attracting and maintaining institutional investment: offshore wind
DESCRIPTION
Slides from Offshore Wind workshop at the Eversheds event: Attracting and Maintaining Institutional Investment in Renewable Energy - 2nd July 2012TRANSCRIPT
Natural Power Consultants LTD Eversheds, Institutional Investor workshop 2nd July 2012
Tuesday, July 03, 2012 2
TABLE OF CONTENTS
1. Natural Power Consultants
2. Capex comparative analysis
3. Offshore WTG technology
4. Foundations
5. Cables
6. Installation
Tuesday, July 03, 2012 3
Renewable energy consultancy, management services and product innovation. Onshore wind, Offshore wind, Wave & Tidal and Biomass energy Founded in 1996 300 Employees 14 Offices 7 Countries
• Energy yield analysis and technical risk reduction
• Project design, ecology surveys, EIA and permitting management
• Construction, ground surveys and contracts management
• Operational A&M and performance analysis
• 360o project due diligence
• Owner and Lender’s Engineering & Technical Advisors
NATURAL POWER CONSULTANTS
Tuesday, July 03, 2012 4
CAPEX COMPARATIVE ANALYSIS1
2.76
3.05 3.40 3.46 3.42 3.30
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
2006 2007 2008 2009 2010 2011
M£/MW
Natural Power data base of 49 OWF, in 7 European countries
1. Capital expenditures have been collected from our confidential data base, reinforced with trade journals, company websites, public data bases and academic and government reports
• From 2006 to 2009 Capex (M£/MW) has grown, the increase has been
driven by cables and foundations costs, in 2010 Capex started to come down • Key factors: distance from the shore, supply bottlenecks, raw materials, installation costs, cable routes
Tuesday, July 03, 2012 5
OFFSHORE WIND TURBINE TECHNOLOGY
After 3-4 MW before 2009, the technology is being oriented to 5-6 MW turbines
Suppliers are now working on: Reducing the weight with less components (DD or semi-integrated solutions), in order to ease foundation design,
installation and maintenance Larger diameters (150-164 m) with same power output
Blades : Diameter is increasing from ac. 90 m (2009 ) to 164 m (2015) Higher bending moment due to larger rotor affects design of the substructure Blades suppliers are now mostly in-house (Siemens, Vestas, Repower, Areva)
Generator technology : Power output from 3-4 MW (2009) to 5-6 MW (2012-2014) Smooth transition from DFIG to DD generators (head mass reduction/power output management) Gearboxes tend to be removed to reduce maintenance and failures Use of permanent magnets leads to high risks on Neodymium supply chain
Tuesday, July 03, 2012 6
Market shares – Turbines suppliers % MW installed to date – source EWEA January 2012
Number of suppliers for the 6 MW+ will increase Areva, REpower are the only leaders with 5-6 MW
WTGs but with still a low track record Historical suppliers have delayed their entrance in this category: Siemens 6 MW focuses on a DD technology, diameters 120 -154m and 50% fewer parts than comparable geared WTG; serial production targeted for Q1 2015, Vestas V164-7.0 MW prototype has been postponed, the first turbine is scheduled for installation in 2013, with series production starting from 2015 New entrants in Europe (Alstom “pure torque” DD 6MW Halliade 150, Gamesa G128-5.0 MW) will be in competition with Asian suppliers (Golwind, Sinovel) Before new entrants will start to produce, the offshore WTG industry will remain a bottleneck in the supply chain
WTG SUPPLY AND INSTALLATION
Tuesday, July 03, 2012 7
Monopiles is the most installed typology of foundation Wind farms currently under construction show the same trend: monopiles maintaining an over 60% share Jackets and Tripods show similar shares (20% and 18% respectively) Currently, no gravity based foundations have been identified in the under construction pipeline. This structure is generally used in wind farms close to shore
Market shares – Foundations installed in 2011 % MW installed – source EWEA January 2012
OFFSHORE FOUNDATION
Tuesday, July 03, 2012 8
MONOPILES’ ISSUES
• Monopolie made for: soft seabed, up to medium water depth, up to medium WTG weight (e.g. the actual monopile designed to support 6.0MW WTG vary from 6.5m to 7m in diameter) • Grouted connection: 65% of all the monopile installed in UK is facing problems subjected to a complex state of stress • Installation (mechanical hammer vs drilling): insufficient wind industry experience to guarantee required pile verticality of <0.25° (bolted flange requirement) during driving operations. •Few players represent a bottle neck in the supply chain
Tuesday, July 03, 2012 9
FOUNDATIONS: NEW TRENDS
Emphasis on cost of fabrication: • use of materials • pre-assembled manufacturing process
Jacket Gravity Base
Emphasis on: • noise emission to avoid limitation during installation • transportation
Tuesday, July 03, 2012 10
OFFSHORE CABLE TECHNOLOGY
Copper price 2009 -2012
Main issues: • Cable Laying: regulation, and natural condition (e.g. salt
marsh) • Supply chain bottlenecks: reluctant cable makers to scale up manufacturing capacity • Scarcity of skilled personnel
0.53
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
0 50 100 150 200 250
Co
st in
M£
/Km
Ex Cable lenght in Km
Ex Cable Supply
Market Players
Market Average
0.20
0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0 50 100 150 200
Co
st in
M£
/Km
Array Cables Lenght in Km
Array Cable Supply
Market Players
Market Average
Tuesday, July 03, 2012 11
INSTALLATION
Latest trends: • Players are developing vessels (e.g. Nordic Yards), which
can install every type of foundations, towers, nacelles and turbines as a single unit • In order to reduce installation time and costs, the vessels are designed to deploy the whole wind turbine in an upright position
Tuesday, July 03, 2012 12
INSTALLATION RATE
Main observations: • No trend, scattered results
• Main drivers: weather and sea conditions, water depths, integration of services, cost reduction, crane capacity
5.7 4.8
0
2
4
6
8
10
0 50 100
Inst
. Rat
e (
day
s/W
TG)
N. of WTG
Offshore Wind Farm WTG Installation Rate
1 vessel
2 vessels
Average 1vessel
Average 2vessel
4.44
2.75
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
0 50 100
Inst
. Rat
e (
day
s/fo
un
dat
ion
)
N. of foundations
Offshore Wind Farm Foundation Installation Rate
1 vessel
2 vessels
AverageMopopile 1vessel
AverageMopopile 2vessels
Tuesday, July 03, 2012 13
THANK YOU FOR YOUR ATTENTION
Offshore Wind in UK –Funding Round 3June 27, 2012
2
Agenda
Funding requirement in UK
Conditions for investment
Funding sources
Utilities and other investors
Investor models
Conclusions
3
Siemens is market leader in offshore turbines with 2.5 GW installed, of which nearly 1 GW in UK
Lynn / Inner Dowsing, UK→ 54 x SWT-3.6-107 (2008)
Rhyl Flats, UK→ 25 x SWT-3.6-107 (2009)
Burbo Banks, UK→ 25 x SWT-3.6-107 (2007)
Frederikshavn, DK→ 1 x SWT-2.3-82 (2003)
Rødsand/Nysted, DK→ 72 x SWT-2.3-82 (2003)
Vindeby, DK→ 11 x 0.45 MW (1991)
Middelgrunden, DK→ 20 x SWT-2.0-76 (2000)
Samsø, DK→ 10 x SWT-2.3-82 (2002)
Rønland, DK→ 4 x SWT-2.3-93 (2002)
Horns Rev II, DK→ 91 x SWT-2.3-92 (2009)
Gunfleet Sands, UK→ 48 x SWT-3.6-107 (2009)
Hywind, NO→ 1 x SWT-2.3-82 (2009)
Lillgrund, SE→ 48 x SWT-2.3-93 (2007)
Rødsand II, DK→ 90 x SWT-2.3-93 (2010)
Pori, FIN→ 1 x SWT-2.3-101 (2010)
Source: SWP
Baltic I, DE→ 21 x SWT-2.3-93 (2010)
Walney, UK→ 51 x SWT-3.6-107→ 51 x SWT-3.6-120
4
Borkum Riffgat, DE→ 30 x SWT-3.6-107
Many projects to come, some with Siemens equity
London Array, UK→ 175 SWT-3.6-120
Sheringham Shoal, UK→ 88 x SWT-3.6-107
Greater Gabbard, UK → 140 x SWT-3.6-107
Lincs, UK→69 x SWT-3.6-120→25% Siemens Project Ventures (Centrica 50%, Dong 25%)
Gwynt Y Mor, UK→160 x SWT-3.6-107→10% Siemens Wind Power (RWE 60%, SWM 30%)
Baltic 2, DE→ 80 x SWT-3.6-120
Anholt, DK→ 111 x SWT-3.6-120
Dan-Tysk, DE→ 80 x SWT-3.6-107
Borkum Riffgrund 1, DE→ 77 x SWT-3.6-120
Source: SWP
Rudong Intertidal, CHN → 21 x SWT-2.3-101
West of Duddon Sands, UK→ 108 x SWT-3.6-120
Teesside, UK→ 27 x SWT-2.3-93
Meerwind Sud Ost, DE→ 80 x SWT-3.6-120
Note: SPV also own 50% of Smart Wind consortium with Mainstream Renewables, developing UK Round 3 Hornsea zone (4 GW). First GW being developed with Dong.
5
Offshore Wind Roadmap and Funding Requirement
18 GW by 2020 under DECC Roadmap
£8-10bn annual funding required
Based on £3m/MW capex, straight line roll out from 2015, excludes OFTOs and capital recycling
Depends on build out which should generate economies of scale to lower construction costs
Source: DECC UK Renewable Energy Roadmap July 2011
6
Conditions for investment
Utilities cannot finance construction of Round 3 on their own and need to tap new investors and banking market
Conditions for entry of new capital
Revenue certainty (FITs, ROCs) Regulatory certainty (EMR, OFTOs) Profitability & risk adjusted returns Visibility on long-term market growth De-risking projects Stable macroeconomic climate
7
Funding Sources in Offshore Wind Development CyclePr
ojec
t ris
k
Development (c. 48+ months, c£10-50m)
Pre-construction (c.24+ months c.£50-
200m)Construction
(c. 24+ months, c£1Bn)
Point in time – decreasing risk and required return over project life cycle
Operation(c. 20+ years)
• Site search• Feasibility study• Environmental studies• Licenses (production / installation)• Permits• Land lease• Commitment to grid
• Turbine order• Balance of plant
(BOP) Long-leaditems
• Design• Met mast• Geotech• Grid connection
• Civil construction• BOP• Turbine• Grid connection
• O&M + Warranty• Zero emission cash
Debt Capital Markets, Utility Bonds, Govt Sponsored Bonds
Project Finance with Sponsors, Multilateral & ECA supportNot availableSenior debt
Utilities, Infrastructure Funds, Direct Financial Investors, Public
Equity Markets
Utilities, Oil & Gas Cos, Private Equity,
Contractors
Utilities, Venture Capital, DeveloperEquity
OperationPre-construction / ConstructionDevelopmentFunding source
8
Utility Investors
UK projects have historically been developed by utilities in contrast to Continental Europe where independent developers are more prevalent
UK projects have generally been financed by utilities on balance sheet unlike Continental Europe where limited recourse project finance is more common. Utilities don’t like project finance as it is expensive and often treated as on balance sheet by rating agencies
Utilities have to find alternative funding sources if they want to maintain ratings & preserve dividends. They are forming partnerships with other utilities and new types of investors to share funding and risks
We estimate of total annual capex of 10 largest European utilities of €40bn about €10bn could go to offshore wind with maybe half of this allocated to UK
9
R3 Funding Sources
Majority of funding from utility balance sheets unlevered
Balance from limited recourse equity (40%) and debt (60%)
More utility funding available → more other funding likely to be available
Additional funding from capital recycled from operational projects not shown
High case – 75% total offshore wind budget allocated by European utilities to UK ; £1.4bn l/r equity; £2.1bn l/r debt
Base case – 50%; £1bn l/r equity, £1.5bn l/r debt
Low case – 30%, £0.6bn l/r equity; £0.9bn l/r debt
0
2.000
4.000
6.000
8.000
10.000
12.000
High case Base case Low case
£m
illion
per
yea
r
Utility balance sheet
Ltd recourse equity
Ltd recourse debt
Estimated annual constructioncosts of £8-10bn
Source: Siemens
10
Other Investors
• Financial/private investors•Private equity / infra funds – SPV / Blackstone / Ampere / Marguerite / Ventizz
•Private investors – Colruyt / Kirkbi Group / Oticon Foundation
•Pension funds – Pension Danmark / PKA / PGGM
•Japanese trading houses – Marubeni
•Sovereign wealth funds – Masdar
• Strategic investors• Oil & gas companies – Statoil / Repsol
• EPC companies – Fluor / Strabag / Hochtief
• Financial/private investors generally have limited appetite for construction or development risk but there are exceptions:
• Masdar / SPV / Blackstone / Colruyt / Marguerite / Ventizz
• EPC companies often take development risk and then sell permitted project before construction
11
Co-Funding Model
Costs shared but project risks stay with utility
Sale of minority stakes to private investors Operating assets
Assets in construction with EPC wrap
De-risking Opex
PPA
Bridge financing
Stakes sold for premium due to risks assumed by utility
Investments stay on balance sheet of utility
Examples: various deals involving Dong
12
Limited Recourse Model – Project Finance
Limited recourse financing by investors
Banks take construction risk Common in Germany and Benelux, but not in UK
Lincs is first UK PF deal with construction risk
Banks requirements Higher pricing
Significant contingency
Debt reserve accounts
Lower gearing and high coverage ratios
Support from multilaterals/development banks and ECAs
Examples: Lincs (Centrica/Dong/SPV); Meerwind (Blackstone)
13
Limited Recourse Model – Minority Stakes
Limited recourse financing of acquisition of minority stakes by investors
Banks do not take construction risk
Same guarantees as under Co-Funding model
Issues for banks Limited step-in rights
No direct security over operating assets/contracts
Change of control
More equity required
Support from multilaterals/development banks and ECAs
Example: Gunfleet Sands (Marubeni)
14
Conclusions
Utilities will play lead role in funding Round 3, but balance sheet pressure means they will not be able to do this alone
Utilities are setting up JVs with other utilities & investors to share funding & risks. Dong leading way bringing in new investors
New investors will require revenue and regulatory certainty, improved profitability, project de-risking & stable macroeconomic conditions
Most financial investors currently have limited appetite for construction risk, but there are exceptions
Limited recourse lending by commercial banks and public financing institutions will be critical, both at the project level and the financing of minority stakes in projects
Peter WestonGlobal Head of Finance & InvestmentSiemens Wind Power+44 7808 824 [email protected]
Thank you
Global Wind Power Finance & investment CongressJune 26-27, 2012, London
Morgan Stanley
Institutional Investors Workshop
July 2, 2012
2
Renewables
Natural Resources
Morgan Stanley Project Finance Transactions
Power
$900 MM
Pre-Export Credit
Facility October 2009
EGPC
$240 MM
Debt
Financing June 2011
$1 Bn
Receivables
Monetization December 2010
EGPC
$240 MM
Acquisition
Financing June 2007
$378 MM
FSA Monetization July 2005
EGPC
$1.55 Bn
FSA Monetization February 2006
EGPC
$117.5 MM
Construction
Financing July 2009
$200 MM
Loraine Wind
Project
Wind Equity
Investment February 2010
10-Year
Commodity Offtake
Provider July 2009
$319 MM
Construction
Financing December 2011
10-Year
Commodity Offtake
Provider December 2011
$132 MM
Construction
Financing
August 2008
$466 MM
Arlington Valley
Solar Energy II
Construction / Term
Financing
January 2012
Infrastructure
$300 MM
FPSO
Financing November 2011
$750 MM
Drillship
Financing March 2012
$1Bn
Railroad Financing December 2005
$1Bn
HANGZOU RING
ROAD
Toll Road Financing December 2005
$1.3 Bn
Construction
Financing
March 2010
$600 MM
Infrastructure
Financing November 2010
$100 MM
Railway
Financing October 2007
$494 MM
Lease Securitization April 2007
$213 MM
Toll Road Financing August 2006
$162 MM
Toll Road Financing February 2006
$950 MM
Acquisition
Financing September 2005
$950 MM
Debt
Refinancing September 2005
$11 Bn
Construction
Refinancing June 2006
$740 MM
MACH Gen
Debt
Refinancing February 2007
$740 MM
Construction
Financing May 2008
$45 Bn
Acquisition
Financing February 2007
$1.65 Bn
Acquisition
Financing March 2006
Approx. $300 MM
West Deptford
Project
Construction/Term
Financing November 2011
$290 MM
Canadian Hills
Wind Project
Construction
Financing
March 2012
Financing Sources For Greenfield Offshore Wind
• Q: Do you believe that
Multilateral agencies will
provide an aggregate value
of €22Bn in capital over the
next 8 years?
Past Projects and Projections
3
Past Projects and Projections: Bloomberg New Energy Finance
1.2
6.1
3.9
2.1
3.23.1
2.82.5
2.1
1.6
0.7
1.3
1.3
1.7
1.9
2.3
2.6
1.0
1.3 4.0
1.8
2.0
2.0
2.1
0.4
0.4
0.5
0.4 1.0
3.23.2
2.73.9
5.27.1
9.0
0.7 1.2
3.53.2
2.2 2.6 2.8 3.1 3.8
0.9
0.3
2.1
0.3
0.3
0.10.4
0.4
0.4
0.4
0.4
0.2 0.4
0.10.3
0.5
0.7
0.9
0.10.1
0.2
0.1
0.1
0.1
0.1
0.1
0.3
0.3
0.3
0.3
0.3
0.3
0%
20%
40%
60%
80%
100%
2012 2013 2014 2015 2016 2017 2018 2019 2020
Equity-Primary Utility Equity-Secondary Utility Equity-Developer Equity-IPP Equity-Institutional Investor
Equity-WTG Equity-Private Equity Debt-Commercial Debt-Multilateral
5.6 10.2 13.8 14.2 12.3 14.4 16.1 18.6 21.3
Annual Investment in Offshore Wind By Year of Commissioning and Investor Type; 2012–2015 by Existing Commitments and 2016–2020 Forecast
€ Bn
Sources Bloomberg New Energy Finance; Rabobank
2012-2020
Country € Bn
Germany 39.2
UK 38.6
France 18.8
Belgium 6.6
Denmark 3.9
Netherlands 3.5
Rest of EU 16.3
Total 126.9
Annual Investment
Sources Bloomberg New Energy Finance; Rabobank
Banks Project Finance Participation Glass Half Empty Or Full?
4
• Q: Do you believe that
commercial banks will
provide an aggregate value
of €35Bn in capital over the
next 8 years?
– Average of ~€4.5Bn per
year
• Approximately 70% of bank
lenders into the offshore
wind sector have only
participated in 2 transactions
• Alternatively, could argue
that banks with 2+
transactions makes ‘a
knowledgeable market’
– 16 banks
• Even assuming
‘knowledgeable market’
doubles to 32 banks, a
€4.5Bn average capital
requirement would require an
average ticket size of
approximately €140MM per
bank
– Concentration concerns?
“Our discussions with industry participants suggest there are around 15-20 commercial lending
banks currently active in offshore wind financing, and that there is appetite to fund €2-2.5Bn of
projects per year”
Morgan Stanley Equity Research
1
1
12
7
4
1
1
1
0 2 4 6 8 10 12
1
2
3
4
5
6
7
8
Banks in Project Finance Offshore Wind Transactions
Number of Transactions
12
19
23
24
25
26
27
28
Institutional Investors as Debt Capital Providers
5
• Pension funds have played a
role in investing in the equity
of offshore wind projects
• Given the scale of the
anticipated build out, expect
that the institutional debt
capital markets will play
some role
– Likely only when
operational
• Renewable sector: interest by institutional debt investors in European renewable sector is increasing,
however it is still early stages
– Several funds have dedicated pools of capital for infrastructure investment, which includes
renewables
– Judgment based upon limited transaction flow and unhelpful precedents (i.e. Breeze) and stability of
regulatory regimes
• Favourable markets: offshore wind predominately located in “core” Northern European markets
Investor Concerns – Not Unsurprising
• Business model - Future incentive / regulatory support risk
• Technology risk: evolving so why invest now?
• Resource risk
– Weather risk (“black swan” winter storm damaging turbines)
How / When To Invest?
• Unlikely that institutional investors would be willing to take construction risk of an early stage
technology without sufficient guarantees or a wrap from an independent party
– Renewable wind power not currently permitted under EU/EIB Project Bond Initiative
– Investment grade?
• Initially, expect that construction financing will be provided by banks with a potential bond takeout
post-construction
• In line with broader European PF bank market, which we expect will morph towards a more formal
mini-perm structure
6
Current Developer / ‘IPP’ Model
Asset
Sponsor(s)
Future Utility Model?
Utility
3rd Party Equity
Investors
• No “On” vs. “Off” balance sheet considerations
• Rating agencies (or public ratings) not necessary
• Continued appetite of the ECAs / commercial
banks critical for this funding approach
• Depending on equity investor / structure, debt
consolidation could be relevant to Utilities
• As Utilities expand their offshore wind portfolios,
additional debt burden puts pressure on balance
sheets and ratings
–While selling down an equity stake recycles
capital to allow for further development, it may
not reduce the Utility’s debt burden
Equity
Debt
Equity/Cash Export Credit
Agencies Debt
Offshore Wind Financing Strategies
Equity (50% +/-)
Asset
Equity (50% +/-)
Debt
Commercial Banks
IssuerCo
7
Banks / Institutional
Investors
Debt Proceeds
Security
Utility 2
Asset
Utility 3
Asset
Utility 2
[X]% [X]%
Utility 1 Other Utility 3
[X]% [X]%
FiT
Utility 2
Utility 1
Other
Utility 3
FiT
FiT
FiT
Utility 1
Asset
Industry Wide Financing Solution? Legal / Ownership Likely to Pose Problems
Institutional Investors Workshop
2 July 2012
Ryan Trow
Forewind
• Forewind is a consortium comprising four leading international energy companies: RWE, SSE, Statoil, and Statkraft.
• The consortium members joined forces to bid for the Dogger Bank Zone Development Agreement as part of The Crown Estate’s third licence round for UK offshore wind farms (Round 3) in 2010.
• Forewind combines extensive experience of international offshore project delivery and renewables development, construction, asset management and operations, with UK utility expertise spanning the complete electricity value chain.
• Together as Forewind we have the experience and expertise to deliver the extraordinary challenges facing Round 3 developers.
• Forewind is committed to securing all the necessary consents required for the construction and development of Dogger Bank, the first of which is anticipated around 2015.
• The Crown Estate is Forewind’s partner in the development of Dogger Bank.
2
Forewind Overall Strategy
Dogger Bank key facts:
• Capacity: Agreed target 9 GW,
with the potential for c.13 GW.
• Area: 8660km2 ; equivalent to size
of North Yorkshire.
• Distance: 125-290 km from shore.
• Depth: 18-63 m; c.4 GW in <30m
water depth, c.8 GW in <35m
water depth; shallow compared
with other Round 3 zones.
• Wind: High wind speeds of
>10 m/s average wind speed
across the zone.
• History: A "dogger“ was a type of
Dutch fishing boat that commonly
worked in the North Sea in the
seventeenth century.
Middlesbrough
Hull
• Forewind’s mission is to deliver development consents for safe, viable offshore wind capacity
• Priority to secure & consent early projects to build momentum & confidence in Forewind for the full zone potential
• We aim to deliver low LCOE projects that maximise value in the Dogger Bank development option
3
Unincorporated Joint Venture
SPV SPV SPV SPV
Funding & guarantees
UJV
• UJV owns assets
• Bizco has legal
personality for
licences and land
agreements etc.
Structure repeated for each 1GW project
4
SPV SPV SPV SPV
Operator
Bizco +
Eight or more individual Projects
First 6 Projects have signed grid agreements
5
Connection point Connection date
P1 – Creyke Beck Yorkshire Apr 2016
P2 – Lackenby Teesside Apr 2017
P3 – Lackenby Teesside Apr 2018
P4 – Creyke Beck Yorkshire Apr 2019
P5 – Tod Point Teesside Apr 2019
P6 – Tod Point Teesside Apr 2020
• Each Project will have
• Around 200 turbines with a cumulative capacity of about 1.2GW
• AC collector transmission substations
• HVDC transmission offshore platform and equivalent onshore station
• Approx. 200km * 2 of transmission cables to connect to shore
• Each project will cost £3bn to £4bn to construct. About £30bn needed in total
• Forewind has accepted grid agreements for first 6 projects in anticipation of an appropriate regulatory environment evolving
Post Consent Risk:
6
• Regulatory risk – current uncertainties include EMR and transmission charging. What regulatory risks will there be when finance is needed?
• Political risk – how much offshore wind is wanted and when?
• Supply chain risk – For example, current global cable manufacturing capability cannot supply Dogger Bank’s current programme. Many other examples of supply chain pinch points
• Finance:
• If pre-construction finance only comes from offshore wind farm developers it will take a long time to recycle funds and slow down overall deployment of offshore wind
• Availability of post construction finance will impact on ability to recycle funds
• Utilities may not want to take on £4bn construction projects on their own. Also, they may not have the capacity and strategic interest in being a non-operating investor
Institutional Investors Workshop
2 July 2012
Ryan Trow