomes. Well written, easily interpreted conditions
are less likely to cause disagreement once the consents have been granted.
Several conditions, including some proposed in the joint expert witness
statements, need rewording to improve clarity, or require further details, such as
timeframes for providing information.
40. Mr Daysh for the applicant has prepared updated draft conditions incorporating
changes recommended by its various experts.4 While a number of the matters
raised by WRC have been included, there are still some amendments and
additions that I consider are required to ensure that the conditions are clear,
3 Lindsay Daysh evidence, paragraph15.46.4 Lindsay Daysh evidence, page 88.
Page 12
24089825_7.docx
certain and enforceable, and will address the adverse effects of the Proposal,
including matters raised in WRC’s submission and evidence. In addition, some of
the changes to the conditions proposed in the Joint Statements of Expert
Witnesses for Erosion and Sediment Control, and Groundwater could be further
reworded to improve clarity. I discuss my recommended condition amendments
below.
RECOMMENDATIONS
41. In the Annexure to my evidence, I set out a number of changes that I recommend
be made to the conditions of the resource consent sought under WRC’s regional
plans, as well as the designation conditions. Further details regarding some of
these amendments are provided in the evidence of other WRC expert witnesses.
I briefly outline the reasons for each of the amendments below, with reference to
the relevant condition numbers.
42. Additional condition amendments may be required to those suggested below once
further information becomes available through the conferencing and hearing
process.
General conditions
43. G.1 – To avoid confusion, a clause should be included which states that the most
recent information has priority where there is conflict between the documents.
44. G.7 – Currently there is only one opportunity provided for WRC to review the
consent conditions in the event of adverse effects arising from the exercise of the
consents, or to review the adequacy of the construction operating and
maintenance processes and the monitoring requirements for the consents to deal
with any adverse effects arising from the exercise of the consents. It is possible
that any adverse effects may not have become apparent by this time, so in my
opinion, additional opportunities to review the consent conditions should be
provided following the one year anniversary of the consents, if granted.
45. G.8 – I do not consider it appropriate to have a dispute resolution condition,
especially in relation to the implementation or monitoring of consent conditions.
Any inaction of monitoring required by consent conditions would be an
Page 13
24089825_7.docx
enforcement matter for WRC. Such a condition would be contrary to WRC’s
enforcement powers.
46. G.9 – The details of a complaint or incident in relation to any granted resource
consents need to be communicated to WRC in a timely manner. Providing a
timeframe of up to five working days, as has been proposed in the draft condition
G.9, to advise of the non-compliance and remedial actions undertaken could
result in additional and potentially significant adverse effects on the environment.
Such a provision is inconsistent with the standard practice for notifying WRC in
the event of an incident, and in my opinion is not appropriate or necessary. In my
opinion, a timeframe of up to 24 hours following the complaint or becoming aware
of the incident is appropriate. Therefore I recommend that the condition be
amended to require notification of the Manager of any complaints in relation to the
works as soon as practicable and within 24 hours of receiving the complaint or
being made aware of the incident. A five working day period for communicating
any remedial actions undertaken remains appropriate.
47. G.10 – While this condition now refers to certification of the management plans
and any amendments to the plans, the wording of the condition could be improved
for clarity. The wording “… any required amendments required by these
conditions.” should be replaced with “any amendments certified in accordance
with condition G.13 or G.15.”
48. G.16 – I agree with the assessment of Mitchell Partnerships Ltd5 regarding the
proposed management plan conditions. The matters that must be included in the
management plans, and the mitigation outcomes that must be achieved via the
implementation of the management plans, need to be clearly stated. Currently, the
draft conditions lack sufficient precision in the way that they guide the preparation
of the various management plans. Condition G.16 should detail the purpose,
objectives, and mitigation outcomes of the CEMP. In addition, part (b) of the
condition should refer to treatment of construction affected groundwater, and
chemical flocculation pre-use testing and management, if chemical flocculation is
to be used.
5Paragraphs 4.0.4 – 4.0.8 of the Section 42A report “Planning Report, First Edition”, prepared by Mitchell Partnerships Limited, dated 25 October 2013.
Page 14
24089825_7.docx
Water permit for groundwater take
49. WP.2 – This condition should include a timeframe for submitting records to WRC.
Dr Jack McConchie and Dr Mark Gyopari have agreed that the monitoring data
should be submitted within two weeks following the installation of the first pile.6
However, if further monitoring of the volumes of water taken is to occur after this
time, a timeframe for submitting this data is required. I recommend that these
records be submitted on a monthly basis to provide time for the data to be
collected, but still submitted in a timely manner.
50. WP.3 – The method for monitoring should be stated. In addition, monitoring
should be undertaken prior to the works beginning, as well as during the works.
Data should be recorded preferably on a continuous basis. To provide for these
matters, Drs McConchie and Gyopari have agreed that the wording should be
amended to “The consent holder shall monitor groundwater levels in boreholes
known as BHTT615 and BHTT10603 continuously using pressure transducers.
Monitoring shall be undertaken over a period extending from 6 months prior to
construction of the first pile until 6 months after completion of the last pile shall
continue for the duration of the project.”7
Land Use Consent
51. LUC.9 – A timeframe for providing the bore log needs to be included. Again, I
recommend a timeframe of one month to allow time for the bore log to be
completed and submitted in a timely manner.
Discharge permit to land
52. DP.1(a) – Typographical amendment required for the units of suspended
sediment concentration. The condition should be amended from “50 grams per
cubic metre 50mg/L” to “50 grams per cubic metre or 50 milligrams per litre” or
just a single measurement unit could be used.
53. DP.1(b) – Typographical amendments also required with the words “…will not
cause” being replaced with “…the discharge shall not cause”.
6 Groundwater Joint Witness Statement, 12 December 2013, page 5.7 Groundwater Joint Witness Statement, 12 December 2013, page 5.
Page 15
24089825_7.docx
54. The conditions of this consent should also reference the construction and
maintenance of erosion and sediment control measures to treat the discharge, to
clarify that these measures are proposed to reduce contaminants prior to being
discharged.
Designation conditions
55. DC.22 and DC.25 – These conditions refer to the communication of traffic
management measures with affected road users and stakeholders including the
WRC Public Transport Group. I consider that this wording, and in particular
reference to ‘communication’ in conditions DC.22 and DC.25, is not adequate to
address the concerns raised in the evidence of WRC’s transport advisers
regarding ensuring an adequate level of input into the development of the CTMP
and SSTMPs. Communication implies a one-sided dialogue, with little opportunity
for input from WRC’s Public Transport Group. In order for the WRC Public
Transport Group to have input into the construction effects and post construction
operational issues affecting public transport operation, involvement in meetings
and effective consultation with the WRC Public Transport Group is required.
56. As noted by Alex Campbell at paragraph 54 of his evidence, given the number of
bus services and passengers potentially affected by construction traffic
management and the issues outlined in his evidence, he recommends WRC
involvement in all stakeholder and associated meetings relating to the traffic
management planning during the construction phase of the project. Furthermore,
WRC should be consulted on the development of the CTMP and SSTMPs in
relation to impacts on the operation of public transport, and any other involvement
to ensure an adequate level of input into these plans.
57. At paragraph 87 of his evidence, Luke Troy notes the need to ensure that the
Proposal will be able to fully incorporate whichever PT Spine Study option is
chosen. Consequently, Mr Troy recommends that there be a requirement that the
detailed design of the Proposal provide for consistency with the preferred option
for the PT Spine Study once that is confirmed. He notes that this may be achieved
through a Network Integration Plan such as has been used in other recent roading
projects including NZTA’s Waterview Connection Project and MacKays to Peka
Peka Expressway projects. A similar condition is proposed for the Peka Peka to
Otaki Expressway project. The Network Integration Plan should require specific
consideration of continuous dedicated public transport lanes around the Basin
Page 16
24089825_7.docx
Reserve, signal priority for public transport vehicles at all relevant intersections to
ensure forecast travel times and improved reliability are achievable, and
consideration of the appropriate location and design of public transport stops.
58. Nick Sargent notes in his evidence at paragraph 97 that additional, more detailed
modelling is required to ensure that the PT Spine Study option that WRC pursues
can be accommodated around the Basin Reserve, providing both acceptable
public transport and highway travel times.
59. In my opinion, the Proposal will be generally consistent with the relevant policies
of the RPS, being Policies 54, 57 and 58, as well as Part 2 of the RMA, provided
that these matters can be incorporated into the conditions of the designation.
60. In summary, WRC’s Public Transport Group seeks a substantial degree of
engagement with the Proposal project team to enable input into the detailed
design of the Proposal and the development of the CTMP and SSTMPs, which will
result in better outcomes for public transport. In order for the WRC Public
Transport Group to have input into the construction effects and post construction
operational issues affecting public transport operation, involvement in meetings
and effective consultation with the WRC Public Transport Group is required. For
the reasons outlined in paragraph 54 of Alex Campbell’s evidence, I recommend
that the wording of the conditions be amended to enable input into the detailed
design of the Proposal and the development of the CTMP and SSTMPs, with
regard to WRC’s role in public transport.
61. For the reasons outlined in paragraph 87 of Luke Troy's evidence, I recommend
that there be a new condition relating to the provision of a Network Integration
Plan that will be prepared in collaboration with WCC and WRC (in respect of the
public transport elements). This plan would demonstrate how the Project
integrates with the existing local road network and with future improvements
identified in the Public Transport Spine Study.
62. DC.38 – I note that Mitchell Partnerships consider this condition redundant due to
the requirements of condition G.16 in relation to the CEMP.8 If this condition is to
be retained, for clarity, this condition should also state that all erosion and
sediment control measures shall be installed and maintained in accordance with
8 Page 86 of the Section 42A report “Planning Report, First Edition”, prepared by Mitchell Partnerships Limited, dated 25 October 2013
Page 17
24089825_7.docx
the WRC Erosion and Sediment Control Guidelines and the NZTA Draft Erosion
and Sediment Control Standard for State Highway Infrastructure.
CONCLUSION
63. WRC generally supports the Proposal due to the overall benefits to the region’s
transport network. However, there remain some outstanding concerns identified
in this evidence and that of other witnesses on behalf of WRC. Suggested
amendments to the draft conditions prepared by the applicant have been
identified.
64. In particular, amendments are required to some conditions to clarify the
requirements of the management plans, the groundwater monitoring requirements
and provision of data. Changes to the conditions relating to the review of the
consents, dispute resolution, and the notification of incidents or complaints are
also recommended.
65. WRC’s Public Transport Group seeks a substantial degree of engagement with
the Proposal project team to enable input into the detailed design of the Proposal
and the development of the CTMP and SSTMPs, which will result in better
outcomes for public transport. It is also recommended that the detailed design of
the Proposal provide for consistency with the preferred option of the PT Spine
Study. A Network Integration Plan could be used to achieve this, with specific
consideration of continuous dedicated public transport lanes around the Basin
Reserve, signal priority for public transport vehicles, and consideration of the
appropriate location and design of public transport stops. Amendments to the
designation conditions are required to provide for this.
66. Subject to addressing WRC’s outstanding concerns in the manner set out in my
evidence, in my opinion, the Proposal is generally consistent with all of the
relevant provisions of the applicable planning and policy documents, and Part 2 of
the RMA.
Michelle Conland
17 December 2013
Page 18
24089825_7.docx
Annexure: Suggested wording of consent conditions
Black text: Conditions as notified.
Red text: Changes proposed in evidence of Lindsay Daysh 25 October 2013.
Green text: Changes proposed as recommended in this evidence, and as a result of
conferencing and submitter discussions (additions underlined, deletions
struck out. For clarity, green text that is underlined and struck out
represents additions made by Lindsay Daysh that have been deleted as
recommended in this evidence, and as a result of conferencing and
submitter discussions).
General Conditions
G.1 Except as modified by the conditions below, the Project shall be undertaken in
general accordance with the information provided by the Consent Holder in the
resource consent applications [insert reference no.] and supporting documents being:
(a) Plan sets:
i. Drawings 1A.01 – 1A.02
ii. Drawings 5A.01 – 5A.14
iii. Drawings 6A.01 – 6A.05
iv. Drawings 6B.01 – 6B.04
v. Drawings 6C.01
vi. Drawings 6D.01 – 6D.02
vii. Drawings 6F.01 – 6F.03
Where there may be contradiction or inconsistencies between the documents lodged
and further information provided by the applicant, the most recent information
applies.
Where there is conflict between the documents lodged and further information, and
the conditions, the conditions shall prevail.
G.7 The Manager may review any or all conditions of this consent by giving notice of their
intention to do so pursuant to Section 128 of the Resource Management Act 1991, at
any time within six months of the first, third, sixth and/or ninth anniversary of the date
of commencement of the works authorised by this consent for any of the following
purposes:
Page 19
24089825_7.docx
(a) To deal with any adverse effects on the environment, which may arise from the
exercise of this consent, and which it is appropriate to deal with at that time;
and
(b) To review the adequacy of the construction operating and maintenance
processes and the monitoring requirements for this consent so as to
incorporate any modifications to the construction operational and maintenance
procedures or monitoring that may be necessary to deal with any adverse
effects on the environment arising from the exercise of this consent.
G.8 Delete
G.9 (a) At all times during construction work, the consent holder shall maintain a
permanent register(s) of any public or stakeholder feedback received and any
incidents or non-compliance noted by the consent holder contractor, in relation
to the construction of the Project. The register(s) shall include:
i. the name and contact details (as far as practicable) of the person
providing feedback or contractor observing the incident/ non-compliance;
ii. identification of the nature and details of the feedback/ incident; and,
iii. location, date and time of the feedback/ incident.
(b) The consent holder shall promptly investigate any adverse feedback, reported
incident or non-compliance. This shall include, but need not be limited to:
i. recording weather conditions at the time of the event (as far as
practicable), and including wind direction and approximate wind speed if
the adverse feedback or incident relates to dust;
ii. recording any other activities in the area, unrelated to the Project that
may have contributed to the adverse feedback/ incident/ noncompliance,
such as non-Project construction, fires, traffic accidents or unusually
dusty conditions generally (if applicable); and,
iii. investigating other circumstances surrounding the incident.
(c) In relation to condition G.9(b), the consent holder shall:
i. record the outcome of the investigation on the register(s);
ii. record any remedial actions or measures undertaken to address or
respond to the matter on the register(s);
iii. respond to the initiator, explaining the outcome of the investigation and
any remedial measures taken, if practicable; and,
iv. where the adverse feedback or incident was in relation to a non-
compliance, the Manager shall be notified as soon as practicable and
within 24 hours of receiving the complaint or being made aware of the
Page 20
24089825_7.docx
incident, and shall be notified in writing of the matter within 5 working
days of the non-compliance, and be informed of the remedial actions
undertaken.
(d) The register(s) shall be maintained on site and shall be made available to the
Manager upon request.
G.10 All works shall be carried out in accordance with the certified management plans
and any required amendments required by these conditions any amendments
certified in accordance with conditions G.13 or G.15. No works shall be
commenced prior to WRC certification, including for any proposed amendments to
the management plans as provided for in Condition G13.
G.16 The CEMP shall be in general accord with the draft submitted with Volume 4 of
lodged documents] and include but need not be limited to:
(a) General:
i. CEMP purpose, objectives and mitigation outcomes;
ii. Project details including anticipated construction activities,
methodology and a schedule of construction activities, including
activities associated with compliance with designation and
resource consent conditions;
iii. Defining what changes in construction methodology and
programme activities will require formal amendment of the
Management Plan or the relevant sub management plans.
(b) Social and environmental management
i. Environmental issues anticipated during construction, including
issues associated with:
The condition and operation of piling and ground
strengthening machinery;
Groundwater including treatment of construction affected
groundwater, methodologies to control higher than
expected groundwater flows and disposal of this water;
Dewatering including any discharges to ground;
Waste management;
Sewage; and
Erosion and sediment control measures proposed to be
installed on site. All erosion and sediment control
measures shall be installed and maintained in
accordance with WRC Erosion and Sediment Control
Page 21
24089825_7.docx
Guidelines and the NZTA Draft Erosion and Sediment
Control Standard for State Highway Infrastructure; and
Chemical flocculation pre-use testing and management (if
used).
ii. The management approach, methods and measures to avoid
and mitigate adverse environmental effects arising in relation to
each environmental issue;
iii. Outline of how the CEMP responds to relevant conditions of
resource consents; and,
iv. An environmental risk register.
Water Permit (groundwater take) – Conditions
WP.1 The location, design, implementation and operation of the groundwater takes shall
be in general accordance with the consent application.
WP.2 The quantum of water discharged from all bores will be monitored to an accuracy
of +/- 10%.
The quantum of water discharged from all bores associated with the construction
of a pile will be monitored daily to an accuracy of +/- 10%. Within two weeks
fFollowing installation of the first pile, a summary of the monitoring data will be
provided to the consent authority. The Manager, Environmental Regulation,
Wellington Regional Council may after reviewing this information authorise that
further monitoring associated with the installation of the piles is unnecessary. If
further monitoring of the volumes of water discharged/taken from the bores is
required, the monitoring data shall be provided to the consent authority on a
monthly basis.
WP.3 Should the rate of water discharged from any bore or excavation exceed one litre
a second (1L/s) then action will be taken to reduce flows following discussion with
the consent authority.
The consent holder shall monitor groundwater levels in boreholes known as
BHTT156 and BH603TT10 continuously using pressure transducers. Monitoring
will continue for the duration of the project. shall be undertaken over a period
extending from 6 months prior to construction of the first pile until 6 months after
completion of the last pile.
Page 22
24089825_7.docx
Monitoring results shall be submitted to the Manager, Environmental Regulation,
Wellington Regional Council on a monthly basis until all groundwater extraction for
piling construction is complete.
Land Use Consent (for pile construction and ground strengthening)
LUC.9 A bore log will be submitted to the consent authority once construction of that bore
has been completed within one month of completion of construction of the bore.
Discharge to permit (land) – Conditions
DP.1 (a) Any construction affected groundwater (displaced whilst constructing
piles) shall be collected and shall only be discharged to the reticulated
stormwater system if it:
• Has a ph value of no greater than 8.5
• Has a suspended sediment concentration no more than 10% higher
than background levels 50 grams per cubic metre or 50 milligrams
per litre50mg/L;
(b) Following reasonable mixing (the bound of reasonable mixing zone shall
be a 50m radius extending in any direction from the stormwater outfall)
the discharge shall will not cause:
• The production of any conspicuous oil or grease films, or scum, or
foams or floatable material;
• Cause an emission of an objectionable odour; and
• Any conspicuous change in colour or visual clarity in the receiving
environment.
• Any significant adverse effects on aquatic life.
DP.2 The Consent Holder shall construct and maintain all erosion and sediment control
measures so that they operate and perform as intended in the certified
Construction Environmental Management Plan and in accordance with the WRC
Erosion and Sediment Control Guidelines and the NZTA Draft Erosion and
Sediment Control Standard for State Highway Infrastructure. The Consent Holder
shall carry out inspections, at a minimum frequency of weekly, of all working areas
of the site, in order to ensure they are well maintained and that discharge control
devices remain effective.
Page 23
24089825_7.docx
Designation Conditions
DC.22 A CTMP shall be prepared in consultation with WRC (in respect of the public
transport elements) which is generally in accordance with the proposed CTMP
submitted with the NOR and shall include, but need not be limited to:
(a) A statement of standards that will be adhered to in the planning and
implementation of Temporary Traffic Management (TTM) during the
project;
(b) Objectives and issues for the delivery of TTM;
(c) Construction sequencing and restrictions to be placed on TTM activities;
(d) Details of proposed accesses to construction areas from the road
network;
(e) The potential effects on the detour routes selected and how these will be
managed to seek to ensure safety for all road users;
(f) Measures to maintain, where practicable, existing vehicle access to
adjacent properties and business;
(g) Details of the measures that will be implemented to screen construction
activity from passing traffic;
(h) A process for the development, submission and approval of Site Specific
Transport Management Plans (and when SSTMPs are required); and,
(i) Roles and responsibilities of key Traffic Management personnel (and/or
governance group).
(j) The measures that will be undertaken by the Requiring Authority to
communicate traffic management measures to affected road users and
stakeholders including specific liaison and recording of outcomes with
the WRC Public Transport Group.; and
(k) Details of how WRC’s Public Transport Group’s comments and
recommendation have been incorporated into the plan.
DC.25 The SSTMP shall be prepared in consultation with WRC (in respect of the public
transport elements) and shall describe the measures that will be taken to manage
the traffic effects associated with the construction of specific parts of the Project
prior to construction of the relevant part(s) of the Project commencing. In
particular SSTMPs shall describe:
(a) How it is consistent with the CTMP;
(b) If relevant, how it is consistent with the principles of CPTED;
(c) Temporary traffic management measures required to manage effects on
road users during proposed working hours;
Page 24
24089825_7.docx
(d) Delay calculations associated with the proposed closure/s and detour
routes;
(e) The capacity of any proposed detour route(s) and their ability to carry the
additional traffic volumes, including diverted bus services, and any
known safety issues associated with the detour route(s), including any
mitigation measures the Requiring Authority proposes to put in place to
address any identified safety issues;
(f) Individual traffic management plans for intersections of the proposed
Project with arterial roads;
(g) Measures to maintain, where practicable, existing vehicle access to
adjacent properties and businesses;
(h) Measures to maintain, where practicable, safe and clearly identified
pedestrian and cyclist access on roads and footpaths adjacent to the
construction works. Where detours are necessary to provide such
access the Requiring Authority shall provide for the shortest and most
convenient detours, which it is reasonably practicable to provide, having
regard to CPTED issues and safety;
(i) Any proposed temporary changes in speed limit;
(j) Provision for safe and efficient access of construction vehicles to and
from construction site(s); and,
(k) The measures that will be undertaken by the Requiring Authority to
communicate traffic management measures to affected road users and
stakeholders including specific liaison and recording of outcomes with
the WRC Public Transport Group.; and
(l) Details of how WRC’s Public Transport Group’s comments and
recommendation have been incorporated into the plan.
Prior to the submission of the SSTMP(s) for certification, the draft SSTMP(s) shall
undergo an independent safety and traffic operational review, and a CPTED
review by a suitably qualified independent person. Feedback received in this
review process shall be provided to the Compliance Officer at the time the SSTMP
is submitted for certification, along with a clear explanation of where any
comments have not been incorporated in the SSTMP and the reasons why.
Exact wording to be determined subject to recommendations by Transport Expert
Witnesses
DC.## The Requiring Authority shall prepare in collaboration with WCC and WRC (in
respect of the public transport elements) a Network Integration Plan (NIP) for the
Page 25
24089825_7.docx
Project, or relevant Project phases, to demonstrate how the Project integrates with
the existing local road network and with future improvements (identified in the
Public Transport Spine Study).
a) The NIP shall include details of proposed physical works at the interface
between the State highway and the local road network, and shall
address such matters as
continuous dedicated public transport lanes around the Basin
Reserve,
signal priority for public transport vehicles and provisions for buses,
to ensure forecast travel times and improved reliability are
achievable,
Changes to bus stop location and design to accommodate longer
vehicles/additional stop infrastructure.
b) The objectives of the NIP shall include integration of the PT Spine Study
options into the overall scheme and design
c) The Requiring Authority shall submit the NIP for certification to the
Manager at least 20 working days prior to commencement of
construction of the Project
d) Works identified in the NIP which are the responsibility of the NZTA,
including any work associated with the relocation of bus stops, will be
undertaken at the time the Project is constructed.
DC.38. Erosion and sediment control measures shall be implemented throughout the
construction phase of the Project in accordance with the CEMP. All works shall be
installed and maintained in accordance with WRC Erosion and Sediment Control
Guidelines and the NZTA Draft Erosion and Sediment Control Standard for State
Highway Infrastructure.