basis risk of hedging
DESCRIPTION
Basis risk of hedging. There is basis risk in two directions. Power production affected by factors other than wind. There will be a payout although it would not be possible to produce. 1. Monthly payouts during course of time. Implicit monthly production (based on Index) - PowerPoint PPT PresentationTRANSCRIPT
1
Basis risk of hedging
1
Insufficient wind Sufficient wind Excessive wind
Turbine operation normal
=> Yes Payout No payout Payout
=> No Payout No payout Payout
Transmission constraint
=> Yes Payout No payout Payout
=> No Payout No payout Payout
There is basis risk in two directions
Power production affected by factors other than wind
There will be a payout although it would not be possible to produce
2
Monthly payouts during course of time
Implicit monthly production (based on Index) 1) Above red line (Put Strike) monthly production is sufficient and there will be no payout
2) Between red and green lines - difference between red line (Put Strike) and green line (Production) will be paid out (shortfall x feed-in tariff)
3) Below the blue line (Exit) there is no further payout (Maximum payout reached)
Pro
duct
ion (
MW
h)
Jan
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
PutStrike
Exit
Production > Put Strike = No Payout
Production < Put Strike = Payout
No additional payout below blue line (maximum payout reached)
Alternative: Put-Option on Annual Production
Annual Production
Payout
Put Strike
0Option Premium
Option payoff
02,0004,0006,0008,000
10,00012,00014,00016,00018,00020,000
Exit
Premium
Dec
Put Strike
Put Limit
3
Testing the value of the hedge
Assumptions
Project Size 102 MW
Wind Resource
P50
2,472 Eqv. Hours / Year
P75
2,226 Eqv. Hours / Year
P90
2,039 Eqv. Hours / Year
P95
1,927 Eqv. Hours / YearProject Costs 117.30 EUR MM
Project Life
20 YearsTotal Costs 124.45 EUR MM
Leverage
75:25
Total Debt
93.33 EUR MM
Debt Tenor
17 Years
Margin 400
Basis Points (above EURIBOR)
Wind farm developed by mid-size sponsor in Spain.
‑ The project is located in a reasonable spot (good wind resource)
‑ Costs are in line with market conditions
ResultsP50Equity IRR 13.48%NPV @ 8% 22.508EUR MMMinimum DSCR 1.53x
P75Equity IRR 10.71%NPV @ 8% 11.227EUR MMMinimum DSCR 1.41x
P95Equity IRR 7.43%NPV @ 8% -2.349EUR MMMinimum DSCR 1.26x
4
Even if only benefits is intangible one of reducing risk of financial distress, costs is relatively low.
Impact of adding Wind Protection on the project's economics
ResultsP50Equity IRR 13.17%NPV @ 8% 21.514EUR MMMinimum DSCR 1.50x
P75Equity IRR 10.44%NPV @ 8% 10.236EUR MMMinimum DSCR 1.38xEven with the associated costs of wind protection in place, the economics of the project are not greatly affected.
Put Option on Wind Power Index• Strike at (P75)• 5 years• 10 EUR MM limit• Premium 1.5 EUR MM1
Buying wind protection
Wind protection in place 75% / 25%
ResultsP50Equity IRR 13.48%NPV @ 8% 22.508EUR MMMinimum DSCR 1.53x
P75Equity IRR 10.71%NPV @ 8% 11.227EUR MMMinimum DSCR 1.41x
No protection in place 75% / 25%
1 Rough estimation
5
Potential benefits of Wind Protection.
ResultsP50Equity IRR 14.87%NPV @ 8% 24.362EUR MMMinimum DSCR 1.41x
P75Equity IRR 11.63%NPV @ 8% 13.058EUR MMMinimum DSCR 1.30x
Wind protection in place + change in Capital Structure 80:20
ResultsP50Equity IRR 13.81%NPV @ 8% 23.776EUR MMMinimum DSCR 1.54x
P75Equity IRR 11.03%NPV @ 8% 12.480EUR MMMinimum DSCR 1.42x
Wind protection in place + reduction in margin of 50 basis points
By placing a floor on the production, the debt capacity of the project increases; lowering capital costs and improving the economics of the project.
With protection in place, lenders may also reduce spreads.
6
Protection creates value across the capital structure
NPV (8%) Before protection
Leverage Lower margins Debt reserve reduction
Total15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
22.5
1.85
2.42
0.25
EUR MM
Totalbenefit
4.52