assured offtake pressures oad workgroup 25 th september 2012
DESCRIPTION
Assured Offtake Pressures OAD Workgroup 25 th September 2012. Network Flexibility. Term that National Grid NTS has used in RIIO to identify the additional operational capability required for the NTS to accommodate the changing flow patterns and changing behaviours / requirements of NTS Users - PowerPoint PPT PresentationTRANSCRIPT
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
Assured Offtake Pressures OAD Workgroup 25th September 2012
2
Network Flexibility
Term that National Grid NTS has used in RIIO to identify the additional operational capability required for the NTS to accommodate the changing flow patterns and changing behaviours / requirements of NTS Users
NTS have proposed that this can be achieved through Rules, Tools or Assets Optimum solution likely being a combination of all three
Assured Offtake Pressures (AOPs) and associated pressure agreements are some of the existing Rules and Tools that are currently used to manage the NTS/LDZ interface Optimisation of NTS/DN system investment
3
Assured Offtake Pressures (AOPs) AOPs provide DNOs with sufficiently high system input
pressures under which to plan, develop and operate their LDZs economically and efficiently
Each Exit Point’s AOPs are applicable for each Day within in a Gas Year and are not linked to demand
The agreed/significant pressures process can be used to agree lower/higher 06:00 operational pressures if required This process is used on the majority of days
4
Why Propose Changes to AOPs
NTS investment / capability analysis assumes that AOPs are met at all demand levels No equivalent of the Agreed Pressures Process for planning
purposes
Majority of investment planning analysis for new supplies / storage sites is undertaken at medium to low demand levels
5
Why do analysis at lower demand levels? Supply flows, mainly at importation facilities, do not
show a correlation with national demand levels
Source: National Grid NTS’ RIIO-T1 submission
6
Entry Capability at lower demand levels As demand reduces, entry capability of the NTS also
reduces as gas needs to be transported further into the system
This results in larger pressure drops making it more difficult to meet AOPs whilst accommodating the level of supply at the terminal.
National Grid NTS may be proposing to invest to meet AOPs that are not required at a particular demand level, leading to potentially inefficient investment
7
AOPs It is often difficult for National Grid NTS to agree to DNO requests
to increase existing AOPs as they are currently equally applicable to summer and winter demand conditions
If AOPs were linked to demand then National Grid NTS could be more confident of efficient
investment at off-peak demand levels National Grid NTS and DNOs may be able to agree increases
to AOPs at higher demand levels, as these would not apply for the entire gas year
We would not be required to agree appropriate pressures with each DNO, each Day via the Agreed Pressure Process
Would allow GNCC to make more efficient decisions when balancing the network and planning for system access
8
Understanding AOPs NTS want to understand each DNOs requirement for high input
pressures to their LDZs so that we can consider potential changes to way AOPs are treated.
Source: NTS Demand Side Modelling - Design of Distribution Systems (GL Noble Denton)
65% of Peak
9
Historical (aggregated) LDZ Demand
0
20
40
60
80
100
120
140
160
180
50-60
60-70
70-80
80-90
90-100
100-110
110-120
120-130
130-140
140-150
150-160
160-170
170-180
180-190
190-200
200-210
210-220
220-230
230-240
240-250
250-260
260-270
270-280
280-290
290-300
300-310
310-320
320-330
330-340
340-350
350-360
Aggregate LDZ Demand
Cou
nt
Sum of #
LDZ demand
10%
65%
of P
eak
Fore
cast
50%
of P
eak
Fore
cast
15%
10
Proposal Proposal to introduce “Bands” of demand
Based on percentage of Peak LDZ demand forecast
For each demand band, DNOs and National Grid NTS would agree:
06:00 (SOD) Assured Offtake Pressure (by exit point)
22:00 (EOD) Assured Offtake Pressure (by exit point)
NTS Exit (Flexibility) Capacity (by exit point) given the associated AOPs
11
Bands of Demand
0% 100%50%25% 75%
Current AOP at a DNO Exit Point
Actual DNO Pressure Requirement?
Demand Bands
Stepped AOPs in line with DNO Requirement
Inpu
t Pre
ssur
e at
Exi
t Poi
nt
Percentage of Forecast Peak Demand
Assumed that a minimum level is required below a certain demand threshold
12
Next Steps? National Grid NTS has discussed this potential proposal with some DNOs
during its annual network planning meetings Not all DNOs took up National Grid NTS’ offer of a meeting this year
National Grid NTS is currently investigating the code, systems and process implications Operational timescales Agreed 06:00 Pressure process Low Demand Days
Will provide further updates at future OAD Workgroups
Draft Modification to be available for industry discussion in October / November