baseline 2 update
DESCRIPTION
Baseline 2 Update. Jeyant Tamby. PRS, TAC and BoD play a key role in the Nodal Change process…. Roles in the Nodal Change Process. NPRRs & Nodal SCRs. White Papers, Change Items and other design and implementation decisions. - PowerPoint PPT PresentationTRANSCRIPT
June 21st, 2007
PRS Meeting
Baseline 2 Update
Jeyant Tamby
2
PRS, TAC and BoD play a key role in the Nodal Change process…
Roles in the Nodal Change Process
NPRRs & Nodal SCRs White Papers, Change Items and other design and
implementation decisions
Approval process is recommendations by PRS
and TAC to the BoD for approval
Approval process is internal to the Nodal Program and subject
to approval by the Executive Director*.
* On selected items, TPTF to endorse essentiality for ‘Go-Live’
3
Summary of June 12th meeting …
• Summary facts from Baseline 1– 12 Groups– 59 Items– 43 NPRRs– Total impact of $5M - $6M
• Key decisions– Recommend IA’s of Baseline 1 NPRRs to TAC
• Action items for the Program– Define Baseline 2, determine related impact analysis and
present to PRS on 6/21/2007 for recommendation to TAC– Splitting costs of NPRR 049. The updated costs are –
• NPRR 049:$100K - $250K
• CI 67:$0.5M - $1.0 M
4
Getting to Baseline 2…
• The Challenge– Draft 9 NPRRs for posting– Share draft information with vendors for rapid cost and schedule
impact assessments– Limited time available to consolidate and integrate information
• Outcome– New NPRRs were not posted 7 days in advance– Preliminary “Impact Assessment” on 11 NPRRs– Full “Impact Assessment” on 18 NPRRs
55
Texas Nodal Program Update
In Baseline 2, PUC requirements is a new source in addition to all the other sources established in Baseline 1…
Initial Nodal Protocols
2004 - 2005
Zonal Protocols
April 2004
PUCT approved Nodal Protocols Baseline 0
May 2006
Nodal Protocols Baseline 2 June/July
2007
Zonal PRRs
April 2005
Source #1 Synchronization
(by ERCOT & TPTF)
2005 - 2007
Source #7 PUC Requirements
Source #5 Consistency, Integration &
Design Authority (IDA) White Papers
Source #6 Market Participant
Requirements
Source #3 Requirements Development
Q1 2006 - 2007
Progression of Nodal Protocols
Sources of change
6 Items
16 Items
3 Items
6 Items
5 Items
Total Items in Baseline 2 – 36•NPRRs – 29•IDA White Papers – 6•Change Items - 1
66
Texas Nodal Program Update
Requested action items for today…
1. Recommend Language on NPRRs in Baseline 2 to TAC
2. Recommend Impact Analysis of NPRRs in Baseline 2 to TAC
Baseline 2 NPRRs
11
29 NPRRs
18
Preliminary Impact Assessment (Raw data from vendors)
Impact Assessment complete including:
• Justification for change
• Justification for cost
Key
For all items in Baselines 1 & 2, the Program will partner with the vendors to minimize cost and schedule impacts
77
Texas Nodal Program Update
Cost summary for all the 29 NPRRs
Category Cost ($’ 000s)
Source 1 $250K-$500K
Source 2 -
Source 3 $100K-$250K
Source 4 -
Source 5 -
Source 6 $100K-$250K
Source 7 $500K - $1M
Cost Impact Level
Number of Items**
<$0 9
<$50K 8
$50K-$100K 4
$100K-$250K 6
$250K-$500K 1
$500K - $1M 1
Total Est. Cost =$2M-$3M
June 21st, 2007
PRS Meeting
Appendix – NPRRs with Impact Assessment Complete
99
Texas Nodal Program UpdateJune 21, 2007
NPRR 20 - ERCOT Nodal Implementation Surcharge
NPRR No. 20
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None
EDS (1/2/3/4) EDS4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR documents how ERCOT shall calculate the
Nodal Implementation Surcharge (NIS) to comply with the
Final Order issued in Public Utility Commission of Texas
(PUCT) Docket No. 32686, Application of the Electric
Reliability Council of Texas for Approval of a Nodal Market
Implementation Surcharge and Request for Interim Relief, to
fund implementation of the nodal market redesign
Cost Drivers: S&B: The proposed solution is to modify the S&B rate
language code to implement the algorithm as defined in
protocol language within NPRR 20. The cost is based on
time and effort required to code the algorithm in the
settlements and billing modules. In addition this includes
time for additional documentation, testing, etc. Not
previously defined in requirements or May 2006 Protocols
EIP: One additional low complexity info flow from S&B to
CMM (Nodal implementation surcharge amount). New info
flow required to support passing surcharge to CMM from
S&B for collateral management.
Risks: None
1010
Texas Nodal Program Update
NPRR 26 - Nodal Implementation Surcharge Verifiable Costs
NPRR No. 26
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None
EDS (1/2/3/4) EDS4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR allows a resource owner an opportunity to
recover the nodal implementation surcharge if and when the
resource owner submits verifiable cost information for any
services provided for reliability.
Cost Drivers: S&B: This has no impact, since it is only a change to a
manual business process.Assumptions:
There are no changes to the equations. This NPRR requires that the surcharge cost be accepted as a valid Verifiable Cost.
The surcharge (in $/MWh), if submitted by the QSE for a Resource, will be included in their Verifiable Costs. [Minimum Energy Costs and verifiable variable O&M costs.]
The increase (due to the inclusion of this cost) in the Minimum Energy Offer Caps for offers submitted into the DAM is acceptable.
The increase (due to the inclusion of this cost) in the amount reimbursed to an RMR owner for all the generation by the RMR Resource is acceptable. (Even when the RMR Resource is selected in the DAM.)
The increase (due to the inclusion of this cost) in the Minimum Energy Cost for a Resource is acceptable and the use of this increased Minimum Energy Cost in RUC settlement is acceptable. (Even for QSE claw-back hours).
The increase (due to the inclusion of this cost) to the Mitigated Offer Caps for those Resources that have submitted verifiable costs above the 14.5 or 10 heat rate times FIP or FOP is acceptable.
Risks: None
June 21, 2007
1111
Texas Nodal Program Update
NPRR 37 - Conforming Section 13 to Nodal Format and Changing Frequency of Transmission Loss Base Case Calculations
NPRR No. 37
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None
EDS (1/2/3/4) EDS 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR provides changes to the frequency of
transmission loss base cases calculations and conforms
Protocol Section 13 to the Nodal Protocol format.
Cost Drivers: COMS: Modify existing data aggregation code to
perform
transmission losses base case calculations monthly. The
cost is based on time and effort required to code the
algorithm in the data aggregation modules. In addition
this includes time for additional documentation, testing,
etc. Not previously defined in requirements or May 2006
ProtocolsRisks: None
June 21, 2007
1212
Texas Nodal Program Update
NPRR 40 - Synchronization of Emergency Electric Curtailment Plan (EECP) Event Realignment
NPRR No. 40
Characteristics
Total $ impact range $100K-$250K
Total schedule impact (weeks) None
EDS (1/2/3/4) EDS 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR incorporates relevant language from: PRR682, EECP Event Realignment, which was
approved by the ERCOT Board on November 14, 2006.
Cost Drivers: MMS:ABB assumes that this NPRR is only related to
EMS. No impact to MMSEMS: Vendor response not available yet. Costs based
on
team assessments.COMS: Registration provides the parameters and
MMS/EMS uses them to do their calculations.EIP: new info flows required to support net dependable
capability requirements; assumed that net dependable
capability would move from REG to MMS and that MMS
will be the system of record and that EMS will perform the
EECP processINT: Additional integration testing to reflect new
information flows. Risks: None
June 21, 2007
1313
Texas Nodal Program Update
NPRR 45 – Wind Power Forecasting
NPRR No. 45
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N)PRS to decide
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR adds definitions for terms used in more than one
section and describes the process for developing the 80%
confidence level forecast for wind-power generators
Cost Drivers: EMS: This is a clarification NPRR. This NPRR does not
introduce any additional requirements except TEWPF
calculation and posting. EMS team estimates no impact.
Risks: None
June 21, 2007
1414
Texas Nodal Program Update
NPRR 54 - Update of Nodal Protocols to Comply with NERC Name Change – Companion to PRR711
NPRR No. 54
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR updates Nodal Protocol References to reflect the
recent NERC name change from North American Electric
Reliability Council to North American Electric Reliability
Corporation.
Cost Drivers: None Risks: None
June 21, 2007
1515
Texas Nodal Program Update
NPRR 55 - Correction of Voltage Support QSE Total Bill Determinants
NPRR No. 55
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This Nodal Protocol Revision Request (NPRR) corrects
Voltage Support QSE Total bill determinants and their
calculations for the purpose of breaking out the Voltage
Support charge types on the settlement statement.
Cost Drivers: S&B: The proposed solution is to modify the S&B rate
language code to implement the algorithm as defined in
protocol language within NPRR 55. The cost is based on
time and effort required to code the algorithm in the
settlements and billing modules. In addition this includes
time for additional documentation, testing, etc. Not
previously defined in requirements or May 2006 Protocols. Risks: None
June 21, 2007
1616
Texas Nodal Program Update
NPRR 58 - Clarification of Standard Form Market Participant Agreement
NPRR No. 58
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR removes discrepancies between Section 16,
Registration and Qualification of MPs, and Section 22 –
former Attachment H, now Attachment B, Standard Form
Market Participant Agreement. The primary change is
removing legacy references to individual Agreements that
have since been consolidated into a single Standard Form
Market Participant Agreement.
Cost Drivers: None Risks: None
June 21, 2007
1717
Texas Nodal Program Update
NPRR 59 - Reconfiguring the Annual CRR Auction
NPRR No. 59
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR reconfigures the annual Congestion Revenue
Right (CRR) Auction from a 24-month simultaneous
optimization of three Time Of Use (TOU) blocks to separate
optimizations for each TOU block for each year.
Cost Drivers: Separate optimizations for each Time Of Use (TOU) for
each year (year one and year two) The annual CRR
Auction can now be solved in a reasonable amount of
time with available software and hardware. Risks:
There is a greater risk to CRR if this is not
implemented.
June 21, 2007
1818
Texas Nodal Program Update
NPRR 62 – Constraint Competitiveness Test
NPRR No. 62
Characteristics
Total $ impact range $50K-$100K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR provides clarification on the process for
determining competitive constraints as defined in Section
3.19, Constraint Competitiveness Test (CCT).
Cost Drivers:MMS: MMS requires NMMS to provide new Classes,
attributes and associations to implement this NPRR. The
changes are mainly related to ERCOT's own processes,
rather than to the CCT function. The changes simplified
certain logic within the engine for CCT. No changes
required to Test Procedures 1 and 2 for CCT.NMMS: This NPRR clarified the CCT requirements in
May
2007. As the clarifications rippled through MMS it was
determined that modifications to existing CIM was
required. New validation code will be necessary to ensure
data management. MIS:Assumes the files will be posted to MIR, with
appropriate metadata, where MIS will retrieve them. No
cost impact. Risks: None
June 21, 2007
1919
Texas Nodal Program Update
NPRR 63 – Electrical Bus Clarification
NPRR No. 63
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR provides clarification on designation of
Electrical Buses within the Network Operations Model that
will meet the needs of the Nodal Market.
Cost Drivers: None Risks: None
June 21, 2007
2020
Texas Nodal Program Update
NPRR 66 – Synchronization of PRR 698, Remove Default QSE Provisions
NPRR No. 66
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR incorporates relevant language from: PRR698, Remove Default QSE Provisions, which was
approved by the ERCOT Board of Directors on 12/12/06.
It revises provisions for the Emergency and Virtual Qualified Scheduling Entity (QSE) to allow them to provide for Resource Entities and Load Serving Entities (LSEs) in the event that their QSEs are suspended.
It removes the Default QSE concept, including all references to a Default QSE.
Cost Drivers: None Risks: None
June 21, 2007
2121
Texas Nodal Program Update
NPRR 68 – Settlement Clarifications to Startup Eligibility, Decommitment Payments and Corrections to RUC Formulas
NPRR No. 68
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR : Clarifies the sections that dealing with whether a
Resource is Eligible for startup compensation in the Day-Ahead and Reliability Unit Commitment (RUC) Make-Whole payment calculations
Modifies the definition of the hours used in calculating the RUC Decommitment Payment in Section 5.7.3.
Corrects the parentheses in three formulas in Section 5.7.1.1
Cost Drivers: S&B: The proposed solution is to modify the S&B rate
language code to implement the algorithm as defined in
protocol language within NPRR 68. The cost is based on
time and effort required to code the algorithm in the
settlements and billing modules. In addition this includes
time for additional documentation, testing, etc.
NPRR slightly modifies language in May 2006 Protocols. Risks: None
June 21, 2007
2222
Texas Nodal Program Update
NPRR 69 - Changes to SURAMP
NPRR No. 69
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None*
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR revises the Security Constrained Economic
Dispatch (SCED) Up Ramp Rate (SURAMP) formulation.
This change removes reserving part of Ramp Rate for
Responsive Reserve Service (RRS) deployment by Load
Frequency Control (LFC)
Cost Drivers: MMS: Change SURAMP formulaEMS:A formula change to use the SURAMP formula in
Resource Limit Calculator (No vendor estimates available.
Team assessments) Risks: None
June 21, 2007
2323
Texas Nodal Program Update
NPRR 072 – Day-Ahead RMR Settlement Clarifications
NPRR No. 072
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR modifies the Day-Ahead Make-Whole Payment
calculation such that an Amount data cut is not calculated
for an eligible Reliability Must Run (RMR) Unit; consistent
with the Protocol requirement prohibiting RMR Units from
receiving payment through the Day-Ahead Make Whole
Payment. DAMWAMT will not be calculated for RMR Units DAMWRMRREV will be calculated for RMR Units
Cost Drivers: S&B: The proposed solution is to modify the S&B rate
language in order to implement the changes as defined in
NPRR 72. The cost is based on the time and effort
required to modify the code in the settlements and billing
modules. In addition this includes time for additional
documentation, testing, etc. The NPRR is a slight change
to the May 2006 Protocols. Risks: None
June 21, 2007
2424
Texas Nodal Program Update
NPRR 073 – Update of Protocol 6 Due to Revisions Found When Processing Requirements, Use Cases and CSDs
NPRR No. 073
Characteristics
Total $ impact range <$50K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR revises Sections 6.6 and 6.7 to align them to the
Requirements, Use Cases and Conceptual System Designs
(CSDs).
Cost Drivers: NoneRisks: None
June 21, 2007
2525
Texas Nodal Program Update
NPRR075 - Settlements Clean-up
NPRR No. 075
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4)
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR: Clarifies the contents of the various invoices. Clarifies the payment dates for the various invoices. Corrects the list of DAM Settlement Charge Types. Specifies contents and timing of RTM Uplift Invoices Corrects the RTAML definition for the ERCOT System
Administrative Charge
Cost Drivers: None Risks: None
June 21, 2007
June 21st, 2007
PRS Meeting
Appendix – NPRRs with Impact Assessment not complete
2727
Texas Nodal Program Update
NPRR 24 - Synchronization of PRRs 627 and 640
NPRR No. 24
Characteristics
Total $ impact range $100K-$250K
Total schedule impact (weeks) None
EDS (1/2/3/4)
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR incorporates relevant language from: PRR627, RMR Transmission Issues and RMR Contract
Extension, that was approved by the Board on 2/21/06; and
PRR640, Update Provisions for Capacity and Energy Payments for RMR Service and Add a New Standard Form Agreement for Synchronous Service, that was approved by the Board on 3/21/06
Cost Drivers: Risks:
June 21, 2007
2828
Texas Nodal Program Update
NPRR 36 - Market Operations Test Environment (MOTE) in the Nodal Market
NPRR No. 36
Characteristics
Total $ impact range $50K-$100K
Total schedule impact (weeks)
EDS (1/2/3/4)6 months post
“Go-Live”
Essential for Go-Live (E/D/N) D
Detail
Item description: Cost Drivers / Risks / Dependencies:
In the nodal Market, Transmission Service Providers (TSPs)
need access to an environment of the ERCOT EMS where
the following are available for their review and analysis Network operations model, Results of the real -time State Estimator (within 5
minutes of the real time solution) including Contingency Analysis.
MOTE serves as a tool to validate the integrity of the ERCOT
Network Operations model, and to perform studies that
facilitate better coordination of network operations between
the TSPs and ERCOT. TSP need to continue to have a tool
like MOTE in the Nodal Market. The new MOTE should have
all the functionality that the current MOTE offers
Cost Drivers:Includes the purchase, installation, base operating
system
of 8 windows server servers and the allocation of 2 virtual
Unix servers to support the environment. Assumptions
are: Sufficient capacity exists in the data centers to
install the equipment. Sufficient unallocated capacity exists in the virtual
Unix environments to allocate the two partitions necessary to support the environment
Licensing costs for the application software to be installed in the environment are excluded from the $100,000 estimated impact.
Risks:
June 21, 2007
2929
Texas Nodal Program Update
NPRR 53 - Creation of a New Trading Hub at Venus Switching Station
NPRR No. 53
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N)PRS to decide
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR creates a new trading hub at Venus Switching
Station.
Cost Drivers: Assumption: The cost is dependent on approval of
NPRR
060 (Hub clarification). The new hub should be included in
the ERCOT hub average pricing calculation. Risks:
June 21, 2007
3030
Texas Nodal Program Update
NPRR 57 - Posting Requirements Pursuant PUC Subst. R. 25.505
NPRR No. 57
Characteristics
Total $ impact range$500K - $1.0M
Total schedule impact (weeks)
EDS (1/2/3/4)
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR implements posting requirements outlined in
new P.U.C. SUBST. R. 25.505, Resource Adequacy in the
Electric Reliability of Texas Power Region.
Cost Drivers: MMS: Posting and Calculation of Generation Capacity
and
Load CapacityEIP: 1 additional medium & 1 additional high complexity
info flows from EMS to MIS (hourly generating resource
capacity & load resource capacity for rolling 1 week) and
Planning to MIS (weekly peak generating resource
capacity & load resource capacity for rolling three years).
New info flows to support posting of requirements to
comply with PUCT order (PUC Subst. R. 25.505)MIS – Assumes the files will be posted to MIR, with
appropriate metadata, where MIS will retrieve them.INT: More integration testing to reflect the new
information flows Risks:
June 21, 2007
3131
Texas Nodal Program Update
NPRR 60 – Hub Clarification
NPRR No. 60
Characteristics
Total $ impact range $0
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR clarifies the concept of “Hub Bus” allowing for
direct assignment of Electrical Buses to a Hub and clarifies
the number of Hub Buses in a Hub based on operating
model Electrical Bus configuration.
Cost Drivers: Risks:
June 21, 2007
3232
Texas Nodal Program Update
NPRR 61 – Scarcity Pricing Mechanism (Companion to PRR709)
NPRR No. 61
Characteristics
Total $ impact range $100K-$250K
Total schedule impact (weeks)
EDS (1/2/3/4)
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR revises the ERCOT Nodal Protocols to provide
for a scarcity pricing mechanism as required by subsection
(g) of P.U.C. SUBST. R. 25.505, Resource Adequacy in the
Electric Reliability Council of Texas Power Region.
Cost Drivers: MMS:
SWCAP part -MI changes: Remove external global parameters for SWCAP. Create internal SWCAP global parameters which is to be populated when settlements passes a new SWCAP.“ change external global parameters for SWCAP to internal procedure to update SWCAP
MA changes: MA needs to read the SWCAP value from MI. SCED needs to use the dynamic SWCAP for proxy curve creation.
Scarcity Pricing Mechanism part: This part is completed new. ABB assumes that this is Settlement's responsibility. No impact to MMS.
EIP: 3 additional low complexity info flows from S&B to
MMS, MIS (system-wide offer cap) and MMS to MIS
(PNM). New info flows to support scarcity pricing
mechanism requirementsMIS: Assumes the files will be posted to MIR, with
appropriate metadata, where MIS will retrieve them.
Risks:
June 21, 2007
3333
Texas Nodal Program Update
NPRR 64 – Modeling of Generic Transmission Constraints
NPRR No. 64
Characteristics
Total $ impact range $250K-$500K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR provides for the definition of and posting of
Generic Transmission Limits (GTLs) in Network Operations
Modeling requirements.
Cost Drivers: MMS: The description of generic transmission constraints in this NPRR
is general and does not contain sufficient information for evaluation.ABB assumes that what this NPRR asks for is what ABB and ERCOT have already agreed. This cost is for implementing the agreed functionality. ABB's analysis also assumes that this NPRR's requirement of posting generic transmission constraints to MIS is to be done by EMS. Assumption is EMS will provide the Generic Constraint data (also called Non-thermal constraints) in a specific interface table on an hourly basis.NMMS: Although the Nodal Protocol descriptions of Network Security Analysis and Congestion Revenue Rights (CRR) Auctions reference the use of “generic” transmission constraints, Section 3.10, Network Operations Modeling and Telemetry does not provide for their definition and for limits on their use. This clarification NPRR was not proposed until May 2007.EIP: New info flows to support addition of GTL constraints
Risks:
June 21, 2007
3434
Texas Nodal Program Update
NPRR 65 – Synchronization of PRR647, Gross and Net MW/Mvar Data Reporting
NPRR No. 65
Characteristics
Total $ impact range $100K-$250K
Total schedule impact (weeks)
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR incorporates relevant language from: PRR647, Gross and Net MW/Mvar Data Reporting, that
was approved by the ERCOT Board (Board) on 1/16/07 NPRR035, Nodal Protocol Clarifications Required For
Net Metering Provisions
Cost Drivers: MMS: Gross/Net MW/MVarNMMS: CIM model will require extensions to provide for
formula distribution. Coordination with all vendors will be
required as this has not been delineated in previous
meetings to the extent that design could occur. This
request was not in Protocols or any other supporting
document.
Risks:
June 21, 2007
3535
Texas Nodal Program Update
NPRR 67 – Modeling of Private Use Networks
NPRR No. 67
Characteristics
Total $ impact range $100K-$250K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This Nodal Protocol Revision Request (NPRR) provides a
mechanism for ERCOT to model generation located within a
Private Use Network.
Cost Drivers: MMS: ABB assumes that no work has to be performed
by
ABB, and all work will be performed by ERCOT.EMS: Potential Areas of Change: CIM Interface, Model
Validation; Load Schedule Adaptation; Load Distribution;
Load Forecast Inputs (No vendor estimates, team
assessment)NMMS: Create Private Use Network classes, attributes,
and associations. Create validation code to effectively
manage new entity. Use Network was recently added to Protocols.
EIP: 1 additional low complexity info flows from
EMS to MMS (private use generator flag) new
information flows required to allow identification and
modeling of privately used generators Risks:
June 21, 2007
3636
Texas Nodal Program Update
NPRR 70 - Changes to DAM clearing start time allocation of McCamey Flowgate Rights in Day-Ahead
NPRR No. 70
Characteristics
Total $ impact range $50K-$100K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This Nodal Protocol Revision Request (NPRR) changes the
requirement for DAM clearing to start at 1000 in the Day-
Ahead Market to allow time for submission validations. This
NPRR incorporates the TPTF discussions for Allocation of
McCamey Flowgate Rights (MCFRIs) in Day-Ahead.
Cost Drivers: MMS: MI changes: Synchronization of DAM and
MI.Change to support up to 10:00 submission. Change
DAM and MI formula. MA changes: This requires DAM to
be executed after Market close and MI has completed
validation. Currently MA already checks the MI market
close flag. MA needs to check additional flag.
Risks: This NPRR is required by NPRR 005.
June 21, 2007
3737
Texas Nodal Program Update
NPRR 071 – Trade Validation by Matching Identical Trade Submissions
NPRR No. 071
Characteristics
Total $ impact range $100K-$250K
Total schedule impact (weeks) None
EDS (1/2/3/4) 4
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR incorporates the TPTF determination regarding
Trade confirmation.
Cost Drivers: MMS: MI & Interface changes: Support for same buying
and selling QS trades. MA SCED changes:retrieve energy
trades for a DSR QSE as both selling and buying parties.
Use this amount in the MA SCED output schedule
validation. ABB assumes that even though, it is not
specifically written in the NPRR texts, ABB assumes that
the Energy Trades with the same buying and selling QSE
will be used to indicate the net energy purchase/sales
between QSE's DSR generators and DSR loads.
therefore, the amount of energy trade with the same
buying and selling QSE will be used in MA SCED real
time Output Schedule validation.
Risks:
June 21, 2007
3838
Texas Nodal Program Update
NPRR 074 – Revisions to Monitoring and Qualification Tests in Section 8, Performance Monitoring and Compliance
NPRR No. 074
Characteristics
Total $ impact range $50K-$100K
Total schedule impact (weeks)
EDS (1/2/3/4)
Essential for Go-Live (E/D/N) E
Detail
Item description: Cost Drivers / Risks / Dependencies:
This NPRR makes the testing and compliance requirements
consistent with NPRR049, Generation Subsystem Changes
to Incorporate Approved Whitepapers, and the white papers
“Generation Resource Responsive Reserve Deployment
and Recall” and “Non-Spin Deployment Notification and
Availability” approved by TPTF located at
http://nodal.ercot.com/docs/pd/mms/index.html#oth.
Cost Drivers: EMS: LFC Ancillary Service Monitoring data collection
and
Calculations. (No vendor estimates available. Team
assessments) Risks:
June 21, 2007