attachment a.1 non technical summary · operations and maintenance (o&m) contractor, with...
TRANSCRIPT
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
Attachment A.1
Non Technical Summary
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
i
CONTENTS
A NON TECHNICAL SUMMARY...................................................... A-1
A.1 General......................................................................................A-1
A.2 Proposed Site Location................................................................A-2
A.3 Management of the Installation ...................................................A-3
A.4 Infrastructure and Operation.......................................................A-4
A.5 Emissions and Impact on the Environment...................................A-7
A.5.A Atmospheric .......................................................................................A-7
A.5.B Surface Waters ...................................................................................A-8
A.5.C Sewer.................................................................................................A-8
A.5.D Ground...............................................................................................A-8
A.5.E Noise..................................................................................................A-8
A.6 Control and Monitoring ...............................................................A-9
A.7 Resource Use, Materials Handling and Energy Efficiency ...............A-9
A.8 Accident, Prevention and Emergency Response ..........................A-11
A.9 Remediation, Decommissioning, Restoration and Aftercare .........A-13
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-1
A Non Technical Summary
A.1 General
Lumcloon Energy Ltd. is applying to the Environmental Protection Agency for an Integrated
Pollution, Prevention and Control Licence for the operation of a gas fired power station at
Lumcloon Cloghan, Co. Offaly. The facility is classed under Class 2.1 “the operation of
combustion installations with a rated thermal input equal to or greater than 50MW” of the
First Schedule of the Protection of the Environment Act, 2004.
The proposed plant will have capability of producing up to a maximum of 350MWe. The plant
is described as a flexible mid-merit power plant capable of running in either open cycle or
combined cycle modes. The proposed power block will comprise four small scale (<50MW)
gas turbines, four heat recovery steam generators (HRSGs) and two steam turbine generators
producing 75MW. Diverter dampers will be installed between the gas turbines and the heat
recovery boilers and this will enhance the generating flexibility of the plant, i.e. the plant will
be capable of responsively altering its load profile to respond to system demand determined
by the Transmission System Operator (TSO). The plant will be capable of starting up and
reaching full load in open cycle (188MW) mode in 25 minutes. In combined cycle mode,
typical start-up times are as follows:
• From cold start (i.e. plant shutdown for more than 64 hours), the plant will take
approximately 300 minutes to reach full load
• From warm start (i.e. plant shutdown for less than 64 hours), the plant will take
approximately 220 minutes to reach full load
• From hot start (i.e. plant shutdown for less than 8 hours), the plant will take
approximately 90 minutes to reach full load
Each HRSG will also be fitted with supplementary gas burners thereby producing additional
output. The supplementary firing ramp-up rate is around 3MW per minute; which means that
the load can increase from combined cycle operation to maximum load within 10-minutes.
The power plant is designed and configured to allow for high efficiency base load, while also
providing for peak power capacity through out a wide load range. The design concept with a
total of four gas turbines and two steam turbines allows for operation at a high efficiency and
low emissions values throughout a wide plant power output by the possibility to reduce the
power on the gas turbines one by one.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-2
A.2 Proposed Site Location
The Lumcloon Energy Ltd power plant will be located on 11 acres of development lands,
which are under the applicant company’s control. The site is situated in the town land of
Lumcloon, approximately 5km south east of Ferbane, 22km south of Athlone and 20km west
of Tullamore. Maps showing site location, existing site layout and proposed site layout are
attached.
The site itself is a brownfield site and formed part of the former Ferbane peat fired power
station site, which was operated by the ESB and fully decommissioned in 2004. The ESB
subsequently obtained planning permission in 2004 for a 100MW gas fired power plant at the
site, but did not proceed with the proposed development. An IPPC licence (IPC Licence
Registration Number P0695-01) was also obtained but has ceased to have effect and the
activity cannot now commence under this licence in accordance with Section 92(1) of the EPA
Acts, 1992 and 2003.
The development site is approximately 11 acres and located adjacent to the R357. The site is
about 5km south east of Ferbane, 22km south of Athlone and 20km west of Tullamore. The
proposed development lands are brownfield and the site is part of the former ESB owned
peat fired power station site, which was decommissioned in 2004. The site is situated in the
Shannon River basin district and the Silver River is located approximately 50m to the East of
the site and flows north into the Clodiagh, which joins the Brosna River, which in turn flows
into the River Shannon. There is a relatively small wooded area in the north western area of
the site. There are large parcels of cutaway bogland and forestry to the south west and
north-west of the site and industrial railway associated with the former peat power station
run out from the former peat power station to the surrounding boglands. The surrounding
topography is generally flat with nearby once-off rural housing primarily located south west of
the site along a local road, which borders the site to the west and runs in a south western
direction from the R357 to the R437.
An Bord Pleanála granted planning permission with conditions for the proposed Lumcloon
Energy Ltd. power station development in March 2010. The plant will have capability of
producing up to a maximum of 350MW of power. The power generation plant will be capable
of running in either open cycle or combined cycle modes. The power block will comprise four
small scale (<50MW) gas turbines, four heat recovery steam generators (HRSGs) and two
steam turbine generators producing a further 75MW. Diverter dampers will be installed
between the gas turbines and the heat recovery boilers and this will enhanced the generating
flexibility of the plant. For example, the four gas turbines in open cycle mode will be capable
of producing electricity in the range of 47MW to 188MW. In the event of shutdown of one of
the steam turbines, the plant would still be capable of producing approximately 224MW of
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-3
power (i.e. operation of two gas turbines in open cycle mode and two gas turbines in
combined cycle). The plant will be capable of starting up and reaching full load in open cycle
(188MW) mode in 25 minutes.
The power plant will be designed and configured to allow for high efficiency base load, while
also providing for peak power capacity throughout a wide load range. The design concept
with a total of four gas turbines and two steam turbines allows for operation at a high
efficiency and low emissions values throughout a wide plant power output by the possibility
to reduce the power on the GTs one by one.
Natural gas, supplied from the Bord Gáis Network (BGN) grid, will be the primary fuel source
for the facility. To comply with Commission for Energy Regulation (CER) regulations, diesel
will be used as a backup fuel in the event of interruption to the natural gas supply. Five days
running capacity of diesel will be stored on site, (approximately 5,200m3).
The proposed facility will operate as a mid merit plant and the proposed hours of operation
will be determined by the Transmission System Operator (TSO), Eirgrid, based on the load
demand of the electricity grid.
This Non -Technical Summary (NTS) is submitted as part of the supporting documentation for
the IPPC Licence application. This section of the NTS provides a brief overview of the
application only. It is recommended that the entire document is reviewed in order to obtain
detailed information relating to the application.
A.3 Management of the Installation
Lumcloon Energy will have the ultimate responsibility for health, safety and environmental
issues relating to the operation of the facility. A suitably qualified and technically competent
Operations and Maintenance (O&M) Contractor, with previous experience operating and
maintaining power plants will be contracted by Lumcloon Energy Limited. The O&M
Contractor will have responsibility for the day to day operation and maintenance of the plant
as well as environmental monitoring and reporting. The contract between the Operator and
the O&M Contractor will specify health and safety and environmental obligations and
responsibilities.
The plant manager will report directly to the director of Lumcloon Energy Ltd. Site specific
management systems and operating procedures will be developed. The systems and
procedures will be continuously reviewed and developed by the operator and O&M contractor
in accordance with the principles of continuous improvement. The Plant Manager will be
directly responsible for the implementation of the Operators Health and Safety; all other site
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-4
personnel will have varying degrees of responsibility for their implementation. Operations will
be carried out in accordance with legislative requirements and the conditions of the IPPC
Licence and Planning Permission.
All personnel will be technically competent and suitably qualified to undertake their assigned
tasks. Training records will be maintained on site, available for inspection.
Personnel with responsibilities for operations, maintenance, health and safety and the
environment will receive task specific technical training, as required. A training needs
programme and matrix will be developed and updated on a regular basis. The programme
will take account of any incidents, amendments to site licence conditions, changes to
legislation, operations, operating procedures, emergency response and best practice
guidelines.
A site specific EMS will be developed and implemented for the facility in accordance with
ISO14001:2004 in due course. The EMS will provide the framework for environmental
management, ongoing assessment of environmental performance and continual improvement
at the power plant. The implementation of the EMS will include regular cross-functional
management reviews and will be subject to both internal and external audits.
A.4 Infrastructure and Operation
The site is predominantly flat generally ranging in height (between 45m ordnance datum
(OD) and 47m OD Malin Head datum).
Access to the site will be from the R357 through the existing entrance/exit to the site. This
will be used as the main entrance and is located beside the administration building in the
north-west area of the site. A second entrance for emergency use further east along the
R357 towards Lumcloon Bridge will be installed.
A two storey administration building will be constructed which will be 10.6m to roof apex
from ground level. Approximately 30 car parking spaces will be provided for employees and
visitors in this area of the site during the operation of the plant. A 400 m2 warehouse
containing a workshop and stores will be located south of the administration block, adjacent
to the switchyard.
The power generation building comprising gas turbine halls, steam turbine halls and heat
recovery steam generator halls) will be constructed as one structure with different roof
heights determined by the plant components within. The total footprint of the power
generation building will be 6,684m2. Two air cooled condenser (ACC) units, each with nine
fans will be located on the eastern side of the power block. The parapet of both ACC units
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-5
will be 24.5m above ground level. A description of all plant components is provided in table
1.0. The tallest structures on the site will be the four exhaust stacks from the HRSG units.
Internal roadways will be tarmac paved and the ground around external plant components
such as the AGI, gas receiving, switchyard and the ACCs will be covered with stone chippings
to facilitate natural drainage.
Table A.4.1 Details of the Facility Components
Component
• Gas Turbine Hall (2 no) – open cycle
• Heat Recovery Steam Generator Hall (2 no)
• Steam Turbine Hall (2 no.)
• Air Cooled Condenser (2 no.)
• Ancillary area of power generation building (1 no.) -ctrl room, lab, etc
• Open Cycle Stacks (4 No.)
• Heat Recovery Steam Generators (HRSG) stacks (4 No.)
• Administration Building (1 no.)
• Warehouse/Workshop/Stores (1 no.)
• Switchyard (1 no.)
• Above ground Installation (1 no.)
• Internal Roads and Car parking
• Bund for Diesel Storage (1 no.)
• Diesel Tank (2 no.)
• Fuel Oil supply pumps canopy (1 no.)
• Raw Water Tank (1 no.)
• Water Treatment Plant (1 no.)
• Demineralised Water Tanks (2 no.)
• Process Wastewater Treatment compound (1 no.) - underground
• Storm water Attenuation tank (1 no.) - underground
The structural design of the main buildings will be conventional structural steel supported on
reinforced concrete foundations. Steel columns will be fire protected as necessary to comply
with the building regulations. Floors will be concrete. The administration building and some
of the smaller buildings will be concrete block construction on concrete reinforced concrete
foundations and rendered with nap plaster finish. Profiled metal cladding will be used for
external walls on power generation buildings. The finished colour of the plant structures will
be designed to favour the reduction of potential visual impacts. Non reflective finishes will be
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-6
used in order to reduce or avoid impacts relating to sunlight reflection or glare. Colours of
buildings will be confirmed with the planning authority prior to construction.
Roofs will be constructed of profiled metal decking on purlins spanning between rafters and
will be flat or shallow pitched. Buildings will be single or two storey with access gantries and
walkways for access to plant and equipment. These will be constructed of stainless /
galvanised steel open grating type flooring supported on steel beams and columns. The
stack will be fabricated from painted insulated carbon steel. External doors and escape doors
will generally comprise of metal flush doors and mild steel frame.
It is envisaged that the facility will operate in excess of 6000 hours per annum and is
designed to operated 365 days per year. The mid merit plant will be capable of responsively
altering its load profile to respond to system demand determined by the Transmission System
Operator (TSO) and therefore running time is a function of demand.
The following describes how power is produced from natural gas at the facility.
Gas Turbine Generator
Air enters the gas turbine where it is compressed, mixed with natural gas and ignited, which
causes it to expand. The pressure created from the expansion spins the turbine blades,
which are attached to a shaft and a generator, creating electricity. In simplistic terms a
generator can be described as a large spinning magnet inside a coil of wire and as the
magnet spins, electricity is created in the wire loops. The hot exhaust gas exits the turbine
and then passes through the Heat Recovery Steam Generator (HRSG).
Heat Recovery Steam Generator (HRSG)
Within a HRSG, there are layers of tall tube bundles, filled with high purity water. The hot
exhaust gas coming from the turbines passes through these tube bundles, which act like a
radiator, boiling the water inside the tubes, and turning that water into steam. The gas then
exits the power plant through exhaust stack(s) at a much cooler temperatures, after having
given up most of its heat to the steam process.
A.4.A.(a) Steam Turbine Generator
The steam generated is sent to the steam turbine. Steam enters the turbine at very high
temperatures and under high pressure. The pressure of the steam is used to spin turbine
blades that are attached to a rotor and a generator, producing additional electricity. After the
steam is spent in the turbine process, the residual steam leaves the turbine at low pressure
and low heat, and passes into a condenser, to be turned back into water. By using a
combined cycle, the plant is capable of producing more electricity. A CCGT generator can
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-7
reach efficiency levels of up to 58%. The efficiency of the proposed CCGT unit means that
this type of generator emits the lowest levels of greenhouse gases per unit of electricity
generated when compared to any conventional generation type.
Flexible mi-merit plant, such as the one that will be installed at Lumcloon, is capable of
varying the power generation across a wide range of power output and can turn on and off
on a daily basis, which allows this unit to maximize the electricity generating potential from
variable renewable energy sources such as wind.
A.4.A.(b) Air Cooled Condenser
An air-cooled condenser (ACC) is used to condense the steam exhausted by the steam
turbine. This solution provides a completely plume free arrangement. The hot process fluid
to be cooled flows through a tube while the cooling air flows across the outer surface to
remove heat. The cooling air is propelled by fans in either a forced draft or induced draft
configuration. The ACC significantly reduces the demand for water (closed loop) and does
not give rise to a visible water vapour plume.
A.5 Emissions and Impact on the Environment
A.5.A Atmospheric
The current air quality in the area of the proposed development was determined through the
use of baseline monitoring using diffusion tubes and a desk study review of published data
available from the EPA and nearby developments. The baseline air quality assessment
determined that existing baseline levels of PM10, NO2, SO2 and benzene are significantly
below the ambient air quality standards in the region of the proposed development.
Air dispersion modelling was undertaken to assess the likely emissions arising from the
proposed power plant, during its operation. A stack height determination was undertaken for
eight stack emission (A2-1 to A2-8) to ensure that appropriate stack heights were determined
for the relevant combined cycle and open cycle emission points. This measure will ensure
that the impact on local air quality will not be significant. The potential air quality impacts
during the operational phase were assessed, based on a ‘worst-case’ scenario approach by
modelling emissions from the eight stacks at the limits which will be imposed on the
development. The assessments predicted that emissions will result in ambient air quality
concentrations that are within the relevant air quality limit values regardless of firing on
natural gas or distillate in combined or open cycle modes of operation.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-8
The power plant will be designed to the highest modern standards and will operate in
accordance with BAT (Large Combustion Plant) techniques to ensure minimum emissions
from the plant. In addition to IPPC licensing requirements, the facility will also be regulated
under the Greenhouse Gas Emissions Permit regimes, ensuring emissions from the facility and
their impact are minimised.
A.5.B Surface Waters
The discharge from the facility will comprise treated process waste water discharge, surface
water run-off discharge and treated foul water discharge. The three emission points (SW1 to
SW3) are discharged into the open drain at the northern boundary of the site which is
culverted at the north east corner of the site where subsequently discharges into the Silver
River.
An assimilative capacity assessment (ACA) was undertaken on the Silver River to provide
precise quantifiable impacts on the receiving water body. This assessment took account of
the proposed foul water discharge, process water discharge and discharges from the proposed
(yet to be constructed) adjoining site to the south and typical discharge concentrations from
similar plants and the proposed plant. The ACA study determined that the proposed discharge
will result in a low quantity of the assimilative capacity of the Silver River being taken up by
proposed discharge.
A.5.C Sewer
There will be no discharges to sewer from the activity.
A.5.D Ground
There will be no discharges to sewer from the activity.
A.5.E Noise
A noise impact assessment was undertaken which considered the existing noise environment,
the predicted noise impact, possible noise mitigation and the residual impact of the proposed
power plant. The closest residential receiver to the power station is approximately 400m
away with two residential receivers located approximately 600m away. The distance of the
proposed power plant from the nearest residential receivers allows for significant noise
attenuation due to distance. When all major noise sources on the proposed site were
modelled, it was found that the noise impact at the three residential receivers is predicted to
be below the EPA noise limits of 55dB LAr,T during daytime (8am to 10pm) and 45 dB LAeq,T
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-9
during night time (10pm to 8am). As the power station will be operation on a 24 hour basis,
the night time scenario defines the actual noise limit on the power station. It is concluded
that the noise impact due to the power station will not result in an exceedance of the relevant
EPA limit values and the recommended daytime and nighttime noise levels in the World
Health Organisation (WHO) Guidelines for Community Noise.
A.6 Control and Monitoring
The activity will operate in accordance with the 2008 BAT Guidance Note for the Energy
Sector (Large Combustion Plant Sector).
The gas turbines at the facility will use dry low emissions technology. Dry abatement will
eliminate the need for production and storage of large quantities of demineralised water for
emissions control purposes. It will also significantly reduce the quantity of process
wastewater (demineralisation process and wet scrubbing process) produced at the facility
during its operation. Dry abatement reduces emissions without reducing efficiency of the
plant.
The proposed facility was designed to incorporate an air cooled condenser thereby
significantly reducing the potential volumes of water consumption and process waste water
generated from the site. A combination suitable abatement measures and monitoring
(routine and continuous) will ensure that emission to atmosphere from stacks (eight) and to
surface water from storm, foul and process wastewater do not adversely impact on the
receiving environment. Ambient environment monitoring will also be undertaken for noise
and surface water (upstream and downstream of the plant on the Silver River).
A.7 Resource Use, Materials Handling and Energy Efficiency
The primary raw materials which will be used at the site are:
• Natural Gas
• Water
• Distillate (Diesel for use as a back up fuel)
Natural gas will be supplied from Bord Gáis Network’s (BGN) at a minimum guaranteed
pressure of 19 bar gauge (bar(g)) and 15oC. The design maximum pressure of the BGN gas
pipeline is 70 bar(g). The pressure of the gas will be regulated to approximately 35 bar(g) in
the AGI. From this compound, gas will be sent to gas receiving plant for conditioning. The
gas conditioning plant located close to the gas turbine hall. It is estimated, based on
operation 365 days per annum, that the annual gas usage will be 5.8 x 108m3 natural gas.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-10
Process water will be sourced from the onsite groundwater abstraction well (served the
former peat fired power station). Raw water will be stored on site in a tank of approximately
3,500m3 capacity. Water will be pumped from the raw water storage tank to the water
demineralisation treatment plant for use in the power generation process. The raw water
storage tank will also serve as a reservoir for fire fighting purposes. An on site water
treatment plant will be required to treat abstracted groundwater for use in the HRSG. Water
will be demineralised to achieve a high purity. The primary reason for process water
treatment is to maintain the integrity and performance of the power plant. Critical plant
applications have water purity or conditioning requirements that must be adhered to for safe,
reliable and efficient power generation. Potable water will be obtained from the Leabeg –
Leamore Group Water Scheme. It is estimated that a maximum of 3.5m3 per day of potable
water will be required for use at the facility, i.e. canteen, washing facilities, etc.
Diesel, to be used as a backup fuel, will be stored in a cylindrical steel tank within a 110%
capacity bund to comply with bunding requirements. Due to the quantity of stored diesel,
estimated an approximately 5,200m3 within two tanks of a combined storage capacity of
6,000m3, the facility is classified as lower tier COMAH in accordance with the requirements of
European Communities (Control of Major Accident Hazards Involving Dangerous Substances)
Regulations 2006 (S.I. No. 74 of 2006). In accordance with legislative requirements, a major
accident hazard (MAH) report was prepared for the proposed development.
Other chemical will be stored and used during the operation of the facility including,
lubricating oils, hydraulic oils, transformer oils, boiler feedwater conditioning chemicals, pH
adjusting chemicals for process wastewater treatment and small quantities chemicals for use
in the on-site test laboratory.
The proposed power plant at Lumcloon compliments that outlined for Mid Merit type plant.
Mid-merit units are modern, efficient power plants that can come on-line quickly in response
to increases in the demand for power. The plant design was selected to ensure that delivery
of an efficient, flexible and responsive plant which will conform to commercial, regulatory,
transmission system requirements and environmental objectives.
Efficiency is dependent on many factors including the plant design, the O&M programme and
the ambient conditions (temperature and barometric pressure).The power plant is designed
and configured to allow for high efficiency base load, while also providing for peak power
capacity through out a wide load range. The plant design includes a total of four gas
turbines, four HRSGs and two steam turbines. This will ensure that the plant can operate at
a high efficiency and produce minimal emission throughout a wide plant power output by the
option of reducing the power on the GTs one by one.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-11
By operating the plant in combined cycle (Heat generated by combustion of gas in the gas
turbine will be recovered as steam in the HRSG and the steam is used to drive the steam
turbine), the plant is capable of producing more electricity. A combined cycle gas turbine
(CCGT) generator can reach efficiency levels of up to 58%. The efficiency of the proposed
CCGT unit means that this type of generator emits the lowest levels of greenhouse gases per
unit of electricity generated when compared to any conventional generation type.
Heat generated by combustion of gas in the gas turbine will be recovered as steam in the
HRSG and the steam will drive a steam turbine. Low pressure steam from the steam turbine
will be used in the de-aerator and other plant uses. The gas and steam turbines will be
coupled to a generator for power generation. Supplementary firing using natural gas and
refinery off-gas will increase the energy efficiency.
Energy efficiency and energy optimisation measures will also be considered and implemented
as part of the detailed design and operation of the plant, including those related to building
structures, equipment (pumps, fans, etc) transport on site, employee training and awareness
and housekeeping. The EMS will also include measures for monitoring and reducing energy
usage on site.
A.8 Accident, Prevention and Emergency Response
All employees will receive comprehensive induction training prior to commissioning of the
plant. In addition, site personnel will receive Emergency Response, EMS and general
Environmental Awareness Training, incorporating resource usage, waste minimisation,
energy, water minimisation and noise control techniques. All personnel will be informed of
their responsibilities to report any and all potential and actual non-compliance issues to the
EHS Manager, the EMS auditing programme will facilitate the process. Additional
environmental, health and safety training, including fire fighting and first aid, will be
implemented. The Safety and Emergency response provision at night, weekends and holiday
periods will be the same as during normal working hours.
From the control room, the plant operators will monitor and operate the facility, via the plants
‘Distributed Control System’, viewing graphic representations of all MEC systems on various
screens. The system gives operators both audible and visual signals to keep them informed
of plant conditions at all times and to determine when preventative maintenance is required.
The installation of emergency spill containment facilities will mitigate against any potential
adverse impacts to the receiving surface waters arising from an accidental spillage. All bunds
and chemical containers will comply with the appropriate standards. All bunds will be leak
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:50
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-12
tested prior to commencement of operations. All containers and bunds will be inspected
regularly to ensure they have not become damaged or degraded.
General plant drainage consists of effluents produced by sample drains, equipment drains,
equipment leakage, area wash-downs, etc. This effluent will be collected in a system of floor
drains and sumps and routed to the condensate pit which represents the lowest drainage
point in the plant. From there it is delivered to the process wastewater treatment plant via a
water/oil separator. The process wastewater treatment plant will comprise a below ground
concrete structure containing a number of chambers which will allow agitating, pH and
temperature correction. Continuous monitoring will be undertaken in the final chamber for
dissolved oxygen, pH, conductivity and temperature. Treated process wastewater will then
be discharged to the wastewater collection system to the Silver River via the discharge point
located in the north eastern corner of the site. An onsite laboratory will also be provided to
facilitate monitoring of specific parameters on site.
All appropriate measures will be taken to minimise the risk of accidental spillages or leaks.
The backup supply of diesel will be stored in a cylindrical steel tank within a 110% capacity
bund. The maximum fill level for 2,600m3 is 5.3m. The bund walls will be of reinforced
concrete, 1.6m high. The total volume thus enclosed equates to 110% of the combined tank
capacity. During times when chemicals are handled isolation valves are to be closed. This is
to assure that accidentally spilled chemicals do not enter the storm water drain. The isolation
valves will only be opened again once it has been assured that contamination of the
downstream system can be excluded.
Water collecting in the bund will be pumped to oil/water interceptor prior to being the surface
water attenuation tank. All other surface water runoff from hard standing areas and roofs will
be directed through a hydrocarbon interceptor and silt trap prior to discharge to the
attenuation tank. Small areas that have the potential for causing oil contamination of surface
drain water will be separated from the overall surface water drainage. This comparably low
volume of surface water with potential for oil contamination will be collected separately and
routed through a water/oil separator and delivered to the plants effluent sump.
In case of fire, the applied fire fighting water will be drained into a system of floor drains and
sumps and routed to the condensate pit which represents the lowest drainage point in the
plant. From there it is delivered to the process wastewater treatment plant via a water/oil
separator and the resulting streams will finally be delivered to the plants storm water drain or
effluent drain. A Fire Emergency Response Management plan will be drawn up in consultation
with the local fire brigade and Offaly County Council.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:51
LUMCLOON ENERGY LTD. ATTACHMENT A: NON TECHNICAL SUMMARY
A-13
Collected surface water will be delivered to the clients storm water drain. In order to assure
that uncontaminated surface drains are not mixing with possibly oil contaminated surface
drains such ‘oil risk areas’ drain into a separate sewer. Such surface water will be treated as
effluent, routed via an oil separator and finally delivered to the client’s effluent drain.
In accordance with the requirements of the 2008 BAT Guidance Note for the Energy Sector
(Large Combustion Plant Sector), the gas turbines will use dry low emissions technology. Dry
abatement will eliminate the need for production and storage of large quantities of
demineralised water for emissions control purposes. It will also significantly reduce the
quantity of process wastewater (demineralisation process and wet scrubbing process)
produced at the facility during its operation. Dry abatement reduces emissions without
reducing efficiency of the plant. Particulate and sulphur dioxide emissions from gas-fired
plant are very low and control measures are generally not required.
The proposed implementation of an Environmental Management System (EMS) at the facility
will address emergency response procedures governing spillages, fire, flooding and malicious
damage.
A.9 Remediation, Decommissioning, Restoration and Aftercare
Subject to the granting of an IPPC licence it is anticipated that operations at the facility will
commence in the first quarter of 2014, the plant is expected to be operational for 30 years.
A detailed Residuals Management Plan will be developed and submitted to the EPA within six
months of commencement of operations, or as otherwise agreed with the EPA, in accordance
with Guidance on Environmental Liability, Risk Assessment, Residuals Management Plans and
Financial Provision, EPA (2006). The plan will be reviewed annually as part of the Annual
Environmental Report (AER) and will take into account forward financial planning for the
process.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:51
Site Location
0 1,000 2,000 3,000 4,000500
Meters
Note: Geological Data Copyright Geological Survey of Ireland andGovernment of Ireland Reproduced under Licence
Note: Base Map Copyright Ordnance Survey Ireland and Government of Ireland Reproduced under licence, number EN 0004909
© WYG
Drawn By: Igor Wodyk - ArcMap 9.3 WYG IrelandAttachment B.2.A
Job Number:CE07335
Finalised by: GB
Date: June 2009
Office: 1404
Client: Lumcloon Energy Ltd.Site Location Map
1:50,000
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:51
WYG
NOTE: Drawing is for diagrammatic purposes only. No measurements to be taken.
©
Lumcloon Energy Ltd
WYG Ireland
Existing Site Layout
Job No. CE0 7335Figure No.1.2 Finalised By - CS
Date. Aug 2009
Office - 1404
Drawn By: Igor Wodyk - CS2,Illustrator
N
Site BoundaryRoadRiver/ Water CourseBuilding/StructureMonitoring Borehole LocationTrial Pit LocationSurface Water Sampling PointAir Monitoring LocationNoise Monitoring LocationDust Monitoring LocationSlope/GradientWater Table (m.OD)Groundwater Contour (m.OD)Groundwater Flow DirectionCross Section A-A’
LEGEND
BHTP
SWAND
10
A A’
0
METRES
25 50 75
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 10-03-2011:03:35:51